Istanbul Bridge Conference August 11-13, 2014 Istanbul, Turkey SHIP COLLISION: REPAIR & REHABILITATION OF A CABLE STAYED BRIDGE Sumitaka KURINO 1 , Hiroshi KUDO 2 , Masaru KUDO 3 and Yuichi YAMAMOTO 4 ABSTRACT The Binh Bridge was officially opened in public in Vietnam in 2005. The bridge is a steel cable-stayed bridge with RC slab on 2 edge girders with 4 car lanes and 2 pedestrian & bike lanes. The bridge length is 1.3 km and the main span is 260 m. The bridge was, however damaged 5 years later. The bridge was collided by ships at the time of landing of the Typhoon Conson in 2010. The 3 cargo vessels were drifted due to strong winds and hit the bridge. The damages occurred. A steel girder was deformed and two cables were broken its plastic covers and wires were exposed. Traffic of the bridge had restricted then. Repair design was carried out in 2011, and works had done in 2012. Damaged parts of the girder was cut and welded by new parts. Damage girder was repaired using temporary supporting member called “Temporary By- Pass Truss”. Damaged two cables were replaced by new one using “Temporary Hanger System”. After completion of rehabilitation, the bridge has been in full re-opening in use in the end of 2012 and the final inspection on defect liability period was passed in 2014. The bridge is a cable stayed structure with RC and steel composite girder and its repair / rehabilitation work was a rare case and precious experience. 1 Project Manager (C/S), Intl. Dept., CHODAI CO., LTD, 730 Higashi-Hiratsuka, Tsukuba, 305-0812 Japan 2 Project Manager (D/D), Intl. Dept., CHODAI CO., LTD, 730 Higashi-Hiratsuka, Tsukuba, 305-0812 Japan 3 Bridge Engineer, Intl. Dept., CHODAI CO., LTD, 730 Higashi-Hiratsuka, Tsukuba, 305-0812 Japan 4 Project Manager (Construction), IHI Infrastructure Asia Co., Ltd. 9F, Hoang Huy Building, 116 Nguyen Duc Canh, Cat Dai, Le Chan, Hai Phong, Viet Nam

Upload: others

Post on 21-Mar-2020

15 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: SHIP COLLISION: REPAIR & REHABILITATION OF A CABLE STAYED ...istanbulbridgeconference.org/2014/ISBN978-605-64131-6-2/papers/088.pdf · Ship Collision: Repair & Rehabilitation Of A

Istanbul Bridge Conference August 11-13, 2014

Istanbul, Turkey

SHIP COLLISION: REPAIR &

REHABILITATION OF A CABLE STAYED

BRIDGE

Sumitaka KURINO1 , Hiroshi KUDO2,

Masaru KUDO3 and Yuichi YAMAMOTO4

ABSTRACT

The Binh Bridge was officially opened in public in Vietnam in 2005. The bridge is a steel

cable-stayed bridge with RC slab on 2 edge girders with 4 car lanes and 2 pedestrian & bike

lanes. The bridge length is 1.3 km and the main span is 260 m. The bridge was, however

damaged 5 years later. The bridge was collided by ships at the time of landing of the

Typhoon Conson in 2010. The 3 cargo vessels were drifted due to strong winds and hit the

bridge. The damages occurred. A steel girder was deformed and two cables were broken its

plastic covers and wires were exposed. Traffic of the bridge had restricted then. Repair

design was carried out in 2011, and works had done in 2012. Damaged parts of the girder was

cut and welded by new parts. Damage girder was repaired using temporary supporting

member called “Temporary By- Pass Truss”. Damaged two cables were replaced by new one

using “Temporary Hanger System”. After completion of rehabilitation, the bridge has been in

full re-opening in use in the end of 2012 and the final inspection on defect liability period

was passed in 2014. The bridge is a cable stayed structure with RC and steel composite girder

and its repair / rehabilitation work was a rare case and precious experience.

1Project Manager (C/S), Intl. Dept., CHODAI CO., LTD, 730 Higashi-Hiratsuka, Tsukuba, 305-0812 Japan 2Project Manager (D/D), Intl. Dept., CHODAI CO., LTD, 730 Higashi-Hiratsuka, Tsukuba, 305-0812 Japan 3Bridge Engineer, Intl. Dept., CHODAI CO., LTD, 730 Higashi-Hiratsuka, Tsukuba, 305-0812 Japan 4Project Manager (Construction), IHI Infrastructure Asia Co., Ltd. 9F, Hoang Huy Building, 116 Nguyen Duc

Canh, Cat Dai, Le Chan, Hai Phong, Viet Nam

Page 2: SHIP COLLISION: REPAIR & REHABILITATION OF A CABLE STAYED ...istanbulbridgeconference.org/2014/ISBN978-605-64131-6-2/papers/088.pdf · Ship Collision: Repair & Rehabilitation Of A

Ship Collision: Repair & Rehabilitation

Of A Cable Stayed Bridge

Sumitaka KURINO1, Hiroshi KUDO2,

Masaru KUDO3 and Yuichi YAMAMOTO4

ABSTRACT The Binh Bridge was officially opened in public in Vietnam in 2005. The bridge is a steel

cable-stayed bridge with RC slab on 2 edge girders with 4 car lanes and 2 pedestrian & bike

lanes. The bridge length is 1.3 km and the main span is 260 m. The bridge was, however

damaged 5 years later. The bridge was collided by ships at the time of landing of the Typhoon

Conson in 2010. The 3 cargo vessels were drifted due to strong winds and hit the bridge. The

damages occurred. A girder was deformed and two cables were broken its plastic covers and

wires were exposed. Traffic of the bridge had restricted then. Repair design was carried out in

2011, and works had done in 2012. Damaged parts of the girder was cut and welded by new

parts. Damage girder was repaired using temporary supporting member called “Temporary

By- Pass Truss”. Damaged 2 cables were replaced by new one using “Temporary Hanger

System”. After completion of rehabilitation, the bridge has been in full re-opening in use in

the end of 2012 and the final inspection on defect liability period was passed in 2014. The

bridge is a cable stayed structure with RC and steel composite girder and its repair /

rehabilitation work was a rare case and precious experience.

Introduction

The Binh Bridge was opened at Hai Phong city in Viet Nam in 2005. The bridge is crossed

over Cum River. The river is a big port just down stream side of the bridge and close to the

sea. The bridge is a 17- span continuous steel bridge and the three spans at the center are

supported by cables as cable stayed system. Span configuration is 50m +6@60m +100m

+260m + 100 m +6@60m +50m =1,280m (Total length). Road width is 22.5m and it has 4

lanes for cars and 2 pedestrian ways. Deck system is Precast RC deck and its thickness is

260mm.

In July 17, 2010 at 22h00, Typhoon Conson landed in Hai Phong City. At that time three

vessels which had anchored at Bach Dang shipyard, about 1 km far from the Binh bridge,

broke anchor ropes and were drifted towards upstream side, and hit and crashed to the bridge

and they were blocked at main span area (at locations near stay cable C23 to C28).

Five towboats were mobilized to rescue the ships, then two ships were pulled out to a nearby

wharf on July 18. From the morning of July 19, rescue workers cut off the cabin on a stacked

ship to loosen it from the bridge and finally the ship was pulled out on the same day.

Upper parts of ships attacked the girder and cables and it caused severe damages. However

structure such as slabs, cross beams and anchorages of cable were not suffered much,

therefore the bridge was escaped from collapse. Then the traffic was restricted only for small

cars, motor bikes and pedestrians at the no- damage side.

After this incident, CHODAI and IHI group did initial check according to requests by the

Page 3: SHIP COLLISION: REPAIR & REHABILITATION OF A CABLE STAYED ...istanbulbridgeconference.org/2014/ISBN978-605-64131-6-2/papers/088.pdf · Ship Collision: Repair & Rehabilitation Of A

bridge owner. Then later, CHODAI did FS design, detailed design in 2011, Construction

Supervision in 2012 together with construction by IIA of IHI group.

Photo 1 Binh Bridge after completion Photo 2 Collision of ships (July 17, 2010)

Photo 3 Stack of a ship (July 19, 2010) Fig 1 Location of collided ships

Fig 2 Location of damage of the bridge

Page 4: SHIP COLLISION: REPAIR & REHABILITATION OF A CABLE STAYED ...istanbulbridgeconference.org/2014/ISBN978-605-64131-6-2/papers/088.pdf · Ship Collision: Repair & Rehabilitation Of A

After Repair /Rehabilitation works in 2012, the bridge was full re-opening and has been in

use since the end of 2012. The final inspection on defect liability period was passed in 2014.

Damage of Ship Collision

Damages were occurred on girder, cables, handrails and curb on slab etc (See Fig 1).

Especially damage of girder and cables were needed special consideration.

Damage of Girder

The damaged part of steel girder was about 23m, from stay cable 27B to stay cable 30B.

Photo 4 Damage of girder Fig 3 Max. deformation of girder

Main girder was deformed and partially buckled due to collision, the flange was buckled.

Web plate was bended inward from C145 to location of cable 29B. At location of cable 28B,

web plate was punched by cross girder. From C140 location of cable 30B, the paint was

damaged at many parts.

Damage of cables

Two stay cable No 23B and 24B were damaged. The length of scratch portion is 2.0m and

7.6 m respectively. HDPE covers were peeled off and wires were exposed.

Photo 5 Damaged cables (Front 23B, then 24B) Photo 6 Close-up of damage 24B

Page 5: SHIP COLLISION: REPAIR & REHABILITATION OF A CABLE STAYED ...istanbulbridgeconference.org/2014/ISBN978-605-64131-6-2/papers/088.pdf · Ship Collision: Repair & Rehabilitation Of A

Fig 4 Location of damage of cable 24B

Evaluation of the damage

Main girder: After the collision, main girder was serious damaged. Web plate, flange, vertical

stiffener and horizontal stiffener were seriously buckled and distorted exceeding the elastic

limit of steel structure. It is necessary to replace all part of web plate, flange, vertical stiffener

and horizontal stiffener.

Cable: Inside wires were affected by seawater. Therefore it was necessary to be replaced by

new cables.

Cross girder: there was no damage, so the repair work was not necessary.

Deck slab, concrete curb: there was no crack on the deck slab. The damaged concrete curb

had to be repaired. The repair work of damaged pieces of deck slab and concrete curb needed

to be carried out at the same time.

Handrail: buckling and bending portions had to be replaced.

Concepts & Design

The bridge is a cable stayed and the damaged parts are supported by cables. Therefore it was

necessary to check its repair procedure carefully. The girder support not only bending &

shear force but also axial compression force. Also effects of construction live load and

equipment should be checked.

To check the safety of repair works, a 2-D frame model was used for F/S design. Then a 3-D

frame model was applied for D/Design. The damaged part of girder was modeled by two

beams and upper beam was no- damage parts and bottom beam was cut parts and temporally

reinforcement members. Among the damaged girder, there are two cables. This means cutting

of girder would cause big bending of existing parts. Thorough these design, it was recognized

that temporary reinforcement of guider was needed during cutting & attaching procedure of

damaged parts of girder (See Fig 5).

A temporary reinforcement was designed as a truss envelope on damaged parts with

triangular cross section called “Temporary By-Pass Truss” later.

Damaged two cables were decided to be replaced because of possibility of corrosion inside.

Removal of a cable was checked in design and confirmed its safety.

Page 6: SHIP COLLISION: REPAIR & REHABILITATION OF A CABLE STAYED ...istanbulbridgeconference.org/2014/ISBN978-605-64131-6-2/papers/088.pdf · Ship Collision: Repair & Rehabilitation Of A

Fig 5 Results of cutting without reinforcement by a frame model

Reinforcement concept of girder is shown in the followings:- Original condition (1) and

adding of temporary reinforcement (2), cutting of damaged parts (3), then loading of

construction live load & equipment (4), and welding new parts (5) and removal of temporary

reinforcement finally (6).

Fig 6 Concept of girder cutting & attaching with reinforcement

Temporary removal of cable was checked using frame models. It was confirmed that the

removal of a cable one by one after repair of girder was safe.

Repair sequence were firstly scaffolding under damaged girder, secondly assembling of

reinforcement member, thirdly repair of girder, fourthly disassembling of reinforcement

member, and replacement of cables finally.

Repair & Rehabilitation Works

According to the above mentioned designs, repair and rehabilitation works had done.

Page 7: SHIP COLLISION: REPAIR & REHABILITATION OF A CABLE STAYED ...istanbulbridgeconference.org/2014/ISBN978-605-64131-6-2/papers/088.pdf · Ship Collision: Repair & Rehabilitation Of A

Gider repair works

Damaged part was located under cable supported area. Thus the temporary support system

had to be assembled by compact parts to move through cables.

A truss system was adopted as temporary supporting member called “Temporary By- Pass

Truss (TB Truss)”. The TB Truss was designed as triangular section to fix existing upper

flange and to make an envelope along damaged parts. Both ends of TB Truss were welded

tightly by anchor blocks to the existing girder.

Cutting area was revised according to examination at the site. Cutting line was designed with

smooth as possible. This line was copied at site and brought to a factory to cutting new parts.

Cutting was done rough cutting first, and then groove cut was carried out. New parts were

temporally assembled at cut place and welded parts by parts.

Fig 7 Cutting & attaching of girder and TB Truss

Photo 7 Installation of scaffolding Photo 8 Cutting of damaged girder

Photo 9 TB Truss (After girder cutting) Photo 10 Installation of new girder parts

Page 8: SHIP COLLISION: REPAIR & REHABILITATION OF A CABLE STAYED ...istanbulbridgeconference.org/2014/ISBN978-605-64131-6-2/papers/088.pdf · Ship Collision: Repair & Rehabilitation Of A

Cable replacement works

Damaged 2 cables were located among healthy cables. Therefore replacements of new cables

were using existing cable as support system not to damage other cables. The details of a

method was developed by the Contractor and called “Temporary Hanger System (TH

system)”. The TH system consists of roller-parts which were connected by wires to move on

existing cable and to hang temporary hangers. Up side of wire was connected to a winch to

move the system up and down along existing cable.

Removal of damaged cable was done by next procedure. Firstly the TH system was

assembled/ put on an upper side cable. Secondly temporary hangers were connected between

the TH system and a damaged cable. Thirdly both ends of damaged cable were taken off from

anchorages. Fourthly the up side of wire was released and the cable was moved towards the

girder and cut it down to pieces.

Installation of a new cable was done by a next procedure. Firstly the HT system was put on

girder by hanging from a wire. Secondly a new cable was pulled out from a cable unreeler.

Thirdly both a new cable and the HT system were connected by hangers and pulled up

towards tower top. Fourthly both ends of a new cable were anchored at anchorages at tower/

girder sides.

Fig 8 Major equipment

Fig 9 Dismantlement of damaged cable Photo 11 Dismantlement of a cable

Page 9: SHIP COLLISION: REPAIR & REHABILITATION OF A CABLE STAYED ...istanbulbridgeconference.org/2014/ISBN978-605-64131-6-2/papers/088.pdf · Ship Collision: Repair & Rehabilitation Of A

Fig 10 Installation of a new cable Photo 12 Installation of a new cable

Monitoring and Study

During the works, monitoring of stress of girder and the TB truss were carried out to confirm

force transition from damaged girder to TB truss and TB truss to new girder parts.

Measurement of cable tension and vertical alignment of deck were carried out too.

Corrosion inspection inside cable was carried out at a girder side socket part. At the time of

ship collision, damage cable was intruded by rain/ sea water. Four days later after damage,

the damaged parts were cover by plastic tape. A 7.6-m cover was damaged and exposed it

wires. But it locates 5.8 m apart from the socket. Wire corrosion was checked 1.7 m length of

cable parts from the socket. Among them a 1.5 m- part was filled by poly-butadiene rubber.

Results showed that there were almost new wires condition about 1.2 m from the socket

except stripe white rust. And there were white rust with slight brown rust at other parts.

Findings of rust inside cable after 2 years, means urgent waterproof measure should be taken

when a cable will be damaged its cover.

Photo 13 A-Line (top) 0-30cm Photo 14 A-Line 60-80cm Close-up

Page 10: SHIP COLLISION: REPAIR & REHABILITATION OF A CABLE STAYED ...istanbulbridgeconference.org/2014/ISBN978-605-64131-6-2/papers/088.pdf · Ship Collision: Repair & Rehabilitation Of A

Fig 11 Corrosion map inside of the cable 24B

Conclusions

The Binh Bridge was damaged due to collision of three ships at the landing of the Typhoon

Conson in 2010. Two cables were broken their covers and a steel edge girder was buckled/

distorted. Traffic of the bridge had restricted then.

- Thorough FS and Detailed design, it was recognized that reinforcement of girder was

needed during cutting & attaching procedure of damaged parts of girder.

- Damage girder was repaired using temporary reinforcement member called “Temporary By-

Pass Truss”. It was a truss envelope system on a damaged girder.

- Damaged 2 cables were replaced by new one using “Temporary Hanger System”. Two

damaged cables among other health one were removed and replaced one by one.

- Inside inspection of cable was done near a socket and corrosion was found. This means

urgent water proof measure of damaged cable is important issue of maintenance.

Acknowledgments

The works had successfully completed to meet a planed schedule, eight months, with

cooperation of many people. Authors have to appreciate related people especially, CHODAI:

Mr. K. Ishida(FD-PM), Mr. N. Son Tung (BE), Hai Phong Bridge Projects Management

Department: D.Tuan Anh(GD, PM at the time), IIA: Mr. T. Tokuchi(DE), Mr. S.

Kawabata(CE), Mr. T. Idani(DE). The works was funded as an urgent assistance by the Japan

International Cooperation Agency (JICA) under ODA program.

References 1. Kurino S, Kudo M, Yamamoto Y, Kawabata S, Tokuchi T, Idani T. Serious Damages by Ship

Collision and its Repair Works: Binh Bridge in Vietnam (in Japanese). Kyoryo to Kiso (Bridge and

Foundation) Vol. 47, 2013 -5, pp33-38