s.cholette, based on mcgraw-hill/irwin managing risk

42
S.Cholette, based on McGraw-Hill/Irwin Managing Risk Managing Risk

Upload: kathlyn-smith

Post on 28-Dec-2015

217 views

Category:

Documents


1 download

TRANSCRIPT

S.Cholette, based on McGraw-Hill/Irwin

Managing Risk

Managing Risk

7-2

7-3

Risk Management Process

Risk Management Process

7-4

The Risk Event Graph

FIGURE 7.1

7-5

Risk Management’s Benefits

Risk Management’s Benefits

7-6

The Risk Managemen

t Process:a 4 Step Program

FIGURE 7.2

7-7

Managing Risk

Managing Risk

7-8

Partial Risk Profile for Product Development Project

FIGURE 7.3

7-9

Risk Breakdown Structure

7-10

Risk Assessment Form:A Typical Example

FIGURE 7.4

Detection Difficulty is a misnomer- better to consider it as “ability to mitigate/avoid upon discovering the problem” before having to resort to a full blown contingency planAlthough the text shows how to calculate “risk value” by multiplying these numbers together, be cautious about relying on such an arbitrary measure

7-11

Impact Scales- One Example

7-12

Risk Severity Matrix- an example

FIGURE 7.5

7-13

Managing Risk

Managing Risk

7-14

Contingency Planning

Contingency Planning

7-15

Sample Risk Response Matrix

FIGURE 7.7

Note: although unclear from this text example the Detailed Response Strategy and Contingency Plans are not the same thing.We might Reduce the chance of User Backlash by designing a more user-friendly interface. But, if we fail to do that, our Contingency Plan is to have a large support staff help frustrated users navigate

7-16

Risk and Contingency Planning

Risk and Contingency Planning

7-17

Contingency Funding and Time Buffers

Contingency Funding and Time Buffers

7-18

Contingency Fund Estimate-Sample

TABLE 7.1

Figures in 000’s $Note: the Management Reserve is too small for my comfort

7-19

Managing Risk (cont’d)Managing Risk (cont’d)

7-20

Risk Goes Hand in

Hand with…

7-21

Change Management Control

Change Management Control

“Your prototype looks great, but can we use a web interface instead?”

Err, I guess so, but…

7-22

Change Management Control

Change Management Control

7-23

The Change Control Process

FIGURE 7.8

7-24

Benefits of a Change Control System

Benefits of a Change Control System

7-25

What is the difference between avoiding a risk and accepting a risk ?

What is the difference between mitigating a risk and contingency planning ?

What are th likely outcomes if a change control process is not used ? If a change control log is not used ?

7-26

Change Request

Form: Sample

FIGURE 7.9

7-27

Change Request

Log: Sample

FIGURE 7.10

7-28

One way of incorporating Risk Planning:PERT—Program Evaluation Review Technique

One way of incorporating Risk Planning:PERT—Program Evaluation Review Technique

7-29

Activity and Project Frequency Distributions

FIGURE A7.1

Why might activity distributions look so skewed?Even with such skewed activity distributions, why is the overall Project distribution symmetric?

7-30

Activity Time Calculations

The weighted average activity time is computed by the following formula:

(7.1)

7-31

Activity Time Calculations (cont’d)

The variability in the activity time estimates is approximated by the following equations:

The standard deviation for the activity:

The standard deviation for the project:

Note the standard deviation of the activity is squared in this equation; this is also called variance. This sum includes only activities on the critical path(s) or path being reviewed.

(7.2)

(7.3)

t

7-32

Example Given the following activities, expected durations and

predecessor information, construct the AoN project network and use the CPM.

a5,a45a6

a36a5

a216a4

a120a3

a113a2

---30a1

predecessorsdurationActivity

7-33

Activity Times and Variances

TABLE A7.1

7-34

Probability of Completing the Project

The equation below is used to compute the “Z” value found in statistical tables (Z = number of standard deviations from the mean), which, in turn, tells the probability of completing the project in the time specified.

(7.4)

7-35

Text Example

Consider the following 6-activity project Draw the AoN and use the CPM to compute the CP, slack Use PERT to analyze the chance the delays on CP activities

does not push the project duration beyond 67 days. Anything else we should consider?

Activity a m b te=(a+b+4m)/6 var=((b-a)/6)^2a1 17 29 47 30 25a2 6 12 24 13 9a3 16 19 28 20 4a4 13 16 19 16 1a5 2 5 14 6 4a6 2 5 8 5 1

7-36

Example: Network, CP, Slack

FIGURE A7.2 (cont’d)

a1

a3 a5

a6

a4a2

7-37

PERT, Considering the CPActivity a m b te=(a+b+4m)/6 var=((b-a)/6) 2̂a1 17 29 47 30 25a2 6 12 24 13 9a3 16 19 28 20 4a4 13 16 19 16 1a5 2 5 14 6 4a6 2 5 8 5 1

nice they div ide by 6! ev en nicer the sqrts are integer!

CPMpaths a1->a2->a4->a6 64 thus this is the critical path

a1->a3->a5->a6 61 total slack = 3

Giv en a scheduled time: Ts 67

Chance project (considering CP) is less:stdev(path) =sqrt( sum var(path) 6.00 still integer-w heee!

z = (Ts-Te)/stdev(Cpath) 0.5so prob = 69% is the chance w e are not later than the scheduled time, considering the CP.

7-38

Example: Possible Project Duration

FIGURE A7.3

7-39

Some Sample Z Values

TABLE A7.3

A z-table listing such values will be provided to you on exams

7-40

What Might We Have Forgotten? In the CPM, it is clear what the critical path is! With PERT we can now consider network sensitivity in

more detail. Extension of the textbook example- what additional analysis

would you do?

7-41

PERT: Caveats Abound For checking project duration considering multiple paths,

it’s not as simple as adding up the probabilities. Different paths usually have some activities in common. Once again, the whole assumption of independence of activity

durations must be considered.

For complex or high-value projects, Monte Carlo simulation is often a more appropriate approach. Beyond scope of this class, take DS851 or DS852 for more!

7-42

Group Exercise Sample question from a DS856 final exam: Use

the following table and a desired completion of 60 days

What is the likelihood that the CP exceeds 60 days?, How do PERT calculations differ from that of CPM, using the “most likely” time?

What should the PM worry about tracking besides CP activities? What doesn’t the PM need to worry about?

Activity predecessor a m bA none 8 10 12B A 5 7 9C B 10 15 20D A 10 15 50E A 18 18 18F C,E,F 20 22 42