Massachusetts Water Resources Authority Presentation to the MWRA Board of Directors Shaft 5A Pipe Break May 6, 2010

Upload: trinhdat

Post on 09-May-2018

216 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: Shaft 5A Pipe Break - mwra.state.ma.us 5A Pipe Break May 6, 2010. 2 SYSTEM OVERVIEW. 3 ... – Stone & Webster Construction Company, Inc. ... 9 45 F Y 9 6 F Y 9 7 F Y 9 8 9 0 F

Massachusetts Water Resources Authority

Presentation to the

MWRA Board of Directors

Shaft 5A Pipe Break

May 6, 2010

Page 2: Shaft 5A Pipe Break - mwra.state.ma.us 5A Pipe Break May 6, 2010. 2 SYSTEM OVERVIEW. 3 ... – Stone & Webster Construction Company, Inc. ... 9 45 F Y 9 6 F Y 9 7 F Y 9 8 9 0 F

2

SYSTEM OVERVIEW

Page 3: Shaft 5A Pipe Break - mwra.state.ma.us 5A Pipe Break May 6, 2010. 2 SYSTEM OVERVIEW. 3 ... – Stone & Webster Construction Company, Inc. ... 9 45 F Y 9 6 F Y 9 7 F Y 9 8 9 0 F

3

Normal Flow

Page 4: Shaft 5A Pipe Break - mwra.state.ma.us 5A Pipe Break May 6, 2010. 2 SYSTEM OVERVIEW. 3 ... – Stone & Webster Construction Company, Inc. ... 9 45 F Y 9 6 F Y 9 7 F Y 9 8 9 0 F

4

Normal Flow

Page 5: Shaft 5A Pipe Break - mwra.state.ma.us 5A Pipe Break May 6, 2010. 2 SYSTEM OVERVIEW. 3 ... – Stone & Webster Construction Company, Inc. ... 9 45 F Y 9 6 F Y 9 7 F Y 9 8 9 0 F

5

Diverted Flow After Leak

Page 6: Shaft 5A Pipe Break - mwra.state.ma.us 5A Pipe Break May 6, 2010. 2 SYSTEM OVERVIEW. 3 ... – Stone & Webster Construction Company, Inc. ... 9 45 F Y 9 6 F Y 9 7 F Y 9 8 9 0 F

6

Shaft 5 Break Site

Page 7: Shaft 5A Pipe Break - mwra.state.ma.us 5A Pipe Break May 6, 2010. 2 SYSTEM OVERVIEW. 3 ... – Stone & Webster Construction Company, Inc. ... 9 45 F Y 9 6 F Y 9 7 F Y 9 8 9 0 F

7

INCIDENT OVERVIEW

Page 8: Shaft 5A Pipe Break - mwra.state.ma.us 5A Pipe Break May 6, 2010. 2 SYSTEM OVERVIEW. 3 ... – Stone & Webster Construction Company, Inc. ... 9 45 F Y 9 6 F Y 9 7 F Y 9 8 9 0 F

8

Surveillance Camera Captures Leak

Page 9: Shaft 5A Pipe Break - mwra.state.ma.us 5A Pipe Break May 6, 2010. 2 SYSTEM OVERVIEW. 3 ... – Stone & Webster Construction Company, Inc. ... 9 45 F Y 9 6 F Y 9 7 F Y 9 8 9 0 F

9

Changes in Flow

Page 10: Shaft 5A Pipe Break - mwra.state.ma.us 5A Pipe Break May 6, 2010. 2 SYSTEM OVERVIEW. 3 ... – Stone & Webster Construction Company, Inc. ... 9 45 F Y 9 6 F Y 9 7 F Y 9 8 9 0 F

10

Charles River Flow Impacts

Page 11: Shaft 5A Pipe Break - mwra.state.ma.us 5A Pipe Break May 6, 2010. 2 SYSTEM OVERVIEW. 3 ... – Stone & Webster Construction Company, Inc. ... 9 45 F Y 9 6 F Y 9 7 F Y 9 8 9 0 F

11

Immediate Response

• 10:01 AM - Loss of communication alarm from Shaft 5 received at Carroll Water Treatment Plant (CWTP)

• 10:05 AM - Chelsea Security calls CWTP to report that water discharge was observed on the camera at Shaft 5

• 10:05 & following initial notifications to and mobilization of MWRA management, operations, engineering, construction and support staff. Flow at Shaft 5 reported to have immediately gone from 200 mgd to 450 mgd

Page 12: Shaft 5A Pipe Break - mwra.state.ma.us 5A Pipe Break May 6, 2010. 2 SYSTEM OVERVIEW. 3 ... – Stone & Webster Construction Company, Inc. ... 9 45 F Y 9 6 F Y 9 7 F Y 9 8 9 0 F

12

Communications

• These parties were quickly provided by phone or e-mail with a preliminary assessment of the incident and the potential impacts:

– MWRA Staff– Board of Directors– Governors Office– Department of Public Health– Department of Environmental Protection– Fire Marshalls– MEMA– Service Area Communities

Page 13: Shaft 5A Pipe Break - mwra.state.ma.us 5A Pipe Break May 6, 2010. 2 SYSTEM OVERVIEW. 3 ... – Stone & Webster Construction Company, Inc. ... 9 45 F Y 9 6 F Y 9 7 F Y 9 8 9 0 F

13

Immediate Operational Response

• Increase plant flows (match flow to demand) to mitigate loss of storage in the Norumbega Reservoir

• Shut down Cosgrove Turbine to avoid potential impacts

• Metropolitan system operation stable and decision to continue flow through the break site

• Contact partial user communities and request use of local sources (Bedford, Woburn, Wakefield, Wellesley, Needham, Peabody, Wilmington, Stoughton)

• Coordinate/control tank fillings to regulate flow (Blue Hills, LoringRoad, etc.)

Page 14: Shaft 5A Pipe Break - mwra.state.ma.us 5A Pipe Break May 6, 2010. 2 SYSTEM OVERVIEW. 3 ... – Stone & Webster Construction Company, Inc. ... 9 45 F Y 9 6 F Y 9 7 F Y 9 8 9 0 F

14

Sudbury System/Chestnut Hill Emergency Pump Station

• Hydraulic grade lines below targets – fire protection

• Fear of catastrophic failure at break site

• Fear of loss of backpressure necessary to start Chestnut Hill Pumps Station and air intrusion in system

• Imminent loss of power at Shaft 5 resulting in significant delay if shut down

Page 15: Shaft 5A Pipe Break - mwra.state.ma.us 5A Pipe Break May 6, 2010. 2 SYSTEM OVERVIEW. 3 ... – Stone & Webster Construction Company, Inc. ... 9 45 F Y 9 6 F Y 9 7 F Y 9 8 9 0 F

15

Sudbury System/Chestnut Hill Emergency Pump Station

• May 1– Operated for 7 hours

• May 2– Operated for 8 hours

• Sudbury Aqueduct– Activated May 1, shut down May 4, 9:30 AM– Transferred approximately 90 million gallons

Page 16: Shaft 5A Pipe Break - mwra.state.ma.us 5A Pipe Break May 6, 2010. 2 SYSTEM OVERVIEW. 3 ... – Stone & Webster Construction Company, Inc. ... 9 45 F Y 9 6 F Y 9 7 F Y 9 8 9 0 F

16

Sudbury System

Page 17: Shaft 5A Pipe Break - mwra.state.ma.us 5A Pipe Break May 6, 2010. 2 SYSTEM OVERVIEW. 3 ... – Stone & Webster Construction Company, Inc. ... 9 45 F Y 9 6 F Y 9 7 F Y 9 8 9 0 F

17

Chestnut Hill

Page 18: Shaft 5A Pipe Break - mwra.state.ma.us 5A Pipe Break May 6, 2010. 2 SYSTEM OVERVIEW. 3 ... – Stone & Webster Construction Company, Inc. ... 9 45 F Y 9 6 F Y 9 7 F Y 9 8 9 0 F

18

Spot Pond

• Staffed, all valving reset and chlorine delivered May 1

• Could have provided another 30-40 million gallons per day

Page 19: Shaft 5A Pipe Break - mwra.state.ma.us 5A Pipe Break May 6, 2010. 2 SYSTEM OVERVIEW. 3 ... – Stone & Webster Construction Company, Inc. ... 9 45 F Y 9 6 F Y 9 7 F Y 9 8 9 0 F

19

Emergency Operations Center Received 4,162 Calls

Page 20: Shaft 5A Pipe Break - mwra.state.ma.us 5A Pipe Break May 6, 2010. 2 SYSTEM OVERVIEW. 3 ... – Stone & Webster Construction Company, Inc. ... 9 45 F Y 9 6 F Y 9 7 F Y 9 8 9 0 F

20

PIPE BREAK AND REPAIR

Page 21: Shaft 5A Pipe Break - mwra.state.ma.us 5A Pipe Break May 6, 2010. 2 SYSTEM OVERVIEW. 3 ... – Stone & Webster Construction Company, Inc. ... 9 45 F Y 9 6 F Y 9 7 F Y 9 8 9 0 F

21

Coupling

Page 22: Shaft 5A Pipe Break - mwra.state.ma.us 5A Pipe Break May 6, 2010. 2 SYSTEM OVERVIEW. 3 ... – Stone & Webster Construction Company, Inc. ... 9 45 F Y 9 6 F Y 9 7 F Y 9 8 9 0 F

22

Pipe Repair Timeline

EVENT DATE/TIME

Leak Detected on Security Cameras May 1/10:00 amTotal Line Shut Down May 1/6:40 pmDewatering of Flooded Area Complete May 1/10:00 pmPipe and Repair Collar Preparation for welding begins May 1/10:00 pmPipe and Collar Preparation Completed May 2/9:15 amWelding of Collar on Bottom Half of Pipe Begins May 2/10:00 amWelding of Collar on Bottom Half of Pipe Complete May 2/10:00 pmChlorine Addition Complete May 2/11:00 pmWelding of Collar on Top Half of Pipe Begins May 2/11:00 pmConcrete Cradle Pour Begins May 2/MidnightConcrete Cradle Pour Complete May 3/12:45 amWelding of Collar on Top Half of Pipe Complete May 3/ 4:00 amFilling of Pipe Begins May 3/ 4:00 amFilling of Pipe Complete May 3/ 4:30 amPipe Pressure Test Begins May 3/ 4:30 amPipe Placed into Service May 3/ 5:30 amFlow Fully Restored May 3/ 6:15 am

Page 23: Shaft 5A Pipe Break - mwra.state.ma.us 5A Pipe Break May 6, 2010. 2 SYSTEM OVERVIEW. 3 ... – Stone & Webster Construction Company, Inc. ... 9 45 F Y 9 6 F Y 9 7 F Y 9 8 9 0 F

23

Dewatering

Page 24: Shaft 5A Pipe Break - mwra.state.ma.us 5A Pipe Break May 6, 2010. 2 SYSTEM OVERVIEW. 3 ... – Stone & Webster Construction Company, Inc. ... 9 45 F Y 9 6 F Y 9 7 F Y 9 8 9 0 F

24

Top of Pipe

Page 25: Shaft 5A Pipe Break - mwra.state.ma.us 5A Pipe Break May 6, 2010. 2 SYSTEM OVERVIEW. 3 ... – Stone & Webster Construction Company, Inc. ... 9 45 F Y 9 6 F Y 9 7 F Y 9 8 9 0 F

25

Rubber Gasket

Page 26: Shaft 5A Pipe Break - mwra.state.ma.us 5A Pipe Break May 6, 2010. 2 SYSTEM OVERVIEW. 3 ... – Stone & Webster Construction Company, Inc. ... 9 45 F Y 9 6 F Y 9 7 F Y 9 8 9 0 F

26

Pipe Joint

Page 27: Shaft 5A Pipe Break - mwra.state.ma.us 5A Pipe Break May 6, 2010. 2 SYSTEM OVERVIEW. 3 ... – Stone & Webster Construction Company, Inc. ... 9 45 F Y 9 6 F Y 9 7 F Y 9 8 9 0 F

27

Probing

Page 28: Shaft 5A Pipe Break - mwra.state.ma.us 5A Pipe Break May 6, 2010. 2 SYSTEM OVERVIEW. 3 ... – Stone & Webster Construction Company, Inc. ... 9 45 F Y 9 6 F Y 9 7 F Y 9 8 9 0 F

28

Installing New Strap

Page 29: Shaft 5A Pipe Break - mwra.state.ma.us 5A Pipe Break May 6, 2010. 2 SYSTEM OVERVIEW. 3 ... – Stone & Webster Construction Company, Inc. ... 9 45 F Y 9 6 F Y 9 7 F Y 9 8 9 0 F

29

Welding Strap in Place

Page 30: Shaft 5A Pipe Break - mwra.state.ma.us 5A Pipe Break May 6, 2010. 2 SYSTEM OVERVIEW. 3 ... – Stone & Webster Construction Company, Inc. ... 9 45 F Y 9 6 F Y 9 7 F Y 9 8 9 0 F

30

Welding Strap in Place

Page 31: Shaft 5A Pipe Break - mwra.state.ma.us 5A Pipe Break May 6, 2010. 2 SYSTEM OVERVIEW. 3 ... – Stone & Webster Construction Company, Inc. ... 9 45 F Y 9 6 F Y 9 7 F Y 9 8 9 0 F

31

New Strap Installation Completed

Page 32: Shaft 5A Pipe Break - mwra.state.ma.us 5A Pipe Break May 6, 2010. 2 SYSTEM OVERVIEW. 3 ... – Stone & Webster Construction Company, Inc. ... 9 45 F Y 9 6 F Y 9 7 F Y 9 8 9 0 F

32

Concrete Cradle Poured

Page 33: Shaft 5A Pipe Break - mwra.state.ma.us 5A Pipe Break May 6, 2010. 2 SYSTEM OVERVIEW. 3 ... – Stone & Webster Construction Company, Inc. ... 9 45 F Y 9 6 F Y 9 7 F Y 9 8 9 0 F

33

WATER QUALITY

Page 34: Shaft 5A Pipe Break - mwra.state.ma.us 5A Pipe Break May 6, 2010. 2 SYSTEM OVERVIEW. 3 ... – Stone & Webster Construction Company, Inc. ... 9 45 F Y 9 6 F Y 9 7 F Y 9 8 9 0 F

34

Activation of Chestnut Hill Pump Station – Water Quality

• Prior to activation, tested raw water at gatehouse for E. coli, VOC, SOC, metals

• Results available 24 hours later – all within health standards

• Chlorine tank truck delivered to site and treatment system prepared

• Hourly monitoring of chlorine residual near first meter/first customer

Page 35: Shaft 5A Pipe Break - mwra.state.ma.us 5A Pipe Break May 6, 2010. 2 SYSTEM OVERVIEW. 3 ... – Stone & Webster Construction Company, Inc. ... 9 45 F Y 9 6 F Y 9 7 F Y 9 8 9 0 F

35

Next Steps

• Worked with DEP to determine criteria for lifting the boil order– Agreed to conducting two rounds of coliform sampling each Sunday and

Monday (continuing as needed)– About 400 samples per round - Each round represents a normal week

of sampling

• Test results include total coliform, E. coli, and chlorine residual

• Agreed with DEP that two rounds of samples about 8 hours apart would allow boil order to be lifted

• Communities contacted Sunday morning to collect two rounds of samples

Page 36: Shaft 5A Pipe Break - mwra.state.ma.us 5A Pipe Break May 6, 2010. 2 SYSTEM OVERVIEW. 3 ... – Stone & Webster Construction Company, Inc. ... 9 45 F Y 9 6 F Y 9 7 F Y 9 8 9 0 F

36

Sample Collections Averaged 8 hours Between First and Second Rounds

Page 37: Shaft 5A Pipe Break - mwra.state.ma.us 5A Pipe Break May 6, 2010. 2 SYSTEM OVERVIEW. 3 ... – Stone & Webster Construction Company, Inc. ... 9 45 F Y 9 6 F Y 9 7 F Y 9 8 9 0 F

37

Boil Order Lifted

• Last of Sunday sample results were available at approximately 1 am Tuesday

• DEP set up emergency operations at the Chelsea facility to monitor results

• Two remaining community results (from Monday first round) available at 2:37 am and 6:30 am

• Boil order lifted at approximately 3 am Tuesday for 29 communities

• Boil order for all 30 communities lifted at about 7 am Tuesday

Page 38: Shaft 5A Pipe Break - mwra.state.ma.us 5A Pipe Break May 6, 2010. 2 SYSTEM OVERVIEW. 3 ... – Stone & Webster Construction Company, Inc. ... 9 45 F Y 9 6 F Y 9 7 F Y 9 8 9 0 F

38

Sampling Locations

Page 39: Shaft 5A Pipe Break - mwra.state.ma.us 5A Pipe Break May 6, 2010. 2 SYSTEM OVERVIEW. 3 ... – Stone & Webster Construction Company, Inc. ... 9 45 F Y 9 6 F Y 9 7 F Y 9 8 9 0 F

39

EMERGENCY RESPONSE PREPARATION

Page 40: Shaft 5A Pipe Break - mwra.state.ma.us 5A Pipe Break May 6, 2010. 2 SYSTEM OVERVIEW. 3 ... – Stone & Webster Construction Company, Inc. ... 9 45 F Y 9 6 F Y 9 7 F Y 9 8 9 0 F

40

Emergency Planning

• The MWRA has developed and maintains contingency or emergency plans for a wide range of events, including:

- 140 Individual Emergency Action Plans for each of the MWRA’s facilities and events

- Emergency Service Unit plans for responding to water contamination

- Specific plans for reactivating backup facilities

- Continuity of Operations Plan

- Emergency Plans for all MWRA Dams

- Integrated Contingency Plans for Deer Island and the Carroll Water Treatment Plant

- Spill Control Plans

Page 41: Shaft 5A Pipe Break - mwra.state.ma.us 5A Pipe Break May 6, 2010. 2 SYSTEM OVERVIEW. 3 ... – Stone & Webster Construction Company, Inc. ... 9 45 F Y 9 6 F Y 9 7 F Y 9 8 9 0 F

41

Training and Drills

• MWRA staff regularly participate in drills and training exercises

• These have included a 2006 exercise that specifically involved damage to Shaft 5 and the resulting need to activate the Sudbury Aqueduct

• Other training and exercises include:

– Major yearly exercises– Monthly Emergency Service Unit drills– Boom Deployment drills using boats

and other equipment– Mobile Disinfection Unit drills and

deployments– Notification Drills

Page 42: Shaft 5A Pipe Break - mwra.state.ma.us 5A Pipe Break May 6, 2010. 2 SYSTEM OVERVIEW. 3 ... – Stone & Webster Construction Company, Inc. ... 9 45 F Y 9 6 F Y 9 7 F Y 9 8 9 0 F

42

Emergency Equipment

Page 43: Shaft 5A Pipe Break - mwra.state.ma.us 5A Pipe Break May 6, 2010. 2 SYSTEM OVERVIEW. 3 ... – Stone & Webster Construction Company, Inc. ... 9 45 F Y 9 6 F Y 9 7 F Y 9 8 9 0 F

43

PRELIMINARY INVESTIGATION

Page 44: Shaft 5A Pipe Break - mwra.state.ma.us 5A Pipe Break May 6, 2010. 2 SYSTEM OVERVIEW. 3 ... – Stone & Webster Construction Company, Inc. ... 9 45 F Y 9 6 F Y 9 7 F Y 9 8 9 0 F

44

Forensics to Date and On Going

• As soon as the site (hole) was dewatered, MWRA Staff and Consultants and Contractor started:– Visual Inspection – Excavation below Pipe

• People under pipe doing inspection• Vactor removal of loose material under pipe• Probing into soil under pipe by geotechnical consultant

– State Police divers in Charles River looking for old collar – Ground penetrating radar and electromagnetic detectors to try locate

old collar – Soil removal from River, with stockpiling on adjacent land to inspect

for old collar or other information – Magnetic Metal Detectors – Metallurgical tests on any metal found

Page 45: Shaft 5A Pipe Break - mwra.state.ma.us 5A Pipe Break May 6, 2010. 2 SYSTEM OVERVIEW. 3 ... – Stone & Webster Construction Company, Inc. ... 9 45 F Y 9 6 F Y 9 7 F Y 9 8 9 0 F

Massachusetts Water Resources Authority

Page 46: Shaft 5A Pipe Break - mwra.state.ma.us 5A Pipe Break May 6, 2010. 2 SYSTEM OVERVIEW. 3 ... – Stone & Webster Construction Company, Inc. ... 9 45 F Y 9 6 F Y 9 7 F Y 9 8 9 0 F

46

Page 47: Shaft 5A Pipe Break - mwra.state.ma.us 5A Pipe Break May 6, 2010. 2 SYSTEM OVERVIEW. 3 ... – Stone & Webster Construction Company, Inc. ... 9 45 F Y 9 6 F Y 9 7 F Y 9 8 9 0 F

47

Page 48: Shaft 5A Pipe Break - mwra.state.ma.us 5A Pipe Break May 6, 2010. 2 SYSTEM OVERVIEW. 3 ... – Stone & Webster Construction Company, Inc. ... 9 45 F Y 9 6 F Y 9 7 F Y 9 8 9 0 F

48

Page 49: Shaft 5A Pipe Break - mwra.state.ma.us 5A Pipe Break May 6, 2010. 2 SYSTEM OVERVIEW. 3 ... – Stone & Webster Construction Company, Inc. ... 9 45 F Y 9 6 F Y 9 7 F Y 9 8 9 0 F

49

Page 50: Shaft 5A Pipe Break - mwra.state.ma.us 5A Pipe Break May 6, 2010. 2 SYSTEM OVERVIEW. 3 ... – Stone & Webster Construction Company, Inc. ... 9 45 F Y 9 6 F Y 9 7 F Y 9 8 9 0 F

50

Page 51: Shaft 5A Pipe Break - mwra.state.ma.us 5A Pipe Break May 6, 2010. 2 SYSTEM OVERVIEW. 3 ... – Stone & Webster Construction Company, Inc. ... 9 45 F Y 9 6 F Y 9 7 F Y 9 8 9 0 F

51

Page 52: Shaft 5A Pipe Break - mwra.state.ma.us 5A Pipe Break May 6, 2010. 2 SYSTEM OVERVIEW. 3 ... – Stone & Webster Construction Company, Inc. ... 9 45 F Y 9 6 F Y 9 7 F Y 9 8 9 0 F

52

Page 53: Shaft 5A Pipe Break - mwra.state.ma.us 5A Pipe Break May 6, 2010. 2 SYSTEM OVERVIEW. 3 ... – Stone & Webster Construction Company, Inc. ... 9 45 F Y 9 6 F Y 9 7 F Y 9 8 9 0 F

53

Page 54: Shaft 5A Pipe Break - mwra.state.ma.us 5A Pipe Break May 6, 2010. 2 SYSTEM OVERVIEW. 3 ... – Stone & Webster Construction Company, Inc. ... 9 45 F Y 9 6 F Y 9 7 F Y 9 8 9 0 F

54

Consultants and Sub-Consultants

• DESIGN CONSULTANT, MWRA Contract No. 5044 • Prime consultant:

– Sverdrup Corporation/Sverdrup Civil, Inc.• Sub-consultants:

– Boston Affiliates– Delon Hampton & Associates– Fay, Spofford & Thorndike, Inc– Goldberg Zoino & Associates– Jacobs Engineering– Lenz Engineering– Judith Nitsch Engineering, Inc– GPR (sub-sub to Goldberg Zoino)– Offset Prep– GZA Geo Environmental, Inc.

Page 55: Shaft 5A Pipe Break - mwra.state.ma.us 5A Pipe Break May 6, 2010. 2 SYSTEM OVERVIEW. 3 ... – Stone & Webster Construction Company, Inc. ... 9 45 F Y 9 6 F Y 9 7 F Y 9 8 9 0 F

55

Consultants and Sub-Consultants

• CONSTRUCTION MANAGEMENT & RESIDENT ENGINEERING CONSULTANT, MWRA Contract No. 5284

• Prime consultant: – Stone & Webster Civil and Transportation Services, Inc. (assigned to

Stone & Webster Massachusetts, Inc. and The Shaw Group)• Sub-consultants:

– Stone & Webster Construction Company, Inc.– Parsons Brinckerhoff Construction Services, Inc.– DMC Engineering, Inc.– H2O Engineering Consulting Associates, Inc.– Judith Nitsch Engineering, Inc.– Regina Villa Associates, Inc.– Toxikon– Hager GeoScience– Revet Laboratories

Page 56: Shaft 5A Pipe Break - mwra.state.ma.us 5A Pipe Break May 6, 2010. 2 SYSTEM OVERVIEW. 3 ... – Stone & Webster Construction Company, Inc. ... 9 45 F Y 9 6 F Y 9 7 F Y 9 8 9 0 F

56

Contractors and Sub-Contractors

• CONSTRUCTION CONTRACTOR, MWRA Contract No. 6374• Prime Contractor:

– Shea-Traylor-Healy, Joint Venture • Sub-contractors:

– Barletta Engineering/Daniel O’Connell’s Sons– Harding & Smith– E.J. Smith Construction Corporation– E.T. & L. Construction Corporation– Determining if others

Page 57: Shaft 5A Pipe Break - mwra.state.ma.us 5A Pipe Break May 6, 2010. 2 SYSTEM OVERVIEW. 3 ... – Stone & Webster Construction Company, Inc. ... 9 45 F Y 9 6 F Y 9 7 F Y 9 8 9 0 F

57

Reviewing Other Projects

• Reviewed 28 Projects to date including other MetroWest Water Supply projects. The failed coupling is the only coupling of its type on the entire MWWST project and the ongoing Hultman Aqueduct Interconnections project

• 8 Projects used similar couplings under varying conditions

– Many existing locations have been retrofitted or included internal joint seals

– Many of the projects included low pressure lines

– Projects where couplings have been used will be evaluated for risk of failure depending on the findings related to the recent event

• Staff will continue to review additional projects since Depend-O-Lok couplings became available

Page 58: Shaft 5A Pipe Break - mwra.state.ma.us 5A Pipe Break May 6, 2010. 2 SYSTEM OVERVIEW. 3 ... – Stone & Webster Construction Company, Inc. ... 9 45 F Y 9 6 F Y 9 7 F Y 9 8 9 0 F

58

HULTMAN REHABILITATION

Page 59: Shaft 5A Pipe Break - mwra.state.ma.us 5A Pipe Break May 6, 2010. 2 SYSTEM OVERVIEW. 3 ... – Stone & Webster Construction Company, Inc. ... 9 45 F Y 9 6 F Y 9 7 F Y 9 8 9 0 F

59

Hultman Aqueduct Rehabilitation and Interconnections

• Two construction contracts

– CP-6A Lower Hultman – under construction• Phase 1: Shaft 4 to Norumbega Covered Storage (9/2009-

9/2011) • Phase 2: Norumbega Covered Storage to Shafts 5/5A and W

(10/2011-9/2014)

– CP-6B Upper Hultman – to be designed • Rehab Hultman from Shaft C to Shaft 4• Rehab Shaft 4 Top of Shaft Structure• (5/2012-5/2014)

Page 60: Shaft 5A Pipe Break - mwra.state.ma.us 5A Pipe Break May 6, 2010. 2 SYSTEM OVERVIEW. 3 ... – Stone & Webster Construction Company, Inc. ... 9 45 F Y 9 6 F Y 9 7 F Y 9 8 9 0 F

60

CP-6A Hultman Aqueduct Rehabilitation and Interconnections with MetroWest Tunnel

Page 61: Shaft 5A Pipe Break - mwra.state.ma.us 5A Pipe Break May 6, 2010. 2 SYSTEM OVERVIEW. 3 ... – Stone & Webster Construction Company, Inc. ... 9 45 F Y 9 6 F Y 9 7 F Y 9 8 9 0 F

61

CP-6A Project Scope and Schedule

• Inspect and rehabilitate 13.5 miles of Hultman Aqueduct and appurtenances

• 4 new interconnections between the Hultman Aqueduct and the MWWST

• 6 new valves on Hultman Branch at River Road in Weston

• Current Project Schedule: September 2009 – September 2014

Page 62: Shaft 5A Pipe Break - mwra.state.ma.us 5A Pipe Break May 6, 2010. 2 SYSTEM OVERVIEW. 3 ... – Stone & Webster Construction Company, Inc. ... 9 45 F Y 9 6 F Y 9 7 F Y 9 8 9 0 F

62

CP-6B Project Scope and Schedule

• Rehabilitate Hultman Aqueduct and appurtenances from Shaft C to Shaft 4

• Rehabilitate Shaft 4 Top of Shaft Structure

• Current Project Schedule: May 2012 – May 2014

CP-6A Project Scope and Schedule

Page 63: Shaft 5A Pipe Break - mwra.state.ma.us 5A Pipe Break May 6, 2010. 2 SYSTEM OVERVIEW. 3 ... – Stone & Webster Construction Company, Inc. ... 9 45 F Y 9 6 F Y 9 7 F Y 9 8 9 0 F

63

CP-6A Current Sequence of Work

• Designed to minimize number of sections that are unavailable at any given time.

• Maintain uninterrupted service to customers during normal operation.

– Valves need to be added at the interconnection between the Hultman 84-in Branch and WASM 3 at River Road in Weston prior to working on Hultmaneast of Norumbega.

– Valve work at River Road in Weston must be completed during low demand winter months

– Improvements must be made to the Waltham water distribution system to allow WASM 3 to be shut down during the River Road valve work

Page 64: Shaft 5A Pipe Break - mwra.state.ma.us 5A Pipe Break May 6, 2010. 2 SYSTEM OVERVIEW. 3 ... – Stone & Webster Construction Company, Inc. ... 9 45 F Y 9 6 F Y 9 7 F Y 9 8 9 0 F

64

Reassessment of Project Schedules for CP-6A & CP-6B

• A comprehensive reassessment of the sequence of work for CP-6A and CP-6B has begun with contractor, designer and MWRA staff. Factors being analyzed:

– Valve manufacturing lead time– Working additional shifts on weekends– Contractor resources– Reevaluating seasonal flow constraints– Coordination with other ongoing MWRA projects– Acceleration of CP-6B contract award– Risk of additional sections out of service for rehabilitation

Page 65: Shaft 5A Pipe Break - mwra.state.ma.us 5A Pipe Break May 6, 2010. 2 SYSTEM OVERVIEW. 3 ... – Stone & Webster Construction Company, Inc. ... 9 45 F Y 9 6 F Y 9 7 F Y 9 8 9 0 F

65

REDUNDANCY INITIATIVES

Page 66: Shaft 5A Pipe Break - mwra.state.ma.us 5A Pipe Break May 6, 2010. 2 SYSTEM OVERVIEW. 3 ... – Stone & Webster Construction Company, Inc. ... 9 45 F Y 9 6 F Y 9 7 F Y 9 8 9 0 F

66

Water Redundancy Spending

Water Redundancy Spending thru FY09 and Projected to FY20 and Beyond($ in Millions)

$1.7 $1.9 $1.0$5.5 $4.4 $4.0

$11.4

$68.7

$104.6

$159.7

$128.9

$114.9

$104.8

$87.3

$40.2

$31.1

$20.1$25.1

$38.3

$47.7

$97.8

$85.7

$53.0

$34.9$43.2

$91.7

$36.1 $34.3$33.7

$42.8$39.0

$27.9

$0.0

$20.0

$40.0

$60.0

$80.0

$100.0

$120.0

$140.0

$160.0

$180.0

FY90FY91FY92FY93FY94FY95FY96FY97FY98FY99FY00FY01FY02FY03FY04FY05FY06FY07FY08FY09FY10FY11FY12FY13FY14FY15FY16FY17FY18FY19FY20

Beyon

d FY20

Average Annual Spending from FY97 through FY10 is

$70.7 Million