shepard energy centre
DESCRIPTION
Shepard Energy Centre. Environmental Stewardship. Overview. Nominal 800 MW Natural Gas Combined Cycle Early 2011 Received Regulatory Approval (Alberta Utilities Commission and Alberta Environment and Sustainable Resource Development) Cost: Approximately 1.35 Billion - PowerPoint PPT PresentationTRANSCRIPT
Shepard Energy Centre
Environmental Stewardship
Overview
Nominal 800 MW Natural Gas Combined CycleEarly 2011 Received Regulatory Approval (Alberta Utilities Commission and Alberta Environment and Sustainable Resource Development) Cost: Approximately 1.35 BillionJoint Venture with Capital PowerCurrently under construction COD: Early 2015
4
TechnologyVideoNatural Gas Combined Cycle2 on 1 Mitsubishi 501G gas turbine
Environmental Attributes - Low Air Emissions
GHG – Less that 0.4 tonnes/MWh (less than half of the emissions from Coal)SOx – Virtually noneNOx – Shepard will only emit between 3 ppm and 6 ppmPM – virtually noneMercury – No mercury emissionsWe did extensive air dispersion modeling and Shepard has minimal impact on air quality in the region.
Environmental Attributes - Water Consumption
Plant MW ML/y ML/MW Comment
Keephills 766 16000 20.9 Inefficient
Battle River 663 6019 9.1 More efficient
Shepard 800 3796 4.7 Very efficient due to plant design and uses reclaimed water
Shepard Site Photos – April 2013
Aerial View Looking South
Shepard Site Photos – April 2013
Fiberglass Cooling Tower Showing End Wall And Louver Installation
Shepard Site Photos – April 2013
HRSG #2 Finger Rack Area
Shepard Site Photos – April 2013
Combustion Turbine #1
Shepard Site Photos – April 2013
Low Pressure Steam Turbine Rotor Insertion