section 7 drawings, conceptual design and design requirement … · 2016. 5. 11. · drawings,...
TRANSCRIPT
Design & Build for Fit-out of
Passenger Terminal Building North Extension
At Macau International Airport (RFQ-221)
Section 7 –
Drawings, conceptual design and
Design Requirement Brief
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING
NORTH EXTENSION AT MACAU INTERNATIONAL AIRPORT
(RFQ-221)
DESIGN REQUIREMENT BRIEF
May 2016
Macau International Airport Co., Ltd. (CAM)
362937 NEA BLD 0011 B
Working Paper 3 - WP3
April 2016
M865-5 Consultancy Services for Automation of Arrival Bags
Working Paper WP3
Submission No.:MOT/M865-5/O/0011/A
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MACAU INTERNATIONAL AIRPORT (RFQ-221)
Design Requirement Brief
May 2016
Macau International Airport Co., Ltd. (CAM)
May 2016 Design Requirement Brief
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
Revision Date Originator Checker Approver Description
- 31 March 2016 Various
Draft
- 26 April 2016 Various Final Draft
- 03 May 2016 Various Final
Issue and revision record
Information class: Secure
This document is issued for the party which commissioned it and for specific purposes connected with the above-captioned project only. It should not be relied upon by any other party or used for any other purpose.
We accept no responsibility for the consequences of this document being relied upon by any other party, or being used for any other purpose, or containing any error or omission which is due to an error or omission in data supplied to us by other parties.
This document contains confidential information and proprietary intellectual property. It should not be shown to other parties without consent from us and from the party which commissioned it.
May 2016 Design Requirement Brief
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
Chapter Title Page
1 Introduction 1
1.1 Overview _________________________________________________________________________ 1 1.2 Abbreviation _______________________________________________________________________ 2
2 Outline Brief 5
2.1 Introduction ________________________________________________________________________ 5 2.2 Services to be provided by the Contractor ________________________________________________ 5 2.2.1 General Scope of Services ____________________________________________________________ 5 2.2.2 General matter covered in the Services __________________________________________________ 6 2.2.3 Services and deliverables specifically required during the work stages of the works ________________ 7 2.3 Technical Schedule _________________________________________________________________ 9 2.3.1 General Requirement ________________________________________________________________ 9 2.3.2 Detailed Design documents __________________________________________________________ 11 2.3.3 Construction documents _____________________________________________________________ 11 2.3.4 As-built documents _________________________________________________________________ 11 2.3.5 BIM Model Files ___________________________________________________________________ 11 2.3.6 Spare materials and parts ___________________________________________________________ 11 2.3.7 Rectifications of Defects and Maintenance During Defects Liability Period ______________________ 11 2.3.8 Net Operational Floor Area ___________________________________________________________ 12 2.3.9 Architectural Building requirements ____________________________________________________ 12 2.3.10 Structural Building requirements ______________________________________________________ 14 2.3.11 Building Services requirements _______________________________________________________ 15 2.3.12 BIM Model requirements ____________________________________________________________ 31 2.3.13 Civil requirements __________________________________________________________________ 32 2.3.14 Requirements of the Works __________________________________________________________ 32
3 Specifications for Architectural and Interior Design Works 35
3.1 Specification ______________________________________________________________________ 35
4 Specifications and Standards for Structure Works 241
4.1 Specification _____________________________________________________________________ 241 4.1.1 Design Load for the Northern Extension ________________________________________________ 241 4.1.2 Design Code _____________________________________________________________________ 242 4.2 Particular Technical Requirements ____________________________________________________ 245 4.2.1 Construction Materials: Cement _____________________________________________________ 245 4.2.2 Construction Materials: Aggregates___________________________________________________ 245 4.2.3 Construction Materials: Concrete ____________________________________________________ 246 4.2.4 Construction Material: Reinforcement _________________________________________________ 247 4.2.5 Formwork and Method of construction _________________________________________________ 248 4.2.6 Placing and Compacting of Concrete __________________________________________________ 249 4.2.7 Sampling and Testing of Concrete ____________________________________________________ 250 4.2.8 Construction Materials: Structural Steel _______________________________________________ 251
Contents
May 2016 Design Requirement Brief
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
4.2.9 Fabrication of Steelwork ____________________________________________________________ 253 4.2.10 Erection of Steelwork ______________________________________________________________ 259 4.2.11 Tolerances ______________________________________________________________________ 260 4.2.12 Touch Up _______________________________________________________________________ 261 4.2.13 Submittals _______________________________________________________________________ 262 4.2.14 Trials ___________________________________________________________________________ 269 4.2.15 Handling, Storage and Transport of Materials ___________________________________________ 270 4.2.16 Construction Materials: Safety Glass__________________________________________________ 271 4.3 Survey of Existing dimensions and levels _______________________________________________ 273
5 Specifications and Standards for Electrical Services 274
5.1 Scope of specification______________________________________________________________ 274 5.1.1 Installations to comply with this general specification ______________________________________ 274 5.1.2 Scope of the installations ___________________________________________________________ 274 5.1.3 Statutory obligations and other requirements ____________________________________________ 274 5.2 Particular Technical Requirements ____________________________________________________ 276 5.2.1 Power Supply and Distribution System_________________________________________________ 276 5.2.2 Essential and Emergency Power System _______________________________________________ 278 5.2.3 Electrical calculations ______________________________________________________________ 279 5.2.4 Uninterruptible Power Supplies (UPS) System ___________________________________________ 279 5.2.5 Lighting System __________________________________________________________________ 280 5.2.6 Earthing and Lightning Protection System ______________________________________________ 282 5.2.7 Lift System ______________________________________________________________________ 283 5.3 Testing and Commissioning _________________________________________________________ 283
6 Specifications and Standards for Fire Services 286
6.1 Specification _____________________________________________________________________ 286 6.1.1 Statutory Obligations and Design Requirements _________________________________________ 286 6.1.2 Particular Requirements ____________________________________________________________ 287 6.2 Testing and Commissioning _________________________________________________________ 288
7 Specifications and Standards for Plumbing and Drainage Services 290
7.1 Specification _____________________________________________________________________ 290 7.1.1 Statutory Obligations and Design Requirements _________________________________________ 290 7.1.2 Particular Requirements ____________________________________________________________ 291 7.2 Testing and Commissioning _________________________________________________________ 293
8 Specifications and Standards for Mechanical Ventilation and Air-conditioning Services 295
8.1 Specification _____________________________________________________________________ 295 8.1.1 Statutory obligations and Design Requirements __________________________________________ 295 8.1.2 Particular Requirements ____________________________________________________________ 296 8.2 Testing and Commissioning _________________________________________________________ 299
9 Specifications and Standards for Airport Systems 301
May 2016 Design Requirement Brief
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
9.1 Scope of Work ___________________________________________________________________ 301 9.2 Design Standards _________________________________________________________________ 303 9.3 Particular Technical Requirements ____________________________________________________ 306 9.4 Testing and Commissioning _________________________________________________________ 324
10 BIM Model Files 327
10.1 Requirements ____________________________________________________________________ 327 10.2 Software Requirements ____________________________________________________________ 327 10.3 Deliverable Requirements __________________________________________________________ 327
11 Specifications and Standards for Civil Works 328
11.1 Scope of Work ___________________________________________________________________ 328 11.2 Design Standards _________________________________________________________________ 328 11.3 Particular Technical Requirements ____________________________________________________ 329 11.3.1 Surveys and Inspections ___________________________________________________________ 329 11.3.2 Bus Staging Area Layout and Configuration _____________________________________________ 329 11.3.3 Site Clearance and Utilities _________________________________________________________ 330 11.3.4 Bus Staging Area Pavement ________________________________________________________ 330 11.3.5 Footpath Island and Pedestrian Canopy _______________________________________________ 332 11.3.6 Surface Water Drainage ____________________________________________________________ 332 11.3.7 Perimeter Fencing ________________________________________________________________ 332 11.4 Testing and Commissioning _________________________________________________________ 333 11.4.1 General _________________________________________________________________________ 333 11.4.2 Pavement Formation ______________________________________________________________ 333 11.4.3 Pavement Works _________________________________________________________________ 333 11.4.4 Drainage Works __________________________________________________________________ 334 11.4.5 Fencing Works ___________________________________________________________________ 334
12 Remote Boarding Gate (Optional) 335
12.1 Introduction ______________________________________________________________________ 335 12.2 Technical Requirement _____________________________________________________________ 336
13 Decorative Solar Film Replacement on Upper Part of Glass Façade in the Airside Departure
Hall 338
13.1 Introduction ______________________________________________________________________ 338 13.2 Work requirements ________________________________________________________________ 338
14 Rectification of Defect Requirements during Defects Liability Period 340
14.1 Requirements ____________________________________________________________________ 340
Appendices 341
Appendix A. Concept Layout __________________________________________________________________ 342 A.1 Concept Layout __________________________________________________________________ 342
May 2016 Design Requirement Brief
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
Appendix B. Room Area and Finishes Schedule ___________________________________________________ 343 Appendix C. Architectural Appendix _____________________________________________________________ 344 Appendix D. Room Data Sheets ________________________________________________________________ 345 Appendix E. Scope of Works carried out by Contract RFQ-198 ________________________________________ 346 Appendix F. Drawings _______________________________________________________________________ 350 F.1 Contract RFQ-198 Drawings for Information ____________________________________________ 350 F.1.1 Architectural _____________________________________________________________________ 350 F.1.2 HVAC __________________________________________________________________________ 352 F.1.3 Electrical Services System __________________________________________________________ 354 F.1.4 Plumbing System _________________________________________________________________ 357 F.1.5 Drainage System _________________________________________________________________ 358 F.1.6 ELV Systems ____________________________________________________________________ 359 F.1.7 Fire Services System ______________________________________________________________ 362 Appendix G. Demolition and A&A Works _________________________________________________________ 363 G.1 Departure Level __________________________________________________________________ 363 G.2 Mezzanine Level _________________________________________________________________ 364 Appendix H. Requirements of Statutory and Detailed Design Documents ________________________________ 365 H.1 DRAWINGS IN ELECTRONIC FORMAT _______________________________________________ 365 H.2 INSTALLATION DRAWINGS ________________________________________________________ 365 H.2.1 Drawing Submission Schedule _______________________________________________________ 365 H.2.2 Size of statutory and detailed design Drawings __________________________________________ 365 H.2.3 Contents of statutory and detailed design Documents and Drawings _________________________ 365 H.2.4 Statutory and Detailed Design Documents and Drawings __________________________________ 366 Appendix I. Requirements of Construction Documents ______________________________________________ 367 I.1 DRAWINGS IN ELECTRONIC FORMAT _______________________________________________ 367 I.2 INSTALLATION DRAWINGS ________________________________________________________ 367 I.2.1 Drawing Submission Schedule _______________________________________________________ 367 I.2.2 Size of Installation Drawings ________________________________________________________ 367 I.2.3 Contents of Installation Documents and Drawings ________________________________________ 367 I.2.4 Builder’s Work Documents and Drawings ______________________________________________ 368 I.2.5 Manufacturer’s Shop Drawings ______________________________________________________ 368 Appendix J. Requirements of As-built Documents __________________________________________________ 370 J.1 DRAWINGS IN ELECTRONIC FORMAT _______________________________________________ 370 J.2 Submission of As–built Drawings _____________________________________________________ 370 J.3 Size of As-built Drawings ___________________________________________________________ 370 J.4 Content of As-built Documents and Drawings ___________________________________________ 370 J.5 Framed Drawings _________________________________________________________________ 371 Appendix K. Requirements of Operation and Maintenance (O&M) Manual and user Manual _________________ 372
i May 2016 Design Requirement Brief
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
1
1.1 Overview
Since the opening of Macau International Airport some 20 years ago,
there are underlying growth in air travel through the airport. The current
terminal and airport site have generally supported the growth in the
operation to date. With the latest recovery and growth in traffic,
expansion of the existing facility shall be built to provide the necessities.
The aforementioned expansion plan includes extension of the existing
Passenger Terminal Building (PTB) to the north of the existing structure
and follows the layout and levels of the existing facility but adding an
additional fourth level to accommodate new office space. It is expected
to accommodate an additional 1,800,000 arriving and departing
passengers a year.
The Arrivals Level will focus on providing additional area in the zones
that require additional processing capacity and remote departure
lounge, while trying to maintain existing facilities.
The Departures Level will be a full build out providing additional area in
the departure lounge, while boosting additional retail and office space.
The extended Mezzanine will provide additional space for departure
lounge, CIP lounge, smoking lounge, offices, retail and food & beverage.
A new office level will be provided to accommodate new office space.
There will be an additional loading bridge connected to the sterile
corridor and the Departures level.
The extension is delivered through a separate Design & Build Contract
for the main structure of the building «RFQ-198» and this Design &
Build Contract for the fit-out of the building «RFQ-221».
The Services to be provided under this Contract comprise the provision
of full design consultancy services and construction services for
the fitting out work project which is intended to provide fit-out works
including architectural, structural, building services works in extension
of the existing Passenger Terminal Building (PTB) and modification,
diversion, alteration and addition works including architectural,
structural, civil, building services works for the diversion areas in Bus
1 Introduction
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
2
staging area, Remote boarding gate and existing terminal of Macau
International Airport.
1.2 Abbreviation
ABWF Architectural and building works and finishes
ACR Automatic Code Reading
ACS Access Control System
AEL Airport Express Line
AODB Airport Operation Database
ATM Air Traffic Movement
BIM Building Information Modelling
BMS Building Management System
CAM Macau International Airport Co., Ltd. (The Authority or
the Employer)
CCTV Closed Circuit Television
CVRM Cost, Value and Risk Management
E&M Electrical and Mechanical
EIA Environmental Impact Assessment
EVA Emergency Vehicle Access
FIDS Flight Information Display System
BMS Building Management System
HoB Head of Stand Road
KPI Key Performance Indicator
LAN Local Area Network
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
3
LMCC Localized Motor Control Centre
LPN Licence Plate Number
LUS Look Up Server
M&E Mechanical and Electrical
MAEDS Machine Automated Explosive Detection System
MCC Motor Control Centre
MCS Manual Coding Station
MCT Minimum Connection Time
MICS Management Information and Control System
mppa million passengers per annum
OEM Original Equipment Manufacturer
OOG Out of Gauge
O&M Operation and Maintenance
PA Public Address PLC Programmable Logic Controllers
PMU Pricing Make-Up
PS Particular Specification
PTB Passenger Terminal Building
PTS Particular Technical Specification
QAP Quality Assurance Plan
RBAS Reclaim Belt Allocation System
REE Registered Electrical Engineer
RF Radio Frequency
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
4
RFID Radio Frequency Identification
RGE Registered Geotechnical Engineer
RHO Ramp Handling Operator
RSE Registered Structural Engineer
RTF Remote Transfer Facilities
STA Scheduled Time of Arrival
STD Scheduled Time of Departure
T&C Testing and Commissioning
TODC Time of Day Clock
TMR Trunk Mobile Radio
TRMICS Total Replacement Management Information and
Control System
UID Unique Identification Tag
ULD United Load Device
VSU Vertical Sort Unit
WP Working Paper
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
5
2.1 Introduction
The Services to be provided under this Contract comprise the provision
of full design consultancy services and construction services for
the fitting out work project which is intended to provide fit-out works
including architectural works, structural works, building services works,
systems works and landscaping works in extension of the existing
Passenger Terminal Building (PTB) and modification, diversion,
alteration and addition works including architectural works, structural
works, civil works, building services works, systems works and
landscaping works for the diversion areas in Bus staging area, Remote
boarding gate and existing terminal.
The Contract shall include for all floors of north extension including but
not limited to office areas, public areas, processing areas, VIP and CIP
areas, back of house areas, hard and soft landscape at the
surroundings of north extension and appropriate design and build
reserves shall be provided to the retail areas.
2.2 Services to be provided by the Contractor
2.2.1 General Scope of Services
The works to be designed and built by the Contractor under this
Contract (the Works) comprise the fit-out works and alteration and
addition (A&A) works which shall include the following:
(a) Design of fit-out works including architectural, structural,
building services works, systems works, landscaping works for
the extension of the existing Passenger Terminal Building
(PTB);
(b) Design of modification, diversion, alteration and addition works
including architectural, civil, structural, building services works,
systems works, landscaping works for the diversion areas in
Bus staging area, Remote boarding gate and existing terminal;
(c) Design coordination with Government departments, CAM,
airport operators and stakeholders, and existing contractors,
Project RFQ198 contractor and consultants;
(d) Liaison with the public utilities companies, other authorities or
public bodies and consultants;
(e) Liaison among the contractors, Project RFQ198 contractor, the
client departments and Government Representatives in relation
to the fit-out works and alteration and addition works;
2 Outline Brief
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
6
(f) Undertaking of all necessary surveys and site investigations,
levels and surroundings for the purpose of or in connection with
the fit-out works and alteration and addition works;
(g) Preparation, vetting and submission of «Statutory Design»,
«Detailed Design» documents (as set out in the Section 2.3.2
of this Brief);
(h) Provision of a detailed programme for the fit-out works and
construction method statements for the fit-out works and to
address any comments on either of which made by
Government, CAM, airport operators and stakeholders, project
manager;
(i) Preparation, vetting and submission of «Construction»
documents (as set out in the Section 2.3.3 of this Brief);
(j) Preparation, vetting and submission of «as-built» documents
(as set out in the Section 2.3.4 of this Brief);
(k) Preparation, vetting and submission of «BIM Model»
documents (as set out in the Section 2.3.5 of this Brief);
(l) any other works described in the following sections of this
Design Brief.
2.2.2 General matter covered in the Services
(a) Statutory procedure
a. Preparation of relevant documents and provisions of
necessary input to complete the statutory procedure,
including resolving objections and revisions of design
and construction to obtain statutory approval.
(b) Employment of specialist consultants
a. Proposals for agreement by the Client if specialist
consultants to be employed by the Contractor.
(c) General submissions for designs
a. Recommendation of design criteria in consultation with
all maintenance and operating departments.
b. Submission of design memoranda to maintenance and
operating departments.
c. Surveys, site investigations, certificates, testings and
independent third party verification/checking if
necessary.
d. Submission of statutory designs, detailed designs –
particular requirements as required by Government,
CAM, airport operators and stakeholders, project
manager.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
7
(d) The Contractor shall verify as-built drawings to ensure that any
inaccuracies and/or lack of detailed information within the as-
built records at early stage of the design process. The
contractor shall carry out survey works as necessary to ensure
the complete integrity of the as-built information on which the
Contractor design is based on.
(e) The Contractor shall submit design proposal on any
modifications to existing elements for CAM Project Manager for
review and approval prior to commencement of works.
(f) The Contractor shall prepare statutory submissions and obtain
approval for their design proposal. The Contractor shall make
such submissions in good time as to ensure there is no delay to
the Works. The Contractor shall be solely responsible for any
delay due to late receipt of such permits, consents or approvals.
(g) The Contractor shall reinstate any damage during construction
and make good finish to existing elements
(h) The Contractor shall comply with the design standards,
statutory requirements and technical requirement as specified
in the specification.
2.2.3 Services and deliverables specifically required during the
work stages of the works
(a) Workstage 1 – Statutory Design Stage
a. Coordinate with stakeholders for developing design
details.
b. Submission of plans, elevations, calculations, reports
for information and review of design and progress of
design development.
c. Prepare, update and submit reasonably accurate and
timely estimates and cash flow forecasts when required
by CAM Project manager.
d. Provide necessary input for preparing the materials,
details and updated project programme when required
by CAM Project manager.
e. Submission of all necessary drawings and documents
to the authorities for obtaining statutory approval of the
design.
(b) Workstage 2 – Detailed Design Stage
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
8
a. Submission of plans, elevations, calculations, reports
for information and review of design and progress of
design development.
b. Prepare, update and submit reasonably accurate and
timely estimates and cash flow forecasts when required
by CAM Project manager.
c. Preparation, vetting and submission of «Detailed
Design» documents (as set out in the Section 2.3.2 of
this Brief);
d. Provide necessary input for preparing the materials,
details and updated project programme when required
by CAM Project manager.
e. Preparation, vetting and submission of «Construction»
documents (as set out in the Section 2.3.3 of this Brief).
(c) Workstage 3 – Construction Stage
a. Submission of monthly financial statements giving
actual and forecast expenditure, cash flow.
b. Submission of monthly programme, progress report
and construction method statements. A covering report
and progress photographs, specific to the fit-out works
shall be provided.
c. Provide estimate and forecast of expenditure and
report progress on expenditure for the processing and
draft estimates.
d. Submit proposals on the investigation and
implementation of prompt mitigation measures.
e. Submission of Shop drawings with installation details,
combined building services drawings and combined
builder works drawings associated with the fit-out
works for CAM Project manager consent prior to
ordering and installation of any fit-out works.
f. Preparation, vetting and submission of «as-built»
documents (as set out in the Section 2.3.4 of this Brief).
(d) Workstage 4 – Post Handover Services
a. Submission of maintenance manuals and operating
manuals upon completion of the fit-out works.
b. Submission of programme reports of the maintenance
and defect rectification works on quarterly basis or at
times as required by the CAM Project manager.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
9
2.3 Technical Schedule
2.3.1 General Requirement
The Contractor shall comply with the following general requirements to
the satisfaction of the CAM Project manager:-
(a) The fit-out works areas and alteration and addition areas shall
be designed and constructed in accordance with good practice
generally and to the particular requirements set out in this
Design Brief and in such a way that future maintenance costs
are minimized and to a standard at least as high as that
achieved in comparable terminal-built facilities and
government-built facilities. Materials and workmanship for all
finishes and features that form an integral part of the fit-out
works areas shall require minimum maintenance and shall
comply with all standards indicated herein or as may be
required by the CAM Project manager, and shall be compatible
with the finishes and features of other integral or adjacent
accommodation within the development.
(b) The Works shall comply with Macau Law and Regulations, all
specification, codes of practice relevant to public works
contracts in Macau, the requirements of the ICAO and relevant
international standards and in particular the specifications and
standards listed in Sections 3 to 9 of this design brief. The
Contractor shall submit a list of standards proposed for the
Works which shall be subject to review without objection by the
CAM Project manager before use. In the event that the CAM
Project manager does not accept the Contractor’s proposed
standards or specifications, CAM shall have the absolute
discretion to specify the standards to be used for the Works.
(c) The Contractor shall ensure that all elements of the design and
build for the Works are fully coordinated and integrated and
that the design is accurately recorded in the deliverables
required. The design and build of the Works shall
incorporate all requirements resulting from the resolution of
interface matters with all other parties who have a relation to
the Works.
(d) The Contractor shall at every stage of the design and build
development process assume full responsibility for liaison
and coordination with all user departments, all stakeholders,
all Relevant Authorities and other relevant parties and shall
develop and finalise details in the client / user brief. The
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
10
Contractor shall also be responsible for the design, build and
development of detailed room data sheets (RDS) to include all
requirements from user departments, all stakeholders, all
Relevant Authorities and other relevant parties.
(e) The Contractor shall prepare presentation papers and drawings
and make presentations to the various user departments as
and when requested by the CAM Project manager.
(f) The Contractor shall submit full details of his design proposals
for CAM Project manager to review without objection at
schematic design, detail layout plan and elevation plans at
various design stages. All proposed finishing materials and
building services installations (with samples on request) shall
be submitted for CAM Project manager to review without
objection prior to the placement of orders.
(g) The submission of design details to or the inspection of the
construction works by, or any pertaining comments by the CAM
Project manager shall not relieve the Contractor from his
responsibility for satisfactory compliance with the above
stipulations and requirements under this design brief.
(h) At the end of each design and build stage, as agreed with
the CAM Project manager, the Contractor shall set up a
series of detailed briefing meetings with all relevant project
stakeholders or users to run through drawings in detail
explaining and demonstrating, with the use of renderings,
computer generated perspectives and physical working
models, as and where appropriate, exactly how the user
requirements have been implemented and illustrating how
user comments have been incorporated in the design and
build works.
(i) The Contractor shall arrange special site inspections and
meetings:-
a. Before substantial completion,
b. Upon substantial completion,
c. Prior to handover,
d. For handover,
e. At the end of the Defects Liability Period – for briefing(s)
on specific electrical/ mechanical and/or other
installations, to be attended by other Government
Departments, airport operators, stakeholders and as
required by the CAM Project manager.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
11
2.3.2 Detailed Design documents
The Contractor shall provide detail design documents in accordance
with the requirements in Appendix C of this Design Brief.
2.3.3 Construction documents
The Contractor shall provide construction documents in accordance
with the requirements in Appendix D of this Design Brief.
2.3.4 As-built documents
The Contractor shall provide as-built documents in accordance with the
requirements in Appendix E of this Design Brief.
2.3.5 BIM Model Files
The Contractor shall provide the BIM Model files in accordance with the
requirements in Section 10 of this Design Brief.
2.3.6 Spare materials and parts
The Contractor shall provide 30 days of the date of handover of the
completed portion(s) of the fit-out works areas to the CAM the following
spare materials and parts to the CAM Project manager:-
(a) Spare and special tools for 1-year operation and maintenance
of all the E&M plant and equipment, a list of which shall have
been agreed by the CAM Project manager;
(b) Materials which in the opinion of the CAM Project Manager are
not readily available in the market, with quantities to be
determined by CAM Project manager.
2.3.7 Rectifications of Defects and Maintenance During Defects
Liability Period
The Contractor shall be responsible for the full rectification of Defects
and maintenance of the installation during the Defects Liability Period.
Detailed requirements are Section 14 of this Design Brief.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
12
2.3.8 Net Operational Floor Area
For the purpose of this Technical Schedule, the Net Operational Floor
Area shall, unless otherwise stated, be taken as the total floor area fit-
out works areas allocated to a user for carrying out the intended
activities, excluding any structures and partitions, circulation areas,
staircases, staircase halls, lift landings, space occupied by toilet
facilities, mechanical and electrical services such as lifts and air-
conditioning systems unless otherwise stated.
2.3.9 Architectural Building requirements
Design / Shop drawings
Contractors shall submit a full set of Design documents:
(a) List of documents
(b) Design criteria (according to Macau / HK / international
standard and regulation, where Macau standard and regulation
should be the first priority to be applied)
(c) Drawings (including construction details in coordination with
existing installations).
(d) Specifications
(e) Equipment schedule
(f) Design finishing schedule
(g) Catalogues for main equipment’s
(h) Calculations and justification (Ex: Hydraulic, cooling, exhaust,
fresh air and ventilation, power supply load, lighting levels,
emergency evacuation routings, etc.)
Scope of Work:
The Contractor shall design, supply, furnish, install, test & commission
all required materials, equipment, fixture, furniture and miscellaneous
accessories necessary to complete the construction for fitting out works
for passenger terminal building (PTB) north extension as specified. No
matter mentioned or not, the Contractor shall completely execute the
detailed works according to the final design.
The fitting out works for the PTB north extension includes ground, M,
first, second and third floors. The fitting out areas of each floor can be
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
13
referred to the highlighted area of the attached reference drawings with
the conceptual layout (drawing no.: MMH-365511-A-C-000-1100~1500).
These drawings are for reference only and final configuration shall
subject to design coordination after contract award.
Ground Floor (Arrival Level):
The ground floor shall include the areas as shown in the attached
reference drawing (drawing no.: MMH-365511-A-C-000-1100). And the
corresponding room areas shall be referred to the area schedule for
reference.
M Floor (Sterile Corridor Level):
The M floor shall include the sterile corridor. The corresponding area
shall be referred to the attached reference drawing (drawing no.: MMH-
365511-A- C-000-1200) for reference.
First floor (Departure Level):
The first floor shall include the areas as shown in the attached
reference drawing (drawing no.: MMH-365511-A-C-000-1300). And the
corresponding room areas shall be referred to the area schedule for
reference.
Second Floor (Mezzanine Level):
The second floor shall include the areas as shown in the attached
reference drawing (drawing no.: MMH-365511-A-C-000-1400). And the
corresponding room areas shall be referred to the area schedule for
reference.
Third Floor (Office Level):
The third floor shall include the areas as shown in the attached
reference drawing (drawing no.: MMH-365511-A-C-000-1500). And the
corresponding room areas shall be referred to the area schedule for
reference.
Design Work
All necessary design work shall be included for completing the project.
The full set design shall include but not be limited to the followings:
design, calculation, drawings, material list, specification, catalogue for
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
14
equipment/furniture/fixture, testing report. The full set design should be
signed by Macau Registered Engineer and approved by Government
Authorities and project related entities. The conceptual layout
plan/drawing is just for reference, the final design should be approved
by related entities. The design criteria are according to Macau / HK /
international standard and regulation, where Macau standard and
regulation should be the first priority to be applied. All design shall be
HIGH CLASS and GOOD QUALITY.
All necessary architecture works for completing the project as in the
design, including but not being limited to the above areas.
2.3.10 Structural Building requirements
The fit-out works areas and alteration and addition areas shall be
designed and constructed to the satisfaction of the CAM Project
Manager and to incorporate, inter alia, the following structural
requirements wherever applicable:-
(a) The Contractor shall verify as-built drawings to ensure that any
inaccuracies and/or lack of detailed information within the as-
built records at early stage of the design process. The
Contractor shall carry out survey works as necessary to ensure
the complete integrity of the as-built information on which the
Contractor design is based on.
(b) The fit-out works loading shall not exceed the design load listed
in clause 4.1.1 or the capacity as per checking of as-built
information by the Contractor. The Contractor shall
demonstrate the fit-out works fulfil the loading requirements.
(c) The Contractor shall submit design proposal on any
modifications to existing structural elements for CAM Project
Manager for review and approval prior to commencement of
works.
(d) The Contractor shall provide design proposal when loading for
fit-out work exceed existing design load and/or alternation to
existing structural elements is required. Design proposals shall
include design calculations to justifying the capacity of existing
structures and method statement of construction for the
proposed works, which shall be agreed by CAM Project
Manager. If such permission is granted, all beams or other
members of the structure which are subjected to loading other
than the design loading shall be strengthened and supported to
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
15
the satisfaction of the Project Manager and the Contractor shall
be responsible for any extra expenses.
(e) The Contractor shall have to prepare statutory submissions and
obtain approval for their design proposal. The Contractor shall
make such submissions in good time as to ensure there is no
delay to the Works. The Contractor shall be solely responsible
for any delay due to late receipt of such permits, consents or
approvals.
(f) The Contractor shall reinstate any damages during construction
and make good finish to structural elements
(g) The fit out work shall comply with the design standards,
statutory requirements and technical requirement as specified
in the specification.
(h) Carry out any necessary tests including concrete cube tests,
steel reinforcement tests and make submission of test reports,
construction records.
2.3.11 Building Services requirements
The fit-out works areas and alteration and addition areas shall be
designed and constructed to the satisfaction of the CAM Project
Manager and to incorporate, inter alia, the following Building Services
requirements wherever applicable:-
(a) Environmental and Building services shall be provided in
accordance with the requirements listed in the Appendixes to
this Design Brief or as may be approved by the CAM Project
Manager.
a. For each party's office areas and processing areas, the
building services inside the areas shall be solely for
and directly serving the areas.
(b) The Contractor shall verify as-built drawings to ensure that any
inaccuracies and/or lack of detailed information within the as-
built records at early stage of the design process. The
Contractor shall carry out survey works as necessary to ensure
the complete integrity of the as-built information on which the
Contractor design is based on. The Contractor shall submit
survey reports to CAM Project Manager.
(c) The provisions shown on the Room Data Sheets attached in
this Design Brief are for reference only. The Contractor shall
at every stage of the design and build development process
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
16
assume full responsibility for liaison and coordination with
all user departments, all stakeholders, all Relevant Authorities
and other relevant parties and shall develop and finalise details
in the client / user brief. The Contractor shall also be
responsible for the design, build and development of detailed
room data sheets (RDS) to include all requirements from user
departments, all stakeholders, all Relevant Authorities and
other relevant parties. The finalised RDS shall obtain no
objection from the CAM Project Manager before construction
on site.
(d) All equipment installed for each department in each group
location shall be operated solely for each department.
(e) All equipment shall be easily accessible and adequate space to
be provided for servicing and replacing equipment.
(f) The Works shall aim to comply with «Manual de Procedimentos
Técnicos para Conservação de Energia em Edifícios de
Macau» developed by DSSOPT for the Works. At the end the
Works, necessary measurement for the Works areas shall be
provided and survey report shall be submitted by this
Contractor to CAM Project Manager.
2.3.11.1 Mechanical Ventilation and Air-conditioning Services requirements
The Mechanical Ventilation and Air-conditioning Services installations
for fit-out works and alteration and addition works shall include, but not
limited to, the following:
(a) This includes the works of the Mechanical Ventilation and Air-
conditioning Services installation that the Contractor shall
design, supply, install, testing and commissioning of the entire
Mechanical Ventilation and Air-conditioning Services
installation as specified in this contract.
(b) Mechanical Ventilation and Air-conditioning to be provided to
areas as referenced in the Room Data Sheets.
(c) The provision of air conditioning, except the primary air and
chilled water supply that may be centrally supplied by the
building, shall be segregated to serve each group of areas by
department or party and separately metered and controlled for
each group of areas by department or party.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
17
(d) The system shall be acoustically treated to achieve a noise
level of NC 40 maximum inside the air-conditioned area and the
air quality and the noise level shall meet the current
requirements of Macau Law, Regulations and Guidance. At the
end the Works, necessary measurement for the Works areas
shall be provided and survey report shall be submitted by this
Contractor to CAM Project Manager.
(e) The system shall achieve IAQ requirements in the IAQ
Guidance issued by the Direcção dos Serviços de Protecção
Ambiental (DSPA). At the end the Works, necessary
measurement for the Works areas shall be provided and survey
report shall be submitted by this Contractor to CAM Project
Manager.
(f) For the PAU solely serves the area, CO2 sensors shall be
provided for demand control.
(g) Where mechanical ventilation is required, it shall achieve
adequate air change rates in accordance with the room data
sheet and the ASHRAE standard. The air quality and the noise
level of such system shall meet the current requirements of
Macau Law, Regulations and Guidance.
(h) The location of any exhausts shall not case nuisance to users
of facility, or the general public.
(i) All thermal insulation for air duct, chilled water pipe works and
raised floor slab shall be either Phenolic Foam or Flexible
closed cell elastomeric insulation.
2.3.11.2 Electrical Services requirements
The electrical services installations for fit-out works and alteration and
addition works shall include, but not limited to, the following:
(a) This includes the works of the electrical services installation
that the Contractor shall design, supply, install, testing and
commissioning of the entire electrical services installation as
specified in this contract.
(b) Demolition/ reinstatement/ diversion/ modification of existing
electrical services installations to suit the renovated E&M
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
18
installation/ architectural layout/ structural layout/ site
conditions/ construction progress etc. and for any demolition of
existing redundant electrical installation, it shall be removal off
site with prior approval from CAM Project Manager
(c) Electrical meter room/ cupboard shall be provided for exclusive
use of the different parties. Electricity supply to each unit shall
be independently metered for each group of areas by user
department or party
(d) Sufficient energy meters shall be provided for each user
department in each group location for energy usage record and
electricity consumption record.
(e) Artificial illumination shall be provided to levels as
recommended by the relevant lighting guides published by the
Chartered Institution of Building Services Engineering. LED
tube lighting and LED type downlight shall be provided at the
fit-out areas and alteration and addition areas, except the
unmanned area (e.g. plant room, equipment room) where T5
tube with electronic ballast shall be provided.
(f) Recessed type luminaires shall be provided in areas with
suspended ceiling.
(g) Sufficient numbers of self-contained emergency luminaires
shall be provided according to Macau Law and Regulations, BS
5266 and BS EN 60598.
(h) Motion sensors (i.e. dual sensor type with by-pass function)
shall be provided at all male/ female showing, locker area,
toilets, associate common corridors and pantry, where
minimum lighting level shall be maintained for security guard
patrol purpose and means of escape requirements.
(i) Day light sensors shall be provided at the zone near to window
with day lighting source for automatically dimming the lighting
down to acceptable level.
(j) Power points shall be provided to rooms and areas as indicated
in the Room Data Sheets. Spare sockets shall be provided for
each room in addition of the requirement stated on Room Data
Sheets:-
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
19
Room Size No. of Socket Outlet(s)
10 sq. m or below
1 socket outlet
Above 10 sq. m
1 socket outlet per each 10 sq. m
All electrical provisions, including socket outlets, inside any
area having water/ weather damage potential shall be
waterproof/ weatherproof.
(k) Electrical provisions to be provided to areas as referenced in
the Room Data Sheets.
(l) The Contractor shall verify if existing electrical system is
suitable for the Works at early stage of the design process. The
Contractor shall carry out survey works as necessary to ensure
the complete integrity of the as-built information on which the
contractor design is based on. The Contractor shall submit
survey reports and design reports to CAM Project Manager.
(m) The Contractor shall design and build an electrical system for
the Works based on the existing electrical system for extension
of the existing Passenger Terminal Building (PTB), Bus staging
area, Remote boarding gate and existing terminal. The
electrical system will cover the demolition, diversion,
modification and addition of HV/LV transformer, HV and LV
switchboards, generator and associated electrical distribution
systems, the LV main switch room; and associated
distribution electrical rooms at Macau Airport PTB Expansion
Area and existing terminal; the fixed link bridge and airbridge
facilities. All excavation, diversion and reinstatement works if
required shall be deemed to be included in the cost provisions
for this power supplies arrangement.
(n) The Contractor shall provide an 11kV/LV transformer unit with
at least 1600kVA power capacity connected to existing HV
switchboards and provide associated electrical system. The
capacity shall be based on electrical load estimation of
extension of PTB for this Works. The electrical loadings shall
be fed from the existing and new 11kV/LV transformers.
(o) The Contractor shall submit the electrical calculations includes
but not limited to the follows:-
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
20
a. Overall electrical load estimation of extension of PTB
with all loadings in this Works: The calculation shall
include normal, essential and emergency power
distributions on transformer(s) and generator(s);
b. Electrical load estimation with all loadings in this Works:
The calculation shall include normal, essential and
emergency power distributions on transformer(s) and
generator(s);
c. Cable and busduct Sizing calculation;
d. Cable containment Sizing calculation;
e. Power system discrimination calculation;
f. Earthing and lightning calculation;
g. Lighting calculation;
h. UPS sizing and battery sizing calculations; and
i. Generator system calculations (if generator set(s) is
modified and added);
i. Generator sizing and fuel supply system
calculation;
ii. Air Pressure Drop Calculations of Generator
system;
iii. Acoustic Treatment Calculation for Generator
Rooms;
iv. Exhaust Back Pressure Calculation for
Generator; and
v. Acoustic Calculation for Exhaust System of
Generator
(p) The Contractor shall provide the Low Voltage (LV) Power
supplies and Distribution System.
(q) The Contractor shall provide General Lighting, Essential and
Emergency Lighting System for office areas and smoking
lounge and modified public area, airside facilities and landside
office/ store area, Back of House area, roof area and plant
rooms in the fit-out areas, .
(r) The Contractor shall be responsible to check the weight
allowed for lift car decoration of the existing lift systems for
stone replacement work. The overall weight of the new stone lift
car floor shall be within the weight allowed for lift car decoration.
The details of the stone replacement work are shown on
Architectural section in this design brief.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
21
(s) The Contractor shall provide the UPS System Installation for
new ELV/ server rooms as well as the CCTV rooms which
related to the Works.
(t) The Contractor shall provide power supplies to all related MEP
systems, Airport ELV Systems, Isolators; Fused Spur Units and
Socket Outlets for Small Power System for the Works.
(u) The Contractor shall provide the Cable Containment System
including cable ladders, cable trays and surface and
concealed type conduit system with mounting and support
accessories for the Works.
(v) The Contractor shall provide the complete Electrical Earthing
and Clean Earthing System for the Works.
(w) The Contractor shall provide Lightning Protection System
Facilities for the Works.
(x) The Contractor shall provide the appropriate demolition
works and manage waste disposal services; adjust any
electrical system elements and items in the existing
interfacing boundary of the existing PTB building to facilitate
for the Works.
(y) The Contractor shall be responsible to liaise with the base
building Contractor for interfacing and connection of new
design, supply and install electrical installation to existing
electrical installation at the Contractor own cost.
(z) The Contractor shall be responsible for the coordination with
other trades to enable the installation works, including
coordination with reflected builder's work. The setting out of the
E&M and electrical installations shall be based on the reflected
builder's work and layout in acceptance to CAM Project
Manager.
2.3.11.3 Fire Services requirements
The fire services installation for this fit-out contract shall include, but not
limited to, the following:
(a) This includes the works of the fire services installation that the
Contractor shall design, supply, install, testing and
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
22
commissioning of the entire fire services installation as
specified in this fit-out contract.
(b) Demolition/ reinstatement/ diversion/ modification of existing
fire services installations to suit the renovated E&M installation/
architectural layout/ site conditions/ construction progress etc.
and for any demolition of existing redundant FS installation, it
shall be removal off site with prior approval from CAM Project
Manager.
(c) Modify/ divert/ make additional provisions/ replace and reinstate
the existing installed equipment to the FS installation to suit the
latest architectural layout, interior design and updated reflected
ceiling plan.
(d) All modification/ revision/ additional works required on the FS
installation shall be included in the Contractor’s tender price.
(e) The Contractor shall be responsible for the protection of
existing F.S. installation.
(f) The Contractor shall be responsible to liaise with the base
building Contractor for interfacing and connection of new
design, supply and install FS installation to existing FS
installation at the Contractor own cost.
(g) The Contractor shall be responsible for the coordination with
other trades to enable the installation works, including
coordination with reflected ceiling plans. The setting out of the
E&M and FS fittings on the false ceiling shall be based on the
reflected ceiling plans and layout in acceptance to CAM Project
Manager.
(h) The Contractor shall be responsible for the design, supply and
installation of sprinklers with all associated pipework and all
necessary accessories to complete the works under this contract.
(i) Design, supply and installation of concealed type sprinkler with
all associated pipework and all necessary accessories on false
ceiling to suit latest layout and to complete the works. All
concealed sprinkler heads colour should match the colour of
the adjacent ceiling and refer to Architecture reflected ceiling
plans. Final approval of colour shall be required by the CAM
Project Manager consent prior to installation.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
23
(j) Design, supply, installation and modification works of sprinkler
heads and associated pipework within ceiling void.
(k) Design, supply, installation and modification works of sprinkler heads under obstruction to suit new E&M installation.
(l) Design, supply, install and modify fire hydrant system with all associated pipework together with associated fire hydrant outlets, F.S. inlets and all necessary accessories to complete the works.
(m) Design, supply, install and modify hose reels with all associated pipework together with associated alarm bells, break glass unit and visual fire alarm with wiring and all necessary accessories to complete the works.
(n) Design, supply, install and modify automatic fire detection and alarm system including detectors, break glass units, alarm bells, visual fire alarm, power supply units, and all necessary equipment and accessories to complete the works. The Contractor shall ensure the proposed materials shall be fully compatible with existing AFA system of base building and this Macau Airport Passenger Terminal Building (PTB) North Extension.
(o) Design, supply and install of clean agent fire extinguishing system for protection of Electrical/ELV equipment rooms and plantrooms with all associated pipework, discharge nozzles, gaseous storage cylinders together with associated control panel, alarm bells, break glass unit, detectors, manual release button, lock off unit and visual fire alarm with wiring and all necessary accessories to complete the works. This system signal shall be full repeated back to this extension building AFA panel in addition to base building control centre AFA panel.
(p) The Contractor shall be responsible for the make good of the existing FS installation which is affected under the works to the satisfaction of CAM Project Manager.
(q) Design, supply and install portable fire extinguishers and fire blankets.
(r) Submission of survey drawings, shop drawings, calculations, sample boards, materials catalogues, as-built drawings, testing and commissioning records, operation and maintenance manuals.
(s) Contractor shall be responsible for the interfacing works with MVAC trade.
(t) The Contractor shall be responsible to set works the FS system including all necessary testing and balancing exercise to obtain the designed performance and to handover in good working
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
24
order of the complete system.
(u) The Contractor shall be responsible to provide testing and commissioning of all equipment and system and training to the management company staff. Carry out performance evaluation of equipment/ systems supplied/installed.
(v) The Contractor shall be responsible to ensure that the final installation of the designed, supplied and installed FS system is in full compliance in accordance with the requirements of Relevant Government Authority and any other requirements and regulations. The Contractor shall be responsible of invitation of fire services inspection and obtaining the relevant Certificate of Government Authority for the complete fire services installation undertaken by then and shall be responsible for all statutory submission; the contractor shall be responsible to submit the Form of “Notification to fire services department on the occasion building FSI is shut down for work: to fire services department for suspension of system during construction period.
(w) The Contractor shall inform the CAM Project Manager well in advance of any necessary change of pipe sizes or F.S. layout in order to suit the site conditions. The Contractor shall be held responsible for the taking down and re-fixing works without charges to the Employer.
(x) Incidental works and attendance to works design, supply, installation and inspection by relevant government authorities are required
(y) The Contractor shall include all necessary costs in water discharging and re-charging from the existing FH/HR and sprinkler system of existing system in order to carry out the interfacing connection, testing and commissioning works and FS inspection. Precaution work shall be provided to the satisfaction of the CAM Project Manager prior to the execution of work.
(z) The Contractor shall include the costs in order to carry out the software re-programming of the deleted and additional of designed, supplied and installed of AFA devices, testing/ commissioning and FS inspection if necessary and the re-programming of the existing Fire Alarm panel shall only be carried out in a time period which is agreed with CAM Project Manager.
(aa) The Contractor shall be responsible for testing and Commissioning of the entire fire services installations including but not limited to the modification areas of the existing fire services installations, fire detection and alarm system, fire hydrant / hose reel system, portable fire extinguishers, emergency lighting and exit signs, emergency power, VAC
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
25
control system, fire shutters, audio visual advisory system. Phasing of the testing and commissioning, if any, should be included.
(bb) The Contractor shall be responsible for the safe guard of the portable equipment design, supply and installed under this contract until the handover of such equipment including the current existing installation. Portable equipment installed for fire services department’s inspection(s) shall not be regarded as being handed over.
(cc) The Contractor shall provide for, make good for, and supervise all builders' work required, including drilling and plugging of walls, floors and ceilings for securing of brackets, and other builders' work as is considered normal to the trade.
(dd) The Contractor shall provide and allow sufficient arrangement for working overnight at site whenever it is considered necessary or as requested by CAM Project Manager.
(ee) Provide maintenance and emergency repair services during the
defect liability period (DLP) including submission of all statutory
documents and drawings.
(ff) All statutory submission for fire services systems including
submission of forms, documents, drawings and calculations.
The Contractor shall be responsible for signing all fire services
certificates in accordance with the requirements and
regulations from the relevant Government Authorities. Attend all
statutory inspections as required.
(gg) Supply, installation and modification works of sprinkler heads
under obstruction to suit new E&M installation.
2.3.11.4 Plumbing and Drainage Services requirements
The plumbing and drainage installation for this fit-out contract shall include, but not limited to, the following:
(a) This includes the works of the plumbing and drainage system that the Contractor shall design, supply, install, testing and commissioning of the entire plumbing and drainage system as specified in this fit-out contract.
(b) The works shall be carried out in a good manner to the satisfactory of CAM Project Manager.
(c) The Contractor shall design, supply and install the plumbing water system including but not limited to pipeworks, valves, fittings, energy meter, motorized valve, water tank, water pump, pneumatic tank, local motor control panel and all necessary
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
26
accessories where as necessary to form a complete and healthy system.
(d) The Contractor shall design, supply and install complete soil, waste water and vent disposal systems including but not limited to floor drains, pipeworks, fittings, stainless steel holding tank, submersible pump, level sensor, local motor control panel and all necessary accessories where as necessary to form a complete and healthy system.
(e) The Contractor shall design, supply and install under basin sump pump system complete with submersible pumps, stainless steel holding tank, local motor control panel, pipeworks, fittings, level sensor and all necessary accessories where as necessary to form a complete and healthy system for remote and isolated basin where gravity drainage is not viable. The discharge of this pumped system connected to gravity drainage network shall be provided with pressure relief treatment of change in state from pressurized to gravity flow prior to entering the gravity network. This drainage provision arrangement shall subject to the approval and acceptance by CAM Project Manager prior to installation.
(f) Provision of all steel sleeves and puddle flanges as required by the plumbing and drainage installation.
(g) The Contractor shall provide for, make good for, and supervise all builders’ work required, including drilling and plugging of walls, floors and ceiling for securing of brackets, and other builders’ work as is considered normal to the trade.
(h) The Contractor shall provide and allow sufficient arrangement for working overnight at site whenever it is consider necessary/requested by CAM Project Manager.
(i) Set to work the plumbing and drainage system including all necessary testing and balancing exercise to obtain the designed performance and to handover in good working order of the complete system.
(j) Provide the balancing, test and commissioning of all equipment and system and training to the management company staff. Carry out performance evaluation of equipment/systems supplied/installed.
(k) The Contractor shall be responsible to ensure that the final installation is in full accordance with the requirements of Relevant Government Authority and any other requirements and regulations. The Contractor shall be responsible of invitation of Water Authority and obtaining the relevant Certificate of Government Authority for the complete plumbing and drainage installation undertaken by them and shall be responsible for all statutory submission.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
27
(l) The Contractor shall inform the CAM Project Manager will in advance of any necessary change of existing pipe size or plumbing and drainage layout in order to suit the site conditions. The Contractor shall be held responsible for the taking down and re-fixing works without charges to Employer.
(m) Testing and commissioning for the entire installation and submit the pipework hydraulic test report to the CAM Project Manager for approval.
(n) Provision of painting and labelling of all equipment, pipeworks and materials in accordance to requirement as stated in this specification.
(o) Incidental works and attendance to works design, supply, installation and inspection by relevant government authorities are required.
(p) The Contractor shall be responsible for liaison with all statutory authorities to obtain all necessary certificates and approvals including the completion, preparation and submission of all forms, calculations, drawings, and other documents necessary for submission purpose and payment of any fees and charge. All the costs for each of the tests required by various statutory authorities shall be included.
(q) The Contractor shall seal all gaps and openings around all sleeve-free service pipes/ducts/cables and outer surface of sleeves with approved fire resisting mastic. Whilst, the gaps between the inner surface of pipe sleeves and the services pipes/ducts/cables shall be sealed up with approved fire resisting and/or waterproof mastic.
(r) The Contractor shall be responsible for checking the actual site conditions during installation works. The Contractor shall coordinate with the other services trades to determine the exact positions of the services without conflict. The Contractor shall be responsible for carrying out adjustment on routing of pipework due to the actual site requirements. The adjustment shall be in no way having any contradiction to the statutory requirements.
(s) The Contractor shall coordinate on site for exact routing for the new plumbing and drainage pipes with existing services installed. For any existing services such as support to existing services, the Contractor shall inform the CAM Project Manager well in advance of necessary change of existing services in order to suit the new installation. The Contractor shall be held responsible for the taking down and re-fixing works without charging the supporting system for the existing services to Employer.
(t) All plumbing and drainage supply and installation work shall be in full compliancy to the satisfactory of statutory bodies
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
28
requirement.
(u) Design, supply, install and connection to all the interfacing points with existing BMS system. The dry contact shall be compatible with existing BMS system.
(v) The Contractor shall be responsible to sterilize, clean and flush down of the completed plumbing system including but not limited to distribution pipeworks, water storage tank, etc. upon acceptance of installation works and prior to handover in accordance to the statutory bodies requirement.
(w) Water sampling to be conducted by this Contractor upon completion of the plumbing system. The sampling point locations and analysis methodology shall be submitted to the CAM Project Manager for approval in accordance to the requirement as stated in the statutory bodies requirement.
2.3.11.5 Airport Systems requirements
(a) In this fit-out works, the following airport systems, but not
limited to the following will be involved:
Closed Circuit Television (CCTV) System
Public Address (PA) System
Private Automated Branch Exchange (PABX) System
Access Control System (ACS)
Wireless Network (WLAN) System
Radio Communication System
Voice and Data Cabling (VDC) System
Building Management System (BMS)
(b) Subsequently, the Contractor shall design for the following airport
systems which shall be extended from the existing systems:
Flight Information Display System (FIDS)
Master Antenna Television (MATV) System
Immigration Desks and Display Systems (Arrival)
(Option) Advance Visual Docking Guidance System
(AVDGS)
(c) The Contractor shall design, develop, construct, programme,
configure, engineer, supply, deliver, install, set up, test and
commission the system works as hereunder described,
Specifications, and any works not specifically mentioned but
required to complete the Works.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
29
(d) The Contractor shall be responsible for undertaken their own
survey and verifying the findings in terms of the existing capacity
and spare provisions and submit the site investigation report to the
CAM Project Manager for consent prior to commencement of any
service diversion works.
(e) In general, the Contractor shall be responsible for all the works
including but not limited to design, supply, configure, installation
and the interface among with different trades.
(f) The Contractor shall liaise closely and be co-operative with the
CAM Project Manager for detail planning of the services in all fit-
out areas.
(g) The Contractor shall relocate, remove and modify of the existing
facilities which will associate to the fit out works. The proposed
modification works shall be submitted for review without objection
by the CAM Project Manager prior to manufacturing and
installation. All the new installation equipment and modification
work shall be considered as part of this project. The Contractor
shall submit the installation program to CAM Project Manager for
consent.
(h) Should there be any modification, reconfiguration, addition of all
the Airport/ELV systems within the fit-out areas, the overall system
performance in the existing systems shall not be degraded in any
form or causing implication to the airport operations of the existing
systems. All the works under this project shall follows the current
MIA operation and existing system arrangement to upgrade or
modification the existing systems without reduce the performance
of existing system.
(i) The Contractor shall design, supply and install cable containment
system for Airport/ELV systems which including all necessary main
and secondary cable containment facilities (trunkings, conduits etc.)
for the complete system installation.
(j) All the proposed equipment shall be compatible with the existing
CCTV system. The Contractor shall be responsible to coordinate
with the existing system throughout the interface, installation and
testing and commissioning of the system.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
30
(k) The Contractor shall be responsible for site survey on the existing
equipment and system in order to have a basic knowledge on the
design criteria and concept.
(l) The Contractor shall submit the System Integration Plan for
system configuration to existing system, re-configure or modify the
existing software in the central computers to accommodate the
additional equipment into the existing system, including the
implementation of the new configuration. Modification of all
software/firmware is needed if necessary, which including but not
be limited to the software and databases that reside in the
headend processors, controllers, databases, server and all
workstations.
(m) Any works to be carried out by the Contractor shall not affect the
normal operation and current accepted performance of the existing
systems. The works shall also be planned to minimise disturbance
to the airport operations.
(n) The Contractor shall be required to obtain sufficient information
from the CAM Project Manager and to co-ordinate with him to
ensure a smooth interconnection to the existing systems without
service interruption. The Contractor shall submit a detailed Method
Statement and Changeover Plan with necessary fallback/
contingency plans for CAM Project Manager’s consent. The
content of the plans shall contain, but not be limited to:
1. Procedure of works;
2. Possible causes of failure;
3. Activation of contingency arrangement; and
4. The Contractor is required to take up any necessary co-ordination role with the suppliers and/or maintainers of the system.
(o) The Contractor shall coordinate with the CAM Project Manager
and work out a detailed contingency plan before interconnection
and re-configuration to the existing systems. The contingency plan
shall include description on how to minimize the disruption or
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
31
operations and ensure some levels of organizational stability and
an orderly recovery after system failure. The plan shall:
5. Provide a sense of preparedness and security;
6. Minimize risk of delays and complications;
7. Define actions for alternative processing systems;
8. Minimize decision-making in the event of a disruptive circumstance
2.3.12 BIM Model requirements
The BIM Model requirements for fit-out works and alteration and
addition works shall include, but not limited to, the following:
(a) The Contractor shall apply BIM as the design authoring tool for
fit-out works and alteration and addition works construction
developments.
(b) The Contractor is to model the fit out design in Autodesk Revit
which is a BIM Authoring tool. This is to be modelled in to Level
of Development (LOD) 300. Design elements under 50mm in
size such as cables do not need to be modelled; however the
cable trays/ conduits are to be modelled.
(c) CAM shall provide a BIM model to the Contractor for
information and for coordination. The model shall be based on
the as- built works in RFQ-198 Contract.
(d) On receipt of the RFQ-198 as-built model, the Contractor is to
coordinate this and carry out clash detection to further finalise
the design. Clash detection is to be undertaken in Autodesk
Navisworks. This will assist in the smooth design of the fit-out
and visualisation of the design for the client. At the end of the
Detailed Design Stage, the Contractor shall submit a complete
Design Model of the works to CAM Project manager in the
native Revit format.
(e) At the end of the construction stage of the fit-out works and
alteration and addition works, the Contractor shall submit the
as-built BIM model of the works to CAM Project Manager in the
native Revit format.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
32
2.3.13 Civil requirements
The external civil works shall be designed and constructed to the
satisfaction of the CAM Project Manager and to incorporate, inter alia,
the following civil requirements wherever applicable:-
(a) The Contractor shall verify as-built drawings to ensure that any
inaccuracies and/or lack of detailed information within the as-
built records at early stage of the design process. The
contractor shall carry out survey works as necessary to ensure
the complete integrity of the as-built information on which the
Contractor design is based on.
(b) The Contractor shall submit design proposal on any
modifications to existing elements for CAM Project Manager for
review and approval prior to commencement of works.
(c) The Contractor shall prepare statutory submissions and obtain
approval for their design proposal. The Contractor shall make
such submissions in good time as to ensure there is no delay to
the Works. The Contractor shall be solely responsible for any
delay due to late receipt of such permits, consents or approvals.
(d) The Contractor shall reinstate any damage during construction
and make good finish to existing elements
(e) The Contractor shall comply with the design standards,
statutory requirements and technical requirement as specified
in the specification.
(f) The Contractor shall carry out any necessary tests including
concrete cube tests, steel reinforcement tests etc. and make
submission of test reports, construction records.
(g) The Contractor shall refer to the drawing “Civil Works Layout
MMH-365511-C-0001” in the Appendix as the basis for his
design development. This drawing provides reference for the
scope of works and the interfaces with existing features and
works by others.
2.3.14 Requirements of the Works
The following table shows typical area type only; the Contractor shall
take reference to the Design Requirement Brief, Concept layout, Room
Area and finishes schedule and Room data sheets for the detailed
requirement of each room (Appendices A to D).
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
33
Typical Area Type General requirements of works for RFQ-221
Office
False ceiling
Sprinklers*
Flooring tiles or raised floor as appropriate
Wall painting
Full MEP provisions including ELV and airport system
Furniture layout design or provide full furniture as appropriate
Room numbers 1-012, 1-013, 3-001
Provide fire extinguisher
CIP Provide Isolators
Provide fire extinguisher
Public Washroom/ Staff Washroom
False ceiling* with sprinkler*
Flooring tiles
Wall tiles
Full MEP provisions including ELV and airport system*
Provide full furniture including sanitary wares, minor etc
Nursery Room False ceiling with sprinkler
Flooring tiles
Wall painting
Full MEP provisions including ELV and airport system
Provide full furniture including sofa, water basin etc
Fire Vestibule Ceiling*
Flooring tiles
Wall painting*
Landside Corridor/
Airside Corridor
Ceiling*
Flooring tiles
Wall painting *
Full MEP provisions including ELV and airport system
Public Staircase Ceiling*
Flooring tiles
Wall painting *
Public Area False ceiling* with sprinkler*
Flooring tiles
Wall painting*
Full MEP provisions including ELV and airport system*
Provide full furniture
New ELV Room Ceiling
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
34
Raised floor
Wall painting
Full MEP provisions including ELV and airport system
Lifts/ Disabled Lift Flooring tiles
Loading Bridge Provide new carpet
Guard House 4 Provide full furniture
Full MEP provisions including ELV and airport system
*Works carried out by RFQ-198, the Contractor shall reinstate or modify
to suit the new layout design and functionality.
The Contactor shall refer to the table attached in Appendix E, which
outlined the scope to be carried out by the other RFQ-198 contractor.
The Contractor shall coordinate closely with the other contractors, such
that provisions to be provided by RFQ-198 are clearly understood and
the Contractor shall take up the final installation to complete the fit out
works as required under this Contract.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
35
3.1 Specification
3.1.1 GENERAL REQUIREMENTS
PART 1 - GENERAL
1.01 MATERIALS
All materials incorporated in the Works shall be in accordance
with the requirements of this Specification and shall be new
and of pristine commercial quality, free from imperfections,
and selected for long life and minimum maintenance under the
conditions specified. Any reference to any specific material or
equipment does not necessarily imply that such is required to
be included in the Works.
The Contractor shall select and/or treat all materials to prevent
any damage from any possible combinations of atmospheric
deterioration, corrosion, wet rot, dry rot, fungi, mold and any
other deleterious effects including atmospheric pollution, saline
atmosphere and pH of the atmosphere either during
manufacturing, finishing, transportation, storage and
installation.
The Contractor shall use materials, fixers, sealing and finishing
materials that, as a minimum, satisfy current environmental
legislation and do not give off emissions of any sort that may
be considered harmful. In-site replacements shall not cause
harm or nuisance to the building users.
At no time shall silicone be used in a visible location unless
specified as such in the Drawings or with the prior consent of
the Employer’s Representative.
The Contractor may propose alternatives to
design/construction provisions and equipment/materials
specified for the consideration of the Employer and the
Employer’s Representative, if, in his opinion, these would
achieve costs savings, accelerate the working program, and
maintain full compliance with building requirements, without
changing the basic design concept.
1.02 WORKMANSHIP
Where not otherwise specified, all materials and workmanship
shall be to a standard of good building practice in Macau. All
materials shall be of first class quality and of an approved
3 Specifications for Architectural and Interior Design Works
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
36
brand and type, fixed and applied strictly in accordance with
the manufacturer’s instructions and to the Employer’s
Representative’s satisfaction.
1.03 COMPLIANCE WITH STANDARDS AND LOCAL
ORDINANCES
The Works shall conform to all Statutory Ordinances, Orders
or Regulations currently having the force of law even if they
supersede the edition specified.
Where the choice of materials or equipment are affected by
the Government of Macau Regulations or local Ordinances,
the materials or equipment supplied shall comply with all
relevant sections of such regulations even though no particular
reference may be mentioned in this Specification.
Where no alternative standards are stated or agreed in the
Contract, all details, materials, equipment and workmanship
for which the British Standards Institution has issued
standards shall be in accordance with such standards, even
though no specific standard may be mentioned in the
Specification. Alternatively, the Employer’s Representative
may approve internationally recognized standards, provided
that all parameters specified can be met.
The Contractor must be able to provide copies of up-to-date
certification for all and any details, materials, equipment or
workmanship procedure, upon request from the Employer’s
Representative.
1.04 MOVEMENTS AND FITTINGS
The Contractor shall construct the Works to withstand all
reasonable static and dynamic loads placed upon it without
causing permanent deformation of components or the failure
of members or opening of joints and shall transmit such loads
safely to the points of support. In particular, all panels provided
shall be stable and free from permanent deformation or
distortion by the worst possible combination of likely
environmental conditions, and withstand all likely static and
dynamic loads applied to them.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
37
PART 2 - ELECTROMAGNETIC COMPATIBILITY AND ELECTRICAL
BONDING
2.01 ELECTROMAGNETIC COMPATIBILITY
The works, including control equipment, microprocessors,
communication links and other items of electronics shall be
designed to achieve the performance criteria in the
electromagnetic environment as specified in the following
standards: BS EN 50082-1 “Electromagnetic compatibility,
generic immunity standard for residential, commercial & light
industry”, BS EN 55014 “Electromagnetic compatibility,
requirements for household appliances, electric tools and
similar apparatus” and BS EN 55015 “Limits and methods of
measurement of radio disturbance characteristics of electrical
lighting and similar equipment”. Immunity shall be
demonstrated by applying test conditions as specified in the
above standards at the various interfaces of the system to the
external electromagnetic environment. In general, the works
shall demonstrably not affect other installations. The
electromagnetic emission of the works shall be controlled to
fall within the limits stipulated in BS EN 50081-1
“Electromagnetic compatibility, generic emission standard for
residential, commercial and light industry”. This restriction shall
apply to the emission from the enclosures and at the coupling
point to the ac (alternating current) mains.
2.02 ELECTRICAL BONDING
The Contractor shall ensure that all extraneous conductive
parts of the works are effectively bonded to earth. (An
extraneous conductive part is defined as being any part, which
is liable to transmit an electrical potential, generally earth
potential, and not forming part of the electrical installation).
Each component shall constitute an extraneous conductive
part. The works shall be electrically continuous as required by
the latest edition of the IEE Regulations. The Contractor shall
provide equipotential bonding in a manner that ensures that
the various exposed conductive parts and extraneous
conductive parts, as defined by the applicable regulations, are
at a substantially equal potential.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
38
PART 3 - WATERPROOFING
3.01 WATERPROOFING GENERAL REQUIREMENTS
The waterproofing of floors and walls and the structural
stability of the finishing system are the prime responsibility of
the Contractor.
The waterproofing requirements shall be in accordance with
each selected product by the Architect (please refer to the
Architecture project “Drawings materials list”, “Finishes
Schedule” and Drawings.
3.02 CEMENTITIOUS COLD APPLIED WATERPROOFING
SLURRY WITH HIGHLY ELASTIC PROPERTIES
The waterproofing of floors and walls and the structural
stability of the finishing system are the prime responsibility of
the Contractor. All floor and wall surfaces on basement shall
be waterproofed by treating with a water repellent coating of
elastomeric cementitious waterproofing membrane and the
Contractor shall particularly make good the water repellent
coating at fixing points. Also areas with plumbing & drainage
services and/or other areas (when specified on drawings) shall
be waterproofed all floor and wall surfaces up to 500mm
A.F.F.L.
This product shall be applied in 2 coats (second coat shall be
applied at right angle to the first coat) with adequate thickness
and dosages required from the manufacturer/supplier. The
contractor shall allow the first coat to dry for 2-4 hours, before
applying the second coat.
This product shall be applied also in the Lower Basement floor
and walls surfaces up to 500mm A.F.F.L. , in 3 coats (second
coat shall be applied at right angle to the first coat, and the 3rd
coat at right angle to the 2nd coat) with adequate thickness
and dosages required from the manufacturer/supplier. The
contractor shall allow the each coat to dry for 2-4 hours, before
applying the next coat.
All waterproofing works shall be warranted for a minimum of 5
years and any defect or water seepage found within the
warranty period shall be sealed and made good all at the
expense of the Contractor.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
39
This waterproofing is a two component cement based, graded
fine-grain aggregates with special additives and synthetic
polymer modified high performance non-toxic waterproofing
membrane, which is applied to concrete and mortar substrates
to prevent the ingress of water. After curing, it forms an elastic
waterproof layer impermeable to chlorides, carbon dioxide and
sulphates. The two components are simply mixed at site to
form a highly workable coating, which is spray, roller or brush
applied to the prepared substrate.
A. Surface Preparation:
Concrete, mortar and masonry surface must be clean, free
from grease, oil, laitance, loosely adhering particles and
sharp edges. Remove all grease oil and loose particles. All
absorbent substrates must be dampened down with clean
fresh water prior to the application.
B. Application:
Pour the liquid component into a clean dry mixing container
and mix using a slow speed drill fitted with a paddle. Slowly
add the powder component into the liquid and continue to
mix. When all of the powder has been added, increase the
mixing speed and continue to mix to produce a lump free
slurry. Spray, roller or brush applies, in two coats or tree
coats (depending on the application surface – consult the
manufacturer advises). The second coat should be applied
at right angles to the first and after the first coat has cured
for 2-4 hours.
3.03 WATERPROOFING PVC MEMBRANE
A. Description:
A single-layer homogeneous, non-reinforced liner, with high
tensile properties and high resistance to static and dynamic
puncturing
Flexibility in low temperatures
Insensitivity to hot-cold cycles
High mechanical resistance
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
40
Vapour permeability
Adaptability to structural movements
Resistance to root growth and micro-organisms
Do not rot.
The surface colors may be chosen from the RAL range
B. Uses:
Typical application are foundations and floor slabs, plaza
decks, roof decks, terraces, fountains, wet rooms, tunnels,
planter boxes, balconies, bathrooms.
C. Application:
After laying the membranes they have to be mechanically
fixed around the perimeter. Weld the membranes using:
The manual hot air welding,
Automatic hot air or wedge welding,
THF solvent welding.
These techniques are not independent of each other; they
can be used simultaneously depending on the particular
circumstances and requirements of each job.
It is essential that the strips of membrane are clean and dry.
3.04 WATERPROOFING CONCRETE SYSTEM
An approval Hydrophobic Waterproof Concrete System, or
other equivalent system as approved by Architect and
Engineer, shall be used in the outdoor areas as indicated /
substantiated on the intention drawing as per above Appendix
(when applicable). The concrete shall contain an approved
Hydrophobic Pore blocking Ingredient as below Table 1’s Type,
Dosage, Thickness and Water absorption rate as measured by
BS 1881: part 122: 1983 except that the age at test shall be at
7 days.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
41
HPI System Dosage
per cubic
meter
Water
Absorption
Thickness of
the concrete
All slab section
for
Waterproofing
concrete
30 litres ≤1% 150mm –
400mm
Beams or
columns
8 litres ≤2% Above
400mm
PART 4 - FIRE RATING
The Works shall be composed of materials which do not
readily support combustion or give off noxious fumes, and
shall be non-toxic and non-hygroscopic. The Contractor shall
design and install the Works in compliance with the relevant
Codes and Statutory Requirements, and the requirements of
the local government fire services department.
Specifically, all fire rated materials used should be tested in
accordance with or assessed against B.S. 476 Parts 20 to 24:
1987 or similar and certified as being capable of resisting the
action of fire for the specified fire rated period (FRP).
All combustible materials, if used as false ceilings, partitions
and wall furnishings, shall be of class 1 or 2 Rate of Surface
Spread of Flame as per British Standard 476: Part 7 or be
brought up to that standard by treating with two coatings of fire
retardant paints/solutions on all exposed parts and certified by
a Registered Fire Service Installation Contractor.
All draperies, curtains and carpet should conform with the
relevant British Standard of fire rating or treated with an
approved fire retardant solution conforming to that standard
and certified by a Macau registered Fire Services Contractor.
PU foam filled mattresses and upholstered furniture shall meet
flammability standard as specified in British Standard BS
7177:1996 and BS 7176:1995 for use in medium hazard
premises/building or standards acceptable to the Director of
the Corpo de Bombeiros (Government of Macau Fire Services
Department).
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
42
Gaps between ducts and openings, as well as those between
sleeves and pipes are to be sealed with approved fire
resistance/waterproof materials to fully comply with Corpo de
Bombeiros requirements.
Similarly, steel dampers/sleeves to all duct penetrations in
walls and slabs shall be grouted for fire isolation.
PART 5 - IRONMONGERY
A. For all ironmongery items, such as door handles, hinges,
locksets, stoppers, etc., refer to “Ironmongery Schedule”
from the Architecture Project. For complete and specific
information about locksets, such as electric/automatic-
controlled locksets devices, etc., refer to Access Control
System Project.
B. All products brands are for reference only. The Contractor
may propose alternatives, with the equivalent quality.
C. Ironmongery is to be supplied and installed in accordance
with the manufacturer’s instructions, care being taken to
ensure that all parts function properly and are not strained.
Screws shall match the finish of the ironmongery, and shall
be of suitable size and head shape. Any screws or
ironmongery damaged during installation shall be replaced
at the Contractor’s own expense. The Contractor shall allow
for cutting mortises, drilling holes, screwing in place, etc. as
required.
D. All locks are to be provided with three keys. Each key shall
be provided with an approved circular chromium plated
brass plate 25mm diameter x 1.5mm thick stamped (by the
Contractor) with the identification of the name or number of
the room to which it is matched.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
43
PART 6 - SECURITY AND FIRE RATED SHUTTERS
A. The metallic security roller shutters shall be in
Galvanized Mild Steel, Stainless Steel Grade 316 or
Aluminum (refer to the drawings for the chosen/specified
material), with motor driven operation, and vertically
orientation. The posts shall be strong and durable
enough to cope under extreme conditions, such as
tropical storms.
B. Electrically operated security roller shutters shall be
used for secure enclosure of openings and shall include
one set of push button.
C. Shutters shall be tested to meet the relevant recognized
standards for impact resistance and fire retardancy.
D. Shutters can include, if specified, polycarbonate infill, UV
stabilized and resistant to staining or discoloration.
E. The electrical motor powering the shutter shall have a
brake release level limit switch, manual chain override
and adjustable pre-set opening and closing speeds.
F. The distance from the power point to the motor shall be
within one metre.
G. The manufacturer shall provide, at least, one year
warranty.
H. For painted shutters, which are from galvanized mild
steel, the painting system shall be applied in the factory
and shall be as follow:
1. Prime paint – Rust inhibitive prime paint base coat,
in accordance with ANSI A250.1;
2. Top coat – Two-part urethane top coat,
electrostatically applied over the primer, and then
oven cured.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
44
PART 7 - VENTILATION LOUVERS
A. The structural stability of the windows and louvres shall be
designed to meeting with the following regulations and
codes:
1. The Building (Construction) Regulation Cap. 123 –
Section B.
2. The Code of Practice under the Building Ordinance for
wind effects.
3. The British Standard Institute Code of Practice no.
118 – “The use of Aluminum”.
All aluminum extrusions used will be of alloy 6063-T5 with a
tensile strength of 22,000 p.s.i. for architectural application.
The surface finish of aluminum will be powder coating, color
to match existing frames.
All louvers shall include an integrated rust-proof metal mesh
screen for protection against animal entry.
Before erection to the structural opening, all aluminum
framings will be covered with protective p.v.c. tape to avoid
scratches and or damages caused by external and internal
wall finishes. Sections installed in contact with dissimilar
materials will be received by a heavy back coating of
bituminous paint to prevent corrosion. Protective tape will be
removed from the frames upon agreement with the
Employer’s Representative and cleaning of aluminum will be
carried out afterwards.
All scaffolding, if required, hoisting facilities, storage space
on site, all concrete box outs, water and electricity supplies
are the responsibility of the Contractor.
B. The ventilation louvers shall be:
1. A single bank universal louvers system type (refer to
Architecture Project Louvers Schedule)
Proprietary louvre system shall be Multi-purpose
Universal Louvre System, manufactured by an
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
45
accredited brand and shall be comprise 1UL/SH
(shallow) Single Bank Louvre (50 pitch).
2. A double bank universal louvers system type (refer to
Architecture Project Louvers Schedule)
Proprietary louvre system shall be Multi-purpose
Universal Louvre System, manufactured by an
accredited brand and shall be comprise 2UL/SH
(shallow) Double Bank Louvre (50 pitch).
C. Quality Assurance
Louvres, trims and all accessories, shall be designed,
produced, fabricated and installed to withstand the loading
Criteria, as specified herein, without failure including
permanent deflection/deformation, failure to meet
performance criteria, finish defects and other defects in the
Work.
Standards: Comply with referenced standards. Refer to
those standards for definitions of louvre terms not otherwise
defined in this section.
Specialist Qualifications: Engage an experienced specialist
who has completed the technical design, fabrication and
installation of proprietary louvre in material, design, and a
record of successful in-service performance. The
manufacturer shall confirm they have obtained ISO9001 (BS
5750 Part 1) certification issued by a certification body
acceptable to the Employer for the design and manufacture
of air and ventilation equipment and shall demonstrate to the
Employer’s Representative satisfaction that the quality
assurance procedures comply with the said standard.
The type of the louvre system shall have a substantial track
record, of not less than 10 years for the design of high
performance louvre systems worldwide in applications with
similar typhoon conditions in Macau and Hong Kong and
tested to standards listed in this specification.
For each panel the supplier shall issue an approved 5 year
warranty in respect of premature failure due to defective
materials or unsatisfactory workmanship in normal use.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
46
D. Architecture
Architecture Full set of shop drawings, structural calculation
and samples shall be submitted to the Employer’s
Representative within 30 days of commencement of
Contract for approval.
Louvre panels shall be formed to give a continuous
horizontal line effect throughout the length of the panel, with
louvre blades supported on hidden mullions.
External louvre blades shall be attached to vertical mullions
without surface drilling on riveting and shall remain
horizontal with equal spacing at all times irrespective of
environmental temperature changes. Louvre fixing shall
allow for day-to-day expansion and contraction without
distortion.
The louvre system should be capable of being installed
horizontally, vertically or inverted and in the case of the
double bank design shall have the same air and rain
defense capabilities as in the conventional mode.
E. Construction
The construction of Louvres shall be from roll-formed alloy
to BS1470: 1972 NS4 H3 or extruded to BS1474, type 6063-
T5.
The louvre shall be supplied in either modular or breakdown
form and shall comprise:
External cill, side and top frames of channel section
Vertical support mullions with drainage channels
Horizontal louvre blades
All component parts shall be aerodynamically shaped and
cold roll formed or extruded to ensure conformity of shape.
The louvres shall incorporate a drainage system such that
water collected within each panel is drained down via the
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
47
mullion and internal drainage channels and down the louvre
face.
Bird guards, where required shall be fitted to the rear of
each panel and manufactured from expanded aluminium
mesh in mill finish.
Blank-off plates shall be fitted at the back of louvers where
the area is not active for ventilation. The blank-off plates
shall be made in aluminium with thickness to be 1.5mm to
3.0mm. Paint finish can be Powder-coating, PVF2 or in mill
finish.
Louvre system shall include all accessories necessary for
fixing and waterproofing of the system, which shall include,
inter alia, all concealed vertical and horizontal members,
bolts, fixing angles, flashings, copings, sealants, trimming
angles, insect screen to openings and blanking plates.
Wind loadings: All components and fixings of the system
shall be designed to withstand wind loadings according to
Macau Codes and Code of Practice on Wind Effects Hong
Kong 1983.
F. Louvres Type/Description
Fixed formed horizontal blades and frame, 1.2mm minimum
thickness; pitch of 50mm; blade angle of 45, sight proof;
hidden vertical support mullions; continuous horizontal line
effect; external mitred corner fittings where indicated on the
drawings; louvres shall incorporate a drainage system such
that water collected within each panel is drained down via
the mullion and internal drainage channels; expanded mesh
bird guards; free area of not less than 60%; blades to be
attached to mullions without surface drilling / riveting and
shall remain horizontal with equal spacing at all times
irrespective of environmental temperature change; fixings to
allow day to day expansion and contraction without
distortion; projecting frames to dimensions indicated on
drawings, including drips and concealed fixings , all to be
fully coordinated with integral profiled aluminium extrusion
head, transom and cill where indicated on the drawings.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
48
G. Performance
1. General
Provide products and accessories capable of
compliance with the requirements specified herein.
2. Performance requirement
Louvres shall be designed to satisfy the following
performance requirements:
Extent Performance Description Requirement
Louvres Deflection Non-permanent No permanent
warpage, sag, or
oil-canning
Louvres Flame Spread Acceptable
rating as noted.
Class 1 or better
Louvres Toxic smoke
release due to
fire.
Acceptable non-
life threatening
incapacitation
level.
Max. LC50
Louvres Vibration &
rattling
Acceptable level. No vibration,
rattling or
dislodgement
due to train
piston effect or
wind.
Static pressure loss shall not be more than 20Pa and
40Pa for single and double bank louvers respectively at
a face velocity of 2.5m/s when tested in accordance to
UK HEVAC standard.
No permanent damage, buckling, undue stress on any
component or assembly, failure of joint, undue stress on
structural elements, damaging loads on fasteners,
reduction of performance, or other detrimental effects
shall occur when louvres and vents and their
components are subjected to the loads and pressures
indicated in the table above.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
49
No permanent damage, buckling, undue stress on any
component or assembly, failure of joint, undue stress on
structural elements, damaging loads on fasteners,
reduction of performance, or other detrimental effects
shall occur when louvres and vents and their
components are subjected to the loads and pressures
indicated in the table above.
Provide holes to accept equipotential bonding by others
in a manner that ensures that the various exposed
conductive parts are at a substantially equal potential.
Louvres shall be free of visual discontinuities and
defects such as: ripples, oil- canning, creases, dents,
bubbles and blisters, variation in colour and gloss, etc.
regardless of the measured deviation from flatness of
the panels.
Where used for ventilation, the specialist louvre shall
provide high volume airflow at the stated (or low)
pressure drop with listed rain defense requirements with
actual performance tests verified by independent
authority (performance class as listed). Louvre blades
shall be aerodynamically shaped to provide minimum
restriction to airflow, low velocity and shall have inlet
coefficient of not less than: Double bank 0.308, (Class
2). The coefficient shall be established as a result of full
scale wind tunnel tests carried out on a louvre
measuring not less than 1200mm x 1200mm to limit the
influence of edge effects and bird guard fitted.
Louvres employed for smoke ventilation shall be
capable of withstanding a temperature up to 250 degree
C for not less than one hour. The Contractor shall
submit test report issued by an authorized laboratory to
confirm compliance of such standard.
The performance of the combination of 2UL/Type R
shall achieve the minimum transmission loss dB as
follows:
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
50
Octave
Band Hz
Octave Band
Centre
1 2 3 4 5 6 7 8
Frequency,
Hz
63 125 250 500 1K 2K 4K 8K
Transmission
loss dB
8 9 12 15 16 17 15 12
Purpose Velocity
m/s
Louvre / Acoustic /
Combination
P drop Pa
Intake 2.0 70
Exhaust 2.0 80
H. Decorative Finishing
1. The colour of decorative finishing shall be approved by
the Employer’s Representative. Contractor to submit
0.4m x 0.4m mock up sample for approval, when the
designed louvre size have the same or bigger
dimension. If the designed louvre size is smaller than
0.4m x 0.4m, the mock up sample for approval shall
have the exact dimension as designed.
Where Louvres are exposed to external, all the louvre
frames, external louvre blades, vertical and horizontal
projections and features attached to louvre system shall
be finished in PVF2 (3-coats system), color (refer to
Architecture Project Louvres Schedule). The inner
louvre blades, mullions shall be finished with polyester
powder coating with colour to match. Where louvres are
set behind the curtain walling features, all the louvre
components shall be finished with a polyester powder
coating to an average thickness of 40/60 microns to a
colour to be agreed by the Employer’s Representative.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
51
Where louvre area is inactive, an aluminium blanking
plate in 1.5mm thickness with finished in polyester
powder coating 'BLACK' colour shall be fitted behind.
2. All exposed components of the louvre system shall
receive PVF2 coating as follows:
Colour Coating(s) shall be PVF2 Polyvinylidene
Fluoride 3 coats system and shall be applied to the
aluminium louvre in accordance with AAMA 605.2-90
and paint manufacturer's specification.
All components shall be factory finished by a single
applicator approved by the coating supplier in order to
ensure consistency of finish.
All components shall receive a spray coat primer on all
significant surfaces (as defined in BS5411: Part 1: 1980)
to the thickness recommended by the supplier and
allowed to cure for the interval recommended by the
manufacturer before the spray application of the
subsequent and top coats to a minimum dry film
thickness of 25 microns. All the coatings including the
primer and top coat shall be provided by the same
supplier.
The over coating of elements shall not be allowed.
All finished surfaces shall be smooth, free from
blemishes pinholes, tears orange peel effect and other
coating defects when evenly illuminated by diffuse light
and viewed using normal corrected vision from a
distance of one metre.
There shall be no 'seeding' of the cured film which shall
be dense and consistent.
3. Colour Uniformity: Limits for acceptable production
variations are to be established between the
Employer’s Representative and the Contractor by
reference samples.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
52
4. Performance Requirements
Hardness - Pencil:
The finish shall achieve a minimum rating of F in
accordance with AAMA 605.6.3.
Film Adhesion:
The finish shall achieve excellent 'Knife' adhesion.
Impact Resistance:
There shall be no removal using a Gardener Variable
Impact Tester as AAMA 605.6.5.
Abrasion Resistance:
The finish shall achieve an abrasion coefficient value of
20 minimum according to AAMA 605.6.6.
Acid Resistance:
Using the Muriatic Acid Spot Test the finish shall show
no signs of attack after 15 minutes as AAMA 605.7.1.
Resistance to Acid Pollutants:
The finish shall achieve not more that 5 E Units (NBS)
as stipulated in AAMA 605.7.3.
Detergent Resistant (3%) immersion at @ 100° F:
The finish shall show no signs of attack after 72 hours
in accordance with AAMA 605.7.4.
Humidity Resistance 100% RH @ 100° F:
The finish shall have fewer than eight blisters after 3000
hours exposure in accordance with AAMA 605.8.1.
Salt Spray Resistance 5% salt @ 100° F:
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
53
The finish shall have 1.5mm maximum undercutting
after 3000 hours exposure in accordance with AAMA
605.8.1.
Colour Retention (ASTM-2244-90):
The finish shall have maximum of 5 E Units (NBS)
colour change after 5 years of 45° North exposure in
accordance with AAMA 605.9.1.1.
Chalk Resistance (ASTM-D-4214-89) (1970):
The finish shall have no more chalking than that
represented by a No.8 rating for colour and a No.6
rating for whites after 5 years of 45° North exposure in
accordance with AAMA 605.9.1.2.
Sealant Compatibility:
No deleterious effects to the coating shall occur in
accordance with AAMA 605.10.
Alkali Resistance (Mortar Pat Test 100% Muriatic Acid
Spot Test):
The finish shall show no signs of attack after 24 hours
in accordance with AAMA 605.7.2.
Erosion:
The finish shall suffer a loss no greater than 20% after 5
years at 45° North Exposure in accordance with AAMA
605.9.2.
I. The inner louvre blades, mullions shall receive powder
coating as follows:
1. Pre-treatment
The following process shall be provided:
Degrease in alkaline solution
Alkaline etched
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
54
Chromate corrosion
Phosphate corrosion
2. Powder coating shall be applied electrostatically.
Louvre to be stored to effect curving of paint 10/15
minutes at 200°C Film thickness achieved with single
coat application average 60 microns. There shall be no
colour variations.
J. Installation and Workmanship
1. General
Materials, products and support system shall be
installed in accordance with the following:
Before the installation work, the installer shall inspect
and accept the conditions of the substrate in which the
work is to be installed on or affixed to. Nothing in the
material, workmanship or construction method used in
the work of this section shall invalidate any
manufacturers’ warranties or reduce their warranty
period.
The installation shall only be carried out by the team
with authorization from the manufacturer and all in
accordance with the method statement advised by the
manufacturer and approved by the Employer’s
Representative.
2. Protection, Delivery and Storage
Protect louvre materials during delivery, storage and
handling complying with manufacturer’s directions and
as required to prevent damage to louvres related
materials from effects of moisture, condensation,
temperature changes, direct exposure to sun, exposure
to subsequent construction activities, and from other
causes.
Store materials at designated locations. Under no
circumstances shall the structure be over-loaded with
stored materials.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
55
3. Preparation
Pre-installation meeting: At the Contractor’s direction,
louvre supplier and other trades relating to the Work of
this section shall meet and review procedures and time
schedule proposed for installation and co-ordination
with other Work.
List installation requirements specific to each primary /
secondary materials / systems.
4. Examination
Examine conditions, with installer present, for
compliance with requirements for installation tolerances
and other conditions affecting performance of louvres.
Provide advance notice of such examination to the
Employer’s Representative, who reserves the right to
be present. Do not proceed with installation until
unsatisfactory conditions have been corrected.
K. Fabrication and Installation
1. Fabrication, General
Maintain equal louvre blade spacing, including
separation between blades and frames at head and sill,
to produce uniform appearance.
Fabricate frames, including integral projecting cills,
transom head and jamb sections, to fit in openings of
sizes indicated, with allowances made for fabrication
and installation tolerances of louvres, adjoining
construction, and perimeter sealant joints.
Include supports, anchorages, and accessories
required for complete assembly.
For Exterior Louvres: Provide vertical mullions of type
and at spacing indicated but not more than
recommended by manufacturer.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
56
2. Installation
Locate and place louvre units plumb, level, and at
indicated alignment with adjacent work.
Use concealed anchorages where possible. Provide
stainless steel washers fitted to screws where required
to protect metal surfaces.
Form closely fitted joints with exposed connections
accurately located and secured.
The louvre system shall be suitable for easy site
assembly where for large panels all components will be
supplied in total breakdown.
All bolts and fixings shall be stainless steel of
appropriate grade and mechanical properties to suit
designed functions.
Louvre panels shall be suitably fixed to prepared
framed openings with support framework/cleats suitably
sized to suit the required wind loadings.
3. Submissions
The Contractor shall submit the name of the
manufacturer with details of track record of the
manufacturer’s previous projects of similar scale and
nature of not less than 10 years. Other submissions
include the followings:
4. Shop Drawings Required
The shop drawings shall comply with the functional and
architectural requirements of the drawings.
The following information is required to be indicated on
the submitted shop drawings.
Complete plans, sections and elevations at a scale of
1:20 indicating all louvre, units, overall dimensions of
each of the panels, number and location of fixings
thereof, to the structural openings, and concealed
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
57
structural framing as required behind long span louvres,
etc.
Dimensioned sections of all jamb, mullion, transom, sill
and head details, drawn at full scale, indicating the
proposed methods of fixing, forming joints, location of
sealants etc. including the relationship of various
sections to the interior and exterior faces of walls.
Details shall indicate all section thicknesses,
dimensional position of blades in respect to frame,
sealant types back up rods, provision for escape of
water around seals, thickness of frame fixing, etc. and
specification for materials and finishes.
5. Calculations Required
The louvre system shall be designed to withstand wind
loading in accordance with the Code of Practice.
Structural calculation shall be provided for structural
supporting members.
Co-ordinate with building service contractor and submit
calculations, certified by a qualified engineer, confirming
individually that all the louvre panels are sized to satisfy
the specified air-flow criteria.
L. Certifications Required
Extent Requirement
General Certify that louvre materials and support systems
furnished comply with the applicable standards,
and manufacturing standards and specified
requirements.
Louvres. Provide certifications for compliance with HEVAC
standard for airflow requirements.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
58
M. Samples Required
Number Size Extent
1 400×400mm Fabricated sample assembly of
louvre required.
Illustrate blade design, spacing
and frame construction.
N. Testing and Inspection
Tests Required
The following testing standards apply to the extent indicated:
Standard Test Extent
Designation Name
UK HEVAC Standard
with Witnessed by
BSRIA
“Testing and Rating of
Weather Louvres When
Subjected to Simulated Rain”
External
Louvres
PART 8 - LIGHTING TROUGHS AND AIR-CONDITIONING GRILLES
A. The Contractor shall be required to check the drawings
of the E & M Contractors and shall obtain full particulars
of their requirements with regard to position, size, the
weight of those fittings, accesses, cuttings, finishing and
other such details in sufficient time to allow in the design
and installation of the suspended ceiling system for
cutting and forming openings and providing additional
framings, stringers, hangers, etc., to accommodate the
said requirements.
PART 9 - ADHESIVES
A. Adhesives used for timberwork and joinery are to be
synthetic resin adhesives of gap filling type complying
with B.S. 1204: “Specification for type MR phenolic and
amino-plastic synthetic resin adhesives for wood”. The
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
59
use of animal glues will not be permitted.
B. Adhesive for fixing laminated plastic sheeting to be an
approved synthetic resin adhesive complying with B.S.
1204 (as above) and when the temperature exceeds
25°C, a “warm-setting” grade of adhesive is to be used.
In such case urea-formaldehyde or resorcinol adhesive
shall be used.
PART 10 - GASKETS
A. The Contractor shall:
1. Bond and mechanically fix all gaskets to their
appropriate panels. All gaskets to be manufactured
from “soft” neoprene profiles as per Drawings with
hardness values of between Shore hardness 50A to
70A when measured to ASTM D2240.00 (Shore /
Durometer Hardness test);
2. Provide all gaskets in a color to match their adjacent
material and with a 30% gloss factor; and,
3. Provide gaskets which do not shrink or warp and shall
not deteriorate between the periods stated in the
Contractor's stated times for replacement in the
Maintenance Guidelines.
PART 11 - SEALANTS
A. The Contractor shall generally not use sealants without
prior approval from the Employer’s Representative when
they shall:
1. Submit proposals to the Employer’s Representative of
type and color and silicone and receive a notice of no
objection prior to ordering;
2. Obtain written confirmation from the sealant
manufacturer and submit to the Employer’s
Representative for consideration as to the suitability of
the sealant for the application intended.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
60
3. The period during which the silicone does not change
in appearance or color shall be stated, and should be
longer than the Signs warranty period. Any
discoloration of silicone during this time shall not be
acceptable;
4. Apply sealant in accordance with the supplier's /
manufacturer's written preparatory and application
procedures;
5. Remove excess silicone and leave all joints neat and
clean;
6. Use sealants compatible with the joint surfaces and to
each other, as stated in the manufacturer's published
data or as certified by the manufacturer for each
application;
7. Determine the proper hardness, compressibility or
consistency of sealants in consultation with the
manufacturer, considering the joint movement and
exposure for the size of joint;
8. Demonstrate to the satisfaction of the Employer’s
Representative that the silicone joints can
accommodate and are compatible with any movements
to which they may be subjected;
9. Use sealant that can withstand the applicable degree of
exposure to wear, abrasion and vandalism. Any sealant
exposed to traffic shall have strength and modulus to
resist damage indentation;
10. Protect silicone joints during the curing process to
avoid contamination by dust and other debris;
11. Use colored silicone to match the adjacent materials
as shown on the Drawings.
12. Use closed cell type backing rods compatible with the
silicone used.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
61
PART 12 - FINISHES
The Contractor shall:
Submit samples of all finishes to the Employer’s
Representative for review prior to commencement of
production manufacture;
Use finishes which are durable, of uniform texture and color,
and resilient to all likely environmental and pollution effects;
Provide finishes, which are uniform in texture, color and
appearance within the limits of the agreed samples and
without irregularities or distortions. Welds, rivets, screws and
stiffeners, etc., which are intended to be visible shall be
treated so that there is no discontinuity of the finished surface
appearance;
Exert all necessary controls to ensure uniformity in
manufacture to maintain uniformity of all surface finishes for
the Works;
Achieve uniformity of identical surface finishes between
adjacent integral units, adjacent whole fabricated units,
between any part of the remainder of the Works as well as any
adjacent or existing finish.
Provide full resistance to any corrosion or any deleterious
effect to the applied finishes caused by manufacturing,
transportation, storage and/or installation. The Contractor shall
ensure total maintenance of the finish systems for components
that are secured or bolted to each other, paying particular
attention to the surface damage caused by such bolting or
securing.
12.01 SUBSTRATE PREPARATION
Prior to the commencement of any installation, check and
verify the elevations and locations of the substrate in all areas
to receive finishes and compare these locations to the
indicated plan dimensions. This verification shall include
checking for walls out-of-square with each other, walls out of
plumb, window and door openings and all other substrate
conditions that might have an impact upon the accurate
placement of finishes.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
62
The Contractor shall examine the background surfaces to
receive the finishes and shall report to the Employer’s
Representative all defects that will prevent proper installation.
The support structure shall be adjusted and completed so that
any stone, metal or timber finishes will be properly and
securely sustained. Work shall not be started until defects
have been corrected.
Backing walls shall be dry and free from dust, dirt, grease or
oil.
The Contractor shall report in writing to the Employer’s
Representative any condition which in his opinion will affect
the satisfactory execution of his work or endanger its
permanency as it will be considered that upon laying the first
piece of render, screed or finish, the surface has been
accepted without reservation and no subsequent claim as to
suitability or otherwise of the base and finishes will be
considered.
When work is not in progress the top of all wall areas where
finishes are being installed, shall be fully protected by a
waterproof cover.
Unless otherwise specified or shown, floor levels shown on
drawings are finished levels and base slabs are to be set down
to allow floor finishes of differing thicknesses to finish level.
Floors shall be finished truly plane either level or to falls as
indicated. All finished surfaces shall be finished to a true and
even surface over whole areas to within -3.0mm when tested
with a 3m long straight edge and the rate of departure shall not
be greater than 1.5mm for each 500mm in distance from any
point of contract along the straight edge.
Adjoining finishes, including those to fall, shall finish at the
same level at doors and elsewhere as applicable.
12.02 GALVANIZING
Unless otherwise specified, all galvanized coatings shall be
applied by the hot dip process and shall consist of a smooth,
clean zinc coating free from defects and of uniform thickness
complying with BS729 [1971 (1994) Specification for hot dip
galvanized coatings on iron and steel articles]. Sherardizing,
parkerizing, or other alternative processes shall not be used
without the Employer’s Representative's review.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
63
All drilling, punching, tapping and bending of parts shall be
completed and all burrs removed before galvanizing is done.
Any works not possible to be undertaken before galvanizing
shall be post-treated in accordance with BS 729 [1971 (1994)
Specification for hot dip galvanized coatings on iron and steel
articles].
The preparation for galvanizing and the galvanizing itself shall
not adversely affect the mechanical properties of the wire or
coated material.
12.03 PAINTING
Workmanship:
All painting shall be carried out by skilled workmen in the best
possible manner to produce a first class finish, free from all
blemishes, brush marks, blisters, weeping, exudation, peeling,
wrinkling etc.
All brushes, tools, pots, etc. used in carrying out the work shall
be clean and free from foreign matter, and shall be thoroughly
cleaned out before being used with a different type or class of
material. The mixing of paints of different types will not be
permitted.
All priming undercoats and finishes used on the same work
shall be supplied by one manufacturer and shall be those
recommended by the manufacturer as suitable for using
together.
All internal and external surfaces shall be perfectly dry before
any paint, etc. is applied. All coats shall be thoroughly dry
before subsequent coats are applied and all rubbing between
coats shall be done with fine glass paper. Successive coats of
paint shall be of slightly differing tints to aid in identifying
uniform coverage.
Unless otherwise specified, all paint shall be applied with
approved quality bristle brushes, or by means of compressed
air spraying or airless spray at the Contractor’s option with the
prior approval from the Employer’s Representative. The use of
rags or cotton waste for painting of any description will not be
permitted.
The Contractor shall ensure that any painted steel surfaces
are sufficiently hard to resist heavy impacts from hand held
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
64
objects without any noticeable change to the surface
appearance. As required by the Employer’s Representative,
he shall undertake tests to demonstrate the performance of
these surfaces in resisting abrasion from maintenance staff
(hands, rings, cleaning fluids, etc.) operations and any other
abrasion resulting from adjacent pedestrian traffic movements.
Preparation and Painting of Plastered and Rendered Surfaces:
All plastered and rendered surfaces shall be thoroughly
washed as necessary, swept down and stopped. “Washing”
shall mean the removal by washing with clean water of all
materials not absorbed into the underlying surfaces. “Swept
down” shall mean the thoroughly dry brushing of any surface
with a stiff broom or brush so as to remove all cobwebs, dust
or loose particles of previous finishes. “Stopping” to plaster
shall be carried out carefully by trimming the edges of all
crevices, cracks or holes of any description and filing with an
approved proprietary brand of filler to produce even, flat
surfaces.
All stains shall be removed from walls, ceilings and other
plastered surfaces prior to decoration.
Preparation and Priming of Metalwork:
All metalwork to be painted shall be first thoroughly scraped
and brushed to remove all rust and mill scale and painted with
one coat of rust inhibitor/primer.
Galvanized metalwork shall be given one coat of Galvanized
Iron Primer. All welded joints where the galvanizing has been
removed are to be painted with a paint that shall work both as
a primer (for conventional oil and alkyd topcoats) and as a
coat finish.
All non-galvanized metalwork not exposed to view such as
backs of angle frames, core rails covered by plastic brackets,
etc., are to be primed with one coat corrosion resistant metal
primer before fixing.
Cleaning Down:
All work, fittings, etc. shall be covered and protected during the
progress of the painting and all splashes shall be removed
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
65
from floors, skirting, etc., and the whole left clean and perfect
on completion.
Plastic Emulsion Paint:
Plastic emulsion paints shall be plasticized Polyvinyl Acetate
base emulsions of approved brands, supplied and used direct
from the manufacturer’s containers. Surfaces to receive
emulsion paint shall be prepared and painted with a minimum
of two coats of emulsion paint all in accordance with the
manufacturer’s specification. The first coat on porous surfaces
may be thinned with 10% (by volume) of water, the material
otherwise being applied in accordance with the manufacturer’s
instructions. Alkyd resin based emulsion paints shall not be
used without prior approval of the Employer’s Representative.
All plastic emulsion paint shall be lead-free of ICI brand or
other approved equivalent, except when other is specified.
Priming Paints
Priming paint for ferrous metal surfaces shall be a corrosion
resistant metal primer or a special rust inhibiting primer of the
same brand as the synthetic paint to be applied following, or
equivalent, except when other is specified.
PART 13 - INTERFACES
13.01 SUITABILITY OF STRUCTURE
Before commencing the Works, the Contractor shall survey the
structure, checking line, level, fixing points and all relative E &
M points and report immediately to the Employer’s
Representative if the structure is unsuitable to receive the
Works. The Contractor shall confirm the suitability of structure
to the Employer’s Representative before starting work on Site.
13.02 CO-ORDINATION
The Contractor shall co-ordinate all interfaces of the works. To
facilitate this process, the Contractor shall obtain detailed
works programs from each separate contractor and supplier
for integration into the overall project program.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
66
13.03 SERVICES INTERFACES
The Contractor shall consider the interfaces with the E&M
engineering services Works, in particular, any service
penetrations through the Works and manage, as necessary,
the relevant nominated sub-contractors. All penetrations shall
be agreed with the Employer’s Representative and no
penetrations through glass, laminated panel, structural
elements or framework shall be permitted unless shown on the
Drawings or agreed with the Employer’s Representative.
All openings for trucking, conduits, pipes and ducts passing
through party walls shall be made good, fire stopped and
sealed with fire rated protection appropriate to match the wall
rating.
PART 14 - SAMPLES, PROTOTYPES AND BENCHMARKS
14.01 SAMPLES
The Contractor shall provide 2 sets of samples of each
proposed finish material and proprietary item for review by the
Employer’s Representative at least two (2) weeks prior to the
latest order date for the said material or item. In addition,
acceptable limits to color deviation from two samples of each
finish shall be agreed with the Employer’s Representative prior
to manufacture. One sample of each material is to be retained
by the Contractor on site (after approval) and the other by the
Employer’s Representative.
For each change of color batch a new sample shall be
prepared and reviewed as before. Where there is a natural
variation in the material, the Contractor shall submit a range of
samples (minimum 3no.) that approximate the natural material.
All flat surface finishes or materials (such as painted or stone
surfaces) shall be provided at a minimum 300mm x 300mm
size, and all linear items no less than 300mm in length.
14.02 PROTOTYPES / BENCHMARKS
The scope and arrangements of the prototypes shall be as
shown below, made by the specified materials, except where
noted as such. All elements should faithfully reflect the
volumetric intent of the Employers Drawings.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
67
1m long all floor-to-floor finish thresholds (when applicable);
1m long typical wall skirting detail (when applicable);
All ceiling-to-ceiling junction details (when applicable);
A 1.2m wide wall tiles finish and 2 rows of floor tiles to show
the wall to floor joints (when applicable);
10sq.m modification of existing general false ceiling with the
installation of new specified light fittings (when applicable);
Other prototypes on request (when applicable);
The prototypes shall be fully examined in terms of details for
suitability and accessibility by the Employer’s Representative,
Designer and Client, and will be subject to changes, which will
then be incorporated into the Contractor Shop Drawings.
Upon approval of the prototype, the Contractor shall clear it
away or, if completed to a fully finished standard, store it on
site as a benchmark, as instructed by the Employer’s
Representative.
Any benchmarks will be studied by the Employer’s
Representative for design accuracy, quality of finish, ease of
use and accessibility (if applicable) and if approved, the
fabrication will establish acceptable standards for the
remainder of these Works.
PART 15 - PROTECTION, CLEANING AND MAINTENANCE
15.01 PROTECTION
The Contractor shall take all precautions to protect finishes
and surfaces and shall replace at his own expense any finish
or surface which is damaged or defaced and shall hand over
all of the works on completion in a clean condition, with
protection removed (as agreed by the Employer’s
Representative). It should be noted that the replacement of
damaged or defaced work, where required, might be extended
at the Employer’s Representative’s discretion to include the
whole of the room or area affected.
The Contractor shall protect all surfaces with plywood and
maintain this protection throughout the duration of the fitting
out works then remove before hand-over to the Employer.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
68
It shall be the Contractor’s responsibility to ensure proper
adhesion between all finishes and the structure and he shall
replace at his own cost any loose or defective works,
notwithstanding any claim by the Contractor that he has
followed the Employer’s Representative’s instruction and
specifications regarding the preparation of the surface.
The Contractor is to protect all walls and floor finishes after
completion, if possible by locking up the area. Traffic over the
floor shall be limited to essential traffic only.
No protective finish is to be laid or applied which will in any
way inhibit fixing of later finishes.
Protection shall include periodic cleaning where required to
prevent dirt, grit etc. from becoming ingrained thereto.
15.02 CLEANING
The contractor must keep the site clean, tidy and free of
rubbish at all times and remove from site all rubbish in sealed
containers as it accumulates. In addition, he shall ensure that
all debris, materials and plant are removed on completion. No
storage of materials and debris will be permitted the public
areas of the building unless otherwise permitted by the
Landlord.
The Contractor shall be responsible for ensuring that all
elements to be used from the existing building in the new
works shall be properly and thoroughly cleaned before re-
installation.
Upon completion, the Contractor is to clean and remove all
marks and dirt from finished surfaces, and ensure that all
fittings, doors, etc., are in proper working order and to the
entire satisfaction of the Employer’s Representative.
In particular stone, shall be cleaned by spraying clean water
onto the stone surface and stains, mortar and other adherents
removed from it with a cleaning chisel, nylon brush, etc. No
acid of any kind shall be used for cleaning stonework surfaces.
If the use of acid is inevitable and agreed with Employer’s
Representative, the Contractor shall protect adjacent
metalwork with proper means to resist oxidation and wash
stone surfaces with ample water to keep the surfaces
completely free of residual acid. After washing, all stone shall
be let to dry and then wiped with a cloth.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
69
The Contractor shall state the frequency and method of all
cleaning required maintaining performance of all finishes in the
Maintenance Guidelines. The Contractor shall inform the
Employer’s Representative the maximum time during which
the performance can be maintained together with the
frequency and method of cleaning required to achieve this.
15.03 WASTAGE
The Employer has allowed reasonable wastage when ordering
of each type of material based on the measurement as
provided by the Contractor. The Contractor will be fully
responsible for any delay or extra costs so caused by
inadequate amount of materials delivered to the site due to
any errors in measurement so provided by the Contractor
and/or the actual wastage of material during construction
higher than the allowance for the reasonable wastage by the
Employer, provided always that the Employer will only be
responsible for the cost for the actual material including
reasonable wastage for the completion of the works. The
Contractor will be also responsible for the unloading of the
material so delivered to the Site and providing proper storage
of the materials to the satisfaction of the Employer. If there are
any damages to the material during the handing and the
construction of the works, the contractor will be required to
reimburse the Employer for all extra costs for ordering of
additional amount of material and also will be responsible for
all the delay so caused to the Contract.
15.04 MAINTENENCE GUIDELINES
The Contractor shall provide maintenance guidelines, to be
submitted as draft documents to the Employer’s
Representative and Designer prior to the project completion
and as final documents within 1 month of receiving approval of
the draft guidelines. The guidelines shall include full details of:
Record drawings of construction;
All details of manufactured items to enable re-supply and
replacement;
Cleaning procedures;
Maintenance procedures;
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
70
All other maintenance requirements deemed necessary by the
Contractor for the proper performance of the Works throughout
the period of warranty.
PART 16 - TRANSPORTATION, HANDLING AND STORAGE OF
MATERIALS
16.01 GENERAL
The Contractor shall ensure the correct and safe handling of
all elements paying particular attention to the protection of
finished materials and surfaces. During transportation and
storage, all containers shall have their contents clearly
identified outside of the packing for quick reference at their
destination. The Contractor shall ensure adequate insurance
protection for their Works, valid up until project completion.
16.02 STORAGE
The Contractor shall provide appropriate storage of all
elements of the works and shall not store materials or
components at the site unless prior agreement is received
from the Employer’s Representative.
END OF SECTION - GENERAL REQUIREMENTS
3.1.2 AAC UNIT MASONRY
PART 1 - GENERAL
1.01 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including
General and Supplementary Condition “General
Requirements” Specifications Sections, apply to this
Section.
B. Specifications throughout all Divisions of the Project Manual
are directly applicable to this Section, and this Section is
directly applicable to them.
1.02 REFERENCE STANDARDS
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
71
A. The latest published edition of a reference shall be
applicable to this Project unless identified by a specific
edition date.
B. All reference amendments adopted prior to the effective
date of this Contract shall be applicable to this Project.
C. All materials, installation and workmanship shall comply
with all applicable requirements and standards.
1.03 QUALITY ASSURANCE
A. Single Source Responsibility for Autoclaved Aerated
Concrete Masonry Units (AAC): Provide exposed masonry
units of uniform texture and color, or a uniform blend within
the ranges accepted for these characteristics, produced by
one only manufacturer.
B. Single Source Responsibility for Mortar Materials: Obtain
dry and in pre-mixed joint mortar, suitable for AAC fixing,
from one manufacturer authorized by the blocks instructions.
C. Field Constructed Mock Ups: Prior to installation of unit
masonry, erect sample wall panels to further verify
selections made under sample submittals and to
demonstrate aesthetic effects as well as qualities of
materials and execution. Build mock ups to comply with the
following requirements, using materials indicated for final
unit of Work:
1. Locate mock ups on Site in locations indicated or, if not
indicated, as directed by Architect.
2. Build mock ups for the following types of masonry in
sizes of approximately 1.50m long by 1.50m high by full
thickness, including face and backup withes as well as
accessories.
a. Each type of exposed unit masonry construction.
b. Typical exterior face brick wall.
c. Typical interior unit masonry wall.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
72
3. Retain and maintain mock ups during construction in
undisturbed condition as standard for judging
completed unit masonry construction.
a. When directed, demolish and remove mock ups from the
Project Site.
1.04 SUBMITTALS
A. Product Data:
1. Material certificates for the following signed by
manufacturer and Contractor certifying that each
material complies with requirements.
a. Each different masonry product required for mortar and
unit block of AAC including name of manufacturer, brand,
type, and weight slips at time of delivery.
b. Each material and grade indicated for reinforcing bars, if
necessary.
2. Samples for verification purposes of the following:
a. Full size units for each different exposed masonry unit
required showing full range of dimensions to be
expected in completed construction.
b. Suitable masonry mortar samples for each AAC unit
blocks. Label samples to indicate type and amount of
colorant used.
c. Accessories embedded in the masonry, with special
attention to molding fixings.
B. Record Documents:
1. Shop drawings for reinforcing detailing fabrication,
bending, and placement of AAC unit masonry
reinforcing bars.
2. Hot weather construction procedures evidencing
compliance with requirements specified in referenced
unit masonry standard.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
73
1.05 DELIVERY, STORAGE AND HANDLING
A. Deliver masonry materials to Project in undamaged
condition.
B.Store and handle masonry units off the ground, under cover,
and in a dry location to prevent their deterioration or
damage due to moisture, temperature changes,
contaminants, corrosion, and other causes.
C. Store dry pre-mixed materials off the ground, under cover,
and in dry location.
D. Store masonry accessories including metal items to prevent
corrosion and accumulation of dirt and oil.
PART 2 - PRODUCTS
2.01 GENERAL
A. All materials shall meet or exceed all applicable referenced
standards and local requirements, and conform to codes
and ordinances of authorities having jurisdiction.
B. Comply with referenced AAC unit masonry standard and
other requirements specified in this Section applicable to
each material indicated.
2.02 BRICK UNITS
A. Comply with the following requirements applicable to each
form of brick required:
1. Provide AAC with the dimensions and the following
technical specifications:
Designation Description
Product description solid – mineral – monolithic, calcium
silicate insulation-Hydrate, lime, sand,
cement, water, air entraining agents
(porosity > 95%-by- volume)
Dimensions 440 x 215 mm, d = 100 / 140 / 215 mm
610 x 215 mm, d = 100 / 140 mm
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
74
Designation Description
Dimensional accuracy ± 2 mm
Density approx. 425 kg/m3
Calculation value for
thermal conductivity
λ = 0.10 W/mK
Heat expansion
coefficient
10-5
/K
Permeability Open to vapour diffusion, water vapour
diffusion resistance coefficient μ = 3
Fire classification Non-combustible – fire classification A1 –
DIN EN 13501-1
Compressive
resistance
Average ≥ 2.9 kPa
Water absorption During short-term immersion according to
DIN EN 1609 WP = 2.0 kg/m2
During long-term immersion according to
DIN EN 12087 WLP = 3.0 kg/m2
Absorption moisture ≤ 6%-by-volume (at 23 °C and 80 %
relative humidity)
Other properties Biological and microbiologically
unobjectionable, inhibiting effect against
mould and micro-organisms,
"environmentally compatible construction
product “according to Construction and
Environmental Institute (Institut Bauen und
Umwelt e. V.) (IBU e.V.) EPD-XEL-
2009212-D, fully recyclable and Naturplus
Quality Number 0404-0812-0881
2.03
A. Comply with requirements indicated below applicable to
each form of concrete masonry unit required.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
75
1. Provide special shapes where indicated and as follows:
a. For lintels, corners, jambs, sash, control joints,
headers, bonding, and other special conditions.
2. Size: Provide AAC masonry units complying with
requirements indicated below for size that are
manufactured to specified face dimensions within
tolerances specified in the for AAC masonry units.
3. Weight Classification: Lightweight
density
approx.
size Block weight
425 Kg/m3
440 × 215mm, thickness
100mm
4.1 Kg
425 Kg/m3
440 × 215 mm, thickness
140mm
5.8 Kg
425 Kg/m3
440 × 215 mm, thickness
215mm
8.9 Kg
425 Kg/m3 610 × 215 mm, thickness
100mm
5.7 Kg
425 Kg/m3
610 × 215 mm, thickness
140mm
8.0 Kg
450-480 Kg/m3
440 × 215 mm, thickness
50mm
2.3 Kg
450-480 Kg/m3
440 × 215 mm, thickness
75mm
3.5 Kg
450-480 Kg/m3
440 × 215 mm, thickness
100mm
4.6 Kg
450-480 Kg/m3
440 × 215 mm, thickness
140mm
6.5 Kg
450-480 Kg/m3
440 × 215 mm, thickness
215mm
10.0 Kg
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
76
2.04 MORTAR AND GROUT MATERIALS
A. Composition
B. Joint mortar dry pre-mixed must be specially designed for
use with aerated concrete blocks.
1. Dry bulk density: 1.425 +/- 75 kg/m3
2. Compressive strength: ≥ 10.0 N/mm2
3. Initial shear strength ≥ 0.3 N/mm2
4. Chloride content < 0.1 % m/m
5. Reaction to fire: Class A1
6. Water absorption < 0.35 kg/m2.min 0.5
7. Water vapour permeability 5 / 20
8. Thermal conductivity λ = 0.52 W/mK
9. Bond strength ≥ 0.30 N/mm2
10. Workable life: ≥ 4 hours
11. Correction time: ≥ 15 minutes
2.05 REINFORCING STEEL
A. Provide reinforcing steel complying with requirements of
referenced unit masonry standard and this article.
2.06 JOINT REINFORCEMENT
A. Provide joint reinforcement complying with requirements of
referenced unit masonry standard and this article, formed
from galvanized carbon steel wire, coating class as required
by referenced unit masonry standard for application
indicated.
B. Description: Welded wire units prefabricated with deformed
continuous side rods and plain cross rods into straight
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
77
lengths of not less than 3m, with prefabricated corner and
tee units.
2.07 TIES AND ANCHORS, GENERAL
A. Provide ties and anchors specified in subsequent articles
that comply with requirements for metal and size of
referenced unit masonry standard and of this article.
B. Galvanized Carbon Steel Wire.
C. Galvanized Steel Sheet.
2.08 MISCELLANEOUS ANCHORS
A. Unit Type Masonry Inserts in Concrete: Cast iron or
malleable iron inserts with suitable type and size.
B. Dovetail Slots: Furnish dovetail slots, with filler strips, of slot
size indicated, fabricated in sheet metal.
C. Anchor Bolts: Steel; hot dip galvanized; of diameter and
length indicated and in the following configurations:
1. Headed bolts.
2. Non-headed bolts, straight.
3. Non-headed bolts, bent in manner indicated.
2.09 POSTINSTALLED ANCHORS
A. Anchors as described below, with capability to sustain,
without failure, load imposed within factors of safety
indicated, conducted by a qualified independent testing
laboratory.
1. Type: Chemical anchors.
2. Type: Expansion anchors.
3. Type: Undercut anchors.
4. Corrosion Protection: Carbon steel components zinc
plated.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
78
5. Corrosion Protection: Stainless steel components, alloy
304 or 316 for bolts and nuts; alloy 304 or 316 for
anchor.
6. For cast-in-place and post-installed anchors in concrete:
Capability to sustain, without failure, a load equal to 4
times loads imposed by masonry.
7. For post-installed anchors in grouted AAC masonry
units: Capability to sustain, without failure, a load equal
to 6 times loads imposed by masonry.
2.10 MISCELLANEOUS MASONRY ACCESSORIES
A. Expansion and Control Joint Fillers:
1. Pre-molded Expansion Joint Filler: Closed cell
polyethylene foam material with a density of ±2psf, and
compatible with most sealants.
2. Construction Joint Filler: Closed cell expanded
neoprene foam material with a density of 15 to 35psf,
flame resistant, and compatible with most sealants
3. Pre-molded Control Joint Strip: Solid rubber strips with
a Shore A Durometer hardness of 60 to 80, designed to
fit standard sash blocks and maintain lateral stability of
masonry wall.
B. Weep Holes: Provide one of the following at Contractor's
option:
1. Aluminum Weep Hole/Vent: One piece L shaped units
made to fit in a vertical mortar joint from sheet
aluminum and consisting of a vertical channel with
louvers stamped in web and a flat horizontal; pre-
painted prior to installation, in color to match that of
masonry or mortar as selected by Architect.
2. Plastic Weep Hole/Vent: One piece flexible extrusion
manufactured from ultraviolet resistant polypropylene
co polymer, designed to weep moisture in masonry
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
79
cavity to exterior, sized to fill head joints with outside
face held back 1/8 inch from exterior face of masonry.
C. Cavity Drainage Material: To prevent mortar from blocking
cavity weep holes, provide one of the following:
1. 25-mm thick, reticulated, nonabsorbent mesh, made
from polyethylene strands and shaped to maintain
drainage at weep holes without being clogged by
mortar droppings.
PART 3 - EXECUTION
3.01 PREPARATION
A. Examine conditions, with Installer present, for compliance
with requirements for installation tolerances and other
specific conditions, and other conditions affecting
performance of AAC unit masonry.
1. For the record, prepare written report, endorsed by
Installer, listing conditions detrimental to performance
of unit masonry.
B. Examine rough in and built in construction to verify actual
locations of piping connections prior to installation.
C. Do not proceed until unsatisfactory conditions have been
corrected.
3.02 INSTALLATION
A. Installation shall meet or exceed all applicable local
requirements, referenced standards and conform to codes
and ordinances of authorities having jurisdiction.
B. All installation shall be in accordance with manufacturer’s
published recommendations.
C. Comply with referenced AAC unit masonry standard and
other requirements indicated applicable to each type of
installation included in Project.
D. Thickness: Build cavity and composite walls and other
masonry construction to the full thickness shown. Build
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
80
single withe walls to the actual thickness of the masonry
units, using units of nominal thickness indicated.
E. Build chases and recesses as shown or required to
accommodate items specified in this and other Sections of
the Specifications.
F. Leave openings for equipment to be installed before
completion of masonry. Use adequate tools for this AAC
masonry. After installation of equipment, complete masonry
to match construction immediately adjacent to the opening.
G. Cut AAC masonry units with saws to provide clean, sharp,
unchipped edges, as instructed by the AAC blocks
manufacturer. Cut units as required to provide continuous
pattern and to fit adjoining construction. Use full size units
without cutting where possible.
3.03 CONSTRUCTION TOLERANCES
A. Comply with construction tolerances of referenced AAC unit
masonry standard.
3.04 LAYING MASONRY WALLS
A. Lay out walls in advance for accurate spacing of surface
bond patterns with uniform joint widths and for accurate
locating of openings, movement type joints, returns, and
offsets. Avoid the use of less than half size units at corners,
jambs, and where possible at other locations.
B. Lay up walls to comply with specified construction
tolerances, with courses accurately spaced and coordinated
with other construction.
3.05 MORTAR BEDDING AND JOINTING
A. Lay AAC units with full appropriate mortar coverage on bed
and head joints. Furrowing of joints will not be permitted.
B. Cut joints flush for masonry walls to be concealed or to be
covered by other materials, unless otherwise indicated.
C. The mortar has to be mixed for 4 minutes with the quantity
of water state don the bag. This is to ensure that water can
mix with all the cement particles. After mixing for 4 minutes
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
81
a creamy mass should have been created with no dry
mortar in the mix.
D. It remains workable within the bucket for approx. 4 hours.
E. It will reach its initial bond strength within 7 to 10 minutes
and full design bond strength within 28days.
3.06 STRUCTURAL BONDING OF MULTIWYTHE
MASONRY
A. Use individual metal ties installed in horizontal joints to
bond withes together.
B. Use continuous horizontal joint reinforcement installed in
horizontal mortar joints for bond tie between withes.
C. Use either of the structural bonding systems specified
above.
D. Use structural bonding system indicated on Drawings.
E. Corners: Provide interlocking masonry unit bond in each
course at corners, unless otherwise shown.
F. Intersecting and Abutting Walls: Unless vertical expansion
or control joints are shown at juncture, provide same type of
bonding specified for structural bonding between withes and
space as follows:
1. Provide individual metal ties.
2. Provide continuity with horizontal joint reinforcement
using prefabricated "T" units.
3.07 ANCHORING MASONRY TO STRUCTURAL
MEMBERS
A. Anchor masonry to structural members where masonry
abuts or faces structural members to comply with the
following:
1. Provide an open space not less than 1 cm in width
between masonry and structural member, unless
otherwise indicated. Keep open space free of mortar or
other rigid materials.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
82
2. Anchor masonry to structural members with flexible
anchors embedded in masonry joints and attached to
structure.
3.08 MOVEMENT (CONTROL AND EXPANSION) JOINTS
A. Install control and expansion joints in unit masonry where
indicated. Build in related items as the masonry progresses.
Do not form a continuous span through movement joints
unless provisions are made to prevent in plane restraint of
wall or partition movement.
B. Joint Spacing: If location of control joints and expansion
joints is not shown, place vertical joints spaced not to
exceed 10 m on center and horizontal joints not to exceed
story height.
1. Locate control joints in face brick at all points of
discontinuity of back up construction, vertical and
horizontal.
3.09 LINTELS
A. Install steel lintels where it is necessary.
B. Provide masonry lintels where necessary. Provide precast
or formed in place masonry lintels. Cure precast lintels
before handling and installation. Temporarily support
formed in place lintels.
C. Provide minimum bearing of 20 cm at each jamb, unless
otherwise indicated.
3.10 REPAIRING, POINTING, AND CLEANING
A. Remove and replace AAC masonry units that are loose,
chipped, broken, stained, or otherwise damaged or if units
do not match adjoining units. Install new units to match
adjoining units and in fresh mortar or grout, pointed to
eliminate evidence of replacement.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
83
B. Final Cleaning: After mortar is thoroughly set and cured,
clean exposed masonry as follows:
1. Remove large mortar particles by hand with wooden
paddles and nonmetallic scrape hoes or chisels.
2. Protect adjacent stone and non-masonry surfaces from
contact with cleaner by covering them with liquid
strippable masking agent, polyethylene film, or
waterproof masking tape.
3. Wet wall surfaces with water prior to application of
cleaners; remove cleaners promptly by rinsing
thoroughly with clear water.
C. Provide final protection and maintain conditions, in a
manner acceptable to Installer, that ensure unit masonry is
without damage and deterioration at time of Substantial
Completion.
END OF SECTION - AAC Unit Masonry
3.1.3 METAL FABRICATIONS
PART 1 - GENERAL
1.01 RELATED DOCUMENTS
Drawings and general provisions of the Contract, including
“General Requirements” Specifications Sections, apply to this
Section.
Specifications throughout all Divisions of the technical
Specifications are directly applicable to this Section, and this
section is directly applicable to them.
1.02 REFERENCE STANDARDS
A. The latest published edition of a reference shall be
applicable to this Project unless identified by a specific
edition date.
B. All reference amendments adopted prior to the effective
date of this Contract shall be applicable to this Project.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
84
C. All materials, installation and workmanship shall comply
with all applicable requirements and standards.
1.03 QUALITY ASSURANCE
A. Fabricator Qualifications: Firm experienced in successfully
producing metal fabrications similar to that indicated for this
Project, with sufficient production capacity to produce
required units without causing delay in the Work.
B. Installer Qualifications: Arrange for installation of metal
fabrications specified in this section by same firm that
fabricated them.
C. Qualify welding processes and welding operators in
accordance with AWS D1.1 "Structural Welding Code
Steel," D1.3 "Structural Welding Code Sheet Steel", and
D1.2 "Structural Welding Code Aluminum."
1. Certify that each welder has satisfactorily passed AWS
qualification tests for welding processes involved and, if
pertinent, has undergone recertification.
1.04 SUBMITTALS
A. Product Data:
1. Product data and installation instructions for each
prefabricated item of miscellaneous metal fabrications
and accessories.
2. Samples representative of materials and finished
products as may be requested by Owner.
B. Record Documents:
1. Shop drawings detailing fabrication and erection of
each metal fabrication indicated. Include plans,
elevations, sections, and details of metal fabrications
and their connections. Show anchorage and accessory
items. Provide templates for anchors and bolts
specified for installation under other sections.
Where installed metal fabrications are indicated to
comply with certain design loadings, include structural
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
85
computations, material properties, and other information
needed for structural analysis that has been signed and
sealed by the qualified professional engineer who was
responsible for their preparation.
1.05 PROJECT CONDITIONS
Field Measurements: Check actual locations of walls and other
construction to which metal fabrications must fit, by accurate
field measurements before fabrication; show recorded
measurements on final shop drawings. Coordinate fabrication
schedule with construction progress to avoid delay of Work.
Where field measurements cannot be made without delaying
the Work, guarantee dimensions and proceed with fabrication
of products without field measurements. Coordinate
construction to ensure that actual opening dimensions
correspond to guaranteed dimensions. Allow for trimming and
fitting.
PART 2 - PRODUCTS
2.01 GENERAL
All materials shall meet or exceed all applicable referenced
standards and local requirements, and conform to codes and
ordinances of authorities having jurisdiction.
2.02 FERROUS METALS
A. For metal fabrications exposed to view upon completion of
the Work, provide materials selected for their surface
flatness, smoothness, and freedom from surface blemishes.
Do not use materials whose exposed surfaces exhibit pitting,
seam marks, roller marks, rolled trade names, roughness,
and, for steel sheet, variations in flatness exceeding those
permitted by reference standards for stretcher leveled sheet.
B. Steel Plates, Shapes, and Bars: ASTM A36.
C. Rolled Steel Floor Plates: ASTM A786.
D. Steel Bars for Gratings: ASTM A569 or ASTM A36.
E. Wire Rod for Grating Cross Bars: ASTM A510.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
86
F. Steel Tubing: Product type (manufacturing method) and as
follows:
1. Cold Formed Steel Tubing: ASTM A500, grade as
indicated below:
2. Grade A, unless otherwise indicated or required for
design loading.
For exterior installations and where indicated, provide
tubing with hot dip galvanized coating per ASTM A53.
G. Uncoated Steel Sheet: Commercial quality, product type
(method of manufacture) as follows:
1. Cold Rolled Steel Sheet: ASTM A366.
H. Galvanized Steel Sheet: Commercial Quality; ASTM A526,
G90 coating designation unless otherwise indicated.
I. Steel Pipe: ASTM A53; finish and type as follows:
1. Black finish, unless otherwise indicated.
2. Galvanized finish for exterior installations and where
indicated.
J. Gray Iron Castings: ASTM A 48, Class 30.
K. Malleable Iron Castings: ASTM A47, grade 32510.
L. Brackets, Flanges and Anchors: Cast or formed metal of the
same type material and finish as supported rails, unless
otherwise indicated.
M. Concrete Inserts: Threaded or wedge type; galvanized
ferrous castings, either malleable iron, ASTM A47, or cast
steel, ASTM A27. Provide bolts, washers, and shims as
required, hot dip galvanized per ASTM A153.
N. Welding Rods and Bare Electrodes: Select in accordance
with AWS specifications for the metal alloy to be welded.
2.03 STAINLESS STEEL
A. Stock: ASTM A276, Type 316.
B. Plate: ASTM A167, Type 316.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
87
2.04 ALUMINUM
A. Extruded Bars and Shapes: ASTM B221, alloys 6063-T6:
B. Aluminum Alloy Rolled Tread Plate: ASTM B632, alloys
6061-T6:
C. Aluminum Sheet for Expanded Aluminum Grating: ASTM
B209, alloy 5052 H32.
2.05 GROUT AND ANCHORING CEMENT
A. Non-shrink Nonmetallic Grout: Premixed, factory packaged,
non-staining, noncorrosive, nongaseous grout complying
with ASTM C1107. Provide grout specifically recommended
by manufacturer for interior and exterior applications of type
specified in this section.
1. "B-6 Construction Grout"; W. R. Bonsal Co.
2. "Diamond Crete Grout"; Concrete Service Materials Co.
3. "Euco N S Grout"; Euclid Chemical Co.
4. "Masterflow 928 and 713"; Master Builders.
5. "Sealtight 588 Grout"; W. R. Meadows, Inc.
6. "Sonogrout 14"; Sonneborn Building Products.
7. "Stoncrete NM1"; Stonhard, Inc.
8. "Five Star Grout"; U. S. Grout Corp.
9. "Vibropruf #11"; Lambert Corp.
B. Interior Anchoring Cement: Factory prepackaged, non-
shrink, non-staining, hydraulic controlled expansion cement
formulation for mixing with water at Project Site to create
pourable anchoring, patching, and grouting compound. Use
for interior applications only.
1. "Bonsal Anchor Cement"; W. R. Bonsal Co.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
88
2. "Por Rok"; Minwax Construction Products Division.
C. Non-shrink Metallic Grout: Premixed, factory packaged,
ferrous aggregate grout complying with ASTM C 1107 2,
specifically recommended by manufacturer for heavy duty
loading applications of type specified in this section.
1. "Metox RM"; Chem Masters Corp.
2. "Hi Mod Grout"; Euclid Chemical Co.
3. "Embeco 885 and 636"; Master Builders.
4. "Ferrolith G Redi Mix and G NC"; Sonneborn Building
Products Div., Rexnord Chemical Products, Inc.
2.06 FASTENERS
A. Provide zinc coated fasteners for exterior use or where built
into exterior walls. Select fasteners for the type, grade, and
class required.
B. Bolts and Nuts: Regular hexagon head type, ASTM A307,
Grade A.
C. Lag Bolts: Square head type, FS FF B561.
D. Machine Screws: Cadmium plated steel, FS FF S92.
E. Wood Screws: Flat head carbon steel, FS FF S111.
F. Plain Washers: Round, carbon steel, FS FF W92.
G. Drilled In Expansion Anchors: Expansion anchors
complying with FS FF S325, Group VIII (anchors,
expansion, [non-drilling]), Type I (internally threaded tubular
expansion anchor); and machine bolts complying with FS
FF B575, Grade 5.
H. Toggle Bolts: Tumble wing type, FS FF B588, type, class,
and style as required.
I. Lock Washers: Helical spring type carbon steel, FS FF W84.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
89
2.07 PAINT
A. Shop Primer for Ferrous Metal: Manufacturer's or
fabricator's standard, fast curing, lead free, universal
modified alkyd primer selected for good resistance to
normal atmospheric corrosion, for compatibility with finish
paint systems indicated, and for capability to provide a
sound foundation for field applied topcoats despite
prolonged exposure complying with performance
requirements of FS TT P645.
B. Galvanizing Repair Paint: High zinc dust content paint for
re-galvanizing welds in galvanized steel, with dry film
containing not less than 94 percent zinc dust by weight, and
complying with DOD P 21035 or SSPC Paint 20.
C. Bituminous Paint: Cold applied asphalt mastic complying
with SSPC Paint 12 except containing no asbestos fibers.
2.08 FABRICATION, GENERAL
A. Form metal fabrications from materials of size, thickness,
and shapes indicated but not less than that needed to
comply with performance requirements indicated. Work to
dimensions indicated or accepted on shop drawings, using
proven details of fabrication and support. Use type of
materials indicated or specified for various components of
each metal fabrication.
B. Form exposed work true to line and level with accurate
angles and surfaces and straight sharp edges.
C. Allow for thermal movement resulting from 100 degrees F
(55.5 degrees C) maximum change (range) in ambient
temperature in the design, fabrication, and installation of
installed metal assemblies to prevent buckling, opening up
of joints, and overstressing of welds and fasteners. Base
design calculations on actual surface temperatures of
metals due to both solar heat gain and nighttime sky heat
loss.
D. Shear and punch metals cleanly and accurately. Remove
burrs.
E. Ease exposed edges to a radius of approximately 1/32 inch,
unless otherwise indicated. Form bent metal corners to
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
90
smallest radius possible without causing grain separation or
otherwise impairing work.
F. Remove sharp or rough areas on exposed traffic surfaces.
G. Weld corners and seams continuously to comply with AWS
recommendations and the following:
1. Use materials and methods that minimize distortion
and develop strength and corrosion resistance of base
metals.
2. Obtain fusion without undercut or overlap.
3. Remove welding flux immediately.
4. At exposed connections, finish exposed welds and
surfaces smooth and blended so that no roughness
shows after finishing and contour of welded surface
matches those adjacent.
H. Form exposed connections with hairline joints, flush and
smooth, using concealed fasteners wherever possible. Use
exposed fasteners of type indicated or, if not indicated,
Phillips flat head (countersunk) screws or bolts. Locate
joints where least conspicuous.
I. Provide for anchorage of type indicated; coordinate with
supporting structure. Fabricate and space anchoring
devices to provide adequate support for intended use.
J. Preassemble items in shop to greatest extent possible to
minimize field splicing and assembly. Disassemble units
only as necessary for shipping and handling limitations. Use
connections that maintain structural value of joined pieces.
Clearly mark units for reassembly and coordinated
installation.
K. Cut, reinforce, drill and tap miscellaneous metal work as
indicated to receive finish hardware, screws, and similar
items.
L. Fabricate joints that will be exposed to weather in a manner
to exclude water, or provide weep holes where water may
accumulate.
2.09 ROUGH HARDWARE
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
91
A. Furnish bent or otherwise custom fabricated bolts, plates,
anchors, hangers, dowels, and other miscellaneous steel
and iron shapes as required for framing and supporting
woodwork, and for anchoring or securing woodwork to
concrete or other structures. Straight bolts and other stock
rough hardware items are specified in Division 06 sections.
B. Fabricate items to sizes, shapes, and dimensions required.
Furnish malleable iron washers for heads and nuts which
bear on wood structural connections; elsewhere, furnish
steel washers.
2.10 STEEL LADDERS
A. Fabricate ladders for the locations shown, with dimensions,
spacing, and anchorages as indicated. Unless otherwise
indicated, fabricate ladders with component parts specified
herein. Comply with requirements of ANSI A14.3.
B.Side rails: Continuous steel flat bars, 1/2 inch x 2 1/2 inches,
with eased edges, spaced 18 inches apart.
C. Bar Rungs: Round steel bars, 3/4 inch diameter, spaced 12
inches on center.
D. Bar Rungs: Square steel bars, 3/4 inch, spaced 12 inches
on center.
E. Fit rungs in centerline of side rails, plug weld and grind
smooth on outer rail faces.
F. Support each ladder at top and bottom and at intermediate
points spaced not more than 5' 0" on center by means of
welded or bolted steel brackets.
1. Size brackets to support design dead and live loads
indicated and to hold centerline of ladder rungs clear of
the wall surface by not less than 7 inches.
2. Extend side rails 42 inches above top rung, and return
rails to wall or structure unless other secure handholds
are provided. If the adjacent structure does not extend
above the top rung, goose neck the extended rails back
to the structure to provide secure ladder access.
G. Provide non slip surface on top of each rung, either by
coating the rung with aluminum oxide granules set in epoxy
resin adhesive, or by using a type of manufactured rung
which is filled with aluminum oxide grout.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
92
2.11 SHIP'S LADDERS
A. Provide ship's ladders where indicated. Fabricate of open
type construction with structural steel channel or steel plate
stringers, pipe handrails, and open steel grating treads,
unless otherwise indicated. Provide all necessary brackets
and fittings for installation.
B. Galvanize all ladders, including, brackets and fasteners.
2.12 ABRASIVE NOSINGS
A. Provide abrasive nosings on stair treads where indicated
fabricated with an aluminum base and an aluminum oxide
or silicon carbide abrasive filler.
1. Provide configuration of nosings as indicated and
appropriate to the stair construction.
2. Size nosings to extend full width of concrete-filled steel
pan treads and approximately 3 inches short of each
end of concrete stair treads.
3. Provide color of filler as selected by Owner from
manufacturer's standards; 8 choices minimum.
B. Product: Subject to compliance with requirements, provide
"Supergrit Safety Nosings" by Wooster Products Inc., or
equal product of one of the following:
1. Amstep Products
2. American Safety Tread Co.
3. Armstrong Products Inc.
4. Safe-T-Metal Co. Inc.
2.13 LOOSE BEARING AND LEVELING PLATES
Provide loose bearing and leveling plates for steel items
bearing on masonry or concrete construction, made flat, free
from warps or twists, and of required thickness and bearing
area. Drill plates to receive anchor bolts and for grouting as
required. Galvanize after fabrication.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
93
2.14 MISCELLANEOUS FRAMING AND SUPPORTS
A. Provide steel framing and supports for applications
indicated or which are not parts of structural steel
framework, as required to complete work.
B. Fabricate units to sizes, shapes, and profiles indicated and
required to receive adjacent other construction retained by
framing and supports. Fabricate from structural steel
shapes, plates, and steel bars of welded construction using
mitered joints for field connection. Cut, drill, and tap units to
receive hardware, hangers, and similar items.
1. Equip units with integrally welded anchors for casting
into concrete or building into masonry. Furnish inserts if
units must be installed after concrete is placed.
Except as otherwise indicated, space anchors 24
inches on center and provide minimum anchor units in
the form of steel straps 1-1/4 inches wide x 1/4 inch x 8
inches long.
2.15 METAL BAR GRATINGS
A. Produce metal bar gratings of description indicated per
NAAMM marking system that complies with the following:
1. Metal Bar Grating Standard "Standard Specifications
for Metal Bar Grating and Metal Bar Grating Treads"
published in ANSI/NAAMM A202.1 "Metal Bar Grating
Manual."
2. Heavy Duty Metal Bar Grating Standard: "Guide
Specifications for Heavy Duty Metal Bar Grating"
published in NAAMM "Heavy Duty Metal Bar Grating
Manual."
B. To establish standards of manufacturer, specification is
based upon products of Reliance Steel Products, Inc.
Subject to compliance with requirements, other
manufacturers offering metal bar gratings that may be
incorporated in the Work include, but are not limited to, the
following:
1. Alabama Metal Industries Corp.
2. Barnett/Bates Corp.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
94
3. Blaw Knox Grating Div., Blaw Knox Corp.
4. IKG Industries
5. Klemp Corp.
6. Ohio Gratings, Inc.
7. Seidelhuber Metal Products, Inc.
8. Trueweld, Inc.
C. Galvanized Steel Bar Grating: Provide Reliance Steel
Products Company hot dipped galvanized steel "Type
3/4R4 Electro Pressure Welded" grating with 1-1/2 inch x ¼
inch bearing bars spaced at 1 inch centers and ½ inch x
3/16 inch rectangular cross bars spaced at 4 inch centers.
Slot bearing bars for rectangular cross bars prior to electro
pressure welding. Provide banding bars of same size as
bearing bars.
D. Prime Painted Steel Bar Grating: Provide Reliance Steel
Products Company "Type 1R4 Electro Pressure Welded"
grating with 1-1/2 inch x ¼ inch bearing bars spaced 1-1/4
inch centers and ½ inch x 3/16 inch rectangular cross bars
spaced at 4 inch centers. Provide one shop coat Tnemec
10 99G (green) modified alkyd rust inhibitive primer as
specified after fabrication.
2.16 STEEL PIPE RAILINGS AND HANDRAILS
A. Fabricate pipe railings and handrails to comply with
requirements indicated for design, dimensions, details,
finish, and member sizes, including wall thickness of pipe,
post-spacing, and anchorage, but not less than that
required to support structural loads.
B. Interconnect railing and handrail members by butt welding
or welding with internal connectors, at fabricator's option,
unless otherwise indicated.
1. At tee and cross intersections, notch ends of
intersecting members to fit contour of pipe to which end
is joined and weld all around.
C. Form changes in direction of railing members as follows:
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
95
1. By insertion of prefabricated elbow fittings.
2. By radius bends of radius indicated.
3. By mitering at elbow bends.
4. By bending.
5. By any method indicated above, applicable to change
of direction involved.
D. Form simple and compound curves by bending pipe in jigs
to produce uniform curvature for each repetitive
configuration required; maintain cylindrical cross section of
pipe throughout entire bend without buckling, twisting,
cracking, or otherwise deforming exposed surfaces of pipe.
E. Provide wall returns at ends of wall mounted handrails,
unless otherwise indicated.
F. Close exposed ends of pipe by welding 3/16 inch thick steel
plate in place or by use of prefabricated fittings, except
where clearance of end of pipe and adjoining wall surface is
1/4 inch or less.
G. Brackets, Flanges, Fittings, and Anchors: Provide wall
brackets, end closures, flanges, miscellaneous fittings, and
anchors for interconnections of pipe and attachment of
railings and handrails to other work. Furnish inserts and
other anchorage devices for connecting railings and
handrails to concrete or masonry work.
H. For exterior steel railings and handrails formed from steel
pipe with galvanized finish, galvanize fittings, brackets,
fasteners, sleeves, and other ferrous components.
I. For interior steel railings and handrails formed from steel
pipe with galvanized finish, galvanize fittings, brackets,
fasteners, sleeves, and other ferrous components.
J. For interior steel railings formed from steel pipe with black
finish, provide non-galvanized ferrous metal fittings,
brackets, fasteners, and sleeves, except galvanize anchors
embedded in exterior masonry and concrete construction.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
96
2.17 STEEL AND IRON FINISHES
A. Galvanizing: For those items indicated for galvanizing,
apply zinc coating by the hot dip process compliance with
the following requirements:
1. ASTM A153 for galvanizing iron and steel hardware.
2. ASTM A123 for galvanizing both fabricated and
unfabricated iron and steel products made of uncoated
rolled, pressed, and forged shapes, plates, bars, and
strip 0.0299 inch thick and heavier.
B. Preparation for Shop Priming: Prepare uncoated ferrous
metal surfaces to comply with minimum requirements
indicated below for SSPC surface preparation specifications
and environmental exposure conditions of installed metal
fabrications:
1. Exteriors (SSPC Zone 1B): SSPC SP6 "Commercial
Blast Cleaning."
2. Interiors (SSPC Zone 1A): SSPC SP3 "Power Tool
Cleaning:
C. Apply shop primer to uncoated surfaces of metal
fabrications, except those with galvanized finish or to be
embedded in concrete, sprayed on fireproofing, or masonry,
unless otherwise indicated. Comply with requirements of
SSPC PA1 "Paint Application Specification No. 1" for shop
painting.
1. Stripe paint all edges, corners, crevices, bolts, welds,
and sharp edges.
PART 3 - EXECUTION
3.01 PREPARATION
A. Coordinate and furnish anchorages, setting drawings,
diagrams, templates, instructions, and directions for
installation of anchorages, including concrete inserts,
sleeves, anchor bolts, and miscellaneous items having
integral anchors that are to be embedded in concrete or
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
97
masonry construction. Coordinate delivery of such items to
the Project Site.
B. Center nosings on tread widths with noses flush with riser
faces and tread surfaces.
C. Set sleeves in concrete with tops flush with finish surface
elevations; protect sleeves from water and concrete entry.
D. Sequencing and Scheduling:
1. Sequence and coordinate installation of wall handrails
as follows:
Mount handrails only on completed walls. Do not
support handrails temporarily by any means not
satisfying structural performance requirements.
Mount handrails only on gypsum board assemblies
reinforced to receive anchors, and where the location of
concealed anchor plates has been clearly marked for
benefit of Installer.
3.02 INSTALLATION
A. Installation shall meet or exceed all applicable federal, state
and local requirements, referenced standards and conform
to codes and ordinances of authorities having jurisdiction.
B. All installation shall be in accordance with manufacturer’s
published recommendations.
C. Fastening to In Place Construction: Provide anchorage
devices and fasteners where necessary for securing
miscellaneous metal fabrications to in place construction;
include threaded fasteners for concrete and masonry
inserts, toggle bolts, through bolts, lag bolts, wood screws,
and other connectors as required.
D. Cutting, Fitting, and Placement: Perform cutting, drilling,
and fitting required for installation of miscellaneous metal
fabrications. Set metal fabrication accurately in location,
alignment, and elevation; with edges and surfaces level,
plumb, true, and free of rack; and measured from
established lines and levels.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
98
E. Provide temporary bracing or anchors in formwork for items
that are to be built into concrete masonry or similar
construction.
F. Fit exposed connections accurately together to form hairline
joints. Weld connections that are not to be left as exposed
joints, but cannot be shop welded because of shipping size
limitations. Do not weld, cut, or abrade the surfaces of
exterior units which have been hot dip galvanized after
fabrication, and are intended for bolted or screwed field
connections.
G. Field Welding: Comply with AWS Code for procedures of
manual shielded metal arc welding, appearance and quality
of welds made, methods used in correcting welding work,
and the following:
1. Use materials and methods that minimize distortion and
develop strength and corrosion resistance of base
metals.
2. Obtain fusion without undercut or overlap.
3. Remove welding flux immediately.
4. At exposed connections, finish exposed welds and
surfaces smooth and blended so that no roughness
shows after finishing and contour of welded surface
matches those adjacent.
H. Corrosion Protection: Coat concealed surfaces of aluminum
that will come into contact with grout, concrete, masonry,
wood, or dissimilar metals with a heavy coat of bituminous
paint or zinc chromate primer.
3.03 FABRICATION
A. Provide miscellaneous metal work fabricated by processes
and techniques which will result in the appropriate
workmanship class as scheduled.
1. Class 1 Workmanship: Sandblast exposed surfaces
smooth with pits, mill marks, nicks, and scratches filled
and ground smooth so that no defects are visible from
a distance of 6' after painting.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
99
Conceal welds where possible. Where exposed, grind
welds to small radius with uniform size cove. Welds
shall be undetectable after painting.
Use only flat head countersunk bolts in exposed
locations.
Fit all joints to hairline finish.
Distortions visible to the eye will be cause for rejection.
2. Items required to have Class 1 Workmanship include:
Stair railings, handrails and guardrails in public and
"high finish level" areas, interior and exterior.
Steel framed stairs in public and "high finish level"
areas, interior and exterior.
3. Class 2 Workmanship: Grind exposed surfaces to
remove surface irregularities. Moderate imperfections
not visible at 20 feet may remain. Mill marks may
remain.
Grind welds to small radius with uniform sized core and
smooth transition between joined pieces.
Use only flat or oval head, countersunk bolts where
exposed to view.
Straightness: Minor distortions will be permitted.
Joints: Provide maximum gap of 1/16 inches.
4. Items required to have Class 2 Workmanship include:
Stair railings, handrails, and guardrails in "back of
house" areas, interior and exterior.
Steel ladders.
Steel framed stairs in "back of house" areas, interior
and exterior.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
100
Steel bollards.
Exposed door supports, guides, and bracing.
Lavatory countertop supports.
Garage overhead clearance bars.
5. Class 3 Workmanship: No improvement from mill finish
required except preparation for priming and galvanizing.
6. Items required to have Class 3 Workmanship include
all concealed items and those items exposed to view
only in "service" areas such as mechanical equipment
rooms, and other areas accessible only to building
maintenance staff.
3.04 SETTING LOOSE PLATES
A. Clean concrete and masonry bearing surfaces of any bond
reducing materials, and roughen to improve bond to
surfaces. Clean bottom surface of bearing plates.
B. Set loose leveling and bearing plates on wedges, or other
adjustable devices. After the bearing members have been
positioned and plumbed, tighten the anchor bolts. Do not
remove wedges or shims, but if protruding, cut off flush with
the edge of the bearing plate before packing with grout.
1. Use metallic non-shrink grout in concealed locations
where not exposed to moisture; use nonmetallic non-
shrink grout in exposed locations, unless otherwise
indicated.
2. Pack grout solidly between bearing surfaces and plates
to ensure that no voids remain.
3.05 INSTALLATION OF STEEL PIPE RAILINGS AND
HANDRAILS
A. Adjust railings prior to anchoring to ensure matching
alignment at abutting joints. Space posts at spacing
indicated, or if not indicated, as required by design loadings.
Plumb posts in each direction.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
101
B. Secure handrails to wall with wall brackets and end fittings.
Provide bracket with not less than 1-1/2 inch clearance from
inside face of handrail and finished wall surface. Locate
brackets as indicated, or if not indicated, at spacing
required to support structural loads. Secure wall brackets
and wall return fittings to building construction as follows:
1. Use type of bracket with flange tapped for concealed
anchorage to threaded hanger bolt.
2. Use type of bracket with pre drilled hole for exposed
bolt anchorage.
3. For concrete and solid masonry anchorage, use drilled
in expansion shield and either concealed hanger bolt or
exposed lag bolt, as applicable.
4. For hollow masonry anchorage, use toggle bolts having
square heads.
5. For wood stud partitions, use lag bolts set into wood
backing between studs. Coordinate with stud
installations for accurate location of backing members.
6. For steel framed gypsum board assemblies, fasten
brackets directly to steel framing or concealed anchors
using self-tapping screws of size and type required to
support structural loads.
3.06 ADJUSTING AND CLEANING
A. Immediately after erection, clean field welds, bolted
connections, and abraded areas of shop paint, and paint
exposed areas with same material as used for shop
painting to comply with SSPC PA 1 requirements for touch
up of field painted surfaces.
1. Apply by brush or spray to provide a minimum dry film
thickness of 2.0 mils.
B. For galvanized surfaces clean welds, bolted connections
and abraded areas and apply galvanizing repair paint to
comply with ASTM A780.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
102
END OF SECTION - METAL FABRICATIONS
3.1.4 METAL DOORS AND FRAMES
PART 1 - GENERAL
1.01 RELATED DOCUMENTS
Drawings and general provisions of the Contract, including
“General Requirements” Specifications Sections, apply to this
Section.
Specifications throughout all Divisions of the technical
Specifications are directly applicable to this Section, and this
section is directly applicable to them.
1.02 REFERENCE STANDARDS
A. All materials, installation and workmanship shall comply
with all applicable requirements and standards.
1.03 QUALITY ASSURANCE
A. Provide doors, panels, and frames complying with the
project drawings.
B. Provide custom steel doors and frames manufactured by a
single firm specializing in the production of this type of work,
unless otherwise acceptable to the Architect and Owner.
C. Fire-Rated Door Assemblies: Assemblies complying with
BS 476 that are listed and labeled by a testing and
inspecting agency acceptable to authorities having
jurisdiction, for fire ratings indicated.
1. Oversize Fire-Rated Door Assemblies: For units
exceeding sizes of tested assemblies provide
manufacturer’s certification that doors conform to all
standard construction requirements of tested and
labeled fire-rated door assemblies except for size.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
103
2. Temperature Rise Rating: At stairwell enclosures,
provide doors that have a temperature rise rating of
232 degrees C maximum in 30 minutes of fire exposure.
1.04 SUBMITTALS
A. Product Data:
1. Product data for each type of door and frame specified,
including details of construction, materials, dimensions,
hardware preparation, core, label compliance, sound
ratings, profiles, and finishes.
B. Shop Drawings:
1. Submit drawings for fabrication and installation of
custom steel doors and frames. Include details of each
frame type, elevations of door design types, conditions
at openings, details of construction, location and
installation requirements of finish hardware and
reinforcements, and details of joints and connections.
a. Coordinate submittals with other doors, frames, and
hardware and use the same “opening number
identification” as given on the Contract Drawings and the
Door Schedule.
Submittals not using the numbering identification shown
on Contract
Drawings and Schedules will be rejected.
2. Label Construction Certification: For door assemblies
required being fire- rated and that exceed limitations of
labeled assemblies, submit manufacturer’s certification
that each door and frame assembly has been
constructed to conform to design, materials and
construction equivalent to requirements for labeled
construction.
C. Record Documents:
1. Provide record approved submittals and warranties.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
104
1.05 DELIVERY, STORAGE AND HANDLING
A. Inspect doors and frames upon delivery for damage. Minor
damages may be repaired provided refinished items are
equal in all respects to new work and acceptable to the
Architect; otherwise remove and replace damaged items as
directed.
B. Store doors and frames at the building Site under cover.
Place units on minimum 4-inch high wood blocking. Avoid
the use of non-vented plastic or canvas shelters that could
create a humidity chamber. If cardboard wrappers on doors
become wet, remove cartons immediately. Provide gap
spaces between stacked doors to promote air circulation.
PART 2 - PRODUCTS
2.01 GENERAL
A. All materials shall meet or exceed all applicable referenced
standards and local requirements, and conform to codes
and ordinances of authorities having jurisdiction.
2.02 MATERIALS
A. Hot-Rolled Steel Sheets: free of scale, pitting or surface
defects; pickled and oiled.
B. Metallic-Coated (Galvanized) Steel Sheets: with zinc or
zinc-iron-alloy coating.
C. Stainless-Steel Sheets: austenitic stainless steel, Type 316.
D. Supports and Anchors: Fabricate of not less than 16-gage
sheet metal. Galvanize after fabrication units to be built into
exterior walls.
E.Inserts, Bolts, and Fasteners: Manufacturer’s standard units,
except hot-dip galvanize items to be built into exterior walls.
F. Shop-Applied Paint: Rust-inhibitive enamel or paint, air-
drying or baking, suitable as base for specified finish paints
on steel surfaces.
G. Intumescent Seals, intumescent fire and smoke seals.
2.03 FABRICATION, GENERAL
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
105
A. Fabricate metal units to be rigid, neat in appearance, and
free from defects, warp, or buckle. Accurately form metal to
required sizes and profiles. Wherever practicable, fit and
assemble units in the manufacturer’s plant. Clearly identify
work that cannot be permanently factory-assembled before
shipment, to assure proper assembly at the Project Site.
Weld exposed joints continuously; grind, fill, dress, and
make smooth, flush, and invisible. Metallic filler to conceal
manufacturing defects is not acceptable.
1. Interior Doors: Minimum 18-gage face sheets.
2. Exterior Doors: Minimum 16-gage face sheets.
B. Unless otherwise indicated, provide countersunk flat or oval
heads for exposed screws and bolts.
C. Prepare doors and frames to receive finish hardware,
including cutouts, reinforcing, mortising, drilling, and tapping
in accordance with final Finish Hardware Schedule and
templates provided by hardware supplier.
1. Reinforce doors and frames to receive surface-applied
hardware. Drilling and tapping for surface-applied finish
hardware may be done at Project Site.
D. Clean, treat, and paint exposed surfaces of steel doors and
frames, including galvanized surfaces, but excluding
stainless steel surfaces.
1. Clean steel surfaces of mill scale, rust, oil, grease, dirt,
and other foreign materials before application of paint.
2. Apply pretreatment to cleaned metal surfaces, using
cold phosphate solution (SSPC-PT2), hot phosphate
solution (SSPC-PT4), or basic zinc chromate-vinyl
butyryl solution (SSPC-PT3).
3. Apply shop coat of prime paint within time limits
recommended by pretreatment manufacturer. Apply a
smooth coat of even consistency to provide a uniform
dry film thickness of not less than 21 microns.
E. Provide stops and moldings around solid, glazed, and
louvered panels where indicated.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
106
1. Form fixed stops and moldings integral with frame,
unless otherwise indicated.
2. Provide removable stops and moldings where indicated
or required, formed of not less than 20-gage steel
sheets matching steel of frames. Secure with
countersunk flat or oval head machine screws spaced
uniformly not more than 30cm on center. Form corners
with butted hairline joints.
3. Coordinate width of rabbet between fixed and
removable stops with type of glass or panel and type of
installation indicated.
2.04 DOORS
A. Provide flush design doors, seamless construction.
1. Unless otherwise required for acoustical or thermal
doors, provide filler of fiberboard, mineral-wool board,
or other insulating material solidly packed full door
height to fill voids between inner core reinforcing
members.
2. Reinforce doors with rigid tubular frame where stiles
and rails are less than 20cm wide. Form tubular frame
with 16-gage steel, welded to outer sheets.
3. Provide internal core constructed of galvanized,
stretcher-leveled steel sheets not less than 18-gage,
vertically reinforced with galvanized sheet steel
sections not less than 22-gage, spaced 6 inches on
center, extending full height of door and spot welded to
both face sheets at not more than 12cm on center.
a. Continuous truss-form reinforcement of 28-gage
galvanized steel may be provided in lieu of spaced steel
sections. Spot weld truss-form reinforcement 7cm on
center vertically and horizontally over entire core surface
on both sides.
4. Reinforce tops and bottoms of doors with galvanized,
18-gage, horizontal steel channels, welded
continuously to core faces. For exterior stainless steel
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
107
doors, close top and bottom edges to provide weather
seal.
B. Painted Exterior Doors: Fabricate exterior doors of two
outer, galvanized, stretcher-leveled steel sheets not less
than 16-gage. Construct doors with smooth, flush surfaces
without visible joints or seams on exposed faces or stile
edges, except around glazed or louvered panel inserts.
Provide weep-hole openings in the bottom of doors to
permit escape of entrapped moisture.
1. Reinforce inside of doors with vertical galvanized sheet
steel sections not less than 22-gage. Space vertical
reinforcing 15 cm on center and extend full door height.
Spot weld at not more than 12 cm on center to both
face sheets.
a. Continuous truss-form inner core of 28-gage galvanized
sheet steel reinforcing may be provided as inner
reinforcement, in lieu of above. Spot weld truss-form
reinforcement 7 cm on center vertically and horizontally
over entire surface of both sides.
2. Reinforce tops and bottoms of doors with 16-gage
horizontal galvanized sheet channels welded
continuously to outer sheets. Close top and bottom
edges to provide flush, waterproof weather seal, as
integral part of door construction or by addition of
inverted steel channels.
C. Painted Interior Doors: Fabricate interior doors of two (2)
outer, cold-rolled, stretcher-leveled steel sheets not less
than 18-gage. Construct doors with smooth, flush surfaces,
without visible joints or seams on exposed faces or stile
edges, except around glazed or louvered panel inserts.
1. Reinforce inside of doors with vertical, hot-rolled, not
less than 22-gage steel sections. Space vertical
reinforcing 15cm on center and extend full door height.
Spot weld at not more than 12cm on center to both
face sheets.
a. Continuous truss-form inner core of 28-gage sheet metal
reinforcing may be provided as inner reinforcement in
lieu of above. Spot weld truss-form reinforcement 7cm
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
108
on center vertically and horizontally over entire surface
of both sides.
2. Reinforce tops and bottoms of doors with 18-gage,
horizontal steel channels, welded continuously to outer
sheets.
D. Stainless Steel Doors: Fabricate from two (2) outer
stainless steel sheets not less than 18-gage, permanently
bonded with contact adhesive to rigid internal steel core.
Construct doors with smooth, flush surfaces without visible
joints or seams on exposed faces or stile edges, except
around glazed or louvered panel inserts. Provide #4 polish
on exposed surfaces with vertical grain direction unless
shown otherwise.
1. Provide Type 316 stainless steel face sheets and
internal components.
E. Fire Rated Doors: Ratings as indicated on Door Schedule,
when tested in accordance with BS 476, labeled by LECM,
or other agency acceptable to the authorities having
jurisdiction.
2.05 FRAMES
A. Fabricate frames of full-welded unit construction, with
corners mitered, reinforced, continuously welded full depth
and width of frame. Knock-down type frames are not
acceptable.
1. Form frames of stainless steel sheets with #4 polish for
openings indicated to receive stainless steel doors.
B. Provide closed or tubular mullions and transom bars where
indicated. Fasten mullions and transom bars at crossings
and to jambs by butt welding. Reinforce joints between
frame members with concealed clip angles or sleeves of
same metal and thickness as frame.
1. Provide false head member to receive lower ceiling
where frames extend to finish ceilings of different
heights.
C. Head Reinforcing: Where installed in masonry, leave
vertical mullions in frames open at top for grouting.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
109
D. Jamb Anchors: Furnish jamb anchors as required to secure
frames to adjacent construction, formed of not less than 18-
gage galvanized steel.
1. Masonry Construction: Adjustable, flat, corrugated, or
perforated, t-shaped to suit frame size, with leg not less
than 5 cm wide by 25 cm long. Furnish at least two (2)
anchors per jamb up to 2.30m in height; Four (4)
anchors up to an 2.40m in jamb height; one (1)
additional anchor for each 0.60m or fraction thereof
over 2.40m in height.
E. Floor Anchors: Provide floor anchors for each jamb and
mullion that extends to floor, formed of not less than 14-
gage galvanized steel sheet, as follows:
1. Monolithic Concrete Slabs: Clip-type anchors, with two
holes to receive fasteners, welded to bottom of jambs
and mullions.
2. Separate Topping Concrete Slabs: Adjustable type with
extension clips, allowing not less than 5 cm height
adjustment. Terminate bottom of frames at finish floor
surface.
F. Head Anchors: Provide two anchors at head of frames
exceeding 1.00 m wide for frames mounted in steel stud
walls.
G. Structural Reinforcing Members: Provide as part of frame
assembly, where indicated at mullions, transoms, or other
locations that are to be built into frame.
H. Head Reinforcing: For frames over 1.20 m wide in masonry
wall openings, provide continuous steel channel or angle
stiffener, not less than 12-gage for full width of opening,
welded to back of frame at head.
I. Spreader Bars: Provide removable spreader bar across
bottom of frames, tack welded to jambs and mullions.
J. Rubber Door Silencers: Except on weather stripped doors,
drill stop in strike jamb to receive three (3) silencers on
single-door frames add drill head jamb stop to receive four
(4) silencers on double-door frames. Install plastic plugs to
keep holes clear during construction.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
110
K. Plaster Guards: Provide 26-gage steel plaster guards or
dust cover boxes, welded to frame, at back of finish
hardware cutouts where mortar or other materials might
obstruct hardware operation and to close off interior of
openings.
2.06 STEEL FINISHES
A. Surface Preparation: Clean surfaces to comply with
“Solvent Cleaning”; remove dirt, oil, grease, or other
contaminants that could impair paint bond. Remove mill
scale and rust, if present, from uncoated steel.
B. Factory Priming for Field-Painted Finish: Apply shop primer
specified below immediately after surface preparation and
pretreatment. Apply a smooth coat of even consistency to
provide a uniform dry film thickness of not less than 0.02
mm.
C. Galvanized Steel Surface Preparation: Clean surfaces with
non-petroleum solvent so surfaces are free of oil and other
contaminants. After cleaning, apply a conversion coating
suited to the organic coating to be applied over it. Clean
welds, mechanical connections, and abraded areas, and
apply galvanizing repair paint (High-zinc dust content paint
for re-galvanizing welds in steel).
D. Galvanized Steel Factory Priming for Field-Painted Finish:
Apply shop primer specified below immediately after
surface preparation and pretreatment. Apply a smooth coat
of even consistency to provide a uniform dry film thickness
of not less than 0.02mm.
E. Shop Primer: Manufacturer’s or fabricator’s standard, fast-
curing, corrosion- inhibiting, lead and chromate-free,
universal primer; compatible with substrate and field-applied
finish paint system indicated; and providing a sound
foundation for field-applied topcoats despite prolonged
exposure.
2.07 STAINLESS STEEL FINISHES
A. Finish designations prefixed by AISI conform to the system
established by the American Iron and Steel Institute for
designating finishes for stainless steel sheet.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
111
B. Unless otherwise indicated, provide Bright, Directional
Polish, AISI No. 4 finish on all stainless steel items.
1. On doors, align direction of polish marks to be vertical.
2. On frames, align direction of polish marks to be vertical
on both jambs and head.
PART 3 - EXECUTION
3.01 INSTALLATION
A. Installation shall meet or exceed all applicable local
requirements, and referenced standards, and conform to
codes and ordinances of authorities having jurisdiction.
B. All installation shall be in accordance with manufacturer’s
published manufacturer’s data, and as herein specified.
1. Setting Masonry Anchorage Devices: Provide masonry
anchorage devices where required for securing frames
to in-place concrete or masonry construction.
a. Set anchorage devices opposite each anchor location, in
accordance with details on final Shop Drawings and
anchorage device manufacturer’s instructions. Leave
drilled holes rough, not reamed, and free from dust and
debris.
2. Floor anchors may be set with powder-actuated
fasteners instead of masonry anchorage devices and
machine screws, if so indicated on final Shop Drawings.
D.Placing Frames: Set frames accurately in position, plumbed,
aligned, and braced securely until permanent anchors are
set. After wall construction is complete, remove temporary
braces and spreaders, leaving surfaces smooth and
undamaged.
1. At in-place concrete or masonry construction, set
frames and secure in place with machine screws and
masonry anchorage devices.
2. Place frames at fire-rated openings in accordance with
BS 476.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
112
3. Make field splices in frames as detailed on final Shop
Drawings, welded and finished to match factory work.
4. Remove spreader bars only after frames or bucks have
been properly set and secured.
E. Install doors after adjacent work is completed and dry. Do
not install doors until closers or stops and holders can be
installed simultaneously for protection of doors.
F. Place fire-rated doors with clearances as specified in BS
476.
3.02 ADJUST AND CLEAN
A. Final Adjustments: Check and readjust operating hardware
items just prior to final inspection. Leave work in complete
and proper operating condition. Remove and replace
defective work, including doors or frames that are warped,
bowed or otherwise unacceptable.
B. Prime Coat Touch-Up: Immediately after erection, sand
smooth any rusted or damaged areas of prime coat and
apply touch-up of compatible air-drying primer.
1. Repair installed dented and damaged units to new
condition by filling with automotive body putty.
2. Fill exposed countersunk anchor screws in countersunk
screw holes with automotive body putty after units are
installed in place.
3. Grind puttied areas smooth, true and even with
surrounding surfaces. Repaint puttied areas with one
additional coat of the specified primer before
proceeding with field painting.
END OF SECTION - METAL DOORS AND FRAMES
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
113
3.1.5 FLUSH WOOD DOORS
PART 1 - GENERAL
1.01 RELATED DOCUMENTS
Drawings and general provisions of the Contract, including
“General Requirements” Specifications Sections, apply to this
Section.
Specifications throughout all Divisions of the technical
Specifications are directly applicable to this Section, and this
section is directly applicable to them.
1.02 REFERENCE STANDARDS
A. The latest published edition of a reference shall be
applicable to this Project unless identified by a specific
edition date.
B. All reference amendments adopted prior to the effective
date of this Contract shall be applicable to this Project.
C. All materials, installation and workmanship shall comply
with all applicable requirements and standards.
1.03 QUALITY ASSURANCE
A. Quality Standards: Comply with the following standards:
1. WDMA Quality Standard: I.S.1A "Architectural Wood
Flush Doors", of Window and Door Manufacturers
Association (WDMA).
2. AWI Quality Standard: "Architectural Woodwork
Quality Standards"; including Section 1300
"Architectural Flush Doors", of Architectural Woodwork
Institute (AWI) for grade of door, core construction,
finish and other requirements exceeding those of
WDMA quality standard.
3. WDMA Quality Marking: Mark each wood door with
WDMA Wood Flush Door Certification Hallmark
certifying compliance with applicable requirements of
WDMA I.S. 1A Series.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
114
4. For manufacturers not participating in WDMA Hallmark
Program, a certification of compliance may be
substituted for marking of individual doors.
B. Obtain doors from a single manufacturer.
1.04 SUBMITTALS
A. Product Data:
1. Door manufacturer's technical data for each type of
door, including details of core and edge construction,
trim for openings and louvers, and factory-finishing
Specifications.
B. Shop Drawings:
1. Submit Shop Drawings indicating location and size of
each door, elevation of each kind of door, details of
construction, location and extent of hardware blocking,
fire ratings, requirements for factory finishing and other
pertinent data.
2. Coordinate submittals with other doors, frames, and
hardware and use the same "opening number
identification" as given on the Drawings and the Door
Schedule.
3. Submittals not using the numbering identification
system shown on Drawings and Schedules will be
rejected.
4. For factory-pre-machined doors, indicate dimensions
and locations of cutouts for locksets and other cutouts
adjacent to visual panels and louver openings.
C. Samples:
1. Submit samples, for the following:
a. Factory-Finished Doors: Each type of factory finish
required.
b. Metal Louvers: Blade and frame in 6" lengths, for each
material and finish required.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
115
c. Metal Frames for visual panels: Metal light frames in 6"
lengths; for each material, type and finish required.
D. Record Documents:
1. Provide record approved shop drawings, samples, and
warranties.
1.05 DELIVERY, STORAGE AND HANDLING
A. Protect doors during transit, storage and handling to
prevent damage, soiling and deterioration. Comply with
requirements of referenced standards and
recommendations of WDMA pamphlet "How to Store,
Handle, Finish, Install, and Maintain Wood Doors", as well
as with manufacturer's instructions.
B. Identify each door with individual opening numbers which
correlate with designation system used on Shop Drawings
for door, frames, and hardware, using temporary,
removable or concealed markings.
1.06 PROJECT CONDITIONS
A. Conditioning: Do not deliver or install doors until conditions
for temperature and relative humidity have been stabilized
and will be maintained in storage and installation areas
during remainder of construction period to comply with the
following requirements applicable to Project's geographical
location:
1. Referenced AWI quality standard including Section
100-S-3 "Moisture Content".
1.07 WARRANTY
A. Warranties shall be in addition to, and not a limitation of,
other rights the Owner may have under the Contract
Documents.
B. Door Manufacturer's Warranty: Submit written agreement in
door manufacturer's standard form signed by Manufacturer,
Installer and Contractor, agreeing to repair or replace
defective doors that have warped (bow, cup or twist) or that
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
116
show telegraphing of core construction in face veneers, or
do not conform to tolerance limitations of referenced quality
standards.
C. Contractor's Responsibilities: Replace or refinish doors
where Contractor's Work contributed to rejection or to
voiding of manufacturer's warranty.
PART 2 - PRODUCTS
2.01 GENERAL
A. All materials shall meet or exceed all applicable referenced
standards, federal, state and local requirements, and
conform to codes and ordinances of authorities having
jurisdiction.
2.02 FLUSH SOLID CORE WOOD DOORS -
PARTICLEBOARD CORE
A. Core Construction: Mat formed wood particleboard core,
complying with ANSI A208.1, Grade LD-2.
1. Bonding: Stiles and rails bonded to core, then entire
unit abrasive planed before veneering.
B. Rails:
1. Top Rail: 5 inch one to three ply closed grain, solid
hardwood or Structural Composite Lumber.
2. Bottom Rail: Hardwood or Structural Composite
Lumber. Provide 5 inch deep rail where concealed door
seal or kick plate is scheduled.
3. Provide 5 inch fire retardant treated, UL approved
hardwood or Structural Composite Lumber top rails at
fire-rated doors.
4. Provide 5 inch fire retardant treated, UL approved
hardwood or Structural Composite Lumber bottom rail
at fire-rated doors where concealed door seal or kick
plate is scheduled.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
117
C. Blocking:
1. Provide lock block reinforcement where mortised
hardware is scheduled.
2. Provide 5 inch hardwood or Structural Composite
Lumber at intermediate- height where exit devices are
scheduled.
3. Provide 5 inch fire retardant treated, UL approved
hardwood or Structural Composite Lumber blocking at
intermediate height at fire-rated doors.
2.03 FLUSH SOLID CORE WOOD DOORS - STAVED
CORE
A. Core: 5-ply bonded low-density wood blocks, random-
lengths, kiln-dried.
1. Bonding: Stiles and rails bonded to core, then entire
unit abrasive planed before veneering.
2.06 FIRE RATED FLUSH WOOD DOORS
A. Core: Incombustible mineral.
1. Provide fire retardant treated, UL approved 5 inch deep
solid hard wood or Structural Composite Lumber top
rail.
2. Provide fire retardant treated, UL approved lock block
reinforcement where mortised hardware is scheduled.
2.07 PLASTIC LAMINATE FACED DOORS, GENERAL
A. AWI grade: Custom
B. Bond: type II water resistant.
C. Plastic Laminate Face Panels: High pressure decorative
laminates complying with NEMA LD3, Grade HGS, 0.048
inches (1.2mm) thick.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
118
D. Colors, Patterns, and Finishes: As selected by Architect
from laminate manufacturer’s full range of colors.
E. Stiles: 1 1/6 inch to 1 1/2 inch wide, one or two ply closed
grain, solid hardwood; paint edge to match laminate faces.
Provide fire retardant treated, UL approved, one or two ply
hardwood stiles at fire-rated doors.
F. Rails:
1. Top Rail: 5 inch one to three ply closed grain, solid
hardwood or Structural Composite Lumber.
2. Bottom Rail: Hardwood or Structural Composite
Lumber. Provide 5 inch deep rail where concealed door
seal or kick plate is scheduled.
3. Provide 5 inch fire retardant treated, UL approved
hardwood or Structural Composite Lumber top rails at
fire-rated doors.
4. Provide 5 inch fire retardant treated, UL approved
hardwood or Structural Composite Lumber bottom rail
at fire-rated doors where concealed door seal or kick
plate is scheduled.
G. Blocking:
1. Provide lock block reinforcement where mortised
hardware is scheduled.
2. Provide 5 inch hardwood or Structural Composite
Lumber at intermediate- height where exit devices are
scheduled.
3. Provide 5 inch fire retardant treated, UL approved
hardwood or Structural Composite Lumber blocking at
intermediate height at fire-rated doors
H. Low Emitting Materials: Provide doors made with adhesives
and composite wood products that do not contain urea
formaldehyde.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
119
2.08 FLUSH SOLID CORE WOOD DOORS, PLASTIC
LAMINATE FACED
A. Construction: Five plies. Mat formed wood particleboard
core, complying with ANSI A208.1, Grade LD-2.
1. Bonding: Stiles and rails bonded to core, with entire
unit abrasive planed before faces and crossbands are
applied.
2.09 FIRE RATED FLUSH WOOD DOORS, PLASTIC
LAMINATE FACED
A. Construction: Incombustible non-asbestos mineral core.
1. Bonding: Stiles and rails bonded to core.
2. Treatment: Components shall be salt free.
2.10 LOUVERS AND LIGHT FRAMES
A. Metal Louvers: Size, type and profile shown and fabricated
from the following: Color Anodized Aluminum: Extruded
aluminum with AA-C22A32, Class II finish.
1. Color: Match Architect's samples.
B. Metal Frames for Light Openings in Fire Doors:
Manufacturer's standard frame formed of 18-gage cold-
rolled steel, factory-primed, and approved for use in door of
fire-rating indicated.
C. Wood Beads for Light Openings in Fire Doors:
Manufacturer's standard fire-rated wood-veneer beads
matching veneer species of door faces.
2.11 FABRICATION
A. Fabricate flush wood doors to produce doors complying
with following requirements:
1. In sizes indicated for Project Site fitting.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
120
2. Factory pre-fit and pre-machine doors to fit frame
opening sizes indicated with the following uniform
clearances and bevels:
a. Comply with tolerance requirements of AWI for
pre-fitting. Comply with final hardware schedules
and door frame Shop Drawings and with hardware
templates.
b. Coordinate measurements of hardware mortises in
metal frames to verify dimensions and alignment
before proceeding with factory pre-machining.
B. Metal Astragals: Pre-machine astragals and formed steel
edges for hardware where required for pairs of fire rated
doors.
C. Openings: Cut and trim openings through doors to comply
with applicable requirements of referenced standards for
kind(s) of doors required.
1. Visual openings: Trim openings with moldings of
material and profile indicated.
2. Louvers: Factory-installed louvers in prepared
openings.
D. Exterior Doors: Treat exterior doors at factory with water
repellent after manufacturing has been completed.
1. Provide manufacturer's standard metal flashing at top
of outswinging units.
E. Fire Rated Wood Doors: Provide wood doors which are
identical in materials and construction to units tested in door
and frame assemblies per ASTM E152 and which are
labeled and listed for ratings indicated by testing and
inspection agency acceptable to authorities having
jurisdiction.
1. Provide UL approved 5 inches deep top rail
reinforcement suitable to hold surface mounted closers
with 1-½ inches x No. 12 fully threaded wood screws
without the use of through-bolted fasteners.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
121
2. At hinge stile, provide additional UL approved
hardwood or high-density material to provide a
minimum 5000 pound screw withdrawal resistance and
minimum 300,000 slam cycles without failure of mortise
hinges.
3. At lock stile, provide additional UL approved "Lock
Block" blocking to provide solid anchorage for
installation of locksets.
4. At mid-rail, provide 5 inches deep continuous blocking
at doors indicated to have exit devices.
PART 3 - EXECUTION
3.01 PREPARATION
A. Examine installed door frames prior to hanging door:
1. Verify that frames comply with indicated requirements
for type, size, location, and swing characteristics and
have been installed with plumb jambs and level heads.
2. Reject doors with defects.
B. Do not proceed with installation until unsatisfactory
conditions have been corrected.
3.02 INSTALLATION
A. Installation shall meet or exceed all applicable federal, state
and local requirements, referenced standards and conform
to codes and ordinances of authorities having jurisdiction.
B. Manufacturer's Instructions: Install wood doors to comply
with manufacturer's instructions and of referenced AWI
standard and as indicated.
1. Install fire rated doors in corresponding fire rated
frames in accordance with requirements of NFPA No.
80.
C. Job Fit Doors: Align and fit doors in frames with uniform
clearances and bevels as indicated below; do not trim stiles
and rails in excess of limits set by manufacturer or
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
122
permitted with fire rated doors. Machine doors for hardware.
Seal cut surfaces after fitting and machining.
1. Fitting Clearances for Non Rated Doors: Provide 1/8
inch at jambs and heads; 1/16 inch per leaf at meeting
stiles for pairs of doors; and 1/8 inch from bottom of
door to top of decorative floor finish or covering. Where
threshold is shown or scheduled, provide ¼ inch
clearance from bottom of door to top of threshold.
2. Fitting Clearances for Fire Rated Doors: Complying
with NFPA 80.
3. Bevel non rated doors 1/8 inch in 2 inches at lock and
hinge edges.
4. Bevel fire rated doors 1/8inch in 2 inches at lock edge;
trim stiles and rails only to extent permitted by labeling
agency.
D. Pre-fit Doors: Fit to frames for uniform clearance at each
edge.
E. Factory Finished Doors: Restore finish before installation, if
fitting or machining is required at the Project Site.
3.03 ADJUSTING AND PROTECTION
A. Operation: Re-hang or replace doors which do not swing or
operate freely.
B. Finished Doors: Refinish or replace doors damaged during
installation.
C. Protect doors as recommended by door manufacturer to
ensure that wood doors will be without damage or
deterioration at time of Substantial Completion.
END OF SECTION - FLUSH WOOD DOORS
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
123
3.1.6 ALUMINIUM WINDOWS
PART 1 – GENERAL
1.01 RELATED DOCUMENTS
Drawings and general provisions of the Contract, including
“General Requirements” Specifications Sections, apply to this
Section.
Specifications throughout all Divisions of the technical
Specifications are directly applicable to this Section, and this
section is directly applicable to them.
1.02 REFERENCE STANDARDS
The latest published edition of a reference shall be applicable
to this Project unless identified by a specific edition date.
All reference amendments adopted prior to the effective date
of this Contract shall be applicable to this Project.
All materials, installation and workmanship shall comply with
all applicable requirements and standards.
1.03 QUALITY ASSURANCE
Installer Qualifications: An experienced installer who has
completed exterior aluminum window systems similar in
material, design, and extent to those indicated for this Project
and whose work has resulted in construction with a record of
successful in-service performance.
Manufacturer Qualifications: A firm experienced in
manufacturing aluminum window systems similar to those
indicated for this Project and with a record of successful in-
service performance.
Source Limitations: Obtain aluminum frames and windows
through one (1) source from a single manufacturer with the
capacity and resources to provide products of consistent
quality in appearance and physical properties.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
124
1.04 PRODUCT OPTIONS
Drawings indicate dimensions, arrangements, alignment, and
profiles of components and assemblies as they relate to
sightlines, to one another, and to adjoining construction size.
Other manufacturers’ products complying with requirements
may be considered.
Do not modify intended aesthetic effects, as judged solely by
Architect, except with Architect’s approval. If modifications are
proposed, submit comprehensive explanatory data to Architect
for review.
1.05 SUBMITTALS
Product Data:
Product data for each type of frame specified, including details
of construction, materials, dimensions, hardware preparation,
label compliance, profiles, and finishes.
Samples:
Furnish representative samples of aluminum finish proposed
for this work for acceptance before any material is shop
assembled, finished, or delivered.
Shop Drawings:
Submit Shop Drawings for fabrication and erection of
prefabricated aluminum window work. Include details of each
frame type, conditions at openings, details of construction,
location, and installation requirements of finish hardware and
reinforcements, and details of joints and connections. Show
anchorage and accessory items. Provide a schedule of frames
using same reference numbers for details and openings as
those on Drawings.
Coordinate submittals with other doors, frames and hardware
and use the same “opening number identification” as given on
the Drawings and the Door Schedule.
Submittals not using the numbering identification system
shown on Drawings and Schedules will be rejected.
1.06 RECORD DOCUMENTS
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
125
Provide record approved product data, shop drawings,
samples, and warranties.
1.07 DELIVERY, STORAGE and HANDLING
Deliver aluminium frames wrapped in protective material or
crated to provide protection during transit and job storage.
Inspect aluminium frame work upon delivery for damage.
Minor damages may be repaired provided the repaired items
are equivalent in all respects to new work; otherwise remove
and replace damaged work as directed.
1.08 SEQUENCING AND SCHEDULING
Conference: Convene a pre-installation conference to
establish procedures to maintain optimum working conditions
and to coordinate this work with related and adjacent work.
1.09 WARRANTY
Warranty: Provide manufacturer's standard limited warranty for
materials and workmanship.
Aluminium Window Warranty Period: 2 year.
Standard Insulating Glass Warranty Period: 5 years.
1.10 SECTION INCLUDES
Aluminium windows
Thermal break aluminum windows; fill and debridge
Thermal break aluminium windows; thermal strut.
PART 2 - PRODUCTS
2.02 WINDOW TYPES
Fixed Frame
Miter-cut assembly, using pin, crimp or self-locating corner
cleats
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
126
Drainage of infiltration and condensation water must be
achieved via oblong slots on the bottom fixed part, with
deflector and membrane
Drip mould sections to shelter external leaves in high exposed
areas for outward opening
Opening Frame
Flush opening sash: Basic opening frame
Opening frame will be made of: Same depth as fixed frame
Miter-cut assembly, using pin, crimp or self-locating corner
cleats
Drip mould section can be fixed:
Outside on fixed frame to shelter from water
Inside on bottom fixed frame to collect condensation water in
colder areas
Weatherproofing
Double weather stripping with a multi-purpose EPDM gasket,
which molds to the shape of the frame corners with no need
for cuts and joints; thanks to its specific dual hardness
technology; on clip on section.
Infill: Takes infill from 3 to 33mm
Glazing beads: 2 design of glazing beads
Square: Assembled at 90º angle
Curved: Miter cut assembly
Mullions:
Mullions can be used as intermediate transom for sash and as
transom or mullion for fixed lights.
Mullions and transoms can be joined together with quarter-turn
junction blocks, or using screw sockets.
In order to accommodate higher wind loads, reinforced
mullions are available in different sizes, according to the
manufacturer instructions.
Locking Hardware and Pull Handles
Locks come with built-in, fool and tamper proof lever system.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
127
Inward and outward opening frames have an integrated
casement stay and ventilation.
Bottom hung frames are fitted with a friction stay.
Tilt and turn fitting comes with a safety friction stay and anti-
unhinging angle bearing.
PERFORMANCES MAX
Water, Air and Wind Resistance Test
European Standards
2.03 MATERIALS
Aluminium profiles are extruded from aluminium alloy
6060 T66 or 6063 T6 to BS1474.
Screws and components are stainless steel or other
corrosion resistant material.
Glazing gaskets and other weather seals are EPDM.
Fixing brackets are rust proofed steel or aluminium as
the installation requires. Do not use welded aluminium for
structural fixings.
2.04 FINISHES
High Performance Organic Coating: AA C12C42R1x
(Chemical Finish: cleaned with inhibited chemicals; Chemical
Finish: chemical conversion coating, acid chromate fluoride
phosphate pretreatment; Organic Coating: as specified below).
Prepare, pretreat, and apply coating to exposed metal
surfaces to comply with coating and resin manufacturer's
instructions.
Fluoropolymer Two (2) Coat Coating System: Manufacturer's
standard two (2) coat thermo cured system, composed of
specially formulated inhibitive primer and fluoropolymer color
topcoat containing not less than 70 percent polyvinylidene
resin by weight; complying with AAMA 605.2.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
128
PART 3 – EXECUTION
3.01 PREPARATION
A. Do not proceed with installation until substrates have been
properly prepared and deviations from manufacturer's
recommended tolerances are corrected. Commencement of
installation constitutes acceptance of conditions.
B. Prepare substrates using the methods recommended by the
manufacturer for achieving the best result for the substrate
under the project conditions.
1. Verify that openings are dimensionally correct and
within allowable tolerances and substrates are plumb,
level, and clean.
2. Verify that anchoring surface is in accordance with
approved shop drawings.
C. If preparation is the responsibility of another installer, notify
Architect in writing of deviations from manufacturer's
recommended installation tolerances and conditions.
3.02 INSTALLATION
A. Install in accordance with manufacturer’s written
instructions and recommendations.
Adjust for proper operation after installation.
3.03 FIELD QUALITY CONTROL
A. Engage a certified testing laboratory to conduct on-site tests
for air infiltration and water infiltration in accordance with
published standards.
B. Repair or replace window units not meeting specified
performance requirements; re-test an equal quantity of
windows.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
129
3.04 CLEANING AND PROTECTION
A. Cleaning:
1. Clean sealants, caulking, and other materials from
surfaces, including adjacent work.
2. Clean window frames, casings, and glass using
materials and methods recommended by the window
and glass manufacturer that do not cause defacement
of work.
3. Clean using methods which comply with AAMA 609.
4. Clean glass using methods which comply with GANA
01-0300.
B. Protect installed products until completion of project.
C. Touch-up, repair or replace damaged products before
Substantial Completion.
END OF SECTION - ALUMINIUM WINDOWS
3.1.7 FINISH HARDWARE
PART 1 - GENERAL
1.01 RELATED DOCUMENTS
Drawings and general provisions of the Contract, including
“General Requirements” Specifications Sections, apply to this
Section.
Specifications throughout all Divisions of the technical
Specifications are directly applicable to this Section, and this
section is directly applicable to them.
1.02 SUMMARY
A. This Section includes items known commercially as finish or
door hardware that are required for swing, sliding, and
folding doors, except special types of unique hardware
specified in the same Sections as the doors and door
frames on which they are installed.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
130
1. Provide cylinders for operation of lock mechanisms
furnished as part of the Work of other Sections such as
entrance doors, rolling doors and grilles, etc.
a. Provide cylinders keyed to building system and
with finish to match adjacent surfaces.
1.03 REFERENCE STANDARDS
A. The latest published edition of a reference shall be
applicable to this Project unless identified by a specific
edition date.
B. All reference amendments adopted prior to the effective
date of this Contract shall be applicable to this Project.
C. All materials, installation and workmanship shall comply
with all applicable requirements and standards.
1.04 QUALITY ASSURANCE
A. Installer Qualifications: An experienced installer who has
completed door hardware installation similar in material,
design, and extent to that indicated for this Project and
whose Work has resulted in construction with a record of
successful in-service performance.
B. Supplier Qualifications: A recognized architectural door
hardware supplier, with warehousing facilities in the
Project's vicinity, that has a record of successful in- service
performance for supplying door hardware similar in quantity,
type, and quality to that indicated for this Project and that
employs an experienced architectural hardware consultant
(AHC) who is available to Owner, Architect, and Contractor,
at reasonable times during the course of the Work, for
consultation.
C. Electrified Door Hardware Supplier Qualifications: An
experienced door hardware supplier who has completed
projects with electrified door hardware similar in material,
design, and extent to that indicated for this Project, whose
Work has resulted in construction with a record of
successful in-service performance, and who is acceptable
to manufacturer of primary materials.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
131
1. Engineering Responsibility: Prepare data for electrified
door hardware, including Shop Drawings, based on
testing and engineering analysis of manufacturer’s
standard units in assemblies similar to those indicated
for this Project.
D. Fire Rated Openings: Provide door hardware for fire rated
openings that comply with NFPA Standard No. 80 and
requirements of authorities having jurisdiction. Provide only
items of door hardware that are listed and are identical to
products tested by UL, Warnock Hersey, FM, or other
testing and inspecting organization acceptable to authorities
having jurisdiction for use on types and sizes of doors
indicated in compliance with requirements of fire rated door
and door frame labels.
E. Source Limitations: Obtain each type and variety of door
hardware from a single manufacturer, unless otherwise
indicated.
1.05 SUBMITTALS
A. Product Data:
1. Include installation details, material descriptions, and
dimensions of individual components, profiles, and
finishes.
B. Shop Drawings:
1. Details of electrified door hardware, indicating the
following:
a. Wiring Diagrams: Detail wiring for power, signal,
and control systems. Differentiate between
manufacturer-installed and field-installed wiring.
Include the following:
1) System schematic.
2) Point-to-point wiring diagram.
3) Riser diagram.
4) Elevation of each door.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
132
2. Details of interface between electrified door hardware
and fire alarm, access control, security, and building
control system.
3. Door Hardware Schedule:
a. Prepared by or under the supervision of supplier,
detailing fabrication and assembly of door
hardware, as well as procedures and diagrams.
Coordinate the final Door Hardware Schedules
with doors, frames, and related Work to ensure
proper size, thickness, hand, function, and finish of
door hardware.
b. Format: Comply with scheduling sequence and
vertical format in DHI’s “Sequence and Format for
the hardware schedule.
c. Organization: Organize the Door Hardware
Schedule into door hardware sets indicating
complete designations of every item required for
each door opening.
d. Use same identifying “set numbers” given in each
Section. Coordinate submittal with doors and
frames submittals and use same “opening number”
identification as given on Drawings and in the Door
Schedule.
e. Submittals not using numbering identification
system shown on Drawings and Schedules will be
rejected.
f. Content: include the following information:
1) Type, style, function, size, and finish of each
hardware item.
2) Name and manufacturer of each item.
3) Fastenings and other pertinent information.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
133
4) Location of each hardware set, cross referenced
to indications on Drawings both on floor plans
and in door and frame schedule.
5) Explanation of all abbreviations, symbols, and
codes contained in schedule.
6) Mounting locations for hardware.
7) Door and frame sizes and materials.
8) Keying information.
9) Description of each electrified door hardware
function, including location, sequence of
operation, and interface with other building
control systems.
g. Submittal Sequence: Submit final schedule at
earliest possible date particularly where
acceptance of hardware schedule must precede
fabrication of other Work that is critical in the
Project construction schedule. Include with
schedule the product data, samples, Shop
Drawings of other Work affected by door hardware,
and other information essential to the coordinated
review of schedule.
4. Keying Schedule: Prepared by or under the supervision
of supplier, detailing Owner’s final keying instructions
for locks. Include schematic keying diagram and index
each key set to unique door designations.
5. Templates for doors, frames, and other specified items
to be factory prepared for the installation of door
hardware. Check Shop Drawings of other Work to
confirm that adequate provisions are made for locating
and installing door hardware to comply with indicated
requirements.
C. Samples:
1. Samples of each type of exposed hardware unit in
finish indicated and tagged with full description for
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
134
coordination with schedule. Submit samples prior to
submission of final hardware schedule.
D. Record Documents:
1. Provide record approved product data, shop drawings,
samples, and warranties.
1.06 COORDINATION
A. Coordinate the Work of this Section with Work of other
sections that interface with hardware.
B. Furnish templates for doors, frames, and other Work
specified to be factory prepared for the installation of door
hardware to the appropriate trades. Check Shop Drawings
of other Work to confirm that adequate provisions are made
for locating and installing door hardware to comply with
indicated requirements.
1.07 HARDWARE ALLOWANCE
A. Selection and Ordering: Furnish door hardware as selected
by Architect and in such quantities as provided for under
Division 01 and other general provisions of the Contract.
B. Door hardware supplier's responsibilities shall be as follows:
1. Submittals: Submit through Contractor required product
data, final hardware schedule, separate keying
schedule, and samples as specified in this Section,
unless otherwise indicated.
2. Construction Schedule: Inform Contractor promptly of
estimated times and dates that will be required to
process submittals, to furnish templates, to deliver
hardware, and to perform other Work associated with
furnishing door hardware for purposes of including this
data in construction schedule. Comply with this
schedule.
3. Coordination and Templates: Assist Contractor as
required to coordinate hardware with other Work in
respect to both fabrication and installation. Furnish
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
135
Contractor with templates and deliver hardware to
proper locations.
4. Product Handling: Package, identify, deliver, and
inventory door hardware specified in this Section.
5. Discrepancies: Based on requirements indicated in
Contract Documents in effect at time of door hardware
selection, furnish types, finishes, and quantities of door
hardware, including fasteners, and Owner's
maintenance tools required to comply with specified
requirements and as needed to install and maintain
hardware. Furnish or replace any items of door
hardware resulting from shortages and incorrect items
at no cost to the Owner or Contractor. Obtain signed
receipts from Contractor for all delivered materials.
C. Contractor's responsibilities shall be as follows:
1. Submittals: Coordinate and process submittals for door
hardware in same manner as submittals for other Work.
2. Construction Schedule: Cooperate with door hardware
supplier in establishing scheduled dates for submittals
and delivery of templates and door hardware.
Incorporate in construction schedule the times and
dates related to furnishing hardware by door hardware
supplier.
3. Coordination: Coordinate door hardware with other
Work. Furnish hardware supplier or manufacturer with
Shop Drawings of other Work where required or
requested. Verify completeness and suitability of
hardware with supplier.
4. Product Handling: Provide secure lock up for hardware
delivered to the Site. Inventory hardware jointly with
representative of hardware supplier and issue signed
receipts for all delivered materials.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
136
1.08 PRODUCT HANDLING
A. Tag each item or package separately with identification
related to final hardware schedule, and include basic
installation instructions with each item or package.
B. Packaging of door hardware is responsibility of supplier. As
hardware supplier from various manufacturers receives
material, sort and repackage in containers clearly marked
with appropriate hardware set number to match set
numbers of approved hardware schedule. Two (2) or more
identical sets may be packed in same container.
1. Levers, handles and pulls shall be provided with cloth
or cotton covered paper coverings, of sufficient size to
completely cover the items, secured to remain in place.
2. Keys: Tag and mark to identify lock, which they will
pass.
C. Inventory door hardware jointly with representatives of
hardware supplier and hardware installer until each is
satisfied that count is correct.
D. Deliver individually packaged door hardware items promptly
to place of installation (shop or Project Site).
E. Provide secure lock up for door hardware delivered to the
Project, but not yet installed. Control handling and
installation of hardware items that are not immediately
replaceable so that completion of the Work will not be
delayed by hardware losses both before and after
installation.
1.09 MAINTENANCE
A. Maintenance Tools and Instructions: Furnish a complete set
of specialized tools and maintenance instructions as
needed for Owner's continued adjustment, maintenance,
and removal and replacement of door hardware.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
137
PART 2 - PRODUCTS
2.01 GENERAL
A. All materials shall meet or exceed all applicable referenced
standards, federal, state and local requirements, and
conform to codes and ordinances of authorities having
jurisdiction.
2.02 MATERIALS AND FABRICATION
A. Base Metals: Produce hardware units of base metal,
fabricated by forming method indicated, using
manufacturer’s standard alloy, composition, temper, and
hardness. Furnish metals of a quality equal to or greater
than that of specified door hardware units and BHMA
A156.18 for finishes. Do not furnish manufacturer’s
standard materials or forming methods if different from
specified standard.
B. Fasteners: Provide door hardware manufactured to comply
with published templates generally prepared for machine,
wood, and sheet metal screws. Provide screws according to
commercially recognized industry standards for application
intended. Provide Phillips flat-head screws with finished
heads to match surface of door hardware, unless otherwise
indicated.
2.03 HINGES, BUTTS, AND PIVOTS
A. Templates: Except for hinges and pivots to be installed
entirely (both leaves) into wood doors and frames, provide
only template produced units.
B. Screws: Provide Phillips flat head screws complying with
the following requirements:
1. For metal doors and frames install machine screws into
drilled and tapped holes.
2. For wood doors and frames install wood screws.
3. For fire rated wood doors install #12 x 1 1/4 inch,
threaded to the head steel wood screws.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
138
4. Finish screw heads to match surface of hinges or
pivots.
C. Hinge Pins: Except as otherwise indicated, provide hinge
pins as follows:
1. Out Swing Exterior Doors: Non-removable pins.
2. Out Swing Corridor Doors with Locks: Non-removable
pins.
3. Interior Doors: Non-rising pins.
4. Tips: Flat button and matching plug, finished to match
leaves, except where hospital tip (HT) indicated.
D. Number of Hinges: Provide number of hinges indicated but
not less than three (3) hinges per door leaf for doors 90
inches or less in height and one (1) additional hinge for
each 30 inches of additional height.
1. Fire Rated Doors: Not less than three (3) hinges per
door leaf for doors 90 inches or less in height with
same rule for additional hinges.
E. Continuous Hinges:
1. Hinge to be manufactured of 6063-T6- aluminum alloy
with anodized finishes (painted finishes available on
entire hinge or gear cap only).
2. Door and frame leaves to be machined, anodized and
assembled as a matched pair. Door and frame leaves
to be anodized after all machining and drilling
processes are complete.
3. All hinge profiles shall be manufactured to template
screw locations, with standard duty and heavy duty
hole patterns identical as to number and placement of
holes. All hinge profiles to be manufactured to template
bearing locations, with standard duty bearing
configurations of 5-1/8 inch spacing with a minimum of
sixteen (16) bearings; and heavy duty at 2-9/16 inch
spacing with a minimum of thirty-two (32) bearings.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
139
4. Hinge leaves to be extruded at a uniform 1/8 inch
thickness from pivot point to outside edge of hinge leaf.
Uncut hinges shall be non-handed and shall be
paintless assembly of three (3) interlocking extrusions
applied to the full height of the door and frame without
mortising.
5. Vertical door loads shall be carried on chemically
lubricated thermoplastic thrust bearings. The door and
frame leaves shall be continuously geared together for
the entire hinge length and this relationship secured
with a full length cover channel so that the hinge will
operate through a full 180 degrees.
6. All rotating areas of the gear cap and geared leaves
shall have a permanent lubrication which is factory
applied along the full length of the hinge, and the
lubricant shall last the life of the hinge with no
additional maintenance required. Fasteners supplied
shall be 410 stainless steel, bright hardened and plated.
2.04 LOCK CYLINDERS AND KEYING
A. Master key and grand master key to the existing "Best"
system. No substitution.
B. Furnish six (6) master keys and three (3) change keys per
key set. All keys and final cores are to be provided direct to
Owner by this supplier. Do not permit best change key
access by anyone other than Owner's personnel.
2.05 LOCKS, LATCHES, AND BOLTS
A. Strikes: Provide manufacturer's standard wrought box strike
for each latch or lock bolt, with curved lip extended to
protect frame, finished to match hardware set, unless
otherwise indicated.
1. Provide flat lip strikes for locks with 3 pieces, antifriction
latch bolts as recommended by manufacturer.
2. Provide extra-long strike lips for locks used on frames
with applied wood casing trim.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
140
3. Provide recess type top strikes for bolts locking into
head frames, unless otherwise indicated.
4. Provide dust proof strikes for foot bolts, except where
special threshold construction provides non recessed
strike for bolt.
5. Provide roller type strikes where recommended by
manufacturer of the latch and lock units.
6. Provide standard (open) strike plates for interior doors
of residential units where wood door frames are used.
B. Lock Throw: Provide 5/8 inch minimum throw of latch on
pairs of doors. Comply with UL requirements for throw of
bolts and latch bolts on rated fire openings.
1. Provide 1/2 inch minimum throw of latch for other bored
and preassembled types of locks and 3/4 inch
minimum throw of latch for mortise locks. Provide 1
inch minimum throw for all dead bolts.
C. Flush Bolt Heads: Minimum of 1/2 inch diameter rods of
brass, bronze, or stainless steel with minimum 12 inch long
rod for doors up to 7 feet 0 inches in height. Provide longer
rods as necessary for doors exceeding 7 feet 0 inches in
height.
D. Rabbeted Doors: Where rabbeted door stiles are indicated,
provide special rabbeted front on lock and latch units and
bolts.
2.06 PROGRAMMABLE / ELECTRIFIED LOCKING
DEVICES
A. Programmable Locking Device:
1. Lock shall be heavy-duty cylindrical type, with a 2-¾
inches backset supplied with a ½ inch throw latch bolt
as standard. Chassis shall accommodate standard 161
cylindrical lock prep for 1-¾ inch doors as standard,
with 1-3/8 inches to 2-¾ inch thick doors in 1/8 inch
increments available. Locksets shall be provided from
the factory with the appropriate handing.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
141
2. Outside and inside levers shall operate independently
of each other. Lock shall use patented, clutch
mechanism to deter vandalism and maximize durability.
Disablement of secured levers shall not permit latch
bolt retraction from secure side while allowing
emergency egress.
3. The lock will be furnished with the Classroom and
Storeroom function which is: The outside lever is
normally locked. The inside lever is always free. The
unit may be momentarily unlocked with an approved
Normal access credential. The unit may be maintained
unlocked by using a Toggle access credential.
4. Emergency mechanical key override utilizes a 1-¼ inch
mortise cylinder with standard straight cam.
5. Outside escutcheon shall contain an integrated 6-
button keypad.
6. Visual red and green LED indicators shall indicate
activation, operational system status, system error
conditions and low power conditions.
7. Device as manufactured by Best Access Systems. No
substitution.
B. Electrified Locking Device: A security platform that
combines mechanical hardware with the ability to monitor
door openings with Owner’s existing access control panel
and software.
1. Complete monitoring of door from the lockset.
2. Panel interface board connects to third party access
control panel.
3. Available in proximity or magnetic stripe.
4. Simplified request to exit component contained in the
inside trim.
5. Industry standard HID Prox coordinates with Owner’s
existing credential.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
142
6. UL tested for use on fire doors up to and including 3
hours. ANSI Grade 1.
2.07 EXIT DEVICES
A. Exit Devices shall be touchpad type, fabricated of bronze,
brass, stainless steel, or aluminum, and plated to the
standard architectural finishes to match the balance of door
hardware.
B. All exit devices shall incorporate a fluid damper, which
decelerates the touchpad on its return stroke and eliminates
noise associated with exit device operation. Touchpad shall
extend a minimum of one half of the door width. All latch
bolts to be dead latching type, with a self-lubrication coating
to reduce wear. Mechanism case and end-cap will be
0.140-gauge attachment to door. Touchpad shall match exit
device finish, and shall be stainless steel for US26, US26D,
US28, US32, and US32D finishes. Only compression
springs will be used in devices, latches, and outside trims or
controls.
C. Exit devices shall be UL listed panic exit hardware. All exit
devices for fire rated openings shall be UL labeled fire exit
hardware.
D. Lever trim for exit devices shall be vandal-resistant type,
which will travel to a 90-degree down position when more
than 35 pounds of torque are applied, and which can easily
be re-set.
E. All exit devices shall be of one manufacturer. No deviation
will be considered.
F. All trim shall be thru-bolted to the lock stile case. Lever
designs to match locksets.
G. Surface vertical rod devices shall be UL labeled for fire door
applications without the use of bottom rod assemblies.
Where bottom rods are required for security applications,
the devices shall be UL labeled for fire door applications
with rod and latch guards by the device manufacturer.
2.08 CLOSERS AND DOOR CONTROL DEVICES
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
143
A. Access-Free Manual Closers: Where manual closers are
indicated for doors required to be accessible to the
physically handicapped, provide adjustable units complying
with ADA and ANSI A-117.1 provisions for door opening
force.
1. At interior doors, adjust closers for door opening force
not to exceed 5 foot- pounds of force. If a door has a
closer, then the sweep period of the closer shall be
adjusted so that from an open position of 90 degrees,
the time required to move the door to a position of 12
degrees from the latch is five (5) seconds minimum.
2. At exterior doors, adjust closers for door opening force
not to exceed 8.5 foot-pounds of force.
3. Where parallel arms are indicated for closers, provide
closer unit one (1) size larger than recommended for
use with standard arms.
B. Door closers shall have fully hydraulic, full rack and pinion
action with a high strength cast iron cylinder. All closers
shall be of one (1) manufacturer. All closers shall utilize a
stable fluid withstanding temperature range of 120 degrees
F to -30 degrees F without seasonal adjustment of closer
speed to properly close the door. Closers for fire-rated
doors shall be provided with temperature stabilizing fluid
that complies with standards UBC 7-2 (1997) and UL 10C.
C. Spring power shall be continuously adjustable over the full
range of closer sizes, and allow for reduced opening force
for the physically handicapped. Spring power adjustment
allows for quick and accurate power adjustment and visually
shows closer power size settings by way of dial adjustment
gauge located on closer spring tube. Hydraulic regulation
shall be by tamper-proof, non-critical valves. Closers shall
have separate adjustment for latch speed, general speed
and back check. Door closers with pressure relief valves
are not acceptable.
D. All closers shall have solid forged steel main arms (and
forearms for parallel arm closers) and where specified shall
have a cast-in solid stop on the closer shoe.
E. All surface closers shall be certified to exceed ten million full
load cycles by a recognized independent testing laboratory.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
144
All closers (overhead, surface and concealed shall be of
one (1) manufacturer and carry manufacturer’s ten (10)
year warranty (electric closers to have two (2) year
warranty).
F. Overhead concealed closers shall have spring power
adjustable for 50 percent increase in closing power and fully
mortised door tracks.
G. Closers to be installed to allow door swing as shown on
plans. Doors swinging into exit corridors shall provide for
corridor clear width as required by code. Where possible,
mount closers on inside of rooms.
H. Provide brackets, mounting plates, and fastener types for
closers as required for proper installation with door and
frame conditions. Closers shall be attached to wood doors
with sex bolts.
I. Powder coating finish to be certified to exceed 100 hours
salt spray testing by ETL, an independent testing laboratory
used by BHMA for ANSI certification.
J. Combination Door Closers and Holder: Provide units
designed to hold door in open position under normal usage
and to release and close door automatically under fire
conditions. Incorporate an integral electromagnetic holder
mechanism designed for use with UL listed fire detectors,
provided with normally closed switching contacts.
K. Magnetic Door Holders to be heavy duty wall or floor
mounted with metal housing and complete mounting
hardware. Provide 24V holding coils unless otherwise
scheduled.
L. Flush Floor Plates: Provide finished metal flush floor plates
for floor closers except where thresholds are indicated and
cover plate is specified to be an integral part of threshold.
Finish floor plate to match hardware sets, unless otherwise
indicated.
M. Recessed Floor Plates: Provide recessed floor plates where
no thresholds are indicated and floor closers are located in
an area of resilient flooring, stone flooring, or terrazzo.
Recess plates to receive an insert of the floor finish material
of the normal thickness as indicated. Provide extended
spindle on closer as may be necessary to accommodate
thickness of floor finish.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
145
1. When floor finish includes metal divider or expansion
strips, match exposed ring of recessed floor plate on
closer with metal of floor strips.
2.09 PUSH / PULL UNITS
A. Concealed Fasteners: Provide manufacturer's special
concealed fastener system for installation, through bolted
for matched pairs but not for single units.
2.10 DOOR TRIM UNITS
A. Fasteners: Provide manufacturer's standard exposed
fasteners for door trim units consisting of either machine
screws or self-tapping screws.
B. Fabricate edge trim of stainless steel to fit door thickness in
standard lengths or to match height of protection plates.
C. Fabricate protection plates not more than 1-1/2 inches less
than door width on hinge side and not more than 1/2 inch
less than door width on pull side by height indicated.
1. Metal Plates: Stainless steel, 0.050 inch (U.S. 18-gage).
2.11 HARDWARE FOR INTERIOR SLIDING DOORS
A. Provide manufacturer's standard hardware for interior
sliding doors when not furnished as part of complete door
package.
B. Operating Hardware for Bypassing Doors: Provide
manufacturer's complete set consisting of extruded
aluminum overhead track, adjustable hangers (carriages),
bumpers, and floor guides designed to accommodate the
number, size, thickness, and weight of door leaves
indicated. Provide flush pulls for each door leaf.
C. Operating Hardware for Pocket Doors: Provide
manufacturer's complete set consisting of extruded
aluminum or galvanized steel overhead track, adjustable
hangers (carriages), galvanized steel split jambs and split
studs, wood nailers for head track, jambs and studs,
galvanized steel brackets for assembly and attachment to
floor and wall framing, bumpers, and nylon floor guides
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
146
designed to accommodate the number (single and bi-
parting), size, thickness, and weight of door leaves
indicated. Provide flush pull and edge pull for each door leaf.
2.12 WEATHERSTRIPPING AND SEALS
A. Provide continuous weatherstripping on exterior doors and
smoke, light, or sound seals on interior doors where
indicated or scheduled. Provide non-corrosive fasteners for
exterior applications and elsewhere as indicated.
B. Replaceable Seal Strips: Provide only those units where
resilient or flexible seal strip is
2.13 HARDWARE FINISHES
A. Match items to the manufacturer's standard color and
texture finish for the latch and lock sets (or push pull units if
no latch or lock sets).
B. Provide finishes that match those established by
ANSI/BHMA or, if none established, match the Architect's
sample.
C. Provide quality of finish, including thickness of plating or
coating, composition, hardness, and other qualities
complying with manufacturer's standards, but in no case
less than specified by referenced standards for the
applicable units of hardware.
D. Provide protective lacquer coating on all exposed hardware
finishes of brass, bronze, and aluminum, except as
otherwise indicated. The suffix "NL" is used with standard
finish designations to indicate "no lacquer."
E. The designations used in schedules and elsewhere to
indicate hardware finishes are those listed in ANSI/BHMA
A156.18, "Materials and Finishes," including coordination
with the traditional U.S. finishes shown by certain
manufacturers for their products.
PART 3 - EXECUTION
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
147
3.01 INSTALLATION
A. Installation shall meet or exceed all applicable federal, state
and local requirements, referenced standards and conform
to codes and ordinances of authorities having jurisdiction.
B. All installation shall be in accordance with manufacturer’s
published recommendations.
C. Mount hardware units at heights indicated in following
applicable publications, except as specifically indicated or
required to comply with governing regulations and except
as otherwise directed by Architect.
1. "Recommended Locations for Builders Hardware for
Standard Steel Doors and Frames" by the Door and
Hardware Institute.
2. "Recommended Locations for Builders Hardware for
Custom Steel Doors and Frames" by the Door and
Hardware Institute.
3. NWWDA Industry Standard I.S.1.7, "Hardware
Locations for Wood Flush Doors"; applicable for flush
wood doors 1-3/8 and1-3/4 inches thick by 6 feet 8
inches and 7 feet 0 inches high.
D. Install each hardware item in compliance with the
manufacturer's instructions and recommendations. Where
cutting and fitting is required to install hardware onto or into
surfaces that are later to be painted or finished in another
way, coordinate removal, storage, and reinstallation or
application of surface protection with finishing Work
specified in the Division 09 Sections. Do not install surface
mounted items until finishes have been completed on the
substrates involved.
E. Set units level, plumb, and true to line and location. Adjust
and reinforce the attachment substrate as necessary for
proper installation and operation.
F. Drill and countersink units that are not factory prepared for
anchorage fasteners. Space fasteners and anchors in
accordance with industry standards.
G. Set thresholds for exterior doors in full bed of butyl rubber
or polyisobutylene mastic sealant complying with
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
148
requirements specified in Division 07 Section "Joint
Sealers."
H. Weatherstripping and Seals: Comply with manufacturer's
instructions and recommendations to the extent installation
requirements are not otherwise indicated.
1. Where adhesive applied items are indicated, abrade or
otherwise prepare the substrate for complete adhesion
to ensure the items will not delaminate.
I. Install manufacturer supplied, temporary keyed construction
cores for all exterior doors, suite entry doors, and doors
where electrified hardware is scheduled. For all other doors,
install Owner-provided, temporary non-keyed plastic
construction cores unless keyed construction cores are
specifically called for.
3.02 ADJUSTING, CLEANING, AND DEMONSTRATING
A. Adjust and check each operating item of hardware and
each door to ensure proper operation or function of every
unit. Replace units that cannot be adjusted to operate freely
and smoothly or as intended for the application made.
1. Where door hardware is installed more than one (1)
month prior to acceptance or occupancy of a space or
area, return to the installation during the week prior to
acceptance or occupancy and make final check and
adjustment of all hardware items in such space or area.
Clean operating items as necessary to restore proper
function and finish of hardware and doors. Adjust door
control devices to compensate for final operation of
heating and ventilating equipment.
B. Clean adjacent surfaces soiled by hardware installation.
C. Instruct Owner's personnel in the proper adjustment and
maintenance of door hardware and hardware finishes.
END OF SECTION - FINISH HARDWARE
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
149
3.1.8 GLASS AND GLAZING
PART 1 - GENERAL
1.01 RELATED DOCUMENTS
Drawings and general provisions of the Contract, including
“General Requirements” Specifications Sections, apply to this
Section.
Specifications throughout all Divisions of the technical
Specifications are directly applicable to this Section, and this
section is directly applicable to them.
1.02 REFERENCE STANDARDS
The latest published edition of a reference shall be applicable
to this Project unless identified by a specific edition date.
All reference amendments adopted prior to the effective date
of this Contract shall be applicable to this Project.
All materials, installation and workmanship shall comply with
all applicable local requirements, and conform to codes and
ordinances of the authorities having jurisdiction.
1.03 DEFINITIONS
Manufacturer is used in this Section to refer to a firm that
produces primary glass or fabricated glass as defined in the
referenced glazing standard.
Deterioration of Coated Glass: Defects developed from normal
use that is attributed to the manufacturing process and not to
causes other than glass breakage and practices for
maintaining and cleaning coated glass contrary to
manufacturer's directions. Defects include peeling, cracking,
and other indications of deterioration in metallic coating.
Deterioration of Laminated Glass: Defects developed from
normal use that are attributed to the manufacturing process
and not to glass breakage and practices for maintaining and
cleaning laminated glass contrary to manufacturer's directions.
Defects include edge separation, delamination materially
obstructing vision through glass, and blemishes exceeding
those allowed by referenced laminated glass standard.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
150
Deterioration of Insulating Glass: Failure of the hermetic seal
under normal use due to causes other than glass breakage
and improper practices for maintaining, and cleaning insulating
glass. Evidence of failure is the obstruction of vision by dust,
moisture, or film on the interior surfaces of glass. Improper
practices for maintaining and cleaning glass do not comply
with the manufacturer's directions.
1.04 QUALITY ASSURANCE
A. Glazing Publications: Comply with published
recommendations of glass product manufacturers and
organizations below, except where more stringent
requirements are indicated. Refer to these publications for
glazing terms not otherwise defined in this Section or in
referenced standards.
B. Safety Glass: Products complying with ANSI Z97.1 and
testing requirements of 16 CFR Part 1201 for Category II
materials.
1. Subject to compliance with requirements, provide
safety glass permanently marked with certification label
of Safety Glazing Certification Council (SGCC) or other
certification agency acceptable to authorities having
jurisdiction.
C. Insulating Glass Certification Program: Provide insulating
glass units permanently marked either on spacers or at
least one component lite of units with appropriate
certification label of inspecting and testing agency indicated
below:
1. Insulating Glass Certification Council (IGCC).
D. Glazier Qualifications: Engage an experienced glazier who
has completed glazing similar in material, design, and
extent to that indicated for Project with a record of
successful in service performance.
E. Single Source Responsibility for Glass: Obtain glass from
one source for each product indicated in the project.
F. Single Source Responsibility for Glazing Accessories:
Obtain glazing accessories from one source for each
product and installation method indicated.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
151
G. Field Constructed Mockups: Prior to glazing, erect mockups
for each glass product indicated below to verify selections
made under sample submittals and to demonstrate
aesthetic effects and quality of materials and execution.
Build mockups to comply with the following requirements,
using materials indicated for final unit of Work:
1. Glass Products: Erect mockups with the following kinds
of glass to match glazing systems required for Project,
including typical lite size, framing systems, and glazing
methods:
a. Heat strengthened coated glass.
b. Fully tempered glass.
c. Spandrel glass.
d. Laminated glass.
e. Coated insulating glass.
2. Place mockups at the Project Site in location and of
size indicated or, if not indicated, as directed by
Architect.
3. Notify Architect one week in advance of the dates and
times when mockups will be erected.
4. Obtain Architect's acceptance of mockups before start
of final unit of Work.
5. Demonstrate the proposed range of aesthetic effects
and workmanship.
6. Retain and maintain mockups during construction in
undisturbed condition as a standard for judging
completed unit of Work.
a. Accepted mockups in undisturbed condition at time
of Substantial Completion may become part of
completed unit of Work.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
152
b. Perform tests under normal environmental
conditions during installation.
7. Schedule sufficient time to test and analyze results to
prevent delay in the Work.
8. Investigate materials failing compatibility or adhesion
tests and get sealant manufacturer's written
recommendations for corrective measures, including
using special primers.
9. Testing is not required when glazing sealant
manufacturer can submit required preparation data that
is acceptable to Architect and is based on previous
testing of current sealant products for adhesion to and
compatibility with submitted glazing materials.
1.05 SUBMITTALS
A. Product Data:
1. Submit manufacturer's technical data for each glazing
material and fabricated glass product required,
including installation and maintenance instructions.
B. Samples:
1. Submit, for verification purposes, 12 inch square
samples of each type of glass indicated except for clear
single pane units, and 12 inch long samples of each
color required (except black) for each type of sealant or
gasket exposed to view. Install sealant or gasket
sample between two strips of material representative of
adjoining framing system in color.
C. Certificate: Submit certificates from respective
manufacturers attesting that glass and glazing materials
furnished for Project comply with requirements.
1. Separate certification will not be required for glazing
materials bearing manufacturer's permanent labels
designating type and thickness of glass, provided
labels represent a quality control program involving a
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
153
recognized certification agency or independent testing
laboratory acceptable to authorities having jurisdiction.
D. Compatibility and Adhesion Test Report: Submit statement
from sealant manufacturer indicating that glass and glazing
materials have been tested for compatibility and adhesion
with glazing sealants and interpreting test results relative to
material performance, including recommendations for
primers and substrate preparation needed to obtain
adhesion.
E. Record Documents:
1. Provide record approved product data, samples,
reports, and certificates.
1.06 DELIVERY, STORAGE AND HANDLING
Protect glazing materials to comply with manufacturer's
directions and as needed to prevent damage to glass and
glazing materials from condensation, temperature changes,
direct exposure to sun, or other causes.
1. Where insulating glass units will be exposed to
substantial altitude changes, comply with insulating
glass fabricator's recommendations for venting and
sealing to avoid hermetic seal ruptures.
1.07 SYSTEM PERFORMANCE REQUIREMENTS
A. Provide glazing systems that are produced, fabricated, and
installed to withstand normal thermal movement, wind
loading, and impact loading (where applicable), without
failure including loss or glass breakage attributable to the
following: defective manufacture, fabrication, and
installation; failure of sealants or gaskets to remain
watertight and airtight; deterioration of glazing materials;
and other defects in construction.
B. Glass Design: Glass thicknesses indicated on Drawings are
for detailing only. Confirm glass thicknesses by analyzing
Project loads and in service conditions. Provide glass lites
for the various size openings in the thicknesses and
strengths (annealed or heat treated) to meet or exceed the
following criteria:
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
154
1. Minimum glass thickness, nominally, of lites in exterior
walls is 6.0.
2. Tinted and heat absorbing glass thicknesses for each
tint indicated are the same throughout Project.
1.08 PROJECT CONDITIONS
Environmental Conditions: Do not proceed with glazing when
ambient and substrate temperature conditions are outside the
limits permitted by glazing materials manufacturer or when
glazing channel substrates are wet from rain, frost,
condensation, or other causes.
PART 2 - PRODUCTS
2.01 GENERAL
All materials shall meet or exceed all applicable referenced
standards, federal, state and local requirements, and conform
to codes and ordinances of authorities having jurisdiction.
2.02 PRIMARY GLASS PRODUCTS
Glass Systems and/or Glazing shall be in accordance to the
materials codes and glass types below (please refer to
Drawings and Drawings Materials List for complementary
information):
GLASS TYPES
Glass Type "1":
Clear float glass conforming to ASTM C 1036, Type I, Class 1,
Quality q3; 6mm thick.
Glass Type "2":
Clear float glass conforming to ASTM C 1036, Type I, Class 1,
Quality q3, which has been fully tempered by manufacturer's
standard process (after cutting to final size), to achieve a flexural
strength of 4 times normal glass strength, in accordance with ASTM
C 1048, Condition A; 6mm thick.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
155
Glass Type "3":
Clear float glass conforming to ASTM C1036 Type I, Class 1,
Quality q3, 10mm thick, with polished edges.
Glass Type "4":
Bronze tinted float glass conforming to ASTM C 1036, Type I, Class
2, Quality q3; 6mm thick unless otherwise indicated with a visible
light transmittance of 55 percent, Reflectance of 6 percent, and a
shading coefficient of 0.73.
Glass Type "5":
Bronze tinted float glass conforming to ASTM C 1036, Type I, Class
2, Quality q3, which has been fully tempered by manufacturer's
standard process (after cutting to final size), to achieve a flexural
strength of 4 times normal glass strength, in accordance with ASTM
C 1048, Condition A; 6mm thick with a visible light transmittance of
55 percent, Reflectance of 6 percent, and a shading coefficient of
0.73.
Glass Type "6":
Laminated glass conforming to ASTM C1172, 9/16 inch nominal
overall thickness, consisting of an outboard light of 6mm thick clear
float glass laminated with a polyvinyl butyral interlayer to an inboard
light of 1/4 inch thick clear float glass.
Glass Type "7":
Laminated glass conforming to ASTM C1172, consisting of 2
sheets of clear float glass, 3mm thick, complying with ASTM C
1036, Type I, Class 2, laminated with a polyvinyl butyral interlayer
by manufacturer's standard heat-plus-pressure process with dirt, air
pockets, and foreign substances excluded.
Glass Type "8":
Insulating glass, 25mm overall thickness, double glass with 12mm
air space; exterior light 6mm thick coated bronze tinted tempered
float glass; interior light 6mm thick clear float glass, LOF "Eclipse
Clear (2)" glazed with the coating on the Number 2 surface as
viewed from the exterior with a visible light transmittance of 36
percent, Reflectance of 42 percent, and a shading coefficient of
0.55.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
156
Glass Type "9":
Insulating glass, 25mm overall thickness, double glass with 12mm
air space; exterior light 6mm thick coated bronze tinted tempered
float glass; interior light 6mm thick clear tempered float glass, LOF
"Eclipse Clear (2)" glazed with the coating on the Number 2 surface
as viewed from the exterior with a visible light transmittance of 36
percent, Reflectance of 42 percent, and a shading coefficient of
0.55.
Glass Type "10":
Insulating glass, 25mm overall thickness, double glass with 12mm
air space; exterior light 6mm thick coated bronze tinted tempered
float glass; interior light 8mm thick clear laminated glass, similar to
LOF "Eclipse Bronze (2)" glazed with the coating on the Number 2
surface as viewed from the exterior with a visible light transmittance
of 21 percent, Reflectance of 19 percent, and a shading coefficient
of 0.41.
Glass Type "11":
Spandrel Glass: 6mm thick coated bronze tinted float glass, fully
tempered by manufacturer's standard process (after cutting to final
size), to achieve a flexural strength of 4 times normal glass
strength, glazed with the coating on the Number 2 surface as
viewed from the exterior, and with 25mm bonded "Black" fiberglass
insulation.
Glass Type “12”:
Insulating glass, 30mm overall thickness, double glass with 10mm
air space; exterior light 6mm thick tinted coated tempered float
glass; interior laminated clear float glass, 66.2, glazed with the
coating on the Number 2 surface as viewed from the exterior with a
visible light transmittance of 76 percent, Reflectance of 42 percent,
and a shading coefficient of 0.58.
Glass Type “13”:
Insulating glass, 30mm overall thickness, double glass with 8mm
air space; exterior light 8mm thick tinted coated tempered float
glass; interior laminated clear float glass, 66.2, glazed with the
coating on the Number 2 surface as viewed from the exterior with a
visible light transmittance of 76 percent, Reflectance of 42 percent,
and a shading coefficient of 0.58.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
157
Glass Type “14”:
Insulating glass, 28mm overall thickness, double glass with 10mm
air space; exterior light 8mm thick tinted coated tempered float
glass; interior laminated clear float glass, 55.2, glazed with the
coating on the Number 2 surface as viewed from the exterior with a
visible light transmittance of 76 percent, Reflectance of 42 percent,
and a shading coefficient of 0.58.
Glass Type “15”:
Insulating glass, 26mm overall thickness, double glass with 10mm
air space; exterior light 8mm thick tinted coated tempered float
glass; interior laminated clear float glass, 44.2, glazed with the
coating on the Number 2 surface as viewed from the exterior with a
visible light transmittance of 76 percent, Reflectance of 42 percent,
and a shading coefficient of 0.58.
Glass Type “16”:
Insulating glass, 38mm overall thickness, double glass with 12mm
air space; exterior light 12mm thick tempered float glass; interior
laminated clear float glass, 6 + 1.5 PVB + 6mm thick, with a visible
light transmittance of 71 percent, Reflectance (external light) of 11
percent, and a shading coefficient of 0.49.
Bullet Resistant Glass:
Laminated, clear float glass, Type I, Class 1, Quality q3, minimum
of 30 mm thickness, conforming to UL Test No. 752, Fifth Edition,
"Standard for Bullet Resisting Equipment" for resistance to medium
power small arms. Appearance and performance data equivalent to
Globe Amerada Glass Company "BR 136" bullet resisting glass.
2.03 CERAMIC COATED SPANDREL GLASS PRODUCTS
(WHEN APPLICABLE)
Ceramic Coated Spandrel Glass: ASTM C1048, Condition B
(spandrel glass, one surface ceramic coated), Type I
(transparent glass, flat), Class 1 (clear), Quality q3 (glazing
select), and complying with requirements specified.
Fallout Resistance: Provide spandrel units identical to those
passing fallout resistant test for spandrel glass specified in
ASTM C1048.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
158
2.04 GLAZING GASKETS
A. Lock Strip Gaskets: Neoprene extrusions in size and shape
indicated, fabricated into frames with molded corner units
and zipper lock strips, complying with ASTM C542, black.
B. Dense Compression Gaskets: Molded or extruded gaskets
of material indicated below, complying with standards
referenced with name of elastomer indicated below, and of
profile and hardness required to maintain watertight seal:
1. Neoprene, ASTM C864.
2. EPDM, ASTM C864.
3. Silicone, ASTM C1115.
4. Thermoplastic polyolefin rubber, ASTM C1115.
5. Any material indicated above.
C. Soft Compression Gaskets: Extruded or molded closed cell,
integral skinned gaskets of material indicated below,
complying with ASTM C A509, Type II, black, and of
profile and hardness required to maintain watertight seal:
1. Neoprene.
2. EPDM.
3. Silicone.
4. Thermoplastic polyolefin rubber.
5. Any material indicated above.
2.05 MISCELLANEOUS GLAZING MATERIALS
Provide products of material, size, and shape complying with
referenced glazing standard, requirements of manufacturers of
glass and other glazing materials involved for glazing
application indicated, and with a proven record of compatibility
with surfaces contacted in installation.
Cleaners, Primers and Sealers: Type recommended by
sealant or gasket manufacturer.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
159
Setting Blocks: Elastomeric material with a Shore A Durometer
hardness of 85 plus or minus 5.
Spacers: Elastomeric blocks or continuous extrusions with a
Shore A Durometer hardness required by glass manufacturer
to maintain glass lites in place for installation indicated.
Edge Blocks: Elastomeric material of hardness needed to limit
glass lateral movement (side walking).
2.06 FABRICATION OF GLASS AND OTHER GLAZING
PRODUCTS
Fabricate glass and other glazing products in sizes required to
glaze openings indicated for Project, with edge and face
clearances, edge and surface conditions, and bite complying
with recommendations of product manufacturer and
referenced glazing standard as required to comply with system
performance requirements.
2.07 DIMENSIONS AND GLASS TYPE FOR DOUBLE
GLAZING
Glass area below 3.5m2 (with maximum dimensions of 2.44 x
1.45m) – Exterior glass tempered 6mm thick;
Glass area from 4.5m2 to 6m
2 – Interior glass laminated 66.2;
Glass area from 2m2 to 4.5m
2 – Interior glass laminated 55.2;
Glass area less than 2m2 – Interior glass laminated 44.2;
PART 3 - EXECUTION
3.01 PREPARATION
A. Examine glass framing, with glazier present, for compliance
with the following:
1. Manufacturing and installation tolerances, including
those for size, squareness, offsets at corners.
2. Presence and functioning of weep system.
3. Minimum required face or edge clearances.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
160
4. Effective sealing between joints of glass framing
members.
B. Do not proceed with glazing until unsatisfactory conditions
have been corrected.
C. Clean glazing channels and other framing members
receiving glass immediately before glazing. Remove
coatings that are not firmly bonded to substrates.
3.02 INSTALLATION
A. Installation shall meet or exceed all applicable federal, state
and local requirements, referenced standards and conform
to codes and ordinances of authorities having jurisdiction.
B. All installation shall be in accordance with manufacturer’s
published recommendations.
C. Glazing – General:
1. Comply with combined recommendations of
manufacturers of glass, sealants, gaskets, and other
glazing materials, except where more stringent
requirements are indicated, including those in
referenced glazing publications.
2. Glazing channel dimensions as indicated on Drawings
provide necessary bite on glass, minimum edge and
face clearances, and adequate sealant thicknesses,
with reasonable tolerances. Adjust as required by
Project conditions during installation.
3. Protect glass from edge damage during handling and
installation as follows:
a. Use a rolling block in rotating glass units to prevent
damage to glass corners. Do not impact glass with
metal framing. Use suction cups to shift glass units
within openings; do not raise or drift glass with a
pry bar. Rotate glass lites with flares or bevels on
bottom horizontal edges so edges are located at
top of opening, unless otherwise indicated by
manufacturer's label.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
161
b. Remove damaged glass from Project Site and
legally dispose of off Site. Damaged glass is
glass with edge damage or other imperfections
that, when installed, weaken glass and impair
performance and appearance.
4. Apply primers to joint surfaces where required for
adhesion of sealants, as determined by preconstruction
sealant substrate testing.
5. Install elastomeric setting blocks in sill rabbets, sized
and located to comply with referenced glazing standard,
unless otherwise required by glass manufacturer. Set
blocks in thin course of compatible sealant suitable for
heel bead.
6. Do not exceed edge pressures stipulated by glass
manufacturers for installing glass lites.
7. Provide spacers for glass sizes larger than 50 united
inches (length plus height) as follows:
a. Locate spacers inside, outside, and directly
opposite each other. Install correct size and
spacing to preserve required face clearances,
except where gaskets and glazing tapes are used
that have demonstrated ability to maintain required
face clearances and comply with system
performance requirements.
b. Provide 1/8 inch minimum bite of spacers on glass
and use thickness equal to sealant width. With
glazing tape, use thickness slightly less than final
compressed thickness of tape.
8. Provide edge blocking to comply with requirements of
referenced glazing publications, unless otherwise
required by glass manufacturer.
9. Set glass lites in each series with uniform pattern, draw,
bow, and similar characteristics.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
162
D. Tape Glazing:
1. Position tapes on fixed stops so that when compressed
by glass their exposed edges are flush with or protrude
slightly above sightline of stops.
2. Install tapes continuously but not in one continuous
length. Do not stretch tapes to make them fit opening.
3. Where framing joints are vertical, cover these joints by
applying tapes to heads and sills first and then to jambs.
Where framing joints are horizontal, cover these joints
by applying tapes to jambs and then to heads and sills.
4. Place joints in tapes at corners of opening with
adjoining lengths butted together, not lapped. Seal
joints in tapes with compatible sealant approved by
tape manufacturer.
5. Do not remove release paper from tape until just before
each lite is installed.
E. Gasket Glazing (Dry):
1. Fabricate compression gaskets in lengths
recommended by gasket manufacturer to fit openings
exactly, with stretch allowance during installation.
2. Secure compression gaskets in place with joints
located at corners to compress gaskets producing a
weathertight seal without developing bending stresses
in glass. Seal gasket joints with sealant recommended
by gasket manufacturer.
3. Install gaskets so they protrude past face of glazing
stops.
F. Sealant Glazing (Wet):
1. Install continuous spacers between glass lites and
glazing stops to maintain glass face clearances and to
prevent sealant from extruding into glass channel weep
systems until sealants cure. Secure spacers in place
and in position to control depth of installed sealant
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
163
relative to edge clearance for optimum sealant
performance.
2. Force sealants into glazing channels to eliminate voids
and to ensure complete wetting or bond of sealant to
glass and channel surfaces.
3. Tool exposed surfaces of sealants to provide a
substantial wash away from glass. Install pressurized
gaskets to protrude slightly out of channel to eliminate
dirt and moisture pockets.
G. Lock Strip Gasket Glazing:
1. Comply with ASTM C 716 and gasket manufacturer's
printed recommendations. Provide supplementary wet
seal and weep system unless otherwise indicated.
H. Mirror Glazing:
1. Install mirrors to comply with printed directions of mirror
manufacturer, and with referenced FGMA standard and
NAMM document. Mount mirrors in place to avoid
distorting reflected images and provide space for air
circulation between back of mirror and face of mounting
surface.
2. Mastic Spot Installation System: Install mirrors with
mastic as follows:
a. Identify and examine surfaces over which mirror is
to be mounted. Comply with manufacturer's printed
installation directions for preparation of mounting
surfaces including coating surfaces with mastic
manufacturer's special bond coating where
applicable.
b. Apply barrier coat to mirror backing where
approved by manufacturers of mirror and backing
material.
c. Apply mastic in spots to comply with mastic
manufacturer's printed directions for coverage and
to allow air circulation between back of mirror and
face of mounting surface.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
164
d. After mastic is applied, align mirror and press into
place while maintaining a minimum air space of
3/16 inch between back of mirror and mounting
surface.
e. For wall mounted mirrors install permanent means
of support at bottom and top edges with bottom
support designed to withstand mirror weight and
top support to prevent mirror from coming away
from wall along top edges.
3.03 PROTECTION AND CLEANING
Protect exterior glass from breakage immediately after
installation by attaching crossed streamers to framing held
away from glass. Do not apply markers to glass surface.
Remove nonpermanent labels, and clean surfaces.
Protect glass from contact with contaminating substances
resulting from construction operations including weld splatter.
If, despite such protection, contaminating substances do come
into contact with glass, remove them immediately as
recommended by glass manufacturer.
Examine glass surfaces adjacent to or below exterior concrete
and other masonry surfaces at frequent intervals during
construction, but not less than once a month, for build-up of
dirt, scum, alkali deposits, or stains, and remove as
recommended by glass manufacturer.
Remove and replace glass that is broken, chipped, cracked,
abraded, or damaged in any way, including natural causes,
accidents and vandalism, during construction period.
Wash glass on both faces in each area of Project not more
than four (4) days prior to date scheduled for inspections that
establish date of Substantial Completion. Wash glass as
recommended by glass manufacturer.
END OF SECTION - GLASS AND GLAZING
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
165
3.1.9 WOOD, PLYWOOD, BLOCKBOARDS, LAMINATE &
COMPOSITE SURFACES
PART 1 - GENERAL
1.01 RELATED DOCUMENTS
Drawings and general provisions of the Contract, including
“General Requirements” Specifications Sections, apply to this
Section.
Specifications throughout all Divisions of the technical
Specifications are directly applicable to this Section, and this
section is directly applicable to them.
1.02 SECTION INCLUDES
Wood, plywood and blockboards for various applications
Wood veneers for various applications
Wood strip grilles
Plastic high-pressure laminate sheeting
Compact grade laminate panels
Solid core acrylic composite surfaces
PART 2 - PRODUCTS
2.01 WOOD, PLYWOOD, BLOCKBOARDS
A. All wood products shall be certified by FSC (Forest
Stewardship Council), which promote the responsible
management of the world's forests, protecting the
endangered trees species, or other certified
programs/organizations, which have the same purpose.
B. The Contractor shall only use plywood and block board
(and any other timber panel products) originating from
temperate or certified sources. Evidence of certification
shall be provided for review as required.
C. Plywood is to comply with B.S. 6566: “Plywood”. The
bonding adhesive for plywood shall be type “M.R.”
(Moisture resistant and moderately weather resistant) as
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
166
defined in B.S. 1203: “Specification for synthetic resin
adhesives for plywood.
D. Plywood for clear or natural finish shall be faced with
“Grade 1 veneer” and plywood for painted finish shall be
faced with “Grade 2 veneer”.
E. Block board to be B.S. 3444: “Specification for block board
and laminboard” with Grade 1 veneer or with Grade 2
veneer as appropriate for the specified finish and bonded
with type MR adhesive obtained from an approved
manufacturer.
2.02 WOOD VENEERS
A. All wood veneers, shall be certified by FSC (Forest
Stewardship Council) which promote the responsible
management of the world's forests, protecting the
endangered trees species, or other certified
programs/organizations, which have the same purpose.
B. Shall be in accordance with each selected product by the
Architect (please refer to the Architecture project “Drawings
materials list”, “Finishes Schedule” and Drawings, and the
tables below for complementary information).
2.03 WOOD STRIP GRILLES
A. All wood strip grilles shall be certified by FSC (Forest
Stewardship Council) which promote the responsible
management of the world's forests, protecting the
endangered trees species, or other certified
programs/organizations which have the same purpose.
B. Shall be in accordance with each selected product by the
Architect (please refer to the Architecture project “Drawings
materials list”, “Finishes Schedule” and Drawings, and the
tables below for complementary information).
2.04 PLASTIC HIGH PRESSURE LAMINATE SHEETING
A. Plastic high pressure laminate
B. Technical Data
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
167
Physical Properties of General Purpose Laminates (Physical
Properties tested in accordance to BS EN 438:1995)
Wear Resistance - 600
Boiling Water Resistance - 8.2 (mass) 8.4 (thickness)
Dry Heat Resistance – Rating 5
Dimensional Stability at Elevated Temperature - 0.19 (length)
0.74 (thickness)
Dimensional Stability at Ambient Temperature - 0.07 (length)
0.36 (thickness)
Impact Resistance - 2.8 newtons
Crack Resistance- Rating 5
Scratch Resistance – 4.0 newtons
Stain Resistance - (Reagent 1+2) 5; (Reagent 3+4) 5
Light Fastness – Wool standard 7
Cigarette Resistance – Rating 4
Steam Resistance - Rating 5
C. Surfacing material are resistant to scratch and impacts
under normal use conditions.
D. Shall be in accordance with each selected product by the
Architect (please refer to the Architecture project “Drawings
materials list”, “Finishes Schedule” and Drawings.
2.05 COMPACT GRADE LAMINATE PANELS
A. Compact grade laminate panels, shall be Formica, ref.
“Compact Grade Laminate”, or equivalent, manufactured
with a solid core built up from several layers of resin-
impregnated quality kraft papers. The decorative paper
impregnated with melamine resin shall be consolidated over
the quality kraft paper at high temperature and pressure to
form a homogeneous laminate, which thickness can be
available from 2.5mm up to 25mm. The result of this
manufacture system shall be a very strong, damage
resistant and structural stability laminate sheet.
B. This material shall be easy to clean, and therefore, ideal
also for wet and high humidity areas.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
168
C. It shall be manufactured in accordance with ISO 9001
criteria and meet or exceed the performance requirements
of NEMA (National Electrical Manufacturers Association)
Standards, LD3-1995 and European National Standards EN
438:1991 and International Standards ISO 4586 for high
pressure decorative laminates and Compact grade laminate.
It shall also fulfil the requirement of environmental
management system specified as ISO 14001:1996.
D. Shall be of sufficient size and adequate for the purpose for
which it is required.
E. The number of joints to be minimum, and where abutted,
their position to be prior agreed with the Employer’s
Representative. Adjacent sheets to match exactly.
F. The finished surface shall be clear and free from rust, oil,
and grease or adhesive.
G. All adhesives shall be applied strictly in accordance with the
manufacturer's instructions.
H. Product Technical Information
Compact Structural Laminate Grade: >2.0 to 25.0 mm thick,
two-sided decorative panel with black core; recommended
for horizontal and vertical interior application.
I. Physical Properties
PROPERTY TEST
METHOD
SPECIFICATION
LIMIT
TYPICAL
VALUE
Density BS
2782/620A
1.35 1.4 g/cm3
Wear
resistance
EN 438-2/10 350 minimum 500
revolutions
Boiling water
resistance
EN 438-2/12 2.0 maximum
2.0 maximum
0.39%mass
1.99%
thickness
Dry heat
resistance
EN 438-2/16 4 minimum Rating 5
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
169
Dimensional
stability at
elevated
temperature
EN 438-2/17 0.23 maximum
0.54 maximum
Machine
direction
0.18%
Cross-
machine
direction
0.15%
Dimensional
stability at
ambient
temperature
EN 438-2/18 0.16 maximum
0.22 maximum
Machine
direction
0.11%
Cross-
machine
direction
0.11%
Impact
resistance
EN 438-2/21 >180 > 350 cm
Scratch
resistance
EN 438-2/25 2
4
Rating 3
Stain
resistance
EN 438-2/26 5 minimum
4 minimum
(Reagents
1+2) 5
(Reagents
3+4) 5
Lightfastness EN 438-2/27 4 to 5 4 to 5
Cigarette
resistance
EN 438-2/30 3 minimum Rating 5
Steam
resistance
EN 438-2/14 4 minimum Rating 5
Crazing
resistance
EN 438-2/24 4 minimum Rating 5
Flexural
modulus
EN ISO 178 9000 minimum 11000 MPa
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
170
Flexural
strength
EN ISO 178 80 minimum 159 MPa
Tensile
strength
EN ISO 527-
2
60 minimum 44 MPa
J. The GREENGUARD Certification Program SM is an
industry-independent, third party testing program for low
emitting interior building materials, furnishings, and finish
systems. All GREENGUARD Certified Products have been
tested for their chemical emissions performance. In 2005,
GEI announced the GREENGUARD Children & Schools
SM standard, which evaluates the sensitive nature of school
populations combined with the unique building
characteristics found in schools, and presents the most
rigorous product emissions criteria to date. To date, more
than 170 manufacturers across various industries offer
GREENGUARD Indoor Air Quality Certified® Products.
These laminates shall be GREENGUARD Indoor Air Quality
Certified® by the GREENGUARD.
K. Shall be in accordance with each selected product by the
Architect (please refer to the Architecture project “Drawings
materials list”, “Finishes Schedule” and Drawings).
2.06 SOLID CORE
A. The Contractor shall use a proprietary stain, heat-and
chemical-resistant solid core acrylic composite product as
described. All sheeting to be of sufficient size and adequate
for the purpose for which it is required and the number of
joints to be minimum, and where abutted, the joints to be
polished to hide the joint-line. Adjacent sheets to match
exactly. The finished surface shall be clear and free from
rust, oil, and grease or adhesive. All adhesives shall be
applied strictly in accordance with the manufacturer's
instructions.
B. All solid core acrylic composite material shall be warranted
for a minimum of 8 years and any defect or deterioration
found within the warranty period shall be made good or the
sheeting fully replaced at the expense of the Contractor.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
171
C. Shall be in accordance with each selected product by the
Architect (please refer to the Architecture project “Drawings
materials list”, “Finishes Schedule” and Drawings).
PART 3 - EXECUTION
3.01 EXAMINATION
Verify site conditions are ready to receive work and framing
and opening dimensions are as indicated on the Drawings.
If preparation is the responsibility of another installer, notify
Architect of unsatisfactory preparation before proceeding.
3.02 PREPARATION
Clean surfaces thoroughly prior to installation.
Prepare surfaces using the methods recommended by the
manufacturer for achieving the best result for the substrate
under the project conditions.
3.03 WORKMANSHIP
Protection measures shall be taken to void any damage to
works / materials other than those included in this contract.
All materials required for execution of the works shall be
protected from damage and shall be delivered in their original
unopened packages. Damaged or deteriorated materials shall
be removed from the premises.
3.04 PROTECTION
Protect work from damage and deterioration until date of
Substantial Completion.
Touch-up, repair or replace damaged products before
Substantial Completion.
END OF SECTION - WOOD, PLYWOOD, BLOCKBOARDS,
LAMINATE & COMPOSITE SURFACES
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
172
3.1.10 WATER RESISTANT GYPSUM BOARD PANELS -
DRYWALLS
PART 1 - GENERAL
1.01 RELATED DOCUMENTS
Drawings and general provisions of the Contract, including
“General Requirements” Specifications Sections, apply to this
Section.
Specifications throughout all Divisions of the technical
Specifications are directly applicable to this Section, and this
section is directly applicable to them.
1.02 SECTION INCLUDES
Gypsum board and joint treatment products.
Water resistant gypsum board and joint treatment products.
Mold and Mildew resistant gypsum board products.
Gypsum shaft liner.
Abuse resistant gypsum board.
Mold resistant gypsum board.
Sound dampening area separation walls.
Gypsum soffit board.
Gypsum sheathing board.
Accessories for the installation and trimming of gypsum board
partitions.
1.03 SCOPE
Supply and installation of metal framework (metal framing
channels, studs etc.) for the fixing of gypsum board panels
with 50mm infill of sound attenuation fire blankets in between
the panels as specified
Supply and installation of additional supporting element inside
the dry wall system for affixing of equipment where required.
1.04 STANDARDS
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
173
ASTM C 36 - Standard Specification for Gypsum Wallboard.
ASTM C 79 - Standard Specification for Gypsum Sheathing
Board.
ASTM C 442 - Standard Specification for Gypsum Backing
Board, Gypsum Coreboard and Gypsum Shaftliner Board.
ASTM C 475 - Standard Specification for Joint Compound and
Joint Tape for Finishing Gypsum Board.
ASTM C 514 - Standard Specification for Nails for the
Application of Gypsum Board.
ASTM C 588 - Specification for Gypsum Base for Veneer
Plasters.
ASTM C 630 - Standard Specification for Water-Resistant
Gypsum Backing Board.
ASTM C 665 - Standard Specification for Mineral-Fiber
Blanket Thermal Insulation for Light Frame Construction and
Manufactured Housing.
ASTM C 754 - Standard Specification for Installation of Steel
Framing Members to Receive Screw-Attached Gypsum Panel
Products.
ASTM C 840 - Standard Specification for Application and
Finishing of Gypsum Board
ASTM C 931 - Standard Specification for Exterior Gypsum
Soffit Board.
ASTM C 954 - Standard Specification for Steel Drill Screws for
the Application of Gypsum Panel Products or Metal Plaster
Bases to Steel Studs From 0.033 in. (0.84 mm) to 0.112 in.
(2.84 mm) in Thickness.
ASTM C 1002 - Standard Specification for Steel Self-Piercing
Tapping Screws for the Application of Gypsum Panel Products
or Metal Plaster Bases to Wood Studs or Steel Studs.
ASTM C 1047 - Standard Specification for Accessories for
Gypsum Wallboard and Gypsum Veneer Base.
ASTM C 1280 - Standard Specification for Application of
Gypsum Sheathing.
ASTM C 1395 - Specification for Gypsum Ceiling Board.
ASTM C 1396 - Standard Specification for Gypsum Board.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
174
ASTM D 3273 - Standard Test Method for Resistance to
Growth of Mold on the Surface of Interior Coatings in an
Environmental Chamber.
ASTM E 90 - Standard Test Method for Laboratory
Measurement of Airborne Sound Transmission Loss of
Building Partitions and Elements.
ASTM E 119 - Standard Test Methods for Fire Tests of
Building Construction and Materials.
ASTM E 413 - Classification for Rating Sound Insulation.
ASTM E 492 - Standard Test Method for Laboratory
Measurement of Impact Sound Transmission through Floor-
Ceiling Assemblies Using the Tapping Machine.
ASTM E 989 - Classification for Determination of Impact
Insulation Class (IIC).
CAN/ULC-S101 - Standard Methods of Fire Endurance Tests
of Building Construction and Materials.
GA-214 - Recommended Levels of Gypsum Board Finish;
Gypsum Association.
GA-216 - Application and Finishing of Gypsum Board; Gypsum
Association.
GA-231 - Assessing Water damage to Gypsum Board;
Gypsum Association.
GA-238 - Guidelines for the Prevention of Mold Growth on
Gypsum Board; Gypsum Association.
GA-253 - Recommended Specifications for the Application of
Gypsum Sheathing; Gypsum Association.
GA-600 - Fire Resistance Design Manual; Gypsum
Association.
GA-801 - Handling and Storage of Gypsum Panel Product;
Gypsum Association.
ITS (Dir) - Directory of Listed Products; Intertek Testing
Services; current edition.
UL 263 - Standard for Fire Tests of Building Construction and
Materials.
UL (FRD) - Fire Resistance Directory; Underwriters
Laboratories Inc.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
175
ULC (FRD) - Fire Resistance Directory; Underwriters'
Laboratories of Canada.
Local Rules and Regulations; Current Editions.
1.05 PERFORMANCE REQUIREMENTS
A. Fire Rated Assemblies: Provide materials and construction
identical to those tested in fire-endurance rated assemblies
by an independent testing agency acceptable to the
authorities having jurisdiction.
B. Sound Rated Assemblies: Provide materials and
construction identical to those tested in STC/IIC-rated
assemblies by an independent testing agency.
1. Test Method: ASTM E 90/E 492 and classified
according to ASTM E 413/E 989.
2. STC Ratings: As indicated on the drawings;
designations listed are from Gypsum Association GA-
600, Fire Resistance Design Manual.
1.06 SUBMITTALS
A. Manufacturer's data sheets on each product to be used,
including:
1. Preparation instructions and recommendations.
2. Storage and handling requirements and
recommendations.
3. Installation methods.
B. Shop Drawings:
1. Indicate locations, fabrication details, reinforcement,
metal framing details, connection details, dimensions,
and relationship to adjacent materials.
2. Indicate special details associated with fireproofing,
acoustic seals, or curved sheet installations.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
176
C. LEED Submittals: Provide documentation of how the
requirements of Credit will be met:
1. Product Data for Credit MR 2.1 and 2.2: For products
being recycled, documentation of total weight of project
waste diverted from landfill.
2. Product Data for Credit MR 4.1 and MR 4.2: For
products having recycled content, documentation
including percentages by weight of post-consumer and
pre-consumer recycled content.
a. Include statement indicating costs for each product
having recycled content.
3. Product Data for Credit IEQ 4.1: For adhesives used to
laminate gypsum board panels to substrates, including
printed statement of VOC content.
4. Product Data for Credit IAQ 4.6 (Schools): For products
used in school construction, including certification
meeting CHPS Low-Emitting Material criteria Section
01350.
5. Product Data for Credit MR 5.1 and Credit MR 5.2:
Submit data, including location and distance from
Project of material manufacturer and point of extraction,
harvest or recovery for main raw material.
a. Include statement indicating cost for each regional
material and the fraction by weight that is considered
regional.
D. Maintenance Data: Manufacturer's recommendations for
cleaning each type of product specified.
E. Manufacturer's Certificates: Certify products meet or exceed
specified requirements.
1.07 QUALITY INSURANCE
A. Installer Qualifications: Installer: Company specializing in
performing Work of this section with minimum three years.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
177
B. Mock-Up: Provide a mock-up of the area indicated on the
Drawings for evaluation of surface preparation techniques
and application workmanship.
1. Locate finish areas designated by Architect.
2. Do not proceed with remaining work until workmanship
and finish is approved by Architect.
3. Refinish mock-up area as required to produce
acceptable work.
1.08 PROJECT CONDITIONS
Maintain environmental conditions (temperature, humidity, and
ventilation) within limits recommended by manufacturer for
optimum results. Do not install products under environmental
conditions outside manufacturer's absolute limits.
Do not install interior products until installation areas are
enclosed and conditioned.
Do not install panels that are wet, those that are moisture
damaged, and those that are mold damaged.
1.09 DELIVERY, STORAGE, AND HANDLING
Deliver and store gypsum board in accordance with GA-801.
Ship materials with a weather tight cover and in
manufacturer's original packages showing manufacturer's
name and product brand name.
Remove plastic shipping bags upon receipt and storage.
Failure to remove may increase the likelihood of mold growth.
Store materials inside and protected from damage by weather
and direct sunlight. Stack flat; protect ends, edges, and faces
of gypsum boards from damage. Protect steel studs and metal
accessories from moisture.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
178
PART 2 - PRODUCTS
2.01 GYPSUM PRODUCTS, GENERAL
Size: Provide maximum lengths and widths available that will
minimize joints in each area that correspond with the support
system indicated.
Jobsite Waste Recycle: In compliance with LEED
requirements.
Recycled Content: Provide gypsum panel products with
recycled content such that post-consumer recycled content
plus one-half of pre-consumer recycled content constitutes a
minimum 50 percent by weight.
2.02 GYPSUM PANELS
Gypsum panels shall be light-weight, conform to BS 1230: Part
1: 1985 and of maximum length, tapered edges. Gypsum
boards are to be identified by grey face to decorative side and
shall conform to BS 476 Part 4 from an accredited laboratory
recognized by HOKLAS
2.03 METAL STUDS
Metal studs and channels to be non-load bearing lipped wall
studs rolled formed from 0.55mm coated steel, punch outs
25mm diameter @ 600mm centers provided for installation of
services. All partition stud and track proprietary system shall
be manufactured from materials that conform to the following
specification and standards.
2.04 PARTITION FRAMING
Drywall steel stud wall shall be installed as per the
manufacturer’s installation instructions.
The track sections shall be fixed to the primary structure as
per manufacturer’s instructions.
Fixing shall not be more than 100mm from either end.
Studs shall be placed at 400mm centers maximum.( for Max
drywall height of 4450mm).
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
179
Studs shall be placed at 300mm centers maximum.( for Max
drywall height of 4750mm).
Studs shall have as standard factory pre – punctured 25mm
diameter bell-mouthed service holes spaced at 600mm
centers up to 2400mm.
There shall be 2 strengthening groove running along each
other for the entire length of the stud.
The studs shall have Mountain Knurling along the fixing face of
each leg to enable screw point to be positively driven into the
steel .The Knurling also allows air to pass between the face of
the studs and building board, keeping the wall cavity dryer.
All areas that are suspending any weight shall have studs
boxed together (with acoustic studs, boxed with Floor track
sections) for the entire span of the partition and there shall be
a row of nogging equally spaced along wall height that acts as
an additional support.
In event of the absence of box studs sections, studs spacing
shall adequately be reduced from 610mm centers box studs to
305mm center single studs.
2.05 METAL SPECIFICATION
Steel Grade: G2Z275
Yield Strength: FY: 300 MPa (Minimum)
Coating Grade: Z275 - 275 g/m2 Zinc
Corrosion Test: ASTM B 117 - 85 Salt Spray Test
2.06 FIRE BLANKETS
Infill sound attenuation fire blankets to be semi-rigid spun
mineral fiber mat (min. 50mm thick x60kg/m3); cut neatly
between studs to ensure no gaps and/or crushing of the
insulation, use approved fixing methods and samples to be
submitted to the Employer for approval.
2.07 CAULKING AND JOINTS
Caulking and jointing materials to be Fire and acoustic sealant
/ jointing system.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
180
2.08 SYSTEMS AND NOMINAL THICKNESS
Systems and nominal thickness shall be in accordance to the
materials codes below (please refer to Drawings and Drawings
Materials List for complementary information):
2.09 PERFORMANCE
Fire Resistance - Not required.
Sound Isolation - Not required.
Test Certificate
The Contractor shall furnish the Employer upon request test
certification for published fire, sound and structural data
covering systems designed and constructed according to its
published specifications.
The Contractor will be required to submit a written guarantee
in an approved form against excessive wear, faulty
workmanship and material for five (5) years after Practical
Completion and also obtain a manufacturer’s warranty for 10
(10) years after Practical Completion for faulty material .
Allowable deflection – N/A
Allowable head deflection
+ 20mm: Bottom and Deflection Head track should be
fastened to structural elements 50mm in from each end of the
track and at max. 600mm centers with suitable masonry
fastened (e.g. Power actuated shot, nylon and anchor or
expanding anchor). Position studs vertically with open sides
facing the same direction, engaging the top and bottom track.
Studs to be cut 20mm short at top track to allow for slab
deflection.
PART 3 - EXECUTION
3.01 EXAMINATION
Verify site conditions are ready to receive work and framing
and opening dimensions are as indicated on the Drawings.
If preparation is the responsibility of another installer, notify
Architect of unsatisfactory preparation before proceeding.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
181
3.02 PREPARATION
Clean surfaces thoroughly prior to installation.
Prepare surfaces using the methods recommended by the
manufacturer for achieving the best result for the substrate
under the project conditions.
3.03 WORKMANSHIP
The whole dry wall system shall be installed in accordance
with the specifications of the manufacturer.
Protection measures shall be taken to void any damage to
works / materials other than those included in this contract.
All materials required for execution of the works shall be
protected from damage and shall be delivered in their original
unopened packages. Damaged or deteriorated materials shall
be removed from the premises.
Steel runners shall be fixed at floor and ceiling to structural
elements with suitable fasteners; all steel studs to be erected
vertically with maximum spacing of 610mm c/c.
Gypsum panels shall be applied with all edges positioned over
steel studs; maximum practical lengths to be used to minimize
end joints; joints to be staggered on opposite sides of partition.
3.04 INSTALLATION
A. Application: Apply and maintain conditions during
installation in accordance with GA-216 and GA-238 and as
follows:
Keep gypsum board dry throughout application.
Do not use gypsum board that has visible mold growth.
Apply gypsum board on walls with a minimum 1/4 inch
(6.4 mm) gap between the gypsum board and the floor.
Do not apply gypsum board over other building materials
where conditions exist that are favorable to mold growth.
Maintain a sound weather-tight building envelope including,
such elements as the roof, sealants, windows, etc.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
182
Immediate and appropriate remediation measures must be
taken as soon as water leaks or condensation sources are
identified.
Provide routine cleaning and maintenance operations to
prevent saturation of the gypsum board.
If gypsum board is damaged by water, assess the need for
replacement in accordance with GA-231.
B. Install accordance with GA 216 and the following:
Metal Framing: ASTM C 754.
Gypsum Sheathing Board: ASTM C 1280 and GA-253.
Fire Resistant Construction: GA 600.
Gypsum Board and Joint Treatment: ASTM C 840 and GA-
214.
Gypsum panel manufacturer's published recommendations.
3.05 FINISHING
A. Finishing: Tape, fill, sand and finish joints in accordance
with ASTM C 840 and GA-214.
B. Provide a level 4 Finish all in accordance to Level 4 as
stated in the Australian / New Zealand Standard AS/NZS
2589.1:1997, Gypsum Linings in Residential & light
Commercial construction – Application & finishing ;Part 1:
Gypsum Plasterboard, clause Finishing of gypsum
plasterboard.
Finishing of gypsum plasterboard
Flush Finishing; flush finishing shall be carried out as follows:
The abutting edges and ends of gypsum plasterboard,
fastener indentations, internal and external corners and minor
surface damage shall be treated with joint cement to give
surfaces suitable for decoration.
Both recessed and butt joints shall be reinforced with a
suitable reinforcing tape. Cements for tape application and
flush finishing may be a drying or setting type. When applied,
the cements shall be of compatible chemical composition with
the previous coat. The use of any additives to modify any of
the properties of cements or compounds shall not be permitted;
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
183
those additives may adversely affect the properties of the
cement or compound.
Drying type cements shall not be applied when the interior
temperature is less than 10 Degrees Celsius. Setting type
cements must be used with caution in hot & dry conditions as
the cement may dry out before setting has taken place.
Adequate ventilation shall be provided to ensure drying,
setting or curing of the cement.
Gypsum plasterboard shall be kept free of any dirt, oil or other
foreign matter, which could cause a lack of bonding. All dents
or gouges shall be filled to a smooth finish in the plane of the
surface of the board.
Taping and finishing shall be carried out using appropriate
hand tools such as board knives and trowels with true edges,
or mechanical tools designed for this work and the joint
treatment cement being used.
Tape shall be properly bedded into the joint cement and
excess cement shall be removed. Refer to the manufacturer
standards for joint details.
A second coat shall be applied with tools of sufficient width to
extend beyond the joint center as manufacturer’s stated
standard. The cement shall be smoothed down to an even
surface. After drying or setting, the treated surface shall be
sanded or scraped to eliminate any high spots or excessive
cement.
A third coat shall be applied with tools, which permit the
feathering of joint treatment edges. After drying, this final coat
shall be lightly sanded to leave a smooth even surface
covering the joint. Caution shall be taken during sanding not to
raise the nap of the linerboard. Fastener heads shall be
covered with successive coats each applied in different
direction.
Care shall be taken to ensure that all tools and containers are
kept clean and free from foreign materials and set plaster.
Only water suitable for drinking shall be used for mixing
powder compounds or for thinning premixed materials.
Cements shall not be allowed to freeze.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
184
Drying cements shall be allowed to dry thoroughly between
successive coats or before sanding. Setting type cements can
receive additional coats after the caulking.
Caulk all perimeter gaps with Fire Sealant.
3.06 SKIRTING
Screw fix skirting to bottom tracks or adhere to the
plasterboard as required.
3.07 INTERNAL CORNERS
Reinforce internal corners using Paper Tape 50mm width and
jointing compound. When thoroughly dry, lightly sand.
3.08 EXPANSION JOINTS
In long partition, install Joint (P/N P35) at maximum centers of
9.0m. Fixing and jointing as per ‘External corners’ application.
3.09 PROTECTION
Protect work from damage and deterioration until date of
Substantial Completion.
Touch-up, repair or replace damaged products before
Substantial Completion.
END OF SECTION - WATER RESISTANT GYPSUM BOARD
PANELS - DRYWALLS
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
185
3.1.11 WATER RESISTANT GYPSUM BOARD PANELS - CEILINGS
PART 1 - GENERAL
1.01 RELATED DOCUMENTS
Drawings and general provisions of the Contract, including
“General Requirements” Specifications Sections, apply to this
Section.
Specifications throughout all Divisions of the technical
Specifications are directly applicable to this Section, and this
section is directly applicable to them.
1.02 SECTION INCLUDES
Gypsum board and joint treatment products.
Water resistant gypsum board and joint treatment products.
Mold and Mildew resistant gypsum board products.
Gypsum shaft liner.
Abuse resistant gypsum board.
Mold resistant gypsum board.
Sound dampening area separation walls.
Gypsum soffit board.
Gypsum sheathing board.
Accessories for the installation and trimming of gypsum board
ceilings.
1.03 SCOPE
Suspended Ceiling which consist 12mm thick screw fixed onto
ceiling system (top cross rail @ 1200mm* ctrs max., furring
channel @ 600 mm* ctrs max., suspension clip and angle
bracket) suspended by 5mm hanger rods. Boards surface to
be flushed finished all fixed in accordance to manufacturer’s
instruction and recommendation.
1.04 STANDARDS
ASTM C 36 - Standard Specification for Gypsum Wallboard.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
186
ASTM C 79 - Standard Specification for Gypsum Sheathing
Board.
ASTM C 442 - Standard Specification for Gypsum Backing
Board, Gypsum Coreboard and Gypsum Shaftliner Board.
ASTM C 475 - Standard Specification for Joint Compound and
Joint Tape for Finishing Gypsum Board.
ASTM C 514 - Standard Specification for Nails for the
Application of Gypsum Board.
ASTM C 588 - Specification for Gypsum Base for Veneer
Plasters.
ASTM C 630 - Standard Specification for Water-Resistant
Gypsum Backing Board.
ASTM C 665 - Standard Specification for Mineral-Fiber
Blanket Thermal Insulation for Light Frame Construction and
Manufactured Housing.
ASTM C 754 - Standard Specification for Installation of Steel
Framing Members to Receive Screw-Attached Gypsum Panel
Products.
ASTM C 840 - Standard Specification for Application and
Finishing of Gypsum Board
ASTM C 931 - Standard Specification for Exterior Gypsum
Soffit Board.
ASTM C 954 - Standard Specification for Steel Drill Screws for
the Application of Gypsum Panel Products or Metal Plaster
Bases to Steel Studs From 0.033 in. (0.84 mm) to 0.112 in.
(2.84 mm) in Thickness.
ASTM C 1002 - Standard Specification for Steel Self-Piercing
Tapping Screws for the Application of Gypsum Panel Products
or Metal Plaster Bases to Wood Studs or Steel Studs.
ASTM C 1047 - Standard Specification for Accessories for
Gypsum Wallboard and Gypsum Veneer Base.
ASTM C 1280 - Standard Specification for Application of
Gypsum Sheathing.
ASTM C 1395 - Specification for Gypsum Ceiling Board.
ASTM C 1396 - Standard Specification for Gypsum Board.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
187
ASTM D 3273 - Standard Test Method for Resistance to
Growth of Mold on the Surface of Interior Coatings in an
Environmental Chamber.
ASTM E 90 - Standard Test Method for Laboratory
Measurement of Airborne Sound Transmission Loss of
Building Partitions and Elements.
ASTM E 119 - Standard Test Methods for Fire Tests of
Building Construction and Materials.
ASTM E 413 - Classification for Rating Sound Insulation.
ASTM E 492 - Standard Test Method for Laboratory
Measurement of Impact Sound Transmission through Floor-
Ceiling Assemblies Using the Tapping Machine.
ASTM E 989 - Classification for Determination of Impact
Insulation Class (IIC).
CAN/ULC-S101 - Standard Methods of Fire Endurance Tests
of Building Construction and Materials.
GA-214 - Recommended Levels of Gypsum Board Finish;
Gypsum Association.
GA-216 - Application and Finishing of Gypsum Board; Gypsum
Association.
GA-231 - Assessing Water damage to Gypsum Board;
Gypsum Association.
GA-238 - Guidelines for the Prevention of Mold Growth on
Gypsum Board; Gypsum Association.
GA-253 - Recommended Specifications for the Application of
Gypsum Sheathing; Gypsum Association.
GA-600 - Fire Resistance Design Manual; Gypsum
Association.
GA-801 - Handling and Storage of Gypsum Panel Product;
Gypsum Association.
ITS (Dir) - Directory of Listed Products; Intertek Testing
Services; current edition.
UL 263 - Standard for Fire Tests of Building Construction and
Materials.
UL (FRD) - Fire Resistance Directory; Underwriters
Laboratories Inc.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
188
ULC (FRD) - Fire Resistance Directory; Underwriters'
Laboratories of Canada.
Local Rules and Regulations; Current Editions.
1.05 PERFORMANCE REQUIREMENTS
A. Fire Rated Assemblies: Provide materials and construction
identical to those tested in fire-endurance rated assemblies
by an independent testing agency acceptable to the
authorities having jurisdiction.
B. Sound Rated Assemblies: Provide materials and
construction identical to those tested in STC/IIC-rated
assemblies by an independent testing agency.
1. Test Method: ASTM E 90/E 492 and classified
according to ASTM E 413/E 989.
2. STC Ratings: As indicated on the drawings;
designations listed are from Gypsum Association GA-
600, Fire Resistance Design Manual.
1.06 SUBMITTALS
A. Manufacturer's data sheets on each product to be used,
including:
1. Preparation instructions and recommendations.
2. Storage and handling requirements and
recommendations.
3. Installation methods.
B. Shop Drawings:
1. Indicate locations, fabrication details, reinforcement,
metal framing details, connection details, dimensions,
and relationship to adjacent materials.
2. Indicate special details associated with fireproofing,
acoustic seals, or curved sheet installations.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
189
C. LEED Submittals: Provide documentation of how the
requirements of Credit will be met:
1. Product Data for Credit MR 2.1 and 2.2: For products
being recycled, documentation of total weight of project
waste diverted from landfill.
2. Product Data for Credit MR 4.1 and MR 4.2: For
products having recycled content, documentation
including percentages by weight of post-consumer and
pre-consumer recycled content.
a. Include statement indicating costs for each product
having recycled content.
3. Product Data for Credit IEQ 4.1: For adhesives used to
laminate gypsum board panels to substrates, including
printed statement of VOC content.
4. Product Data for Credit IAQ 4.6 (Schools): For products
used in school construction, including certification
meeting CHPS Low-Emitting Material criteria Section
01350.
5. Product Data for Credit MR 5.1 and Credit MR 5.2:
Submit data, including location and distance from
Project of material manufacturer and point of extraction,
harvest or recovery for main raw material.
5.1. Include statement indicating cost for each
regional material and the fraction by weight
that is considered regional.
D. Maintenance Data: Manufacturer's recommendations for
cleaning each type of product specified.
E. Manufacturer's Certificates: Certify products meet or exceed
specified requirements.
1.07 QUALITY INSURANCE
A. Installer Qualifications: Installer: Company specializing in
performing Work of this section with minimum three years.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
190
B. Mock-Up: Provide a mock-up of the area indicated on the
Drawings for evaluation of surface preparation techniques
and application workmanship.
1. Locate finish areas designated by Architect.
2. Do not proceed with remaining work until workmanship
and finish is approved by Architect.
3. Refinish mock-up area as required to produce
acceptable work.
1.08 PROJECT CONDITIONS
Maintain environmental conditions (temperature, humidity, and
ventilation) within limits recommended by manufacturer for
optimum results. Do not install products under environmental
conditions outside manufacturer's absolute limits.
Do not install interior products until installation areas are
enclosed and conditioned.
Do not install panels that are wet, those that are moisture
damaged, and those that are mold damaged.
1.09 DELIVERY, STORAGE, AND HANDLING
Deliver and store gypsum board in accordance with GA-801.
Ship materials with a weathertight cover and in manufacturer's
original packages showing manufacturer's name and product
brand name.
Remove plastic shipping bags upon receipt and storage.
Failure to remove may increase the likelihood of mold growth.
Store materials inside and protected from damage by weather
and direct sunlight. Stack flat; protect ends, edges, and faces
of gypsum boards from damage. Protect steel studs and metal
accessories from moisture.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
191
PART 2 - PRODUCTS
2.01 GYPSUM PRODUCTS, GENERAL
Size: Provide maximum lengths and widths available that will
minimize joints in each area that correspond with the support
system indicated.
Jobsite Waste Recycle: In compliance with LEED
requirements.
Recycled Content: Provide gypsum panel products with
recycled content such that post-consumer recycled content
plus one-half of pre-consumer recycled content constitutes a
minimum 50 percent by weight.
2.02 GYPSUM PANELS AND SUSPENSION CEILING
FIXING SYSTEM
Suspended Concealed Ceiling, a lightweight, non- combustible,
economical system consisting of Wet Area 12mm thick screw
fixed to ceiling system and finished, providing a smooth and
continuous surface. The ceiling is suspended from concrete
soffit or roof structure, or may be fixed directly to the underside
of timber or steel framing members.
2.03 PLASTERBOARD
Wet Area 12mm thick
2.04 FRAMING
Top Cross Rail
Furring Channel
Joiner/ Locking clip
Suspension Bracket
Suspension Rod
Suspension Clip
Fastener: 25mm Type ‘S’ Needle Point Screws
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
192
2.05 FASTENER
25mm Type ‘S’ Needle Point Screws
2.06 JOINT TYPE
Paper Tape 50mm width
2.07 SYSTEMS AND NOMINAL SIZES
Systems and nominal sizes shall be in accordance to the
materials codes below (please refer to Drawings and Drawings
Materials List for complementary information):
2.08 PERFORMANCE
Mass - 13.6 kg/m2
Fire Resistance - Not required.
Acoustic Rating - Not required.
PART 3 - EXECUTION
3.01 EXAMINATION
Verify site conditions are ready to receive work and framing
and opening dimensions are as indicated on the Drawings.
If preparation is the responsibility of another installer, notify
Architect of unsatisfactory preparation before proceeding.
3.02 PREPARATION
Clean surfaces thoroughly prior to installation.
Prepare surfaces using the methods recommended by the
manufacturer for achieving the best result for the substrate
under the project conditions.
3.03 WORKMANSHIP
The whole dry wall system shall be installed in accordance
with the specifications of the manufacturer.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
193
Protection measures shall be taken to void any damage to
works / materials other than those included in this contract.
All materials required for execution of the works shall be
protected from damage and shall be delivered in their original
unopened packages. Damaged or deteriorated materials shall
be removed from the premises.
Steel runners shall be fixed at floor and ceiling to structural
elements with suitable fasteners; all steel studs to be erected
vertically with maximum spacing of 610mm c/c.
Gypsum panels shall be applied with all edges positioned over
steel studs; maximum practical lengths to be used to minimize
end joints; joints to be staggered on opposite sides of partition.
3.04 INSTALLATION
A. Application: Apply and maintain conditions during
installation in accordance with GA-216 and GA-238 and as
follows:
Keep gypsum board dry throughout application.
Do not use gypsum board that has visible mold growth.
Apply gypsum board on walls with a minimum 1/4 inch (6.4
mm) gap between the gypsum board and the floor.
Do not apply gypsum board over other building materials
where conditions exist that are favorable to mold growth.
Maintain a sound weather-tight building envelope including,
such elements as the roof, sealants, windows, etc.
Immediate and appropriate remediation measures must be
taken as soon as water leaks or condensation sources are
identified.
Provide routine cleaning and maintenance operations to
prevent saturation of the gypsum board.
If gypsum board is damaged by water, assess the need for
replacement in accordance with GA-231.
B. Install accordance with GA 216 and the following:
Metal Framing: ASTM C 754.
Gypsum Sheathing Board: ASTM C 1280 and GA-253.
Fire Resistant Construction: GA 600.
Gypsum Board and Joint Treatment: ASTM C 840 and GA-
214.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
194
Gypsum panel manufacturer's published recommendations.
3.05 FINISHING
A. Finishing: Tape, fill, sand and finish joints in accordance
with ASTM C 840 and GA-214.
B. Provide a level 4 Finish all in accordance to Level 4 as
stated in the Australian / New Zealand Standard AS/NZS
2589.1:1997, Gypsum Linings in Residential & light
Commercial construction – Application & finishing ;Part 1:
Gypsum Plasterboard, clause Finishing of gypsum
plasterboard.
Finishing of gypsum plasterboard
Flush Finishing; flush finishing shall be carried out as follows:
The abutting edges and ends of gypsum plasterboard,
fastener indentations, internal and external corners and minor
surface damage shall be treated with joint cement to give
surfaces suitable for decoration.
Both recessed and butt joints shall be reinforced with a
suitable reinforcing tape. Cements for tape application and
flush finishing may be a drying or setting type. When applied,
the cements shall be of compatible chemical composition with
the previous coat. The use of any additives to modify any of
the properties of cements or compounds shall not be permitted;
those additives may adversely affect the properties of the
cement or compound.
Drying type cements shall not be applied when the interior
temperature is less than 10 Degrees Celsius. Setting type
cements must be used with caution in hot & dry conditions as
the cement may dry out before setting has taken place.
Adequate ventilation shall be provided to ensure drying,
setting or curing of the cement.
Gypsum plasterboard shall be kept free of any dirt, oil or other
foreign matter, which could cause a lack of bonding. All dents
or gouges shall be filled to a smooth finish in the plane of the
surface of the board.
Taping and finishing shall be carried out using appropriate
hand tools such as board knives and trowels with true edges,
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
195
or mechanical tools designed for this work and the joint
treatment cement being used.
Tape shall be properly bedded into the joint cement and
excess cement shall be removed. Refer to the manufacturer
standards for joint details.
A second coat shall be applied with tools of sufficient width to
extend beyond the joint center as manufacturer’s stated
standard. The cement shall be smoothed down to an even
surface. After drying or setting, the treated surface shall be
sanded or scraped to eliminate any high spots or excessive
cement.
A third coat shall be applied with tools, which permit the
feathering of joint treatment edges. After drying, this final coat
shall be lightly sanded to leave a smooth even surface
covering the joint. Caution shall be taken during sanding not to
raise the nap of the linerboard. Fastener heads shall be
covered with successive coats each applied in different
direction.
Care shall be taken to ensure that all tools and containers are
kept clean and free from foreign materials and set plaster.
Only water suitable for drinking shall be used for mixing
powder compounds or for thinning premixed materials.
Cements shall not be allowed to freeze.
Drying cements shall be allowed to dry thoroughly between
successive coats or before sanding. Setting type cements can
receive additional coats after the material has set and before it
dries completely.
3.06 CAULKING
Caulk all perimeter gaps Fire Sealant.
3.07 EXPANSION JOINTS
In long partition, install Control Joint at maximum centers of
9.0m. Fixing and jointing as per ‘External corners’ application.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
196
3.08 PROTECTION
Protect work from damage and deterioration until date of
Substantial Completion.
Touch-up, repair or replace damaged products before
Substantial Completion.
3.09 SAFETY AND FIRST AID
Although there are no health hazards known in the normal use
and application of plasterboard, the following precautions
should be observed:
Avoid creating dust when handling plasterboard or mixing
plaster products.
Reduced sanding by passing a wet sponge over the edge of
the finished joints after trowelling.
If dry sanding is necessary and dust is created, provide
adequate ventilation, wear eye protection and a disposable
respiratory mask conforming to Australian/New Zealand
Standard AS/NZS 1716:1994 Respiratory Protective Devices
Keep all construction materials and tools out of reach of
children
If plaster compound or dust comes into contact with eyes -
wash eyes thoroughly with water
If plaster compound or dust comes into contact with skin -
wash skin thoroughly with soap and water
If plaster dust is inhaled - move to a fresh air environment
If plastering compound or dust is ingested - drink plenty of
water
END OF SECTION - WATER RESISTANT GYPSUM BOARD
PANELS - CEILINGS
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
197
3.1.12 CERAMIC TILES
PART 1 – GENERAL
1.01 RELATED DOCUMENTS
Drawings and general provisions of the Contract, including
“General Requirements” Specifications Sections, apply to this
Section.
Specifications throughout all Divisions of the technical
Specifications are directly applicable to this Section, and this
section is directly applicable to them.
1.02 REFERENCE STANDARDS
The latest published edition of a reference shall be applicable
to this Project unless identified by a specific edition date.
All reference amendments adopted prior to the effective date
of this Contract shall be applicable to this Project.
All materials, installation and workmanship shall comply with
all applicable requirements and standards.
1.03 QUALITY ASSURACE
Single Source Responsibility for Tile: Obtain each color, grade,
finish, type, composition, and variety of tile from a single
source with resources to provide products of consistent quality
in appearance and physical properties without delaying
progress of the Work.
Single Source Responsibility for Setting and Grouting
Materials: Obtain ingredients of a uniform quality from one
manufacturer for each cementitious and admixture component
and from one source or producer for each aggregate.
Installer Qualifications: Engage an experienced Installer who
has successfully completed tile installations similar in material,
design, and extent to that indicated for Project.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
198
1.04 SUBMITALS
Samples:
Submit samples for initial selection purposes of each tile type
and grout in form of manufacturer's color charts consisting of
actual units or sections of units showing full range of colors,
textures, and patterns available for each type of finish
indicated.
Where finish involves normal color and texture variations,
include sample sets composed of two or more units showing
full range of variations expected.
Include similar samples of material for joints and accessories
involving color selection.
Submit samples for verification purposes of each type, class,
and color/ pattern of tile required, not less than 18 inches
square on plywood or hardboard backing, and grouted as
required. Architect's review will be for color, pattern and
texture only.
Compliance with all other requirements is the exclusive
responsibility of the Contractor. Prepare and submit new
samples, if requested, until appearance is acceptable to the
Architect.
Product Data:
Submit manufacturer's product data and
installation/maintenance instructions for all manufactured
products and materials.
Shop Drawings:
Submit plans of all areas to receive tile Work showing location
of expansion and control joints, layout of tile units, and other
conditions affecting the Work.
Include details showing setting methods, expansion joint
constructions, and relationships to adjacent substrates.
Locate precisely each joint and crack in tile substrates by
measuring, record measurements on shop Drawings, and
coordinate them with tile joint locations, in consultation with
Architect.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
199
Provide manufacturer's Master Grade Certificate bearing TCA
Certification mark and stating type, grade and location of
material for all tile specified to be "Standard Grade".
Record Documents:
Provide record approved shop drawings, samples, and
warranties.
1.05 MOCK-UP INSTALATION
Prior to beginning tile installation, arrange for a meeting, on-
site, with the Architect to review proposed tile layout in each
area scheduled to receive tile.
Arrange for a "mock-up" installation of tile at certain areas as
directed to establish acceptable appearance standards.
In general, mock-up areas will be limited to approximately 40
square feet each and will be located at intersections of floor
and wall, at corners of rooms.
1.06 DELIVERY, STORAGE, AND HANDLING
Deliver and store packaged materials in original containers
with seals unbroken and labels intact until time of use. Comply
with requirement of ANSI A137.1 for labeling sealed tile
packages.
Prevent damage or contamination to materials by water,
freezing, foreign matter, and other causes.
Handle tile with temporary protective coating on exposed
surfaces to prevent coated surfaces from contacting backs or
edges of other units. If, despite these precautions, coating
does contact bonding surfaces of tile, remove coating from
bonding surfaces before setting tile.
1.07 PROJECT CONDITIONS
Maintain environmental conditions and protect Work during
and after installation to comply with referenced standards and
manufacturer's printed recommendations.
Vent temporary heaters to exterior to prevent damage to tile
Work from carbon dioxide buildup.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
200
Maintain temperatures at 50 degrees F (10 degrees C) or
more in tiled areas during installation and for seven (7) days
after completion, unless higher temperatures are required by
referenced installation standard or manufacturer's instructions.
1.08 EXTRA MATERIALS
Deliver extra materials to Owner. Furnish extra materials that
match products installed as described below, packaged with
protective covering for storage and identified with labels clearly
describing contents.
Tile and Trim Units: Furnish quantity of full size units equal to
3 percent of amount installed, for each type, composition, color,
pattern, and size.
PART 2 - PRODUCTS
2.01 GENERAL
All materials shall meet or exceed all applicable referenced
standards, federal, state and local requirements, and conform
to codes and ordinances of authorities having jurisdiction.
2.02 MANUFACTURERS
The notes and schedules on the Drawings establish
manufacturer and model/design of tile products required for
the Project. Provide the products listed unless Architect
approves products of other manufacturer specifically for this
Project.
2.03 PRODUCTS, GENERAL
ANSI Standard for Ceramic Tile: Comply with ANSI A137.1
"American National Standard Specifications for Ceramic Tile"
for types, compositions, and grades of tile indicated.
Furnish tile complying with "Standard Grade" requirements
unless otherwise indicated.
ANSI Standard for Tile Installation Materials: Comply with
ANSI standard referenced with products and materials
indicated for setting and grouting.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
201
A. Colors, Textures, and Patterns: Where manufacturer's
standard products are indicated for tile, grout, and other
products requiring selection of colors, surface textures,
patterns, and other appearance characteristics, provide
specific products or materials complying with the
following requirements:
Match Architect's sample.
Match color, texture, and pattern indicated by reference to
manufacturer's standard designations for these
characteristics.
Provide selections made by Architect from manufacturer's
full range of standard colors, textures, and patterns for
products of type indicated.
Factory Blending: For tile exhibiting color variations within
the ranges selected during sample submittals, blend tile in
factory and package accordingly so that tile units taken
from one package show the same range in colors as those
taken from other packages and match approved samples.
Mounting: Where factory mounted tile is required, provide
back or edge mounted tile assemblies as standard with
manufacturer unless another mounting method is indicated.
For glazed wall tile, provide "Standard Grade" units,
complying with ANSI A137.1. Provide units, trim and
special shapes as indicated and required.
Accessories for Glazed Wall Tile: Provide vitreous china
accessories of type and size indicated and in color and
finish to match adjoining glazed wall tile.
2.04 MORTAR SETTING BED MATERIALS
Provide Portland cement mortar as specified in the ANSI A
108 Series, Materials, and Installation Specifications with a
Portland Cement mortar/sand mix in 1:6 proportion.
For "Thin Set/Dry Set" mortar bed setting, provide factory
sanded Portland Cement mix with manufacturer's standard
acrylic latex additive conforming to ANSI A 118.4.
For wall applications, provide mortar that complies with
requirements for non-sagging mortar in addition to the other
requirements in ANSI A118.4.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
202
2.05 ADHESIVE SETTING MATERIALS
For wall tile adhesive, provide factory mixed organic adhesive
complying with ANSI A136.1, Type I, with manufacturer's
certification of conformance.
2.06 JOINT GROUT
For mosaic tile and glazed tile grout, provide manufactured
joint grout conforming to ANSI A118.6.
For epoxy grout, provide two-component epoxy grout
conforming to ANSI 118.3.
2.07 MIXING MORTARS AND GROUT
Mix mortars and grouts to comply with requirements of
referenced standards and manufacturers including those for
accurate proportioning of materials, water, or additive content;
type of mixing equipment, selection of mixer speeds, mixing
containers, mixing time, and other procedures needed to
produce mortars and grouts of uniform quality with optimum
performance characteristics for application indicated.
PART 3 - EXECUTION
3.01 PREPARATION
Examine substrates and areas where tile will be installed, with
Installer present, for compliance with requirements for
installation tolerances and other conditions affecting
performance of installed tile.
Verify that substrates for setting tile are firm, dry, clean, and
free from oil or waxy films and curing compounds.
Verify that installation of grounds, anchors, recessed frames,
electrical and mechanical units of Work, and similar items
located in or behind tile has been completed before installing
tile.
Do not proceed with installation until unsatisfactory conditions
have been corrected.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
203
Blending: For tile exhibiting color variations within the ranges
selected during sample submittals, verify that tile has been
blended in factory and packaged accordingly so that tile units
taken from one package show the same range in colors as
those taken from other packages and match approved
samples. If not factory blended, either returns to manufacturer
or blend tiles at the Project Site before installing.
3.02 INSTALLATION
Installation shall meet or exceed all applicable local
requirements, referenced standards and conform to codes and
ordinances of authorities having jurisdiction.
All installation shall be in accordance with manufacturer’s
published recommendations.
Before starting the installation operations of any surface, we
recommend you make sure that the ceramic batch is adequate
and sufficient in terms of quantity, tone and calibration. If in
case of large environments joints must be positioned at regular
intervals, in small environments a small gap between the tiles
and perimeter walls is sufficient: the skirting board will cover
the gap and provide the finishing effect. Avoid walking on the
floor for at least 2/3 days after the installation. If walking on the
floor is necessary, lay wooden planks on the surface. Please
notice that if the tiles are installed with the traditional
procedure and no additives are added to the mortar, at least
one month has to elapse before the floor can be subjected to
stress and operating loads.
Extend tile Work into recesses and under or behind equipment
and fixtures to form a complete covering without interruptions
except as otherwise shown. Terminate Work neatly at
obstructions, edges, and corners without disrupting pattern or
joint alignments.
Accurately form intersections and returns. Perform cutting and
drilling of tile without marring visible surfaces. Carefully grind
cut edges of tile abutting trim, finish, or built in items for
straight aligned joints. Fit tile closely to electrical outlets, piping,
fixtures, and other penetrations so that plates, collars, or
covers overlap tile. Carefully lay out tile in an endeavor to
center the tiles to space them evenly, and to avoid cutting
them. If cutting is necessary, cutting shall be done by saw cut
or drilling only, no tile cutters or snipped edges allowed; all cut
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
204
ends shall be rubbed smooth and even. Unless otherwise
shown, lay out tile so that no tile less than 1/2 size occurs. For
height stated in feet and inches, maintain full courses to
produce nearest attainable heights without cutting tile. Align
joints in wall tile vertically and horizontally. No staggering of
joints will be permitted. All cutting and drilling shall be done
without marring surfaces and shall be done neatly to fit closely
around pipes, fixtures, and fittings so that cover plates will
overlap cuts.
Unless otherwise shown, lay tile in grid pattern. Align joints
when adjoining tiles on floor, base, walls, and trim are same
size. Lay out tile Work and center tile fields in both directions
in each space or on each wall area. Adjust to minimize tile
cutting. Provide uniform joint widths unless otherwise shown.
Confirm locations of joints in substrate will align with planned
expansion joints in tile Work. Adjust layout of tile if necessary
to align expansion joints with substrate conditions.
Expansion Joints: Locate expansion joints and other sealant
filled joints, including control, Contraction, and isolation joints,
where indicated during installation of setting materials, mortar
beds, and tile. Do not saw cut joints after installation of tiles.
Locate joints in tile surfaces directly above joints in concrete
substrates.
Grout tile to comply with the requirements of the following
installation standards:
3.03 GROUT
Wall Joints (less than 1/8 inches wide): Unsanded Grout.
Floor and Wall Joints (1/8 inch to 5/8 inch wide): Sanded Grout.
Floor Joints in Showers, and all Quarry Tile Joints (1/16 inch to
3/8 inch wide): Epoxy Grout.
3.04 EXPANSION JOINT INSTALLATION
At all floor tile installations, provide expansion joints at
perimeter of area to be tiled, at all penetrations in tile Work,
and 12 feet 0 inches on center both ways as recommended in
the TCA "Handbook for Ceramic Tile Installation" unless closer
spacing is indicated or required by Project conditions. Install
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
205
removable strips of the same depth as the finished tile system
including setting bed. Remove strips after grouting and curing
operations.
Install joints in accordance with TCA Method EJ711.
3.05 CLEANING AND PROTECTION
Initial Cleaning:
It is normally performed once before using the floor and it is
obligatorily after the installation. Its purpose is to eliminate any
trace of lime, cement or resin residues contained in the grouts
used for the joints. During this phase all the typologies
products must be washed using a solution of hydrochloric acid
(2/3 water, 1/3 acid). To prevent the acid-based product used
for the initial cleaning from corroding the cement-based joint
filler, we recommend you wet the floor prior to cleaning so that
the joints are impregnated and thus protected from the
corrosive action of the acid. If the initial cleaning is carried out
after the floor has been used, before applying the acid product
it is advisable to first remove any greasy or similar substances
using suitable cleaning products. After cleaning, the floor must
be rinsed thoroughly and the residual water collected.
Routine Cleaning:
For everyday cleaning, simply wash the floor with water and
normal cleaning products suitable for ceramic surfaces.
Unglazed tile may be cleaned with acid solutions only when
permitted by tile and grout manufacturer's printed instructions,
but no sooner than fourteen (14) calendar days after
installation. Protect metal surfaces, cast iron, and vitreous
plumbing fixtures from effects of acid cleaning. Flush surface with
clean water before and after cleaning.
When recommended by tile manufacturer, apply a protective material
to completed tile walls and floors. Protect installed tile Work with kraft
paper or other heavy covering during construction period to prevent
staining, damage, and wear.
Prohibit foot and wheel traffic from tiled floors for at least seven (7)
calendar days after grouting is completed.
Before final inspection, remove protective coverings and rinse neutral
cleaner from tile surfaces.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
206
END OF SECTION - CERAMIC TILES
3.1.13 STONEWARE TILING
PART 1 - GENERAL
1.01 RELATED DOCUMENTS
Drawings and general provisions of the Contract, including
General and Supplementary Conditions and Division 01
Specification Sections, apply to this Section.
Specifications throughout all Divisions of the Project Manual
are directly applicable to this Section, and this Section is
directly applicable to them.
1.02 REFERENCE STANDARDS
The latest published edition of a reference shall be applicable
to this Project unless identified by a specific edition date.
All reference amendments adopted prior to the effective date
of this Contract shall be applicable to this Project.
All materials, installation and workmanship shall comply with
all applicable requirements and standards.
1.03 QUALITY ASSURACE
Single Source Responsibility for Tile: Obtain each color, grade,
finish, type, composition, and variety of tile from a single
source with resources to provide products of consistent quality
in appearance and physical properties without delaying
progress of the Work.
Single Source Responsibility for Setting and Grouting
Materials: Obtain ingredients of a uniform quality from one
manufacturer for each cementitious and admixture component
and from one source or producer for each aggregate.
Installer Qualifications: Engage an experienced Installer who
has successfully completed tile installations similar in material,
design, and extent to that indicated for Project.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
207
1.04 SUBMITALS
A. Samples:
Submit samples for initial selection purposes of each tile
type and grout in form of manufacturer's color charts
consisting of actual units or sections of units showing full
range of colors, textures, and patterns available for each
type of finish indicated.
Where finish involves normal color and texture variations,
include sample sets composed of two or more units showing
full range of variations expected.
Include similar samples of material for joints and
accessories involving color selection.
Submit samples for verification purposes of each type, class,
and color/ pattern of tile required, not less than 18 inch
square on plywood or hardboard backing, and grouted as
required. Architect's review will be for color, pattern and
texture only.
Compliance with all other requirements is the exclusive
responsibility of the Contractor.
Prepare and submit new samples, if requested, until
appearance is acceptable to the Architect.
B. Product Data:
Submit manufacturer's product data and
installation/maintenance instructions for all manufactured
products and materials.
C. Shop Drawings:
Submit plans of all areas to receive tile Work showing
location of expansion and control joints, layout of tile units,
and other conditions affecting the Work.
Include details showing setting methods, expansion joint
constructions, and relationships to adjacent substrates.
Locate precisely each joint and crack in tile substrates by
measuring, record measurements on shop Drawings, and
coordinate them with tile joint locations, in consultation with
Architect.
Provide manufacturer's Master Grade Certificate bearing
TCA Certification mark and stating type, grade and location
of material for all tile specified to be "Standard
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
208
Grade".
D. Record Documents:
Provide record approved shop drawings, samples, and
warranties.
E. Warranty:
Provide guarantee on waterproofing membrane stating that
the waterproofing membrane will not leak, cause
delamination of tile installation, or otherwise fail to perform
as protective waterproofing for a period of five (5) years from
the Date of Substantial Completion.
1.05 PERFORMANCE REQUIREMENTS
Load-Bearing Performance: For ceramic tile installed on
walkway surfaces, provide installations rated for the following
load-bearing performance level based on testing assemblies
according to ASTM C 627 that are representative of those
indicated for this Project.
Extra Heavy: Passes cycles 1 through 14
Heavy: Passes cycles 1 through 12
Moderate: Passes cycles 1 through 10
Light: Passes cycles 1 through 6
Residential: Passes cycles 1 through 3
1.06 MOCK-UP INSTALATION
Prior to beginning tile installation, arrange for a meeting, on-
site, with the Architect to review proposed tile layout in each
area scheduled to receive tile.
Arrange for a "mock-up" installation of tile at certain areas as
directed to establish acceptable appearance standards.
In general, mock-up areas will be limited to approximately 40
square feet each and will be located at intersections of floor
and wall, at corners of rooms.
1.07 DELIVERY, STORAGE, AND HANDLING
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
209
Deliver and store packaged materials in original containers
with seals unbroken and labels intact until time of use. Comply
with requirement of ANSI A137.1 for labeling sealed tile
packages.
Prevent damage or contamination to materials by water,
freezing, foreign matter, and other causes.
Handle tile with temporary protective coating on exposed
surfaces to prevent coated surfaces from contacting backs or
edges of other units. If, despite these precautions, coating
does contact bonding surfaces of tile, remove coating from
bonding surfaces before setting tile.
1.08 PROJECT CONDITIONS
Maintain environmental conditions and protect Work during
and after installation to comply with referenced standards and
manufacturer's printed recommendations.
Vent temporary heaters to exterior to prevent damage to tile
Work from carbon dioxide buildup.
Maintain temperatures at 50 degrees F (10 degrees C) or
more in tiled areas during installation and for seven (7) days
after completion, unless higher temperatures are required by
referenced installation standard or manufacturer's instructions.
1.09 EXTRA MATERIALS
Deliver extra materials to Owner. Furnish extra materials that
match products installed as described below, packaged with
protective covering for storage and identified with labels clearly
describing contents.
Tile and Trim Units: Furnish quantity of full size units equal to
3 percent of amount installed, for each type, composition, color,
pattern, and size.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
210
PART 2 - PRODUCTS
2.01 GENERAL
All materials shall meet or exceed all applicable referenced
standards and local requirements, and conform to codes and
ordinances of authorities having jurisdiction.
2.02 MANUFACTURERS
The notes and schedules on the Drawings establish
manufacturer and model/design of tile products required for
the Project. Provide the products listed unless Architect
approves products of other manufacturer specifically for this
Project.
2.03 PRODUCTS, GENERAL
Stoneware tiles are full-bodied porcelain stoneware, dry-
pressed, highly compact, weather and chemical agent
resistant and with low porosity.
For installation methods consult detailed information from each
brand before starting the works.
A. Properties and process features:
Full-body porcelain stoneware slabs, made using systems of
patented multi-loading with computerized control, calibrated,
rectified.
The slabs consist of single, compact, frost proof, impervious
mass that resists chemical attacks, achieved through dry-
pressing of high-quality bodies made up of natural raw
materials (kaolin minerals, feldspars and inert materials),
atomized, and mixed in the press. The slabs are made
mechanically resistant through a sintering process at very
high temperatures.
Tiles must be rectified with straightens edges perfectly
squared.
B. Dimensions according to the drawings.
C. Materials supplied rectified and squared at caliber 7
(monocaliber).
D. Technical Features:
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
211
1. Shall be in accordance with each selected product by
the Architect (please refer to the Architecture project
“Drawings materials list”, “Finishes Schedule” and
Drawings, and the table in this “Technical
Specifications”, section 09 30 02, item 2.03, G, for
complementary information).
2. If there is no mention of a specific product/brand, the
general technical features for the stoneware tiles shall
be as below:
a. Water Absorption (ISO 10545.3) - 0,02 % - 0,04 %
b. Sizes (ISO 10545.2)
c. Length and width - ± 0.1%
d. Thickness - ± 5%
e. Edge straightness - ± 0.1%
f. Orthogonality - ± 0.1%
g. Flatness - ± 0.2%
h. Modulus Of Rupture (R) (ISO 10545.4) - 50 N/mm2
i. Resistance to deep abrasion (ISO 10545.6) -
135mm3
j. Coefficient of linear thermal expansion (ISO
10545.8) – 6,2MK-1
k. Resistance to thermal shock (ISO 10545.9) –
Resistant
l. Resistance to frost (ISO 10545.12) - Frostproof
m. Resistance to chemicals (ISO 10545.13) –
Conforms
n. Stain resistance (ISO 10545.14) – Conforms
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
212
o. Color resistance to light (DIN 51094) – No change
regarding brightness and color of samples
p. Fire proof (Decision 96/603 CE) - Class A1
E. If with Hydrotect technology, the tiles must have the
following capabilities:
1. Air purification mechanism;
2. Self-cleaning photo catalyst layer also with activated
oxygen;
3. Antibacterial, anti-mold, anti-dirt and anti-odor.
F. Anti-slip resistance:
1. Anti-slip resistance rating is required according to the
non-slip level in particular conditions, such as:
a. R9 suitable for dry conditions;
b. R10 suitable for wet conditions;
c. R11 suitable for internal and external commercial
pedestrian areas that are specifically designed for
wet bare foot conditions;
d. R12 suitable for ramp conditions;
e. R13 is the resistance recommended for public wet
areas such as showers and changing rooms.
2. At locations indicated, provide tile manufacturer's
abrasive grit surfaced tile for slip-resistant finish.
G. Colors, Textures, and Patterns:
1. Where manufacturer's standard products are indicated
for tile, grout and other products requiring selection of
colors, surface textures, patterns, and other
appearance characteristics, provide specific products
or materials complying with the following requirements:
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
213
a. Match color, texture, and pattern indicated by
reference to manufacturer's standard designations
for these characteristics.
2. Shall be in accordance with each selected product by
the Architect (please refer to the Architecture project
“Drawings materials list”, “Finishes Schedule” and
Drawings, and the table below for complementary
information)
H. Factory Blending:
For tile exhibiting color variations within the ranges selected
during sample submittals, blend tile in factory and package
accordingly so that tile units taken from one package show
the same range in colors as those taken from other
packages and match approved samples.
I. Trim and Special Shapes:
1. Provide tile trim and accessories that match color and
finish of adjoining flat tile.
2. Rounded external corners, and trim shapes at head,
jamb, and sills of opening, of same material and finish
as tile, and as follows:
a. Base: At tiled walls, integral cove base;, field tile
and surface bullnose to form a base of height
indicated.
b. External Corners: Surface bullnose shapes.
c. Internal Corners: Field butted square, except use
square corner- combination angle and stretcher
type cap.
3. At locations indicated, provide tile manufacturer's
abrasive grit surfaced tile for slip-resistant finish.
2.04 WATERPROOFING
Please refer to the Architecture project “Technical
Specifications”, section General Requirements, Part 3 -
Waterproofing, for detailed Information. The installer shall
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
214
certify the compatibility of all wet trades with the tiles, together
with the manufacturer, prior to its installation.
PART 3 - EXECUTION
3.01 PREPARATION
Examine substrates and areas where tile will be installed, with
Installer present, for compliance with requirements for
installation tolerances and other conditions affecting
performance of installed tile.
Verify that substrates for setting tile are firm, dry, clean, and
free from oil or waxy films and curing compounds.
Verify that installation of grounds, anchors, recessed frames,
electrical and mechanical units of Work, and similar items
located in or behind tile has been completed before installing
tile.
Do not proceed with installation until unsatisfactory conditions
have been corrected.
Blending: For tile exhibiting color variations within the ranges
selected during sample submittals, verify that tile has been
blended in factory and packaged accordingly so that tile units
taken from one package show the same range in colors as
those taken from other packages and match approved
samples. If not factory blended, either returns to manufacturer
or blend tiles at the Project Site before installing.
3.02 INSTALLATION
Installation shall meet or exceed all applicable local
requirements, referenced standards and conform to codes and
ordinances of authorities having jurisdiction.
All installation shall be in accordance with manufacturer’s
published recommendations.
Before starting the installation operations of any surface, we
recommend you make sure that the stoneware batch is
adequate and sufficient in terms of quantity, tone and
calibration. If in case of large environments joints must be
positioned at regular intervals, in small environments a small
gap between the tiles and perimeter walls is sufficient: the
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
215
skirting board will cover the gap and provide the finishing
effect. Avoid walking on the floor for at least 2/3 days after the
installation. If walking on the floor is necessary, lay wooden
planks on the surface. Please notice that if the tiles are
installed with the traditional procedure and no additives are
added to the mortar, at least one month has to elapse before
the floor can be subjected to stress and operating loads.
Extend tile Work into recesses and under or behind equipment
and fixtures to form a complete covering without interruptions
except as otherwise shown. Terminate Work neatly at
obstructions, edges, and corners without disrupting pattern or
joint alignments.
Accurately form intersections and returns. Perform cutting and
drilling of tile without marring visible surfaces. Carefully grind
cut edges of tile abutting trim, finish, or built in items for
straight aligned joints. Fit tile closely to electrical outlets, piping,
fixtures, and other penetrations so that plates, collars, or
covers overlap tile.
Carefully lay out tile in an endeavor to center the tiles to space
them evenly, and to avoid cutting them. If cutting is necessary,
cutting shall be done by saw cut or drilling only, no tile cutters
or snipped edges allowed; all cut ends shall be rubbed smooth
and even. Unless otherwise shown, lay out tile so that no tile
less than 1/2 size occurs. For height stated in feet and inches,
maintain full courses to produce nearest attainable heights
without cutting tile. Align joints in wall tile vertically and
horizontally. No staggering of joints will be permitted. All
cutting and drilling shall be done without marring surfaces and
shall be done neatly to fit closely around pipes, fixtures, and
fittings so that cover plates will overlap cuts.
Unless otherwise shown, lay tile in grid pattern. Align joints
when adjoining tiles on floor, base, walls, and trim are same
size. Lay out tile Work and center tile fields in both directions
in each space or on each wall area. Adjust to minimize tile
cutting. Provide uniform joint widths unless otherwise shown.
Confirm locations of joints in substrate will align with planned
expansion joints in tile Work. Adjust layout of tile if necessary
to align expansion joints with substrate conditions.
Expansion Joints: Locate expansion joints and other sealant
filled joints, including control, Contraction, and isolation joints,
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
216
where indicated during installation of setting materials, mortar
beds, and tile. Do not saw cut joints after installation of tiles.
Locate joints in tile surfaces directly above joints in concrete
substrates.
3.03 GROUT
Grout tile to comply with the requirements of the following
installation standards:
Wall Joints (less than 1/8 inches wide): Unsanded Grout.
Floor and Wall Joints (1/8 inch to 5/8 inch wide): Sanded Grout.
Floor Joints in Showers, and all Quarry Tile Joints (1/16 inch to
3/8 inch wide): Epoxy Grout.
3.04 EXPANSION JOINT INSTALLATION
At all floor tile installations, provide expansion joints at
perimeter of area to be tiled, at all penetrations in tile Work,
and 12 feet 0 inches on center both ways as recommended in
the TCA "Handbook for Ceramic Tile Installation" unless closer
spacing is indicated or required by Project conditions. Install
removable strips of the same depth as the finished tile system
including setting bed. Remove strips after grouting and curing
operations.
Install joints in accordance with TCA Method EJ711.
3.05 CLEANING AND PROTECTION
Initial Cleaning:
It is normally performed once before using the floor and it is
obligatorily after the installation. Its purpose is to eliminate any
trace of lime, cement or resin residues contained in the grouts
used for the joints. During this phase all the typologies
products must be washed using a solution of hydrochloric acid
(2/3 water, 1/3 acid). To prevent the acid-based product used
for the initial cleaning from corroding the cement-based joint
filler, we recommend you wet the floor prior to cleaning so that
the joints are impregnated and thus protected from the
corrosive action of the acid. If the initial cleaning is carried out
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
217
after the floor has been used, before applying the acid product
it is advisable to first remove any greasy or similar substances
using suitable cleaning products. After cleaning, the floor must
be rinsed thoroughly and the residual water collected.
Routine Cleaning:
For everyday cleaning, simply wash the floor with water and
normal cleaning products suitable for ceramic surfaces.
Unglazed tile may be cleaned with acid solutions only when
permitted by tile and grout manufacturer's printed instructions,
but no sooner than fourteen (14) calendar days after
installation. Protect metal surfaces, cast iron, and vitreous
plumbing fixtures from effects of acid cleaning. Flush surface
with clean water before and after cleaning.
When recommended by tile manufacturer, apply a protective
material to completed tile walls and floors. Protect installed tile
Work with kraft paper or other heavy covering during
construction period to prevent staining, damage, and wear.
Prohibit foot and wheel traffic from tiled floors for at least
seven (7) calendar days after grouting is completed.
Before final inspection, remove protective coverings and rinse
neutral cleaner from tile surfaces.
END OF SECTION - STONEWARE TILING
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
218
3.1.14 METALIC CEILINGS
PART 1 - GENERAL
1.01 RELATED DOCUMENTS
Drawings and general provisions of the Contract, including
“General Requirements” Specifications Sections, apply to this
Section.
Specifications throughout all Divisions of the technical
Specifications are directly applicable to this Section, and this
section is directly applicable to them.
1.02 REFERENCE STANDARDS
A. The latest published edition of a reference shall be
applicable to this Project unless identified by a specific
edition date.
B. All reference amendments adopted prior to the effective
date of this Contract shall be applicable to this Project.
C. All materials, installation and workmanship shall comply
with all applicable requirements and standards.
1.03 QUALITY ASSURANCE
A. Installer Qualifications: Engage an experienced Installer
who has successfully completed false ceilings similar in
material, design, and extent to those indicated for Project.
B. Fire Performance Characteristics: Provide false ceilings that
are identical to those tested for the following fire
performance characteristics. Identify false ceiling
components with appropriate markings of applicable testing
and inspecting organization.
1. Fire Resistance Ratings: As indicated by reference to
design for types of assemblies in which false ceilings
function as a fire protective membrane.
a. Protect lighting fixtures and air ducts to comply
with requirements indicated for rated assembly.
C. Single Source Responsibility for Ceiling Units: Obtain each
type of metallic ceiling unit from a single source with
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
219
resources to provide products of consistent quality in
appearance and physical properties without delaying
progress of the Work.
D. Single Source Responsibility for Suspension System:
Obtain each type of suspension system from a single
source with resources to provide products of consistent
quality in appearance and physical properties without
delaying progress of the Work.
E. Coordination of Work: Coordinate layout and installation of
metallic ceiling units and suspension system components
with other construction that penetrates ceilings or is
supported by them, including light fixtures, HVAC
equipment, fire suppression system components (if any),
and partition system (if any).
1.04 SUBMITTALS
A. Coordination Drawings:
1. Reflected ceiling plans drawn accurately to scale and
coordinating penetrations and ceiling mounted items.
Show the following:
a. Ceiling mounted items including light fixtures; air outlets
and inlets; speakers; sprinkler heads; and special
moldings at walls, column penetrations, and other
junctures with adjoining construction.
B. Samples:
1. Samples for initial selection purposes in form of
manufacturer's color charts consisting of actual metallic
units or sections of units showing full range of colors,
textures, and patterns available for each type of unit
indicated.
2. Samples for verification purposes of each type of
exposed finish required, prepared on samples of size
indicated below and of same thickness and material
indicated for final unit of Work. Where finishes involve
normal color and texture variations, include sample
sets showing full range of variations expected.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
220
C. Product Data:
1. Submit manufacturer's product data and
installation/maintenance instructions for all
manufactured products and materials.
D. Record Documents:
1. Provide record approved samples, product data, and
coordination drawings.
1.05 DELIVERY, STORAGE AND HANDLING
A. Deliver acoustical ceiling units to Project Site in original,
unopened packages and store them in a fully enclosed
space where they will be protected against damage from
moisture, direct sunlight, surface contamination, and other
causes.
1.06 EXTRA MATERIALS
A. Deliver extra materials to Owner. Furnish extra materials
described below that match products installed, are
packaged with protective covering for storage, and are
identified with appropriate labels.
1. Metallic Ceiling Units: Furnish quantity of full size units
equal to 2.0 percent of amount installed.
2. Suspension System Components: Furnish quantity of
each component equal to 2.0 percent of amount
installed.
1.07 PROJECT CONDITIONS
A. Space Enclosure: Do not install interior metallic ceilings
until space is enclosed and weatherproof, wet Work in
space is completed and nominally dry, Work above ceilings
is complete, and ambient conditions of temperature and
humidity will be continuously maintained at values near
those indicated for final occupancy.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
221
PART 2 - PRODUCTS
2.01 GENERAL
A. All materials shall meet or exceed all applicable referenced
standards and local requirements, and conform to codes
and ordinances of authorities having jurisdiction.
2.02 METAL SUSPENSION SYSTEMS, GENERAL
A. Standard for Metal Suspension Systems: Provide
manufacturer's standard metal suspension systems of types,
structural classifications, and finishes indicated.
B. Finishes and Colors: Provide manufacturer's standard
factory applied finish for type of system indicated.
C. Attachment Devices:
1. Cast-In-Place and Post-installed Anchors in Concrete:
Anchors of type indicated below, fabricated from
corrosion resistant materials, with holes or loops for
attachment of hangers of type indicated and with
capability to sustain, without failure, a load equal to 5
times that imposed by ceiling construction.
a. Chemical anchors.
b. Expansion anchors.
c. Undercut anchors.
D. Hanger Rods: Mild steel, zinc coated, or protected with rust
inhibitive paint.
E. Flat Hangers: Mild steel, zinc coated, or protected with rust
inhibitive paint.
F. Edge Moldings and Trim: Metal or extruded aluminum of
types and profiles indicated or, if not indicated,
manufacturer's standard moldings for edges and
penetrations that fit type of edge detail and suspension
system indicated. Provide trim with hemmed edges.
1. For lay in panels with reveal edge details, provide
stepped edge molding that forms reveal of same depth
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
222
and width as that formed between edge of panel and
flange at exposed suspension member.
2. For circular penetrations of ceiling, provide edge
moldings fabricated to diameter required to fit
penetration exactly.
3. For narrow faced suspension systems, provide
suspension system manufacturer's standard edge
moldings that match width and configuration of
exposed runners.
2.03 METALLIC UNIT MATERIALS
A. Refer to Finish Schedule on Drawings for type of acoustic
units to be provided.
PART 3 - EXECUTION
3.01 PREPARATION
A. Examine substrates and structural framing to which ceiling
system attaches or abuts, with Installer present, for
compliance with requirements specified in this and other
sections that affect installation and anchorage of ceiling
system. Do not proceed with installation until unsatisfactory
conditions have been corrected.
B. Coordination: Furnish layouts for preset inserts, clips, and
other ceiling anchors whose installation is specified in other
sections.
3.02 INSTALLATION
A. Installation shall meet or exceed all applicable local
requirements, referenced standards and conform to codes
and ordinances of authorities having jurisdiction.
B. All installation shall be in accordance with manufacturer’s
published recommendations.
C. Suspend ceiling hangers from building structural members
and as follows:
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
223
1. Install hangers plumb and free from contact with
insulation or other objects within ceiling plenum that are
not part of supporting structural or ceiling suspension
system.
2. Where width of ducts and other construction within
ceiling plenum produces hanger spacing that interfere
with the location of hangers at spacing required to
support standard suspension system members, install
supplemental suspension members and hangers in
form of trapezes or equivalent devices. Size
supplemental suspension members and hangers to
support ceiling loads within performance limits
established by referenced standards.
3. Secure wire hangers by looping and wire tying, either
directly to structures or to inserts, eye screws, or other
devices that are secure and appropriate for substrate,
and in a manner that will not cause them to deteriorate
or otherwise fail due to age, corrosion, or elevated
temperatures.
4. Secure flat, angle, channel, and rod hangers to
structure, including intermediate framing members, by
attaching to inserts, eye screws, or other devices that
are secure and appropriate for structure to which
hangers are attached as well as for type of hanger
involved, and in a manner that will not cause them to
deteriorate or fail due to age, corrosion, or elevated
temperatures.
5. Do not support ceilings directly from permanent metal
forms; furnish cast in place hanger inserts that extend
through forms.
D. Install suspension system runners so they are squared and
securely interlocked with one another. Remove and replace
dented, bent, or kinked members.
3.03 CLEANING
A. Clean exposed surfaces of metallic panel ceilings, including
trim, edge moldings, and suspension system members.
Comply with manufacturer's written instructions for cleaning
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
224
and touchup of minor finish damage. Remove and replace
ceiling components that cannot be successfully cleaned and
repaired to permanently eliminate evidence of damage.
END OF SECTION - METALIC CEILINGS
3.1.15 STONE FLOORING
PART 1 - GENERAL
1.01 RELATED DOCUMENTS
Drawings and general provisions of the Contract, including
“General Requirements” Specifications Sections, apply to this
Section.
Specifications throughout all Divisions of the technical
Specifications are directly applicable to this Section, and this
section is directly applicable to them.
1.02 DESCRIPTION
The requirements for stone flooring, set in mortar on a rigid
base are covered in this section.
1.03 RELATED WORK
A. Section includes
1. The following interior dimension stone hand set with
anchors with cavity:
a. Floors.
B. See drawings for the paving/surface pattern.
1.04 ALLOWABLE TOLERANCES
A. Floor surface true to plane within 1 in 1000 (1/8-inch in 10
feet) not cumulative.
B. Joint width deviation not greater than 10 percent of
dimension shown.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
225
1.05 SUBMITTAL
A. Shop drawings, product data and samples.
B. Samples: Five individual samples of stone showing extreme
variations in color and texture.
C. Shop Drawings: Special stone shapes.
1.06 PRODUCT DELIVERY, STORAGE AND HANDLING
A. Deliver masonry materials in original sealed containers
marked with name of manufacturer and identification of
contents.
B. Store masonry materials under waterproof covers on
planking clear of ground, and protect from handling damage,
dirt stain, water and wind.
1.07 APPLICABLE PUBLICATIONS
A. The publications listed below form a part of this
specification to the extent referenced. The publications are
referenced in the text by the basic designation only.
B. American Society for Testing and Materials (ASTM):
C144-04 .................. Aggregate for Masonry Mortar
C150-09 .................. Portland Cement
C241-09 .................. Abrasion Resistance of Stone
Subjected to Foot Traffic
C270-10 .................. Mortar for Unit Masonry
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
226
PART 2 - PRODUCTS
2.01 GENERAL
A. All materials shall meet or exceed all applicable referenced
standards and local requirements, and conform to codes
and ordinances of authorities having jurisdiction.
B. Varieties and Source: Subject to compliance with
requirements, provide stone of the variety-listed below.
C. Products shall be in accordance with each selected product
by the Architect (please refer to the Architecture project
“Drawings materials list”, “Finishes Schedule” and Drawings,
and the table below for complementary information)
2.02 MATERIALS
A. Stone Slabs: With abrasion resistance of at least 25 as
measured by ASTM C241. Stone slabs to be uniform in
quality and texture, free from shale, excess mica, seams,
sealing and disintegration.
B. Portland Cement: ASTM C150.
C. Coloring Pigments: Pure mineral pigments, lime proof and
non-fading; added to grout / mortar by the manufacturer.
Job colored grout / mortar is not acceptable.
2.03 MORTAR
ASTM C270, Type S. No admixtures permitted. Type N lime is
not permitted.
2.04 GROUT FOR STONE JOINTS
A. One part Portland cement and three parts sand by volume.
Mix with enough water for flow ability.
B. 2mm width.
2.05 STONE ACCESSORIES
A. Temporary Setting Shims: Rigid plastic shims, non-staining
to stone, sized to suit joint thickness.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
227
B. Setting Shims: Strips of resilient plastic or neoprene, non-
staining to stone, of thickness needed to prevent point
loading of stone on anchors and of depths to suit anchors
without intruding into required depths of pointing materials.
C. Cleaner: Stone cleaner specifically formulated for stone
types, finishes, and applications indicated, as
recommended by stone producer. Do not use cleaning
compounds containing acids, caustics, harsh fillers, or
abrasives.
D. Stone Impregnation (water and dirt repellent): Silicone basis
impregnation sealer (based on modified oligomere
alkylalkoxysiloxanes).
1. Suitable for internal/external surfaces;
2. Suitable for natural and cast stone (polish ground or
rough surfaces of marble, limestone, granite, gneiss,
porphyr, cotto, terrazzo, unglazed ceramic tiles, etc.),
bricks, sand lime bricks, concrete and mineral-based
plaster.
3. Applications:
a. For internal use: saturate the 5 sides (front + 4
sides);
b. For external use: saturate the 6 sides (front + 4
sides + back).
PART 3 - EXECUTION
3.01 APPLICABLE
A. General: Do not use stone slabs with chips, cracks,
discoloration or other visible defects.
B. Installation with Portland Cement Grout:
1. Spread and screed mortar setting bed mixture 13 mm
to 25 mm (1/2-inch to 1-inch) in thickness true to plane.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
228
2. Limit setting bed to minimum amount which can be
covered with stone before initial set.
3. Apply 1 mm (1/32-inch) layer of neat cement paste over
setting bed. Set and level each stone immediately.
Tamp stone to completely contact setting bed.
4. Grout joints as soon as initial set is achieved. Place
grout in joints, strike flush and tool slightly concave.
5. Cure grout by maintaining in a damp condition for
seven days.
C. Installation with Portland Cement Mortar:
1. Install in full bed joint. Remove excess mortar. Strike
joints flush with top surface of stone and tool slightly
concave.
2. Cure mortar by maintaining in a damp condition for
seven days.
END OF SECTION - STONE FLOORING
3.1.16 RESILIENT SHEET FLOORING
PART 1 - GENERAL
1.01 RELATED DOCUMENTS
Drawings and general provisions of the Contract, including
“General Requirements” Specification Sections, apply to this
Section.
Specifications throughout all Divisions of the Technical
Specifications are directly applicable to this Section, and this
Section is directly applicable to them.
1.02 REFERENCE STANDARDS
The latest published edition of a reference shall be applicable
to this Project unless identified by a specific edition date.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
229
All reference amendments adopted prior to the effective date
of this Contract shall be applicable to this Project.
All materials, installation and workmanship shall comply with
all applicable requirements and standards.
1.03 QUALITY ASSURANCE
Installer Qualifications: Engage Installer that is certified by
floor covering manufacturer as competent in the technique for
heat welding seams.
Single Source Responsibility for Resilient Sheet Flooring:
Obtain each type, color, and pattern of floor covering from a
single source with resources to provide products of consistent
quality in appearance and physical properties without delaying
progress of the Work.
Standard of Quality Sample: After approval of submittals and
prior to proceeding with the Work of this Section, at a location
determined by Owner, lay resilient sheet flooring of not less
than an entire room. Demonstrate cutting and trimming
techniques around obstructions. The Work will be reviewed by
Owner and Architect and, upon approval, will become the
standard upon which the quality of materials and workmanship
will be judged.
1.04 SUBMITTALS
Samples:
1. Samples for initial selection purposes in form of
manufacturer's color charts consisting of actual
sections of resilient sheet floor coverings showing full
range of colors and patterns available for each different
product indicated.
2. Samples for verification purposes in form of 6 inch by 9
inch sections of each different color and pattern of
resilient sheet floor covering product specified, showing
full range of variations expected in these characteristics.
Product Data:
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
230
1. Submit manufacturer’s catalog cuts and descriptive
information on each product used. Include information
on installation materials substantiating that they are
recommended for use by the resilient sheet flooring
manufacturer.
2. Submit manufacturer’s installation and maintenance
instructions for all manufactured products and materials.
Shop Drawings:
1. Shop drawings showing location of seams and edge
strips. Indicate location of columns, doorways,
enclosing partitions, built-in cabinets, and locations
where cutouts are required in flooring.
Record Documents:
1. Provide record approved samples, product data, and
shop drawings.
1.05 DELIVERY, STORAGE AND HANDLING
Deliver resilient sheet floor coverings and installation
accessories to the Project Site in original manufacturer's
unopened cartons and containers, each bearing names of
product and manufacturer, Project identification, and shipping
and handling instructions.
Store flooring materials in dry spaces protected from the
weather with ambient temperatures maintained between 10
degrees C and 32 degrees C.
Move resilient sheet floor coverings and installation
accessories into spaces where they will be installed at least 48
hours in advance of installation.
1.06 EXTRA MATERIALS
Deliver extra materials to Owner. Furnish extra materials
matching products installed as described below, packaged
with protective covering for storage and identified with labels
clearly describing contents.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
231
1.07 PROJECT CONDITIONS
Maintain a minimum temperature of 21 degrees C in spaces to
receive resilient sheet floor coverings for at least 48 hours
prior to installation, during installation, and for not less than 48
hours after installation. After this period, maintain a
temperature of not less than 13 degrees C.
Do not install resilient sheet floor coverings until they are at the
same temperature as the space where they are to be installed.
Close spaces to traffic while installing resilient sheet floor
covering.
1.08 SEQUENCING AND SCHEDULING
Install resilient sheet floor coverings and accessories as late in
the construction schedule as practical, and after other finishing
operations, including painting, have been completed.
Do not install resilient sheet floor coverings over concrete
slabs until the slabs have cured and are sufficiently dry to
bond with adhesive as determined by floor covering
manufacturer's recommended bond and moisture test.
PART 2 - PRODUCTS
2.01 GENERAL
All materials shall meet or exceed all applicable referenced
standards and local requirements, and conform to codes and
ordinances of authorities having jurisdiction.
2.02 MANUFACTURERS
The notes and schedules on the Drawings establish
manufacturer and model/design required for the Project.
Provide the products listed unless Architect approves products
of other manufacturer specifically for this Project.
2.03 INSTALLATION ACCESSORIES
Concrete Slab Primer: Non-staining type as recommended by
flooring manufacturer.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
232
Trowelable Underlayments and Patching Compounds: Latex
modified, Portland cement based formulation provided or
approved by floor covering manufacturer for applications
indicated.
Adhesives (Cements): Water resistant, stabilized type as
recommended by manufacturer to suit resilient sheet floor
covering products and substrate conditions indicated.
Seam Sealer: Formulation provided or approved by floor
covering manufacturer for products indicated.
Rod for Heat Welding Seams: Product of floor covering
manufacturer in color complying with the following requirement.
1. Match field color of sheet vinyl floor covering.
PART 3 - EXECUTION
3.01 PREPARATION
Concrete Subfloors: Verify that concrete slabs comply the
following:
1. Slab substrates are dry and free of curing compounds,
sealers, hardeners, and other materials whose
presence would interfere with bonding of adhesive.
Determine adhesion and dryness characteristics by
performing bond and moisture tests recommended by
floor covering manufacturer.
2. Subfloors are free of cracks, ridges, depressions, scale,
and foreign deposits of any kind.
Comply with manufacturer's installation specifications to
prepare substrates indicated to receive resilient sheet floor
coverings.
Use trowelable leveling and patching compounds per floor
covering manufacturer's direction to fill cracks, holes, and
depressions in substrates.
Broom or vacuum clean substrates to be covered by resilient
sheet floor coverings immediately before installation.
Following cleaning, examine substrates to determine if there is
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
233
visually any evidence of moisture, alkaline salts, carbonation,
or dust.
Apply concrete slab primer, if recommended by flooring
manufacturer, prior to application of adhesive. Apply according
to manufacturer's directions.
3.02 INSTALLATION
Installation shall meet or exceed all applicable local
requirements, referenced standards and conform to codes and
ordinances of authorities having jurisdiction.
All materials and installation methods shall be in accordance
with manufacturer’s published recommendations. Where
installation methods and, or materials are at variance with
manufacturer’s recommendations, Contractor shall bear full
responsibility for any resulting deficiencies.
Installation of resilient sheet flooring shall be accomplished as
late in the construction schedule as is practical.
Comply with resilient sheet floor covering manufacturer's
installation instructions and other requirements indicated that
are applicable to each type of floor covering installation
included in Project.
Lay out resilient sheet floor coverings in conformance with the
approved seaming diagram and to comply with the following
requirements:
1. Maintain uniformity of resilient sheet floor covering
direction.
2. Arrange for a minimum number of seams and place
them in inconspicuous and low traffic areas, but in no
case less than 6 inches away from parallel joints in
flooring substrates.
3. Match edges of resilient floor coverings for color
shading and pattern at seams.
4 Avoid cross seams.
Scribe, cut, and fit resilient sheet floor coverings to butt tightly
to vertical surfaces, permanent fixtures, and built in furniture,
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
234
including cabinets, pipes, outlets, edgings, thresholds, and
nosings.
Extend resilient sheet floor coverings into toe spaces, door
reveals, closets, and similar openings.
Adhere resilient sheet floor coverings to flooring substrates by
method approved by floor covering manufacturer.
1. Produce completed installation without open cracks,
voids, raising and puckering at joints, telegraphing of
adhesive spreader marks, or other surface
imperfections.
2. Comply with floor covering manufacturer's directions
including those for trowel notching, adhesive mixing,
and adhesive open and working times.
Heat weld seams in resilient sheet floor coverings where this
seaming method is indicated. Prepare, weld, and finish seams
to produce a surface flush with adjoining sheets.
Hand roll resilient sheet floor coverings in both directions from
center out to embed floor coverings in adhesive and eliminate
trapped air. At walls, door casings, and other locations where
access by roller is impractical, press floor coverings firmly in
place with flat bladed instrument.
3.03 CLEANING AND PROTECTION
Perform the following operations immediately after installing
resilient sheet floor coverings:
1. Remove visible adhesive and other surface blemishes
using cleaner recommended by floor covering
manufacturers.
2. Sweep or vacuum floor thoroughly.
3. Do not wash floor until after period recommended by
floor covering manufacturer.
4. Damp mop floor to remove black marks and soil.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
235
5. Apply protective floor polish to resilient sheet floor
covering surfaces that are free from soil, visible
adhesive and surface blemishes.
a. Use commercially available cross linked acrylic product
acceptable to floor covering manufacturer.
b. Coordinate selection of floor polish with Owner's
maintenance service.
Where application of a surface sealer is recommended by the
flooring manufacturer, provide sealer materials, and number of
coats, as recommended or approved by the flooring
manufacturer and apply following printed instructions.
Protect flooring against mars, marks, indentations, and other
damage from construction operations and placement of
equipment and fixtures during remainder of construction period.
Use protection methods indicated or recommended in writing
by floor covering manufacturer.
1. Do not move heavy and sharp objects directly over
sheet vinyl floor coverings. Place plywood or hardboard
panels over floor coverings and under objects while
they are being moved. Slide or roll objects over panels
without moving panels.
Clean resilient sheet flooring not more than two (2) days prior
to dates scheduled for inspections intended to establish date
of Substantial Completion in each area of Project. Clean floor
coverings by method recommended by manufacturer.
1. Strip protective floor polish that was applied after
completing installation, prior to cleaning.
2. Reapply floor polish after cleaning and buff/burnish to a
level acceptable to Owner.
END OF SECTION - RESILIENT SHEET FLOORING
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
236
3.1.17 CARPET
PART 1 - GENERAL
1.01 RELATED DOCUMENTS
Drawings and general provisions of the Contract, including
“General Requirements” Specifications Sections, apply to this
Section.
Specifications throughout all Divisions of the technical
Specifications are directly applicable to this Section, and this
section is directly applicable to them.
1.02 REFERENCE STANDARDS
A. The latest published edition of a reference shall be
applicable to this Project unless identified by a specific
edition date.
B. All reference amendments adopted prior to the effective
date of this Contract shall be applicable to this Project.
C. All materials, installation and workmanship shall comply
with all applicable requirements and standards.
1.03 QUALITY ASSURANCE
A. Carpet Surface Burning Characteristics: Provide carpet
identical to that tested for the following fire performance
characteristics, per test method indicated below, by testing
and inspecting organizations acceptable to authorities
having jurisdiction. Identify carpet with appropriate markings
of applicable testing and inspecting organization.
B. Factory Runs: Provide Carpet from one factory run and one
dye lot with colors and shades guaranteed to be uniform
throughout the entire area run for type of carpet specified.
C. Vermin and Dampproofness: Provide moth and vermin
proof carpet, compatible with installation over concrete slab
on grade floors.
1.04 SUBMITTALS
A. Shop Drawings:
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
237
1. Layout and seaming diagrams:
a. Indicate pile or pattern direction and locations and types
of edge strips.
b. Indicate columns, doorways, enclosing walls or partitions,
built in cabinets, and locations where cutouts are
required in carpet.
c. Show installation details at special conditions.
B. Samples:
1. Samples for verification purposes in manufacturer's
standard size, showing full range of color, texture, and
pattern variations expected. Prepare samples from
same material to be used for the Work. Submit the
following:
a. 30 cm square samples of each type of carpet
material required.
b. Two (2) full-size samples of each carpet tile
required.
c. 30 cm long samples of each type exposed edge
stripping and accessory item.
1.05 DELIVERY, STORAGE AND HANDLING
A. Deliver materials to Project Site in original factory
wrappings and containers, labeled with identification of
manufacturer, brand name, and lot number.
B. Store materials in original undamaged packages and
containers, inside well ventilated area protected from
weather, moisture, soilage, extreme temperatures, and
humidity. Lay flat, blocked off ground. Maintain minimum
temperature of 20 degrees C at least three days prior to and
during installation in area where materials are stored.
1.06 EXTRA MATERIALS
A. Furnish extra materials matching products installed as
described below, packaged with protective covering for
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
238
storage and identified with labels describing contents.
Deliver extra materials to Owner's storage location.
1. Broadloom Carpet: Before installation begins, furnish
quantity of full width for each type of material equal to 5
percent of amount installed.
2. Carpet Tile: Before installation begins, furnish quantity
of full size tiles for each type of material equal to 10
percent of amount installed.
1.07 WARRANTY
A. Special Carpet Warranty: Submit a written warranty
executed by carpet manufacturer and Installer agreeing to
repair or replace carpet that does not meet requirements or
that fails in materials or workmanship within the specified
warranty period. Failures include, but are not limited to:
1. Wear: Carpet materials shall evidence no more than 10
percent loss of face fiber.
2. Edge Raveling: Carpet material shall exhibit no edge
ravel, snags, and runs under normal use.
3. Delamination: Carpet materials shall not delaminate
from primary or secondary backing.
4. Shrinkage: Carpet materials shall show no shrinkage.
B. Warranty Period: Five (5) years from date of Substantial
Completion.
PART 2 - PRODUCTS
2.01 GENERAL
A. All materials shall meet or exceed all applicable referenced
standards and local requirements, and conform to codes
and ordinances of authorities having jurisdiction.
B. The notes and schedules on the Drawings establish
manufacturer and model/design required for the Project.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
239
Provide the products listed unless Architect approves
products of other manufacturer specifically for this Project.
2.02 MANUFACTURERS
A. To establish standards of manufacture, operation,
performance, and appearance, drawings and specifications
are based on the specific manufacturer's products and
color/patterns shown on the Drawings. If accepted in
advance by the Architect, and provided compliance with
requirements, products of other manufacturers may also be
acceptable:
2.03 ACCESSORIES
A Carpet Edge Guard: Extruded aluminum carpet edge, mill
finish aluminum.
B. Seaming Cement: Hot melt adhesive tape or similar product
recommended by carpet manufacturer for taping seams and
butting cut edges at backing to form secure seams and to
prevent pile loss at seams.
C. Carpet Adhesive: Non-solvent based, water resistant, and
non-staining as recommended by carpet and carpet tile
manufacturer to comply with flammability requirements for
installed carpet and compatible with substrate.
D. Trowelable Underlayments and Patching Compounds:
Latex modified, Portland cement based formulation
provided or approved by floor covering manufacturer for
applications indicated.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
240
PART 3 - EXECUTION
3.01 PREPARATION
A. Clear away debris and scrape up cementitious deposits
from concrete surfaces to receive carpet; apply sealer to
prevent dusting.
B. Patch holes and level to a smooth surface. If previous finish
chemically stripped, reseal concrete. Seal powdery or
porous surfaces with sealer recommended by carpet
manufacturer.
C. Patch holes and cracks. Sand to level. Remove wax. Seal
surface with sealer recommended by carpet manufacturer.
D. Replace missing pieces of existing resilient flooring or patch
to level. Cut out peaked sheet goods seams and fill with
latex underlayment.
E. Remove chemical finish on terrazzo; patch grout lines and
cracks to level with latex underlayment.
INSTALLATION
A. Installation shall meet or exceed all applicable local
requirements, referenced standards and conform to codes
and ordinances of authorities having jurisdiction.
END OF SECTION - CARPET
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
241
4.1 Specification
4.1.1 Design Load for the Northern Extension
Superimposed dead load:
Finishes Loading
(kPa)
Ceiling & Services Loading
(kPa)
Partition
(kPa)
Ground Floor
Mezzanine Level
1st Floor
2nd
Floor
3rd
Floor
Roof Level
2.5
2.0
2.0
2.0
2.0
3.0
-
0.5
0.5
0.5
0.5
0.5
2.8
-
2.2
2.3
1.7
-
Imposed load:
Loading (kPa)
Corridors, Staircases and landing 5.0
Toilets
G/F, 1/F, 2/F
3/F
5.0
3.0
Arrival and Departure Lobby, Retail, Public area (G/F,1/F,2/F)
5.0
Offices (3/F) 3.0
Accessible Roof 2.0
Plantroom 7.5
MVAC plantroom and fuel tank 10.0
Emergency generator room and 15.0
4 Specifications and Standards for Structure Works
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
242
switchroom
Water tank (2m deep) 20.0
The Contractor shall ensure any of the above loading provisions will not
be exceeded; otherwise provide a full structural assessment, at the
Contractor’s expense, to justify not any part of the building is
overloaded.
4.1.2 Design Code
The local Macau standards shall be followed and supplemented by
Eurocode 2 and International Building Code.
(i) 56/96/M: 屋宇結構及橋樑結構之安全及荷載規章
(ii) 42/97/M: 混凝土標準
(iii) 24/95/M: 防火安全規章
(iv) 47/96/M: 地工技術規章
(v) 60/96/M: 鋼筋混凝土及預應力混凝土結構規章
(vi) 64/96/M: 鋼筋混凝土用熱軋筋標準
(vii) 63/96/M: 水泥標準
(viii) GB50011-2001:
中華人民共和國國家標準 –
建築抗震設計規範基礎設計指引
(ix) 29/2001/M 建築鋼結構規章
In addition, the following British Standards should be referenced:
- BS12: Specification of Portland Cement
- BS812: Testing aggregates
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
243
- BS882: Specification for aggregates from natural source for
concrete
- BS1881 Testing concrete
- BS4466: Specification for scheduling, dimensioning, bending
and cutting of steel reinforcement for concrete.
- BS4483: Specification for steel fabric for the reinforcement of
concrete
- BS8007: Code of Practice for design of concrete structures for
retaining aqueous liquid
- BS 4: Structural steel sections. Part 1: Specification for hot
rolled sections.
- BS 427: Method for Vickers hardness test. Part 1: Testing of
metals.
- BS 729: Hot dip galvanized coatings on iron and steel articles.
- BS 1449: Steel plate, sheet and strip. Part 1: Specification for
carbon and carbon manganese plate, sheet and strip.
- BS 1706: Electroplated coatings of cadmium and zinc on iron
and steel.
- BS 2989: Specification for continuously hot-dip zinc coated and
iron zinc alloy coated steel: wide strip, sheet/plate and slit wide
strip.
- BS 3692: ISO metric precision hexagon bolts, screws and nuts.
- BS 4320: Metal washers for general engineering purposes.
- BS 4360 Specification for weldable structural steels.
- BS 4464: Spring washers for general engineering and
automobile proposes (metric series).
- BS 4570: Fusion Welding of Steel Castings.
- BS 4604:The use of high strength friction grip bolts in structural
steelwork, metric series.
Part 1: General grade.
Part 2: Higher grade (parallel shank)
Part 3: Higher grade (waisted shank)
- BS 4848: Hot-rolled structural steel sections.
Part 2: Hollow sections.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
244
Part 4: Equal and unequal angles.
- Approval testing of welder when welding procedures approval
is not required.
- BS 4872: Part 1: Fusion welding of steel.
- BS 4921: Sherardized coatings on iron and steel articles.
- BS 5289: Code of practice for visual inspection of fusion
welded joints.
- BS 5400: Steel, Concrete and Composite Bridges; all parts.
- BS 5950: Structural use of steelwork in building.
Part 1: Code of practice for design in simple and continuous
construction; hot rolled sections.
Part 2: Specification for materials, fabrication and erection; hot
rolled sections.
- BS 5996: Methods for ultrasonic testing and specifying quality
grades of ferritic steel plate.
- BS 6072: Method for magnetic particle flaw detection.
- BS 6780: Specification for through-thickness reduction of area
of steel plates and wide flats.
- BS EN 287-1: Qualification test of welders - Fusion welding
Part 1: Steels.
- BS EN 288-1: Specification and Approval of Welding
Procedures for Metallic Materials Part 1: General Rules for
Fusion Welding.
- BS EN 499: Welding Consumables-Covered Electrodes for
Manual Metal Arc Welding of Non Alloy and Fine Grain Steels -
Classification.
- BS EN 571-1: Penetrant Flaw Detection.
- BS EN 1011-1: Welding - Recommendations for welding of
metallic materials Part 1: General guidance for arc welding.
- BS EN 1011-2: Welding - Recommendations for Welding of
Metallic Materials -Part 2: Arc Welding of Ferritic Steels.
- BS EN 1714: Non-destructive testing of welds - Ultrasonic
testing of welded joints
- CORR 10286.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
245
- BS EN 14399: Specifications on High-Strength Structural
Boltings.
- Eurocode 3 Design of steel structures
- Eurocode 4 Design of composite steel and concrete structures
- National Structural Steelwork Specification (NSSS)
4.2 Particular Technical Requirements
The completed structure’s deflection and other structural movements
shall comply with the requirements of the designated codes of practices
and the standards referenced therein.
4.2.1 Construction Materials: Cement
All cement shall be fresh Ordinary Portland cement shall comply with
BS12 Part 2 1991. Other types of cement shall not be permitted without
the written acceptance of the Engineer. The cement shall be produced
by a manufacturer of good repute and subject to the endorsement of
CAM Project Manager. All cement to be used on the works shall be
supplied from the same source unless alternate sources are endorsed
by CAM Project Manager.
The Contractor shall obtain a manufacturer’s certificate of test in
accordance with the appropriate standards for each consignment of
cement delivered to the site for use in the work. CAM Project Manager
may require that any cement, delivered to the site for use in the works
to be sampled and tested in accordance with BS4550. Any batch of
cement so tested which fails to comply with this specification will be
rejected.
4.2.2 Construction Materials: Aggregates
Aggregates for concrete shall be from natural sources and shall comply
with BS882 unless otherwise specified. In additional, the flakiness index
when determined by the sieve method described in BS882 shall not
exceed 35 for any sizes of aggregates. Aggregates finer than zone 4 of
BS882 shall not be used. All aggregates shall be hard, durable, free
from coatings of deleterious matter and shall be non porous. The
grading of fine and coarse aggregates shall be to BS882:1992 and such
as to produce a dense concrete of suitable workability with proportions
of cement and water to be used.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
246
The CAM Project Manager may require that any aggregate to be test
for sulphate soundness in accordance with the latest edition of ASTM
Test C289 before giving endorsement to any proposed source of supply.
Notwithstanding any certificate of compliance or any prior endorsement
given by the CAM Project Manager may, at any time, require that any
aggregate deliver to the site, or else for use in the works, to be sampled
and tested before it may be used. Any aggregate so tested which fails
to comply with this specification may be rejected.
4.2.3 Construction Materials: Concrete
Structural concrete is specified in accordance with Macau Standard
60/96/M.
All concrete grade with prefix B denote designed mix. The reactive
alkali of concrete expressed as the equivalent sodium oxide per cubic
metre of concrete shall not exceed 3 kg. The concrete testing is to be
undertaken in accordance with the requirements of the Macau
Standards. The testing to be carried out include but not limited to
compressive strength, flexural strength and early age compressive
strength testing at 7 and 14 days.
The Contractor shall at his own expense provide all labour and
materials including transportation to the testing laboratory, required to
conduct concrete cube tests.
Concrete test cubes shall be made in 150mm cube steel moulds, filled
in three 50mm layers, each layer being thoroughly compacted with a
steel bar 380mm long having ramming surface of 25mm square and
weighing 1.8kg for at least 35 strokes.
The cubes shall be suitably identified and recorded at the time of mould
mix of concrete and location in the works from which the concrete has
been taken for the cubes. A tank shall be provided by the Contractor for
the purpose of curing test cubes to the satisfaction of the CAM Project
Manager.
Should the test cubes fail to achieve the minimum resistance to
crushing required for the concrete designed mix, the CAM Project
Manager may instruct the Contractors to carry out in-situ test at his own
expenses to the CAM Project Manager’s satisfaction and/or reject the
placed concrete. The Contractor shall also at his own expenses
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
247
increase the proportion of cement in future mixes until such tests satisfy
the concrete designed mix requirements.
Designed mixes, whose proportions shall be calculated by the
Contractor shall conform to the table below and the requirements set
out in Macau Standard 60/96/M.
Min. Works Cube
Strength at 28 days (N/mm
2)
Max Size of Aggregate
(mm)
Min Cement Content (Kg/m
3)
Max. Water
Cement Ratio
Max. Cement Content (kg/m3)
45 (B45) 20 375 0.44 530
40 (B40) 20 350 0.44 530
40 (B40) 10 400 0.44 530
35 (B35) 20 330 0.45 530
30 (B30) 20 300 0.46 530
30 (B30) 10 300 0.46 530
4.2.4 Construction Material: Reinforcement
All steel reinforcement including wire mesh to be tensile steel with fsyk
=460MPa in accordance with Macau standard 60/96/M or equivalent
and shall be cut, bent and scheduled in conformity with BS4446. The
Contractor must satisfy himself that the schedules are correct before
ordering, cutting and bending the reinforcement.
The Contractor is required to submit certificates of origin, test and mill
reports, chemical composition data and provide test lengths for testing
by a laboratory for each diameter and grade of steel from each supply
source to be delivered to the site.
Notwithstanding any manufacturer’s certificate, the CAM Project
Manager may require that any reinforcement delivered to the site be
sampled and tested. Should any test specimens fail to comply with this
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
248
Specification, the CAM Project Manager may require further test all at
the Contractor’s expense or reject the whole or part of this particular
consignment, which must be immediately removed from the site.
All reinforcement shall be stored at least 150mm clear of the ground or
floor, in clean conditions and in an orderly manner to the satisfaction of
the Engineer.
All reinforcement shall, at the time of concreting, be free from loose
scale, rust, oil or dirt or any other deleterious matter.
All reinforcement shall be fixed in the position shown on the drawings
by adequate use of spacers, tying wire, chairs, stools, etc. and shall be
so maintained during the concreting operation. Special attention shall
be given to all starter bars, which shall be rigidly supported by
temporary bracing near the free ends in such a way that they cannot
move when accidentally knocked or pulled.
4.2.5 Formwork and Method of construction
The Contractor shall be responsible for the design, stability, supply,
fixing and alignment of all formwork and supports. Formwork shall be so
designed and constructed that concrete can be properly placed and
thoroughly compacted to the true shape, line and dimensions without
loss of cement grout or other harmful effect to the finished structure.
Formwork shall be adequately strutted, braced or tied, it shall be
capable of adjustment to the lines and dimensions of the finished
concrete and shall be sufficiently strong to withstand the pressure
resulting from placing the concrete, including the method of compaction
employed, without undue deflections or loss of alignment.
Any device for securing formwork shall not remain with the concrete. All
joints in the formwork shall be either horizontal or vertical.
The Contractor shall inform the CAM Project Manager before he
intends to remove any formwork. The time at which the formwork is
removed shall be the Contractor’s responsibility but the minimum period
before the completion of any concreting and the removal of forms shall
be as follows:
Vertical formwork to columns, walls 12 hours
Soffit formwork to slabs with props left in 4 days
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
249
Soffit formwork to beams with propos left in 7 days
Props to slabs 10 days
Props to beams 14 days
Props to cantilevers 28 days
The periods given above are based on the use of ordinary Portland
cement under average weather conditions. Should the Contractor
propose to reduce these striking times, he must satisfy the CAM Project
Manager that the strength of the concrete at such time and the
structural system is adequate to withstand the dead and imposed loads
applied to it. Before reducing the striking times, the CAM Project
Manager’s endorsement shall be obtained in writing.
4.2.6 Placing and Compacting of Concrete
No concrete shall be placed until the disposition of the steel
reinforcement, formwork etc. has been checked and endorsed by the
Engineer. The Contractor shall give adequate notice to the CAM Project
Manager on the day prior to concreting and when everything is ready
for concreting in order that the CAM Project Manager may conduct his
inspection.
The Contractor shall clean all areas where concrete is to be placed and
render free from standing water immediately before placing of the
concrete, except for concrete placed under water.
Concrete shall be placed in its final position as soon as possible after
mixing and in such a manner as to avoid segregation of the concrete
and displacement of the reinforcement or formwork. Placing shall be
continuous between construction joints.
All concrete shall be compacted unless otherwise specified. The
compaction shall be carried out by an experienced operator using
immersion type vibrators to the CAM Project Manager’s satisfaction.
Placing of concrete shall be carried out in layers not exceeding 600mm
deep and in sequence from one end of the form to the other.
Concrete shall not be dropped from a height of greater than 3 metres,
thrown or otherwise treated so that segregation, undesirable finish or
defective structural quality may result.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
250
4.2.7 Sampling and Testing of Concrete
The costs for all concrete sampling and testing in accordance with
Norma de Betóes (Macau) are deemed to have been included in the
Contract. The Contractor shall comply with instructions issued by the
CAM Project Manager during the progress of the works with regard to
sampling and testing of the concrete. The Contractor shall be
responsible for the delivery of all test samples to an independent
laboratory and the name of the laboratory shall be submitted to the
CAM Project Manager for approval at the commencement of the
Contract.
Test cubes shall be clearly and indelibly marked for identification and
the Contractor shall furnish the laboratory with details of date of casting,
mix, workability of sample and identification of the part of the structure
represented by sample, which information shall be incorporated on the
test certificates issued by the laboratory. Keep records on site.
Slump tests shall be carried out at the Contractor's expense, in
accordance with B.S. 1881 or as directed by the Project Manager.
Non-destructive tests and/or coring tests on the site concrete shall be
carried out at contractor’s own cost if required by the Project Manager
and/or if the test cubes are found below standard.
Non-compliance of Standard of Acceptance
Should the test cubes not comply with the standard of acceptance as
specified in the Norma de Betóes (Macau) and this specification, the
Main Contractor shall undertake any one of the following steps or a
combination thereof at his own expense as the Project Manager
considers appropriate:
- Adjust the mix proportion and carry out further trial mixes until a
new proportion satisfying the requirements in the specification
is obtained and approved.
- Improve the standard of quality control before proceeding with
concreting works.
- Carry out, at the Contractor's expense, other tests as direct by
the Project Manager.
- Replace any site concrete condemned as a result of failing to
comply with the standards of acceptance specified and meet all
costs arising from such replacement. Submit for approval the
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
251
method statement for replacing the condemned concrete before
the replacement is carried out. In certain cases the Project
Manager may require the method statement to be prepared and
theremedial work to be supervised by a qualified Project
Manager.
During the progress of work, the Project Manager may order any other
tests in accordance with B.S.1881 or other relevant Standard where
practicable due to local conditions or other non-destructive tests such
as Schmidt hammer test. All such tests including the provision of
calibrated equipment shall be at the Contractor expense.
When Standard mix concrete is tested either in a plastic or hardened
condition by chemical analysis or other means for cement content it
shall be deemed not to comply with the specification if the cement
content is found to be below the specified figure after making due
allowance for the accuracy of the test method employed.
4.2.8 Construction Materials: Structural Steel
All structural steelwork design undertaken by the Contractor and/or his
Steelwork Sub-Contractor shall be designed strictly in accordance with
Macau Design Code 29/2001/M Regulation of Steel Structures;
Eurocode 3 Design of Steel Structures, Eurocode 4 Design Steel
Composite Structures and the latest version of British Standards (BS)
and European Norm (EN) where applicable, except where more
stringent requirements are specified herein, the Drawings, and/or
written instructions issued by CAM Project Manager.
All structural steel bars and plates, angles, channels and hot rolled
sections shall be grade S355JR to BS EN 10025-1:2004. All structural
members with plates/flange thickness greater than 35mm and less than
or equal to 50mm shall be Grade S355J0 to BS EN 10025-1:2004. All
structural members with plates/flange thickness greater than 50mm
shall be Class 1 Grade S355J2 to BS EN 10025-1:2004.
The grades of weldable steel used shall have the chemistry,
mechanical properties, ductility and notch toughness to provide the
least residual stress and maintain the integrity of the joints and
members with respect to strength and ductility.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
252
The required structural steel strengths from BS EN 10025 Standard
Codes are as follows:
Thickness Minimum Yield
t < 40mm 355 N/mm2 40 < t < 100m 335 N/mm2
All steel shall be new and shall be well and cleanly rolled to the
dimensions, sections and weights specified. It shall be sound and free
from cracks, surface flaws, laminations and other defects and shall be
finished in a workmanlike manner. Steel shall not be more heavily pitted
or rusted than Grade C of Swedish Standard 05 59 00.
All electrodes, welding rods and filler metals as follows:
Code Standard: To BS EN 1011-1 & 2 and BS EN 499 (Previously
named BS499), E51,Class B, C, R or RR for T=50mm or less, and
class B(H) for T greater than 50mm. Compatible in strength with the
parent material joined. Submerged arc and gas shielded welding shall
be as required by BS EN 499.
Bolts, screws and nuts shall comply with the British Standards and
strength grades stated in Table 2.01.1 unless other strength grades or
British Standards are stated in the Contract.
Washers for high strength friction grip bolts and nuts shall comply with
the following:
- High strength friction grip bolts and associated nuts and
washers for structural engineering:
(1) General grade: BS 4395: Part 1.
(2) Higher grade bolts and nuts and general grade washers: BS
4395:Part 2.
- Plain washers for other bolts, screws and nuts shall comply
with BS 4320; tapered washers for other bolts, screws and nuts
shall comply with BS 3410.
Internal bolt assembles, including cast-in holding down bolts, shall have
standard black finish. Exposed surfaces of bolts shall be clean and free
of corrosion when installed and be suitable for immediate prime painting.
For all exposed structural steelwork, bolt assemblies to be herardized in
accordance with BS 4921, Class 1
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
253
Welding consumables used in metal-arc welding of grades of steel
complying with BS EN 10025 shall comply with BS EN 1011. Welding
consumables used in the fusion welding of steel castings shall comply
with BS 4570. Welding consumables used in metal-arc welding of
austenitic stainless steels shall comply with BS EN 1011 Part 3.
Welding consumables and the procedures used shall be such that the
mechanical properties of the deposited weld metal shall not be less
than the respective minimum values of the parent metal being welded.
Welding consumables used with grades of steel other than those
complying with BS 10025 shall be such that the performance
requirements stated in BS 5400: Part 6, Table 1 or BS 5950: Part 2,
Table 1 as appropriate are achieved.
4.2.9 Fabrication of Steelwork
Fabrication of steelwork shall comply with BS EN 1011, BS 5400: Part 6,
Clauses 4.1 to 4.16 or BS 5950: Part 2, Sections 3 and 4 and with
relevant additional requirements specified in this Section.
Welding, heating and cutting:
- Welding shall be carried out by welders who possess a valid
welding certificate for the appropriate category of welding. A
welder shall cease to carry out welding if any of the
circumstances stated in BS 4570, Clause 21.1, BS EN 287-1 or
BS 4872: Part 1, Clause 6 as appropriate occurs.
- Presetting, prebending, skip welding, back-step techniques and
other measures shall be taken as necessary to counteract
shrinkage or distortion due to welding, gouging, thermal cutting
or heat treatment.
- Butt welds in each component part shall be completed before
the final assembly of built-up assemblies.
- Welding of austenitic stainless steel shall be carried out in
accord with BS EN 1011 Part 3
- Temporary welded attachments shall not be used unless
permitted by the Project Manager.
- Welding, heating or thermal cutting processes which give off
toxic or irritant gases shall not be used unless permitted by the
Project Manager; if permitted, precautions, including the
provision of exhaust ventilation, breathing apparatus and
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
254
display of warning signs, shall be taken to enable the work to
be carried out in safe conditions. Welding, heating or thermal
cutting shall not be carried out within 2 m shop coatings until
contents of shop coatings are verified as compatible with
welding or cutting procedures.
- Welding of structural steelwork shall be by an approved method.
The procedure to be followed, plant and equipment to be used
and the testing and inspection to be applied shall all be to the
satisfaction of the Project Manager and shall conform generally
with the requirements of BS EN 1011 and with the further
requirements contained in the Specification.
- All welding shall be carried out by fully trained and experienced
welders tested in accordance with BS EN 287 Part 1 or BS
4872 Part 1 appropriate to the type of welding they are to
perform.
- Size and length of welds shall not be less than those shown on
the Drawings nor shall they be substantially in excess of those
requirements without approval. The locations of welds shall not
change without approval by the Project Manager.
- All welds shall be finished full and made with the correct
number of runs, the welds being kept free from slag and other
inclusions.
- No joints or welds shall be made in any position except where
shown on drawings.
- Preheat and interpass temperatures and post-weld heat
treatment of welding sites shall be in accord with the
requirements of BS EN 1011.
Shop and site welding:
- Shop welding shall be carried out under specified welding
procedures and continuous supervision exercised.
- All welding shall, where possible, be carried out under cover in
the workshop.
- Site welding will only be permitted with the Project Manager’s
prior written approval.
Welding procedures:
- Develop welding procedures that in conjunction with overall
fabrication methods will produce members and structures
meeting quality requirements of these Specifications
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
255
- Obtain the Project Manager’s approval of welding procedures
before commencing work.
- Welding procedures shall be such that distortion is reduced to
the minimum practicable and local distortion is rendered
negligible in the final structure.
Assembly:
Structures shall be assembled in jigs that firmly and accurately locate
the individual members in their correct position. Prior to final welding,
members shall be tack welded in accord with BS EN 1011.
Electrodes for welding:
- Electrodes used for welding shall conform to BS EN 499 with
strength and toughness equal to the grade of steel (to BS EN
10025) to be welded, as recommended by the manufacturers.
- Electrodes that have areas of flux covering broken away or
damaged shall be discarded.
- Contractor shall ensure that electrodes are kept dry in order to
maintain the flux covering in good condition.
Fusion faces and preparation for welding:
- Fusion faces shall be free from irregularities and properly
prepared such that accuracy of the specified size of welds can
be maintained. Fusion faces and surrounding surfaces shall be
free from heavy scale and oil, paint or any substance that might
affect the quality of the weld.
- Butt welds shall be prepared by manual flame cutting and shall
be in accord with BS EN 1011, either single bevel or double
bevel full penetration butt welds with a maximum misalignment
of parts of 3mm. Use of a backing bar is optional. Flame cut
edges shall be substantially smooth and regular and shall be
left free of slag, faces shall be ground, filed or dressed to
remove irregularities and to maintain tolerances specified.
Defects in otherwise satisfactory flame cut edges shall be
limited to occasional notches and gouges not more than 5mm
deep. Correction of defects shall be to the approval of the
Project Manager.
- Thoroughly clean weld site of all slag and oxides between runs.
Fillet welds:
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
256
- Fillet welds shall be in accord with BS EN 1011.
- Parts to be fillet welded shall be brought into close contact and
the gap due to incorrect fit up shall not exceed 1.5mm.
- The minimum leg length of a fillet weld as deposited shall not
be less than the specified size, and the throat thickness as
deposited not less than 0.7 of the leg size where the fusion
faces are at right angles to each other.
Butt welds:
- The faces of butt welds shall be at all places proud of the
surfaces of parent metal. Where a flush surface is required, the
surplus metal may be dressed off by an approved method.
- Butt welds for thicknesses of more than 12mm shall be welded
from both sides.
- When welding from both sides the root of the initial weld shall
be gouged, chipped or otherwise removed to sound metal and
sealed with root passes before welding is started on that side.
- Butt welds made with the use of backing shall have the weld
metal thoroughly fused with it. The backing shall be fitted so
that a minimum space between it and the parts to be joined
exists. Splices in backing shall be made with full penetration
butt welds.
- Butt welds shall be terminated at the ends of a joint using
extension bars or runoff plates to ensure sound welds. Such
bars or plates shall be removed after welds have cooled.
- Ends of welds shall be ground smooth and flush with edges of
abutting parts.
Welded tubes:
- Tubular steelwork shall be continuously welded and interior of
all tubes shall be kept clean, dry and free from loose scale, etc.,
and shall be completely sealed, other than blow holes where
required for galvanizing.
- All welds shall be full penetration butt welds and, with the
exception of continuous tube-making processes, longitudinal
welds shall be made with extension plates at the starting and
finishing points of each seam.
Control of distortion and shrinkage stresses:
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
257
In assembling and joining parts of structure or of built-up members and
in welding reinforcing parts to members, procedure and sequence shall
be such as will minimize distortion and shrinkage.
Dimensional tolerances:
Dimensions of welded structural members shall be within the following
specified tolerances:
- Deviation from straightness of welded members where there is
no specified camber or sweep:
- 1mm x No. of metres of total length but not over 9mm.
- Deviation from straightness of welded members:
(1) +1mm x No. of metres of total length/3, or
(2) +6mm whichever is greater.
Weld profiles: Faces of fillet welds may be slightly convex, flat or slightly
concave. Except at outside corners, the convexity shall not exceed the
value 0.1S + 1mm where S is the actual size of the fillet weld in mm.
Quality of welds:
- Welds shall be uniform and of specified sizes. They shall fuse
thoroughly with the base metal and with successive layers of
weld metal, and shall be free from overlaps or abrupt edges or
grooves and from incomplete penetration, slag inclusions,
undercutting, burn troughs, voids, cracks, porosity and other
defects.
- Surfaces of welds shall be visually inspected and shall be
regular and uniform with a minimum amount of reinforcement
and reasonably free from overlap. All craters shall be filled to
the full cross-section of welds.
Corrections:
- A piece or member containing welding that is unsatisfactory or
that indicates inferior workmanship shall be rejected or
corrected by measures approved by the Project Manager.
- Defective or unsound welds or base metal shall be corrected by
removing and replacing the entire weld.
- Removal of weld metal or portions of the base metal may be
done by machining, grinding, chipping, oxygen gouging, or air
carbon-arc gouging and in such a manner that the remaining
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
258
weld metal or base metal is not nicked or undercut. Defective
portions of the weld shall be removed without substantial
removal of the base metal.
- Additional weld metal to compensate for deficiency in size shall
be deposited using an electrode smaller than that used for
making the original weld, and in any case not more than 4mm
in diameter. Thoroughly clean surfaces before welding.
- Improperly fitted parts shall be cut apart and rewelded as
directed.
Length of bolts: The length of HSFG bolts shall comply with BS 4604:
Part 1 or BS 4604: Part 2 as appropriate. The length of bolts complying
with BS 3692, BS 4190 and BS 4933 shall be such that the end of the
bolt will project above the nut by at least one thread, but by not more
than one nominal bolt diameter, after tightening.
Length of threads: The length of threads on bolts shall be determined in
accord with BS 3692, BS 4190, BS 4395: Part 1, BS 4395: Part 2 or BS
4933 as appropriate. If additional locknuts or other nuts are specified,
the thread length shall be increased by one nominal bolt diameter for
each additional nut.
Use of nuts: Nuts shall not be used with bolts or screws that comply
with a different standard.
Use of washers: Provide washers for HSFG bolts in accord with BS
4604: Part 1 or BS 4604: Part 2 as appropriate. Provide washers for
bolts complying with BS 3692, BS 4190 and BS 4933 under the nut or
bolt head, whichever is rotated during tightening, if parts to be
connected are to be coated with protective coatings before assembly.
Provide washers under nuts and heads of bolts in oversized and slotted
holes.
Tightening of bolts: Bolts shall be tightened in such a manner that the
contact surfaces of permanent bolted joints are drawn into close contact.
Defects in steelwork: Defective components for steelwork shall not be
used in the Permanent Works unless repair of the defects is permitted
by the Project Manager; if permitted, defective components shall be
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
259
repaired by methods having been reviewed without objection by the
Project Manager.
Review of fabricated steelwork by the Project Manager. Fabricated
steelwork shall not be:
- Covered with protective coatings, concrete or other materials.
- Erected, or
- Dispatched from the place of fabrication if fabricated off the site,
until the steelwork, including any repaired areas, complies with
specified test and inspection requirements and has been
reviewed without objection by the Project Manager.
4.2.10 Erection of Steelwork
Temporary supports and fastenings to steelwork:
- Steelwork shall be secured in position by temporary supports
and fastenings until sufficient permanent connections are
complete to withstand loadings liable to be encountered during
erection. Temporary supports and fastenings shall be capable
of withstanding loadings that may be encountered during
erection and shall not damage the steelwork or the protective
coatings.
- Riveted and bolted connections shall be aligned using drifts
complying with BS 5400: Part 6, Paragraph 4.12 and shall be
temporarily fastened using service bolts.
Alignment of steelwork:
- Steelwork shall be erected in such a manner that the alignment
and levels of the steelwork comply with the erection tolerances
specified. Allowance shall be made for the effects of
temperature on the steelwork.
- Measures shall be taken to ensure that the steelwork will
remain stable before temporary supports and fastenings are
slackened or removed for lining, levelling, plumbing or other
purposes. The temporary supports and fastenings shall be
retightened or replaced as soon as the adjustments are
complete and at the end of each continuous period of working.
- Permanent connections shall be made as soon as a sufficient
portion of the steelwork has been lined, levelled and plumbed.
Temporary supports and fastenings shall be replaced by
permanent connections progressively and in such a manner
that the parts connected are securely restrained in the aligned
position at all times.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
260
- Permanent connections for each portion of steelwork shall be
completed not more than 14 days after the portion has been
erected.
Supporting devices for steelwork: The material, size, position and cover
of packs, shims and other supporting devices for steelwork that are to
be embedded shall be as having been reviewed without objection by
the Project Manager
Erection:
- Adopt an erection procedure such that all members can be
placed and fixed in position without distortion.
- Contractor takes full responsibility for the safety and stability of
the steelwork during erection and until such time as it is finally
completed and handed over, must take all precautions
including temporary bracing necessary to ensure stability of the
partially assembled structure against wind forces, and those
stresses exerted due to erection equipment and its operation
tending to distort or deform the framework.
- Allow for the cost of temporary erection bracing required and
any professional advice required in connection with such
bracing.
- As each section of steel is erected, all members shall be lined,
levelled and plumbed before final bolting up commences. The
ties, jacks braces etc. used in lining, levelling and plumbing the
steelwork shall be left in position until all bolts have been finally
tightened.
- Mark every separate member with paint to show its mark,
position and direction. Such markings shall, where no finish
coat is subsequently applied, be in a position not visible after
completion of erection and cladding work.
4.2.11 Tolerances
Tolerances - fabrication of steelwork:
- Fabrication tolerances for steelwork shall comply with BS 5400:
Part 6, Paragraph 4.2 or BS 5950: Part 2, sub-section 7.2 as
appropriate.
- Steelwork shall be free from twists and localized deviations
from true line. The deviation from straightness of members
shall not exceed 1/1000 of the length of the member.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
261
- When two or more such lengths are joined the deviation from
straightness shall not exceed 1/1000 of the completed length
unless otherwise agreed by the Project Manager.
Tolerances - erection of steelwork:
- Steelwork shall be erected to within the following tolerances
after lining, levelling, plumbing and making the permanent
connections.
- The position in plan of vertical components at the base shall be
within 10mm of the specified position along either principal
setting out axis.
- The level of the top of base plates and the level of the lower
end of vertical or raking components in a pocket base shall be
within 10mm of the specified level.
- The thickness of bedding shall be within 1/3 of the nominal
thickness or 10mm, whichever is less, of the specified nominal
thickness.
- The line of vertical or raking components other than in portal
frames shall be within 1 in 600 and within 10mm of the
specified line in every direction.
- The line of vertical or raking components in portal frames shall
be within 1 in 600 and within 10mm of the specified line in
every direction.
- The position and level of components connected with other
components shall be within 5mm of the specified position and
level relative to the other components at the point of connection.
- The position of components supported on a bearing shall be
within 5mm of the specified position relative to the bearing
along both principal axes of the bearing.
- The difference in level between adjacent sloping or horizontal
components connected by a deck slab shall be within 10mm of
the specified difference in level.
- Erect, fix, adjust and maintain all members in their intended
vertical and lateral alignment and level. Members that do not
meet the specified tolerances shall be liable to rejection. Where
no specific tolerances are specified herein, they shall comply
with applicable British Standards.
4.2.12 Touch Up
Shop coat: Touch up shop coating damaged during installation. Clean
(in accord with coating manufacturer's recommendations, but not less
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
262
than specified for shop preparation requirements) and coat spots or
abrasions where paint has been removed, damaged, or burned. Apply
specified primer over all such surfaces, including field bolts, washers,
and other areas not embedded in concrete to the minimum DFT
specified for shop coating. Finish as specified for shop painting.
Galvanizing and metal coat: Touch up field cuts, holes, abrasions,
welds (including welds at grounding conductor connections), with field-
applied zinc-rich cold galvanizing compound coating touch-up material
in accord with BS 5493 and manufacturer's instructions.
4.2.13 Submittals
Information required from Contractor:
Submit a method statement accompanied by drawings and calculations
checked and approved by Project Manager supplementing to this
Specification and fully describing the following:
- Fabrication and assembly procedures and sequences in
addition to those described in this Specification. Particular
attention shall be given to the means of ensuring accurate
fitting of members and the avoidance of excessive distortion
stresses in assembly.
- Lifting and control procedures.
- Quality control procedures
- Quality control and assurance especially for bolt connection
- Corrosion protection system.
Submit manufacturer's test certificates, analyses and mill sheets for all
structural steel to the Project Manager. Certificates shall state the
process of manufacture and shall include a test sheet signed by the
manufacturer giving the results of the mechanical tests applied to the
steel purchased and its chemical composition. Should the Project
Manager require structural steel to be tested, samples shall be tested at
an independent testing station for compliance with BS EN 10025.
Details of shop drawings:
- Prepare all necessary shop and erection detail drawings and
submit duplicate copies of the same to the Project Manager for
approval at least 21 days before approval is required.
- Contractor's workshop drawings shall give complete information
necessary for the fabrication of joints and component parts of
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
263
the structure, including the location, type size and extent of
bolts and welds. They shall clearly distinguish between:
o Plans and necessary details with setting out and
member marks.
o Different grades and qualities of steel.
o Grades of bolts.
o Types and positions of welds.
o Manual and automatic welding.
o Shop and site welds.
- Shop drawings shall show weld preparation, the welding
process, filler metal and all joints design and details.
- On all shop drawings, welding procedure sheets, etc., terms
and symbols relating to the welding shall be in accord with the
relevant British Standard.
- Methods of jointing other than those shown as typical on the
Drawings may be employed subject to the Project Manager’s
approval.
- Design and details of all joints and connections, butt and fillet
welds and the permissible working stresses to be used therein
shall comply with BS EN 1011 except as may be otherwise
specified or shown on the Contract Drawings.
- Single bolt connections will not be allowed.
- All shop details and erection drawings shall be approved in
writing by the Project Manager prior to fabrication. Contractor
shall be solely responsible for the correctness of his shop
details, notwithstanding approval by the Project Manager.
- The Project Manager’s approval shall not in any way relieve
Contractor of responsibility for any errors subsequently
discovered in the details.
Details of delivery of steelwork:
The following details of steelwork fabricated off the site shall be
submitted to the Project Manager:
- Expected and actual arrival dates.
- Name of carrier.
- Duplicate copies of bill of lading and packing list for steelwork
transported by sea.
- Duplicate copies of delivery note and a list showing the marking
and weight of each component for steelwork transported by
land.
- The details of expected arrival date and name of carrier shall
be submitted to the Project Manager at least 21 days before the
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
264
due date; other details shall be submitted to the Project
Manager within 3 days after delivery of the steelwork to the site.
Details of method of erecting steelwork:
- At least 6 weeks before erection of steelwork starts, the
Contractor shall submit for the Project Manager review, a fully
detailed method statement of his proposed method of erection
of steelwork including the following particulars :
o Sequence and method of erection of steelwork.
o Method of lifting and handling the components.
o Method of preventing damage to protective coatings on
steelwork during handling.
o Procedure for aligning, levelling and plumbing steelwork,
including temporary supports and method of making
beddings for column bases.
o Sequence of casting concrete bonded to the steelwork.
- During handling and erection the steelwork shall not be
distorted or damaged and the stress limits specified in the
Regulamento de Estruturas de Aco para Edifcious (建築鋼結構
規章) shall not be exceeded.
- The Contractor shall submit, as soon as possible, calculations
of setting out, temporary structures, and all erection loads and
stresses. The calculations shall be in sufficient detail to satisfy
the Project Manager as to the soundness of the erection
scheme.
- The contractor shall make all necessary revisions or corrections
to satisfaction of the Project Manager prior to his
commencement of the erection works.
- The Contractor shall provide all temporary bracing scaffolding
and plant to ensure the safe erection of the structure.
- Any stanchions, beams, and steel trusses shall be carefully
erected, plumbed,set in alignment and levelled by approved
means and to the Project Manager's satisfaction prior to
grouting. Grouting shall be examined to ensure that it has been
properly and effectively carried out and any bases where the
grouting is considered to be unsatisfactory shall be brought to
the notice of the Project Manager. Nuts to holding-down bolt
assemblies are to be tightened down not less than 7 days after
grouting.
- It is the responsibility of the Contractor to determine the actual
position on site of holding down bolts, shear key pockets,
foundations, and other supporting members, before
commencing erection.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
265
- Site connections shall be made with black bolts, except where
fitted bolts or site welding is required. All bolts in external
locations shall be galvanised unless the member is to be
encased in concrete. A minimum of two bolts shall be used in
any bolted connection. Drift pins or podgers shall not be used in
such a way as to enlarge holes or distort work. New holes or
enlargement of existing holes shall be made on Site by drilling
and not by burning.
- Quality assurance and quality plan for bolt and nuts shall be
submitted to Project Manager for approval 2 weeks before site
works commencement.
- The Contractor shall be responsible for the safety of the
structural steelwork during erection, and any temporary ties,
scaffolding, shoring or bracing necessary to ensure such safety
shall be of sufficient number and strength to withstand the
effects of gales and typhoons and any superimposed loads.
- All members joined by bolted connections shall be securely
bolted into position and not left loosely attached. Members
which have remained loose for purposes of alignment or
levelling shall be made secure before the end of the day's work.
- Steelwork shall be secured in position by temporary supports
and fastenings until sufficient permanent connections are
complete to withstand the loadings encountered during erection.
The temporary supports and fastenings shall be capable of
withstanding loadings which may be encountered during
erection and shall not damage the steelwork or the protective
coatings.
- Bolted connections shall be aligned using drifts complying with
BS 5400 : Part 6, Clause 4.12 and shall be temporarily
fastened using service bolts.
- Steelwork shall be erected in such a manner that the alignment
and levels of the steelwork comply with the specified tolerances,
allowances shall be made for the effects of temperature on the
steelwork.
- Measures shall be taken to ensure that the steelwork will
remain stable before temporary supports and fastenings are
slackened or removed for lining, levelling, plumbing or other
purposes. The temporary supports and fastenings shall be re-
tightened or replaced as soon as the adjustments are complete
and at the end of each continuous period of working.
- Permanent connections shall be made as soon as a sufficient
portion of the steelwork has been lined, levelled and plumbed.
Temporary supports and fastenings shall be replaced by
permanent connections progressively and in such a manner
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
266
that the parts connected and securely restrained in the aligned
position at all times.
- Permanent connections for each portion of steelwork shall be
completed not more than 14 days after the portion has been
erected.
- The whole of the work shall be accurately positioned to correct
level and alignment.
- The Contractor shall supply all necessary falsework and
staging, labour, tools, erection plant, drifts, service bolts, nuts
and washers and other materials necessary to carry out the
work and shall remove the same as the progress of the erection
permits.
Welder certificates:
- Certificates endorsed by an inspecting authority having been
reviewed without objection by the Project Manager shall be
submitted to the Project Manager to show that each welder has
been approved in accord with BS EN 287-1. The extent of
approval of the welder shall be appropriate to the categories of
welds that he will carry out.
- The welder certificates shall be submitted at least 4 weeks
before fabrication of the steelwork starts.
Details of welding procedures:
- The following details of the proposed welding procedures shall
be submitted to the Project Manager:
o Welding procedures in accord with BS EN 1011 Part 1,
Clause 20 for each type and size of weld.
o Documentation endorsed by an inspecting authority
approved by the Project Manager to show that the
welding procedure has complied with the procedure
trial requirements stated in the Contract in previous
tests, or that the welding procedure for steel castings
complies with the exemption criteria stated in BS 4570,
Clause 20.1.1.
- The welding procedures for permanent welds shall be
submitted to the Project Manager at the same time as welder
certificates are submitted. The welding procedures for
temporary welds shall be submitted to the Project Manager at
the same time as welder certificates are submitted.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
267
Details of stud welding, flame cutting and shearing procedures:
The following details of the proposed stud welding, flame cutting and
shearing procedures for steelwork complying with BS EN 288 shall be
submitted to the Project Manager:
- Procedures for stud welding, flame cutting and shearing
processes complying with BS EN 288
- Documentation endorsed by an inspecting authority having
been reviewed without objection by the Project Manager to
show that the stud welding, flame cutting or shearing procedure
has complied with the procedure trial requirements stated in the
Contract in previous tests.
The details shall be submitted to the Project Manager at least 6 weeks
before fabrication of the steelwork starts.
Details of method of non-destructive testing: Details of the proposed
method for carrying out non-destructive testing on welds shall be
submitted to the Project Manager at least 4 weeks before the tests start.
Details of inspecting authority and testing consultant:
- The name of the proposed inspecting authority endorsing
welder certificates and records of tests for welding procedures
shall be submitted to the Project Manager. The name shall be
submitted at least 3 weeks before tests start or, if tests are not
required, at the same time as the welder certificates are
submitted.
- The name of the proposed testing consultant shall be submitted
to the Project Manager at least 3 weeks before the testing
consultant commences work.
- All tests required in the specification or as shown on drawings
shall be carried out by an independent testing consultant
employed by the Contractor and having been reviewed without
objection by the Project Manager.
- The Contractor shall submit to the Project Manager test results
for all test required within 7 days of the carrying out of the test,
together with a report from the Testing Organization on the
acceptability or otherwise of the results.
Details of corrosion protection system:
The following details of the proposed paints and associated products
shall be submitted to the Project Manager:
- Name of manufacturer.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
268
- Duplicate copies of the manufacturer's data sheets including
temperature, humidity and other conditions at the workshop or
on the Site under which the paint is to be applied.
- Manufacturer's product specifications, product range and
technical information.
- Surface preparation system for steelwork corrosion protection.
Samples of materials:
- A sample of blast cleaned steel plate shall be submitted to the
Project Manager for review at least 14 days before blast
cleaning starts. The sample shall be 150mm x 150mm x 6mm
and shall be enclosed in a sealed, colourless, transparent
wrapping. The grade of steel and the method of blasting shall
be representative of those that will be used in the Permanent
Works.
- Two samples of painted tin plates for each corrosion protection
system shall be submitted to the Project Manager at least 14
days before painting starts. Each plate shall be 150mm x 75mm
x 1mm and shall have smooth edges and 10mm corner radii.
The plates shall be brush cleaned and painted on one face with
the corrosion protection system in such a manner that each
coat is stepped back from the underlying coat in equal strips.
- Samples of each type of nut, bolt, washer, stud and rivet shall
be provided within 3 days after the material is delivered to the
site.
A test plan should be developed and submitted to Project Manager for
approval before commencement of test. The test plan should include
the following:
- Aim of the test including the number of specimens
- Description of the test specimen/structural model together with
the loading to be applied with particular attention to parameters
and tolerances in dimensions and materials
- during fabrication and erection that might affect the
performance.
- Possible modes of failure.
- Details of material and dimensional tests to be carried out on
the specimens.
- Testing arrangements including measures taken to ensure
adequate strength and stiffness for any supporting rig as well
as sufficient clearance to allow for deflections. This must take
into account all possible failure mechanisms.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
269
- Details of loading and restraints and how the load will be
controlled, i.e. either stress or strain control
- Details of what measurements are to be taken and frequency of
measurements.
- Details of what measurements are to be taken and frequency of
measurements.
- Accuracy of measurements.
The test plan should take into account the knowledge and experience of
those carrying out the tests as well as the facilities and equipment being
used.
4.2.14 Trials
Painting trials:
- A painting trial shall be carried out for each corrosion
protection system which will be applied to areas exceeding
100m2 to demonstrate that the proposed materials and
methods of application will produce a painted surface which
complies with the specified requirements.
- Painting trials shall be carried out at the place where painting to
the Permanent Works will be carried out and using the
employees and equipment which will be used to carry out
painting to the permanent work.
- Painting trials shall be carried out on blast cleaned steel.
Results of painting trials: If the painted surface produced in a painting
trial does not comply with the specified requirements for the paintwork,
the cause of failure shall be established by Contractor and details of
proposed changes shall be submitted to the Project Manager. Proposed
changes to the paint formulation, other than an adjustment in
the amount of thinners, shall be carried out at the paint manufacturer's
works before the final painting trial and before the first batch of paint is
delivered.
Commencement of painting: Painting shall not commence until the
painted surface produced in painting trials complies with the specified
requirements for paintwork.
Changes in materials and methods of application for painting: Unless
permitted by the Project Manager, the materials and methods of
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
270
application used in a painting trial that complies with the specified
requirements shall not be changed.
4.2.15 Handling, Storage and Transport of Materials
Handling and transport of steelwork:
- Steelwork shall not be subject to rough handling, shock loading
or dropping from a height.
- During handling and transport of coated steelwork, the
steelwork shall be separated from wires and lashings by rubber
padding in such a manner that the coatings are not damaged or
discoloured. Free ends shall be stiffened, measures shall be
taken to prevent permanent distortion and machined surfaces
and faying surfaces shall be protected.
- Steelwork shall not be lifted from the painting bed until the last
applied coating is sufficiently dry or cured for handling.
- Rivets, bolts, nuts, washers, screws and small plates and
articles shall be packed in containers marked to identify the
contents.
Storage of steelwork:
- Steelwork shall be stored off the ground on level supports in
well-drained areas in a manner that will not result in damage or
deformation to the steelwork or coatings or in contamination of
the steelwork or coatings. Packings shall be placed between
steelwork that is stacked.
- Covered places in which steelwork is stacked shall be
ventilated.
- Different types and sizes of steelwork shall be stored
separately.
- Steelwork shall not be stored on or adjacent to concrete
surfaces that form part of the Permanent Works.
- Steelwork shall be protected from exposure to conditions that
may affect the steelwork or coatings.
- Wet paint films, steelwork surfaces that are to be primed or
overcoated and joint surfaces that are to be assembled shall be
protected from exposure to conditions that may affect the film
or surface. Undercoats that contain anatase titanium dioxide
shall be protected from exposure to direct sunlight.
- Steelwork shall be stored in an enclosed workshop and
protected from conditions which may adversely affect the
steelwork until the following times:
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
271
o When the second undercoat to painted steelwork has
hard dried.
o When the coating process to galvanized, electroplated
or metal-sprayed steelwork has been completed.
o When the sealer to metal sprayed and sealed
steelwork has been completely absorbed.
o When the first undercoat to metal sprayed and painted
steelwork has hard dried.
- Primed steelwork surface may be exposed outside the
enclosed workshop for the minimum period necessary to move
the steelwork from one part of the workshop to the other; the
undercoated surfaces shall be covered when the steelwork is
being moved.
- All painted steelwork shall be checked for intercoat
contamination prior to application of following coats.
4.2.16 Construction Materials: Safety Glass
All glass units shall be supplied, coated, manufactured, assembled and
warranted by a single manufacturer. The glass shall all be from a single
source and the Contractor shall submit details of how he will control the
colour consistency for each elevation prior to glass ordering.
The source of glass supply shall be subject to review without
objection by the Project Manager. The source must have a
satisfactory proven track record of glass supplied for the type, size and
thickness concerned, appropriate QNQC measures, and compliance
with the design/ manufacturing/ testing standards as specified in this
specification or the best practice in glass manufacture as reviewed
without objection by the Project Manager.
The Contractor shall ensure that no glass or glazing combination
develops stresses that may lead to damage of glass, glazing materials,
components and/or framing systems.
The Contractor shall conduct a thermal stress analysis, undertake
thermal calculations and make due allowance for any tempered glass
which may be required.
The Contractor must satisfy himself that glass toughening
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
272
requirements are satisfactory to loads anticipated in the Safety Glass
Barrier. The prime manufacturer of the tempered
glass shall be made aware of its intended use in the construction. Any
drilling and notching is to be done with the agreement of the prime
manufacturer of tempered glass and prior to the toughening being
carried out. All tempered glass shall be tempered on a roller hearth
furnace eliminating tong marks and shall conform to BS 6206 Class A.
All tempered glass I glass exceeding surface and edge stresses of
7500 psi (50 MPa) shall be one hundred percent off line (i.e. glass
allowed to cool to room temperature for 24 hours prior to heat soaking)
heat soak tested with a 3-hour duration at 29000, in accordance with
BS EN 14179, to convert all critical Nickel Sulphide inclusions from the
alpha to the B phase so that the glass will fracture in the test. After the
test the probability of failure in service should be less than one in 400
tonnes. The manufacturer shall, at the request of the Project Manager,
show by statistical analysis of test data that the probability of failure is
not greater than the value quoted above.
Real time temperature-time curve for heat soaking of each batch of
process glass shall be recorded and witnessed by an independent
laboratory appointed by the Contractor. The accredited laboratory for
the oven calibration and witnessing the heat soak process shall be
nominated during tender stage for review without objection by the
project manager. All heat soak test records issued by the glass
manufacturer shall be countersigned by the Independent laboratory and
the Contractor and shall be submitted to the Project Manager for review
following glass delivery to the assembly factory or site.
Any glass breakage which takes place before the end of the DLP due to
Nickel Sulphide inclusions shall be replaced at the
Contractor's cost.
The surface compressive stress of the tempered glass shall be
demonstrated by non-destructive testing to be controlled at the factory
within the range of 70 N/mm2 to 100 N/mm2•
The surface compressive stress of the heat strengthened glass shall be
demonstrated by non-destructive testing to be between 38 Nlmm2 and
48 N/mm2.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
273
Four samples of project size glass with designated heat treatment and
coating shall be provided for each type of glass to demonstrate the
appearance of the final product. The samples shall also demonstrate
the quality of any repairs likely to the glass e.g. polishing of scratches.
The samples shall be to a standard reviewed without objection by the
Project Manager. The accepted trial samples shall be kept by the
Project Manager as control samples.
Repair record sheets shall be logged by the Contractor and
submitted to the Project Manager on completion of the Glass Safety
Barrier together with the coating warranty documents.
4.3 Survey of Existing dimensions and levels
Prior to commencing erection, the Contractor shall survey and report at least the following:
- Any discrepancies beyond specified tolerances to the Engineer
- Required adjustments to detailing and member lengths to
accommodate existing conditions when they are within
specified tolerances.
The Contractor shall submit structural steel shop drawings and erection drawings showing field surveyed dimensions of the Works including:
- Elevations of concrete on which structural steel is to be placed;
- Elevations of concrete on which structural steel is to be placed;
- Location and elevation of existing steel work, or steel work of
other Steel Subcontractors to which structural steel will be
connected; and
- Locations of existing works that may affect fabrication and
erection.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
274
5.1 Scope of specification
5.1.1 Installations to comply with this general specification
The Electrical Installation shall comply with this Specification which
details the intrinsic properties (including materials and workmanship) of
the Installations.
5.1.2 Scope of the installations
This Specification, Equipment Schedule and Drawings detail the
performance requirements of the Installations. The Installations to be
carried out in accordance with this Specification shall include the design
where specified, installation and supply of all materials necessary to
form a complete Installations including any necessary tests,
adjustments, commissioning and maintenance as prescribed and all
other incidental sundry components together with the necessary labour
for installing such components, for the proper operation of the
Installations.
5.1.3 Statutory obligations and other requirements
Electrical system design shall be developed to comply with the requirements of the Statutory Authorities, industry recognized standards and Codes of Practice in Macau, professional guides and recommendations issued by relevant professional bodies, institutions and organizations. Authorities and Utilities Companies:
(a) Direcção dos Serviços de Solos, Obras Públicas e Transportes, (DSSOPT)
(b) Public Works Department, Macau (c) Companhia de Electricidade de Macau-CEM, S.A, Supply
Rules and relevant Electricity Supply Ordinance (d) Companhia de Telecomunicações de Macau (CTM) –
Supply Rules and Relevant Communications Supply Ordinance
Standards and Codes: (a) BSI British Standards Institution (b) ICAO/IATA International Civil Aviation Organization (c) CIBSE Chartered Institution of Building Services Engineers (d) IET Institution of Engineering and Technology (e) ISO International Organization for Standardization
5 Specifications and Standards for Electrical Services
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
275
(f) IEC International Electrotechnical Committee (g) UL Underwriters' Laboratories, Inc. (h) DIN Deutsches Institut für Normung (German Institute for
Standardization) (i) Local Code Macau Local Code of Practice (j) TIA Telecommunications Industry Association (k) RAEM Região Administrativa Especial de Macau (l) SMACNA The Sheet Metal and Air Conditioning Contractors'
National Association
The Installations shall conform in all respects with the following:
5.1.3.1 Statutory Obligations
All Enactments and Regulations, in particular, the Contractor’s attention is drawn to the followings:
(a) Aprova os Regulamentos de Segurança de Instalações de Utilização de Energia Eléctrica e de Instalações Colectivas de Edifícios e Entradas (Decreto-Lei N.º 740/74)
(b) Ministérios da Administração Interna, das Finanças e do Plano, do Trabalho e Segurança Social e da Agricultura, Florestas e Alimentação (Decreto-Lei n.º 90/84/M)
(c) Portugal Standard NP
(d) RSIUEE - Regulamento de Segurança de Instalações de Utilização de Energia Eléctrica (RSIUEE) (Dec. Lei 740/74 of 26.12.1974)
(e) Institituto para os Assuntos Civicos e Municipais (IACM) – Recomendations and codes of practices
(f) Manual de Procedimentos Técnicos para Conservação de Energia em Edifícios de Macau» developed by DSSOPT;
(g) Code of Practice for the Electricity (Wiring) Regulations 2012 Edition issued by Electrical and Mechanical Services department, HKSAR (EMSD)
(h) Code of Practice for Energy Efficiency for Building Services Installation 2012 Edition Issued by EMSD
(i) BS 7671: Institution of Engineering and Technology (IET) Wiring Regulations – Regulations for Electrical Installations, 18th Edition. (hereinafter referred to as the IET Wiring Regulations)
(j) BS7430 : Earthing
(k) BSEN 62305: Protection against Lightning, 2006
(l) General Specification for Electrical Installation in Government Buildings of the Hong Kong Special Administrative Region 2012 Edition
(m) Relevant British Standard
(n) Any other authorities having jurisdiction over the installation
The Contractor shall adopt the latest development in the technology and use hi-tech, reliable, flexible, environmental friendly and sustainable system and equipment to formulate the final design.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
276
The Contractor shall at an early design stage liaise and consult with the relevant Government Departments, Authorities and Utility Undertakings such as Fire Services Department (CB), Power Utilities Company (CEM) etc. to obtain their requirements for incorporation into the design.
5.2 Particular Technical Requirements
The Contractor shall make full reference to the technical and design
standards and adopt the same or better design approach and
installation provision wherever applicable.
The Electrical Services Installation includes the works for design review
and selection, add or modify the existing electrical services system,
to establish the new electrical services system for the Works.
The design process shall ensure the proper and correct matching of all
the components constituting these systems are working properly in
order to conform to the performance requirements for the complete
Electrical Services Installation.
5.2.1 Power Supply and Distribution System
The incoming sources for the Works shall be obtained from the existing
substation 2 at 11kV side, existing 1600kVA transformer and a new
11kV/LV transformer in extension of the existing Passenger Terminal
Building (PTB) and the existing terminal. Modification, demolition,
diversion, alteration and addition works on the existing electrical system
shall be designed and built for the Works.
The Contractor shall provide an 11kV/LV transformer unit with at least
1600kVA power capacity connected to existing HV switchboards and
provide associated electrical system. The capacity shall be based on
electrical load estimation of extension of PTB for this Works. The
electrical loadings shall be fed from the existing and new 11kV/LV
transformers.
The Contractor shall design and build a complete electrical system for
the Works based on the existing electrical system in extension of the
existing Passenger Terminal Building (PTB) and existing terminal to
ensure adequate power provision shall be provided. The electrical
system will cover the modification and addition of HV/LV transformer,
HV and LV switchboards, generator and associated electrical
distribution systems, the LV main switch room; and associated
distribution electrical rooms at Macau Airport PTB Expansion Area and
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
277
existing terminal; the fixed link bridge and airbridge facilities. All
excavation, diversion and reinstatement works if required shall be
deemed to be included in the cost provisions for this power supplies
arrangement.
The electrical distribution systems shall be designed with a spare
capacity of not less than 20% for future extension or expansion.
The design shall incorporate power security for critical systems and
public area lighting.
The design shall incorporate protection and discrimination scheme
in order to isolate the electrical fault and confine the impact on the
airport operation to a minimum. and the associated LV main
switchroom with LV main switchboard and associated power
quality equipment shall be provided at MEP plant area or at each
group of areas by departments or parties.
Interleaving circuit strategy for PTB Building Expansion shall be
provided for the power supply network.
The electrical distribution systems includes but not be limited to electrical distribution equipment , electrical panel boards (with type test certificate provided), wiring and cables, cable containment system, wiring and accessories, miscellaneous electrical equipment, etc.
A complete cable containment system shall be for the use by the wiring system. The wiring system shall be deemed to include electrical services items such as lighting and small power, MVAC control, FS cables, Communication cabling, etc. A complete cable containment system shall include cable support means such as cable ladder, cable trays, hangers and wall-mounted cable trays and related support accessories and fixing provisions.
The design shall incorporate the requirements of voltage dip ride-through capability for all critical equipment including ELV system equipment, including without limitation the control systems, lighting systems, mechanical systems and lifts.
Wiring for low voltage circuits shall be LSOH to BS 7211.
Wiring for control circuits shall be carried out in flexible LSOH cable to BS 7211.
The cable containment system shall include surface cable conduit system works for power & lighting and provisions of cast-in & concealed
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
278
conduits for the Works. Co-ordination with builder's works is required among different discipline trades.
Unless otherwise specified, the hidden conduit works and concealed conduit works for lighting and small power shall be co-ordinated with the architectural and builder requirements. Painting shall also be provided in accordance with relevant architectural scope. Conduit System for other trades such as fire services, MVAC control and COMM/ IT system, etc shall be provided and shown in relevant system scope.
Underfloor cable containment system for low voltage wiring and COMM
system wiring distribution shall also be provided for departure lounges.
5.2.2 Essential and Emergency Power System
A complete Essential and Emergency Power System for the Works
shall be provided to backup the essential services which include:
(a) Fire services installations
(b) Essential and Emergency lighting
(c) Ventilation for fire services pump room
(d) Smoke Extraction system
(e) Ventilation control system
(f) Audio Visual Advisory system
(g) Fire Shutters
(h) Smoke Curtain
(i) Building Management system
(j) Security systems
(k) Airport Operation and ELV Systems not limit to :
a. Closed Circuit Television (CCTV) System
b. Public Address (PA) System
c. Private Automated Branch Exchange (PABX) System
d. Access Control System (ACS)
e. Wireless Network (WLAN) System
f. Radio Communication System
g. Flight Information Display System (FIDS)
h. Voice and Data Cabling (VDC) System
i. Master Antenna Television (MATV) System
j. Building Management System (BMS)
k. Passenger Check-in System
l. Baggage Handling and Screening System
m. Immigration Desks
n. Port Health System/Equipment
o. Customs System/Equipment
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
279
(l) Fixed Link Bridge Facilities
(m) Plumbing and drainage system
5.2.3 Electrical calculations
The Contractor shall submit the electrical calculations includes but not
limited to the below in his design and build designs for the CAM Project
Manager Consent.
(a) Overall electrical load estimation of extension of PTB with all
loadings in this Works: The calculation shall include normal,
essential and emergency power distributions on transformer(s)
and generator(s);
(b) Electrical load estimation with all loadings in this Works: The
calculation shall include normal, essential and emergency
power distributions on transformer(s) and generator(s);
(c) Cable and busduct Sizing calculation;
(d) Cable containment Sizing calculation;
(e) Power system discrimination calculation;
(f) Earthing and lightning calculation;
(g) Lighting calculation;
(h) UPS sizing and battery sizing calculations; and
(i) Generator system calculations (if generator set(s) is modified
and added);
a. Generator sizing and fuel supply system calculation;
b. Air Pressure Drop Calculations of Generator system;
c. Acoustic Treatment Calculation for Generator Rooms;
d. Exhaust Back Pressure Calculation for Generator; and
e. Acoustic Calculation for Exhaust System of Generator
5.2.4 Uninterruptible Power Supplies (UPS) System
The UPS system shall be equipped with the following requirements
unless noted otherwise from user departments.
Critical systems and control panels shall be backed up by UPS
to ensure monitoring and control functions remain unaffected in
case of voltage dips. The UPS shall be equipped with external
maintenance bypass facility allowing the non-break power switching in
the event that UPS is required to disconnect from the electrical system
for maintenance or repair.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
280
For ELV systems, dual UPS configuration (each rated at 100% load)
shall be considered and provided. External maintenance bypass
facility shall be included to allow the non-break power switching in
the event that both UPS are required to disconnect from the
electrical system for maintenance or repair. The UPS shall be
equipped with remote monitoring mechanism fully compatible and
capable of integrating with UPS monitoring system. The design
shall include associated cabling and equipment.
Each UPS system shall be equipped with adequate power capacity for
all essential power provisions to be provided for the Works.
UPS system shall be provided for Communication (IT) Rooms housing
ELV core equipment. The UPS shall provide a minimum backup time of
120 minutes at the full load for communication rooms depends on the
requirements by user departments for the Works.
5.2.5 Lighting System
A complete lighting system and intelligent lighting control system shall
be provided. Timer control shall also be included.
The lighting levels for various areas shall be designed generally
according to the recommendations of CIBSE Lighting Codes and
guidebooks. The maintenance factor shall be based on manufacturer’s
recommendation and it shall not be less than 0.8.
Unless otherwise stated from Government departments, CAM, airport operators and stakeholders, the following areas shall be illuminated to meet CIBSE Lighting Codes and the following average maintained illumination shown in the lux table below:
Location Average
Illumination
level
(Lux)
Uniformity
(Minimum
illuminance
to Average
illuminance)
Task
Uniformity
(Minimum
illuminance to
Average
illuminance)
Public areas (on floor) 200 0.4 -
General circulation
areas (on floor)
200 0.4 -
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
281
Seating areas (areas
nearby the seat but
not under the seat)(on
floor)
200 0.4 -
Queuing area (on
floor)
200 0.4 -
Toilet areas (on sink
and on floor)
200 (floor) &
350 (sink)
0.4 -
Passenger Queuing
Area |(floor level)
300 0.4 -
Entrance Check Point
(desk level)
400 - 0.7 for task
area
APV (inside of
building) (on wall)
100 0.4 -
APV (outside of
building) (on floor)
200 0.25 -
Office corridor (on
floor)
200 0.4 -
Normal and emergency lighting shall be provided for the areas of the
Works.
Sufficient numbers of self-contained emergency luminaires shall be
provided according to Macau Law and Regulations, BS 5266 and BS
EN 60598.
At least 50% of general lighting in the public areas shall be fed
by essential power supply from generators. At least 10% of the
essential lighting shall be incorporated with 2 hours self-contained
battery.
The lighting for public areas shall be controlled and monitored by the
BMS.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
282
The lighting systems shall be considered with different circuits
feed to minimise the operational impacts in the event of power fault.
The selection of light fittings shall consider energy efficiency,
maintenance frequency and spare part availability. The selection of light
fittings shall be based on the latest technology and energy efficiency.
LED type general Iighting shall be considered where practicable.
The lighting circuitry shall be arranged with interleaving circuits such
that there is no total blackout in the event of single power supply failure.
The lighting and control system shall be designed with flexibility in the
circuit arrangement to allow for future optimization of operation
schedule to achieve energy saving.
Unless otherwise stated from Government departments, CAM, airport
operators and stakeholders, intelligent lighting control system with
scenes shall be provided for meeting rooms and function rooms. The
illumination levels of lightings can be adjusted by groups and scenes.
Unless otherwise stated from Government departments, CAM, airport
operators and stakeholders, motion sensors (i.e. dual sensor type with
by-pass function) shall be provided at all male/ female showing, locker
area, toilets, associate common corridors and pantry, where minimum
lighting level shall be maintained for security guard patrol purpose and
means of escape requirements.
Unless otherwise stated from Government departments, CAM, airport
operators and stakeholders, day light sensors shall be provided at the
zone near to window with day lighting source for automatically dimming
the lighting down to acceptable level.
5.2.6 Earthing and Lightning Protection System
Lightning protection system shall be included for all structures and
systems for the Works.
The electrical earthing system shall be designed in accordance with BS
7430.
The lightning protection system shall be designed in accordance
with BSEN62305. The Contractor may propose equivalent
International Standard for Lightning Protection Systems but
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
283
submission is required to obtain Project Manager Consent prior to
works.
Clean Earthing System shall be provided for communication rooms
housing Airport ELV System equipment.
5.2.7 Lift System
The Contractor shall be responsible to check the weight allowed for lift
car decoration of the existing lift systems for stone replacement work.
The overall weight of the new stone lift car floor shall be within the
weight allowed for lift car decoration. The details of the stone
replacement work are shown on Architectural section in this design brief.
The fireman lifts shall comply with all statutory regulations.
The Contractor shall closely liaise with the Client and his
representatives in connection with the existing system in order to avoid
from conflict and disruption of airport operation with building structure
and existing utility services.
5.3 Testing and Commissioning
The Contractor shall be responsible to prepare and submit a full
set of Test and Commissioning documentation (T&C) for electrical
services Systems to the Project Manager for Approval.
The T&C documents shall be submitted at least 8 weeks before
the commencement of any T&C activities. The T&C Document
shall include as minimum containing the following information with
provisions or connections serving the Works.
(a) Proposed methodology and test procedure details
(b) Requirements of testing Instruments, testing conditions and
proposed acceptance criterion for operation performance
(c) Specific items of Factory Acceptance Test (FAT) and Site
Acceptance Test (SAT)
(d) List of Electrical Services System and Equipment which shall
not limit to :
a. Transformer
b. HV Switchboard and HV Switchgear
c. LV Switchboard and LV Switchgear
d. UPS Power
e. General Lighting
f. Emergency Lighting System
g. Lightning Protection System
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
284
h. Earthing System
i. Emergency Generator Power
j. LV Power and ELV Cables
(e) The T&C Items shall generally include
a. Visual Inspection;
b. Functional Checklist for respective electrical services
sub-systems ;
c. Instrumentation and Protection Device Operation;
d. Cable/Conductor Continuity Test;
e. Insulation Tests;
f. Polarity Check Test;
g. Earth Fault Loop Impedance Test;
h. Earth Rod Resistance Test;
i. Circuitry function Test;
j. Charge and Battery Test;
k. System Integrated Testing ( If required) ;
l. Interface Check with Existing PTB Systems ;
m. General and Performance Checking recommended by
suppliers and;
n. Statutory Compliance Checking and Demonstration
required by the Authorities.
o. Measurement Record
Prior to energizing, all systems shall be tested to ensure:
(a) Systems are free from short circuits and grounds and any faults
shall be rectified immediately on discovery unless associated
with wiring carried out by others, in which case they shall be
recorded and submitted as directed.
(b) Systems are free from mechanical and electrical defects. All
equipment, cabling etc is electrically safe.
(c) All exposed metal works is properly bonded and earthed with
statutory requirements and that all connections and points
required to be earthed for safety and satisfactory operation
are properly earthed in accordance with the manufacturer’s
requirements
(d) All cable cores and terminations are properly made off,
secure, properly supported and correctly identified and
coloured
(e) All phases, polarities, neutral and common connections are
correctly switched as required, that power is correctly available
at all points and that voltage and frequency at all equipment are
correct and in accordance with requirements for correct working
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
285
(f) All supplies are properly fused, or otherwise protected to give
satisfactory discrimination and safe disconnection under fault
conditions;
(g) All protective covers are properly fitted, all warning label and
designating labels are correct and in position and the inside of
all boxes and cubicles are clean and free of cable strippings;
(h) Battery, if provided are properly ventilated, installed,
connected and fitted, and that battery chargers are working
correctly.
(i) All instruments and meters are energised with correct polarity
and working properly
(j) All essential equipment fed from battery systems continue
to function correctly and without disturbance during all supply
failure, restoration and standby sequences
(k) All interlocking and sequencing; protection for normal and
operations are in order and checked, fitted and adjusted.
(l) Any faults shall be rectified immediately on discovery unless
associated with wiring carried out by others, in which case they
shall be recorded and submitted as directed.
(m) Where short circuit ratings are specified, documentary
evidence of compliance with such requirements shall be
provided.
(n) Compliance of Performance as requirement by local electrical
code and BS 7671.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
286
6.1 Specification
6.1.1 Statutory Obligations and Design Requirements
Fire Services Systems for this fit-out work contract are designed based on and shall comply with following codes:
The Contractor shall make full reference to the technical and design standards/specifications appended as annexes of this section and adopt the same or better design concept and installation provision wherever applicable.
Macau Fire Services regulation “ Regulamento de Seguranca Contra Incendios” and Decree Law 24/95/M
Direcção dos Serviços de obras Públicas e Transportes (DSSOPT) – Applicable codes and standards
Regulamento de Segurança Contra incêndios (RSCI) – Dec.Lei 24/95/M of 09.06.1995
Regulamento de Á guas e de Drenagem de Á guas Residuais de Macau (RADARM)) (Dec. Lei 46/96/M of 19.08.1996)
RSIUEE - Regulamento de Segurança de Instalações de Utilização de Energia Eléctrica (RSIUEE) (Dec. Lei 740/74 of 26.12.1974)
RSICEE - Regulamento de Segurança de Instalações Colectivas de Edificios e Entradas (Dec. Lei 740/74 of 26.12.1974)
Companhia de Electrcidade de Macau (CEM) – Supply Rules and Relevant Electricity Supply Ordinance
Serviço de Abastecimento de Á guas de Macau (SAAM) – Supply Rules and Relevant Water Supply Ordinance
Companhia de Telecomunicações de Macau (CTM) – Supply Rules and Relevant Communications Supply Ordinance
Institituto para os Assuntos Civicos e Municipais (IACM) – Recomendations and codes of practices
NFPA 72 –National Fire Alarm Code
NFPA 2001 – Standard on Clean Agent Fire Extinguishing Systems
Any other authorities having jurisdiction over the installation
The installation materials and equipment shall be supplied and installed using the best available quality materials and workmanship and shall comply with the latest requirements of the standard codes, guides and
6 Specifications and Standards for Fire Services
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
287
other documents issued by the authorities, institutions and organizations referred to in various sections of the Specifications, including the following:
BSI British Standard Institution
CIBSE Chartered Institution of Building Services Engineers
IEE Institution of Electrical Engineers
ISO Institution of Electrical Engineers
IEC International Electrotechnical Committee
DIN International Standard
ASHRAE American Society of Heating, Refrigeration and Air-Conditioning Engineers, Inc.
IPC International Plumbing Code
JIS Japanese International Standard
NFPA National Fire Protection Association
6.1.2 Particular Requirements
The Contractor shall make full reference to the technical and design standards and adopt the same or better design concept and installation provision wherever applicable in this fit-out contract. The Contractor shall be responsible for the design, supply and install testing and commissioning of all necessary Fire Service Installations in accordance with the performance requirements under this fit-out contract. The Contractor shall be responsible for design, select, add or modify the required fire service installation including the proper and correct matching of all the components constituting these systems in order to ensure that the systems conform to the performance requirements and are suitable for use as part of the Fire Service Installation. The existing Fire Alarm and Detection system for the Macau Airport Passenger Terminal Building (PTB) North Extension is of separate system and independent system from base terminal buildings systems. The Fire Alarm and Detection system under this fit-out contract for the Macau Airport Passenger Terminal Building (PTB) North Extension shall be connected to existing AFA panel systems of this building. The Contractor shall be responsible to ensure the new proposed Fire Services installation under this fit-out contract shall be compatible with existing Fire system the Automatic Fire alarm system of this building. The new fire alarm signals under this fit-out contract from Macau Airport Passenger Terminal Building (PTB) North Extension shall be repeated to existing Fire Services control centre for control and reporting. All the fire signals shall be repeated to existing two control points. With the F.S.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
288
fit-out works involve, the required modification, reconfiguration or addition to the existing Fire Services installation, the overall system performance of the existing Fire Services installation system shall not be degraded in any form. The Fire Services Wet systems under this fit-out contract for the Macau Airport Passenger Terminal Building (PTB) North Extension, the Contractor shall be responsible for the installation of sprinkler system and F.S. systems under the required fit-out works from the existing installation. Under circumstances where upgrading or alteration of the existing systems as require, the involved work shall include but not limited to sprinkler pipeworks, F.S. pipeworks, etc if necessary. Clean Agent Fire Extinguishing Systems – Novec 1230 [complying to NFPA] shall be employed under this fit-out contract whereas applicable for the protection of Electrical/ ELV equipment rooms and Electrical / ELVplant rooms including but not limited to battery room, Lan server room, ELV control room, ELV equipment rooms, etc.
Any works to be carried out by the Contractor under this fit-out contract shall not affect the normal operation and current accepted performance of the system. The works shall also be planned to minimize disturbance to the airport operations, night time working may be required. The Contractor shall make allowance in this regard in arranging their work tasks.
6.2 Testing and Commissioning
a) The Contractor shall arrange full testing and commissioning for all fire service installation to the CAM Project Manager showing that the fire service installation is in order and complies with Authority’s requirements before requesting Authority for statutory inspection and testing and the building handover. The Contractor shall carry out more and/or additional tests when required by the client if any part of the test fails.
b) The Contractor shall allow adequate time in his programme for the test and re-testing before completion of the Contract.
c) The Contractor shall liaise with all concerned parties for the timely completion of all works affecting the final fire services inspection by Authority including portable firefighting equipment, water supplies, EXIT signs, the whole Fire Service Installation, normal and essential electricity supply, control of the A/C works, fireman’s lift, all related builder’s works, etc. before the submission of relevant application forms to Authority requesting for inspection.
d) The Contractor shall carry out all tests for equipment and installation to be covered up before proceeding further any work, such as hydraulic test for sprinkler system piping before
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
289
the installation of false ceiling, etc. to the satisfaction of the to the CAM Project Manager. The Contractor shall be liable of all possible consequences if he fails to do so.
e) The Contractor shall submit the testing and commissioning details for the review without objection by the CAM Project Manager before implementation.
f) After having satisfied himself of the performance of the installation, the Contractor shall demonstrate to the satisfaction of the CAM Project Manager that the installations comply with all the statutory requirements.
g) The Contractor shall provide all necessary facilities and instruments for the witnessing and checking of such tests, but this shall not relieve the Contractor of his responsibility for testing and satisfying himself of the adequacy of the installation beforehand.
h) The Contractor shall make complete records of the tests as carried out and when the tests have been successfully completed, he shall provide the CAM Project Manager with test records in triplicate on a form to be agreed upon.
i) All instruments shall have been recalibrated within 6 months of the start of commissioning or testing. The Calibration of all instruments shall be certified by the instruments manufacturer or an approved calibration agency.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
290
7.1 Specification
7.1.1 Statutory Obligations and Design Requirements
The plumbing and drainage system for this fit-out work contract shall comply with the current rules and regulations established by the following authorities and utility companies:
Direcção dos Serviços de obras Públicas e Transportes (DSSOPT) – Applicable codes and standards
Regulamento de Segurança Contra incêndios (RSCI) – Dec.Lei 24/95/M of 09.06.1995
Regulamento de Á guas e de Drenagem de Á guas Residuais de Macau (RADARM)) (Dec. Lei 46/96/M of 19.08.1996)
RSIUEE - Regulamento de Segurança de Instalações de Utilização de Energia Eléctrica (RSIUEE) (Dec. Lei 740/74 of 26.12.1974)
RSICEE - Regulamento de Segurança de Instalações Colectivas de Edificios e Entradas (Dec. Lei 740/74 of 26.12.1974)
Companhia de Electrcidade de Macau (CEM) – Supply Rules and Relevant Electricity Supply Ordinance
Serviço de Abastecimento de Á guas de Macau (SAAM) – Supply Rules and Relevant Water Supply Ordinance
Companhia de Telecomunicações de Macau (CTM) – Supply Rules and Relevant Communications Supply Ordinance
Institituto para os Assuntos Civicos e Municipais (IACM) – Recomendations and codes of practices
Any other authorities having jurisdiction over the installation
The installation materials and equipment shall be supplied and installed using the best available quality materials and workmanship and shall comply with the latest requirements of the standard codes, guides and other documents issued by the authorities, institutions and organizations referred to in various sections of the Specifications, including the following:
BSI British Standard Institution
CIBSE Chartered Institution of Building Services Engineers
IEE Institution of Electrical Engineers
7 Specifications and Standards for Plumbing and Drainage Services
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
291
ISO Institution of Electrical Engineers
IEC International Electrotechnical Committee
DIN International Standard
ASHRAE American Society of Heating, Refrigeration and Air-Conditioning Engineers, Inc.
IPC International Plumbing Code
JIS Japanese International Standard
NFPA National Fire Protection Association
UL Underwriters Laboratory, Inc.
7.1.2 Particular Requirements
The Contractor shall make full reference to the technical and design standards and adopt the same or better design concept and installation provision wherever applicable in this fit-out contract. The Contractor shall be responsible for the design of all necessary Plumbing and Drainage Service Installation in accordance with the performance requirements in this fit-out contract. The Contractor shall be responsible for design, select, add or modify the required existing plumbing and drainage installation including the proper and correct matching of all the components constituting these systems in order to ensure that the systems conform to the performance requirements and are suitable for use as part of the Plumbing and Drainage Service Installation. The Contractor shall be responsible to design and provide water supply including but not limited to all necessary make-up storage water tanks with sufficient volume, pumping (duty and standby) facilities and control (automatic and manual) facilities to meet the user requirement on flow rate and pressure of water supply. Complete foul and storm water disposal system including all aboveground and underground pipeworks, fittings, traps and equipment in this fit-out contract.
The proposed design criteria for potable, flushing, cleansing and A/C make-up water supply are as follows:
Minimum water pressure for sanitary fixtures : 1.5 bar
Maximum water pressure for sanitary fixtures : 3.0 bar
The plumbing system under this fit-out contract for the Macau Airport Passenger Terminal Building (PTB) North Extension shall be a concealed system. All vertical pipes shall run in pipe ducts and all
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
292
horizontal pipe runs shall be concealed in the ceiling void, horizontal ducts or vanity cabinets. Adequate access panels shall be provided to the pipe ducts or false ceiling to enable maintenance work to be carried out. No piping shall be cast into concrete structures or block walls. The drainage system under this fit-out contract for the Macau Airport Passenger Terminal Building (PTB) North Extension shall be a concealed system. All vertical drainage pipes shall run inside pipe ducts and horizontal drainage pipes shall run inside ceiling voids, horizontal ducts or vanity cabinets. No drainage pipes shall be bedded in concrete structures or block walls. The Contractor shall be responsible to design and provide the plumbing and drainage system under this fit-out contract to connect and support the existing plumbing and drainage system on site. The Contractor shall closely liaise with the CAM Project Manager in connection with the existing plumbing and drainage system and drains on site in order to avoid from conflict with building structure and existing services installation. The Contractor shall allow all cost and time for diversion, modification, upgrading the existing plumbing and drainage system on site if considered necessary. Should there be any modification, reconfiguration or addition of plumbing and drainage installation, the overall system performance of the existing plumbing and drainage system shall not be degraded in any form. The Contractor shall submit detailed proposal including detailed calculation to the CAM Project Manager for approval. In the proposal, the Contractor shall demonstrate the design of the proposed plumbing and drainage system can cater the works under this fit-out contract. Cold and hot water supply shall be provided for the following locations/rooms:
Areas Cold Water Hot Water
Stand-alone wash hand basins at Office areas
Yes Yes
Wash hand basins at locker/changing rooms, Pantry
Yes Yes
Shower Units Yes Yes
Wash hand basins at staff toilets Plant Operations and Administration
Yes No
Wash hand basins at public Yes No
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
293
toilet/lavatory
Any works to be carried out by the Contractor under this fit-out contract shall not affect the normal operation and current accepted performance of the system. The works shall also be planned to minimize disturbance to the airport operations, night time working may be required. The Contractor shall make allowance in this regard in arranging their work tasks.
7.2 Testing and Commissioning
(a) The Contractor shall arrange full testing and commissioning for all Plumbing and Drainage Service Installation to the CAM Project Manager showing that Plumbing and Drainage Service Installation is in order and complies with Authority’s requirements before requesting Authority for statutory inspection and testing and the building handover. The Contractor shall carry out more and/or additional tests when required by the client if any part of the test fails.
(b) The Contractor shall allow adequate time in his programme for the test and re-testing before completion of the Contract.
(c) The Contractor shall liaise with all concerned parties for the timely completion of all works affecting the final Plumbing and Drainage Service Installation inspection by Authority including normal and essential electricity supply, all related builder’s works, etc. before the submission of relevant application forms to Authority requesting for inspection.
(d) The Contractor shall carry out all tests for equipment and installation to be covered up before proceeding further any work, such as hydraulic test for Plumbing and Drainage Service Installation piping before the installation of false ceiling, etc. to the satisfaction of the to the CAM Project Manager. The Contractor shall be liable of all possible consequences if he fails to do so.
(e) The Contractor shall submit the testing and commissioning details for the review without objection by the CAM Project Manager before implementation.
(f) After having satisfied himself of the performance of the installation, the Contractor shall demonstrate to the satisfaction of the CAM Project Manager that the installations comply with all the statutory requirements.
(g) The Contractor shall provide all necessary facilities and instruments for the witnessing and checking of such tests, but this shall not relieve the Contractor of his responsibility for
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
294
testing and satisfying himself of the adequacy of the installation beforehand.
(h) The Contractor shall make complete records of the tests as carried out and when the tests have been successfully completed, he shall provide the CAM Project Manager with test records in triplicate on a form to be agreed upon.
(i) All instruments shall have been recalibrated within 6 months of the start of commissioning or testing. The Calibration of all instruments shall be certified by the instruments manufacturer or an approved calibration agency.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
295
8.1 Specification
8.1.1 Statutory obligations and Design Requirements
Mechanical ventilation and Air-conditioning (MVAC) Services Systems for this fit-out work contract are designed based on and shall comply with following codes:
The Contractor shall make full reference to the technical and design standards/specifications appended as annexes of this section and adopt the same or better design concept and installation provision wherever applicable.
Direccao dos Servicos de obras Publicas e Transportes (DSSOPT) – Applicable codes and standards
Regulamento de Seguranca Contra incendios (RSCI) – Dec.Lei 24/95/M of 09.06.1995
Regulamento de Aguas e de Drenagem de Aguas Residuais de Macau (RADARM)) (Dec. Lei 46/96/M of 19.08.1996)
RSIUEE - Regulamento de Seguranca de Instalacoes de Utilizacao de Energia Electrica
(RSIUEE) (Dec. Lei 740/74 of 26.12.1974)
RSICEE - Regulamento de Seguranca de Instalacoes Colectivas de Edificios e Entradas (Dec. Lei 740/74 of 26.12.1974)
Companhia de Electrcidade de Macau (CEM) – Supply Rules and Relevant Electricity Supply Ordinance
Servico de Abastecimento de Aguas de Macau (Macau Water) – Supply Rules and Relevant Water Supply Ordinance
Companhia de Telecomunicacoes de Macau (CTM) – Supply Rules and Relevant Communications Supply Ordinance
Institituto para os Assuntos Civicos e Municipais (IACM) – Recomendations and codes of practices
Hong Kong Building Energy Efficiency Ordinance from EMSD HKSAR
Any other authorities having jurisdiction over the installation The installation materials and equipment shall be supplied and installed using the best available quality materials and workmanship and shall comply with the latest requirements of the standard codes, guides and other documents issued by the authorities, institutions and organizations referred to in various sections of the Specifications, including the following:
BSI British Standard Institution
CIBSE Chartered Institution of Building Services Engineers
IEE Institution of Electrical Engineers
ISO Institution of Electrical Engineers
8 Specifications and Standards for Mechanical Ventilation and Air-conditioning Services
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
296
IEC International Electrotechnical Committee
DIN International Standard
ASHRAE American Society of Heating, Refrigeration and Air-Conditioning Engineers, Inc.
IPC International Plumbing Code
JIS Japanese International Standard
NFPA National Fire Protection Association
8.1.2 Particular Requirements
Design Criteria
Outdoor Design Conditions:
Summer: 33.5 deg C DB, 68% RH
Winter: 7.0 deg C DB, 40% RH
Indoor Design Conditions:
Room / Space
Indoor Design Condition
Design Occupancy
Min. Fresh Air Rate per person
Acceptable Noise Level
Summer Winter
General Office
22-24 degC,
50-60% RH
18-20 degC,
50-60%RH
Note (a) 10 l/s/psn
NC45
Arrival & Departure Hall
22-24 degC,
50-60% RH
18-20 degC,
50-60%RH
Note (a) 5 l/s/psn
NC45
Nursing Room
22-24 degC,
50-60% RH
18-20 degC,
50-60%RH
Note (c) 10 l/s/psn
NC45
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
297
Smoke Lounge
22-24 degC,
50-60% RH
18-20 degC,
50-60% RH
Note (c) 10 l/s/psn
NC45
Lobby & Corridor Area
24degC,
50-60% RH
- - 0.3 l/s/per m2
-
Toilet 24degC,
50-60% RH
- - Note (b)
NC45
IT room/ ELV equipment room
20-22 DegC,
50-60% RH
20-22 DegC,
50-60% RH
- - -
Notes:
(a) The design occupancy of arrival & departure hall shall refer to latest approved patronage data from CAM.
(b) To provide the base provisions, e.g. chilled water and fresh air provisions, with control & isolation valves / dampers at boundary of F&B areas for future tenant’s connection. The design occupancy rate & minimum fresh air rate shall satisfy to latest licensing requirement of F&B / restaurant. The kitchen exhaust & makeup air system would be designed by future tenant.
(c) The occupancy density shall be provided by client.
Temperature and Humidity sensors shall be located at various locations to measure the indoor and outdoor conditions. The BMS shall be programmed to enable the free cooling mode when the outside air temperature and enthalpy are less than the indoor air temperature and enthalpy. Independent thermostat and sensor shall be provided for each IT/ELV room.
CO2 sensors shall be provided in the return air ducts to measure the CO2 levels under 1000 ppm in the concourse areas. The modulating type return and fresh air dampers are designed to provide optimum fresh air as per the measured CO2 levels.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
298
Dry contact shall be provided from the ventilation RI/O or I/O modules for VAC shut down the affected area non-emergency equipment in case of fire.
Toilet
The Contractor shall check and alternation the existing Mechanical exhaust system for all male, female and disable toilets with mechanical exhaust capacity can provide of not less than 15 air changes per hour. The exhaust system shall comprise of Inline centrifugal duct type exhaust fan with exhaust air ducts connected to the exhaust grilles for discharge, and the exhaust air discharge shall arranged at location without short circuiting to any building fresh air intake points.
Corridor Lobby
Air-conditioning shall be provided to the Corridor Lobby using chilled water fan coil units.
Technical services Rooms
An additional Clean Agent Fire extinguishing system - Novec 1230 and exhaust duct system shall be providing for technical room if existing system are not available.
Smoke Lounge
Air purifier shall be installed inside the smoke lounge. The performance of air purifier shall be able to remove odour and tobacco dusts, etc. Therefore, the air purifier shall be composed of different types of filter in order to filtrate different kind of air pollutants in the lounge. The room environment shall better than <Air Quality Guideline at Smoking Room in Japan> standard.
Other Areas
All other areas where not been addressed in this document, the
contractor shall design and proposed the system performance
requirement for Authority & Client acceptance.
All flexible duct used for connection shall not exceed 2 m length.
The louvre, grille, diffuser selected shall ensure face velocity not
exceed 2m/s.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
299
8.2 Testing and Commissioning
(a) The Contractor is required to responsible for the overall
planning, organizing, coordinating, supervising and monitoring
of the testing and commissioning works and also certifying all
results and reports from the testing and commissioning works.
(b) The Contractor is required to provide, at no cost to the
Employer, all necessary equipment, apparatus, tools and
materials for carrying out of testing and commissioning works.
(c) The Contractor is required to submit detailed inspection, testing
and commissioning methods and procedures together with
report formats for reporting inspection, testing and
commissioning results for the client’s approval at least one
months before commencement of the testing and
commissioning works.
(d) The Contractor is responsible for provision of all labour and
both consumable and non-consumable materials for carrying
out testing and commissioning works at their expenses.
Electricity supply, water and LP gas and town gas for carrying
out of testing and commissioning works shall also be arranged
and provided by the Contractor at no cost to the Employer.
(e) The Contractor is required to supply the calibrated equipment
and instrument for testing and commissioning works in
accordance with the requirements as requested by CAM
Project Manager.
(f) The Contractor shall liaise with all concerned parties for the
timely completion of all works affecting the final MVAC
installation inspection by Authority including the whole MVAC
installation, normal and essential electrical power supply,
control equipment, and all related builder’s works, etc. before
the submission of relevant application forms to Authority
requesting for inspection.
(g) Any defects of workmanship, materials and performance,
maladjustments or other irregularities which become apparent
during commissioning or testing shall be rectified by the
Contractor at no cost to the Employer and the relevant part of
the commissioning or testing procedure shall be repeated at the
Contractor’s expenses.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
300
(h) The Contractor shall carry out all tests for equipment and
installation to be covered up before proceeding further any
work, such as hydraulic test for chilled water supply system
piping and ductwork leakage test before the installation of false
ceiling, etc. to the satisfaction of the to the CAM Project
Manager. The Contractor shall be liable of all possible
consequences if he fails to do so.
(i) If considered appropriate, the Contractor shall be required to
carry out demonstration to dismantle those parts/components
of the Installations which are considered difficult/impossible for
maintenance access. The Contractor shall be responsible for
carrying out all necessary modification work at no extra charge
to the Employer to alleviate the difficulties associated with
dismantling or maintenance access.
(j) After having satisfied himself of the performance of the
installation, the Contractor shall demonstrate to the satisfaction
of the CAM Project Manager that the installations comply with
all the statutory requirements.
(k) The Contractor shall provide all necessary facilities and
instruments for the witnessing and checking of such tests, but
this shall not relieve the Contractor of his responsibility for
testing and satisfying himself of the adequacy of the installation
beforehand.
(l) The Contractor shall make complete records of the tests as
carried out and when the tests have been successfully
completed, he shall provide the CAM Project Manager with test
records in triplicate on a form to be agreed upon.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
301
9.1 Scope of Work
In this MIA fit-out works for PTB North Extension, the following ELV
systems will be involved as minimum:
Closed Circuit Television (CCTV) System
Public Address (PA) System
Private Automated Branch Exchange (PABX) System
Access Control System (ACS)
Wireless Network (WLAN) System
Radio Communication System
Voice and Data Cabling (VDC) System
Building Management System (BMS)
Information on the work scopes undertaken by the North Extension PTB
(RFQ-198) can be referred to the Appendix E.
On the other hand, the Contractor shall be responsible to the following
airport systems which have no alteration or expansion works to be
carried out:
Flight Information Display System (FIDS)
Master Antenna Television (MATV) System
Immigration Desks and Display Systems
Advance Visual Docking Guidance System (AVDGS)(option)
All Works shall be covered to areas within the North Extension PTB
which will involve with the fit-out works under this contract and the
interception area between Extension Building and Macau International
Airport Terminal. The works area shall be referred to the room data
sheets under this project. The following list has indicated the types of
ELV and Airport provisions provided to the locations which shall be
seamless to the existing arrangement for reference. The Contractor
shall :
Fit out Work Locations
System Enhancement provisions
ELV Rooms / CCTV rooms /
EOC
CCTV system; ACS system; BMS system and Radio Communications system
Public access area/ Corridor
PA system; CCTV system; WLAN system;
9 Specifications and Standards for Airport Systems
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
302
(front of house)/ Passenger
staircase
ACS system; and Radio Communications system
Toilets (public/ staff/ Disabled)
PA system; and WLAN system
Office area/ Corridor (Back of house)
PA system; CCTV system; ACS system; and Radio Communications system
CIP Lounge
PA system; FIDS; MATV; WLAN system; and Radio Communications system
Smoking Lounge
PA system; CCTV system; WLAN system; BMS system and Radio Communications system
Staircases/ lobbies (back of house)
PA system; CCTV system; ACS system; BMS system and Radio Communications system
Equipment & Plant Rooms
CCTV system; ACS system; BMS system and Radio Communications system
All the works under this project shall follow the current MIA operation
and existing system arrangement to re-configurate the existing terminal
systems without reduce the performance of existing system. The
contractor shall extend all the Airport / ELV systems to the new EOC.
The Contractor shall submit the Systems and Interface Management
Plan for system interface with the existing system - re-configure or
modify the software in the central computers to accommodate the
additional equipment into the existing system, including the
implementation of the new configuration. Modification of all
software/firmware is needed if necessary, which including but not be
limited to the software and databases that reside in the headend
processors, controllers, databases, server and all workstations.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
303
The Contractor shall relocate, remove or modify all the existing facilities
while the works of Airport / ELV system under this project is affected the
existing facilities. These replacement or relocation works shall be
submitted for review without objection by the CAM Project Manager
prior to manufacturing and installation. All the new installation
equipment and modification work shall be considered as part of this
project. The Contractor shall provide the installation program to CAM
Project Manager without objection to show that no interruption for the
existing system operation.
The Contractor shall provide the cable containment system and power
provision for Airport and ELV system.
Final testing and commissioning of the overall system inclusive of the
Contractor’s works and demonstrate the final system performance
including at the headend of the existing system to the satisfaction of the
CAM Project Manager. Any changes to the original design shall not be
made prior to the review without objection by the CAM Project Manager.
The final T&C works shall follows the Design requirement Brief clause
9.4.
9.2 Design Standards
The following design codes and standards will be referenced in the
Airport systems Design:
ICAO Annex 17, Security
ANSI/TIA/EIA SP2840 Commercial Building Telecommunications
Cabling Standard
EIA/TIA 606 Administration Standard for Telecommunications
Infrastructure of Commercial Buildings
ANSI/TIA/EIA-607 Grounding and Bonding Requirements for
Telecommunications in Commercial Buildings
BS 7671 Regulations for Electrical Installations - IEE Wiring
Regulations 17th Edition or the latest edition
BS 6833.2 Apparatus Using Cordless Attachments (Excluding
Cellular Radio Apparatus) for Connection to Analogue Interfaces of
Public Switched Telephone Networks
BS EN60950 Specification for Safety of Information Technology
Equipment including Electrical Business Equipment
IEC 61082 – Preparation of documents used in Electrotechnology
IEC 65 - Safety requirements for mains operated electronic and
related apparatus for household and similar general use
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
304
Relevant Customer Technical Guides of FTNS Operator(s)
Laws and Regulations of the Bureau of Telecommunication
Regulations, Macao
CCITT Q.931 Standard – ISDN User Interface Layer 3 Specification
for Basic Call Control
CCITT Q.761 Standard – Functional Description of the ISDN User
Part of Signaling System No 7
CCITT I.420 Standard – Basic Rate User Network Interface
CCITT I.421 Standard – Primary Rate User Network Interface
CCITT G.703 Standard – Physical/Electrical Characteristics of
Hierarchical Digital Interfaces
CCITT G.704 Standard – Synchronous Frame Structures Used at
Primary and Secondary Hierarchical Level
EIA RS-232C – Specification of the Mechanical and Electrical
Characteristics of the Interface used for Connecting Data Circuit
Terminating Equipment and Data Terminal Equipment
EIA RS-422A – Electrical Characteristics of Balanced Voltage
Digital Interface Circuits
EIA RS-449 – General Purpose 37 Pin and 9 Pin Interface for Data
Terminal Equipment and Data Circuit Terminating Equipment
Employing Serial Binary Data Interchange
EIA/TIA 568 – Commercial Building Telecommunications Wiring
Standard
EIA/TIA 569 – Commercial Building Standard for
Telecommunications Pathways and Spaces
BS EN 50173:2007 Information Technology – General Cabling
Systems
BS EN 50174:2001 Information Technology – Cabling Installation
ANSI/EIA/TIA Technical Services Bulletin TSB36
EIA/TIA 570 – Residential and Light Commercial
Telecommunications Wiring Standard
ETS GSM 11.10 – GSM DCS 1800 Mobile Station Conformity
Specification
IEEE 802.3 – CSMA/CD Access Method and Physical Layer
Specifications (Ethernet)
IEEE 802.5 – Token Ring Access Method and Physical Layer
Specifications
IEEE 802.11b/g/n/ac Wireless LAN standard
IEEE 802.3u Fast Ethernet over Fibre Optic
IEEE 802.3z 10G b/s Ethernet standards
IEEE 802.3a 10G b/s Ethernet over Twisted Pair
IEEE 802.3a Link aggregation for parallel links
IEEE 802.3af Power over Ethernet
IEEE 802.3ae 10G b/s Ethernet over Fibre Optic
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
305
IEEE 802.1q VLAN Tagging
IEEE 802.1p Traffic Class Expediting
IEEE 802.1d Spanning Tree Protocol
IEEE 802.1w Rapid Spanning Tree Protocol
IEEE 802.1s Multiple Spanning Tree Protocol
IEEE 802.1x Port-Based Network Access Control
IEC 529 – Degree of Protection Provided by Enclosures for
Electrical Equipment
IEC 11 – Limits and Methods of Measurement of Electromagnetic
Disturbance Characteristics of Industrial, Scientific and Medical
Radio-Frequency Equipment
IEC 79-7 – Increased Safety Requirement for Electrical Equipment
for use in Explosive Atmospheres
IEC 79-11 – Guidelines for Design and Assessment of Intrinsically
Safe Circuits
IEC 79-15 – Requirements for Non-Sparking Electrical Equipment
BS 6513 Wideband Cabled Distribution Systems
EIA-422-A Electrical Characteristics of Balanced Voltage Digital
Interface Circuits
IEC 96-3 Radio Frequency Cables, Part 3 - General requirements
and tests for single unit coaxial cables for use in cabled distribution
systems
CCIR Recommendation 500-3, 562-2, 567-2
The relevant codes and guides published by the Building Services
Research and Information Association (BSRIA-UK)
EN55022 / CISPR 22 Class A standards issued by the European
Committee for Electrotechnical Standardization (CENELEC)
IEC Display Monitor Standard 60065
IEC Display Monitor Standard 60950
BS 5954 Dimensions of Mechanical Structures of the 482.6 (19 in)
series Part 2 Specification for Cabinets and Pitches of Rack
Structures; Part 3 Specification for Subracks and Associated Plug-
In Units
BS 6527 Specification for Limits and Methods of Measurement of
Radio Interference Characteristics of Information Technology
Equipment
BS 7151 Representation of Dates and Times in Information
Interchange
EIA 422-A Electrical Characteristics of Balanced Voltage Digital
Interface Circuits
EN50081 Electromagnetic compatibility. Generic emission
standard Part 1 Residential, Commercial and Light Industry
EN50082 Electromagnetic compatibility: Generic immunity standard
Part 1 Residential, Commercial and Light Industry
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
306
ISO/IEC11801- Information technology –Generic cabling for
customer premises
ISO/IEC 24764 - Information technology -- Generic cabling systems
for data centres
TIA-942 - Telecommunications Infrastructure Standards for Data
Centers
9.3 Particular Technical Requirements
This section of Particular Technical Requirements (PTR) specifies the
particular technical and performance requirements for the ELV and
Airport systems to be affected by the fit-out works in the PTB North
Extension Project in MIA.
Master Antenna Television (MATV) System
The system shall be an extension of the existing MATV system
provided in the Passenger Terminal Building (PTB) in the MIA to
provide carries signals for the airport passengers.
The Contractor shall be responsible for design, supply, install of the
MATV equipment with all necessary equipment and accessories.
The Contractor shall coordinate with relevant stakeholders for the
completion of the installation.
All new equipment to be supplied under this Contract shall integrate
into the existing MATV system.
The Contractor shall be responsible for sourcing technical
information including from the relevant existing system
management contracts and Operation & Maintenance manuals to
ascertain the details of the interface requirements.
Any works to be carried out by the Contractor shall not affect the
normal operation and current accepted performance of the systems,
unless with the no objection from the Project Manager. The works
shall also be planned to minimize disturbance to the airport
operations.
In order to maintain continuous services and not to disrupt the
normal operation of the airport terminal, night time working shall be
required for certain works which would cause downtime of the
affected system and affect the normal operation of the system. The
Contractor shall make allowance in this regard in arranging their
work tasks.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
307
In general, the works shall include but not be limited to the supply,
installation, testing and commissioning of the followings:
– Video splitters and distribution taps;
– Optical RF splitters, RF / data optical transceivers;
– MATV (Television) outlets;
– Amplifiers;
– MATV Distribution Frame (MTF);
– The TV sets (including mounting frames and brackets)
and the final drop leads (coaxial) for connecting the MATV
outlets with the TV sets.
– All RF coaxial and fibre distribution cabling among CRs and
from CRs to MTFs / MATV outlets; and
– All RF and optical fibre patch cables, RF cable leads, drop
cables, patch cables and other necessary components and
sundry items required to make the entire MATV system fully
functional and operational.
The MATV system performance shall follow the existing MIA MATV
general requirements and standards.
The Contractor shall provide documentation to the Project Manager
for review without objection. These shall include, but not be limited
to, the followings:
– Single line schematics for the MATV system;
– As Constructed Drawings;
– Wiring diagrams;
– Equipment cabinet layouts;
– Equipment cabinet mounting details; and
– O&M manuals.
The Contractor shall submit to the Project Manager for review
without objection samples and the accompanying manufacturer's
design documentation which shall include but not be limited to:
– Samples of splitters, TV outlets, faceplates, signal cables;
– Samples of equipment, such as amplifiers, RF / data optical
transceivers and cable labels; and
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
308
– Other equipment that shall be installed in public areas or shall
interface directly with architectural, structural or building
services elements of this contract.
The minimum MATV signal level measured from any MATV outlets
in the MATV shall be better than:
– Carrier to Noise Ratio: 46dB or higher;
– Carrier to Cross Modulation: 54dB or higher;
– Carrier to Composite Triple Beat: 54dB or higher;
– TV signal to be at least 65dB ; and
– Tilting among various channels shall not exceed 6dB.
Flight Information Display System (FIDS)
The signal source shall be an extension of the existing system
provided in the Passenger Terminal Building (PTB) in the MIA.
In general, the works shall include but not be limited to the following:
– Provision of all necessary hardware and software as described
for the works. All the proposed equipment shall be compatible
with the existing FIDS installed in the existing PTB;
– The design and configurations of the mounting brackets/poles
and necessary accessories shall be reviewed without objection
by the CAM Project Manager prior to manufacturing and
installation;
– Provision of all necessary local cable containment for the power
and control cables required;
– Prepare complete performance test plan and test schedules for
review without objection by the CAM Project Manager before
testing and commissioning; and
– As the minimum requirements, the FIDS display panel shall be
provided with 46 inch LCD displays in the departure areas; the
FIDS workstations shall be provided at VIP Lounge. The
location of FIDS equipment shall be reviewed without objection
by the CAM Project Manager prior to manufacturing and
installation;
The Contractor shall provide documentation to the Project Manager
for review without objection. These shall include, but not be limited
to, the followings:
– Single line schematics for the FIDS system;
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
309
– As Constructed Drawings;
– Wiring diagrams;
– Equipment cabinet layouts;
– Equipment cabinet mounting details; and
– O&M manuals.
The Contractor shall supply and install the patch cabling for the field
equipment and shall assist the Employer for the overall testing and
commissioning of the systems.
The FIDS system performance and FIDS equipment hardware
requirements shall be compatible to the existing system
performance.
Immigration Desk Equipment and Display System (IDEDS)
The Immigration desk equipment shall be connected to the existing
system provided in the Passenger Terminal Building (PTB) in the
MIA.
In general, the works shall include but not be limited to the following:
a) Provision of all necessary hardware and software as described
for the works. All the proposed equipment shall be equivalent
and compatible with the existing IDEDS installed in the existing
PTB;
b) The Contractor shall coordinate with the fit-out works Contractor
in order to propose installation arrangement for the Immigration
Desk equipment which shall be reviewed without objection by
the CAM Project Manager prior to manufacturing and
installation;
c) Provision of all necessary local cable containment for the power
and control cables required;
d) Prepare complete performance test plan and test schedules for
review without objection by the CAM Project Manager before
testing and commissioning; and
The Contractor shall provide documentation to the Project Manager
for review without objection. These shall include, but not be limited
to, the followings:
– Single line schematics for the IDED equipment;
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
310
– As Constructed Drawings;
– Wiring diagrams;
– Equipment cabinet layouts;
– Equipment cabinet mounting details; and
– O&M manuals.
The Contractor shall supply and install the patch cabling for the field
equipment and shall assist the Employer for the overall testing and
commissioning of the systems.
The system performance and IDED equipment hardware
requirements shall be compatible to the existing system
performance.
Closed Circuit Television (CCTV) Enhancement System
The Contractor shall be responsible for all the works with associate
to the fit-out works including but not limited to the CCTV system
equipment design, supply, installation, modification, relocation,
testing and commissioning, documentation, and the interface co-
ordination with the main existing CCTV system. The works shall
include but not be limited to the provisions of all necessary
hardware and software as described in this PTR for the works.
Such hardware shall include but not be limited to:
a) IP fixed and pan/tilt/zoom cameras, lens, housing and brackets.
The camera shall have at least 720p high definition video
quality for general surveillance and 1080p high definition video
quality for critical areas such as Bosch 50022 series or
equivalent;
b) CCTV POE network switches such as CISCO 2960 series or
equivalent;
c) Equipment enclosures, power supplies, optical transceivers
with fibre cable organizers;
d) Mounting brackets and poles;
e) Surge arresters for all outdoor equipment installations;
f) Fibre patch cord and horizontal fibre cables to and from
cameras to new or existing ELV Room(s) and their termination
and accessories;
g) Coaxial cabling and coaxial patch cords, their termination and
accessories; and
h) All necessary local cable containment for the power and control
cables required connected to the main trunking.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
311
The Contractor shall carry out the design and installation of the
mounting brackets/poles and necessary accessories, which shall be
submitted for review without objection by the CAM Project Manager
prior to manufacturing and installation.
Alternative equipment proposed by the Contractor will be subject to
review without objection by the CAM Project Manager.
The Contractor shall design, install, test and commission all the field
devices as well as the main CCTV existing system.
The Contractor shall provide documentation to the CAM Project
Manager for review without objection. These shall include, but not
be limited to, the following:
a) Detailed, coordinated shop drawings including CCTV System
field equipment installation and detailed connection method and
maintenance access arrangement together with equipment box
locations;
b) Single line schematics for the CCTV system with interface
demarcation with the existing system shall be indicated;
c) camera layout plan including camera location and coverage
drawings, if there are any proposed alternatives;
d) wiring diagrams;
e) equipment cabinet layouts;
f) equipment cabinet mounting details;
g) all types of camera and monitor installation including masts,
winches and mounting details;
h) Testing and commissioning records; and
i) as-constructed drawings and O&M Manual.
Private Automated Branch Exchange (PABX) Enhancement
System
All telephone system services for airport staff and public use at
various locations in the Extension Building, such as gate desk
phone and help phone, shall be served by existing PABX system in
PTB.
The Contractor shall be responsible for all the works with associate
to the fit-out works including but not limited design, supply,
installation, modification, relocation, testing and commissioning,
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
312
documentation, and the interface co-ordination with the existing
PABX system. The works shall include but not be limited to the
provisions of all necessary hardware and software as described in
this PTR for the works. Such hardware shall include but not be
limited to:
a) Provision of analogue telephone set which is equivalent to
Avaya series;
b) Provision of 8-pairs telephone cables with the local cable
containment and appropriate type of phone jack for the end
devices;
c) Coordinate with other services for the mounting design /
claddings of the telephone at each location; and coordinate with
the other parties on interfaces issues;
d) Prepare a complete performance test plan and test schedules
for review without objection by the CAM Project Manager before
testing and commissioning; and
e) Prepare documentation such as shop drawings, installation
drawings, as-built drawings, cable termination schedule, test
procedures/specifications and operation and maintenance
manuals.
The system shall be an extension of the existing Avaya system
installed in the Passenger Terminal Building (PTB) in the MIA.
Each telephone point shall be equipped with one analogue
telephone set. Locations and quantities of telephone points shall be
liaised with relevant stakeholders.
All cables shall be PVC insulated, and shall be housed in
galvanized-screwed or PVC conduit and/or galvanized trunking,
unless higher quality trunking is required by any applicable
regulation.
The Contractor shall terminate all telephone cables at the existing
IDF in the PTB Extension, whereas PABX System configuration and
programming and cable jumpering shall be provided by others.
Access Control System (ACS)
The Contractor shall be responsible for all the works with associate
to the fit-out works including but not limited to the ACS system
equipment design, supply, installation, modification, relocation,
testing and commissioning, documentation, and the interface co-
ordination with the main existing ACS system. The works shall
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
313
include but not be limited to the provisions of all necessary
hardware and software as described in this PTR for the works.
Such hardware shall include but not be limited to:
a) Door controller with 2 hours UPS backup facilities and other
access control devices such as card readers, integrated card
reader with PIN pad, door release button, biased magnetic
sensors, breakglasses, and the like, including all
interconnections, field equipment cabling, and cabling back to
the associated Controller(s) (i.e. Honeywell PW-Series) located
at new IDF room in PTB Extension.
b) Provision of all containment as required for the connection to
the final field equipment devices. This shall include but not be
limited to cable trunking, trays, cable ladders, concealed
conduits, back boxes, termination boxes, flexible conduits, etc.
All such last-run connections in conduits shall be concealed
unless otherwise specified.
c) Provision for interface with the fire services system by means of
the electromagnetic (EM) door lock. The Contractor shall study
the existing arrangement and implement the same arrangement
at the new EM door locks into the new controlled doors for the
fit out works.
All the proposed ACS equipment shall be compatible with the
existing Access Control System (Honeywell PW series or equivalent)
in MIA.
The Contractor shall provide documentation to the CAM Project
Manager for review without objection. These shall include, but not
be limited to, the following:
a) detailed, coordinated shop drawings including ACS System field
equipment installation, relocation, detailed connection method,
maintenance access arrangement together with equipment box
locations;
b) single line schematics for the ACS system;
c) access control type connection and installation diagrams;
d) wiring diagrams;
e) equipment cabinet layouts;
f) equipment cabinet mounting details;
g) O&M manuals; and
h) as-constructed Record Drawings.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
314
Wireless Network (WLAN) System
The system is a flexible data communications system implemented
as an extension to the existing airport wide Wireless LAN system.
Using radio frequency (RF) technology, the system transmits and
receives data over the air, minimizing the need for wired
connections.
The system standard to be used shall be based on IEEE 802.11b
(Wi-Fi) standard and also IEEE 802.11a/g. The existing Wireless
LAN installed in the airport is based on IEEE 802.11b standard but
shall also support the IEEE 802.11g standard.
The Contractor shall be responsible for all the works with associate
to the fit-out works including but not limited to the Wireless Lan
Access Points equipment design, supply, installation, modification,
relocation, testing and commissioning, documentation, and the
interface co-ordination with the existing WLAN system. The works
shall include but not be limited to the provisions of all necessary
hardware and software as described in this PTR for the works.
Such hardware shall include but not be limited to:
a) The Contractor shall review the wireless LAN coverage base on
the fit-out work arrangement, and shall allow provisions of
Access Points with wireless controllers to the blind spot
locations;
b) Coordinate with other services for the mounting design /
ceilings of the Access Points location; and coordinate with the
other parties on interfaces issues;
c) The Contractor shall provide all necessary horizontal cabling
from the new and existing ELV rooms for all the Access Points
and a POE Network Switch (i.e CISCO 2960 or equivalent)
connection. The Contractor shall coordinate with the existing
system for system configuration and arrange system testing
and commissioning.
d) Provision of all necessary hardware and software in order to
complete the system;
e) Design and develop equipment mounting brackets/poles and
necessary accessories, which shall be subject to review without
objection by the CAM Project Manager prior to manufacturing
and installation;
f) Provision of cables with the minor cable containment for the
end devices;
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
315
g) Prepare a complete performance test plan and test schedules
for review without objection by the CAM Project Manager
before testing and commissioning; and
h) Prepare documentation such as shop drawings, installation
drawings, as-built drawings, test procedures/specifications and
operation and maintenance manuals.
The quantities and locations of Access Points shall be restricted by
the available ports at POE edge switches and licenses on the
wireless controllers. The Contractor shall evaluate the coverage
based on the particular equipment to be provided, and develop the
layout in details with coordination among other related services
including architectural and electrical. The Contractor shall submit,
for review without objection by the CAM Project Manager, the
equipment details and locations to demonstrate the required
coverage and performance can be met before implementation.
The Contractor shall undertake detailed site survey and signal
strength measurements for the review without objection by the CAM
Project Manager, to confirm the final quantities and locations of the
Access Points to achieve or ensure acceptable signal coverage in
the areas required.
Radio Communication System
The Contractor shall be responsible for all the works with associate
to the fit-out works including but not limited to the Radio Antenna
system equipment design, supply, installation, modification,
relocation, testing and commissioning, documentation, and the
interface co-ordination with the main existing Radio Communication
system. The works shall include but not be limited to the provisions
of all necessary hardware and software as described in this PTR for
the works. Such hardware shall include but not be limited to:
a) Provision of all necessary hardware as described for the fit-out
works. The Contractor shall review the radio coverage based on
the fit-out work arrangement to design for the system
enhancement for the radio antenna coverage;
b) All the proposed equipment shall be compatible with the
existing radio communication system (Motorola TDMA Trunk
system) installed in PTB;
c) The design and configurations of the mounting brackets/poles
and necessary accessories shall be reviewed without objection
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
316
by the CAM Project Manager prior to manufacturing and
installation; and
d) Provision of all necessary local cable containment for the power
and control cables with all cables and associated cabling /
termination as required.
The Contractor shall provide the documentation including
equipment submission (with equipment specification), signal
strength calculation (i.e. link budget calculation), design / calculation
on coverage prediction / analysis, antenna mounting design
drawings, installation drawings and etc. to obtain review without
objection by the CAM Project Manager.
e) The Contractor shall base on the existing signal source to
design and develop the antenna network in order to strengthen
antenna signal to other blind spot areas in the fit-out locations.
f) The modification works on the existing system shall be carried
out by Others.
Voice and Data Cabling (VDC) System
The voice and data cabling infrastructure design in the Extension
Project shall be modelled on the existing voice and data cabling
arrangement in MIA.
All outdoor cables for both copper and fibre cables, e.g. passing
through external ducts, if any, shall be armour-type cables suitable
for external outdoor use. No direct buried cable installation shall be
allowed.
All voice and data cabling outlets, fibre and copper termination
frames, media converters, junction boxes, termination boxes,
faceplates, etc. which are installed in exposed outdoor environment
shall be provided with suitable weather-proof housing by the
Contractor with a minimum standard of IP65 rating.
The Contractor shall develop, construct, programme, supply, deliver,
install, set up, test and commission the system works as hereunder
described, as well as any works not specifically mentioned but
required to complete the works.
The Contractor shall construct extra new IDF in the new ELV
room(s) which would take care all various signalling service and
networking provision under the fit-out provisions.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
317
The design and implementation of new IDF, shall follow the local
code, international standard and industry requirement such as
ISO/IEC 11801, ISO/IEC 24764, TIA-942, etc. Where there is a
difference or conflict between such international standard and in the
Macau local codes, Macau local codes shall prevail.
The structure cabling system in the new PTB extension shall not be
separated from the existing structure cabling system. The design
shall connect or integrate the new system into the existing system
to form a complete System in order to allow a smooth and effective
operation in the PTB including its new extension, or even to other
buildings within MIA.
The scope of works of the Contract includes the following as a
minimum:
a) All cabling for airport systems described in this PTR including
all fibre and copper cables carrying voice, data or multimedia
traffic;
b) Supply, installation, diversion, testing and commissioning of
cabling components including but not be limited to the following
components as a minimum:
c) Multipair / UTP / STP copper cables;
d) Single mode / Multimode fibre cables;
e) Patch panels and patch cords;
f) Termination frames including mounting frames, termination
blocks and cable management modules for the termination
frames;
g) Data / voice / fibre socket outlets and faceplates;
h) Equipment cabinets in new IDF Room and/or closets
i) Equipment cabinet accessories such as cable management
rings, channels, wiring managers, in-cabinet containments,
ventilation fans, equipment shelves, raised floor tile grommets,
floor-cut-outs, etc;
j) All copper, coaxial and fibre cable connectors;
k) Termination boxes and back boxes;
l) Cross connecting cables for the jumpering of voice and data
connections across frame verticals;
m) Cable labelling, numbering and marker for all cables, patch
panels, equipment racks, frames, outlets, patch cords, etc; in
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
318
particular, all the external cables shall be labelled properly in
each drawpit at cable entry and exit points;
n) Final connections (jumpering / patching) from the new VDC
infrastructure to the existing infrastructure to connect necessary
circuits;
o) All other relevant accessories and sundry items required for the
complete operation of the VDC system; and
g) All cabling provisions shall be low smoke and fume (LSF/LSOH)
type and shall apply to optic fibre and Cat 5e or Cat 6 UTP
cables.
h) Voice and Data Outlets (VDO) and Distribution Frames in all
locations shall be marked on the Contractor’s Design Drawings.
i) Allocation and recording of the cable utilization records and
coordination of the utilization cable space and positioning in
risers, cable trays, cable ducts, etc, to ensure efficient and neat
utilization of commonly used cable routes. This shall include
but not be limited to BMS, ACS, CCTV, WLAN, FIDS, PA,
MATV, PABX, etc;
j) Installation of associated necessary items such as secondary
cable containment such as cable tray, conduit, trunking and
other such items will be required to connect to the backbone
tray and trunking scheme;
k) Contractor's Drawings (shop drawings, design calculations, etc);
l) As-built Record Drawings with the indication of cable length and
cable paths from the VDOs to the distribution frame;
m) Testing and commissioning of all system components; and
n) Operational and Maintenance Manual
Public Address (PA) System
Any works to be carried out by the Contractor shall not affect the
normal operation and current accepted performance of the system.
The works shall also be planned to minimize disturbance to the
airport operations, night time working may be required. The
Contractor shall make allowance in this regard in arranging their
work tasks.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
319
The PA system provided at the PTB Extension shall be an
extension of the existing Bosch Digital PA System and be fully
operated within the PTB Extension both in system control and
management.
The Contractor shall include the engineering, design, development,
construction, supply, delivery, installation, fabrication, assembly, ,
installation set up, testing and commissioning, documentation,
training and warranty of the PA System.
Should there be any modification, reconfiguration, addition of Public
Address devices, the overall system performance of the existing PA
system shall not be degraded in any form and be carried out by
others
The Contractor shall obtain sufficient information from the supplier
or maintenance contractor or even site inspection of the existing PA
system to formulate the design criteria and concept and to ensure a
smooth integration/changeover to the extended PA system in PTB
Extension without service interruption.
The Contractor shall base on their design to install the PA System
equipment at the new IDA Room(s) and provide associated cabling
works for the field PA Speakers. Suitable quantity of PA system
equipment cabinet(s) shall be supplied and installed by the
Contractor.
In general, the works shall include but not be limited to the following:
a) Provide all system engineering and design necessary to
develop the complete systems such as system schematics,
hardware drawings, system diagrams, schedules and lists;
b) Provision of all necessary hardware
c) Provide design, supply, install and configuration of the
mounting brackets/poles and necessary accessories, which
shall be subject to review without objection by the CAM
Project Manager prior to manufacturing and installation;
d) Provision of all necessary local cable containment for the
power and control cables required;
e) Submit a detailed changeover plan with necessary
fallback/contingency plans for review without objection by
CAM Project Manager.
f) The modification works on existing system shall be carried
out by others.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
320
Building Management System (BMS)
The Contractor shall supply, install, configure, test and
commissioning the BMS installation, including provision of all
necessary hardware, software and associate software license,
testing at the manufacturer's works, delivery to Site, interfacing
work for other services, certificates and guarantees.
Should there be any modification, reconfiguration, addition of BMS
devices, the overall system performance in the existing BMS
system shall not be degraded in any form or causing implication to
the operations of the existing BMS system;
The Contractor shall include and provide all interface components
for BMS, including dry contacts, relay, high level interface, cables,
trunking, conduits and local I/O panel etc. to interface with the
Building Services (BS) / Electrical & Mechanical (E&M) equipment;
The Contractor shall be responsible for the completion of Building
Management System (BMS) as specified including but not be
limited to the following:
a) Supply and install the complete communication networks which
consist but not be limited to optical fibre cables, Cat 5e copper
cables, network switches, optical fibre transceiver and receiver
and routers. The BMS shall be interfaced to the existing BMS
system. The Contractor shall provide all the hardware and
software for transmitting and receiving BMS signals to and from
the PTB.
b) Supply and install of all necessary cables and cable
containment facilities (trunkings, conduits etc.) for the complete
system installation.
c) Supply and install all necessary field control cabling and
containment systems for cables run between the I/O panels and
monitoring/controlling devices;
d) Preparation of all colour graphical displays including system
schematic diagrams and all layout plans for the system from the
highest level (Site overview) to the lowest level (field
equipment). If the PTB extension layout shall be displayed at
the existing BMS Workstation, the graphical configuration works
shall be carried out by others.
e) Perform a full testing and commissioning of the complete
system.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
321
f) Liaison and co-ordination with all interfacing disciplines for
testing and commissioning of the complete BMS system and
connected systems for building services and electrical &
mechanical plants and equipment installed in the PTB
extension generally.
g) Provision of full sets of operation and maintenance manuals for
all the equipment including hardware, software with licence and
the circuit diagrams, such that the end users shall be able to
modify the system to their needs without interaction to the
manufacture or vendor.
h) Provision of full training with not less than three sessions and at
minimum ten staff per session to the Employer’s staff for proper
operation and maintenance including circuit diagram description,
for the operators to self repair, maintain and trouble shoot the
system without the assistance from the Contractor. The training
shall enable the operators to achieve self-development and
modification of the entire BMS systems without consulting the
Contractor.
i) The Contractor shall be responsible for sourcing technical
information including from the relevant existing system
management contracts and Operation & Maintenance manuals
to ascertain the details of the interface requirements, system
operation procedure and method.
j) Any works to be carried out by the Contractor shall not affect
the normal operation and current accepted performance of the
systems. The works shall also be planned to minimise
disturbance to the airport operations.
k) The Contractor is required to develop a full point schedule
listing the exact quantities of devices for each type of field
devices requested in the BMS Point Schedules according to the
respective E&M System if necessary. Such schedule shall
include the location of the I/O panel, and the field equipment
under the monitoring and control by the I/O PLC and I/O
module. The Contractor shall be required to design, supply and
install the BMS I/O panels, with sufficient quantities to control
and monitor all the field equipment type required in the BMS
Point Schedules;
The following typical point schedule is for reference:
System Signal Action
Escalator Emergency Stop Alarm
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
322
Fault Stop Alarm
Down Status
On/Off Status
Up Status
HVAC Temperature Measure
Exhaust Fan Control –
Start/Stop
Command
Exhaust Fan - Running Status
Jet Fan Control –
Start/Stop
Command
Jet Fan - Running Status
AC Unit - Running Status
AC Unit Common Alarm Status
ELV Call Circuit - Fail Alarm
Fire Alarm
Power Failure Alarm
Limit Exceeded Alarm
Passenger Emergency Alarm
Up Status
Down Status
Emergency Safety Circuit Alarm
Display Segment Status
Electrical Dist. Feeder CB – Open/Close Status
Incoming CB –
Open/Close
Status
Incoming HV CB –
Open/Close
Status
TX high Temp Trip Alarm
Max Demand Metering Metering
Lighting
Control
Circuit – ON/Off Status
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
323
Circuit - Control Command
Toilet Distress Alarm – On/Off Alarm
l) The Contractor shall submit for review without objection by the
CAM Project Manager all necessary documents, design
development, testing & commissioning results.
m) All modification and re-configuration works for the existing
Honeywell BMS shall be carried out by others.
Option A - Advance Visual Docking Guidance System (AVDGS)
Provision
The following equipment shall be designed, supplied, installed and
commissioned by the Contractor for the new parking stand with all
associated mountings, housings and necessary accessories:
a) AVDGS display unit (equipped with 3D-scanner and AVDGS
controllers /processors);
b) AVDGS Operator Panel with emergency stop button;
c) Optical transceiver and receiver; and
d) Associated transmission equipment and data/communications
cablings with secondary cable containment; and
e) Mounting and with all necessary fixing and housing for the
equipment.
The Contractor shall take full responsibility for the design,
development, manufacture, configuration, installation and testing &
commissioning of the system.
The AVDGS shall be building mounted which shall follow from the
same arrangement as the existing parking stands.
All new equipment to be supplied under this Contract shall integrate
into the existing AVDGS system.
The AVDGS system shall be required to interface with other
systems. The Contractor shall coordinate with other system
provisions to ensure the successful completion of the interfaces as
required.
Due to the specialist nature of the system, any integration works
shall be planned and coordinated with the Employer and Other
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
324
Contractors and will be submitted to the CAM Project Manager for
review without objection before the works are carried out.
The Contractor shall be responsible for sourcing technical
information including from the relevant existing system
management contracts and Operation & Maintenance manuals to
ascertain the details of the interface requirements.
In order to maintain continuous services and not to disrupt the
normal operation of the airport terminal, night time working shall be
required for certain works which would cause downtime of the
affected system and affect the normal operation of the system. The
Contractor shall make allowance in this regard in arranging their
work tasks.
The Contractor shall provide documentation to the Project Manager
for review without objection. These shall include, but not be limited
to, the followings:
– Single line schematics for the AVDGS system;
– As Constructed Drawings;
– Wiring diagrams;
– Equipment cabinet layouts;
– Equipment cabinet mounting details; and
– O&M manuals.
9.4 Testing and Commissioning
The Contractor shall refer to all related international standards, code of
practices and guidelines for the inspection, testing and commissioning
of the aforementioned systems. The Contractor shall take into account
of, but not limited to, the following:
Systems requirements
a) All testing and commissioning shall be pre-planned and
scheduled in order that it is fully coordinated with other relevant
services and shall be carried out in a safe and efficient manner
with a minimum of inconvenience to all concerned.
b) The installation shall be tested progressively as construction
progresses and then finally on completion to ensure that the
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
325
installation complies with the requirements and operates
correctly under normal, emergency and fault conditions.
Control, protection and operative devices shall be checked for
correct adjustment and rating. Records of all testing shall be
kept and reviewed without objection by the CAM Project
Manager.
c) All equipment or materials found to be faulty during testing shall
either be replaced or repaired free of charge.
For cable testing, the Contractor shall:
a) Test all point to point wiring, where applicable.
b) Provide documentary evidence of all cable test results of point
to point wiring installation.
c) Report the extent of any failures identified during testing which
may affect the installation programme.
d) Correct any wiring faults discovered during the testing and
commissioning at no additional cost to the Contract.
The Contractor shall also note:
a) The installation shall be thoroughly tested by the Contractor so
as to ensure every point and item of plant is being controlled
and/or monitored correctly.
b) The Contractor shall carry out all of the tests and any other
tests required by the CAM Project Manager to demonstrate that
the complete system is fully operational and satisfactory, and in
accordance with the requirements of the PTS. The Contractor
shall provide all equipment and personnel required for the
testing and commissioning.
c) In the event of any test indicating failure to comply, that test and
those proceeding tests, the results of which may have been
influenced by the fault indicated, shall be repeated after the
fault has been rectified.
d) If failure to provide the required and reliable coverage for the
Extension Building areas, the Contractor shall be responsible
for modifying the proposed design to achieve the required
standard and specification at no additional cost.
e) It is a requirement that the system is tested and commissioned
by personnel who have gained an intimate understanding of the
project throughout its design stages. These personnel must
also have had at least five years of experience in the related
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
326
field. Should any commissioning personnel not meet these
requirements the Contractor shall apply and shall obtain review
without objection by the CAM Project Manager prior to allowing
the said commissioning persons on site.
f) The Contractor shall submit the testing and commissioning
details for the review without objection by the CAM Project
Manager before implementation.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
327
10.1 Requirements
The LOD 300 definition used in the the fit-out BIM model will be in line
with the industry leading standard “Level of Development Specification
© 2015 by BIMForum“.
The “Level of Development Specification © 2015 by BIMForum“ could
be downloaded from:
http://bimforum.org/wp-content/uploads/2015/11/Files-1.zip
10.2 Software Requirements
The Contractor shall use Autodesk Revit 2015 to create the fit-out BIM
model.
10.3 Deliverable Requirements
The Contractor shall submit the native Autodesk Revit 2015 file for
CAM Project Manager.
The Design model is to be submitted with the detailed design
deliverable drawings.
The as-built model is to be submitted with the as-built drawings.
10 BIM Model Files
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
328
11.1 Scope of Work
The Contractor shall be responsible for the civil works in the area
surrounding the Passenger Terminal Building extension, which shall
provide a paved interface between the Terminal Building extension and
the existing roads and car parks. The scope of the work shall include
design, construction, testing and commissioning of the following items:
Bus Staging Area layout and configuration;
Site clearance, and utility diversions if required;
Bus Staging Area pavement;
Footpath island pavement and pedestrian canopy;
Surface water drainage;
Perimeter fencing.
The Contractor shall also be responsible for:
Topographic, geotechnical and utility surveys, prior to undertaking
the works.
The Contractor shall note that the site area is currently classified as
“airside” but may temporarily revert to “landside” as part of the
commissioning of the Contractor’s works.
11.2 Design Standards
The following design standards shall apply:
Highway and pavement design: Macau DSAT Highways standards;
Road markings: Macau DSAT Highways standards;
Paving Blocks: BS 6717 Part 1 1986;
Hot-Rolled Asphalt: BS EN 13108-4 and BS 594987;
Surface water drainage: Serviço de Abastecimento de Á guas de
Macau (SAAM) – Supply Rules and Relevant Water Supply
Ordinance;
Manhole covers: BS EN 124:1994;
Pedestrian Canopy: refer to Structural section;
Chain-link fences: BS 1722 Part 1; BS 4848 Parts 2 and 4.
The Contractor shall ensure all working methods and material
selections minimise the risk of debris occurring in the airside areas,
which may later lead to damage to airside equipment or aircraft (known
11 Specifications and Standards for Civil Works
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
329
as “Foreign Object Damage” or “FOD”), e.g. the risk of spalling concrete
shall be minimised by sealing joints and chamfering edges of exposed
concrete.
11.3 Particular Technical Requirements
11.3.1 Surveys and Inspections
The Contractor shall carry out all surveys deemed necessary to
understand the existing constraints, facilities etc. and to minimise
disturbance of existing facilities during construction of the works. The
surveys shall include:
topographic survey;
below-ground utility survey, and
geotechnical investigation to determine the subgrade type and
subgrade bearing capacity for pavement design purposes.
Prior to the commencement of site clearance and demolition, and after
completion, the Contractor shall undertake joint inspections with the
CAM Project Manager of all existing structures to be retained within the
Site and produce a Condition Survey Report submitted to the CAM
Project Manager for review. Any damage noted to the structures during
the second inspection shall be made good by the Contractor to the
satisfaction of the Project Manager. Photographic records, taken by the
Contractor and reviewed without objection by the Project Manager,
shall be kept as part of the joint inspection.
11.3.2 Bus Staging Area Layout and Configuration
The Contractor shall design the Bus Staging Area to accommodate 8nr
bus parking spaces adjacent to the terminal building extension, and 4nr
remote bus parking spaces.
The design passenger bus shall be the Cobus 3000, or as otherwise
agreed with the CAM Project Manager.
The layout shall take into account the safe manoeuvring of the buses
and the swept path of the buses during their manoeuvring in and out of
the parking spaces. The Contractor shall use swept path analysis
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
330
software such as AutoTrack for this purpose and present the swept
path analysis drawing to the CAM Project Manager for review.
The Contractor shall design the road layout and road markings in
accordance with Macau DSAT highway standards. The markings
design shall take into account the existing road markings, traffic
direction, traffic speeds, sightlines, proposed bus manoeuvring and
access into the loading dock (currently being constructed by others).
The proposed road markings layout design shall be agreed with the
CAM Project Manager before implementation.
11.3.3 Site Clearance and Utilities
Following the topographic and below-ground utility survey, the
Contractor shall propose the facilities to be removed, diverted or
retained and agree them with the CAM Project Manager prior to
commencing the site clearance works. As a minimum, the Contractor
shall break out and remove existing pavement/hard-standing/spoil
within the footprint of the new pavement area, and carry out earthworks
to excavate and remove existing fill material, to facilitate the pavement
construction. The Contractor shall note that the existing concrete
pavement in the remote bus staging area is a temporary pavement and
shall be removed.
For any live utilities crossing the site and affected by the construction
works, the Contractor shall design and construct temporary or
permanent protection, or diversions to their routing. Any phasing for
this work shall be agreed with the CAM Project Manager before
implementation. Any unchartered utilities shall be recorded and the
scope of protection or diversion work shall be subject to agreement with
the CAM Project Manager.
Any existing chambers, or any new chambers required as part of a
proposed diversion of existing utilities, shall have a cover and frame
specified as E600 loading category.
11.3.4 Bus Staging Area Pavement
The Contractor shall design and construct highway pavement to serve
the Bus Staging Area. The pavement system shall comprise
interlocking precast concrete paving blocks laid on bedding sand and a
lean concrete base, or other material system (e.g. asphalt pavement)
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
331
proposed by the Contractor and agreed with the CAM Project Manager.
The blocks shall be suitable for vehicle loading and joints between
paving blocks shall be filled with a joint sealing compound.
The pavement design method shall follow an appropriate Macau
highways standard design method proposed by the Contractor and
agreed with the CAM Project Manager.
The pavement design life shall be 40 years (or 20 years if an asphalt
pavement system is used) and shall cater for an appropriate number of
standard axle passes over the design life, as determined by the
Contractor and agreed with the CAM Project Manager. The subgrade
strength shall be determined by the Contractor from the geotechnical
investigation. For asphalt pavement (if used), the Contractor shall
propose the asphalt mix properties and the mix design.
Earthworks shall be carried out as follows prior to the pavement works.
Topsoil, grass, and other organic matter shall be removed. Soft spots,
boulders and other materials which are unsuitable or unstable shall be
removed. The Contractor shall prepare the formation by compacting
suitable fill material in layers to a stable condition as soon as
practicable after deposition, to achieve the required in-situ density as
specified in the selected design method.
Prior to commencement of block paving construction, the Contractor
shall construct a trial area of at least 500m². The trial will be used to
determine the adequacy of the Contractor's equipment, placement
methods and ability to meet the specified tolerances
The pavement grading shall be designed to effectively drain, with
minimum gradient of 0.5% and maximum gradient of 5% falling towards
new or existing surface water drainage gullies or channels. There shall
be no flat spots and no ponding water. The pavement levels shall
match surrounding kerb levels and pavement levels at the interface
points and shall permit a smooth transition to existing pavement
gradients, i.e. no abrupt change of gradient and no level difference.
Where the pavement will interface with the footpath currently being
constructed by others, the pavement shall tie-in to the underside of kerb
level along the new footpath, allowing a kerb height of 125mm.
The Contractor shall provide new road markings for the bus parking
spaces and other required markings using highways-grade
thermoplastic paint proposed by the Contractor and agreed by the CAM
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
332
Project Manager. Marking details such as colour, setting-out etc. shall
follow Macau DSAT highway standards.
11.3.5 Footpath Island and Pedestrian Canopy
The Contractor shall design and construct a footpath island as an
extension of the footpath currently being built by others. The paving
material and kerb heights shall match the footpath currently being built
by others.
The Contractor shall design and construct a pedestrian canopy as a
free-standing structure but continuing the alignment of the canopy
currently being built by others. The visual appearance including
structural form, material selection, colour, steel member sizes etc. shall
match the canopy currently being built by others. The canopy shall be
sufficient to protect pedestrians from rain but shall not obstruct the
sightlines for vehicles using the road or bus staging area, and shall be
high enough not to strike buses or other road vehicles.
The canopy shall be drained using downpipes discharging to the
surface water drainage system.
11.3.6 Surface Water Drainage
The Contractor shall survey the existing surface water drainage network
and assess its condition and its capacity for accommodating the
discharge from the new bus staging area.
The Contractor shall design surface water drainage to serve the new
catchment. Such new drainage shall comprise gullies, drainage
channels, pipes and the like, to achieve the following criteria:
No ponding after a 100 year return period storm;
Self-cleansing velocity of 1m/s.
The Contractor shall be responsible for temporary drainage during the
construction works and shall agree the temporary drainage scheme
with the CAM Project Manager prior to implementation.
11.3.7 Perimeter Fencing
The Contractor shall provide an airside security fence along the
perimeter of the bus staging area. The design shall match the existing
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
333
fence details and the new fence shall integrate seamlessly with the
existing fence.
11.4 Testing and Commissioning
11.4.1 General
This document is intended to be a guideline for the required testing and
commissioning for the civil works. The Contractor shall be
responsible for preparing and submitting a fully detailed testing and
commissioning (T&C) specification for the works, as part of his quality
plan which shall be submitted to the CAM Project Manager for review.
11.4.2 Pavement Formation
The following tests shall be included in the T&C Plan for earthworks:
Moisture content;
Particle Size Distribution;
Maximum Dry Density and In-Situ Dry Density to determine Relative
Compaction;
Bearing strength tests e.g. CBR value as required by the selected
design method.
11.4.3 Pavement Works
All pavement materials shall be subject to testing of their material
properties before being selected for use and at regular intervals during
the construction.
Level survey of the finished course shall be performed by the
Contractor at all changes of gradient and on a 5m grid. Finished
pavement levels shall be within a tolerance of +/-6mm from their design
level.
The finished surface course shall be tested for surface regularity on a
grid layout agreed with the CAM Project Manager using a rolling
straightedge. The finished surface of each course shall not vary in
regularity by more than 4mm per 3m.
All paving blocks shall be visually inspected to ensure that no joint
spacing or differences in level between adjacent paving blocks exceed
the absolute maximum specified.
For asphalt paving materials (if used), the mixture shall be tested per
batch for particle size distribution, bitumen content and specific gravity.
After placement, cores shall be extracted from the asphalt pavement
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
334
and tested for compaction, layer thickness, air voids content and the
like, as required in accordance with the selected pavement design
method and technical specification. Granular sub-base courses shall
be tested for in-situ density (relative compaction).
11.4.4 Drainage Works
The cleanliness, bore, linearity and joints of pipelines of 450 mm
diameter or less shall be checked by pulling a mandrel through the
completed pipeline, or parts of the pipeline if permitted by the CAM
Project Manager, after cleaning. The mandrel shall be 750 mm long and
12 mm less in diameter than the nominal diameter of the pipe.
Batches of pipes and fittings shall be tested for their material properties.
Gravity pipelines shall be tested by water test or air test after the pipes
have been jointed and the bedding has been placed and immediately
before haunch or surround is placed or fill material is deposited; and
after haunch and surround has been placed and fill material has been
deposited and compacted.
11.4.5 Fencing Works
The commissioning shall include security matters related to converting
the landside site to “airside”. The commissioning of the perimeter
fencing will not be deemed to be complete until the site has been
restored to “airside” category. The Contractor shall phase the works in
a manner agreed with the CAM Project Manager and other related
stakeholders to ensure the site complies with all aviation security
aspects at all times.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
335
12.1 Introduction
The Contractor shall build one (1) set of new Remote Boarding Gate
at new loading bridge for facilitating the normal boarding operation and
avoid excessive concentration of passengers at north remote
boarding gates in Departure Airside level. The Remote Boarding
Gates shall be connected to the existing Passenger Boarding Bridges.
The Contractor shall provide all required professional provisions to the
design works, site survey, off-site fabrication and site
construction/installation of the aforesaid 1 set of Remote Boarding
Gate and its interfacing.
The Contractor shall provide for CAM Project Manager’s approval the
preliminary design and final design reports that include the
structural/foundation design, design calculations, all plans, sections,
elevations, interior & exterior finishing schedule, and related E&M
system, etc. for construction. The contractor shall also consider the
theme of “Cultural Airport” and other aviation elements, reflecting
the current architectural themes inside the terminal building and
aviation elements. Moreover, all design work shall comply with the
legislation and technical regulations of Macau SAR.
Design reports must be signed by Macau registered Engineer and
architectural drawings must be signed by Macau Registered
Architect, complying with current ICAO/IATA standards if necessary.
Three dimensional (3D) views showing the overall effect to the adjacent
MIA facilities/buildings shall be required. Declaration letters of Design
Engineer(s) and Architect(s) registered at DSSOPT, namely
affidavit, must be provided to prove relevant design qualifications in civil,
electrical, HVAC, fire service design, etc. All designs and drawings
must be signed by aforesaid engineer(s) and architect
The Contractor shall perform the physical works based on the approved
final design including but not limited to the following items for
completing the Remote Boarding Gates;
Civil, Structure and Builder’s Works
- All necessary removal/ demolition/ diversion works;
- Ground works;
12 Remote Boarding Gate (Optional)
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
336
- Foundation works;
- Roofing system and waterproofing system;
- External works (e.g. pavement, service utilities, etc.);
Electrical & Mechanical Systems
- Electrical system;
- Communication system;
- HVAC system;
- Fire services system and Drainage system;
- Necessary electrical & mechanical works;
Specialist systems
- Signage system;
- Public Address system;
- CCTV system.
Declaration letters of Instruction Engineer(s) registered in DSSOPT as
instruction category, namely affidavit, must be provided to prove
relevant instructing qualifications in the construction works.
See Architectural Appendix 11 for reference on image.
12.2 Technical Requirement
- These remote boarding gates will be constructed at the
emergency stairs connecting the existing boarding bridges at
aircraft parking stands . The gross floor area shall be ascertained and
specified by the bidder after site investigation. The construction works
are basically to build a cover on the emergency stairs of the existing
boarding bridges so that they can be used for remote boarding
purposes. Therefore, it is suggested to use a metallic structure and
glass envelope similar to the existing boarding bridges and MIA
Passenger Terminal Building Facades;
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
337
- The Contractor shall measure the existing emergency staircase on
site and calculate the exact dimension of cover during the design phase;
- Stairs finishing material should be the same as that of boarding
bridges floor;
- The Contractor shall take the responsibility to review the original
structure design calculation of exiting boarding bridges emergency
stairs and must reinforce the structure if it is required after checking.
- The covered remote gate should have one door at the access to the
fixed boarding bridge. The remote gate should have two doors at the
bottom: One for passenger boarding to Co-Bus and one for emergency
exit;
- A parking area for Co-bus should be considered;
- Air-conditioning and Electrical system shall be installed inside
the gate cover accordingly;
- The Contractor shall optimize the land usage to enable passengers
walking in a smooth flow and undisrupted manner;
- The staircase should have some windows for natural lighting;
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
338
13.1 Introduction
The Contractor is responsible to supply, furnish all labour, equipment
and film materials to perform the work necessary for completing the
project stipulations. The Contractor shall take site visit for actual
measurement and get familiar with the project premises and analyze
the effect on existing conditions during their service period which will
affect ongoing execution of work. The Contractor shall ensure no
misunderstanding arises as to the character or as to the extent of the
work to be done, and shall advise and acquaint themselves with all
precautions to be taken in order to avoid injury to person or property of
another. No additional compensation will be granted to the Contractor
because of any unusual difficulties or CAM Project Manager’s special
requests that may be encountered in the execution of any portion of the
work. The scope of works under this Contract shall include but not
limited to the following:
See Architectural Appendix 6 for reference on image and location.
The Contractor shall be responsible to fabricate the approved
decorative film as specified in the B.Q. and to place the film on Upper
Part of glass façade in the North Extension Airside Departure Hall.
Details of the design theme shall be provided after contract award.
A mock-up on selected section is required for approval prior to
implementation of entire replacement works.
13.2 Work requirements
-The decorative (solar) film shall be 3M brand or equivalent products as
specified in the Bill of Quantities. The bidder must provide technical
submission and project catalogue in supporting the quality of the
proposed products during the tendering stage.
-In general, the applied decorative film shall be suitable for application
to interior glass, exterior glass and panel surface and perfect in
decorative and architectural applications. The proposed decorative film
or decorative vinyl should be of high quality and best fit for the localized
application and design graphics.
13 Decorative Solar Film Replacement on Upper Part of Glass Façade in the Airside Departure Hall
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
339
-The film material should be excellent in abrasion and chemical
resistance, dimensionally stable, and should repel stain coatings and be
non-flammable.
-For the filming on the terminal façade, additional features shall be
possessed, namely resistance against prolonged sunlight exposure and
temperature control.
-The adhesive method and workmanship should follow the industry
standard and supplier’s recommendations.
-The applied solar film should block 99% UV rays, reduce heat (at least
40%) and glare, possess low-emissivity for improving the insulation
properties.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
340
14.1 Requirements
The Contractor shall in accordance with any instruction issued during
the Defects Liability Period:
a) Investigate the cause of any defect, imperfection or fault related
to the work under the Contract; and
b) Execute maintenance work including any work of replacement,
repair, rectification and making good any defect, imperfection,
settlement or other fault (whether intermittent or otherwise) identified
before the expiry of the Defects Liability Period. The work shall be
executed within such period as instructed, or in the absence of such
instruction, as soon as is practicable.
All the above work shall be fully finished before the completion of the
Defect Liability Period.
14 Rectification of Defect Requirements during Defects Liability Period
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
341
Appendices
Appendix A. Concept Layout ___________________________________________________________________ 342 Appendix B. Room Area and Finishes Schedule ____________________________________________________ 343 Appendix C. Architectural Appendix _____________________________________________________________ 344 Appendix D. Room Data Sheets ________________________________________________________________ 345 Appendix E. Scope of Works carried out by Contract RFQ-198 ________________________________________ 346 Appendix F. Drawings ________________________________________________________________________ 350 Appendix G. Demolition _______________________________________________________________________ 363 Appendix H. Requirements of Statutory and Detailed Design Documents ________________________________ 365 Appendix I. Requirements of Construction Documents ______________________________________________ 367 Appendix J. Requirements of As-built Documents __________________________________________________ 370 Appendix K. Requirements of Operation and Maintenance (O&M) Manual and user Manual __________________ 372
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
342
A.1 Concept Layout
Drawing Number Drawing Title
MMH-365511-A-C-000-1100
CONCEPT LAYOUT GROUND FLOOR (ARRIVAL LEVEL)
MMH-365511-A-C-000-1200
CONCEPT LAYOUT M FLOOR (STERILE CORRIDOR LEVEL)
MMH-365511-A-C-000-1300
CONCEPT LAYOUT 1 FLOOR (DEPARTURE LEVEL)
MMH-365511-A-C-000-1400
CONCEPT LAYOUT 2 FLOOR (MEZZANINE LEVEL)
MMH-365511-A-C-000-1500
CONCEPT LAYOUT 3 FLOOR (OFFICE LEVEL)
MMH-365511-C-0001-0
CIVIL WORKS LAYOUT
Please refer to the A1 Concept Layout folder
Appendix A. Concept Layout
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
343
Please refer to the B Room Area and finishes schedule folder
Appendix B. Room Area and Finishes Schedule
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
344
Please refer to the C Architectural Appendix folder
Appendix C. Architectural Appendix
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
345
The room data sheets (RDS) provided in this document is for reference
only. The Contractor shall further develop the details and consult all
related stakeholders to finalise the requirements in the design before
implementation.
The finalised RDS shall be confirmed by CAM Project Manager before
proceeding into construction / implementation.
Please refer to the D Room Data Sheets folder
Appendix D. Room Data Sheets
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
346
Appendix E. Scope of Works carried out by Contract RFQ-198
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
347
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
348
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
349
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
350
F.1 Contract RFQ-198 Drawings for Information
The drawings from the PTB extension contract RFQ-198 is provided for
reference. They are subjected to further development as the
construction is currently in progress.
The Contractor shall coordinate with the RFQ-198 contractor for the
details during all stage of this project.
Please refer to the D2 Drawings for Information folder
F.1.1 Architectural
Drawing Number Drawing Title
AR-001 Location Plan
AR-002 Master Plan
AR-003 Axes Setting Out Plan
AR-004(a) Arrival Level Plan (a)
AR-004(b) Arrival Level Plan (b)
AR-005(a) Sterile Corridor Plan (a)
AR-005(b) Sterile Corridor Plan (b)
AR-006(a) Departure Level Plan (a)
AR-006(b) Departure Level Plan (b)
AR-007(a) Mezzanine Level Plan (a)
AR-007(b) Mezzanine Level Plan (b)
AR-008(a) Office Level Plan (a)
AR-008(b) Office Level Plan (b)
AR-009(a) Roof Level Plan (a)
AR-009(b) Roof Level Plan (b)
AR-010 Setction A-A & Section B-B
AR-011 Setction C-C & Section D-D
AR-012 Elevation N1-N5 & Elevation N5-N1
AR-013 Elevation NA-NJ & Elevation NJ-NA
AR-014 Elevation Dimensions N1~N5
AR-015 Elevation Dimensions N5~N1
AR-016 Elevation Dimensions NA~ND
Appendix F. Drawings
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
351
AR-017 Elevation Dimension NE~NJ
AR-018 Elevation Dimension NJ~NE
AR-019 Elevation Dimension ND~NA
AR-020 Stair - STR1 - Plans & Section
AR-021 Stair - STR2 - Plans & Section
AR-022 Stair - STR3 - Plans & Section
AR-023 Typical Details of Stairs
AR-024 Roof Details
AR-025 Expansion Joints Details
AR-026 Doors & Windows Schedule (1)
AR-027 Doors & Windows Schedule (2)
AR-028 Express Link Fencing & Gate Plan & Elevations
AR-029 Express Link Fencing & Sliding Gate Details
AR-030 Glass Balustrade Details
AR-031 Elevator Pit Ladder Details
AR-032 Water Tank Access Door and Ladder Details
AR-033 Indoor Manhole / Road and Walk-way Details
AR-034 Pavement Details
AR-035 Traffic Signage
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
352
F.1.2 HVAC
Drawing Number Drawing Title
NF-AC-001 LEGEND, SYMBOL AND ABBREVIATION – I
NF-AC-002 LEGEND, SYMBOL AND ABBREVIATION – II
NF-AC-011 EQUIPMENT SCHEDULE– I
NF-AC-012 EQUIPMENT SCHEDULE– II
NF-AC-013 EQUIPMENT SCHEDULE– III
NF-AC-014 EQUIPMENT SCHEDULE– IV
NF-AC-015 EQUIPMENT SCHEDULE– V
NF-AC-201A HVAC AIR SIDE LAYOUT PLAN FOR ARRIVAL LEVEL (A)
NF-AC-201B HVAC AIR SIDE LAYOUT PLAN FOR ARRIVAL LEVEL (B)
NF-AC-202A HVAC AIR SIDE LAYOUT PLAN FOR STERILE CORRIDOR (A)
NF-AC-202B HVAC AIR SIDE LAYOUT PLAN FOR STERILE CORRIDOR (B)
NF-AC-203A HVAC AIR SIDE LAYOUT PLAN FOR DEPARTURE LEVEL (A)
NF-AC-203B HVAC AIR SIDE LAYOUT PLAN FOR DEPARTURE LEVEL (B)
NF-AC-204A HVAC AIR SIDE LAYOUT PLAN FOR MEZZANINE LEVEL (A)
NF-AC-204B HVAC AIR SIDE LAYOUT PLAN FOR MEZZANINE LEVEL (B)
NF-AC-205A HVAC AIR SIDE LAYOUT PLAN FOR OFFICE LEVEL (A)
NF-AC-205B HVAC AIR SIDE LAYOUT PLAN FOR OFFICE LEVEL (B)
NF-AC-206A HVAC AIR SIDE LAYOUT PLAN FOR ROOF LEVEL (A)
NF-AC-206B HVAC AIR SIDE LAYOUT PLAN FOR ROOF LEVEL (B)
NF-AC-402A HVAC WATER SIDE LAYOUT PLAN FOR STERILE CORRIDOR (A)
NF-AC-402B HVAC WATER SIDE LAYOUT PLAN FOR STERILE CORRIDOR (B)
NF-AC-403 HVAC WATER SIDE LAYOUT PLAN FOR DEPARTURE LEVEL
NF-AC-404 HVAC WATER SIDE LAYOUT PLAN FOR MEZZANINE LEVEL
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
353
NF-AC-405A HVAC WATER SIDE LAYOUT PLAN FOR OFFICE LEVEL (A)
NF-AC-405B HVAC WATER SIDE LAYOUT PLAN FOR OFFICE LEVEL (B)
NF-AC-406 HVAC WATER SIDE LAYOUT PLAN FOR ROOF LEVEL
NF-AC-501 AIR SIDE SYSTEM DIAGRAMS
NF-AC-502 WATER SIDE SYSTEM DIAGRAMS– I
NF-AC-503 WATER SIDE SYSTEM DIAGRAMS– II
NF-AC-504 AIR BALANCING DIAGRAM AT ARRIVAL LEVEL
NF-AC-505 AIR BALANCING DIAGRAM AT STERILE CORRIDOR
NF-AC-506 AIR BALANCING DIAGRAM AT DEPARTURE LEVEL
NF-AC-507 AIR BALANCING DIAGRAM AT MEZZANINE LEVEL
NF-AC-508 AIR BALANCING DIAGRAM AT OFFICE LEVEL
NF-AC-601 INSTALLATION DETAIL– I
NF-AC-701 CONTROL SYSTEM DIAGRAMS– I
NF-AC-702 CONTROL SYSTEM DIAGRAMS– II
NF-AC-703 CONTROL SYSTEM DIAGRAMS– III
NF-AC-706 LMCP SCHEDULE– I
NF-AC-707 LMCP SCHEDULE– II
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
354
F.1.3 Electrical Services System
Drawing Number Drawing Title
NF-EL-001 LEGEND AND ABBREVIATION
NF-EL-101 ELECTRICAL SYSTEM SCHEMATIC DIAGRAM (HV)
NF-EL-102 ELECTRICAL SYSTEM SCHEMATIC DIAGRAM (LV)
NF-EL-103 LV SWITCHBORAD SCHEMATIC DIAGRAM
NF-EL-104 EXIT SIGN AND STAIRCASE LIGHTING SCHEMATIC DIAGRAM
NF-EL-105 LUMINAIRE SCHEDULE
NF-EL-106 UPS SYSTEM SCHEMATIC DIAGRAM
NF-EL-110 DISTRIBUTION BOARD DETAIL - I
NF-EL-111 DISTRIBUTION BOARD DETAIL - II
NF-EL-112 DISTRIBUTION BOARD DETAIL - III
NF-EL-113 DISTRIBUTION BOARD DETAIL -IV
NF-EL-201A LIGHTING LAYOUT PLAN AT ARRIVAL LEVEL (A)
NF-EL-201B LIGHTING LAYOUT PLAN AT ARRIVAL LEVEL (B)
NF-EL-202 LIGHTING LAYOUT PLAN AT STERILE CORRIDOR
NF-EL-202A LIGHTING LAYOUT PLAN FOR STERILE CORRIDOR (A)
NF-EL-202B LIGHTING LAYOUT PLAN FOR STERILE CORRIDOR (B)
NF-EL-203A LIGHTING LAYOUT PLAN AT DEPARTURE LEVEL (A)
NF-EL-203B LIGHTING LAYOUT PLAN AT DEPARTURE LEVEL (B)
NF-EL-204A LIGHTING LAYOUT PLAN AT MEZZANINE LEVEL (A)
NF-EL-204B LIGHTING LAYOUT PLAN AT MEZZANINE LEVEL (B)
NF-EL-205A LIGHTING LAYOUT PLAN AT OFFICE LEVEL (A)
NF-EL-205B LIGHTING LAYOUT PLAN FOR OFFICE LEVEL (B)
NF-EL-206A LIGHTING LAYOUT PLAN FOR ROOF LEVEL (A)
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
355
NF-EL-206B LIGHTING LAYOUT PLAN FOR ROOF LEVEL (B)
NF-EL-300 11KV CABLE ROUTE LAYOUT PLAN
NF-EL-301A ELECTRICAL POWER LAYOUT PLAN AT ARRIVAL LEVEL (A)
NF-EL-301B ELECTRICAL POWER LAYOUT PLAN AT ARRIVAL LEVEL (B)
NF-EL-302 ELECTRICAL POWER LAYOUT PLAN AT STERILE CORRIDOR
NF-EL-303A ELECTRICAL POWER LAYOUT PLAN AT DEPARTURE LEVEL (A)
NF-EL-303B ELECTRICAL POWER LAYOUT PLAN AT DEPARTURE LEVEL (B)
NF-EL-304A ELECTRICAL POWER LAYOUT PLAN AT MEZZANINE LEVEL (A)
NF-EL-304B ELECTRICAL POWER LAYOUT PLAN AT MEZZANINE LEVEL (B)
NF-EL-305A ELECTRICAL POWER LAYOUT PLAN AT OFFICE LEVEL (A)
NF-EL-305B ELECTRICAL POWER LAYOUT PLAN AT OFFICE LEVEL (B)
NF-EL-306A ELECTRICAL POWER LAYOUT PLAN AT ROOF LEVEL (A)
NF-EL-306B ELECTRICAL POWER LAYOUT PLAN AT ROOF LEVEL (B)
NF-EL-401A CABLE CONTAINMENT LAYOUT PLAN AT ARRIVAL LEVEL (A)
NF-EL-401B CABLE CONTAINMENT LAYOUT PLAN AT ARRIVAL LEVEL (B)
NF-EL-402A CABLE CONTAINMENT LAYOUT PLAN AT STERILE CORRIDOR (A)
NF-EL-402B CABLE CONTAINMENT LAYOUT PLAN AT STERILE CORRIDOR (B)
NF-EL-403A CABLE CONTAINMENT LAYOUT PLAN AT DEPARTURE LEVEL (A)
NF-EL-403B CABLE CONTAINMENT LAYOUT PLAN AT DEPARTURE LEVEL (B)
NF-EL-404A CABLE CONTAINMENT LAYOUT PLAN AT MEZZANINE LEVEL (A)
NF-EL-404B CABLE CONTAINMENT LAYOUT PLAN AT MEZZANINE LEVEL (B)
NF-EL-405A CABLE CONTAINMENT LAYOUT PLAN AT OFFICE LEVEL (A)
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
356
NF-EL-405B CABLE CONTAINMENT LAYOUT PLAN AT OFFICE LEVEL (B)
NF-EL-406 CABLE CONTAINMENT LAYOUT PLAN AT ROOF LEVEL (A)
NF-EL-501A EARTHING AND LIGHTNING LAYOUT PLAN AT ARRIVAL LEVEL (A)
NF-EL-501B EARTHING AND LIGHTNING LAYOUT PLAN AT ARRIVAL LEVEL (B)
NF-EL-502A EARTHING AND LIGHTNING LAYOUT PLAN AT STERILE CORRIDOR (A)
NF-EL-502B EARTHING AND LIGHTNING LAYOUT PLAN AT STERILE CORRIDOR (B)
NF-EL-503A EARTHING AND LIGHTNING LAYOUT PLAN AT DEPARTURE LEVEL (A)
NF-EL-503B EARTHING AND LIGHTNING LAYOUT PLAN AT DEPARTURE LEVEL (B)
NF-EL-504A EARTHING AND LIGHTNING LAYOUT PLAN AT MEZZANINE LEVEL (A)
NF-EL-504B EARTHING AND LIGHTNING LAYOUT PLAN AT MEZZANINE LEVEL (B)
NF-EL-505A EARTHING AND LIGHTNING LAYOUT PLAN AT OFFICE LEVEL(A)
NF-EL-505B EARTHING AND LIGHTNING LAYOUT PLAN AT OFFICE LEVEL(B)
NF-EL-506 EARTHING AND LIGHTNING LAYOUT PLAN AT ROOF LEVEL
NF-EL-701 INSTALLATION DETAILS - I
NF-EL-702 INSTALLATION DETAILS - II
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
357
F.1.4 Plumbing System
Drawing Number Drawing Title
NF-AG-001 LEGEND, SYMBOL AND ABBREVIATION
NF-AG-201A PLUMBING LAYOUT PLAN FOR ARRIVAL LEVEL (A)
NF-AG-201B PLUMBING LAYOUT PLAN FOR ARRIVAL LEVEL (B)
NF-AG-202A PLUMBING LAYOUT PLAN FOR STERILE CORRIDOR (A)
NF-AG-202B PLUMBING LAYOUT PLAN FOR STERILE CORRIDOR (B)
NF-AG-203A PLUMBING LAYOUT PLAN FOR DEPARTURE LEVEL (A)
NF-AG-203B PLUMBING LAYOUT PLAN FOR DEPARTURE LEVEL (B)
NF-AG-204A PLUMBING LAYOUT PLAN FOR MEZZANINE LEVEL (A)
NF-AG-204B PLUMBING LAYOUT PLAN FOR MEZZANINE LEVEL (B)
NF-AG-205A PLUMBING LAYOUT PLAN FOR OFFICE LEVEL (A)
NF-AG-205B PLUMBING LAYOUT PLAN FOR OFFICE LEVEL (B)
NF-AG-206A PLUMBING LAYOUT PLAN FOR ROOF LEVEL (A)
NF-AG–501 PLUMBING SYSTEM SCHEMATIC DIAGRAM
NF-AG–601 INSTALLATION DETAILS – I
NF-AG–602 INSTALLATION DETAILS – II
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
358
F.1.5 Drainage System
Drawing Number Drawing Title
NF-EG-001 LEGEND, SYMBOL AND ABBREVIATION
NF-EG-011 SCHEDULE
NF-EG-201A DRAINAGE LAYOUT PLAN FOR ARRIVAL LEVEL (A)
NF-EG-201B DRAINAGE LAYOUT PLAN FOR ARRIVAL LEVEL (B)
NF-EG-202A DRAINAGE LAYOUT PLAN FOR STERILE CORRIDOR (A)
NF-EG-202B DRAINAGE LAYOWUT PLAN FOR STERILE CORRIDOR (B)
NF-EG-203A DRAINAGE LAYOUT PLAN FOR DEPARTURE LEVEL (A)
NF-EG-203B DRAINAGE LAYOUT PLAN FOR DEPARTURE LEVEL (B)
NF-EG-204A DRAINAGE LAYOUT PLAN FOR MEZZANINE LEVEL (A)
NF-EG-204B DRAINAGE LAYOUT PLAN FOR MEZZANINE LEVEL (B)
NF-EG-205A DRAINAGE LAYOUT PLAN FOR OFFICE LEVEL (A)
NF-EG-205B DRAINAGE LAYOUT PLAN FOR OFFICE LEVEL (B)
NF-EG-206A DRAINAGE LAYOUT PLAN FOR ROOF LEVEL (A)
NF-EG-206B DRAINAGE LAYOUT PLAN FOR ROOF LEVEL (B)
NF-EG-501A DRAINAGE SYSTEM SCHEMATIC DIAGRAM – I
NF-EG-501B DRAINAGE SYSTEM SCHEMATIC DIAGRAM – II
NF-EG-501C DRAINAGE SYSTEM SCHEMATIC DIAGRAM – III
NF-EG–502 RAIN WATER DRAINAGE SYSTEM SCHEMATIC DIAGRAM
NF-EG–601 INSTALLATION DETAILS – I
NF-EG–602 INSTALLATION DETAILS – II
NF-EG-603 INSTALLATION DETAILS – III
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
359
F.1.6 ELV Systems
Drawing Number Drawing Title
NF-ELV-101 CCTV SYSTEM SCHEMATIC DIAGRAM
NF-ELV-102 PA SYSTEM SCHEMATIC DIAGRAM
NF-ELV-103 ACCESS CONTROL SYSTEM SCHEMATIC DIAGRAM
NF-ELV-104 WLAN SYSTEM SCHEMATIC DIAGRAM
NF-ELV-105 RADIO COMMUNICATION SYSTEM SCHEMATIC DIAGRAM
NF-ELV-106 VOICE/DATA CABLING SYSTEM SCHEMATIC DIAGRAM
NF-ELV-107 BUILDING MANAGEMENT SYSTEM SCHEMATIC DIAGRAM
NF-ELV-201 CCTV SYSTEM LAYOUT PLAN AT ARRIVAL LEVEL
NF-ELV-202 CCTV SYSTEM LAYOUT PLAN AT STERILE CORRIDOR
NF-ELV-203 CCTV SYSTEM LAYOUT PLAN AT DEPARTURE LEVEL
NF-ELV-204 CCTV SYSTEM LAYOUT PLAN AT MEZZANINE LEVEL
NF-ELV-205 CCTV SYSTEM LAYOUT PLAN AT OFFICE LEVEL
NF-ELV-206 CCTV SYSTEM LAYOUT PLAN AT ROOF LEVEL
NF-ELV-301 PA SYSTEM LAYOUT PLAN AT ARRIVAL LEVEL
NF-ELV-302 PA SYSTEM LAYOUT PLAN AT STERILE CORRIDOR
NF-ELV-303 PA SYSTEM LAYOUT PLAN AT DEPARTURE LEVEL
NF-ELV-304 PA SYSTEM LAYOUT PLAN AT MEZZANINE LEVEL
NF-ELV-305 PA SYSTEM LAYOUT PLAN AT OFFICE LEVEL
NF-ELV-401 ACCESS CONTROL SYSTEM LAYOUT PLAN AT ARRIVAL LEVEL
NF-ELV-402 ACCESS CONTROL SYSTEM LAYOUT PLAN AT STERRILE CORRIDOR
NF-ELV-403 ACCESS CONTROL SYSTEM LAYOUT PLAN AT DEPARTURE LEVEL
NF-ELV-404 ACCESS CONTROL SYSTEM LAYOUT PLAN AT MEZZANINE LEVEL
NF-ELV-405 ACCESS CONTROL SYSTEM LAYOUT PLAN AT
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
360
OFFICE LEVEL
NF-ELV-406 ACCESS CONTROL SYSTEM LAYOUT PLAN AT ROOF LEVEL
NF-ELV-501 WLAN SYSTEM LAYOUT PLAN AT ARRIVAL LEVEL
NF-ELV-502 WLAN SYSTEM LAYOUT PLAN AT STERRILE CORRIDOR
NF-ELV-503 WLAN SYSTEM LAYOUT PLAN AT DEPARTURE LEVEL
NF-ELV-504 WLAN SYSTEM LAYOUT PLAN AT MEZZANINE LEVEL
NF-ELV-505 WLAN SYSTEM LAYOUT PLAN AT OFFICE LEVEL
NF-ELV-601 RADIO COMMUNICATION LAYOUT PLAN AT ARRIVAL LEVEL
NF-ELV-602 RADIO COMMUNICATION LAYOUT PLAN AT STERRILE CORRIDOR
NF-ELV-603 RADIO COMMUNICATION LAYOUT PLAN AT DEPARTURE LEVEL
NF-ELV-604 RADIO COMMUNICATION LAYOUT PLAN AT MEZZANINE LEVEL
NF-ELV-605 RADIO COMMUNICATION LAYOUT PLAN AT OFFICE LEVEL
NF-ELV-701 VOICE/DATA CABLING SYSTEM LAYOUT PLAN AT ARRIVAL LEVEL
NF-ELV-702 VOICE/DATA CABLING SYSTEM LAYOUT PLAN AT STERILE CORRIDOR
NF-ELV-703 VOICE/DATA CABLING SYSTEM LAYOUT PLAN AT DEPARTURE LEVEL
NF-ELV-704 VOICE/DATA CABLING SYSTEM LAYOUT PLAN AT MEZZANINE LEVEL
NF-ELV-705 VOICE/DATA CABLING SYSTEM LAYOUT PLAN AT OFFICE LEVEL
NF-ELV-801 BUILDING MANAGEMENT SYSTEM LAYOUT PLAN AT ARRIVAL LEVEL
NF-ELV-802 BUILDING MANAGEMENT SYSTEM LAYOUT PLAN AT STERILE CORRIDOR
NF-ELV-803 BUILDING MANAGEMENT SYSTEM LAYOUT PLAN AT DEPARTURE LEVEL
NF-ELV-804 BUILDING MANAGEMENT SYSTEM LAYOUT PLAN AT MEZZANINE LEVEL
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
361
NF-ELV-805 BUILDING MANAGEMENT SYSTEM LAYOUT PLAN AT OFFICE LEVEL
NF-ELV-806 BUILDING MANAGEMENT SYSTEM POINT SCHEDULE
NF-ELV-901 MAIN TRUNKING SYSTEM LAYOUT PLAN AT ARRIVAL LEVEL
NF-ELV-902 MAIN TRUNKING SYSTEM LAYOUT PLAN AT DEPARTURE LEVEL
NF-ELV-903 MAIN TRUNKING SYSTEM LAYOUT PLAN AT MEZZANINE LEVEL
NF-ELV-904 MAIN TRUNKING SYSTEM LAYOUT PLAN AT OFFICE LEVEL
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
362
F.1.7 Fire Services System
Drawing Number Drawing Title
NF-FS‐001 Fire Service Diagram
NF-FS‐002a/b Arrival Level Plan
NF-FS‐003a/b Sterile Corridor Plan
NF-FS‐004a/b Departure Level Plan
NF-FS‐005a/b Mezzanine Level Plan
NF-FS‐006a/b Office Level Plan
NF-FS‐007a/b Roof Level Plan
NF-FS‐D‐001 Hose Reel and fire hydrant installation detail
NF-FS‐D‐002 sprinkler installation detail
NF-FS‐D‐003 Fire inlet and street hydrant installation deta
NF-FS‐D‐004 Dry fire devices installation detail
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
363
G.1 Departure Level
Demolition and modification of existing part of Passenger Terminal
Building and re-build a wall within an existing room (room 11065,
highlighted in yellow colour) on departure level, please refer to Bill of
Quantities – Bill Nr. 3 for details:
Appendix G. Demolition and A&A Works
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
364
G.2 Mezzanine Level
Demolition, modification and expansion of existing room (room 12061,
highlighted in yellow colour) of Passenger Terminal Building on Mezzanine
level, please refer to Bill of Quantities – Bill Nr. 3 for details:
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
365
H.1 DRAWINGS IN ELECTRONIC FORMAT
The Contractor shall provide drawings in electronic format as required
in the following clauses.
H.2 INSTALLATION DRAWINGS
H.2.1 Drawing Submission Schedule
The Contractor shall submit a statutory and detailed design drawing submission schedule and programme to CAM. The Contractor shall allow reasonable time in the programme for vetting of the installation drawings by CAM and for drawing resubmissions as necessary. The Contractor shall submit to the CAM a comprehensive “Submission Schedule” of installation drawings and builder’s work drawings within 2 weeks after the acceptance of Tender, taking into account of the overall programme of the Installations including any Specialist Works and works by the utility undertakings. No equipment shall be delivered to the Site and no Installations shall be executed until the installation drawings have been checked by CAM without any objection. The Contractor shall ensure that installation drawings and builder’s work drawings are progressively submitted in accordance with the approved “Submission Schedule”.
The Contractor shall provide at least 7 hard copies and one electronic
copy, unless otherwise specified in the Contract or the Sub-contract as
appropriate, of the installation drawings to CAM for distribution.
H.2.2 Size of statutory and detailed design Drawings
For statutory submissions, the Contractor shall follow the Macau regulations for the drawing scale and size. Design and construction drawings submitted by the Contractor shall only be of standard sizes from A0 to A4 or B1 size as stipulated in ISO 5457:1999.
H.2.3 Contents of statutory and detailed design Documents and
Drawings
The Contractor shall provide all statutory and detailed design report, specifications, calculations and drawings with contents according to requirements as stated in design brief and all AACM/DSSOPT requirements including but not limit to the requirements in guidelines and manuals as follows:-
Appendix H. Requirements of Statutory and Detailed Design Documents
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
366
(a) <Conjunto de Instruções para Elaboração de Projectos de
Obras de Construção e de Ampliação>
a. <Á rea de Arquitectura> b. <Á rea da Engenharia Electromecânica> c. <Á rea de Gases Combustíveis ou de Combustíveis> d. <Á rea de Engenharia Civil>
(b) <Instruções para Apreciação, Aprovação, Vistoria e Operação
dos Equipamentos de Elevadores>
(c) <Directrizes para os Projectos de Iluminação Pública de
Macau>
(d) <Manual de Procedimentos Técnicos para Conservação de
Energia em Edifícios de Macau>
(e) <Critérios de Apreciação de Projectos de Obras de Construção
e de Ampliação e Instruções de Procedimentos
Administrativos>
The Contractor shall ensure all statutory and detailed design drawings are accurate representation of the Installations, before submitting them to CAM. All installation drawings shall be fully dimensioned and suitably scaled showing construction, sizes, weights, arrangements, operating clearances and performance characteristics. The statutory and detailed design drawings shall be dimensioned and
showing construction, sizes, weights, arrangements, operating clearances, performance characteristics and the necessary builder’s work involved. Installation drawings for conduit layout shall clearly indicate the proposed position and size of conduit runs together with the number of cables, size and circuiting of the cables therein.
H.2.4 Statutory and Detailed Design Documents and Drawings
Unless otherwise agreed by CAM, the Contractor shall submit the detailed design documents and drawing to the CAM in accordance with the approved “Submission Schedule”, 7 copies of drawings showing details of all detailed design work required
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
367
I.1 DRAWINGS IN ELECTRONIC FORMAT
The Contractor shall provide drawings in electronic format as required
in the following clauses.
I.2 INSTALLATION DRAWINGS
I.2.1 Drawing Submission Schedule
The Contractor shall submit a detailed installation drawing submission schedule and programme to CAM. The Contractor shall allow reasonable time in the programme for vetting of the installation drawings by CAM and for drawing resubmissions as necessary. The Contractor shall submit to the CAM a comprehensive “Submission Schedule” of installation drawings and builder’s work drawings within 2 weeks after the acceptance of Tender, taking into account of the overall programme of the Installations including any Specialist Works and works by the utility undertakings. No equipment shall be delivered to the Site and no Installations shall be executed until the installation drawings have been checked by CAM without any objection. The Contractor shall ensure that installation drawings and builder’s work drawings are progressively submitted in accordance with the approved “Submission Schedule”.
The Contractor shall provide at least 7 hard copies and one electronic
copy, unless otherwise specified in the Contract or the Sub-contract as
appropriate, of the installation drawings to CAM for distribution.
I.2.2 Size of Installation Drawings
For statutory submissions, the Contractor shall follow the Macau regulations for the drawing scale and size.
Installation/Construction Drawings submitted by the Contractor shall only be of standard sizes from A0 to A4 or B1 size as stipulated in ISO 5457:1999.
I.2.3 Contents of Installation Documents and Drawings
The Contractor shall provide all Installation documents including but not limit to material submissions, schedules, proposals, calculations, method statements, samples and drawings with contents according to requirements as stated in design brief and all DSSOPT requirements including but not limit to the requirements in guidelines and manuals as follows:-
Appendix I. Requirements of Construction Documents
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
368
(a) <Conjunto de Instruções para Elaboração de Projectos de
Obras de Construção e de Ampliação>
a. <Á rea de Arquitectura> b. <Á rea da Engenharia Electromecânica> c. <Á rea de Gases Combustíveis ou de Combustíveis> d. <Á rea de Engenharia Civil>
(b) <Instruções para Apreciação, Aprovação, Vistoria e Operação
dos Equipamentos de Elevadores>
(c) <Directrizes para os Projectos de Iluminação Pública de
Macau>
(d) <Manual de Procedimentos Técnicos para Conservação de
Energia em Edifícios de Macau>
(e) <Critérios de Apreciação de Projectos de Obras de Construção
e de Ampliação e Instruções de Procedimentos
Administrativos>
The Contractor shall ensure all installation drawings are accurate representation of the Installations, before submitting them to CAM. All installation drawings shall be fully dimensioned and suitably scaled showing construction, sizes, weights, arrangements, operating clearances and performance characteristics. Installation drawings shall be dimensioned and showing construction, sizes, weights, arrangements, operating clearances, performance characteristics and the necessary builder’s work involved. Installation drawings for conduit layout shall clearly indicate the proposed position and size of conduit runs together with the number of cables, size and circuiting of the cables therein.
I.2.4 Builder’s Work Documents and Drawings
Unless otherwise agreed by CAM, the Contractor shall submit the builder’s work drawing to the CAM in accordance with the approved “Submission Schedule”, 7 copies of drawings showing details of all builder’s work required e.g. the weight and the load on each support of equipment. Such drawings shall clearly indicate the details and positions of all openings, holes, trenches, ducts and cutting required and construction details for plinths and equipment bases.
I.2.5 Manufacturer’s Shop Drawings
The manufacturer’s shop drawings are drawings for equipment or plant to be manufactured by a specialist manufacturing supplier in their own workshops and places away from the Site.
The drawings shall show detailed construction, principal dimensions,
weights and clearances for maintenance, etc. Immediately after placing
of any order or at any event within 4 weeks unless otherwise approved
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
369
in writing by CAM, the Contractor shall forward to CAM for comment, 4
copies of manufacturer’s shop drawings indicating detailed construction,
principal dimensions and weights, clearances for withdrawals and/or
cleaning, etc. No Installations shall proceed on or off Site unless
drawings requiring approval are so approved in writing by CAM.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
370
J.1 DRAWINGS IN ELECTRONIC FORMAT
The Contractor shall provide drawings in electronic format as required
in the following clauses.
J.2 Submission of As–built Drawings
The Contractor shall submit 3 sets of the first draft prints of as-built drawings upon construction completion in accordance with the Contract
to CAM for checking. CAM after checking the above draft prints shall
return one set of the marked up copies of these as-built drawings to the Contractor with comments. The Contractor shall within a further 21 days from the date of receiving the CAM’s comments on the draft as-built drawings re-submit to CAM for his review another 3 sets of the second draft prints of as-built drawings with CAM’s comments incorporated. This process of submission and approval shall continue until the final review of CAM on these as-built drawing is obtained. The final checked as-built drawings without objection shall be in 7 sets of hard copies and 7 sets of electronic copies. These shall be submitted within 14 days from the date of checked without objection. Each electronic copy shall be in the form of CD-ROM, labelled, with cross reference to a printed list of files explaining the contents and purpose of each file and supplied in sturdy plastic containers. The detailed requirements and the media of as-built drawings set out in the Contract shall be followed as appropriate.
J.3 Size of As-built Drawings
As-built drawings shall follow Macau Regulations and be of standard sizes of A0, A1 or B1 size as stipulated in ISO 5457:1999.
J.4 Content of As-built Documents and Drawings
The Contractor shall provide all Installation documents and drawings with contents according to requirements as stated in design brief and all DSSOPT requirements including but not limit to the requirements in guidelines and manuals as follows:-
(a) <Conjunto de Instruções para Elaboração de Projectos de
Obras de Construção e de Ampliação> a. <Á rea de Arquitectura> b. <Á rea da Engenharia Electromecânica> c. <Á rea de Gases Combustíveis ou de Combustíveis> d. <Á rea de Engenharia Civil>
(b) <Instruções para Apreciação, Aprovação, Vistoria e Operação
dos Equipamentos de Elevadores>
Appendix J. Requirements of As-built Documents
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
371
(c) <Directrizes para os Projectos de Iluminação Pública de
Macau>
(d) <Manual de Procedimentos Técnicos para Conservação de
Energia em Edifícios de Macau>
(e) <Critérios de Apreciação de Projectos de Obras de Construção
e de Ampliação e Instruções de Procedimentos
Administrativos>
The Contractor shall ensure all as-built drawings are accurate representation of the Installations, before submitting them to CAM. The as-built drawings required to be provided by the Contractor for various types of BS/E&M installations shall include, but not limited to the following:
(a) Building services layout plans such as ducting arrangement, trunking arrangement, piping arrangement, etc;
(b) System schematic diagrams, control diagrams and wiring diagrams;
(c) Concealed work layout plan such as concealed conduit routing, etc; and
(d) Installation details and assembly drawings such as L.V. cubicle switchboard layout, motor control cubicle layout, etc.
As-built drawings shall show the positions of all conduits, cables, switchgear, distribution boards, luminaires, lightning protection and earthing and all other items which have been installed.
J.5 Framed Drawings
The Contractor shall provide framed drawings to each major switchroom and electrical room showing the schematic wiring diagrams, tables or charts to indicate the type and composition of circuits, identification and location of item of equipment from that switchroom and electrical room. The framed drawings shall be fixed to the wall in such a way that it can easily be removed for reference.
DESIGN AND BUILD FOR FIT-OUT OF PASSENGER TERMINAL BUILDING NORTH EXTENSION AT MIA (RFQ-221) DESIGN REQUIREMENT BRIEF
May 2016 Design Requirement Brief
372
The Contractor shall provide Operation and Maintenance Manuals for
different installations bounded into separate volumes.
The Operation and Maintenance Manuals shall include:-
(a) Project Information
(b) System Description
(c) List of installed Equipment
(d) Spare Parts Lists
(e) Manufacturer's Certificates/ Guarantees/ Warranties
(f) Safety Precautions for Operation and Maintenance
(g) Operation Instructions
(h) Maintenance instructions, Maintenance schedules
(i) As-built Drawings
(j) Technical Literature
Appendix K. Requirements of Operation and Maintenance (O&M) Manual and user Manual