s40_case study rapid embankment construction of us 17 bypass interchange over soft compressible...
TRANSCRIPT
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
1/124
Case Study: Rapid Embankment Construction of
US 17 Bypass Interchange Over Soft Compressible Soils
Using Lightweight Aggregate
Myrtle Beach, South Carolina
Ed Tavera, PE
Jeff Speck, PE
February 17 - 20, 2013
Presented By:
Louisiana
Transportation Conference
Big River Industries, Inc.
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
2/124
Project Overview & Design Requirements
Project Constraints
Geotechnical Challenges
Rapid Embankment Construction
Lightweight Aggregate Borrow Proposed
Compaction Verification
Lightweight Aggregate Supply & Delivery Automated Geotechnical Instrumentation & Results
Project Construction Pictures
Closing
Presentation Agenda
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
3/124
PROJECTOVERVIEW
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
4/124
Project LocationMyrtle Beach, SC
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
5/124
Project Location
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
6/124
Project Site
US17 Bypass
East
N. Myrtle BeachMurrels Inlet
SC 707
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
7/124
Relieve growing traffic congestion
Provide a facility to handle future
development and growth
Construct a safe, signature projectfor the
stakeholders (Horry County, SC)
Purpose
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
8/124
US 17 Bypass
Farrow Parkway
SC 707
Ramp C
Ramp A
Ramp D
Ramp B
Project Layout
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
9/124
Proposed Interchange
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
10/124
175 225 300 175 140225
Bridge Span Lengths(Bridge Length 1,240 Feet)
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
11/124
Bridge Aesthetic Features
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
12/124
Bridge Features
Interior Bent Cap Extensions
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
13/124
Retaining Wall Features
(Rendering)
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
14/124
Wall Features
Columbia
International
AirportInterchange
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
15/124
Local Funding - led to higher
expectations for project
completion
Heavy traffic volumes
necessitated accelerated
construction
Elimination of long
settlement waiting period Led to innovative
geotechnical design and
construct techniques
Schedule
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
16/124
DESIGNREQUIREMENTS
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
17/124
AASHTO LRFD Design
Strength Limit State
Service Limit State
Extreme Event I Limit State (Seismic)
Extreme Event II Limit State (Collision)
Design Requirements
Performance Based Design
Service Limit State
Extreme Event I Limit State (Seismic)
Extreme Event II Limit State (Collision)
AASHTO LRFD Design
Strength Limit State
Service Limit State
Extreme Event I Limit State (Seismic)
Extreme Event II Limit State (Collision)
Performance Based Design
Service Limit State
Extreme Event I Limit State (Seismic)
Extreme Event II Limit State (Collision)
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
18/124
US Earthquakes 1705 - 1996
Seismic Hazard
1886
Charleston
Earthquake
MW 7.3
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
19/124
Charleston fault zone
(Woodstock fault) and
the Zone of River
Anomalies (ZRA) faultsource
Moment magnitude from
7.0 to 7.5. 1886 Charleston
Earthquake
SC Seismic Hazard
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
20/124
SC Seismic Hazard
FEE PGA 0.06g @ B/C Boundary
SEE PGA 0.24g @ B/C Boundary
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
21/124
Safety Evaluation Earthquake (SEE),ground
shaking having a 3% probability of exceedance
in 75 years (2,500 year return period)
PGA = 0.39g
Functional Evaluation Earthquake (FEE),
ground shaking having a 15% probability of
exceedance in 75 years (500 year return period)
PGA = 0.13g
Extreme Event I Limit State
SC Design Earthquakes
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
22/124
PROJECT
CONSTRAINTS
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
23/124
High existing traffic volume
No lane closures during summer
months
Maintaining access to numerousbusinesses
Traffic Control
Complex construction traffic control plan
8 proposed stages of construction
Maintain existing number of lanes Temporary pavement
Multiple traffic shifts
Temporary alignments
Detour routes
http://www.canstockphoto.com/file_view.php?id=5654193 -
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
24/124
Traffic Control Maintain Existing Number of Lanes
& Access to Numerous Business
Embankment Construction Traffic Control Stages 2,
3, and 4
Project Geometry and Layout
Existing Alignment
Limited R/W
Limited Construction Staging Areas
Construction Time Requirements3.5 years
Project
Constraints
http://www.canstockphoto.com/file_view.php?id=5654193 -
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
25/124
GEOTECHNICALCHALLENGES
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
26/124
Fantasy Harbour
US 17/SC 707
(Backgate)
2 Miles Away!
Myrtle Beach, SC
Regional Experience
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
27/124
2 Miles North of US 17 /SC 707 Interchange
New Alignment
Bridge Over the Atlantic Intracoastal Waterway
3.1 Miles Roadway Approaches and Bridge
Fantasy Harbour
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
28/124
Fantasy Harbour West
Abutment Subsurface Soils
SB2 RB-24 RB-25 RB-27 SB1 RB-28 RB-29
0 ft-
msl
-50 ft-
mslPee Dee Formation
Very soft to medium
CLAYs (CL/CH)
Very loose to medium SANDs (SP/SC/SM)
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
29/124
Fantasy Harbour East
Abutment Subsurface Soils
RB-13 SB6 SB1 RB-11 RB-16 SB2-A
SB3-A
SB5
0 ft-msl
-50 ft-
msl
Very loose to medium SANDS (SP/SM/SC
Pee Dee Formation
Very soft to medium CLAYs (CL/CH)
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
30/124
10 42 Embankment,
Settlement 9 to 67
Liquefaction Loose Sands
Embankment SlopeInstability (Static/Seismic)
Fantasy Harbour
Geotechnical Experience
Ground Improvement!!!
2 Year Embankment Construction Contract 2-3 Year Bridge Construction Contract
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
31/124
North Bridge
Approach
South Bridge
Approach
Lets Return To US 17/ SC707
Interchange (Backgate)
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
32/124
South Bridge Approach
Subsurface General Profile
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
33/124
North Bridge Approach
Subsurface General Profile
http://www.canstockphoto.com/file_view.php?id=5654193 -
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
34/124
30 to 60 - Soft to Firm Clay
Pockets of Loose Sands in upper 10
Intermediate Medium Sands (253+00 to 256+00) Loose Sands above Dense Sands (Liquefiable)
Pee Dee Formation
Geotechnical
Challenges
http://www.canstockphoto.com/file_view.php?id=5654193 -
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
35/124
Bridge Abutment Settlement
(Normal Weight Fill 120 pcf)
http://www.canstockphoto.com/file_view.php?id=5654193 -
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
36/124
Poor Site Subgrade (2 3 Bridging Required)
Excessive Settlement (Total & Differential)
Static Slope Embankment Instability/Bearing
Seismic Slope Embankment Instability (Liquefaction)
Geotechnical
Challenges
http://www.canstockphoto.com/file_view.php?id=5654193 -
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
37/124
RAPID
EMBANKMENT
CONSTRUCTION
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
38/124
Geotechnical
Challenges
Project
Constraints
Rapid Embankment
Construction
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
39/124
Settlement Total & Differential
Embankment Slope Instability / Bearing
(Static/Seismic) Bridge Abutment Foundation
Performance - Extreme Event I and II
Limit States
MSE Wall Construction Over Soft Soils
Geotechnical
Key Design Issues
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
40/124
Lightweight Aggregate Borrow Reduce Magnitudeof Settlement
Prefabricated Vertical Drain (PVD) / GranularSurcharges Increase Rate of Settlement andFacilitate Rapid Construction
Deep Soil Mixing Improve Seismic Slope Stabilityand Bridge Abutment Foundation Performance
Mechanically Stabilized Earth (MSE) Walls 2-Stage and 3-Stage MSE Wall Construction
Vertical Slip Joints
Geotechnical
Design Approach
Granular Surcharge &
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
41/124
Granular Surcharge Properties: = 32 degrees
Unit Weight: 125 pcf
Granular Surcharge
Lightweight Aggregate
Borrow Material
Lightweight Aggregate Properties:
= 40 degrees
Short Term Unit Weight: 60 pcf
Long Term Unit Weight: 70 pcf
MSE Wall Backfill Properties
NormalWeight
Normal
Weight
Lightweight
Aggregate
Granular Surcharge &
Lightweight Aggregate Borrow
Li ht i ht A t B
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
42/124
Lightweight Aggregate Borrow
(Rotary Kiln Produced)
226,000 CY
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
43/124
3 Million LF
PVD
Installation
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
44/124
PVD
PVD Triangular Installation Pattern
PVD
S
2 Drainage Sand Layer
Geotextile Separator Fabric
s = 3 and 4
PVD Installation
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
45/124
Predrilling PVD Installation
309,000 LF
PVD Installation
Obstructions!!!
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
46/124
Permanent MSE Walls Two-Stage Construction
Three-Stage Construction (w/Drainage Structures)
Temporary MSE Walls
(Welded Wire Mesh Facing)
30,500 SF
51,500 SF
MSE Walls
il i i l
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
47/124
Seismic Slope Stabilization Shear Key Improved Performance of Bridge Abutment Foundations
2013
35,600 CY
Deep Soil Mixing Columns
(Overlap Block Pattern)
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
48/124
Bridge Abutment DSMLongitudinal DSM Longitudinal DSM
Deep Soil Mixing Columns(Overlap Block Pattern)
D S il Mi i
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
49/124
Legend
Test Lime-Cement Columns (Test LCC)
DSM-LCC Test Section 1
(Block Type Pattern)
DSM-LCC Test Section 2
(Single Line Pattern)
10 Feet Min.
10Fe
etMin.
Test LCC No. 1 2 3 4
Test Pile 1 (HP
14x117)
Test LCC Sampling
Quadrants
1 2
4 3
Deep Soil Mixing
Test Sections
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
50/124
CONSTRUCTIONSEQUENCE
P j t C t ti St
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
51/124
Ramp BStage 2
Ramp DStage 3
Bridge Approach EmbankmentStage 4
Project Construction Stages
(North Abutment 252+01)
Bridge Abutment Construction
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
52/124
Bridge Abutment Construction
(North Abutment End Bent 7)
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
53/124
HP 14x117
22 Piles/row
30 Feet
DSM-LCCBlock Type
Pattern MSE Wall Leveling Pad
PVD
(Wick Drains)
MSE Wall Concrete
Panel Facing
Bridge Wing Wall Vertical Slip Joints
Bridge Abutment Construction
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
54/124
LIGHTWEIGHT
AGGREGATEBORROW
PROPOSED
Lightweight Aggregate Borrow
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
55/124
Lightweight Aggregate Borrow(Proposed New Material)
Lightweight Aggregate Borrow
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
56/124
Lightweight Aggregate Borrow
(Rotary Kiln Produced)
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
57/124
0
10
20
30
40
50
60
70
80
90
100
0.0100.1001.00010.000100.0001000.000
%Passing
Grain Size (mm)
LWF Min
LWF Max
713 Min
713 Max
BR Min
BR Max
LWA (S15922)
Section 713
MSE Wall
Big River
Proposed
Lightweight
Aggregate
1 " " 3/8" # 4 # 100# 40# 30 # 200
Grain Size Curve
Lightweight Aggregate
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
58/124
Lightweight Aggregate Borrow Soil Properties (Item 2033020)
Soil Properties SCDOT Specified Proposed
Minimum: Dry Unit Weight, gDry (pcf) 55 43*
Maximum: Dry Unit Weight, gDry (pcf) 60 45**
Minimum: Wet Unit Weight, gWet (pcf) 60 55**
Maximum: Wet Unit Weight, gWet (pcf) 70 60**
* 95% Maximum Density**Estimated based on laboratory testing submitted by Big River Industries
Lightweight AggregateDensity Properties
Lightweight Aggregate Borrow
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
59/124
Higher Fines Content
Lower Dry Unit Weight
Total Unit Weight 15% Less Than Designed
High Absorption
Gradation Coarse Sand Vs. Aggregate Compaction Verification Required by SCDOT
Lightweight Aggregate Borrow(Proposed New Material Differences)
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
60/124
Test Section #1 (Dry)
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
61/124
Test Section #1 (Wet)
Granular Surcharge &
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
62/124
Granular Surcharge
Granular Backfill
Lightweight Aggregate
Borrow Material
Design Team Performed a Redesign
Reduced the Lightweight Quantity by15%
Saved Horry County $2 Million
Granular Surcharge &
Lightweight Aggregate Borrow
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
63/124
COMPACTIONVERIFICATION
Lightweight Aggregate Borrow
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
64/124
Interparticle Moisture
Interparticle Voids
Particle Absorbed Moisture
Particle Pore Voids
Particle Ceramic Solids
Lightweight Aggregate Borrow
Compaction Verification Challenges
C i C l
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
65/124
Laboratory Compaction Curves
Target 95% Max Dry Density = 43 pcf
Moisture Content Varied Significantly for the
same Dry Density
Compaction Control
Test Section #2
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
66/124
Test Section #2 - Evaluate Compaction ControlMethods
Compaction Control - 1 Cu. Ft. Steel Box,
Calibrated Nuclear Density Gauge, Sand Cone,and EDG.
Test Section #2
Compaction Control
Test Section #2
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
67/124
SC = Sand ConeNG = Nuclear Gauge
EDG = Electric Density Gauge
STB = Steel Test Box
EDG-1
Compacted
Lightweight
Aggregate
BorrowMC-3
STB
EDG-2SC-1
SC-2
SC-3
MC = Hot Plate & Oven Moisture ContentMT = Moisture Tester
MTB = Moisture Tester in Steel Box
MC-1 MC-2
EDG-3
NG-1
NG-2
NG-3
MT-1
MT-2
MT-3MT-4
MTB-1MT-5 MT-6
MT-7 MT-8MTB-2
MTB-3
Test Section #2
Field Testing Set
Test Section #2
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
68/124
Test Section #21 Cu. Ft Steel Box (Control Test)
Test Section #2
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
69/124
Test
SetMoisture Added Process Compaction Effort
1 As delivered Compact 3 passes with vibratory roller
2 No Water Added Scarify & Compact 4 passes with a vibratory roller
3
Added Water - 1 Pass Scarify & Compact 8 passes with a walk behind
vibratory flat plate compactor
4Added Water - 2 Passes Scarify & Compact
3 passes with a vibratory roller
5 No Water Added Scarify & Compact 4 passes with a vibratory roller
6 No Water Added Scarify & Compact 8 passes with a vibratory roller
7
Added Water- 2.5 Passes
(Saturated)Scarify & Compact
3 passes with a vibratory roller
Test Section #2
Field Testing Sets
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
70/124
Test Section #2
Compaction Control
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
71/124
Compaction Control
Calibrated Nuclear Gauge
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
72/124
LIGHTWEIGHT
AGGREGATE
SUPPLY & DELIVERY
Big River Industries
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
73/124
Big River IndustriesLivingston, AL Myrtle Beach, SC
Big River Industries
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
74/124
Big River Industries500 Mile Radius Livingston, AL
Livlite
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
75/124
Livlite
Big River Industries
Lightweight Aggregate Borrow
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
76/124
Lightweight Aggregate Borrow
Pre-conditioning
Lightweight Aggregate Borrow
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
77/124
g g gg g
Pre-conditioning
Ramp B Construction
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
78/124
CONSTRAINTS
Ramp B ConstructionPre-conditioned Lightweight Aggregate
Ramp B Construction
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
79/124
CONSTRAINTS
pPre-conditioned Lightweight Aggregate
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
80/124
GEOTECHNICALINSTRUMENTATION
Geotechnical Instrumentation
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
81/124
Settlement Monitoring 4 Magnetic Extensometer
10 Settlement Plates
12 VW Settlement Sensors
17 VW Piezometers
2 VW Data Collection Centers
Slope Stability
6 Slope Inclinometers
Geotechnical Instrumentation
VW Magnetic Extensometers
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
82/124
Spider MagnetPre-Assembled ME Telescoping Section
VW Magnetic Extensometers
Instrumentation Results
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
83/124
-70
-60
-50
-40
-30
-20
-10
0
10
20
-10.0-9.0-8.0-7.0-6.0-5.0-4.0-3.0-2.0-1.00.01.0
Elevation(feet)
Settlement (Inches)
12/1/2011
12/7/2011
12/14/2011
12/19/2011
12/21/2011
12/27/2011
12/29/2011
1/4/20121/12/2012
1/18/2012
1/25/2012
2/1/2012
12-22-2011
Embankment
Construction
Finished
-8
-7
-6
-5
-4
-3
-2
-1
0
1
2
3
4
5
6
7
8
9
10
11
12
0 7 14 21 28 35 42 49 56 63 70
EmbankmentH
eight(Feet)
Days
Embankment
HeightTop of LWF
Datum Magnet
SA-1
SA-2
Settlemen
t(Inches)
ME Extensometers
VW Piezometers
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
84/124
VW Piezometers
Instrumentation Results
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
85/124
VW Piezometers
Settlement Plates
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
86/124
Settlement Plates
VW Settlement Sensors
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
87/124
VW Settlement Sensors
VW Settlement Sensor
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
88/124
Data Collection
Automated Data Collection
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
89/124
VW Data
Collection
Logger
VW
Settlement
Sensors
VW
Piezometers Engineer
Internet
Power Source
(Solar Power)
Database
ServerCellular Phone
VW Device
Connection
Board
VW Data Collection Center
Automated Data Collection
VW Device Connections
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
90/124
VW Devices connected to 16-channel Board
VW Device Connections
Data Collection Center
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
91/124
iSite Logger with Solar Controller
Charging Battery
Inside DCC Enclosure
& Solar Panel
Data Collection Center
X-Section End Bent 1
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
92/124
(South Bridge Abutment, 237+50)
Settlement Transverse Profile
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
93/124
Ramp A
(South Bridge Abutment 237+83)
Ramp A
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
94/124
Settlement Measurements
2-12-2011
Embankment
Construction
Finished
2-14-2012
Surcharge
Removed
-6
-5
-4
-3
-2
-10
1
2
3
4
5
6
7
8
9
10
11
12
13
14
0 714
21
28
35
42
49
56
63
70
77
84
91
98
105
112
119
126
133
140
147
154
161
168
175
182
189
196
203
210
217
224
231
238
EmbankmentHe
ight(Feet)
Days Since VWSS Installed
US-17 Bypass
Settlement Sensor A-VWSS-2
Embankment Height
Lightweight Fill Height
SS Reading No. 1- 5:00
SS Reading No. 2- 12:00
SS Reading No. 3- 19:00
SS Reading No. 4- 23:00
Settlement
Settlement Transverse Profile
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
95/124
Ramp C
(South Bridge Abutment 237+83)
Ramp C
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
96/124
Settlement Measurements
9-13-2012 Emankment
Construction Finished
12-14-2012
Surcharge
Removed
-3
-2
-1
0
1
2
3
4
5
6
7
8
9
10
11
12
13
0 714
21
28
35
42
49
56
63
70
77
84
91
98
105
112
119
126
133
140
147
154
161
168
175
182
189
196
203
210
217
224
EmbankmentH
eight(Feet)
Days Since VWSS Installed
Embankment Height
Lightweight Fill Height
SS Reading No. 1- 5:00
SS Reading No. 2-
11:00
Settlement(Inches)
X-Section End Bent 7
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
97/124
(North Bridge Abutment, 250+26)
Settlement Transverse Profile
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
98/124
Ramp B
(North Bridge Abutment - 250+26)
Ramp B
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
99/124
12-22-2011
Embankment
Construction
Finished
4-10-2012
Surcharge
Removal
-12
-11
-10
-9
-8
-7
-6-5
-4
-3
-2
-1
0
1
2
3
4
5
6
7
8
9
10
11
12
0 714
21
28
35
42
49
56
63
70
77
84
91
98
105
112
119
126
133
140
147
154
161
168
175
182
189
196
203
210
217
224
231
238
245
252
259
266
Embankment
Height(Feet)
Days Since VWSS Installed
Settlement Sensor
Embankment Height
Lightweight Fill Height
SS Reading No. 1 - 5:0:0
SS Reading No. 2 - 12:0:0
SS Reading No. 3 - 19:0:0
SS Reading No. 4 - 23:0:0
Settlement
Settlement Measurements
Settlement Transverse Profile
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
100/124
Ramp D
(North Bridge Abutment - 250+26)
Ramp D
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
101/124
Settlement Measurements
10-26-2012
Emankment
Construction Finished
2-5-2013 Surcharge
Removed
-14-13-12-11-10
-9-8-7-6-5-4-3-2-10123456789
1011
12131415161718192021222324
0 14 28 42 56 70 84 98 112 126 140 154 168 182
EmbankmentH
eight(Feet)
Days Since VWSS Installed
Embankment
HeightLightweight Fill
HeightSS Reading No. 1-
5:00SS Reading No. 2-
12:00SS Reading No. 3-
19:00
Settlement
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
102/124
PROJECTCONSTRUCTION
Traffic Control Stage 2
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
103/124
MSE Walls
Lightweight Aggregate Borrow Material
2, and 3 Granular Surcharge (Normal Weight)3 and 4 Triangular Spacing PVD
Geotechnical Instrumentation
Ramp BRamp A
Traffic Control Stage 2
Traffic Control Stage 2
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
104/124
Traffic Control Stage 2
Ramp A Construction
US 17 Bypass NB
Traffic Control Stage 2
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
105/124
Traffic Control Stage 2
Ramp B Construction
US 17 Bypass NB
Construction Ramp A & B
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
106/124
(PVD Installation)
Construction Ramp A & B
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
107/124
(PVD Installation)
Construction Ramp A & B(MSE W ll E b k C i )
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
108/124
(MSE Wall Embankment Construction)
Construction Ramp A & B( ll b k )
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
109/124
(MSE Wall Embankment Construction)
Sloped Lightweight
A t E b k t
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
110/124
2 Feet Thick Cover of Borrow
Silty or Clayey Soil Materials
Lightweight Aggregate
Borrow Material
4 Feet Long Biaxial Geogrids
Placed on 2 Feet Vertical
Spacing
Aggregate Embankment
Sloped Lightweight
A t E b k t
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
111/124
Aggregate Embankment
Traffic Control Stage 3
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
112/124
Ramp C
Ramp D
MSE Walls
Lightweight Aggregate Borrow Material
1, 2, and 4 Granular Surcharge (Normal Weight)3 and 4 Triangular Spacing PVD
Geotechnical Instrumentation
g
Traffic Control Stage 3(R A & B C l t d)
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
113/124
Constructed Ramps A/B
(Completed Stage 2)
Existing NB= Stage 3 SBRamps C/D UnderConstruction -Stage 3
(Ramps A & B Completed)
Traffic Control Stage 3(R A & B C l t d)
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
114/124
Traffic on Ramp A
Existing NB = Stage 3 SB
(Ramps A & B Completed)
Construction Ramp C
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
115/124
Traffic on Ramp C
p
US 17 Bypass SB
Construction Ramp C
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
116/124
Traffic on Ramp C
p
US 17 Bypass SB
Construction Ramp C
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
117/124
Ramp D
US 17 Bypass SB
Construction Ramp D
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
118/124
Traffic on Ramp B
Ramp D
Traffic Control Stage 4
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
119/124
South Bridge Approach North Bridge ApproachBackgate Bridge
MSE Walls
Lightweight Aggregate Borrow Material
1, 2, and 3 Granular Surcharge (Normal Weight)
3 Triangular Spacing PVD
Geotechnical Instrumentation
Bridge Abutment DSM
(South 30 x 133 x 50deep North 30 x 141 x 70deep )
Longitudinal DSM (South 5 Wide / North 8 Wide)
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
120/124
CLOSING
Project Status
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
121/124
Project Status
Preliminary Engineering: 2008 - 2009
Right of Way Acquisition: 2009 - 2011
Construction: 2011 2014
Approximately 33% complete
UnderConstruction
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
122/124
Construction
Traffic Stage 3 Ramps C/D have been
constructed and will be ready to be paved in the
near future
Traffic Stage 4Scheduled to Start April 2013
Deep Soil Mixing : Test Section / Test Pile / Production
Bridge Abutment Foundation Construction
Construct Bridge Approach Embankment & MSE Walls
Closing
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
123/124
Geotechnical techniques are speeding upconstruction
Positive feedback regarding construction traffic
congestion and shifts Estimated project completion: Fall 2014
Project Cost $75.8 Million
g
Thank You
-
7/29/2019 S40_Case Study Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate, Myrtle Beach, South Carolina_LTC20
124/124
Thank You
Any Questions?