PARIS– 15 November 2017 SCL Radial Joint Design – Bank Station Capacity Upgrade Bethan Haig BSCU SCL Radial Joint Design – Bethan Haig

Upload: others

Post on 25-Mar-2021

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: SCL Radial Joint Design – Bank Station Capacity Upgrade · 2017. 11. 21. · No entrance to sealed tunnel face Change behaviour in the tunnel. PARIS– 15 November 2017. The Design

PARIS– 15 November 2017

SCL RadialJoint Design –Bank StationCapacity Upgrade

Bethan Haig

BSCU SCL Radial Joint Design– Bethan Haig

Page 2: SCL Radial Joint Design – Bank Station Capacity Upgrade · 2017. 11. 21. · No entrance to sealed tunnel face Change behaviour in the tunnel. PARIS– 15 November 2017. The Design

PARIS– 15 November 2017

StakeholdersDr Sauer & Partners – SCL Designer

Dragados – Design & Build Contractor

London Underground – The Client

BSCU SCL Radial Joint Design– Bethan Haig

Page 3: SCL Radial Joint Design – Bank Station Capacity Upgrade · 2017. 11. 21. · No entrance to sealed tunnel face Change behaviour in the tunnel. PARIS– 15 November 2017. The Design

PARIS– 15 November 2017

The Project

BSCU SCL Radial Joint Design– Bethan Haig

Bank Station Capacity Upgrade

Page 4: SCL Radial Joint Design – Bank Station Capacity Upgrade · 2017. 11. 21. · No entrance to sealed tunnel face Change behaviour in the tunnel. PARIS– 15 November 2017. The Design

PARIS– 15 November 2017

The Project

BSCU SCL Radial Joint Design– Bethan Haig

Page 5: SCL Radial Joint Design – Bank Station Capacity Upgrade · 2017. 11. 21. · No entrance to sealed tunnel face Change behaviour in the tunnel. PARIS– 15 November 2017. The Design

PARIS– 15 November 2017

The Team

BSCU SCL Radial Joint Design– Bethan Haig

Page 6: SCL Radial Joint Design – Bank Station Capacity Upgrade · 2017. 11. 21. · No entrance to sealed tunnel face Change behaviour in the tunnel. PARIS– 15 November 2017. The Design

PARIS– 15 November 2017

The Team Approach

BSCU SCL Radial Joint Design– Bethan Haig

Biweekly constructability review meetings

Sketch Draft Design Compliance SubmissionIDC IFCFinal Design

SCL DETAILED DESIGN

• More than 30 biweekly workshops including members of LU and Dragados

• Collaborative approach to improve health and safety and efficiency throughdesign

Page 7: SCL Radial Joint Design – Bank Station Capacity Upgrade · 2017. 11. 21. · No entrance to sealed tunnel face Change behaviour in the tunnel. PARIS– 15 November 2017. The Design

PARIS– 15 November 2017

SCL Safety Hazards and Quality Issues

BSCU SCL Radial Joint Design– Andreas Feiersinger

• Fallouts• Complex connections of reinforcement

at radial joints• Poor quality jointing• Poorly executed design

Page 8: SCL Radial Joint Design – Bank Station Capacity Upgrade · 2017. 11. 21. · No entrance to sealed tunnel face Change behaviour in the tunnel. PARIS– 15 November 2017. The Design

PARIS– 15 November 2017

The Design Solution

BSCU SCL Radial Joint Design– Bethan Haig

No entrance to sealed tunnel face

Change behaviour in the tunnel

Page 9: SCL Radial Joint Design – Bank Station Capacity Upgrade · 2017. 11. 21. · No entrance to sealed tunnel face Change behaviour in the tunnel. PARIS– 15 November 2017. The Design

PARIS– 15 November 2017

The Design Solution

BSCU SCL Radial Joint Design– Bethan Haig

Stage 1

Excavate top heading/benchApply primary SCL

Stage 2

Excavate bench/invertBreak off toe to form min.150mm construction joint

Stage 3

Apply primary SCL to fullthickness

Page 10: SCL Radial Joint Design – Bank Station Capacity Upgrade · 2017. 11. 21. · No entrance to sealed tunnel face Change behaviour in the tunnel. PARIS– 15 November 2017. The Design

PARIS– 15 November 2017

Trialling the Design and Workmanship

BSCU SCL Radial Joint Design– Bethan Haig

The joint was tested as part of thepre-construction trials

Page 11: SCL Radial Joint Design – Bank Station Capacity Upgrade · 2017. 11. 21. · No entrance to sealed tunnel face Change behaviour in the tunnel. PARIS– 15 November 2017. The Design

PARIS– 15 November 2017

Trialling the Design and Workmanship

BSCU SCL Radial Joint Design– Bethan Haig

The joint was tested as part of the pre-construction trials

Option A joint core Normal core

Page 12: SCL Radial Joint Design – Bank Station Capacity Upgrade · 2017. 11. 21. · No entrance to sealed tunnel face Change behaviour in the tunnel. PARIS– 15 November 2017. The Design

PARIS– 15 November 2017

The Design in Use- The project has seen excellent implementation of the joint in the construction stage.

- Excellent workmanship

- Tight Supervision

BSCU SCL Radial Joint Design– Bethan Haig

Page 13: SCL Radial Joint Design – Bank Station Capacity Upgrade · 2017. 11. 21. · No entrance to sealed tunnel face Change behaviour in the tunnel. PARIS– 15 November 2017. The Design

PARIS– 15 November 2017

The Design in UseThe SCL construction process is now completely mechanised

BSCU SCL Radial Joint Design– Bethan Haig

Page 14: SCL Radial Joint Design – Bank Station Capacity Upgrade · 2017. 11. 21. · No entrance to sealed tunnel face Change behaviour in the tunnel. PARIS– 15 November 2017. The Design

PARIS– 15 November 2017

The Feedback

BSCU SCL Radial Joint Design– Bethan Haig

The implementation of this joint design has gleaned the following feedback from theconstruction team and miners:

This is one of the mostpositive changes to theindustry in the last 20years

The joint is one safetychange that we can seereally and truly making adifference to the team onsite – Nice one!

Once mastered it couldbe said that this is astep change for tunnelhealth and safety

We are particularly impressedwith the elimination of HAVs,removal of honeycombing aroundbars and the associated defectrepair