s0241845 - part 2 - evst20002 assignment 3 - robert mitchell
TRANSCRIPT
2015
Robert Mitchell
EVST20002 – Land Management and
Rehabilitation
9/10/2015
Part 2: Restoration Proposal
1
09 October 2015
Site Contracts and Environmental Managers,
Sibelco Australia Pty Ltd
246 Boundary Road,
Parkhurst QLD, 4720
ATTENTION: MR STEVE WILCOCK (Sibelco Kunwarara and Parkhurst Environmental
Manager).
Dear Mr Wilcock,
Oh behalf RM Environmental Management, we would like to thank Sibelco for giving us this
opportunity to put forward recommendations, following baseline review of onsite remediation practice,
to manage restoration over the next three (3) years at the Kunwarara Mine site.
All costs as part of the following restoration proposal submissions as deemed ‘order of costs’ and
specific to baseline study (Part 1). Please note that costs are guaranteed for the first 12 months and are
subject to change following annual review OR if remediation goals are changed as a result of legislative,
social or economic constrains experienced under the existing Environmental Authority (issued 2nd May
2013).
We appreciate the opportunity, and your favourable consideration, as you move through the following
proposal. We look forward to working alongside Sibelco to achieve best practice restoration goals onsite
now and in years to come.
Yours sincerely,
Robert Mitchell
General Manager
RM Environmental Management.
2
Contents
1. Executive Summary: ...................................................................................................................... 3
1. Baseline Technical Summary: ........................................................................................................ 4
2. Uniform rehabilitation framework: ................................................................................................ 5
2.1. Landscape Function Analysis (Qualitative): ........................................................................... 5
2.2. Soil Physical and Chemical Analysis (Quantitative): ............................................................. 5
3. Training Program: .......................................................................................................................... 6
4. Remediation Plan: .......................................................................................................................... 6
5. Order of Cost and Financial Considerations: ................................................................................. 6
6. KPI’s and Targets: .......................................................................................................................... 7
6.1. Training KPI’s: ....................................................................................................................... 7
6.2. Testing and Monitoring KPI’s ................................................................................................ 7
6.2.1. Pre – Excavation: ............................................................................................................ 7
6.2.2. Topsoil Storage: .............................................................................................................. 7
6.2.3. Post – Mining / Restoration: ........................................................................................... 7
6.3. Audit KPI’s ............................................................................................................................. 8
Appendix A: ............................................................................................................................................ 9
Appendix B ........................................................................................................................................... 10
Appendix C ........................................................................................................................................... 13
Appendix D ........................................................................................................................................... 14
7. References: ................................................................................................................................... 15
3
1. Executive Summary: The response, following the Sibelco Pty Ltd Kunwarara Magnesia mine site baseline review, is the
provision of actions aimed to provide best possible approach to achieving environmental management
goals as outlined by section H of current Environmental Authority (Appendix B), including:
Provision of comprehensive technical report current mining and remediation practice success
in achieving landscape functionality best practice.
Delivery of uniform rehabilitation framework, Landscape Function Analysis (LFA), to identify
problems, implement technologies and monitor landscape functionality trends onsite (Tongway
and Ludwig, 2011).
Implement of uniform quantitative (LFA) and qualitative testing procedures (physical and
chemical), including Soil Surface Assessment (SSA), Landscape Organisation Assessment
(LOA) and Ephemeral Drainage-Line Assessments (EDA).
Delivery of technical training and familiarisation courses, to ensure Sibelco RP’s are capable
first time responders in reacting to immediate remediation threats.
Provide recommendations and solution following baseline analysis (Part 1).
Establish order of cost structures relative to both RM Environmental Management and Sibelco
staff for the purpose of budgeting upon reflection of baseline analysis (Subject to variation).
Provision of site and EA specific KPI’s onsite to provide decision making stability against
trended data.
Complete quarterly audits (3 monthly) and submitting findings in written form addressed to the
environmental manager(s) to ensure KPI’s are achieved and managed.
The following proposal is for a contract term of 36 months subject to performance review, with potential
extension to 72 months. Sibelco may terminate the agreement at any time, without penalty and at its
discretion subject to performance failure, within 30 days’ notice following written request to the RM
Environmental Management General Manager.
4
1. Baseline Technical Summary: The purpose is to evaluate variable landscape functionality to promote best practice landscape
remediation practice in accordance with economic, environmental, legislative and social constraints and
establish compliance in accordance with condition A11 of the current EA outlining (Department of
Environment and Heritage, 2014) (Appendix B).
Analysis portrayed current remediation onsite as relatively mature, where the rehabilitation processes
had been successful for a number of years on multiple revegetated site. Despite remediation success,
this summary identify those areas outside of best practice, potentially reducing remediation efficiency
via pathways as outlined below:
Topsoil Bulk Density:
Quantitative significant difference in bulk density sample mean between bare (newly topsoiled)
(µ= 1.422) and revegetated site µ=0.749).
Indicative increased root impedance and subsequent decrease in overall revegetation progress
during primary succession of target site (McKenzie et al., 2004).
Qualitative (SSA) results showing significant variation in sample mean infiltration, stability
and nutrient cycling ability when comparing bare and revegetated sites.
Storage Procedures Post – Disturbance:
Significant mean pH reduction between bare (newly topsoiled) and revegetated sites (bare;
µ=6.064. Revegetated; µ=7.626. t (4) = -12.95, P < 0.001).
Attribute to trace ore oxidisation following initial topsoil disturbance and subsequent storage
as a result of water and oxygen ingress (Mulligan, 1996).
Influenced by time where topsoil samples were stored for extended periods without regular
chemical checks or core checks.
Topsoil redistribution:
Occurring upon completion of counter flow slurry fill (section 2.2 figure 3) with no seasonal
variation in temperature and rainfall taken into account.
Pulse events unlikely during dry season due to lack of trigger events (figure 6, figure 7)
(Tongway and Ludwig, 2011).
In summary, the common trend when comparing non-functional (bare) and functional (rehabilitated)
sites was the variation in bulk density and subsequent infiltration, nutrient cycling capability, stability
and pH drop (Part 1). Results leading to subsequent proposal scope, addressing the management of
topsoil reuse in rehabilitation, from initial excavation through to storage and eventual re-application.
5
2. Uniform rehabilitation framework:
2.1. Landscape Function Analysis (Qualitative): This proposal aims to implement landscape - function based approach by application of LFA procedures
to achieve remediation goals onsite.
The purpose of LFA is to determine changes in the biophysical functionality of a target landscape over
time, in a complex subtropical environment (Part 1, figures 6 and figure 7). (Tongway and Ludwig,
2011).
LFA utilises four time effective methods that are designed to provide uniform information across a
number of sites, allowing remediation targets to be trended and managed accordingly (table 1).
Table 1: Summarises LFA subject, purpose and management benefit (Tongway, 2010).
Method Purpose: Management Benefit
Landscape
Organisation
Assessment
(LOA).
Assessment of Landscape attributes.
Consider biophysical processes
involved in resource retention.
Map landscape organisation,
Plot vegetation density in conjunction
with VSA assessments.
Address self-sustaining vegetation requirements
of the EA (Appendix B).
Progress mapping and trending when comparing
other sites and technologies.
Forecasting and remediation projection when
correlating with climate data.
Soil Surface
Assessment
(SSA).
Aid in generation LOA data relative to
patch vs inter patch variation between
sites.
Assesses stability, infiltration and
nutrient cycling indices of target site.
Qualitative testing style allowing
accurate analysis that is easily
documented.
Used in conjunction with quantitative
soil test results (physical/ chemical
properties).
Provide indicative results to allow baseline
understanding of target site.
Allows remediation techniques to be selected to
promote landscape function (i.e. increase
infiltration, storage capacity and nutrient cycling).
Addresses EA requirement; stable landform
formation similar to surrounding landscape
(Appendix B).
Functional vs. non-functional comparisons.
Ephemeral
Drainage-
Line
Assessments
(EDA).
Drainage stability class of soils onsite.
Assess slope characteristics and
likelihood of active erosion.
Assess drainage line condition and
vegetation function within the drainage
line.
Provide management guidance on target site
erosion probabilities and topsoil loss.
Conjunctional use alongside SSA to determine
soil stability management practice.
Provide grounds to establish water management
KPI’s onsite.
Vegetation
Structure
Assessment
(VSA).
Analyse vegetation structural and
functional role in landscape
remediation.
Assess vegetation density alongside
LOA.
Evaluate patch vs inter patch data and
spatial organisation across sites.
Consider vegetation composition (i.e.
target species).
Address self-sustaining vegetation and
organisation requirements of the EA (Appendix
B).
Trend, map and forecast landscape vegetation
composition and distribution against surrounding
landscapes. I.e. progress indicators.
Provide indicative flora/ fauna distribution
correlations and assumptions when comparing
disturbed and target structure.
2.2. Soil Physical and Chemical Analysis (Quantitative): Bulk density testing using conventional core methods, where the saturated weight and dry weight and
volume are to be used to determine bulk density (g/ cm³) (Carter and Gregorich, 2008) (Appendix C).
pH and conductivity testing will be conducted using conventional 1:5 soil to deionised water
methodologies.
6
3. Training Program: Both RM Environmental Management and Sibelco Pty Ltd are accountable in achieving training KPI’s
as outlined in section 6. Therefore training courses will be delivered by RM Environmental to ensure
restoration practitioners have above average understanding of restoration goals, analysis methodologies
and data interpretation.
Training documents will be supplied in the form of modular units addressing each aspect of LFA
application and analysis, soil property sample collecting, testing and recording as outlined in section 2.
This proposal recognises that training is continual and therefore will be conducted bi-annually and
documented in accordance with Appendix D.
4. Remediation Plan: The following remediation plan addresses specific baseline analysis summaries (section 1). The
overlying purpose is to achieve landscape functionality in an optimal time frame, through revised
topsoil management alongside overall site management. From initial excavation through to storage and
eventual re-application (appendix A).
Best practice methodologies to promote mutualistic mining and remediation goals are defined with the
overall objective to improve both remediation efficiencies, but also optimise mining practice and
Sibelco profitability.
5. Order of Cost and Financial Considerations: The following addresses RM Environmental Management specific costs associated with overview
analysis, consulting, auditing, training and project management (Table 2).
Table 2: Show annual cost based on estimated time in preparation and onsite – subject to variation.
Item Function Quantity Cost Per
Unit
Annual
Spend Results and
Analysis
Weekly Data Review 4 $110 $22,880
Training and
Upskilling
Annual Training and Preperation (16 hours prep, 10 hours
onsite)/ two per year.
56
$110 $6,160
Two days accomodation, flights, transport and meals – two
people two nights.
2 $3,800 $6,760
Auditing and
Reporting
Three monhtly auditing (best practice compliance) 24 hours/ audit.
96 $110 $10,560
Two days accomodation, flights, transport and meals – two
people two nights – Exectuive meetings and presentations.
2 $3,800 $6,760
Project
Management
Project management as required by Sibelco (hourly rate) - $110 -
Project management accomodation, flights, transport and meals per day.
- $3,800 -
Total Spend $53,120
7
6. KPI’s and Targets: KPI’s are in accordance with EA requirements outlined in Appendix B of the following proposal and
are subject to bi-annual review (6 monthly) and annual review (12 monthly) by Sibelco Management
and RM Environmental Management.
6.1. Training KPI’s:
Training will be conducted by RM Environmental Management in bi-annual intervals following
annual reviews to refresh and implement any strategic changes.
Training will be formal, in setting and presented in modular format where a review of operation
manual will be supplied to all involved.
Sibelco will commit to having 4 designated RP’s involved in training to ensure implementation
is achieved and goals are met. Sibelco may include up to 6 additional staff if deemed necessary.
Training logs (Appendix D) will be completed post training where compliance will be assessed
at time of bi-annual review. Non-compliance and additional trading requirements will be at
Sibelco Pty Ltd expense.
6.2. Testing and Monitoring KPI’s
6.2.1. Pre – Excavation:
Soil, organisation and vegetation structure qualitative and quantitative properties will be
measured and recorded ten days prior to initial site excavation to determine baseline/ target
restoration goals in accordance with EA.
Topsoil depth profiles ten days prior to excavation will be recorded to achieve topsoil storage
excavation depths (Appendix A).
6.2.2. Topsoil Storage:
(Where it is not able to be reused immediately):
Soil chemical (including mineral analysis via external source) and physical analysis to be
completed, on each topsoil stock pile, fortnightly. Results trended and collected for fortnightly
RM Environmental Management Review.
Topsoil storage will not exceed 3 months to ensure baseline findings are addressed as outlined
in section 1 of this proposal.
6.2.3. Post – Mining / Restoration:
3 monthly LFA testing to be completed on all restored sites < 3 years old to determine progress
in compared to reference site (non-disturbed site). Results to be trended and sites to be
photographed for RM Environmental Management review.
3 monthly soil chemical and physical analysis to be completed alongside LFA analysis to
determine trend correlations for RM Environmental Management Review.
8
Sites > 3 years will be assumed functional. LFA, physical and chemical monitoring to occur
annually prior RM Environmental annual review.
All post mining analysis will be subject to review and action at both bi annual and annual
meetings.
6.3. Audit KPI’s
Audits will be completed twice a year by RM Environmental Staff over a period of two days
where training and testing complicate will be analysed and addressed as competence and
information are paramount to decision making.
Audit results will be reviewed 6 monthly and decisions will be made surrounding training,
testing and technologies implemented to ensure EA targets are met.
The audit process will be structured around “continual improvement”, where environmental
management and remediation with work institute with mining practice onsite.
Technologies implemented subject to cost benefit review to determine onsite effectiveness
following a period of one year.
9
Appendix A: Kunwarara mine site continual rehabilitation beat practice – Following baseline assessment (Section 1).
Current Site Practice Baseline Interpretation Best Practice / Recommendation Strengths and Weaknesses Topsoil excavation and
storage practice for
period of up to 5 years.
Increase in bulk density between revegetated site and bare site.
Significant reduction topsoil pH – Likely a result ore oxidation following disturbance and exposure to air /
water (Anawar, 2015).
SSA indication of low nutrient cycling ability, infiltration and soil stability as a result of increased
bulk density (Annan-Afful, 2004).
Several changes in physical, chemical and microbial properties as a result of extended storage (Ghose,
2001).
Topsoil excavation following vegetation clearing and mining disturbance (Ghose, 2001).
Excavation to be completed when soil is dry (i.e. during dry season (Baseline report – Figures 6 and 7).
Topsoil horizon depth testing and excavation planning to
determine appropriate scraper depth (i.e. mineral deposit: topsoil contamination kept to a minimum) (Ghose, 2001).
Where possible prevent topsoil storage (i.e. manage mine site
remediation alongside mining practice).
Storage should be on stable ground where erosion control (wind/ water) and unnecessary compaction are taken into
account (Ghose, 2001).
Protect primary root medium from contamination and subsequent productivity, i.e. leaching OR reduction in soil pH as a result of increased
aeration and moisture exposure (Ghose, 2001).
Reduced compaction to topsoil, and therefore bulk density, as a function of reduced smearing remoulding (Ghose, 2001).
Retained topsoil quality (i.e. chemical, physical and microbial) as a result of minimal disturbance as a result of sequential rehabilitation and mining
operations.
Potential reduction in fertilizer program costs to supplement vegetation growth post disturbance.
Potentially negative influence on mining operations and therefore annual ore output, due to climatic variations.
Topsoil re – application
varied across site (i.e. soils
sorted for long periods
used to revegetate).
Significant water: soil ratios as a result of variable storage durations.
Rehabilitation using potentially infertile soils (physical, chemical and microbial) following SSA
analysis.
Topsoil removal and storage practice resulting impeded root growth, nutrient and water availability.
Topsoil re-application and seasonality not taken into account (all year round re application).
Topsoil application to depth recorded during excavation, in compliance with EA goals.
Re – seeding prior to rainfall and seasonal suitability (i.e. beginning of wet season) OR promote irrigation usage onsite
through booms or flood irrigation.
Completed soil chemical analysis to determine soil fertility and vegetation selection, in accordance with EA requirements and
vegetation tolerance to immediate conditions.
Improved topsoil fertility (nutrient, water availability and microbial activity).
Increased response following pulse event (Tongway and Ludwig, 2011)
Improved likelihood of germination success as a result of sequential chemical and physical soil analysis in conjunction with vegetation species
selection.
Reduced likelihood of soil infertility as a result of lengthy storage (McKenzie
et al., 2004).
Increased likelihood of achieving revegetation goals, in optimal time, onsite.
Seed (result of topsoil
storage for period of up to
5 years).
SSA vegetation structure assessment not applicable following topsoil application onto bare site.
High soil bulk density as a result of compaction (µ = 1.442), indicative of root growth restrictions
(McKenzie et al., 2004).
Management of sequential topsoil removal and topsoil filling.
Establish seed bands/ outsource supply of seed bank storage to local contractors.
Implement re – seeding techniques and community
involvement and volunteering (i.e. school groups, university groups or community groups).
Mitigate likely formation of biologically sterile topsoil and seed bank (Ghose, 2001)
Increased likelihood of achieving pasture richness goals as outlined by the EA.
Improved community engagement and environmental perception through planting and education on mining activities.
Topsoil contouring and
ripping. – Slope gradient
< 2.
SSA collection showing minimal signs of erosion given “moderate drainage” across site following high
rain fall evets.
No change to practice required.
Deep ripping and contouring stored soil to remain constant.
Improved topsoil quality at time of re-application, resulting in improved infiltration and storage capacity (Kolka and Smidt,
2004).
Reduction topsoil loss due to mechanical restriction and reduced overland flow carrying capacity (Wu et al., 2010).
Improved infiltration rate as a result of reduced flow rate (Wu et al., 2010).
Significant reduction surface run off volume, sediment production and bulk
density (Kolka and Smidt, 2004).
Engineering and equipment costs can be costly and significantly influence required payback periods.
Monitoring remediation
based on visual analysis
and comparisons with
mature sites in
accordance with EA.
Remediated landscapes often successful with
desirable soil pH and bulk density, VSA, LOA and
SSA.
Ongoing quantitative and qualitative results non-
existent, remediation efficiencies not established
timeframe optimisation
Implement routine remediation analysis, qualitative and
quantitative (Section 2).
Implement RP training program to promote Sibelco staff swift first time response to changes in goals or practice AND
promote remediation across site.
Introduce remediation monitoring and trending as per adaptive learning loop outlined by Tongway and Ludwig 2011.
Promote data and record collection for period of 5 years to allow review and auditing (both independent and as per EA
requirements).
Likely meet EA goals faster by collecting data trends and optimising
remediation efficiencies (time and best practice) (Tongway and Ludwig,
2011).
Long-term cost effective option (i.e. implementation costs < penalty costs).
Adapt to trends and make changes to meet EA requirements (Appendix A).
Review management of restoration onsite to allow budget formation and
determine applicable financial, social or stakeholder value.
10
Appendix B – Sibelco Land Remediation – Obtained from current Environmental Authority (EA) (Department of Environment and Heritage, 2014).
13
Appendix C - Method obtained section 57.2.1 CORE Methods – Materials and supplies, procedures and Calculations (Carter and Gregorich, 2008).
14
Appendix D – Training Schedule and Recording:
Training Date Module Attendees Signature
Robert Mitchell
General Manager
RM Environmental Management.
15
7. References: ANAWAR, H. M. 2015. Sustainable rehabilitation of mining waste and acid mine drainage using
geochemistry, mine type, mineralogy, texture, ore extraction and climate knowledge. Journal
of Environmental Management, 158, 111-121.
ANNAN-AFFUL, E. 2004. Nutrient and bulk density characteristics of soil profiles in six land use
systems along topo-sequences in inland valley watersheds of Ashanti region, Ghana. Soil
Science & Plant Nutrition, 50, 649.
CARTER, M. R. & GREGORICH, E. G. 2008. Soil sampling and methods of analysis. [electronic
resource], [Pinawa, Manitoba] : Canadian Society of Soil Science ; Boca Raton, FL : CRC
Press, c2008.
DEPARTMENT OF ENVIRONMENT HERITAGE AND PROTECTION. 2014. Permit
Environmental Protection Act: Environmental Authority EPML00651713. In:
DEPARTMENT OF HERITAGE AND PROTECTION. (ed.).
2nd ed.
GHOSE, M. 2001. Management of topsoil for geo-environmental reclamation of coal mining areas.
Environmental Geology, 40, 1405-1410.
KOLKA, R. K. & SMIDT, M. F. 2004. Effects of forest road amelioration techniques on soil bulk
density, surface runoff, sediment transport, soil moisture and seedling growth. Forest Ecology
& Management, 202, 313-323.
MCKENZIE, N., JACQUIER, D., ISBELL, R. F. & BROWN, K. 2004. Australian Soils and
Landscapes. [electronic resource] : An Illustrated Compendium, Melbourne : CSIRO
Publishing, 2004.
MULLIGAN, D. R. 1996. Environmental management in the Australian minerals and energy industries
: principles and practices. [electronic resource], Sydney : UNSW Press, 1996.
TONGWAY, D. J. 2010. The LFA monitoring procedure [Online]. [Accessed 5 October 2015].
TONGWAY, D. J. & LUDWIG, J. A. 2011. Restoring Disturbed Landscapes : Putting Principles Into
Practice, Washington, D.C., Island Press.
WU, J. Y., HUANG, D., TENG, W. J. & SARDO, V. I. 2010. Grass hedges to reduce overland flow
and soil erosion. Agronomy for Sustainable Development (EDP Sciences), 30, 481-485.