salvador da bahia landfill gas project : baseline methodology

22
Salvador Da Bahia Landfill Gas Project: Baseline Methodology Baseline Methodology 1 of the 1 st 2 methodologies approved by the CDM Executive Board, August 2003

Upload: selene

Post on 05-Jan-2016

29 views

Category:

Documents


0 download

DESCRIPTION

Salvador Da Bahia Landfill Gas Project : Baseline Methodology 1 of the 1 st 2 methodologies approved by the CDM Executive Board, August 2003. Description of the project activity :. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Salvador Da Bahia  Landfill Gas Project : Baseline Methodology

Salvador Da Bahia Landfill Gas Project:

Baseline MethodologyBaseline Methodology

1 of the 1st 2 methodologies approved by the CDM Executive Board,

August 2003

Page 2: Salvador Da Bahia  Landfill Gas Project : Baseline Methodology

Description of the project activity:

• The landfill has a total capacity of 18,000,000 m3 and receives approximately 850,000 tonnes/year of domestic waste.

• The Project involves installing equipment for methane destruction with capacity of 6,250 m3/hr in 2000 (expanding to 46,250 m3/hr in 2020).

• The equipment will consist of enclosed flaring with controlled burning condition.

Page 3: Salvador Da Bahia  Landfill Gas Project : Baseline Methodology

. Brief explanation of how the anthropogenic emissions of anthropogenic GHGs by sources are to be reduced by the proposed CDM project activity...

• Anthropogenic emission of GHG at Salvador Landfill occurs when methane produced at the landfill is not destroyed;

• The proposed project activity pretends to better the landfill gas capture and destruction efficiency by increasing the total amount of gas to be destroyed over the amount determined by the landfill concession contract.

Page 4: Salvador Da Bahia  Landfill Gas Project : Baseline Methodology

Why the emission reductions will not occur in the absence of the proposed activity?

Landfill contract barriers to investment:

• The Salvador municipality established the maximum price to be paid for the landfill activity in 1999 at 16.69 R$/ton (5.6 US$/ton).

• The winning price Vega has proposed was 15.86R$/ton (5.3 US$/ton).

• The price includes landfill design, licensing, construction, operation and aftercare for a period of 20 years.

Page 5: Salvador Da Bahia  Landfill Gas Project : Baseline Methodology

Why the emission reductions will not occur in the absence of the proposed activity? (Cont.)

• There was no specific requirement on gas management. Any investment or operation to destroy more than the contractual amount is additional and will not have other form of remuneration other than the CERs. In baseline study the total cost was estimated to be 45 Millions of BRL for the period 2003 to 2019 shared between investment cost (flares and gas capture works) and operation cost (electricity for pumping gas, gas network maintenance, handiwork..).

Page 6: Salvador Da Bahia  Landfill Gas Project : Baseline Methodology

Why the emission reductions will not occur in the absence of the proposed activity? (Cont.)

National and sectoral policies

• Typical recovery of methane or biogas is minimal and there is no regulatory requirement governing its recovery.

• A conservative estimate of 20% recovery of methane gas for passive system has been considered as the best practice based on a waste management study.

Page 7: Salvador Da Bahia  Landfill Gas Project : Baseline Methodology

Why the emission reductions will not occur in the absence of the proposed activity? (Cont.)

National and sectoral policies

• There is no national framework governing landfill practice and only technical norms issued by the Brazilian Association of Technical Norms without any technical requirement on LFG management.

• A Study on basic sanitation for State of Bahia shows that in 2000, 60% of MSW was treated in inappropriate site or with simple control, and 39.4% in sanitary landfills.

Page 8: Salvador Da Bahia  Landfill Gas Project : Baseline Methodology

Project Additionality Assessment

• Baseline: Concession agreement between VEGA and the Municipal Government of Salvador da Bahia– Capture and destruction rate of 19-24% of the

methane that will be generated from the entire landfill

• CDM Project: Collection system and destruction capacity will be expanded and improved so that an estimated 75-80% of the methane will be destroyed

Page 9: Salvador Da Bahia  Landfill Gas Project : Baseline Methodology

Project Additionality Assessment

• Procedure: Investment analysis– Baseline has a higher NPV

• Baseline has NPV > 0– Concessionaire is paid fixed fee per ton of waste

entering the landfill covering all construction and operating cost

• Without CERs, CDM Project has NPV < 0– If there are no CER revenues, concessionaire will

not receive additional revenue (from the present contract) to improve significantly landfill capture and destruction efficiency which will be costly

Page 10: Salvador Da Bahia  Landfill Gas Project : Baseline Methodology

Project Additionality Assessment

0

NPV

Present Contract CDM Project

CCEERRss

Baseline

No CERs

Page 11: Salvador Da Bahia  Landfill Gas Project : Baseline Methodology

B. Baseline methodology

Title and reference of the methodology applied to the project activity:

Contractual amount of landfill gas capture and flaring defined through public concession contract.

Page 12: Salvador Da Bahia  Landfill Gas Project : Baseline Methodology

Justification of the choice of the methodology and why it is applicable to the project activity

• The selection of baseline is straightforward because of the existing contractual document between VEGA and the municipality governing the volume of methane gas to be captured;

• The legal document covers the contractual lifetime and therefore represents an actual crediting period;

• There is no regulatory requirement governing the recovery of methane or biogas in Brazil;

Page 13: Salvador Da Bahia  Landfill Gas Project : Baseline Methodology

Description of how the methodology is applied in the context of the project activity:

• The calculation of baseline and project emissions is estimated from the volume of landfill methane destroyed as measured in the project minus the volume indicated in the original technical proposal submitted to the Municipal Government of Salvador;

• The emissions from existing electricity generation and the avoided emissions from displaced electricity generation have not been used to calculate CERs to ensure a straightforward and conservative baseline;

Page 14: Salvador Da Bahia  Landfill Gas Project : Baseline Methodology

Description of how the methodology is applied in

the context of the project activity (cont):

• The emissions reductions from proposed landfill gas management project are calculated by:

• Project Life-time Emissions Reductions = yr (Annual Emissions Reductions) = yr [(EmLandfillbaseline - EmLandfillProj.)

Where:

EmLandfillbaseline = baseline emissions from landfilled waste

EmLandfillproj. = project emissions from landfilled waste

Yr = project years

Page 15: Salvador Da Bahia  Landfill Gas Project : Baseline Methodology

Discussion on the conservatism of the baseline methodology when applied to Salvador project.

• Previous studies including World Bank studies, and a recent Brazilian Environment Ministry study show that gas capture and flaring is not conducted in more than 90% of Brazilian landfills.

• The Salvador de Bahia Landfill as designed by VEGA in its technical proposal is probably the only municipal landfill in Brazil that respect European technical standard in relation to bottom lining system, complete drainage layer and water management. The project is The Best Practice on the matter.

Page 16: Salvador Da Bahia  Landfill Gas Project : Baseline Methodology

Description of how the definition of the project boundary related to the baseline methodology is applied to the project activity:

•All of the generation of waste occurs locally, within the confines of the country.

•The Baseline Study has not found leakage since the project is a closed system.

•Two potential sources of emissions were identified and were assessed immaterial:

1) CO2 emissions generated from CH4 produced by plastic decomposition;

2) Emissions resulting from electricity used to pump methane gas.

X

X

Page 17: Salvador Da Bahia  Landfill Gas Project : Baseline Methodology

Recommendations of the Meth Panel on the baseline methodology:

• The methodology is applicable to landfill gas capture and flaring project activities where there exists a contractual agreement to capture a certain volume of methane from a landfill;

• Some of the required changes are:

1. The presentation of the methodology lacks clarity and conciseness. Consolidate Annex 3 and 4.

2. The contractual volume may vary with the quantity of waste disposal. Explicitly state

the relationship.

Page 18: Salvador Da Bahia  Landfill Gas Project : Baseline Methodology

Recommendations of Meth Panel on the baseline methodology cont…:

3. It is not clear if electricity generated is part of the baseline. In case methane used to generate electricity in the baseline is greater than the contracted amount, it is necessary to include this methane burnt as part of the baseline. The schematic equation should be :

ER calculation =

CH4 captured less (CH4 contracted amount or CH4 baseline power generation which ever is greater)

Compared to proposed:

ERCH4 = CH4 captured in project scenario - CH4 captured in baseline scenario

Page 19: Salvador Da Bahia  Landfill Gas Project : Baseline Methodology

Recommendations of Meth Panel on baseline methodology cont…:

4. The financial analysis referred to in the “Baseline Study” needs to be detailed and included in Annex 3 to strengthen the additionality statement.

5. Specify the COP-accepted value for the GWP of methane (21, IPCC 1995 Guidelines) and, where necessary, perform all calculations accordingly using the correct (21 instead of 23) GWP.

Page 20: Salvador Da Bahia  Landfill Gas Project : Baseline Methodology

Evaluation of Meth Panel on the proposed new methodology

1. General approach:

The project participant choose a mix of approaches of paragraphs 48 (b) and 48 (c) of the CDM M & P although the focus is on approach 48 (c) : “The average emissions of similar project activities undertaken in the previous five years, in similar social, economic, environmental and technological circumstances, and whose performance is among the top 20 per cent of their category”. The methodology is based on the level of emissions that this top 20% would create, which was very conservatively determined.

Page 21: Salvador Da Bahia  Landfill Gas Project : Baseline Methodology

Evaluation of Meth Panel on the proposed new methodology (cont.)

Applicability of methodology across project types and regions.

This methodology is applicable to landfill gas capture and flaring project activities where:

• There exists a contractual agreement to capture a certainvolume of biogas from a landfill;

• The concession obligation stipulate the amounts of landfill gas to be collected by the concessionaire;

• Given the possibility of generating electricity from captured landfill gas, there should be no electricity generation planned.

Page 22: Salvador Da Bahia  Landfill Gas Project : Baseline Methodology

Marina T. MallareClimate Change Information CenterManila ObservatoryTel. No : 426-08-37Email : [email protected]