saso certificate for saudi arabia power-plant projects stephan ghys , logistics manager
DESCRIPTION
SASO certificate for Saudi Arabia Power-Plant projects Stephan Ghys , Logistics Manager Research-Cottrell Dry Cooling CCBLA – Antwerp, 24 Sept 2013. Introduction to Hamon. International, leading engineering & contracting company, with headquarters in Belgium Founded in 1904 - PowerPoint PPT PresentationTRANSCRIPT
SASO certificate for Saudi Arabia Power-Plant projects
Stephan Ghys, Logistics ManagerResearch-Cottrell Dry Cooling
CCBLA – Antwerp, 24 Sept 2013
Introduction to Hamon
International, leading engineering & contracting company, with headquarters in Belgium
Founded in 1904
Listed on Brussels stock exchange (Euronext) since 1997
Among the leaders in its niche markets
Well established business with strong reputation and large installed base
International organisation
A worldwide industrial network with approx. 40 subsidiaries: branches, representative offices, licensees, and joint-ventures.
A presence in 25 countries, spread over 5 continents.
More than 50.000 references in 90 countries.
Air Quality SystemsHeat Recovery
Dust emission controlFlue gas treatment
(deNOx, deSOx, …)
ChimneysSilos
LinersDucts
Cooling SystemsNatural draftMechanical draftWet/dry systems
Process Heat ExchangersAircoolersFinned tubesHairpin HE
44%
15%
16%
18%
7%
Sales 2012
Major Player in engineering & contracting
Hamon Thermal Wet Cooling Natural draft CTFan assisted natural draft CTMechanical draft CTPlume abated (Wet/Dry –
Hybrid)
Research-Cottrell Dry CoolingIndirect – jet condenserIndirect – surface condenserDirect – air cooled condenser
(ACC)Direct – natural draft air cooled
condenser
Cooling Systems
PP 10, Saudi Arabia, 10 X 350 MW
Research-Cottrell Dry Cooling
SEC No. of Streets (per ACC) 5
Power Generation 10 units each of 350 MW No. of Modules (per ACC) 20
Thermal Duty 10 ACC each of 299 MW Fan 36 ft diameter
Total Steam Flow (per ACC)
143.50 kg/s Rating of Fan Motor 185 kW
Turbine back pressure 351 mbar Atmospheric pressure 955.30 mbar
Air Temperature 50 °C Dimension ACC (w x l) 12,9 m x 14,9 m
Noise Power Level 119 DB(A) Delivery and completion 2013 and 2014
PP10 + PP12
PP10 : Volume in containers (FOB): 824
PP10 : Volume in shipments : 180 PP12 : 340 cont + 60 shipments
TIANJIN 560 x 40' OTQINGDAO 40 x 40' DCVIGO 30 x 40' OTMUMBAI 50 x 40'HCANTWERP 140 x 40' HC/OTLIVORNO 4 x 40"OT
Grand total (est) 824
Starting Point
1. Contractual condition: « Conformity certificate with Saudi standards, issued and signed by inspection agent assigned by SASO. » (Saudi Arabian Standards Organization.)
2. L/C condition: idem + « The agent is INTERTEK. »
Sept 2012: meeting INTERTEK France + SGS Belgium
Registration
How did we obtain the SASO Certificate of Conformity ?
Step 1. Registration of products All products Per supplier or per product ? Divided into 25 families: gearbox, motor, fans, bundles, valves, … PO: ‘Supplier has to deliver all documentation necessary for
obtention CoC enabling product to be imported in S-A.’ ISO-certificates – Test reports – Techical data sheets
Step 2. Inspection of products
When? Pre-shipment , in crates
What? Country of Origin + TAG-plate markings
Important: Irremovable engravement of Country of Origin on each product Only 1 Country of Origin per crate
Inspection
Operation
In practice?
Supplier: Cargo is ready RCDC: « Request for Certification + Declaration of
Conformity » + ProForma Invoice + Packing List SGS: Visual Inspection of Tag-plates + Country of Origin SGS: Draft + Issue Certificate of Conformity
Conclusion
Essential:
Start on time ! Be strict to avoid blocked containers Country Of Origin markings Partnership