San Roque Watershed
Rehabilitation Subproject
Subproject Completion Report
-
TABLE OF CONTENTS
Executive Summary ---------------------------------------------------------------- i
I. Subproject Description --------------------------------------------------------- 1
1. Purpose/ Objectives
2. Subproject Scope and Dimension
A. Comparison of Original and
Actual Scope and Dimensions
B. Reasons for Revision/ Modification
Of Scope and Dimensions
C. Contribution of Subproject to
Relevant (Sub) Sectors
II. Subproject Implementation -------------------------------------------------- 14
1. Organizations for Implementing
Subproject
2. Implementation Period
3. Subproject Cost
4. Comments on Performance of
AO, AP, PO, M&E, and Infra Contractors
5. Other Matters Relating to
Subproject Implementation
III. Action taken by the AO, AP, and PO --------------------------------------- 26
Relating to Recommendation(s)
IV. Initial Operation and Maintenance
Of the Subproject Facilities ------------------------------------------------ 27
1. Present Condition of Facilities
2. Organization for Operation and Maintenance
3. Annual Budget or Actual Expenditure
For Operation and Maintenance (by year)
4. Maintenance Method
V. Benefits Derived from the Project ------------------------------------------ 37
1. Indirect Effects
VI. Conclusions and Recommendations ------------------------------------------ 39
-
ANNEXES:
1. Organizational Structure ------------------------------------------------------ 65
1a. PO
1b1-1b3. M & E Contractor
1c. SUSIMO
1d. Infrastructure
1e. Functional Relationship
2. Pictures ------------------------------------------------------------------------- 72
3. CSD Accomplishment Map ----------------------------------------------------- 74
-
i
EXECUTIVE SUMMARY
The Community-Based Forest Management Program (CBFMP)
revolutionized forest development and rehabilitation efforts of the government
when it was institutionalized in 1995 by virtue of Executive Order No. 263.
Before the adoption of the CBFM approach, the sole motivating factor of
contract reforestation awardees was primarily financial gains. With the
implementation of the Forestry Sector Project (FSP) using CBFM as its main
strategy to rehabilitate the upland ecosystem, it empowered beneficiary
communities economically, socially, technically and politically while transforming
them into environmentally responsible managers. The tenurial right to develop
subproject sites alongside the various inputs from the Subproject deepened
their commitment to collaborate with other stakeholders in the implementation
of these subprojects.
The San Roque Watershed Rehabilitation Subproject is located in the
Municipality of San Nicolas, Pangasinan and plays a crucial role as it complements
the San Roque Multi-Purpose Dam responsible for generating hydroelectric
power and irrigating rice fields of Pangasinan. The San Roque Multi-Purpose dam
is the biggest in Asia and 11th in the world.
With San Roque Dam’s goal to generate 345 megawatts of electricity and
irrigate around 70,500 hectares of rice fields, the implication of the
Watershed’s rehabilitation on agriculture, industries and domestic requirements
is enormous. Its impact on the environment equally so with the reduction of
recurring floods as vegetative cover is improved, among others.
The San Felipe Watershed Management Inc. (SAFEWATER), one of two
people’s organizations established in 1997, entered into a PHP28.8 million
contract with the DENR to rehabilitate the San Nicolas side of the watershed.
It was able to establish a total of 1,638 hectares plantation composed of: 1,389
hectares reforestation plantation, 145 hectares. agro forest plantation, 22
hectares Rattan plantation, and 82 hectares Assisted Natural Regeneration.
These plantations established are expected to significantly increase stumpage
production and improved vegetative cover to minimize soil erosion while
enhancing the ecological habitat of the remaining wildlife in the area.
In terms of employment generation and improvement of socio-economic
condition of the communities, the Subproject was able to provide regular
employment for 207 PO members in the performance of its plantation
establishment activities apart from assistance in livelihood projects. This
undertaking increased their annual gross income from PHP 71,774 to PHP126,
-
ii
290. With this, the PO members were able to provide their children primary
and secondary education unlike before.
Infrastructure facilities also proved to be vital in the sustainability and
promotion of livelihood projects of the PO. The water system irrigated the agro
forestry area enabling the PO members to increase their production and
harvest. The farm-to-market road on the other hand facilitated primarily the
transport of agricultural and agro forest products to the market. Nonetheless
the road also makes possible accessibility in going to and from the Subproject
site as well as in linking the community to health and other basic services.
-
1
SUBPROJECT COMPLETION REPORT
Of
SAN ROQUE WATERSHED SUBPROJECT
Loan Agreement No. PH-P 135
Forestry Sector Project
I. SUBPROJECT DESCRIPTION
The San Roque Watershed Rehabilitation Subproject is located in the
Municipality of San Nicolas, Pangasinan and covers one of the tributaries of
Lower Agno River. It lies between longitude 1200 30’ to 1200 45’ and latitude 160
07’ to 160 12’. It is bounded on the
north by a public forest and the San
Roque Multi-Purpose Dam; on the
south by alienable and disposable land;
on the east by a public forest and on
the West by the lower Agno River.
The topography of the area ranges
from hilly to mountainous with
moderate slopes to very steep slope
towards the boundary of Benguet.
The Subproject is accessible by any type of vehicle, 1.0 kilometer coming from
the Multi-Purpose Dam and about 3.5 kilometers from Barangay San Felipe East.
The rehabilitation of the area complements the San Roque Multi-Purpose Dam,
constructed by the National Power Corporation (NAPOCOR). The Dam generates
hydroelectric power and irrigates the rice fields of Pangasinan.
1. Purpose/Objectives
A) Original (at the time of appraisal)
The subproject was aimed at establishing a sustainable watershed and
empowering the local community to manage the watershed resources.
It specifically aimed to:
1. Strengthen and empower the local communities in order to
capacitate them as watershed resources managers on a
sustained basis;
-
2
2. Establish a total of 2,195 hectares of f orest plantations using
site adaptable species;
3. Develop a total of 605 hectares of agro forestry areas for the
economic benefits of the community participants as well as the
environmental protection of the upland watershed;
4. Enrich the existing secondary forest by integrating rattan in
499-hectare secondary forest within the watershed
5. Produce sufficient and good quality water to support agro-
industrial development in Pangasinan and the surrounding areas;
and
6. Uplift the socio-economic well-being of the community people
by providing them employment and ecologically-sound livelihood
activities.
B) Modification
a. Modified purpose/objectives
1. To rehabilitate a total area of 1,389.0 hectares of denuded
forest land by planting Mahogany, Narra, Gmelina, Eucalyptus
and Benguet Pine;
2. To developed 145 hectares of agroforestry area by planting
mango intercropped with kakawate cuttings.
3. To establish 22 has. inadequately stocked area with rattan
and enrich 82 has. Assisted Natural Regeneration (ANR) area
with Narra and Mahogany.
b. Reasons for the modification
The reason for modification was the cancellation of the San
Manuel side area. The original scope of the San Roque Watershed
Rehabilitation Subproject is to develop 3,299 hectares forest
area within the Municipalities of San Nicolas and San Manuel. The
cancellation of the San Manuel side led to the reduction of the
target area to 1,638 hectares left for the San Nicolas side to
accomplish.
2. Subproject Scope and Dimension
A. Comparison of Original and Actual Scope & Dimensions
-
3
a.1. Please check: There has been ( revision and/or modification or
no revision and/or modification) of the Subproject scope and
dimensions.
a.2. If “revision and/or modification”, please complete the Table.
ITEM
Original Scope and
Dimensions (At the
time of
appraisal/Planned)
Revised/Modified
(Actual)
1.Reforestation/Watershed/
CBFM
A. SMP
B. CO 1
- San Nicolas
- San Manuel
Schedule: January 18,
1996 to May 3, 1996
Target Area: 2,000 has
Schedule: August 19,
1996 to August 19, 1998
Target Area: 1560 has
Schedule: August 20,
1996 to August 20, 1998
Target Area: 750 has
a. Conduct of
Information,
Education, and
Communication
Campaigns
b. Gathering of primary
and secondary data
c. Social Investigation
d. Identification of
possible FLMA/ CBFMA
Schedule: January 18,
1996 to May 3, 1996
Area: 2,000 has
Schedule: August 19,
1996 to August 19,
1998
Area: 1560 has
Cancelled
-
4
C. CSD
1. SOIL EROSION
CONTROL
a. Infrastructure
b. Trail and Footpath
c. Plantation
- hedgerows
2. VEGETATIVE MEASURE 2
a. Agroforestry
b. Assisted Natural
Regeneration
c. Enrichment Planting
d. Tree Plantation
d.1. Bamboo
d.2. Rattan
d.3. Mangrove
d.4. Plantation Species
e. Timber Stand
Improvement
f. Agrosilvipasture
3. INVENTORY RESIDUAL
FOREST
4. INCOME ENHANCEMENT
PROJECT
5. INFRASTRUCTURE
-Bunkhouse
-Look-out Tower
recipients
e. Conduct of
Community Organizing
Activities
f. PO Formation
g. Conduct of Training
h. Assistance in the
preparation of site
development and
management plan for
FLMA/CBFMA
70.80 has
605 has
499 has
2195 has
6
6
24
145 has
82 has
22 has
1389 has
2 bunkhouse
3 look out towers
-
5
-Graded Trail and
Footpath
-Water System
-PO Office
D. INFRASTRUCTURE
COMPONENT
1. Rehabilitation of Farm-
to-Market Road
2. Small Water
Impounding Structure
E. MONITORING AND
EVALUATION
Year 1
Year 2
Year 3
no specified quantity
Not planned in the
appraisal
1 unit
Inspection Chart
Mapping
20 km graded
trail/footpath
Constructed 4 cu.m.
water tank/ 15 km
1 unit
2.4 km
1 unit
1,380 has (physical and
institutional)
April 11, 2000 – May
11, 2001
1638 has (physical)
January 17, 2002 –
February 19, 2003
1638 has
(institutional)
November 14, 2001 –
February 19, 2003
1638 has (physical)
December23, 2002 –
June 23, 2003
1638 has
(institutional)
December 23, 2002 –
March 23, 2003
Activities for Physical
M&E:
1. Relocation of
Boundaries, UTM
monuments,
Block Corner Posts
-
6
2. 100%
Inventory/Charting
(4 passes)
3. Height
Measurement
4. Other activities -
e.g.
Inspection of
Infrastructures &
other support
activities
5. Systematic
Sampling
Activities for the
Institutional and
Project Benefits M&E
A. Leveling-off and
presentation meeting /
Preparatory Activities
B. Secondary data
gathering
C. Primary data
collection and field
assessment
1. PO Capability
Assessment
2. Proj. Benefit
Assessment
3. Sustainable
Resource
Use and Dev't
Assessment
D. Integration,
Preparation,
Presentation of draft
report, and
-
7
2.SUSIMO Equipment
Provided to the Office 3
Conduct of research
Trainings
-Attended 4
Submission of Final
Report
1 unit KIA Ceres
2 units Motorcycle
1 unit Computer
1 unit Printer
1 unit Typewriter
1 unit Kubota engine
generator
4 pcs Brunton Compass
2 pcs Steel tape
4 pcs Abney hand level
1 unit Rain gauge
3 pcs Binocular
1 pc Leroy lettering
set
2 units GPS
2 units Handheld Radio
1 unit Base
Transceiver
2 units Forester’s
transit
1 set GIS maptitude
1 pc Plainmeter
2 pcs Diameter Tape
1 unit UPS
1 unit Grass Cutter
N/A
-Site Coordinators
Assessment
-Orientation Course of
SUSIMO staff
-FSP Re-Orientation
Course For SUSIMO
and other Project
Implementation
Mentors
-FSP Phase-out/Phase
In Planning Workshop
-
8
Others
1. SUSIMO Office
2. Site Engineer’s Office
2. SUSIMO Staff
for DENR and PO
staff
-Enhanced Forest
Management Through
GIS and GPS
-Leadership and
Organizational
Management
35 sq. m. floor area
30 sq. m. floor area
5 Staff
- 1 Permanent
Employee from CENRO
Urdaneta City
- 3 Contractual
Employees from NFDO
- 1 Contract of
Service
1 Please refer to Table 1 for details of trainings attended by PO’s 2 Table 2 details the subproject performance in terms of area planted 3 Table 3 shows the details of equipment provided to SUSIMO 4 Table 4 shows the trainings attended by the SUSIMO staff
B. Reasons for Revision/Modification of scope and Dimensions
b.1. Where there has been “revision/modification” of the Subproject
scope and dimensions.
Please choose the reason(s) from the following list and check.
Revision of the superior plan (e.g. sector development plan,
etc.)
Revision of the supply-and-demand estimate
Large fluctuation in the Subproject cost
Substantial revision of design due to the unforeseeable physical
condition at the time of the original design (e.g. poor soil
condition, etc.)
Natural disaster/unseasonable weather
-
9
Unusual circumstances beyond the control of the Executing
Agency
Structural and organizational problems of the agencies
concerned (e.g. lack of staff, inadequate coordination with
other agencies, etc.)
Availability of funds (e.g. lack of funds, use of contingency,
fluctuation of the exchange rate, etc.)
Unrealistic initial plan/Technical problems
Procurement problems
Performance of contractor/supplier
Performance of consultant
Change in construction period
Others
b.2. Detailed statement of reasons (with background)
Substantial Revision of design due to the unpredictable physical
condition at the time of appraisal
Community Organizing
The community organizing activities for San Manuel side was
undertaken by a Non-Government Organization: SAVED for Greener
Environment. The contract was not completed because the
contractor had been deliquent in accomplishing the target activities.
The contract was eventually cancelled due to the cancellation of the
CSD contract of the People’s Organization (PO).
Comprehensive Site Development (CSD)
The original scope of the subproject covers a total area of 3,299
hectares situated in the municipalities of San Nicolas and San
Manuel, Pangasinan. The target comprises 2,195 hectares of forest
plantations, 605 hectares of agroforestry areas, and 499 hectares
of rattan plantation within the secondary forest.
Two POs were organized as contractors of the CSD activities. For
the San Nicolas Side, the San Felipe Watershed Management Inc
(SAFEWATER) was formed in 1997. For San Manuel, the Community
Environmental Protectors Association of San Roque (CEPAR), the
PO organized by the SECAL Project of DENR, was contracted for
the CSD of that area. For its part, SAFEWATER was very active in
strengthening its organization in the course of its CSD activities.
On the hand, CEPAR encountered organizational and technical
problems in its CSD activities alongside the existing conflict
between the PO and the Local Government. Finally, the construction
-
10
of the San Roque Dam aggravated the situation that eventually led
to the cancellation of the San Manuel Side.
From 1997-1998, CEPAR has developed 190 hectares reforestation
plantation and raised seedlings for the Agroforestry and Rattan
Components. Planting of a total of 2.6 hectares of hedgerows for
soil erosion control was also accomplished. But all of these were for
naught when the area was submerged to give way to the San Roque
Dam.
The cancellation of CEPAR resulted to the reduction of the target
area from 3,299 to 1,638 hectares. The 1,638 hectares was the
development plan for the San Nicolas Side. SAFEWATER fully
accomplished the said target.
Infrastructure Facilities for CSD
The infrastructure facilities required to be put up within the CSD
areas was subsequently reduced with the cancellation of CEPAR. The
required facilities for the San Nicolas side on the other hand were
retained : three (3) bunkhouses, two (2) lookout towers, and one (1)
unit PO Office.
SAFEWATER was able to establish the required infrastructures.
However, only two (2) of the constructed bunkhouses are being
maintained and operational. A Water System, constructed to
support the CSD activities and made of four (4) cubic meters water
tank and 15-kilometer pipe that supplies potable water to the PO
and SUSIMO Office was also built.
Others (Accomplishments of SAFEWATER)
Change of component due to root rot disease
SAFEWATER met the set target of 1,638 hectares composed of
1,389 hectares reforestation plantation, 145 hectares Agroforest
plantation, 22 hectares Rattan plantation, and 82 hectares Assisted
Natural Regeneration. Target area for the Rattan component, as
stipulated in their original contract, was to plant 104 hectares
situated in the secondary forest of the watershed. But the
established 104-hectare Rattan plantation was infested by root rot
disease resulting to a very low survival yield, only 22 hectares
remained. In 2002, instead of replanting rattan in the secondary
forest area, they transformed the remaining area into Assisted
Natural Regeneration (ANR). Within the said ANR area, they also
planted Narra and Mahogany species to attain the required stock
density of the area.
-
11
Others (New guidelines was released)
Monitoring and Evaluation
It was the consensus during the appraisal stage of project
implementation that Inspection Chart Mapping activities will be
undertaken for the monitoring and evaluation of the area. Later on,
new guidelines were formulated on the monitoring and evaluation
process for the FSP sites.
C. Contribution of Subproject to Relevant (Sub) Sector(s)
c.1. (Sub) Sector(s) to which the Subproject belongs
Electric power and Gas Telecommunication Social services
(Multipurpose) Dams Telecommunications Water supply
Power Plants Broadcasting Sewerage
Transmission lines Education
Distribution Systems Irrigation and Flood control Health
Gas Irrigation Tourism
Others Flood control Others
Transportation Agriculture, Forestry and Fisheries
Roads Agriculture and Forestry
Bridges Fisheries
Railways
Airport Mining and Manufacturing
Ports Mining
Marine Transportation Manufacturing
Others
c.2. Original (At the time of appraisal/Planned)
Item
Description
1. Plantation Establishment The reforestation activities would yield
significant increase of stumpage
production.
Land uses would improve and consequently
minimize accelerated soil erosion,
landslides, and stream bank erosion.
-
12
The established vegetative cover would
enhance the ecological habitat of the
remaining wildlife in the area and the
surrounding communities.
Water yield and quality would improve and
support the irrigation, industrial, and
domestic needs of the down stream
communities.
2. Allocation scheme of Land
Management Units
To effectively implement the subproject
development activities and to ensure better
protection and maintenance of the
established plantations, the total area for
development shall be allotted among
households as Land Management Units
(LMU).
3. Support to San Roque
Dam Project
The increase in water discharge from Agno
River would complement the San Roque Dam
Project.
The San Roque Dam aims to:
a. Generate 1.16 Billion KWH of electricity.
b. Irrigate around 70,500 hectares in
Pangasinan and would increase palay yield by
5.3 million cavans per year.
c. Improve water yield and quality. Would
reduce recurring floods.
d. Trap upstream mine tailings that are
polluting the Lower Agno River System.
4. Employment Generation
and Increase in Household
Income
The community would be organized and will
be in the forefront in implementing
plantation establishment activities. This
would create employment opportunities and
livelihood options thereby uplifting the
socio-economic condition of the people.
c.3. Present situation and outlook for the future
Item
Description
1. Long drought The area falls under climatic type I where
there is long dry season. This condition
-
13
however is mitigated as a result of project
intervention in the area, resulting to
increased vegetative cover and lowering
of temperature.
3. Support to the San Roque
Dam
The rehabilitation of the San Roque
Watershed supports/complements the San
Roque Dam. The continuous yield of water
from the San Roque Watershed will greatly
enhance the fullest the function of the
dam as it generates electricity and
supplies water for irrigation. The
rehabilitation of the watershed will ensure
continuous supply of water to the dam and
reduce the occurrence of floods.
4. Awarding of Tenurial
Rights/ CBFMA
The issuance of CBFMA on December 15,
1998 ensures the sustainability of the
project. Through this, the PO is bound to
manage and protect the Subproject area
for 25 years renewable for another 25
years. Within this span of period the
protection of the San Roque Dam is thus
assured.
5. Employment Generation,
Increase in Household
Income, and Creation of
Livelihood Project.
The implementation of the Subproject
provided regular employment for the 207
members of the PO. There were periods
that non-members were also hired to
perform the CSD activities.
In effect, the annual gross income of the
members increased from PHP 71,774 to
PHP 126,290.
Subproject implementation was not limited
only to physical accomplishments in the
area, but also empowering the People’s
Organization and the community was
another focus. While performing plantation
establishment activities, the DENR
assisted the PO in establishing viable
livelihood projects. The on-going livelihood
projects will support future activities of
the PO and ensure the income generation
-
14
of the community.
Increase in the household income of the PO
members have improved their socio-
economic condition. Proper education is
provided to the beneficiaries’ children, a
great improvement of the situation before
project implementation with children not
being able to complete primary education.
With the presence of the subproject and
its positive financial effects, children of
the PO members were able to finish
Primary and Secondary education.
6. Construction of Farm to
Market Road
The 2.4 kilometer Farm to Market was
rehabilitated to facilitate accessibility in
going to and from the subproject site. The
rehabilitation primarily supported the
transportation of agricultural and
agroforest tree products to the market. It
also linked the community to health and
other basic services and made education
accessible to children.
7. Construction of Water
System
The Water System irrigates the
established plantation specially the agro
forest trees and the farmlands within the
subproject and adjoining areas. The
irrigation of farmlands will increase
production and harvest. Moreover, the
water system now benefits households for
their domestic use.
5 Please refer to Table 5 for livelihood projects implemented by PO’s
II. SUBPROJECT IMPLEMENTATION
1. Organizations for Implementing Subproject
Function in the Name of Organization Reasons
for
Subproject
Implementation
(1) Original (2)
Changed
Change
1. SMP
-Geo-Surveys and
N/A
-
15
2. AO for CO
- San Nicolas
- San Manuel
3. Assisting
Professional
4. PO
- San Nicolas
- San Manuel
4. M&E Contractor
Year 1
Year 2
Mapping, Inc
(GSMI)
Sustainable
Technology for
Eastern
Pangasinan (STEP)
SAVED for
Greener 2000
Association
Ms. Edna Padio
San Felipe
Watershed Mgt.
Association, Inc.
(SAFEWATER)
Community
Environment
Protectors
Association of San
Roque (CEPAR)
Environment
Conscious
Humanitarian
(ECHO) Inc.
(physical and
institutional)
RHR Consult
Services Inc.
(physical)
Wellspring
Management
Corporation
(institutional)
N/A
N/A
N/A
N/A
N/A
N/A
Cancelled
Cancelled
-
16
Year 3
5. Infrastructure
Component
Contractor
Friends of the
Environment for
Development and
Sustainability
(FRENDS)
(physical)
Friends of the
Environment for
Development and
Sustainability
(FRENDS)
(instiitutional)
R. C. Tagala
Construction
N/A
N/A
N/A
Please state:
1.1 Reasons for the change (N/A).
1.2 Problems arising, counter measures adopted and results
People’s Organization for Comprehensive Site Development
Relocation of the area due to the construction of San Roque Dam
When plantations particularly on the western side of the area were
found to be part of the basin of the San Roque Dam, another area,
equivalent to the submerged portion was utilized instead. The area
covering 115.0 hectares, is higher in elevation and situated in Sitio
Kabayawasan, San Felipe East, San Nicolas, Pangasinan. The area
however was only developed in CY 2000. Still, the total target area
was successfully accomplished.
Burned Plantation due to the clearing operation for the construction
of San Roque Dam
The construction of the dam required clearing of the area.
Uncoordinated burning by the clearing contractor unfortunately
affected part of the subproject area. Payment was made however by
the contractor to the PO through insurance. The plantation was
rehabilitated in CY 2002.
Inactivity of Members
Another factor that hampered the completion of the target on the
set date, specifically on plantation establishment, was the decrease in
-
17
number of active members during the peak of the construction of San
Roque Dam. The construction coincided with the CSD activities.
Members preferred to work in the construction site due to higher
wages. As counter measure, SAFEWATER granted advance payments
in terms of day-to-day basic needs such as rice and grocery items to
active members. Likewise, the granting of Individual Property Rights
(IPR) on the established plantations was initiated. These efforts
motivated the PO members to actively participate in the activities.
1.3 The latest organization chart (or equivalent) for the implementation
of the Subproject is ( attached or not available as Annex 1).
1.4 If the organizational chart (or equivalent) is not available, please
state the reason.
2. Implementation Period
A. Comparison of Original Schedule and Actual Period
Please fill in the following blanks with actual period for each item.
ITEM
ORIGINAL SCHEDULE
ACTUAL PERIOD
1. SMP Contractor
2. Contract of AO for CO
-San Nicolas
-San Manuel
3. Contract of PO for
CSD
-San Nicolas
-San Manuel
4. Contract of NGO for
M&E
January 18, 1996 to May
3, 1996
August 19, 1996 to
August 19, 1998
August 20, 1996 to
August 20, 1998
July 14, 1997 to July 14,
2002
July 14, 1997 to July 14,
2002
January 18, 1996 to May
3, 1996
August 19, 1996 to
August 19, 1998
August 20, 1996 to June
18, 1998 (Cancelled)
July 14, 1997 to June 30,
2003
July 14, 1997 to
February 3, 1999
(Cancelled)
-
18
Year 1
-Environment Conscious
Humanitarian (ECHO)
Inc. (physical and
institutional)
Year 2
-RHR Consult
Services Inc.
(physical)
-Wellspring
Management
Corporation
(institutional)
Year 3
-Friends of the
Environment for
Development and
Sustainability
(FRENDS) (physical)
-Friends of the
Environment for
Development and
Sustainability
(FRENDS)
(instiitutional)
5. Contract of
Infrastructure
Component
Completion of
Subproject
April 11, 2000 -
December 11, 2000
January 17, 2002 – July
17, 2002
Nov. 14, 2001 to
February 14, 2002
December 23, 2002 to
June 23, 2003
December 23, 2002 to
March 23, 2003
October 3, 2002 to June
11, 2003
July 2000
April 11, 2000 – May 11,
2001
January 17, 2002 –
February 19, 2003
November 14, 2001 to
February 14, 2002
December 23, 2002 to
June 23, 2003
December 23, 2002 to
March 23, 2003
October 3, 2002 to July
15, 2003
September 2003
Please refer to Table 6 for the Subproject Status Report
Notes: Completion of the Subproject was defined as ( completion
ceremony or final disbursement or other than the above.)
The completion date was scheduled for July 2000 (at the time of
appraisal) and is indicated (thus ) in the above Table.
-
19
B. Reasons for Delay or Early Completion
b.1 In case of delay or early completion, please choose the reason(s)
from the following list and check.
Change in scope/dimensions
Natural disaster/Unseasonable weather (e.g. earthquake,
typhoon, etc.)
Shortage of funds/Fluctuation of the exchange rate
Problems in procurement
Inflation
Unusual circumstances beyond the control of the Executing
Agency
Structural and organizational problems of the agencies
concerned (e.g. lack of staff, inadequate coordination with
other agencies, etc.) CSD
Legislative matters
Unrealistic initial plan/Technical problems
Performance of contractor/supplier
Performance of consultant
Others
b.2. Reason and background for early delay or early completion
Performance of Contractor
Monitoring and Evaluation
For the 1st pass/year of M&E, the contractor, Environment Conscious
Humanitarian (ECHO), Inc. did not follow the specifications stipulated
in the MC 2000-04: Guidelines in the Conduct of M&E.
For the 2nd pass/year, the contractor, RHR Consult Services Inc.
likewise did not follow the guidelines on some compartments. An
example of which was the adoption of the quadrant method instead of
conducting the strip method.
The contractor for the 3rd pass/year M&E was the Friends of the
Environment for Development and Sustainability (FRENDS). They
established the baseline along roads/trails instead of the longest line
in each compartment.
Infrastructure Component
Contract to undertake the Infrastructure Development Component
of the subproject from October 2002-June 9, 2003 was awarded to
RC Tagala Construction. The re-survey of the route of pipelines for
-
20
Water System and late delivery of materials hampered the
completion of the component on the date stipulated in the contract.
Natural Disaster/ Unreasonable Weather
CSD Component
The CSD of San Roque Watershed Rehabilitation Subproject started
in July 1997 and scheduled to be completed in July 2000. However,
due to the el niño phenomenon that affected the quality of the
plantation, the contract was extended until June 2003.
Monitoring and Evaluation
Harsh weather condition affected the implementation of M&E
activities. Hence, the contractors did not accomplish the target on
the specified time.
Infrastructure Component
The frequent occurrence of rain and typhoons, that started as early
as April was another reason identified for the late completion of the
contract.
C. Remedial Action Taken in Each Case of Delay
Monitoring and Evaluation
The remedial actions for the first and second pass M & E was the
conduct of a “re-do” activity in consonance with MC 2000-04. For the
third pass, a revalidation was conducted by the DENR.
CSD Component
The implementation of MC 2000-19 known as the “Guidelines
Governing the Updating Cost Estimate and Intensification of
Plantation Maintenance and Protection Activities for DENR
FSP Watershed Subproject Under JBIC Funding” in CY 2001,
improved the quality of established plantations;
Incentives given to active PO members thru advance payment
in terms of rice and grocery items, sustain commitment and
participation of members to the project;
The extension of the implementation of Maintenance and
Protection activities enabled the PO to intensify the conduct
of replanting in CY 2001 and CY 2002 to address the
occurrence of low survival rate; and
-
21
Adoption of Individual Property Right (IPR) scheme to
deserving/active members on Agro-forestry Component,
sustain activities in maintenance and protection of the
plantations
Infrastructure Development Component
Survey was re-routed to a more accessible way; and
The contractor worked overtime as soon as supplies and
materials were made available and whenever favorable weather
condition prevails.
The extension of contract enabled the contractor to
accomplish the specified activities stipulated in the agreement.
3. Subproject Cost
A. Comparison of Original Estimated Cost and Actual Expenditure (by
Component)
Item
Original Cost
(in M pesos)
Actual Expenditures
(in M pesos)
1. SMP 1.350000 1.350000
2. C O 3.755700 2.979855
3. CSD 40.757905
31.112439
4. M&E 2.982837 2.757661
5. Infrastructure 11.531043 11.531043
6. PMO (SUSIMO) 2.592320 2.392471
TOTAL 62.969805 52.123471
Please refer to Tables 7,8,9 and 10 for details on the cost of SMP, CO, CSD & M and E. Table 11 shows the lists of infra projects with corresponding cost.
B. Reasons for Difference between Original Estimated Cost and Actual
Expenditure
b.1 If there is any difference between Table a.1 and Table a.2 in
Paragraph a, please choose the reason(s) from the following list
and check.
Increase in reconstruction cost arising from natural
disaster/unreasonable weather (e.g. earthquake, typhoon, etc.)
-
22
Increase or decrease arising from a change in construction
period
Increase or decrease arising from inflation
Increase or decrease arising from fluctuation in the exchange
rate
Increase or decrease arising from a change in the scope/work
volume of the Subproject
Decrease arising from keen competition in tender
Unusual circumstances beyond the control of the Executing
Agency
Unrealistic cost estimates/Technical problems
Others
b.2. Description of the detailed reason(s) and background
Community Organizing
The difference in the cost in community organizing is attributed
to the cancellation of the contract of SAVED for Greener
Environment.
Comprehensive Site Development
Major reason of the difference in the amount of CSD is the
cancellation of the contract of CEPAR. The other reason was
attributed to the revision of contracts of SAFEWATER. The
original contract cost of SAFEWATER was P22,561,576 which was
revised to P31,127,718.68 and finally reduced to 28,866,955.52.
The revision was due to the enforcement of MC 2000-19, the
Guidelines Governing the Updating of Cost Estimates and
Intensification of Plantation Maintenance and Protection
Activities for FSP Watershed Subproject. SAFEWATER fully
utilized the final revised cost of their contract. For the activities
undertaken by CEPAR before its cancellation, a total of
P2,245,484.01 was disbursed.
Creation of SUSIMO
The SUSIMO was created in 2000 through Department Order
No. 2000-65. The creation of SUSIMO intensified the monitoring,
supervision, and facilitation by DENR in the Subproject site as
compared to the old system of just deploying a site coordinator in
the area. A total of Php 2,592,320 was allotted for the operation
of the SUSIMO and a total of Php 2,392,470.55 was disbursed.
The Php199,849.45 difference was already obligated and ready
for disbursement.
-
23
C. Action taken in Case of Cost Overrun and Results
There was no cost overrun. The updated cost enabled the PO to
accomplish and improve the quality of plantation.
D. Comparison of Original Estimated Expenditure and Actual
Expenditure (by Year)
Calendar Year
Original Cost
(Mil pesos)
Actual Expenditures
(Mil pesos)
1996
1997
1998
1999
2000
2001
2002
2003
1.404659
10.875695
16.640522
9.754073
5.920447
2.894188
3.566359
11.913862
0.564284
6.838087
8.940110
6.307381
2.912855
4.814932
8.752401
12.993419
Total 62.969805 52.124458
Please refer to Table 12 on details of the Annual Work & Financial Plan
4. Comments on Performance of Assisting Organizations (AOs), Assisting
Professionals (APs), Peoples Organizations (POs), M&E and
Infrastructure contractors.
Please describe the performance of each organization after checking the
item(s) in the relevant lists on which you have any comment.
A. Performance of Assisting Organizations & Assisting Professionals (if
any) Peoples Organizations, M&E and Infrastructure contractors
a.1. Overall performance Design
Contract administration Construction supervision
Expertise Staff qualifications
Coordinating ability Compliance with Contracts
Performance related to any other than the Subproject scope,
if any.
Others
a.2 Description (in detail)
-
24
Overall Performance
Assisting Professional (AP)
The Assisting Professional, Ms. Edna Padio gave many valuable
administrative and technical advices on the improvement of
delivery of services of the PO. Her enthusiasm towards her tasks
however waned as manifested by the decrease in the frequency of
her visits towards the end of the contract. Her overall
performance was rated 7, where 1 is the lowest and 10 is the
highest.
People’s Organization – SAFEWATER
The Officers and Members of the SAFEWATER, Inc. are fast
learners and receptive to change. They adhered to policies, laws
and regulations in the implementation of the project.
Recommendations and suggestions for the good of the project
were well undertaken. SAFEWATER performed well in
accomplishing all the CSD activities. They strove hard to
understand and improve their technical abilities to implement the
project. On Organizational Management, slowly through the help
of the AP and the SUSIMO, they were able to learn how to
actively run the organization and keep it intact. The development
of PO’s capabilities in the financial management came late. But
through the support of the SUSIMO and the PO’s enthusiasm to
learn, a clear financial system was formulated and is being
implemented. The overall performance of SAFEWATER is rated 8,
where 1 is the lowest and 10 is the highest.
Expertise and Coordinating Ability
Assisting Professional (AP)
Ms. Edna Padio is an expert in Community Organizing work. Also,
through her networking capability she was able to link the PO with
the Local Government of San Roque-Pangasinan and Benguet State
University for trainings and possible livelihood option.
Compliance with Contracts
Assisting Organization (AO)
The Assisting Organization satisfactorily imparted all the
knowledge needed to improve the capability of the BOD and its
members in the supervision and management of the subproject.
They have also imparted technical skills to all members of the PO
to work hand in hand for the success of the project.
-
25
Monitoring & Evaluation Contractor
The success of the project was a priority for most of the M & E
contractors. When the validation team from the regional office
found out that there were activities that had to be repeated
because they did not follow the procedure as stipulated in the
contracts, these contractors unquestioningly repeated said
activities without charging additional cost to the DENR.
Infrastructure Development Contractor
R.C. Tagala Construction, Inc., the contractor of the Farm-to-
Market Road and Water System has satisfactorily followed the
specification in their contract. They rehabilitated 2.4 kilometers
of farm-to-market Road and constructed about 9 kilometers of
access road that serves as permanent fire line at the center of
the project.
Other matters relating to Subproject Implementation
Please choose the item(s) from the following list on which you have any
comment, check it (them), and describe it (them) with measure and
results in (B) below.
A. Technical Financial Institutional Economic
Social/Distributional Others
B. Description (in detail)
1. Technical
During the time of appraisal, limited timeframe was given to
undertake this activity that resulted to some failure such as the site
species adaptability. The Subproject appraisal did not also anticipate
the effect of the construction of the San Roque Dam in implementing
subproject activities.
2. Institutional
The institutionalization of the Subproject Site Management Office
(SUSIMO) in the subproject came late. However, this strategy had
helped a lot in the success and in ensuring the proper implementation
of the activities.
-
26
3. Social/Distributional
The location of the Subproject covers various ethnic groups. There
were members of the communities that could easily grasp the
beneficial effects of the subproject. There were some, especially the
Indigenous People (Ibaloys) who refused to comprehend the good
intentions of the Subproject. But when they started to see the
tangible developmental effects of the Subproject, both physical and
socio-economic aspects, they voluntarily joined the project (Wait and
See Attitude).
II. A
III. CTION TAKEN BY THE AOs, APs AND POs RELATING TO
RECOMMENDATION(S)
Recommendation(s) made by
SUSIMO
Action Taken and Results
a. Assisting Professional
To extend assistance on the
refinement of PO Manual of
Procedure (MOP) and formulation of
additional policies relevant to the
improvement of Organization,
Constitution and By-Laws (CBL)
review, formulation of feasibility
studies and training design and
establishment of linkages with other
funding institutions, agencies and
private entities in the development
of the livelihood projects.
The AP had implemented the
recommendations made by the
SUSIMO in various aspects of
Capability Building and Strengthening.
The MOP was refined; additional
policies relevant to the improvement
of Organization were created; CBL was
ratified; feasibility studies and
training designs were formulated and
linkages with other institution like DA,
DSWD, CDA, BSU, CLSU, SRPC and
others were established. Pledges in
terms of providing assistance were
obtained. The MOP, CBL, FS and
Training Designs were put into place.
These activities strengthened the
leadership capabilities in managing the
organization.
b. Peoples Organization (PO)
The SUSIMO has constantly
reminded the PO to strictly adhere
to their existing policies, rules and
The PO strictly adhered to existing
policies, rules and regulation. Plans
were approved by the Board of
-
27
regulation and all transactions/plans
should be approved by the Board of
Directors before any actions be
made. Follow technical advise during
monitoring and evaluation of CSD
activities.
The SUSIMO advised the PO to have
a fix financial management system.
Directors before any actions were
carried out. Technical advice
recommended during evaluations
improved the quality of activities.
The PO sought the assistance of
SUSIMO in formulating a clear-cut
financial management system. The PO
is in the process of implementing the
formulated system.
IV. INITIAL OPERATION AND MAINTENANCE OF SUBPROJECT
FACILITIES
1. Present Condition of Facilities
A. Please check: This article is ( applicable due to problem(s) or not
applicable. No particular problem has occurred since the initial
operation started). If there have been any problems, please check the
relevant space in the Table.
PO FACILITIES
Item Status Initial
Operation
Maintenance Management
1.) 3 units Look-out
Tower
2.) 3 units Bunkhouse
3.) Water System
4.) Office Building
(7mx10m)
5.) Tractor
6.) Truck
7.) Rice Thresher
-2 unit
functional
-2 units
functional
-Operational
-Operational
-Operational,
needs repair
-Unserviceable,
needs repair
-
28
8). Sprayer
9.) Electric Fan
-Operational
-Serviceable
SUSIMO FACILITIES
Item
Status
Initial
Operation
Mainte-
nance
Management
1.) 2 units Motorcycle
2.) 1 unit KIA Ceres
3.) 1 set Computer
4.) 1 unit Printer
5.) 1 unit Typewriter
6.) 1 unit Kubota engine
generator
7.) 4 pcs Brunton
Compass
8.) 2 pcs Steel tape
9.) 4 pcs Abney hand
level
10.) 1 unit Rain gauge
11.) 3 units Binocular
12.) 1 unit Leroy
lettering set
13.) 2 unit GPS
14.) 2 units Handheld
Radio
15.) 1 unit Base
Transceiver
-Serviceable,
needs repair
- do -
- do -
- do -
Serviceable
- do -
- do -
- do -
- do -
- do -
- do -
- do -
- do -
- do -
-Serviceable,
needs repair
-
29
16.) 2 units Forester’s
transit
17.) 1 set GIS
maptitude
18.) 1 pc Planimeter
19.) 2 pcs Diameter
Tape
20.) 1 unit UPS
21.) 1 unit Grass cutter
22.) Office building
(5m x 7m)
23.) Site Engineer’s
Office Building
(5m x 6m)
-Serviceable
-Serviceable
-Defective
-Serviceable
-Serviceable
-Serviceable
- Serviceable
- Serviceable
B. Please check: The Problem(s) has arisen owing to the following
reason(s).
Technical Financial Institutional Economic
Social/Distributional Others (calamity)
C. Description (in detail)
PO Facilities
Calamity
One look-out tower and two Bunkhouses were damaged during the
onslaught of typhoon “Harurot”. The PO, right after the typhoon,
conducted repair of the damaged infrastructure.
Technical
The truck needs overhauling of cylinder head and replacement of
tractor rotavator.
-
30
SUSIMO Facilities
Technical
1. The motorcycles need replacement of Tail light and battery
2. The KIA SEU 674 needs overhaul of transmission and body
repainting
3. Upholstery of passenger and driver seat of KIA
4. Repair of radio transmitter
5. Repair of central processing unit of the Computer
6. Planimeter (vernier caliper is not aligned)
D. Aspect of utilizing the Subproject facilities
PO FACILITIES
Item Original Plan Actual Operation
Bunkhouse
Look out Towers
Graded Trails/Footpath
Water System
Office building
Tractor
Rice Thresher
Truck
Electric Fan
Sprayer
To serve as quarter for
laborer
To detect fire
occurrence.
For foot patrolling in the
area.
For irrigation and source
of water for the
established plantation.
Hold Office and
conferences
For IGP
For IGP
For IGP
For Office use
For IGP
As planned
As planned
As planned and in addition
for supply potable water
for the community
As planned and in
addition, as stock room
for equipment
For IGP
For IGP
For IGP and service to
ferry members.
For Office use
For IGP
-
31
SUSIMO FACILITIES
Item
Original Plan
Actual Operation
Motorcycle
KIA ceres 674
Computer
Printer
Typewriter
Kubota engine
generator
Brunton Compass
Steel tape
Abney hand level
Rain gauge
Binocular
Leroy lettering set
GPS
Handheld Radios
Base transceiver
Forester’s transit
GIS maptitude
Planimeter
Diameter Tape
UPS
Grass cutter
Office building
Site Engineer’s Office
3 Units for SUSIMO use
1 unit for SUSIMO use
1 unit for Office use
1 unit for Office use
1 unit for Office use
1 unit for Office use
4 unit for field use
2 unit for Office use
4 units for Field use
1 unit for Field use
3 units for Field use
1 unit for Office use
2 unit for Field use
2 units for Field use
1 unit for Office use
2 units for Field use
1 unit for Office use
1 unit for Office use
2 unit for Field use
1 unit for Office use
1 unit for Office use
1 unit for Office use
To hold Office and
meetings
1 unit for Office of the
Engineer’s of Infra
Development Component.
Upon completion of the
Infra project, the office
will be used by the
SUSIMO
3 Units for SUSIMO
&PO use
1 unit for SUSIMO &PO
use
1 unit for Office use
1 unit for Office use
1 unit for Office use
1 unit for Office use
4 unit for field use
2 unit for Office use
4 units for Field use
1 unit for Field use
3 units for Field use
1 unit for Office use
2 unit for Field use
2 units for Field use
1 unit for Office use
2 units for Field use
1 unit for Office use
1 unit for Office use
2 unit for Field use
1 unit for Office use
1 unit for Office use
1 unit for Office use
To hold Office and
meetings
1 unit for Office of the
Engineer’s of Infra
Development Component.
Upon completion of the
Infra project, the office
was used by the SUSIMO
2. Organization for Operation and Maintenance
A. Name
-
32
a.1 Please give the name of PO and/or Body in charge of O/M.
PO: San Felipe Watershed Management Association, Inc
Mr. Fernando D. Amarillo – President, SAFEWATER, Inc. – Head
of the Executive Body
SUSIMO: San Roque Watershed Rehabilitation Subproject Site
Management Office
Forester Marcelino S. Ramos – Site Management Officer-
Head of SUSIMO
a.2 Please check:
The latest organization chart (or equivalent) for O/M of the
Subproject facilities is ( attached or not available as Annex
1).
a.3. If the organization chart (or equivalent) is not available, please
state the reason.
B. Number of staff/workers of the PO or Body for Operation and
Maintenance of Subproject Facilities.
PO: 8 members of the executive Body
9 members of the Legislative Body
SUSIMO: 4 Staff- COSU Head, SDMU Head, VBU Head and One
Data Encoder
C. Please check and explain the following.
c.1 The number of staff is currently ( sufficient or insufficient).
If “Insufficient”, please describe your estimate of the
optimum number of staff and your plan for providing them.
c.2 Average employment period of the present staff
PO: 6 years
SUSIMO: 17 years
c.3 Availability of training program to promote the vocational ability
of the staff, its contents and expected effects. N/A
3. Annual Budget or Actual Expenditure for Operation and
Maintenance (by Year)
-
33
A. Original Expected Expenditure
There was no recorded financial allotment for the maintenance
and repair of the facilities of SAFEWATER, Inc.
SUSIMO
Item
Calendar year
Maintenance
Operation
Total
(mil.pesos)
2000
0.265000
0.265000
2001
0.190000
0.494750
0.684750
2002
0.040000
0.286000
0.326000
2003
0.100000
0.490480
0.590480
TOTAL 0.330000 1.536230 1.866230
B. Actual and Currently Expected Expenditure
PO-SAFEWATER
Item
Calendar
year
Maintenance
Operation
Maintenance
(For
expanded &
operation
portion)
Total
(Mil pesos)
1997-1998
-Repair of
equipment
and facilities
-Power and
Electricity
0.000495
0.000334
0.000495
0.000334
Subtotal 0.000495 0.000334 0.000829
1999
-Supplies
-Repair and
Maintenance
0.010000
0.007500
0.007500
0.010000
Subtotal 0.010000 0.007500 0.017500
2000
-
34
-Supplies
-Repair and
Maintenance
-Power and
Electricity
-Telephone/
Mobile Phone
0.006883
0.008882
0.000085
0.001329
0.008882
0.006883
0.000085
0.001329
Subtotal 0.006883 0.010296 0.017179
2001
-Supplies
-Repair and
Maintenance
-Power and
Electricity
-Telephone/
Mobile Phone
0.038118
0.010726
0.001114
0.001840
0.010726
0.038118
0.001114
0.001840
Subtotal 0.038118 0.013680 0.051798
2002
-Supplies
-Gasoline
-Repair of
Water
System
-Truck
Repair and
Spare parts
-Computer
Repair
-Electric
Installation
-Electric Bill
-Telephone/
Mobile Phone
0.004000
0.008522
0.008800
0.002605
0.005553
0.016000
0.000855
0.000300
0.002605
0.005553
0.004000
0.008522
0.008800
0.016000
0.000855
0.000300
Subtotal 0.021322 0.025313 0.046635
2003
-Fuel, Oil, &
Lubricants
-Office
Supplies
-Truck
Repair
-Office
Improvement
-Electric Bill
0.027862
0.010791
0.019614
0.007244
0.001309
0.019614
0.007244
0.027862
0.010791
0.001309
Subtotal 0.038653 0.028167 0.066820
-
35
TOTAL 0.115471 0.085290 0.200761
SUSIMO
Note: Actual and currently expected expenditure for expansion,
replacement or any other improvement purposes
Item
Calendar year
Maintenance
Operation
Maintenance & Operation
(for expanded portion)
Total
2000
-SUSIMO Office
- Gasoline, Oil, and
Lubricants for Vehicles
0.032000
0.015000
0.032000
0.015000
Subtotal 0.047000 0.047000
2001
-SUSIMO Office
-Gasoline, Oil, and
Lubricants for Vehicles
-Repair and Maintenance
of Vehicle
0.079631
0.171916
0.027000
0.171916
0.027000
0.079631
Subtotal 0.079631 0.198916 0.278547
2002
-SUSIMO Office
-Gasoline, Oil, and
Lubricants for Vehicles
-Repair and Maintenance
of Vehicle
0.074444
0.170159
0.098938
0.170159
0.098938
0.074444
Subtotal 0.074444 0.269097 0.343541
2003
-SUSIMO Office
-Gasoline, Oil, and
Lubricants for Vehicles
-Repair and Maintenance
of Vehicle
0.138216
0.130758
0.128936
0.130758
0.128936
0.138216
Subtotal 0.138216 0.259694 0.397910
2004
-SUSIMO Office
-Gasoline, Oil, and
Lubricants for Vehicles
-Repair and Maintenance
of Vehicle
0.030000
0.037500
0.022500
0.037500
0.022500
0.030000
Subtotal 0.030000 0.060000 0.090000
TOTAL 0.292291 0.774707 0.030000 0.060000 1.156998
-
36
Please describe the basis for the above estimate and your financing plan
for the same.
The People’s Organization has no allotment or financial plan for
maintenance and operation of equipment. The basis for allotment for the
SUSIMO’s maintenance and operational expenses was the actual needs
and expenditure of previous implemented projects of the same nature.
4. Maintenance Method
PO Facilities
The PO regularly maintained the infrastructure facilities constructed in
support of the Comprehensive Site Development Component of the
Subproject through repair of these structures. Power and electricity
for the PO Office is included in its maintenance and operation. Other
maintenance efforts included replacement of pipes for the constructed
water system; regular maintenance of PO truck : Gear Oil, Replacement
of Tire, Transmission Overhauling, Engine Change Oil, and the Gasoline
for Operation. Other equipment like the Tractor, Thresher, and Power
Spray were maintained/ repaired only when needed. The Executive Body
of SAFEWATER was the one tasked to facilitate the repair and
maintenance of equipment and facilities, as the need arose.
SUSIMO Facilities
Content of Method
Frequency
For KIA
- Gear oil
- Replacement of Tire
- Transmission Over hauling
- Engine change oil
- Gasoline
- every six months
- every two years
- every five years
- Every six months
Motor Cycle
- Change Oil
- Replacement of tire
- Replacement of Spar plug
- Replacement of brake shoe
- Replacement of hand brake
- Gasoline
- monthly
- every year
- every three months
- every six months
- every three months
Computer
- Replacement of cartridge ink
- every two months
-
37
V. BENEFITS DERIVED FROM SUBPROJECT
1. Indirect Effects
With the implementation of the subproject, the following
A. Please choose and check the item(s) which are dealt with this Article
by you.
Technological transfer (e.g. application of technology used in the
Subproject to other similar projects and subprojects)
Employment creating (e.g. during construction, contribution to the
sector(s) after completion)
Income-raising (e.g. income of the residents in the region)
Other intended or unintended effects on the relevant sector(s)
and/or the region concerned
B. Please give details for each of the item(s) you checked.
Employment creation
The implementation of the subproject created job opportunities
and livelihood activities for the participating communities. The
subproject regularly employed 270 members for the period of six
(6) years.
Income-raising
The total annual gross household income before the project
implementation of the subproject was estimated at PHP71,774.
Income from farm activities was estimated at PHP38,387 per
household per annum while off-farm and non-farm sources
contributed P33,387 per year.
For the first five years of project implementation the average
annual gross income of the area became PHP 126,290, including on-
farm, off-farm and non-farm activities.
PO members as well as other community residents benefited from
forest management operations through added income derived from
wages earned as workers in the CSD activities and in the
construction of infrastructures. Some members interviewed
attested that they were able to improve their houses made of
cogon and have these converted to concrete houses. They were
also able to buy some appliances. All of these materialized
because of the Project.
-
38
Other intended or unintended benefits
1. It was apparent that women have very strong involvement
and participation in the various phases of the CSD
activities, trainings and livelihood projects. This is a
manifestation that women in the area had been empowered
by the project.
2. With the rehabilitation of 2.4 km. farm-to-market road,
the accessibility of the area was improved through
shorter travel time and through various types of vehicles
all year round.
3. The construction of nine kilometer (9.0 k) Water System
will enable the agro forestry area to be irrigated, thus
capacitate the PO members to plant short term and medium
agricultural cash crops in between mangos during the dry
season. The comfort and convenience brought by these
infrastructures are being enjoyed by the participating
communities and nearby barangays.
-
39
VI. CONCLUSIONS AND RECOMMENDATIONS
The rehabilitation of the 1,638 hectares of the San Nicolas side of
the Subproject was accomplished as per its development plan.
The Subproject has succeeded in empowering members of the
communities including women.
Financial viability to sustain the plantations is ensured with the
contribution of the CSD income of SAFEWATER members to the
CFDF for its livelihood projects
Infrastructures have opened new opportunities for the
communities in terms of production, mobility, access to services.
It is recommended that special emphasis be given to the Appraisal
Stage of the Subproject to avoid a repeat of similar circumstances
that led to the cancellation of the San Manuel Side of the
Watershed Subproject.
All development projects within the project area and its effect on
the implementation process should be identified and anticipated in
order to avoid conflicts
It is advisable to organize a new PO as contractor for the CSD
rather than tap previous PO that had conflicts with the LGU and
encountered organizational problems
It is recommended that the SUSIMO be established in the early
part of project implementation because of its crucial role in
monitoring and strengthening the support mechanism of the DENR
to the PO.
It is recommended that similar projects be implemented in the
future.
-
FORESTRY SECTOR PROJECT
LOAN NO. PH-P 135
Table 1. Trainings Attended by PO
# of
TRAINING TRAINORS PARTICIPANTS INCLUSIVE DATES
1. Seminar and Workshop
Training on Livelihood
Development and
Management
STEP Inc 38 April 9-10, 2003
2. Seminar Workshop
Training on Fire
Protection
DENR-PENRO 35 March 12-13, 2003
3. Bookeeping Seminar Benguet State
University
26 February 11, 2003
4. Cooperative Seminar
and Training
CDA 32 November 22, 2001
5. GAD Training and
Seminar
DENR-PENRO 40 January 30, 2001
6. Livelihood Seminar AP- Edna Padio 40 November 6-8, 2001
7. Bookkeepping Seminar
and Accounting
AP- Edna Padio 34 November 20-23, 2001
-
FORESTRY SECTOR PROJECT
LOAN NO. PH-P 135
Table 2. Subproject Performance
Year Planted Component Species Planted Area Planted Survival
1997 208 87.82
Mix CEPAR 190 -
Agroforestry Mango 55 82.72
1998 Reforestation
571 has
Gmelina and
Mahogany21
86.78
Gmelina, Narra
and Eucalyptus 261 87.15
Benguet Pine and
Gmeline 98 84.64
Eucalyptus, 116 86.64
Gmelina and
Narra 75 84.71
Calamus sp 22 86.37Changed to
Narra and
Mahogany for
ANR in 2002 82 84.48
Agroforestry Mango 52 96.55
1999 Reforestation Gmelina and
Eucalyptus 25 96.48
Benguet Pine &
Eucalyptus 316
Eucalyptus and
Gmelina 129
Gmelina 25
2000 Reforestation Eucalyptus and
Benguet Pine 115 82.06
Agroforestry Mango 38 89.24
GRAND TOTAL 1,638.00
AVERAGE SURVIVAL RATE 87%
Mahogany and
Gmelina
Rattan
Plantation
140 has
Reforestation
398 has
-
FORESTRY SECTOR PROJECT
LOAN NO. PH-P 135
Table 3. Subproject Site Management Office Equipments
ITEMS SPECIFICATION QTY
PROCURED
DATE/ YEAR
PROCURED
COST (P)
1. Power Generator Engine, Gasoline, GS280,
3.5 KVA
I unit 4/23/2001 44,096.00
2. Computer HP Brio PC Intel Pentium
III 733 mhg
1 set 2/20/2001 70,850.00
3. Printer HP Deskjet model 840C 1 unit 4/27/2001 5811.52
4. UPS Gamatronic Compact model
520VA
1 unit 4/15/2001 5,720.00
5. GIS Maptitute Comb. Of software &
geographic data
1 set 3/28/2001 44,460.00
6. GPS Global Positioning Power 2 sets 3/28/2001 210,000.007. Handheld Radio VHF/FM COM- model IC-
F3G
2 sets 1/12/2001 29,933.28
8. Base Radio VHF/FM ICOM 1 unit 1/12/2001 64,789.929. Foresters Transit Surveying Compass,
Uskikata, model S-27
2
units
5/21/2001 65,680.00
10. Manual Typewriter Olivetti, 18 carriage 1 unit 3/28/2001 8,309.6011. Brunton Compass Kataoka br., model BCD-90 4 pcs 3/28/2001 19,552.00
12. Steel Nylon Tape Tajima br. 2pcs 4/23/2001 2,700.0013. Diameter Tape 2 pcs 3/29/2001 1,330.2014. Planimeter OSKK KOIZUMI 1 pc 10/26/2001 7,800.0015. Abney Hand Level Model: OSK 17251 4 pcs 5/21/2001 9,568.0016. Rain Guage Digital Rainwise 1 unit 5/28/2001 6,300.0017. Binocular 3 pcs 5/28/2001 12,168.0018. Lettering Set Leroy set 1 pc 5/28/2001 4,992.0019. Grass Cutter Kawasaki 1HP 1 unit 5/28/2001 17,000.00 TOTAL 631,060.52
-
FORESTRY SECTOR PROJECT
LOAN NO. PH-P 135
Table 4. Trainings Attended by the SUSIMO
# of
TRAINING TRAINORS PARTICIPANTS INCLUSIVE DATES
1. Site Coordinators Assessment DENR-NFDO-
OIDCI 5
May 3-6, 2000
2. Orientation Course of
SUSIMO staff
DENR-NFDO-
OIDCI 5
Oct. 17-19, 2000
3. FSP Re-Orientation Course
For SUSIMO and other Project
Implementation Mentors
DENR-NFDO-
OIDCI5
Feb. 26-28, 2002
4. FSP Phase-out/Phase In
Planning Workshop for DENR
and PO staff
DENR-NFDO-
OIDCI5
Oct. 15-19, 2002
5. Enhanced Forest
Management Through GIS and
GPS
DENR-NFDO-
GIS5
May 16-26, 2001
6. Leadership and Organizational
Management
OIDCI
5
April 1-2, 2003
-
FORESTRY SECTOR PROJECT LOAN NO. PH-P 135Table 5a. Livelihood Projects of the PO
Name of Livelihood Project Tilapia Production
Implementor SAFEWATER Inc.
No. of beneficiaries 270
Amount of Investment Php 3,774.00
Date of Feasibility Study No FS
Date Started 1998
Status Operation was terminated in 1998 becauseof the El Nino Phenomenon
CFDF/CBU Php 578,000.00
Linkages Developed LGU, CDA, CLSU, FIDA, DA, SRPC
-
FORESTRY SECTOR PROJECT LOAN NO. PH-P 135Table 5b. Livelihood Projects of the PO
Name of Livelihood Project SAFEMART (Consumer Store)
Implementor SAFEWATER Inc.
No. of beneficiaries 270
Amount of Investment Php 50,000.00
Date of Feasibility Study No FS
Date Started 1998
Status Operation was terminated and the funds financedthe CSD Activities
CFDF/CBU Php 578,000.00
Linkages Developed LGU, CDA, CLSU, FIDA, DA, SRPC
-
FORESTRY SECTOR PROJECT LOAN NO. PH-P 135Table 5c. Livelihood Projects of the PO
Name of Livelihood Project Truck for Hire
Implementor SAFEWATER Inc.
No. of beneficiaries 270
Amount of Investment P275,000.00
Date of Feasibility Study No FS
Date Started 1999
Status The project was terminated. The truck is forrepair and was used to trasport plantation workers
CFDF/CBU Php 578,000.00
Linkages Developed LGU, CDA, CLSU, FIDA, DA, SRPC
-
FORESTRY SECTOR PROJECT LOAN NO. PH-P 135Table 5d. Livelihood Projects of the PO
Name of Livelihood Project Goat Raising
Implementor SAFEWATER Inc.
No. of beneficiaries 14
Amount of Investment Donated by DENR Regional Office
Date of Feasibility Study No FS
Date Started 1999
Status The project temporarily ceasedoperation due to the El Nino Phenomenon
CFDF/CBU Php 578,000.00
Linkages Developed LGU, CDA, CLSU, FIDA, DA, SRPC
-
FORESTRY SECTOR PROJECT LOAN NO. PH-P 135Table 5e. Livelihood Projects of the PO
Name of Livelihood Project Thresher for Hire
Implementor SAFEWATER Inc.
No. of beneficiaries 270
Amount of Investment Php 125,000.00
Date of Feasibility Study No FS
Date Started 2000
Status It was stopped because the machineis for repair
CFDF/CBU Php 578,000.00
Linkages Developed LGU, CDA, CLSU, FIDA, DA, SRPC
-
FORESTRY SECTOR PROJECT LOAN NO. PH-P 135Table 5f. Livelihood Projects of the PO
Name of Livelihood Project Tractor for Hire
Implementor SAFEWATER Inc.
No. of beneficiaries 270
Amount of Investment Php 135,000.00
Date of Feasibility Study No FS
Date Started 2002
Status The project was stopped because the tractoris for repair
CFDF/CBU Php 578,000.00
Linkages Developed LGU, CDA, CLSU, FIDA, DA, SRPC
-
FORESTRY SECTOR PROJECT LOAN NO. PH-P 135Table 5g. Livelihood Projects of the PO
Name of Livelihood Project Power Spray for Hire
Implementor SAFEWATER Inc.
No. of beneficiaries 270
Amount of Investment Php 13,000.00
Date of Feasibility Study No FS
Date Started 2002
Status The project discontinued because it isbeing used by the PO members in maintenance of agroforestryplantation (mango fruit production) and for fire suppression.
CFDF/CBU Php 578,000.00
Linkages Developed LGU, CDA, CLSU, FIDA, DA, SRPC
-
FORESTRY SECTOR PROJECT
LOAN NO. PH-P 135
Table 6. Subproject Status Report
SMP CO CSD M & E INFRA
I San Roque Watershed 1,638 49,730,998.78 C C C C CRehabilitation Subproject
Status of Progress
(O: on-going, C: Completion)RegionName/Location of
Subproject
Project
Area (ha)
Project Cost
(Million Peso)
-
FORESTRY SECTOR PROJECT
LOAN NO. PH-P 135
Table 7. SMP Cost Estimate Per activity
ACTIVITIES ACTUAL ACTIVITIES*TARGET
OUTPUTUWM UNIT COST TOTAL COST
I. SURVEY AND MAPPING I. SURVEY AND MAPPING
a. Perimeter survey, area a. Mobilization
computation, site characterization 1. Aircraft, Fuel, & Personnel
and map preparation positioning
b. Field Section and Blocking b. Aerial Photography 2,000.00 has P168.75 337,500.00
1. Indexed Photographs
c. Present Land Use Survey and 2. Photomosaic
Mapping 3. Photo Control Points
d. Topographic Survey & Mapping c. Ground Survey 2,000.00 has 202.50 405,000.00
1. Ground Control Points
e. Soil/Land Capability Survey and 2. Soil Analysis
Mapping 3. Interviews
f. Agro-socio economic studies
(ave. 3 household/ha.)
g. Climate, geology and water
resourced survey
SUB-TOTAL P371.25 742,500.00
II. PLANNING II. PLANNING
a. Data synthesis and analysis a. Maps (10 types) 2,000.00 has 101.25 202,500.00
b. Report Writing b. Feasibility Study and Written 2,000.00 has 202.50 405,000.00
Technical Report
SUB-TOTAL 303.75 607,500.00
GRAND TOTAL 2000 has 675.00 1,350,000.00
* SMP Thru Aerial Photo
-
FORESTRY SECTOR PROJECT
LOAN NO. PH-P 135
Table 8. Community Organizing Cost Estimate Per Activity
UNIT
ACTIVITIES TARGET of UNIT COST TOTAL COST
MEASURE
PHASE I (3 months) 2310.0 has 157.75 364,395.00
1. Social Investigation (SI)
2. Information and Education
Campaign
3. Documentation
4. Identification of Possible FLMA
SUB - TOTAL 364,395.00
PHASE II (21 months) 2310.0 has 1,132.23 2,615,459.70
1. Organizing Activities
2. Community Activities
3. Documentation Process
4. Contingency (10%)
SUB - TOTAL 2,615,459.70
GRAND TOTAL 2310 has 1,289.98 2,979,854.70
-
FORESTRY SECTOR PROJECTLOAN NO. PH-P 135
TARGET UNIT OF UNIT TOTALOUTPUT MEASURE COST COST
1. SEEDLING PRODUCTION 54,747.00 seedlings 48.74 2,668,189.16a. Nursery Site Preparationb. Planting Stockc. Bagsd. Soil Collectione. Bagging
Subtotal 2,668,189.162. PLANTATION ESTABLISHMENT 145 hectares 145.00 21,025.00
a. Strip brushing/ clearingb. Stakingc. Hole Diggingd. Haulinge. Planting
Subtotal 21,025.003. MAINTENANCE & PROTECTION
a. Ringweeding and cultivation (2 passes) 145 hectares 2,196.71 318,523.33b. Fertilization 3800 spots 13.18 50,065.00c. Replanting 2900 spots 45.30 131,361.20d. Patrol Works 145 hectares 1,095.60 158,861.42e. Fireline (establishment and maintenance) 16686.99 sq.m. 4.05 67,555.10
Subtotal 726,366.054. ADMINISTRATION & SUPERVISION
a. Fisrt and Second Year 107 hectares 1,144.42 122,453.17b. Third Year 107 hectares 736.55 78,811.01c. Fourth Year 145 hectares 57.12 8,282.12d. Fifth Year 145 hectares 434.48 62,999.99e. Sixth Year 145 hectares 559.02 81,058.41f. Seventh Year 145 hectares 53.78 7,798.27
Subtotal 361,402.97T O T A L 145.00 hectares 26,048.16 3,776,983.18
* Cost Estimate presented is for San Nicolas Side only. See table 12a.
ACTIVITIES
Table 9a. Cost Estimate for Agroforestry Per Activity
-
FORESTRY SECTOR PROJECTLOAN NO. PH-P 135Table 9b. Cost Estimate for Assisted Natural Regeneration Per Activity
UNITMAJOR ACTIVITY / ACTIVITY of Unit Cost Total Cost
MEASURE
I. NURSERY OPERATIONS has 785.64 82 64,422.531. Barefoot (70%)2. Cuttings (30%)
SUB-TOTAL 64,422.53
II. LOCATING REGENERATIONS1. Locating and Marking / Staking of
RegenerantsSUB-TOTAL
III. RELEASING REGENERATIONS1. Under brushing and slashing2. Ringweed and cultivate
SUB-TOTAL
IV. ENHANCING REGENERATIONS1. Site Preparation
1.1 Spot hoeing2. Planting (including holing)
SUB-TOTAL
V. MAINTENANCE and PROTECTION has 498.00 82 40,860.341. Ringweed and Cultivate2. Replanting (10% of Enrichment)3. Patrol Work (2 passes)
SUB-TOTAL 40,860.34
VI. PROJECT MANAGEMENTa. Fisrt and Second Yearb. Third Yearc. Fourth Yeard. Fifth Yeare. Sixth Year has 549.18 82 45,032.45f. Seventh Year has 52.83 82 4,332.36
SUB-TOTAL 49,364.81G R A N D T O T A L has 1,885.95 82 154,647.68
* Cost Estimate presented is for San Nicolas Side only. See table 12a.
Target Output
-
FORESTRY SECTOR PROJECTLOAN NO. PH-P 135Table 9c. Cost Estimate for Rattan Plantation Per Activity
TARGET UNIT OF UNIT TOTALOUTPUT MEASURE COST COST
1. SEEDLING PRODUCTION 104 hectares 6,063.65 630,620.00a. Nursery Site Preparationb. Planting Stockc. Bagsd. Soil Collectione. Bagging
Subtotal 630,620.002. PLANTATION ESTABLISHMENT 104 hectares 900.00 93,600.00
a. Strip brushing/ clearingb. Stakingc. Hole Diggingd. Haulinge. Planting
Subtotal 93,600.003. MAINTENANCE & PROTECTION
a. Ringweeding and cultivation (2 passes)b. Fertilizationc. Replantingd. Patrol Works 104 hectares 1,151.74 119,781.14e. Fireline (establishment and maintenance) 66,747.96 sq.m. 0.44 29,584.88
Subtotal 149,366.024. ADMINISTRATION & SUPERVISION
a. First and Second Year 104 hectares 588.83 61,238.80b. Third Year 104 hectares 757.80 78,811.00c. Fourth Year 104 hectares 53.09 5,521.42d. Fifth Year 104 hectares 403.85 41,999.99e. Sixth Year 22 hectares 409.39 9,006.49f. Seventh Year 22 hectares 39.39 866.47
Subtotal 197,444.17T O T A L 22* hectares 48,683.19** 1,071,030.19
* the actual accomplished area for rattan is 22 hectares** the computed unit cost includes the expenses for 104 hectares established plantation from
1998-2001. From the 104 has. only 22* has. have considerable survival rate. Instead of replanting the 82has. invalidated plantation, it was transformed into an ANR area.*** Cost Estimate presented is for San Nicolas Side only. See table 12a.
ACTIVITIES
-
FORESTRY SECTOR PROJECTLOAN NO. PH-P 135Table 9d. Cost Estimate for Tree Plantation/Reforestation Per Activity
TARGET UNIT OF UNIT TOTALOUTPUT MEASURE COST COST
1. SEEDLING PRODUCTION 2,064,750 seedlings 3.90 8,059,439.80a. Nursery Site Preparationb. Planting Stockc. Bagsd. Soil Collectione. Bagging
Subtotal 8,059,439.802. PLANTATION ESTABLISHMENT 1,389 hectares 2,116.89 2,940,359.96
a. Strip brushing/ clearingb. Stakingc. Hole Diggingd. Haulinge. Planting
Subtotal 2,940,359.963. MAINTENANCE & PROTECTION
a. Ringweeding and cultivation (2 passes) 1,844,000 spots 1.39 2,567,788.20b. Fertilization 820,000 spots 0.55 453,050.00c. Replanting 255,083 spots 10.80 2,753,520.10d. Patrol Works 1,389 hectares 1,096.90 1,523,586.18e. Fireline (establishment and maintenance) 1,435,081.14 sq.m. 0.44 638,079.90
Subtotal 7,936,024.384. CSD INFRASTRUCTURE
a. Graded Trail 20 km 6,180.00 123,600.00b. Bunkhouse 2 units 48,800.00 97,600.00c. Office 1 unit 417,065.22 417,065.22d. Lookout Tower 3 units 18,958.00 56,874.00e. Water System 15 km 29,400.00 441,000.00f. Fireline/ Firebreak
Subtotal 1,136,139.225. ADMINISTRATION & SUPERVISION
a. Fisrt and Second Year 869 hectares 828.76 720,193.03b. Third Year 1129 hectares 732.96 827,515.57c. Fourth Year 1389 hectares 56.31 78,220.06d. Fifth Year 1389 hectares 428.37 594,999.94e. Sixth Year 1389 hectares 551.15 765,551.65f. S