shakopee west end study

Upload: brad-tabke

Post on 06-Jul-2018

229 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/18/2019 Shakopee West End Study

    1/45

  • 8/18/2019 Shakopee West End Study

    2/45

    ACKNOWLEDGEMENTS

    In the Spring of 2015, the City of Shakopee

    initiated a process to complete a master plan for an

    approximately 850 acre area in western Shakopee

    and Jackson Township. This area is the next logical

    area for future municipal growth. The purpose

    of the land use study is to determine optimal

    mix of land uses within the area and to provide

    a preliminary guide to the future installation of

    infrastructure (roads, sanitary sewer, potable water,

    and storm water) that will help facilitate growth in

    the area.

     To complete the study, the City of Shakopee

    retained the services of Hoisington Koegler

    Group Inc., a planning and landscape architectureconsulting firm based in Minneapolis, working

    in collaboration with SRF Consulting Group,

    a multidisciplinary consulting firm based in

    Plymouth.

     The project began in April of 2015.

     The final study was accepted by the City Council on

    _______________, 2016.

     The project was overseen and managed by KyleSobota, Senior Planner with the City of Shakopee.

    Figure 1: Project Area Context 1Figure 2: Property Ownership 3

    Figure 3: Slope Percentages Throughoutthe Project Area 4

    Figure 4: Existing Roadway FunctionalClassification 6

    Figure 5: Existing Sanitary Sewer Utilities 7

    Figure 6: Drinking Water Utilities 8

    Table 1: Regulatory Matrix ForStorm Water Treatment 9

    Figure 7: Stormwater Features 10

    Figure 8: Utilities Summary Diagram 11

    Figure 9: Future Land Use Plan 13

    Figure 10: Existing Zoning Map(City of Shakopee) 15

    Table 2: THRIVE MSP 2040 DevelopmentProjections for Shakopee(Current as of 2015) 19

    Figure 11: Existing Vacant Land in Shakopee 19

    Figure 12: Land Use Master Plan 22

    Table 3: Development Summary 23Figure 13: Proposed Parks & Open Space 26

    Figure 14: Ridge Feature & Land UseInteraction 27

    Table 4: Stormwater BMP FootprintBased on Development Program 29

    Figure 15: Phasing of Infrastructure 30

    Figure 16: Proposed TransportationInfrastructure & Access Points 31

    Table 5: MnDOT Access Management

    Guidelines 32

    Table 6: Scott County AccessManagement Guidelines 33

    Table 7: Four Levels of FunctionalClassification 33

    Figure 17: Right-of-Way Sections 34

    Figure 18: Development Phasing Concept 37

    Figure 19: Opportunities for HigherDensity Housing Dependingon Market Demand 43

    CONTENTS

    01 | INTRODUCTION + PROCESS 1

    02 | PROJECT AREA DESCRIPTION 3

    03 | POLICY DIRECTION GUIDING DOCUMENTS 13

    04 | MASTE R PLAN CONCEPT 21

    05 | IMPLEMENTATION STRATEGIES  39

    TABLES + FIGURES

  • 8/18/2019 Shakopee West End Study

    3/45

    1

    I   N T R  O  D  U  C T 

    I    O N 

    +P R  O  C E  S  S 

    W E S T E R N S H A K O P E E J A C K S O N T O W N S H I P L A N D U S E S T U D Y & M A S T E R P L A NDRAFT

    01 | I N T R O D U C T I O N + P R O C E S S

    PURPOSE AND PROCESS

     The Western Shakopee/Jackson Township Land Use Study and Master Plan

    was initiated to coordinate development potential and public improvementneeds within an undeveloped portion of Western Shakopee and a portion of

    Jackson Township. The master planning process conducted in 2015 included

    conversations and meetings with larger land owners within the project area in

    addition to key agencies: Jackson Township, MnDOT, Scott County, Shakopee

    Public Utilities, and the various departments within the City of Shakopee.

    Historically, a number of planning concepts have been explored by private land

    owners for portions of the project area, mostly the area within the current city

    limits. These concepts date back to 2005 and before in some cases. Propertyowner meetings revealed a lot of common concepts and understanding of

    issues over the years. This master plan carries many of these concepts forward,

    validates many assumptions, and moves many of the outstanding questions

    a little closer to clarity. The master planning process included exploring

    and evaluating a range of concepts and alternatives ultimately arriving at a

    preferred master plan concept which is the subject of this plan.

     The land use study seeks to illustrate the relationship between land uses and

    community systems needed to serve the development. Community systems

    include transportation (roads/transit/trails), sanitary sewer and potable water

    infrastructure, stormwater, and parks/open space networks.

    WHAT THE MASTER PLAN IS AND WHAT IT IS NOT

     The master plan establishes a land use pattern and development projection

    that informs the sizing (capacity) and location of key infrastructure. This master

    plan provides a basis for more detailed infrastructure planning and design that

    would ultimately provide information to update the City’s Capital Improvement

    Program (CIP). The master plan also informs implementation of broader city

    Figure 1: Project Area Context

     A 2005 developer submitted concept for a portion of the project area “The Bluffs at Marystown” 

    PROJECTAREA

  • 8/18/2019 Shakopee West End Study

    4/45

    2

        I    N    T    R    O    D    U    C    T    I    O    N

       +    P    R    O    C    E    S    S

    W E S T E R N S H A K O P E E J A C K S O N T O W N S H I P L A N D U S E S T U D Y & M A S T E R P L A N DRAFT

    policies regarding park and recreation systems,

    natural resource/open space preservation, storm

    water management approaches, and development/

    infrastructure phasing.

     This master plan is not an amendment to the

    Comprehensive Plan; however, the information

    and analysis contained within it may be used to

    evaluate upcoming comprehensive planning

    processes.

     The master plan is not a “law” or legal document.

     The master plan does not amend the current

    orderly annexation agreement between the City of

    Shakopee and Jackson Township nor does it initiate

    any annexation of lands in Jackson Township into

    the City of Shakopee. The master plan may be usedas a source of information to inform or evaluate

    such requests for annexation.

     The master plan does not “rezone” property. Official

    public hearings and ordinance adoption is required

    to rezone property. The master plan may inform or

    help to evaluate revisions or amendments to the

    City Zoning and Subdivision Ordinance. The master

    plan provides a basis for evaluating future zoning

    requests or re-zoning requests initiated by private

    land owners or developers.

    WHAT THE MASTER PLAN DOES

     The land use master plan serves the following

    functions:

     » The plan provides continuity across time

     » It is a means by which a community can

    balance competing private interests » It is the means by which a community can

    protect public investments

     » It allows communities to plan development in

    a way that protects valued resources

     » It provides guidance for shaping the

    appearance of districts or neighborhoods

    within the community

     » It promotes economic development

    » It provides justification for decisions

     » The process allows for stakeholder dialogue

    and expression of a collective vision

    Source: Adapted from an article by Gary Taylor, Iowa State

    University Extension Service

  • 8/18/2019 Shakopee West End Study

    5/45

    3

    P R  O  J  E  C T A R 

    E A 

     D E  S  C R I   P T I    O N 

    W E S T E R N S H A K O P E E J A C K S O N T O W N S H I P L A N D U S E S T U D Y & M A S T E R P L A NDRAFT

    02 | P R O J E C T A R E A D E S C R I P T I O N

    BOUNDARIES

     The project area consists of approximately 850 gross acres and is generally

    bound on the north by Vierling Drive, on the west by Old Brickyard Road (CR69), on the south by CSAH 78, and on the east by Marystown Road (CSAH 15).

    Approximately 67% of the project area (570 acres) is located within the City

    of Shakopee’s current city limits. The remainder (280 acres) is located within

    Jackson Township.

    PARCELS/PROPERTY OWNERSHIP

     The vast majority of property is owned by a handful of family estates.

    Some of the City of Shakopee holdings include Tahpah Park and remnants fromthe Old Brickyard Road (CR 69) and Highway 169 interchange construction. The

    remnant parcels are available for development.

    Green Acres (MS 273.111)

    A large percentage of the land holdings within the project area are enrolled

    in the Green Acres program. The Minnesota Green Acres Program provides

    property tax relief for owners of agricultural property in areas where the market

    value of land is being affected by development pressure, sale of recreational

    land, or other non-agricultural factors. Properties are enrolled in the program atthe request of the property owners through the county assessor. To be eligible

    properties must meet certain requirements including being at least 10 acres in

    size, or a nursery or greenhouse; and be primarily devoted to the production of

    agricultural products among other requirements.

    Once enrolled, property owners will pay real estate taxes based on the

    agricultural value of their land. The difference between the agricultural taxes

    and the higher value taxes is deferred until the property is sold or no longer

    qualifies for the Green Acre program. Once the property is sold, transferred or

    Figure 2: Property Ownership

    CSAH 16

    CSAH 78

        C    R    6    9

        C    S    A    H    1    5

    HWY 169

    VIERLING DR

    Project Area

    Shakopee City Limits

  • 8/18/2019 Shakopee West End Study

    6/45

  • 8/18/2019 Shakopee West End Study

    7/455

    P R  O  J  E  C T A R 

    E A 

     D E  S  C R I   P T I    O N 

    W E S T E R N S H A K O P E E J A C K S O N T O W N S H I P L A N D U S E S T U D Y & M A S T E R P L A NDRAFT

    no longer qualifies the deferred tax for the current

    tax payable year and two prior years must be

    paid to the county. In addition to local property

    taxes, special local assessments may be deferred

    while in Green Acres. Special assessments are due

    with interest accrued when the property is sold,

    transferred, or otherwise withdrawn from theprogram.

    TOPOGRAPHIC FEATURES/NATURALRESOURCES

    A large ridge line runs from the northeast portion

    of the property to the west central portion of the

    project area and continues beyond the project

    area to the west, see Figure 3. This ridge consistsof steep and severely steep slopes and wooded

    areas. The ridge itself has been minimally disturbed

    and only a few home sites have been built within

    it. A 2002 natural resource inventory studied the

    ridge line and in 2005 the City established the

    City of Shakopee Natural Resources Prioritization

    Matrix which categorized city resources into three

    categories: good, better, and best. The ridge line

    through the project area contains some of thegood and better resources in the City. A portion

    of the ridge like feature contains slopes exceeding

    18%. Some of these meet the definition of “bluff”

    as provided in the Natural Resources Corridor

    Design Criteria (NRCDC). The City of Shakopee

    Subdivision Ordinance requires application and

    adherence of these criteria. Anything meeting the

    requirements of a bluff or within the bluff impact

    zone is considered non-developable. Other steep

    slope areas (defined as averaging over 10%) are

    also subject to certain regulations under the

    NRCDC; however, steep slopes less than 18% that

    are not considered bluffs do not prohibit new

    development.

     The significance of the natural ridge line that

    extends through the project site is that it would

    be one of the largest intact woodlands left in

    Shakopee. It is considered high quality woodland

    based on the species present (oak, hickory, maple,

    etc) and the minimal impact from invasive species.

    A number of woods, draw like features, and rolling

    topography extends across the remainder of the

    site. The highpoint of the site is located on the

    south central tier of the project site.

    EXISTING LAND USES

    South of Highway 169, the project area consists of

    farmsteads and agriculture fields predominantly.

    A few scattered single family estate residents also

    exist. North of Highway 169, urban land uses exist

    including low and moderate density housing and

    public park facilities. Adjacent land uses within

    the City of Shakopee include similar urban land

    use patterns while unsewered lands adjacent the

    site are mostly similar ag uses with some rural

    residential land use patterns. A number of public

    facilities are adjacent the project area including

    churches, Jackson Town Hall, an elementary school

    and Fire Station.

    Farmstead in southern project area on CR 78

    Forested & agricultural land in the southwest project area

    Open field adjacent to Friendship Church

    http://www.shakopeemn.gov/home/showdocument?id=262http://www.shakopeemn.gov/home/showdocument?id=262http://www.shakopeemn.gov/home/showdocument?id=262http://www.shakopeemn.gov/home/showdocument?id=262

  • 8/18/2019 Shakopee West End Study

    8/456

        P    R    O    J    E    C    T    A    R    E    A    D

        E    S    C    R    I    P    T    I    O    N

    W E S T E R N S H A K O P E E J A C K S O N T O W N S H I P L A N D U S E S T U D Y & M A S T E R P L A N DRAFT

    TRANSPORTATION AND ROADS

    Roads serving the project area consist mostly of

    County Roads and limited local streets. Access to

    Highway 169 is available at two interchanges: one

    at Old Brickyard Road (CR 69) and one at Marystown

    Road (CSAH 15). Transit service currently does not

    extend to the project area; however, the recently

    constructed Marschall Road Transit Center is located

    less than two miles to the east of the project area.

    INFRASTRUCTURE AND UTILITIES

    Sanitary Sewer

    Existing sanitary sewer and water infrastructure is

    available to serve the site at its edges on the north

    and north east. A Metropolitan Council Sanitary

    sewer interceptor runs along the south side of

    Highway 169. The line runs largely within the

    highway ROW and thus any easement does not

    materially affect project development. Metropolitan

    Council Environmental Services (MCES) policy is

    that connections to the interceptor be through

    approved connection points via city sewer mains.

     The existing interceptor along the north propertyline is a two barrel forcemain (30” and 20” pipes).

    MCES does not allow for a direct connection into

    their forcemain as it is a pressurized system. The

    interceptor changes from forcemain to gravity

    sewer at Marystown Road.

    Potable Water

    Future water supply connections are available

    east of Marystown and south of Highway 169

    Figure 4: Existing Roadway Functional Classification

  • 8/18/2019 Shakopee West End Study

    9/457

    P R  O  J  E  C T A R 

    E A 

     D E  S  C R I   P T I    O N 

    W E S T E R N S H A K O P E E J A C K S O N T O W N S H I P L A N D U S E S T U D Y & M A S T E R P L A NDRAFT

    Figure 5: Existing Sanitary Sewer Utilities

    View of powerline at top of ridge

    Commercial land for sale in the eastern project area

    Existing CR 69 running north

    Gas Line

    Easement

  • 8/18/2019 Shakopee West End Study

    10/458

        P    R    O    J    E    C    T    A    R    E    A    D

        E    S    C    R    I    P    T    I    O    N

    W E S T E R N S H A K O P E E J A C K S O N T O W N S H I P L A N D U S E S T U D Y & M A S T E R P L A N DRAFT

    Figure 6: Drinking Water Utilities

    for the majority of the site. Existing facilities will

    adequately provide services to the portion of the

    project area that lies north of Highway 169 with

    minimal upgrades. Areas south of Highway 169 will

    require extending water supply infrastructure via

    existing connection points. Capital improvements

    made to provide potable water facilities forthe project area need to consider long term

    development implications beyond the project area

    consistent with the Future Facilities Plan and long

    term planning done by Shakopee Public Utilities

    (SPU). Future water system and utilities should be

    coordinated through both SPU and the city.

    Storm Water

     The project area spans two watershed agencies, theLower Minnesota River Watershed District and the

    Scott County Watershed Management Organization

    (WMO). The Lower Minnesota River Watershed

    District has rules defined in the Third Generation

    Watershed Management Plan, but defers plan

    review to Local Government Units. However, the

    Lower Minnesota River Watershed District should

    be notified about projects throughout the design

    process. The Scott County WMO also has rulesfor the incorporated areas of the project area.

    Furthermore, the City of Shakopee has stormwater

    management policies defined its Comprehensive

    Water Resources Management Plan 2012. This

    management plan has specific policies for the

    unincorporated Jackson annexation area.

    Each of these agencies have requirements for water

    quality treatment, the control of peak discharge

    Gas Line

    Easement

  • 8/18/2019 Shakopee West End Study

    11/459

    P R  O  J  E  C T A R 

    E A 

     D E  S  C R I   P T I    O N 

    W E S T E R N S H A K O P E E J A C K S O N T O W N S H I P L A N D U S E S T U D Y & M A S T E R P L A NDRAFT

    rates, and volume reduction. Due to the fact that

    the project area has several different regulatory

     jurisdictions, the most stringent rules were applied

    to determine the estimates for water quality

    treatment. See Table 1 for the regulatory matrix,

    with the most stringent requirements shown in

    bold.As development occurs, projects will be subject to

    the National Pollutant Discharge Elimination System

    (NPDES) Permit requirements. In addition, the

    project area drains to the Minnesota River, which

    is an impaired water and is within one mile of the

    project area. Thus, the Minnesota Pollution Control

    Agency will require that the Stormwater Pollution

    Prevention Plan (SWPPP) be submitted for review

    30 days before construction.

    Other notable requirements include:

     » No karst features, FEMA floodplain, or public

    waters were found within the project area.

    » Some small, isolated wetlands are shown on

    the National Inventory of Wetlands in some

    low lying areas and will need to be considered

    during the design phases of the development.

    » A Scott County Natural Area Corridor is located

    within a large portion of the project area;

    however, the land use concept recognizes this

    area by preserving the land for future parks

    and open spaces.

     » The proposed development is almost entirely

    (98%) located within a Drinking Water Supply

    Management Area (DWSMA) and the designer

    AGENCY RATE CONTROLWATER

    QUALITYVOLUME

    CONTROL

    EROSIONAND

    SEDIMENTCONTROL

    COMMENTS

        C    i   t   y   o    f    S    h   a    k   o   p   e   e

        C    i   t   y   o    f    S    h   a    k   o   p   e   e

    Shall not exceed 1/3 cfsper acre for 100-yearcritical duration events,

    but the minimum outletorifice must be at least an8-in opening to allow thedetention area to drawdown to within one footof the normal run-outelevation within 72 hours.

    Permanent pool

    volume at least2.5” rainfall overthe contributingdrainage area(assuming fulldevelopment).

        J   a   c    k   s   o   n    T   o   w   n   s    h    i   p

       a   n   n   e   x   a   t    i   o   n   a   r   e   a

    2-, 10-, and 100-year stormevents to presettlement

    rates with given CNs forsoil groups.

        L    M    R    W    D

    Shall not exceedpredevelopment conditionrunoff rates for the 1- or2-year, 10-year and 100-yr24-hour storm events

    Shall meetNPDES Permitrequirements

    0.5 in of newimpervioussurfaces,except whereinfeasible

    Shall meetNPDES Permitrequirements

        S   c   o   t   t    C   o   u   n   t   y

        W    M    O

    Unincorporated areas –discharge rates shall notexceed pre-settlementrates.

    Control .5 in ofrunoff for newimpervioussurfaces

    Additional

    rules: ScottCountyNatural AreaCorridor – Bluffconstraints

        N    P    D    E    S    /    M    P    C    A WQ Volume of

    1” of runoff fromnew impervioussurfaces shall betreated beforeinfiltration.

    At least 1” ofwater qualityvolume shallbe infiltratedwhereconditions

    allow.

    See NPDESPermit fortemporary andpermanentErosion ControlRequirements

    Table 1: Regulatory Matrix For Storm Water Treatment

  • 8/18/2019 Shakopee West End Study

    12/4510

        P    R    O    J    E    C    T    A    R    E    A    D

        E    S    C    R    I    P    T    I    O    N

    W E S T E R N S H A K O P E E J A C K S O N T O W N S H I P L A N D U S E S T U D Y & M A S T E R P L A N DRAFT

    should confirm with the City, watershed

    agency, and Minnesota Department of Health

    whether infiltration practices will be allowed.

     » The area below the ridge line south of

    Highway 169, may have poor drainage

    conveyance. Detailed planning and design

    of building and public improvements shouldconsider this issue early in the process.

    Private Utilities

    A major Excel Energy transmission line also spans

    the northern portion of the site south of Highway

    169. This transmission line includes a 240 easement

    that prohibits building development but would

    allow roads, parking area, landscaping, and storm

    water uses. Two gas lines also cross the propertyincluding an excel energy gas line running north/

    south through the center of the site and a Rahr

    Malting gas line running along the western edge of

    Marystown Road (CSAH 15).

    SUMMARY OF OPPORTUNITIES ANDCONSTRAINTS

    In summary, the project area offers a numberof opportunities and challenges. The ridge line

    and natural resources present the greatest site

    opportunity. Such features provide a desirable site

    amenity and one that could include an improved

    trail network for recreation purposes. Such trail

    and open space resources are a desirable amenity

    for neighborhood residential development as well

    as employment opportunities. The ridge line also

    presents a physical development barrier. Steep

    Figure 7: Stormwater Features

    Gas Line

    Easement

  • 8/18/2019 Shakopee West End Study

    13/451 1

    P R  O  J  E  C T A R 

    E A 

     D E  S  C R I   P T I    O N 

    W E S T E R N S H A K O P E E J A C K S O N T O W N S H I P L A N D U S E S T U D Y & M A S T E R P L A NDRAFT

    Figure 8: Utilities Summary Diagram

    RAHR Gas PipelineEasement

    slopes create challenges for road connections and

    development.

    Large parcels under common ownership presents

    opportunities for master planned communities

    and coordinated development. Proximity to utility

    (sewer and water) connections will dictate to a

    large degree the phasing and timing of futuredevelopment.

    Power line easements and gas easements create

    physical development barriers and in many cases,

    the locations of these easements in proximity to

    other physical barriers such as steep slopes or

    existing highways can often create challenges

    with how parcels are configured for development

    purposes.

    Coupled with the topographic challenges and

    various easements, gaining access from the

    regional roadway network becomes vary limited

    to key locations. Such access challenges can have

    an impact on key land uses. However, proximity to

    two key interchanges on Highway 169 and visibility

    from the corridor makes the northern portion of the

    project area well suited for larger retail uses in the

    eyes of developers and landowners.

  • 8/18/2019 Shakopee West End Study

    14/4512

        P    R    O    J    E    C    T    A    R    E    A    D

        E    S    C    R    I    P    T    I    O    N

    W E S T E R N S H A K O P E E J A C K S O N T O W N S H I P L A N D U S E S T U D Y & M A S T E R P L A N DRAFT

    THIS PAGE IS INTENTIONALLY LEFT BLANK

  • 8/18/2019 Shakopee West End Study

    15/45

  • 8/18/2019 Shakopee West End Study

    16/45

    14

        P    O    L    I    C    Y    D    I    R    E    C

        T    I    O    N

           G    U    I    D    I    N    G

        D    O    C    U    M    E    N    T    S

    W E S T E R N S H A K O P E E J A C K S O N T O W N S H I P L A N D U S E S T U D Y & M A S T E R P L A N DRAFT

    Scott County Comprehensive Plan guides the

    area south and east of the Old Brickyard Road

    (CR 69) and Highway 169 interchange as Urban

    Business Reserve, generally consistent with the City

    Comprehensive Plan.

    Parks, Trails, and Open Space

     The comprehensive plan establishes the following

    park categories:

    » Neighborhood Parks – 2 to 10 acres in size with

    a ¼ to ½ mile service radius.

     » Hybrid Park – 10 to 20 acres in size with a ½

    mile to 1 mile service radius. Intention is to

    create a larger amount of open space and

    more diversity in activities. Hybrid Parks could

    include an entire neighborhood.

     The Project Area is within a search area (Figure 3.5

    of the comprehensive plan) for future parkland and

    focus for this area is emphasized as an opportunity

    for an Active Park/Natural Resource park facility.

    For comparison purposes, national park standards

    include Neighborhood Parks – 2.2 acres per 1,000

    people to 6 acres per 1,000 people.

     The plan identifies a series of key “Tactics” including

    » 1.1c Provide system wide safe trail access

    within ¼ mile of all residents.

     » 1.2a Provide neighborhood parks within ½

    mile of homes.

     » 1.3a Review and enhance the current zoning

    ordinance requiring developers to dedicate

    trail easements to the City

    » 1.3b Strongly encourage that all trails not

    follow a road system.

    Roadways and Transportation

     The comprehensive plan depicts the extension

    of 17th Avenue (CSAH 16) through the site as

    a Collector street. A frontage road connecting

    Marystown Road (CSAH 15) with Old Brickyard

    Road (CR 69) was also envisioned at the time the

    plan was updated. Since the comprehensive plan

    has been completed, this connection has been re-

    evaluated and would likely serve as more of a local

    frontage road. Further evaluation of this concept

    poses many difficult challenges including: access

    to Marystown road and intersection controls, steep

    topography, parcel usability based on the impacta new road corridor would have on developable

    area, and navigating the existing utility easements

    in the corridor. Future land uses may warrant the

    need for a local frontage road. There are potential

    constraints with this endeavor that will likely make

    it challenging to construct and increase costs.

    ZONING ORDINANCE

     The majority of the project area is currently zoned

    to residential or commercial zoning districts. Within

    the City of Shakopee, the residential districts

    include the:

     » R1B Urban Residential district which

    allows single family detached or attached

    development at a maximum density of 5 units

    per acre.

    Search area map - Figure 3.5 of the City Comprehensive Plan

  • 8/18/2019 Shakopee West End Study

    17/45

  • 8/18/2019 Shakopee West End Study

    18/45

    16

        P    O    L    I    C    Y    D    I    R    E    C

        T    I    O    N

           G    U    I    D    I    N    G

        D    O    C    U    M    E    N    T    S

    W E S T E R N S H A K O P E E J A C K S O N T O W N S H I P L A N D U S E S T U D Y & M A S T E R P L A N DRAFT

    development with municipal infrastructure is most

    efficiently coordinated.

    SUBDIVISION ORDINANCE AND THENATURAL RESOURCES CORRIDOR

    Sect. 12.24 Design Criteria states that the City has

    established certain design criteria to which all

    divisions of land must conform. This includes the

    Natural Resources Corridor. Section 12.32 states

    that sidewalks and trail shall be provided where

    specified in the City’s sidewalk and trail plans.

    Section 12.34 addresses Park Land Dedication.

    A standard of one acre of parkland for every 75

    people is established. Population assumptions

    include: 3 persons per lot for Single-family and

    Duplex-Twin homes; 1 person per bedroom forApartments, Townhomes, Condominiums, other

    multiple family dwellings. For non-residential uses

    and plats, the subdivision ordinance requires that

    an amount of land equal to 10% of the buildable

    land as guided be dedicated for park land.

    ORDERLY ANNEXATION AGREEMENTOAA

    Approximately 1/3 of the project area is located

    within Jackson Township. An existing orderly

    annexation agreement is in place between Jackson

     Township and the City of Shakopee. Jackson

     Township has conducted recent fiscal impact study

    (Ehlers) to understand the impact on the township

    of future annexations. The study found that the

    land area within the project area will not have

    a significant impact on the township when it is

    annexed into Shakopee. Key points of consideration

    regarding the orderly annexation agreement are as

    follows:

     » Currently the Municipal Boundary Adjustment

    Unit (MBAU) of the Office of Administrative

    Hearings administers and adjudicates the

    system of municipal boundary adjustments.Consideration by the MBAU is not needed if an

    annexation occurs as stipulated in the OAA.

    » All land in the Township is subject to

    annexation according to the OAA. The City is

    limited to a maximum of 250 acres per year of

    City-initiated annexation area of developed

    and undeveloped property. The limit does not

    include publicly owned or properties exempt

    for local property taxes. (Sections I. 6 & IV.1)

     » Joint Board (Sections I. 13 -16) – Jackson/

    Shakopee Joint Orderly Annexation Board was

    established between the Township, City, and

    Scott County. Land Use and planning authority

    of the annexed land rests with the City once

    the MBAU orders the annexation. Prior to

    annexation, planning and land use authority

    for lands outside of the City rests with Scott

    County.

     » Property Owner Annexation Petition (Sections

    II. 2 & 4)

     -  Any landowner or combination of multiple

    landowners with contiguous property adjacent

    to the municipal boundary may be annexed.

    http://156.142.28.130/WebLink8/DocView.aspx?id=111296&dbid=0http://156.142.28.130/WebLink8/DocView.aspx?id=111306&dbid=0http://156.142.28.130/WebLink8/DocView.aspx?id=111306&dbid=0http://156.142.28.130/WebLink8/DocView.aspx?id=111296&dbid=0

  • 8/18/2019 Shakopee West End Study

    19/45

    1 7

    P  O L  I    C Y  D I   R E  C T I    O N 

     G  U I    D I   N  G 

     D  O  C  U ME N T  S 

    W E S T E R N S H A K O P E E J A C K S O N T O W N S H I P L A N D U S E S T U D Y & M A S T E R P L A NDRAFT

     -  Adjacent means 50 feet or more of the subject

    annexation area boundary is shared with the

    boundary of the City 

     » City Initiated Annexation (Sections II. 3, 7 & 8)

     - Undeveloped property – The City of Shakopee

    may annex undeveloped property or multiple

     properties which are at least 50% surrounded by

    the municipal boundary of the City based on the

     perimeter of the entire area to be annexed.

    - Developed Property – City may annex

    developed property or multiple properties which

    are completely surrounded by the municipal

    boundary of the City. The City must provide a

    minimum of one year notice. The pay back time

    on assessments for improvements associatedwith the annexation shall be for a period of not

    to exceed 10 years, unless requested by property

    owners for it to be extended.

    » Township Requested Annexation (Section

    IV. 2) – the township can require the City

    at any time to annex properties that are

    completely surrounded by the City. If this

    occurs, the City shall have a period of one year

    to initiate the annexation of the properties.

    No reimbursement shall be required and the

    annexation would not contribute to the area

    limitation for City initiated annexations.

    » Municipal Reimbursement (Section III. 1)

     - Reimburse for a period of two years of the

     proportional amount of taxes that would have

    been due the Township without annexation

    based on the assessed value of the annexed

     property as of January 2nd the year the parcel is

    annexed.

     - Reimbursement for publicly owned or local

     property tax exempt properties is not required.

    2014 Ehlers Annexation Fiscal Impact Analysis

    In 2014 Ehlers was engaged through Scott County

    to assist Jackson Township in evaluating how

    potential future annexations would affect the

     Town’s future property tax collections and overall

    finances. The objective was to determine a “tipping

    point” at which it is no longer financially feasible

    to operate as a separate unit of government. The

    analysis developed a set of 5 annexation “target”

    areas with which to evaluate the potential fiscalimpact of future annexation. Target Area B, which

    encompasses 7 parcels with 226 acres, is the

    portion of this project’s study area that falls in

    Jackson Township south of Highway 169. The area

    represents 3.1% of the Town’s total market value

    and 1.2% of the Town’s net tax capacity ($1,752 levy

    dollars). Relevant findings of the study include:

     » The low tax values on agricultural and green-

    acres designated parcels means that although

    the entire set of target areas evaluated in

    the Fiscal Impact Analysis comprised more

    than 1,600 acres, the total tax capacity of the

    75 parcels equaled only 26.4% of the Town’s

    existing tax base.

    » 2013 rates were 12.207% for Jackson Township

    and 41.996% for Shakopee

  • 8/18/2019 Shakopee West End Study

    20/45

    18

        P    O    L    I    C    Y    D    I    R    E    C

        T    I    O    N

           G    U    I    D    I    N    G

        D    O    C    U    M    E    N    T    S

    W E S T E R N S H A K O P E E J A C K S O N T O W N S H I P L A N D U S E S T U D Y & M A S T E R P L A N DRAFT

     » Estimating the fiscal impact of an annexation-

    driven reduction is complicated by the fact

    that the Town’s annual levy is generated from

    two sources: (a) the Town’s net tax capacity

    after its contribution of commercial tax

    based to the Fiscal Disparities (FD) pool and

    (b) its Fiscal Disparities distribution. Whileestimates can be made on how annexations

    will affect the Town’s levy and/or tax rate, it

    is difficult to know the impacts to the Fiscal

    Disparities distribution so the study assumed a

    proportional reduction.

    » The study found that the annexation of Target

    Area B would have an impact of 1.2% of tax

    base.

    » Analysis of budget expenditures indicate that

    the Town’s annual costs would not decrease

    notably through annexation. This means that

    reducing annual expenses to be a potentential

    fiscal response to annexation. The Town will

    likely have to either use fund balance and/or

    raise the tax rate.

    » Analysis found that if the Township wished

    to remain autonomous there was not an

    annexation scenario that would present the

    financial “tipping point” whereby it is no longer

    financially feasible for the Town to operate.

    THRIVE MSP 2040

    Shakopee is designated as a Suburban Edge

    community by the Metropolitan Council Regional

    Plan. This designation covers cities that experienced

    significant residential growth beginning in the

    1990s where there are still significant amounts

    of land for future development. Shakopee will

    be required to plan and stage development for

    forecasted growth through 2040 and beyond at

    overall average net densities of 3 to 5 dwelling

    units per acre. Jackson Township is designatedas Diversified Rural. The project area consists

    of lands in both categories. Because there is an

    existing orderly annexation agreement (OAA) in

    place, there is an expectation that the current

    designation of lands within Jackson Township may

    be re-designated to an urban designation. In order

    for this to occur a more detailed staging plan for

    orderly annexation needs to be completed.

    One of the components considered in community

    designation assignment implies that the Urban

    categories are in the MUSA (Metropolitan Urban

    Services Area) and the rural designations are not.

    Approximately 120 acres of the project area is not

    within the planned MUSA area (see Figure 10 which

    shows the current MUSA boundary.)

    MUSA is distinguished from the Rural Service Area.

    Community and land with MUSA receive a higherlevel of regional services in exchange for building

    higher levels of development that economically

    support the regional services. MUSA supported

    through investments such as regional wastewater

    services, regional highways, transit service, the

    Regional Park System, and programs that support

    redevelopment.

    Thrive MSP 2040 community designations

  • 8/18/2019 Shakopee West End Study

    21/45

    1 9

    P  O L  I    C Y  D I   R E  C T I    O N 

     G  U I    D I   N  G 

     D  O  C  U ME N T  S 

    W E S T E R N S H A K O P E E J A C K S O N T O W N S H I P L A N D U S E S T U D Y & M A S T E R P L A NDRAFT

    SHAKOPEE SCHOOL DISTRICT

     The Shakopee School District (ISD 720) currently

    has lands within the project area or immediately

    adjacent (Jackson Elementary) the project. At

    this time, there are no plans for additional school

    facilities in the project area. However, as residential

    growth occurs in the project area, additionaldemands will be placed on schools and the

    possibility of locating a school in the project area

    may be a future consideration.

    DEVELOPMENT PROJECTIONS ANDLAND DEMAND

    In 2012 Maxfield Research Inc. conducted a

    Commercial/Industrial Market Analysis for ScottCounty. The focus of the study was to estimate

    excess demand for commercial and industrial

    acreage in Scott County from 2012 to 2030.

    Scott County has a 2030 goal to employ 50%

    of the County’s labor force within Scott County.

    Absorption of commercial and industrial space

    is expected to expand between 2012 and 2020.

    1,500 acres will be needed (county-wide) to

    accommodate projected growth. The study

    generally indicated adequate land was available

    to accommodate growth demand through 2015,

    but additional lands would need to be guided to

    account for growth beyond 2015.

    Shakopee currently has less than 170 acres of land

    guided for commercial, business park, or industrial

    type uses, a portion of which is located in the

    project area along Highway 169.

    FORECAST YEAR HOUSEHOLDS POPULATION EMPLOYMENT

    2010 12,772 37,076 18,831

    2020 15,400 43,900 25,500

    2030 18,400 52,800 28,500

    2040 21,600 62,300 31,9002010-2040 Growth 8,828 25,224 13,069

    Table 2: THRIVE MSP 2040 Development Projections for Shakopee (Current as of 2015)

    Figure 11: Existing Vacant Land in Shakopee

  • 8/18/2019 Shakopee West End Study

    22/45

    20

        P    O    L    I    C    Y    D    I    R    E    C

        T    I    O    N

           G    U    I    D    I    N    G

        D    O    C    U    M    E    N    T    S

    W E S T E R N S H A K O P E E J A C K S O N T O W N S H I P L A N D U S E S T U D Y & M A S T E R P L A N DRAFT

     The Metropolitan Council Thrive MSP 2040 process

    provided development projections for the City of

    Shakopee, which are displayed in Table 2.

    RESIDENTIAL LAND DEMANDANALYSIS

    Maxfield Research also prepares periodic housing

    studies for Scott County communities. Using key

    assumptions from the Maxfield Research, and

    looking at recent building permit trends for the

    City of Shakopee, we have projected a demand

    for roughly 1,800 acres of residentially guided

    lands over the next 25 year period, to 2040. Using

    historical data and Maxfield Research assumptions,

    this figure can be split into 1,360 acres of low to

    moderate density guided lands and 440 acres of

    more moderate to high density guided lands (see

    Figure 11).

     The City of Shakopee currently has available for new

    development less than 200 acres of moderate to

    high density guided lands and nearly 2,000 acres of

    lower density guided lands. However, a significant

    portion (300-400 acres) of the lower density guided

    lands are in areas that are highly difficult to serve

    with municipal sanitary sewer and as such are likely

    beyond the 2040 planning horizon.

    Even if we assume some higher density housing

    will be absorbed within redevelopment areas more

    proximate to existing centers (such as downtown

    or key commercial nodes), there is a need to guidefuture moderate to high density housing areas in

    the city.

    Other factors to consider in planning new land

    areas for population or employment growth

    include the notion that not all property owners may

    be willing or interested in selling land. Furthermore,

    the City needs to make sure that the land supply

    available for development is planned ahead so that

    the supply is not so low that it affects land prices

    negatively.

     To adequately serve future demand for population

    and employment growth, Shakopee will need to

    add roughly 500 to 1,000 acres of land to the city

    within the next 25 years and absorb some future

    growth through redevelopment at higher densities

    near existing centers.

  • 8/18/2019 Shakopee West End Study

    23/45

    2 1

    MA  S T E R P L  A 

    W E S T E R N S H A K O P E E J A C K S O N T O W N S H I P L A N D U S E S T U D Y & M A S T E R P L A NDRAFT

    04 | MA S T E R P L A N C O N C E P T

     This land use plan is general in nature. It does not prescribe a specific

    development pattern nor does it dictate an architectural or design aesthetic. It

    does define key land use patterns and quantities, the major roadway network,

    a preferred land use and open space system, and general guidance for theextension of public infrastructure.

    GUIDING PRINCIPLES

     The land use pattern recommended works to balance market driven

    development demands, community wide vision and aspirations, and

    community planning principles. At the beginning of the process, a number of

    key principles were derived from existing policy plans as a means of guiding

    the master plan development:

     » Expand employment opportunities in areas with good transportation

    access and with compatible land use transitions.

    » Create desirable and sustainable neighborhoods with a range of housing

    types to meet a variety of lifestyle and economic needs.

    » Encourage an efficient land use pattern that optimizes both initial

    (capital) and ongoing (operations and maintenance) public infrastructure

    investments.

     » Balance traditional infrastructure systems with green infrastructure

    strategies to enhance ecological function of natural systems.

     » Protect and enhance natural features that provide opportunities for

    recreation, or contribute to the ecological, social, or cultural value of the

    landscape and built environment.

     » Promote a range of safe and efficient transportation options (auto, bike,

    walk, transit) that provide connection to local employment centers,

    commercial centers, downtown, schools, and parks, while anticipating

    multi-modal connections to the broader metro area.

  • 8/18/2019 Shakopee West End Study

    24/45

    22

        M

        A    S    T    E    R    P    L    A    N

    W E S T E R N S H A K O P E E J A C K S O N T O W N S H I P L A N D U S E S T U D Y & M A S T E R P L A N DRAFT

    Figure 12: Land Use Master Plan

    Access at Marystown Road near TH 169, the

    possibility of a frontage road, internal circulation,

    connection/access to the extension of CSAH 16,

    and development viability are all interdependent

    factors for this node. All factors are impacted by

    unique topography and natural features. The

    illustration provides an alternative that attempts

    to minimize impacts on the natural features and

    allow for a mix of land uses that would contribute

    to a sustainable neighborhood node. These

    alternatives do not meet access guidelines and

    would require variances from County and MNDOT

    policies. This alternative should be considered

    when development is proposed. Additional study

    and analysis will be necessary, once an ultimate

    land use is determined.0 500 1,000 2,000

    FEET

    0 500 1,000

    FEET

  • 8/18/2019 Shakopee West End Study

    25/45

    2 3

    MA  S T E R P L  A 

    W E S T E R N S H A K O P E E J A C K S O N T O W N S H I P L A N D U S E S T U D Y & M A S T E R P L A NDRAFT

    FUTURE LAND USEDESIGNATION

    TOTALACRES

    % OFTOTAL

    HOUSING UNITSCOMMERCIAL

    SQUARE FOOTAGE

    LOW HIGH LOW HIGH

    Low Density (SingleFamily - SF)

    134 22% 270 400 

    - -

    Medium Density(Small Lot SF)

    86 14% 260 430 

    - -

    Medium DensityMixed (Townhouse/Small Lot SF)

    81 13% 400 970 

    - -

    High DensityResidential (HDR)

    12 2% 300 370 

    - -

    Mixed Use (HDR/Retail)

    7 1% 160 200 44,300 73,800

    Retail 32 5% - - 207,100 345,200

    Mixed Use (Retail/Business Park)

    81 13% - - 883,400 1,236,800

    Parks & Open Space 120 20% - - - -

    ROW 50 8% - - - -

    GRAND TOTAL 603 100% 1,390 2,370 1,134,800 1,655,800

    AVG. RESIDENTIALDENSITY

    4.34 U/A 7.4 U/A

    Table 3: Development Summary

    DEVELOPMENT MAGNITUDE

     Table 3 represents a development summary that is

    based on the assumed residential densities outlined

    above and average floor area ratios (FAR – the ratio

    of gross usable square feet to the lot area) derived

    from an evaluation of area development projects

    and best management practices for commercialdevelopment.

    LAND USE

    For all residential land use categories, lot sizes and

    housing types are encouraged to be varied to the

    extent the market would support such variations.

    Adherence to general density ranges will ensure

    adequate transportation, infrastructure, and park/

    open space system planning.

    » Low Density (Single Family) – This land use

    category is most reflective of traditional

    detached single family housing. The

    development pattern here is typically a larger

    lot pattern with average densities in the 2 to 3

    units per acre range.

     » Medium Density Small Lot (Single Family) –

     This land use category provides for a moremoderate density ranging from 3 to 5 units per

    acre and thus a greater ability to vary housing

    types.

     » Medium Density Mixed (Townhouse/Small

    Lot Single Family) – This land use category

    bumps up the density range from 5 to 12

    units per acre and thus the greatest ability to

    vary housing types. This category begins to

  • 8/18/2019 Shakopee West End Study

    26/45

    24

        M

        A    S    T    E    R    P    L    A    N

    W E S T E R N S H A K O P E E J A C K S O N T O W N S H I P L A N D U S E S T U D Y & M A S T E R P L A N DRAFT

    Character precedent for low density development 

    Character precedent for medium density small lot development 

    Character precedent for medium density mixed development 

    Character precedent for high density residential development 

    Character precedent for retail development 

    Character precedent for mixed use (HDR/retail) development 

    Character precedent for mixed use (retail/business park) development 

    introduce an attached side by side housing

    product or smaller vertical stacked housing

    types.

    » High Density Residential – This category

    excludes detached single unit housing types.

    Instead a vertical oriented stacked housing

    product will be the primary housing type inthis district. Attached side by side with tuck

    under garages may also be mixed into this

    category. The density range in high density

    residential category will generally exceed 12

    units per acre and may range to be greater

    than 30 acres depending on market forces.

    » Retail – this land use is predominantly

    oriented towards the sale of goods and

    services and supporting professional offices.

    Retail areas could include institutions such

    as post secondary/tech colleges, post offices,

    museums, or other similar uses. In this land use

    category, the typical pattern of development

    is for one or two story buildings with surface

    parking.

    Mixed Use is a term used to define land use

    patterns where uses might be market based and

    consist of one or the other identified use. Or, the

    uses might consist of a vertically oriented mixed use

    configuration; however, such building configuration

    is not perceived highly in the suburban market area

    represented in the project area. These categories

    are location specific and based on uncertainties

    surrounding property access , market conditions,

    and development timing.

  • 8/18/2019 Shakopee West End Study

    27/45

    2 5

    MA  S T E R P L  A 

    W E S T E R N S H A K O P E E J A C K S O N T O W N S H I P L A N D U S E S T U D Y & M A S T E R P L A NDRAFT

     » Mixed Use (HDR/Retail) – this category is

    applied near Marystown Road (CSAH 15) and

    Highway 169/17th Avenue (CR 16) extension.

    Uses may include all high density residential

    or all retail services. Alternatively, a multi-story

    building with commercial uses on ground

    floor and housing or office uses above could

    be a supported development configuration in

    this category.

     » Mixed Use (Retail/Business Park) – this

    category is applied to the southeast quadrant

    of Old Brickyard Road (CR 69) and Highway

    169. This land area is well suited to retail

    because of it’s visibility and proximity to

    the interchange at Highway 169 and Old

    Brickyard Road (CR 69). However, access is

    somewhat challenging and may lend more to

    a destination oriented use such as a business

    park. The area of approximately 50 acres could

    support a small business park, a retail, auto

    oriented power center, or a mix of both uses.

     This category also applies to the southwest

    quadrant of Vierling Drive.

    Both mixed use areas could include institutionssuch as post secondary/tech colleges, post offices,

    museums, or other similar uses.

    Character precedent of low density neighborhood with a public street fronting on open space.

    Bioretention integrated with park and trail system

  • 8/18/2019 Shakopee West End Study

    28/45

    26

        M

        A    S    T    E    R    P    L    A    N

    W E S T E R N S H A K O P E E J A C K S O N T O W N S H I P L A N D U S E S T U D Y & M A S T E R P L A N DRAFT

    PARK AND OPEN SPACE NETWORK

     The ridge line is a high valued amenity. The concept

    for parks and open space focuses on the ridge line,

    but also provides for a hybrid park that will serve

    much of the new residential growth in the district

    with Neighborhood Park like facilities and an open

    play field area. To best serve the neighborhoodsunder this concept, the residential lot pattern

    needs to encourage highly connected streets and

    walkable blocks. Sidewalk connectivity and trail

    connectivity is important so that homes are within

    a comfortable and safe walking distance to the

    park. Park dedication from the entire project area

    should be pooled and used to secure the ridgeline

    as public park/open space through a combination

    of acquisition and dedication. Small neighborhood

    scale pocket parks could also be located along

    the ridge line open space to provide great park

    connectivity and provide efficient maintenance of

    the park system.

    As a high value amenity, the ridge line as an

    open space will add value across all residential

    neighborhoods that are within close proximity (1/4

    mile). Maintaining a portion of the public frontageon the open space is a critical design policy. Studies

    have shown that such public frontage spreads the

    value of lot premiums across a broader area, rather

    than limiting that value to the lots backing on the

    open space. The tendency from the market place

    is to have individual residential lots back up to the

    open space. This pattern would then support a

    premium value limited to that first row of residential

    lots adjacent the open space.

    Figure 13: Proposed Parks & Open Space

    Existing Parks/Open Space

    Proposed Open Space

    0 500 1,000 2,000FEET

  • 8/18/2019 Shakopee West End Study

    29/45

    2 7

    MA  S T E R P L  A 

    W E S T E R N S H A K O P E E J A C K S O N T O W N S H I P L A N D U S E S T U D Y & M A S T E R P L A NDRAFT

    The desire expressed in

    the master plan is to find a balance

    between “prime” home sites that abut the

    open space amenity provided by the ridge line

    and public frontage provided through a right-

    of-way or accessible park feature. The illustration

    provided shows potential opportunities to offer public

    access along the bluff either by small neighborhood pocketparks with street frontage on the south and the open space

    access (or views) on the north. Alternatively, a local street could

    be designed to offer both conditions as it meanders along the south

    side of the ridge. Future developers are encouraged to incorporate this

    concept into subdivision design.

    This illustration shows a street adjacent to the bluff and is a

    demonstration of how the bluff features adds value to the

    “neighborhood” but extending a greater degree of public

    access.

    Mississippi River Boulevard, St. Paul, MN / Source: Google Maps

    This illustration shows a houses that back up to the bluff

    area and is a demonstration of how the value of the

    amenity is limited to the adjacent tier of homes.

    South of Riley Lake, Chanhassen, MN / Source: Google Maps

    Using park dedication from development parcels

    that currently contain part of the ridge line

    coupled with cash park dedication secured from

    development projects with no park land needed

    will account for the majority of the resources

    needed to secure the ridge. However, more detailed

    study is needed to understand market values and

    acquisition needs for the full ridge line. Other

    strategies might include conservation easements,

    grant resources, philanthropic resources, or

    bonding.

     The unique topography of the area and the

    ridgeline feature offers opportunities for alternative

    recreation such as mountain biking trails, hiking

    trails, nature learning center programs, or other

    passive open space programs.

    Co-locating some of the storm water management

    needs or potable water facilities with the linear

    components of the open space network can also

    serve to help with funding of some of the open

    space areas.

    Multi-purpose off street trail corridors should be

    planned within these open space corridors to

    allow for recreational use as well as to connectresidential neighborhoods with key destinations.

    An important trail connection to incorporate into

    future improvements along Marystown Road is to

    provide a safe pedestrian crossing over Highway

    169 linking the project area to Tahpah Park and the

    rest of Shakopee.

    Figure 14: Ridge Feature & Land Use Interaction

    Pocket Park

    & Open Space

    Access

    Pocket Park

    & Open SpaceAccess

    Pocket Park

    & Open Space

    Access

  • 8/18/2019 Shakopee West End Study

    30/45

    28

        M

        A    S    T    E    R    P    L    A    N

    W E S T E R N S H A K O P E E J A C K S O N T O W N S H I P L A N D U S E S T U D Y & M A S T E R P L A N DRAFT

    UTILITIES

    Storm Water Approaches

    Various Best Management Practices (BMPs) can

    be used to meet the stormwater requirements for

    future development controlling for volume control,

    flood management, and water quality. Two types

    of BMPs are recommended for the project area:

    bioretention basins and wet ponds.

     The isolated development areas in the northwest

    and northeast corners of the project area (those

    north of Highway 169) will require their own

    treatment system, and cannot be combined with

    the lower portion of the project, whereas the lower

    portion may be able to have a regional treatment

    system.

    A strategy for the drainage area above the ridgeline

    is to design a regional stormwater treatment system

    of rain gardens and wet ponds along the open

    space network. The linear park and trail system

    follow existing drainage paths and will naturally

    receive a significant portion of water.

    At the bottom of the ridge, where more significant

    commercial development is proposed, a regionalponding strategy could meet the stormwater

    requirements. As discussed with MnDOT staff,

    a portion of excess MnDOT right-of-way along

    Highway 169 at the Old Brickyard Road (CR 69)

    interchange could be purchased and used as a

    proposed ponding area. Additional coordination

    between the City and MnDOT will need to

    occur to determine the feasibility of this site to

    accommodate stormwater requirements from a

    development perspective. This coordination will

    also need to identify the responsible party (city or

    developer) for the future maintenance of the site.

    If it is not possible to use the MnDOT right-of-way

    or other existing easements, other stormwater

    management options are available that consume

    less area. Examples of these practices include

    permeable pavement, tree trenches, and bioswales.

    Sanitary Sewer

    Sanitary Sewer serving the site will connect to

    existing trunk mains located in Marystown Road

    (CSAH 15). The lower portion of the ridge line

    (Breeggemann Parcel) would connect to sanitary

    sewer through a gravity line running easterly and

    connecting in at Marystown Road. As an alternative

    approach, the City and developer could inquire and

    pursue with Metropolitan Council Environmental

    Services (MCES) a direct connection to the

    interceptor. However, this is not a preferred option

    and may not be permitted by the MCES. The MCES

    interceptor in this location is a pressurized system

    and establishing a new connection could be a

    costly project.

    Services to the area further south on the top of the

    ridge also connects near Marystown Road (CSAH

    15) and 17th Avenue (CR 16). A trunk sanitary sewer

    system would run generally south through the

    project area and would be sized to accommodate

    longer term potential development south of CSAH

    78.

    Services to areas north of Highway 169 are simple

    connections to adjacent service.

  • 8/18/2019 Shakopee West End Study

    31/45

    2 9

    MA  S T E R P L  A 

    W E S T E R N S H A K O P E E J A C K S O N T O W N S H I P L A N D U S E S T U D Y & M A S T E R P L A NDRAFT

    NE QUADRANT

    Area of Biofiltration/Rain Gardens: 0.3 acres

    Area of Wet Ponds (at HWL): 0.8 acres

    1.1 acres

    NW QUADRANT

    Area of Biofiltration/Rain Gardens: 0.5 acres

    Area of Wet Ponds (at HWL): 0.9 acres

    1.4 acres

    SOUTH QUADRANT AREA SOUTH OF HI GHWAY 169

    Area of Biofiltration/Rain Gardens: 5.2 acres

    Area of Wet Ponds (at HWL): 4.9 acres

    10.1 acres

    Total Stormwater BMP Footprint 12.6 acres

    Table 4: Stormwater BMP Footprint Based on

    Development Program There is sufficient capacity within the regional

    system and within the existing collection system to

    handle the projected demand from future growth.

    Infrastructure would be located within street

    right-of-way or within public greenway corridors or

    existing utility corridors.

    Potable Water

    Services to the two areas with development

    potential north of Highway 169 can be served

    through connections to existing 12 inch mains

    along Vierling Drive.

    Services to the area south of Highway 169

    become more challenging due to topographic

    challenges and the Highway 169 barrier. The Water

    Distribution Plan and Future Facilities Plan preparedin 2004 by Shakopee Public Utilities (SPU) shows

    future water main extensions along the north side

    of the ridgeline extending from a connection point

    at Marystown Road and CR 16 westerly to CR 69.

     This extension would serve the land areas between

    the ridge and Highway 169. This area currently

    consists of three parcels owned by three separate

    entities (see Figure 2). Phasing of the improvements

    and associated development would occur in an

    east to west direction from Marystown Road. The

    same system would need to be sized to be able

    to provide future services to areas west of CR 69

    and to the south beyond the project area. Some

    discussion was had (prompted by developer/land

    owners) regarding the ability to connect to existing

    water distribution systems north of Highway 169 by

    boring under the highway.

     The SPU plan is a preferred plan representing an

    economical and sustainable solution to providing

    water service to the area at the bottom of the

    ridge line and areas beyond the project boundary.

     The alternative to connect to existing water

    infrastructure north of Highway 169 may be a

    plausible alternative. However, this alternative

    has not been studied in detail. At a concept level,

    it would require additional capital investments

    in boosters and pressure reducing stations and

    would still require the recommended infrastructure

    services to ensure adequate service. Alternative

    approaches may prove less sustainable over time

    (more facilities that require maintenance); however,

    such an approach could be studied in greater detail

    if development pressures warranted an alternativeapproach.

     This alternative approach would enable the

    property owners to develop independently of other

    developer/landowner decisions. This option is not

    a preferred option as it would carry significant

    infrastructure costs and implications for future

    service areas beyond the project area to the south

    and west. Additional system wide study as well as

    detailed analysis of this option would need to be

    done before pursuing it further. This study should

    be coordinated with SPU.

    South of the ridge, water service would be provided

    from the connection point at Marystown Road

    (CSAH 15) and 17th Avenue (CR 16). Future water

    services could be phased in the following manner:

  • 8/18/2019 Shakopee West End Study

    32/45

    30

        M

        A    S    T    E    R    P    L    A    N

    W E S T E R N S H A K O P E E J A C K S O N T O W N S H I P L A N D U S E S T U D Y & M A S T E R P L A N DRAFT

    Figure 15: Phasing of Infrastructure

    0 500 1,000 2,000FEET

    Existing Sanitary Sewer

    Existing Watermain

    Phase One

    Phase Two/Three

      C  o  n  t  o  u

      r   8   2  5

       (    F   i  r  s

      t    H   i  g   h

       S  e  r  v   i  c  e

        Z  o  n  e   )

      C o  n  t o

      u  r   9  1

      5   (   S e

     c o  n d   H

      i g  h   S e  r  v  i

     c e   Z o

      n e   )

    Phase 1

    Initially, water service can be provided by

    connecting to the 12” watermain at Marystown

    Road and extending the watermain through ROW

    of the ultimate development plan. As development

    occurs this system can be looped to the east side of

    Marystown Road with a second connection to the12” watermain. However, this infrastructure will only

    serve development that occurs up to an elevation

    of 915 (per Future Facilities Plan from SPU).

    Phase 2

    Any development that occurs over an elevation

    of 915 will require a booster station to meet water

    service needs. It is assumed that the station will be

    located on the eastern portion of the site near theboundary between the two high elevation service

    districts..

    Phase 3

    Ultimately a water tower/tank will be required

    to serve the south quadrant as a whole. It is

    anticipated that it will be installed at or near the

    highest point in the development. Integration

    of the site into a park or open space could be aconsideration. The installation of the tank/tower

    and supporting facilities will be integrated with

    development of the site.

  • 8/18/2019 Shakopee West End Study

    33/45

  • 8/18/2019 Shakopee West End Study

    34/45

    32

        M

        A    S    T    E    R    P    L    A    N

    W E S T E R N S H A K O P E E J A C K S O N T O W N S H I P L A N D U S E S T U D Y & M A S T E R P L A N DRAFT

    system. In this case, State and County Access

    Management Guidelines will apply.

     The proposed 17th Avenue (CR 16) Extension

    will serve a higher function. At this point in time,

    the 17th Avenue (CR 16) Extension should be

    considered as a future Collector. This east-west

    extension provides regional significance byconnecting to Minor Arterial streets (CSAH 15 and

    CR 69). This extension will serve as a thoroughfare

    for local traffic accessing the north-south routes to

    Highway 169 (Principal Arterial). Furthermore, the

    existing 17th Avenue (CR 16) east of Marystown

    Road (CSAH 15) is an “A” Minor Arterial, which

    stretches throughout the County. In that respect,

    the 17th Avenue (CR 16) Extension may be more

    appropriately designated as an “A” Minor Arterialin the long-term if future traffic volumes and

    development warrant the change. CR 16 serves as a

    reliever to Highway 169 during extreme congestion

    times or in rare event-based road closings.

    Finally, it is important to recognize Scott County’s

    Future Functional Classification Plan. CSAH 78 south

    of the project area is planned to be a Principal

    Arterial. This designation will be held to differentaccess management requirements. In that respect,

    future access along CSAH 78 should be planned

    accordingly to align with a Principal Arterial

    designation.

    Table 5: MnDOT Access Management Guidelines

  • 8/18/2019 Shakopee West End Study

    35/45

    3 3

    MA  S T E R P L  A 

    W E S T E R N S H A K O P E E J A C K S O N T O W N S H I P L A N D U S E S T U D Y & M A S T E R P L A NDRAFT

    Table 6: Scott County Access Management Guidelines

    FUNCTIONAL CLASSIFICATION MOBILITY ACCESS

    Principal Arterial Highest Mobility No Direct Land Access

    Minor Arterials High Mobility Limited Land Access

    Collector Streets Moderate Mobility Moderate Land Access

    Local Streets Low Mobility Unrestricted Land Access

    Table 7: Four Levels of Functional Classification

    Access Management

    Access management is a strategic,

    multidimensional set of policies, methods

    and tools to manage connectivity to public

    roadways from various types of land uses. Access

    management seeks to provide an appropriate

    balance between mobility needs and connectionsto property. Good access management supports

    a wide array of transportation system goals. These

    goals include creating a safe travel environment

    for all modes and users of the transportation

    system, encourages a balance between roadway

    capacity and accessibility, and encourages an

    active transportation system (e.g., integration of

    multimodal facilities and context sensitive design

    principles).

    Access management also plays an important role

    in maintaining roadway capacity and maximizing

    mobility, while supporting the jurisdictions

    functional classification system plans. Scott

    County’s 2030 Comprehensive Plan recognizes

    the relationship between a roadway’s functional

    classification, mobility and access. The Plan states

    “most roadways serve both access and mobilityfunctions to varying degrees, and this planned

    degree of access and mobility determines the

    roadways functional classifications (table).”

    A roadway’s functional classification is also the

    determining factor in understanding the State

    and County’s Access Management Guidelines (see

     Table 5 and Table 6). Access spacing guidelines

    are important because they define a starting

  • 8/18/2019 Shakopee West End Study

    36/45

    34

        M

        A    S    T    E    R    P    L    A    N

    W E S T E R N S H A K O P E E J A C K S O N T O W N S H I P L A N D U S E S T U D Y & M A S T E R P L A N DRAFT

    Frontage Roadconsideration dependent

    on ultimate land use

    configurations andintensity. See discussionon key roadway issues.

        1    5    0    ’    R    O    W   -

        4    l   a   n   e   s   e   c    t    i   o   n

        1    2    0    ’    R    O    W   -

        3    l   a   n   e   s   e   c    t    i   o   n

        7    0    ’    R    O    W

        6    6    ’    R    O    W

    COMPLETE STREETS

    Future streets will both consider the context of the community and create

    a comprehensive and connected network within the project site. They will

    serve as a mode for vehicular traffic, while supporting pedestrians, bicyclists,

    and potential future transit users of all ages and abilities. The integration of

    streetscape features and landscaping will increase the aesthetic qualities of

    the corridors, while also providing opportunities to mitigate stormwater.

    Figure 17: Right-of-Way Sections

    The above illustrations are examples. Ultimate street design will be determined by more detailed traffic studiesand consistent with applicable city or county standards.

  • 8/18/2019 Shakopee West End Study

    37/45

    3 5

    MA  S T E R P L  A 

    W E S T E R N S H A K O P E E J A C K S O N T O W N S H I P L A N D U S E S T U D Y & M A S T E R P L A NDRAFT

    point for balancing property access, safety, and

    mobility concerns. For example, providing access

    management in some form (whether it is through

    grade-separated crossings, frontage roads or right-

    in/right-out access) reduces the number of conflict

    points, which results in improved safety.

    Findings The proposed roadway network aligns with the

    State and County Access Management Guidelines,

    with the exception of the proposed future access to

    CSAH 15 at the on/off ramps south of the Highway

    169. Continued discussions with MnDOT will need

    to occur to determine the appropriate access

    control.

    Traffic Volume Estimates

    A high-level traffic assessment was conducted

    based on the preferred concept’s land uses and

    proposed roadway network. Year 2030 daily traffic

    volumes were developed based on a review of the

    current daily traffic volumes (provided by MnDOT)

    and development trips generated by the preferred

    land use plan. The Institute of Transportation

    Engineers (ITE) Trip Generation Manual, 9th Edition

    was used to develop trip generation estimatesusing the preferred land use types and sizes

    (square feet or number of units). The projected

    trips were distributed throughout the study area

    based on current travel patterns, future access, and

    engineering judgment. For comparison purposes,

    results of this assessment were compared to the

    2030 traffic volumes developed for the Shakopee

     Transportation Plan. A technical memorandum

    documenting methodologies and findings based

    on current and best available data was prepared

    and is available in city files.

    Findings

    In general, the projected 2030 traffic volumes from

    the Shakopee Transportation Plan will increase as a

    result of the new land uses being proposed. In that

    respect, an additional analysis was completed to

    determine the potential roadway facilities needed

    to accommodate projected trips. This assessment

    included a planning level evaluation of the existing

    roadway network by facility type, projected

    traffic volumes (2030), and the facility type’s daily

    capacity ranges. The capacity ranges were based

    on guidance from the Highway Capacity Manual

    (HCM).

    Results of this review indicated that the projected2030 traffic volumes will exceed the current

    roadway capacity along Marystown Road

    (CSAH 15) near the Highway 169 South Ramps.

     To accommodate year 2030 traffic volumes,

    Marystown Road (CSAH 15) should be expanded to

    a four-lane roadway from Highway 169 through the

    17th Avenue (CR 16) intersection. Furthermore, this

    evaluation determined the appropriate facility type

    to accommodate the 17th Avenue (CR16) Extension.

    In essence, the 17th Avenue (CR 16) Extension

    should be a four-lane facility west of Marystown

    Road (CSAH 15) to accommodate the existing four-

    lane facility to the east. The 17th Avenue (CR 16)

    Extension should be tapered to a three-lane facility

    with turn lanes west of the proposed commercial

    development.

     The ultimate design of the 17th Avenue (CR 16)

    extension should be pedestrian friendly whilepreserving the functionality of the road. Designs

    should support lower speeds of 35-40 miles per

    hour.

  • 8/18/2019 Shakopee West End Study

    38/45

    36

        M

        A    S    T    E    R    P    L    A    N

    W E S T E R N S H A K O P E E J A C K S O N T O W N S H I P L A N D U S E S T U D Y & M A S T E R P L A N DRAFT

    KEY ROADWAY ISSUES ANDDISCUSSIONS

    Much discussion and discourse has been had

    over the years regarding the idea of connecting a

    frontage road from Old Brickyard Road (CR 69) to

    Marystown Road (CSAH 15) and accessing directly

    opposite the on/off ramp to Highway 169. MnDOTmaintains permitting authority for access at this

    location with input from the City and Scott County.

    In order to consider an access point here, more

    detailed land use, development analyses, and traffic

    analyses will be required by MnDOT. Specific traffic

    controls would be a key outcome of this discussion

    in the event access is provided in this location.

     The master plan shows access at Marystown Road

    (CSAH 15) at the on-ramp location via a local

    street that connects south to the extension of

    17th Avenue (CR 16). Further analysis and review is

    required to confirm the feasibility of this alignment.

     The idea of a frontage road connecting the two

    county roads had been widely discussed over the

    years as well. While the frontage road may provide

    a valuable connection for development on the

    lower portion of the ridge (Breeggemann, NORCOR,

    and DR Horton parcels - see Figure 2), there are

    significant design challenges and constraints

    with constructing a frontage road through this

    area. These challenges include topography, utility

    easements and narrow areas for development

    parcels, particularly on the NORCOR parcel. No

    existing property owners are advocating for the

    frontage road at this time.

    Access at Marystown Road near TH 169, the

    possibility of a frontage road, internal circulation,

    connection/access to the extension of CSAH 16,

    and development viability are all interdependent

    factors for this node. All factors are impacted by

    unique topography and natural features. The

    illustration provides an alternative that attempts

    to minimize impacts on the natural features andallow for a mix of land uses that would contribute

    to a sustainable neighborhood node. These

    alternatives do not meet access guidelines and

    would require variances from County and MNDOT

    policies. This alternative should be considered

    when development is proposed. Additional study

    and analysis will be necessary, once an ultimate

    land use is determined.

    Development alternative requiring further study 

    0 500 1,000

    FEET

    Additional study needs to be done to determine

    the feasibility of a frontage road. However, the

    proposed land use plan does not warrant the need

    for a future frontage road at this time.

    17th Avenue (CR 16) Extension

    17th Avenue (CR 16) currently stops at Marystown

    Road (CSAH 15). Numerous past studies have

    illustrated a future road connection extending

    westerly through the site to Old Brickyard Road (CR

    69). The master plan carries this concept forward

    with the extension functioning as a collector street

    with Scott County jurisdiction and ending at Old

    Brickyard Road (CR 69).

  • 8/18/2019 Shakopee West End Study

    39/45

  • 8/18/2019 Shakopee West End Study

    40/45

    38

        M

        A    S    T    E    R    P    L    A    N

    W E S T E R N S H A K O P E E J A C K S O N T O W N S H I P L A N D U S E S T U D Y & M A S T E R P L A N DRAFT

     THIS PAGE IS INTE NTIONA LLY LEFT B LANK 

  • 8/18/2019 Shakopee West End Study

    41/45

    3 9

    I   MP L  E ME N T A T I    O N 

    W E S T E R N S H A K O P E E J A C K S O N T O W N S H I P L A N D U S E S T U D Y & M A S T E R P L A NDRAFT

    05 | IMPLEMENTATION STRATEGIES

    While the master plan describes a vision for transition of the study area from

    rural to developed, this section discusses where the community goes from

    here in implementing the vision. Questions about procedures and actions

    toward implementation are addressed in this section with discussion about

    land use guidance, annexation, infrastructure needs, open space and parkland

    establishment, and developer performance incentives.

    LAND USE GUIDANCE

     The following actions are recommended to establish the plan as official land

    use guidance for the study area:

     » Adopt the master plan as an official land use guide for future

    development within the study area.

     » Incorporate the land use plan of this study into the future Comprehensive

    Plan update expected to take place in 2016/2017.

     » Conduct an Alternative Urban Area-wide Review (AUAR) environmental

    review of the entire study area building.

    Approval of this Master Plan represents the first step in a methodical transition

    of the study area from a rural to a developed landscape that will likely take over

    a decade or more to realize. The study area is within the City of Shakopee and

    partially outside. The City of Shakopee is preparing this plan to guide future useof lands adjacent to its corporate limits as well as within.

    In the Twin Cities metro area, land use guidance is proposed and administered

    by local jurisdictions but must be reviewed by affected agencies and

     jurisdictions and accepted by the Metropolitan Council. This review is typically

    done through community comprehensive plans that are completed by the

    local community and submitted to the Metropolitan Council for acceptance.

    In cases where proposed development does not conform to current land use

    guidance, a formal comprehensive plan amendment must be submitted to the

    Met Council for review and approval before a project can proceed.

     The issue of formal land use guidance is closely linked to annexation issues.

    Just like this plan, communities often plan for lands outside of their corporate

    limits. The Metropolitan Council’s approach to this situation is to provide

    formal comprehensive plan review and acceptance of land use plans within

    corporate limits and within areas subject to orderly annexation agreements.

    For the project area, the City of Shakopee and Jackson Township should seek

    an amendment to the Thrive MSP designation for the lands within Jackson

     Township to an urban designation (Suburban Edge or Emerging Suburban

    Edge.)

    Alternative Urban Area-wide Reviews (AUAR) have become a common

    environmental review technique for large land areas like the study area. AnAUAR offers the ability to conduct environmental review in advance and in lieu

    of individual project reviews. This will streamline future project approvals and

    identify environmental mitigation measures that can be accomplished with

    subsequent development projects. Because future developments within the

    project area are intricately connected, collaborating on an AUAR may prove

    beneficial. A significant body of work already exists towards this effort through

    this master plan and the Bluffs of Marystown EAW completed in 2005/6.

    ZONING/SUBDIVISION

     Traditional zoning districts may apply within the project area. However, a

    number of recommend actions may better support an approach to zoning that

    would achieve the key principles identified in the plan. These actions include:

    » Increased density: the current residential districts limit residential

    densities to 12 units per acre. In the market place, this density is extremely

    prohibitive of achieving a diversity of housing types to serve changing

    housing demands and to maintain a degree of affordability. Densities of

  • 8/18/2019 Shakopee West End Study

    42/45

    40

        I    M    P    L

        E    M    E    N    T    A    T    I    O    N

    W E S T E R N S H A K O P E E J A C K S O N