river linking project - oneworld.net.in · these lines, india’s national river linking project...

13

Upload: others

Post on 07-Oct-2020

9 views

Category:

Documents


0 download

TRANSCRIPT

  • [email protected]

    February 2011

    Governance Knowledge CentrePromoted by Department of Administrative Reforms and Public GrievancesMinistry of Personnel, Public Grievances and Pensions, Government of Indiahttp://indiagovernance.gov.in/

    Researched and Documented by

    OneWorld Foundation India

    River Linking ProjectJalgaon, Maharashtra

  • Transparency and Accountability

    Governance Knowledge CentrePromoted by Department of Administrative Reforms and

    Ministry of Personnel, Public Grievances and Pensions

    Government of India

    Table of Contents Executive Summary ................................

    Background ................................

    Objective ................................................................

    Working Design ................................

    Financial Resources ................................

    Methodology ................................

    Key Stakeholders ................................

    Lessons Learned ................................

    Taking Small Steps ................................

    Using Strengths of Local Topography

    Extensive Field Assessment

    Participatory Approach

    Strong Leadership ................................

    References ................................

    Appendix A – Interview Questionnaire

    Transparency and Accountability

    Governance Knowledge Centre Promoted by Department of Administrative Reforms and Public Grievances

    Ministry of Personnel, Public Grievances and Pensions

    Researched and documented by

    OneWorld Foundation India

    Water and Sanitation

    River Linking Project

    ................................................................................................

    ................................................................................................................................

    ................................................................................................

    ................................................................................................................................

    ................................................................................................

    ................................................................................................................................

    ................................................................................................................................

    ................................................................................................................................

    ................................................................................................

    Using Strengths of Local Topography ................................................................

    Extensive Field Assessment ................................................................................................

    ................................................................................................

    ................................................................................................

    ................................................................................................................................

    Interview Questionnaire ................................................................

    Transparency and Accountability

    Case Study Water and Sanitation

    River Linking Project – Jalgaon, Maharashtra

    February 2011

    1

    .................................................................. 2

    ................................................ 2

    ..................................................... 3

    ........................................ 4

    ........................................................ 8

    .............................................. 8

    ....................................... 9

    ........................................ 9

    .......................................................... 9

    ....................................................... 10

    ......................................... 10

    ................................................ 10

    ......................................................... 10

    ................................................ 11

    .............................................................. 12

  • Transparency and Accountability

    Governance Knowledge CentrePromoted by Department of Administrative Reforms and

    Ministry of Personnel, Public Grievances and Pensions

    Government of India

    Executive SummaryRiver connectivity is seen as a possible way to equally distribute of water across a geographical

    region. Conceptually, inter-linking water ways is appreciated by policy practitioners to resolve

    water problems but the practical ecological concerns usually

    these lines, India’s National River Linking Project that aims to connect the rivers in the Ganges

    basin to rivers in western and southern India has been an issue of debate. The displacement of

    people due to land acquisition

    acclaimed river linking project in Jalgaon has overcome these ch

    strengths in geography and existing infrastructure.

    This best practice documentation intends to provi

    of the River Linking Project that has been successful in making adequate water available for

    irrigation and human consumption throughout the district.

    Jalgaon, due to its location, receives inadequate rainfall d

    storage facilities also means that reservoirs, canals, and ground water supply are always below

    the minimum storage level. In 2005, when the district witnessed an almost drought like

    situation, the local administration fel

    was already a network of canals and reservoirs to channel the water, interlinking of waterways

    seemed to be an appropriate solution. Planning looked to restore the capacity of the existing

    infrastructure and allow for excess water from nearby dams to irrigate water scarce areas.

    This initiative is inspiring as it was conceptualised, planned and implemented within four

    months. The participatory and proactive approach taken by district administra

    they gained the support of the local people in fulfilling the project objectives.

    Background Jalgaon, located in the north of Maharashtra, falls in a rain shadow area with a higher

    probability of drought compared to its neighbouring districts. Local topography also adds to

    the problem through unequal distribution of rainfall in the natural drainag

    tributaries - Girna, Bori, Anjani, Titur and Waghur

    being a major source of water supply at the south west corner of district. Even though there are

    man-made canals to network the water for local i

    storage capacity never reaches its minimum level. As such, the recurring problem of water

    scarcity is usually addressed by supplying water tankers to provide temporary relief.

    Transparency and Accountability

    Governance Knowledge Centre Promoted by Department of Administrative Reforms and Public Grievances

    Ministry of Personnel, Public Grievances and Pensions

    Researched and documented by

    OneWorld Foundation India

    Water and Sanitation

    River Linking Project

    Executive Summary River connectivity is seen as a possible way to equally distribute of water across a geographical

    linking water ways is appreciated by policy practitioners to resolve

    water problems but the practical ecological concerns usually delay the implementation. Along

    these lines, India’s National River Linking Project that aims to connect the rivers in the Ganges

    basin to rivers in western and southern India has been an issue of debate. The displacement of

    people due to land acquisition is also a cause for concern. Nevertheless, the nationally

    acclaimed river linking project in Jalgaon has overcome these challenges by exploiting regional

    strengths in geography and existing infrastructure.

    This best practice documentation intends to provide insights into the design and achievements

    of the River Linking Project that has been successful in making adequate water available for

    irrigation and human consumption throughout the district.

    Jalgaon, due to its location, receives inadequate rainfall during monsoon season. Inefficient

    storage facilities also means that reservoirs, canals, and ground water supply are always below

    the minimum storage level. In 2005, when the district witnessed an almost drought like

    situation, the local administration felt the need to look for a long term solution. Given that there

    was already a network of canals and reservoirs to channel the water, interlinking of waterways

    seemed to be an appropriate solution. Planning looked to restore the capacity of the existing

    astructure and allow for excess water from nearby dams to irrigate water scarce areas.

    This initiative is inspiring as it was conceptualised, planned and implemented within four

    months. The participatory and proactive approach taken by district administra

    they gained the support of the local people in fulfilling the project objectives.

    Jalgaon, located in the north of Maharashtra, falls in a rain shadow area with a higher

    probability of drought compared to its neighbouring districts. Local topography also adds to

    the problem through unequal distribution of rainfall in the natural drainag

    Girna, Bori, Anjani, Titur and Waghur - are the important rivers, with Girna Dam

    being a major source of water supply at the south west corner of district. Even though there are

    made canals to network the water for local irrigation and storage purposes, the reservoir

    storage capacity never reaches its minimum level. As such, the recurring problem of water

    scarcity is usually addressed by supplying water tankers to provide temporary relief.

    Transparency and Accountability

    Case Study Water and Sanitation

    River Linking Project – Jalgaon, Maharashtra

    February 2011

    2

    River connectivity is seen as a possible way to equally distribute of water across a geographical

    linking water ways is appreciated by policy practitioners to resolve

    delay the implementation. Along

    these lines, India’s National River Linking Project that aims to connect the rivers in the Ganges

    basin to rivers in western and southern India has been an issue of debate. The displacement of

    is also a cause for concern. Nevertheless, the nationally

    allenges by exploiting regional

    de insights into the design and achievements

    of the River Linking Project that has been successful in making adequate water available for

    uring monsoon season. Inefficient

    storage facilities also means that reservoirs, canals, and ground water supply are always below

    the minimum storage level. In 2005, when the district witnessed an almost drought like

    t the need to look for a long term solution. Given that there

    was already a network of canals and reservoirs to channel the water, interlinking of waterways

    seemed to be an appropriate solution. Planning looked to restore the capacity of the existing

    astructure and allow for excess water from nearby dams to irrigate water scarce areas.

    This initiative is inspiring as it was conceptualised, planned and implemented within four

    months. The participatory and proactive approach taken by district administration ensured that

    they gained the support of the local people in fulfilling the project objectives.

    Jalgaon, located in the north of Maharashtra, falls in a rain shadow area with a higher

    probability of drought compared to its neighbouring districts. Local topography also adds to

    the problem through unequal distribution of rainfall in the natural drainage area. Tapti’s

    are the important rivers, with Girna Dam

    being a major source of water supply at the south west corner of district. Even though there are

    rrigation and storage purposes, the reservoir

    storage capacity never reaches its minimum level. As such, the recurring problem of water

    scarcity is usually addressed by supplying water tankers to provide temporary relief.

  • Transparency and Accountability

    Governance Knowledge CentrePromoted by Department of Administrative Reforms and

    Ministry of Personnel, Public Grievances and Pensions

    Government of India

    In 2005, when Jalgaon was experi

    conceptualised the river linking project to resolve perennial water crises by diverting excess

    water from Girna dam to water

    new, was executed in an innovative way which helped to overcome the challenge of balancing

    ecological concerns, human displacement and high costs. In this case, the local administration

    followed a methodical approach to sustainably implement the project in a timely

    minimal costs.

    At the start, Girna Dam, located at Nashik

    excess rainwater. As such, the plan became that Girna Dam, through the river, would be linked

    to other rivers, canals, reservoirs t

    administration conducted a study to understand the developmental strengths and weaknesses

    of the district. From this assessment, existing infrastructure was identified and incorporated

    into new linkages to reduce costs and minimise any negative environmental impact.

    Objective The project aims to equitably distribute water and to resolve water scarcity for drinking and

    irrigation purposes by linking various water channels. Its specific objectives are to:

    • Divert water from water surplus areas to arid and semi

    • Increase the efficiency of different water storage structures

    • Conserve water by channelling it through canals ducts, drains, nallahs, natural drains

    etc. into drought-prone

    • Identify the inter-relationships of recharge areas with geology and geomorphology

    practices to examine the soils and structure of the area

    • Detect land use changes over time and determine their relationship with changes in the

    area of connectivity

    • Carry out qualitative and quantitative assessment of water resources

    • Suggest suitable sites and methods for artificial recharge to augment ground water

    recharge in the area

    • Establish and evaluate long

    sustainable development in the area under benefit

    • Assess the socio-economic impact of the river connectivity initiative

    Transparency and Accountability

    Governance Knowledge Centre Promoted by Department of Administrative Reforms and Public Grievances

    Ministry of Personnel, Public Grievances and Pensions

    Researched and documented by

    OneWorld Foundation India

    Water and Sanitation

    River Linking Project

    In 2005, when Jalgaon was experiencing drought-like conditions, the then district collector

    conceptualised the river linking project to resolve perennial water crises by diverting excess

    water from Girna dam to water-deficit regions. This idea of connecting rivers, although not

    executed in an innovative way which helped to overcome the challenge of balancing

    ecological concerns, human displacement and high costs. In this case, the local administration

    followed a methodical approach to sustainably implement the project in a timely

    At the start, Girna Dam, located at Nashik-Jalgaon border, was identified as the key source of

    excess rainwater. As such, the plan became that Girna Dam, through the river, would be linked

    to other rivers, canals, reservoirs to make the water flow into areas that needed it. The

    administration conducted a study to understand the developmental strengths and weaknesses

    of the district. From this assessment, existing infrastructure was identified and incorporated

    to reduce costs and minimise any negative environmental impact.

    The project aims to equitably distribute water and to resolve water scarcity for drinking and

    irrigation purposes by linking various water channels. Its specific objectives are to:

    Divert water from water surplus areas to arid and semi-arid parts of the district

    Increase the efficiency of different water storage structures

    Conserve water by channelling it through canals ducts, drains, nallahs, natural drains

    prone areas

    relationships of recharge areas with geology and geomorphology

    practices to examine the soils and structure of the area

    Detect land use changes over time and determine their relationship with changes in the

    Carry out qualitative and quantitative assessment of water resources

    Suggest suitable sites and methods for artificial recharge to augment ground water

    Establish and evaluate long-term research on monitoring, measuring and planning for

    sustainable development in the area under benefit

    economic impact of the river connectivity initiative

    Transparency and Accountability

    Case Study Water and Sanitation

    River Linking Project – Jalgaon, Maharashtra

    February 2011

    3

    like conditions, the then district collector

    conceptualised the river linking project to resolve perennial water crises by diverting excess

    deficit regions. This idea of connecting rivers, although not

    executed in an innovative way which helped to overcome the challenge of balancing

    ecological concerns, human displacement and high costs. In this case, the local administration

    followed a methodical approach to sustainably implement the project in a timely manner with

    Jalgaon border, was identified as the key source of

    excess rainwater. As such, the plan became that Girna Dam, through the river, would be linked

    o make the water flow into areas that needed it. The

    administration conducted a study to understand the developmental strengths and weaknesses

    of the district. From this assessment, existing infrastructure was identified and incorporated

    to reduce costs and minimise any negative environmental impact.

    The project aims to equitably distribute water and to resolve water scarcity for drinking and

    irrigation purposes by linking various water channels. Its specific objectives are to:

    arid parts of the district

    Conserve water by channelling it through canals ducts, drains, nallahs, natural drains

    relationships of recharge areas with geology and geomorphology

    Detect land use changes over time and determine their relationship with changes in the

    Carry out qualitative and quantitative assessment of water resources

    Suggest suitable sites and methods for artificial recharge to augment ground water

    term research on monitoring, measuring and planning for

    economic impact of the river connectivity initiative

  • Transparency and Accountability

    Governance Knowledge CentrePromoted by Department of Administrative Reforms and

    Ministry of Personnel, Public Grievances and Pensions

    Government of India

    Working Design The project was developed with the goal of completing the task within the limited time period

    of two to three months to ensure that the surplus rainwater from the 2005 monsoon was used in

    time. The project entails a combination of rain water conservation and utilisation of flood water

    run-off to replenish natural and artificial water bodies through natural drainage channels

    To create the linkage architecture, the administration first took the following steps to assess the

    on the ground scenario:

    • A detailed field level survey (undertaken by the irrigation department) to investigate

    water scarce areas and to study the effi

    • Identification and assessment of existing infrastructure to minimise construction of new

    canals

    • An evaluation to understand the natural contours of the region that could be exploited

    to divert water

    • Discussion with beneficiaries to understand the needs of the local population

    One of the major hindrances to undertaking a river connectivity project is the acquisition of

    land for digging link canals. As a consequence, the administration followed a consultative

    approach to include the stakeholders at the conceptualisation stage. On

    administration met with landowners affected by the project to discuss the initiative and also to

    inform them about the increased productivity of land resulting from improved irrigation. This

    encouraged the landowners to donate t

    value of the land that was otherwise considered barren. The administration was also proactive

    in consulting with stakeholders from various government departments and elected

    representatives to increase support for the project.

    After initial exploration, the five tributaries

    inter-linked with various canals and reservoirs to develop water resources for the area. The

    following are the five route maps:

    Transparency and Accountability

    Governance Knowledge Centre Promoted by Department of Administrative Reforms and Public Grievances

    Ministry of Personnel, Public Grievances and Pensions

    Researched and documented by

    OneWorld Foundation India

    Water and Sanitation

    River Linking Project

    The project was developed with the goal of completing the task within the limited time period

    ensure that the surplus rainwater from the 2005 monsoon was used in

    time. The project entails a combination of rain water conservation and utilisation of flood water

    off to replenish natural and artificial water bodies through natural drainage channels

    To create the linkage architecture, the administration first took the following steps to assess the

    A detailed field level survey (undertaken by the irrigation department) to investigate

    water scarce areas and to study the efficiency of the groundwater recharge structure

    Identification and assessment of existing infrastructure to minimise construction of new

    An evaluation to understand the natural contours of the region that could be exploited

    n with beneficiaries to understand the needs of the local population

    One of the major hindrances to undertaking a river connectivity project is the acquisition of

    land for digging link canals. As a consequence, the administration followed a consultative

    approach to include the stakeholders at the conceptualisation stage. Once identified, the district

    administration met with landowners affected by the project to discuss the initiative and also to

    inform them about the increased productivity of land resulting from improved irrigation. This

    encouraged the landowners to donate their land for the project as it enhanced the commercial

    value of the land that was otherwise considered barren. The administration was also proactive

    in consulting with stakeholders from various government departments and elected

    e support for the project.

    After initial exploration, the five tributaries - Girna, Bori, Titur, Mhasva and Anjani

    linked with various canals and reservoirs to develop water resources for the area. The

    following are the five route maps:

    Transparency and Accountability

    Case Study Water and Sanitation

    River Linking Project – Jalgaon, Maharashtra

    February 2011

    4

    The project was developed with the goal of completing the task within the limited time period

    ensure that the surplus rainwater from the 2005 monsoon was used in

    time. The project entails a combination of rain water conservation and utilisation of flood water

    off to replenish natural and artificial water bodies through natural drainage channels.

    To create the linkage architecture, the administration first took the following steps to assess the

    A detailed field level survey (undertaken by the irrigation department) to investigate

    ciency of the groundwater recharge structure

    Identification and assessment of existing infrastructure to minimise construction of new

    An evaluation to understand the natural contours of the region that could be exploited

    n with beneficiaries to understand the needs of the local population

    One of the major hindrances to undertaking a river connectivity project is the acquisition of

    land for digging link canals. As a consequence, the administration followed a consultative

    ce identified, the district

    administration met with landowners affected by the project to discuss the initiative and also to

    inform them about the increased productivity of land resulting from improved irrigation. This

    heir land for the project as it enhanced the commercial

    value of the land that was otherwise considered barren. The administration was also proactive

    in consulting with stakeholders from various government departments and elected

    Girna, Bori, Titur, Mhasva and Anjani - were

    linked with various canals and reservoirs to develop water resources for the area. The

  • Transparency and Accountability

    Governance Knowledge CentrePromoted by Department of Administrative Reforms and

    Ministry of Personnel, Public Grievances and Pensions

    Government of India

    Transparency and Accountability

    Governance Knowledge Centre Promoted by Department of Administrative Reforms and Public Grievances

    Ministry of Personnel, Public Grievances and Pensions

    Researched and documented by

    OneWorld Foundation India

    Water and Sanitation

    River Linking Project

    Route 1: Connecting Dam to River

    Girna Dam was first linked with Bori

    River to increase the water supply at

    Bori dam as it is the main source of

    supply for 74 villages. Excess flood

    water from Girna is diverted to Panzan

    left bank canal and then short

    connections were created to divert

    surplus water from Panzan Canal to

    Bori river, which was not possible

    earlier.

    Route 2: Connecting Canal to Pond

    The second step was to connect Girna

    to Mhasva pond. The project was

    planned in such a way that overflowing

    water released from the Girna dam

    could be diverted to Parola

    canal and then, through a link, canal

    water was used to fill the pond.

    Transparency and Accountability

    Case Study Water and Sanitation

    River Linking Project – Jalgaon, Maharashtra

    February 2011

    5

    Route 1: Connecting Dam to River

    Girna Dam was first linked with Bori

    River to increase the water supply at

    Bori dam as it is the main source of

    supply for 74 villages. Excess flood

    water from Girna is diverted to Panzan

    left bank canal and then short

    ections were created to divert

    surplus water from Panzan Canal to

    Bori river, which was not possible

    Route 2: Connecting Canal to Pond

    The second step was to connect Girna

    ond. The project was

    planned in such a way that overflowing

    water released from the Girna dam

    could be diverted to Parola branch

    anal and then, through a link, canal

    water was used to fill the pond.

  • Transparency and Accountability

    Governance Knowledge CentrePromoted by Department of Administrative Reforms and

    Ministry of Personnel, Public Grievances and Pensions

    Government of India Transparency and Accountability

    Governance Knowledge Centre Promoted by Department of Administrative Reforms and Public Grievances

    Ministry of Personnel, Public Grievances and Pensions

    Researched and documented by

    OneWorld Foundation India

    Water and Sanitation

    River Linking Project

    Route 3: Connecting Canal to River

    A new link canal was built to make water

    flow from Parola Branch Canal to An

    river and Kala bandhara.

    Route 4: Connecting Rivers

    Girna river was connected to Titur river

    through existing Jamda Right canal by

    creating a new link canal. This was done

    to provide additional water to Titur river

    from Girna dam.

    Transparency and Accountability

    Case Study Water and Sanitation

    River Linking Project – Jalgaon, Maharashtra

    February 2011

    6

    Route 3: Connecting Canal to River

    A new link canal was built to make water

    flow from Parola Branch Canal to Anjani

    river and Kala bandhara.

    Route 4: Connecting Rivers

    Girna river was connected to Titur river

    through existing Jamda Right canal by

    creating a new link canal. This was done

    to provide additional water to Titur river

  • Transparency and Accountability

    Governance Knowledge CentrePromoted by Department of Administrative Reforms and

    Ministry of Personnel, Public Grievances and Pensions

    Government of India

    Transparency and Accountability

    Governance Knowledge Centre Promoted by Department of Administrative Reforms and Public Grievances

    Ministry of Personnel, Public Grievances and Pensions

    Researched and documented by

    OneWorld Foundation India

    Water and Sanitation

    River Linking Project

    Route 5: Increasing Water Storage

    Capacity

    The water from Girna

    channelled through canals and a new link

    nala to provide additional water for

    storage at Pimpri bandhara.

    River Connectivity in Jalgaon

    Transparency and Accountability

    Case Study Water and Sanitation

    River Linking Project – Jalgaon, Maharashtra

    February 2011

    7

    5: Increasing Water Storage

    The water from Girna dam was

    channelled through canals and a new link

    nala to provide additional water for

    storage at Pimpri bandhara.

  • Transparency and Accountability

    Governance Knowledge CentrePromoted by Department of Administrative Reforms and

    Ministry of Personnel, Public Grievances and Pensions

    Government of India

    Modifications to Existing Infrastructure

    Apart from building new links, the capacity of existing canals was improved by modifying the

    height with mud. Canals were also lined with PVC paper to avoid leakages and increase the

    flowing capacity, also known as the

    Bank Canal and Panzan Left Bank Canal were upgraded using low cost PVC papers at canal

    apexes and aqueduct beds as they are the main channels

    other water bodies.

    Storage capacity of reservoirs/bandhara was al

    water by creating temporary fences using gunny bags. A safe level was maintained in case of

    flooding and so that the barriers could easily be removed in such a situation.

    Financial Resources

    Funding for the project was provided by elected officials and the state government. The district

    administration presented the project development report to the local leaders, and once the

    elected representatives were convinced about the significance of the

    grants from the Member of Parliament Local Area Development Scheme (MPLADS) were made

    available to partially fund the project.

    A cost-benefit analysis was presented separately to the state government to request for funding.

    The project was proposed as a plan to overcome water scarcity issues in the area and not

    simply connecting rivers. It was shown that the overall cost of implementing the initiative was

    much lower as compared to undertaking additional measures for improving t

    water. The Government of Maharashtra allocated Rs. 2 crores from the scarcity fund.

    Methodology For the purpose of this best practice, the OneWorld Foundation India Governance Knowledge

    Centre (GKC) research team conducted a telephonic interview with Mr. Vijay Singhal, the

    former District Collector of Jalgaon, who was instrumental in conceptualising

    addition, data was gathered from sources available on the public domain.

    Further documents on technicalities of river connectivity in Jalgaon can be found on the District

    Administration’s website accessible at

    Transparency and Accountability

    Governance Knowledge Centre Promoted by Department of Administrative Reforms and Public Grievances

    Ministry of Personnel, Public Grievances and Pensions

    Researched and documented by

    OneWorld Foundation India

    Water and Sanitation

    River Linking Project

    Infrastructure

    Apart from building new links, the capacity of existing canals was improved by modifying the

    height with mud. Canals were also lined with PVC paper to avoid leakages and increase the

    flowing capacity, also known as the Gauckler-Manning coefficient. Specifically, J

    Bank Canal and Panzan Left Bank Canal were upgraded using low cost PVC papers at canal

    apexes and aqueduct beds as they are the main channels of diverting water from Girna

    Storage capacity of reservoirs/bandhara was also increased to retain maximum amount of

    water by creating temporary fences using gunny bags. A safe level was maintained in case of

    flooding and so that the barriers could easily be removed in such a situation.

    Funding for the project was provided by elected officials and the state government. The district

    administration presented the project development report to the local leaders, and once the

    elected representatives were convinced about the significance of the project for the community,

    grants from the Member of Parliament Local Area Development Scheme (MPLADS) were made

    available to partially fund the project.

    benefit analysis was presented separately to the state government to request for funding.

    e project was proposed as a plan to overcome water scarcity issues in the area and not

    simply connecting rivers. It was shown that the overall cost of implementing the initiative was

    much lower as compared to undertaking additional measures for improving t

    water. The Government of Maharashtra allocated Rs. 2 crores from the scarcity fund.

    For the purpose of this best practice, the OneWorld Foundation India Governance Knowledge

    Centre (GKC) research team conducted a telephonic interview with Mr. Vijay Singhal, the

    former District Collector of Jalgaon, who was instrumental in conceptualising

    addition, data was gathered from sources available on the public domain.

    Further documents on technicalities of river connectivity in Jalgaon can be found on the District

    Administration’s website accessible at http://jalgaon.gov.in/Html/River_Linkage.htm

    Transparency and Accountability

    Case Study Water and Sanitation

    River Linking Project – Jalgaon, Maharashtra

    February 2011

    8

    Apart from building new links, the capacity of existing canals was improved by modifying the

    height with mud. Canals were also lined with PVC paper to avoid leakages and increase the

    coefficient. Specifically, Jamda Left

    Bank Canal and Panzan Left Bank Canal were upgraded using low cost PVC papers at canal

    of diverting water from Girna dam to

    so increased to retain maximum amount of

    water by creating temporary fences using gunny bags. A safe level was maintained in case of

    flooding and so that the barriers could easily be removed in such a situation.

    Funding for the project was provided by elected officials and the state government. The district

    administration presented the project development report to the local leaders, and once the

    project for the community,

    grants from the Member of Parliament Local Area Development Scheme (MPLADS) were made

    benefit analysis was presented separately to the state government to request for funding.

    e project was proposed as a plan to overcome water scarcity issues in the area and not

    simply connecting rivers. It was shown that the overall cost of implementing the initiative was

    much lower as compared to undertaking additional measures for improving the availability of

    water. The Government of Maharashtra allocated Rs. 2 crores from the scarcity fund.

    For the purpose of this best practice, the OneWorld Foundation India Governance Knowledge

    Centre (GKC) research team conducted a telephonic interview with Mr. Vijay Singhal, the

    former District Collector of Jalgaon, who was instrumental in conceptualising the project. In

    addition, data was gathered from sources available on the public domain.

    Further documents on technicalities of river connectivity in Jalgaon can be found on the District

    http://jalgaon.gov.in/Html/River_Linkage.htm.

  • Transparency and Accountability

    Governance Knowledge CentrePromoted by Department of Administrative Reforms and

    Ministry of Personnel, Public Grievances and Pensions

    Government of India

    Key Stakeholders • Jalgaon District Collectorate: The District Collector’s office played a pivotal role in

    conceptualising the project. The project was conceived in order to address

    water problem, which is the collector’s responsibility.

    • Irrigation Department: The irrigation department assisted with initial funding for the

    project and also provided the technical guidance in needs assessment.

    • Elected Representatives:

    the project.

    • State Government: Funding for the project was provided by the government under

    Water Scarcity.

    • Landowners: People donated part of their land for construction of new link canals.

    Lessons Learned By distributing surplus water to deficit areas, the government has successfully made resources

    available to 128 villages and 5 municipal corporations. In total, 8.5 lakh people have benefitted

    and the total irrigated area has increased from

    The impact of project was assessed through a socio

    watershed surveillance and research institute in Jalgaon. The survey covered a random sample

    of 840 households in 42 villages, out of the total population of 300 villages. Over 84percent of

    the people are in favour of river linking efforts, and nearly 54 percent of farmers have noticed

    increases in the level of water in their wells with 57 percent of people reporting

    drinking water.

    Successful implementation of this river linking project is encouraging at a time when the

    national river linking project is being questioned as an environmental disaster. The following

    lessons derived from Jalgaon’s experience can aid i

    initiatives.

    Taking Small Steps

    The national river linking project has the ambitious goal of connecting perennial Himalayan

    Rivers to monsoon dependent rivers in west and south India. Changing the entire course of

    river through creating artificial linkages could prove disastrous for the

    Jalgaon, these issues were addressed by taking small steps. Girna Dam, due to its location in

    Transparency and Accountability

    Governance Knowledge Centre Promoted by Department of Administrative Reforms and Public Grievances

    Ministry of Personnel, Public Grievances and Pensions

    Researched and documented by

    OneWorld Foundation India

    Water and Sanitation

    River Linking Project

    Jalgaon District Collectorate: The District Collector’s office played a pivotal role in

    conceptualising the project. The project was conceived in order to address

    water problem, which is the collector’s responsibility.

    Irrigation Department: The irrigation department assisted with initial funding for the

    project and also provided the technical guidance in needs assessment.

    Elected Representatives: Financial support was offered by political leaders to implement

    State Government: Funding for the project was provided by the government under

    Landowners: People donated part of their land for construction of new link canals.

    By distributing surplus water to deficit areas, the government has successfully made resources

    available to 128 villages and 5 municipal corporations. In total, 8.5 lakh people have benefitted

    and the total irrigated area has increased from 13,000 hectares to 30,000 hectares in 2008.

    The impact of project was assessed through a socio-economic survey in 2007 by JalaSRI, a

    watershed surveillance and research institute in Jalgaon. The survey covered a random sample

    lages, out of the total population of 300 villages. Over 84percent of

    the people are in favour of river linking efforts, and nearly 54 percent of farmers have noticed

    increases in the level of water in their wells with 57 percent of people reporting

    Successful implementation of this river linking project is encouraging at a time when the

    national river linking project is being questioned as an environmental disaster. The following

    lessons derived from Jalgaon’s experience can aid in the planning process of other such

    The national river linking project has the ambitious goal of connecting perennial Himalayan

    Rivers to monsoon dependent rivers in west and south India. Changing the entire course of

    river through creating artificial linkages could prove disastrous for the natural environment. In

    Jalgaon, these issues were addressed by taking small steps. Girna Dam, due to its location in

    Transparency and Accountability

    Case Study Water and Sanitation

    River Linking Project – Jalgaon, Maharashtra

    February 2011

    9

    Jalgaon District Collectorate: The District Collector’s office played a pivotal role in

    conceptualising the project. The project was conceived in order to address the recurring

    Irrigation Department: The irrigation department assisted with initial funding for the

    project and also provided the technical guidance in needs assessment.

    Financial support was offered by political leaders to implement

    State Government: Funding for the project was provided by the government under

    Landowners: People donated part of their land for construction of new link canals.

    By distributing surplus water to deficit areas, the government has successfully made resources

    available to 128 villages and 5 municipal corporations. In total, 8.5 lakh people have benefitted

    13,000 hectares to 30,000 hectares in 2008.

    economic survey in 2007 by JalaSRI, a

    watershed surveillance and research institute in Jalgaon. The survey covered a random sample

    lages, out of the total population of 300 villages. Over 84percent of

    the people are in favour of river linking efforts, and nearly 54 percent of farmers have noticed

    increases in the level of water in their wells with 57 percent of people reporting adequate

    Successful implementation of this river linking project is encouraging at a time when the

    national river linking project is being questioned as an environmental disaster. The following

    n the planning process of other such

    The national river linking project has the ambitious goal of connecting perennial Himalayan

    Rivers to monsoon dependent rivers in west and south India. Changing the entire course of

    natural environment. In

    Jalgaon, these issues were addressed by taking small steps. Girna Dam, due to its location in

  • Transparency and Accountability

    Governance Knowledge CentrePromoted by Department of Administrative Reforms and

    Ministry of Personnel, Public Grievances and Pensions

    Government of India

    Nashik district, had water available during monsoon season, but since there was no way of

    controlling the additional water, it would flow

    extra water from Girna could be diverted in a planned way to boost the volume of available

    water in the existing water network. Only short linkages were created between already present

    water bodies to divert water to required areas.

    Using Strengths of Local Topography

    Due to a widespread power crisis, and the high cost of installing electric pumps to facilitate the

    flow of water, the administration opted to exploit the geographical strengths of the region

    towards improving the flow of water. The natural contours were identified through a baseline

    study and the route for link canals were decided after that. This helped in keeping the cost of

    the project low.

    Extensive Field Assessment

    This initiative was implemented after doing a baseline assessment to understand the local

    conditions and needs. Villagers and agriculturalists

    current scenario of water availability.. This helped in planning the routes in a well

    manner and also to gain support from the villagers as they became aware of the project

    planning.

    Participatory Approach

    The absence of any objection from various sections of society makes this project unique. The

    administration proactively included all

    and build confidence. Villagers were educated about benefits of the project and encouraged to

    be a part of it. As mentioned previously, land for creating new link canals were donated by the

    local people with no compensation from the government.

    Strong Leadership

    The project was implemented success because of the strong leadership offered by the

    administration and namely, the District Collector. With a background in civil engineering, he

    was able to visualise the project for the region and could also anticipate the challenges.

    Research was carried out by OneWorld Foundation India (OWFI), Governance Knowledge Centre (GKC) team.

    Documentation was created by

    For further information, please contact

    Transparency and Accountability

    Governance Knowledge Centre Promoted by Department of Administrative Reforms and Public Grievances

    Ministry of Personnel, Public Grievances and Pensions

    Researched and documented by

    OneWorld Foundation India

    Water and Sanitation

    River Linking Project

    Nashik district, had water available during monsoon season, but since there was no way of

    controlling the additional water, it would flow into the Arabian Sea. It was thus identified that

    extra water from Girna could be diverted in a planned way to boost the volume of available

    water in the existing water network. Only short linkages were created between already present

    t water to required areas.

    Using Strengths of Local Topography

    Due to a widespread power crisis, and the high cost of installing electric pumps to facilitate the

    flow of water, the administration opted to exploit the geographical strengths of the region

    towards improving the flow of water. The natural contours were identified through a baseline

    study and the route for link canals were decided after that. This helped in keeping the cost of

    Extensive Field Assessment

    mplemented after doing a baseline assessment to understand the local

    conditions and needs. Villagers and agriculturalists were approached to comprehend the

    current scenario of water availability.. This helped in planning the routes in a well

    er and also to gain support from the villagers as they became aware of the project

    Participatory Approach

    The absence of any objection from various sections of society makes this project unique. The

    administration proactively included all stakeholders in the planning process to gather support

    and build confidence. Villagers were educated about benefits of the project and encouraged to

    be a part of it. As mentioned previously, land for creating new link canals were donated by the

    mpensation from the government.

    The project was implemented success because of the strong leadership offered by the

    administration and namely, the District Collector. With a background in civil engineering, he

    alise the project for the region and could also anticipate the challenges.

    Research was carried out by OneWorld Foundation India (OWFI), Governance Knowledge Centre (GKC) team.

    Documentation was created by Research Associate, Aryamala Prasad

    information, please contact Naimur Rahman, Director, OWFI, at [email protected]

    Transparency and Accountability

    Case Study Water and Sanitation

    River Linking Project – Jalgaon, Maharashtra

    February 2011

    10

    Nashik district, had water available during monsoon season, but since there was no way of

    into the Arabian Sea. It was thus identified that

    extra water from Girna could be diverted in a planned way to boost the volume of available

    water in the existing water network. Only short linkages were created between already present

    Due to a widespread power crisis, and the high cost of installing electric pumps to facilitate the

    flow of water, the administration opted to exploit the geographical strengths of the region

    towards improving the flow of water. The natural contours were identified through a baseline

    study and the route for link canals were decided after that. This helped in keeping the cost of

    mplemented after doing a baseline assessment to understand the local

    were approached to comprehend the

    current scenario of water availability.. This helped in planning the routes in a well-organised

    er and also to gain support from the villagers as they became aware of the project

    The absence of any objection from various sections of society makes this project unique. The

    stakeholders in the planning process to gather support

    and build confidence. Villagers were educated about benefits of the project and encouraged to

    be a part of it. As mentioned previously, land for creating new link canals were donated by the

    The project was implemented success because of the strong leadership offered by the

    administration and namely, the District Collector. With a background in civil engineering, he

    alise the project for the region and could also anticipate the challenges.

    Research was carried out by OneWorld Foundation India (OWFI), Governance Knowledge Centre (GKC) team. ryamala Prasad

    [email protected]

  • Transparency and Accountability

    Governance Knowledge CentrePromoted by Department of Administrative Reforms and

    Ministry of Personnel, Public Grievances and Pensions

    Government of India

    References Jalgaon District Administration Website: Jalgaon.gov.in

    Pictures sourced from Jalgaon administration website:

    Transparency and Accountability

    Governance Knowledge Centre Promoted by Department of Administrative Reforms and Public Grievances

    Ministry of Personnel, Public Grievances and Pensions

    Researched and documented by

    OneWorld Foundation India

    Water and Sanitation

    River Linking Project

    Jalgaon District Administration Website: Jalgaon.gov.in

    Pictures sourced from Jalgaon administration website: jalgaon.gov.in/html/river_linkage.htm

    Transparency and Accountability

    Case Study Water and Sanitation

    River Linking Project – Jalgaon, Maharashtra

    February 2011

    11

    jalgaon.gov.in/html/river_linkage.htm

  • Transparency and Accountability

    Governance Knowledge CentrePromoted by Department of Administrative Reforms and

    Ministry of Personnel, Public Grievances and Pensions

    Government of India

    Appendix A – Interview Questionnaire1. It is impressive to know that project was planned and executed within 4 months. What

    steps were taken to complete the project in such a short amount of time?

    2. Who are the stakeholders in this project? What are their roles and responsibilities?

    a. How did the administration coordinate between different stakeholders to ensure

    on time completion?

    3. River linking is a technical project that needs a good geographical understanding of

    area. What kind of technical guidance was available for the project?

    a. Was there any use of GIS mapping to plan/execute the project?

    4. How were the water bodies for river connectivity identified?

    5. The project seems to have utilised natural contours to mak

    direction. Was new infrastructure built to channel the water? If so, what?

    6. The design of the project relies on excess water from Girna dam to provide water for

    rivers. Is that the only source of water? What happens when the wa

    low?

    a. Is there any monitoring mechanism to check the water level?

    7. In terms of planning the project, how was the participatory approach undertaken? Was

    it at district level or village level? How did the use of participatory planning cont

    to the success of this project?

    8. Residents of Jalgaon gave their land for the project voluntarily. What motivated them?

    Was there any compensation given for the land?

    a. Often there are environmental protests against river connecting projects in India.

    How did the Jalgaon administration tackle this issue?

    9. Given that Girna dam is in Nashik district, were there any administrative issues with

    neighbouring districts?

    10. Considering that Jalgaon is a drought prone area, were there any projects in the pipeline

    to resolve water scarcity issue prior to the river linking project? What about today?

    11. How I the water situation in Jalgaon today? Has it experienced drought after 2005?

    Transparency and Accountability

    Governance Knowledge Centre Promoted by Department of Administrative Reforms and Public Grievances

    Ministry of Personnel, Public Grievances and Pensions

    Researched and documented by

    OneWorld Foundation India

    Water and Sanitation

    River Linking Project

    Interview Questionnaire It is impressive to know that project was planned and executed within 4 months. What

    steps were taken to complete the project in such a short amount of time?

    stakeholders in this project? What are their roles and responsibilities?

    How did the administration coordinate between different stakeholders to ensure

    on time completion?

    River linking is a technical project that needs a good geographical understanding of

    area. What kind of technical guidance was available for the project?

    Was there any use of GIS mapping to plan/execute the project?

    How were the water bodies for river connectivity identified?

    The project seems to have utilised natural contours to make the water flow in specific

    direction. Was new infrastructure built to channel the water? If so, what?

    The design of the project relies on excess water from Girna dam to provide water for

    rivers. Is that the only source of water? What happens when the wa

    Is there any monitoring mechanism to check the water level?

    In terms of planning the project, how was the participatory approach undertaken? Was

    it at district level or village level? How did the use of participatory planning cont

    to the success of this project?

    Residents of Jalgaon gave their land for the project voluntarily. What motivated them?

    Was there any compensation given for the land?

    Often there are environmental protests against river connecting projects in India.

    How did the Jalgaon administration tackle this issue?

    Given that Girna dam is in Nashik district, were there any administrative issues with

    neighbouring districts?

    Considering that Jalgaon is a drought prone area, were there any projects in the pipeline

    to resolve water scarcity issue prior to the river linking project? What about today?

    How I the water situation in Jalgaon today? Has it experienced drought after 2005?

    Transparency and Accountability

    Case Study Water and Sanitation

    River Linking Project – Jalgaon, Maharashtra

    February 2011

    12

    It is impressive to know that project was planned and executed within 4 months. What

    steps were taken to complete the project in such a short amount of time?

    stakeholders in this project? What are their roles and responsibilities?

    How did the administration coordinate between different stakeholders to ensure

    River linking is a technical project that needs a good geographical understanding of the

    area. What kind of technical guidance was available for the project?

    Was there any use of GIS mapping to plan/execute the project?

    e the water flow in specific

    direction. Was new infrastructure built to channel the water? If so, what?

    The design of the project relies on excess water from Girna dam to provide water for

    rivers. Is that the only source of water? What happens when the water in reservoir is

    Is there any monitoring mechanism to check the water level?

    In terms of planning the project, how was the participatory approach undertaken? Was

    it at district level or village level? How did the use of participatory planning contribute

    Residents of Jalgaon gave their land for the project voluntarily. What motivated them?

    Often there are environmental protests against river connecting projects in India.

    Given that Girna dam is in Nashik district, were there any administrative issues with

    Considering that Jalgaon is a drought prone area, were there any projects in the pipeline

    to resolve water scarcity issue prior to the river linking project? What about today?

    How I the water situation in Jalgaon today? Has it experienced drought after 2005?