rp: prc: anjing reservoir subproject in pingyi county ... · anjing reservoir was performed. the...

42
Resettlement Planning Document The resettlement plan is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature. Document Stage: Final Project Number: 40683 August 2010 PRC: Risk Mitigation and Strengthening of Endangered Reservoirs in Shandong Province Project Final Resettlement Plan for Anjing Reservoir Subproject in Pingyi County (English) Prepared by the Shandong Provincial Government.

Upload: hoanglien

Post on 26-Apr-2019

217 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: RP: PRC: Anjing Reservoir Subproject in Pingyi County ... · Anjing Reservoir was performed. The reservoir is judged as grade-Ⅲ dilapidated reservoir, and this result was checked

Resettlement Planning Document

The resettlement plan is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature.

Document Stage: Final Project Number: 40683 August 2010

PRC: Risk Mitigation and Strengthening of

Endangered Reservoirs in Shandong Province

Project

Final Resettlement Plan for Anjing Reservoir

Subproject in Pingyi County (English)

Prepared by the Shandong Provincial Government.

Page 2: RP: PRC: Anjing Reservoir Subproject in Pingyi County ... · Anjing Reservoir was performed. The reservoir is judged as grade-Ⅲ dilapidated reservoir, and this result was checked

Pingyi county Anjing Reservoir Risk Mitigation Project

Under

Risk Mitigation of Endangered Reservoir Project

in Shandong Province

Of

The People’s Republic of China

Resettlement Plan

Water Resources Design and Research Institute of Shandong Province

December 2009

Page 3: RP: PRC: Anjing Reservoir Subproject in Pingyi County ... · Anjing Reservoir was performed. The reservoir is judged as grade-Ⅲ dilapidated reservoir, and this result was checked

Letter of Endorsement

Pingyi county Water Resources Department (PCWRD) received the approval of constructing the Risk Mitigation of Anjing Reservoir Project in Pingyi county from the related departments. This Project is proposed to be started in Jan. 2010, and completed by November 2010. Pingyi county Government, through Ministry of Finance, has requested a loan from the Asian Development Bank (ADB) to finance part of the Project. Accordingly, the Project will be implemented in compliance with ADB social safeguard policies. This Resettlement Plan (RP) represents a key requirement of ADB and will constitute the basis for land acquisition and resettlement. The RP fully complies with requirements of the relevant laws, regulations and policies of the People’s Republic of China (PRC), Shandong Province and Pingyi county Government as well as complies with ADB’s policy on involuntary resettlement.

Pingyi county Government and PCWRD hereby affirm the contents of this Resettlement Plan prepared dated in October 2009 and ensures that the resettlement will be made available as stipulated in the budget. PCWRD has discussed the draft resettlement Plan with relevant local officials and has obtained their concurrence. Pingyi county Anjing Reservoir Project Management Bureau under Pingyi county Government was authorized as the responsible agency to manage the implementation of the Project and related resettlement activities.

Governor, Pingyi county Government

___________________ (signature)

___________________ (date)

Page 4: RP: PRC: Anjing Reservoir Subproject in Pingyi County ... · Anjing Reservoir was performed. The reservoir is judged as grade-Ⅲ dilapidated reservoir, and this result was checked

Abbreviation

ADB Asian Development Bank

AHs Affected Households

APs Affected Persons

EA Executing Agency

EIA Environmental Impact Assessment

FSR Feasibility Study Report

IA Implementing Agency

IMA Independent Monitoring Agency

PLAB Pingyi Land Administration Bureau

LAR Land Acquisition and Resettlement

PCG Pingyi county Government

PCWRD Pingyi county Water Resources Department

M&E Monitoring and Evaluation

ARPMB Anjing Reservoir Project Management Bureau

PMO Project Management Office

PPTA Project Preparatory Technical Assistance

PRC People’s Republic of China

RP Resettlement Plan

SPMO Shandong Project Management Office

SES Socioeconomic Survey

TA Technical assistance

TOR Terms of reference

Page 5: RP: PRC: Anjing Reservoir Subproject in Pingyi County ... · Anjing Reservoir was performed. The reservoir is judged as grade-Ⅲ dilapidated reservoir, and this result was checked

Table of Contents

EXECUTIVE SUMMARY ............................................................................................................................. 1

I. INTRODUCTION ................................................................................................................................. 2

1.1 PROJECT BACKGROUND ............................................................................................................ 2 1.2 PROJECT DESCRIPTION……………………………………………………………………………….3

II. IMPACTS OF LAND ACQUISITION AND RESETTLEMENT ............................................... 5

2.1 MEASURES TAKEN TO AVOID OR MINIMIZE LAR IMPACTS ............................................................ 5 2.2 PHYSICAL INDICES SURVEY ....................................................................................................... 5 2.3 SCOPE OF LAND ACQUISITION AND RESETTLEMENT ................................................................... 5

III. SOCIO-ECONOMIC PROFILE IN AFFECTED AREAS ........................................................... 8

3.1 SOCIO ECONOMIC PROFILE OF PINGYI……………………………………………………………….8 3.2 SOCIO-ECONOMIC PROFILE OF AFFECTED TOWNSHIP ................................................................ 8 3.3 SOCIO-ECONOMIC PROFILE OF AFFECTED VILLAGE .................................................................... 8 3.4 SOCIO-ECONOMIC SITUATION OF AFFECTED HOUSEHOLDS ........................................................ 8

3.4.1 Population Distribution by Age ............................................................................................ 9 3.4.2 Population Distribution by Education ................................................................................. 9 3.4.3 Productive Resources .......................................................................................................... 9 3.4.4 Household Annual Income and Expenditure .................................................................... 9

IV. POLICY FRAMEWORK, ENTITLEMENT AND COMPENSATION .................................... 13

4.1 APPLICABLE LAWS, REGULATIONS & POLICIES FOR RESETTLEMENT ......................................... 13 4.2 OBJECTIVES AND PRINCIPLES OF RESETTLEMENT .................................................................... 13 4.3 ELIGIBILITY OF COMPENSATION ................................................................................................ 14 4.4 COMPENSATION STANDARDS ................................................................................................... 14

4.4.1 Compensation Standards for Permanent Land Acquisition ................................................ 14 4.4.2 Compensation Standard for temporary Land use ................................................................ 14 4.4.3 Compensation Standards for Attachments ........................................................................... 15

4.5 ENTITLEMENT.......................................................................................................................... 15

V. REHABILITATION MEASURES ..................................................................................................... 16

5.1 OBJECTIVES OF RESETTLEMENT .............................................................................................. 16 5.2 REHABILITATION PLAN FOR PERMANENT LAND ACQUISITION ..................................................... 16

5.2.1 Rehabilitation Plan for Affected Households ........................................................................ 16 5.3 RESTORATION MEASURES FOR TEMPORARY LAND OCCUPATION .............................................. 17 5.4 RESTORATION MEASURES FOR GROUND-ATTACHMENTS .......................................................... 17 5.5 TRAINING FOR THE AFFECTED PERSONS .................................................................................. 17 5.6 JOB OPPORTUNITIES FROM THE PROJECT ................................................................................ 18 5.7 INCOME RESTORATION PLAN OF WOMEN ................................................................................. 18

VI. COST ESTIMATE AND IMPLEMENTATION SCHEDULE .................................................... 19

6.1 RESETTLEMENT COST ............................................................................................................. 19 6.2 MANAGEMENT AND DISBURSEMENT OF RESETTLEMENT FUNDS ................................................ 19

VII. POST-RESETTLEMENT PROGRAM FOR ORIGINAL RESETTLERS ............................... 21

7.1 POST-RESETTLEMENT PROGRAM FOR RESETTLERS IN RESERVOIR AREA ................................. 21 7.1.1 Background and Remaining Issues ....................................................................................... 21

7.1.2 Post-resettlement Support Approaches ................................................................................ 21 7.2 POST-RESETTLEMENT SUPPORT IN RESERVOIR AREA .............................................................. 22

VIII. IMPLEMENTATION SCHEDULE .......................................................................................... 23

IX. PUBLIC PARTICIPATION AND GRIEVANCE REDRESS .................................................. 24

Page 6: RP: PRC: Anjing Reservoir Subproject in Pingyi County ... · Anjing Reservoir was performed. The reservoir is judged as grade-Ⅲ dilapidated reservoir, and this result was checked

9.1 PUBLIC PARTICIPATION ............................................................................................................ 24 9.2 GRIEVANCE PROCEDURE ......................................................................................................... 24

X. INSTITUTIONAL ARRANGEMENT .......................................................................................... 26

10.1 RESPONSIBLE INSTITUTIONS FOR RESETTLEMENT IMPLEMENTATION ....................................... 26 10.2 TRAINING PLAN FOR RESETTLEMENT MANAGEMENT STAFF .................................................... 27

XI. MONITORING AND EVALUATION ............................................................................................... 28

APPENDIX 1 APPLICABLE LAWS AND REGULATIONS ................................................................. 29

APPENDIX 2 TERMS OF REFERENCE FOR EXTERNAL MONITORING ..................................... 35

Page 7: RP: PRC: Anjing Reservoir Subproject in Pingyi County ... · Anjing Reservoir was performed. The reservoir is judged as grade-Ⅲ dilapidated reservoir, and this result was checked

1

Executive Summary

Anjing Reservoir used to be a mini-(1) type reservoir built in June 1958 and extended to a medium one in December 1966. Since Anjing Reservoir was built, there are many serious safety problems of the dam, spillway, and diversion tunnel. Therefore, it is urgent to carry on the risk mitigation and strengthening and reinforcement of Anjing Dam and Reservoir, eliminate all kinds of dangers in the project in order to make it operate normally, and perform its proper economic benefits and social benefits of flood prevention, irrigation, aquiculture, and so on.

Based on the field survey for Construction Map Design (CMD), no inundation impacts are caused by the Project. However, the land requisition of the spillway construction will acquire 4.2 mu irrigable land, involving Liangjiaya village of Bianqiao town. 5 households with 29 persons will be affected by permanent land acquisition. All lands are farmer contracted land. Land acquisition of temporary road, facilities for construction will acquire 110.8 mu arable land, involving Liangjiaya village of Bianqiao town. 39 households with 120 persons will be affected by temporary land acquisition. The other engineering construction organization activities are all within the scope of reservoir management and only affect the ground attachment of some trees and some special facilities. The total cost for land acquisition and resettlement is CNY 388,318.9.

According to the “Notice on the Adjustment of Land occupying Annual Production And Compensation Standard, which is forwarded by General Office of Shandong Provincial People’s Government, and issued by Shandong Province People's government Office” Luzhengbanfa [2004] No.51, project influenced area, Pingyi, belongs to the forth-class areas. The Annual Average Output Value (AAOV) of the forth-class area is 1,200 Yuan per mu. Land compensation for arable land is 8 times of AAOV, and resettlement subsidy for farmland is 8 times of AAOV. So the total arable land compensation standard is 19,200 Yuan/Mu. For the temporary occupied land, the compensation fee per year calculated by per mu output of arable land is 1200 yuan.

According to the field interview, the affected village and all affected households agree adjust land within the village. The compensation directly paid for village will be used in 2 ways: I) improve the village road; ii) improve the irrigated infrastructure.

The APs have participated in the planning process and their concerns have been integrated into the RP. The draft RP will be distributed to the affected village in Jan. 2010. In accordance with ADB’s public communications policy, the draft RP will be posted on the ADB website prior to loan appraisal. An effective and transparent channel for lodging complaints and grievances has been established, and relevant institutions shall accept the complaints and grievances lodged by the APs free of charge. The reasonable costs incurred shall be covered by the contingency of the project.

In order to implement RP successfully and achieve the goals of resettlement, the implementation of RP will be subject to internal and external monitoring according to ADB resettlement policies. The external monitoring and evaluation will be done by an independent monitoring agency (IMA). The external monitoring and evaluation institution shall undertake regular monitoring and evaluation of the resettlement implementation activities and provide necessary consultative proposals.

Page 8: RP: PRC: Anjing Reservoir Subproject in Pingyi County ... · Anjing Reservoir was performed. The reservoir is judged as grade-Ⅲ dilapidated reservoir, and this result was checked

2

I. INTRODUCTION

1.1 Project Background

1. Anjing Reservoir used to be a mini-(1) type reservoir built in June 1958 and extended to a medium one in December 1966. The dam, drainage tunnel, the open spillway were finished in May 1967 and the spillway gate was built in March 1968 and finished in December the same year. The upstream of the reservoir is low mountain relief and its water catch area is 35.12 km2; the main buildings include the main dam, the secondary dam, the spillway and the water release tunnel.

2. The original construction of Anjing Reservoir inundated a village. Based on the “Shandong Rural Resettlers Registration and Ratification Method of Large and Medium-sized Reservoirs”, totally 158 households or 429 persons were involved in resettlement. All resettlers were resettled in Bianqiao town.

3. Since Anjing Reservoir was built under the abnormal state that planning, designing, and constructing were conducted simultaneously, so the standard of engineering construction is somewhat low and the quality of construction is bad. There are many serious safety problems of the dam, spillway, and diversion tunnel. After 20 years of operation, the project begins aging. And during operation, it has exposed a series of hidden defect which affects safety of the dam. Particularly, the current flood control capacity of the reservoir cannot meet the Recent Standards issued by Ministry of Water Resources; the upstream reservoir’s dry stone pitching is broken; the dam has the potential safety hazard of seepage and drainage facilities are not complete; the drainage tunnel gate’s upstream apron is badly broken and the absorption basin and apron cannot meet the requirements of resisting impact; the outlet channel influences flood discharge safety; the drainage tunnel body has cracks and leaks water and the gate and hoist equipment are seriously aging; observation facilities of the dam are lacking; engineering administrative conditions are backward and the facilities are old-fashioned. In 2007, according to the Ministry of Water Conservancy Reservoir Dam Safety Evaluation Method, the Department of Water Conservancy of Shandong, safety evaluation on

Anjing Reservoir was performed. The reservoir is judged as grade-Ⅲ dilapidated reservoir,

and this result was checked by Dam Safety Management Center under Ministry of Water Conservancy. Figure 1-1 is the sketch map of Anjing Reservoir.

4. Anjing reservoir is located 20km east of Pingyi county seat. It is a medium-sized reservoir on Jinxianhe River—tributary of Junhe River of Yihe River water system. The upstream reservoir is low mountains and hills. The control catchment area is 35.12km2. Jinxianhe River originates from Mengshan mountain range, which belongs to the ephemeral streams, whose

course is short and whose flow is quick. The bed width is usually 70~150m. The riverway’s

average slope is 2.18%. In the downstream Anjing Reservoir, there are two towns and main lines of communication such as 327 national highway, Yanshi railway, Ri-Dong expressway and Wensi road. The geographical position of the reservoir is vital. In order to guarantee the safety of towns, communications, industrial and mining enterprises and the masses in the downstream reservoir, it is quite necessary to carry out the danger removal and reinforcement engineering of the reservoir, remove hidden dangers, meet design standards, guarantee safe operation of the reservoir, give full play to its economic benefits and social benefits in flood control, irrigation and aquaculture, ease supply and demand conflict of the local water resources, promote rapid development of economy, and improve the standard of living of the local urban and rural people. The local government and people also press for this.

Page 9: RP: PRC: Anjing Reservoir Subproject in Pingyi County ... · Anjing Reservoir was performed. The reservoir is judged as grade-Ⅲ dilapidated reservoir, and this result was checked

3

1.2 Project Description

5. The project works include: to reinforce the main dam and to reinforce and lengthen the secondary dam to make them meet the flood control standards and requirements; to deal with the problem of seepage of the dam and reinforce it; to reconstruct or construct the upstream slope protection; to reconstruct the drainage facility of the downstream slope surface; to rebuild the downstream displacement hull; to rebuild and reconstruct the spillway gate; to rebuild the drainage tunnel and hoisting equipment; to improve the management facilities and add observation facilities. The time limit of the project is two and a half years, from July 2008 to December 2010.

6. The overall risk mitigation works was divided into 2 phases. The first phase started in Aug. 2008, including reinforces the main dam and reconstructs the drainage facility of the downstream slope surface. The above-mentioned engineering works and corresponding construction activities were implemented on unused land within the existing reservoir management scope, so no land acquisition or temporary land use impacts were involved. The other parts of the engineering works were followed into the 2nd phase, referred as the Project.

7. Based on the field survey for Construction Map Design (CMD), the engineering risk mitigation and strengthening does not raise the storage reservoir nor the elevation of dam crest. Therefore, it does not increase the inundation-affected area of upstream reservoir area. According to the hydrological data computation, the one-in-50-year flood level of upstream reservoir is 154m. And according to the reconnaissance to the upstream reservoir there are no inundation impacts caused by the Project. However, the land requisition of the spillway construction will acquire 4.2 mu irrigable land, involving Liangjiaya village of Bianqiao town. 5 households with 29 persons will be affected by permanent land acquisition. All land are farmer contracted land. Land acquisition of temporary road, facilities for construction will acquire 110.8 mu arable land, involving Liangjiaya village of Bianqiao town. 39 households with 120 persons will be affected by permanent land acquisition. The other engineering construction organization activities are all within the scope of reservoir management and only affect the ground attachment of some trees and some special facilities. The total cost for land acquisition and resettlement is CNY 388,318.9.

8. The Project is planned to start in Jan. 2010 and be completed in December 2010; project construction period is 12 months. The Project construction will necessitate permanent land acquisition, temporary land occupy. To mitigate the impacts, the short resettlement plan (RP) has been prepared by Shandong Water Resources Surveying and Design Institute on behalf of Anjing Reservoir Management Bureau in line with the Asian Development Bank’s (ADB) Involuntary Resettlement Policy (1995) and the relevant laws, regulations and guidelines issued by the governments of People’s Republic of China (PRC) and Shandong Province.

Page 10: RP: PRC: Anjing Reservoir Subproject in Pingyi County ... · Anjing Reservoir was performed. The reservoir is judged as grade-Ⅲ dilapidated reservoir, and this result was checked

4

Figure 2.1 shows the Anjing Reservoir and the project area.

Page 11: RP: PRC: Anjing Reservoir Subproject in Pingyi County ... · Anjing Reservoir was performed. The reservoir is judged as grade-Ⅲ dilapidated reservoir, and this result was checked

5

II. IMPACTS OF LAND ACQUISITION AND RESETTLEMENT

2.1 Measures Taken to Avoid or Minimize LAR Impacts

9. In order to avoid or reduce LAR impacts to the minimum, engineering alternatives have been carefully reviewed and the optimal option has been adopted during the Project design phase. All engineering works except broaden spillway will be implemented within the reservoir management property and has no negative impacts on people’s lives. At the same time, various compensation measures are prepared for affected persons who are unavoidably affected by land acquisition for the project. During the construction phase, a reasonable construction plan has been formed before the start of construction, and the construction sites should be strictly controlled within the scope of red line and awareness of responsibilities for construction workers should be raised to minimize the land acquisition and resettlement.

2.2 Physical Indices Survey

10. The physical indices survey was conducted based on Specifications on Land Requisition and Resettlement Design for Construction of Water Resources and Hydropower Engineering (SL290-2003) in August 2009. As per the engineering CDM and the scope of land acquisition and occupation, the detailed investigation of each physical index in engineering construction land acquisition scope was measured and recorded on August 24-25, 2009. The participants in survey include staff of Anjing Reservoir Management Bureau, the Design Institute, the affected town government and involved Villages.

2.3 Scope of Land Acquisition and Resettlement

11. The land requisition of broadened spillways will acquire 4.2 mu irrigable land permanently, involving Liangjiaya village of Bianqiao town. 5 households with 29 persons will be affected by permanent land acquisition. All land is farmer contracted land. Table 2-1 and Table 2-2 provide the details of impact of permanent land acquisition. Although the land loss per household ranges from 12% to 32%, the income loss only ranges from 0.3% to 9% because these farmers have substantial non-farm income sources. Replacement land is available within the village which can be allocated to APs to ensure their income will be restored. No vulnerable people will be affected. Figure 2-1 shows the land for spillways to be affected.

Table 2-1 Summary of Permanent Land Acquisition of Flood Control Road

town village No. of

household Number of

people

Current land

(mu)

Affected land Land loss rate

per household

(%) Irrigable land

Miao

zi

Nan

fuwang

1 5 3.5 0.8 0.22

2 9 6.3 0.8 0.12

3 6 4.2 0.8 0.19

4 5 3.5 0.9 0.25

5 4 2.8 0.9 0.32

total 5 29 20.3 4.2

Page 12: RP: PRC: Anjing Reservoir Subproject in Pingyi County ... · Anjing Reservoir was performed. The reservoir is judged as grade-Ⅲ dilapidated reservoir, and this result was checked

6

Table 2-2 Impact Analysis of Permanent Land Acquisition

Range of Land Loss Ratio Range of income Loss Ratio

Anjing Village

AHs (No.)

Percentage (%)

1% - 10% n.a. 0 0%

11% - 25% 0.3%-7.5% 4 80%

26% - 35% 7.8%-9% 1 20%

TOTAL 5 100%

Figure 2-1 land to be affected by

spillways

12. Temporary land acquisition means the land temporarily used during the project construction period, including earth and rock material area, construction plant, construction warehouse, temporary living areas during the construction period and temporary road area. The project temporarily occupies 110.8 mu land, involving Liangjiaya village of Bianqiao town. 39 households with 120 persons will be affected by temporary land acquisition. It is shown in Table 2-3.

Table 2-3 Temporary land acquisition of Anjing Reservoir Project unit: mu

County Township Village Total Arable land(mu)

Pingyi Bianqiao Liangjiaya 110.8 110.8

13. This project influences some ground attachments including 825 poplars.

14. Land acquisition for permanent use reaches 4.2 mu of the project, all land are farmer contracted land of Liangjiaya village. 5 households with 29 persons are affected by permanent land acquisition and 39 households with 120 persons are affected by temporary land use of the project (see Table 2-4). The farmers average lost land 0.14 mu per capita.

Table 2-4 Summary of Survey of the Impact of Land Acquisition of Pingyi Anjing Reservoir Danger Removal and Reinforcement Project

Item Unit Total Bianqiao Town

Ⅰ Administrative region

Page 13: RP: PRC: Anjing Reservoir Subproject in Pingyi County ... · Anjing Reservoir was performed. The reservoir is judged as grade-Ⅲ dilapidated reservoir, and this result was checked

7

Item Unit Total Bianqiao Town

1. Township (office) number 1 1

2. Administrative village (residential

committee) number 1 1

Ⅱ Population affected by the project

1. Affected by permanent land

acquisition

Household number 5 5

Population number 29 29

Include: Population to be

resettled for production

number 15 15

2. Affected by temporary land

acquisition

Household number 39 39

Population number 120 120

3. Total population affected by the

project 149 149

Ⅲ Attachments

1. poplar number 825 825

Ⅳ Permanent land acquisition mu

Collective land mu 4.2 4.2

1. irrigable land mu 4.2 4.2

Ⅴ. Temporary land occupation mu

Arable land mu 110.8 110.8

15. Anjing Reservoir is located in mountainous area surrounded by waste hills with deep slopes, which is not suitable for farming. Based on the “Anjing Reservoir Management and Protection Method” issued by Pingyi county Government, it is prohibited to farm land and graze within reservoir management scope in order to protect water quality. The reservoir management scope include: i) reservoir below utilization benefit level; ii) dam protection area including 200m beyond the foot of dam slope ; iii) channel protection area including 40m beyond the foot of the main canal slope; iv)water conservancy structures protection area including 50m beyond the side line of the main structures. Consequently, there are no crops being grown within the drawdown zone, so there will be no impact when the reservoir is filled to its originally designed full storage level.

16. According to the field investigation, all the affected persons are Han (i.e., no ethnic minority people) and there are no vulnerable persons affected by this project.

Page 14: RP: PRC: Anjing Reservoir Subproject in Pingyi County ... · Anjing Reservoir was performed. The reservoir is judged as grade-Ⅲ dilapidated reservoir, and this result was checked

8

III. SOCIO-ECONOMIC PROFILE IN AFFECTED AREAS

17. From August, 2009, Anjing Reservoir Project Management Bureau and the Design Institute organized an investigating group to investigate the impacts of land acquisition by the Project. At the same time, socio-economic information of the APs was also collected. This survey on socio-economic conditions of the affected households is carried out by one by one interview.

3.1 Socio-economic Profile of Pingyi

18. Pingyi county governs 16 townships, 1056 administrative villages, with a total population of 991.1 thousand people. Its economy grew rapidly in 2008, and its GDP has reached 10.8 billion, 26% more than that in 2007. The output value of primary industry is 1.808 billion Yuan, an increase of 9.1%; the secondary industry 5.5 billion Yuan, an increase of 31%; the tertiary industry 3.492 billion Yuan, an increase of 27.2%. The annual per capita net income of farmers is 7,384 Yuan, 15% more than that in 2007.

3.2 Socio-economic Profile of Affected Township

19. One township (Bianqiao) is affected by land acquisition, details are as follows:Bianqiao Township is situated in the southeast 22 kilometers of Pingyi County, with an area of 131 square kilometers, total population 42,000 including 3,000 urban population and 39,000 rural

populations. There is 29,970 h ㎡ of farmland. The annual per capita net income of farmers is

7293 Yuan, which is relatively high1.

3.3 Socio-economic Profile of Affected Village

20. One village (Liangjiaya Village) is affected by land acquisition. The basic socio-economic condition of the Liangjiaya Village is shown in Table 3-1. The socio-economic survey indicates that Liangjiaya Village is situated 23km south-east of Pingyi county. The total farmland of the village is 921 mu in 2008.

Table 3-1 Socio-economic Survey of Liangjiaya Village

county town village

Present arable

land area

Total

Population

Average per person net

income(RMB)

(mu) (people) agriculture other total

Pingyi Bianqiao Liangjiaya 650 921 1750 4450 6200

3.4 Socio-economic Situation of Affected Households

21. In Aug. 2009, Anjing Reservoir Management Bureau carried out a questionnaire investigation in Anjing village on the 5 affected households. The characteristics of the surveyed population can be seen in

22.

23. Table 3-2.The survey indicates that most of the affected laborers go out for migrate work. Their agricultural income accounts for 30% of their total income. The per capita farmland is 0.7 mu. The average per capita loss of land is 0.14 mu (20% of their farmland).

1 The poverty line for rural households is 1196 yuan per capita per year.

Page 15: RP: PRC: Anjing Reservoir Subproject in Pingyi County ... · Anjing Reservoir was performed. The reservoir is judged as grade-Ⅲ dilapidated reservoir, and this result was checked

9

Table 3-2 Statistical Characteristic of People Affected by Land Acquisition

Item Quantity %

agricultural population 26 90%

non-agricultural population 3 10%

gender

woman 14 48%

Labor force 15 52%

student 3 10%

others 2 7%

Age

≤6 years old 2 7%

6-16 years old 3 10%

16-60 years old 21 72%

≥60 years old 3 10%

Education

illiterate and almost illiterate 2 7%

primary schooling 6 21%

middle school schooling 18 62%

high school schooling 2 7%

college schooling and above 1 3%

3.4.1 Population Distribution by Age

24. Among 29 surveyed persons in 5 households, 2 persons are under 6 years old, accounting for 7% of total population; 3 persons are ranging from 6 to 16 years old, accounting for 10% of total population; 21 persons are ranging from 16 to 60 years old, accounting for 72% of total population; 3 persons are above 60 years old, accounting for10% of total population.

3.4.2 Population Distribution by Education

25. Among 29 surveyed persons in 5 households, 2 persons are illiterate and almost illiterate, accounting for 7% of total population; 6 persons are primary schooling, accounting for 21%; 18 persons are ranging middle school schooling, accounting for 62% of total population; 2 persons are high school schooling, accounting for 7% of total population; 1 persons are college schooling and above, accounting for 3% of total population.

3.4.3 Productive Resources

26. Among 29 surveyed persons in 5 households, the total farmland is 20.3 mu, with 0.7 mu per capita.

3.4.4 Household Annual Income and Expenditure

27. According to the 5 households’ statistical data, the total annual gross family income is 36714 yuan in 2008. Among them: the crop production income is 10585 yuan accounting for

Page 16: RP: PRC: Anjing Reservoir Subproject in Pingyi County ... · Anjing Reservoir was performed. The reservoir is judged as grade-Ⅲ dilapidated reservoir, and this result was checked

10

29%; the animal husbandry income is 3944 yuan accounting for 11%; going out and hiring out for working income is 19575 yuan accounting for 53%; and other incomes are 2610 accounting for 7%. According to the 5 households’ statistical data, the total annual family expenditure was 26680 yuan in 2008. Among them: buying the seed, agricultural chemicals and the chemical fertilizer expenditure is 5220 accounting for 20%; the water, the electricity and fuel fee is 580 yuan accounting for 2%; the mechanical work expense is 1,160 yuan accounting for 4%; the education and the medical expense is 5,220 yuan accounting for 20%; the daily life fee is 14500 yuan accounting for the total family expense of 54%. According to the analysis of the survey result, the average per capita gross income is 6330 yuan, among them 29% from the agriculture which show that the farmers have much dependence on the land. Income and Expenditure structure is shown in Table 3-3.

Table 3-3 Annual Income and Expenditure Structure of Affected Households

item

Per household)

Income

(Yuan)

Per capita

Income

(Yuan/person)

Proportion (%)

Gross Annual

family Income

Crop production 10585 1825 29

animal husbandry 3944 680 11

Work outside 19575 3375 53

other 2610 450 7

Total 36714 6330

Annual family

expenditure

Seed, pesticide and

chemical fertilizer 5220 900 20

Water, electricity and fuel 580 100 2 mechanical work 1160 200 4 Education and medicine 5220 900 20 Daily life 14500 2500 54

total 26680 4600

Net income

(Gross income – Production expense) 29754 5130

Net savings 10034 1730

Public Opinion Survey

In Aug 2009, the project management office organized public survey opinion and

suggestions by the Office of the Pingyi Water Conservancy Bureau and the relevant

township government. The scope of the survey involves the village which was affected by

the project, and investigated 30 households. The results of the survey show that of the 30

households in the investigation:

- 90% of the surveyed households knew about the construction of this project, 5% of

the surveyed households did not know about the construction of this project, 5% of

the surveyed households still do not know about the construction of this project;

- 95% of the surveyed households are in favor of the construction of this project, 5%

does not matter;

- 100% of the households’ surveyed think this project is beneficial to the country, 100%

said that the collective benefits from it, 100% of that of personal benefit.

Users also have a deep understanding of the possible impact of flood disasters and

hazards that the floods would cause the loss of housing and property accounted for 10

percent, affecting 30% of agricultural production, destruction of infrastructure accounted

Page 17: RP: PRC: Anjing Reservoir Subproject in Pingyi County ... · Anjing Reservoir was performed. The reservoir is judged as grade-Ⅲ dilapidated reservoir, and this result was checked

11

for 50%, affecting the health of residents accounted for 80%, would affect the investment

environment accounted for 40%;

- 70% of the surveyed households think flooding may cause serious harm, 15% of the

surveyed households consider flooding may cause serious harm; 10% of the

surveyed households that flooding may cause harm but not serious; 5% of the

surveyed households think that the floods may not result in harm;

- 95% of the households surveyed think this project will protect life and property safety,

90% think it will improve the level of agricultural production, 85% think it will improve

the living environment, 60% think it will increase employment opportunities

For the adverse effects the project may result in, 10% of the respondents believe that

land acquisition may reduce the economic income, 10% said that the relocation may

cause the implementation of economy, 20% said that the construction will affect

production and living, 70% said that no adverse effects;

- 70% of the respondents understand the land requisition compensation and

resettlement policy, and 20% of the land requisition compensation and resettlement

policy has some understanding of relocation, 10% do not know the land requisition

compensation and resettlement policy of demolition;

In the process of land acquisition demolition, if the legitimate rights and interests have

been violated, 95% of the respondents are aware of the procedure for complaints.

The findings of public opinion and recommendations are shown in Table 3-3.

Table 3-3 Questionnaire for the Anjing Reservoir reinforcement project in Pingyi county

No. Problems Responses results(%)

1 2 3 4 5

1

Do you know the

construction of Anjing

Reservoir reinforcement is

going to put into practice?

(1) clear (2) vague

(3)unclear 90 5 5

2 Do you agree with

constructing this project?

(1)agree (2)disagree

(3)nothing 95 5

3

Who do you think this

construction project

benefit?(multiple choices

proved)

a)state (1)yes (2)no 100 100

b)collection (1)yes (2)no 100 100

c)individuality (1)yes (2)no

100 100

4

The possible harm you

know that the flood may

cause(multiple choices

proved)

(1)housing treasure loss

(2)agricultural yield

influences (3)basic facilities

demolishment (4)affect

citizens’ health (5)affect

investment environment

10 30 50 80 40

5

To what extent doest flood

do to your living and

manufacturing?

(1)nothing (2)not serious

(3)serious (4)very serious 5 10 15 70

6 Benefits you consider this

project will bring you

(1) protect life and property

safety (2)improve the level of

agricultural production (3)

improve the living

environment (4) increase

95 90 85 60

Page 18: RP: PRC: Anjing Reservoir Subproject in Pingyi County ... · Anjing Reservoir was performed. The reservoir is judged as grade-Ⅲ dilapidated reservoir, and this result was checked

12

employment opportunities

7 Disadvantages you think

this project will do on you

(1)no bad effect

(2)construction will affect

living and manufacturing

(3)moving house may cause

economic losses

(4)requisition of the land

would low down economic

income

70 20 10 10

8

Do you know about the

requisition and relocating

policies?

(1)know (2)know some

(3)unknown 70 20 10

9

In the process of

requisition, will you

appeal to court when you

proper rights are

encroached?

(1)know

(2)unknown 95 5

Page 19: RP: PRC: Anjing Reservoir Subproject in Pingyi County ... · Anjing Reservoir was performed. The reservoir is judged as grade-Ⅲ dilapidated reservoir, and this result was checked

13

IV. POLICY FRAMEWORK, ENTITLEMENT AND COMPENSATION

4.1 Applicable Laws, Regulations & Policies for Resettlement

28. The resettlement policy for this project is established mainly in accordance with the relevant laws of China and the relevant policies of ADB, including:

ADB Policies

Safeguard Policy Statement, July 2009 (effective from 20 January 2010) Handbook on resettlement A Guide to Good Practice (effective from 1998) Gender and Resettlement Analysis, February 2003.

Laws and Regulations of the PRC

Land Administration Law of the People’s Republic of China (effective from January 1, 1999, latest version on August 28, 2004) The State Council's Decision on Deepening Reform and Managing Land Strictly (Guo Fa [2004] No.28) (effective from October 21, 2004) Guidelines on Improving the System of Land Acquisition Compensation and Resettlement (Guo Tu Zi Fa [2004] No.238) (effective from November 3, 2004) Regulations on Land Requisition Compensation and Resettlement for Construction of Large and Medium-sized Water Conservancy and Hydropower Projects (effective in 2006) Specifications on land requisition and resettlement design for construction of water

resources and hydropower project (SL 290—2003).

Relevant Policies of Shandong Province

The Implementation Regulations of Shandong Province for the PRC Land Administration Law Circular of Shandong Provincial Government Concerning the Adjustment of the Annual Output Value and Compensation Standard of Acquired Land (Lu Zheng Ban Fa [2004] No. 51) Circular of Shandong Provincial Government Concerning the Approval of the Associated Attachments Compensation Standard of Acquired Land (Lu Jia Fei Fa [1999] No.314).

4.2 Objectives and Principles of Resettlement

29. The primary objective of the LAR program is to ensure that the APs will improve their standards of living, or at least will not be made worse off because of the Project. The principles of the compensation and entitlements established for the Project are as follows: (i) Compensation and entitlements provided must be adequate to allow APs to at least maintain their pre project standard of living, with the prospect of improvement; (ii) Compensation and entitlements provided are based on market value or replacement value and must be adequate; (iii) Compensation should not be paid to those people who occupy land or construct structures and auxiliaries in the project area after cut-off date determined by the local government; (iv) Adequate compensation should be provided to the APs timely; (vi) All the APs will be adequately informed about eligibility, compensation rates and standards, livelihood and income restoration plans and project timing; and (vii) Close monitoring and timely actions will be carried out to identify and resolve any problems.

Page 20: RP: PRC: Anjing Reservoir Subproject in Pingyi County ... · Anjing Reservoir was performed. The reservoir is judged as grade-Ⅲ dilapidated reservoir, and this result was checked

14

4.3 Eligibility of Compensation

30. The Project APs who are entitled to receive compensation from the Project refer to the persons affected by the involuntary taking of land resulting in: (i) permanent or temporary loss of land or access to land; (ii) loss of income sources or means of livelihood, whether or not the affected persons must move to another location; and (iii) loss of ground attachments and standing crops.

31. All landowners and users in the Project areas affected by land acquisition and resettlement as a consequence of the Project will be eligible for fair compensation and rehabilitation according to the type of loss and quantities as well as the cut-off date determined by the government within the completion date of the construction map and investigation. The newly cultivated land and newly built houses shall not be compensated after the cut-off date. The cut-off date is Nov,30 2009.

4.4 Compensation Standards

4.4.1 Compensation Standards for Permanent Land Acquisition

32. According to the Land Administration Law of the People’s Republic of China, the Implementation Regulations of Shandong Province for the PRC Land Administration Law, the compensation standard for land acquisition is determined in coordination with villages whose land is to be acquired. According to the “Notice on the Adjustment of Land Occupying Annual Production and Compensation Standard, which is forwarded by General Office of Shandong Provincial People’s Government, and issued by Shandong Province People's government Office” Luzhengbanfa [2004] No.51, project influenced area, Pingyi, belongs to the forth-class areas. The Annual Average Output Value (AAOV) of the forth-class area is 1,200 Yuan per mu.

33. Land compensation for arable land is 8 times of AAOV, and resettlement subsidy for farmland is 8 times of AAOV. So the total arable land compensation standard is 19,200 Yuan/Mu. For details see Table 4-1.

34. According to regulations in regarding "Compensation Standard in Rizhao city and other 8 Cities for Ground Attachments and Young Crops Fee", young crops compensation of permanent land acquisition is calculated as output value of the affected crop, which is 600 yuan per mu.

Table 4-1 Compensation Rate of Permanent Land Acquisition

Type of Land

Land Compensation (Yuan/mu) Resettlement Subsidy

(Yuan/mu) Total (Yuan/mu)

AAOV Multiple Cost

(Yuan/mu) AAOV Multiple

Cost (Yuan/mu)

Arable land 1,200 8 9,600 1,200 8 9,600 19,200

4.4.2 Compensation Standard for temporary Land use

35. When the land is occupied, the standing crops will be compensated. During the occupation, given the compensation for the output value, the compensation fee per year calculated by per mu output of arable land is 1200 yuan.

Page 21: RP: PRC: Anjing Reservoir Subproject in Pingyi County ... · Anjing Reservoir was performed. The reservoir is judged as grade-Ⅲ dilapidated reservoir, and this result was checked

15

36. After finishing main project, temporary land acquisition needs reclamation. The land rehabilitation fee will be calculated as 500 yuan per mu in reference to the neighbouring project.

4.4.3 Compensation Standards for Attachments

37. Compensation standards for the ground attachments are according to regulations in regarding Compensation Standard in Rizhao city and other 8 Cities for Ground Attachments and Young Crops fee, which will be compensated according to intermediate standard of this regulation. Poplar is 40 yuan per plant. For details see Table 4-2.

Table 4-2 Compensation Standards for Attachments

Item Unit Compensation Rate (CNY)

poplar No. 40

4.5 Entitlement

38. The entitlements to be applied to this sub-project are summarized in Table 4-3.

Table 4-3 Entitlement Matrix Affected

type

Affected

object Entitlement Compensation standard

Permanent

land

acquisition

5 households

with 29 persons

Affected;

Liangjiaya

village

1. The affected village and all affected households agree

to adjust land within the village.

The compensation directly paid for village will be used

in 2 ways: i) improve the village road; ii) improve the

irrigated infrastructure.

2. The village will provide the AHs with replacement

land.

3. Production skill training for APs mainly includes the

training of cultural knowledge and practical skills

training.

4. About 80 temporary job opportunities (55% are

unskilled) will be created for Ahs during the project

construction stage.

Compensation fee per mu for

arable land is 19,200 yuan.

Young crops fee per mu is

600 yuan.

Temporary

land use

39 households

with 120 persons

Affected

During the occupation, given the compensation for the

output value.

The compensation fee per

year is 1200 yuan

Liangjiaya

village

the land rehabilitation fee will pay for affected village,

and the village is responsible for the land reclamation

The land rehabilitation fee is

500 yuan per mu

Ground

attachments Owner of title

In the project compensation fee or replanting cost for the

scattered trees shall be paid. Poplar:40 yuan per tree

Page 22: RP: PRC: Anjing Reservoir Subproject in Pingyi County ... · Anjing Reservoir was performed. The reservoir is judged as grade-Ⅲ dilapidated reservoir, and this result was checked

16

V. REHABILITATION MEASURES

5.1 Objectives of Resettlement

39. The objective of resettlement is to compile a resettlement and rehabilitation action plan for APs to ensure their living standard can be improved or at least recovered to the former level after project construction.

5.2 Rehabilitation Plan for Permanent Land Acquisition

5.2.1 Rehabilitation Plan for Affected Households

40. In Liangjiaya Village, 5 households will be affected by land acquisition of 4.2 mu farmland due to the construction of spillways. Based on the compensation policy and standards, the land compensation will be 83160 yuan for the affected households and village. The details compensation to affected persons is shown in table 5-1. According to the field interview, the village and all affected households agreed with adjust land. The village will provide the AHs with replacement land and the village will use the compensation in improving the road and irrigated infrastructure. The measures are following:

i) Land adjustment. There is 35 mu collective land owned by Liangjiaya village collectivity, including 15 mu irrigable land. The Liangjiaya village agreed adjusts 4.2 mu collective land to 5 affected households in order to rehabilitate the livelihood of the affected households. The compensation will be paid to the village, And the young crops fee will be paid to the affected households.

ii) The affected village around the reservoir is poor in infrastructures, roads and Irrigation and water conservancy facilities. Through the discussion with the affected village committees and villager representatives, the villages plan to improve the village road and purchasing irrigation facilities. The earth road runs through the village in south-north direction and it is the necessary path to farmland and the other villages. The road condition is very poor, especially in rainy days when covered by sludge. The road is 500 m long and 3 m wide. The investment of improvement of the road, including cement road will be 69000 yuan. Purchasing irrigation facilities including pumping and water transferring tubes, to increase the output of crops through improvement the irrigation conditions, the village will purchase pumps with the total investment of 10,800 yuan. The Reservoir Bureau will provide some equipment to help improve the road. The detailed arrangement of the compensation for rehabilitation measures is presented in Table 5-2.

Table 5-1 Compensation for the affected persons

town village Land owner Land

(mu)

Including:

Arable land

(mu)

Compensation

(yuan) household people

Bianqiao Liangjiaya Farmer

contracted 4.2 4.2 83160 5 29

Table 5-2 Rehabilitation Measures and Budget

Programs Unit Price Quantity AHs (No.) Investments (CNY)

Young crops 600 yuan per mu 4.2mu 5 2520

concreting Road 46 yuan each 500m*3m 15 69000

Purchasing irrigation facilities 2,700 yuan each 4 8 10800

Page 23: RP: PRC: Anjing Reservoir Subproject in Pingyi County ... · Anjing Reservoir was performed. The reservoir is judged as grade-Ⅲ dilapidated reservoir, and this result was checked

17

total 26 82320

5.3 Restoration Measures for Temporary Land Occupation

41. 110.8 mu of land will be used for construction arrangement, including construction camps, temporary road, stockyard and temporary road. Before construction activities, the surface fertile soil of 30 cm will be collected. During the construction period, the land may be hardened. After the completion, the land will be plowed and loosened and the top soil will be recovered. The reclamation rate is CNY 1,000/mu. All land will be restored to its original purpose by contractor and be inspected and accepted by both of Pingyi County LAB and affected people.

5.4 Restoration Measures for Ground-attachments

42. The compensation for the ground attachments will be compensated to the property holders by project unit; and the affected units will take the responsibility to reconstruct the lost ones.

5.5 Training for the Affected Persons

43. Production skill training for APs mainly includes the training of cultural knowledge and practical skills training, which mainly uses long-term training, short-term training and key technical training. Young people with a certain cultural qualities are selected to study in Shandong Agricultural University and Shandong Academy of Agricultural Sciences to provide a number of technical staff to the project area; taking the provincial and county resettlement training center as the carrier to hold all kinds of practical skill training so that a certain number of APs will master 1-2 practical skills, and promote the prosperity of other APs by using science and technology. Production skill training for APs mainly includes:

44. 1) Resettlement cadres training: it is planned to send a number of children of resettlers with higher educational background or enthusiasm or resettlement cadres to study in Shandong Agricultural University to receive medium or long-term training and education, to become leaders in the production and development.

45. 2) Farming technology training: mainly through lecturing and on-site demonstrations by agricultural experts to guide the greenhouse vegetable production technology, high-quality hybrid rice and double-low rape technology promotion.

46. 3) Breeding technology training: lecturing and on-site demonstrations by agricultural experts to guide poultry feeding technology and animal breeding.

47. It is planned that 3 training courses will be held for the APs. 45 resettlers and cadres will be trained, among which 37 resettlers will be trained in two courses and 8 resettlement cadres will be trained in one course. The planned investment in livelihood production training for APs is shown in Table 5-3. The investment will be included in the Basic Contingencies.

Page 24: RP: PRC: Anjing Reservoir Subproject in Pingyi County ... · Anjing Reservoir was performed. The reservoir is judged as grade-Ⅲ dilapidated reservoir, and this result was checked

18

Table 5-3 Schedule of Training for APs

5.6 Job Opportunities from the Project

48. About 80 temporary job opportunities (55% are unskilled) will be created during the project construction stage. In the project construction stage, the main unskilled job opportunities include manual laborers for excavation, material handling, greening, etc.

49. According to the survey, since the affected villages are located far from urban area and 11 affected laborers from 5 AHs work in their own farmland normally, they hope to join the project construction while working time has no conflict with their fruit planting activities. PCG and ARPMB will arrange the jobs and training for them as a priority.

5.7 Income Restoration Plan of Women

50. In the stage of RP preparation, the affected women were organized to actively participate in the survey of project impacts so as to understand their ideas on income restoration. As a result, women hold a positive attitude toward project construction by thinking that the project will help improve the environment and improve the flood control road; and land acquisition has little impacts on their lives.

51. Women will fully participate in the compensation and resettlement activities through the information disclosure and village meetings; they have equal entitlement with men in receiving compensation, employment and training. In addition, the following measures will be taken to improve women’s income:

(1) During the project construction, ARPMB has ensured that the affected women will be given priority in unskilled jobs, including food and cleaning service. As per labor laws, women will get equal pay to men for the same work.

(2) Technical training program including farming technology training, etc. will be provided for the affected female laborers (at least 50% will be women) to ensure their income would not be reduced.

Location Mode Trainer Trainee

Number

of

trainee

Contents

Number

of

courses

Time of

training

(day)

Fund

(10000

Yuan)

Shandong

Agricultural

University

Advanced

study

Teachers from

Shandong

Agricultural

University

Resettlement cadres and

children of APs

12

1. Production

technology

management;

2.

Agricultural

technology

management;

3. Mixed

farming in

agricultural

production.

1 6

months 1.2

Town Project

Resettlement

Office

Learning

course

Management

personnel and

agricultural

technical

experts from

municipal

resettlement

office

AP

representatives

from towns and

villages

25

1. Farming

technology

training;

2. Breeding

technology

training.

1 7 0.1

Total 37 2 1.3

Page 25: RP: PRC: Anjing Reservoir Subproject in Pingyi County ... · Anjing Reservoir was performed. The reservoir is judged as grade-Ⅲ dilapidated reservoir, and this result was checked

19

VI. COST ESTIMATE AND IMPLEMENTATION SCHEDULE

6.1 Resettlement Cost

52. The estimated cost of land acquisition is CNY 388,318.9 in 2009 prices, including contingency. In terms of the categories of resettlement impacts, compensation of rural resettlement is CNY 304520, accounting for 78%. According to Shandong Province Implementation methods of Law of Land Administration of PRC, the land reclamation fee is 6,720 Yuan per mu according to” Notification on Relevant Issues of Building-purposed Land-use for Water Conservancy and Hydropower Engineering” promulgated by National Land Resources Department [2001] No.355.Table 6-1 provides the cost estimation of LAR.

Table 6-1 Budget of Land Acquisition and Resettlement

No. item unit amount price total

(yuan) (yuan)

Part 1 Compensation fees for rural resettlement 304,520

1 Permanent land acquisition

(1) land compensation fees, resettlement subsidies

Cultivated land mu 4.2 19200 80,640

(2) Young crops fee mu 4.2 600 2,520

2 Temporary land use

(1) Compensation for the occupation of land

Cultivated land mu 110.8 1200 132,960

(2) Land reclamation fees mu 110.8 500 55,400

3 Compensation for scattered fruit trees

(1) poplar 825 40 33,000

Part 2 1、survey and design fees 304,520 0.03 9,135.6

2、facilities management fees 304,520 0.03 9,135.6

3、technical training fees 304,520 0.005 1,522.6

4、assessment of supervision and monitoring fees 304,520 0.01 3,045.2

Part 3 Contingency

1、Physical contingency 327,359 10% 32,735.9

Part 4 Relative expenses of taxation

1、land reclamation fees mu 4.2 6,720 28,224

Total 388,318.9

6.2 Management and Disbursement of Resettlement Funds

53. Pingyi county Water Resources Bureau will provide the entire fund for resettlement activities and ensure that land acquisition and resettlement budgets are delivered on time for timely implementation of the RP. All LAR cost will be paid in Jan. 2010, before the construction of the Project. Land compensation and resettlement subsidy will be disbursed in full to the APs. Compensation for attachments will be paid to the affected unit or individuals directly.

54. In order to ensure the funds for land acquisition is paid to the APs in full and in a timely manner in line with the compensation policies and standards of the resettlement plan, a strict fund appropriation plan has been established, the principles of which are as follows:

All the costs related to resettlement are covered in the general budget of this project.

Page 26: RP: PRC: Anjing Reservoir Subproject in Pingyi County ... · Anjing Reservoir was performed. The reservoir is judged as grade-Ⅲ dilapidated reservoir, and this result was checked

20

The land compensation and resettlement subsidy must be paid up before the land acquisition. To ensure the land compensation is implemented successfully, financial and supervisory agencies will be set up to make all funds appropriate in a timely manner. The budget is based on the resettlement cost estimate. The resettlement costs may increase due to changes in the actual resettlement impacts and other factors such as inflation. Meanwhile, the resettlement budget includes a contingency cost and will be modified based on the actual needs.

Page 27: RP: PRC: Anjing Reservoir Subproject in Pingyi County ... · Anjing Reservoir was performed. The reservoir is judged as grade-Ⅲ dilapidated reservoir, and this result was checked

21

VII. POST-RESETTLEMENT PROGRAM FOR ORIGINAL RESETTLERS

7.1 Post-resettlement Program for Resettlers in Reservoir Area

7.1.1 Background and Remaining Issues

55. Since the founding of new China, a number of large and medium-sized reservoirs have been constructed and brought into huge benefits in flood control, irrigation and ecological aspects. A large number of resettlers of large and medium-sized reservoirs made major contributions to effectively promote the national economy and social development. In order to help them to improve production and living conditions, the country has established the reservoir area fund of the large and medium-sized reservoirs and tries to solve the remaining resettlement issues in reservoir area. But due to the low support level and insufficient direct benefit to resettlers, at present their production and living conditions are still generally poorer. To help the resettlers in reservoir shaking off the poverty and promote the economic and social development in the new period, the central government of PRC issued the “Suggestions on Perfecting Post-resettlement Support Policies for Large and Medium-sized Reservoirs Resettlers” in 2006 (Guofa [2006]No.17).

56. The central government has distributed special fund of CNY 1.89 million since the construction of the Reservoir to 2005 to help improve the living condition of resettlers in Anjing Reservoir Area. Due to the out-dated infrastructure and limited income sources some villages still have some troubles in aspect of drinking water, transportation, medical service and education. In addition, the employment difficulties stayed with resettlement villagers. The remaining issues include:

57. Economic income. Since most of the resettlement villages have not any industrial and sideline production programs, they relied on agricultural activities for living. Income of resettlement villagers lagged greatly behind other people outside the reservoir area.

58. Land Resources. The reservoir area is located in mountainous area where poor land quality and limited farmland resources lead to the limited output value. Although the resettlers were allocated some farmland in host area, the farmland available is very poor and output is low as well. The per capita farmland is much less than they have before relocation.

59. Infrastructure Situation. The poor infrastructure condition includes the poor road, limited and poor quality of domestic water supply, no access to electricity, health care service and education facilities. 85% of the households have the cable TV and 85% of households have telephone. 96% of children at compulsory education age entered school. 75% of resettlers join the rural medical insurance programs. The above-mentioned percentages are much lower than the average level in Pingyi county.

7.1.2 Post-resettlement Support Approaches

60. Based on the “Suggestions of State Council on Perfecting the Post-resettlement Support Policies of Large and Medium-sized Reservoir Resettlement” and the corresponding Implementation Method issued by Shandong provincial government, Pingyi county government led the preparation of the post-resettlement program for Anjing Reservoir. The goals of the programs include :i) the per capita farmland will be at least 1 mu; ii) the drinking water quality will be secured; iii) road access between administrative villages; iv) power supply is available in each resettlement village; v) each administrative village has clinic; vi) 100% children at education age join the compulsory education program; vii) at least 2 labor from each household, including one female labor can join the technical skill training program; viii) cable and telephone are accessible in each village.

Page 28: RP: PRC: Anjing Reservoir Subproject in Pingyi County ... · Anjing Reservoir was performed. The reservoir is judged as grade-Ⅲ dilapidated reservoir, and this result was checked

22

61. Based on the “ Management Method of Post-resettlement Support Fund of Large and Medium-sized Reservoirs in Shandong Province”, the support fund can be paid directly to resettlers or be used in actual development programs. In Pingyi county, after full consultation with affected people, all support fund has been paid to resettlers directly at the annual rate of CNY 600/person. The total resettlers are 429 persons in one township of Pingyi county that were identified as the support target of Anjing Reservoir. The term of the fund subsidy is 20 years. The total cash payment will be CNY 5.148 million for resettlers of Anjing reservoir area. The cash subsidy was paid quarterly. In addition to the cash payment, some other development programs has been planned and implemented since 2006. The details of such programs and implementation status of Anjing Reservoir Area is presented in Table 7-1. The support will last for 4 and a half year in the duration of 2006-2010. It is planned that 7 development programs have been or will be implemented in reservoir area villages from 2006 to 2010, including water farmland improvement, and transportation works. The implementation of the programs will be monitored during the Project period. It is expected through the improvement of infrastructures the living condition of people in Anjing Reservoir Area will be better-off.

Table 7-1 Post-resettlement Support Program of Anjing Reservoir

Programs Contents Beneficiaries of Resettlers (No.)

Investment (CNY 104)

low-yielding farmland Improvement

Well drilling, pipeline installation, irrigation equipment, water storage pond, terrace plowing, etc.

210 19.6

Transportation

(Road) Village-village road 368 41.6

Total 578 61.2

7.2 Post-resettlement Support in Reservoir Area

62. In Pingyi county, The total investment of Post-resettlement Support is CNY 96.79 million, including fund support and development programs. After full consultation with affected people, all support fund has been paid to resettlers quarterly at the annual rate of CNY 600/person. The term of the subsidy is 20 years. The total cash payment will be CNY 5.148 million for resettlers of Anjing reservoir area. In addition to the cash payment, some other development programs has been planned and implemented since 2006. The project support will last for 4 and a half year in the duration of 2006-2010. The total budget of the programs is CNY 0.612 million. The progress varies in different programs. All support funds will be allocated by central government. Table 7-2 presents the details of the budget of the programs. All the funds will be disbursed by 2010 and the activities will be completed by 2011. The implementation of the programs will be monitored during the Project period.

Table 7-2 Investment and Implementation of Post-resettlement Support

Programs Number of the projects

Budget (CNY104)

Beneficiaries of Resettlers (No.)

Implementation in Cost(CNY 104)

Progress

(%)

low-yielding farmland Improvement

2 19.6 210 8.9 45

Transportation

(Road) 4 41.6 368 13.4 32

Total 6 61.2 578 22.3 36

Page 29: RP: PRC: Anjing Reservoir Subproject in Pingyi County ... · Anjing Reservoir was performed. The reservoir is judged as grade-Ⅲ dilapidated reservoir, and this result was checked

23

VIII. IMPLEMENTATION SCHEDULE

63. The resettlement is scheduled to begin in Jan. 2010 and complete in November 2010, with reflecting the linkage and consistency between the time schedule of LAR and civil works construction tasks. Civil works will not begin before compensation for the APs are paid in full, which is in accordance with the recently promulgated State Council Decree #31. All compensation for residential structures and ground attachments will be paid before construction. Table 8-1 provides the resettlement activities and supervision milestone. Based on these surveys, the short RP will be updated and submitted to ADB for concurrence.

Table 8-1 Resettlement Activities Milestone

No. Compensation Task Targets

Responsibilities

Agencies

Deadline Progress

Status

1. Information Disclosure

1.1 -Resettlement Plan disclose 92 households with 324 persons in five Villages

ARPMB 2010.1 Planned

1.2 -Publish Resettlement Plan on ADB website

ADB 2010.1 Planned

2. Approval of RP & Budget PCG 2010.1 Planned

3 Compensation Agreement

3.1 -Compensation rates Anjing village PCG, ARPMB,PLAB, VC 2010.1 Planned

3.2 -Household agreements 11 AHs PCG, MRPMB,PLAB, VC 2010.1 Planned

3.3 -Approval of land use certificate ARPMB,PLAB 2010.1 Planned

4. Monitoring and Evaluation

4.1 -Baseline Survey (additional) one village ARPMB 2010.1 Planned

4.2 -Establish Internal M&E mechanism

As per RP AWRMD, ARPMB 2009.09 Completed

4.3 -Sign contract with External M&E agency

PCG, ARPMB 2010.1 Planned

4.4 - Internal M&E Report Quarterly Report

AWRMD, ARPMB 2010.03 Planned

4.5 - External M&E Report Semi-annually Report

ARPMB,,IMA 2010.03 2010.09

Planned

4.6 - Evaluation report 2 Report ARPMB,,IMA Dec. 2010, Dec. 2011

Planned

4.7 -Resettlement Completion Report 1 Report ARPMB,,IMA As work is

completed

Planned

5 Consultation documentation ARPMB/VC Ongoing

6 Grievance and appeal files ARPMB /VC Ongoing

8 Capital/compensation payment

8.1 - Paid to affected village 2010.1 Planned

8.2 - Paid to affected Households 2010.1 Planned

9 Commencement of civil works Flood control road

ARPMB 2010.1 Planned

Page 30: RP: PRC: Anjing Reservoir Subproject in Pingyi County ... · Anjing Reservoir was performed. The reservoir is judged as grade-Ⅲ dilapidated reservoir, and this result was checked

24

IX. PUBLIC PARTICIPATION AND GRIEVANCE REDRESS

9.1 Public Participation

64. The RP was prepared with full public participation and full information sharing with APs. The Anjing Reservoir Project Management Bureau (ARPMB) has informed the resettlement policies to all the APs via socio-economic survey, social impact survey and other communication and consultation channels. ARPMB also has consulted with various affected persons through consultation meetings. Through wide consultation, coordination and communication, related local government, affected villages and APs can fully understand the resettlement impacts, resettlement policies and formulate feasible income restoration measures.

65. ARPMB contacted the affected village committee in August 2009, and discussed the Project and compensation costs, compensation policies, entitlement, and impacts of the Project on the village and APs. ARPMB will disclose the draft RP to affected people and then sign the land agreement with APs and the affected village in Jan. 2010. The RP approved by PCG will be redistributed to village committee in Jan. 2010 to any one wishing to consult the document at the affected village. Copies of the short RP will be kept in the Project office and the affected VC. At the same time this short RP will be posted on the ADB’s website in Jan. 2010. The public consultation activities and schedule is presented in Table 9-1.

Table 9-1 Public Consultation Activities and Schedule

Objectives Task Date Organizations

Involved Participant

1. Inform and discuss issues related with LA;

Obtain suggestion or advices

Release of location and area of LA, compensation standards, and resettlement, etc.

February

2009

PCWRD, ARPMB and VC

Representatives of each organization

2. Survey on affected physical index, and preparation of RP

Field survey of affected, physical index, and socioeconomic status of affected households

August

2009

ARPMB, Pingyi LAB, and VC

Representatives of each organization

3. Land acquisition agreement signed with Anjing Village

Agreement of complementation standards, and grievance appeal procedures

Jan. 2010 QRPMB, Pingyi LAB, and VC

Representatives of each organization

4. RP disclosure on ADB website

Release of draft RP Jan. 2010 ADB

6. Implementation of Final RP

Verification and implementation of Final RP

Jan. 2010 ARPMB, Pingyi LAB, and VC

Representatives of each organization

7. Monitoring & Evaluation of RP

Survey on the rehabilitation of APs after resettlement implementation

Jan. 2010 ARPMB, Pingyi LAB, VC, and IMA

Socioeconomic sample survey

9.2 Grievance Procedure

66. During the preparation and implementation of the RP, public participation is encouraged, and thus there should not be any major issues or grievances. However, some unforeseen issues may occur during such process. In order to settle such issues effectively and make the construction and land acquisition implement successfully, an effective and transparent channel for lodging complaints and grievances has been established. The basic stages for grievance redress are:

Page 31: RP: PRC: Anjing Reservoir Subproject in Pingyi County ... · Anjing Reservoir was performed. The reservoir is judged as grade-Ⅲ dilapidated reservoir, and this result was checked

25

Stage 1: The APs submit an oral or written petition/complaint to the village committee. For an oral complaint, the village committee must make written records properly and give a clear reply within 2 weeks.

Stage 2: If the complainant is not satisfied with the reply in Stage 1, he can appeal to the township government/sub-district office after receiving the reply in Stage 1 and the township government/sub-district office will deal with the complaint within 2 weeks.

Stage 3: If the affected person is still not satisfied with the reply of township government/sub-district office, he can appeal to Pingyi Land Resources Bureau and Pingyi Land Resources Bureau must give a reply within 30 days.

Stage 4: If the affected person is still not satisfied with the reply of Pingyi Land Resources Bureau, he can appeal to SPMO after receiving the reply of Stage 3. They also have the right to appeal to the civil court within 3 months of receiving the reply.

67. Besides the established channel above, the external monitor can also receive grievances from APs and the APs can even submit directly to ADB2. The appeal process, institutions, sites, leaders, and telephone numbers for redress of grievances will be publicized to APs via meetings, notices and the information handbook. In this way, the APs will fully realize their rights of appeal. Meanwhile, the system of information dissemination will be strengthened through use of the media, and all APs feedback will be compiled and distributed to all involved organizations.

68. Relevant institutions shall accept the complaints and grievances lodged by the APs free of charge. The reasonable costs incurred shall be covered by the contingency of the project. During the whole process of project construction, these grievance procedures remain valid so that the APs may deal with relevant issues.

2 ADB has an Accountability Mechanism to ensure policy compliance. APs are required to seek grievance resolution using

the above procedures, but if they still believe that their concerns have not been resolved in accordance with this RP or ADB's

Involuntary Resettlement Policy (1995), they may submit a complaint to ADB. The procedures are provided on ADB's

website: http://www.adb.org/Accountability-Mechanism/default.asp

Page 32: RP: PRC: Anjing Reservoir Subproject in Pingyi County ... · Anjing Reservoir was performed. The reservoir is judged as grade-Ⅲ dilapidated reservoir, and this result was checked

26

X. INSTITUTIONAL ARRANGEMENT

10.1 Responsible Institutions for Resettlement Implementation

69. The departments responsible for planning, implementation, management, and monitoring of the resettlement activities of the Pingyi Anjing Reservoir ADB Loan project are:

Pingyi Water Resources Department Anjing Reservoir Project Management Bureau Pingyi Land Resources Bureau Bianqiao Township Government Affected Village committees Design Institute.

70. Pingyi Water Resources Department is in charge of resettlement investigation, development of the RP and implementation of land acquisition.

71. Anjing Reservoir Project Management Bureau is the specific implementing agency, which is responsible for the socio-economic investigation, coordinating with Pingyi Land Resources Bureau, governments and the affected village committees, and implementing the work of land acquisition and resettlement.

72. Pingyi Land and Resources Bureau is responsible for collective land acquisition, directing the implementation of resettlement, organizing and coordinating.

73. Bianqiao Township government is responsible for coordinate with City Project Office about relative work on the land requisition and demolition, organizing villagers to relocate and developing production.

74. Affected village committees are responsible for providing the land contract, assisting or participating in the various surveys and the work of land acquisition, community mobilization activities for publicity, and undertaking the verification of the measurement, valuation and finalization of demolition agreements after APs negotiations together with the relevant technical personnel.

75. Design institute is responsible for the design of the project and defining the scope of affected land and assets.

76. The staffing of institutional arrangement for LAR is presented in Table 10-1

Table 10-1 Staffing of Institutional Arrangement for LAR

Name of Institution Staff (No.)

Personnel Composition Male Female

Pingyi Water Resources Department 1 Official

Pingyi county Anjing Reservoir Project Management Bureau

3 Officials

Pingyi county LAB 1 Officials

Bianqiao Township Government(1) 6 5 Officials

Affected village committees (1 15 8 Cadres and representatives of APs

TOTAL 26 13

Page 33: RP: PRC: Anjing Reservoir Subproject in Pingyi County ... · Anjing Reservoir was performed. The reservoir is judged as grade-Ⅲ dilapidated reservoir, and this result was checked

27

10.2 Training Plan for Resettlement Management Staff

77. A system for staff training and human resource development will be established at all levels of resettlement management institutions. The training plan is organized by ZWRD, and the form of training will include specialist lectures, technical training seminars, inspection of other similar projects and site training, etc. The training plan is shown in Table 10-2, while the training contents will include: resettlement principles and policies, planning and management of projects with resettlement, resettlement planning and design, resettlement progress management, resettlement financial management, resettlement quality control and resettlement monitoring assessment.

Table 10-2 Schedule for Resettlement Implementation Training

Time Location Training methods

Recipients Training content

Feb. 2010 Jinan City Centralized

course Resettlement

work staff Resettlement business training

Jun. 2010 Domestic Learn from

demonstration Key personnel of

the office The implementation site visit of the ADB project

Oct. 2010 Jinan City Seminars Resettlement

work staff Discuss the resettlement experience and the problems

Page 34: RP: PRC: Anjing Reservoir Subproject in Pingyi County ... · Anjing Reservoir was performed. The reservoir is judged as grade-Ⅲ dilapidated reservoir, and this result was checked

28

XI. MONITORING AND EVALUATION

78. In order to ensure the successful implementation of the RP and accomplish the objectives to achieve appropriate resettlement, monitoring and evaluation should be carried out for the implementation of resettlement in accordance with the requirement of the ADB resettlement policies. The monitoring include both internal and external. The reporting schedules were shown in Table 8-1.

79. The external monitoring and evaluation is done by an independent monitoring agency (IMA). The IMA will carry out semi-annual monitoring and evaluation of the resettlement activities.

80. The IMA, approved by ADB and PCG, will undertake the independent monitoring of the Project in respects of: (i) extent of consultation undertaken with APs; (ii) compensation disbursement to the APs and affected village or group; (iii) production and livelihood rehabilitation measures for the APs; (iv) schedule of above LAR activities; (v) compliance with the policies and regulations of the resettlement plan; (vi) participation and consultation during the project implementation; (vii) grievances, problem resolution and follow-up; (viii) staffing, training, schedule and work efficiency of the resettlement officers. The IMA, being independent of the project, will inspect the whole implementation from an overall and long-term point of view. The IMA will put forward recommendations to SPMO, PCG and ARPMB in time so that the problems taking place in the implementation of the resettlement can be solved as soon as possible. The terms of reference for external monitoring and evaluation is presented in Appendix 2.

81. The major external monitoring and evaluation indicators are as follows:

(1) M&E on Progress of Land Acquisition Implementation: i) progress of land

acquisition; ii) progress of temporary land occupation; and iii) progress of project impacts;

(2) M&E on Fund Disbursement and Usage: i) Fund disbursement; and ii) Fund usage

(planning and actual fund usage).

(3) M&E on Rehabilitation of APs’ Production and Livelihood: i) Production and living conditions of the APs before land acquisition; ii) Production and living conditions of the APs after land acquisition; iii) Analysis and evaluation of employment and living condition before and after the resettlement; and iv) Grievance mechanism and problem resolution.

(4) M&E on capabilities of resettlement institution, public participation, grievance and

appeal procedures.

Page 35: RP: PRC: Anjing Reservoir Subproject in Pingyi County ... · Anjing Reservoir was performed. The reservoir is judged as grade-Ⅲ dilapidated reservoir, and this result was checked

29

Appendix 1 Applicable Laws and Regulations

The Applicable Provisions in Land Administration Law of the People’s Republic of China

Article 43 All entities and individuals that need land for construction purposes shall, in accordance with law, apply for the use of state-owned land, with the exception of the collective economic organizations and farmers of such entities that have lawfully obtained approval of using the land owned by farmer collectives of these organizations to build township or town enterprises or to build houses for villagers and the entities and individuals that have lawfully obtained approval of using the land owned by farmer collectives to build infrastructure or public welfare undertakings of a township (town) or village.

“State-owned land” referred to in the preceding paragraph includes land owned by the state and land originally owned by farmer collectives but expropriated by the state.

Article 44 Where farmland is to be used for construction purposes, the formalities of examination and approval shall be gone through for the conversion of use.

Where farmland is to be converted to land for the construction of road, pipeline or large infrastructure projects, for which approval has been obtained from people’s governments of provinces, autonomous regions and municipalities directly under the Central Government, or for the construction of projects for which approval has been obtained from the State Council, the conversion shall be subject to approval by the State Council.

Where farmland is to be converted to land for construction of projects in order to carry out the overall plan for land utilization within the limits of the area of land fixed in the plan for construction projects of cities, villages or towns, the conversion of use of land shall, in accordance with the annual plan for land utilization, be subject to approval in batches by the organ that originally approved the overall plan for land utilization. Land for construction of specific projects within the limits of the area of farmland, conversion of the use of which has been approved, may be subject to approval by people’s governments of cities or counties.

Where farmland is to be converted to land for construction projects other than what is provided for in the second and third paragraphs of this Article the conversion shall be subject to approval by people’s governments of provinces, autonomous regions and municipalities directly under the Central Government.

Article 46 Where land is to be expropriated by the State, the expropriation shall, after approval is obtained through legal procedure, be announced by people’s governments at or above the county level, which shall help execute the acquisition.

Entities and individuals that own or have the right to the use of the land under expropriation shall, within the time limit fixed in the announcement, register for compensation with the land administration department of the local people’s government by presenting their certificates of land ownership or land-use right.

Article 47 Land expropriated shall be compensated for on the basis of its original purpose of use.

Compensation for expropriated farmland shall include compensation for land, resettlement

Page 36: RP: PRC: Anjing Reservoir Subproject in Pingyi County ... · Anjing Reservoir was performed. The reservoir is judged as grade-Ⅲ dilapidated reservoir, and this result was checked

30

subsidy and compensation for attachments and young crops on the acquisitioned land. Compensation for expropriated of farmland shall be six to ten times the average annual output value of the expropriated land, calculated on the basis of three years preceding such acquisition. Resettlement subsidy for expropriated farmland shall be calculated according to the agricultural population needing to be resettled. The agricultural population needing to be resettled shall be calculated by dividing the area of expropriated farmland by the average area of the original farmland per person of the entity the land of which is expropriated. The standard resettlement subsidy to be divided among members of the agricultural population needing resettlement shall be four to six times the average annual output value of the expropriate farmland calculated on the basis of three years preceding such expropriation. However, the maximum resettlement subsidy for each hectare of the expropriated farmland shall not exceed fifteen times its average annual output value calculated on the basis of three years preceding such expropriation.

Rates of land compensation and resettlement subsidy for expropriation of other types of land shall be prescribed by provinces, autonomous regions and municipalities directly under the Central Government with reference to the rates of compensation and resettlement subsidy for expropriation of farmland.

Rates of land compensation and resettlement subsidy for expropriation of other types of land shall be prescribed by provinces, autonomous regions and municipalities directly under the Central Government with reference to the rates of compensation and resettlement subsidy for expropriation of farmland.

For expropriation of vegetable plots in city suburbs, the land users shall pay towards a development and construction fund for new vegetable plots in accordance with the relevant regulations of the State.

If land compensation and resettlement subsidy paid in accordance with the provisions of the second paragraph in this Article are still insufficient to enable the farmers needing resettlement to maintain their original living standards, the resettlement subsidy may be increased upon approval by people’s governments of provinces, autonomous regions and municipalities directly under the Central Government. However, the total land compensation and resettlement subsidy shall not exceed 30 times the average annual output value of the expropriated land calculated on the basis of three years preceding such expropriation.

The State Council may, in light of the level of socio-economic development and under special circumstances, raise the rates of land compensation and resettlement subsidy for expropriation of farmland.

Article 48 Once a plan for compensation and resettlement subsidy for acquisitioned land is decided on, the local people’s government concerned shall make it known to the general public and solicit comments and suggestions from the collective economic organizations, the land of which is acquisitioned, and the farmers.

Article 49 The rural collective economic organization, the land of which is expropriated, shall accept supervision by making known to its members the income and expenses of the compensation received for land expropriation.

The compensation and other charges paid to the entity for its land expropriated is forbidden to be embezzled or misappropriated.

Article 50 Local people’s governments at all levels shall support the rural collective economic organizations, the land of which is acquisitioned, and the farmers in their efforts to engage in

Page 37: RP: PRC: Anjing Reservoir Subproject in Pingyi County ... · Anjing Reservoir was performed. The reservoir is judged as grade-Ⅲ dilapidated reservoir, and this result was checked

31

development or business operation or to start enterprises.

Article 51 The rate of compensation for expropriation of land to build large or medium-sized water conservancy or hydroelectric projects and the measures for resettling the migrants shall be prescribed separately by the State Council.

Article 52 During the feasibility study of a construction project, land administration department may, in accordance with the overall plan for land utilization, the annual plan for land utilization and the standard area of land for the use of construction, examine the matters related to land for construction and offer its comments and suggestions.

Article 53 Where a construction entity needs to use state-owned land for construction of an approved project, it shall apply to the land administration department of the people’s government at or above the county level that has the approval authority by presenting the relevant documents as required by laws and regulations. The said department shall examine the application before submitting it to the said people’s government for approval.

Article 54 A construction entity that wishes to use state-owned land shall get it by such means of compensation as assignment. However, land for the following purposes may be allocated with the lawful approval of a people’s government at or above the county level:

(1) for state organs or military purposes;

(2) for urban infrastructure projects or public welfare undertakings;

(3) for major energy, communications, water conservancy and other infrastructure projects supported by the state; and

(4) other purposes as provided for by laws or administrative regulations.

Article 55 A construction entity that obtains right to the use of state-owned land by such means of compensation as assignment shall, in accordance with the rates and measures prescribed by the State Council, pay, among other charges, compensation for use of land such as charges for the assignment of land-use right, before it can use the land.

Beginning from the date of implementation of this Law, 30 percent of the compensation paid for the use of additional land for construction shall go to the Central Government and 70 percent to the local people’s governments concerned, both of which shall exclusively be used for developing farmland.

Article 56 A construction entity that uses state-owned land shall do so in agreement with the stipulations of the contract governing compensation for the use of land such as the assignment of the land-use right or with the provisions in the documents of approval for allocation of the land-use right. Where it is definitely necessary to change the purposes of construction on this land, the matter shall be subject to agreement by the land administration department of the people’s government that originally approved the use of land. Where the land the purposes of use of which need to be changed is located in the area under city planning, the matter shall be subject to agreement by the city planning administration department concerned before it is submitted for approval.

Article 57 Where land owned by the State or by farmer collectives needs to be used temporarily for construction of projects or for geologic prospecting, the matter shall be subject to approval by the land administration department of a people’s government at or above the county level. However, if the land to be temporarily used is located in the area covered by city

Page 38: RP: PRC: Anjing Reservoir Subproject in Pingyi County ... · Anjing Reservoir was performed. The reservoir is judged as grade-Ⅲ dilapidated reservoir, and this result was checked

32

planning, the matter shall be subject to agreement by the city planning administration department concerned before it is submitted for approval. The land user shall, depending on who owns the land and who has the land-use right, enter into a contract for the temporary use of the land with the land administration department concerned, or the rural collective economic organization, or the villagers committee, and pay compensation for it in accordance with the provisions of the contract.

The temporary land user shall use the land for purposes stipulated in the contract for temporary use of the land and may not build permanent structures on it.

Generally, the period for temporary use of land shall not exceed two years.

The Implementation Regulations of Shandong Province for the PRC Land Administration Law

Article 24 Within the scope of construction land defined in the overall land use plan, the use of state-owned construction land and state-owned unused land in detail construction project should transact the following procedure:

(1) Land occupation below 2 hectares should be approved by city/county Peoples’ Government and reported step by step to province Peoples’ Government for record;

(2) Land occupation between 2 hectares and 8 hectares should be approved by city (govern districts) Peoples’ Government or regional government, and then reported to province Peoples’ Government for record;

(3) Land occupation exceeding 8 hectares should be approved by province Peoples’ Government for record.

As for state important project construction, military establishment construction, multi-provincial project construction and other construction regulated by State Council, the use of state-owned unused land defined in the overall land use plan should be approved by State Council.

It should be approved by State Council or Peoples’ Government of province if the land used is out of the range of construction land in city, village and town, which is defined in the overall land use plan.

Article 25 Land acquisition compensation rate should be as follows:

(1)If farmland (including garden plot, pond and lotus root pool, the same below) within urban planning district is acquired, land compensation should be 8 to 10 times the AAOV of the three years preceding such acquisition;

(2)If farmland out of urban planning district is acquired, land compensation should be 6 to 8 times the AAOV of the three years preceding such acquisition;

(3)If farmland such as woodland, grassland, reed pool and water surface is acquired, land compensation should be 5 to 6 times the AAOV of preceding three years in nearest common farmland;

(4)If collective-owned land occupied by public establishment, commonweal industry,

Page 39: RP: PRC: Anjing Reservoir Subproject in Pingyi County ... · Anjing Reservoir was performed. The reservoir is judged as grade-Ⅲ dilapidated reservoir, and this result was checked

33

township business or rural residential house is acquired, land compensation should be 5 to 7 times the AAOV of preceding three years in nearest common farmland;

(5)If unused land is acquired, land compensation should be 3 times the AAOV of preceding three years in nearest common farmland.

Article 26 Compensation rate of movement subsidy should be as follows:

(1) Movement subsidy for farmland acquisition shall be calculated according to the agricultural population needing to be resettled. The agricultural population needing to be resettled shall be calculated by dividing the amount of acquisitioned farmland by the average amount of the original farmland per person of the entity the land of which is acquisitioned. The standard resettlement subsidy to be divided among members of the agricultural population needing resettlement shall be 4 to 6 times the average annual output value (AAOV) of the acquisitioned farmland for three years preceding such acquisition. However, the highest resettlement subsidy for each hectare of the acquisitioned farmland shall not exceed 15 times its average annual output value (AAOV) for the three years preceding such acquisition.

(2) If woodland, grassland, reed pool, water surface and village collective-owned construction land are acquired, the standard resettlement subsidy of agricultural population needing resettlement shall be 4 times the average annual output value (AAOV) of preceding three years in nearest common farmland. However, the highest resettlement subsidy for each hectare of acquired land shall not exceed 10 times the average annual output value (AAOV) of preceding three years in nearest common farmland.

Article 27 Ground attachments and young crop compensation rate for acquired land should be as follows:

(1) Young crop compensation is calculated at output value of one crop rotation;

(2) As for the tree on acquired land, transplant should be organized if possible; the labor cost for the transplanter and loss of sapling should be compensated for. If trees are impossible to transplant, compensation should be pay after evaluation.

(3) The attachments on acquired land shall be compensated for by converting into money according relevant regulation, or by reconstructing the same quality and same quantity as the former.

Trees and green seeding planted during land acquisition period will not be compensated for, so are the constructions building during land acquisition period. Constructions and other establishments built on illegal-occupied land will not be compensated for.

Article 38 If project implementation and geology perambulation need to occupy state-owned land or collective-owned land temporarily, the examination and approval on temporary land occupation should be conducted according to the Article 57 of Land Administration Law of the PRC. And compensation for temporary land occupation should be paid.

The time for temporary land occupation should be no more than two years. If exceeding two years, the examination and approval on temporary land occupation should be conducted again.

Article 39 Compensation rate for temporary land occupation should be as follows:

Page 40: RP: PRC: Anjing Reservoir Subproject in Pingyi County ... · Anjing Reservoir was performed. The reservoir is judged as grade-Ⅲ dilapidated reservoir, and this result was checked

34

(1) When construction land within urban planning district is occupied temporarily, compensation should be calculated at the price of land use right in corresponding period. When construction land out of urban planning district is occupied temporarily, compensation should be calculated according to local temporary occupation compensation rate for common farmland. Ground attachments destroyed should be compensated for appropriately according to the actual condition.

(2) Temporary farmland occupation should be compensated for according to AAOV for the three years preceding such acquisition; ground attachments destroyed should be compensated for appropriately according to the actual condition.

(3) Temporary unused land occupation should be compensated for at 30% of the compensation rate for common farmland.

The temporarily occupied farmland should revert by the construction entity within one year after expiry of temporary occupation.

Circular of Shandong Provincial Government Concerning the Adjustment of the Annual Output Value and Compensation Standard of Acquired Land (Lu Zheng Ban Fa [2004] No. 51)

1. Define the lowest standard of AAOV. According to the socio-economic condition of different places, the AAOV is divided into 4 types in Shandong Province in reference to the compensation for newly added construction land use. The detail standards are as follows: the first district is 1,800 Yuan/mu, the second district is 1,600 Yuan/mu, the third district is 1,400 Yuan/mu, and the fourth district is 1,200 Yuan/mu. The lowest AAOV is 1,000 Yuan/mu out of the urban planning area in the whole province. According to the socio-economic condition and difference of corps, municipal government can be compile specific, implementing standards on the basic of the lowest AAOV. And the modified standards should be submitted to Price-Fixing Bureau, Financial Bureau, and Land Recourses Bureau of Shandong Province.

2. Define the standard of land compensation. Land compensation includes land compensation, resettlement subsidy and young crop compensation. In reference to “The Implementation Regulations of Shandong Province for the PRC Land Administration Law”, the standard of land compensation and resettlement subsidy is defined on the basic of the AAOV. The multiple is not below the middle limit of the statutory multiple. The young crop compensation is defined by the municipal government, and is implemented after the approval of the Price-Fixing Bureau, Financial Bureau and Land Recourses Bureau of Shandong Province.

When land acquisition is happened in the urban planning area, compensation standard should be defined reasonably in different places.

3. Set up hearing system of land acquisition. When the compensation standard is defined, hearing should be set up to hear the party’s statement. After defining the compensation standard, the results should be noted to accept supervision.

Page 41: RP: PRC: Anjing Reservoir Subproject in Pingyi County ... · Anjing Reservoir was performed. The reservoir is judged as grade-Ⅲ dilapidated reservoir, and this result was checked

35

Appendix 2 Terms of Reference for External Monitoring

A Objectives of resettlement monitoring and evaluation

In accordance with the requirements of ADB’s resettlement policies, it is to undertake external monitoring and evaluation for resettlement of Risk Mitigation of Endangered Reservoir Project in Shandong Province. Through monitoring the progress, funds mobilization and management of land acquisition, demolition and resettlement, it is to analyze and compare the changes and restoration of the production and livelihoods of the affected people, and thus to provide with follow-up evaluation in this connection. In addition to the regular reports (twice a year in resettlement implementation period) respectively submitted to ADB, SPMO and relevant competent authorities. This process shall also provide information and suggestions to all departments for implementation. Through external monitoring and evaluation, ADB and the project administrative agencies can have full understanding of the conditions and existing problems of land acquisition, demolition and resettlement, such as timely implementation of the resettlement plan, full achievement of the expected targets as well as the suggestions for improvement, etc.

B Major contents of resettlement monitoring and evaluation

(1) Baseline Survey should include: (i) family information; (ii) household annual income and expenditure; (iii) affected land production and income loss; and (iv) affected informal land production and income loss.

(2) Monitoring and evaluation of the progress of land acquisition include: (i) progress of land acquisition; (ii) progress of temporary land occupation; and (iii) progress of house demolition and reconstruction.

(3) Monitoring and evaluation of funds mobilization and utilization include: (i) situation of in-place funds; and (ii) utilization of funds (planned and actual).

(4) Monitoring the implementation of agreed rehabilitation measures, training programns, and post-reservoir development investment.

(5) Monitoring and evaluation of living standards of relocated of people include: (i) production and living conditions before displacement; (ii) production and living conditions after displacement; and (iii) comparative analysis and evaluation of the employment and living conditions before and after displacement.

(6) Evaluation of the capacity of resettlement institutions and the situation of public participation and complaints handling.

C External Monitoring Agency

The external monitoring agency in this project will be undertaken by an external institution entrusted by SPMO and acceptable to ADB.

D Organization and work division for resettlement monitoring and evaluation

Page 42: RP: PRC: Anjing Reservoir Subproject in Pingyi County ... · Anjing Reservoir was performed. The reservoir is judged as grade-Ⅲ dilapidated reservoir, and this result was checked

36

SPMO entrusts external institutions take charge of the investigation, date collection, computing and analysis about the monitoring and evaluation work, and review the research results; The external monitoring institutes compose the Monitoring and Evaluation Group of the Risk Mitigation of Endangered Reservoir Project, the tasks of which conclude monitoring and evaluating the resettlement according to the Involuntary Resettlement Policy of ADB; designing an outline of the monitoring and evaluation work; setting the monitoring spot; monitoring field investigation and internal analysis; and preparing monitoring and evaluation reports in Chinese and English; SPMO provides support in terms of staffing, contacting relevant officials, project documents and transport for the Independent Resettlement Monitoring and Evaluation Institution during on-the-spot monitoring and investigation.

E. Methods of resettlement monitoring and evaluation.

Monitoring and evaluation shall adopt the combined methods of site survey, computational analysis and expert review; The method of point-area method shall be adopted in the survey. The progress, funds, organizations and management of resettlement implementation shall be fully explored; the progress, funds, organizations and management of the resettlement implementation shall be fully explored. Sample survey shall be conducted for the APs; The random sampling method shall be adopted in the sampling survey, while the typical samples shall be followed up for survey. (Samples are taken and categorized among all the affected households involved in the socio-economic surveys at the project preparatory stages. It is primarily decided that all households affected by land acquisition are sampled. All of the vulnerable groups if any are surveyed as sample families). The methods of tabular format survey, interview discussion, archives consultation etc. shall be adopted in the full-coverage survey; In addition to the written materials, other materials such as photos, recordings, videos and articles in-kind shall be also collected.

F M&E Report for resettlement external monitoring

According to the requirements of ADB and the project schedule, the external monitoring and evaluation agency would submit to ADB and SPMO the monitoring report twice a year during resettlement implementation, followed by two annual evaluation reports. The last report will be prepared as a resettlement completon report (i.e., summarizing the entire process and results).