sdg&e experience with distribution synchrophasors and ... · pdf filetitle: microsoft...
TRANSCRIPT
Copyright © SDG&E and SEL 2016
SDG&E Experience With Distribution Synchrophasors and
Catching Falling Conductors
Tariq RahmanSan Diego Gas & Electric
Kamal GargSchweitzer Engineering Laboratories, Inc.
Copyright © SDG&E and SEL 2016
• 22,000 miles of lines• 60% underground and 40% overhead• 12.47, 12.0, and 4.16 kV voltage levels• Grounded at substation with three- and
four-wire systems
SDG&E Distribution System
Copyright © SDG&E and SEL 2016
• Falling conductor protection (patent pending)• Voltage profile monitoring and control • Selective load shedding and restoration• Power quality monitoring • Apparatus and system condition monitoring• Secure communication
Advanced SCADA PlanningMore Than 60 Cases Defined
Copyright © SDG&E and SEL 2016
• Increased accuracy – voltage and current sensors• Phase angle• GPS time-stamped data• Remote engineering access and event reports• High-speed, near real-time control
Advanced SCADA Features
Copyright © SDG&E and SEL 2016
• Advanced visualization • Improved security Log and audit access
Active directory passwords
Network anomaly detection sensor and technology
Advanced SCADA Features
Copyright © SDG&E and SEL 2016
0
5
10
15
20
25
30
0.00 0.25 0.50 0.75 1.00 1.25
Con
duct
or H
eigh
t (ft)
Time (s)
Falling Conductor Timeline
0.5 s, 4 ft
1 s, 16 ft
Conductor hits ground at 1.37 s
Detect Broken Conductor and Trip Circuit Before Line Hits the Ground?
2 2dg
1d gt t22(30)t32.2
time 1.37s
Copyright © SDG&E and SEL 2016
Feeder ModelFalling Conductor PMU Locations
Copyright © SDG&E and SEL 2016
RTDS Feeder Model
Copyright © SDG&E and SEL 2016
Copyright © SDG&E and SEL 2016
Sequence Components Analysis
c1 b2
a2a1
b1 c2
a0
b0
c0
c2 2 a2c1 a1
b1 2 a1a0 b0 c0 b2 a2
Copyright © SDG&E and SEL 2016
• dV/dt (change detection) • V0 and V2 magnitude• V0 and V2 angle
Detection Methods
Copyright © SDG&E and SEL 2016
Example Lab Test Results PV Off, Loop OpenLoad % FC1 FC2 FC3 FC4
100 3 3 3 375 3 3 3 325 3 3 3 3
PV On, Loop OpenLoad % PV% FC1 FC2 FC3 FC4
100
100 3 3 3 375 3 3 4 450 3 3 3 325 3 3 3 3
25
100 3 3 3 375 3 3 3 350 3 3 3 325 3 3 3 3
Copyright © SDG&E and SEL 2016
0
10
20
0–99 100–199 200–299 300–399 400–499
Arc Speed = 5 m/s
FC1 FC2 FC3 FC4(ms)
Arc Speed and Results ComparisonNumber of Test Cases Versus dV/dt Pickup Times
0
10
20
0–99 100–199 200–299 300–399 400–499
Arc Speed = 0 m/s
FC1 FC2 FC3 FC4(ms)
Copyright © SDG&E and SEL 2016
• First system installation in January 2015• Falling conductor protection (FCP) in monitoring mode• Simulation of conductor breaks with disconnect switch
opening on recloser• 100% correct operation• Ethernet radio tuning required
Field Installation and Testing
Copyright © SDG&E and SEL 2016
dV/dt OperationCapacitive Voltage Sensors
Pha
se A
V
olta
gedV
A/d
tdV
0/dt
Time
Load SideSource Side
Nominal 6.9 kV
dVA/dt > 1,000 V/s
dV0/dt > 400 V/s
–400 V/s
577 V/s
0
0
–1.7 kV/s
2.8 kV/s6.8 kV
11 kV
Copyright © SDG&E and SEL 2016
FCP Detects CT Insulation Failure
Copyright © SDG&E and SEL 2016
Nuisance Trip Diagnostics and Analysis
Copyright © SDG&E and SEL 2016
Ease of Application• Key requirement achieved – no
circuit-dependent application settings
• FCP logic only needs topology of circuit and PMU IEDs
To Control Centervia WAN
P P
P
P
P
P
P
P
N.O.
P
P
P
Line Monitor
VR4
R1
P
VR1VR2
PV11 MW
PV21 MW
S
DVC
Feeder Relay
69 kV/12 kV
R3
VR6
VR3
R5 VR5
R4
C3
C2
C1
P
Substation
PDC and Controller Switchyard
Fiber
Copyright © SDG&E and SEL 2016
• Falling conductor takes ≈1.4 s to reach the ground• FCP methods detect and isolate in ≤0.7 s• Change detection and steady-state detection
algorithms operate in parallel
Conclusions
Copyright © SDG&E and SEL 2016
• Change detection picks up reliably for almost all falling conductor test cases
• Steady-state sequence methods (magnitude and angle) back up change detection in case of datapacket loss
• Dependable falling-conductor detection observed in lab and field
Conclusions
Copyright © SDG&E and SEL 2016
• FCP tripping is being enabled at first installation• Scalable design works on all studied circuits and needs
only circuit layout information• Twelve more circuits to be commissioned in 2016, with
more to come
Conclusions
Copyright © SDG&E and SEL 2016
Questions?