7/16/2019 SAP MRP Configuration http://slidepdf.com/reader/full/sap-mrp-configuration 1/27 SAP MRP Configuration SAP MRP Configuration The following are the Major Configuration items explained in detail: a) Activating MRP and Planning File Entry b) SAP MRP Plant Level MRP Parameters Configuration c) SAP MRP, MRP Group Level Parameters Configuration d) Configuring SAP MRP Types e) Configuring SAP MRP Scope of Planning for the Total Planning Run f) Configuring SAP MRP Planning time fence and Roll Forward Period g) Configuring SAP MRP Areas h) SAP MRP Dynamic Safety Stock (Range of coverage Profile) i) Configuring SAP MRP Days Supply and Receipt Days Supply SAP MRP Configuration Activating MRP and Planning File Entry a) Activating SAP's Material Requirements Planning (MRP) This configuration allows you to choose the plant for which you would want to activate SAP Material Requirement Planning (SAP MRP). Activating MRP for the plant allows one to use the SAP MRP tool for the plant. SAP Transaction code OMDU and the SAP path is Logistics > Production > MRP > Planning File Entry > Activate MRP and Set up Planning File b) Activating Planning File Entries for a Plant 

Upload: devasap

Post on 30-Oct-2015

455 views

Category:

Documents


68 download

TRANSCRIPT

Page 1: SAP MRP Configuration

7/16/2019 SAP MRP Configuration

http://slidepdf.com/reader/full/sap-mrp-configuration 1/27

SAP MRP Configuration

SAP MRP Configuration

The following are the Major Configuration items explained in detail:

a) Activating MRP and Planning File Entry

b) SAP MRP Plant Level MRP Parameters Configuration

c) SAP MRP, MRP Group Level Parameters Configuration

d) Configuring SAP MRP Types

e) Configuring SAP MRP Scope of Planning for the Total Planning Run

f) Configuring SAP MRP Planning time fence and Roll Forward Period

g) Configuring SAP MRP Areas

h) SAP MRP Dynamic Safety Stock (Range of coverage Profile)

i) Configuring SAP MRP Days Supply and Receipt Days Supply

SAP MRP Configuration

Activating MRP and Planning File Entry

a) Activating SAP's Material Requirements Planning (MRP) 

This configuration allows you to choose the plant for which you would want to activate SAP Material 

Requirement Planning (SAP MRP). Activating MRP for the plant allows one to use the SAP MRP tool for

the plant. SAP Transaction code OMDU and the SAP path is Logistics > Production > MRP > Planning File

Entry > Activate MRP and Set up Planning File

b) Activating Planning File Entries for a Plant 

Page 2: SAP MRP Configuration

7/16/2019 SAP MRP Configuration

http://slidepdf.com/reader/full/sap-mrp-configuration 2/27

 Activating Planning file entry for the plant (through a variant that can be rescheduled) allows you to

collect all the material in a planning file list, which has an MRP Type in the material master MRP 1 View

(other than MRP Type XO)

The process of recording a planning file entry for a material, can be run periodically using a batch job

scheduling method. The transaction code to set up the variant and period scheduling is OMDO and thePath for activating the planning file set up is Logistics > Production > MRP > Planning File Entry > Activate

MRP and Set up Planning File

All the entries in the planning file will have a “change indicator” specifying that a material has

undergone a change (change in receipts elements or issues elements). This indicator will help you to

choose only those materials that have undergone a change, through the use of planning key called “Net

Change Planning” when running MRP.

The planning file record for a material also has a “net change planning in the current horizon” field

which will be set if the change in the materials receipt or issue element is valid in the planning horizon.

This indicator will help you choose only those materials which have undergone a change in the planning

horizon; through the use of a planning key, in an MRP run, called “Net change planning in the planning

horizon”.

Plant Level configuration for MRP

Plant Level configuration for MRP 

SAP MRP is run at plant level or at a group of plant level (called as scope of planning), thus the MRP

configuration is done at Plant level.

The configuration done for SAP MRP at Plant level would also be true for SAP Consumption BasedPlanning (SAP CBP) settings.

Transaction code OPPQ takes you in to the SAP MRP configuration called as – Plant Parameters for

Material Requirement Planning. The Path which can be used is Logistics > Production > Material

Requirement Planning > Plant Parameters > Carry out Overall Maintenance of Plant Parameters.

The Transaction code for Consumption Based planning is OMI8 and the Path is Logistics > Materials

Management > Consumption Based Planning > Plant Parameters > Carry out Overall Maintenance of 

Plant Parameters.

Page 3: SAP MRP Configuration

7/16/2019 SAP MRP Configuration

http://slidepdf.com/reader/full/sap-mrp-configuration 3/27

 

Fig MRP - Config 1 

In the transaction code for Plant level parameters for SAP MRP, you should first input the plant and

press the maintain button.

If you have already maintained the configuration for the parameters, then it states so, if you haven’t

then it simply says – “To Maintain” next to the parameter 

Page 4: SAP MRP Configuration

7/16/2019 SAP MRP Configuration

http://slidepdf.com/reader/full/sap-mrp-configuration 4/27

 

Fig MRP - Config 2 

Following are the parameters that need to maintain as a part of SAP MRP/CBP Configuration:

a) Number ranges 

The number range ID’s are maintained for the following objects: 

the Planned orders

the reservations,

the dependent requirements,

the simulative dependent requirements,

the purchase requisitions,

the MRP Lists,

In this section only the number range ID’s are maintained. While the actual number range is configured,

for the number range ID, using a transaction code OMI2 (for the above mentioned objects created in the

Page 5: SAP MRP Configuration

7/16/2019 SAP MRP Configuration

http://slidepdf.com/reader/full/sap-mrp-configuration 5/27

planning run). One can also use the transaction code OMI3 for the objects created manually in the front

end.

Every number range interval, created using OMI2 and OM13, has an ID, which can be allocated to the

objects at plant level, i.e., every plant can have a different number range for the objects mentioned

above.

b) Availability Check rule for Backorder Processing 

As per standard SAP, the Availability checking rule for the backorder processing is “PP”, though you can

have your own availability check rules created or configured.

Every Availability checks rule (availability checking scope defined) has a set of receipts (Purchase orders,

Production orders) and issues (Sales orders, dependent requirements, reservations, planned

independent requirements etc) which are to be considered or not to be considered during the SAP

availability checks.

To have the checking rule work along with the configuration, you should have the Availability checking

groups maintained in the material master. The Checking groups are configured to be associated with the

checking rules (checking scopes).

The availability checking rule (checking rule scope) has to be maintained, for a given SAP functionality

and it has to be assigned to the availability checking group maintained in the material master. The SAP

functionalities that use availability checks to check the availability of the header materials as well as

components at the plant at the time of sales order creation, the availability checks of the header

material at the time of sales order delivery, the availability checks for components in production – thus

reporting the missing parts list, the backorder processing etc.

c) Reporting

This configuration is used for the following purposes.

• To configure the objects, which are to be considered in the calculation of the “receipts days supply”

like the production orders/process orders, firmed planned orders, purchase orders, assigned planned

orders, firmed purchase requisitions, QM Inspection lots, reservations, safety stocks

• To configure the reporting of “periods totals” in terms of a defined period (day, week, month, periods

as per planning calendar) of in Stock requirement list, MRP list, simulative MPR or interactive MRP

d) MRP Controllers 

This is a mandatory configuration. Here you can configure the list of MRP controllers for the plant. A

MRP Controller is a person or a group of people, which is responsible for planning a material or a given

list of materials.

Page 6: SAP MRP Configuration

7/16/2019 SAP MRP Configuration

http://slidepdf.com/reader/full/sap-mrp-configuration 6/27

You have to assign the MRP controller to the Material Master MRP 1 View, so as to delegate the

responsibility of the planning and evaluation of planning for that material.

e) Floats 

Floats are buffers in the total lead time, that are provided in production/process order or in the planned

orders created manually or during an MRP run. The schedule margin key is used in the Material Master

MRP 2 View. It is used in MRP as well as in production order.

The floats are defined using the scheduling margin key.

Opening period : Number of working days between the date that the order is created and the planned

start date. This time is available for the MRP controller to convert a planned order into a purchase

requisition or a production order.

Float after production: Number of working days between the scheduled finish date and the order finish

date; used as a float in production scheduling.

Float before production: Number of working days between the order start date and the scheduled start

date; used as a float in production.

Scheduling release period : Number of workdays between the planned start date and the date for

releasing the order. If the order release indicator is set, the production order is released by a

background program that takes all dates into account.

Plant Plant

Name 

Margin

Key 

Opening

Period (In

Days) 

Fl. Before

Production (In

Days)

Fl. After

Production (In

Days) 

Release

Period (In

Days)

0001 0001 001 5 2 2 5

0001 0001 002 5 3 3 5

0001 0001 002 5 4 4 5

f) Special Procurement 

The special procurement function helps you to configure and assign special procurement to the

materials which can be used during an MRP run while creating the procurement proposal.

The special procurement functions are withdrawal from alternate plant, production in alternate plant,

subcontracting, direct production, phantom item planning,

https://sites.google.com/site/sapswords/home/learn-sap-pp/sap-material-master/sap-mrp2-view 

Example: For Stock Transfer from Plant C001 to Plant C002

Page 7: SAP MRP Configuration

7/16/2019 SAP MRP Configuration

http://slidepdf.com/reader/full/sap-mrp-configuration 7/27

Create the Special procurement key (Key number = 12 as an example) in the plant C002 with the

procurement type as “F” and special procurement as “U” (Stock transfer) and the special procurement

plant as “C001”. Normally when creating the special procurement key use Z, Y or X to the Key number,

so instead of having Key number as 12, we could have something like Z2 or YA etc.

Fig MRP - Config 3 

Similarly for Withdrawal from Alternate plant, you could have a Configuration as below:

Fig MRP - Config 4 

Similarly for Subcontracting, you could have a Configuration as below:

Page 8: SAP MRP Configuration

7/16/2019 SAP MRP Configuration

http://slidepdf.com/reader/full/sap-mrp-configuration 8/27

 

Fig MRP - Config 5 

Similarly for Production in alternate plant, you could have a Configuration as below:

Fig MRP - Config 6 

g) Conversion for Planned orders 

In this configuration parameter, you can maintain the production order type or the process order type,

which the system should use as default during the planned order conversion. Setting defaults in the

plant parameters configuration allows the system to fix and select the order type for a plant during the

conversion process.

Note: This can be a useful tool when you are using one production order type and one process order

type, but if you are using multiple production/process order types, then you should not be maintaining

defaults here.

Also for the purchase requisition conversion, you are given an option in the configuration to define the

maximum number of planned orders that can be converted in to Purchase requisition.

Page 9: SAP MRP Configuration

7/16/2019 SAP MRP Configuration

http://slidepdf.com/reader/full/sap-mrp-configuration 9/27

 

Fig MRP - Config 7 

g) Dependent Requirements availability check

When carrying out the availability check for each of the components in a MRP BOM explosion, the

system needs to know the availability checking scope rule. Again we would maintain the standard

Checking rule as PP or you could alternatively configure one for yourselves.

h) BOM/Routing Selection ID 

This configuration parameter is really important and it is mandatory to maintain one, since it helpsselection of BOM and task lists in the planned orders. Though there is one more place in the planned

order Scheduling parameters MRP configuration, where you can maintain the selection ID for selection

of the Task lists (Routing/Recipe/Rate Routing).

A selection procedure is set to select BOM or Routing/Recipe on priorities set for the BOM usage or for

the task list types and the task list status. Knowing the selection procedures allows the MRP run to select

the right BOM and task list for the planned orders.

In other words, you could have the BOM Selection being set for selection of the Production BOM Usage

first and if a BOM for the material with the Usage – production (Usage = 1), is not found, you could have

the system search for a BOM of universal Usage (Usage = 3).

Similarly, you could have a task list of type Routing or Recipe or reference operation sets selected and

set in priorities of selection (1st

  – Routing, 2nd

  – Reference operation sets, 3rd,

which has a Status

Released for all purposes or released for costing) etc.

h) Scheduling of Planned orders 

This configuration parameter is really important and it is mandatory to maintain one. It allows you to set

the control parameters for scheduling of planned orders of type LA at a given plant and for a given MRP

Controller. You can leave the MRP controller as “*” to have the scheduling parameters true for all the

planned orders across all the MRP controllers.

The following control parameters can be configured here:

· The Routing/Recipe Selection ID, specifying the routing/recipe that would be selected for detailed

scheduling, as per the priorities set for task list type and task list status.

Page 10: SAP MRP Configuration

7/16/2019 SAP MRP Configuration

http://slidepdf.com/reader/full/sap-mrp-configuration 10/27

· The Detailed scheduling, using the task list is only carried for the scheduling Horizon mentioned, i.e., if 

the planned orders dates lie beyond the scheduling horizon, then the basic date scheduling is used

where the in house production times from the material master is used.

· Allow Scheduling Indicator allows the planned orders to be scheduled using the detailed scheduling or

basic date scheduling, either of the two, depending upon the availability of the task list and schedulingtype selected for the MRP run.

· Generate Capacity requirements indicator allows generation of the capacity requirements for the work

centers and loads them accordingly. The loading of the work centers is as per the use of the work center

determined through the scheduling carried out.

· The Task list selection, scheduling horizon, scheduling indicator and the capacity indicator can also be

set for rough cut planning used for Long term planning purposes.

· The next configuration parameter talks about the configuration of the selection of the type of 

scheduling level that should be used for adjusting the basic dates of planned orders. The various optionsavailable are rate based scheduling, lead time scheduling, scheduling using takt times.

· The Adjust planned order dates configuration option allows you to readjust the scheduling results or

the basic dates every time you carry out Scheduling. Though there is one more scheduling configuration

option provided by the system for overwriting/adjusting the existing basic dates by the new dates

arrived at, through rescheduling (using the scheduling level as mentioned).

The system not only offers an option to adjust the basic dates for the planned order arrived at by using

the scheduling level set, but it also setting the dates of the dependent requirements to the operation

start date or the order start date.

This configuration not only adjusts or sets the dates of the header planned order and the dependent

planned orders, but it also generates capacity requirements for the same.

See below for the details of adjusting dates in scheduling and adjusting dates for capacity requirement

generation:

· You can adjust the Basic Dates of the header planned order using the scheduling level and adjust (or

set) the dependent requirements to the start of the header planned order

· You can adjust the Basic Dates of the header planned order using the scheduling level and adjust (or

set) the dependent requirements to the start of the respective operation to which the dependentrequirements are assigned to

· You can decide not to adjust the Basic Dates of the header planned order arrived at by using the

scheduling level and at the same time not-adjust (or not set) the dependent requirements to the start of 

the header planned order

Page 11: SAP MRP Configuration

7/16/2019 SAP MRP Configuration

http://slidepdf.com/reader/full/sap-mrp-configuration 11/27

· You can decide not to adjust the Basic Dates of the header planned order arrived at by using the

scheduling level and at the same time not-adjust (not set) the dependent requirements to the start of 

the respective operations to which the dependent requirements are assigned to

· You are also provided an option to configure the scheduling type  – whether forward or backward

scheduling. It is a normal behavior for the standard system to have this configured as “backwardscheduling” so that SAP MRP (material requirement planning) never misses the customer delivery date

or order availability date. An option is also provided to not-to-schedule, any orders during the breaks set

in the factory calendar.

· Start date in the in the past options allows you to push the start date of the planned orders to a

certain number of days in past. If the order start date goes beyond the number of days allowed, then

the system uses the concept of ‘today’s scheduling” and sets the start date of the planned order to

today’s date and carrying out forward scheduling there-after.

· One of the scheduling parameters is “reduction measures”, used to reduce the total order lead time in

circumstances designed. You can avoid configuration of reduction measures, if you are not using it.

Fig MRP - Config 8 

i) Default Values for External Processing

For external purchasing, one can maintain the default lead time required for conversion of Purchase

requisition into purchase order, using the planned delivery lead times from the purchase info record or

Page 12: SAP MRP Configuration

7/16/2019 SAP MRP Configuration

http://slidepdf.com/reader/full/sap-mrp-configuration 12/27

purchasing agreement. So as to use the planned delivery times from the purchase info record, one

should also maintain the source list for the material, with the same vendor in the source list and the

purchase info record.

Using the planned delivery times from the material master or from purchase info record, is totally a

decision of the consultant. It is indeed a nice additional option provided by SAP for using the lead timefrom info records.

 j) Planning Horizon 

Maintaining a planning horizon helps the system to plan only those demands, which fall in the planning

horizon starting from today. When an MRP Run is taken, the planning horizon is number of work days as

mentioned (let’s say 180 days) from today’s date; the system would not plan any orders whose start

date lies beyond this horizon.

k) Available stock for net requirement calculations 

SAP MRP offers you a choice to select the most controversial stock types, in its net requirement

calculations. The stock types are – stock in transfer (stock in transfer is considered as stock at the

receiving plant as it is already issued from the sending plant), blocked stock, restricted batch stock (stock

of batches marked with restricted batch)

Fig MRP - Config 9 

l) Option to trigger direct Production in MRP or in production planning

 j) Allowing start date in the past 

MRP Group Level configuration for MRP

MRP Group Level configuration for MRP 

Page 13: SAP MRP Configuration

7/16/2019 SAP MRP Configuration

http://slidepdf.com/reader/full/sap-mrp-configuration 13/27

The entire configuration that is created as a part of SAP MRP Plant level parameter in the above steps

can be also set for an MRP Group. You can group materials using MRP Groups. Each of the MRP Group

can have its own MRP Parameter set. You can set the MRP group in the material master MRP 1 View.

MRP Group can be maintained using transaction code OPPR or the transaction path – Logistics >

Production > MRP > MRP Groups >

Advantage of working with MRP Groups: 

Working with MRP groups can be convenient for a plant or an organization, since by assigning the MRP

groups to a set of materials, would allow planner to configure these materials (through MRP Groups) to

behave in a certain manner for planning purposes. In other words, all the materials in the group would

then have a unique planning method or unique planning features. Thus the organization can device

multiple MRP groups with their own planning features and characteristics rather than having one set of 

planning features set at the plant level. The group could have its own unique:

Strategy group,

Conversion order types,

Planning horizon,

Planning time fence and roll forward periods,

BOM and task list selection ID’s,

Direct procurement parameters,

Planned order scheduling parameters,

Start number of days allowed in the past

Availability checking groups,

Strategy Groups 

The strategy groups can be set for a given MRP group at a given plant. The strategy group consists of a

number of planning strategies assigned in a sequence of priorities. In other words, the strategy groups,

groups together the relevant planning strategies of a material. If you don’t see the default strategy

groups, then we would have to manually maintain the strategy groups on the materials MRP 3 view.

Defaulting the strategy groups is a nice idea when the strategy groups would remain the same across all

the materials which would be assigned with a given strategy group.

For example:

A material can have the priority 1 strategy as Made-to-Stock (planning strategy 40) and then priority 2

planning strategy as Made-to-Order (planning strategy 20). Assigning this “strategy group” for a MRP

Page 14: SAP MRP Configuration

7/16/2019 SAP MRP Configuration

http://slidepdf.com/reader/full/sap-mrp-configuration 14/27

group in the MRP Group Parameters configuration and then subsequently assigning the MRP Group to

the material master would make the material work on a planning strategy 40 and planning strategy 20 in

a sequence of priority.

The primary strategy for the material is 40 – Made-to-stock while the secondary strategy is 20 – Made-

to-order, which means that every time you plan or produce a material or create a sales order for thematerial it will always primarily work as a made-to-stock material. Nevertheless, you can also make to

material work as a made-to-order material, by changing the requirement type – “KE” of the material in

the sales order procurement tab, to suit for made-to-order, which the system would allow since the

material’s secondary planning strategy is made-to-order.

Configuring SAP MRP Types

Configuration of SAP MRP Types 

In all probabilities, MRP Types is not something which one should configure in SAP; it is used as a

standard configuration. Nevertheless, a consultant should know the importance of MRP types and theinvolved pre-configured parameters.

Fig MRP - Config 10 

Page 15: SAP MRP Configuration

7/16/2019 SAP MRP Configuration

http://slidepdf.com/reader/full/sap-mrp-configuration 15/27

 

a) MRP Procedures

MRP Procedures defines the type of MRP to be used – Reorder point planning methods, Material

requirement planning or demand based planning methods, Forecast based planning methods, Time

phased planning methods, MPS and the no planning procedures to mark a material with a MRP types

that does not plan a material at all.

b) Firming Type

In the category of MRP procedure called – MRP or demand based planning method and MPS, SAP offers

8 different MRP types with Firming namely P1, P2, P3, P4 and M0, M1, M2, M3, M4.

When working with the planning time fence, one needs to set the firming methods & the scheduling

methods of the procurement proposals within the planning time fence.

Firming type  0  1  2  3  4 

MRP Types  M0  P1 

M1 

P2 

M2 

P3 

M3 

P4 

M4 

Firming Methods for Procurement Proposals in the Planning time fence 

No Firming of Procurement Proposals within

the planning time fence

X

Automatic Firming of Procurement Proposals

within the planning time fence

X X

Manual Firming of Procurement within the

planning time fence (No Automatic Firming of 

the procurement proposals )

X X

Treatment with New Order Proposals in the Planning time Fence 

Automatic Creation of New ProcurementProposals to cover the shortages within the

planning time fence. But the dates of these

new Procurement Proposals are pushed

outside the planning time fence

X X

No New Procurement Proposals created to X X

Page 16: SAP MRP Configuration

7/16/2019 SAP MRP Configuration

http://slidepdf.com/reader/full/sap-mrp-configuration 16/27

Cover the material shortages within the

planning time fence

c) Include External Requirements 

The inclusion of external requirements in net requirement calculations is available to be set, when you

are working with reorder point planning based MRP types. Actually there are 2 options in this field, i.e.,

include external requirements in the total planning horizon or restrict the inclusion of the external

requirements only within the replenishment lead time.

For example:

If the external requirements are set to be considered in the total horizon (of 7 weeks) then in the

today’s MRP run, the Customer demand will be considered as it falls in the planning horizon and it will

reduce the warehouse stock proportionately which would trigger the reorder point planning

procurement once the stock falls below the reorder point.

If the external requirements are set to be considered in the Replenishment lead time, let’s say the

Replenishment lead time is 1 week, then in that case, only in a MRP run triggered one week before the

start date of the external demand, this customer demand will be considered, thus triggering reduction in

warehouse stocks.

Fig MRP - Config 11 

SAP also offers an option to select the additional external requirements that should also be included in

the net requirement planning calculations like the - components supplied to the vendor in a

subcontracting case, reservations set for the components in a production order, reservations of 

components in plant maintenance orders, requirements to satisfy the Stock transfer order to anotherplant, stock transfer requisitions created for Stock transfer orders, requirements raised because of stock

transfer delivery schedules.

c) Forecasting for MRP 

Forecasting MRP Types have a “forecasting indicator” as obligatory, unlike other MRP types which

normally have the forecasting indicator set to optional.

Page 17: SAP MRP Configuration

7/16/2019 SAP MRP Configuration

http://slidepdf.com/reader/full/sap-mrp-configuration 17/27

Also the historical data is updated in the material master as total consumption (planned consumption

 plus unplanned consumption) or unplanned consumption. When the consumption is planned as per the

MRP reservations, planned consumption is updated and when the consumption is not planned as per

the reservation or is greater than the reservation quantities, then unplanned consumption is updated.

In MRP type configuration, you have an option of choosing the type of historical consumption of amaterial to be used for planning whether total consumption (planned + unplanned consumption) or

unplanned consumption.

After choosing the historical date type, you should configure, the type of forecast requirements to be

considered in MRP planning run, whether total consumption (planned + unplanned consumption) or

unplanned consumption.

The reduction method for forecast requirements is also configurable. The default is reduction by

consumption.

d) Planning method 

The MRP type offers you to plan the materials in an external system, like the MRP Type X0. The indicator

called the planning method allows you to choose external planning so as to plan materials in the

external system.

e) Automatic Calculations 

You can have the safety stock and the reorder point calculated automatically by the system, when you

are using the automatic reorder point planning methods. In the automatic calculations the system uses

the forecast data.

Configuring SAP MRP Scope of Planning for the Total Planning Run

Configuring SAP MRP Scope of Planning for the Total Planning Run 

SAP provides an option to plan multiple plants together or multiple MRP areas in one planning run in a

sequence. Transaction code OM0E can be used for configuration or the logical SAP path – SAP

Customizing Implementation Guide > Production > MRP > Planning > Define Scope of Planning for Total

Planning, can be used to configure.

Step 1 – Define the Name of the Scope of planning run

Step 2 – Define the plants or MRP areas to be included in the planning run arranged in a sequence. The

sequence is defined by the first field called

Configuring SAP MRP Planning time fence and Roll Forward Period

Configuring SAP MRP Planning time fence and Roll Forward Period 

Page 18: SAP MRP Configuration

7/16/2019 SAP MRP Configuration

http://slidepdf.com/reader/full/sap-mrp-configuration 18/27

The transaction path to configure the planning time fence and roll forward period is: SAP Customizing

Implementation Guide > Production > Material Requirements Planning > Planning > MRP Areas > MRP

Calculation > Define Planning Time Fence and Roll Forward Period

Planning Time Fence: 

The planning time fence is the number of work days, within which you can protect the master plan (or in

other words the procurement proposals of a master plan) from being disturbed or changed from any

automatic changes (of an MRP Run). The procurement proposals are firmed so as to protect them from

any changes. The firming of the procurement proposals (planned orders, purchase requisitions, delivery

schedules) in the planning time fence prevents the proposals in the time fence from being adopted in

the next planning run.

In other words, in the planning time fence, the system does not create or delete any procurement

proposals nor does it changes the existing proposals.

The system calculates the time fence from today’s date plus the “number of days mentioned as planningtime fence” in the material master or in the MRP configuration (where you can define the planning time

fence for plant or for a given MRP group). It is needless to say that any new requirements are not

included in this time period nor the existing requirements are changed. MRP carries its usual planning

outside this fence without interrupting this fenced period.

Configure Planning Time fence and Roll Forward Period

Plant MRP Group Planning Time fence Roll forward Period

0001 0001 14 3-

0001 0002 14 2-

It is logical that any procurement proposal lying outside this fence would start moving in to the fence

one by one; when the fence moves ahead on the time scale. When they move in to this fence, they are

automatically firmed for protection.

Firming for automatically created procurement proposals: 

The automatically created procurement proposals in the MRP Run are not firmed by the system, so that

they are available for adjusting dates and quantities in the next planning run, in cases where there is

change in BOM or task list.

You can though manually firm the planned orders individually or collectively using transaction code

MD19

Note - Automatically created planned orders in the planning time fence are only remain firm till they are

in the planning run.

Page 19: SAP MRP Configuration

7/16/2019 SAP MRP Configuration

http://slidepdf.com/reader/full/sap-mrp-configuration 19/27

Firming for manually created procurement proposals: 

For manually created or changed procurement proposals or even when you reschedule the planned

order in the graphical planning table, the system always marks them with a firming indicator. Though

you can remove or delete this firming indicator.

Firming for component’s planned orders: 

In case of a planned order, you can manually firm it by selecting the “firming planned order Indicator” in

the planned order header. And in order to make sure that the BOM levels below are not exploded or

changed in a planning run, you have to set the “firming components indicator”

See the below Example – Planning time fence is 3 days.

Planning

Start

Date 

Today – 

Day 1

Day 2 Day 3 Day 4 Day 5 Day 6 Day 7 Day 8

Planning time fence 

Planned

Order 1

Planned

Order 2

Planned

Order 3

Planned

Order 4

Planned

Order 5

Planned

Order 5

Planned

Order 6

Planned

Order 7

Auto

Firmed

Auto

Firmed

Auto

Firmed

Not-firmed Firmed Not-firmed Not-firmed Not-

firmed

Next

Planning

Start Date

Planning time fence 

Planned

Order 4

Planned

Order 5

Planned

Order 5

Auto Firmed Auto

Firmed

Auto

Firmed

Roll Forward Period 

The Roll Forward Period adds the functionality of automatic deletion of firmed planned orders, from the

master plan. It also creates new proposals to cover any requirements pending during the MRP run. This

Page 20: SAP MRP Configuration

7/16/2019 SAP MRP Configuration

http://slidepdf.com/reader/full/sap-mrp-configuration 20/27

period can be defined for number of days in past or future. The system deletes all the firmed planned

orders that lie before the roll forward period.

Using the roll forward period, you can have the system delete all useless old firmed planned orders,

which otherwise the system would never had deleted, since they were firmed. This allows for

reorganizing the planned orders.

Configuring SAP MRP Areas

Configuring SAP MRP Areas 

Long ago, SAP MRP was only at the plant level or at MRP controller level (activated through a user exit).

Then SAP came up with the concept of running MRP at MRP areas. You can define your own area for

which you want to run MRP without disturbing other areas.

Running MRP for MRP Areas: For running MRP at a MRP area, you would have to create a scope of 

planning in MRP configuration, which contain the MRP area or a set of MRP areas arranged in sequence

of planning.

Assigning MRP areas: To have the “MRP Areas” work, you have to activate the MRP areas and then

create them and then assign them to the material master MRP 1 view. If a MRP area is not assigned to

the material, then it will work as per the plant level MRP area.

Configuring MRP areas 

Step 1: Activate MRP Area: Use the transaction path: SAP Customizing Implementation Guide >

Production > Material Requirements Planning > Master Data > MRP Areas > Activate MRP for MRP Areas

Step 2: Define MRP Areas: Use transaction path: SAP Customizing Implementation Guide > Production >

Material Requirements Planning > Master Data > MRP Areas > Define MRP Areas

Types of MRP Areas: 

Plant MRP Areas: You can create one MRP area for several plants, so that when you run the MRP for this

MRP area, the run is for all the plants configured in the MRP area.

Storage Location MRP Areas: You can create MRP areas for several storage locations at a plant. You

cannot use one storage location in multiple MRP areas.

Subcontractors MRP Areas: You can create MRP areas for several subcontractors for a plant. You cannotuse one subcontractor in multiple MRP areas.

Configuring SAP MRP Dynamic Safety Stock (Range of coverage Profile)

Configuring SAP MRP Dynamic Safety Stock (Range of coverage Profile)

Page 21: SAP MRP Configuration

7/16/2019 SAP MRP Configuration

http://slidepdf.com/reader/full/sap-mrp-configuration 21/27

The Range of coverage profile is configured for the use of Dynamic safety stock for a given material. The

range of coverage configuration contains the parameters for the calculation of the dynamic safety stock.

The dynamic safety stock is a stock calculated based on the average daily requirements for a period

rather than the actual requirements over the period, therefore it is more statistical value rather than an

absolute value.

Safety stock as we know is used to cover the fluctuations in the requirements, so is the dynamic safety

stock, the only difference being, the safety stock is an absolute value provided directly for a material

whereas the dynamic safety stock is calculated by the system on the basis of the coverage period and

average daily stock calculated internally by the system.

The Dynamic safety stock is calculated in every planning run.

The transaction path is: SAP Customizing Implementation Guide > Production > Material Requirements

Planning > Planning > MRP Calculations > Define Range of Coverage Profile (Dynamic Safety Stock)

Range of coverage Configuration: 

Fig MRP - Config 12 

Configuration for calculation of average daily requirement for a period  

Period indicator - Indicate the type of period, whether week or month or according to PP planning

calendar. (Let’s say it is W – Week)

Number of Periods – Number of periods used to calculate the average daily requirements (Let’s say it is

13 Weeks)

Type of Period length – It defines the number of days in the period, if the period length is in terms of 

workdays, then the factory calendar work days are considered, if the period length is in terms of 

calendar days then it is considered in terms of Gregorian calendar, and if it is terms of standard days,

Page 22: SAP MRP Configuration

7/16/2019 SAP MRP Configuration

http://slidepdf.com/reader/full/sap-mrp-configuration 22/27

then you would have to enter the number of days in a period in the configuration (Let’s say that the

configuration was done with workdays and the factory calendar has 7 days per week)

Therefore Average daily requirement =

= Requirements in the period (Requirements in 13 Weeks – Lets say 910 Units) / (Number of Periods – 

Lets say 13 Weeks) * (Number of days in the period – Lets say 7 days)

= 910 / (13*7)

= 10 Units

Configuration parameters for calculation of Dynamic Safety Stock for the Range of Coverage

You can define 3 different range of coverage – minimum, maximum, and target range of coverage,

which is used to calculate 3 different stocks using the average daily requirements (range of coverage

multiplied by the period length). The Target range of coverage defined here would be used to calculate

the Dynamic Safety Stock for the period of the coverage.

The Period of the coverage is specified in the configuration. The coverage’s and the periods for which

they should work for, are defined for 2 separate period lengths and the 3rd period length is for the rest

of horizon.

In the example, we have defined the safety stock to cover a period of 7 days (minimum, target and the

maximum range of coverage). The minimum, target and the maximum stock is calculated for the

average daily requirement over the respective coverage periods.

You can check the minimum, maximum, target stock levels, minimum range of coverage, maximum

range of coverage, target range of coverage in the MRP List or Stock requirements list’s “Period Total

Display” Section.

As per our example, for the first period of 13 weeks, all the 3 stocks levels – minimum, maximum, and

target stock levels would be 70 Units and for the next period of 26 weeks it will be 70 units as well and

for the rest of the horizon it will be 70 units again.

Normally when the available stock falls below the minimum stock level, SAP planning run, would

immediately create planned orders to suffice at least the target stock level. For example if the minimum

stock level is 30 and the maximum is 80 and the target stock is 50 units, then if the available stocks fall

below the 30 units mark, SAP creates a procurement proposal for 50 units to reach back to the targetstock level. Whereas in the example below, all the 3 stocks types are 70 units, therefore when the stocks

fall below the 70 units, the system will try to raise a procurement proposal to reach back to 70 units.

As per our example in the configuration screen shot – 

Dynamic safety stock

formula summarized as

Dynamic safety stocks

 for the 1st period of 

Dynamic safety stocks

 for the 2nd period of 26

Dynamic safety stocks

 for the rest of the

Page 23: SAP MRP Configuration

7/16/2019 SAP MRP Configuration

http://slidepdf.com/reader/full/sap-mrp-configuration 23/27

= Average Daily Stock *

Range of coverage

13 weeks  weeks  Horizon 

Minimum safety stock 70 Units 70 Units 70 Units

Target safety stock 70 Units 70 Units 70 Units

Maximum safety stock 70 Units 70 Units 70 Units

Another Example of Dynamic Safety Stock

Fig MRP - Config 14 

Step a) Demand for 8 Weeks = 800

Step b) Average Daily Requirements

= 896 Units of Demand for 8 Weeks / (8Weeks * 7 Days Per Week)

= 896/(8*7)

= 896/56

= 16 Units

Step c) Calculation of Safety Stock for the coverage period

As per our example in the configuration screen shot – 

For the first period, when the stock falls below 32 units (minimum Stock Level), the SAP MRP run would

create the procurement proposals (Let’s Say planned order) for a quantity to suffice at least the target

safety stock level or the dynamic safety stock level = 8 Units.

Page 24: SAP MRP Configuration

7/16/2019 SAP MRP Configuration

http://slidepdf.com/reader/full/sap-mrp-configuration 24/27

Dynamic safety stock

formula summarized as

= Average Daily Stock *

Range of coverage

Dynamic safety stocks

 for the 1st period of 8 

weeks 

Dynamic safety stocks

 for the 2nd period of 8 

weeks 

Dynamic safety stocks

 for the rest of the

Horizon 

Minimum safety stock = 2 * 16 = 32 = 2 * 16 = 32 = 2 * 16 = 32

Target safety stock = 5 * 16 = 80 = 5 * 16 = 80 = 5 * 16 = 80

Maximum safety stock = 7 * 16 = 112 = 7 * 16 = 112 = 7 * 16 = 112

Configuring SAP MRP Day's Supply and Receipt Day's Supply

Configuring SAP MRP Day's Supply and Receipt Day's Supply

The days of supply is not a mandatory configuration, you can only configure the days supply if you feel

the SAP pre-configured ones are not what you want.

SAP offers 2 types of evaluations in SAP, the days supply and the receipt day’s supply.

In the SAP MRP Evaluation transactions such as stock requirement list or MRP list, the days supply would

calculate the number of days on the time axis, till the material requirements can be satisfied purely by

the current available stock.

While the Receipt Day’s supply would indicate how long would the current stock and the expected

receipts would cover the requirements. There are 2 receipt day’s supply evaluations offered by SAP

called as the receipt day’s supply 1 and receipt days supply 2. SAP offers a configuration to select the

receipts elements for receipt day supply 1 and 2 evaluations. There is also an option to have the receipt

day’s supplies to be calculated when the stocks fall below the safety stock or below the current available

stocks.

The days supply values or the receipt days supply values can be correlated with the range of coverage

concept. These tools comes with traffic lights – red, yellow and green which offer warnings to the MRP

Controllers/users and lets him/her strategically know when the material stock would be totally

consumed out, which would help the planner to foresight and take necessary actions in advance.

The transaction path for the same is SAP Customizing Implementation Guide > Production > Material

Requirements Planning > Evaluations > Define Receipt Elements for Receipt Days' Supply

Page 25: SAP MRP Configuration

7/16/2019 SAP MRP Configuration

http://slidepdf.com/reader/full/sap-mrp-configuration 25/27

 

Fig MRP - Config 13 

Number of Days Stocks will Cover the Requirements  Day’s Supply   Receipt 

Day’sSupply 1 

Receipt 

Day’s Supply 2 

Consider Current Stocks only in calculation of Days Supply 

Only Consider Current available Stocks to cover

Requirements

X

Consider Receipts also along with Current Stock in Calculation of Days Supply 

Firmed Planned orders, Planned orders assigned with Production versions, Purchase orders, Schedule

lines, Firmed Purchase Requisitions, Receipt Reservations, Shipping Notifications

Consider all the possible receipt elements along with

the plant stock

Example – Firmed Planned orders, Planned orders

assigned with Production versions, Purchase orders,

Schedule lines, Firmed Purchase Requisitions, Receipt

Reservations,

X

Consider all the Most Certain receipt elements along

with the plant stock

Example - Production order, Shipping Notifications, QM

Inspection Lots

X

Example for Days Supply and Receipt Days Supply: 

Page 26: SAP MRP Configuration

7/16/2019 SAP MRP Configuration

http://slidepdf.com/reader/full/sap-mrp-configuration 26/27

Days’ Supply for Material M1 on Today = 3 days 

(Receipts are not considered)

Day  Requirements  Available Qty  Stock Balance Left after covering

Requirements 

Today - 20 Current Stock = 100 100 – 20 = 80

2nd

Day - 30 Stock Available = 80 80 – 30 = 50

3rd

Day - 50 Stock Available = 50 50 – 50 = 0 (Stock = 0) 

4th

Day - 52

5th

Day - 40

6th

Day - 20

Days’ Supply on Today = Coverage’s Considering without the receipts = 3 Days Exactly

Receipts Days’ Supply for Material M1 on Today = A little more than 4 days 

(Receipts are also considered – This example can be for Receipt Days supply 1 or 2)

Day  Reqmts  Expected Receipts  Available Stock  Stock Balance Left

after covering

Requirements 

Today - 20 Firmed Planned order = 10

Production order = 5

Total Receipts on day = 15 

Available = 100 (100 + 15) -20 = 95

2nd

 

Day

- 30 Total Receipts on day = 0 Available = 95 (95 + 0 ) – 30 = 65

3rd

 

Day

- 50 Production order = 25

Total Receipts on day = 25 

Available = 65 (65 + 25) – 50 = 40

4th 

Day 

- 47 Planned order = 8

Production order = 5

Total Receipts on day = 13 

Available = 40 (40 + 13) – 47 = 6

Page 27: SAP MRP Configuration

7/16/2019 SAP MRP Configuration

http://slidepdf.com/reader/full/sap-mrp-configuration 27/27

5th

 

Day

- 40 Planned order = 5

Total Receipts on day = 0 

Available = 6 (1 + 5) – 40 = - 34 

Shortage 

6th

 

Day

- 20

Receipt Day’s Supply on Today = Coverage’s Considering the receipts

= 5 – 1 + (6/40) = 4 + 0.15 = 4.15 Days

Next Step >>> Creation of Material Master MRP Views and Assignment of MRP Types