romtech _ products _ beamform on-site - toe beams
TRANSCRIPT
7/29/2019 ROMTECH _ Products _ Beamform on-Site - Toe Beams
http://slidepdf.com/reader/full/romtech-products-beamform-on-site-toe-beams 1/2
8/30/13 ROMTECH | Products | Beamform On-Site - Toe Beams
www.rom-tech.co.uk/products/beamform_on_site_toe_beams.aspx 1/2
Home >> Products >> Groundworks >> Beamform>> Beamform On-Site >> Beamform On-Site - Toe Beams
Beamform On-Site - Toe Beams
A further way in which we can demonstrate the flexibility of Beamform is in its utilisation to form toe beams at a raft edge.
The pictures below show a semi detached house plot on a major UK house builders’ site. The house builder was concerned with the program delays and waste
being generated by using traditional methods of construction (strip/bent mesh, ‘Z’ bars, straight rebar and standard sheets of mesh). This particular house typ
required 4-5 days to complete, allowing concrete to cure between 2 pours, with materials costing £562 (6 uses allowed on timber formwork) and labour costing
£606 (Total cost of £1168).
The ROMTECH solution was to re-design the house type to incorporate prefabricated toe beam cages, Beamform permanent formwork and mesh manufacture
to suit the house type as an improved method of construction. Approval was given on the re-design by both the Structural Engineer and the NHBC. The materi
cost for these components was £771 and these were installed in 1 day at a labour cost of £230 (Total cost of £1001).
Since there were 150 houses on this site to complete, with varying house types, it soon became apparent to the house builder that our method was the way
forward. This was proved by the fact that the savings on this house type alone, due to the change in the method of construction, meant that the remaining
plots of this type (21No), were in effect FREE OF CHARGE.
The effect on programme, (4 plots of this type prepared Monday to Thursday and all poured Friday), meant that the following trades were not competing for
space, plant or other machinery.
The financial savings to the house builder relating to finance and interest charges were such that this is now their preferred method of construction.
The differences between the two forms of construction can clearly be seen from the photographs below. These show how modern methods of construction in
conjunction with Value Engineering, of f-site Prefabrication, Best Practice and ROMTECH Groundworks’ experience can clearly demonstrate that the cheapest
price is not always the best value.
Traditional Method Beamform Method
Traditional Method Beamform Method
Using Timber Formwork, installat ion through Installed and Poured in ONE DAY!
to pouring can take 4-5 DAYS!
Add t o enquiry list
7/29/2019 ROMTECH _ Products _ Beamform on-Site - Toe Beams
http://slidepdf.com/reader/full/romtech-products-beamform-on-site-toe-beams 2/2
8/30/13 ROMTECH | Products | Beamform On-Site - Toe Beams
www.rom-tech.co.uk/products/beamform_on_site_toe_beams.aspx 2/2
Make an enquiry Email this item Print this page
Related Products:
Beamform On-Site - Prefab Cages and Beamform
Beamform On-Site - Toe Beams
Beamform Other Applications
© Part of the ROM Group of Companies | Terms & Conditions | Legal notice | Privacy statement | Terms & Conditions of Trading