session 9 design/build projects...session 9 design/build projects facilitator: mariano berrios,...
TRANSCRIPT
![Page 1: Session 9 Design/Build Projects...Session 9 Design/Build Projects Facilitator: Mariano Berrios, Florida DOT Participants: Darren O’Neill, Delaware DOT Amber Phillips, Georgia DOT](https://reader034.vdocument.in/reader034/viewer/2022051823/5fed9929e0da1677527dd089/html5/thumbnails/1.jpg)
Session 9 Design/Build Projects
Facilitator: Mariano Berrios, Florida DOT Participants:
Darren O’Neill, Delaware DOT Amber Phillips, Georgia DOT Mariano Berrios, Florida DOT Noel Alcala, Ohio DOT Discussant: Greg Smith, North Carolina DOT
![Page 2: Session 9 Design/Build Projects...Session 9 Design/Build Projects Facilitator: Mariano Berrios, Florida DOT Participants: Darren O’Neill, Delaware DOT Amber Phillips, Georgia DOT](https://reader034.vdocument.in/reader034/viewer/2022051823/5fed9929e0da1677527dd089/html5/thumbnails/2.jpg)
Design Build and CM/GC
An Alternative
Project Delivery Method
![Page 3: Session 9 Design/Build Projects...Session 9 Design/Build Projects Facilitator: Mariano Berrios, Florida DOT Participants: Darren O’Neill, Delaware DOT Amber Phillips, Georgia DOT](https://reader034.vdocument.in/reader034/viewer/2022051823/5fed9929e0da1677527dd089/html5/thumbnails/3.jpg)
What is the project need ?
Design Build - A project delivery system where design and construction activities are taken on by one entity
CM/GC - Owners coordinate and manage the entire project with both the design and construction entities working together early on
![Page 4: Session 9 Design/Build Projects...Session 9 Design/Build Projects Facilitator: Mariano Berrios, Florida DOT Participants: Darren O’Neill, Delaware DOT Amber Phillips, Georgia DOT](https://reader034.vdocument.in/reader034/viewer/2022051823/5fed9929e0da1677527dd089/html5/thumbnails/4.jpg)
The Master Building Philosophy
3 Jobs – Owner, Designer and Builder 1 Goal – Complete the project
![Page 5: Session 9 Design/Build Projects...Session 9 Design/Build Projects Facilitator: Mariano Berrios, Florida DOT Participants: Darren O’Neill, Delaware DOT Amber Phillips, Georgia DOT](https://reader034.vdocument.in/reader034/viewer/2022051823/5fed9929e0da1677527dd089/html5/thumbnails/5.jpg)
Master Building Resurgence
Trending back towards having the design team and the builder/contractor team work in unison for an owner
Incorporate a builder’s skills, techniques, equipment, resources and availability into the development of the design
![Page 6: Session 9 Design/Build Projects...Session 9 Design/Build Projects Facilitator: Mariano Berrios, Florida DOT Participants: Darren O’Neill, Delaware DOT Amber Phillips, Georgia DOT](https://reader034.vdocument.in/reader034/viewer/2022051823/5fed9929e0da1677527dd089/html5/thumbnails/6.jpg)
I guess I would build it this way!?!?
The Designer
• Creativity • Design
Standards • Assumptions
![Page 7: Session 9 Design/Build Projects...Session 9 Design/Build Projects Facilitator: Mariano Berrios, Florida DOT Participants: Darren O’Neill, Delaware DOT Amber Phillips, Georgia DOT](https://reader034.vdocument.in/reader034/viewer/2022051823/5fed9929e0da1677527dd089/html5/thumbnails/7.jpg)
Why did they design it this way ????
The Builder
• Resources • Materials • Innovation
![Page 8: Session 9 Design/Build Projects...Session 9 Design/Build Projects Facilitator: Mariano Berrios, Florida DOT Participants: Darren O’Neill, Delaware DOT Amber Phillips, Georgia DOT](https://reader034.vdocument.in/reader034/viewer/2022051823/5fed9929e0da1677527dd089/html5/thumbnails/8.jpg)
The Owner
Change orders Arguments Finger pointing Delays Increased costs
![Page 9: Session 9 Design/Build Projects...Session 9 Design/Build Projects Facilitator: Mariano Berrios, Florida DOT Participants: Darren O’Neill, Delaware DOT Amber Phillips, Georgia DOT](https://reader034.vdocument.in/reader034/viewer/2022051823/5fed9929e0da1677527dd089/html5/thumbnails/9.jpg)
Bring all groups together for one goal – a Successful Project
Owner
Designer Contractor
Design - Bid - Build
![Page 10: Session 9 Design/Build Projects...Session 9 Design/Build Projects Facilitator: Mariano Berrios, Florida DOT Participants: Darren O’Neill, Delaware DOT Amber Phillips, Georgia DOT](https://reader034.vdocument.in/reader034/viewer/2022051823/5fed9929e0da1677527dd089/html5/thumbnails/10.jpg)
Bring all groups together for one goal – a Successful Project
Owner
Design Build Team
Design - Build
![Page 11: Session 9 Design/Build Projects...Session 9 Design/Build Projects Facilitator: Mariano Berrios, Florida DOT Participants: Darren O’Neill, Delaware DOT Amber Phillips, Georgia DOT](https://reader034.vdocument.in/reader034/viewer/2022051823/5fed9929e0da1677527dd089/html5/thumbnails/11.jpg)
Bring all groups together for one goal – a Successful Project
Design Contractor
Owner
Construction Manager / General Contractors (CM/GC)
![Page 12: Session 9 Design/Build Projects...Session 9 Design/Build Projects Facilitator: Mariano Berrios, Florida DOT Participants: Darren O’Neill, Delaware DOT Amber Phillips, Georgia DOT](https://reader034.vdocument.in/reader034/viewer/2022051823/5fed9929e0da1677527dd089/html5/thumbnails/12.jpg)
Design Build
![Page 13: Session 9 Design/Build Projects...Session 9 Design/Build Projects Facilitator: Mariano Berrios, Florida DOT Participants: Darren O’Neill, Delaware DOT Amber Phillips, Georgia DOT](https://reader034.vdocument.in/reader034/viewer/2022051823/5fed9929e0da1677527dd089/html5/thumbnails/13.jpg)
Prescriptive – Tell contractor how to do it (means and methods) Performance – Tell the Design - Build Team what you want as a final product
![Page 14: Session 9 Design/Build Projects...Session 9 Design/Build Projects Facilitator: Mariano Berrios, Florida DOT Participants: Darren O’Neill, Delaware DOT Amber Phillips, Georgia DOT](https://reader034.vdocument.in/reader034/viewer/2022051823/5fed9929e0da1677527dd089/html5/thumbnails/14.jpg)
Benefits of Design Build
Single point of Responsibility Ability to Lower Overall costs Fast track the project delivery
![Page 15: Session 9 Design/Build Projects...Session 9 Design/Build Projects Facilitator: Mariano Berrios, Florida DOT Participants: Darren O’Neill, Delaware DOT Amber Phillips, Georgia DOT](https://reader034.vdocument.in/reader034/viewer/2022051823/5fed9929e0da1677527dd089/html5/thumbnails/15.jpg)
0 20 40 60 80 100
Transportation Healthcare
Water/Wastewater Higher Education
Municipal Shopping Center
Hotels/Motels Officies
Manufacturing
Industry Direction for Design Build
Growing Maintaining Shrinking
![Page 16: Session 9 Design/Build Projects...Session 9 Design/Build Projects Facilitator: Mariano Berrios, Florida DOT Participants: Darren O’Neill, Delaware DOT Amber Phillips, Georgia DOT](https://reader034.vdocument.in/reader034/viewer/2022051823/5fed9929e0da1677527dd089/html5/thumbnails/16.jpg)
Construction Manager / General Contractor (CM/GC)
![Page 17: Session 9 Design/Build Projects...Session 9 Design/Build Projects Facilitator: Mariano Berrios, Florida DOT Participants: Darren O’Neill, Delaware DOT Amber Phillips, Georgia DOT](https://reader034.vdocument.in/reader034/viewer/2022051823/5fed9929e0da1677527dd089/html5/thumbnails/17.jpg)
Federal Highway Administration – Alternative Contracting Methods
The contractor acts as a consultant during the design process and can offer constructability and pricing feedback on design options and can identify risks based on the contractor's established means and methods. As noted, this process also allows the owner to be an active participant during the design process and make informed decisions on design options based on the contractor's expertise.
http://www.fhwa.dot.gov/construction/contracts/acm/cmgc.cfm#proc
![Page 18: Session 9 Design/Build Projects...Session 9 Design/Build Projects Facilitator: Mariano Berrios, Florida DOT Participants: Darren O’Neill, Delaware DOT Amber Phillips, Georgia DOT](https://reader034.vdocument.in/reader034/viewer/2022051823/5fed9929e0da1677527dd089/html5/thumbnails/18.jpg)
Why States are considering/using CM/GC
• Inherent project risk • Opportunities for innovation • Need for specialized qualifications • Benefits from early procurement • Limited or fixed budget • Every day counts initiative ( EDC)
![Page 19: Session 9 Design/Build Projects...Session 9 Design/Build Projects Facilitator: Mariano Berrios, Florida DOT Participants: Darren O’Neill, Delaware DOT Amber Phillips, Georgia DOT](https://reader034.vdocument.in/reader034/viewer/2022051823/5fed9929e0da1677527dd089/html5/thumbnails/19.jpg)
Shortening Project Delivery
Preliminary Design
Detailed/Final Design Bid Construction
Preliminary Design
CM/GC Procurement
Detailed/Final Design
Construction
Preliminary Design
Design-Build Procurement
Detailed/Final Design
Construction
Design-Bid-Build
CM/GC
Design-Build
![Page 20: Session 9 Design/Build Projects...Session 9 Design/Build Projects Facilitator: Mariano Berrios, Florida DOT Participants: Darren O’Neill, Delaware DOT Amber Phillips, Georgia DOT](https://reader034.vdocument.in/reader034/viewer/2022051823/5fed9929e0da1677527dd089/html5/thumbnails/20.jpg)
2 Phase Process Phase 1
1. Owner selects
a. Design Firm b. Independent Cost Estimator (ICE) c. The Owner selects a CM/GC
![Page 21: Session 9 Design/Build Projects...Session 9 Design/Build Projects Facilitator: Mariano Berrios, Florida DOT Participants: Darren O’Neill, Delaware DOT Amber Phillips, Georgia DOT](https://reader034.vdocument.in/reader034/viewer/2022051823/5fed9929e0da1677527dd089/html5/thumbnails/21.jpg)
2 Phase Process
Phase 2 Owner asks CM/GC to submit final Construction Cost:
Two estimates: Designer-furnished Engineers Estimate Independent Cost Estimate (ICE)
Two Possible Outcomes: Owner gets fair price – Proceed with build Owner doesn’t get fair price – potential to then Bid the project
out to all contractors.
![Page 22: Session 9 Design/Build Projects...Session 9 Design/Build Projects Facilitator: Mariano Berrios, Florida DOT Participants: Darren O’Neill, Delaware DOT Amber Phillips, Georgia DOT](https://reader034.vdocument.in/reader034/viewer/2022051823/5fed9929e0da1677527dd089/html5/thumbnails/22.jpg)
How it Benefits Owners
Opportunities for innovation
Owners can own the design
Improved cost control
Improved design quality
Value Engineering on the front side
Schedule optimization
Collaboration
![Page 23: Session 9 Design/Build Projects...Session 9 Design/Build Projects Facilitator: Mariano Berrios, Florida DOT Participants: Darren O’Neill, Delaware DOT Amber Phillips, Georgia DOT](https://reader034.vdocument.in/reader034/viewer/2022051823/5fed9929e0da1677527dd089/html5/thumbnails/23.jpg)
GENERAL SUITABILITY OF DELIVERY MODELS
Project Traits D-B-B CM/GC D-B
Risk Management Very limited Very effective Best for risk shifting
Collaboration w/Designer & Contractor
Very limited Very collaborative Moderate collaboration, contractual limitations
Price Certainty None, subject to over-runs and change orders
Very effective, early price certainty during project development
Very effective, early price certainty during project development
Schedule Acceleration/ Compression
No ability to overlap design & construction, can accelerate construction with A+B
Ability to overlap design & construction, ability to optimize schedule not just accelerate
Ability to overlap design & construction, very effective for accelerating project delivery
Construction Quality
Low bid can compromise quality
Very beneficial to building a quality project
Very beneficial to building a quality project
Comparison of Delivery Methods
![Page 24: Session 9 Design/Build Projects...Session 9 Design/Build Projects Facilitator: Mariano Berrios, Florida DOT Participants: Darren O’Neill, Delaware DOT Amber Phillips, Georgia DOT](https://reader034.vdocument.in/reader034/viewer/2022051823/5fed9929e0da1677527dd089/html5/thumbnails/24.jpg)
GENERAL SUITABILITY OF DELIVERY MODELS
Project Traits D-B-B CM/GC D-B
Innovation Design Innovation only, very limited opportunities for contractor innovation
Very effective for capturing design and construction innovation
Very effective for capturing design and construction innovation
Constructability
Very difficult to obtain construction input during design
Optimal delivery method for obtaining construction input before design is complete
Effective delivery method for obtaining construction input before design is complete
Owner Control High level control Optimal level of owner control
Somewhat limited owner control, more performance based outcome
Competitive Pricing High level Somewhat limited, competitive
markup not final project cost Good Competition, but usually limited to short-listed teams
Comparison of Delivery Methods
![Page 25: Session 9 Design/Build Projects...Session 9 Design/Build Projects Facilitator: Mariano Berrios, Florida DOT Participants: Darren O’Neill, Delaware DOT Amber Phillips, Georgia DOT](https://reader034.vdocument.in/reader034/viewer/2022051823/5fed9929e0da1677527dd089/html5/thumbnails/25.jpg)
Each project needs to consider which delivery method is right for that project
![Page 26: Session 9 Design/Build Projects...Session 9 Design/Build Projects Facilitator: Mariano Berrios, Florida DOT Participants: Darren O’Neill, Delaware DOT Amber Phillips, Georgia DOT](https://reader034.vdocument.in/reader034/viewer/2022051823/5fed9929e0da1677527dd089/html5/thumbnails/26.jpg)
Different owners view different criteria as more important
Initial cost Time Impacts Community Change orders Risk
![Page 27: Session 9 Design/Build Projects...Session 9 Design/Build Projects Facilitator: Mariano Berrios, Florida DOT Participants: Darren O’Neill, Delaware DOT Amber Phillips, Georgia DOT](https://reader034.vdocument.in/reader034/viewer/2022051823/5fed9929e0da1677527dd089/html5/thumbnails/27.jpg)
Challenges in Design Build and CM/GC
Lacks Standard Competitive Low Bids Selections Criteria is subjective Public Scrutiny of Selected firms/Teams
![Page 28: Session 9 Design/Build Projects...Session 9 Design/Build Projects Facilitator: Mariano Berrios, Florida DOT Participants: Darren O’Neill, Delaware DOT Amber Phillips, Georgia DOT](https://reader034.vdocument.in/reader034/viewer/2022051823/5fed9929e0da1677527dd089/html5/thumbnails/28.jpg)
Working Together can improve safety and avoid major problems !
![Page 29: Session 9 Design/Build Projects...Session 9 Design/Build Projects Facilitator: Mariano Berrios, Florida DOT Participants: Darren O’Neill, Delaware DOT Amber Phillips, Georgia DOT](https://reader034.vdocument.in/reader034/viewer/2022051823/5fed9929e0da1677527dd089/html5/thumbnails/29.jpg)
Noise Studies and Analysis in a non traditional project delivery method
![Page 30: Session 9 Design/Build Projects...Session 9 Design/Build Projects Facilitator: Mariano Berrios, Florida DOT Participants: Darren O’Neill, Delaware DOT Amber Phillips, Georgia DOT](https://reader034.vdocument.in/reader034/viewer/2022051823/5fed9929e0da1677527dd089/html5/thumbnails/30.jpg)
Typical Options 1) The State transportation agency secures permits and the
Design-Build Contractor is responsible for modifying and/or complying with permits
2) The State transportation agency secures some early action high risk permits and the Design-Build Contractor is responsible for modifying and complying with those permits as appropriate, as well as for obtaining the remaining permits
3) The Design-Build Contractor is responsible for obtaining and complying
![Page 31: Session 9 Design/Build Projects...Session 9 Design/Build Projects Facilitator: Mariano Berrios, Florida DOT Participants: Darren O’Neill, Delaware DOT Amber Phillips, Georgia DOT](https://reader034.vdocument.in/reader034/viewer/2022051823/5fed9929e0da1677527dd089/html5/thumbnails/31.jpg)
Balance the Risk – Topics for Discussion Local Environmental Agency acceptance
Typically states lean toward obtaining permits and NEPA
documents Right of way impacts could be affected depending on the size
and magnitude of mitigation. Design Build teams will try to engineer out the feasible or
reasonableness requirements thus saving lots of $$ Commitments to communities may be challenged
![Page 32: Session 9 Design/Build Projects...Session 9 Design/Build Projects Facilitator: Mariano Berrios, Florida DOT Participants: Darren O’Neill, Delaware DOT Amber Phillips, Georgia DOT](https://reader034.vdocument.in/reader034/viewer/2022051823/5fed9929e0da1677527dd089/html5/thumbnails/32.jpg)
Thank You
DBIA www.dbia.org
Microsoft Clipart www.google.com
http://www.fhwa.dot.gov/construction/cqit/cm.cfm
![Page 33: Session 9 Design/Build Projects...Session 9 Design/Build Projects Facilitator: Mariano Berrios, Florida DOT Participants: Darren O’Neill, Delaware DOT Amber Phillips, Georgia DOT](https://reader034.vdocument.in/reader034/viewer/2022051823/5fed9929e0da1677527dd089/html5/thumbnails/33.jpg)
A Delicate Balance Amber Phillips GA DOT
Design Build & Noise
![Page 34: Session 9 Design/Build Projects...Session 9 Design/Build Projects Facilitator: Mariano Berrios, Florida DOT Participants: Darren O’Neill, Delaware DOT Amber Phillips, Georgia DOT](https://reader034.vdocument.in/reader034/viewer/2022051823/5fed9929e0da1677527dd089/html5/thumbnails/34.jpg)
Types Of Design Build Projects
• Design Build – A contract that is let and awarded to a Design-
Build Team who designs and constructs the project.
• Design Build Finance (Public Private Partnership (P3)) – A contract that is let and awarded to a
Developer/Private Concessionaire who designs, finances and constructs the project.
![Page 35: Session 9 Design/Build Projects...Session 9 Design/Build Projects Facilitator: Mariano Berrios, Florida DOT Participants: Darren O’Neill, Delaware DOT Amber Phillips, Georgia DOT](https://reader034.vdocument.in/reader034/viewer/2022051823/5fed9929e0da1677527dd089/html5/thumbnails/35.jpg)
Approach • Study Noise Impacts in NEPA with a
reasonable assumed design. Identify Likely walls
• Reevaluate for revised design/location • Conduct Public Outreach • In Practice it is not always this straight
forward!
![Page 36: Session 9 Design/Build Projects...Session 9 Design/Build Projects Facilitator: Mariano Berrios, Florida DOT Participants: Darren O’Neill, Delaware DOT Amber Phillips, Georgia DOT](https://reader034.vdocument.in/reader034/viewer/2022051823/5fed9929e0da1677527dd089/html5/thumbnails/36.jpg)
Challenges • Noise Policy
– Differing Interpretations – Fitting D/B Projects into the mold for Traditional
Design Bid Build Projects
• Public Involvement – Timing of Outreach vs Timing of Construction Areas
• Future Projects – Potential Conflicts with Wall Placement, Public
Outreach, and Commitments
![Page 37: Session 9 Design/Build Projects...Session 9 Design/Build Projects Facilitator: Mariano Berrios, Florida DOT Participants: Darren O’Neill, Delaware DOT Amber Phillips, Georgia DOT](https://reader034.vdocument.in/reader034/viewer/2022051823/5fed9929e0da1677527dd089/html5/thumbnails/37.jpg)
Solutions • Policy Clarification
– Update Policy to close interpretation loop holes, make sure all policies, design, procedures, etc. do not conflict.
– Contract wording • Close Teamwork
– Good communication – Joint Team Meetings – Work closely with FHWA
![Page 38: Session 9 Design/Build Projects...Session 9 Design/Build Projects Facilitator: Mariano Berrios, Florida DOT Participants: Darren O’Neill, Delaware DOT Amber Phillips, Georgia DOT](https://reader034.vdocument.in/reader034/viewer/2022051823/5fed9929e0da1677527dd089/html5/thumbnails/38.jpg)
Conclusion • In Georgia more Complex Projects are moving
to Design Build • We are Updating our Noise Policies to cover
Design Build rather than only covering Design Bid Build.
• Learning from each unique situation strengthens the Process
![Page 39: Session 9 Design/Build Projects...Session 9 Design/Build Projects Facilitator: Mariano Berrios, Florida DOT Participants: Darren O’Neill, Delaware DOT Amber Phillips, Georgia DOT](https://reader034.vdocument.in/reader034/viewer/2022051823/5fed9929e0da1677527dd089/html5/thumbnails/39.jpg)
Noise Barrier Design Challenges with Florida’s Design-Build and Public-Private Partnership Projects
Mariano Berrios Environmental Programs Coordinator
I-75 Express Noise Barrier
CEE Noise Practitioners Summit 2015 October 21-22, 2015
Baltimore, MD
Credits: Jim Mykytka – RS&H Tampa
![Page 40: Session 9 Design/Build Projects...Session 9 Design/Build Projects Facilitator: Mariano Berrios, Florida DOT Participants: Darren O’Neill, Delaware DOT Amber Phillips, Georgia DOT](https://reader034.vdocument.in/reader034/viewer/2022051823/5fed9929e0da1677527dd089/html5/thumbnails/40.jpg)
Design-Build (DB)/Public-Private Partnerships (PPP) Projects
• General Objectives • Compress Design and
Construction Schedules! • Bonuses for Early Completion
• Penalties for Late Completion
• Promotes Innovations! • Reduces Costs of Providing
Infrastructure Improvements! • FDOT’s Cost Savings Initiative
(CSI) Program • Contractor receives 50% of the
net reduction in cost savings
![Page 41: Session 9 Design/Build Projects...Session 9 Design/Build Projects Facilitator: Mariano Berrios, Florida DOT Participants: Darren O’Neill, Delaware DOT Amber Phillips, Georgia DOT](https://reader034.vdocument.in/reader034/viewer/2022051823/5fed9929e0da1677527dd089/html5/thumbnails/41.jpg)
Noise Abatement Considerations for DB/PPP Projects
• Make sure RFPs accurately identifies the noise barrier requirements!
• Tendency for DB Firms to evaluate designs that eliminate or modify recommended noise barriers to reduce their bids
• FDOT is responsible for any additional noise/barrier analysis required during the DB Process!
D/B teams cannot perform environmental re-evaluations!
![Page 42: Session 9 Design/Build Projects...Session 9 Design/Build Projects Facilitator: Mariano Berrios, Florida DOT Participants: Darren O’Neill, Delaware DOT Amber Phillips, Georgia DOT](https://reader034.vdocument.in/reader034/viewer/2022051823/5fed9929e0da1677527dd089/html5/thumbnails/42.jpg)
DB/PPP Projects
• Biggest Challenges • Accurately defining RFP noise
requirements
• Inevitable design changes during DB/PPP process require iterative noise analyses to end up with an effective noise barrier design
• Major Reconstruction Projects have a higher potential for design changes affecting the effectiveness of noise barriers • Mainline and Ramp Profiles
• Ramp Alignments and Gores
• MSE Wall Locations
• Cross Slopes
![Page 43: Session 9 Design/Build Projects...Session 9 Design/Build Projects Facilitator: Mariano Berrios, Florida DOT Participants: Darren O’Neill, Delaware DOT Amber Phillips, Georgia DOT](https://reader034.vdocument.in/reader034/viewer/2022051823/5fed9929e0da1677527dd089/html5/thumbnails/43.jpg)
Noise Barriers and DB/PPP Projects
• Project noise analyst should be involved from the procurement phase through the design phase! • Involved in the DB RFP Development
• Involved in the Evaluation of Alternative Technical Concepts (ATCs) if changes to Noise Barriers are proposed • Approval Process for Proposed Deviations
from the RFP
• Roadway and Structures Plans Reviews
• Noise barrier RFP requirements related to location are based on PD&E statement of likelihood and subsequent design level commitments
![Page 44: Session 9 Design/Build Projects...Session 9 Design/Build Projects Facilitator: Mariano Berrios, Florida DOT Participants: Darren O’Neill, Delaware DOT Amber Phillips, Georgia DOT](https://reader034.vdocument.in/reader034/viewer/2022051823/5fed9929e0da1677527dd089/html5/thumbnails/44.jpg)
Request for Proposal (RFP) Development
• DB Standard RFP – Modified by Pre-Scoping Questions • http://www.dot.state.fl.us/construc
tion/DesignBuild/DBDocuments/DBDocsMain.shtm
• Guidance Materials for Conducting Noise Studies and Designing Noise Barriers • Plans Preparation Manual, Vol. 1,
Chapter 32 (Topic No. 625-000-007)
• Design Standard Indexes & Instruction to Designers 5200 – 5215
• PD&E Manual Part 2, Chapter 17 Noise
![Page 45: Session 9 Design/Build Projects...Session 9 Design/Build Projects Facilitator: Mariano Berrios, Florida DOT Participants: Darren O’Neill, Delaware DOT Amber Phillips, Georgia DOT](https://reader034.vdocument.in/reader034/viewer/2022051823/5fed9929e0da1677527dd089/html5/thumbnails/45.jpg)
RFP Development
• Don’t assume when it comes to developing noise requirements for DB RFPs
• Confirm that the Noise Study Report(s) to be attached to the RFP addresses all of the noise barrier requirements for the project including Aesthetics requirements!
• Are the barrier heights and limits reasonable and consistent along the project corridor?
• Were the heights and locations of the recommended noise barriers based on design level noise modeling including design survey data?
• Have all public involvement activities including those related to outdoor advertising sign conflicts related to noise barriers been completed?
• Has a preliminary constructability review been completed including potential drainage and utility conflicts?
• Are TNM files available for the project corridor to assess design changes if warranted?
![Page 46: Session 9 Design/Build Projects...Session 9 Design/Build Projects Facilitator: Mariano Berrios, Florida DOT Participants: Darren O’Neill, Delaware DOT Amber Phillips, Georgia DOT](https://reader034.vdocument.in/reader034/viewer/2022051823/5fed9929e0da1677527dd089/html5/thumbnails/46.jpg)
RFP Development
• Include a statement in the RFP that the horizontal limits and heights of the recommended noise barriers shall not be changed except as approved by the Department
• Identify minimum top wall elevations in RFP if applicable
• Include language to minimize changes to top wall elevations
• Require 100’ versus 500’ cross sections for preliminary and subsequent design submittals
• Require DB firms to provide unit costs for design and construction of noise barriers
• Require DB firms to provide both PDFs and electronic design files for review
![Page 47: Session 9 Design/Build Projects...Session 9 Design/Build Projects Facilitator: Mariano Berrios, Florida DOT Participants: Darren O’Neill, Delaware DOT Amber Phillips, Georgia DOT](https://reader034.vdocument.in/reader034/viewer/2022051823/5fed9929e0da1677527dd089/html5/thumbnails/47.jpg)
Confirming Limits of Recommended Noise Barriers in DB Design Plans
• Reviews of RFP and Design Phase Submittals (90%, 100% and RFC) – Roadway and Noise Barrier Plan Sets • Confirm Noise Barrier Types and Limits
• Confirm Heights & Top Wall Elevations
• Check Reasonableness of Top Wall Elevation Changes
• Horizontal and Vertical Roadway Changes
• Review of Cross Sections
• Review of Proposed Drainage Systems including Locations of Stormwater Ponds
![Page 48: Session 9 Design/Build Projects...Session 9 Design/Build Projects Facilitator: Mariano Berrios, Florida DOT Participants: Darren O’Neill, Delaware DOT Amber Phillips, Georgia DOT](https://reader034.vdocument.in/reader034/viewer/2022051823/5fed9929e0da1677527dd089/html5/thumbnails/48.jpg)
Design Plan Reviews
• Changes to ramp profiles can require modifications to barrier limits
• Sufficient noise barrier overlapping • 3 to 4 times distance between
barriers
• Check for changes to cross slopes
Shoulder Noise Barrier
Ground Mounted Noise Barrier
Station 273+00
Station 273+00
![Page 49: Session 9 Design/Build Projects...Session 9 Design/Build Projects Facilitator: Mariano Berrios, Florida DOT Participants: Darren O’Neill, Delaware DOT Amber Phillips, Georgia DOT](https://reader034.vdocument.in/reader034/viewer/2022051823/5fed9929e0da1677527dd089/html5/thumbnails/49.jpg)
Design Plan Reviews
• Review Locations of Changes in Top Wall Elevation • Property owner concerns related to
changing heights in the middle of parcels
• Confirm noise barriers extend beyond residential parcels
Initial Top Wall Elevations
Revised (Lowered) Top Wall Elevations
![Page 50: Session 9 Design/Build Projects...Session 9 Design/Build Projects Facilitator: Mariano Berrios, Florida DOT Participants: Darren O’Neill, Delaware DOT Amber Phillips, Georgia DOT](https://reader034.vdocument.in/reader034/viewer/2022051823/5fed9929e0da1677527dd089/html5/thumbnails/50.jpg)
RFP Development and Design Plan Reviews
• Consequences of a poorly written RFP can result in all sorts of issues • Schedule delays
• Potential claims
• Cost overruns
• Less effective noise barriers
• Public complaints
• Recommend noise analyst be actively involved throughout the DB Process!
![Page 51: Session 9 Design/Build Projects...Session 9 Design/Build Projects Facilitator: Mariano Berrios, Florida DOT Participants: Darren O’Neill, Delaware DOT Amber Phillips, Georgia DOT](https://reader034.vdocument.in/reader034/viewer/2022051823/5fed9929e0da1677527dd089/html5/thumbnails/51.jpg)
QUESTIONS
Jim Mykytka, RS&H, Inc. Brian Kirkpatrick P.E., RS&H, Inc.
Mariano Berrios, FDOT (Contributor)
![Page 52: Session 9 Design/Build Projects...Session 9 Design/Build Projects Facilitator: Mariano Berrios, Florida DOT Participants: Darren O’Neill, Delaware DOT Amber Phillips, Georgia DOT](https://reader034.vdocument.in/reader034/viewer/2022051823/5fed9929e0da1677527dd089/html5/thumbnails/52.jpg)
Noise Barrier Design/Build Projects: Lessons Learned AASHTO CEE Noise Practitioner Summit October 2015 Noel Alcala, OhioDOT
1
![Page 53: Session 9 Design/Build Projects...Session 9 Design/Build Projects Facilitator: Mariano Berrios, Florida DOT Participants: Darren O’Neill, Delaware DOT Amber Phillips, Georgia DOT](https://reader034.vdocument.in/reader034/viewer/2022051823/5fed9929e0da1677527dd089/html5/thumbnails/53.jpg)
Noise Barrier Design/Build Projects: Lessons Learned (Project Specific; Things to avoid) Bottom Of Wall Elevations In Analysis And DB Scope In Conflict With Field
Insufficient Wall Sf In Scope Or Buried Wall Sf Is Not Included In The Quantities
Inaccurate Noise Barrier Design Details In The Analysis.
Distance Offset Of Wall From EOP In Conflict With Field
Added Cost For A New Wall Can’t Be Added To DB Project. Must Be A Separate Project.
Existing Ground Elevation In Scope Is Different Than What DBT Surveyors Shot
Added Transparent Barrier Issue. Bottom Concrete Panel Too Tall
Existing Utilities Found To Be In Conflict With Proposed Noise Wall Location. Not Clearly Described In DB Scope. Utilities Need To Be Clearly Described And Relocations Addressed In The DB Scope, If There Is A Conflict.
Increased Sf For Smooth Tow Profile Rejected. Sf Evenly Distributed For Smoother TOWP. Added A Colored Sealer For The Panels. No Color On The Panels Suggestion Rejected.
2
![Page 54: Session 9 Design/Build Projects...Session 9 Design/Build Projects Facilitator: Mariano Berrios, Florida DOT Participants: Darren O’Neill, Delaware DOT Amber Phillips, Georgia DOT](https://reader034.vdocument.in/reader034/viewer/2022051823/5fed9929e0da1677527dd089/html5/thumbnails/54.jpg)
Noise Barrier Design/Build Projects: Lessons Learned (General) Design Changes Causes Delays And Contracting Issues
Fast Track Schedule, Hence, Reluctance To Address Minor Comments
Less Flexibility And Reluctance To Make Changes
Noise Wall Construction Plan Prep Schedule Is Unknown Until It Sells.
Less Review Time; Less Issues Get Caught
DOT Should Implement A Better System Of Checks And Balances.
DOT Should Negotiate To Retain The Ability To Make Minor Changes To Project Scope Without Incurring Major Additional Costs Or Granting Time Extensions.
We Identify Some Of These Items, Look At The Risk, Make A Decision On Whether Design Build Is Is Appropriate
3
![Page 55: Session 9 Design/Build Projects...Session 9 Design/Build Projects Facilitator: Mariano Berrios, Florida DOT Participants: Darren O’Neill, Delaware DOT Amber Phillips, Georgia DOT](https://reader034.vdocument.in/reader034/viewer/2022051823/5fed9929e0da1677527dd089/html5/thumbnails/55.jpg)
Session 9 - Questions Phillips, GA: What is the timing of Public Outreach to Vote
on Wall Desire? Normally it is conducted after final design due to unforeseen design issues that could come up prior to committing to constructing a wall. (Issues Design build projects start constructing in one area before design is done on another. The noise wall area may not be able to be truly evaluated if the wall traverses through a phase I and phase II area, making it impossible to answer questions such as wall location, height, and sometimes feasibility if they are still doing coring looking at moment slab, existing retaining walls to see if they can or can’t be re-constructed…etc.)
Polcak, MD: Discuss general experiences (good and bad) with design/build projects involving noise barriers.
![Page 56: Session 9 Design/Build Projects...Session 9 Design/Build Projects Facilitator: Mariano Berrios, Florida DOT Participants: Darren O’Neill, Delaware DOT Amber Phillips, Georgia DOT](https://reader034.vdocument.in/reader034/viewer/2022051823/5fed9929e0da1677527dd089/html5/thumbnails/56.jpg)
Session 9 - Questions Burcham, MO: What have states provided to contractors and
what sort of follow-up analysis has been done? For example, what kind of re-evaluations occur when design changes (how do you get them to do it, contractually)?
Newvine, OR: How do states make this work? Is there something in the project development process that leads to better outcomes when dealing with a Design/Build project?
For Public Private Partnerships (P3), who is writing the proposal? Who is responsible for reevaluations?