Second Avenue Subway
Quarterly Public Workshop
February 25, 2015
2 MTA Capital Construction
• Overall Construction Progress is 78.7% complete as of 2/1/2015.
• All 10 SAS Contracts have been awarded for Phase 1
• 5 Construction Contracts Completed: − Tunnel Boring Machine Tunneling − 86th St Excavation, Utility Relocation, and Road Decking − 96th St Site Work and Heavy Civil − 72nd St Cavern Mining, Tunnels and Heavy Civil (1/14/14) − 86th St Cavern Mining & Heavy Civil (12/16/14)
Current Project Status
3
96th Street Proposed Art Installation Artist – Sarah Sze, MTA Arts & Design commissioned work
Station Renderings
63rd Street Mezzanine Fare Array
72nd Street Platform Level
86th Street Mezzanine - South Goto http://www.mta.info/SAS and click on Vision Gallery
3
4 4
Community Information Center & Community Tours
Hours Monday: 10AM - 6PM Tuesday: 11AM - 7PM Wednesday: 10 AM - 6PM Thursday: 11AM - 7PM Friday: 10AM - 6PM Saturday: 11AM - 3PM* Sunday: Closed Closed most public holidays *Open the second Saturday of every month.
• 9,300 visitors to date • 48 presentations to school groups with over 1,375 students attending • New exhibit coming in March 2015 • Community Tours- we have hosted 47 tours with 1,493 participants
Opened July 2013
5 MTA Capital Construction
96th Street Station Area
6 6 Above ground Ancillary 1 work at 93rd Street – January 2015
7 96th Street Ancillary 1 Rendering NE corner 93rd Street and Second Avenue
7
8
96th Street Station Area - Utility Installation 93rd – 94th Street & Second Avenue Looking South January 2015
Twin 42” Water Main
30” Gas Main Con Ed Electric
60” Water Main
8
9
Backfill over Utilities 95th – 96th Street and Second Avenue 9
10 MTA Capital Construction
86th Street Station Area
11
11
86th Street Station Mezzanine and Platform Dec. 2014 Looking North
86th Street Milestones
Oct. 3, 2014
All blasting completed on contract and entire Phase 1 project
Nov. 19, 2013
April 10, 2014
Completed dismantling of 83rd - 84th Street Muck House
Aug. 8, 2014
Completed casting of concrete arch ceiling
Completed dismantling of 86th - 87th Street Muck House
Highlight Completed 96% of lower mezzanine slabs in cavern
Dec. 16, 2014
Cavern Mining and Heavy Civil contract substantially completed
11
12 Muck House removal at 86th Street and Second Avenue October 3, 2014
May 2014
12
13 MTA Capital Construction 13 Yorkshire Building at 86th Street and Second Avenue January 28, looking East
14
New 20 foot sidewalks poured on 86th Street
between 1st and 2nd Avenues, East of Yorkshire building
86th Street Station Area
14 Looking east
15 MTA Capital Construction
72nd Street Station Area
16 MTA Capital Construction
72nd Street Station Area
New fence wrap installed in January between 69th and 70th Streets, looking south.
17
72nd Street Station Area
Ancillary 2/Entrance 2 at northwest corner of 72nd Street and Second Ave 17
18
72nd Street Entrance 2 / Ancillary 2 Rendering NW corner 72nd Street and Second Avenue
19 19
72nd Street Station - Mezzanine Public Area Looking North at 69th Street
Ductwork
Arch Ceiling
Electrical Conduits Ventilation Ducts
20 MTA Capital Construction
Lexington Ave / 63rd Street Station Area
21 MTA Capital Construction
Pre repair Post repair
Sidewalk repair 163 E. 63rd Street
Lexington Ave/63rd Street Station Area
21 Looking east towards Third Ave Looking west towards Lexington Ave
22
Water treatment tanks removed from the eastside of Third Avenue between E. 62nd and E. 63rd Streets.
Lexington Ave/63rd Street Station Area
23
Lexington Ave/63rd Street Station Station rehabilitation includes new track wall tiles, ceilings and lighting Lower Level Platform - February 2015
23
24 MTA Capital Construction
Streetscape “Visioning” Process
25
Streetscape “Visioning” Process
• MTACC wanted to give the community something better
• Numerous meetings, emails and calls with city agencies, including DOT and Parks
• Community input solicited at a November 3rd workshop
• Meeting with CB8 Second Avenue Subway Taskforce and CB11 Transportation Committee members to select streetscape components
• Full CB8 board meeting on February 18th
MTA Capital Construction
26
Typical Pre-Construction Block
MTA Capital Construction 26
27 MTA Capital Construction
For conceptual purposes only. Placement and selection of specific street elements to be decided.
Concept Rendering Post-Construction Block
28
City Light
29
Street Trees: Large Canopy Linden Bald Cypress Sweetgum Zelkova
• Red/bronze fall color
• One of the most common street trees • Yellow fall color
• Strong pyramidal shape • Orange/brown fall color
• Strong, yellow fall color
5-inch diameter trees will be used whenever possible
30
Street Trees: Columnar Form
Fastigiata Oak Zelkova Musachino
31
Street Trees: Small Understory
Serviceberry Eastern Redbud Japanese Tree Lilac
Community Board committees decided to let Parks Department make decisions as appropriate
32
Rail Guards for Tree Pits
MTA Capital Construction
33
City Benches
MTA Capital Construction
34
Bicycle Rack
MTA Capital Construction
35
Way-Finding Signage To be installed by DOT at SBS Bus Stops
MTA Capital Construction