1 Secant Pile Construction OSIS Augmentation & Relief Sewer (OARS) Phase 2 Shafts # 3, 4 & 5 DFI – ADSC Drilled Shaft Seminar Support with Confidence July 11-12, 2013 Secant Piles Construction Structural foundation element consisting of overlapping piles forming a continuous wall. Reinforced concrete (rebar cages or soldier piles). Depth depends upon final design & soil and equipment characteristics. Piles diameters usually based on metric tooling size. Typically 760, 880, 1000 and 1180 mm are used. Other sizes are available. Secant piles walls to be cantilevered or braced. Any geometric shape is possible. The more unique the shape the more difficult the bracing system becomes.

Upload: dohanh

Post on 12-Apr-2018

226 views

Category:

Documents


4 download

TRANSCRIPT

Page 1: Secant Pile Construction - PolyMolding LLCpolymoldingllc.com/wp-content/uploads/2017/06/10-Risberg-PPT.pdf · 1 Secant Pile Construction OSIS Augmentation & Relief Sewer (OARS) Phase

1

Secant Pile ConstructionOSIS Augmentation & Relief Sewer (OARS) Phase 2 Shafts # 3, 4 & 5

DFI – ADSC Drilled Shaft SeminarSupport with Confidence

July 11-12, 2013

Secant Piles Construction

• Structural foundation element consisting of overlapping piles forming a continuous wall.

• Reinforced concrete (rebar cages or soldier piles).

• Depth depends upon final design & soil and equipment characteristics.

• Piles diameters usually based on metric tooling size.  Typically 760, 880, 1000 and 1180 mm are used.  Other sizes are available. 

• Secant piles walls to be cantilevered or braced.  Any geometric shape is possible.  The more unique the shape the more difficult the bracing system becomes.

Page 2: Secant Pile Construction - PolyMolding LLCpolymoldingllc.com/wp-content/uploads/2017/06/10-Risberg-PPT.pdf · 1 Secant Pile Construction OSIS Augmentation & Relief Sewer (OARS) Phase

2

Secant Piles Construction

• Selection of secant piles vs. other earth retention support systems is based on:– Available work space / site logistics

– Layout of wall

– Impact restrictions on adjacent structures

– Design parameters (stiffness of wall, cutoff requirements…)

– Material handling requirements

– Excavation capabilities in difficult soil conditions

Secant Piles Construction

• Sequence of construction– Guide‐walls installation

– Primary or lagging piles installation• Sectional casing rotation in advance of auger removing soil inside of the 

casing– Dry or wet drilling depending upon soils conditions

• At drilling completion, cleaning of pile bottom & placement of concrete – Free fall placement in dry condition and with a tremie pipe in wet conditions

• Extraction of casing at pour completion

– Secondary or closing piles installation• Sectional casing rotation in advance of auger removing soil inside of the 

casing– Dry or wet drilling depending upon soils conditions

• At drilling completion, cleaning of pile bottom & placement of reinforcement followed by concrete 

– Free fall placement in dry condition and with a tremie pipe in wet conditions

• Extraction of casing at pour completion

Page 3: Secant Pile Construction - PolyMolding LLCpolymoldingllc.com/wp-content/uploads/2017/06/10-Risberg-PPT.pdf · 1 Secant Pile Construction OSIS Augmentation & Relief Sewer (OARS) Phase

3

Secant Piles Construction

• Sequence of construction– Guide‐walls installation

Secant Piles Construction

• Sequence of construction– Primary or lagging piles installation

• Piles typically un‐reinforced

• Lower strength concrete can be used.  Dependent on design and final

Page 4: Secant Pile Construction - PolyMolding LLCpolymoldingllc.com/wp-content/uploads/2017/06/10-Risberg-PPT.pdf · 1 Secant Pile Construction OSIS Augmentation & Relief Sewer (OARS) Phase

4

Secant Piles Construction

• Sequence of construction– Primary or lagging piles installation

• Sectional casing rotated ahead of auger cleaning inside of casing

Secant Piles Construction

• Sequence of construction– Primary or lagging piles installation

• Sectional casing rotation ahead of auger cleaning inside of casing

Page 5: Secant Pile Construction - PolyMolding LLCpolymoldingllc.com/wp-content/uploads/2017/06/10-Risberg-PPT.pdf · 1 Secant Pile Construction OSIS Augmentation & Relief Sewer (OARS) Phase

5

Secant Piles Construction

• Sequence of construction– Secondary or closing piles installation

• Piles are reinforced using rebar cages or soldier piles

• High strength concrete is typically used

Secondary Piles

Primaryiles

Secant Piles Construction

• Sequence of construction– Secondary or closing piles installation

• Design may required all piles to be reinforced, in that case the lagging piles will be poured using structural concrete

Page 6: Secant Pile Construction - PolyMolding LLCpolymoldingllc.com/wp-content/uploads/2017/06/10-Risberg-PPT.pdf · 1 Secant Pile Construction OSIS Augmentation & Relief Sewer (OARS) Phase

6

Secant Piles Construction

• Sequence of construction– Secondary or closing piles installation

• Piles overlap is critical to guarantee continuity of wall

• Overlap is depending of depth of drilled piles and drilling verticality tolerance

Secant Piles Construction• Sequence of construction

– Secondary or closing piles installation• Load bearing caissons can be easily incorporated into secant wall

Page 7: Secant Pile Construction - PolyMolding LLCpolymoldingllc.com/wp-content/uploads/2017/06/10-Risberg-PPT.pdf · 1 Secant Pile Construction OSIS Augmentation & Relief Sewer (OARS) Phase

7

Secant Piles Construction

• Case History

Project: OSIS Augmentation & Relief Sewer (OARS) Phase 2 Shafts # 3, 4 & 5

Project Information: 397 Each – 1180 mm Shafts 

3 independent sites located approximately ½ mile from each other

Each secant pile wall system comprised of an drop shaft and approach channel.

Each secant pile for the access shaft was keyed 5’ into shale bedrock.

Average Secant Pile Drill Length was 62’.

OARS Phase 2 Case History – Shaft Locations

Page 8: Secant Pile Construction - PolyMolding LLCpolymoldingllc.com/wp-content/uploads/2017/06/10-Risberg-PPT.pdf · 1 Secant Pile Construction OSIS Augmentation & Relief Sewer (OARS) Phase

8

OARS Phase 2 Project  – Subsurface Profile

Drop Shafts: Secant Pile Compression Ring Design

All 4,500 psi Concrete

No reinforcement required for design as long verticality tolerance met, < 0.5% plumbness.

Reinforcing placed anyway due to grout pipe requirement for future Subcontractor’s work.

Seal of 5’ into Shale adequate for water cutoff.

Approach Channels: Internally braced excavation secant pile wall system.

W Section Placed every secondary pile.

4,000 psi concrete used for secondary piles, 2,500 psi concrete used for primary piles.

Seal of 5’ into Shale adequate for water cutoff.

OARS Phase 2 Project  – Basis of Design

Page 9: Secant Pile Construction - PolyMolding LLCpolymoldingllc.com/wp-content/uploads/2017/06/10-Risberg-PPT.pdf · 1 Secant Pile Construction OSIS Augmentation & Relief Sewer (OARS) Phase

9

OARS Phase 2 Project  – Shaft 3 Layout

85 each Secant Piles @ 53’ Long

OARS Phase 2 Project  – Shaft 4 Layout

173 each Secant Piles @ 64’ Long

Page 10: Secant Pile Construction - PolyMolding LLCpolymoldingllc.com/wp-content/uploads/2017/06/10-Risberg-PPT.pdf · 1 Secant Pile Construction OSIS Augmentation & Relief Sewer (OARS) Phase

10

OARS Phase 2 Project  – Shaft 5 Layout

139 each Secant Piles @ 65’ Long

OARS Phase 2 Project  – KODEN Ultrasonic DeviceVerticality Control

Page 11: Secant Pile Construction - PolyMolding LLCpolymoldingllc.com/wp-content/uploads/2017/06/10-Risberg-PPT.pdf · 1 Secant Pile Construction OSIS Augmentation & Relief Sewer (OARS) Phase

11

OARS Phase 2 Project  – Jean Lutz GyroscopeVerticality Control

OARS Phase 2 Project  – KODEN Ultrasonic Device Output

Pile #17B:Pile Depth = 57.83ftDeviation in x' direction = .78inDeviation in y direction = 1.57inTotal deviation = 1.75 < 7.08in = accepted

Page 12: Secant Pile Construction - PolyMolding LLCpolymoldingllc.com/wp-content/uploads/2017/06/10-Risberg-PPT.pdf · 1 Secant Pile Construction OSIS Augmentation & Relief Sewer (OARS) Phase

12

OARS Phase 2 Project Photo’s

OARS Phase 2 Project Photo’s

Page 13: Secant Pile Construction - PolyMolding LLCpolymoldingllc.com/wp-content/uploads/2017/06/10-Risberg-PPT.pdf · 1 Secant Pile Construction OSIS Augmentation & Relief Sewer (OARS) Phase

13

OARS Phase 2 Project Photo’s

OARS Phase 2 Project Photo

Page 14: Secant Pile Construction - PolyMolding LLCpolymoldingllc.com/wp-content/uploads/2017/06/10-Risberg-PPT.pdf · 1 Secant Pile Construction OSIS Augmentation & Relief Sewer (OARS) Phase

14

OARS Phase 2 Project Photo

OARS Phase 2 Project Photo

Page 15: Secant Pile Construction - PolyMolding LLCpolymoldingllc.com/wp-content/uploads/2017/06/10-Risberg-PPT.pdf · 1 Secant Pile Construction OSIS Augmentation & Relief Sewer (OARS) Phase

15

OARS Phase 2 Project Photo

QUESTIONS ?

Secant Piles Construction