risk management in tunnelling 6-7 september 2017 · pdf file · 2018-01-31......

51
Risk Management in Tunnelling 6-7 September 2017– Santiago, Chile Risk Management Plan: content, role and responsibilities, governance and organization Tarcisio B. Celestino University of São Paulo São Carlos Engineering School

Upload: dodiep

Post on 22-Mar-2018

212 views

Category:

Documents


0 download

TRANSCRIPT

Risk Management in Tunnelling

6-7 September 2017– Santiago, ChileRisk Management Plan:

content, role and responsibilities, governance and organizationTarcisio B. Celestino

University of São PauloSão Carlos Engineering

School

Risk Management in Tunnelling6-7 September 2017– Santiago, Chile

Outline

1. Definitions

2. Risk Assessment and Management; risk evaluation

3. Risk Assessment

4. Special duties of the Client

5. Special duties of the Designer

6. Risk management at diferente stages of the Project

7. Deliverables for use by Contract Insurers

8. Site and ground investigation

9. Management of change of design

Risk Management in Tunnelling6-7 September 2017– Santiago, Chile

Risk Management Plan

“A document identifying the means and methods for the regular monitoring and review of the construction stage project risk register, of formally recording hazards and associated risks which arise during the course of the construction stage; of recording progress in the reduction/mitigation of the overall impact/number of risks; and of updating the construction phase project risk register and hence any changes to the project risk profile during the construction stage of the tunnel works”

(ITIG, 2006)

Risk Management in Tunnelling6-7 September 2017– Santiago, Chile

Risk register

“A formalized record of risks identified form the risk assessment process including full descriptive details of mitigation and control measures, risk owners and with appropriate cross references. The risk register is the primary means of recording and monitoring the risk management process.”

(ITIG, 2006)

Risk Management in Tunnelling6-7 September 2017– Santiago, Chile

Risk assessment

“The formalized process of identifying hazards and associated risks, of evaluating their consequences and probability of occurrence, and of preparing strategies as appropriate for preventative and contingent actions”

(ITIG, 2006)

Risk Management in Tunnelling6-7 September 2017– Santiago, Chile

Risk management

“The overall systematic process of risk assessment and providing for risk mitigation and control”

(ITIG, 2006)

Risk Management in Tunnelling6-7 September 2017– Santiago, Chile

Project risk profile

“An assessment of the residual risks at any point in time during tunnel works which potentially impact on the outcome of the project”

(ITIG, 2006)

Risk Management in Tunnelling6-7 September 2017– Santiago, Chile

Risk assessment and management

Risk Management in Tunnelling6-7 September 2017– Santiago, Chile

Quantification of ALARP concept

“Hazard identification and management of risk to ensure their reduction to a level ‘as low as reasonably practicable’ (ALARP) shall be integral considerations in planning, design, procurement and construction of tunnel works.”

(ITIG, 2006)

As low as reasonably practicable: quantitative guidelines in codes; reliability index -> probability of failure

Risk Management in Tunnelling6-7 September 2017– Santiago, Chile

Risk Management in Tunnelling6-7 September 2017– Santiago, Chile

Risk

• Code 4.1.2: Risk is defined as the combination of the consequences (or severity) of a ‘hazard’ and its likelihood.

• Deterministic design does not reflect potential deviations (load, properties)

• Probabilistic approach can explore that

Risk Management in Tunnelling6-7 September 2017– Santiago, Chile

Variability in geotechnicalengineering

• Potential consequences “... on cost, program, environment, third parties and existing facilities”

Risk Management in Tunnelling6-7 September 2017– Santiago, Chile

Definition of consequence classes(Eurocode 7)

Ultimate limit state

Risk Management in Tunnelling6-7 September 2017– Santiago, Chile

Recommended minimum valuesfor reliability index b (Eurocode 7)

Risk Management in Tunnelling6-7 September 2017– Santiago, Chile

Calculation of reliability index b

SourceTon VrouwenvelderTU Delft

Risk Management in Tunnelling6-7 September 2017– Santiago, Chile

Example

SourceTon VrouwenvelderTU Delft

Risk Management in Tunnelling6-7 September 2017– Santiago, Chile

Calculation

SourceTon VrouwenvelderTU Delft

Risk Management in Tunnelling6-7 September 2017– Santiago, Chile

Reliability index and probability of failure

b 1.3 2.3 3.1 3.7 4.2 4.7

P(F)=F(-b) 10-1 10-2 10-3 10-4 10-5 10-6

Risk Management in Tunnelling6-7 September 2017– Santiago, Chile

Calculation of reliability index in complex situations

• Calculation with different scenarios (load and parameters): Monte Carlo Simulation

• Time consuming with large numerical models

• Other methods available, e.g. point estimate method (Napa et al., 2017)

Risk Management in Tunnelling6-7 September 2017– Santiago, Chile

Risk assessment

• Risk assessment required at each stage of a Project

• Summarized in appropriate risk registers

• Risk registers shall clearly indicate the party responsiblefor control and management

• Parameters to be used in the assessment – probabilityof occurrence of a hazard and severity of impact – shellbe Project specific and appropriate to the project stage.

• Insurance should not be considered as a contingency ormitigation measure in risk assessment for tunnelWorks.

Risk Management in Tunnelling6-7 September 2017– Santiago, Chile

Risk registers

• Risk assessment and the subsequent preparation of risk registers: identification of the ownership of risks

• Detail clearly how the risks are to be allocated, controlled, mitigated and managed

• Risk registers: live documents. Updated as new information becomes available at different stages of the project. Example: lower insurance premium

Risk Management in Tunnelling6-7 September 2017– Santiago, Chile

Client role and responsiblity

Risk Management in Tunnelling6-7 September 2017– Santiago, Chile

Contract

• Standard form of contract e.g. FIDIC, Institution of Civil Engineers (UK)

• Specific contracts desirable. Danger of questionable innovations

• Importance of the connection between contract and risk policy; specific risk clauses required in the contract (Eskessen et al., 2004)

• ITA – FIDIC book: to be released in 2018

Risk Management in Tunnelling6-7 September 2017– Santiago, Chile

Client

• Shall have demonstrable technical and contractmanagement competence appropriate to the

• In the absence of appropriate experience, Client’srepresentative shall be appointed

Risk Management in Tunnelling6-7 September 2017– Santiago, Chile

ITA Strategic Plan

• Clients without technical tradition to beapproached

• Tendency to hire services based on minimum cost

• Higher rate of accidents in other áreas, e.g. dams

• Essential to keep high level of enginnering services

Risk Management in Tunnelling6-7 September 2017– Santiago, Chile

ITA Strategic Plan SWOT 2017

Risk Management in Tunnelling6-7 September 2017– Santiago, Chile

Potential problems in the relationship between client, designer and contractor

• Authoritarian attitude by client; Code 8.1.3: Designers should be provided with a brief, this brief and identify deficiencies or omissions. Example of designer asking for clarifications at tender stage; no answer from client.

• Statement from contractor in Washington DC during workshop on contractual practices: objectives during contract are make money, make money and do a good job.

• Clients trying to get as much from contractor as possible. Contractor: do the job and leave the site as soon as possible.

Risk Management in Tunnelling6-7 September 2017– Santiago, Chile

Potential problems in the relationship between client, designer and contractor

(cont.)• Authoritarian attitude by designer (sometimes due

to contract limitations but not always)

• Code 7.4.1: Provisions shall be made by the Client for reasonable time for tendering to reflect type of contract, complexity of the project…

Risk Management in Tunnelling6-7 September 2017– Santiago, Chile

Designer role and responsibility

Risk Management in Tunnelling6-7 September 2017– Santiago, Chile

Design

• Design where the risk of failure is extremely remote duringconstruction and design life

• Design risk assessment shall consider realistic variation in thedesign criteria and/or design values adopted e.g. rock joint orientation

• Consider intermediate stages of construction e.g. excavationstability

• Observational approach: pre-planned and pre-designedcontingency (monitoring frequency, ground treatment, additional support, ...) measures needed connected to‘trigger levels’

• Include assessment of the impact on third partyinfrastructure

Risk Management in Tunnelling6-7 September 2017– Santiago, Chile

Example of realistic variation

• Influence of joint orientation on excavation stability

• Tapered blocks may become potentially unstable blocks

• Anticipated roof instability may turn into wall instability

Risk Management in Tunnelling6-7 September 2017– Santiago, Chile

Impact on third party infrastructure(Celestino and Ferreira, 1996)

0

5

10

15

20

25

30

35

40

45

50

< 0

,5

0,5

- 1

1 -

1,5

1,5

- 2

2 -

2,5

2,5

- 3

3 -

3,5

3,5

- 4

4 -

4,5

4,5

- 5

>5

v s (%)

%

Volume loss recorded

Recorded repair cost (US$/m)

<70

<200

600

Risk Management in Tunnelling6-7 September 2017– Santiago, Chile

Constructability - design

• Appropriate design in terms of constructability including health and safety considerations and impacts on third parties

• Detail excavation support sequences for temporary conditions (important: not only final situation; e.g. Paulo Afonso IV underground power station; Tarbela diversion tunnels)

Risk Management in Tunnelling6-7 September 2017– Santiago, Chile

Paulo Afonso IV underground power station

∎Cavern original design (unconstructable)

Risk Management in Tunnelling6-7 September 2017– Santiago, Chile

Paulo Afonso IV underground power station

• Problems with original design: almost no progress during construction

• 32.6m excavation span

• 1.8m thick reinforced concrete arch

• Fractured rock mass; RMR ~60

• Design changed during construction

• Pilot tunnel and two wing excavations

• 0.15m thick shotcrete and rockbolts

• Construction completed ahead of schedule

Risk Management in Tunnelling6-7 September 2017– Santiago, Chile

Risk management at different stages of the project

(Eskessen et al., 2004)

Risk Management in Tunnelling6-7 September 2017– Santiago, Chile

Risk management at different stages of the project

(Eskessen et al., 2004)

Risk Management in Tunnelling6-7 September 2017– Santiago, Chile

Risk management at different stages of the project

(Eskessen et al., 2004)

Risk Management in Tunnelling6-7 September 2017– Santiago, Chile

Deliverables for use by Contract Insurers

Risk Management in Tunnelling6-7 September 2017– Santiago, Chile

Deliverables for use by ContractInsurers (cont.)

Risk Management in Tunnelling6-7 September 2017– Santiago, Chile

Deliverables for use by ContractInsurers (cont.)

Risk Management in Tunnelling6-7 September 2017– Santiago, Chile

Deliverables for use by Contract Insurers(cont.)

Risk Management in Tunnelling6-7 September 2017– Santiago, Chile

Site and ground investigation

• Shall be carried out in accordance with local National Standards and/or Codes of Practice

• If not available, adopt internationally recognized standard

• Provide sufficient information on pertaining site conditions, ground, groundwater, etc.

• “… shall be executed by organizations who are suitably qualified and experienced and hence competent for such work”

Risk Management in Tunnelling6-7 September 2017– Santiago, Chile

Typical borehole profile

Risk Management in Tunnelling6-7 September 2017– Santiago, Chile

N-SPT of two borehole campaignsat same locations

Risk Management in Tunnelling6-7 September 2017– Santiago, Chile

Management of change of design

• Design changes instructed by the Client orintriduced by the Contractor shall be reviewed; revised risk assessment submitted for approval

• Value engineering proposals submitted for approvalto the Client shall include statement settig out technical benefits and revised risk assessment. Example José Eusébio Shaft

Risk Management in Tunnelling6-7 September 2017– Santiago, Chile

José Eusébio ShaftLine 4 São Paulo Metro

Risk Management in Tunnelling6-7 September 2017– Santiago, Chile

José Eusébio ShaftLine 4 São Paulo Metro

• Tender design: secant bored piles to protect building foundation

• Execution of bored piles would get closer to building foundation

• Value engineering proposal: remove bored piles

• 20-cm shotcrete only at the upper part; 40 cm at lower part

• Cheaper, faster, safer

Risk Management in Tunnelling6-7 September 2017– Santiago, Chile

Final remarks

• Need for risk management in geotechnical projects, mainly in tunneling projects

• Potential for large damage to the Project, third parties, environment,...

• Risk managemnt activities at all stages of the Project

• Responsibilities by all parties involved: Client, Tenderers, designer, Contractor

• Need for flexible contract including risk clauses

• Good record of projects with risk management implemented

Risk Management in Tunnelling6-7 September 2017– Santiago, Chile

References

• Celestino, T.B. and Ferreira, A.A. (1996) Building damagesassociated to recente tunnels constructed for the São Paulo Subway. Proc. World Tunnel Congress 1996, ITA, Washington.

• Eskessen, S.D., Tengborg, P., Kampmann, J. and Veicherts, T.H. (2004) Guidelines for tunnelling risk management: InternationalTunnelling Association, Working Group No. 2. Tunnelling and Underground Space Technology, :19, 207-237.

• International Tunnelling Insurance Group (2006) A Code ofPractice for Risk Management of Tunnel Works.

• Napa- Garcia, G.F., Beck, A.T. Celestino, T.B. (2017) Reliability analyses of underground openings with the point estimate method. Tunnelling and Underground Space Technology, :64, 154-163.

Disclaimer

a) The speakers are presenting their own personal views and are not expressing the viewof the Foundation.

b) Papers and documents displayed or handed out during the Event are copyrighted. The participants must observe and comply with all applicable law regulations concerning the copyright.

Risk Management in Tunnelling

6-7 September 2017– Santiago, Chile