selective coordination study

Upload: jlpirela1000

Post on 07-Aug-2018

212 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/21/2019 Selective Coordination Study

    1/9

    Selective Coordination Study

    Recommended Procedures

    14

    The following steps are recommended when

    conducting a selective coordination study.

    1. One-Line Diagram

    Obtain the electrical system one-line diagram that identifies

    important system components, as given below.

    a. TransformersObtain the following data for protection and coordination infor-

    mation of transformers:

    - KVA rating

    - Inrush points

    - Primary and secondary connections

    - Impedance

    - Damage curves

    - Primary and secondary voltages

    - Liquid or dry type

    b. Conductors - Check phase, neutral, and equipment

    grounding. The one-line diagram should include infor-

    mation such as:

    - Conductor size

    - Number of conductors per phase- Material (copper or aluminum)

    - Insulation

    - Conduit (magnetic or non-magnetic)

    From this information, short circuit withstand curves can be

    developed. This provides information on how overcurrent

    devices will protect conductors from overload and short

    circuit damage.

    c. Motors

    The system one-line diagram should include motor

    information such as:

    - Full load currents

    - Horsepower

    - Voltage

    - Type of starting characteristic

    (across the line, etc.)

    - Type of overload relay

    (Class 10, 20, 30)

    Overload protection of the motor and motor circuit can be

    determined from this data.

    d. Fuse Characteristics

    Fuse Types/Classes should be identified on the one-line

    diagram.

    e. Circuit Breaker Characteristics

    Circuit Breaker Types should be identified on the one-line

    diagram.

    f. Relay Characteristics

    Relay Types should be identified on the one-line diagram.

    2. Short Circuit Study

    Perform a short circuit analysis, calculating maximum

    available short circuit currents at critical points in the

    distribution system (such as transformers, main switchgear,

    panelboards, motor control centers, load centers, and large

    motors and generators.) (Reference: Bussmann Bulletin,Engineering Dependable Protection - EDPI.)

    3. Helpful Hints

    a. Determine the Ampere Scale Selection. It is most

    convenient to place the time current curves in the center of

    the log-log paper. This is accomplished by multiplying or

    dividing the ampere scale by a factor of 10.

    b. Determine the Reference (Base) Voltage. The best

    reference voltage is the voltage level at which most of the

    devices being studied fall. (On most low voltage industrial

    and commercial studies, the reference voltage will be 208,

    240, or 480 volts). Devices at other voltage levels will be

    shifted by a multiplier based on the transformer turn ratio.

    The best reference voltage will require the least amount ofmanipulation. Modern computer programs will automat-

    ically make these adjustments when the voltage levels of

    devices are identified by the input data.

    c. Commencing the Analysis. The starting point can be

    determined by the designer. Typically, studies begin with

    the main circuit devices and work down through the

    feeders and branches. (Right to left on your log-log paper.)

    d. Multiple Branches. If many branches are taken off one

    feeder, and the branch loads are similar, the largest rated

    branch circuit should be checked for coordination with

    upstream devices. If the largest branch will coordinate, and

    the branch devices are similar, they generally will

    coordinate as well. (The designer may wish to verify other

    areas of protection on those branches, conductors, etc.)e. Don't Overcrowd the Study. Many computer generated

    studies will allow a maximum of ten device characteristics

    per page.

    f. One-Line Diagram. A one-line diagram of the study

    should be drawn for future reference.

  • 8/21/2019 Selective Coordination Study

    2/9

    The following pages will analyze in detail the system

    shown in Figure 11. It is understood that a short circuit

    study has been completed, and all devices have adequate

    interrupting ratings. A Selective Coordination Analysis is the

    next step.

    Examples of Selective Coordination Studies

    15

    M

    JCN80EIFLA=42A

    5.75% Z1000KVA

    -Y480/277V

    LOW-PEAK

    KRP-C-1600SP

    Fault X120,000A RMS Sym

    Main Switchboard

    1

    LOW PEAK

    LPS-RK-200SPLOW-PEAK

    LPS-RK-400SPLOW-PEAK

    LPS-RK-225SP

    200A Feeder 400A Feeder 150KVA-Y

    208/120V2% Z

    LOW-PEAK

    LPN-RK-500SPLOW-PEAK

    LPS-RK-100SP

    20A Branch

    20A CB

    20A CB

    LP1

    60HP 377A FLA

    1600A Main Bus

    PDP

    13.8KV

    Overcurrent Relay

    #6 XLP

    #3/0 THW

    100A Motor Branch

    #1 THW

    250 kcmil2/ THW

    #12 THW

    This simple radial system will involve three separate

    time current curve studies, applicable to the three feeder/

    branches shown.

    Figure 11

  • 8/21/2019 Selective Coordination Study

    3/9

    Example

    Time Current Curve #1 (TCC1)

    16

    Device ID Description Comments

    1 1000KVA XFMR 12 x FLA

    Inrush Point @ .1 Seconds

    2 1000KVA XFMR 5.75%Z, liquid

    Damage Curves filled

    (Footnote 1)

    (Footnote 2)

    3 JCN 80E E-Rated Fuse

    4 #6 Conductor Copper, XLP

    Damage Curve Insulation

    5 Medium Voltage Needed for XFMR

    Relay Primary Overload

    Protection

    6 KRP-C-1600SP Class L Fuse

    11 LPS-RK-200SP Class RK1 Fuse

    12 3/0 Conductor Copper THW

    Damage Curve Insulation

    13 20A CB Thermal Magnetic

    Circuit Breaker

    14 #12 Conductor Copper THW

    Damage Curve Insulation

    Footnote 1: Transformer damage curves indicate when it will be damaged,thermally and/or mechanically, under overcurrent conditions.

    Transformer impedance, as well as primary and secondaryconnections, and type, al l wil l determine their damagecharacteristics.

    Footnote 2: A -Y transformer connection requires a 15% shift, to the right,of the L-L thermal damage curve. This is due to a L-Lsecondary fault condition, which will cause 1.0 p.u. to flowthrough one primary phase, and .866 p.u. through the twofaulted secondary phases. (These currents are p.u. of 3-phasefault current.)

    Notes:

    1. TCC1 includes the primary fuse, secondary main fuse,

    200 ampere feeder fuse, and 20 ampere branch circuit

    breaker from LP1.

    2. Analysis will begin at the main devices and proceed

    down through the system.

    3. Reference (base) voltage will be 480 volts, arbitrarily

    chosen since most of the devices are at this level.

    4. Selective coordination between the feeder and branch

    circuit is not attainable for faults above 2500 amperes that

    occur on the 20 amp branch circuit, from LP1. Notice the

    overlap of the 200 ampere fuse and 20 ampere circuit

    breaker.

    5. The required minimum ratio of 2:1 is easily met between

    the KRP-C-1600SP and the LPS-RK-200SP.

  • 8/21/2019 Selective Coordination Study

    4/9

    Example

    Time Current Curve #1 (TCC1)

    17

    CURRENT IN AMPERES X 10 @ 480V

    TIMEIN

    SECONDS

    FLA

    11

    2

    2

    3

    5

    12

    14

    13

    1

    6

    #12 DAMAGE

    3/0 DAMAGE

    20A MCCB

    XFMRDAMAGE

    4

    JCN 80E

    MV OLR

    1000KVA5.75%Z-Y480/277V

    JCN80E

    13.8KV

    KRP-C-1600SP

    LPS-RK-200SP

    200AFeeder

    #6 XLP

    #3/0 THW

    OvercurrentRelay

    20A CB

    #12 THW20A CB

    KRP-C-1600SP

    TXINRUSH

    600

    400

    300

    200

    100

    80

    60

    40

    30

    20

    10

    8

    6

    4

    3

    2

    1

    .8

    .6

    .4

    .3

    .2

    .1

    .08

    .04

    .06

    .03

    .02

    .01

    800

    1000

    1 2 3 4 6 810

    20

    30

    40

    60

    80

    100

    200

    300

    400

    600

    800

    1000

    2000

    3000

    4000

    6000

    8000

    10

    ,000

    LPS-RK-200SP

    #6 DAMAGE

  • 8/21/2019 Selective Coordination Study

    5/9

    Example

    Time Current Curve #2 (TCC2)

    18

    Notes:

    1. TCC2 includes the primary fuse, secondary main fuse,

    400 ampere feeder fuse, 100 ampere motor branch fuse,

    77 ampere motor and overload relaying.

    2. Analysis will begin at the main devices and proceed

    down through the system.

    3. Reference (base) voltage will be 480 volts, arbitrarily

    chosen since most of the devices are at this level.

    Device ID Description Comment

    1 1000KVA XFMR 12 x FLA

    Inrush Point @ .1 seconds

    2 1000KVA XFMR 5.75%Z, liquid

    Damage Curves filled

    (Footnote 1)

    (Footnote 2)

    3 JCN 80E E-Rated Fuse

    4 #6 Conductor Copper, XLP

    Damage Curve Insulation

    5 Medium Voltage Needed for XFMR

    Relay Primary Overload

    Protection

    6 KRP-C-1600SP Class L Fuse

    21 LPS-RK-100SP Class RK1 Fuse

    22 Motor Starting Curve Across the Line

    Start

    23 Motor Overload Relay Class 10

    24 Motor Stall Point Part of a Motor

    Damage Curve

    25 #1 Conductor Copper THW

    Damage Curve Insulation

    Footnote 1: Transformer damage curves indicate when it will be damaged,thermally and/or mechanically, under overcurrent conditions.

    Transformer impedance, as well as primary and secondaryconnections, and type, al l wil l determine their damagecharacteristics.

    Footnote 2: A -Y transformer connection requires a 15% shift, to the right,of the L-L thermal damage curve. This is due to a L-Lsecondary fault condition, which will cause 1.0 p.u. to flowthrough one primary phase, and .866 p.u. through the twofaulted secondary phases. (These currents are p.u. of 3-phasefault current.)

  • 8/21/2019 Selective Coordination Study

    6/9

    Example

    Time Current Curve #2 (TCC2)

    19

    KRP-C-1600SP

    LPS-RK-400SP

    LPS-RK-100SP

    60HP

    400A Feeder

    CURRENT IN AMPERES X 10 @ 480V

    TIMEIN

    SECOND

    S

    MV OLR

    2

    2

    3

    5

    1

    6

    4

    21

    2225

    23

    24

    FLA

    MS

    JCN80EMTR START

    LPS-RK-100SP

    MTR OLRXFMR DAMAGE

    M

    #1 THW

    TXINRUSH

    #6 XLP

    13.8KV

    OvercurrentRelay

    JCN 80E

    1000KVA5.75%Z-Y480/277V

    600

    400

    300

    200

    100

    80

    60

    40

    30

    20

    10

    8

    6

    4

    3

    2

    1

    .8

    .6

    .4

    .3

    .2

    .1

    .08

    .04

    .06

    .03

    .02

    .01

    800

    1000

    1 2 3 4 6 810

    20

    30

    40

    60

    80

    100

    200

    300

    400

    600

    800

    1000

    2000

    3000

    4000

    6000

    8000

    10

    ,000

    KRP-C-1600SP

    #1 DAMAGE

    #6 DAMAGE

  • 8/21/2019 Selective Coordination Study

    7/9

    Example

    Time Current Curve #3 (TCC3)

    20

    Notes:

    1. TCC3 includes the primary fuse, secondary main fuse,

    225 ampere feeder/transformer primary and secondary

    fuses.

    2. Analysis will begin at the main devices and proceed

    down through the system.3. Reference (base) voltage will be 480 volts, arbitrarily

    chosen since most of the devices are at this level.

    4. Relative to the 225 ampere feeder, coordination between

    primary and secondary fuses is not attainable, noted by

    overlap of curves.

    5. Overload and short circuit protection for the 150 KVA

    transformer is afforded by the LPS-RK-225SP fuse.

    Device ID Description Comment

    1 1000KVA XFMR 12 x FLA

    Inrush Point @ .1 seconds

    2 1000KVA XFMR 5.75%Z, liquid

    Damage Curves filled

    (Footnote 1)

    (Footnote 2)

    3 JCN 80E E-Rated Fuse

    4 #6 Conductor Copper, XLP

    Damage Curve Insulation

    5 Medium Voltage Needed for XFMR

    Relay Primary Overload

    Protection

    6 KRP-C-1600SP Class L Fuse

    31 LPS-RK-225SP Class RK1 Fuse

    32 150 KVA XFMR 12 x FLA

    Inrush Point @.1 Seconds

    33 150 KVA XFMR 2.00% Dry Type

    Damage Curves (Footnote 3)

    34 LPN-RK-500SP Class RK1 Fuse

    35 2-250kcmil Conductors Copper THW

    Damage Curve Insulation

    Footnote 1: Transformer damage curves indicate when it will be damaged,thermally and/or mechanically, under overcurrent conditions.

    Transformer impedance, as well as primary and secondaryconnections, and type, al l wil l determine their damagecharacteristics.

    Footnote 2: A -Y transformer connection requires a 15% shift, to the right,of the L-L thermal damage curve. This is due to a L-Lsecondary fault condition, which will cause 1.0 p.u. to flowthrough one primary phase, and .866 p.u. through the twofaulted secondary phases. (These currents are p.u. of 3-phasefault current.)

    Footnote 3: Damage curves for a small KVA (

  • 8/21/2019 Selective Coordination Study

    8/9

    Example

    Time Current Curve #3 (TCC3)

    21

    CURRENT IN AMPERES X 10 @ 480V

    600

    400

    300

    200

    100

    80

    60

    40

    30

    20

    10

    8

    6

    4

    3

    2

    1

    .8

    .6

    .4

    .3

    .2

    .1

    .08

    .04

    .06

    .03

    .02

    .01

    TIMEIN

    SECOND

    S

    800

    1000

    4

    5

    2

    FLA FLA

    MV OLR

    XFMR DAMAGE

    JCN80E

    XFMR DAMAGE 33

    35

    LPS-RK-225SP

    LPN-RK-500SP

    KRP-C-1600SP

    TXINRUSH

    TXINRUSH

    132

    6

    #6 XLP

    JCN 80E

    13.8KV

    OvercurrentRelay

    250 kcmil2/ THW

    31

    34

    KRP-C1600SP

    23

    1000KVA5.75%Z-Y480/277V

    150KVA2.0%Z-Y208/120V

    1 2 3 4 6 810

    20

    30

    40

    60

    80

    100

    200

    300

    400

    600

    800

    1000

    2000

    3000

    4000

    6000

    8000

    10

    ,000

    LPS-RK-225SP

    LPN-RK-500SP

    2-250 DAMAGE

    #6 DAMAGE

  • 8/21/2019 Selective Coordination Study

    9/9

    Unnecessary power OUTAGES, such as the

    BLACKOUTS we so often experience, can be stopped by

    isolating a faulted circuit from the remainder of the system

    through the proper selection of MODERN CURRENT-

    LIMITING FUSES.

    Time-Delay type current-limiting fuses can be sizedclose to the load current and still hold motor-starting

    currents or other harmless transients, thereby

    ELIMINATING nuisance OUTAGES.

    The SELECTIVITY GUIDE on page 10 may be used for

    an easy check on fuse selectivity regardless of the short-

    circuit current levels involved. Where medium and high

    voltage primary fuses are involved, the time-current

    characteristic curves of the fuses in question should be

    plotted on standard NEMA log-log graph paper for proper

    study.

    The time saved by using the SELECTIVITY GUIDE will

    allow the electrical systems designer to pursue other areas

    for improved systems design.

    Conclusions

    22