s. no. particular page no. -...
TRANSCRIPT
INDEX
S. NO. PARTICULAR PAGE NO.
1. FORM -1 1- 22
2. PRE – FEASIBILTY REPORT 1- 38
Table Of Content – Form 1
S. No. PARTICULAR PAGE NO.
(i) BASIC INFORMATION 1
(ii) ACTIVITY 4
(iii) ENVIRONMENTAL SENSITIVITY 19
(iv) PROPOSED TERMS OF REFERENCE FOR EIA STUDIES 22
UNDERTAKING 23
Table of Content – PFR
S. NO. TITLE PAGE NO.
1. EXECUTIVE SUMMARY 1
2. INTRODUCTION OF PROJECT /
BACKGROUND INFORMATION 19
3. PROJECT DESCRIPTION 21
4. SITE ANALYSIS 33
5. PLANNING BRIEF 35
6. PROPOSED INFRASTRUCTURE 37
7. REHABILITATION & RESETTLEMENT PLAN 37
8. PROJECT SCHEDULE AND COST ESTIMATES 38
Annexure:
Annexure – 1 : Environmental Settings Map
Expansion Project Of Manufacturing Kraft Paper (From 60 TPD To 110 TPD) From Agro-Based Residues Raw Material At 7th K.M. Stone, Moradabad Road, Kashipur – 244713 (Distt. Udham Singh Nagar),
Uttarakhand.
Pre-Feasibility Report
M/s Sidharth Papers Ltd. 1
PRE-FEASIBILITY REPORT
1. EXECUTIVE SUMMARY:
1.1 INTRODUCTION
The company is registered under The Companies Act, 1956 vide Regn. No.
24268 on 07.10.1986 for manufacturing of Kraft Paper by its Promoter Sh.
Jitender Kumar, a noted industrialist with vast experience to run the paper
mills since last 30 years.
Sidharth Papers Limited was also established under his guidance and was
commissioned in the year 1987. Recently, the adjoining mill Siddheshwari
Paper Udyog Limited established a Common Chemical Recovery Plant of 120
TPD Black Liquor solids to treat the black liquor generated from both
Sidharth Papers Limiterd and Siddhaeshwari Paper Udyog Limited, This
shows its continual commitment towards environment protection.
A 6 MW captive power plant is also set up at Sidheshwari Paper Udyog Ltd. to
meet the power requirement of both the paper mills.
As on day, the unit is manufacturing 60 TPD of quality kraft paper using agro-
wastes like bagasse and wheat straw and also Indian waste paper. Both kinds
of raw materials are sourced from nearby area.
1.2 COST ESTIMATES
1. Land - 0.00 Lacs
2. Site Development - 10.00 Lacs
3. Building & Materials - 115.00 Lacs
4. Plant & Machines - 150.00 Lacs
5. Environment Management System - 90.00 Lacs
6. Utilities & Other Fixed Assests - 20.00 Lacs
7. Pre-operative Expenses - 10.00 Lacs
8. Interest during construction period- 32.00 Lacs
Expansion Project Of Manufacturing Kraft Paper (From 60 TPD To 110 TPD) From Agro-Based Residues Raw Material At 7th K.M. Stone, Moradabad Road, Kashipur – 244713 (Distt. Udham Singh Nagar),
Uttarakhand.
Pre-Feasibility Report
M/s Sidharth Papers Ltd. 2
Total Project Cost - 427.00 Lacs
9. Working Capital (Additional) - 600.00 Lacs
Total Finance Required - 1027.00 Lacs
Remarks –
• As the project is proposed on existing land, no additional land is
required to be procured for the said project.
• Approx. 32% of the total expenses are reserved for developing &
strengthening the Environment Management within the plant campus.
1.3 REQUIREMENTS FOR THE PROJECT
1. Name of the Industry M/S Sidharth Papers Ltd.
2. Products to be
manufactured
Kraft Paper
4. Total Plot Area 27080 Sq. Mtrs. + 21720 sq. Mtrs for green belt
No Additional Land required
5. Water Requirement
S.
No.
Source
Existing
Quantity
(m3/day)
Quantity after
expansion
(m3/day)
1. Wet washing
system
Nil 940
2. Pulp Mill 400 900
3. Paper 1550 1850
Existing water
requirement
Proposed water
requirement Source
2400 m3/day
2000 m3/day
(Total 4400
m3/day)
Borewell
Expansion Project Of Manufacturing Kraft Paper (From 60 TPD To 110 TPD) From Agro-Based Residues Raw Material At 7th K.M. Stone, Moradabad Road, Kashipur – 244713 (Distt. Udham Singh Nagar),
Uttarakhand.
Pre-Feasibility Report
M/s Sidharth Papers Ltd. 3
machine
4. DM Plant/
Boiler/
Cooling
Tower
140 270
5. Evaporators 70 120
6. Miscellaneous 240 320
Total 2400 4400
6. Steam Requirement
Existing steam
requirement
Proposed steam
requirement Source
162 TPD
135 TPD
(Total 297 TPD)
Boiler of 45
TPH capacity
at
Sidheshwari
Papers Udyog
Ltd.
However one
standby 12
TPH boiler is
provided to
meet the
steam
requirement
during
shutdown of
45 tph boiler
for 2-3 days in
a year.
Expansion Project Of Manufacturing Kraft Paper (From 60 TPD To 110 TPD) From Agro-Based Residues Raw Material At 7th K.M. Stone, Moradabad Road, Kashipur – 244713 (Distt. Udham Singh Nagar),
Uttarakhand.
Pre-Feasibility Report
M/s Sidharth Papers Ltd. 4
6. Power Requirement Existing
power
requirement
Proposed power
requirement
Source
27000
kwh/day 49500 Kwh/day
1. Own captive
power plant
2. 500 KVA
load from
UPCL
7. Manpower
Requirement Particular No.
Total employees in
existing plant 77
Additional Employees
required after expansion 15
Total Employees after
expansion 92
8. Transportation
Density (No. of
vehicles/day)
• Existing
• Proposed
Commercial only -
Average = 22/day
Expected = 35/day
1.4 EMPLOYMENT GENERATION
This expansion shall provide a limited direct employment but there will be huge
indirect employment through raw and finished goods material transport and
other allied activities.
1.5 PROJECT DESCRIPTION
a. Process Description
Raw Material Handling & Processing – The agricultural waste residues are
stored in large open yards and fed directly into five nos. of digesters.
Expansion Project Of Manufacturing Kraft Paper (From 60 TPD To 110 TPD) From Agro-Based Residues Raw Material At 7th K.M. Stone, Moradabad Road, Kashipur – 244713 (Distt. Udham Singh Nagar),
Uttarakhand.
Pre-Feasibility Report
M/s Sidharth Papers Ltd. 5
The waste paper is mixed with water in high consistency (HICON) pulpers to
produce the pulp for blending with agro pulp.
Pulping – The agro-residues are cooked in five nos. of rotary batch digesters in
the presence of steam for high temperature & pressure and caustic, which helps
in softening & release of cellulosic fibres from other non-cellulosic elements like
lignin, pectin etc. The pulp from digesters is blown to blow tank and after
releasing the flash steam through it, it is allowed to enter into screw conveyor
that fed the pulp in two stage screw press.
The first stage screw press squeezes the pulp and the pressed pulp is fed into
second-stage screw press. Then, the pulp is washed finally in the potcher. The
back water from potcher is fed into second-stage screw press and the back water
collected from it is fed into first stage screw press. This system runs in counter-
clockwise direction making a close loop for black liquor. It also helps in
increasing concentration of solids in black liquor and thus, improving economy
of scale of operation of chemical recovery plant.
Paper Making – The agro-pulp & waste paper pulp is mixed in required ratio
prior to feeding in head box of the paper machine. Other factors like burst factor,
consistency, tensile strength, optical properties etc. are maintained in the pulp
through refiners in the pulp mill prior to feeding.
Sheet Formation – The pulp is fed to wire part of the machine and the excess
water is drained out through hydro-foils and vacuum boxes. At the end of the
wire part, the fibers cross-linked each other making a web to form a sheet. It is
picked up by Pick-up roll and pressed between nip of two rolls. The drained
moisture from the nip by pressing action is carried by synthetic forming fabric.
Drying – The paper is passed through a series of steam heated dryers, by which
the inherent moisture of the fiber evaporates, making the sheet dry.
Glazing – Wet paper having moisture content approx. 15-20% passes over the
M. G. (Mono-Glaze) Dryer to give the single side glaze to the paper.
Pope Reel: The paper is rolled on the large spools and then passed for
converting and finishing section.
Expansion Project Of Manufacturing Kraft Paper (From 60 TPD To 110 TPD) From Agro-Based Residues Raw Material At 7th K.M. Stone, Moradabad Road, Kashipur – 244713 (Distt. Udham Singh Nagar),
Uttarakhand.
Pre-Feasibility Report
M/s Sidharth Papers Ltd. 6
Finishing & Converting – The paper rolls are converted into reels of requisite
size as per market orders and packed in HDPE cloth before finally sent to the
customer.
Process flow chart: shown in Fig. 1
b. Location Map
Location Map showing general location, specific location and project boundary and
project site layouts with coordinates is shown in Fig. 2
Expansion Project Of Manufacturing Kraft Paper (From 60 TPD To 110 TPD) From Agro-Based Residues Raw Material At 7th K.M. Stone, Moradabad Road,
Kashipur – 244713 (Distt. Udham Singh Nagar), Uttarakhand.
Pre-Feasibility Report
M/s Sidharth Papers Ltd. 7
Fig. 1 : Process Flow Diagram
Expansion Project Of Manufacturing Kraft Paper (From 60 TPD To 110 TPD) From Agro-Based Residues Raw Material At 7th K.M. Stone, Moradabad Road, Kashipur – 244713 (Distt. Udham Singh Nagar),
Uttarakhand.
Pre-Feasibility Report
M/s Sidharth Papers Ltd. 8
Fig 2: Location Map
Expansion Project Of Manufacturing Kraft Paper (From 60 TPD To 110 TPD) From Agro-Based Residues Raw Material At 7th K.M. Stone, Moradabad Road, Kashipur – 244713 (Distt. Udham Singh Nagar),
Uttarakhand.
Pre-Feasibility Report
M/s Sidharth Papers Ltd. 9
1.6 EXPANSION PLAN
The present production plant is capable to produce 60 TPD of Quality Kraft
Paper. To increase the capacity of the production to 110 TPD, a thorough change
in the existing equipment and some additional equipment is needed. The
adequacy of the existing as well as proposed equipments is described as given
below –
1. Digester
Existing –
No. of Digesters = 05
Capacity of Each Digester = 05 MT per cycle
No. of cycles in a day = 02
Total Agro pulp production = 50 TPD
Proposed Modification –
Installation of additional Rotary Digester (Ф14’)-
The digester is available with the company, however, it is not installed.
This digester will be installed along with other five digesters to make the
counting six and cycle time of the digesters to be increased to 3 times a
day. Hence, total production of 90 TPD of agro pulp will be achieved
through it.
2. HiCon pulper –
Existing -
No. Of HiCon Pulper = 01 No.
Capacity = 15 m3
Consistency = 10%
No. Of cycles = 14 cycles
Each cycle completion time = 35-40 minutes
Total Waste paper pulp prod. = 21 TPD
Expansion Project Of Manufacturing Kraft Paper (From 60 TPD To 110 TPD) From Agro-Based Residues Raw Material At 7th K.M. Stone, Moradabad Road, Kashipur – 244713 (Distt. Udham Singh Nagar),
Uttarakhand.
Pre-Feasibility Report
M/s Sidharth Papers Ltd. 10
Proposed Upgradation –
The HiCon pulpers are capable to operate at higher consistency level.
Keeping the batch timing of 35-40 minutes and continuous supply from
our own captive power generation plant, the total no. of batches can be
increased to 25 nos., thus producing 30 MT of waste paper pulp on OD
basis per day.
3. Refiners in Stock Preparation –
Existing –
There are two nos. of refiners available to refine 50 TPD of agro-pulp.
After mixing both agro & waste paper pulp @ 70 TPD, there are two
refiners to increase the OSR of the pulp.
Proposed –
To enhance the capacity of pulping from 50 TPD to 85 TPD, an additional
refiner of 600 mm disc size is required, that is able to refine 35 TPD of
agro-pulp, hence, the pulp refining capacity can be increased with
increased production of pulp.
After Mixing, two additional refiners in stock preparation to increase
pulp refining capacity to 125 TPD are required.
4. Approach Flow System, Paper Machine & Converting Section –
Existing –
The existing approach flow system is capable to handle 70 TPD of pulp.
Proposed –
To update approach flow system, so that it may handle 125 TPD of pulp,
following updation is required –
•Existing pressure screen to be replaced by new larger one of size
Ф1000 mm x 800 mm from the existing Ф600 mm x 600 mm.
•Open type head box to be replaced by hydraulic head box.
•Increased load in pneumatically loaded roller presses to increase dryness of
Expansion Project Of Manufacturing Kraft Paper (From 60 TPD To 110 TPD) From Agro-Based Residues Raw Material At 7th K.M. Stone, Moradabad Road, Kashipur – 244713 (Distt. Udham Singh Nagar),
Uttarakhand.
Pre-Feasibility Report
M/s Sidharth Papers Ltd. 11
mechanically dried web from 42% to 48% resulting in more speed and
energy conservation.
•To increase the speed of wire part, press part and dryer part, AC drives
of machine needs to be replaced with more efficient AC drives. The
higher speed of machine would produce vibration, hence optical
dynamic balancing of machine shall also be carried out in the expansion
project.
• To handle the additional paper production, one rewinder at the converting
section shall be procured that work in addition to the existing rewinder.
5. Effluent Treatment Plant –
Existing –
The existing effluent treatment plant is capable to handle daily effluent
generation of 2000 m3/day. As the production capacity of the plant is
expected to increase in future to 110 TPD, there will be additional fresh
water consumption and additional effluent generation. As per the
prepared water balance of the mill, the effluent generation is expected to
increase to 3000 m3/day, hence modification/ upgradation of existing
ETP is necessary.
The present ETP comprises of the following units –
S. No. Unit Specification
1. Sump Pit Capacity - 37 m3
2. Vibrating Screen Two
3. Krofta Minicell Op. Capacity - 220 m3/hr
4. Primary Clarifier Capacity – 219 m3
5. Aeration Tank I Capacity – 980 m3
Aerator – 4 x 25 HP
Expansion Project Of Manufacturing Kraft Paper (From 60 TPD To 110 TPD) From Agro-Based Residues Raw Material At 7th K.M. Stone, Moradabad Road, Kashipur – 244713 (Distt. Udham Singh Nagar),
Uttarakhand.
Pre-Feasibility Report
M/s Sidharth Papers Ltd. 12
6. Aeration Tank II Capacity – 395 m3
Aerator – 1 x 30 HP
7. Secondary Clarifier Capacity – 365 m3
8. Sludge Drying Beds Capacity – 210 m3
(7 Nos. – 30m3 each)
To update/ modify the existing Effluent Treatment Plant, the adequacy
requirement of each equipment of the ETP with respect to the flow &
parameters of the effluent is carried out and is given below :
A. POLLUTION LOAD –
Parameter Inlet to ETP (Aeration Tank) Net Pollution Load
Flow, m3/day 3000 m3/day -
pH 6.5 - 7.5 -
COD, mg/l 1200 3600 kg/day
BOD, mg/l 400 1200 kg/day
TSS, mg/l 1200 3600 kg/day
TDS, mg/l 1400 4200 kg/day
ETP Process Description of Existing Plant - After
Expansion -
The waste water from the pulp mill is collected in equalization tank,
from where it is pumped to hill screens where coarse materials are
removed in a rotary screen from the waste water. Then, the effluent is
pumped to Mini Sedi Cell. The Sedi Cell is based on D.A.F. (Dissolved Air
Floatation) technology; the air is mixed with effluent along with anionic
coagulants & flocculants having opposite charge of the waste water. Due
Expansion Project Of Manufacturing Kraft Paper (From 60 TPD To 110 TPD) From Agro-Based Residues Raw Material At 7th K.M. Stone, Moradabad Road, Kashipur – 244713 (Distt. Udham Singh Nagar),
Uttarakhand.
Pre-Feasibility Report
M/s Sidharth Papers Ltd. 13
to reverse charge, the fibers started floating on the surface and are
collected by scum collector rotating continuously on top of the tank. The
so collected fibers are pumped back to the process for use in paper
making and the clear effluent is fed to primary clarifier.
The primary clarifier is fed with lime, alum/PAC and cationic polymers
to settle the floating fines. The fine suspended particles settled at bottom
are collected in a sludge tank and pumped back to the paper
manufacturing section where it is mixed with waste paper pulp.
The effluent from the primary clarifier overflow is conveyed to aeration
tank. The aeration tank is diffused aeration based and the tubular
diffusers are placed in the aeration tank at bottom. The air is diffused
through twin-lobe type root blowers that create a positive pressure in
the system and the air, in the form of fine bubbles, started diffusing the
oxygen while travelling from bottom to tank top. Before, bubbles reaches
top surface, it diffused almost 95% of the oxygen to the water which is
helpful in maintaining the required D.O. level in the aeration tank. Also,
the aeration tank is supplied with the N & P nutrients for bacteria.
Together with nutrients, food and oxygen, the bacteria start degrading
the complex organic molecules and thus COD and BOD reduction
happens in the waste water.
After the aeration system, the effluent is passed through the two
secondary clarifiers, in parallel, where the settled MLSS is circulated,
partially, back to the aeration tank and remaining are collected in sludge
drying beds for dewatering and utilization as manure in green belt in
and around the industry.
DETAILS OF ETP EQUIPMENTS AFTER MODIFICATION
S. No. Unit Specification
1. Sump Pit Capacity - 85 m3
2. Vibrating Screen and Hill Two & one respectively
Expansion Project Of Manufacturing Kraft Paper (From 60 TPD To 110 TPD) From Agro-Based Residues Raw Material At 7th K.M. Stone, Moradabad Road, Kashipur – 244713 (Distt. Udham Singh Nagar),
Uttarakhand.
Pre-Feasibility Report
M/s Sidharth Papers Ltd. 14
Screen
3. Krofta Minicell Op. Capacity - 220 m3/hr
4. Flash Mixing Tank 4 chambers of 4 m3 each
5. Primary Clarifier Capacity – 219 m3
6. Aeration Tank
Dim. – 30.3 m x 16.5 m x 3.5m
Volume – 1750 m3
No. Of Diffusers – 504 Blowers – 2 x 1800 m3/hr
Motor – 2 x 50 HP each
7. Secondary Clarifier No. 1 Capacity – 395 m3
8. Secondary Clarifier No. 2 Capacity – 365 m3
9. Sludge Drying Beds Capacity – 210 m3
(7 Nos. – 30m3 each)
ETP layout: ETP layout for existing unit and after proposed expansion are shown in fig.
3 & 4
Expansion Project Of Manufacturing Kraft Paper (From 60 TPD To 110 TPD) From Agro-Based Residues Raw Material At 7th K.M. Stone, Moradabad Road, Kashipur – 244713 (Distt. Udham Singh Nagar),
Uttarakhand.
Pre-Feasibility Report
M/s Sidharth Papers Ltd. 15
Fig: 3 ETP Flow Chart- Existing
MINICELL
AERATION TANK
No. 1
VOL – 980 M3
Expansion Project Of Manufacturing Kraft Paper (From 60 TPD To 110 TPD) From Agro-Based Residues Raw Material At 7th K.M. Stone, Moradabad Road, Kashipur – 244713 (Distt. Udham Singh Nagar),
Uttarakhand.
Pre-Feasibility Report
M/s Sidharth Papers Ltd. 16
Fig:4 ETP Flow Chart- Proposed
SECONDARY
CLARIFIER NO. 2
SECONDARY
CLARIFIER NO.1
AERATION TANK
VOL – 1750 M3
MINICELL
Expansion Project Of Manufacturing Kraft Paper (From 60 TPD To 110 TPD) From Agro-Based Residues Raw Material At 7th K.M. Stone, Moradabad Road, Kashipur – 244713 (Distt. Udham Singh Nagar),
Uttarakhand.
Pre-Feasibility Report
M/s Sidharth Papers Ltd. 17
6. Boiler & Power Generation –
A common boiler of 45 TPH capacity and a common captive power
generation plant of 6 MW capacity is installed at Siddheshwari Paper
Udyog Ltd. to meet the demand of steam and continuous power of two
units – Sidharth Papers Limited and Siddheshwari Paper Udyog Limited.
Both the units are manufacturing Kraft paper with almost similar
capacity of production.
A 500 KVA connection from Uttarakhand Power Corporation Limited is
also taken to meet out the power demand in case of Turbine shutdown.
A standby boiler of 12 TPH, 10.5 KG/cm2 pressure is also installed at the
Sidharth Papers Ltd. for steam supply to process. The boiler runs only
when there is annual shut of the co-generation plant for few days in a
year.
7. Chemical Recovery Plant –
The chemical recovery plant is based on non-conventional recovery of
sodium carbonate (commonly called soda ash) from the generated black
liquor from the pulping process.
M/s Sidharth Papers Limited has established a Common Chemical
Recovery Plant (CCRP) in collaboration with M/s Siddheshwari Paper
Udyog Limited in their campus. The black liquor is transferred in OD 8”
MS pipeline to the WBL storage tank of CCRP. Also, as an alternate
arrangement, the mill has constructed a RCC drain of 300 mm wide &
500 mm deep to meet out the emergency like rupture of the pipeline or
other unforeseen conditions thereof.
The process description of CCRP is as follows –
• Multiple Effect Evaporator :-
Evaporation is done in long tube multiple effect evaporators (6 –
Effect). The low pressure steam (3–3.5 kg/cm2) is used from turbine
Expansion Project Of Manufacturing Kraft Paper (From 60 TPD To 110 TPD) From Agro-Based Residues Raw Material At 7th K.M. Stone, Moradabad Road, Kashipur – 244713 (Distt. Udham Singh Nagar),
Uttarakhand.
Pre-Feasibility Report
M/s Sidharth Papers Ltd. 18
exhaust as heating media in 1st – effect and weak black liquor feeding
in 5th effect. Black liquor and vapors flow in the system in counter –
current except 6th effect where vapours and liquor flow in the same
direction. The liquor produced is called semi–concentrated black
liquor and collected in separate tanks. Vapors from last body (6th
effect) are condensed in a surface condenser where 680mm of Hg
vacuum is created with the help of a vacuum pump.
Foul condensate and clear condensate of live steam are used in pulp
mill for unbleached pulp washing and in boiler house for steam
generation respectively. Each set of evaporation plant is capable to
concentrate black liquor from 9% to 24% at evaporation rate of 75
TPH and steam economy 4.2 : 1.
• Cope Land Fluidized Bed Reactor (F.B.R.):-
The combustion of semi – concentrated black liquor is completed in a
Reactor. We have selected Fluidized Bed Reactor, which is more
suitable for agro – based black liquor, which have low calorific value
and higher viscosity.
The SCBL is further concentrated from 25% dry solids to 45% in a
direct contact ventury scrubber by hot flue gasses coming from
fluidized bed reactor (F.B.R.). Fluidized bed reactor operates at lower
temperature, i.e., 680 – 700 0C and produce pellets of Sodium
Carbonate on continuous basis.
The FBR consists of a chamber with the wind box at the bottom
which contains the orifice plate and the air nozzles. The orifice plate
in the wind box ensures uniform distribution of fluidizing air. The
bed can be divided into lower bed and upper bed levels which can be
distinguished by bed material density and temperature. The
temperature of the lower bed is higher than that of the upper bed.
The temperature profile of the reactor is wind box – 800 C, lower bed
Expansion Project Of Manufacturing Kraft Paper (From 60 TPD To 110 TPD) From Agro-Based Residues Raw Material At 7th K.M. Stone, Moradabad Road, Kashipur – 244713 (Distt. Udham Singh Nagar),
Uttarakhand.
Pre-Feasibility Report
M/s Sidharth Papers Ltd. 19
– 6800 C – 7000 C, upper bed – 6750 C, and free board – 6200 C.
The upper zone of the reactor is known as the free board. To keep the
temperature of the free board below the melting point of Soda ash,
water is sprayed into the free board from the reactor top. Partially
dried and charred materials move downwards the fluidized bed
zone. The bed materials are kept in suspension by the fluidized air.
The bed temperature is maintained at 680 – 7000C. Pellets of soda
ash are taken out through the side discharge nozzles of the bed at a
predetermined rate so that the bed level is more or less maintained.
The rate of discharge of pellets is controlled by the rate of black
liquor solids firing at the top of the FBR.
2.0 INTRODUCTION OF THE PROJECT/ BACKGROUND INFORMATION
(i) Identification of project and project proponent:
Project Name: Expansion Of Existing 60 TPD Kraft Paper To 110 TPD
Kraft Paper Manufacturing
Project Proponent: M/S Sidharth Papers Ltd.
(ii) Brief description of nature of the project
The present production plant is capable to produce 60 TPD of Quality
Kraft Paper. To increase the capacity of the production to 110 TPD, a
thorough change in the existing equipments and some additional
equipment is needed.
(iii) Need for the project and its importance to the country
The present market conditions and the future trend of the consumption
of kraft paper in various segment like corrugation & packaging for
FMCG companies etc. is increasing northwards, particularly in India.
Increases in productivity through the adoption of more efficient
technologies in the manufacturing sector will be most effective in
merging economic, environmental, and social development objectives.
Expansion Project Of Manufacturing Kraft Paper (From 60 TPD To 110 TPD) From Agro-Based Residues Raw Material At 7th K.M. Stone, Moradabad Road, Kashipur – 244713 (Distt. Udham Singh Nagar),
Uttarakhand.
Pre-Feasibility Report
M/s Sidharth Papers Ltd. 20
The booming Indian economy and a flourishing organised retail have
raised the expectations that consumption of corrugated packaging will
begin to expand again as the number and volume of goods packaged in
corrugated increases. MNCs are demanding corrugated boxes of
international standards and the pattern of buying the packaging is
changing.
The industry is converting about 2 million tons of Kraft paper into
corrugated boxes. Factories are spread out in all parts of India, even in
the remote industrially backward areas.
This present scenario is already being challenged by the sweeping
changes that are beginning to take shape. More and more in-line
automatic plants are being set up, as corrugated box makers gear up to
meet the new demands for high precision boxes with attractive graphics
and large integrated production capacities and hence, the consumption
trend of kraft paper is bound to increase with increasing economic
activities.
Future Trends:
� Increasing demand and high volumes will trigger consolidation and
setting up of efficient plants.
� Use of kraft paper for display/promotional packs, POPs and
dispensers.
� Advances in multicolour, flexo-printing will facilitate in-house
flexo-printing and do away with screen printing, contract printing
on offset presses.
� The emergence of e-commerce, reverse bidding, concept of First
Pak will give large scale units the advantage of competitiveness and
the concept of locating kraft units nearer to user locations will
become obsolete.
Expansion Project Of Manufacturing Kraft Paper (From 60 TPD To 110 TPD) From Agro-Based Residues Raw Material At 7th K.M. Stone, Moradabad Road, Kashipur – 244713 (Distt. Udham Singh Nagar),
Uttarakhand.
Pre-Feasibility Report
M/s Sidharth Papers Ltd. 21
� Large Corporate and Bulk users looking for single/multiple
alternative vendors – capable of meeting stringent specifications,
offering alternative designs, test-in-time deliveries at optimum
cost.
(vi) Employment Generation (Direct and Indirect) due to the project
TABLE – 1
MAN POWER REQUIREMENT
Particular No.
Total employees in existing plant 77
Additional Employees required after
expansion 15
Total Employees after expansion 92
3.0 PROJECT DESCRIPTION
(i) Type of Project including interlinked and independent projects if
any:
The project is a case of expansion in production capacity of Kraft paper
from 60 to 110 TPD from agro based residues raw material.
This is a case of interlinked project as steam and power will be sourced
from M/S Siddheshwari Paper Udyog Ltd. And black liquor will be
treated in Common Chemical Recovery Plant located at M/S
Siddheshwari Paper Udyog Ltd.
(ii) Location
TABLE – 2
DETAILS OF THE AREA
S.
No.
Particulars Details
A. Location details
Expansion Project Of Manufacturing Kraft Paper (From 60 TPD To 110 TPD) From Agro-Based Residues Raw Material At 7th K.M. Stone, Moradabad Road, Kashipur – 244713 (Distt. Udham Singh Nagar),
Uttarakhand.
Pre-Feasibility Report
M/s Sidharth Papers Ltd. 22
1. Name of the Villages(s) Hariawala & Basai
2. Tehsil Kashipur
3. District Udham Singh Nagar
4. State Uttarakhand
5. Latitude
Longitude
29011’53”N
78054’03”E
6. Total Project area
• Existing land Area
• Proposed land Area
27080 Sq. Mtrs. + 21720 sq. Mtrs for green
belt
No Additional Land required
7. Khasra Details 156Ka, 155, 195, 153Ka, 154, 300Ka, 301,
302Kha
B. Production Capacity 110 TPD from existing capacity of 60 TPD
C. Environmental settings
1. Nearest Village Hariawala & Basai
2. Nearest City 1. Thakurdwara at a distance of 3.07 km in
WSW direction.
2. Kashipur at a distance of ~5.2 km in E
direction from the project site.
3. National Highway/ State
Highway/ Express Highway
NH-74 ~ 3.7 km in ENE direction
NH-121 ~ 7.2 km in NE direction
4. Nearest Railway Station Kashipur Railway Station ~ 6Km in ENE
direction
5. Nearest Airport Pant Nagar Airport ~ 59 Km in ESE direction
6. National Parks/ Wild Life
Sanctuaries/ Biosphere
Reserves within 10 km radius
None within 10 km radius area.
7. Reserved / Protected Forest
within 10 km radius (Boundary
to boundary distance)
None
Expansion Project Of Manufacturing Kraft Paper (From 60 TPD To 110 TPD) From Agro-Based Residues Raw Material At 7th K.M. Stone, Moradabad Road, Kashipur – 244713 (Distt. Udham Singh Nagar),
Uttarakhand.
Pre-Feasibility Report
M/s Sidharth Papers Ltd. 23
8. Source of Water Borewells
9. Power Requirement Existing
power
require
ment
Propose
d power
require
ment
Source
27000
kwh/day
49500
Kwh/day
Own captive power
plant at adjoining
Siddheshwari Paper
Udyog Ltd. and
additionally 500 KVA
from UPCL.
10 Seismic Zone Zone - V
D. Cost details
1. Total Cost of Project Rs. 427 Lakhs
(Additional working capital required is Rs.
600 Lacs, hence the total required capital
during & after project is Rs. 1027 Lacs.)
2. Capital Cost of EMP (for
expansion only)
Rs. 130 Lakhs (Approx. 1/3rd of total project
cost)
3. Recurring cost/ annum for
environmental pollution control
measures
Approx. Rs. 95 Lacs per annum
(including chemicals, power, manpower &
maintenance)
(iv) Details of alternative site consideration and basis of selecting the
proposed site particularly the environmental
No alternate site is considered as expansion is proposed in the existing unit
only.
(v) Size or magnitude of operation
Details of Existing & Proposed Products
Expansion Project Of Manufacturing Kraft Paper (From 60 TPD To 110 TPD) From Agro-Based Residues Raw Material At 7th K.M. Stone, Moradabad Road, Kashipur – 244713 (Distt. Udham Singh Nagar),
Uttarakhand.
Pre-Feasibility Report
M/s Sidharth Papers Ltd. 24
Product Existing capacity Proposed capacity
Kraft Paper 60 TPD 110 TPD
(vi) Project description with process details
Detailed manufacturing process has been already covered in section 1.5.
(vii) Raw material required along with estimated quantity, likely source,
marketing area of final products, mode of transport of raw material
and finished product.
S. No.
Particulars
Units
Existing
Production
(60 TPD)
Additional
Production
(50 TPD)
Total
Production
(110 TPD)
(A) Raw material consumption
i. Wheat Straw MT 30 38 68
ii. Bagasse MT 22 33 55
iii. Indian Waste
Paper MT 31 19 50
(B) Chemical Consumption
i. Caustic Soda MT 5.0 4.0 9.0
ii. Fortified Rosin MT 195 kg 161 kg 356 kg
iii. Alum MT 4.55 TPD 3.75 TPD 8.3 TPD
Material Balance: Material Blance for existing unit and after expansion are shown in
figures 6 & 7
Expansion Project Of Manufacturing Kraft Paper (From 60 TPD To 110 TPD) From Agro-Based Residues Raw Material At 7th K.M. Stone, Moradabad Road,
Kashipur – 244713 (Distt. Udham Singh Nagar), Uttarakhand.
Pre-Feasibility Report
M/s Sidharth Papers Ltd. 25
Fig 6: Material Balance For Existing Unit
Expansion Project Of Manufacturing Kraft Paper (From 60 TPD To 110 TPD) From Agro-Based Residues Raw Material At 7th K.M. Stone, Moradabad Road,
Kashipur – 244713 (Distt. Udham Singh Nagar), Uttarakhand.
Pre-Feasibility Report
M/s Sidharth Papers Ltd. 26
Fig 7: Material Balance After Proposed Expansion
Expansion Project Of Manufacturing Kraft Paper (From 60 TPD To 110 TPD) From Agro-Based Residues Raw Material At 7th K.M. Stone, Moradabad Road, Kashipur – 244713 (Distt. Udham Singh Nagar),
Uttarakhand.
Pre-Feasibility Report
M/s Sidharth Papers Ltd. 27
(viii) Resources optimization/ recycling and reuse envisaged in the project, if
any, should be briefly outlined.
• The solid waste generation has been minimised by utilizing the sludge
from Minicell and Primary Clarifier into the pulp mill. This helps in
reducing the sludge handling and cost-economics of the mill by
recovering the fibre and utilizing in paper manufacturing again.
• The condensate water is recycled to the boiler for steam generation.
• The treated effluent utilization in pulp mill for waste paper slushing.
• The treated effluent utilization in decker shower and pulp dilution at
potchers.
• Further, the mill is following the CPCB proposed Charter for Pollution
Prevention and Water Recycling in Pulp & Industries in Ganga River
Basin, into which the mill has proposed to utilise the treated effluent into
low pressure showers of Paper Machine.
(ix) Availability of water its source, energy /power requirement and source
should be given
A. Water Requirement and Source
Table 2.2.2
Water Consumption
Existing water
requirement
Proposed water
requirement
Source
2400 m3/day
2000 m3/day
(Total 4400 m3/day)
Borewell
Water balance chart: Water balance chart for existing unit and after
expansion are shown in figs 8 & 9.
Expansion Project Of Manufacturing Kraft Paper (From 60 TPD To 110 TPD) From Agro-Based Residues Raw Material At 7th K.M. Stone, Moradabad Road,
Kashipur – 244713 (Distt. Udham Singh Nagar), Uttarakhand.
Pre-Feasibility Report
M/s Sidharth Papers Ltd. 28
Fig 8: Water Balance Chart for Existing Unit
Expansion Project Of Manufacturing Kraft Paper (From 60 TPD To 110 TPD) From Agro-Based Residues Raw Material At 7th K.M. Stone, Moradabad Road,
Kashipur – 244713 (Distt. Udham Singh Nagar), Uttarakhand.
Pre-Feasibility Report
M/s Sidharth Papers Ltd. 29
Fig 9: Water Balance Chart After Proposed Expansion
Expansion Project Of Manufacturing Kraft Paper (From 60 TPD To 110 TPD) From Agro-Based Residues Raw Material At 7th K.M. Stone, Moradabad Road, Kashipur – 244713 (Distt. Udham Singh Nagar),
Uttarakhand.
Pre-Feasibility Report
M/s Sidharth Papers Ltd. 30
B. Power Requirement and Source
The total power requirement for the project will be as follows:
Table 2.2.3
Existing power
requirement
Proposed power
requirement
Source
27000 kwh/day 49500 Kwh/day
Own captive
power plant at
adjoining
Sidheshwari
Papers and
additionally 500
KVA from UPCL.
(x) Quantity of waste to be generated (liquid and solid) and scheme for their
management/disposal
A) Solid Wastes
S. No. Solid waste Section
Existing
Quantity
(MT/day)
Quantity
after
expansion
(MT/day)
1. ETP Sludge ETP Nil*1 Nil*1
2. Boiler Ash* Boiler House Nil*2 Nil*2
3. Lime sludge Hypo
preparation Nil*3 Nil*3
4. Lime sludge Caustisizing Nil*3 Nil*3
Total Waste 0 0
*1. The ETP Sludge from Primary Clarifier & Krofta is recycled back to
process manufacturing for kraft paper making. The secondary
Expansion Project Of Manufacturing Kraft Paper (From 60 TPD To 110 TPD) From Agro-Based Residues Raw Material At 7th K.M. Stone, Moradabad Road, Kashipur – 244713 (Distt. Udham Singh Nagar),
Uttarakhand.
Pre-Feasibility Report
M/s Sidharth Papers Ltd. 31
sludge is partly recycled to aeration tank and remaining is dried in
sludge drying beds and used in green belt within the plant.
*2. The boiler (45 TPH) & captive power plant (6 MW) is common for
Sidharth Papers Limited & Siddheshwari Paper Udyog Limited,
established in Siddheshwari Paper Udyog Limited. Both the units
have their separate steam & energy meters for calculating the steam
& electricity consumption of each unit. The ash generation is taking
place in Siddheshwari Paper Udyog Ltd., which is sold to the brick
manufacturers.
*3. Lime sludge in any form is not produced as there is neither
bleaching sequence in production line the causticizing plant in
chemical recovery section.
B) Quantity of Effluent generated and its treatment
i. Black Liquor Generation:
Existing pulp mill
(m3/d)
Proposed pulp mill
(m3/d)
209 385
ii. Treatment of Black Liquor
A Common Chemical Recovery Plant (CCRP) has been established at
Siddheshwari Paper Udyog Limited. It is non-conventional based CCRP to
produce Soda ash from black liquor. The capacity of CCRP is 120 TPD black
liquor solids firing.
iii. Details and capacity of Chemical Recovery Plant
Existing capacity
(tons solid/day)
Proposed capacity
(tons solid/day )
Expansion Project Of Manufacturing Kraft Paper (From 60 TPD To 110 TPD) From Agro-Based Residues Raw Material At 7th K.M. Stone, Moradabad Road, Kashipur – 244713 (Distt. Udham Singh Nagar),
Uttarakhand.
Pre-Feasibility Report
M/s Sidharth Papers Ltd. 32
120 TPD Existing is sufficient. No expansion
plan in CCRP.
iv. Details of ETP for waste water treatment
Details are already given in section 1.6, point no-5
Expansion Project Of Manufacturing Kraft Paper (From 60 TPD To 110 TPD) From Agro-Based Residues Raw Material At 7th K.M. Stone, Moradabad Road, Kashipur – 244713 (Distt. Udham Singh Nagar),
Uttarakhand.
Pre-Feasibility Report
M/s Sidharth Papers Ltd. 33
4.0 SITE ANALYSIS
The existing Sidharth Papers Ltd. plant was established in 1986. The site for
the existing plant was finalized considering the ideal location for the
industries. Following factors were considered while selecting the site for the
existing plant:-
� Nearness to rail route & National Highway No.74 and 121 makes it
easier to import raw materials & final product at market.
� The basic power requirement are met by our own captive power plant
located in campus of adjoining M/S Siddheshwari Paper Udyog Ltd., the
water demand is fulfilled by borewells. There is no shortfall of these
two basic requirements.
� The unit is located in the Terai area and hence copious amount of water
is available.
� Location in considerably lesser industrial & less developed area which
ensured adequate availability of manpower at marginally lower rates
compared to metro cities of India.
� Environment suitability of the present site as large enough space to
provide for all the off sites, auxiliaries, safety, utilities & pollution
abatement systems for air, water & solid waste pollution control.
(i) Connectivity
Kashipur is tehsil in District Udham Singh Nagar. The plant location is well
connected to Thakurdwara city and Kashipur city via National Highway No.
74. Pant Nagar Airport is the nearest airport from the site.
(ii) Land form, Land use and land ownership
The total land area of project site is 48800 Sq meters out of which 21720 sq.
m (~ 44.5%) area is already developed as a green area within site; same will
be maintained through regular monitoring of health of trees / plants. Land is
owned by the unit.
(iii) Topography
Expansion Project Of Manufacturing Kraft Paper (From 60 TPD To 110 TPD) From Agro-Based Residues Raw Material At 7th K.M. Stone, Moradabad Road, Kashipur – 244713 (Distt. Udham Singh Nagar),
Uttarakhand.
Pre-Feasibility Report
M/s Sidharth Papers Ltd. 34
The topography of the area is generally flat with small undulations.
(iv)Existing land use pattern
Land use data as per the 2001 census records belongs to <1% area under
Forest, approximately 62% under cultivation, <2% as Culturable waste and
about 5.6% under `Area Not Available for Agriculture’:
(v) Existing Infrastructure
The proposed proposal is an Expansion project of manufacturing Kraft paper
(from 60 TPD to 110 TPD) from agro-based residues raw material at 7th K.M.
stone, Moradabad Road, Kashipur – 244713 (Distt. Udham Singh Nagar),
Uttarakhand. M/s. Sidharth Papers Ltd. existing unit was established in the
Year 1986 hence the infrastructural facilities are well established, which
shall also be used for the proposed expansion.
(vi) Soil Classification
Most of the study area soils are slightly acidic to neutral, well textured and
possess such physical & chemical characteristics which can support good
vegetative growth. The soils of the agricultural fields are levelled and well
drained. This fact is evident from the thick vegetative cover enjoined by the
Terai region, which is a zone of recently formed gangetic alluvium.
(vii) Climatic data from secondary sources
The climate of the Udham Singh Nagar District varies from Sub-tropical and
sub-humid with three distinct seasons i.e. summer, monsoon (rainy season)
and winter. The rainy season starts from the month of middle June to
September end, and followed by the winter season, which starts from the end
of October and goes up to February. The winter rains are generally
experienced in late December or early January, which brings down the
temperature and that’s how December and January are the coldest months
in the district. The summer season starts from March and it goes up to June.
The hottest months of the year are May and June. The maximum temperature
in the district goes up to 42ºC during the summers and the minimum
Expansion Project Of Manufacturing Kraft Paper (From 60 TPD To 110 TPD) From Agro-Based Residues Raw Material At 7th K.M. Stone, Moradabad Road, Kashipur – 244713 (Distt. Udham Singh Nagar),
Uttarakhand.
Pre-Feasibility Report
M/s Sidharth Papers Ltd. 35
temperature is between 1 and 4ºC, further north of the district, the
temperature comes down to 0.4ºC in winter season.
Rainfall, spatially, is highly variable depending upon the altitude. The
intensity of the rainfall increases from south to north and the amount of
rainfall decreases in generally from west to east. About 90% of the rainfall
received during the monsoon period, and the remaining 10% of the rainfall
in non-monsoon period. The average annual rainfall is 1071.9 mm at the
neasrest IMD station at Bareilly.
(viii) Social Infrastructure available
Population – of Kashipur city is 121610 for the year 2011.
5.0 PLANNING BRIEF
(i) Population Projection
M/s Sidharth Papers Ltd. will plan awareness programs in nearby
area of the project site for control the population under corporate social
responsibilities programs.
(ii) Assessment of infrastructure demand (Physical & Social)
M/s Sidharth Papers Ltd. will assess the demand of infrastructure
(Physical & Social) in nearby area of the site and will be developed
under corporate social responsibilities programmes.
(iii) Amenities/Facilities
M/s Sidharth Papers Ltd. will develop the Amenities/Facilities in
nearby area of the project site as per requirement of local people of the
nearby area under Corporate Social Responsibilities programs.
Plant layout is shown in Figure 10.
Expansion Project Of Manufacturing Kraft Paper (From 60 TPD To 110 TPD) From Agro-Based Residues Raw Material At 7th K.M. Stone, Moradabad Road,
Kashipur – 244713 (Distt. Udham Singh Nagar), Uttarakhand.
Pre-Feasibility Report
M/s Sidharth Papers Ltd. 36
Fig 10: Plant Layout
Expansion Project Of Manufacturing Kraft Paper (From 60 TPD To 110 TPD) From Agro-Based Residues Raw Material At 7th K.M. Ston
Kashipur – 244713 (Distt. Udham Singh Nagar), Uttarakhand.
M/s Sidharth Papers Ltd. 37
6.0 PROPOSED INFRASTRUCTURE
(i) Industrial Area (processing area)
The total land area of the project / plant site is 48800 Sq. m. and the
enhancement in Production Capacity of Kraft Paper (From 60 TPD to
110 TPD) will be within Existing Plant Premises at 7th K.M. stone,
Moradabad Road, Kashipur – 244713 (Distt. Udham Singh Nagar),
Uttarakhand.
(ii) Residential Area (Non processing area)
Residential colony is not proposed for proposed project, as all workers
come from nearby area and for proposed enhancement the preference
will be given to local population in employment opportunities.
(iii) Green Belt
The company has already developed green belt in 44.5 % plot area. Care
had been taken to ensure that the plants in the second row are
staggered between the plants of the first row. Plantation of selected tree
species, which are suitable to condition, has been done for attenuation
of air & noise pollution.
(iv) Social Infrastructure
Project will result in growth of the surrounding areas by increased
direct and indirect employment opportunities in the region including
ancillary development and supporting infrastructure.
(v) Connectivity
The proposed project is well connected with Rail and Road.
(vi) Industrial Waste management
The proposed project will follow CPCB/PCB guidelines for waste
management.
7.0 REHABILITATION AND RESETTLEMENT (R & R) PLAN
Expansion Project Of Manufacturing Kraft Paper (From 60 TPD To 110 TPD) From Agro-Based Residues Raw Material At 7th K.M. Ston
Kashipur – 244713 (Distt. Udham Singh Nagar), Uttarakhand.
M/s Sidharth Papers Ltd. 38
(i) Policy to be adopted (Central/State)in respect of the project
affected persons including home oustees, land oustees and
landless laborers (brief outline to be given)
No rehabilitation and resettlement plan is applicable, as the expansion
in production of Kraft Paper will take place in the existing plant
premises itself.
8.0 PROJECT SCHEDULE AND COST ESTIMATES
(i) Likely date of start of construction and likely date of completion
(time schedule for the project to be given)
The proposed production will start after obtaining Environmental
Clearance from MoEF and all other required clearances and will
complete within one year of commencement.
(ii) Estimated project cost along with analysis in terms of economic
viability of the project
The Total Cost of the project is Rs 427 Lacs.
Additional working capital required is Rs. 600 Lacs, hence the total
required capital during & after project is Rs. 1027 Lacs.