scraft building goi thao
TRANSCRIPT
-
8/10/2019 Scraft Building Goi THao
1/5
Contract Appendix 1/3
CONTRACT APPENDIX 01
(Of the contract ofNo: 01/TD/DD/LIXIL/2013signed March 28, 2013)
PHLC HP NG 01(Thuc hp ngS: 01/TD/DD/LIXIL/2013k ngy 28/03/2013)
TITLE Package 15A- SCRAF BUILDING
Gi thu 15A -
SUBJECT STEEL STRUCTURE SUPPLY AND INSTALLATION PACKAGE.
HNG MC Gi thu cung cp v lp t kt cu thp
Appendix made and entered into this day 27 May 2013
Phlc c lp vo ngy 27 May 2013
BETWEEN TRUNG DUNG CONSTRUCTION COMPANY LIMITED. ("The contractor)
CNG TY TNHH XY DNG V SAN LP NN TRUNG DNG
Address: 151-151Bis Vo Thi Sau Str., District 3, Ho Chi Minh City.
a ch: 151-151Bis V ThSu, Phng 6, Qun 3, Tp. HCh Minh
And DAI DUNG HI TECH MECHANICAL (TheSub-contractor)
V CNG TY CP C KH CNG NGHCAO I DNG II(t hu Ph)
Address: Binh Tien 2 Hamlet, Hoa Ha Commune, Duc Hoa District, Long An Province
a ch: p Bnh Tin 2, X Ha H, Huyn c Ha, Tnh Long An
1. The Subcontract Sum- Thu phtrn gi
1.1. The Lump Sum Amount of 128,183,974 VND (Vietnam dong: One hundred twentyeighty million one hundred eighty three thousand nine hundred seventy four)
excluding value added tax (V.A.T) 10% (12,818,397) subject to the following key terms
and conditions.
-
8/10/2019 Scraft Building Goi THao
2/5
Contract Appendix 2/3
1.1. Tng gi tr: 128,183,974 ng (ng Vit Nam:mt trm hai mi tm triu mt
trm tm mi ba ngn chin trm by mi bn ng)chabao gm thugi trgia
tng, (VAT) 10% (12,818,397ng)
1.2. This appendix shall be a fixed price lump sum contract and shall not subject to re-
measurement for any reason whatsoever.
Gi trn phlc hp ng ny l gi trn gi cnh v khng iu chnh v bt kl do
g.
1.3. Variation will only apply in event of a change in the scope of work and at the sole
discretion of the Contractor. The Subcontract is deemed to have allowed in his Lump
sum for all items required to complete the works and there will be no variations for any
design development or amendment of shop drawings.Pht sinh schc p dng trong trng hp c sthay i trong phm vi cng vic
v quyt nh ring tNh thu. Nh thu phc xem l trn gi cho tt ccc mc
cn thit hon thnh cng vic v sc khng tnh pht sinh trong vic iu chnh
bn vthit khoc bsung bn vthi cng.
1.4. There will be no adjustment for price increases (fluctuations) for material, plant and
equipment nor for any change in legislation which may impact taxes or import duties or
the like and the Subcontract is deemed to have made all necessary allowances in the
Lump sum Subcontract Sum
Skhng c iu chnh tng gi (bin ng) vt t,my mc v thit bcng khng cho
bt kthay i no trong thuhoc ngha vnhp khu hoc cc loi tng tv Nh
thu phc coi l thc hin tt ccc khon phcp cn thit trong hp ng
trn gi
2. Programme- Tin
2.1 25 days from the date signed contract appendixTin thi cng trong vng 25 ngy ktngy k phlc hp ng
2.2 The issues of the Taking Over Certificate (completion certificate) shall be contingents on
the following events being satisfactorily completed so as to represent substantial
completionof the Subcontractor works.
BB nghim thu bn giao (bin bn hon thnh cng vic) sc xem l hon tt
i din cho phn ln cng vic m thu ph hon thnh
-
8/10/2019 Scraft Building Goi THao
3/5
Contract Appendix 3/3
- completion of all test and inspections to the satisfaction of the Contractor
Hon thnh vic kim tra, kim nh bi nh thu chnh
- remedy of defects indentified in such test and inspections
Khc phli c thhin trong kim tra v kim nh
- handover of all approved shop-drawing and as-built drawings
Bn giao tt cbn vgia cng trnh duyt v bn vhon cng
- removal of all Subcontractor plant and equipment
Loi btt cmy mc, nh xng ca nh thu ph
- provision of all signed executed warranties as prescribed in the Invitation to Tender
Cung cp tt cbo hnh k theo quy nh ca th mi thu
- third party of authority approvals ( if relevant)
Bn duyt ca bn thba (nu c)
The Contractor shall have sole discretion in deciding when the works as substantially
completion for the issue of the Taking Over Certificate.
Nh thu chnh l n v duy nht c quyn quyt nh phn ln cng vic c
hon thnh pht hnh BB nghim thu bn giao
2.3 The period of the Defects Liability Period will be 2 years from the date of the Taking
Over Certificate of the Main Contract at which time 2.5% of retention shall be released to
the Subcontractor and the balance 2.5% being released on expiry of the period and paid
in the Final Certificate.
Thi gian bo hnh l 2 nm ktngy k BB nghim thu bn giao tnh thu chnh,
trong 2,5% tin bo hnh s trcho nh thu phkhi BB nghim thu c duyt,
2,5% cn li sc thanh ton vo ngy c gia hn v thanh ton khi c chng cui
cng
2.4 Liquidated Damages shall be at a rate of 12,818,397 VND per day pro-rata for each
building based on the proportional Subcontract Sum. Maximum liability of liquidated
damages is 10% of Subcontract Sum.
Tin bo hnh sl 12,818,397 VND nhng khng vt qu 10%GTH
NOW IT IS HEREBY AGREED AND DECLARED AS FOLLOWS:
Cc iu khon sau y c xem l ng :
-
8/10/2019 Scraft Building Goi THao
4/5
Contract Appendix 4/3
1. For the consideration hereinafter mentioned the Subcontractor will upon and subject to
the condition annexed hereto execute and complete the Subcontract Works shown
upon the Sub Contract Document, and described by or referred to the attached Bill of
quantity, Subcontract Drawing, Preambles, Specification and remedy defects therein in
conformity in all respects with the provisions of Subcontract.
Nh thu phphi thc hin theo cc phlc nh km di y trong vic trin khai
thc hin v hon thnh cng trnh: phlc hp ng thu ph, bng khi lng, bn
vca nh thu ph, li mu, quy cch v cc khim khuyt cn hn chtheo quy
nh ca hp ng thu ph
2. The Contractor will pay to the Subcontractor the Lump sum Amount of 128,183,974
VND (Vietnam dong: Nine hundred seventy two million four hundred thirty nine
thousand one hundred twenty) excluding Value Added Tax (V.A.T) 10%
(herein after referred to as the Subcontract Sum) or such other sum as shall be come
payable hereunder at the times and in the manner specified in the said Condition
Nh thu sthanh ton cho cc nh thu phStin trn gi 128,183,974 VND (ng
Vit Nam: Chn trm by mi hai triu bn trm ba mi chn ngn mt trm hai
ming) chabao gm thugi trgia tng (VAT) 10%
(sau y gi l "tng gi trgi thu ph") hoc cc khon tng ti khc sc thanh
ton theo thi im v cch thc quy nh ti cc iu kin trng hp ng
Appendices of this contract is an inseparable part of the contract No: 01/TD/DD/LIXIL/2013
signed on 28 Mar 2013. The other terms of the contract No: 01/TD/DD/LIXIL/2013 signed on
28 Mar 2013, not listed above remain unchanged
Phu luc Hp ong nay la mot phan khong the tach ri cua Hp ong so:01/TD/DD/LIXIL/2013 k ngy 28/03/2013. Nhng ieu khoan khac cua hp ongso 01/TD/DD/LIXIL/2013 k ngy28/03/2013 khong c neu tren van gi nguyenkhong thay oi.
Appendix contract takes effect from the date of signing until the end of the warranty periodwork of this annex
Phlc Hp ng c hiu lc ktngy k cho n ngy ht hn bo hnh cc cng vic
ca phlc hp ng ny.
These contract appendix are drawn out into 04 originals, each party keeps 02 originals
-
8/10/2019 Scraft Building Goi THao
5/5
Contract Appendix 5/3
Phlc hp ng ny c lp thnh 04 bn c gi trphp l tng ng nhau, mi bn
gihai bn
FOR THE SUB CONTRACTOR FOR THE CONTRACTORNh thu ph Nh thu