Page 1: Robert Pak, FVTX Annual Review Nov 2008 1 Mechanical Integration WBS 1.8.1 Robert Pak Brookhaven National Laboratory

Robert Pak, FVTX Annual Review Nov 2008

1

Mechanical IntegrationWBS 1.8.1

Robert PakBrookhaven National Laboratory

Page 2: Robert Pak, FVTX Annual Review Nov 2008 1 Mechanical Integration WBS 1.8.1 Robert Pak Brookhaven National Laboratory

Robert Pak, FVTX Annual Review Nov 2008

2

WBS 1.8.1 Mechanical Integration

• Personnel:– Walt Sondheim:

Mechanical Project Engineer– Don Lynch:

PHENIX Chief Engineer– Robert Pak:

Integration Manager• WBS 1.8.1:

– 3Q FY08 through 4Q FY11

Page 3: Robert Pak, FVTX Annual Review Nov 2008 1 Mechanical Integration WBS 1.8.1 Robert Pak Brookhaven National Laboratory

Robert Pak, FVTX Annual Review Nov 2008

3Integration Manager’sPrimary Responsibilities:

• Coordinate mechanical design reviews with HYTEC and PHENIX engineering staff

• Coordinate safety reviews

• Coordinate installation of infrastructure in PHENIX IR

• Coordinate assembly and installation of VTX/FVTX detectors

• Work with subsystem managers to keep project on schedule and at cost

Page 4: Robert Pak, FVTX Annual Review Nov 2008 1 Mechanical Integration WBS 1.8.1 Robert Pak Brookhaven National Laboratory

Robert Pak, FVTX Annual Review Nov 2008

4

Off Project

Page 5: Robert Pak, FVTX Annual Review Nov 2008 1 Mechanical Integration WBS 1.8.1 Robert Pak Brookhaven National Laboratory

Robert Pak, FVTX Annual Review Nov 2008

5

Smaller dia Be section

Page 6: Robert Pak, FVTX Annual Review Nov 2008 1 Mechanical Integration WBS 1.8.1 Robert Pak Brookhaven National Laboratory

Robert Pak, FVTX Annual Review Nov 2008

6

New Be beam pipe schedule

• Sole source justification completed• BNL paperwork for procurement in progress

– PPM will push for sole source– In parallel, ad placed in Fed Biz Ops

• ~ 9 mos. delivery schedule ARO– 6 mos. gun-drill Be tube– 3 mos. electron-beam weld stainless steel

cuffs• Deliver to BNL and reship to Europe for NEG

coating (6 wks.)• Install prior to RHIC Run-10

Page 7: Robert Pak, FVTX Annual Review Nov 2008 1 Mechanical Integration WBS 1.8.1 Robert Pak Brookhaven National Laboratory

Robert Pak, FVTX Annual Review Nov 2008

7NEG coating & bake-out of beam pipe

• $106k for entire 47 ft warm straight section in PHENIX• Also add ~$20k for heating jackets and misc. M&S

|------+-------------------------------------------+------------|| Item | Description | Price ||------+-------------------------------------------+------------|| 1 | 5 m long pipe CF125/CF75 (dwg 44035003-03)| $23,250.00 ||------+-------------------------------------------+------------|| 2 | 1.75 m conical pipe CF125/CF75 (dwg | $12,450.00 || | 44035003-04) | ||------+-------------------------------------------+------------|| 3 | 0.55 m pipe CF75/CF40 (dwg 105-0500-40 | $12,000.00 || | -part 01) | ||------+-------------------------------------------+------------|| 4 | 2.03 m pipe CF75/CF40 (dwg 105-0500-40- | $12,000.00 || | part 02) | ||------+-------------------------------------------+------------|| 5 | 1.8 m long pipe, CF 125 | $12,450.00 ||------+-------------------------------------------+------------|| 6 | 2.57 m long Be-section pipe, CF 35 ( dwg | $27,750.00 || | 002 0500-019) | ||------+-------------------------------------------+------------|

• Quote from SAES Getters SpA, Lainate, Italy :

Page 8: Robert Pak, FVTX Annual Review Nov 2008 1 Mechanical Integration WBS 1.8.1 Robert Pak Brookhaven National Laboratory

Robert Pak, FVTX Annual Review Nov 2008

8Additional stainless sections

D. Lynch has RFQ into Central Shop

Page 9: Robert Pak, FVTX Annual Review Nov 2008 1 Mechanical Integration WBS 1.8.1 Robert Pak Brookhaven National Laboratory

Robert Pak, FVTX Annual Review Nov 2008

9A-frame Support Structure

• BNL responsibility• HYTEC to provide

tolerance and mechanical requirements along with STEP translation files for the isolation mounts

• Kick-off on Sept. 11th BNL, LANL & HYTEC

Page 10: Robert Pak, FVTX Annual Review Nov 2008 1 Mechanical Integration WBS 1.8.1 Robert Pak Brookhaven National Laboratory

Robert Pak, FVTX Annual Review Nov 2008

10

Magnet Bridge

Shared infrastructure for VTX/FVTX/RPC electronics

Page 11: Robert Pak, FVTX Annual Review Nov 2008 1 Mechanical Integration WBS 1.8.1 Robert Pak Brookhaven National Laboratory

Robert Pak, FVTX Annual Review Nov 2008

11

Platform InfrastructureCooling manifolds and cable trays

Cooling watersupply and return

Electrical service for the bridge

Photos by D. Lynch

Page 12: Robert Pak, FVTX Annual Review Nov 2008 1 Mechanical Integration WBS 1.8.1 Robert Pak Brookhaven National Laboratory

Robert Pak, FVTX Annual Review Nov 2008

12

Rack lay-out

New Platform

HBD/RXNP(not shown)

MuTrgrFEE N

MuTrgrFEE S

VTX Power

FVTX

RPC1 S

RPC1 N

New Platform

RPC1 NS

VTX FEM

CAD courtesy of D. Lynch

More details in next talk from

E. Mannel

Page 13: Robert Pak, FVTX Annual Review Nov 2008 1 Mechanical Integration WBS 1.8.1 Robert Pak Brookhaven National Laboratory

Robert Pak, FVTX Annual Review Nov 2008

13

Bleed the boil-off5200 gal. capacity

LN2 Storage Dewar for Dry Nitrogren System shared by BBC/VTX/FVTX

Dry N2 System

Page 14: Robert Pak, FVTX Annual Review Nov 2008 1 Mechanical Integration WBS 1.8.1 Robert Pak Brookhaven National Laboratory

Robert Pak, FVTX Annual Review Nov 2008

14

Summary

• Beam pipe procurement underway

• External cooling system falls under VTX project (to start later in FY09)

• Detector support structure started in FY08

• Power & water in IR: progress off project

• Infrastructure for dry N2 system completed

Page 15: Robert Pak, FVTX Annual Review Nov 2008 1 Mechanical Integration WBS 1.8.1 Robert Pak Brookhaven National Laboratory

Robert Pak, FVTX Annual Review Nov 2008

15Summary:WBS 1.8.1 Cost & Schedule

• Cost $271k• Cost Basis Labor rates• Cost Contingency 14%• Schedule 3Q FY08 – 4Q FY11• Schedule Contingency None• Risk Low

Page 16: Robert Pak, FVTX Annual Review Nov 2008 1 Mechanical Integration WBS 1.8.1 Robert Pak Brookhaven National Laboratory

Robert Pak, FVTX Annual Review Nov 2008

16

Summary: WBS 1.8.1 Technical

• Specification Document: TDR

• Workforce (On project): – WBS 1.8.1, Mech. Eng. 1/3 FTE/Year– Scope: Duration of project

• Institutions Involved: LANL/BNL

• Infrastructure Defined: Draft