shaw river power station ees panel report - … · shaw river power station project ees & moyne...

177
SHAW RIVER POWER STATION PROJECT ENVIRONMENT EFFECTS STATEMENT & AMENDMENT C36 TO THE MOYNE PLANNING SCHEME INQUIRY PANEL REPORT JULY 2010

Upload: nguyenkhue

Post on 07-Oct-2018

221 views

Category:

Documents


0 download

TRANSCRIPT

 

 

 

SHAW RIVER POWER STATION PROJECT

ENVIRONMENT EFFECTS STATEMENT & AMENDMENT C36 TO THE MOYNE PLANNING SCHEME

 

 

 

 

 

INQUIRY PANEL REPORT

 

 

 

 

 

 

 

 

 

 

 

 

JULY 2010

 

 

SHAW RIVER POWER STATION PROJECT

ENVIRONMENT EFFECTS STATEMENT & AMENDMENT C36 TO THE MOYNE PLANNING SCHEME

 INQUIRY PANEL REPORT

 

 

 

Cathie McRobert, Chair 

 

Ian Coles 

 

 

Jacqui McLeod  

 

Greg Sharpley 

 

JULY 2010

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

Contents

OVERALL CONCLUSIONS & CONSOLIDATED RECOMMENDATIONS ................................................................................................. 4 Overall Conclusions........................................................................................................... 4 Consolidated Recommendations ................................................................................... 10 Amendment C36 .............................................................................................................. 14

1. INTRODUCTION.................................................................................................. 18 1.1 The Project ................................................................................................................ 18 1.2 Overarching Policy Context................................................................................... 21 1.3 Overview of Statutory Approvals Required ....................................................... 22 1.4 EES Evaluation Objectives ..................................................................................... 24 1.5 Identification of Issues............................................................................................ 24

2. POWER GENERATION: EFFICIENCY, AFFORDABILITY AND GREENHOUSE GAS EMISSIONS .................................................................... 25

2.1 Rationale for Additional Gas-fired Power Generation ...................................... 25 2.2 Greenhouse Gas Emissions.................................................................................... 26

2.2.1 Regulatory Framework and Policy Context .................................................. 26 2.2.2 EES Assessment - Greenhouse Emission Estimates ..................................... 27 2.2.3 Submissions and Proponent Response .......................................................... 30 2.2.4 Discussion and Conclusions.......................................................................... 32

2.3 The Power Station Site Selection and Design Efficiency.................................... 32 2.3.1 EES Assessment - Power Station Site Selection and Design Efficiency ...... 32 2.3.2 Discussion and Conclusions.......................................................................... 34

2.4 The Gas Pipeline Design and Route Options ...................................................... 34 2.4.1 Regulatory Framework and Policy Context .................................................. 34 2.4.2 The EES Assessment - Gas Pipeline ............................................................. 35 2.4.3 Submissions and Proponent Response .......................................................... 35 2.4.4 Discussion and Conclusions.......................................................................... 37

2.5 Compressor Station Design and Site Selection ................................................... 38 2.5.1 EES Assessment - Compressor Station Site Selection and Design............... 38 2.5.2 Submissions and Proponent Response .......................................................... 38 2.5.3 Discussion and Conclusions.......................................................................... 38

2.6 Water Supply Infrastructure.................................................................................. 39 2.6.1 EES Assessment and Evidence– Water Supply Infrastructure Design ......... 39 2.6.2 Submissions................................................................................................... 40 2.6.3 Discussion and Conclusions.......................................................................... 40

3. PROTECTION OF CATCHMENT VALUES.................................................... 41 3.1 Surface Water, Hydrology and Water Quality.................................................... 41

3.1.1 Regulatory Framework and Policy Context .................................................. 41 3.1.2 EES Assessment and Evidence - Potential Impacts on Surface Waters........ 42 3.1.3 Submissions and Proponent Responses......................................................... 45 3.1.4 Discussion and Conclusions.......................................................................... 48

3.2 Groundwater............................................................................................................ 49 3.2.1 Regulatory Framework and Policy Context .................................................. 49 3.2.2 EES Assessment and Evidence – Groundwater ............................................ 49 3.2.3 Submissions................................................................................................... 50 3.2.4 Discussion and Conclusions.......................................................................... 50

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

4. BIODIVERSITY...................................................................................................... 52 4.1 Regulatory Framework and Policy Context ........................................................ 52

4.1.1 Commonwealth Legislation - Environment Protection and Biodiversity Conservation Act 1999................................................................................. 52

4.1.2 State Legislation and Policy.......................................................................... 53 4.2 Terrestrial Ecology .................................................................................................. 55

4.2.1 EES Assessment and Evidence - Terrestrial Ecology ................................... 55 4.2.2 Submissions and Proponent Response .......................................................... 58 4.2.3 Discussion and Conclusions.......................................................................... 62

4.3 Aquatic Ecology....................................................................................................... 65 4.3.1 EES Assessment and Evidence - Aquatic Ecology ....................................... 65 4.3.2 Submissions and Proponent Response .......................................................... 67 4.3.3 Discussion and Conclusions.......................................................................... 67

5. PROTECTION OF CULTURAL HERITAGE ................................................... 69 5.1 Aboriginal Cultural Heritage ................................................................................ 69

5.1.1 Regulatory Framework.................................................................................. 69 5.1.2 EES Assessment - Aboriginal Cultural Heritage .......................................... 69 5.1.3 Discussion and Conclusions.......................................................................... 70

5.2 Non-Aboriginal Cultural Heritage ....................................................................... 71 5.2.1 Regulatory Framework.................................................................................. 71 5.2.2 EES Assessment - Non-Aboriginal Cultural Heritage .................................. 71 5.2.3 Submissions and Response............................................................................ 72 5.2.4 Discussion and Conclusions.......................................................................... 72

6. HEALTH, SAFETY AND AMENITY IMPACTS ............................................. 73 6.1 Noise ......................................................................................................................... 73

6.1.1 Regulatory Framework and Policy Context .................................................. 73 6.1.2 EES Assessment and Evidence – Noise Criteria........................................... 74 6.1.3 Submissions and Proponent Response - Noise Criteria ................................ 76 6.1.4 Discussion and Conclusions – Noise Criteria ............................................... 78 6.1.5 EES Assessment and Evidence - Power Station, Compressor Station

and Recycled Water Treatment Plant Operation Noise................................ 79 6.1.6 Submissions and Proponent’s Response – Power and Compressor

Station Operation Noise ............................................................................... 81 6.1.7 Discussion and Conclusions - Power and Compressor Station

Operation Noise ........................................................................................... 81 6.1.8 EES Assessment and Evidence – Noise from Construction Activities ......... 82 6.1.9 Discussion and Conclusions – Noise from Construction Activities.............. 83 6.1.10 Noise Monitoring And Complaints Procedures ............................................ 83

6.2 Air Quality................................................................................................................ 86 6.2.1 Regulatory Framework and Policy Context .................................................. 86 6.2.2 EES Assessment and Evidence - Air Emissions ........................................... 87 6.2.3 Submissions - Air Emissions......................................................................... 90 6.2.4 Discussion and Conclusions - Air Emissions................................................ 91

6.3 Safety......................................................................................................................... 92 6.3.1 Regulatory and Policy Framework................................................................ 92 6.3.2 EES Assessment - Safety .............................................................................. 93 6.3.3 Submissions and Proponent Response .......................................................... 94 6.3.4 Discussion ..................................................................................................... 95

6.4 Landscape and Visual Amenity ............................................................................ 97 6.4.1 EES Assessment and Evidence – Visual Impacts ......................................... 97 6.4.2 Submissions................................................................................................. 100 6.4.3 Discussion and Conclusions........................................................................ 101

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

6.5 Lighting................................................................................................................... 105 6.5.1 EES Assessment - Lighting......................................................................... 105 6.5.2 Submissions................................................................................................. 105 6.5.3 Discussion and Conclusions........................................................................ 105

7. DISRUPTION OF EXISTING LAND USES, INFRASTRUCTURE, TRAFFIC AND LOCAL COMMUNITIES ...................................................... 107

7.1 Land Use Disruption............................................................................................. 107 7.1.1 EES Assessment- Land Use Disruption ...................................................... 107 7.1.2 Discussion and Conclusions – Land Use Disruption .................................. 108

7.2 Traffic Management.............................................................................................. 108 7.2.1 EES Assessment and Evidence – Traffic Management .............................. 108 7.2.2 Submissions and Proponent Response ........................................................ 110 7.2.3 Discussion and Conclusions – Traffic Management ................................... 111

7.3 Disruption of Infrastructure ................................................................................ 113 7.3.1 EES Assessment - Disruption of Infrastructure .......................................... 113 7.3.2 Submissions and Proponent Response ........................................................ 114 7.3.3 Discussion and Conclusions........................................................................ 114

8. SOCIO- ECONOMIC IMPLICATIONS .......................................................... 115 8.1 Economic and Employment Impacts.................................................................. 115

8.1.1 EES Assessment and Evidence - Economic and Employment Impacts...... 115 8.1.2 Submissions................................................................................................. 116 8.1.3 Discussion ................................................................................................... 117

8.2 Community Services, Housing and Construction Camp(s)............................ 118 8.2.1 EES Assessment and Evidence - Community Services and Housing ......... 118 8.2.2 Submissions................................................................................................. 120 8.2.3 Discussion ................................................................................................... 121

9. OTHER MATTERS.............................................................................................. 125 9.1 Decommissioning.................................................................................................. 125

9.1.1 EES Assessment - Decommissioning ......................................................... 125 9.1.2 Submissions................................................................................................. 125 9.1.3 Discussion ................................................................................................... 125

9.2 Batching Plant ........................................................................................................ 126

10. CUMULATIVE IMPACTS ................................................................................. 127 10.1.1 EES Assessment and Evidence ................................................................... 127 10.1.2 Submissions................................................................................................. 129 10.1.3 Discussion and Conclusions........................................................................ 130

11. FRAMEWORK FOR MANAGING ENVIRONMENTAL EFFECTS AND RISKS........................................................................................................... 134

11.1 Certainty, Community Consultation and Accountability ............................... 134 11.1.1 Certainty...................................................................................................... 134 11.1.2 Co-ordination Between Regulatory Agencies............................................. 137 11.1.3 Consultation ................................................................................................ 138 11.1.4 Compliance Testing .................................................................................... 140 11.1.5 Access to Appropriate Expertise ................................................................. 140

11.2 Environmental Management Plans .................................................................... 141 11.2.1 The Power Station Site................................................................................ 142 11.2.2 Gas Pipeline and Compressor Station ......................................................... 143 11.2.3 Water Pipelines ........................................................................................... 144 11.2.4 Complaints Management............................................................................. 145

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

11.3 Moyne Planning Scheme Amendment C36....................................................... 146 11.3.1 Schedule 2 to the Special Use Zone (SUZ2)............................................... 146 11.3.2 Schedule to Clause 52.03 ............................................................................ 149 11.3.3 Clause 52.17................................................................................................ 151 11.3.4 Environmental Significance Overlay 4 ....................................................... 151

Appendices

APPENDIX A: EES INQUIRY PANEL TERMS OF REFERENCE..................... 155

APPENDIX B: LIST OF SUBMITTERS.................................................................. 158

APPENDIX C: EES TABLE 2.1: SUMMARY OF KEY APPROVALS AND ASSESSMENTS REQUIRED ........................................................ 159

APPENDIX D: POTENTIAL BENT-WING BAT AND WATER MONITORING PRINCIPLES....................................................... 163

APPENDIX E:  LIST OF ABBREVIATIONS USED ............................................. 170

 

List of Figures

Figure 1 Locality Map (Source: EES Summary Report).......................................... 18 Figure 2 The Power Station Site

(Source: EES Summary Report Figure 4)................................................... 19 Figure 3 Compressor Station Layout (Source: EES Figure 8.2).............................. 20 Figure 4 Power Station Noise Contours (weather category 6) .............................. 80 Figure 5 Compressor Station Noise Contours (weather category 6) .................... 80 Figure 6 Power Station, Switchyard and Pylon Visualisation

(Source: EES Appendix 15 Figure 1.6) ....................................................... 97

Page 1

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

SHAW RIVER POWER STATION PROJECT EES & 

MOYNE PLANNING SCHEME AMENDMENT C36 

The Project The project comprises: 

a gas‐fired power station near the town of Orford; 

a gas compressor station north‐west of Port Campbell; 

a gas pipeline from Iona to Orford; and 

water supply infrastructure at Port Fairy and two water pipelines 

from Port Fairy to Orford. 

Amendment 

C36 

Amendment C36 is proposed to facilitate the development of the 

Power Station and water pipelines by: 

rezoning the Power Station site from Farming Zone (FZ) to a 

Special Use Zone 2 (SUZ2); 

introducing an Environmental Significance Overlay (ESO4) to 

manage the introduction of noise sensitive uses around the Power 

Station site; 

using Clause 52.03 to exempt the following elements of the 

proposal from planning scheme requirements if the associated 

incorporated document requirements are met: 

native vegetation removal associated with altered access at the 

intersection of Riordans Road and Hamilton – Port Fairy Road,  

and new water pipelines from Port Fairy to the power station 

site; and 

a workers construction camp near the Power Station site. 

exempting the Power Station site from Clause 52.17 permit 

requirements relating to the removal, destruction or lopping of 

native vegetation. 

The 

Proponents 

Power Station and Gas Pipeline: Shaw River Power Station Pty Ltd (a 

subsidiary of Santos Ltd). 

Water supply infrastructure: Wannon Water. 

EES Scoping  On 7 November 2008, the Minister for Planning advised Shaw River 

Power that an EES was required for the project under the Environment 

Effects Act 1978.  A technical reference technical reference group of 

relevant agency and authority representatives was convened to guide 

the scoping and development of the EES.  The draft scoping 

requirements for the EES were finalised in July 2009 after public 

exhibition. 

Exhibition  The EES, Amendment C36 to the Moyne Planning Scheme and Works 

Approval Applications WA67398, WA67399 and WA67400 were placed 

on concurrent public exhibition from 12 March to 27 April 2010. 

Pipeline Licence Applications PL271 and PL272 were advertised 

concurrently under the Pipelines Act 2005. 

Page 2

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

Submissions 12 written submissions were received, 8 of which were from local 

government and government agencies, three were from residents 

living in the vicinity of the project and one was from a Proponent for a 

proposed Wind Energy Facility.

The EES 

Inquiry 

Panel 

On 25 March 2010 the Minister for Planning appointed an Inquiry 

Panel under Section 9 of the Environment Effects Act 1978 comprising: 

Cathie McRobert (Chair); 

Ian Coles; 

Jacqui McLeod; and 

Greg Sharpley. 

A Panel with the same composition was appointed under Sections 151 

and 153 of the Planning and Environment Act 1987 to consider 

submissions relating to Amendment C36 to the Moyne Planning 

Scheme. 

Terms of 

Reference 

The Inquiry Terms of Reference (See Appendix D) require the Inquiry 

Panel: 

i.  To inquire into and make findings regarding the potential 

environmental effects of the Shaw River Power Station Project, 

including the construction and operation of the Power Station, the 

high‐pressure gas pipeline and water pipeline and associated 

infrastructure requirements. 

ii.  To consider the exhibited EES, all submissions received in response 

to the exhibited EES as well as other relevant matters. 

iii  To recommend any modifications to the Shaw River Power Station 

Project as well as environmental mitigation and management 

measures that may be needed to achieve acceptable environmental 

outcomes, within the context of applicable legislation and policy.

Hearings Directions hearing: 17 May 2010 at Port Fairy. 

Hearings:  9‐11 June 2010 at Port Fairy; 

15 June 2010 at Melbourne; and 

17‐ 18 June 2010 at Warrnambool. 

Inspections Accompanied inspections: 7 and 8 June 2010.  These full day 

inspections visited submitter properties and sensitive environmental 

locations such as pipeline river and road crossings.  The Panel also 

made unaccompanied inspections of various parts of the project areas 

and the Mortlake Power Station (under construction) during the course 

of the hearing.

Page 3

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

Hearing 

Appearances 

Department of Planning and Community Development represented 

by Margo Kozicki, Ashley Stephens and Bart Gane. 

Shaw River Power Station Pty Ltd and Wannon Water represented by  

Tim Power and Anna Williams of Freehills who called evidence from: 

Barton Napier of Coffey Environments – Environment, 

infrastructure site and route selection. 

Andrew Clark of Matrix – Planning scheme amendment, land use 

and planning assessment. 

Paul Carter of Arup – Traffic. 

Nicole Sommerville of Sinclair Knight Mertz – Socio‐economic  

Aaron Organ of Ecology Partners – Terrestrial and Aquatic 

Ecology, Net Gain Offsets. 

Robin Ormerod of PAEHolmes – Greenhouse gas, air quality, air 

emissions and drinking water. 

Chris Turnbull of Sonus – Noise. 

John Shinkfield of AECOM – Visual. 

Peter Wilson of Wannon Water – water allocation issues. 

Mark Trickey of GHD – water technology / processes regarding 

water infrastructure. 

The following expert witnesses prepared and circulated  statements 

relating to water infrastructure but the Panel did not require them to be 

called: 

Barry Cook of GHD – air issues 

V Pavasovic of GHD – noise issues. 

Department of Primary Industries represented by Michelle Hendricks 

and Terry McInley. 

Morgan‐Payler Family represented by Barnaby Chessell, Barrister.  Mr 

Morgan‐Payler also addressed the Panel on the final day of hearing. 

Environment Protection Authority represented by John Frame and Mr 

Nancarrow. 

Department of Sustainability and Environment represented by 

Andrew Pritchard and Claire Tesselaar. 

Moyne Shire represented by Russell Guest. 

Corangamite Shire represented by Sophie Segafredo and Jileena 

Baensch. 

Page 4

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

OVERALL CONCLUSIONS & CONSOLIDATED RECOMMENDATIONS

Overall Conclusions

The Panel’s overall findings based on the analysis in the EES, submissions 

and expert evidence are set out below in terms of the EES assessment 

objectives. 

EES Assessment Objective: To provide for the development of base load and 

intermediate load power generation capacities in the context of government 

policy objectives to maintain a secure, efficient and affordable supply of 

energy while reducing the intensity of greenhouse gas emissions from the 

energy sector. 

The Panel accepts the information and analysis provided that the project can 

be regarded as best practice in terms of efficiency and minimising 

environmental emissions.  Firstly, the project represents an efficient siting 

option, being west of Melbourne, on the 500kV grid, and comparatively close 

to the Iona gas fields.  Secondly, although greenhouse gas emissions will be 

significant, the combination of the natural gas fuel and the technology 

employed will result in substantially less greenhouse gas emissions per unit 

of electricity produced than the current Victorian average and the alternative 

of power generation from coal.  This is consistent with State government 

objectives and represents a major environmental benefit. 

EES Assessment Objective: To avoid or minimise effects on species and 

communities listed under the Flora and Fauna Guarantee Act 1988 to the 

extent practicable, to avoid or minimise effects on other native species and 

communities, and to comply with net gain requirements for biodiversity 

outcomes. 

The Panel accepts the EES assessment, evidence and submissions, including 

from DSE, demonstrating that there has been a consistent objective to avoid 

and minimise adverse impacts on native flora and fauna in site and route 

selection, preferred pipeline construction techniques, the proposed design 

and management plans.  The need to comply with conditions of the Referral 

under the Environment Protection and Biodiversity Conservation Act 1999 (EPBC 

Act) relating to pipeline construction has been acknowledged and there is a 

commitment to offset losses that cannot be avoided. 

Page 5

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

Preliminary net gain assessments have been prepared but the difficulty in 

meeting the Framework’s ‘like for like’ criterion for offsets of losses of native 

vegetation of very high conservation significance has been identified.  In the 

absence of any specific information on the types of offsets being pursued by 

the Proponent and therefore the relative conservation benefits associated 

with different offset options, the Panel cannot give any guidance about 

whether departures from ‘like for like’ requirements for very high 

conservation value vegetation should be supported.  This is a matter that 

remains for determination by the Minister for Energy and Resources, under 

the Pipelines Act 2005, but should be on the advice of the Minister for 

Environment and Climate Change. 

Although the native vegetation losses due to this project are relatively 

limited, incremental losses contribute to more significant cumulative effects 

and the Panel encourages DSE to work towards identifying strategic 

opportunities for the provision of consolidated offsets. 

Surveys of aquatic native vegetation at the proposed stream crossing sites 

have not been undertaken and the Panel has recommended further targeted 

surveys and offsetting of any losses in accordance with the Framework. 

The EPBC Act Referral did not identify potential impacts from the project on 

the Southern Bent‐wing Bat and evidence indicated that the bat is unlikely to 

be adversely affected by the Power Station operation.  However, given the 

uncertainties about bat usage of the site and possible impacts, DSE sought a 

monitoring regime.  The Panel accepts that the principles of the monitoring 

program put forward after the hearing should be implemented but notes that 

responses if bat mortality is identified may well be in the form of 

adjustments to lighting, or offsets in the form of improvements to bat habitat 

elsewhere. 

EES Assessment Objective: To protect catchment values, including surface 

water quality, stream flow, aquatic health and groundwater values, to the 

extent practicable. 

Water quality in waterways may be impacted during construction of the gas 

and water pipelines, the Power Station, the proposed upgrading of Riordans 

Road, and during the operation of the Power Station.  However, the Panel is 

satisfied that risks to water quality can be mitigated through the design of 

the stormwater management system for the Power Station site to maintain 

the current discharge hydrology by maximising on‐site use and minimising 

the volume of water discharged to Shaw River, together with the 

implementation of best practice sedimentation and pollution control 

measures during project construction and power station operation. 

Page 6

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

The Panel endorses the consensus view at the hearing that: 

Horizontal Directional Drilling (HDD) is the preferred pipeline 

construction method to avoid environmental impacts at sensitive 

locations such as river crossings, subject to further geotechnical 

investigation to determine the feasibility of this method; 

Contingency plans should be in place prior to the commencement of 

construction in the event that HDD proves unsuccessful; and 

Specific measures for each watercourse crossing should be incorporated 

in Construction EMPs. 

EES Assessment Objective: To protect Aboriginal and non‐Aboriginal 

cultural heritage to the extent practicable. 

The EES has not identified any Aboriginal cultural heritage places.  

However, there are unsurveyed areas affected by the project works that have 

been identified as having high sensitivity and potential to contain Aboriginal 

heritage places or artefacts.  Other approvals must be consistent with an 

approved Cultural Heritage Management Plan for the project under the 

Aboriginal Cultural Heritage Act and this establishes an appropriate 

framework to manage any issues that may arise. 

There are no non‐aboriginal heritage places on the Heritage Register or 

protected by heritage overlays but the Construction EMP should ensure 

impacts on dry‐stone walls along the pipeline route, a bluestone drinking 

trough and bluestone bridge and culvert are minimised.  The Panel is of the 

view that, like exemptions for removal of native vegetation along the water 

pipelines, works affecting dry‐stone walls should also be exempt under 

clause 52.03, subject to a requirement for the protection and re‐instatement 

being included in the Construction EMP. 

EES Assessment Objective: To avoid or minimise noise, visual and other 

adverse amenity effects, as well as health and safety implications, on local 

residents during the development and operation of the power station, 

compressor station and gas and water pipelines. 

There will be some impact on the amenity of properties in the vicinity of the 

various elements of the project.  Some transitory disruption and amenity 

impacts during the construction phase are inevitable but can be minimised 

through management plans and/or PEA works approvals, which address 

matters such as compliance with specified noise limits, rehabilitation plans 

and dust suppression. 

Page 7

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

During operations, the Panel concludes that: 

noise from power station and compressor station operations will be 

audible at the nearest houses but compliance with the recommended 

limits can be achieved and this would mean normal residential activities 

should not be disrupted, including during the night time period; 

the Power Station will be a large structure that will be visually prominent 

in the immediate area, particularly after the harvesting of adjoining 

timber plantations.  However, these visual impacts do not affect 

landscapes of recognised significance and the outlook from the relatively 

few residential properties affected is currently quite visually contained 

due to the interception of views by either timber plantations or other 

plantings around homesteads; 

with regard to air emissions from the Power Station and compressor 

station, ground level concentrations for all cases considered will be much 

lower than the relevant health‐based ambient air design criteria in SEPP‐

AQM; rainwater would not be contaminated at any nearby residences; 

and sealing of the main vehicle routes plus management to suppress dust 

in other trafficked areas is recommended; and 

there will be a minimal increase in odour from the Recycled Water 

Treatment Plant. 

The Panel considers that the impacts on amenity in the locality are acceptable 

given the benefits to the wider community but, like wind energy facilities, 

compliance with specified noise limits should be verified and properties 

within three kilometres of the Power Station and compressor station should 

be offered landscaping to screen views to the infrastructure.  The Panel 

considers, although a long term consideration, the community should be 

assured that rehabilitation of the Power Station will occur after 

decommissioning, preferably through a bond if the necessary administrative 

framework can be established. 

Preliminary HAZID analysis in the EES indicate that that safety impacts can 

be appropriately managed through EMPs.  It is understood that the design of 

the project considers the risk of explosion to existing uses such as dwellings 

but the Panel has questioned whether the risk to future dwellings, which in 

some circumstances are as of right, has been addressed.  The Panel 

recommends further consideration of design specifications and/or the need 

for an overlay to ensure safety risk is considered and addressed before 

dwellings (or other sensitive uses) are built in the vicinity of the project.  The 

extent of such an overlay would be determined on the basis of risk and a 

consultative process would be necessary to allow those who may be affected 

to present their views.  As the Power Station will be a Major Hazard Facility 

Page 8

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

ongoing training should be provided by the Proponent to ensure adequately 

trained CFA and SES personnel are available locally to assist in emergency 

situations. 

EES Assessment Objective: To minimise the disruption of existing land uses, 

infrastructure, traffic and local communities, including in relation to the 

availability of housing and the potential need to upgrade infrastructure. 

Project traffic will be directed to main roads with minimal use and impact on 

the local road network.  Riordans Road is proposed to be upgraded, 

VicRoads approval will be required for over‐dimensional vehicle routes and 

the Traffic Management Plan provides an appropriate mechanism to 

minimise disruption, particularly during construction. 

The project will provide a substantial stimulus to the local economy, 

particularly during the construction and future maintenance phases, but will 

also place substantial demands on the local labour market, community 

services and housing.  The strain on accommodation and services will be 

compounded if construction of a number of the major infrastructure projects 

proposed in the region occurs at once. 

The Panel recognises there will be substantial challenges in meeting the 

additional demand for housing while minimising adverse impacts on 

affordable housing options for existing residents and accommodation 

associated with tourism.  A range of housing options are likely to be 

required.  The Panel does not think the strategic justification for as of right 

development of construction camps (as proposed under Amendment C36) 

has been established but it supports providing discretion for Council to 

consider the merits of a construction camp on the Power Station site and 

Santos land to the east of Old Dunmore Road if other options prove to be 

insufficient. 

The Panel endorses the EES view that early and ongoing consultation is 

required with various stakeholders and service providers but emphasises 

that there is an immediate need to advance strategic planning work beyond 

the broad overview analysis in the EES Socio‐economic Impact Assessment 

to identifying practical options that are capable of implementation within the 

required timeframes.  The sooner this work commences the better as delay 

leads to more and more constraints on realisable responses.  Therefore a 

formal commitment to undertake or contribute to this work linked to 

approval of Amendment C36 is preferable to the proposed SUZ2 

requirements for the issue to be addressed at a later stage within the 

Construction EMP.  The socio‐economic impact assessment of the Mortlake 

power station project, being undertaken by Moyne Shire Council should 

provide useful insights for further project planning processes. 

Page 9

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

EES Assessment Objective: To provide a transparent framework with clear 

accountability for managing environmental effects and risks associated with 

the project to achieve acceptable outcomes. 

Exhibition of the EES resulted in surprisingly few submissions for a project 

of this scale – three submissions from property owners in the vicinity of the 

project, one submission from a wind energy facility proponent in the region 

and submissions from the proponents, and seven agencies that were 

members of the technical reference group who responded to the Panel 

invitation to submit.  None of the submissions or material presented to the 

Panel has suggested that the project should not proceed. 

It was apparent from the presentations to the Panel that the EES Technical 

Reference Group (TRG) has worked constructively to resolve most issues.  

This is a credit to both the Proponent (and those working on its behalf) and 

the regulatory agencies.  This positive relationship provided a level of 

confidence from those presenting at the hearing that outstanding matters or 

issues that may yet arise should be capable of acceptable resolution.  It will 

continue to be important that those with responsibility for future approvals 

have access to relevant expertise on technical matters such as noise, air 

quality and protection of biodiversity values.  The TRG and the Shire of 

Moyne’s community liaison processes appear to have opened channels of 

communication and these co‐operative working arrangements should be 

maintained to facilitate project specific co‐ordination of approval processes 

and monitoring of implementation. 

Management plans provide the primary mechanism for managing safety and 

environmental impacts from the project under the key pieces of legislation.  

The Panel finds that the Strategic EMP in the EES establishes a sound 

framework and basis for the development of more detailed Construction 

EMPs, Operations EMPs and Safety Management Plans (SMPs).  Compliance 

testing by suitably qualified people at key stages is also recommended to 

provide a level of certainty that commitments are met and to minimise the 

need for future reactive enforcement actions. 

The Panel has endorsed the purpose of Amendment C36 to facilitate the 

implementation of the project (except for a possible construction camp) by 

providing for as of right development of the Power Station with secondary 

approval processes for more detailed plans.  However, the Panel considers 

SUZ2 should specify some key performance expectations, rather than just 

indicating the scope of plans to be submitted.  To provide greater certainty 

about the basis for assessment of the subsequent Development Plan and 

EMPs, SUZ2 should explicitly state that the EES and Ministers Assessment 

establish the basis for subsequent approvals.  Key parameters, such as 

Page 10

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

maximum noise levels, establishing the need for DSE approval of offsets for 

any losses of native vegetation and provision for off‐site landscaping to 

mitigate visual impacts, should be specified in the schedule.  This provides 

affected third parties with an avenue to pursue enforcement of compliance 

with requirements that would not be available under other approvals. 

The Panel considers that the SUZ2 should indicate that the Planning 

Authority should have regard to the views of nominated agencies when the 

Development Plan and EMP are assessed.  This will recognise that review is 

required by those with more specific expertise than is available to Council. 

EES Assessment Objective: To enable outcomes consistent with ecologically 

sustainable development over the short and long term, having regard to the 

likely overall economic, social and environmental effects. 

On the basis of the information presented, the Panel finds that the project 

will result in a net benefit to the community.  The EES has established that 

there is a sound planning rationale for the project to generate power with 

lower intensity of greenhouse gas emissions and provides a solid framework 

for further development of the project plans to mitigate potential 

environmental impacts. 

The Panel sees strategic planning and co‐ordination of regulatory processes 

on a sub‐regional level as important to achieve optimum outcomes from the 

very substantial investment in the energy sector anticipated for the region.  

DPCD would appear to be the appropriate agency to lead such a process 

which should involve the range of stakeholders including local government, 

public and private service/infrastructure providers, project proponents, 

representatives of business organisations, and members of the community 

affected by infrastructure projects.  The Panel emphasises, however, that a 

pragmatic approach with a strong focus on specific outcomes that can be 

realised within the lead time of the projects will be vital. 

Consolidated Recommendations

Based on the reasons set out in this Report, the Inquiry Panel recommends 

that: 

1. Ensure that construction of the gas and water pipelines is undertaken in accordance with the requirements of the Referral Decisions under 

the EPBC Act. 

2. Ensure the EMPs under the various approvals  are consistent and are generally in accordance with the  Strategic EMP and Environmental 

Commitments exhibited with the EES, as varied by recommendations 

Page 11

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

of this Panel and the Minister’s Assessment under the Environment 

Effects Act. 

3. The Proponent actively pursue the option of providing accommodation for power station and gas pipeline construction workers in towns or 

other existing facilities. 

4. DPI consult with the relevant Shire about the location and conditions that should apply if, despite this Panel’s recommendations, a 

construction camp is proposed along the gas pipeline route for 

construction workers. 

5. Implement the following noise limits at the nearest residence in the EPA Works Approval and the EMPs for the Power Station and 

compressor station: 

operational noise: 

34 dB(A) under worst case weather, (CONCAWE Category 6) 

32 dB(A) under neutral weather (CONCAWE Category 4); and 

construction noise: 

55 dB(A) during the daytime (7am to 6pm); 

37 dB(A) during the evening (6pm to 10pm); and 

32 dB(A) at night (10pm to 7am). 

6. Incorporate specific control measures for each watercourse crossing in Construction EMPs. 

7. Manage acid sulphate soils found at the Curdies River in accordance with the requirements of the EPA and DSE policies and guidelines. 

8. Design the stormwater management system for the Power Station site to implement best practice sedimentation and pollution control 

measures to the satisfaction of EPA, and limit impacts to maintain the 

current discharge volume hydrology to Shaw River. 

9. Undertake targeted aquatic flora surveys once stream crossing points and techniques are confirmed, in order to identify the relevant EVCs 

and prepare net gain assessments where required. 

10. Ensure that site specific requirements are included in construction EMPs, including appropriate rehabilitation techniques and monitoring 

measures for rehabilitation success, specific to terrestrial flora and 

fauna identified through targeted surveys. 

11. Manage the noise impacts of the construction of the gas and water pipelines under the EPA Noise Control Guidelines (Publication 1254: 

October 2008, and in particular: 

Page 12

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

Other than in unusual circumstances, the gas pipeline 

construction activities should be restricted to 6am to 6pm, seven 

days per week (noting lower noise threshold requirements for 

activities conducted on Saturdays and Sundays).  Early‐morning 

activities from before 7am should be restricted to low‐noise 

work, such as vehicle arrivals and toolbox meetings. 

Water pipelines construction activities should be restricted to 

7am to 6pm Monday to Friday, and 7pm to 1pm on Saturdays. 

12. Inform residents of the nature of the works, expected noise levels, duration of works and a method of contact. 

13. Monitor noise at the sensitive receptors nearest to the Power Station and compressor station under representative conditions during the 

commissioning of each stage of the project to confirm compliance with 

the criteria. 

14. Make the results of any noise monitoring of the project and responses to noise complaints available to the community liaison forum.  Ensure 

Construction EMPs for the gas and water pipelines require: 

Appropriate works to ensure rehabilitation to former condition; 

Immediate post construction audits to confirm native vegetation 

losses and offsets; and 

Follow‐up audits at two years post construction, to confirm 

actual native vegetation losses and revise offsets, if required. 

15. Require a monitoring program broadly in line with that outlined in Appendix D to: 

Assess the impact of water discharged from the Power Station. 

Establish the occurrence of the Southern Bent‐wing Bat on the 

Power Station site and the need for management or ‘offsetting’ 

measures if impacts from the Power Station are identified. 

16. Ensure that, in addition to commitments in the EES, lighting: 

Is the minimum required for access and safe operation of parts of 

the facility that are actually in use; 

Incorporates sensor activation; and 

Is baffled to avoid light spill above the horizontal. 

17. Review the design of the intersection of Riordans and Hamilton–Port Fairy Roads in consultation with VicRoads with a view to providing an 

acceleration lane for fully laden B Double trucks turning left from 

Riordans Road onto the Hamilton – Port Fairy Road. 

18. Provide a sealed upgrade of Riordans Road from the Hamilton–Port Fairy Road intersection to: 

Page 13

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

The entrance of the Power Station before development starts, 

and internally for all roads regularly used by B double vehicles; 

and 

The entrance of the camp before development starts, if a 

construction camp is proposed in the vicinity of the Power 

Station. 

19. Provide a free bus service, at the cost of the Proponent, for construction workers from locations identified in the accommodation strategy (eg 

Warrnambool, Port Fairy and Mortlake) to the Power Station for the 

duration of construction. 

20. Review and address potential impacts of the concrete batching plant in the Traffic Management Plan. 

21. Include requirements relating to decommissioning of the project in relevant project approvals. 

22. Ensure Construction EMPs for the gas and water pipelines include measures to protect and re‐instate dry‐stone walls that may be impacted 

by construction. 

23. Ensure appropriate management of safety risks to future development associated with the project (Options to consider include both pipe 

thickness specification in areas with potential for future development 

and an overlay for land where risks associated with the proximity to the 

project either preclude development or require specific design 

measures). 

24. Ensure the Proponent provides ongoing training to both the CFA and SES to enable effective responses to potential emergency situations. 

25. Require independent compliance auditing and testing by suitably qualified people at relevant stages of the development process with 

performance requirements of the following matters: 

Air emissions. 

Noise emissions. 

Surface water management systems and the quality of water 

discharged from project sites. 

Impacts on native vegetation. 

Post construction rehabilitation of pipeline easements. 

Page 14

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

26. Maintain a Project Liaison and Monitoring Committee which: 

Is led by the Shire of Moyne with active participation by the 

Proponent and relevant agencies (including EPA, DPI, DSE); 

Includes representation of nearby residents; and 

Is resourced by the Proponent. 

27. Establish a similar community liaison forum led by the Shire of Corangamite to operate during the construction and rehabilitation 

phases of the gas pipeline and Compressor Station. 

28. Include complaints handling processes in EMPs that adopt the principles outlined in Australian Standard Customer Satisfaction – 

Guidelines for complaints handling in organizations (AS10002:2006). 

29. Evaluate the merits of: 

Requiring a bond to guarantee site rehabilitation after 

decommissioning of project infrastructure. 

Upgrading roads to provide better connections between the 

Shaw River and Tarrone power station sites with the quarry to 

the south east, and, if substantial benefits are identified, the 

appropriate basis for contributions to such works. 

The potential to upgrade the capacity of the water supply mains 

to the Power station to meet the needs of the proposed Tarrone 

Power Station and other users along the pipeline route. 

Amendment C36

Based on the reasons set out in this Report, the Panel recommends that 

Amendment C36 be adopted with the changes listed below: 

30. Require the Proponent to enter into a Section 173 agreement before Amendment C36 is approved to the satisfaction of the DPCD and the 

planning authorities to ensure early conduct of an accommodation and 

community services strategy for the project. 

SUZ2 

31. Revise the table of the uses in the Schedule 2 to the SUZ to apply the existing Farming Zone table with the additional as of right uses in the 

exhibited SUZ2 (except that construction camp would be a section 2 

use). 

Page 15

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

32. Revise the Schedule 2 to the SUZ and the Clause 52.03 incorporated document to require a permit for a temporary construction camp. 

33. Revise the exemptions from permit requirements in Clause 3 of Schedule 2 to the SUZ for buildings and works as follows: 

‘Rearrange, alter or renew existing plant if the location, area or 

height of the plant is not increased.’ 

Delete the exemption ‘‘result in a minor rearrangement of on‐site 

roads and access ways, car parking areas and landscaping 

provided that their areas and effectiveness are not diminished.’ 

Are accommodation and temporary amenities provided for 

persons constructing and commissioning any plant on the land. 

34. Specify that the Development Plan and EMPs must address the principles, actions and commitments contained in the exhibited 

Environment Effects Statement,  including the Strategic EMP and 

Environmental Commitments, except where they are specifically varied 

in the Minister’s assessment of Environmental Effects and Panel Report 

or by the conditions of other statutory approvals. 

35. Specify that the Responsible Authority will have regard, as appropriate, to the views of relevant agencies (including DPI, EPA, 

DSE, VicRoads, ESV, WorkSafe Victoria) when the Development Plan 

and EMPs are considered. 

36. Specify in the schedule the particular requirements recommended by this Panel, including: 

Compliance with recommended noise limits. 

Compliance with SEPP (Air Quality Management) and SEPP 

(Waters of Victoria) design criteria and standards. 

Matters identified in Chapter 6.2 recommendations relating to 

Safety Management Plans. 

A sealed upgrade of Riordans Road from the Hamilton – Port 

Fairy Road intersection to the entrance of the Power Station 

(before development starts) and internally for all roads regularly 

used by B double vehicles. 

Provision of sufficient parking at the Power Station to meet 

requirements during construction phase and maintenance 

periods. 

Incorporation of management measures from the approved 

Cultural Heritage Management Plan. 

An ‘Off‐site Landscaping Plan’ to mitigate the visual impact. 

Page 16

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

Site specific requirements in construction EMPs which include 

appropriate rehabilitation techniques and monitoring measures 

for both aquatic and terrestrial flora. 

Southern Bent‐wing Bat monitoring on the Power Station site. 

37. Require the Construction EMP and Operations EMP for the Power Station to include a Safety Management Plan prepared by a suitably 

qualified person. 

38. Provide for the responsible authority to have regard to the views of ESV in the Operations EMP. 

39. Include a Development Plan requirement for an ‘Off‐site Landscaping Plan’ to mitigate the visual impact of the Power Station from dwellings 

within 3km of the Power Station site.  Where an offer is accepted, the 

plan should: 

Be prepared by the relevant landowner or the Proponent; 

Incorporate the species to be used, timetable, and maintenance 

arrangements; 

Be implemented within 12 months of the endorsement (unless 

otherwise agreed between the landowner and the Proponent); 

and 

Specify that all costs for design, implementation and 

maintenance are to be the responsibility of the Proponent or 

operator. 

40. Apply a sunset provision to the SUZ2 to revive the previous Farming Zone if the Power Station use does not operate for a nominated time 

(say five years). 

41. In Clause 3 ‘Rearrange, alter or renew existing plant if the location, area or height of the plant is not increased. 

Clause 52.03 

42. Include the address of the land to the east of Old Dunmore Road in the table in the schedule to Clause 52.03 and attach the relevant maps to the 

schedule to that Clause. 

43. Revise the Clause 52.03 incorporated document to extend exemptions from permit requirements to alterations and removal of dry stone walls 

along the water pipeline alignment. 

44. Require a Construction EMP where exemptions from permit requirements are provided under Clause 52.03. 

Page 17

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

OTHER RECOMMENDATIONS 

45. Develop a strategy for and implement specific measures to ensure effective responses to the cumulative impacts of major energy projects 

in the regions (Note: DPCD is suggested as the appropriate agency to 

lead such a process). 

46. Include cumulative impacts in the scoping requirements for future EES assessments or matters to be addressed in application documentation 

for future major infrastructure projects. 

47. Require the Proponent (and proponents for future infrastructure projects) to enter into a Section 173 agreement to the satisfaction of the 

DPCD and the relevant planning authorities to contribute to the cost of 

planning for and developing co‐ordinated responses to the various 

major infrastructure projects in the region. 

Page 18

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

1. Introduction

1.1 The Project

The project comprises: 

A gas‐fired power station near the town of Orford; 

A gas compressor station north‐west of Port Campbell; 

A gas pipeline from Iona to Orford; and 

Water supply infrastructure, including new recycled water treatment 

plant (RWTP), and two water pipelines from Port Fairy to Orford (Figure 

1). 

The project responds to the forecast shortfall in generating capacity in the 

National Electricity Market from 2012/13 by using eastern Australia gas 

reserves to generate electricity at a lower intensity of greenhouse gas 

emissions than coal fired power. 

 

Figure 1  Locality Map (Source: EES Summary Report) 

The gas fired power station is proposed on a 110 ha site approximately 27 

km north of Port Fairy at the corner of Riordans and Old Dunmore Roads, 

Orford.  It will connect to the Victorian and national electricity grid via a 

switchyard adjacent to the Moorabool–Portland 500‐kV overhead 

transmission line which passes through the site.  Surrounding land uses 

include timber production and broad scale dryland farming.  The site is well 

removed from urban areas and the nearest houses are 1.6 km away. 

Page 19

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

The Power Station development would occur in three stages as a baseload, 

intermediate or peaking generator to ultimately provide a peak capacity of 

1,500MW.  The EES assessed the following options to provide flexibility to 

develop the project in response to electricity market conditions: 

1. Option 1 is to develop three combined‐cycle gas turbine stages (500MW 

capacity each) resulting in a total capacity of 1,500MW.  This Stage 1 

option would principally be used for baseload generation but can be 

deployed for intermediate generation; and 

2. Option 2 is for Stage 1 to be developed as an open‐cycle gas turbine (255 

to 312MW capacity) which may be converted to a 500MW combined‐cycle 

gas turbine after either Stage 2 or Stage 3 is constructed.  This Stage 1 

option has the capacity to generate peak, intermediate or baseload 

electricity from ‘cold starts’, and has the flexibility to be deployed in any 

of these formats to respond to market conditions. 

The EES assumes that each stage will be developed and brought into 

operation before the next stage is commenced.  However, witness statements 

assessed an ‘alternative development scenario’ with a staggered construction 

of Stages 1 and 2. 

 

Figure 2  The Power Station Site (Source: EES Summary Report Figure 4) 

The 2.4 ha Compressor Station site is approximately 5 km north of Port 

Campbell and approximately 500m north of the intersection of Smokey Point 

and Pascoes Roads.  Infrastructure to be installed at the compressor station 

comprises six 4.6MW gas‐fired turbines (compressor units) necessary for 

operation of the Power Station at full capacity, inlet gas filtering equipment, 

meters for pressure and flow control, gas quality monitoring equipment, a 

Page 20

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

scraper launcher and receiver station, a control building, amenities, 

workshop and storage area.  The compressor station site will be sealed or 

covered with gravel. 

   

Figure 3  Compressor Station Layout (Source: EES Figure 8.2) 

A high‐pressure, underground Gas Pipeline of approximately 94 km is 

proposed between the Iona and Otway gas plants near Port Campbell and 

the proposed Power Station at Orford (see Figure 1).  This new pipe would 

connect to the South West Pipeline (east of Otway Gas Plant).  The pipeline 

alignment within the nominally 500m wide pipeline corridor1 has been 

progressively refined.  A 100 to 200 m wide strip centred on the conceptual 

gas pipeline alignment was nominated for detailed investigations required to 

inform the EES.  Except for road and waterway crossings, the gas pipeline 

alignment will generally be through private land which is predominantly flat 

to gently undulating, cleared dryland pasture. 

Wannon Water proposes to build, own and operate upgraded Water Supply 

Infrastructure with the following components to supply water to the 

proposed power station: 

Use of recycled water for processing, to avoid reducing local drinking 

water supplies.  The process water supply will be either used directly in 

the Power Station, or further treated for use in the steam cycle. 

1 The corridor is wider at sites where there is potential need for realignment has been identified.

Page 21

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

New infrastructure at existing Wannon Water facilities in Port Fairy to 

supply amenity (potable) water and up to 450 ML per annum of process 

(recycled) water to the Power Station. 

Two approximately 28‐km long pipelines in a shared trench to carry the 

process and amenity water from Port Fairy to the Power Station. 

At Port Fairy, the amenity water pipeline runs from the Port Fairy water 

treatment plant to a proposed recycled water treatment plant(RWTP).  The 

proposed RWTP occupies less than 1 hectare of disused land in the northern 

portion of the larger 35 ha Wannon Water site which is approximately two 

kilometres northeast of the Port Fairy town centre.  From the new RWTP, the 

amenity and process water pipelines follow the water reclamation plant 

access road to Hamilton–Port Fairy Road.  The pipeline is then generally 

aligned along Hamilton–Port Fairy and Old Dunmore Roads. 

The Wannon Water site, including the RWTP and land directly surrounding 

it, is zoned Public Use – Service and Utility.  Land surrounding the site is 

primarily used for agriculture, with low density housing further to the east. 

Construction Camps 

The EES indicates that the construction workforce may live in existing 

accommodation in nearby towns and commute to the site in light vehicles 

and buses or potentially could live within a temporary construction camp 

established for the project near the power station site, along the pipeline 

routes or in towns nearby.  Amendment C36 provides for as of right 

development of construction camps on the Power Station site, on land 

immediately to the east of the Power Station or along the pipeline route. 

1.2 Overarching Policy Context

Planning policy encourages development that makes efficient use of energy 

and minimises greenhouse gas emissions (SPPF Clause 15.12‐1).  It also 

provides for delivery of high pressure pipeline infrastructure at minimal risk 

to people and the environment (the Pipelines Act 1995, SPPF Clause 18.11).  

While there is a predisposition in favour of projects that advance these broad 

‘sector specific’ policies, the assessment of process must encompass and 

integrate relevant environmental, social and economic factors.  It is the 

government expectation that planning decisions making will ‘balance 

conflicting objectives in favour of net community benefit and sustainable 

development.’ (SPPF Clause 11). 

Specific policy guidance is referred to in subsequent chapters but it is not 

proposed to restate in this report all of the relevant local and state planning 

policies which are set out in the EES. 

Page 22

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

1.3 Overview of Statutory Approvals Required

The complex regulatory framework for the project was the subject of some 

discussion at the Hearing and the Panel returns to the regulatory 

implications, where relevant, in our discussion of issues in subsequent 

chapters of this report.  Chapter 2 of the EES summarises the approvals, 

licences, consents and permits required for the three main components of the 

project.  A copy of EES Table 2.1 which summarises key approvals and 

assessments required is included in Appendix C of this report.  The main 

statutory approvals required for the project were summarised as: 

The Power Station 

Generation Licence and Connection Agreement under the Electricity 

Industry Act 2000.  These approvals take the EES stakeholder consultation 

into consideration but do not rely upon the EES to inform the process. 

Registration and Licence to Operate a Major Hazard Facility under the 

Occupational Health and Safety Act 2004.  A Safety Case must be prepared 

and will be informed through the preparation of the EES. 

Amendment C36 proposes to change approval requirements under the 

Moyne Planning scheme (see discussion in Chapter 11.3). 

Works Approval and licence to discharge under the Environment 

Protection Act 1970 are triggered by the Power Station classification as a 

Scheduled Premises under the Environment Protection (Scheduled Premises 

and Exemptions) Regulations, the potential air emissions from the Power 

Station, sewage treatment and the on‐site water treatment to upgrade the 

process water. 

The Gas Pipeline (including compressor station and a possible associated 

construction camp) 

Licence to Construct and Operate a Pipeline under the Pipelines Act 2005 

(which sets aside planning scheme provisions that would otherwise 

apply)2 which is administered by DPI and involves: 

Permission to access private and public land. 

Approval of a  consultation plan by the Minister for Energy and 

Resources (DPI) before giving notice of the intention to enter land 

or notice of a pipeline corridor to landholders (approved for the 

project in October 2008). 

2 The consensus view at the hearing was that exemption from planning scheme provisions under the

Pipelines Act (s85) extends to the inlet metering station, compressor station and the midline valve as they form part of the pipeline system apparatus to convey the gas. It was suggested that this exemption would apply to a temporary camp for pipeline construction workers.

Page 23

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

Approved safety management plans for construction and for 

operation which must be accepted by Energy Safe Victoria before 

construction or operation of the gas pipeline commence. 

Approved EMPs for construction and operations. 

Written consent to operate a pipeline from the Minister for Energy 

and Resources. 

Works approval and licence to discharge under the Environment Protection 

Act 1970 triggered by emissions of nitrogen oxides from the compressor 

station. 

A Connection Agreement under the Gas Industry Act 1997 from the 

Australian Electricity Market Operator (AEMO). 

The Water Supply Infrastructure and Pipelines 

A licence under the Water Act 1989 to construct, alter, remove or abandon 

works on a waterway through several waterways, including Ware Creek, 

to meet the requirements of the local water authorities and DSE. 

Works approval and licence to discharge under the Environment Protection 

Act 1970 for the upgrade to the Port Fairy water reclamation plant. 

Amendment C36 proposes to change approval requirements under the 

Moyne Planning scheme (see discussion in Chapter 11.3). 

Environmental Management Plans (EMPs) 

Management plans provide the primary mechanism for managing safety and 

environmental impacts from the project under the key pieces of legislation.  

A detailed Strategic EMP was publicly exhibited with the EES (EES 

Attachment 5) and its content will not be repeated in this report.  Much of the 

Strategic EMP content was also incorporated in the Environmental 

Commitments in EES Attachment 4.  The Strategic EMP addresses: 

The legislative context and standards; 

Environment, health and safety management systems which encompass 

policy, planning, implementation, checking, corrective action and 

management review; 

Integrated risk assessment, including residual risks; and 

Management guidelines relating to geology, soils and landforms; 

hydrology, surface water and groundwater; ecology; air quality; noise; 

visual impacts; traffic management; cultural heritage; land access; and the 

management of waste and hazardous materials. 

These plans will also draw on and form part of established systems for 

matters such as environmental management and occupational health and 

safety that already guide the actions of the Proponents. 

Page 24

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

The Panel finds that the Strategic EMP establishes a sound framework and 

basis for the development of more detailed Construction EMPs, Operations 

EMPs and Safety Management Plans (SMPs). 

1.4 EES Evaluation Objectives

The scoping requirements issued by DPCD specified the following 

evaluation objectives to guide the evaluation of the project and the EES.  

These objectives establish the basis for the Panel assessment.  In summary, 

the EES objectives relate to the efficient supply of energy and the intensity of 

greenhouse gas emissions; impacts on biodiversity values; impacts on water 

catchment values; Aboriginal and Non‐Aboriginal cultural heritage; health, 

safety and amenity impacts; disruption to landuse and infrastructure; the 

framework for managing environmental impacts; and the overall economic, 

social and environmental effects. 

These objectives are clearly relevant to the Panel’s evaluation of the project 

and have determined the structure of this report. 

1.5 Identification of Issues

For a project of the scale proposed there were few issues raised in 

submissions to the Panel which provided a high degree of confidence that 

outstanding matters were capable of resolution. 

The remainder of this report is structured on the basis of the EES evaluation 

Objectives.  Some of the key issues addressed relate to: 

the noise criteria to be adopted for the project and the assurances in the 

regulatory framework proposed of compliance with the criteria; 

the management of pipeline crossings of sensitive waterways, the efficacy 

of Horizontal Directional Drilling (HDD) in these circumstances and the 

need for contingency plans; 

the nature of offsets for unavoidable losses of native vegetation; 

the need for further assessment of aquatic ecological values; 

the need to ensure the planning framework requires consideration of 

safety along the gas pipeline when new development is proposed; 

housing for workers, including whether construction camps should be 

facilitated; 

the cumulative impacts of multiple infrastructure projects in the region; 

and 

ensuring subsequent approval processes can draw on appropriate levels 

of technical expertise. 

Page 25

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

2. Power Generation: Efficiency, Affordability and Greenhouse Gas Emissions

EES Evaluation Objective: To provide for the development of base load and 

intermediate load power generation capacities in the context of government policy 

objectives to maintain a secure, efficient and affordable supply of energy while 

reducing the intensity of greenhouse gas emissions from the energy sector. 

2.1 Rationale for Additional Gas-fired Power Generation

The EES notes that reliance on gas‐fired generation to facilitate the transition 

to low‐emissions technologies is emphasised in the Victorian Minister for 

Energy and Resources’ statement, Energy for Victoria (NRE, 2002a): 

Natural gas is widely seen as playing a significant role in providing a 

secure energy supply source. 

This is because natural gas: produces substantially lower greenhouse 

emissions than brown coal technologies; is more competitive than current 

renewable sources; and has sufficient flexibility to fuel large base load 

and peaking plants as well as small‐scale distributed and high‐efficiency 

generation. 

The EES (Chapter 3) describes the rationale for the project, based on 

opportunities in the gas and electricity markets, the forecast conditions that 

create the need for additional electricity generation capacity, and specifically 

in the case of Shaw River Power Station, the following: 

Victorian electricity baseload generation is nearing peak capacity.  The 

EES notes that maximum demand under a medium‐growth scenario is 

forecast to increase by an annual average rate of 2% for the winter period 

and 2.4% for the summer period, over the 10 years to the end of 2018/19.  

Forecast summer electricity supply‐demand shows that additional 

generating capacity will be required in Victoria and South Australia from 

start 2012/13, with the additional capacity initially required in South 

Australia.  The proposed Power Station, which is planned to commence 

operation in late 2012 or early 2013, would contribute to meeting the 

predicted shortfall in electricity supply; 

while the proposed Power Station will contribute to greenhouse gas 

emissions, the lower emissions intensity of natural gas and the proven 

efficiency of combined‐cycle, gas‐turbine technology will reduce the 

average greenhouse gas intensity of the Victorian electricity supply (See 

EES Chapter 3.4); 

Page 26

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

the proposed emissions trading scheme is evolving towards facilitation of 

less carbon intensive power generation using gas as a transitional fuel; 

reliable baseload capacity is needed in addition to more intermittent 

supply from renewable energy technologies.  Even with substantial 

advances in renewable energy, investment in gas‐fired generation will be 

required to compensate for reduced coal‐fired generation and to ensure a 

secure and reliable baseload electricity supply.  It is expected that carbon 

prices under a functional Carbon Pollution Reduction Scheme (yet to be 

proposed) will make it unlikely that new brown coal‐fired generating 

plants will be built in the future without carbon capture and storage 

capability; 

responsible use of water resources through the use of recycled water and 

low consumption technologies is now a state government priority; and 

high efficiency equipment for the generation of electricity will be used. 

2.2 Greenhouse Gas Emissions

2.2.1 Regulatory Framework and Policy Context

The Kyoto Protocol legally requires developed countries to reduce domestic 

greenhouse gas emissions to the country’s internationally agreed target.  

Australia’s national annual target is 108% of our 1990 emissions.  Preliminary 

estimates of Australia’s greenhouse gas emissions for 2007 over 2006 data 

show an overall increase of 1.6% and greenhouse gas emissions from the 

energy sector increased by 3%.  This is within the Kyoto target of 108%, being 

106% over 1990 levels (DCC 2008a).  On a sectoral basis, greenhouse gas 

emissions from the stationary power sector have increased by over 47% from 

1990 to 2006. 

The National Greenhouse and Energy Reporting Act 2007 establishes a 

mandatory corporate reporting system for greenhouse gas emissions, energy 

consumption and production. 

SEPP (AQM) provides the framework for assessment of greenhouse gas 

emissions and the Victorian Protocol for Environmental Management 

Greenhouse Gas and Energy Efficiency in Industry (PEM) requires 

implementation of best practice in greenhouse gas emissions and energy 

consumption.  Compliance with the SEPP (AQM) greenhouse gas emission 

and energy efficiency reporting requirements is also required.  Once in 

operation, the Shaw River Power Station facility will be required to: 

manage greenhouse gas emissions and energy consumption as part of 

their integrated environmental management practices; 

Page 27

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

report to the Victorian EPA through its annual license holders report: 

annual energy consumption; greenhouse gas emissions; and actions 

implemented and to be implemented the following year; and 

regularly review operations to identify opportunities to further reduce 

energy use. 

Environment and Resource Efficiency Plan (EREP) program requires large 

users of energy and water, such as Shaw River Power Station3, to: 

assess energy and water use, and waste generation; 

develop an EREP that includes actions with a three year or better payback 

to reduce energy, water and waste production; and 

implement the actions in the approved EREP and report on progress. 

The Proponent indicates it will employ commercially proven power 

generation technology which will operate at efficiency beyond applicable 

benchmarks in Australia (see EES Figure 4.1).  The Proponent will be subject 

to ongoing emissions and energy reporting commitments under NGER.  In 

this context it is the intention to apply for a five‐year exemption to the EREP 

requirements, subject to approval of the Victorian EPA. 

State Planning Policy (Clause 15.12 Energy Efficiency) seeks to encourage 

land use and development that is consistent with the efficient use of energy 

and the minimisation of greenhouse gas emissions. 

2.2.2 EES Assessment - Greenhouse Emission Estimates

The EES greenhouse gas emission forecasts accounted for: 

direct emissions from sources that are owned or controlled by the 

reporting entity (Scope 1); 

indirect emissions from the generation of energy products (eg. electricity, 

steam/heat and reduction materials used for smelting) purchased by the 

entity (Scope 2); and 

other indirect emissions that are a consequence of entity activities but are 

from sources not owned or controlled by that entity (Scope 3). 

For the Power Station development the bulk of the annual operational Scope 

1 emissions, 98.2%, is associated with combustion of natural gas in the Power 

Station; the remainder is predominately associated with gas compressor 

operation.  It was considered Scope 3 emissions contribute approximately 

3 Shaw River Power Station will be required to participate in the EREP program as it will use more

than 100TJ of energy per year.

Page 28

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

10.2% to annual operational greenhouse gas estimates; Scope 3 emissions 

being predominately associated with the supply of natural gas. 

The EES indicated construction greenhouse gas emissions contributes a very 

small fraction of the entire project emissions over a forecast 25‐year lifespan. 

Greenhouse Intensity of Electricity Generation 

The EES indicates that each unit of energy provided by the combustion of 

natural gas results in less greenhouse gas emissions in comparison with 

other fossil fuels, particularly coal.  In Victoria most electricity is supplied at 

present by brown coal fuelled generation which, due to high moisture 

content, has particularly high greenhouse gas emissions per unit of usable 

energy released. 

Combined cycle gas turbines have significantly higher thermal efficiencies 

than the current fleet of power generators in Australia.  The electricity 

generated by Shaw River Power Station will produce significantly less 

greenhouse gas emissions per unit of generation than current Australian and 

Victorian averages. 

The emissions intensity of electricity generated by the proposed Power 

Station will increase if Option 2 is selected, as the open cycle gas turbine does 

not employ cogeneration.  The emissions intensity of the open cycle gas 

turbine and combined cycle gas turbines are both lower than those detailed 

for relevant Australian Best Available Technology benchmarks.  The overall 

emissions intensity of the Power Station can be decreased by converting the 

open cycle gas turbine to combined cycle as soon as possible. 

Comparisons with Best Available Technology standards sourced from the 

Australian Greenhouse Office (now Department of Climate Change DCC), 

provides a useful Australian benchmark for greenhouse intensity (i.e., kg 

CO2‐e/MWh sent out) in electricity generation, based on the most efficient 

currently available equipment for each fuel and generation type.  This 

comparison indicates that Shaw River Power Station is approximately: 

57% less greenhouse intensive than wet cooled black coal fuelled ultra 

supercritical boiler; 

68% less greenhouse intensive than wet cooled brown coal fuelled ultra 

supercritical boiler; 

40% less greenhouse intensive than a natural gas fired open cycle gas 

turbine; and 

6% less greenhouse intensive than benchmark natural gas fuelled 

combined cycle gas turbine with wet cooling.

Page 29

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

The Figure below shows the Australian benchmarks for various fuels and 

technologies compared with the forecast performance of the project and the 

current Victorian average.  The EES Greenhouse Gas Assessment (Appendix 

7) concluded that the proposed Power Station will be up to 70% less 

greenhouse intensive (kg CO2‐e per megawatt‐hour sent out) than the current 

Victorian power production average.  This fits with Victorian Government 

policy that seeks an orderly transition to low‐emissions technologies to assist 

Victoria to reduce emissions from the stationary energy sector. 

 

The thermal efficiency of a power station describes the quantity of electricity 

generated per unit of energy input in the form of fuel.  There is a direct link 

between efficiency and greenhouse intensity.  Figure 4.2 shows the thermal 

efficiency of the proposed Power Station, in comparisons against Best 

Available Technology standards for power generators4. 

4 Sourced from Technical Guidelines: Generator Efficiency Standards published by the Australian

Greenhouse Office (AGO 2006).

Page 30

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

 

Impact of Shaw River Power Station 

Currently the carbon intensity of electricity generation in Victoria is 1220 kg 

CO2‐e/MWhr (carbon dioxide equivalents per Megawatt hour)(DCC 2008c).  

Victoria’s carbon intensity is the highest of all the states, and can be 

attributed to the extensive use of brown coal. 

Despite being a significant direct emitter of greenhouse emissions, operation 

of the proposed Power Station will cause an overall reduction in greenhouse 

emissions intensity associated with electricity supply in Victoria.  Every 

Megawatt hour (MWhr) of electricity generated by the proposed Power 

Station at 342 kg CO2‐e/MWhr will reduce the average intensity of the 

current Victorian generation supply. 

2.2.3 Submissions and Proponent Response

The Corangamite Shire submission noted that the project would lead to 

increased greenhouse gas emissions estimated between 3‐4 million t CO2‐e 

annually. 

In response  Mr Ormerod noted that: 

The development is part of a long‐term and state‐wide process of 

progressively meeting new electrical demand by installing lower 

Page 31

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

carbon intensity generation capacity, and building the basis for 

the replacement of aged and inefficient power stations that have 

very high carbon intensity. 

The EPA submission noted that further technical details will need to be 

provided to adequately assess whether or not the requirements of the PEM 

are met.  The EPA’s written submission identified requirements in relation to 

efficiency and green house gas emissions as follows: 

The Greenhouse PEM requires identification and implementation of best 

practice with respect to greenhouse gas emissions and energy 

consumption for Victorian businesses subject to EPA works approvals 

and licensing.  Exactly what constitutes best practice will depend on 

technical, logistical and financial considerations that need to be 

demonstrated by the Proponent.  Under the PEM, Works Approval 

applicants need to demonstrate that they have identified and will be 

implementing best practice in relation to energy use and greenhouse gas 

emissions associated with works/activities/processes that are the subject 

of the application. 

Further technical and logistical consideration of measures to 

minimize, sequester and/or offset greenhouse gas (‘GHG’) 

emissions will be needed to assess the practicability of different 

technologies and practices. 

The Proponent has indicated that the proposal will have greenhouse 

benefits, as the use of gas to fuel electricity generation is less greenhouse 

intensive than energy from coal fired sources. 

In relation to energy use related greenhouse gas emissions, Shaw River 

will be required to comply with the requirements of the PEM and 

demonstrate that its equipment choice meets the best practice 

requirements of the PEM.  Information confirming that the specific 

process and options proposed are best practice in terms of energy 

efficiency and GHG emissions will be required.  It is noted in 

particular that the proposal to construct the open cycle plant will not 

constitute best practice for energy efficiency or GHG emissions, though 

there may be mitigating factors such as required response times that can 

be taken into account. 

Ancillary plant items such as motors and drives, lighting, compressed air 

systems, etc will also need to be addressed in terms of best practice 

energy efficiency.  The intention that energy efficiency be included as a 

design criterion for equipment selection is noted. 

At the hearing it was noted that the above EPA view about the project 

included significant qualifications (as indicated by the added emphasis) but 

Page 32

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

Mr Frame confirmed that, based on the information provided to the EPA, the 

Power Station as proposed is best practice.  He further confirmed that as a 

part of the detailed review of the Licence application the EPA would be 

carefully reviewing the information provided to ensure that the power plant 

when constructed would be best practice in terms of efficiency and 

environmental impacts. 

2.2.4 Discussion and Conclusions

EPA’s comments regarding open cycle plants not necessarily meeting best 

practice are noted by the Panel, but it is also noted that the project proposes 

staged implementation to meet market demand and the conversion from 

open cycle plant to closed cycle over time. 

The Panel accepts the information and analysis provided in the EES, the 

expert evidence of Mr Ormerod and the submission from EPA that the 

project can be regarded as best practice and therefore satisfies the 

requirements of the PEM. 

The proposed power station will be a significant emitter of greenhouse gases 

when operational.  However, the combination of the natural gas fuel and the 

technology employed will result in the generation of electricity with 

substantially less greenhouse gas emissions per unit of electricity produced 

than the current Victorian average.  This is consistent with state government 

objectives and represents a major environmental benefit. 

2.3 The Power Station Site Selection and Design Efficiency

2.3.1 EES Assessment - Power Station Site Selection5 and Design Efficiency

The majority of baseload electricity is generated in the Latrobe Valley’s 

brown coal‐fired power stations in eastern Victoria.  The EES notes that 

considerable line losses are incurred in transmitting electricity to the west of 

Melbourne and a baseload power station in western Victoria would reduce 

line losses and improve electricity grid integrity. 

The location of the proposed power station was governed by two key factors 

– access to a natural gas supply and proximity to the Victorian electricity 

grid.  These factors are important from a project‐cost perspective to reduce 

the cost of gas and electricity transmission infrastructure required to connect 

the Power Station to its fuel supply and to the National Electricity Market.  

5 EES Chapter 6

Page 33

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

Lower fuel supply costs and reduced transmission losses increase the cost‐

effective electricity generation and the competitiveness of the Power Station 

in the National Electricity Market. 

Western Victoria was found to be the most desirable location for the 

proposed power station due to its proximity to the Otway Basin natural gas 

reserves and the Victorian Principal Transmission System at Iona Gas Plant 

and its strategic position with respect to electricity grid performance. 

The Power Station site selection process identified an area of interest 

extending from Derrinallum to Heywood and 5 km either side of the 

Moorabool–Portland 500‐kV overhead transmission line.  Developing the 

Power Station near the existing electricity transmission line would reduce or 

negate the need to construct overhead transmission lines, thereby reducing 

land use and amenity impacts.  Proximity to the Iona Gas Plant and existing 

gas pipelines would reduce gas pipeline length and provide opportunities to 

utilise existing infrastructure or existing infrastructure corridors. 

A constraints analysis using a geographic information system was 

undertaken to identify areas of least constraint for the proposed power 

station site, compressor station site and gas pipeline route.  Each site was 

evaluated and rated against potential constraints to development as set out 

below to identify most suitable sites for the proposed development.  Eleven 

sites were initially identified for consideration of which five sites were 

further evaluated in more detail in relation to the following criteria: 

site altitude; 

site electricity supply; 

site topography and inferred geotechnical conditions; 

electricity grid connection; and 

access to a reliable water supply to meet the requirements. 

Based on a review of site constraints of the final two sites, the Shaw River site 

was chosen. 

Mr Power advised that the development of the Power Station is proposed to 

be undertaken in three stages of nominal 500MW to a peak capacity of 

1,500MW, with timing and output determined by electricity and gas market 

prices.  Mr Napier advised that combined‐cycle technology, involving a gas 

turbine and a separate steam turbine in series on a single shaft driving a 

single electricity generator is the most efficient method of generating 

electricity from gas.  However, depending on the conditions of the National 

Electricity Market when the plant is constructed, the Proponent may 

construct two stages at once with one stage being an open cycle F‐class gas 

turbine unit.  While the open cycle is slightly less efficient than a combined 

Page 34

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

cycle it is more readily able to be used for peak power generation.  Gas 

consumption differences between combined and open cycle were estimated 

by PAEHolmes for the Proponent at less than 2%6.  Mr Napier advised that 

as the market matures it is anticipated that the open cycle turbine would be 

converted to a combined cycle unit and the Shaw River Power Station would 

be operated as a base load power station. 

2.3.2 Discussion and Conclusions

The Panel acknowledges that the proposed power station location is an 

efficient siting option, being west of Melbourne, on the 500kV grid, and 

comparatively close to the Iona gas fields.  It also notes that the proposed 

power station location, in an area with limited environmental constraints and 

low population densities has resulted in few critical objections from either 

local residents or agencies responsible for regulating the development.  The 

Panel notes in Chapter 10 however, that these same characteristics have 

attracted a number of energy generation projects along the transmission line 

corridor and it is suggested that strategic planning for the region should 

address access to this important infrastructure. 

Based on the information presented to the Panel, in particular the submission 

by the EPA in terms of further requirements in terms of efficiency and green 

house gas design requirements (see Chapter 2.2)  the Panel accepts that the 

Power Station will be designed to a high level of efficiency and to minimise 

environmental emissions. 

2.4 The Gas Pipeline Design and Route Options

2.4.1 Regulatory Framework and Policy Context

The Pipelines Act 2005 provides a specific regulatory regime for the gas 

pipeline which accords substantial authority to the Minster for Energy and 

Resources in determining pipeline routes and sets aside planning scheme 

provisions that would otherwise apply to the pipeline development and 

operation.  State planning policy (Clause 18.11) identifies strategies for the 

delivery of high pressure pipeline infrastructure at minimal risk to people 

and the environment which include: 

Existing transmission‐pressure gas pipelines should be recognised in 

planning schemes and protected from further encroachment by residential 

development or other sensitive land uses, unless suitable additional 

protection of pipelines is provided. 

6 Appendix 8.

Page 35

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

The siting of new pipelines should be planned along routes with adequate 

buffers to residences, zoned residential land and other sensitive land uses 

and with minimal impacts on waterways, wetlands, flora and fauna, 

erosion prone areas and other environmentally sensitive sites. 

2.4.2 The EES Assessment - Gas Pipeline

The EES identified three gas pipeline routes for further investigation: a route 

to the north of the SEA Gas and Western pipelines, a route to the south of 

those pipelines and a route along those pipelines.  A drive‐by inspection and 

an aerial reconnaissance by helicopter were carried out to verify the mapping 

information used to identify the gas pipeline route options, to determine the 

feasibility of the routes and to refine the proposed gas pipeline route. 

The EES stated that community concerns about the proliferation of gas 

pipelines in western Victoria were a major consideration in the evaluation of 

gas supply options.  Options using existing gas pipeline easements were 

explored but rejected due to legal and commercial issues, and the 

arrangement of the gas pipelines in the easements.  The northern gas pipeline 

route was found to be the most favourable route as it minimised pinch points 

and engineering constraints and reduced the potential for impacts on land 

use and ecology. 

Geographic information system data, high‐resolution satellite imagery and 

site inspections were used to design the conceptual gas pipeline alignment.  

A 100‐200 m wide corridor centred on the conceptual gas pipeline alignment 

was nominated for detailed geotechnical, ecological, and cultural heritage 

investigations required to inform the EES.  The conceptual alignment was 

progressively refined to address landowner concerns and issues identified in 

the detailed investigations.  Additional studies have been undertaken to 

assess the potential environmental impacts of the realignments incorporated 

in the latest version of the proposed gas pipeline alignment. 

2.4.3 Submissions and Proponent Response

Geoff Saffin, who is a landholder along the proposed gas pipeline route, 

raised concerns about the route of the pipeline and in particular why the 

pipeline is not proposed to be constructed in easements for other existing gas 

pipelines.  He noted that previous pipeline easements were of a similar 

width to enable the installation of a second pipe if required and requested 

that the Proponent be required to construct the gas pipeline in the existing 

easement across his property. 

Page 36

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

Mr Napier responded that a separate easement was sought because the 

existing easements could not be used for commercial and technical reasons.  

He advised that the width of easements was in part provided to allow 

duplication of an existing main, in the event that it was required to be 

decommissioned due to technical issues.  He further advised that the route 

chosen had been kept as straight as possible and where feasible was parallel 

and immediately adjacent to other pipeline easements.  Mr Napier spent 

some time explaining the rationale for various deviations from existing 

easements both at the hearing and during the site inspection.  In general 

these were related to avoiding significant flora and fauna and to avoid pinch 

points where the construction of the pipeline would be constrained due to 

other infrastructure.  Ms Hendricks for the DPI confirmed that in Victoria 

most pipelines are in separate easements, apart from adjacent to major gas 

plants. 

Mr Saffin also raised a concern that the gas pipeline alignment can deviate 

within the 500 m wide pipeline corridor.  Mr Napier responded that the 

Proponent has spent considerable time working with landowners and 

specialists to ensure that the current pipe centreline is acceptable, the most 

appropriate and achievable.  He advised that only unforseen circumstances 

would cause it to make minor adjustments to the alignment currently 

proposed.  Further Mr Power highlighted that any modification made to the 

Gas Pipeline alignment between preparation of the EES and when the 

pipeline licence is issued, is at the discretion of the Minister for Energy & 

Resources.  He submitted that: 

‘… the same principles underpinning the assessment of the Gas Pipeline 

in the EES will continue to be applied to any modifications that are made 

to the alignment between now and when the licence is issued. 

The second reason we say there is no concern about such matters is that 

the Pipelines Act 2005 contains a number of environmental ‘checks and 

balances’ to address the environmental impacts of gas pipelines in 

Victoria.  These checks and balances are much more sophisticated than 

what one typically encounters in the planning system.’ 

Ms Hendricks confirmed that the DPI is currently considering Mr Saffin’s 

submission in relation to the pipeline route across his property. 

The Panel noted that a number of submitters discussed the use of HDD for 

constructing the pipeline under sensitive areas, particularly in the case of 

river crossings.  The Panel heard from Ms Hendricks of the DPI that while 

the use of HDD appears an ideal solution in relation to passing under 

sensitive areas it can result in increased environmental issues if the drilling 

results in leakage from the drill hole ‘Frac‐out’.  Ms Hendricks advised that 

Page 37

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

HDD should not be mandated for any site.  It was Ms Hendricks’ submission 

that where technically feasible HDD should be considered, however this 

should only be undertaken following detailed site geotechnical 

investigations.  She further opined that for all sites the Proponent should be 

required to develop an alternative pipe crossing method which could be 

used if frac‐out occurred.  Mr Napier for the Proponent confirmed that for all 

proposed HDD sites an alternative crossing method would be developed 

prior to the commencement of construction.  He further confirmed that HDD 

would only be used where a detailed site investigation indicated its 

feasibility and that any alternative crossing method would be approved by 

the relevant authorities prior to commencing construction. 

2.4.4 Discussion and Conclusions

As described by Mr Napier, the gas pipeline route is, subject to various 

constraints, generally straight in order to provide for the most cost‐efficient 

construction and the final diameter and operating pressure are to be 

optimised by modelling during the detailed design phase. 

The Panel notes that there was only one private submission in relation to the 

approximately 100 km gas pipeline route and that the Proponent referred to 

various negotiated amendments to the proposed route to meet landholder 

requirements.  Apart from the issue of route selection, there were no issues 

raised in relation to the efficiency or affordability of the gas pipeline. 

The Panel noted the concern raised by Mr Saffin about the location of the 

pipeline route through his property and the potential for deviations from the 

current proposed alignment within a broad corridor.  The Panel accepts 

advice from the Proponent and DPI that the alignment adopted through Mr 

Saffin’s property was adjusted to move the pipeline route to the north of his 

property in order to minimise impacts but further changes would have 

consequences for the acceptability of other parts of the route, such as the 

horse property to the west.  It is noted that the route proposed in the EES is 

considered to be close to the final alignment and Ms Hendricks of the DPI 

advised that any deviations from the pipeline alignment presented in the EES 

would require review and approval by the DPI.  The Panel is satisfied that 

any changes to the alignment which arise at the detailed design stage will be 

reviewed by the DPI to ensure that environmental and landholders concerns 

are addressed. 

The Panel is of the opinion that at this stage of the design, the Proponent has 

balanced land owner preferences and the various environmental and 

infrastructure constraints to optimise the route of the pipeline. 

Page 38

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

The Panel is satisfied that the Proponent has identified the most appropriate 

method of crossing each river, etc in the EES and accepts that the use of HDD 

at the sites nominated should only be undertaken following detailed site 

geotechnical investigations.  It is noted that the Proponent has committed to 

preparing alternative crossing method designs to the approval of the relevant 

authorities for all HDD sites and that the alternative crossing method will not 

be undertaken without the approval of the relevant authorities. 

2.5 Compressor Station Design and Site Selection

2.5.1 EES Assessment - Compressor Station Site Selection and Design

Compressor station site selection was informed by the relevant site 

constraints criteria and gas pipeline design requirements.  Hydraulic 

modelling of the proposed gas pipeline nominated 7 km as the maximum 

distance the compressor station should be located from the start of the 

pipeline.  The Port Campbell Creek valley, with its steep side slopes, limited 

potential sites to either: 

adjacent to the Iona and Otway gas plants, which was rejected due to 

landuse constraints; or 

several sites in the vicinity of Smokey Point Road with access being a key 

factor in the selection of the proposed compressor station site. 

2.5.2 Submissions and Proponent Response

The EPA noted the installation of equipment that operates to ‘best practice’ 

standards is required for both greenhouse gas and air emissions i.e. Low NOx 

burners and high efficiency motors.  Mr Napier confirmed that low NOx 

burners and high efficiency motors are to be used at the compressor station.  

Mr Power also noted the EMP requirements under the Pipeline Regulations 

2007 to include systems, practices and procedures to ensure that adverse 

environmental impacts and risks are eliminated or minimised so far as is 

reasonably practicable. 

2.5.3 Discussion and Conclusions

The Panel is satisfied that the Compressor Station site selection process was 

sound.  The site’s location relative to other infrastructure meets a 

fundamental functional requirement and in a sparsely settled rural area, 

reduces the potential for adverse impacts on sensitive residential uses. 

The Panel accepts that the Proponent’s commitments, together with the 

review of the more detailed designs by the EPA as part of the Works 

Approval and Licence to Discharge processes and the DPI, under the 

Page 39

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

Pipelines Act application will ensure that the compressor station will be 

constructed to minimise emissions and to achieve a high level of efficiency. 

2.6 Water Supply Infrastructure

2.6.1 EES Assessment and Evidence– Water Supply Infrastructure Design

Prior to evaluating the potential power station sites in detail, the power 

station Proponent discussed water supply and wastewater disposal options 

with Wannon Water, who advised that: 

the region was supplied with water from the Gellibrand River and the 

Dilwyn Aquifer.  The Gellibrand River supplies the Warrnambool, 

Mortlake, Terang, Camperdown and Derrinallum areas.  The Dilwyn 

Aquifer supplies Port Fairy and Heywood; 

there is capacity to supply potable water to the proposed power station 

from the Camperdown, Warrnambool and Port Fairy water treatment 

plants; 

groundwater resources in the Mortlake area were already allocated; 

an alternative supply using treated wastewater was identified which 

involved the supply of recycled water from the Warrnambool or Port 

Fairy water reclamation plants7 which currently discharges to the ocean; 

and 

wastewater, principally brine concentrate, from the proposed power 

station could be accepted at the Warrnambool water reclamation plant. 

Investigations indicated a pipeline was more efficient than transporting 

water by road to the Power Station, whereas road transport of brine 

concentrate was found to be the more economic option. 

The water pipeline route is relatively straight and is generally constructed in 

easements on private farm land abutting the Hamilton – Port Fairy Road 

reserve to minimise the impact on native vegetation. 

7 The Camperdown water reclamation plant had the capacity to supply the required volume and

quality of water but recycled water was currently allocated for irrigation purposes.

Page 40

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

2.6.2 Submissions

Mr Wilson of Wannon Water advised the Panel that: 

the use of treated waste water from the Port Fairy WWTP would reduce 

the volume of class B treated water discharged to ocean by approximately 

half.  No other potential use was identified due to the salt content; 

the existing ground water supply for Port Fairy has more than adequate 

capacity to supply the utility water required at the Power Station as it was 

equivalent to only 5 houses; and 

should supply from the WWTP be temporarily interrupted, the existing 

water supply bores have adequate capacity to meet both the urban and 

power station requirements for a number of days. 

There were no other submissions in relation to the efficiency of the proposed 

water supply to the Power Station nor the disposal of brine to the 

Warrnambool Water Reclamation Plant. 

2.6.3 Discussion and Conclusions

The Panel is satisfied that the water supply to the Power Station is an 

efficient and environmentally appropriate solution and that the proposed 

route both minimises the distance and potential impacts on valuable flora 

and fauna.  The Panel notes that the volume of brine proposed to be tankered 

to the Warrnambool WRP is less than 0.5% of the volume of waste water 

received and would therefore have negligible impact on the operation of the 

plant. 

Page 41

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

3. Protection of Catchment Values

EES Evaluation Objective: To protect catchment values, including surface water 

quality, stream flow, aquatic health and groundwater values, to the extent 

practicable. 

3.1 Surface Water, Hydrology and Water Quality

3.1.1 Regulatory Framework and Policy Context

The following legislation, policy and guidelines are relevant to the protection 

of surface water environmental values during the construction and operation 

of the project: 

The Water Act 1989 has purposes to allocate, conserve and manage 

surface water and groundwater throughout Victoria.  In the project area, 

Southern Rural Water manages licences for surface water extraction and 

implements regulations and policies under this Act. 

Under the Catchment and Land Protection Act 199 catchment 

management authorities are responsible for the licensing and regulation 

of works on designated waterways and for floodplain and drainage 

management. 

Australian and New Zealand Guidelines for Fresh and Marine Water 

Quality 2000 (ANZECC guidelines) (ANZECC/ARMCANZ, 2000).

Under SPPF Clause 15.01-2, Planning and responsible authorities should ensure proposals minimise nutrient contributions to waterways and 

water bodies consistent with the SEPP (Waters of Victoria), the Victorian 

Nutrient Management Strategy (Government of Victoria 1995) and the 

Urban Stormwater Best Practice Environmental Management Guidelines 

(CSIRO 1999).  Responsible authorities should use appropriate measures 

to restrict sediment discharges from construction sites in accordance with 

EPA Guidelines8. 

Under the Environment Protection Act 1970, the SEPP (Waters of 

Victoria)9 sets a statutory framework for the protection of uses and values 

of Victoria’s fresh and marine water environments.  The policy identifies 

8 Construction Techniques for Sediment Pollution Control (EPA 1991), Environmental Guidelines for

Major Construction Sites (EPA 1996 - Publication 480) and Doing it Right on Subdivisions: Temporary Environment Protection Measures for Subdivision Construction Sites (EPA 2004 - Publication 960)

9 State Environment Protection Policy (Waters of Victoria) No S107 (SEPP (Waters of Victoria)) (Victorian Government, 2003.)

Page 42

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

beneficial uses of watercourses and establishes environmental quality 

objectives to ensure the protection of these uses.  The policy objectives are 

regionally specific and specify levels of nutrients, water quality 

parameters and biological parameters for particular beneficial uses. 

A range of generic policies and guidelines10 relevant to the protection of 

surface water in the project area will apply, in particular during the 

construction phase. 

The beneficial uses listed in the SEPP for the two segments in which Shaw 

River Power Station Project is located are: 

aquatic ecosystems that are slightly to moderately modify; and 

water suitable for: primary and secondary contact recreation, aesthetic 

enjoyment, indigenous and non‐indigenous cultural and spiritual values, 

agriculture (stock watering), irrigation and aquaculture industrial and 

commercial use. 

Human consumption of surface waters (potable water) is not a beneficial use 

for this area unless suitably treated. 

3.1.2 EES Assessment and Evidence - Potential Impacts on Surface Waters

Potential Impacts of Pipeline Construction on Surface Waters 

The EES includes three separate assessments relating to surface water, 

hydrology and water quality undertaken for the project (see Appendices 2, 6 

and 27) which are summarized in EES Chapter 10. 

Project activities, particularly the construction of the pipelines through 

watercourses, have the potential to impact adversely on surface water 

environments due to disruption of stream flow or reduction in water quality. 

The proposed gas pipeline alignment crosses four rivers and many smaller 

streams and channels.  Minor creeks and streams east of the Hopkins River 

tend to be typified by well‐defined, V‐shaped valleys, due to the undulating 

nature of the landscape whereas to the west of the Hopkins River they are 

typically shallow depressions with no distinct channels that collect surface 

runoff from the plains. 

10 For example: Code of Environmental Practice – Onshore Pipelines (APIA, 2009), Draft Strategy

for Coastal Acid Sulphate Soils in Victoria June, 2008 (DSE), Acid Sulphate Soil and Rock Publication Number 655. August, 1999 (EPA Victoria), Industrial Waste Management Policy (Waste Acid Sulphate Soils) No S-125 August 1999 (EPA Victoria), Bunding Guidelines (EPA Publication No. 347) (EPA, 1992), Guidelines for Stabilising Waterways – Standing Committee on Rivers and Catchments (Working Group on Waterway Management, 1991), Technical Guidelines for Waterway Management (DSE 2007c).

Page 43

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

The largest watercourse crossed by the proposed water pipeline alignment is 

Ware Creek, which is a minor creek and intermittent in nature.  The water 

pipelines alignment intersects 16 other smaller ephemeral watercourses and 

one small dam.  Frequent localised flooding occurs during winter, 

particularly in lower areas in the southern portion of the water pipelines 

alignment. 

The EES notes that there is the possibility of acid sulphate soils in the Curdies 

River area, and indicates that if found, these will be managed in accordance 

with EPA and DSE requirements. 

The EES outlines two methods proposed for crossing watercourses during 

pipeline construction: 

Open cut methods which involve excavating a trench through the 

watercourse, laying the pipeline and then backfilling the trench.  If the 

watercourse is flowing at the time of construction, partial or complete 

diversion is required.  Open cut methods typically result in hydrological 

and water quality impacts, as well as in‐stream habitat and bank stability 

impacts, when it is undertaken in flowing water.  It is the preferred 

technique for crossing ephemeral watercourses, where construction can 

occur during low or no‐flow periods.; and 

Horizontal directional drilling (HDD) which involves drilling a hole at a 

shallow angle under the watercourse with a specialised drilling rig.  The 

pipeline is then pulled through the hole.  HDD avoids disruption of 

surface water flow but presents other risks, including HDD failure (e.g., 

collapse of the borehole due to geological conditions), with subsequent 

water quality impacts, such as streambed collapse.  HDD also requires a 

large area for the drill entry and exit pads and is a moderately water‐

intensive activity.  HDD is generally the preferred crossing technique for 

perennial watercourses and watercourses with sensitive environments. 

The Proponent indicated that the final crossing technique will be determined 

during the detailed design phase, following consideration of a number of 

site‐specific factors, including safety, risk, hydrology, stream substrate and 

geology, environmental sensitivities and engineering feasibility, as well as 

consultation with the catchment management authorities. 

Without appropriate controls, hydrological impacts and increased 

sedimentation or water quality impacts could occur during construction of 

the Power Station and pipelines watercourse crossings.  A Strategic EMP, 

together with generic mitigation and management measures have been 

proposed.  These will form the basis of more specific measures for each 

watercourse crossing to be incorporated in Construction EMPs.  It is also 

proposed that the Construction EMPs will include contingency measures to 

Page 44

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

enhance erosion and sediment controls, or halt works in sensitive 

environments, when heavy rainfall or natural flood events are forecast. 

Potential Impacts on Surface Waters – Power Station and Environs 

The proposed power station site is within the Shaw River catchment, a 

relatively small catchment with an area of 117 km2.  The Shaw River is a 

narrow, ephemeral waterway that has a mixture of substrate types and a 

diversity of isolated pools along its length during summer.  Threatened 

aquatic species historically found in the Shaw River include the nationally 

listed Yarra Pygmy Perch and Dwarf Galaxias (see Chapter 4.3). 

Drainage at the Power Station site does not follow defined drainage lines; 

rather, the gently sloping land drains south and southwest towards an 

ephemeral tributary of the Shaw River.  Wetlands are present in low‐lying 

areas on the site. 

Flood modelling showed that the Power Station site will not experience any 

inundation in the 100‐year flood event, the 500‐year flood event, or the 

probable maximum flood event. 

According to the EES there will be no discharge of process waters to the 

environment.  The power plant wastewater system will treat wastewater 

from the power plant water system so that it can be reused in the power 

plant.  This system will include a water neutralisation plant and two 

independent reverse osmosis plants (desalination plants). 

Stormwater management will direct all potentially contaminated water to 

storage tanks via triple interceptor traps to remove oily substances.  Triple 

interceptor traps will be located adjacent to the power block and at the 

switchyard.  After passing through the triple interceptor traps, stormwater 

will be directed to a sedimentation pond where suspended sediment will be 

allowed to settle out before the water overflows to the ephemeral wetlands 

located on the site.  Several design options, capable of managing runoff 

under a range of storm events are being considered for the sedimentation 

ponds.  The final design specification will be determined in consultation with 

the relevant authorities.  The stormwater management system will be 

constructed early in the construction program to provide management of 

stormwater runoff from the site as soon as practicable. 

Rain falling on building roofs will be collected and stored in tanks for use in 

dust suppression, landscaping, toilet flushing and potentially, as part of the 

power plant water system. 

Page 45

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

Cut‐off drains will divert stormwater runoff from land uphill of the Power 

Station and switchyard away from the benches to the existing watercourses 

and drainage lines that discharge to the ephemeral wetlands.  Landscaping 

will be undertaken to enhance the wetlands’ ecosystem function and their 

capacity to filter stormwater before discharge to a tributary of the Shaw 

River. 

The EES indicates that any discharge of stormwater will not cause a 

reduction in the water quality of Shaw River, and will be of a quality that 

will meet the SEPP (Waters of Victoria) objectives.  Stormwater discharge 

from the sedimentation ponds will be sampled and tested at regular intervals 

to ensure compliance with the SEPP. 

The EES (Appendix 6) indicates that the impact of the discharge from Shaw 

River depends on the volume, quality and the timing of the discharge.  It 

outlines a number of measures that are recommended for the protection of 

the aquatic values that are present at Shaw River.  It also identifies the need 

to develop a detailed EMP to outline measures to ensure ecological values of 

Shaw River are protected during construction activities; and best practice 

sedimentation and pollution control measures to the satisfaction of EPA are 

undertaken at all times. 

3.1.3 Submissions and Proponent Responses

The Corangamite Shire submission sought the following measures to address 

the impacts on surface waters and aquatic vegetation of the gas pipeline 

construction activities: 

a wet weather ‘stop work’ rule for watercourse crossings and work 

adjacent to watercourse crossings; 

under boring all watercourses with HDD (and specifically for the Curdies 

River, Spring Creek and Whiskey Creek, Port Campbell Creek and 

Wallaby Creek crossings).  The crossing location should be chosen to 

ensure this is possible; 

spill and hazardous materials management procedures for the gas 

pipeline, not just the Power Station; and 

proper management of acid sulphate soils at the Curdies River. 

The DPI and DSE both raised concerns over the potential use of HDD.  While 

they acknowledged the environmental benefits of successful HDD, they 

pointed out that HDD can be quite risky and the failure rate is around 50%.  

The environmental consequences of failure – or frac out – can be significant, 

including smothering of riparian and or/roadside native vegetation and 

stream turbidity and sedimentation from spilled drill fluids.  They stressed 

that HDD should not be relied upon and contingency plans should be in 

Page 46

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

place in the event that HDD proves unsuccessful at locations where it is 

used. 

In response, the Proponent and Mr Napier’s evidence indicated that: 

a ‘stop work’ rule for watercourse crossing construction activities or 

construction activities adjacent to watercourses is not practical and could 

leave partially completed works exposed to rising water levels which 

may increase the risk of sedimentation, rather than avoiding or reducing 

such impacts; 

it agrees with DPI and DSE on the use of HDD to cross environmentally 

sensitive areas.  The criteria to be used in assessing the most appropriate 

crossing method are detailed in Table 8.1 of the EES which reflect the 

considerations nominated by DPI.  Several factors determine the choice of 

watercourse crossing method.  In some circumstances, under boring or 

HDD may pose a greater risk to the environmental values of the 

watercourse, particularly in the situation where a ‘frac out’ occurs (or has 

the potential to occur) as a consequence of unsuitable geotechnical 

conditions; 

in most instances it is not possible to move watercourse crossings to 

locations favourable for under boring or HDD, as the key considerations 

of geological formations and geotechnical conditions are often expansive; 

HDD of the Curdies River, Spring Creek and Whiskey Creek crossings 

has been nominated as the preferred crossing method but the ultimate 

crossing method will be determined following the pipeline design and 

construction risk assessment (in accordance with AS 2885.1‐2007 Pipelines 

– Gas And Liquid Petroleum – Design And Construction) and detailed 

design, having regard to the criteria set out in EES Table 8.1; 

the EES did not identify any environmentally sensitive issues that would 

support HDD of Port Campbell and Wallaby Creeks.  Open‐cut trenching 

has been successfully used for previous pipeline crossings of Port 

Campbell Creek and those crossings have been successfully reinstated 

and rehabilitated; 

the Proponent has committed to the preparation of site specific 

management plans for significant watercourse crossings which could be 

expanded to include contingency plans.  The EES impact assessment of all 

watercourse crossings considered a worst‐case scenario, including the 

potential extent of native vegetation removal; 

the Strategic EMP prepared for all construction and operation activities 

(EES Attachment 5) for the Power Station, gas pipeline and water 

pipelines includes controls for the management of spills and hazardous 

materials.  Detailed Construction EMPs will need to be developed and 

Page 47

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

implemented in line with the requirements and objectives of the Strategic 

EMP; and 

acid sulphate soils found at the Curdies River will be managed in 

accordance with the requirements of the following policies and guidelines 

included as Attachment 5 to the EES: 

- Draft strategy for coastal acid sulphate soils in Victoria, June 

2008 (DSE) (This incorporates the Draft Best Practice Guidelines 

for Assessment and Management of Acid Sulfate Soils in 

Victoria). 

- Acid Sulphate Soil and Rock Publication Number 655 (EPA 

1999). 

- Industrial Waste Management Policy (Waste Acid Sulphate Soils) 

No S‐125 August, 1999 (EPA Victoria). 

DSE commented on the uncertainty about changes to the hydrology of Shaw 

River and consequential impacts to aquatic ecosystems.  Species of particular 

concern are the Dwarf Galaxis and the Yarra Pigmy Perch.  In general DSE is 

satisfied that the majority of impacts should be able to be confined to the 

construction phase, however monitoring and adaptive management is 

required for the operational phase.

Following discussions between the Proponent and DSE it has been agreed 

(see Appendix D) that the Proponent will consider design responses to limit 

potential impacts including: 

zero discharges, with stormwater either stored or being directed to other 

parts of the property for irrigating pasture, crops, screening plantations 

and maintenance and enhancement of the Power Station site ephemeral 

wetlands; 

designing a discharge regime and regulating discharges to ensure there is 

no significant adverse impact; and 

installation of water saving devices and implementation of processes to 

enhance recycling to reduce discharge volumes. 

Further, DSE and the Proponent agree that residual risk will be assessed at 

the final design and approvals stage and this will inform the detailed scope 

of a monitoring program generally along the lines below: 

a pre‐ and post‐construction monitoring program should detect any 

significant effects on aquatic ecology, particularly the Yarra Pygmy Perch 

and Dwarf Galaxias resulting from changed hydrology in the Shaw River; 

monitoring will be undertaken at two sites: one just upstream and the 

other downstream from the point of discharge into Shaw River; and 

Page 48

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

monitoring will commence pre‐construction and continue for a minimum 

period of two years post‐construction, at which time it will be reviewed to 

determine whether further monitoring is warranted.  If construction is 

undertaken in stages, the two years post‐construction monitoring may be 

required at completion of each stage, and will be informed by the results 

of the preceding monitoring program. 

3.1.4 Discussion and Conclusions

Without appropriate controls, hydrological impacts and increased 

sedimentation or water quality impacts could occur during construction of 

the Power Station and pipelines watercourse crossings. 

While successfully implemented HDD can significantly reduce 

environmental impacts, it can be risky and the environmental consequences 

of failure – or frac out – can be significant.  The Panel endorses the consensus 

view at the hearing that HDD may not be feasible in all the locations and, 

where it is identified as the preferred method, contingency plans should be 

in place in the event HDD proves unsuccessful. 

Specific measures for each watercourse crossing should be incorporated in 

Construction EMPs. 

The Panel notes that acid sulphate soils are likely to be found at the Curdies 

River.  They should be managed in accordance with the requirements of the 

EPA and DSE policies and guidelines. 

Water quality in Shaw River may be impacted during construction of the 

Power Station and the proposed upgrading of Riordans Road, and during 

the operation of the Power Station.  However, the design of the stormwater 

management system for the Power Station site should implement best 

practice sedimentation and pollution control measures to the satisfaction of 

EPA.  The Panel is satisfied that impacts can be limited through careful 

design to maintain the current to volume of water discharged to Shaw River. 

Recommendations 

Incorporate specific control measures for each watercourse crossing in 

Construction EMPs. 

Manage acid sulphate soils found at the Curdies River in accordance with 

the requirements of the EPA and DSE policies and guidelines. 

Design the stormwater management system for the Power Station site to 

implement best practice sedimentation and pollution control measures to 

Page 49

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

the satisfaction of EPA, and limit impacts to maintain the current discharge 

volume hydrology to Shaw River. 

Require a monitoring program to assess the impact of water discharged 

from the Power Station site to be undertaken broadly in line with that 

outlined in Appendix D. 

3.2 Groundwater

3.2.1 Regulatory Framework and Policy Context

DSE manages Victorian groundwater resources in accordance with the Water 

Act 1989.  The DSE delegates responsibility for groundwater licensing and 

administration in south western Victoria to the Southern Rural Water 

Authority. 

The EPA manages groundwater quality in accordance with the Environment 

Protection Act 1970 and the SEPP (Groundwaters of Victoria)11 which aims to 

maintain and, where necessary, improve groundwater quality to protect 

existing and potential future uses of groundwaters.  The policy classifies 

groundwater into five ‘segments’ based on the background concentration of 

total dissolved solids (TDS) – which are predominantly salts – and defines 

the beneficial uses in each segment that require protection. 

In addition to the SEPP (Groundwaters of Victoria), EPA guidelines for 

sediment pollution control and management of construction sites referred to 

in 3.1.1 are also relevant to the protection of groundwater during 

construction activities. 

3.2.2 EES Assessment and Evidence – Groundwater

The EES (Chapter 10 and Appendix 3) provides information on the 

characteristics of the groundwater environment in the project area. 

There are 325 DSE‐registered groundwater bores within 1 km of the 

proposed gas pipeline alignment and power station site, including 17 state 

observation bores and 14 registered irrigation bores.  Most of the bores are 

private bores used for stock and domestic purposes and are installed in the 

Newer Volcanic basalts.  The deeper bores (for irrigation purposes) generally 

source groundwater from the Port Campbell Limestone. 

11 State Environment Protection Policy (SEPP) (Groundwaters of Victoria) No S95 (Victorian

Government, 1997a).

Page 50

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

There are 27 private bores within 500 m of the water pipelines alignment.  

Bores range in depth from 6 to 55 m, with most bores greater than 30 m 

depth. 

Groundwater in deeper formations is used extensively for municipal supply 

throughout the Otway Basin.  For example, supplies for Koroit and 

Warrnambool are sourced from the Port Campbell Limestone, and supply for 

Port Fairy is sourced from the Dilwyn Aquifer. 

The EES noted the following aspects of the project that could reduce the 

levels, supply or quality of groundwater: 

the depth to groundwater along the gas pipeline alignment is expected to 

typically exceed the maximum depth of excavation but short‐term and 

local disturbance of groundwater is likely to occur during construction, 

particularly toward the western end of the alignment in the Stony Rises 

where shallow groundwater may be encountered; 

since widespread and long‐term dewatering will not be required, the 

potential for groundwater impacts during the construction phase is 

minimised.  The implementation of monitoring and management 

techniques should ameliorate impacts associated with any shallow 

dewatering that may be necessary; 

groundwater impacts during the operational phase are also reduced as no 

groundwater extraction for water supply purposes is proposed; 

the implementation of management measures will reduce the likelihood 

that springs, wetlands and other groundwater‐discharge related features 

near the Power Station or gas pipeline will be affected.  In addition, any 

potential impacts are likely to be of small scale and short duration; and 

overall, the project is considered to pose a low risk to groundwater levels, 

quality or existing/future users. 

3.2.3 Submissions

There were no submissions received related to groundwater issues. 

3.2.4 Discussion and Conclusions

The absence of submissions on this issue is taken to represent acceptance 

from relevant agencies of the rigour of the analysis and support for the 

management regimes proposed. 

The Panel notes that the Strategic EMP outlines comprehensive avoidance, 

mitigation and management measure to be implemented during construction 

works to protect groundwater resources. 

Page 51

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

The Panel accepts the information and analysis provided in the EES and 

considers that: 

the project will not pose any significant long‐term risk to groundwater 

supply or quality; and 

while it is likely that there may be local and short‐term disturbance 

during construction activities, the implementation of monitoring and 

management techniques specified in respective Construction EMPs can 

ameliorate such impacts. 

Page 52

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

4. Biodiversity

EES Evaluation Objective: To avoid or minimise effects on species and 

communities listed under the Flora and Fauna Guarantee Act 1988 to the extent 

practicable, to avoid or minimise effects on other native species and communities, 

and to comply with net gain requirements for biodiversity outcomes. 

4.1 Regulatory Framework and Policy Context

4.1.1 Commonwealth Legislation - Environment Protection and Biodiversity Conservation Act 1999

The Commonwealth EPBC Act provides for the protection of listed 

threatened species and communities and migratory species of national and 

international environmental significance.  Three referrals under the EPBC 

Act were submitted to the Department of the Environment, Water, Heritage 

and the Arts (DEWHA) relating to Shaw River Power station, the gas 

pipeline and the water pipelines.  The Power Station has been assessed as 

‘not a controlled action’ and will not require any further assessment. 

The gas pipeline and water pipelines have both been assessed as ‘not a 

controlled action if undertaken in a particular manner’.  The Referral Decisions 

specify measures to be undertaken to avoid significant impacts on listed 

threatened terrestrial species, including Southern Brown Bandicoot (known 

to occur in the project area) and Long‐nosed Potoroo and communities along 

the gas pipeline route.  Measures include controls for erosion, pollutant spill 

and chemical storage and specific controls in identified key habitat areas, 

including restrictions to construction corridor width, salvage and relocation 

of species and restoration of disturbed habitat. 

The Referral Decisions specify measures to be undertaken to avoid 

significant impacts on listed aquatic species and communities.  They include: 

specific controls for sedimentation, erosion, pollutant spill and chemical 

storage; and specific controls in identified key habitat areas where open cut 

trench works are proposed, including restrictions to construction corridor 

width, salvage and relocation of species, avoidance of breeding seasons and 

restoration of disturbed habitat. 

Measures along the water pipeline routes include specific controls such as 

thrust boring or HDD to be used to lay the pipeline underneath the two 

patches of Natural Temperate Grassland of the Victorian Volcanic Plain that 

Page 53

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

are intersected by the pipeline alignment.  Contingency measures are also 

specified where there is a failure of boring techniques. 

For the water pipelines, the Referral Decision further notes that in the event 

of trenching being used for the Ware Creek crossing, additional targeted 

surveys of listed aquatic species will be required and if found, construction 

activities must not be undertaken during the breeding seasons for these 

species. 

Construction of the gas and water pipelines must be undertaken in 

accordance with the requirements specified in the decision notices. 

4.1.2 State Legislation and Policy

Relevant State legislation and planning policy applying to the protection of 

biodiversity is as follows: 

The Flora and Fauna Guarantee Act 1988 (FFG Act) establishes 

procedures for the conservation, management or control of flora and 

fauna and the management of potentially threatening processes.  DSE 

administers the FFG Act, including ‘Permits to take protected flora’ and 

‘Permit to conduct activities relating to protected fish’. 

Victoria’s Biodiversity Strategy (1997) complements the National 

Strategy and the FFG Act.  It provides the overarching direction for 

biodiversity conservation and management in Victoria. 

Planning schemes require: 

Planning decisions to have regard to The Victorian Government 

Native Vegetation Management Framework: A Framework for 

Action 2002 (the Framework) (SPPF Clause 15.09).  The Framework 

aims to achieve a reversal of the long‐term decline in the extent and 

quality of native vegetation ‐ this reversal is commonly referred to 

as ‘net gain’.  It adopts the principles of  firstly avoiding the removal 

of native vegetation, if removal cannot be avoided then planning 

and design should minimise the loss of native vegetation and, where 

native vegetation must be removed, offsets should be provided to 

ensure a net gain outcome (as defined in the Framework).  Other 

regulatory agencies often draw on DSE expertise in relation to 

biodiversity issues and the implementation of the Framework.  In 

some cases the arrangement is formalised, such as approval of 

extractive industry proposals where a memorandum of 

understanding between DPI and DSE has been established relating 

to decisions affecting native vegetation losses. 

A permit under Clause 52.17 to remove, destroy or lop native 

vegetation, unless specified exemptions apply.  DSE is designated as 

Page 54

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

a referral authority for specified types of applications involving the 

loss of native vegetation and is often consulted on other 

applications.  However, a planning permit to remove native 

vegetation is not required for a pipeline developed under the 

Pipelines Act 2005.  Amendment C36 proposes to exempt other 

elements of the project from requirements to obtain a permit to 

remove native vegetation, although DPI advise they will require a 

native vegetation removal and offset plan to be prepared to the 

satisfaction of DSE. 

The Wildlife Act 1975 requires permits for the collection and 

translocation of protected fauna.  DSE administers this Act, in particular 

granting ‘Wildlife Management Authorisations’. 

The Pipelines Act 2005 regulates all works associated with the gas 

pipeline and substitutes for processes in planning schemes.  This Act is 

administered by DPI, which adopts the practice of obtaining advice from 

DSE regarding biodiversity‐related components during the development 

of the Construction EMP under the Act and during auditing  of plan 

implementation. 

The Water Act 1989 requires permits for works on designated waterways 

and such works may impact on biodiversity.  Catchment Management 

Authorities are responsible for issuing permits and DSE regularly 

provides advice on biodiversity issues. 

The Catchment and Land Protection Act 1994 controls noxious weeds 

and pest animals.  DPI is responsible for these biosecurity matters under 

the Act which will be addressed through EMPs for the project. 

Although without legislated protection, species listed under Advisory Lists 

of Rare and Threatened Plants, DSE 2005 and Vertebrate Fauna, DSE 2007 

and species listed in A Census of the Vascular Plants of Victoria, Walsh & Stajsic 

2007 have also been considered in the assessments. 

Page 55

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

4.2 Terrestrial Ecology

4.2.1 EES Assessment and Evidence - Terrestrial Ecology

Methodology for Terrestrial Ecology Assessments 

Ecology Partners undertook Flora and Fauna Surveys and Preliminary Net 

Gain Assessments for the power station and gas and water pipelines (EES 

Appendices 4, 5, 29, 30).  Study methods for the terrestrial flora and fauna 

assessment included desk top analysis and field surveys.  Surveys of the gas 

pipeline and immediate surrounds were conducted over 27 days between 

November 2008 and September 2009.  Surveys were carried out for the water 

pipelines over six days during December 2008 and January 2009. 

Surveys were undertaken at a time when the detection of most flora and 

fauna species is relatively high, and combined with the highly modified 

environment the majority of the study area is located in, the methodology is 

considered sound. 

Survey Results 

The project area crosses two bioregions.  The Victorian Volcanic Plain (VVP) 

Bioregion lies inland from the coast and is characterised by open areas of 

grassland, small patches of open woodland, stony rises (old lava flows), 

extinct volcanoes and numerous small lakes.  The Warrnambool Plain (WP) 

Bioregion is located along the coast and is characterised by more patches of 

remnant vegetation, an undulating landscape and incised river valleys and 

coastal cliffs. 

The Power Station site and much of the surrounding landscape have been 

cleared for agriculture.  Native vegetation is mostly confined to road and rail 

reserves, watercourses, isolated pockets and stands of scattered trees. 

Native flora and fauna communities and species, listed under the EPBC Act 

that were recorded in the project area include: 

two ecological communities: Natural Temperate Grassland of the 

Victorian Volcanic Plain and Grassy Eucalypt Woodland of the Victorian 

Volcanic Plain; 

two plant species: Curly Sedge and Swamp Greenhood; and 

two terrestrial animal species: Southern Bent‐wing Bat and Long‐nosed 

Potoroo. 

The surveys provided a detailed comparison of desk top and field survey 

results.  Flora and fauna were described across levels of national, regional 

Page 56

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

and local significance.  Detailed results of flora and fauna surveys can be 

found in EES Appendices, for the Power Station site and gas pipeline 

(Appendix 4) and the water pipelines (Appendix 30). 

No other sites or areas of wilderness, scientific or other special conservation 

significance were identified. 

EES Assessment of Impacts and Mitigation 

Potential project impacts on terrestrial ecology (including communities and 

species of conservation significance) are summarised in the EES Chapter 10.5.  

The Strategic EMP (EES Attachment 5) provides an integrated risk 

assessment of residual risks (Chapter 1) and a comprehensive set of 

management guidelines (Chapter 4) that will assist with the management of 

impacts and implementation of mitigation measures which will be included 

in the Construction and Operations EMPs for the gas and water pipelines. 

As already noted, the Referral Decisions under the EPBC Act oblige the 

implementation of specified measures to avoid significant impacts on listed 

threatened species. 

Clearing of native vegetation is not proposed for any of the areas on the 

Power Station site.  The operation of the Power Station will increase noise 

and light in the local landscape.  These disturbances are at the immediate 

local scale and may change how some species, such as the Southern Bent‐

wing Bat use the area, despite the absence of preferred habitat on the 

proposed power station site. 

Appropriate plans, such as salvage and/or management plans, are proposed 

to be prepared for significant species (including the Curly Sedge, Large‐

flower Cranesbill, Basalt Leek‐orchid, Swamp Flax‐lily, Swamp Skink and 

Long‐nosed Potoroo), in the detailed Construction EMPs. 

The gas and water pipeline alignments were selected to avoid or minimise 

impacts on significant areas of vegetation (including grasslands and remnant 

mature trees) and associated fauna habitat.  The alignments primarily 

intersect cleared country (98%).Where significant areas could not be avoided, 

construction methods have been varied to reduce impacts, including 

reducing the width of the construction right of way and in special cases, 

proposing the use of HDD or boring where road and/or river crossings are 

proposed.  The use of these techniques will be determined following detailed 

geotechnical surveys for specific sites. 

Page 57

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

Preliminary Net Gain Assessments 

Earlier flora and fauna surveys and mapping of the overall study area 

indicate there are approximately 62.71 hectares (ha) of native vegetation in 

the gas pipelines study area12.  Clearing of native vegetation for the gas 

pipeline and power station is predicted to total 3.43 ha.  This includes 

approximately 1.03 ‘habitat hectares’ which is a combined quality‐quantity 

measuring system under the NVMF, consisting of 0.17 habitat hectares from 

the WP Bioregion and 0.86 habitat hectares from the VVP Bioregion of 

medium, high and very high conservation significance.  The resulting net 

gain target for this vegetation is 1.83 habitat hectares, comprising 0.27 habitat 

hectares from the WP Bioregion and 1.56 habitat hectares from the VVP 

Bioregion. 

There are approximately 37.7 ha of native vegetation in the water pipelines 

study area.  Construction of the water pipelines will require clearing of 2.29 

ha, comprising 0.55 habitat hectares of high conservation significance 

vegetation from the VVP Bioregion.  This equates to a net gain target for the 

water pipeline of 0.84 habitat hectares. 

There are also areas of less significant vegetation dominated by Austral 

Bracken and classified as Degraded Treeless Vegetation along the gas and 

water pipelines routes proposed to be cleared.  Removal of this vegetation 

will require an equivalent offset of this or any similar native vegetation, due 

to their floristic and habitat values.  Clearing is also proposed for a range of 

scattered trees and shrubs.  Net gain assessments have been calculated for 

these losses. 

Preliminary net gain assessments13 will be finalised once the final pipeline 

routes are agreed and the road and river crossing methods determined.  It is 

also proposed to audit the final offset requirements post construction. 

12 Comprising: 15.39 ha from the WP Bioregion and 47.32 ha from the VVP Bioregion,

approximately 20.09 ha of Austral Bracken (2.17 ha from the WP Bioregion and 17.92 ha from the VVP Bioregion) and 13.88 ha of ‘Degraded Treeless Vegetation’ (all from the VVP Bioregion).

13 Full details of net gain assessments, including conservation significance and impacts on individual Ecological Vegetation Classes (EVCs) for each bioregion for the gas and water pipeline alignments are contained in the EES Appendices 5 and 30, respectively.

Page 58

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

4.2.2 Submissions and Proponent Response

Pipeline Rehabilitation 

Landowner Geoff Saffin’s submission indicated concerns over potential 

problems with land restoration in the gas pipeline easement, given his 

previous experience of installation of the SEA Gas pipeline on his property.  

The Shire of Corangamite’s submission requested that a ‘Re‐instatement of 

Land Inspection and Repair Service’ be carried out for 12 months from 

completion of the pipeline. 

The Shire of Corangamite also noted that rehabilitation to full recovery 

would be highly important for the Curdies River, Spring Creek and Whiskey 

Creek.  The Shire requested that areas rehabilitated with native vegetation be 

maintained for a minimum of 2 years. 

Mr Napier responded to these issues, presenting details of the proposed 

rehabilitation of the pipeline construction right of way at the Panel hearing, 

including the respective processes for reinstatement, revegetation and re‐

establishment of previous land use.  Mr Napier highlighted that: 

The Strategic EMP (Attachment 5 to the EES) states that rehabilitation 

will be monitored at three monthly intervals for the first year and 

annually for up to two years, including following major storm events or 

prolonged periods of heavy rainfall.  The Strategic EMP requires Shaw 

River Power to remediate any unsuccessful rehabilitation. 

DPI advised at the hearing that requirements for rehabilitation are covered 

under the Pipelines Act, including rehabilitation commitments, rehabilitation 

plan, compliance with standards and rehabilitation bond.  The Panel was 

informed that there was not a statutory period for monitoring rehabilitation 

but a rehabilitation period could be specified under the Construction EMP.  

In addition, should there be complaints, the Proponent will be required to 

undertake further rehabilitation works as required. 

Native Vegetation Impacts and ‘Net Gain’  

The Shire of Corangamite raised a general concern in relation to potential 

impacts of large scale infrastructure projects on flora and fauna and the 

importance of construction management.  The Shire indicated a preference to 

offset native vegetation within the municipality. 

Mr Power responded that Mr Organ’s evidence had comprehensively 

addressed the submissions made on flora and fauna and in particular that 

Page 59

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

construction management would be adequately addressed.  He submitted 

that: 

The majority of the concerns raised in the submissions can and should be 

addressed in the EMPs.  Notably, EMPs for the Gas Pipeline must be 

approved by the DPI and DSE under the Pipelines Act and we submit 

that this is the most effective way of ensuring that the specific 

environmental issues along the various areas of each pipeline route are 

managed. 

Shire of Corangamite requested that HDD be used at roadside crossings, 

including Warre Road, Smoky Point Road, North‐South Road, Timboon‐

Peterborough Road, Boundary Road and Timboon‐Curdievale Road, in order 

to avoid native vegetation removal.  The use of HDD techniques, as 

discussed previously, will require further geotechnical investigation in order 

to determine feasibility. 

DSE advised it is satisfied that the Framework’s three step approach has been 

applied in the EES assessment and the preliminary net gain assessments. 

However, DSE questioned the approach to determining tree clearance 

distances from construction for old trees, suggesting that the methodology in 

the ‘Australian Standard for the Protection of Trees on Development Sites 2009’ 

should apply.  Mr Organ noted that this is a new standard and the distance is 

greater than applied in the assessment to date.  It was noted that this new 

standard would result in assumptions that further trees would be lost  and 

the offset calculations would require updating.  He advocated verifying 

actual losses after construction. 

DSE anticipated that the main outstanding challenge for the project with 

regard to native vegetation would be locating offsets for very high 

conservation significance vegetation that meet the like for like requirements 

of the Framework.  The Proponent confirmed that the task of identifying 

appropriate offsets is proving difficult but indicated that the process is being 

undertaken in close consultation with DSE, with regard to determining the 

nature, location and extent of offsets prior to seeking formal approval.  Mr 

Organ informed the Panel that a range of offsets may be available through 

the Trust for Nature and Bush Broker programs and that these were being 

actively investigated, as well as other potential options for the purchase of 

private land with appropriate  native vegetation. 

The ecological benefits of finding like for like offsets in small fragmented 

areas across a range of EVCs were questioned.  DSE and Mr Organ concurred 

that it may be more ecologically beneficial to find one and/or a small number 

of larger consolidated offset areas across a smaller range of EVCs.  However, 

Page 60

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

DSE emphasised the scarcity of very high conservation significance native 

vegetation and highlighted the importance of achieving offsets that satisfy 

the like for like requirements for this native vegetation.  DSE indicated that 

Ministerial approval will be necessary for the losses of very high 

conservation significance vegetation and the Proponent will be required to 

demonstrate that appropriate offsets can be provided. 

The Panel queried which mitigation measures recommended by Ecology 

Partners were not fully or only partially adopted by the Proponent.  Mr 

Napier presented a detailed written response, outlining the reasons against 

each of the recommended mitigation measures.  In summary, the range of 

mitigation measures not adopted related to certain monitoring requirements 

no longer required because impacts were designed out or mitigated through 

other means; specific boring techniques requiring geotechnical investigation; 

pre‐clearance surveys for aquatic weed species not being required due to 

proposed mitigations for the construction phase; and there being no need for 

a management plan for the burrowing crayfish as it had not been detected (It 

was noted that such a plan would be prepared if the species is identified in 

pre‐construction clearance surveys for other threatened species). 

Partially adopted recommendations included development of a generic 

stormwater plan for gas and water pipelines construction rather than site 

specific stormwater management plans; monitoring and mitigation measures 

of discharges from the Power Station site to be determined in consultation 

with authorities if impacts on threatened fish species are detected (it is noted 

that a preliminary monitoring program has now been prepared (see 

Appendix D)); and the appropriate route alignment at Gapes Road to be 

determined as part of detailed design, in order to minimise native vegetation 

impacts. 

DPI and the Shire of Corangamite raised issues in relation to weed and 

pathogen hygiene.  Mr Napier noted that the Strategic EMP includes 

objectives and high level procedures for the control of weeds and plant and 

animal pathogens.  The Construction and Operations EMPs will adopt the 

Strategic EMP requirements and include more detailed procedures for the 

management of weeds and pathogens. 

Impacts on Fauna 

DSE was satisfied that most impacts on fauna can be confined to short‐term 

impacts during the construction phase through implementation of 

appropriate mitigation measures.  However, DSE raised a concern about the 

potential impact of the Power Station on the Southern Bent‐wing Bat which is 

listed as Critically Endangered under the EPBC Act and listed as ‘threatened’ 

Page 61

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

under the FFG Act.  DSE advised that little is known about the flight paths 

and migratory patterns for the species but noted in its submission that: 

The proposal is at the outer limits of the nightly foraging areas, but lies 

in between a number of known caves.  The project is unlikely to have a 

significant adverse effect on this species.  However, it is important that 

post construction monitoring and adaptive management processes are in 

place to detect and manage any impacts that do occur. 

DSE queried whether there would be hazards such as flares or heat from the 

exhaust stacks that may pose a threat to the Southern Bent‐wing Bat.  The 

EES notes that the process of flaring is to be avoided (EES Ch. 10, p.127).  Mr 

Ormerod advised that the heat of the plumes from the open and closed cycle 

gas turbines would be 90 and 500 degrees respectively at the exit points into 

the atmosphere and this would be followed by a rapid process of 

temperature reduction.  Mr Organ considered that the operation of the 

Power Station would pose minimal risks to bats and other avifauna.  Mr 

Organ also stated that the artificial lighting to be installed on the site would 

not be unique to the area and would be unlikely to cause adverse impacts on 

bats.  Mr Organ further noted that harvesting of blue gum forests was likely 

to result in loss of the bat’s foraging habitat.  Mr Power highlighted that the 

Power Station had been referred under the EPBC Act and that the 

Commonwealth determined it was not a controlled action and did not 

specify any management requirements relating to bats.  He submitted that: 

‘any conditions related to post‐construction monitoring on site 

utilisation and mortality for key species of bats such as the Southern 

Bent‐wing Bat (as suggested by DSE) is unnecessary and if imposed 

would be a disproportionate and onerous condition on Shaw River 

Power.’ 

The Panel sought further advice about the nature of bat monitoring and 

adaptive management measures envisaged by DSE.  DSE prepared a 

preliminary monitoring program in consultation with the Proponent, a copy 

of which is provided in Appendix D to this report. 

Local resident, Ms Nicholls’ submitted  that the EES does not adequately 

address the effect of the project on Brolga nestling sites on properties along 

Riordans Road. 

The EES Flora and Fauna Survey report (EES Appendix 4) noted that 

significant fauna species such as the Brolga are known to occur in the local 

area of the Power Station site.  The report also noted that although the 

proposed power station and associated infrastructure are unlikely to directly 

impact this species, there is the potential for indirect impacts such as 

disturbance from lighting and noise.  However, DSE’s assessment of 

Page 62

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

submissions and presentation of evidence did not identify any fauna, other 

than the Southern Bent‐wing Bat that should be monitored on the Power 

Station site.  Further, DSE’s submission did not identify any outstanding 

issues in relation to the local Brolga population. 

Cumulative Impacts 

The Shire of Corangamite identified the importance of protecting refuges and 

habitats due to losses of original grassland ecosystems across the region 

which is elevated due to cumulative impacts of development. 

DSE asked the Panel to note the general growth of major infrastructure 

projects in the south west of Victoria and to comment on how the issue of 

cumulative impacts should be considered regionally.  It was noted whilst 

project specific impacts may be manageable, there is a cumulative habitat 

loss from successive projects.  DSE advised that a regional assessment of 

cumulative effects on flora and fauna communities and the identification of 

strategic provision of consolidated offsets has not been undertaken. 

4.2.3 Discussion and Conclusions

It is the Panel’s view that the EES has comprehensively addressed the EES 

objectives in relation to terrestrial flora and fauna impacts and mitigation.  

The Panel is satisfied with the Proponent’s overall approach to the 

assessment of biodiversity impacts and the development of measures to 

avoid, minimise and/or offset those effects.  The outcome also supports the 

view put to the Panel that the technical reference group has worked 

constructively to resolve issues as they have arisen. 

Further, the Panel notes that the Strategic EMP (EES Attachment 5) provides 

an integrated risk assessment, identifying residual risks for terrestrial 

ecology, as well as a comprehensive set of guidelines for managing impacts 

on terrestrial ecology.  These inclusions in the EES are a further 

demonstration of the rigorous approach taken by the Proponent.  As such, 

the Strategic EMP will provide leading guidance for the development of the 

Construction and Operations EMPs for the project. 

The Panel is also satisfied that concerns over the potential impacts on flora 

and fauna at specific sites can be minimised through the preparation of site 

specific EMPs that would form part of the overall construction EMPs across 

the various project components. 

The Panel was also generally satisfied with the Proponent’s responses to the 

range of issues raised in submissions. 

Page 63

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

The Panel agreed that concerns in relation to land rehabilitation along the 

pipelines are capable of being adequately addressed through requirements of 

the Construction EMPs which will specify a rehabilitation monitoring period 

and require further rehabilitation works where warranted through 

complaints. 

The Proponent has commenced negotiations for appropriate offsets and these 

will be determined in consultation with DSE and subject to final approval 

from DSE.  The Panel understands the difficulties in obtaining like for like 

native vegetation offsets.  However, in the absence of any specific 

information on the types of native vegetation offsets being pursued by the 

Proponent and therefore the relative conservation benefits associated with 

different offset options, the Panel cannot give any guidance about whether 

departures from like for like requirements for very high conservation value 

vegetation are justified.  This is a matter that remains for determination by 

the Minister for Energy and Resources, under the Pipelines Act 2005, 

presumably on the advice of the Minister for Environment and Climate 

Change. 

The Panel notes that the native vegetation losses associated with this project 

are relatively small (offset targets of 1.83 habitat hectares and 0.84 habitat 

hectares for the gas and water pipelines respectively) and that the offsets 

provided should achieve net gain in terms of environmental outcomes.  

However, continuing incremental losses of these proportions, coupled with 

the overall long term decline in extent and quality of native vegetation can 

result in considerable cumulative effects.  This is evident in the 

acknowledged difficulty of finding like for like offsets for very high 

conservation significance vegetation.  The Panel notes that the losses have 

been minimised as far as possible and that the Proponent is working closely 

with DSE, in order to find appropriate offsets.  Nevertheless, the Panel 

encourages DSE to work towards identifying strategic opportunities for the 

provision of consolidated offsets, possibly through the Trust for Nature and 

Bush Broker programs. 

The Panel accepted DSE’s evidence and determined that the EMP should 

adopt the standards and practices for clearance distances from trees during 

construction, as provided for in the ‘Australian Standard for the Protection of 

Trees on Development Sites 2009’.  However, the Panel was of the view that this 

should not compromise the pipeline route but noted it may result in 

increased offsets, where trees may be vulnerable.  Further, given the likely 

uncertainties encountered in assessing tree survival, the Panel determined 

that a post construction audit of net gain success should be conducted two 

years after construction and reviewed with respect to actual losses. 

Page 64

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

The Panel accepts the evidence that impacts of the Power Station operation 

on the Southern Bent‐wing Bat are unlikely.  Even if bats are attracted to the 

illuminated power station, there are no moving parts and the emissions from 

the Power Station are not expected to impact on the bats.  Nevertheless, the 

further monitoring regime put forward after the hearing is supported due to 

the uncertainties about bat usage of the site and possible impacts.  The Panel 

notes that responses if bat mortality is identified may well be in the form of 

adjustments to lighting, or offsets in the form of improvements to bat habitat 

elsewhere, rather than the imposition of significant new constraints on the 

operation of the Power Station. 

In relation to the potential impacts of the Power Station on local Brolga 

populations, neither the evidence presented nor DSE’s submissions 

identified any fauna other than the Southern Bent‐wing Bat that should be 

monitored on the Power Station site.  Further, DSE’s submission did not 

identify any outstanding issues in relation to the local Brolga population.  

The Panel concludes that the potential for indirect off‐site impacts of the 

Power Station operation on the local Brolga population does not warrant 

further specific investigation. 

The effective management of the regulatory processes subsequent to the EES 

will be crucial to ensuring that environmental effects are mitigated during 

construction and operation of the Power Station and gas and water pipelines.  

These processes are discussed in more detail in Chapter 11 in this report. 

Recommendations 

Ensure that construction of the gas and water pipelines is undertaken in 

accordance with the requirements of the Referral Decisions under the 

EPBC Act. 

Ensure that site specific requirements are included in construction EMPs, 

including appropriate rehabilitation techniques and monitoring measures 

for rehabilitation success, specific to terrestrial flora and fauna identified 

through targeted surveys. 

Ensure Construction EMPs for the gas and water pipelines require: 

appropriate follow up works to ensure rehabilitation to former 

condition; 

immediate post construction audits to confirm native vegetation offsets; 

and 

follow‐up audits at two years post construction, to confirm actual native 

vegetation losses and revise offsets, if required. 

Page 65

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

Adopt the standards and procedures in ‘Australian Standard for Protection 

of Trees on Development Sites 2009’ in Construction EMPs and review net 

gain assessments for any implied further losses of native trees. 

Monitor the occurrence of the Southern Bent‐wing Bat on the Power 

Station site and identify management or ‘offsetting’ measures if impacts 

from the Power Station are identified.  (Monitoring should be generally in 

accordance with the program as set out in Appendix D of this report.) 

4.3 Aquatic Ecology

4.3.1 EES Assessment and Evidence - Aquatic Ecology

Methodology 

The EES addresses aquatic ecology in Chapter 10.6 and sets out the Ecology 

Partners aquatic ecology assessments for the Power Station and Gas Pipeline 

(EES Appendix 6) and the Water Pipelines (EES Appendix 30).  The aquatic 

impact assessments for the proposed power station and gas pipeline 

involved desk top and field survey approaches with surveys carried out 

between November 2008 and June 2009.  Several watercourses could not be 

sampled or have a habitat assessment undertaken because they were dry, but 

a desktop review of all watercourses in the local area was undertaken. 

The EES noted that an aquatic flora investigation was outside the scope of 

the current project. 

Survey Results 

The field surveys during 2008 and 2009 recorded two fish species listed 

under the EPBC Act and the FFG Act: Dwarf Galaxias and Yarra Pygmy 

Perch.  The Australian grayling, the third species of national and state 

significance identified during the desktop survey, was not recorded during 

the field surveys but has previously been found in the Hopkins River. 

Most watercourses have not been fenced to exclude livestock; therefore, bank 

erosion, increases in water turbidity, pugging (the holes created when 

livestock step into the muddy substrate), and increases in nutrient loads were 

evident.  This has implications for the consideration of existing impacts on 

aquatic ecology.  Riparian zone structure is poor in the majority of the 

watercourses in the project area, the exceptions being Whiskey Creek, the 

Hopkins River and the Shaw River.  Most watercourses are also relatively 

low in macro invertebrate and fish species diversity.  However, Back Creek, 

Murray Brook, the Shaw River (upstream of Riordans Road), Mosquito 

Creek, Spring Creek and Wallaby Creek contained a high number of 

Page 66

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

macrophytes, including floating plants, submerged aquatic plants and 

emergent aquatic plants. 

EES Assessment of Impacts and Mitigation 

Potential project impacts on aquatic ecology (including communities and 

species of conservation significance) are summarised in the EES Chapter 10.6.  

The Strategic EMP (EES Attachment 5) provides an integrated risk 

assessment of residual risks and a comprehensive set of management 

guidelines (Chapter 4) that will assist with the management of impacts and 

implementation of mitigation measures which will be included in the 

Construction and Operations EMPs for the gas and water pipelines. 

The Proponent has committed to the preparation of site specific management 

plans for significant watercourse crossings (EES Chapter 8.2.6), in order to 

ensure appropriate mitigation measures. 

As already noted, the Referral Decisions under the EPBC Act oblige the 

implementation of specified measures to avoid significant impacts on listed 

threatened species. 

The EES noted that proposed avoidance, mitigation and management 

measures will address the threatening processes identified in the national 

recovery plans for threatened species and the FFG Act Action Statements. 

Impacts on marine flora and fauna, as a result of increased waste discharges 

from the Warrnambool Water Reclamation Plant have not been assessed.  

However, analysis of the potential wastewater streams indicates that water 

quality variables are well within the discharge limits specified in Wannon 

Water’s Corporate Licence.  It is reasonable to conclude there would be no 

additional impacts on marine flora and fauna. 

Preliminary ‘Net Gain’ Assessments 

Aquatic habitat surveys have not been undertaken at the proposed stream 

crossing sites for the pipelines in order to identify EVCs present.  Therefore, 

it has not been possible to carry out net gain assessments for aquatic 

vegetation and further assessments will be required. 

Page 67

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

4.3.2 Submissions and Proponent Response

There were few issues raised in submissions in relation to potential impacts 

on aquatic ecosystems. 

The Shire of Corangamite indicated concern over the initial technical reports 

prepared for the EES, leading to a lack of confidence in the research.  In 

particular, the Shire requested that the Proponent seek additional 

information about the presence of the Yarra Pygmy Perch in the Curdies 

River and investigate further impacts to significant orchids through the 

removal of Swamp Scrub vegetation at Whiskey Creek. 

Mr Power submitted that the measures required under the EPBC Act Referral 

Decision, which are designed to ensure protection of the nationally 

significant species and communities, have been incorporated in the 

mitigation measures set out in the EES.  At a number of points in the hearing, 

it was noted that further investigations would be undertaken, particularly 

through pre‐construction clearance surveys and that site specific construction 

management plans would provide further information where lacking.  The 

EES (EES Chapter 10, p.10‐70) also noted that site specific management plans 

for flora and fauna will be developed to detail requirements for management 

and will be consistent with advice provided by DSE. 

The Panel inspected a number of key sites where the proposed gas pipeline 

road and stream crossings sought to avoid important remnant native 

vegetation and where HDD was the preferred option.  The Panel noted that 

the need for open cut methods of stream crossings could be particularly 

problematic for instream flora and fauna communities, where HDD 

techniques are not feasible.  This is not so critical in streams of low or 

intermittent flows but for streams with regular flows, open cut methods will 

require the construction of sheet pile coffer dams or use of water filled 

bladders.  These measures are designed to hold up stream flow over half the 

stream bed during construction.  Measures to maintain stream flow have 

been included in the EES (EES Ch. 10, Section 10.3). 

4.3.3 Discussion and Conclusions

The Panel is of the view that the EES has reasonably addressed the EES 

objectives in relation to aquatic impacts and mitigation.  The surveys were 

carried out at a time of year when the chance of detecting most species 

would have been relatively high; and combined with database search results 

and discussions with local experts, limitations were unlikely to significantly 

affect the findings and recommendations. 

Page 68

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

However, given there were no surveys done of aquatic native vegetation at 

the proposed stream crossing sites, the Panel determined that further 

assessments will need to be undertaken during the pre‐construction phase.  

Whilst the EES includes a commitment to re‐instatement of the stream bed 

post construction, the assessment of the types of aquatic flora species and/or 

communities that may be disturbed was not explicit.  DSE confirmed in the 

hearing that the NVMF applies equally to instream aquatic vegetation, 

including the principle of net gain which should be assessed in terms of the 

most appropriate wetland EVC benchmark.  The Panel noted that the 

targeted aquatic surveys to be undertaken once stream crossing points are 

determined, would guide the mitigation measures to be included in site 

specific EMPs and would also guide the net gain assessments. 

The Panel considers that the site specific construction EMPs for the gas and 

water pipelines should detail rehabilitation techniques specific to aquatic 

flora, including measures to address the constraints on re‐establishment of 

aquatic flora species, imposed by stream flow. 

Recommendations 

Ensure that construction of the gas and water pipelines is undertaken in 

accordance with the requirements of the Referral Decisions under the 

EPBC Act. 

Undertake targeted aquatic flora surveys once stream crossing points and 

techniques are confirmed, in order to identify the relevant EVCs and 

undertake net gain assessments where required. 

Ensure site specific requirements in Construction EMPs, include 

appropriate rehabilitation techniques and monitoring measures for 

rehabilitation success, specific to aquatic flora identified through targeted 

surveys. 

Page 69

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

5. Protection of Cultural Heritage

EES Evaluation Objective: To protect Aboriginal and non‐Aboriginal cultural 

heritage to the extent practicable. 

5.1 Aboriginal Cultural Heritage

5.1.1 Regulatory Framework

The Aboriginal Heritage Act 2006 requires that a Cultural Heritage 

Management Plan (CHMP) be prepared in respect of any works for which an 

EES is required.  The CHMPs must recommend measures to manage 

Aboriginal cultural heritage before, during and after an activity and must be 

endorsed by either a registered Aboriginal party or approval can be gained 

from the Secretary of DPCD.14 

5.1.2 EES Assessment - Aboriginal Cultural Heritage

The EES addresses the potential environmental effects on Aboriginal cultural 

heritage and measures to mitigate impacts15 are also identified in the   

Strategic EMP (EES Attachment 5).  The EES describes the Aboriginal 

heritage context.  It reports that neither a search of government and non‐

government registers nor preliminary Aboriginal Cultural Heritage 

Assessments (CHAs) revealed any Aboriginal cultural heritage places within 

the Power Station site, gas pipeline or water pipelines alignments.  However, 

unsurveyed areas the Power Station have been identified as having potential 

to contain Aboriginal heritage places.  Areas of high potential sensitivity 

include the Curdies, Merri, Hopkins and Moyne Rivers which are likely to 

contain stone artefacts, hearths, charcoal and freshwater shellfish and may 

possibly contain fish traps, mounds, burials and scarred trees. 

CHMPs are currently being prepared by Andrew Long & Associates for the 

Power Station site and gas pipeline and for the water pipelines and are due 

to be completed, once the construction contractor is chosen.  These CHMPs 

will guide the protection and management of both known and unknown 

14 Other legislation and regulations relevant to the protection of Aboriginal cultural heritage values

in the Project area include: Environment Protection and Biodiversity Conservation Act 1999, Native Title Act 1993; Australian Heritage Council Act 2003; Aboriginal and Torres Strait Islander Heritage Protection Act 1984; Aboriginal Heritage Act 2006 and Aboriginal Heritage Regulations 2007.

15 See Chapters 5 and 11.7, and the preliminary Aboriginal cultural heritage assessments for the Power Station and gas pipeline (EES Appendix 20 prepared by Andrew Long & Associates Pty Ltd); and for the water pipelines, (Appendix 36 prepared by Tardis Enterprises Pty Ltd).

Page 70

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

Aboriginal places.  While there are no registered Aboriginal parties in the 

study area, the following local Aboriginal groups have applied for registered 

Aboriginal party status: 

Framlingham Aboriginal Trust; 

Gunditj Mirring Traditional Owners Aboriginal Corporation; and 

Kuuyang Maar Aboriginal Corporation. 

Consultations with the applicant registered Aboriginal parties during the 

CHAs revealed that the project area contains Aboriginal values in the form of 

plants commonly used for food and fibre by traditional Aboriginal 

communities.  No information regarding oral tradition, specific cultural 

places or places of significance in the area was provided during the 

consultations.  Of the three applicant registered Aboriginal parties invited to 

comment on specialist reports, one response was received from Framlingham 

Aboriginal Trust.  The response stated that Framlingham Aboriginal Trust 

does not endorse the results and recommendations provided in the specialist 

study due to a conflict of belief in the definition of significance and potential 

sensitivity (Refer to EES Appendix 20 for the full response).  Shaw River 

Power and Wannon Water are working with the applicant registered 

Aboriginal parties and seeking to address the concerns raised by 

Framlingham Aboriginal Trust, through the final CHMP. 

No native title claims have been made on the project area. 

5.1.3 Discussion and Conclusions

The Panel invited AAV as a member of the Technical Reference Group, to 

make a submission and present at the hearing.  However, AAV did not make 

any submission and there were no submissions raising any concerns relating 

to Aboriginal cultural heritage. 

The Panel notes that approval of the CHMPs underpins the approval of all 

other regulatory processes associated with the project and this establishes an 

appropriate framework to manage any issues that may arise. 

Page 71

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

5.2 Non-Aboriginal Cultural Heritage

5.2.1 Regulatory Framework

The project area is not affected by any Heritage Overlay under either the 

Corangamite or Moyne Planning Schemes. 

The Planning Scheme (Clause 52.37) requirement for a planning permit for 

works affecting dry‐stone walls applies except along the gas pipeline which 

is exempt from the provisions of planning schemes. 

5.2.2 EES Assessment - Non-Aboriginal Cultural Heritage

The EES assessment of non‐Aboriginal cultural heritage16 involved desktop 

studies, field surveys and significance assessments.  The search of 

government and non‐government registers did not reveal any non‐

Aboriginal cultural heritage places within the Power Station site, the gas 

pipeline alignment or the water pipelines alignment.  However, the field 

surveys along the pipeline alignments identified: 

seven dry‐stone wall complexes (one in the gas pipeline project area and 

six in the water pipelines project area); 

a bluestone drinking trough in the gas pipeline project area; 

a bluestone bridge and culvert outside the water pipelines project area; 

and 

an area of domestic artefact scatters in the water pipelines project area. 

The Strategic EMP and Environmental Management Commitments include 

Management Guidelines for heritage places. 

The Proponent has committed to minimising impacts on dry‐stone walls.  In 

some instances temporary removal of dry‐stone walls will be required but it 

is proposed to minimise impacts by reducing the width of the construction 

right of way in these locations and to re‐instate the walls to reflect former 

condition.  Temporary fencing to indicate no‐go zones will be erected around 

the bluestone drinking trough and domestic artefact scatters to prevent 

accidental damage from construction works.  There is little potential for 

disturbance to these places during operation of the pipelines. 

16 See EES Chapter 11.8, the Strategic EMP (EES Attachment 5) and Environmental Management

Commitments (EES Attachment 4). Two non-Aboriginal cultural heritage assessments were undertaken: one for the Power Station site/ gas pipeline alignment (Appendix 20 prepared by Andrew Long & Associates Pty Ltd) and one for the water pipelines alignment (Appendix 36 prepared by Tardis Enterprises).

Page 72

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

Additional non‐Aboriginal cultural heritage field surveys of the Power 

Station site and the entire gas and water pipelines alignments, including 

subsurface testing along Old Dunmore Road, are proposed prior to 

commencement of any works.  Impacts on any additional heritage places 

found during construction will be reduced by ceasing all works within 5 m of 

the affected area until appropriate management is formulated in consultation 

with Heritage Victoria. 

5.2.3 Submissions and Response

The only submission relating  to non‐Aboriginal cultural heritage was the 

Shire of Corangamite request that the Corangamite Shire Heritage Study 

Volumes 1 and 2 be included as part of the desktop study for non‐Aboriginal 

cultural heritage.  The Panel notes that the EES has referred to this study 

(EES Chapter 11.8.1). 

5.2.4 Discussion and Conclusions

The Panel is satisfied with the EES approach to the assessment of Non‐

Aboriginal cultural heritage and with the measures identified to minimise 

impacts on heritage places. 

As the gas pipeline is exempt from the planning scheme provisions, the 

Panel is of the view that a requirement for the protection and re‐instatement 

of dry‐stone walls should be included in the construction EMP associated 

with the licence under the Pipelines Act 2005. 

It is noted that a planning permit is required under Clause 52.37 to remove or 

alter a dry‐stone wall for the water pipelines.  As removal of native 

vegetation from the water pipelines route is proposed to be exempt from the 

planning scheme provisions, the Panel is of the view that works affecting 

dry‐stone walls should also be exempt under that clause, subject to a 

requirement for the protection and re‐instatement being included in the 

construction EMPs. 

Recommendations 

Revise the Clause 52.03 incorporated document to extend exemptions from 

permit requirements to alterations and removal of dry stone walls along 

the water pipeline alignment. 

Ensure Construction EMPs for the gas and water pipelines include 

measures to protect and re‐instate dry‐stone walls that may be impacted by 

construction. 

Page 73

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

6. Health, Safety and Amenity Impacts

6.1 Noise

6.1.1 Regulatory Framework and Policy Context

The Environment Protection Act 1970 (Section 46) requires noise emissions 

to comply with state environment protection policies that specify acceptable 

conditions for emitting noise and it is an indictable offence to emit 

‘objectionable noise’ within the meaning of the regulations (Section 48). 

State Environment Protection Policy (Control of Noise from Commerce, 

Industry and Trade) No N‐1 (SEPP‐N1) was developed to protect noise‐

sensitive areas in the Melbourne metropolitan region and does not impose 

noise limits on industry in regional Victoria.  However SEPP N1 does: 

provide useful definitions of ‘day’, ‘evening’ and ‘night’; 

define the ‘background level’ for each of these periods as the arithmetic 

average of LA9017 noise levels for each hour of the period; and 

Sets out procedures for background noise monitoring. 

Interim Guidelines for Control of Noise from Industry in Country Victoria (EPA, 1989) (the Interim Guidelines) apply specifically to rural areas with 

low background noise levels (i.e., less than 25 dB(A) at night or 30 dB(A) 

during the day or evening period).  For construction noise, the Interim 

Guidelines state: 

During construction of an industry the daytime limit shall be raised by 

10 dB(A) except where this would result in a limit greater than 

68 dB(A).  In this case the daytime construction noise limit shall be 

68 dB(A).  Limits for other time periods shall be the same as those set for 

the ongoing industrial operation. 

SPPF Clause 15.05 states that decision‐making by planning and responsible 

authorities must be consistent with any relevant aspects of the Interim 

Guidelines. 

The EPA Noise Control Guidelines (EPA, 2008b) also deal with construction 

site noise (see Chapter 6.1.8).

17 LA90 represents the lowest 10% of the noise in the hour.

Page 74

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

As outlined above there are a number of policies and guidelines that could 

be applicable to or used for the determination of appropriate noise criteria 

for the project. 

For rural areas, background levels can be very low, even in areas zoned for 

industrial and commercial activities.  The Interim Guidelines apply 

specifically to rural areas with low background noise levels (i.e., less than 

25 dB(A) at night or 30 dB(A) during the day or evening period.  The Interim 

guidelines establish maximum noise levels of 45 dB(A) during the day, 

37 dB(A) during the evening, and 32 dB(A) at night at residential premises.

The recent EPA Draft Guidelines ‘Noise from Industry in Regional Victoria’, like SEPP N1, propose a zoning based procedure to determine 

recommended maximum levels in rural areas with low background noise 

levels.  Using these Draft Guidelines, and on the basis that the noise is 

generated in a SUZ and sensitive receptors are in a Farming Zone, the 

relevant limits would be: 50 dB(A) during the day, 45 dB(A) during the 

evening, and 40 dB(A) at night. 

6.1.2 EES Assessment and Evidence – Noise Criteria

The EES documents the methodology and findings of the noise assessments 

for the Power Station, compressor station and gas pipeline18 and the water 

supply infrastructure19.  Mr Turnbull, who was the primary author of the 

Power Station and pipeline assessments provided at the Hearing, 

summarised the noise assessments and responded to submissions that raised 

noise related issues.  Mr Pavasovic, who prepared the noise assessment for 

the water infrastructure, was available to attend the Hearing but the Panel 

advised it would rely on the material in the EES. 

Background (LA90) noise levels have been monitored on the basis of SEPP 

N‐1, at selected sensitive receptor locations near to the Power Station, 

compressor station, water pipelines, Port Fairy recycled water treatment 

plant and Port Fairy water treatment plant sites. 

These background levels were almost all below 25 dB(A) at night; hence the 

Interim Guidelines classify the areas near the Power Station and compressor 

site areas as generally having the potential for ‘very low’ background noise.  

Because the Power Station, compressor station and recycled water treatment 

plant and pump stations may operate at any time of the day or night, the 

appropriate and critical criterion to be applied to these facilities under the 

18 EES Appendices 13 and 14 19 EES Appendix 33

Page 75

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

Interim Guidelines is the night‐time noise limit of 32 dB(A) measured at the 

nearest sensitive receptor. 

EPA generally supported this approach in its written submission. 

The EPA publication - A guide to the measurement and analysis of noise 

states: 

‘Weather conditions can markedly affect the noise level received at a noise 

sensitive area.  This is particularly important when the level is low and 

the distance between the noise sensitive area and the source exceeds 200 

metres.  When it is believed that the noise received at the noise sensitive 

area is affected by weather conditions, then a derived point may be used.  

It is advisable to use this point in all cases where the noise source is more 

than 500 metres from the noise sensitive area because weather conditions 

are likely to be the major source of variability in the noise level at this 

distance. 

Where a suitable derived point is not available, Policy N‐l requires three 

measurements to be taken within a 30 day period at the noise sensitive 

area; this is used as an alternative to the derived point method to account 

for the variability in received noise caused by weather conditions.’ 

The EES and Mr Turnbull’s evidence acknowledged the requirements of the 

Interim Guidelines and used the CONCAWE weather categories20 to predict 

noise levels at the sensitive receptors under different meteorological 

conditions and as a basis for monitoring. The EES proposed noise criteria for 

the Power Station and the compressor station measured at the closest 

sensitive receptor at night, being: 

32 dB(A) measured under neutral meteorological conditions (CONCAWE 

Category 4); and 

34 dB(A) when measured under worst case meteorological conditions 

(CONCAWE Category 6). 

According to Mr Turnbull, the proposed monitoring methodology provides a 

more robust and more readily verifiable method than the current SEPP N1 

methodology.  It is based on consideration of 12 months of weather data, the 

percentage of time each weather category occurred for the sensitive receptor, 

compared with the SEPP methodology of averaging 3 measurements taken 

over a 30‐day period. In addition, these criteria have been used for similar 

projects (eg Mortlake Power Station). 

20 The weather categories are based on wind speed, wind direction, time of day, and level of cloud

cover.

Page 76

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

6.1.3 Submissions and Proponent Response - Noise Criteria

The EPA’s written submission noted that, while there are no statutory noise 

criteria that apply outside Metropolitan Melbourne, it has a general power 

and duty to protect the environment through tools such as Works Approvals 

for new works and Pollution Abatement Notices.  EPA’s submission and 

questioning of Mr Turnbull by Mr Nancarrow on behalf of EPA, made the 

following key points: 

the noise assessment  notes that the background level is not below 

25 dB(A) at receptor 107.  Nevertheless, it adopts the very low assumption 

that the background level goes below 25 dB(A) during the night period 

(but not when averaged in accordance with the definition of ‘background 

level’ under SEPP N‐1)to determine the design target relevant as the 

modelling basis (discussed below).  It was noted that this basis for 

modelling may need review; 

under SEPP N‐1 the noise indicator is a 30‐minute average, and where 

propagation of noise is affected by atmospheric conditions then the noise 

is measured as the average of three measurements in 30 days (clause 6 of 

part A 2 of Schedule A of SEPP N‐1); 

where atmospheric conditions provide a frequent enhancement of noise 

at a receiving location then the representation of the average of the three 

highest measurements attainable in a 30 day period is well represented by 

the worst case CONCAWE Category 6 conditions.  Where the degree of 

atmospheric enhancement is not as clear, then EPA’s advice in other cases 

has been that noise should be modelled under weather conditions that 

favour propagation of noise no more than 20% of the time after 

examining the distribution of weather conditions at a site; 

there are a number of uncertainties with the Proponent’s assessment of 

noise impact of the Power Station and EPA believes that the noise 

modelling basis for the Power Station needs some review; and 

although clarification on modelling is needed, other factors are equally 

important to consider in regard to whether reasonable outcomes are 

achieved: 

no statutory noise criteria exist in regional Victoria; 

N3/89 does not specify Location 109 as being in a ‘very low’ 

background environment and the limit of 32 dB(A) is not 

automatically adopted under the interim guidelines; 

as non‐statutory criteria, the reasonableness of the noise impact in 

terms of the potential for alternative sites is important; and 

the practicability of noise control options to further reduce noise 

levels; the Proponent has stated that Option 1 will employ 

Page 77

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

‘commercially available’ noise control and Option 2 will require 

additional noise control with its open cycle turbine. 

The EPA noted: 

setting numerical noise level targets at receptors in Works Approvals and 

licences can be problematic and may lead to perverse outcomes.  

Proponents may be required to spend money on additional attenuation 

measures just to achieve a number, irrespective of whether non‐

compliance with the noise level is a perceptible problem or not; and 

current EPA preference is not to set noise level to be achieved at sensitive 

receptors in Works Approvals.  The example of the Works approval 

issued to Woodside Energy Ltd  (WA66800) was given as the best 

example of the current EPA Approach.  In this Works Approval, 

Woodside must undertake during commissioning noise monitoring of the 

compressor and other equipment at source to assess compliance with the 

noise emissions and specifications listed in the Works Approval 

application.  These noise emissions relate to the equipment and not noise 

levels at sensitive receptors. 

At the Hearing Mr Frame indicated that the EPA had agreed with the 

Proponent on both the methodology used to develop the criteria and the 

numerical criteria used in the EES. 

The Corangamite Shire noted that compliance with the proposed noise 

guidelines will potentially cause annoyance to some residents.  As expected 

for a rural community, the existing background level is low (less than 

25 dB(A) and the proposed the operational noise level of 34 dB(A) is an 

increase of 2 dB(A) above the current EPA acceptable level of 32 dBA.  Thus a 

nine decibel increase would be permitted, which is very significant.  It is 

council’s experience that 34 dB(A) is unacceptably high for the area of the 

compressor station, and 32 dB(A) will still be significantly high for the 

residents within the region.  The Shire submitted that the compressor station 

be insulated to a greater degree to reduce nuisance noise at nearby 

residences. 

The Morgan‐Paylers submitted that the Schedule to the SUZ should specify 

an EMP requirement to comply with the noise limits specified in the EPA 

Interim Guidelines. 

In further evidence, Mr Turnbull made the following key points: 

the operational criteria adopted for the project were developed and 

adopted in consultation with the EPA through the Technical Reference 

Group process; 

Page 78

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

the adopted criteria are 32 dB(A) in neutral weather conditions and 

34 dB(A) in worst case weather conditions.  The most stringent criterion 

in the Interim Guidelines is a night time criterion of 32 dB(A).  Although 

meteorological conditions are not defined in the Interim Guidelines, 

SEPP No N‐1 requires an average of noise levels to be measured.  In these 

circumstances, use of neutral weather conditions to achieve the non‐

mandatory criterion of 32 dB(A) is considered to be appropriate; 

notwithstanding assessment against the Interim Guidelines, under the 

recently released Draft Guidelines ‐ ‘Noise from Industry in Regional 

Victoria’ would result in limits of 46 dB(A) during the day, 41 dB(A) 

during the evening and 36 dB(A) at night.  The most stringent of these is 

less stringent than the 34 dB(A) criterion adopted; 

for most people, a difference in noise level of 2 dB(A) would be barely 

discernable, a difference of 3 dB(A) would be detectable, and a difference 

of 10 dB(A) would be a doubling of the noise; and 

the adopted criteria would be used to determine the design of the 

facilities and the necessary acoustic treatments required to achieve those 

levels.  In his opinion, the proposed equipment and acoustic treatment 

would meet the criteria, but more could and would be done ‐ at a cost – if 

required. 

Mr Power strongly opposed specifying noise performance standards in the 

planning scheme (see discussion in Chapter 12). 

6.1.4 Discussion and Conclusions – Noise Criteria

The Panel notes that wind energy facilities in the region (and potentially in 

the immediate vicinity of the subject site) have night‐time noise limit set at 

40 dB(A).  This is substantially higher than the limit proposed for the Power 

Station and compressor station.  Further, the most recent EPA view 

regarding noise in quiet rural areas, expressed in the Draft Guidelines, also 

suggest a higher noise limit than either the Interim Guidelines or the limits 

proposed for the project. 

The Panel notes with some concern the range of guidelines that can be used 

to establish noise criteria in rural areas with very low night‐time background 

noise levels.  The Panel is also concerned that the EPA provided differing 

views in its written submission to those previously agreed with the 

Proponent through the TRG process, and provided verbally to the Panel.  In 

this context it is difficult to establish a clear and acceptable methodology to 

determine appropriate noise criteria. 

Notwithstanding the above, the Panel has considered the material and expert 

opinion provided and believes that there is an adequate and appropriate 

Page 79

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

basis for the noise criteria that have been adopted in the EES.  Further, the 

Panel does not believe that there is any significant basis for further review of 

the modelling methodology as suggested in the EPA written submission.  

The use of the CONCAWE weather categories provides a more robust and 

more readily verifiable method than the current EPA methodology.  It is 

based on consideration of 12 months of weather data, the percentage of time 

each weather category occurred for the sensitive receptor, compared with the 

SEPP methodology of averaging 3 measurements taken over a 30‐day period. 

While acknowledging that there will be some noise impacts in areas of very 

low background noise, the criteria provide a conservative approach to the 

setting of criteria for the project.  The Panel accepts that the limits adopted 

will mean noise from the power and compressor stations would be audible 

but would not disrupt normal residential activities, including during the 

night time period.  The Panel considers the appropriate noise criteria for the 

Power Station and compressor station operations to be achieved at the 

nearest sensitive receptors should be: 

32 dB(A) when measured under neutral meteorological conditions 

(CONCAWE Category 4); and 

34 dB(A) when measured under worst case meteorological conditions 

(CONCAWE Category 6). 

Regulatory mechanism to ensure compliance with the noise criteria is 

discussed in Chapter 11. 

6.1.5 EES Assessment and Evidence - Power Station, Compressor Station and Recycled Water Treatment Plant Operation Noise

According to the analysis provided in the EES, with appropriately designed 

noise attenuation measures, compliance with noise criteria adopted will be 

achieved for both options of power station operation (See Figure 4 below).  

On the basis of the modelling there is no additional attenuation required for 

the combined cycle turbines in order to meet the criteria.  However the 

combined noise from one open cycle and the two combined cycle gas 

turbines would exceed the criteria with the above sound power levels 

without additional noise attenuation beyond the typical low noise design 

acoustic treatment provided for the modelled open cycle turbine.  The 

additional noise attenuation requirements are expected to be achievable by 

applying commercially available noise attenuation techniques including the 

use of inlet and exhaust silencers and equipment enclosures. 

Modelling of the noise from the operation of the proposed compressor 

station, with the option for acoustic treatment provided by the manufacturer, 

Page 80

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

also predicts compliance with the noise criteria adopted for the project (see 

Figure 5 below). 

For the RWTP, the noise emissions assessment indicates that modelled noise 

emissions operations will meet the applicable operational noise criteria at the 

identified nearest sensitive receivers and at the 300 m buffer.  This is 

provided that equipment noise emissions are considered in the design of the 

proposed works and noise control measures such as buildings with concrete 

walls as outlined in the EES are incorporated into design. 

  

Figure 4  Power Station Noise Contours (weather category 6) 

 

Figure 5  Compressor Station Noise Contours (weather category 6) 

Page 81

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

6.1.6 Submissions and Proponent’s Response – Power and Compressor Station Operation Noise

The Morgan‐Payler Family expressed concerns about increased noise from 

the project (predicted to be up to 25 dB(A)).  They sought noise attenuation 

measures on their land and post construction noise measurements to confirm 

the predicted noise levels. 

Mr Turnbull responded that an outdoor noise level of less than 30 dB(A), as 

expected at the Morgan‐Payler property, is well below the level suggested by 

any authority for the consideration of impacts and does not warrant noise 

control measures.  He noted that the noise control measures proposed on the 

Power Station site have effectiveness in maintaining indoor and outdoor 

amenity for all sensitive receptors. 

The Corangamite Shire acknowledged that noise modelling for the 

compressor station suggests compliance with noise limits adopted for the 

project but, as noted above, the guidelines were questioned and it was 

submitted that the Limits in the Interim guidelines should be maintained.  

Council noted that the EES states that for the compressor station area, at SR 

58, the minimum background noise level for during the day was 40 dB(A), 

which it considered surprising, as the site is located in open farmland, and 

not near any major roads.

Shirley Nicholls and Moyne Shire submitted that the cumulative impacts of 

noise from the adjacent uses needs to be assessed (see Chapter 10).  Moyne 

Shire also submitted that detailed enforceable protocols provided to enable 

any such issues, if they arise, be satisfactorily resolved. 

6.1.7 Discussion and Conclusions - Power and Compressor Station Operation Noise

The Panel is satisfied that with appropriate design and operation, the Power 

Station under either configuration can meet the noise criteria adopted for the 

project.  The Panel also considers that with appropriate design and operation 

the Compressor Station can meet these noise criteria. 

As discussed in Chapter 6.1.10, noise should be measured during 

commissioning at nearby residences to the Power Station (including the 

Morgan‐Payler residence) and compressor station in order to confirm 

compliance with noise limits.  The results of this noise monitoring program 

should be made available to the occupiers of the respective residences, the 

Responsible Authority and the EPA. 

Page 82

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

6.1.8 EES Assessment and Evidence – Noise from Construction Activities

Evidence from Mr Turnbull indicated that as the construction of the power 

and compressor stations is likely to occur over an extended period, it is 

appropriate to ensure that noise levels at nearby sensitive receptors achieve 

the noise criteria as set down by Interim Guidelines N3/89. 

Based upon the existing background noise levels measured in the vicinity of 

the site, the Interim Guidelines result in noise criteria for the construction of 

the power plant of 55 dB(A) during the daytime (7am to 6pm), 37 dB(A) 

during the evening (6pm to 10pm), and 32 dB(A) at night (10pm to 7am), 

when measured at sensitive receptors in the vicinity. 

The EPA Noise Control Guidelines which also deal with construction site 

noise, with limits (are summarised in the Table below) that vary slightly 

from the recommendations contained in the Interim Guidelines. 

 

Table 1  EPA Noise Control Guidelines recommended Construction Noise Limits 

(Source EES Table 11.1) 

It was further noted that when considering noise levels associated with the 

construction of the pipelines, construction activities would be expected to 

occur in the vicinity of any one particular sensitive receptor for periods no 

greater than one or two weeks, with sporadic vehicle movements along the 

pipeline corridor at other times.  It is noted that this level of acoustic impact 

on a sensitive receptor would be similar to the level of impact from many 

farming operations near sensitive receptors.  In these circumstances, it is 

considered more appropriate to ensure that work practices at sensitive 

receptors in the vicinity of the pipelines are in general accordance with the 

requirements of the Noise Control Guidelines. 

Page 83

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

6.1.9 Discussion and Conclusions – Noise from Construction Activities

The Panel accepts that noise sensitive receivers may potentially be impacted 

by construction activities.  The EES identified the restrictions on construction 

activities and construction noise management measures which should be 

included in the Construction EMPs for the project.  These mitigation 

measures should be implemented and all potentially impacted residents 

should be informed of the nature of the works, expected noise levels, 

duration of works and a method of contact. 

The noise impacts of the construction of the gas and water pipelines should 

be managed under the EPA Noise Control Guidelines (Publication 1254: 

October 2008, and in particular: 

other than in unusual circumstances, the gas pipeline construction 

activities should be restricted to 6am.  to 6pm, seven days per week 

(noting lower noise threshold requirements for activities conducted on 

Saturdays and Sundays).  Early‐morning activities from 6.00  to 7.00 a.m. 

should be restricted to low‐noise work, such as vehicle arrivals and 

toolbox meetings; and 

water pipelines construction activities should be restricted to 7am to 6pm 

Monday to Friday, and 7am to 1pm on Saturdays. 

Due to the extended nature of the construction of the Power Station, 

compressor station, recycled water treatment plant and pump stations, the 

noise impacts should be managed under the Interim Guidelines n3/89 and 

meet the criteria when measured at sensitive receptors in the vicinity: 

- 55 dB(A) during the daytime (7am to 6pm); 

- 37 dB(A) during the evening (6pm to 10pm); and 

- 32 dB(A) at night (10pm to 7am). 

These requirements should be incorporated into the respective Works 

Approvals and Construction EMPs for the project. 

6.1.10 Noise Monitoring And Complaints Procedures

The EES outlines noise monitoring procedures and proposes remedial action 

in the event that noise levels exceed noise objectives for the project.  It states 

that Shaw River Power will investigate and act on noise complaints received 

during project operations.  Monitoring may be required at the sensitive 

receptor concerned to determine whether noise limits are being breached.  

Accidences of noise limits will trigger action to identify the cause and take 

steps to remedy the impact. 

Page 84

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

Mr Chessell for the Morgan‐Payler family submitted that the Proponent 

should be strongly held to account to meet the noise criteria.  Specifically, he 

proposed that: 

Noise monitoring should be required as follows (as a minimum) at 

various sensitive noise receptors in the vicinity of the site (including the 

Morgan‐Payler premises): 

- on a monthly basis during construction of each stage of the 

facility; 

- on a quarterly basis during the operation of the facility; and 

Circulation of the results of those measurements to the relevant 

landowners and to the Responsible Authority should occur within one 

week of the measurements being taken. 

In addressing this issue, Mr Frame from EPA submitted that it routinely 

investigates complaints and reports back to complainant on the outcome of 

its investigations.  Where problems are identified, these can be addressed 

through a Pollution Abatement Notice.  The Environment Protection Act 1970 

does not envisage third party enforcement.  It provides for criminal not civil 

proceedings. 

Mr Guest from the Moyne Shire submitted: 

the EES scoping requirements foreshadowed the need for a monitoring 

and dispute resolution procedure.  Exactly how this is envisaged to work 

is yet to be resolved for this proposal, and will also need to have the 

capacity to deal with interactions with other developments if and when 

they are constructed; and 

Section 13(a) of the Planning and Environment Act 1987 states that 

enforcement responsibilities rest with the local council, unless the 

planning scheme specifies another person as the responsibility authority.  

As such, a local council has primary responsibility for enforcement of the 

planning scheme and permit conditions.  In this case other agencies have 

a role, eg the EPA. 

The EPA noted that a community monitoring program can provide a 

community forum in which to raise the broadest range of issues associated 

with the Power Station. 

The Panel agrees with submissions that compliance with noise limits should 

be verified by a suitably qualified person as each stage of the project is 

completed and commissioned.  It is actual noise levels at key locations and 

the consequential effect on amenity that is of concern, rather than the 

accuracy of modelling inputs, which appeared to be the focus of the EPA 

suggestions relating to verification of noise production from equipment used 

Page 85

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

in the project.  The purpose of compliance monitoring and enforcement is to 

control noise levels, not to review assessment methods. 

The outcome of this monitoring should be provided to the relevant Council, 

the EPA and the residents of the house where monitoring took place.  It 

should also be available on request to members of the public.  The Panel 

endorses the Shire of Moyne initiative in establishing a forum for liaison 

between the local community and relevant agencies, including EPA.  This 

process should ensure noise complaints are responded to promptly and noise 

monitoring results are publicly available (See Chapter 11.2.4 for discussion of 

Complaint Management). 

Recommendations 

Include restrictions on construction activities and construction noise 

management measures to the satisfaction of EPA and the Responsible 

Authority in the Construction EMPs for the project. 

Inform residents of the nature of the works, expected noise levels, duration 

of works and a method of contact. 

Manage the noise impacts of the construction of the gas and water 

pipelines under the EPA Noise Control Guidelines (Publication 1254: 

October 2008, and in particular: 

Other than in unusual circumstances, the gas pipeline construction 

activities should be restricted to 6am to 6pm, seven days per week 

(noting lower noise threshold requirements for activities conducted on 

Saturdays and Sundays).  Early‐morning activities from before 7am 

should be restricted to low‐noise work, such as vehicle arrivals and 

toolbox meetings. 

Water pipelines construction activities should be restricted to 7am to 

6pm Monday to Friday, and 7pm to 1pm on Saturdays. 

Implement the following noise limits at the nearest residence in the EPA 

Works Approval and the EMPs for the Power Station and compressor 

station: 

operational noise: 

34 dB(A) under worst case weather, (CONCAWE Category 6); 

32 dB(A) under neutral weather (CONCAWE Category 4); and 

construction noise: 

55 dB(A) during the daytime (7am to 6pm); 

37 dB(A) during the evening (6pm to 10pm); and 

32 dB(A) at night (10pm to 7am). 

Page 86

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

Monitor noise at the sensitive receptors nearest to the Power Station and 

compressor station under representative conditions during the 

commissioning of each stage of the project to confirm compliance with the 

criteria. 

Make the results of any noise monitoring of the project and responses to 

noise complaints available to the community liaison forum. 

6.2 Air Quality

The principal emissions to air of the project arise from: 

the operation of the Power Station for the two options for the Power 

Station configuration at Stage 3: 

- Option 1: Three combined‐cycle gas turbines (CCGT); and 

- Option 2: One open‐cycle gas turbine (OCGT) and two combined‐

cycle gas turbines. 

the operation of the compressor station; and 

fugitive dust during construction of the Power Station, compressor 

station and recycled water plant and the gas and water pipelines. 

Other issues addressed in the EES and submissions related to the potential 

for impacts of combustion gases on drinking water supplies, and for odour 

emissions. 

6.2.1 Regulatory Framework and Policy Context

The legislation and guidelines relevant to controlling air quality impacts 

during construction and operation of the project are: 

Works approvals and discharge licenses are required under the 

Environment Protection Act 1970, which is administered by the EPA; 

The State Environment Protection Policy (Air Quality Management) (SEPP 

AQM) (Victorian Government, 2001) protects air quality in Victoria 

through a combination of quality objectives for specific indicators (such 

as pollutants, dust and odour emissions) that can be applied to the 

design, construction and operations phases of the project; 

The State Environment Protection Policy (Ambient Air Quality) (Victorian 

Government, 1999) (SEPP(Ambient Air Quality))  sets air quality 

objectives and goals for Victoria; 

Victoria’s Best Practice Environmental Management: Environmental Guidelines for Major Construction Sites (EPA, 1996) provides guidelines for dust 

control during construction but do not specify air quality criteria; 

Page 87

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

The Australian Pipeline Industry Association Code of Environmental Practice 

(APIA, 2009) provides generic guidelines for the control of emissions to 

air, including dust, during the construction of the pipelines; and 

The Australian Water Quality Guidelines (Australian Government, 2004) 

provide a framework for good management of drinking water supplies 

that will assure safety at point of use. 

6.2.2 EES Assessment and Evidence - Air Emissions

Power Station 

In the EES emissions of carbon monoxide (CO) and oxides of nitrogen (NOx) 

have been assessed.  Emissions of other pollutants were acknowledged, but 

the quantities of emissions were considered to be insignificant, and their 

impacts were not assessed.  Mr Ormerod  has assessed the potential impacts 

of other pollutants and his findings were presented to the Hearing. 

Ground‐level atmospheric concentrations of CO and NO2 were assessed 

against the air quality ‘design criteria’, sourced from the SEPP(Air Quality 

Management): 

Nitrogen dioxide (NO2)–190 μg/m3 (0.1 ppm), 1 hour average, 99.9th 

percentile; and 

Carbon monoxide (CO)–29,000 μg/m3 (25 ppm), 1 hour average, 99.9th 

percentile. 

The impact assessment modelling was conducted in accordance with the 

requirements of Schedule C, Modelling Emissions to Air, SEPP‐AQM, and in 

consultation with EPA. 

Atmospheric dispersion modelling using the regulatory model Ausplume 

was undertaken to predict the potential impact of emissions to air of oxides 

of nitrogen and carbon monoxide for the following cases: 

Shaw River Power Station – Option 1 (3 x CCGTs): Normal (100 & 60% 

Load) & Start‐up Operations; and 

Shaw River Power Station – Option 2 (1 x OCGT + 2 x CCGTs): Normal 

(100% Load) & Start‐up Operations. 

The results of the air impact assessment demonstrate that the ground level 

concentrations for all cases considered will comply with the relevant health‐

based ambient air design criteria in SEPP‐AQM as indicated in Table 2 

below. 

In evidence provided by Mr Ormerod, the impacts of pollutants not 

considered in the EES were evaluated, based on Victorian EPA air quality 

Page 88

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

guidelines and the estimated maximum concentration of each pollutant at 

sensitive receptors.  He concluded that the ground level concentrations of all 

of the emissions substances are well below the SEPP AQM guideline levels. 

Table 2:  Predicted 1‐hour Average ‘Maximum’ Ground Level Concentration – 

Power Station Option 1, Option 2 and Compressor Station 

(Source” Derived from EES Tables) 

(3 x CCGTs) ‐ Normal Operations, 100% Load Indicator Maximum (99.9

percentile) Predicted Ground Level Concentration (μg/m3)

Worst-affected Residential Property (99.9 percentile) Predicted Ground Level Concentration (μg/m3)

Design Criterion (μg/m3)

Compliance Status

Predicted 1‐hour Average ‘Maximum’ Ground Level Concentration – Power 

Station Option 1 Nitrogen

Dioxide (NO2) 46.1  27.6  190  Yes Carbon

Monoxide (CO)

154.8  139.7  29,000  Yes 

Predicted 1‐hour Average ‘Maximum’ Ground Level Concentration – Power 

Station Option 2 Nitrogen

Dioxide (NO2) 38.7  24.3  190  Yes Carbon

Monoxide (CO)

148.7  137.0  29,000  Yes 

Predicted 1‐hour Average ‘Maximum’ Ground Level Concentration – 

Compressor Station ‐ Normal Operations Nitrogen

Dioxide (NO2) 64.7  25.5  190  Yes Carbon

Monoxide (CO)

224  145  29,000  Yes 

Compressor Station 

As for the Power Station, the EES assesses emissions of carbon monoxide 

(CO) and oxides of nitrogen (NOx). Ground‐level atmospheric concentrations 

of CO and NO2 were assessed against the air quality ‘design criteria’, sourced 

from the SEPP Air Quality Management.  The air impact assessment 

demonstrated that the ground level concentrations for all cases considered 

will comply with the relevant health‐based ambient air design criteria as 

indicated in Table 2 above. 

Page 89

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

A cumulative assessment of all sources (ie existing Otway, Minerva and Iona 

gas plants and the proposed compressor station) was also conducted for NO2 

concentrations, with the results demonstrating compliance with the design 

criteria (see below). 

Construction of the Power Station, Compressor Station, Recycled Water 

Treatment Plant the Gas and Water pipelines 

The EES indicates that it is possible that construction of the Power Station, 

compressor station, recycled water treatment plant and pipelines could result 

in fugitive dust emissions that could affect sensitive receptors, if dust control 

measures are not properly implemented. 

According to the EES and Mr Napier’s evidence, the Proponent and its 

contractors will base EMPs on the recommendations in EPA Victoria’s 

Environmental Guidelines for Major Construction Sites and the APIA 

Code of Environmental Practice. 

The Potential Impact of Air Emissions on Domestic Water Supplies 

PAEHolmes analysed the potential impact of air emissions on domestic 

water supplies.  Contamination of rain employed for human consumption 

with atmospheric pollutants can cause health problems – if the resultant 

concentrations in the collected water exceed relevant drinking water 

guidelines. 

The pollutants emitted with potential to impact drinking water quality are 

NOx which can react to form nitrite (NO2‐) and nitrate (NO3‐) in water.  The 

Australian Drinking Water Guidelines (ADWG 2004) are set by the National 

Health and Medical Research Council and are based on a maximum safe 

level of intake through ingestion of drinking water over a lifetime.  The 

detailed analysis undertaken in the EES (Appendix 12) concluded: 

that based on the conservative assumptions used in the assessment, the 

dissolution of NO and NO2 into dissolved phase nitrite and nitrate would 

result in levels that are orders (and in some cases many orders) of 

magnitude less than the levels in the Australian Drinking Water Guidelines 

(2004); and 

the emissions from the Power Station do not have the potential to cause 

rainwater contamination at any nearby residences. 

Recycled Water Treatment Plant 

The EES assessment of odour emissions from the proposed recycled water 

treatment plant to be constructed at the Port Fairy water reclamation plant 

concluded that: 

Page 90

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

the risk of increased odour emissions from the reverse osmosis facility 

impacting on nearby residents will be minimised by housing processes 

within the recycled water treatment plant building and by monitoring the 

treatment system; 

any odour from the exposed water surfaces in the RO plant will be 

minimal compared to the other odour sources in the plant; and 

air quality will be managed according to the SEPP AQM. 

There will be an extension to the existing buffer zone around the Port Fairy 

water reclamation plant to accommodate the addition of the recycled water 

treatment plant and reverse osmosis facility.  As a 300‐m buffer already 

encompasses most of this area, the total increase in buffer zone area around 

the site will be 3.88 ha to the north west of the site, a total increase in buffer 

area of 1%. 

6.2.3 Submissions - Air Emissions

The Morgan‐Paylers expressed concern about the increase in dangerous air 

emissions and requested that the Development Plan required under the 

SUZ2 should include a requirement to regularly monitor the air emissions 

and to provide air purification systems to the house situated on the land if 

necessary. 

The Proponent responded that the impact assessment modelling 

demonstrates compliance with the relevant ambient design criteria in SEPP 

AQM at all locations, including at the ‘Myndarra’ property (sensitive 

receptor #102), with the scale of the impacts indicating that ambient air 

monitoring is not required.  The modelling results are based on conservative 

assumptions with the highest of the resulting predictions at #102 being less 

than 16% of the ambient design criterion (29.7 μg/m3 of NO2 under start‐up 

conditions). 

Corangamite Shire noted that there is no reference to potential adverse air 

quality impacts other that during the construction stage.  The Shire stated 

that the figures for NO2 and CO emissions are based on the modelling of a 

certain type of power station to be built but this could change.  Council 

requested compliance with the relevant SEPP and on‐going EPA Licence 

compliance. 

The Proponent responded that operational air quality assessments were 

carried out and presented in the EES.  The expert evidence (well as the EES 

itself21) indicate that SEPP (AQM) will be complied with, and of course Shaw 

21 Pages 11-20

Page 91

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

River Power will need to comply with any Works Approval or Licence 

issued by EPA. 

The EPA written submission and Mr Frame’s verbal submission highlighted 

the following points: 

if a peaking power station (open cycle) is approved, the EPA has insisted 

that the energy be recovered from the fuel and the pollutants produced 

per unit of electricity (best practice) be minimised; the EPA has also 

requested that when a peaking station is operated for extended periods, 

consideration be given as to whether it is practicable to convert the 

peaking power station into a combined cycle power station; 

emissions of NOx are minimised from gas turbines by the application of 

NOx control technology and it has been usual to apply dry low NOx 

technology to large turbines.  It is understood that the turbines for the 

Power Station proposed have dry low NOx burners, but there may be a 

slight energy penalty with this technology; 

the turbine and compressor technologies proposed in the EES are 

generally considered to satisfy the ‘best practice’ test, but this would be 

confirmed when the actual equipment to be used is identified; 

modelling of the key air emissions has been undertaken using EPA’s 

approved model, Ausplume and applied according to the SEPP (AQM).  

The assumptions used in the modelling are conservative and include an 

appropriate estimate of emission rates based on a worst case scenario 

during normal operation; 

the modelling in the EES indicates that the air emissions will meet the 

design criteria of the SEPP (AQM) for both the Power Station and the 

compressor station; and 

for the Recycled Water Treatment Plant the most likely impact is odour 

and it is expected that there will be a minimal increase in odour. 

6.2.4 Discussion and Conclusions - Air Emissions

The Panel notes the EPA’s comments regarding open cycle plants not 

necessarily meeting best practice, but it is also noted that the project 

proposes staged implementation to meet market demand and the conversion 

from open cycle plant to closed cycle over time. 

The Panel accepts the EES assessment, the evidence and the EPA advice that: 

the turbine and compressor technologies proposed in the EES are 

generally considered to satisfy the ‘best practice’ test to be applied by 

EPA; 

the results of the air impact assessment of emissions from the operation of 

the Power Station and compressor station demonstrate that the ground 

Page 92

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

level concentrations for all cases considered will comply with the relevant 

health‐based ambient air design criteria in SEPP‐AQM; 

there will be a minimal increase in odour from the Recycled Water 

Treatment Plant; 

the emissions from the Power Station do not have the potential to cause 

rainwater contamination at any nearby residences; 

cumulative impacts at the sensitive receptors near the compressor station 

are dominated by the emissions from the existing adjacent sources 

(particularly from the Iona and Otway Gas Plants), but the resulting 

cumulative impacts are predicted to comply with relevant design criteria 

in the SEPP (AQM); and 

while there is a potential for cumulative effects in relation to air quality 

from the proposed Tarrone power station, it is likely that any increase 

will be small, and the resulting impacts will comply with the requirement 

of the SEPP (AQM). 

Dust from construction of the Power Station, compressor station, recycled 

water plant, gas pipeline and water pipelines can and should be managed 

through Construction EMPs based on the recommendations in EPA 

Victoria’s Environmental Guidelines for Major Construction Sites and the 

Australian Pipeline Industry Association Code of Environmental Practice. 

6.3 Safety

6.3.1 Regulatory and Policy Framework

The DPI submission noted that the construction and operation of the gas 

pipeline (including the compressor station) is regulated by the Pipelines Act 

2005, in conjunction with Energy Safe Victoria (ESV).  Ms Hendricks advised 

that ESV would be the authority responsible for reviewing and approving 

the safety aspects of the gas pipeline. 

Mr Power noted that consent is required under Occupational Health and Safety 

Act 2004.  Under the Act, Registration or a Licence to Operate a Major 

Hazard Facility must be obtained from the AEMO prior to operating the 

Power Station.  The Safety Case for the Power Station will be informed 

through the EES, and the development of appropriate training packages and 

implementation plans, including occupational health and safety management 

plans and emergency response plans. 

Page 93

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

6.3.2 EES Assessment - Safety

EES Appendix 22 presents the Preliminary Hazard and Risk Assessment for 

the Power Station and gas pipeline.  This study was to identify the nature 

and scale of hazards that might be present during the construction, 

operational life and decommissioning phase of the proposed power station, 

gas pipeline and compressor station.  The key hazards identified were: bush 

fires as a potential from a ruptured pipe, disruption of infrastructure during 

construction of the gas pipeline and traffic accidents due to the increased 

traffic volumes during construction. 

EES Appendix 38 presents the preliminary hazard analysis for the water 

pipelines and associated water infrastructure.  Key hazards identified 

included: chemical spills at the treatment plant, disruption of infrastructure 

during construction of the pipeline and water damage from a burst of the 

water mains. 

The EES advised that, as Shaw River Power is a wholly owned subsidiary of 

Santos, the Santos EHSMS 22 will be adopted as the basis for managing the 

construction and operation of the Power Station, gas pipeline and associated 

infrastructure.  The contracting strategy will require the major contractors for 

the project to maintain systems that reflect the requirements of the Santos 

EHSMS and that these requirements form part of the project EHSMS.  The 

environmental, health, safety and security systems of the major contractors 

will be audited prior to final contractor engagement. 

Wannon Water’s standards and procedures for environmental management 

will provide the framework for the management of the water pipelines and 

associated water infrastructure at Port Fairy.  The contractor appointed for 

the construction of the water pipelines and associated infrastructure will 

adopt Wannon Water’s standards, in addition to their own environmental 

management standards, to ensure a high level of environmental 

performance. 

From a legislative perspective safety aspects of the gas pipeline [and 

compressor station] are addressed in the Pipeline Regulations 2007 as 

summarized by Mr Power below: 

Before carrying out any pipeline operation (including the construction of 

the pipeline) licensees are required to provide a Safety Management Plan 

to Energy Safe Victoria23.  These plans must identify the public safety 

risks, specify what the licensee proposes to do to eliminate or minimise 

22 Attachment 5 to the EES 23 Section 126.

Page 94

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

those risks, and set out the matters specified in Part 6 of the Pipeline 

Regulations 2007. 

The pipeline operation cannot commence until the Safety Management 

Plan has been accepted by Energy Safe Victoria in writing.  Energy Safe 

Victoria must not do so unless it is satisfied that the licensee has, in 

preparing the plan, consulted any person who owns, occupies or manages 

the land on which the pipeline operation is to be carried out. 

These plans must be reviewed by the licensee every five years, and the 

outcome of the review must be reported to Energy Safe Victoria within 

28 days of completion of the review. 

It is a criminal offence to carry out a pipeline operation without an 

approved Safety Management Plan24 and for a licensee to breach the 

plan.25 

6.3.3 Submissions and Proponent Response

DPI submitted that the Construction EMP and Operations EMP should be 

used as the main regulatory documents to capture safety conditions for the 

gas pipeline.  The Proponent strongly supported this position. 

Corangamite Shire Council highlighted: 

the need for emergency management training for local SES/CFA and 

others involved in disaster planning and emergency response; and 

the potential impact of road closures during the declared Fire Danger 

Period may impact on the CFA’s operational response for incidents in the 

vicinity of construction work. 

Mr Guest of Moyne Shire advised of concerns in relation to emergency 

evacuation/response issues associated with a construction camp in the event 

of a bush fire. 

The CFA raised the issue of work permits associated with construction work 

on declared days of Total Fire Ban in its submission.  However the issue of 

training was not specifically raised, nor was emergency response issues 

associated with either the Power Station or a construction camp. 

The EES and Mr Napier acknowledged the need for further consultation with 

emergency service providers, including the Country Fire Authority (CFA) 

and SES, in the preparation of emergency response procedures, emergency 

management plans, and the identification of implications for upgraded 

24 Section 127. 25 Section 129.

Page 95

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

infrastructure or additional training.  The need to notify the CFA of any road 

closures during the Declared Fire Danger Period was also noted, together 

with the desirability of avoiding road closures on total fire ban days (where 

possible). 

6.3.4 Discussion

The Panel did not receive a submission from ESV and has therefore had to 

rely on the submissions from the Proponent and the DPI that ESV will ensure 

appropriate safety requirements etc for the gas pipeline and compressor 

station. 

The Panel noted that the preliminary HAZID analysis (Appendices 22 and 

38) identified that safety impacts could be appropriately managed through 

the development of Construction Safety Plans, and Construction and 

Operations EMPs.  However the Panel has some concerns related to the 

omission of discussion in the EES in relation to setback distances for future 

development along the gas pipeline.  The Panel further notes that Part 6 of 

the Pipeline Regulations specifically addresses requirements for Safety 

Management Plans. 

However while the Construction EMP and Operations EMP for the gas 

pipeline are required to be approved [and monitored] by DPI which has 

appropriate safety resources and experience, the Panel is concerned in 

relation to the specific expertise of the Moyne Shire to review and monitor 

the Construction EMP and Operations EMP for the Power Station.  During 

discussion at the hearing it was noted that the Power Station site is defined 

as a Major Hazard Facility and therefore the Safety Management Plan should 

be referred to WorkSafe Victoria for review and approval.  Clause 66.06 

would also require referral to WorkSafe Victoria for this type of proposal if 

an application for permit was required. 

The Panel notes that the proposed SUZ2 does not refer to a Safety 

Management Plan for the Power Station in either the Construction EMP or 

the Operations EMP.  The Panel considers that the SUZ 2 should explicitly 

require safety to be addressed in management plans and should provide for 

a formal review by the appropriate authority. 

The Panel heard from Mr Napier that the thickness of the wall of the gas 

pipeline is dependant on a variety of issues including the explosive impact 

distance of the pipeline to dwellings and other sensitive uses.  The Panel has 

not been able to identify how future dwelling construction in proximity to 

the pipeline will be regulated where development is allowed as‐of‐right 

under the planning scheme.  Further consideration is needed of design 

specifications and/or the need for an overlay to ensure safety risk is 

Page 96

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

considered and addressed before dwellings (or other sensitive uses) are built 

in the vicinity of the project.  The extent of such an overlay would be 

determined on the basis of risk and a consultative process would be 

necessary to allow those who may be affected to present their views. 

As the Power Station will be a Major Hazard Facility the Panel considers the 

Proponent should provide ongoing training for the CFA and SES to ensure 

that adequately trained personnel are available locally to assist in emergency 

situations. 

Recommendations 

Revise the proposed SUZ2 to require: 

the Construction EMP and Operations EMP for the Power Station to 

include a Safety Management Plan prepared by a suitably qualified 

person; and 

the responsible authority to have regard to the views of ESV, WorkSafe 

Victoria, the CFA and the SES on the Safety Management Plans. 

Ensure appropriate management of safety risks to future development 

associated with the project (Options to consider include both pipe 

thickness specification in areas with potential for future development and 

an overlay for land where risks associated with the proximity to the project 

either preclude development or require specific design measures). 

Ensure the Proponent provides ongoing training to both the CFA and SES 

to enable effective responses to potential emergency situations. 

Page 97

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

6.4 Landscape and Visual Amenity

6.4.1 EES Assessment and Evidence – Visual Impacts26

Jon Shinkfield, the primary author of the LVIA, appeared at the Hearing and 

his expert report responded to submissions that raised issues about visual 

impacts. 

The LVIA determined visual impacts by taking into account the degree of 

visual modification and the degree of viewer sensitivity.  Residential areas 

were deemed to have higher visual sensitivity, for example, than industrial 

areas largely because of the greater importance of visual amenity to the 

residents.  Despite a short duration of view, roads were also identified as 

potentially being of higher sensitivity as there may be large numbers of 

viewers. 

The Power Station 

The LVIA considered the visibility of the following Power Station elements: 

13 additional transmission line pylons with a nominal height 65 m above 

proposed finished surface levels; and 

three heat recovery steam generator stacks and three cladding boxes to air 

cooled condensers with respective nominal heights of 50 m and 32.9 m 

above the proposed concrete platform. 

 Figure 6  Power Station, Switchyard and Pylon Visualisation 

(Source: EES Appendix 15 Figure 1.6) 

26 EES Appendix 15 documents the methodology and findings of the Landscape and Visual Impact

Assessment (LVIA) for the Power Station, compressor station and gas pipeline. EES Appendix 34 addressed visual impacts from water infrastructure.

Page 98

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

The LVIA identified the following potential measures to mitigate visual 

impacts: appropriate lighting design; staging or construction method; 

materials and colour selection and buffer planting. 

The LVIA identified a large ‘Zone of Visual Influence’, particularly toward 

the southwest of the project site, from which the Power Station would 

theoretically be visible.  Seven photo simulations depicted the proposed 

development both before and approximately five years after planting to 

mitigate impacts.  Five of the viewpoints were along the Hamilton‐Port Fairy 

Road, one viewpoint was to the north from Woolsthorpe‐Heywood Road 

and one viewpoint was at the southern boundary of the Power Station site.  

The Panel directed that further simulations be prepared from nearby 

residential properties to address a gap in the analysis in the EES.  These 

additional simulations from receptors 89, 102, 109 showed the visual impacts 

before and after harvesting of plantations. 

Existing vegetation and topography partially screened views to the Power 

Station site from Viewpoints 1 and 4, while the plantations partially obscure 

elements of the Power Station in Viewpoints 2, 3, and 7.  Plantations on 

adjoining properties immediately to the north, south and west of the Power 

Station site, are due to be harvested.  The EES assessment from relevant 

viewpoints assuming that the plantations have been harvested indicated that 

impacts would increase from properties to the north and south (including 

Viewpoints 2, 3 and 5.). 

The LVIA identified: 

visual modification ranging from ‘None’ at Viewpoints 1 and 4, through 

to ‘High’ at Viewpoint 6; 

visual impact ranging from ‘Negligible’ at Viewpoints 1 and 4 through to 

moderate adverse at Viewpoints 3 and 6; and 

planting along the Power Station site boundary would reduce the 

residual visual impact level for Viewpoints 2, 3, 5 and 6 but the rating of 

the adverse impact at Viewpoint 7 would be unchanged (EES Table 6.1). 

The further simulations in Mr Shinkfield’s evidence from three residential 

receptors within 2km of the site illustrated: 

at the northern boundary of receptor 89 (the Morgan‐Payler property) the 

absence of visual impacts with the plantations in place but new impacts 

after harvesting; 

at receptor 109 an established hedge of medium height screens lower 

elements of the Power Station but additional pylons would be apparent.  

A greater proportion of pylons would be apparent after harvesting of 

Page 99

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

plantations.  Impacts would be greater for other properties with views in 

this sector without comparable established planting; and 

at receptor 89, plantations do not influence visual impacts and vegetation 

around the house appears to effectively screen views from that location. 

Development of the Power Station within the proposed SUZ2 is as of right 

but the Development Plan required must include: ‘Details of proposed 

landscaping, including such landscaping measures as appropriate both on the land 

and on surrounding land to screen views of the development from existing dwellings. 

The Strategic EMP (4.8 Aspect 8) refers to planting vegetation screening, 

consisting of mixed plants of local provenance including some fast growing 

species, within the Power Station and compressor station site, where 

appropriate.  It also refers to minimising disturbance to the landscape and 

rehabilitation to pre‐existing conditions, designing infrastructure and 

selecting materials to reduce glare, and adopting lighting strategies to 

minimise night time visual impacts. 

The Compressor Station & Pipelines 

The 2.4 ha compressor station site is on a localised high point within 

predominantly cleared agricultural land.  There are 14 sensitive receptors 

within 2 km of the compressor station that could theoretically have a view of 

the compressor station but the number is reduced if the screening effects of 

vegetation, structures, etc are taken into account. 

The LVIA assumed all of the compressor station elements will be less than 

3.5m in height except for the stacks (6‐7m high and 1.2m diameter) and the 

fire water tanks (nominal height 5.0 m).  The EES did not include any visual 

representations of the proposed compressor station.  The LVIA found the 

visibility of the compressor station would be restricted to higher elevations 

given the undulating nature of the surrounding area and the low height and 

size of the proposed structures.  The LVIA found ‘Views of the compressor 

station would be likely to remain as distant background from very few vantage points 

associated with residences.’  The majority of the gas and water pipelines 

alignments traverse highly disturbed landscapes of predominantly cleared 

farmland.  The EES acknowledged the short‐term visual impacts caused by 

the construction of the compressor station and pipelines.  However, 

rehabilitation works along the pipeline route are expected to result in 

negligible long term visual impacts from the pipeline. 

The management of visual impacts would be via the conditions and EMPs 

associated with the License under the Pipelines Act 2005 and the EPA Works 

Approval. 

Page 100

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

Port Fairy Recycled Water Treatment Plant 

The RWTP will be a single storey building located on the south side of the 

existing Wannon Water site in Port Fairy.  The EES (Appendix 34) indicated 

there will be no external activities associated with the operation of the plant 

and visual impacts are only associated with the structure.  As the proposed 

structures will be very similar to existing structures and existing vegetation 

is not proposed to be removed, visual simulations were not prepared.  The 

EES indicated that vegetation on the site to the north, east and west 

intercepts views from houses and nearby roads.  Works at the Port Fairy 

Water Treatment Plant will be within an existing building and will have no 

visual impact. 

The management of visual impacts for the water supply infrastructure would 

be via the Works approval. 

6.4.2 Submissions

The Morgan‐Paylers submitted that the Power Station constitutes a large and 

imposing industrial facility that is wholly out of keeping with the existing 

rural character of the area.  In addition to planting around the boundary of 

the Power Station site, they sought screen planting along the entire northern 

boundary and part of the western boundary of their property to mitigate the 

visual impacts on the property. 

The Shire of Moyne submission at the hearing indicated that, in addition to 

on site screening, it will require the Management Plans to provide for a post 

construction program whereby the applicants approach all landowners 

within approximately 5‐7 kilometres from the site to assess what measures 

can be undertaken to screen the proposal from that aspect.  This procedure 

has been used successfully at the Yambuk Wind Energy Facility and will take 

place for the Mortlake power station currently under construction. 

The Shire of Corangamite highlighted visual impacts of the introduction of 

the compressor station into a rural landscape and sought a commitment to 

implement EES recommendations relating to building materials. 

Page 101

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

6.4.3 Discussion and Conclusions

The Power Station 

The LVIA acknowledges that visual impact assessment involves firstly 

determining how a particular view would be affected and then making a 

judgement about the sensitivity of the landscape and its capacity to 

accommodate change.  Visual simulations illustrate impacts and are 

important in informing consultative processes and the exercise of that 

judgement.  As the LVIA states ‘The use of photo simulations plays an important 

part in visual impact assessments to convey the proposals to the assessors, decision 

makers and the local community.  A total of seven photo simulations have been 

prepared to explore and illustrate the likely effect of the scheme on particular views.’ 

The Panel has a number of concerns about the visual impact assessment and 

the EES assertion that the viewing points ‘were representative views.  The views 

selected within this analysis were chosen based upon the ZVI analysis, identification 

of sensitive receptors and on site observations and are likely to represent locations 

from which the proposed development will be most highly visible.’ 

The methodology concentrated on views from roads as they are accessible to 

the largest number of potential receptors in the broader community and to 

avoid private residences in order to eliminate the possibility of undue bias to 

suit only a small number of receptors.  This was despite the fact that all 

residential receptors were recognised as highly sensitive and the viewpoints 

were from roads with volumes of less than 600 vehicles per day.  Further, the 

locations selected for three of the seven simulations were almost certain to 

indicate a very limited impact.  The distance between the site and two of the 

viewpoints (3.9 and 4.9km) meant impacts were dismissed and views from a 

third view point (Orford Town Centre) were screened by buildings and 

vegetation. 

Nevertheless, the Panel is satisfied that the preparation and circulation of 

additional simulations from residential receptors remedied this limitation in 

the analysis. 

The Panel considers the LVIA understated the visual impacts. 

Unfortunately the Panel has no confidence that the simulations actually 

reflect the likely visual impacts from the project.  As the LVIA noted that 

‘many of the photomontage images presented in this report (refer to Appendix A) 

were taken during overcast weather conditions.  The low light levels of the base 

photography ‘darkens’ the foreground elements.  A stronger visual contrast between 

the existing foreground elements and the objects located on and along the horizon or 

Page 102

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

‘skyline’ therefore becomes more apparent.  The ‘sky’ then provides a background for 

the simulated objects (power and compressor station infrastructure).  The overall 

colour variation of the sky has been slightly altered to provide a more consistent 

background onto which the simulated elements can be assessed.’ 

The comparison during the site inspection of the representation of the 

existing conditions where pylons are visible with the actual perception of 

those views, made it clear that the pylons were much more prominent than 

represented.  This flaw appears to have been translated to the proposed 

elements of the Power Station in the simulations which show very limited 

contrast between the background and the Power Station infrastructure.  In 

addition, the foreground and middle views appear to be exaggerated, 

whereas in all cases the proposed power station components have receded to 

more distant components and are understated.  Our comparison of the 

Mortlake power station currently under construction also suggests that the 

representation of the presence of the Power Station may be understated. 

Mr Shinkfield’s responded to questions from the Panel that the use of a 

28mm lens camera meant that the more distant elements in the view receded.  

The Panel understands that similar concerns have been raised about 

photomontages prepared for some recent Wind Energy Facility proposals. 

The Panel also questions the LVIA judgment that ‘Given the existing visibility 

of the OHTL pylons, potential visibility of the new switchyard infrastructure and 

additional OHTL pylons, and likely screening of the main built form, the proposed 

development is seen as an intensification of the existing landscape character.’  The 

existing powerline does currently have some presence in this rural setting 

but the extent of the infrastructure proposed goes well beyond the current 

intrusion. 

Importantly, the timber plantations to the north, west and south of Site are 

due to be harvested.  The LVIA discussion recognised that visibility and 

impacts from many views will increase when the screening provided by the 

plantations is removed. 

The Panel is of the view that the Power Station will be prominent in the rural 

landscape in the locality, particularly after harvesting of timber plantations 

adjoining the Site.  However, no one has suggested that these impacts 

outweigh the benefits to the broader community from the project and, 

provided appropriate measures to mitigate visual impacts are adopted, this 

should not be fatal to the project.  Major infrastructure projects invariably 

have significant visual impacts but in this case those impacts have been 

minimised by selecting a site in an area with a dispersed settlement pattern 

that is not recognised as a significant landscape.  The influence of plantations 

on the views from roads and the closest houses also means that existing 

Page 103

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

views comprise relatively contained landscapes in some instances (as in the 

case of the Morgan‐Paylers’ property) and/or the relevant view sector 

affected by the project is already modified to screen views to the wider 

landscape. 

The proposed planting around the Power Station perimeter will be a 

significant mitigation measure in reducing short range views and the Panel 

also endorses the use of low reflective materials of muted tones.  In addition, 

the Panel considers that off‐site mitigation of visual impacts should be 

provided on nearby properties.  Indeed the schedule to the proposed SUZ2 

specifically contemplates that off‐site planting to screen the Power Station 

may be required. 

While the visual impacts associated with the Power Station will differ from 

WEFs27, the Panel agrees with Council that the principles established for the 

mitigation of visual impacts from WEFs provide a useful approach that 

should be adopted here.  Key principles that should be adopted include: 

The focus on the mitigation of visual impacts is from dwellings to protect 

the area used most intensively for leisure and recreation, rather than the 

farming workplaces.  This includes the dwelling used as a Bed and 

Breakfast at the Morgan‐ Paylers’ property but the Panel does not support 

their submissions that landscaping should be provided along their 

property boundaries.  Planting close to this most sensitive location will 

intercept the views more effectively than more remote planting along the 

farm boundary.  Of course, they have the option of undertaking planting 

themselves to ensure the screening currently provided by the plantation 

is maintained. 

In addition to on‐site planting, within 6 months after the Development 

Plans are endorsed, owners of properties within 3 km of the Power 

Station site should be offered screen planting around the curtilage of 

existing dwellings on a voluntary basis.  This should include 

consideration of the size of plantings (ie a mix of advanced trees and tube 

stock should be options), the inclusion of species with rapid growth rates; 

consideration of whether the age and health of current vegetation 

supports a need for reinforcement planting; responsibility and timeframe 

for maintenance (at least 2 years); and any implications for existing native 

vegetation.  Offers should remain open to residents for up to 12 months 

after Stage 1 of the Power Station is commissioned. 

27 For example, the much larger footprint of WEFs means the turbines may affect much wider

sectors of views, wind turbines are much higher and the movement of blades attracts viewers but the Power Station is a much bulkier structure (equivalent to 10 storeys).

Page 104

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

The scope of off‐site mitigation should be foreshadowed in the schedule to 

the SUZ2. 

The Panel notes that a number of properties that currently do not have 

dwellings would be exposed to views of the Power Station.  However, the 

future development of those properties would allow siting and orientation of 

house and their gardens to ‘design out’ unwanted views to the Power 

Station. 

The Compressor Station and Pipelines 

Given the site’s remote location, the low height of compressor station 

structures which will not break the horizon line and the proposed screen 

planting around the perimeter of the compressor station, the Panel agrees 

with Mr Shinkfield that few receptors would have any view of the facility 

once the perimeter planting has matured.  The Panel expects long‐term 

visual impacts to be largely eliminated through the implementation of 

commitments to develop screen planting around the compressor station and 

use materials with low‐glare properties in colours and textures to blend with 

the surrounding landscape28.  These commitments should be incorporated in 

subsequent approvals. 

As noted in Chapters 3 and 4, the Panel is satisfied there has been significant 

effort to avoid and minimise vegetation losses and to minimise disturbance 

where pipelines cross water courses.  The Panel has also emphasised the 

importance of effective rehabilitation of the pipeline route after construction 

in Chapter 4.  In addition to achieving biodiversity and operational 

objectives, these design and management measures also substantially reduce 

the long term visual impact along the pipeline routes. 

The Panel accepts that the visual impacts associated with the gas and water 

pipelines are largely temporary changes during the construction phase, such 

as the presence of construction machinery and stockpiled spoil.  The 

transient nature of these impacts reduces the significance of the impact. 

Port Fairy Recycled Water Treatment Plant 

The Panel is satisfied from the EES assessment and its own site inspections 

that the visual impacts from development of water infrastructure in Port 

Fairy will not be significant.  The use of the site for this function is 

established and recognised by the zoning of the land and the Shire of Moyne 

advised that further industrial development in the locality has been 

foreshadowed and endorsed by the Priority Development Panel.  The 

28 See EES Attachment 4 Commitments 59 and 61.

Page 105

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

proposed development maintains a compact footprint and will be consistent 

with the existing built form and scale of structures on the site.  The proposed 

works are separated and screened from sensitive viewpoints from roads and 

houses. 

Panel Recommendations 

Amend the Schedule 2 to SUZ Development Plan provisions to include an 

‘Off‐site Landscaping Plan’ to mitigate the visual impact of the Power 

Station from all dwellings within 3km of the Power Station site.  Where an 

offer is accepted, the plan should: 

be prepared by the relevant landowner or the proponent; 

incorporate the species to be used, timetable, and maintenance 

arrangements; 

be implemented within 12 months of the endorsement (unless 

otherwise agreed between the landowner and the Proponent); and 

specify that all costs for design, implementation and maintenance are to 

be the full the responsibility of the Proponent or operator. 

6.5 Lighting

6.5.1 EES Assessment - Lighting

To minimise the impacts of night‐time lighting on residents and motorists, 

the EES commitments29 include the use of: passive means of lighting (eg 

reflector roadway markers, lines, warnings or information signs) and 

directional lighting mounted no higher than 6 m from the ground.  The 

proposed SUZ2 requires lighting to be addressed in the EMPs. 

6.5.2 Submissions

The Shire of Corangamite submitted that impacts on the dark rural landscape 

at night should be minimised by ensuring manual operation of compressor 

station night lighting on an as required basis. 

29 See EES Attachment 4 Commitment 60.

Page 106

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

6.5.3 Discussion and Conclusions

While night lighting would be an addition to the night sky view, there would 

be relatively few night time viewers due to the low density of population and 

low usage of the local road network.  Given the separation of the project 

elements from sensitive receptors, adverse impacts from lighting on the 

amenity enjoyed by nearby residents would be limited. 

The Panel agrees with the Shire of Corangamite that lighting should be the 

minimum required to meet safety objectives and operational requirements 

for areas that are actually in use.  The commitments made in the EES are 

endorsed but in addition, specific consideration should be given to the use of 

sensor activated lighting and baffling of lights to direct lighting downward 

to the intended location and to avoid light spill above the horizontal.  The 

Panel considers that Schedule 2 to the SUZ, the works approval and licence 

under the Pipelines Act should require this approach to be adopted in 

subsequent approval processes. 

Panel Recommendation 

Ensure that, in addition to commitments in the EES, lighting: 

is the minimum required for access and safe operation of parts of 

the facility that are actually in use; 

incorporates sensor activation; and 

is baffled to avoid light spill above the horizontal. 

Page 107

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

7. Disruption of Existing Land Uses, Infrastructure, Traffic And Local Communities

EES Evaluation Objective: To minimise the disruption of existing land uses, 

infrastructure, traffic and local communities, including in relation to the availability 

of housing and the potential need to upgrade infrastructure. 

7.1 Land Use Disruption

7.1.1 EES Assessment- Land Use Disruption

The table below presents the EES summary of the potential disruption of 

land use and associated mitigation measures (other than due to traffic 

management impacts discussed separately). 

Potential Impact Mitigation Measures

. Acquisition of agricultural land for the Power Station, gas pipeline and compressor and water pipeline.

. Potential impact on use of land within the easements for the gas pipeline and water pipeline.

. Spread of weeds during construction and reinstatement of pipeline corridor.

. Restriction of uses within the pipeline easements.

. Ensure access is maintained in the vicinity of construction works.

. Progressive reinstatement of land affected by the pipeline construction.

. Ongoing communication and consultation with affected property owners, including provision of information on the reinstatement of land following construction and restrictions on the use of land within the pipeline easement.

. Implementation of environmental management measures during construction to control the spread of weeds.

. Compensation to property owners in accordance with the relevant legislation.

The Proponent advised that the proposed Farm Management Agreement 

attached to the Option Agreements with landowners along the gas pipeline 

route sets out: 

the pipeline construction  methodology on the property to allow farming 

operations to continue with as little impact as possible; 

agreement to re‐pasture following completion of the works; and 

rights to compensation which take into account  ‘Farm Management 

Compensation’ for the costs of: lost productive capacity; increases in farm 

management time; extraordinary disturbance such as dust or noise near 

the homestead, difficulties with access to the property; temporary 

Page 108

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

severing of telephone lines; unexpected stock loss; and re‐seeding and 

rehabilitation costs. 

7.1.2 Discussion and Conclusions – Land Use Disruption

The Panel recognises that construction activities inevitably involve some 

disruption.  That disruption can be significant, albeit transient, for 

development of substantial scale over an extended period and for linear 

infrastructure projects that affect extensive areas. 

The established regulatory framework and the EES acknowledge impacts on 

construction sites and the Panel emphasises that it is vital that, in addition to 

the compensation to be provided to landowners, a conscientious approach is 

adopted to minimising disruption and mitigating impacts.  The Panel notes 

that it is in both the landowners’ and the Proponents’ interests to minimise 

disruption and maximise co‐operation.  The material presented in the EES, 

the credibility of the evidence presented that the Proponent intends to 

maintain constructive working arrangements with landowners, notably by 

Mr Napier, and the fact that only one landowner made an objecting 

submission, provide a level of confidence that the level of disruption will be 

minimised. 

The ongoing disruption due to the project is addressed in other chapters, 

particularly with regard to noise and traffic impacts (see Chapters 6 and 7.2).  

The Panel has concluded that these potential impacts are capable of effective 

management.  The Panel has found that the Power Station will impact on the 

visual amenity of the locality and this is particularly relevant to amenity 

dependant uses such as existing houses and the Morgan‐Paylers’ Bed and 

breakfast after plantations are harvested.  Nevertheless, the Panel considers 

that the mitigation measures proposed provide an acceptable outcome. 

7.2 Traffic Management

7.2.1 EES Assessment and Evidence – Traffic Management

Traffic issues for the two alternative development scenarios for the Power 

Station are discussed in Appendices 16 and 17 of the EES.  The traffic aspects 

reviewed included an assessment of the road network capacity and 

capabilities together with various traffic scenarios related to both 

construction and operation, including access for over‐dimensional loads.  

The Panel noted that the impact on the local road network will be minimised 

as the proposed access routes to the Power Station are all via main roads 

(apart from Riordans Road, which is proposed to be upgraded). 

Page 109

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

Following the preparation of the EES, further investigations were undertaken 

to consider a possible location of the Power Station construction camp and 

also, in response to queries from the Panel, the suitability of alternate routes 

for over‐dimensional vehicles travelling to the Power Station site from 

Portland.  An alternative development scenario for the construction of the 

Power Station was also assessed and was discussed in Mr Carter’s expert 

witness statement and presentation. 

During the Panel hearing specific issues were raised by both the Panel and 

the Morgan–Payler Family in relation to access to the Power Station site 

using an alternative route along McGraths Road, in preference to Riordans 

Road.  Mr Carter and Mr Organ advised of their traffic and flora and fauna 

concerns in relation to the alternative route30.  Mr Carter advised that the 

length of road required to be upgraded would be increased and would 

provide a less satisfactory vehicle access route than Riordans Road.  Mr 

Organ’s written response concluded that the alternative access route has the 

potential to impact a greater area of remnant native vegetation and a larger 

number of threatened species, compared with the proposed access route.  Mr 

Power on behalf of the Proponent confirmed that it is the Proponent’s 

intention to use Riordans Road as the primary access route to the Power 

Station and if established, the Construction Camp. 

Mr Carter advised that the Hamilton Port Fairy Road currently has the 

highest of Vic Roads service level during peak hour and noted that during 

the construction of the Power Station this would only be reduced to level B 

[the second highest level]; even if all construction staff were to travel to the 

site by light vehicle. 

There was some discussion in relation to the detailed requirements for the 

upgrade of the Hamilton‐ Port Fairy Road / Riordans Road intersection.  Mr 

Carter advised that the design requirements would be dependant on where 

the construction camp and concrete batching plant were situated in relation 

to the Power Station and provided the design requirements for the worst 

case.31 

30   Letter [P28] dated 16 June 2010 from Mr Carter addressing traffic issues and letter [P29] 

dated 16 June from Mr Organ addressing flora and fauna issues. 31   Based on the Austroads guidelines, the design requirements for Hamilton–Port  Fairy 

Road/Riordans Road/Smyths Road intersection layout would include: (the Panel has 

chosen to highlight only the following point): 

• Provision of a 3.5 m wide right turn lane in accordance with a Type AUR (Auxiliary 

right turn lane) treatment on the south approach to the intersection.  The length of the 

auxiliary widening is 60 m with a 60 m long taper, providing adequate length for 

deceleration prior to the storage of a B double to waiting for an appropriate gap in 

traffic to turn.

Page 110

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

In summary the key likely impacts identified by Mr Carter during the 

construction and operation phases of the Power Station, gas pipeline and 

water pipelines are: 

a minimal reduction of the level of service of the Hamilton‐Port Fairy 

Road during the peak construction period of the Power Station.  It was 

noted that the increased traffic is well within the capacity of the regional 

road network and would amount to less than 5% of the Hamilton‐ Port 

Fairy Roads capacity; 

a requirement to upgrade the Hamilton‐Port Fairy Road/Riordans Road 

intersection to VicRoads requirements; 

upgrading and possible minor realignment of Riordans Road from the  

intersection to the entrance of the Power Station, and possibly further to 

the east if a construction camp is constructed on the Shaw River Power 

land east of Old Dunmore Road; 

the provision and enforcement of Traffic Management Plan(s) approved 

by Moyne and Corangamite Shires, to minimise the impacts on the local 

road network as the Power Station, gas pipeline, possibly a construction 

camp and water pipelines are constructed; 

the provision and enforcement of a Traffic Management Plan approved 

by Moyne Shire to minimise usage by workers vehicles of other roads 

adjacent to the Power Station site during the operation of the Power 

Station; 

the use of horizontal boring or HDD for crossing all sealed roads, where 

practical, with open trenching an option for unsealed roads; and 

upgrading of Smokey Point Road from Langleys Road, to provide all 

weather access.  It was noted from Mr Napier’s presentation and the site 

inspection that the upgrade is proposed to minimise the impacts on the 

flora and fauna in the road reserve along Smokey Point Road. 

7.2.2 Submissions and Proponent Response

Submissions were received from the Morgan‐Payler family in relation to the 

usage of roads adjacent to their property, the CFA in relation to road closures 

during the declared Fire Danger Period and Corangamite and Moyne Shires 

in relation to a variety of road infrastructure and traffic issues. 

In addressing the Morgan – Payler Family concerns Mr Carter advised that 

while traffic will need to use McGraths Road as part of the construction of 

the gas pipeline, Shaw River Power has advised that access to the gas 

pipeline from McGraths Road will only require use for approximately 5 

weeks.  Measures will be taken to limit the use of McGraths Road by power 

Page 111

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

station construction or operation traffic as part of the Traffic Management 

Plan. 

In relation to the various concerns raised by both Moyne and Corangamite 

Shires Mr Carter indicated that the Shires’ concerns can be addressed in the 

Traffic Management Plan which is to be prepared by the Proponent and 

approved by the Shires prior to the commencement of construction. 

Concerns were raised by the Moyne and Corangamite Shires in relation to 

the use of regional roads by over‐dimensional vehicles during the 

construction of the compressor station and power station.  Mr Carter advised 

that the movement of over‐dimensional loads will be subject to the policies, 

guidelines and approvals process outlined by VicRoads as outlined in the 

EES.  The routes for the movement of over‐dimensional loads will form part 

of the Traffic Management Plan and will be provided to VicRoads and the 

Shires (where utilising roads for which the Shire is the responsible authority) 

for comment and approval. 

Mr Carter advised that consultation and communication with all emergency 

services, including the Country Fire Authority, will form part of the Traffic 

Management Plan.  It is not anticipated that full road closures will be 

required for pipeline road crossings.  However, if temporary road closures 

are required, measures such as detours, rapid trench backfill and steel plate 

crossing would be defined in the Traffic Management Plan.  The Traffic 

Management Plan will include key project contact numbers in the event of 

emergency. 

7.2.3 Discussion and Conclusions – Traffic Management

The Panel accepts the evidence from the Proponents traffic expert that traffic 

issues related to the project are not significant in terms of the capacity of the 

existing road infrastructure.  It is appropriate that the routes adopted 

maximise the use of main roads and minimise the demands placed on the 

local road network.  The Panel is also satisfied that traffic management issues 

have been adequately reviewed and issues raised by the various submitters 

can be resolved, primarily by the preparation of the Traffic Management 

Plan(s) which will require the Proponent to satisfactorily address the 

concerns of the shires (which include those of the Morgan–Payler Family). 

The Panel accepts that the traffic volume along the Hamilton–Port Fairy 

Road is low and acknowledges that the Proponent has undertaken to 

upgrade the intersection, including a right turn lane but remains concerned 

in relation to the requirement for two B Doubles to undertake a greater than 

900 left turn from Riordans Road onto the 100 kmh Hamilton – Port Fairy 

Road each day and the potential for the slowly accelerating fully laden 

Page 112

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

vehicles to cause other vehicles to break heavily or to overtake as the truck 

accelerates.  The Panel considers that the provision o f a left turn acceleration 

lane on the Hamilton–Port Fairy Road should be considered.  The Panel 

acknowledges that the provision of an acceleration lane will likely result in 

the loss of additional native flora [including Swamp flax Lily] however the 

Panel remains concerned with the safety aspects and highlights the issue for 

resolution from VicRoads, which is the authority responsible for this road. 

The Panel noted the Shire’s concerns in relation to the time required for them 

to be able to adequately review the Traffic Management Plan and the 

Proponents advice that it would make all endeavours to provide the traffic 

management plan to the shires at least three months prior to the 

commencement of construction. 

The Proponent has not committed to providing a sealed upgrade to Riordans 

Road despite the much greater use of this road both during construction and 

operations by both light and heavy vehicles (including two B Double vehicles 

each day).  The Panel notes the traffic experts’ advice that the upgrading of 

this road would provide a higher degree of safety, reduced maintenance 

requirements and a reduced potential for dust.  The Panel is also concerned 

that the provision of an unsealed road to any proposed construction camp in 

the vicinity of the Power Station would not be of a suitable safety standard. 

The Panel notes that SUZ2 specifies rates of parking provisions and that 

parking requirements at the Power Station will be addressed as part of 

detailed design.  However the Panel is cognisant of the need to ensure that 

there is adequate parking area for the increased numbers of vehicles likely 

during both the construction and the maintenance periods.  Provision for 

parking of construction and maintenance worker vehicles should be 

addressed in the Development Plan and the Construction EMP’s. 

As the location of the concrete batching plant was not identified in the EES 

the traffic impacts were assessed in general, however when the site is 

identified the Proponent will need to include a review of potential impacts in 

the Traffic Management Plan. 

Based on the evidence of Ms Sommerville, Mr Carter and Mr Napier the 

Panel acknowledges that significant portions of the construction work force 

are likely to be accommodated in Warrnambool and Port Fairy and possibly 

Mortlake and that the provision of a bus service for the construction work 

force would reduce traffic impacts both on the regional and local road 

networks and also the parking requirements on the Power Station site.  The 

Panel considers that the provision of the bus service at the cost of the 

Proponent would assist in promoting the major urban areas for 

accommodation in comparison to other areas. 

Page 113

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

Recommendations 

Review the design of the intersection of Riordans Hamilton–Port Fairy 

Roads consultation with VicRoads with a view to providing an 

acceleration lane for fully laden B Double trucks turning left from 

Riordans Road onto the Hamilton – Port Fairy Road. 

Provide a sealed upgrade of Riordans Road from the Hamilton – Port Fairy 

Road intersection to: 

the entrance of the Power Station before development starts, and 

internally for all roads regularly used by B double vehicles; and 

the entrance of the camp before development starts, if a construction 

camp is proposed in the vicinity of the Power Station. 

Provide a free bus service, at the cost of the Proponent, for construction 

workers from locations identified in the accommodation strategy (eg 

Warrnambool, Port Fairy and Mortlake) to the Power Station for the 

duration of construction. 

Review and address potential impacts of the concrete batching plant in the 

Traffic Management Plan. 

7.3 Disruption of Infrastructure

7.3.1 EES Assessment - Disruption of Infrastructure

The EES has identified a number of areas where existing infrastructure will 

or might be disrupted.  These are primarily related to the construction of the 

pipelines and are typically at road crossings where existing services are to be 

crossed.  The Panel noted that the Proponent proposes to use horizontal 

boring or HDD under sealed roads and open trenching as an option for 

unsealed roads, this will assist in minimising the disruption of existing 

services and minimise the disruption to local traffic on the roads.  

Disruptions to farm operation will occur as the pipeline spread moves along 

the pipe route.  The disruption will be for a short period of time. 

It is anticipated that Riordans Road will have to be temporarily closed or 

restricted to enable the upgrade of the road to the Power Station entrance, 

and possibly to the construction camp.  However as there are other routes 

locally available the inconvenience is anticipated to be minimal and for a 

short duration. 

A services identification and impact assessment was undertaken for the 

water pipelines and is proposed to be undertaken for the gas pipeline once 

the route is finalised and prior to the commencement of design. 

Page 114

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

7.3.2 Submissions and Proponent Response

Submissions from Corangamite and Moyne Shires raised issues of road 

interruptions due to traffic increases and also of road degradation due to the 

increased numbers of heavy vehicles.  Mr Carter acknowledged both issues 

but confirmed that the existing capacity of the road network was well in 

excess of the proposed temporary increased volumes and that as part of the 

Traffic Management Plan the Proponent, in coordination with the shires, 

would undertake condition surveys of proposed heavily trafficked roads 

before and after construction and that the Traffic Management Plan would 

include reinstatement obligations. 

Mr Guest on behalf of the Moyne Shire noted that the Proponent does not 

propose to source fill material external to the site and that in the case of the 

Mortlake Power Station this involved 20,000 truck movements from a quarry 

to the site.  Mr Napier confirmed that the Proponent was proposing to obtain 

fill material from onsite which would assist in minimising traffic impacts 

during the early part of construction. 

7.3.3 Discussion and Conclusions

The only other impacts identified by the Panel were temporary impacts as 

the start up power supply to the Power Station site is established, and 

potentially cut in disruptions at the Wannon Water water treatment and 

recycled water treatment plants at commissioning of new works. 

The Panel is satisfied that given the undertakings provided in the EES and at 

the Hearing that the interruption to existing infrastructure will be minimised 

and can be adequately monitored by the relevant authorities. 

Page 115

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

8. Socio- Economic Implications

The EES Socio‐economic Impact Assessment (SIA)32 provided an overview of 

the area’s existing demography, employment, business and industry, social 

infrastructure and ‘community values’.  In this chapter the focus is on the 

project implications for employment opportunities, accommodation and 

community and emergency services.  Other potential impacts relating to 

matters such as amenity and traffic management are addressed in other 

chapters dealing specifically with those issues.  Evidence from Nicole 

Sommerville summarised the EES analysis and findings and responded to 

submissions that raised issues about socio‐economic impacts. 

8.1 Economic and Employment Impacts

8.1.1 EES Assessment and Evidence - Economic and Employment Impacts

The EES indicates that the project has the potential to induce an economic 

impact nationally in the order of $2.18 billion (direct and indirect) during the 

construction phase33 but the induced impact on the southwest Victoria region 

will be substantially less.  Local businesses will supply goods and services to 

the project, such as catering/ food services, transportation, sub‐contract 

construction skills, accommodation, and personal services.  Increased activity 

in the regions economy will also support economies of scale in regional 

purchasing, the development of new supply markets, extended access to 

goods and services and increased employment opportunities. 

During construction the project is expected to generate an average of about 

400 direct jobs (360 for Option 2), with about 30% of workers sourced locally.  

The direct additional spend in the region would be $20.7 million if it is 

assumed that 50% of the approximately $41.3 million construction workforce 

wages are spent in the region.  The permanent operational workforce (see 

below) would result in a total ongoing spend in the region by the Stage 1 

workforce of about $2.73 million annually34. 

Stage Option 1 Option 2

1 30 day/20 night 4-6 day/2-4 at night

2 40 day/28 at night 40 day/28 at night

3 50 day/35 at night 50 day/35 at night

32 The EES SIA is set out in Chapters 5.4 and 11.6 and in Appendices 18 and 19. 33 ABS National Multipliers indicate multipliers of 2.67 for direct spending in the construction and

0.974 for spending in the electricity supply sector during operation of the Project. 34 Assuming an average weekly pay rate of $1,500 per worker, of which 70% is spent within the

region, approximately $54,600 per worker is expected to be spent in the region per annum.

Page 116

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

Increased shortages of skilled labour in the region in some industries are 

expected during the project construction phase, with the potential to either 

increase the cost of those services or the difficulty in accessing them.  The 

EES suggests that appropriate skilling and employment programs prior to 

construction and sourcing labour from towns such as Portland35 could 

enhance the extent to which the regional community captures the potential 

benefits and avoids adverse impacts associated with an influx of workers. 

In addition to significant economic benefits to the local community, the 

increased economic activity places additional demands, with associated 

economic costs, on a range of services and infrastructure, particularly during 

the construction phase.  Productivity losses may result from increased travel 

times for passengers and freight and the greater use of roads may increase 

road maintenance and vehicle operating costs.  The potential for economic 

impacts from less tangible impacts, such as increased driver stress and losses 

in amenity for properties adjacent to major construction transport routes, 

was also identified.  The EES assessment does not quantify these costs but 

they are not expected to be significant.  The EES suggested that these impacts 

could be mitigated through effective traffic management planning (See 

Chapter 7.2). 

8.1.2 Submissions

The Shire of Moyne advised that the direct employment generated during 

the construction of the smaller Mortlake gas fired power station peaked at 

approximately 450 employees and this was around 70 more than was 

predicted in the project planning phase.  The Shire is preparing a social and 

economic impact assessment of the Mortlake project which draws on a 

survey of workers on site during March 2010 (70 survey responses).  

Preliminary survey results indicate that most workers (93%) come from out 

of the region with only 7% come from Moyne and Corangamite Shires.  

Moyne Shire is currently working with Origin and Bilfinger Berger Services 

to gather information on local business engagement in the project.  However, 

preliminary analysis suggests that the benefits from the Mortlake project 

have been more in terms of value adding to the local community rather than 

in direct employment.  Most businesses in the Mortlake township have 

experienced increased levels of business as a result of the project, particularly 

cafes and hotels, fuel outlets, the newsagency and other retailers.  Businesses 

in Terang and Camperdown have also reported increased trade due to some 

workers utilising motel accommodation on a short term basis. 

35 Portland was identified as having a pool of skilled workers who had recently experienced job

losses.

Page 117

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

The Shire of Moyne supports the project and the associated economic 

stimulus to the region but noted that, while not a reason to refuse 

infrastructure proposals, it is conscious that businesses will need to adjust to 

lower levels of activity after projects have been completed.  Concern was also 

expressed by Corangamite Shire that there could be longer term impacts that 

could seriously impair the appeal of the locality to tourists if temporary use 

of tourist accommodation to house workers results in prospective tourists 

being frustrated when places to stay are not available.  This is believed to 

have impacted on Port Campbell during the gas plant construction. 

8.1.3 Discussion

The EES provided a broad brush analysis of economic implications of the 

project and the extent of local expenditure and, as suggested by preliminary 

data collected by the Shire of Moyne relating to the Mortlake project, the 

generic assumptions made in the SIA analysis may understate the overall 

level of employment generated and the extent to which labour is imported 

from outside the region. 

It is clear, however, that a project of this scale will inject substantial stimulus 

into the region’s economy that far outweighs the loss of 110 ha of grazing 

land from production.  The Panel accepts that approval of the project is 

supported by the substantial benefits to local businesses and those seeking 

employment, particularly during the construction phase but also extending 

at a lower level to the longer term operation (including major maintenance 

cycles). 

The Panel endorses the EES view that, in order to maximise benefits for the 

local community and minimise adverse economic impacts, project 

development should incorporate early consultation with local schools, TAFE 

and employment providers to plan for the expansion of employment and 

training programs to incorporate technical skills training directly associated 

with project needs.  The Mortlake project should provide useful insights into 

labour market (and other) requirements that should be incorporated in 

further project planning processes.  The Panel understands that 

infrastructure programs often promote the use of local goods and service 

providers through early consultation with local businesses organisations, 

registers of businesses expressing interest in supplying goods or services, 

and promoting the use of local businesses by primary contractors.  This 

project also provides opportunities for ‘local engagement’ initiatives. 

Page 118

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

8.2 Community Services, Housing and Construction Camp(s)

8.2.1 EES Assessment and Evidence - Community Services and Housing

The SIA and Ms Sommerville’s evidence indicated that: 

the majority of workers who relocate with their families (assumed to be 

approximately 20% of workers) are expected to live in Warrnambool, but 

towns such as Port Fairy, Koroit, Port Campbell and Hamilton would also 

be likely to attract workers; 

depending on the extent of construction worker sharing of housing, 

estimates of additional dwelling requirements ranged between average 

requirements of 110 to 250 and peak requirements between 170 to 425 

dwellings; 

there is a shortage of rental housing in the study area, which has resulted 

in high rental costs in some towns.  The SIA survey of real estate agents 

indicated further upward pressure on rental prices is anticipated as 

vacancy rates are expected to remain low.  This would particularly impact 

on access to affordable rental housing; and 

the use of tourist accommodation could ease pressure on rental 

accommodation with benefits for proprietors but the ability to meet peak 

tourist demand would need to be carefully managed to avoid longer‐term 

impacts on the tourism sector. 

Measures identified to mitigate impacts on affordable housing included 

maximising the employment of people who already living in the area, 

encouraging workers to live in a number of towns across the area by 

providing a bus service to the construction site and promoting sharing of 

accommodation. 

Construction Camps 

The Works Approval application suggested that ‘It is anticipated that 

construction workers will be housed in existing accommodation in nearby towns and 

settlements.  The need for a construction camp to house the construction workforce 

has not been established.  The decision regarding accommodation of the construction 

workforce will be the responsibility of the engineer‐procure‐construct contractor, 

once appointed to the Project’36. 

However, the SIA and Ms Sommerville’s evidence indicated that: 

36 See section 3.5 of the Works Approval Application

Page 119

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

the need for a construction camp should be determined by the Proponent 

during the detailed planning phase of the project, having regard to other 

projects either under construction or planned in the area and the 

availability of suitable accommodation at that time; 

a camp at the Power Station site (on the eastern side of Old Dunmore 

Road) would avoid the need for workers to travel and reduce traffic on 

local roads; 

services such as recreation, first aid, dining, etc. would be provided at the 

construction camp; and 

management of resident behaviour at the construction camp would avoid 

potential impacts on the nearby area and communities.  These typically 

include matters such as such as drug and alcohol management, security 

and safety, camp access and hours of movement outside of the camp, 

access for non‐camp residents, noise management and worker health. 

Ms Sommerville suggested that construction camps would need to be 

consistent with the planning scheme and the location of would be 

determined in consultation with local Councils and landowners.  She 

expected that, if a separate construction camp is established for gas pipeline 

workers, it is likely to be located mid‐way along the pipeline (near 

Warrnambool).  Her evidence statement provided a rural Queensland 

example of a construction camp. 

Community Services and Infrastructure 

The SIA anticipates that schools, hospitals and emergency services in the area 

have sufficient capacity to cater for the expected influx of population 

(approximately 490 workers and their families) during the construction 

phase but the existing difficulty in meeting the demand for child care places 

and medical services, particularly general practitioners and dental care, 

could be exacerbated.  Increased demand for these services could impact on 

levels of service and waiting times.  It also suggests that the workers and 

their families may also support the viability of some sporting and recreation 

clubs and facilities but there was some concern that the need to upgrade 

some facilities would be reinforced. 

The measures to mitigate impacts on community services recommended in 

the SIA and Ms Sommerville’s evidence focussed on ‘early and ongoing 

consultation’ with the various service providers to allow them to take the 

influx of population into account in their planning and operations.  The 

providers identified include the Department of Education and Early 

Childhood Development, Department of Human Services, local schools, local 

hospitals and emergency services, housing support agencies, Victoria Police, 

Page 120

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

Rural Ambulance Service, Country Fire Authority and State Emergency 

Services, child care and school bus operators. 

8.2.2 Submissions

The Shire of Corangamite raised the potential for negative social implications 

of housing such a large number of workers in an isolated location without 

social and community services.  It suggested construction camps should be in 

towns on appropriately zoned land rather than along the pipeline route to 

minimise adverse social impacts and potentially benefit the local community.  

At the hearing, Council highlighted the potential for facilities such as 

Brucknell Park Scout Camp and caravan parks, which have significant spare 

capacity outside of the peak holiday periods, with a complementary 

potential role for Glenormiston College in meeting temporary 

accommodation at peak times.  The Shire submitted that past experience of 

deferring planning and responsibility to the project contractor for projects 

such as the gas plants illustrated the need for much earlier planning. 

The Shire of Moyne is concerned about the possible impact of this project on 

the availability and cost of housing in the region.  The Mortlake power 

station worker survey responses to date37  indicate that, of 65 non‐local 

respondents: 

49% lived in Warrnambool; 29% in Mortlake and the remaining 22% lived 

in Port Fairy, Terang, Camperdown, and the rural area surrounding 

Mortlake; and 

56% were living in a shared house, 21% were the sole occupant of a 

house, 21% lived in a flat or apartment and 2% lived in caravan parks, 

cabins, bed and breakfast accommodation, pubs and private board. 

The Shire advised that anecdotal feedback from real estate agents, a regional 

supported accommodation advisory committee, local people, and workers 

suggests that the influx of Mortlake Power Station construction workers has 

contributed substantially to increased rental prices, and to a reduction in the 

availability of rental properties in Mortlake and Warrnambool.  It is 

Council’s understanding that very few construction workers at the Mortlake 

Power Station workers relocated their families to the region. 

Mr Power emphasised that, while the Proponent has a role in analysing 

potential social impacts associated with the project, responsibility for broader 

37 There were 70 responses to a survey of workers on the Mortlake gas fired power station

construction site during March 2010. Council is awaiting more completed surveys to gain a stronger indication of worker origin and accommodation patterns.

Page 121

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

strategic planning or for the provision of housing and community services  

rests with others, particularly State and local government. 

8.2.3 Discussion

The SIA recognised that the project would create challenges in meeting the 

additional demand generated for housing and a range of community services 

but provided only a broad overview of the existing supply of housing and 

reference to consultation with service providers.  Unfortunately the SIA did 

not specifically addressed whether there are towns experiencing decline with 

spare infrastructure capacity to accommodate additional population; 

whether it would be better to direct the additional population to 

Warrnambool; or whether a construction camp (discussed further below) 

provides a model that effectively addresses needs.  The Mortlake power 

station, which was under construction at time the SIA and accommodation 

surveys were done, provides a local example of a directly comparable 

infrastructure project, albeit at a smaller scale.  However, there appears to 

have been no attempt in the SIA to document the actual impacts and learn 

from the experience gained through that project.  Such an analysis could 

have provided insights about how the housing market and community 

services have responded. 

The development of potential mitigation measures was also limited and 

largely comprised recommendations for ‘early and ongoing consultation’.  

The SIA provides limited progress towards more specific documentation of 

where capacity exists in particular services or analysis of where it may be 

most appropriate to augment services. 

The following view expressed by the Panel considering the Mortlake  power 

station also applies in this case ‘the survey data in this respect fell well short of 

providing convincing evidence that accommodation needs would be satisfactorily met 

without significant impacts on the local accommodation markets.’  The Mortlake 

EES Inquiry Panel recommended that the adoption of the associated 

Amendment should be subject to a Section 173 agreement under the Planning 

and Environment Act 1987 relating to the ‘Early conduct of an accommodation and 

community services strategy for the Project’.  Unfortunately this 

recommendation was not implemented, apparently due to concern that there 

was insufficient lead time available for effective outcomes. 

The work now being undertaken by the Shire of Moyne is a positive initiative 

and should inform the development of strategic planning responses for the 

housing and service requirements generated by a major infrastructure 

project(s). 

Page 122

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

This Panel considers there continues to be a clear need for more rigorous 

planning to achieve more effective responses to the demands for housing and 

community services associated with this (and other) major infrastructure 

proposals.  The proposed SUZ2 requires a housing and community services 

strategy before development commences.  The sooner this work commences 

the better as delay leads to more and more constraints on realisable 

responses.  Therefore a formal commitment to undertake or contribute to this 

work linked to approval of Amendment C36 is preferable to the proposed 

SUZ requirements for the issue to be addressed at a later stage within the 

Construction EMP. 

The Panel agrees with submissions for the Proponent that it cannot be 

burdened with responsibility for the provision of services but the input of 

information and a contribution towards the funding of a co‐ordinated 

regional response to the provision of housing and community services is 

justified.  The Panel is of the firm view that this work should not be delayed.  

Rather than relating requirements to the commencement of the project, as 

proposed in exhibited documents, approval of Amendment C36 should be 

subject to a firm commitment to undertake or contribute to this work. 

Construction Camp(s) 

DPI advised that a construction camp for workers constructing the pipeline 

is deemed to form part of the pipeline and therefore planning scheme 

provisions would not apply.  However, it is noted that the application for the 

licence under the Pipelines Act made no reference to a construction camp. 

Amendment C36 would, subject to approval of specified plans by the 

responsible authority, enable as of right development of a construction camp 

on the Power Station site (under SUZ2) and on land owned by the Proponent 

to the east of Old Dunmore Road (under Clause 52.03). 

SUZ2 specifies for the Power Station site that: 

The Construction EMP must address: 

Accommodation and community services, including but not limited to: 

−  A strategy to manage the accommodation needs of the workforce 

−  Identification of measures to minimise adverse impacts on the delivery 

of social and community services to the broader community 

Specifies the Operations EMP must address: 

Protocols and procedures to ensure that surrounding amenity levels are 

not adversely affected by activities and noise generated by persons resident 

in the workers construction camp. 

Page 123

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

The proposed incorporated document associated with Clause 52.03 would 

also require a development plan and an operations plan (to be approved by 

the responsible authority) for a construction camp on the land to the east of 

Old Dunmore Road. 

The EES did not suggest that a construction camp would necessarily be 

required but proceeded on the basis that the option of a temporary 

construction camp should be available to the construction contractor.  The 

proposed SUZ2 seems to envisage that the justification for the construction 

camp will be provided via a housing and community services strategy after 

approval of the planning framework via Amendment C36 but prior to the 

commencement of development. 

The EES provided virtually no information about or assessment of the 

impacts of a construction camp and the Amendment C36 specified only very 

generic requirements for a development plan. 

Ms Sommerville’s evidence did address the potential form and management 

of camps, however, citing an example from outback Queensland.  

Construction camps may be the only accommodation option in areas that are 

very remote from established settlements but it is the Panel’s view that this is 

not the case here. 

Ms Sommerville’s evidence highlighted potential benefits associated with the 

reduced need for workers to travel but she eventually acknowledged at the 

hearing that accommodation in towns normally represents a more desirable 

outcome.  The Panel agrees with Corangamite Shire that accommodating 

workers in towns is preferable to the establishing an enclave of workers in a 

construction camp(s) that is isolated from urban services, to minimise 

management demands and the potential amenity impacts on Orford. 

It seems likely that various forms of housing will be required to meet 

workers’ needs.  Tourism accommodation and caravan parks in off‐peak 

periods, holiday homes, scout camps, and Glenormiston College may all 

form part of the accommodation mix.  The ongoing construction activity on a 

range of infrastructure projects, may also provide the basis for investment in 

additional rental housing, possibly managed by a housing association, which 

would create a long term legacy for the region.  These options should be 

actively pursued. 

The Panel recognises that the provision of some accommodation in the form 

of a construction camp may prove to be necessary but, like the Shire of 

Moyne, considers a large construction camp that may be used for a number 

of years warrants more careful attention than a short term camp.  As the 

Shire of Moyne highlighted, the siting of the construction camp anywhere 

Page 124

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

but adjoining the Hamilton‐Port Fairy Road will impact greatly on road 

infrastructure, and a camp on the land east of Old Dunmore Road would 

require  significant upgrading of access to cater for the increased traffic.  The 

EES traffic assessment was on the basis that workers would be 

accommodated in towns with bus services provided for workers. 

The Panel does not think that the strategic justification for as of right 

construction camps as proposed under Amendment C36 has been 

established.  However, it does support establishing discretion for Council to 

consider the merits of a construction camp on the Power Station site and 

Santos land to the east of Old Dunmore Road if other options prove to be 

insufficient.  This is a pragmatic response that would: 

maintain some incentive to pursue alternative housing strategies; 

recognise that a construction camp may need to form part of the housing 

strategy if other options prove to be inadequate; and 

provides third party rights to those who may be affected. 

Nor does the Panel consider sound justification has been established yet for a 

construction camp to service the gas pipeline workers.  However, if this 

option is pursued despite the Panel’s reservations about the need and 

desirability of establishing a construction camp for pipeline workers, the 

Panel considers that DPI should consult the Shire of Corangamite about the 

location and conditions that should apply. 

Recommendations 

Require the Proponent to enter into a Section 173 agreement before 

Amendment C36 is approved to the satisfaction of the DPCD and the 

planning authorities to ensure early conduct of an accommodation and 

community services strategy for the project. 

The Proponent actively pursue the option of providing accommodation 

for power station and gas pipeline construction workers in towns or 

other existing facilities. 

Revise the Schedule 2 to the SUZ and the Clause 52.03 incorporated 

document to require a permit for a temporary construction camp. 

DPI consult with the Shire of Corangamite about the location and 

conditions that should apply if, despite this Panel’s recommendations, 

a construction camp is proposed along the gas pipeline route for 

construction workers. 

Page 125

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

9. Other Matters

9.1 Decommissioning

9.1.1 EES Assessment - Decommissioning

The EES (Chapter 7.5) indicates that the project has a design life of at least 25 

years and the relevant authorities will be consulted and a decommissioning 

plan will be developed to rehabilitate the sites to meet all regulatory and 

environmental requirements applicable at that time.  The plan will set out 

procedures and measures for the: 

removal or retention of buildings, plant, equipment and infrastructure; 

rehabilitation of disturbed areas to a standard suitable for agreed future 

uses; and 

identification and management measures for known contaminated areas. 

The EES notes (section 8.4) that ‘The gas pipeline will be decommissioned in 

accordance with the requirements of the Pipelines Regulations 2007, Australian 

Standards AS 2885: 2008, Pipelines ‐ gas and liquid petroleum and the APIA Code 

of Environmental Practice ‐ Onshore Pipelines (APIA, 2009) at a minimum, or the 

prevailing decommissioning standards in place at that time.  Potential methods of 

decommissioning include suspension, abandonment and removal of the pipeline.’ 

9.1.2 Submissions

The Proponent and the Shire of Moyne did not see any necessity to address 

decommissioning of the Power Station via the planning process.  The Shire of 

Moyne noted that the planning scheme provides for the Mortlake power 

station site to revert to its previous zoning, five years after the Power Station 

has ceases operation. 

9.1.3 Discussion

Division 3 of the Pipelines Act 2005 establishes the legislative framework for 

rehabilitation after decommissioning of the gas pipeline (including the 

decompression station). 

Despite an apparently high level of comfort amongst all parties to the EES 

process regarding decommissioning of the project, the Panel is conscious that 

there may be few obvious options for reuse of the Power Station and, given 

the scale of the facility, decommissioning could involve substantial costs, 

technical capacity requirements and logistical demands.  The Panel considers 

Page 126

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

there should be an assurance that the visual impacts from the Power Station 

will be removed when it no longer creates a benefit to the community.  While 

in principle the Panel considers that commitments relating to 

decommissioning under the relevant approvals should be ‘backed up’ by a 

bond to assure the community that rehabilitation will occur, it is conscious 

that the necessary administrative framework may not be in place and the 

development of such a framework would require detailed consideration (see 

discussion in Chapter 13.3 of the Panel Report relating to the Lal Lal Wind 

Energy Facility February 2009). 

Recommendation 

Include requirements relating to decommissioning of the project in 

relevant project approvals. 

Apply a sunset provision to the SUZ2 to revive the previous Farming Zone 

if the Power Station use does not operate for a nominated time (say five 

years). 

Evaluate the merits of requiring a bond to guarantee site rehabilitation 

after decommissioning of project infrastructure. 

9.2 Batching Plant

The Proponent responded to queries from the Panel that the location of a 

batching plant for construction of the project will be determined by the 

principal construction contractor.  It could be located at the quarry, at the 

Power Station site, or somewhere between.  A review of potential batching 

plant locations and access routes by the Proponent concluded that in all 

instances, aggregate or concrete would be transported to the proposed power 

station site from a route relying on Hamilton–Port Fairy Road as the 

principal means of access.  Therefore assumptions adopted in the EES, and 

by Arup in its traffic assessment, therefore reflect reasonable worst‐case 

scenarios for traffic distribution. 

Page 127

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

10. Cumulative Impacts

Within 30km of the site the following energy projects are operating or at 

various stages of the planning process: 

Codrington Wind energy facility  and Yambuk Wind energy facility 

(operating); 

Ryan Corner Wind energy facility, Macarthur Wind energy facility, 

Hawkesdale Wind energy facility, Woolsthorpe Wind energy facility 

(planning permit granted); and 

Tarrone gas fired power station (determination under Environment 

Effects Act but applications not yet submitted). 

Council also advised there have been preliminary discussions regarding a 

geothermal project at Warrong and further potential wind energy projects at 

Orford (between the proposed Shaw River and Tarrone power stations), 

Warndoo and Penshurst. 

Extensive areas of timber plantation are also due to be harvested. 

10.1.1 EES Assessment and Evidence

The issue of cumulative impacts of this and other proposals in the locality 

was not included in the scoping requirements and was not addressed in the 

EES. 

At the directions hearing the Panel requested that submissions address the 

cumulative impacts of proposed energy facilities and timber production in 

the area on roads and bridges, visual and acoustic amenity, biodiversity 

values, water supply, labour supply, the supply of accommodation and 

social infrastructure and services. 

Although it was emphasised by the Proponent that it does not have access to 

comprehensive information, cumulative impacts from the project with others 

in the area were addressed in expert statements as follows: 

Traffic: Mr Carter undertook further assessment of traffic impacts having 

regard to the traffic impact assessments for the Shaw River Water 

Pipeline, Tarrone Gas Fired Power Station and Ryan Corner Wind energy 

facility38.  He concluded that the available information indicates that the 

38 Shaw River Water Pipeline Traffic Impact Assessment report (GHD August 2009), Tarrone Gas

Fired Power Station and Gas Pipeline (Environment Effects Referral Form, 8 December 2009) and Ryan Corner Wind energy facility (Ryan Corner Wind Farm Environment Effects Inquiry, March 2008).

Page 128

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

cumulative traffic impacts of the multiple projects will be minor when 

compared to the theoretical capacity of the road network.  He noted that 

‘if it is assumed that the Ryan Corner Wind Farm construction will coincide 

with both the combined peak for the Power Station and water pipeline 

construction, the traffic volume on Hamilton‐Port Fairy Road may increase to 

approximately 930 vehicle trips per day.  Again, this is less than 7% of the 

theoretical capacity of Hamilton‐Port Fairy Road.’ 

Noise: Mr Turnbull addressed the combined noise from operation of both 

the project and the proposed Tarrone Lane project (approximately 6km to 

the east).  He predicted that the contribution of noise from the project will 

be less than 24 dB(A) under worst case conditions at the mid‐point 

between the two power stations (approximately 3km from each).  As this 

is at least 10 dB(A) below the criterion, addition of the noise from the two 

power stations will not create any potential for the criterion to be 

exceeded.  That is, contributions of 34 dB(A) and less than 24 dB(A) from 

noise sources combine to a total noise level of 34 dB(A). 

Air Quality near the Power Station:  Dr Ross’s statement referred to an 

EES referral document39 for the Tarrone Power Station which modelled 

cumulative air emissions from the proposed Shaw River and Tarrone 

power stations using the CALPUFF modelling system and found the 

maximum concentrations predicted were below the SEPP (AQM) design 

criteria for all modelled scenarios.  While Dr Ross noted he did not have 

the information necessary to validate that modelling, he considered that 

the assumptions adopted by URS were overly conservative.  Mr Ross 

conducted preliminary testing of the potential for cumulative impacts 

using the Ausplume model which confirmed that any increase in NOx at 

ground level would be small40 and the resulting impacts would comply 

with the requirement of the SEPP (AQM). 

Air Quality near the Compressor station:  Dr Ross analysed the 

cumulative air quality impacts arising from the compressor station and 

the existing adjacent sources – the Iona Gas Plant, Otway Gas Plant and 

Minerva Gas (EES Appendix 11).  He found the predicted impacts at the 

sensitive receptors are dominated by emissions from the existing adjacent 

sources (particularly from the Iona and Otway Gas Plants), the proposed 

compressor station results in only a negligible change, and the cumulative 

impacts predicted comply with relevant design criteria in the SEPP AQM.  

This outcome is due to the impacts arising from the emissions from the 

39 Local Air Quality and Greenhouse Gas – Tarrone Power Station. Report to AGL Energy Ltd.

URS Reference 43283491/AQ/05. October 2009. 40 The maximum increase in the NO2 ground level concentration around the Shaw River PS is

approximately 1 μg/m3. The only sensitive receptor around the Shaw River PS with any predicted increase as a result of the Tarrone PS is #106 to the west (with an increase of approximately 1 μg/m3).

Page 129

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

compressor station being small under the meteorological conditions that 

lead to the highest impacts from the gas plants and, conversely, the 

meteorological conditions under which the compressor station impacts 

are largest are typically not those under which the impacts from the 

existing sources are largest. 

10.1.2 Submissions

The written submission from Ms Nicholls, who is a long term resident of 

Orford living within 3 km of the Site,  expressed concern about the lack of 

evaluation of the cumulative impacts of the project, timber plantation 

harvesting and other major energy infrastructure projects proposed in the 

area.  She considers the impacts from traffic, pollution, loss of native flora 

and fauna and demands of housing and social infrastructure were 

understated in the EES as the combined effects of multiple projects were not 

addressed. 

The Shire of Moyne highlighted that the 500kV line to Portland, which passes 

through the Site, is a critical element of state infrastructure and a key 

criterion in terms of location and overall feasibility of current and proposed 

energy projects in the region.  While Council does not take issue with the 

connection of either the Mortlake or Shaw River Power Stations to the grid, it 

submitted that planning for future above ground significant power line 

connections for other major uses, namely wind energy facilities, is needed.  

Council also emphasised the importance of traffic management measures to 

avoid potential adverse impacts associated with multiple projects. 

Mr Power and DPCD both referred to the guidance on the issue in the 

Ministerial guidelines for assessments under the Environment Effects Act 1978 

which state: 

While cumulative effects may be a relevant consideration for the 

assessment of a project, a proponent may not have a practical ability to 

provide such an assessment, for example, because of their limited access to 

information on the effects of other existing activities or potential projects.  

Similarly, the ability of a proponent to provide a regional perspective in an 

EES will depend on the availability – usually from government agencies – 

of relevant regional policies, plans, strategies, as well as regional data. 

A proponent will at least need to provide an assessment of relevant effects 

(e.g. on landscape values, risks to fauna or emissions to air) in a form that 

can be integrated with information relating to other projects or activities, 

and thus enable the Minister to assess the potential cumulative effects……. 

Because of the factors constraining quantitative assessment of cumulative 

effects, often only a qualitative assessment will be practicable. 

Page 130

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

Mr Power submitted it would be preferable for Government to provide a 

policy structure and coordinate responses to potential cumulative impacts. 

10.1.3 Discussion and Conclusions

The Panel agrees with Ms Nichols that it is important that cumulative 

impacts of the major infrastructure projects in the immediate area and the 

region are assessed and measures to minimise adverse outcomes are 

identified.  Indeed, State planning policy (Clause 11.03‐7) recognises the need 

for co‐ordinated planning and decision making to achieve sustainable 

development and effective and efficient use of resources where economic, 

social or environmental impacts extend beyond municipal boundaries. 

The Panel recognises that the EES scoping did not specifically require 

cumulative impacts to be addressed, the EES guidelines acknowledge that 

there are constraints on the Proponents’ capacity to determine the nature of 

impacts, and it is likely that many of the responses to cumulative impacts 

will be beyond the influence of individual applicants.  Nevertheless, there is 

an expectation in the guidelines that cumulative impacts will be assessed to 

the extent reasonably possible and the information that is in the public 

domain should inform such an assessment.  It is a weakness in the EES 

Assessment that this has not occurred and this limits the Panel’s capacity to 

draw conclusions about cumulative impacts.  In particular the Panel was 

disappointed that the EES and Panel Hearing process had not adequately 

addressed: 

potential accommodation impacts and potential practical solutions; 

future cumulative regional visual impact of power stations, wind farms 

and overhead transmission line connections to the 500kV grid; and 

the potential for water pipelines to be used for supply other uses, such as 

the proposed Tarrone Power Station to the north east of the Shaw River 

Power Station and for other users along the route. 

The evidence presented to the Inquiry provided comfort that, having regard 

to other projects in the immediate area, the noise and air quality impacts due 

to the Power Station should be acceptable.  Further assessment of noise, 

visual and other impacts would clearly be required if the potential Wind 

Energy Facility to the east of the project is pursued. 

The traffic evidence confirmed that, on available information, there is 

significant capacity in the existing arterial road network in the immediate 

vicinity of the Shaw River and from Tarrone Power Stations and Ryans 

Corner Wind Energy Facility.  The potential for cumulative impacts will need 

to be reassessed as more certainty becomes available on the timing, traffic 

volumes and traffic routes of the various projects.  The Panel is satisfied that 

Page 131

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

the proposed traffic management plans can address the implications of 

multiple projects and the local road network issues raised by Council but 

considers that the SUZ2 EMP provisions should specifically highlight the 

issue as a matter to be addressed. 

The Panel noted the presence of a quarry approximately 15 km south east of 

the Power Station site, and Mr Guest of Moyne Shires statement that the 

provision of a bridge upgrade and 8 km of road upgrade would reduce the 

current travel distance to the site from 40 km.  The Panel is concerned that 

the potential development of the Tarrone Power Station  will result in a 

similar 40 km travel requirement and recommends that Moyne Shire works 

in collaboration with both Shaw River Power and Tarrone Power Station 

proponents to identify if the upgrade of the shorter connecting road  could 

be feasibly undertaken jointly. 

The Panel also notes that there is potential for the water pipelines to be used 

for supply to the proposed Tarrone Power Station to the north east of the 

Shaw River Power Station and for other users along the route.  The Panel 

considers Wannon Water should further investigate the potential for the 

pipelines to be upgraded to meet the needs of the Tarrone Power Station, 

should that project proceed. 

In Chapter 6.2, it is acknowledged that the project has minimised and 

avoided native vegetation losses and it is proposed to offset the losses that 

cannot be avoided.  Nevertheless, the cumulative effect of relatively small 

incremental losses of native vegetation is noted, and DSE is encouraged to 

monitor cumulative losses and offset obligations through its data bases and 

to take a proactive strategic approach to the identification of consolidated 

offset opportunities, potentially in conjunction with the Trust for Nature and 

Bushbroker programs. 

Despite the apparently low risk of impacts on Southern Bent‐wing bats a 

preliminary monitoring program has been developed by DSE (in 

consultation with the Proponent) and is endorsed by the Panel.  Whereas 

adverse impacts on Brolgas have been a prominent concern in a number of 

WEF proposals, the material presented to the Panel did not establish 

concerns about significant residual ecological impacts from the project that 

would compound impacts from other projects in the locality. 

The visual impacts from the extensive areas in western Victoria affected by 

energy generation infrastructure proposals are increasingly raised in 

objections to WEF applications.  The EES and evidence to the Inquiry did not 

address this issue.  The proposed power station at Orford will have a 

significant presence (see Chapter 6.4) but it is located in an area with a low 

density of houses and, compared to WEFs, the smaller foot print and height 

Page 132

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

of the Power Station confines the visual impacts to a more limited area.  The 

Panel has concluded that the adverse visual impacts from the project are 

acceptable but the cumulative visual impacts will require consideration as 

further projects are assessed.  It is noted that there may be potential for 

strategic off‐site landscaping to mitigate the cumulative visual impacts from 

multiple projects.  For example, roadside planting could be an effective 

means of reducing visual impacts (and could also secure biodiversity 

benefits). 

The 500kV grid is critical infrastructure for energy projects and a number of 

energy generation projects have been attracted to locations along the 

transmission line corridor.  At a strategic planning level, the Panel sees merit 

in anticipating the various implications of continued demand for 

development in proximity to the 500kV power transmission line and gas 

pipelines. 

As noted in Chapter 8.1, the project is also expected to place significant 

demands on the labour market, housing and community services and both 

the benefits and demands would be compounded by concurrent construction 

of multiple projects. 

It is noted that DSE has already established a dedicated officer to ensure 

effective responses to major infrastructure projects.  After the hearing the 

Shire of Moyne forwarded a copy of a letter from the Minister for Planning 

(dated 10 June 2010) which responded to Municipal Association of Victoria’s 

proposal for a ‘partnership approach’ to the planning and development of 

Wind Energy facilities in Victoria.  In that letter the Minister supported the 

allocation of resources for regional co‐ordination and a dedicated wind farm 

project manager  and the development a regional‐scale dataset for South 

West Victoria to assist in the assessment of cumulative effects of wind energy 

facilities. 

In addition to project based consultative processes as initiated by the Shire of 

Moyne, the Panel sees strategic planning and co‐ordination of regulatory 

processes on a sub‐regional level as important to achieve optimum outcomes 

from the very substantial investment in the energy sector anticipated for the 

region.  The Panel considers the scope of initiatives being considered at a 

state level should extend to other major energy projects.  DPCD would 

appear to be the appropriate agency to lead such a process involve the range 

of stakeholders including local government, public and private 

service/infrastructure providers, project proponents, representatives of 

business organisations, and members of the community affected by 

infrastructure projects.  The Panel emphasises, however, that a pragmatic 

approach with a strong focus on specific outcomes that can be realised within 

Page 133

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

the lead time of the projects will be vital.  This is likely to involve identifying 

‘the low hanging fruit’ and measures that can be readily employed rather 

than exhaustive analysis and consultative processes. 

Recommendations 

Develop a strategy for and implement specific measures to ensure effective 

responses to the cumulative impacts of major energy projects in the 

regions (Note: DPCD is suggested as the appropriate agency to lead such a 

process). 

Include cumulative impacts in the scoping requirements for future EES 

assessments or matters to be addressed in application documentation for 

future major infrastructure projects. 

Require the Proponent (and proponents for future infrastructure projects) 

to enter into a Section 173 agreement to the satisfaction of the DPCD and 

the relevant planning authorities to contribute to the cost of planning for 

and developing co‐ordinated responses to the various major infrastructure 

projects in the region. 

Evaluate the merits of upgrading roads to provide better connections 

between the Shaw River and Tarrone power station sites with the quarry 

to the south east, and, if substantial benefits are identified, the appropriate 

basis for contributions to such works. 

Wannon Water investigate the potential to upgrade the capacity of the 

water supply mains to the Power Station to meet the needs of the proposed 

Tarrone Power Station and other users along the pipeline route. 

Page 134

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

11. Framework for Managing Environmental Effects and Risks

EES Evaluation Objective: To provide a transparent framework with clear 

accountability for managing environmental effects and risks associated with the 

project to achieve acceptable outcomes. 

11.1 Certainty, Community Consultation and Accountability

11.1.1 Certainty

The appropriate balance between certainty and flexibility provided by the 

planning framework is a perennial issue of concern to both proponents and 

those who are directly affected by proposals.  On the one hand the proponent 

seeks an efficient approvals process with assurances about the basis for 

approvals but with a level of flexibility to respond to issues that may arise as 

designs develop.  On the other hand, others who may be directly affected 

generally seek certainty that their interests will be protected and that the 

basis for the EES submissions and assessment is not compromised by 

subsequent changes. 

The proposed regulatory framework (ie planning scheme, EPA works 

approvals and licences, pipeline license) prescribes requirements or 

performance expectations in relation to: 

air and water quality (via SEPPs); and 

SUZ2 specifies the following matters, all of which can be varied with the 

approval of the responsible Authority: 

a maximum building footprint and overall height via the SUZ2 

development plan requirements ‐ 45 hectares (including the switch 

yard area but excluding the area used for accommodation, outdoor car 

parking and landscaping) and a maximum overall height of 50 metres 

above ground level; 

the Hamilton – Port Fairy and Riordans Road intersection is to be 

upgraded to the satisfaction of VicRoads and the responsible 

authority; and 

provision of 50 staff car parking spaces and 5 visitor car parking 

spaces (Operations EMP). 

Page 135

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

Otherwise, the framework proposed specifies the scope of matters to be 

addressed in subsequent planning approvals or licenses but does not address 

the nature of responses that are expected. 

As the submission on behalf of the Morgan‐Paylers emphasised, the EES 

process constitutes the only opportunity for third parties to voice their 

concerns about potential amenity impacts, to ensure that appropriate 

mechanisms and safeguards are in place to adequately mitigate impacts on 

the locality, and to secure rights in relation top enforcement if breaches of 

obligations occur.  It was submitted that the basic parameters for EMPs 

should be established in the regulatory framework. 

Mr Chessell argued that the SUZ2 does not provide sufficient assurance of 

compliance with appropriate noise criteria.  He argued that without an 

effective monitoring regime specified in the Schedule third parties would 

have little opportunity to pursue meaningful enforcement proceedings in the 

event that the facility fails to comply with the terms of the Construction EMP 

and Operations EMP.  Mr Chessell submitted that the SUZ2 should specify 

an EMP requirement to comply with the noise limits specified in the EPA 

Interim Guidelines. 

The Panel is concerned that the EPA does not intend to specify noise limits at 

the nearest residence in the Works Approval.  During questioning Mr Napier 

advised that the Power Station would be constructed as a ‘turn key’ contract 

which would include a noise limit requirement as part of the contract 

conditions.  If there is no limit specified by the EPA then there is a reduced 

incentive to ensure that the Proponent makes all appropriate efforts to 

minimise the impact of noise on the adjacent properties. 

Mr Power strongly opposed specifying noise limits in the SUZ.  He 

submitted that it is not common practice to specify noise performance 

standards in the planning scheme and referred to a general principle 

expressed by VCAT in Australia Pty Ltd and PWM (Lyndhurst) Pty Ltd v 

Greater Dandenong CC (the Sita decision) that planning permits should not 

duplicate matters more appropriately regulated via licenses and works 

approvals administered by the EPA, which is the pre‐eminent expert body in 

relation to controlling pollution.  The decision adopted the view that 

conditions in planning permits should not seek to control the same matters 

that are controlled by an EPA license or works approval,  although a 

planning permit condition requiring compliance with a license or works 

approval was seen as acceptable.  The reason for this approach was the fixed 

nature of planning permit conditions compared to EPA license conditions 

which are continually upgraded to reflect improvements to environmental 

best practice and changes in government policy.  The decision emphasised 

Page 136

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

that it is in the community’s best interests that current best practice is 

observed when dealing with potentially polluting uses. 

The Panel notes that the Sita decision related to a permit and associated 

conditions, rather than establishing the planning framework parameters 

under which, for example, it is determined when a use should be as of right 

or when third party rights should apply.  The Panel also notes that the EPA 

has no statutory power to licence noise. 

It is usual in Planning Schemes to adopt the noise criteria specified in 

nominated EPA Guidelines.  For example, SPPF Clause 15.09 and 

Corangamite SUZs for Gas Processing Plant refer to compliance with the 

Interim Guidelines.  However, the criteria supported in this instance 

represent a departure from the standards referred to in SPPF Clause 15.09.  

Further, the EES assessment of the Power Station and the endorsement of the 

use being as of right had regard to the compliance with various development 

parameters, including the noise levels that would be experience by sensitive 

uses. 

It is our opinion that the neighbours are entitled to an assurance of the noise 

limit that will apply to the project and these third parties should have an 

avenue to enforce the noise limits.  Reliance only on the EPA Works 

Approval does not provide that right and the EPA does not ‘license’ noise 

emissions.  Similarly, the Proponent should be provided with a clearly 

defined and acceptable noise level for both design and operation.  The Panel 

considers noise limits should be specified as requirements for the Operations 

EMP in Schedule 2 to the SUZ.  The works approval for the project should 

also specify the maximum noise criteria to be satisfied. 

The Panel also notes comments of the Panel that considered the Mortlake 

Power Station EES which are also relevant to the current EES: 

The Panel is concerned in particular that some of the ‘mitigation’ measures 

that the Proponent is suggesting will be put in place do not neatly fit 

within the legal ambit of some of the other regulatory mechanisms.  Also 

some of the subsequent approvals will not take place for a number of years 

and the Proponent has indicated that the responsibility for seeking the 

subsequent secondary authorisations may fall to contractors or indeed sub‐

contractors.  Also relevant is the fact that the EES assessment processes do 

not treat a proposed project as a finite  ‘application’ in the same way that 

planning permit processes do.  Accordingly there is no certainty that a 

project which might gain Panel support will remain the same (including in 

terms of detailed processes and procedures and mitigation commitments) 

through subsequent approvals processes. 

Page 137

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

Whereas that Mortlake Panel advocated the use of an agreement made under 

Section 173 of the Planning and Environment Act to ensure that commitments 

made in the EES are implemented and can be enforced, the Panel agrees with 

the view put by Mr Power that that the use of agreements should be avoided 

where possible. 

The Panel considers that it is reasonable to anticipate that the agencies 

responsible for subsequent approval of works approvals, licenses and EMPs 

will give considerable weight to the commitments in the EES and the 

Minister’s assessment.  We also recognise that the EPA and Minister for 

Energy and Resources have robust powers under the Environment 

Protection Act and the Pipelines Act respectively. 

Nevertheless, the Panel does appreciate the concerns expressed by the 

Morgan‐Paylers, particularly in relation to the Power Station, which has 

greater potential for ongoing impacts than the other elements of the project.  

Like the zones applied to gas plants in the region, the Panel considers that 

the SUZ2 should explicitly recognise the EES and the Minister’s assessment 

as the basis for secondary approvals.  The schedule to the zone should also 

establish key performance expectations rather than simply specifying the 

scope of the further plans to be submitted for approval (see further 

discussion in Chapter 11.3). 

11.1.2 Co-ordination between Regulatory Agencies

There was a consensus from those who presented at the Hearing that the EES 

Technical Reference Group (TRG) had been a constructive process.  Indeed 

the process appears to have established a high degree of confidence amongst 

those involved that that it will be possible to identify appropriate response to 

those issues that remain to be resolved or are likely to arise during further 

development of the project design.  This is a credit to both the Proponent 

(and those working on its behalf) and the regulatory agencies.  The TRG and 

the Shire of Moyne’s community liaison processes appear to have opened 

channels of communication between agencies and these co‐operative 

working arrangements should be maintained. 

The planning framework seeks to avoid duplication of approval processes by 

minimising the number of separate approvals with an expectation that 

agencies responsible for particular approvals will draw on the specialist 

expertise of other agencies where necessary.  For example, the Clause 52.03 

incorporated document requires DSE approval of offset plans for the 

removal of native vegetation and, although there is no statutory obligation to 

do so, DPI advised that approval to remove native vegetation on the gas 

pipeline and the offsets required would also be subject to approval by DSE. 

Page 138

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

The Panel considers that the SUZ2 should specify that the Planning 

Authority should have regard to the views of nominated agencies when the 

Development Plan and EMP are assessed.  This will recognise that review is 

required by those with more specific expertise than is available to Council 

(see discussion below). 

11.1.3 Consultation

The Shire of Moyne advised it intends to continue a forum for Proponents, 

community members and relevant agencies relating to major infrastructure 

projects, such as the Mortlake Power Station and the current project. 

After the hearing the Shire of Moyne forwarded a copy of a Draft charter for 

a ‘Community Engagement Committee’ for this project which would include 

the Mayor, two councillors, three community representatives and two 

representative of the proponent with others invited to attend meetings but 

they would not be regarded as members of the Committee.  The Draft 

Charter identifies the following purposes for the Committee: 

1. To provide advice on strategies to ensure the effective flow of information 

to and from the community regarding the proposed Shaw River Power 

Station project. 

2. To act as a conduit for information flow between Council, the project 

proponent and the community, regarding the progress of the Shaw River 

Power Station project. 

3. To contribute to a transparent planning process for the project, whilst not 

duplicating the required statutory components of that process. 

4. To assist where relevant in the resolution of issues that may arise during 

the pre‐construction, and if necessary during the construction and 

operational phases of the Shaw River Power Station. 

5. If the project proceeds to construction, be a forum to assist Shaw River 

Power to demonstrate their performance against the regulatory 

obligations. 

The EPA also indicated that monitoring of the project should be developed in 

consultation with the local community consistent with an environmental 

improvement program.  EPA guidance and assistance to develop such a 

program is available41. 

The Shire of Moyne is commended for implementing this initiative.  It was 

evident at the hearing that these consultative arrangements have provided a 

41 Environment Improvement Plans – An Overview Publication 938 February 2004, Guidelines For

Running Community Liaison Committees November 2001 Publication 740

Page 139

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

valuable avenue for communication between Council, the Proponent and the 

community during the preparation of the EES. 

Consultative arrangements will continue to be important and will have an 

extended role during construction and operational phases of the project.  The 

Panel sees significant merit in the operation of a forum with the roles 

identified above.  However, it considers the participation of key agencies is 

necessary to fulfil the roles of facilitating co‐ordination between regulatory 

agencies (particularly Council, EPA, DSE and DPI), reporting construction 

progress and performance monitoring information, and establishing a point 

to expedite action on complaints identified.  As Council (and other agencies) 

have specific statutory responsibilities, the Panel also queries the 

circumstances where voting, as opposed to recording views in minutes, 

would be necessary or appropriate. 

The need for meetings will vary over the life of the project and should be 

regularly reviewed. 

A similar but more limited process, led by the Shire of Corangamite, should 

also be in place during construction and rehabilitation phases for land in that 

shire affected by the pipeline. 

The Panel considers the Proponent should agree to contribute to resourcing 

the process. 

After the hearing, the Shire of Moyne forwarded a copy of a letter from the 

Minister for Planning (dated 10 June 2010) which responded to Municipal 

Association of Victoria’s proposal for a ‘partnership approach’ to the 

planning and development of Wind Energy Facilities in Victoria.  In that 

letter the Minister supported, amongst other things: 

the allocation of resources for regional co‐ordination and a dedicated 

wind farm project manager to, amongst other things explore models for 

co‐funding so that access to independent technical expertise is improved; 

and 

investigation of opportunities to develop a regional‐scale dataset for 

South West Victoria to assist in the assessment of cumulative effects of 

wind energy facilities. 

The Panel considers these are both positive initiatives and their scope should 

be extended to encompass other major energy projects, such as the proposed 

gas fired power stations and possible geothermal proposals. 

Page 140

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

11.1.4 Compliance Testing

Accountability for compliance with commitments in the EES and subsequent 

conditions of approvals is important to maintain community confidence as 

well as achieving the expected mitigation of potential impacts.  The Panel 

considers that compliance testing by a suitably qualified, independent person 

at relevant stages of the development process is important to ensure the 

implementation process is adequately informed and breaches are resolved at 

the earliest opportunity.  This approach should avoid adverse impacts and 

minimise the need for subsequent enforcement processes.  It also 

supplements the expertise available to the regulatory authority in the 

determination of compliance on technical matters. 

11.1.5 Access to Appropriate Expertise

The Minister for Planning’s response (dated 10 June 2010) to the Municipal 

Association of Victoria’s proposal for a ‘partnership approach’ to the 

planning and development of Wind Energy Facilities in Victoria is also 

relevant to other major infrastructure projects put forward for development 

in the region.  It is noted that the Minister did not support the establishment 

of a technical reference group such as would support an EES but he advised 

that sufficient independent expertise exists within the State Government and 

the pilot can explore how to improve Council access to those skills. 

This Panel considers the task of identifying options to augment local 

government expertise in relation to Wind Energy Facilities should extend to 

other major infrastructure projects in the region.  For the project currently 

being considered, the following recommendations have a role in ensuring 

decisions are underpinned by an appropriate level of technical expertise: 

nominating in the SUZ2 that the Responsible Authority should have 

regard to the comments of the nominated agencies (including DPI, EPA, 

DSE, VicRoads, ESV, WorkSafe Victoria) as relevant; 

independent auditing of compliance with specified criteria by a suitably 

qualified person; and 

active ongoing involvement in project specific consultative arrangements 

by agencies with responsibility for project approvals or with specific 

technical expertise. 

Panel Recommendations 

Include in EMPs, requirements for independent compliance testing by 

suitably qualified people, at relevant stages of the development process. 

Page 141

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

11.2 Environmental Management Plans

Environmental management plans (EMPs) are to be prepared under separate 

regulatory frameworks for each of the three project components: the Power 

Station site; gas pipeline and compressor station; and water pipelines.  These 

plans are the principal implementation tools to manage environmental 

impacts during construction and operation and as such, should reflect the 

various regulatory requirements. 

The exhibited Strategic EMP sets the framework for development of the 

EMPs.  The Strategic EMP is supported by an Integrated Risk Assessment 

that includes an assessment of residual risks, thus far in the project and also 

contains Management Guidelines for the full range of aspects of the project.  

The Management Guidelines provide a summary of environmental 

management issues, objectives for management, performance criteria, 

mitigation and management measures (identified through the impact 

assessment process) and monitoring requirements for each environmental 

management aspect relevant to the project. 

Site specific water course crossing management plans are proposed to be 

prepared under the Construction EMPs for both the gas pipeline and water 

pipelines.  This approach will address the residual risks associated with 

finalising the pipeline routes and construction methods, particularly where 

subject to geotechnical investigations.  Final impacts on flora and fauna 

cannot be assessed until crossing methods are determined and further 

targeted surveying may be required, such as for aquatic communities. 

In addition to site specific management plans, species specific mitigation 

measures have been identified for significant flora and fauna species and will 

be incorporated in the Construction EMPs. 

Measures that are site specific and go beyond the generic have been 

consolidated into the table of Environmental Management Commitments.  

The Panel considers the Strategic EMP and Environmental Management 

Commitments provide a sound starting point for development of the 

Construction EMPs.  Therefore, the Panel has confined its attention to those 

issues considered to be outstanding, in relation to requirements of the EMPs. 

The following section consolidates various recommendations to address key 

issues identified at the hearing through specific inclusions in the EMPs. 

Page 142

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

11.2.1 The Power Station Site

Both Construction and Operations EMPs are proposed as part of 

Amendment C36 and will be subject to approval and monitoring of 

implementation by Moyne Shire Council.  Moyne Shire noted that the scope 

of the environmental management plans, as presented in the proposed 

Amendment C36 was not well developed.  The Panel agrees with this view 

and recommended the addition of more specific requirements on key issues. 

Additional requirements in the Construction and Operations EMPs (required 

under both SUZ2 and EPA approvals) for the Power Station site, arising from 

the Panel’s recommendations include: 

monitoring program for the Southern Bent‐wing Bat on the Power Station 

site, generally in accordance with the preliminary monitoring program in 

Appendix D; 

monitoring for the impacts of discharges from the Power Station site on 

aquatic ecosystems in the Shaw River, generally in accordance with the 

preliminary monitoring programs in Appendix D; 

vegetation management plans for any vegetation removal associated with 

construction on the Power Station site and surrounds, in order to provide 

appropriate management guidelines for these works and prepared to the 

satisfaction of DSE; 

restrictions on construction activities and construction noise management 

to the satisfaction of EPA and the Responsible Authority; 

noise monitoring under representative conditions at sensitive receptors 

near the Power Station and compressor station during the commissioning 

of each stage of the project to confirm compliance with the criteria; 

compliance with the specified operational noise limits to be included in 

Operations EMP; 

an Off‐site Landscaping Plan to mitigate the visual impact of the Power 

Station from all dwellings within 3km of the Power Station site; 

management of air emissions (dust) from construction of the Power 

Station, based on the recommendations in EPA Victoria’s Environmental 

Guidelines for Major Construction Sites; 

Safety Management Plan, prepared by a suitably qualified person; this 

should also provide for the Responsible Authority to have regard to the 

views of ESV, WorkSafe Victoria, the CFA and the SES. 

Page 143

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

11.2.2 Gas Pipeline and Compressor Station

Construction and Operations EMPs are required under the Pipelines Act, for 

the gas pipeline and compressor station.  Approval and implementation of 

the Construction and Operations EMPs are overseen by DPI and Energy Safe 

Victoria, respectively. 

The Pipelines Regulations 2007 specify the scope of a Construction EMP which 

must encompass all pipeline construction activities and must address specific 

environmental protection strategies and risk mitigation methodologies. 

DPI advised that it adopts the following practices before it accepts the 

Construction EMP: 

a Cultural Heritage Management Plan must be accepted by the RAP or 

equivalent; 

specialist technical advice from DSE will also be sought in relation to flora 

and fauna management issues to be incorporated in the Construction 

EMP  and a Native Vegetation Offset Plan must be accepted by DSE; and 

referral of the Construction EMP to relevant government agencies for 

expert comments. 

Prior to the commencement of the construction or operation of the gas 

pipeline, a safety management plan must be accepted by Energy Safe 

Victoria and must include both Construction and Operations safety 

management plans, prepared in accordance with the appropriate Australian 

Standards.  Additional requirements in the Construction and Operations 

EMPs for the gas pipeline and compressor station, arising from the Panel’s 

recommendations include: 

measures to protect and re‐instate dry‐stone walls that may be impacted 

by construction, to be included in the Construction EMP; 

rehabilitation to former condition including: 

rehabilitation monitoring for a minimum period of three years; 

immediate post construction audits to confirm native vegetation 

offsets; and 

audits at two years post construction, to confirm actual native 

vegetation losses and revise offsets, if required. 

site specific rehabilitation techniques and monitoring measures for 

rehabilitation success, specific to terrestrial flora and fauna identified 

through targeted surveys; 

rehabilitation techniques and monitoring requirements to be included in 

the Construction EMP, specific to aquatic flora, including measures to 

address the constraints on re‐establishment of aquatic flora species, 

imposed by stream flow; 

Page 144

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

management of air emissions (dust) from construction based on the EPA  

Environmental Guidelines for Major Construction Sites and the 

Australian Pipeline Industry Association Code of Environmental Practice; 

include restrictions on construction activities and construction noise 

management measures to the satisfaction of EPA and the Responsible 

Authority; 

inform residents of the nature of the works, expected noise levels, 

duration of works and a method of contact; 

manage the noise impacts of the construction of the gas and water 

pipelines under the EPA Noise Control Guidelines (Publication 1254: 

October 2008; and 

adopt the standards and procedures in ‘Australian Standard for Protection 

of Trees on Development Sites 2009’ net gain assessments for any implied 

further losses of old trees with post‐construction auditing of actual losses. 

11.2.3 Water Pipelines

Permission will be required to construct the water supply pipelines through 

several waterways, including Ware Creek through a ‘Works on Waterways’ 

permit issued by CMAs.  This will be supported through the site specific 

water crossing management plans that will be prepared by the Proponent 

and incorporated in the Construction EMP. 

Additional requirements in the Construction and Operations EMPs for the 

water pipelines, arising from the Panel’s recommendations include: 

rehabilitation to former condition including: 

the management of excess excavated material; 

rehabilitation monitoring for a minimum period of three years; 

immediate post construction audits to confirm native vegetation 

offsets; and 

audits at two years post construction, to confirm actual native 

vegetation losses and revise offsets, if required. 

requirements for the protection and re‐instatement of dry‐stone walls in a 

Construction EMP (under Clause 52.03); 

site specific rehabilitation techniques and monitoring measures for 

rehabilitation success, specific to terrestrial flora and fauna identified 

through targeted surveys, to be included in the Construction EMP; 

rehabilitation techniques and monitoring requirements to be included in 

the Construction EMP, specific to aquatic flora, including measures to 

address the constraints on re‐establishment of aquatic flora species, 

imposed by stream flow; 

Page 145

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

vegetation management plans for any vegetation removal associated with 

construction on the Power Station site and surrounds, in order to provide 

appropriate management guidelines for these works and prepared to the 

satisfaction of DSE; 

management of air emissions (dust) from construction based on the EPA 

Victoria’s Environmental Guidelines for Major Construction Sites; 

include restrictions on construction activities and construction noise 

management measures to the satisfaction of EPA and the Responsible 

Authority; 

inform residents of the nature of the works, expected noise levels, 

duration of works and a method of contact; 

manage the noise impacts of the construction of the gas and water 

pipelines under the EPA Noise Control Guidelines (Publication 1254: 

October 2008; and 

adopt the standards and procedures in ‘Australian Standard for Protection 

of Trees on Development Sites 2009’ in Construction EMPs and review net 

gain assessments for any implied further losses of old trees. 

11.2.4 Complaints Management

The Construction and Operations EMPs should include complaints 

management procedures.  The Panel suggests that the Australian Standard 

Customer satisfaction – Guidelines for complaints handling in organizations 

(AS10002:2006) and the associated handbook The Why and how of complaints 

handling HB 229‐2006 provides valuable guidance on the establishment and 

operation of an effective complaints management regime.  This Standard 

includes the following features: 

readily accessible information, flexibility in methods of making 

complaints and the ability for complaints to be made free of cost to the 

complainant; 

immediate acknowledgement of all complaints with on‐going on 

responses to address issues raised; 

closure of complaints by acceptance by the complainant of the actions 

taken or, where necessary, advice to the complainant on alternative forms 

of recourse available; 

clear responsibility and accountability for development and 

implementation of action plans and progress reporting; 

detailed recording of complaints including the tracking through the entire 

process; and 

regular auditing of the complaints handling process. 

Page 146

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

It is noted that, while these procedures aim to expedite the resolution of 

complaints internally where possible, enforcements actions under the 

relevant legislation may also be relevant. 

Recommendation 

Ensure the EMPs under the various approvals  are consistent and are 

generally in accordance with the  Strategic EMP and Environmental 

Commitments exhibited with the EES, as varied by recommendations of 

this Panel and the Minister’s Assessment under the Environment Effects 

Act. 

Include complaints handling processes in EMPs that adopt the principles 

outlined in Australian Standard Customer Satisfaction – Guidelines for 

complaints handling in organizations (AS10002:2006). 

11.3 Moyne Planning Scheme Amendment C36

Amendment C36 is proposed to facilitate the development of the Power 

Station and water pipeline by: 

rezoning the Power Station site from Farming Zone (FZ) to a Special Use 

Zone 2 (SUZ2); 

introducing an Environmental Significance Overlay (ESO4) to manage the 

introduction of noise sensitive uses around the Power Station site; and 

using Clause 52.03 to exempt the elements of the proposal from planning 

scheme requirements if the associated incorporated document 

requirements are met. 

11.3.1 Schedule 2 to the Special Use Zone (SUZ2)

The rezoning of the Power Station site to SUZ2 establishes a regulatory 

framework that provides for: 

as of right use and development of gas‐fired power generation and 

accommodation in moveable buildings for power station construction 

workers (provided that conditions of the clause are satisfied); 

approval of development plan and Construction EMP by the responsible 

authority before development starts; and 

approval of an Operations EMP by the responsible authority before the 

use starts. 

The SUZ2 regulatory framework relies on secondary approvals of the 

Development Plan and EMPs rather than permit processes.  As noted in 

Chapter 11.2, the SUZ2 establishes the scope of these plans by indicating the 

generic content but the only requirements specified (which can be varied 

Page 147

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

with approval of the responsible authority) relate to the Power Station height 

and footprint, the upgrade of the Hamilton – Port Fairy and Riordans Road 

intersection and a requirement for 50 staff and 5 visitor car parking spaces 

during operation. 

The Panel considers the EES has established that there is a sound planning 

rationale for the project and key environmental constraints are capable of 

being addressed.  In these circumstances, it is appropriate to for the zoning of 

the land to establish a high degree of certainty for further approvals.  The 

Panel supports the as of right status of the Power Station but, as discussed in 

Chapter 8.2, the Panel considers a construction camp should be subject to a 

permit as the strategic justification for this use being as of right has not been 

established. 

Further, as noted in Chapter 11.1, the Panel considers the SUZ should specify 

some key performance expectations, rather than just indicating the scope of 

plans to be submitted. 

Mr Clarke advised that the proposed SUZ 2 was modelled on the zoning 

adopted for the Mortlake Power Station.  However, in considering whether 

noise and other matters should be specified in the regulatory framework for 

the project, the Panel also reviewed other zones applied to infrastructure 

projects in the region, such as SUZ1 and SUZ4 which apply to the Iona and 

Woodside Gas Processing Plants at Port Campbell.  In these SUZs, the 

development of the gas plants is as of right but additional guidance is 

provided about the expected performance on key matters.  Significantly, the 

zones applied to the gas processing plants specify that: 

The Development Plan must: 

be generally in accordance with a plan that is nominated; and 

provide that the light emissions are no greater than those required 

by safety regulations. 

Requirements specified for the  EMPs include: 

air emissions.  The limits for CO, nitrogen oxides expressed as 

‘NOx’ and mercaptans and other emissions must accord with the 

limits established in the specified Works Approval and Licence 

Framework Plan; 

the noise limits must be established in accordance with the Interim 

Guidelines, and prescribe octave band levels of no greater than 

Lbg plus 10 dB(A); 

the EMP must address the principles, actions and commitments 

contained the exhibited Environment Effects Statement except 

where they are specifically varied in the Minister’s assessment of 

Page 148

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

Environmental Effects and Panel Report or by the conditions of 

other statutory approvals; and 

the EMP must provide for agreements made pursuant to Section 

173 of the Planning and Environment Act 1987 in relation to a range 

of maters such as: off‐site vegetation buffers, dams to meet fire 

fighting requirements,  the sealing of nominated roads,  control of 

use of adjacent roads by heavy vehicles, the use of a particular 

property as a construction camp, the fire management/emergency 

plan (including training their personnel), the setting up of an 

Environmental Review Committee, and provision for owners of 

land generally within 800 metres of the plant to forgo further 

development for sensitive uses in exchange for financial 

reimbursement. 

The Panel supports specifying in the SUZ2 that the Development Plan and 

EMPs must address the principles, actions and commitments contained in 

the exhibited Environment Effects Statement except where they are 

specifically varied in the Minister’s assessment of Environmental Effects and 

Panel Report or by the conditions of other statutory approvals.  In addition, 

the Panel’s recommendations from earlier chapters that relate to particular 

requirements should be specified in the requirements in the relevant further 

plans required under SUZ2.  These include: 

compliance with recommended noise limits; 

compliance with SEPP (Air Quality Management) and SEPP (Waters of 

Victoria) design criteria and standards; 

matters identified in Chapter 6.2 recommendations relating to Safety 

Management Plans; 

a sealed upgrade of Riordans Road from the Hamilton – Port Fairy Road 

intersection to the entrance of the Power Station (before development 

starts) and internally for all roads regularly used by B double vehicles 

incorporation of management measures within the approved Cultural 

Heritage Management Plan; 

‘Off‐site Landscaping Plan’ to mitigate the visual impact; 

site specific requirements in construction EMPs which include 

appropriate rehabilitation techniques and monitoring measures for both 

aquatic and terrestrial flora; and 

Southern Bent‐wing Bat monitoring on the Power Station site. 

The Panel has reviewed the drafting of the exhibited Schedule 2 to the SUZ 

and makes the following comments: 

it is noted that SUZ2 does not require a permit for buildings and works 

that rearrange, alter or renew existing plant if the area or height of the 

Page 149

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

plant is not increased.  While the apparent intent of this exemption 

appears reasonable, the Panel considers that the location of the plant or 

works is also likely to be relevant in the original approval of development 

and management plans (for example to avoid wetlands) and therefore 

should also be included as a condition of this exemption; 

the exemptions also apply to ‘… a minor rearrangement of on‐site roads and 

access ways, car parking areas and landscaping provided that their areas and 

effectiveness are not diminished.’  The Panel is concerned that this exemption 

could allow changes to parking or access which could have adverse 

environmental impacts eg on water management.  It considers  the 

exemption applicable though the Development Plan process, which could 

incorporate a significant degree of flexibility regarding car parking and 

access, allows the range of issues to be addressed; 

it may be clearer to refer to mitigation of impacts of the power on the 

character and amenity of the surrounding area in the purpose of the zone; 

and 

the Panel also questions the adoption of the ‘open ended’ nature of uses 

for which a permit may be sought.  It is considered more appropriate to 

translate the use table from the existing Farming Zone with the additional 

as of right uses in the exhibited SUZ2 (except that construction camp 

would be a section 2 use). 

11.3.2 Schedule to Clause 52.03

Amendment to the schedule to Clause 52.03 proposes to replace planning 

scheme provisions applicable to the following aspects of the project: 

altering the access to Hamilton–Port Fairy Road at its intersection with 

Riordans Road (with plans to be approved by the responsible authority 

and VicRoads); 

native vegetation removal associated with the upgrading of the Riordans 

Road and Hamilton– Port Fairy Road intersection; 

the use of land owned by the Proponent to the west and east of Old 

Dunmore Road for a workers construction camp; and 

the construction of the water pipelines from Port Fairy to the Power 

Station site. 

The removal of native vegetation allowed under the clause is subject to a 

requirement for approval by DSE and the Responsible Authority of a plan 

showing the extent of vegetation losses and an offset plan.  It is noted that an 

estimate of losses with post‐construction auditing to verify actual losses and 

associated offset obligations is possible under this clause whereas the 

incorporation of a native vegetation precinct plan under section 52.16 would 

Page 150

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

require losses and offsets to be finalised and ‘locked in’ via incorporation into 

the planning scheme before any development occurs. 

Clause 52.03 has a purpose42 to: 

To provide in extraordinary circumstances specific controls designed 

to achieve a particular land use and development outcome (Panel 

emphasis). 

Site specific provisions in Clause 52.03 are only expected to be used to 

achieve a particular land use or development outcome that cannot be 

achieved otherwise and ‘which is consistent with a major issue of policy or 

necessary to achieve or develop the planning objectives of Victoria43. 

The Panel is satisfied that the facilitation of the development of this major 

project satisfies the criteria.  Further, the EES has provided an opportunity 

for views on the project to be presented and the requirements for approvals 

by DSE and Council relating to vegetation removal and VicRoads and 

Council relating to the intersection works ensure appropriate scrutiny of the 

nominated works. 

However, in addition reference should be made in this clause to 

Construction EMPs for the works.  This will ensure that appropriate 

environmental management measures are adopted for the road and water 

pipeline works for which exemptions from permit requirements are 

provided eg including a vegetation management plan, post development 

audits of to enable adjustments to pre‐construction estimates of vegetation 

losses and associated offsets, standard construction management techniques 

and the like. 

As discussed in Chapter 8.2, the Panel considers a construction camp should 

be subject to a permit as the strategic justification for this use being as of 

right has not been established.  The assessment of any such application 

would have regard to the outcomes of the accommodation and community 

services strategy, as well as site specific design and management 

considerations. 

The original submission by the Proponent sought the deletion of the water 

pipelines route maps in the Schedule to Clause 52.03, and instead propose 

referencing almost identical maps in the incorporated document.  The Panel 

agrees with Mr Clarke that it is much more transparent to include the maps 

of the land to which the clause applies in the schedule rather than the less 

42 The other purpose relates to transitional provisions to accommodate some site specific planning

scheme provisions that applied when new format planning schemes were introduced. 43 See for example Pages 7 and 11 Manual for Victoria Planning Provisions.

Page 151

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

accessible incorporated document.  The Panel also considers that the 

schedule should indicate the address (as well as title and map details) for the 

Proponents land to the east of Old Dunmore’s Road where it is 

recommended that there should be discretion to apply for a permit for a 

temporary construction camp. 

11.3.3 Clause 52.17

It is proposed to exempt removal of native vegetation within SUZ2 from 

permit requirements that would otherwise apply under Clause 52.17. 

The Power Station is proposed on cleared land currently used for cattle 

grazing and avoids remnant native vegetation on the site.  If some losses of 

native vegetation on the site do occur, the Proponent has committed offset 

the losses in accordance with the Framework.  There was no opposition to 

this provision and the Panel accepts that appropriate commitments have 

been made and will be implemented. 

11.3.4 Environmental Significance Overlay 4

It is proposed to apply ESO4 to land extending from approximately 400‐

1,200m around the Power Station site which is predicted to be affected by 

noise at a level of 34 dB(A) or more under adverse weather conditions.  The 

overlay introduces a permit requirement for development associated with 

accommodation uses44. 

There are currently no dwellings on the land to which it is proposed to apply 

ESO4.  Much of the land affected is currently owned by the Proponent (land 

to the east of Old Dunmore Road) and or under plantation (adjoining land to 

the north, south and west). 

There were no submissions objecting to ESO4, although the Shire of Moyne 

suggested it may be inconsistent to on the one hand apply the overlay and 

then provide an exemption from permit requirements for the use and 

development of a construction camp on the Proponent’s land to the east of 

Old Dunmore Road. 

The Panel accepts the justification of ESO4 to enables consideration of the 

potential for landuse conflict and the creation of additional constraints on 

power station operation due to the encroachment of sensitive uses.  The 

overlay would have a valuable role in identifying land where noise 

emissions should be taken into account in future public and private decision 

44 The Panel notes that some properties affected by the proposed ESO4 have lot sizes that satisfy the

condition for as of right development of a dwelling under the FZ.

Page 152

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

making.  The primary purpose of the farming zone can continue but the 

overlay triggers consideration of measures to protect the amenity of 

associated residential uses and foreshadows the possible for the design of 

any accommodation to incorporate measures to attenuate internal noise 

levels and therefore reduce the potential for conflict. 

Elsewhere the Panel has indicated that it does not support as of right 

development of a construction camp on the land to the east of Old 

Dunmore’s Road and the provisions of ESO4 would apply to that use.  The 

Panel notes that mitigation of noise in construction camp dwellings would be 

a consideration after the first stage of developments the Power Station would 

be operational.  However, it is also noted that, while the noise levels are 

higher than normally expected in rural area, they comparable to noise levels 

in many urban areas with established residential uses and are not so great as 

to automatically render the land as uninhabitable, particularly for temporary 

residential use directly associated with the noise source. 

Recommendations 

Maintain a Project Liaison and Monitoring Committee which: 

is led by the Shire of Moyne with active participation by the Proponent 

and relevant agencies (including EPA, DPI, DSE); 

includes representation of nearby residents; and 

is resourced by the Proponent. 

Establish a similar community liaison forum led by the Shire of 

Corangamite to operate during the construction and rehabilitation phases 

of the gas pipeline and Compressor Station. 

Revise the proposed SUZ2 table of the uses to apply the existing Farming 

Zone table with the additional as of right uses in the exhibited SUZ2 

(except that construction camp would be a Section 2 use). 

Specify in the SUZ2 that the Development Plan and EMPs: 

must address the principles, actions and commitments contained in the 

exhibited Environment Effects Statement except where they are 

specifically varied in the Minister’s assessment of Environmental 

Effects and Panel Report or by the conditions of other statutory 

approvals; 

that the Responsible Authority with have regard to the views of 

relevant agencies (including DPI, EPA, DSE, VicRoads, ESV, WorkSafe 

Victoria) as appropriate; 

the particular requirements recommended by the Panel, including: 

compliance with recommended noise limits; 

Page 153

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

compliance with SEPP (Air Quality Management) and SEPP 

(Waters of Victoria) design criteria and standards; 

matters identified in Chapter 6.2 recommendations relating to 

Safety Management Plans; 

a sealed upgrade of Riordans Road from the Hamilton – Port 

Fairy Road intersection to the entrance of the Power Station 

(before development starts) and internally for all roads regularly 

used by B double vehicles; 

provision of sufficient parking at the Power Station to meet 

requirements during construction phase and maintenance 

periods; 

incorporation of management measures from the approved 

Cultural Heritage Management Plan; 

an ‘Off‐site Landscaping Plan’ to mitigate the visual impact; 

site specific requirements in construction EMPs which include 

appropriate rehabilitation techniques and monitoring measures 

for both aquatic and terrestrial flora; and 

Southern Bent‐wing Bat monitoring on the Power Station site. 

Include requirements in EMPs for auditing and testing of compliance by 

suitably qualified people at key stages of development with performance 

requirements of the following matters: 

air emissions; 

noise emissions; 

surface water management systems and the quality of water discharged 

from project sites; 

impacts on native vegetation; and 

post construction rehabilitation of pipeline easements. 

Revise the exemptions from permit requirements in Clause 3 of Schedule 2 

to the SUZ for buildings and works as follows: 

‘Rearrange, alter or renew existing plant if the location, area or 

height of the plant is not increased.’ 

Delete the exemption ‘‘result in a minor rearrangement of on‐site 

roads and access ways, car parking areas and landscaping 

provided that their areas and effectiveness are not diminished.’ 

Are accommodation and temporary amenities provided for 

persons constructing and commissioning any plant on the land. 

Page 154

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

Include the address of the land to the east of Old Dunmore Road in the 

table in the schedule to Clause 52.03 and attach the relevant maps to the 

schedule to that Clause. 

Require a Construction EMP for exemptions from permit requirements 

under Clause 52.03. 

Page 155

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

Appendix A EES Inquiry Panel Terms of Reference

Page 156

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

TERMS OF REFERENCE

INQUIRY UNDER ENVIRONMENT EFFECTS ACT 1978

SHAW RIVER POWER STATION PROJECT ____________________________________________________________________________

1. BACKGROUND In September 2008, Shaw River Power Station Pty Ltd (a subsidiary of Santos Ltd) referred the proposed Shaw River Power Station Project to the Minister for Planning under the Environment Effects Act 1978.

The major components of the project are: A nominal 1500 MW gas-fired power station on farming land near Orford in Moyne Shire. A high-pressure gas pipeline (including a compressor station) from the existing gas

transmission system near the Iona and Otway gas plants at Port Campbell. A water supply pipeline from the Port Fairy Water Reclamation Plant to the proposed

power station (to be constructed and operated by Wannon Water).

In November 2008, the Minister for Planning decided that an Environment Effects Statement (EES) was required under the Environment Effects Act 1978 to assess the potentially significant effects of the Shaw River Power Station Project.

In July 2009, the Minister approved scoping requirements for the EES, which specify a range of matters to be addressed in the EES, including the investigation of relevant alternatives.

The EES was placed on public exhibition from 12 March to 27 April 2010, together with Amendment C36 to the Moyne Planning Scheme and Works Approval Applications WA67398, WA67399 and WA67400). Pipeline Licence Applications PL271 and PL272 were advertised concurrently under the Pipelines Act 2005.

Works cannot commence until a cultural heritage management plan has been approved under the Aboriginal Heritage Act 2006.

The Inquiry for the Shaw River Power Station Project is to be appointed by the Minister for Planning under section 9(1) of the Environment Effects Act 1978. After the Inquiry provides its report to the Minister for Planning, the Minister will prepare an Assessment of the environmental effects45 of the project under the Environment Effects Act 1978 to inform the relevant Victorian statutory decisions.

2. TASK The Inquiry is required:

i. To inquire into and make findings regarding the potential environmental effects of the Shaw River Power Station Project, including the construction and operation of the power station, the high-pressure gas pipeline and water supply pipeline and associated infrastructure requirements.

ii. To consider the exhibited EES, all submissions received in response to the exhibited EES as well as other relevant matters.

iii. To recommend any modifications to the Shaw River Power Station Project as well as environmental mitigation and management measures that may be needed to achieve

45 Under the seventh edition of the Ministerial guidelines for assessment of environmental effects (June 2006), environment

for the purposes of assessment includes the physical, biological, heritage, cultural, social, health, safety and economic aspects of human surroundings, including the wider ecological and physical systems within which humans live.

Page 157

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

acceptable environmental outcomes, within the context of applicable legislation and policy.

3. METHOD The Inquiry must consider the exhibited EES, any submissions received in response to the exhibited EES, the proponent’s response to submissions and other relevant information provided to or obtained by the Inquiry.

The Inquiry must conduct a public hearing and make other such enquiries as are relevant to its consideration of the potential environmental effects of the Shaw River Power Station Project. The Inquiry must be conducted in accordance with the following principles:

The inquiry hearings will be conducted in an open, orderly and equitable manner, in accordance with the rules of natural justice, with a minimum of formality and without the necessity for legal representation.

The inquiry process will aim to be exploratory and constructive, where adversarial behaviour is minimised.

Parties without legal representation will not be disadvantaged – cross-examination will be strictly controlled and prohibited where not relevant by the inquiry chair.

The Inquiry will meet and conduct hearings when there is a quorum of at least two of its members present including the Inquiry Chair.

4. OUTCOMES To prepare a report for the Minister for Planning presenting:

The Inquiry’s response to the matters detailed in section 2.

Relevant information and analysis in support of the Inquiry’s recommendations.

A description of the proceedings conducted by the Inquiry and a list of those consulted and heard by the Inquiry.

5. TIMING The Inquiry is required to report to the Minister for Planning in writing within six weeks of its last hearing date.

6. FEES The members of the Inquiry will receive the same fees and allowances as a panel appointed under Division 1 of Part 8 of the Planning and Environment Act 1987. APPROVED:

Page 158

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

Appendix B List of Submitters

CFA South West Area 

Corangamite Shire 

Department of Primary Industries 

Environment Protection Authority 

Glenelg Hopkins Catchment Management Authority 

Moyne Shire 

Ms Shirley Nicholls 

Mr Geoff Saffin 

Santos Limited 

The Morgan‐Payler Family 

Wannon Water 

Wind Farm Developments 

Page 159

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

Appendix C EES Table 2.1: Summary of Key Approvals and Assessments Required

Page 160

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

Page 161

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

Page 162

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

Page 163

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

Appendix D Potential Bent-Wing Bat and Water Monitoring Principles

Page 164

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

 

Page 165

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

Page 166

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

Page 167

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

Page 168

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

Page 169

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

Page 170

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

Appendix E  List of Abbreviations Used 

Departments, Organisations and Businesses 

AAV    Aboriginal Affairs Victoria 

AEMO   Australian Electricity Market Operator 

CFA    Country Fire Authority 

DPCD    Department of Planning and Community Development 

DPI    Department of Primary Industry 

DSE    Department of Sustainability and Environment 

EPA    Environment Protection Authority 

ESV    Energy Safe Victoria 

SES    State Emergency Service 

Zones and Overlays 

ESO  Environmental Significance Overlay 

FZ  Farming Zone 

PUZ  Public Use Zone 

SUZ   Special Use Zone  

Other Terms 

CCGT    Combined‐cycle gas turbines 

CHA    Cultural Heritage Assessment 

CHMP   Cultural Heritage Management Plan 

dB(A)    Decibels, A weighting 

EHSMS  Environment, Health and Safety Management System 

EMP    Environmental Management Plan 

EPBC Act  Environment Protection and Biodiversity Act 

EREP    Environment and Resource Efficiency Plan  

EVC    Ecological Vegetation Community 

FFG    Flora and Fauna Guarantee 

HAZID  Hazard Identification 

ha    Hectare 

HDD    Horizontal Directional Drilling 

km    Kilometre 

Page 171

SHAW RIVER POWER STATION PROJECT EES & MOYNE PLANNING SCHEME AMENDMENT C36 INQUIRY PANEL REPORT: JULY 2010

kV    Kilovolt 

LPPF    Local Planning Policy Framework 

LVIA     Landscape and Visual Impact Assessment  

MRET    Mandatory Renewable Energy Target 

MSS    Municipal Strategic Statement 

NGER    National Greenhouse and Energy Reporting Act 2007 

NVMF   Native Vegetation Management Framework 

OCGT    One open‐cycle gas turbine 

RAP    Registered Aboriginal Party 

RWTP    Recycled water treatment plant  

SEPP    State Environment Protection Policy 

SEPP AQM  SEPP (Air Quality Management) 2001 

SEPP N‐1  SEPP (Control of Noise from Commerce, Industry and Trade) No N‐1 

1989. 

SIA    Socio‐economic Impact Assessment 

SPPF    State Planning Policy Framework 

vpd    vehicles per day 

VVP    Victorian Volcanic Plain 

WEF    Wind Energy Facility 

WP    Warrnambool Plain 

WRP    Water Reclamation Plant 

WWTP  Waste Water Treatment Plant