RRMM Architects
Renovations and Expansions to Salem High School
Exploring a Lower Cost Strategy – November 27, 2017
Discussion Agenda
• 1. Brief Overview of Existing Conditions and
Improvement Goals
• 2. Previous Design Concept and Budget
• 3. What if $30M – $35M?...Sobering Statistics
• 4. Proposed Strategy, Alternatives, and Cost
Estimates
• 5. The Impact of Yearly Escalation
The Level of Detail Needed at Each Phase
Decisions should move from Big to Small…
from Macro to Micro…
Existing Site Plan
Second Floor
+ Extensive Facilities+ Excellent Solar Orientation
- Vehicular Challenges- Limited Expansion Options
Existing First Floor Plan
Second Floor
First Floor
+ Well Functioning Major Spaces+ Recent Renovations in Select Areas
- Poor Circulation, Undersized Classrooms (Inadequate for 21st Century Learning)- Mechanical / Electrical Systems need a Major Replacement or Upgrade- Lack of Natural Light- Aged Finishes and Low Quality Walls
Existing Conditions
Second Floor
First Floor
Existing Second Floor Plan
Second Floor
First Floor
Goals, Aspirations, and Priorities
• Develop a Master Plan
• Security and Safety
• Durable, functional, cost
effective
• Appropriate Design v.
Design Awards
• Consider Phasing
• Maximize Current Assets
• Upgrade Building
Systems
• Distinct, visitor-friendly
entrances
• Increase after-hours use for
the community while
limiting access to academic
areas
• Improved Circulation
• Natural Light
• Spaces geared for students
• Maintain a culture of
openness and hospitality
• Commitment to Excellence
• Explore Many Options
Vital Statistics of Previous Plan (2016)
Total Existing Area: 221,000 SF
Total Additions: 75,000 SF
Combined Total: 296,000 GSF
211 SF/Pupil based on enrollment of 1400
RENOVATION / ADDITION: $53 M
Assumed Built in 2 Major Phases separated by 2-3 years
NEW HS (284,000 X $225 - 240.00)/.85 = $75M – $80M
Assumed 4% less SF than a Renovation / Expansion
RATIO OF RENO / NEW: $53M / $75 - $80M = .67 - .70
Future Sports Complex $12M - $13M
What if the Project Budget = $30M - $35M?
Sobering Statistics from the Study completed in Fall 2016:
Phase 1 $26.1M
Phase 2 $27.0M
Total $53.1M
$35M / 53.1M = 66%
$30M / 53.1M = 57%
Volatile Market Adjustment to 57M?
Sitework alone = $4.9M
Heating and Cooling System Improvements = $22M
Bottom Line? A significantly different approach is needed to
work within a range of $30M - $35M…
A New Approach…
• 1. Greatly limit the sitework, “we can live with it…”;
• 2. Build the Additions to solve space shortages, to solve
security issues, and to prepare for future renovations;
• 3. Perform strategic renovations on the lower floor;
• 4. Except for select corridor and vertical circulation
improvements, and strategic, life-extending improvements to
the HVAC system, leave the second floor classroom area
mostly untouched.
Total Project: $37.5M (30% reduction from previous plan)
RRMM Architects
Previous Design Concept
RRMM Architects
Reduced Scope for Site Improvements
RRMM Architects
Reduced Scope for Site Improvements
RRMM Architects
Previous First Floor Plan (2016)
RRMM Architects
Proposed First Floor Plan – Reduced Scope
RRMM Architects
Previous Second Floor Plan (2016)
RRMM Architects
Proposed Second Floor Plan – Reduced Scope
Vital SF Statistics of Proposed Plan
Previous Proposed
Total Existing Area: 221,000 SF 221,000 SF
Total Additions: 75,000 SF 58,000 SF
Combined Total: 296,000 GSF 279,000 SF
RRMM Architects
Potential Master Plan for Second Floor (Phase 2)
RRMM Architects
Exterior design improvements mostly remain…
RRMM Architects
Original Plan (2016)
RRMM Architects
Exterior Design Character
RRMM Architects
Clear Identification of Entrances
RRMM Architects
Clear Identification of Entrances
RRMM Architects
Compatible with Existing Building
RRMM Architects
RRMM Architects
Dining Courtyard Buffered from Parking
RRMM Architects
Birdseye View of Dining Courtyard
North Addition…now or later?
$37.5M v. $32.1M
North Addition…now or later?
• Reasons to make it part of Phase 1:
• 1. Beating escalation ($5.4M now v. $6.6M after 7 years)
• 2. Right sizing classrooms / improved environment now
• 3. Promotes more flexibility and opportunity for incremental
improvements of second floor classroom area from cash
reserves
• 4. Allows you to test classroom configurations before making a
larger investment
• 5. Shortened construction time
• 6. More tangible results for your Phase 1 investment
• Reason to wait until Phase 2:
• 1. Lower cost for Phase 1
• Existing (not including science): 43
• Proposed Plan (North + South Additions): 55*
• If North Addition is not built now: 45
* With proposed plan, more classrooms are right-
sized and incremental improvements can occur on
the second floor over time
“Core Subject” Classroom Changes
Keeping Escalation in Mind…