STA CLARA International CO. W.L.L.

General & Technical Capabilities

PROFILE

Rafea Bin Salama Street , Nuaija East , Al Hilal –Doha Qatar , P.O.Box-8325 , Office Tel. 44672785 Fax : 44567549

Email : [email protected] Website : www.staclaraqatar.com

STA . CLARA International Co. W.L.L.

Committed to Continual Improvement

COMPANY PROFILE

Committed to Continual Improvement

The role of STA. CLARA INT’L CO. W.L.L. Group is to ensure that all of ourstakeholders benefit from our continued growth, development and success. Key tothis is to further build and capitalize on the strengths accruing from our ongoingdiversification activities.

Our responsibility, therefore, is to be actively involved in setting and overseeingthe implementation of strategic plans, financial policies and fund allocations,ensuring that our activities yield positive growth, developing technical expertiseand managing the competency of our main business core.

Our commitment to succeed is underpinned by our core values: over the past 34years we have built stability, created exponential efficiencies and group-widesynergies. Our standards-approved products and services and our numerousinternational joint ventures partnerships and value acquisitions, along withbusiness enabling technology, have resulted in an enhanced customer offering.Sound management principles, a customer-focused vision and the dedication,support and commitment of our numerous strong workforce help drive ourbusiness and industry and position us as leaders at local and international levels.

Our adherence to these principles has earned us the trust, confidence and respectof our customers. We contemplate the future with the same dedication andcommitment.

We practice our core values and communicate them to all our stakeholdersevery day:

Honesty & Integrity - We believe goodwill and good reputation is core toour business. We uphold Honesty, Integrity, Professionalism and a high levelof business ethics. We observe prudence and fairness in dealings with ourstakeholders.Customer & Excellence - We are diligent about understanding and fulfillingour customers' needs. We strive to please our customers with excellence inquality and services. We listen to our customers and 'go the extra mile' tosatisfy them.Innovation & Change - We are passionate about meaningful innovation.We are a learning organization. We learn from our experiences and global bestpractices, and we innovate to create leading local solutions leveraging onworld-class knowledge. We embrace positive change brought forth byinnovation and aspirations to grow our business.Leadership & Prudence - We cultivate talent and leadership to createsound business solutions, to best meet our customer needs, and to developmarkets, people and shareholder value. We do so by optimizing use of funds,resources, materials, and technologies. We build prudence and cost-effectiveness in our leadership culture passing on benefits to our customers.

ENGR. LYDIO R. RANON

Deputy General Manager Message :

About us• With Limited Liability type of Organization ( 51% Qatari / 49 % Filipino )

• 34 years of solid experience in construction

STA. CLARA INT’L CO. W.L.L.. is one of the leading Engineering andMain Contracting Group operating worldwide in the Oil, Gas &Petrochemicals, Power, Infrastructure and Civil Engineering sectors.. TheGroup’s reputation and success have been achieved because of itsstrong technology orientation and advanced skills in ProjectManagement, Engineering, Procurement and Construction (EPC)services for the implementation of complex projects worldwide. It hasdeveloped and demonstrated major expertise in Horizontal DirectionalDrilling activities, and managing medium EPC projects on a turnkeybasis in different countries and regions. The Group combines high qualityand planning standards with a focus on multicultural and environmentalissues.

Specifically, STA. CLARA can offer: market research services andfeasibility studies; design and engineering services; site management;works execution; systems start up; technical assistance to operationsand maintenance subsequent to start up; and customer personneltraining.

Committed to Continual Improvement

Committed to Continual Improvement

Areas of Operation

Petrochemical Industries

Refineries ( Oil & Gas )

Fertilizer Industry

Transmission and Distribution Substation

Power Generating Plants and Facilities

Polymers Plastics

Offsite and Utilities

Commercial & Residential Buildings & Factories

Roads & Bridges

General Facility Maintenance

Committed to Continual Improvement

Activities

Civil and Architectural Works Projects

Horizontal Directional Drilling Works Projects

Electrical Works Division

Mechanical Works Division

Heating, Ventilation and Air-Conditioning Division

Surface Preparation for all Types of Materials

Facility Maintenance

Professional & Technical Manpower Support

Services Division

Field of Expertise

Committed to Continual Improvement

Construction of Overhead Power Lines

High Voltage Cable Installation

Transformer Installation

Street Lightings Installation

Low Voltage Cable Installation

Cable Splicing, Test & Commissioning

Ground System Installations

Electrical Works Division

Committed to Continual Improvement

General RTR/PVC Piping for Sewage & Fire Water

PVC Piping for Potable Water Distribution System

Installation of Pump Equipments, Blowers and Fans

System Testing and Commissioning

Installation of Steel Pipe conduit for Hydro Power

Projects

Mechanical Works Division

Committed to Continual Improvement

Installation of Chiller-Type System

Installation of Split-Type Unit

Testing, Balancing and Commissioning

Heating, Ventilation & Air-Conditioning

Committed to Continual Improvement

Grit Blasting

Garnett Blasting

Sand Blasting

Surface Preparation for all Types of Materials

Committed to Continual Improvement

All types of AC Units including Package Unit

All types of Electrical Equipment & Appliances

All types of Architectural Finishing

All types of Plumbing and Mech. Equipment.

Facility Maintenance

Committed to Continual Improvement

Committed to Continual Improvement

General ManagerMr. Nobukazu Kotake

A.V.P. Mktg./ Buss. Dev.

Engr. Gary Lopez

HR/Admin. Mngr.Mr. Joseph Tolentino

Purchasing Dept. Mngr.

Finance & Accts . Mngr.

Managing DirectorMR. NICANDRO G. LINAO

Warehouse Controller

Projects & Estimation Dept.

Construction Dept.

Deputy General Manager

Engr. Lydio R. Ranon

Logistics

Project Management Team

Engineering Mngr.QA/QC HSE

Mngr.

ORGANIZATIONAL CHART

Support Services Dept.

Mngr.

Staff MixSupervisors

& Technicians

56%

Support Staff

9%Professional

31%

Middle Management

3%

Top Management

1%

Committed to Continual Improvement

On-Going Service Contracts for HDD Projects & Techno-Professional Manpower Support Services Contracts @

Doha Qatar Geographic territory

S/N

Client Description of Work Location

Contract Duration

From To

1. PUNJLLOYD LTD. Horizontal Directional Drilling for Power Cables

Abu Nakla Umm AlAFAI

07-2010

12-2010

2. ETA STAR HDD for Power Cables MESAIEED 07-2010

09-2010

3. SIEMENS LTD. HDD for Power Cables

Al KhorAirport Road ,

NAEEJA West.

06-2010 -

4.TECHNICAL CADRES CONTRACTING

HDD for Power Cables AL KHOR 07-2010 -

5. STFA MARINE CONSTRUCTION

Complete Civil Works for 33KV Cable Route .Fire Water and Service Water Line Installation

MESAIEED 05-2010

Committed to Continual Improvement

Completed Construction Projects Civil Works ( Trenching & H.D.D. )

S/N

Client Description of Work LocationDate of

Completion

1.HELIOPOLIS

ELECTRIC COMPANY

Horizontal Directional Drilling for GTC/124/2006D - Completion of several Crossings located in Mai-ther Area.

QATAR June 2007

2. CEPCO

HDD for GTC/14/2003 & GTC/22/2004 - Completion of several crossings passing thru Qatar Petroleum Gas Pipe line.

QATAR June 2006

3. QATAR BUILDING COMPANY

HDD for GTC/117/2006 –Completion of road crossings covering route from NDIA and Ras Abu Fontas S/S .

QATAR January 2008

4. MITSUBISHI CORPORATION

HDD for GTC/22/2004 –Completion of all civil related works for the road crossings.

QATAR Sept. 2006

5. SIEMENS LTD.

CIVIL WORKS for GTC/123/2006 –Completion of all civil works for High voltage cabling at Wakrah-2 S/S and Abu Hamour S/S.

QATAR November 2009

6. ETA STAR L.L.C.

Civil works for GTC/142B/2006 Completion of Civil works for 66KV High Voltage Power Cables for Cable route between Doha Super S/S to Musherib-2 S/S. Civil Works for GTC/142B/2006 Complete Civil Works for 66KV extra High Voltage Power cables for route between Al-Wajbah Super S/S to Rayyan West S/S.

QATAR June 2010

7.STFA MARINE

CONSTRUCTION COMPANY

Civil Works for GC 07106000 –Epic for Gabbro Berth Expansion Package 1 at Masaieed Port.

QATAR January 2010

8. UNICON LIMITED HDD for GTC/148/2007 ( provision of Water Network at Doha Qatar North Areas Phase 11.

QATAR March 2010

Completed Construction Projects Civil Works ( Trenching & H.D.D. )

S/N

Client Description of Work Location

Date of Completion

1.STFA MARINE

CONSTRUCTION COMPANY

GTC 08112800 –EPIC for Container Terminal ( Berth 7 ) at MESAIEED Port .

QATAR June 2010

2.. KONSTRUKTOR –Engineering d.d.

Construction of Micro-Tunneling permanent shafts . QATAR On-going

STA. CLARA INTL, WLL

CR NUMBER: 34771

OFFICE ADDRESS:

P.O. BOX: 8325 - DOHA, QATAR

The Qatar branch was established June 2004and the main activity is HorizontalDirectional Drilling (HDD) forunderground pipes and cables. It has eight (8)drilling rigs, various support equipment and all-Filipino crew.

HDD for GTC/124/2006D (QATAR)

(Left)

Client: HELIOPOLIS ELECTRIC COMPANY

Sta. Clara has completed several crossings under Heliopolis Electric Company for the GTC/124/2006 project. Most of the crossings are located in Maither Area.

The bore size is 450mmØ with each bore consisting of 3-160mmØ + 1-90mmØ HDPE pipes.

HDD for GTC/14/2003 & GTC/22/2004

(Left) (QATAR)

Client:CEPCO

The GTC/14/2003project involves severalcrossings passing thruQP Gas Pipe line. Due tolimited space in someareas to launch thedrilling from the groundsurface, the machinehas to be lowered to thebottom of the pit usingcrane .

HDD for GTC/117/2006 (QATAR)

(Right)

Client: QATAR BUILDING COMPANY

Sta.Clara has completed the road crossings

covering the route from NDIA and Ras Abu Fontas s/s of

GTC/117/2006. The bore diameter is

minimum of 600mmØ consisting of 3-250mmØ + 2-110mmØ HDPE.

HDD for GTC/22/2004 (QATAR)

(Right)

Client: MITSUBISHI CORPORATION

GTC/57/2005 projectcovers the route from DNSs/s to POG. All civil relatedworks for the roadcrossings are part of Sta.Clara’s scope. The workincludes the provision ofBentonite grout to fill theannulus between HDPEpipes and the borehole.

CIVIL Works for GTC/123/2006 (QATAR)

(Right)

Client: SIEMENS LTD.

Sta. Clara hascompleted all civil worksfor high voltage cabling atWakrah-2 substation andAbu Hamour substationModification.

CIVIL Works for GTC/142B/2006(QATAR) (Top and Right)

Client: ETA STAR L.L.C.

Sta. Clara has completed the complete civil works for66kV Extra High Voltage power cables for the cable routebetween Doha Super substation to Musherib-2substation.

CIVIL Works for GTC/142B/2006 (QATAR)

(Top and Left)

Client: ETA STAR L.L.C.

The GTC/142B/2006 Project involves complete civil works for 66kV Extra High Voltage power cables for the cable route between Al-Wajbah Super substation to Rayyan West substation.

CIVIL Works for GC 07106000 (Epic for Gabbro Berth Expansion, Package I at Mesaieed Port, Qatar)

Client:

STFA MARINE CONSTRUCTION COMPANY

Sta. Clara has completed all civil works of 11kV cable route from MIC-3 substation to Substation—9 and Substation-1.

HDD for GTC/148/2007 (Provision of Water Network at Doha and Qatar

North Areas—Phase II)

(Client: UNICON LIMITED

Sta. Clara has completed the provision of holes for 600mmØ water pipeline by

Horizontal Directional Drilling.

HDD for GTC/124/2006D (QATAR)

(Left)

Client: HELIOPOLIS ELECTRIC COMPANY

Sta. Clara has completedseveral crossings underHeliopolis Electric companyfor the GTC/124/2006project. Most of thecrossings are located inMai-ther Area. The boresize is 450mmØ with eachbore consisting of 3-16mmØ + 1-90mmØ HDPEpipes.

HDD for GTC/124/2006D (QATAR)

(Above)

Client: HELIOPOLIS ELECTRIC COMPANY

The crossing s are located between Dukhan road Super s/s and Al Wajba Super s/s. Ground condition inthese areas are extremely hard requiring top of the line tooling for successful drilling.

RLOC-MCC-EP2-0024 PIPELINE (QATAR)

(Above & Below)

Client : PUNJLLOYD

Epic for Multi-product Pipeline from QP Refinery to Doha Depot. The work covers the installation of 18inches steel pipes with 1.5 inches thick concrete coating by HDD Method.

GTC 08112800—EPIC FOR CONTAINER TERMINAL (BERTH 7) AT MESAIEED

PORT, QATAR Client: stfa MARINE CONSTRUCTION COMPANY

Completed 33kV Cable distribution network from MIC to Container Berth No. 7 Substation.

ERC 1400/D20/C2—INDUSTRIAL INTERCHANGE, PACKAGE 3

(Above) Client: KONSTRUKTOR—ENGINEERING d.d., Qatar

Construction of micro-tunneling permanent shafts.

Completed Construction projects( Buildings & Factories )

S/N Client Description of Work Location

Date of Completion

10. Monde M.Y. San Corp. Construction of 3 storey bldg. and Biscuit Manufacturing Plant with a Total Floor Area = 62,665 m2.

CalmelrayIndustrial

park , Calamba

City Philippines

April 2009

11. (SCIC)

Construction of Highway 54 Plaza Bldg. ( 3 storey commercial bldg. with Total floor area of 2,810 m2.

EDSAMandaluyong

PhilippinesApril 2006

12.MONDE NISSIN

NOODLEPLANT

Construction of 4 storey , 30,000 square meters Plant

Sta Rosa Laguna

Philippines

August 2005

13. ODEON TERMINAL MALL

Construction of 3 storey , 4,851 m2

Commercial bldg. complex .MANILA

Philippines January

2005

14. SANKYO SEIKI FACTORY BLDG.

Construction of 3 storey Factory Bldg. comprises 40,000 m2

Subic Free Port

Philippines Oct. 2001

15. NISSAN MOTOR PHILIPPINES INC.

Construction of 7,662 square meters Spare Parts Building .

Sta Rosa Laguna

Philippines July 1995

MONDE M.Y. SAN MANUFACTURING FACILITY = PHILIPPINES(Below)Completed: April 2009This major project of Monde M.Y. San Corporation is located in Calmelray Industrial Park at CalambaCity, Laguna. It is a three (3)-storey office building and a biscuit manufacturing plant with a total floorarea of 62,665 square meters.

Project Value : PHP 654,205,820.00 ( USD $ 14,537,907.11 )

HIGHWAY 54 PLAZA (Left) Completed: Aug 2006Strategically located alongEpifanio delos SantosAvenue (EDSA), inMandaluyong City, thisnewly built 3-storeycommercial building has atotal floor area of 2,810square meters, with a bigparking area in front. Ithouses the corporate officeof Sta. Clara InternationalCorp.Project Value:PHP 152,720,455.00

or( USD $ 3,393,787.89 )

COMMERCIAL BUILDINGS & FACTORIES

MONDE NISSIN NOODLE PLANT (Right)

Completed: Aug 2005

This 4-storey 30,000 square meters plant is the most modern noodle-making plant in the Philippines. Located in Sta. Rosa, Laguna, it manufactures the famous Lucky Me! noodles brand.

CONTRACT VALUE :

PHP 282,740,646.00 or

( USD $ 6,283,125.47 )

ODEON TERMINAL MALL (Right)

Completed: Jan 2005

The formerly Odeon Theatre, a famous landmark in downtown Manila is now converted to a 3-storey, 4,851 square meters commercial building complex.

CONTRACT VALUE :

PHP 55,864,372.00or

( USD $ 1,241,430.50 )

COMMERCIAL BUILDINGS & FACTORIES

SANKYO SEIKI FACTORY BLDG (Left)

Completed: Oct 2001

This 3-storey factory building comprises 40,000 square meters; 2 stories comprise the production space and the other floor is used for warehousing. This is located in Subic Freeport.

CONTRACT VALUE :

PHP 117,885,442.00or

( USD $ 2,619,676.49 )

NISSAN MOTOR PHILIPPINES SPARE PARTS BUILDING (Right)

Completed: July 1995

Nissan Philippines, Inc. housed a training facility, spare parts center and a canteen for employees use on a 7,662 square meters building. Initial site development works were completed in the 18.3 hectares site in StaRosa, Laguna.

CONTRACT VALUE :PHP 115,482,592.00

or( USD $ 2,566,280.00 )

COMMERCIAL BUILDINGS & FACTORIES

S/N

Client Description of Work Location

Date of Completion

1. NATIONAL POWER CORPORATION

KALAYAAN UNDERGROUND PENSTOCK

KalayaanLaguna

Philippines

April 2002

2.NPC – BAKUN AC HYDRO POWER –BAKUN BENGUET

Construction of Twin Underground de-sander chambers - works include installation of 1.20 kilometer steel liner , excavation & concreting.

BakunBenguet

Philippines

August 2004

3. SBMA

Construction of Tunnel along 2 lane 8.5 kilometers expressway toll road going to Subic Bay Free Port,.

ZambalesPhilippine

sJune 1997

Completed Construction projects( TUNNELING )

KALAYAAN UNDERGROUND PENSTOCK Completed: April 2002

A major part of the Kalayaan II Hydro-Electric PowerPlant Penstock System is the underground penstockconsisting of among others the 154m long x 90mdiameter inclined shaft, the 100m long x 4.5m x 5maccess adit, two (2) units of 24 meter long x 3.5m x3m penstock galleries and the 36m x 14m highbifurcation cavern.

TUNNELING

S/N

Client Description of Work Location

Date of Completion

1.MACO TAILINGS MANAGEMENT

FACILITY

Installation of 8,300 square meters (HDPE) liner

MindanaoPhilippine

s July 2008

2.NATIONAL

IRRIGATION AUTHORITY

CASECNAN MULTI-PURPOSE IRRIGATION AND POWER PROJECT ( CMIPP-IC-S1 )Construction of an eight barrel intake structure and 11 kilometers concrete-lined canals. It aimed to irrigate a combined area of 137,500 hectares of farmlands .

RizalNueva Ecija

Philippines

November 2005

3. NATIONAL POWER CORPORATION

Plugging & Concreting of NPC’s CALIRAYA Service Spillway .

CalirayaLaguna

Philippines

May 2006

4. NPC

LAOAG RIVER BASIN FLOOD CONTROL & SABO PROJECT – 6.9 kilometer earth dike with dry boulder riprap slope protection works .

LaoagRiverIlocosNorte

Philippines

March 2007

5. NPC

AGNO ALLIED RIVERS URGENT REHABILITATION and REVETMENT Works Site : AG-126,133 B,C,D,E & HAccomplished a total of 6.77 kilometers of River Banks protection works

UrbiztndoPangasina

nPhilippine

s

August 2001

6. NPC Construction of TAMBANGAN DAM AND IRRIGATION FACILITIES .

Sta Cruz Marinduqu

ePhilippine

s

February 1994

Completed Construction projects( DAMS IRRIGATION , RESERVOIR ,& FLOOD CONTROL)

CBK HYDRO POWER PROJECT (Top)Completed: August 2004

This hydro power project is located in Lumban, Laguna, 104 kilometers south of Manila. Contracted works include the construction of the New Caliraya Dam & Spillway, the rehabilitation of Botocan hydro electric power plant, improvement of various existing tunnels and construction of various access road.

PLUGGING AND CONCRETING OF NPC’S CALIRAYA SERVICE SPILLWAY (Top and Left)

Completed: May 2006

The existing approximately 0.20 kilometer Caliraya service spillway was plugged with concrete and closed to operations. A new spillway was constructed, completed and opened up.

DAMS, IRRIGATION, RESERVOIR & FLOOD CONTROL

S/N

Client Description of Work Location

Date of Completion

1. NLEX

Construction of SUBIC-CLARK-TARLAC EXPRESSWAY Embankment of 1.2 million cubic meters laharfor th 8 kilometers section including base course, cement treated base , and 8 RCDG Bridges , 2 underpasses , drainage structures & slope protection works.

Subic, Clark , &

TarlacExpresswa

yPhilippines

12/2006

2. MOJON

Construction of MOJON Bridge,RCDG 5 Span Bridge , 175 long x 6.7m approach road, including river bank & slope protection works.

Rural Roads in Visayas

Philippines

12/2006

3 Metro-Rail Transit

MRT Station 10 , 3 Level 2,800 sq. meters structures , a 3 Kilometer Track Rails , Construction of Concrete Plinth including rail installation of elevated guide way. Also included installation of ballasted Track ( bottom and Top Ballast , pc sleepers , and rails .)

EDSA Philippines

12/2002

4 TOYO Construction Co, Ltd. ,

Mindanao Int’l Container Terminal : Construction of 400 meter container berth

Dry Dock –Bauan Batanggas : Construction of 40,000 DWT Dry Dock, 280,000 m3 excavation, concrete works , sheet piling , drainage and road works .

Cagayan De Oro , MisamisOriental

BauanBatangas

2004

1997

Completed Construction projects( ROADS & BRIDGES ) & (Tracks & Railways ) & ( SITE DEVELOPMENT ) & (MARINE WORKS )

SUBIC-CLARK-TARLAC EXPRESSWAY PROJECT (PACKAGE 1, SUBIC-CLARK)

(Top and Left)

Completed: December 2006

This is a premier expressway project inLuzon, linking the Subic Bay Freeport, inSubic, Zambales, to Clark InternationalAirport in Clark, Pampanga, (bothformer US Bases). Package I involvedembankment of 1.2 million cubic meterslahar for the 8 kilometers sectionincluding base course, cement-treatedbase and 8 RCDG bridges, 2underpasses, drainage structures andslope protection works.

This is MOJON BRIDGE, RCDG 5-span bridge, 175m long x 8.3m wide. Also constructed was a 200m x 6.7m approach road, including riverbank and slope protection works as shown in foreground.

ROADS AND BRIDGES

NINOY AQUINO INTERNATIONALAIRPORT TERMINAL 3

(Right)

Completed: Dec 2002

This is the NAIA 3, currently the Philippines’ premier international airport terminal located in Pasay City, Metro Manila. Construction works included site development, laying of base and sub-base courses, and drainage works along the runway area.

210MW MINDANAO COAL FIRED POWER PLANT

(Left)

Completed: Nov 2002

This Mindanao Coal Fired Power Plant Project involves 120,000 square meters site preparation work for the powerhouse.

METRO RAIL TRANSIT STATION 10 (3 LEVEL)(Right)Completed: August 2000

The Metro Rail Transit Station 10 is a 3-level 2,800 square meters structures that serves commuters along Buendia Avenue and EDSA. Part of the work done by Sta. Clara was the 3km track rails connecting Buendia and Taft Ave. Station.

METRO RAIL TRANSITTRACK WORKS(Left & Below)Completed: December 2000

As part of the Metro Rail Transit (MRT) network construction, this project entailed the construction of the concrete plinth including rail installation of the elevated guide-way. Also included were the installation of ballasted track(bottom and top ballast, pc sleepers, and rails.)

TRACKS & RAILWAYS

MINDANAO INTERNATIONAL CONTAINER TERMINAL -Cagayan de Oro, Misamis Oriental - PHILIPPINESDESCRIPTION:400 meter container berth was completed for this container terminal.CLIENT: TOYO Construction Co. Ltd

DRY DOCK - Bauan, Batangas PHILIPPINESDESCRIPTION:Construction of 40,000 DWT Dry Dock, 280,000 cu.m. excavation, concrete works, sheet piling, drainage and roadworks

CLIENT: TOYO CONSTRUCTION CO. LTD.

MARINE WORKS

Committed to Continual Improvement

List of Equipments

QTY

1 Earthmoving Equipment

Bulldozer 22

Wheel Lader 17

Motor Grader 8

Hydraulic Excavator 30

Vibratory Roller 17

Backhoe Loader 2

2 Hauling Equipment

Dump Truck 34

Cargo Trucks 5

Trailer Low Bed 8

3 Lifting Equipment

Crawler Crane 1

Rough Terrain 5

Truck Crane 1Forklift 2

Truck with Crane 8

4 Mining Equipment

Articulated Trucks 5Jumbo Drill 1Rock Drill 15

5 Plants QTY

Concrete Batch Plant 6

Crushing Plant 1

Truck Mixer 22

Concrete Pump Mobile 3

Concrete Pump Stationary 2

6 Special Foundation Equipment

Electric Vibro Hammer 2

Grout Machine 3

Shotcrete Machine 5

7 Horizontal Directional Drilling 7

8 Trenching Machine

Wheel 3

Track 1

List of Equipments

List of Equipments

QTY

9 Special Support Equipment

Water truck 6Fuel Truck 5

Machine Truck 3

Service Pickup 70

10 Miscellaneous Equipment

Generator Set 40

Air Compressor 15

Dewatering Equipment

(LP/HP Pumps) 30

Welding Machine 49

Horizontal Directional Drilling EQUIPMENTS

Horizontal Directional Drilling EQUIPMENTS

Horizontal Directional Drilling EQUIPMENTS

Managed by experienced technical personnel and fully equipped with state-of-the-art equipmentlike articulated trucks, heavy duty excavators, and mechanized drills, Sta. Clara serves therequirement of both tunnel and open pit type of mining and quarrying. Add to this thecapability of constructing the facility and infrastructure requirements of the mining andquarrying operations from infrastructures such as dams, channels, tunnels, by-passes, toshelters of concrete and steel structures.

Mining , Quarrying , and Batching Plant

Sta. Clara produces its own qualityconcrete for its various projects from thecompany’s own concrete batching plantand truck mixers. The plants are supportedby highly qualified and experiencedpersonnel. Support laboratory office andequipment ensure high quality of theconcrete.

Mining , Quarrying , and Batching Plant

Committed to Continual Improvement

List of Manpower

No. Classification Numbers Nationality

A ENGINEERING DIVISION

1 Engineering Manager 1 Filipino

2 Mechanical Estimator 1 Filipino

3 Electrical Estimator 1 Filipino

4 Civil Estimator 1 Filipino

5 Structural Design Engineer 1 Filipino

6 Auto CADD Operator 1 Filipino

Committed to Continual Improvement

List of Manpower

No. Classification Numbers Nationality

B CONSTRUCTION DIVISION

1 Construction / Project Manager 1 Filipino

2 QA/QC HSE Manager 1 Filipino

3 Site Engineers 6 Filipino

6 Planning Engineer (Scheduler) 1 Filipino

7 Site Supervisors 13 filipino

8 Material and Logistic Officer 1 Filipino

9 Multi-Trade Skilled Worker 44 Filipino

Committed to Continual Improvement

MISSION & VISIONTo be a leading Engineering & Construction

Company by year 2015

Serving selected business segments worldwide with distinctive capabilitiesand a strong technology orientation, to provide added value to ourstakeholders, and to contribute through innovation to a sustainable andenvironmentally friendly global development.

VALUES : Honesty & Integrity , Customer & Excellence ,Innovation & Change , Leadership & Prudence

Committed to Continual Improvement

Honesty & Integrity - We believe goodwill and good reputation is core toour business. We uphold Honesty, Integrity, Professionalism and a high levelof business ethics. We observe prudence and fairness in dealings with ourstakeholders.Customer & Excellence - We are diligent about understanding andfulfilling our customers' needs. We strive to please our customers withexcellence in quality and services. We listen to our customers and 'go theextra mile' to satisfy them.Innovation & Change - We are passionate about meaningful innovation.We are a learning organization. We learn from our experiences and globalbest practices, and we innovate to create leading local solutions leveraging onworld-class knowledge. We embrace positive change brought forth byinnovation and aspirations to grow our business.Leadership & Prudence - We cultivate talent and leadership to createsound business solutions, to best meet our customer needs, and to developmarkets, people and shareholder value. We do so by optimizing use of funds,resources, materials, and technologies. We build prudence and cost-effectiveness in our leadership culture passing on benefits to our customers.

Quality Policy

&

Quality Management System

Committed to Continual Improvement

STA. CLARA INT’ERNATIONAL CO. W.L.L. has implemented atailored Quality Management System (QMS) in accordance with ISO9001:2000 standard to develop policies and objectives which take intoaccount specific customer needs and a general requirement to continuallyimprove quality performance. An action plan concerning a new version ofthe standard (ISO 9001:2008) is currently being implemented and shouldbe completed by the end of 2010.

The general objectives of the quality policy are the following:

Understanding and meeting customer needs; Fulfillment of contract obligations and meeting technical and economic

requirements; Compliance with statutory and regulatory obligations (standards and codes in

force in the country of destination).

The quality policy is communicated to Company personnel through theQuality Manual and corporate intranet and is also displayed at prominentlocations in STA. CLARA INT’L CO. W. L. L. offices. Every employeeand each department carries the responsibility of achieving its objectivesthrough accurate document control, equipment supervision, monitoring ofconstruction, and handover activities.

page 1 of 2

Quality Policy and Quality Management System

Committed to Continual Improvement

STA CLARA INT’L CO.W.L.L. top management strives continually toimprove the effectiveness of the Quality Management System through aperiodic review of results, remedial action in the case of deviations, andorganizational changes that could affect the QMS itself. The review of theQMS is carried out by analyzing the QMS Report, which consists mainly offeedback from customers, coupled with audit results, process performance,and product conformity analyses.

The QHSE Manager is the management representative with responsibility forQuality. The basic references of STA CLARA Group’s QMS documentationare the Code of Ethics .Other relevant documentation includes the QualityManual and Quality Policy, Organizational Procedures, and WorkInstructions. The QHSE Department establishes and maintains an internalaudit programs to verify conformity, effectiveness, results and possibleimprovements to QMS. The audits are conducted by qualified internalpersonnel, independent of the area being examined. In addition, STA CLARAauditors carry out external audit activities on vendors and subcontractorsduring the qualification, manufacturing/service provision and constructionphases.

The STA CLARA INT’L CORP. Quality Management System’s compliancewith ISO 9001 was certified by Det Norske Veritas (DNV). Yearly re-assessment audits have been performed with positive results since then.Services covered by the certificate include: project management, basic anddetailed engineering, procurement, construction and installationmanagement and turnkey supply of industrial plants (in particularrelevant to chemicals and petrochemicals, oil and gas, and power) andinfrastructures.

Quality Policy and Quality Management System

page 2 of 2

Committed to Continual Improvement

Maximum Efficiency

Highest Quality

Protect The Employee , The Client, The Public and The

Environment , Health & Safety

ABSOLUTE

TOTAL CLIENT SATISFACTION

CORPORATE MOTTO

COMMERCIAL

FINANCIAL HIGHLIGHTS

QATAR COMMERCIAL REGISTRATIONCOMMERCIAL REGISTRATION NO.

34771TYPE OF COMPANY

WLLNATIONALITY OF THE COMPANY

QATARI (51% ) / PHILIPPINES (49 %)COMMERCIAL ACTIVITIES

GENERAL CONTRACTING

Bank References:

HSBC - Doha

Standard Chartered Bank - Doha

PARTICULARS 2009 2008 2007 2006 2005 2004

GROSS REVENUE 27,554,569.00 15,586,998.00 10,144,982.00 2,561,827.10 1,031,402.50 218,344.00

GROSS INCOME 4,748,264.00 2,987,908.00 2,528,406.00 815,534.53 711,226.52 106,053.22

NET INCOME 1,133,176.00 455,692.00 619,994.00 159,194.55 356,709.43 (413,903.98)

TOTAL ASSETS 13,399,530.00 6,597,731.00 6,237,778.00 1,495,794.26 798,395.95 379,005.23

TOTAL LIABILITIES 10,990,668.00 5,322,045.00 5,417,784.00 1,393,794.26 855,590.50 792,909.21

STOCKHOLDER’S EQUITY 2,408,862.00 1,275,686.00 819,994.00 102,000.00 (57,194.55) (413,903.98)

CURRENT RATIO 1.03 0.91 0.82 0.99 0.76 0.24

DEBT TO EQUITY 4.56 4.17 6.61 13.66 (14.96) (1.92)

GROSS PROFIT MARGIN 0.17 0.19 0.25 0.32 0.69 0.49

PROFIT MARGIN 0.04 0.03 0.06 0.06 0.35 (1.90)