shms feaisbility studies of q1 , qd30 and support structure · 2004. 1. 21. · 12 gev/c, 2 mstr,...

34
SHMS Feasibility Studies of Q1, QD30 and Support Structure Jan 10 , 2004 Paul Brindza SHMS Design Update-Revised QD30 coil Feasibility Studies of SHMS Critical Technical Elements Future SHMS Work Conclusions

Upload: others

Post on 02-Oct-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: SHMS Feaisbility Studies of Q1 , QD30 and Support Structure · 2004. 1. 21. · 12 Gev/c, 2 mStr, 1x 10^-3 dP/P, 5.5 ... The Q1 current lead design will likely require redesign and

SHMS Feasibility Studies of Q1, QD30 and Support Structure Jan 10 , 2004 Paul Brindza SHMS Design Update-Revised QD30 coil Feasibility Studies of SHMS Critical Technical Elements Future SHMS Work Conclusions

Page 2: SHMS Feaisbility Studies of Q1 , QD30 and Support Structure · 2004. 1. 21. · 12 Gev/c, 2 mStr, 1x 10^-3 dP/P, 5.5 ... The Q1 current lead design will likely require redesign and

SHMS Design update-revised QD 30 coil The original QD30 design used a high current density( 11,000 A/cm^2) to achieve the required dipole field and compact size. The dipole winding was redesigned to lower the current density ( 5600 A/cm^2) and make the QD30 completely cryogenically stable. This was achieved by doubling the number of turns in the dipole winding, Redesigning the coil for a bit more efficiency and Re-arranging all winding to keep the magnetic performance. The current , field and temperature ,margins were re-eavluated The dipole and quad coil stability were calculated Cryogenic stability represents the most conservative design condition available. I have located 24,000 meters of Surplus SSC SC cable and am acquiring for the QD30 . This 30 strand Rutherford cable easily meets the requirements of the QD30 We still have to do some testing, soldering into a copper channel and insulate. This superconductor has a value of $ 900,000 !! Happy Holidays!!

Page 3: SHMS Feaisbility Studies of Q1 , QD30 and Support Structure · 2004. 1. 21. · 12 Gev/c, 2 mStr, 1x 10^-3 dP/P, 5.5 ... The Q1 current lead design will likely require redesign and
Page 4: SHMS Feaisbility Studies of Q1 , QD30 and Support Structure · 2004. 1. 21. · 12 Gev/c, 2 mStr, 1x 10^-3 dP/P, 5.5 ... The Q1 current lead design will likely require redesign and

Original designQD30 with 10,600 A/cm^2 current density

Page 5: SHMS Feaisbility Studies of Q1 , QD30 and Support Structure · 2004. 1. 21. · 12 Gev/c, 2 mStr, 1x 10^-3 dP/P, 5.5 ... The Q1 current lead design will likely require redesign and

Revised QD30 with 5060 A/cm^2 current density

Page 6: SHMS Feaisbility Studies of Q1 , QD30 and Support Structure · 2004. 1. 21. · 12 Gev/c, 2 mStr, 1x 10^-3 dP/P, 5.5 ... The Q1 current lead design will likely require redesign and

critical current at 4.4 K and load lines

0

2000

4000

6000

8000

10000

12000

14000

16000

18000

0 1 2 3 4 5 6 7 8

Field (Tesla)

Cur

rent

Am

ps Series1

Series2

Series3

Series4

critical current at 4.4 K

SHMS Dipole load lineSHMS quad load line

critical current at 6.97 K

SHMS superconductor short sample curve and qd30 quad and dipole load lines

Page 7: SHMS Feaisbility Studies of Q1 , QD30 and Support Structure · 2004. 1. 21. · 12 Gev/c, 2 mStr, 1x 10^-3 dP/P, 5.5 ... The Q1 current lead design will likely require redesign and

MAD conductor critical current and coil load lines

0

2000

4000

6000

8000

10000

12000

14000

16000

18000

0 1 2 3 4 5 6 7 8

Field in Coils (Tesla)

Cur

rent

(Am

ps)

Series1

Series2

Series3

Series4

Series5

Series6

conductor critical [email protected]

MAD1 dipole

MAD1 quad

MAD2 dipole

MAD2 quad

conductor critical current @ 7 17 K

MAD superconductor short sample curve and MAD quad and dipole load lines

Page 8: SHMS Feaisbility Studies of Q1 , QD30 and Support Structure · 2004. 1. 21. · 12 Gev/c, 2 mStr, 1x 10^-3 dP/P, 5.5 ... The Q1 current lead design will likely require redesign and

Cryogenic stability by Stekely Criteria qd30 D qd30 Q MAD1 D MAD1 Q MAD2 D MAD2 Q Bmax T 4.8 4.1 3.7 4.3 4.8 4.65 RRR 200 200 200 200 200 200 area cm^2 0.8 0.8 0.8 0.8 0.8 0.8 perimeter cm^2 5 5 5 5 5 5 gamma 0.6 0.6 0.6 0.6 0.6 0.6 Tc K 6.97 7.46 7.87 7.15 7.54 8.07 To K 4.42 4.42 4.42 4.42 4.42 4.42 Tc-To K 2.55 3.04 3.45 2.73 3.12 3.65 Imax A 5600 5040 4111 5750 4100 2800 Ic (B,4.2K) A 12912 15057 16367 14425 12912 13356 Ic(B,4.4K) A 12333 14381 15632 13778 12333 12757 Hc W/cm^2/K 0.2 0.2 0.2 0.2 0.2 0.2 rho(273) ohm-cm 1.60E-06 1.60E-06 1.60E-06 1.60E-06 1.60E-06 1.60E-06 Rho(4.4K) 8.00E-09 8.00E-09 8.00E-09 8.00E-09 8.00E-09 8.00E-09 Rho(Bmax,4.4K) 3.10E-08 2.77E-08 2.58E-08 2.86E-08 3.10E-08 3.03E-08 alpha 0.79 0.48 0.26 0.72 0.35 0.14 RRR Residual Resitivity Ratio Hc Peak Nucleate Boiling Heat Flux perimeter of conductor gamma per cent of perimeter exposed to Lhe Tc Critical temperature To Operating temperature Tc-To Tempearture margin Rho(Bmax,4.4T) Resistivity at max Magnetic field and operating temperature Ic(Bmax,T0) Critical current at max field and operating temperature Alpha Stekely Parameter Alpha= I^2 * rho/(Hc*A*L*(Tc-To)) Alpha Ratio of heat produce to heat lost per unit length Alpha < 1 magnet is unconditionally stable !

Page 9: SHMS Feaisbility Studies of Q1 , QD30 and Support Structure · 2004. 1. 21. · 12 Gev/c, 2 mStr, 1x 10^-3 dP/P, 5.5 ... The Q1 current lead design will likely require redesign and

SHMS Critical technical elements Q1 at 1350 Amps QD30 combined function magnet Support Structure for SHMS at 5.5 Degree Lab Angle These items represent the essential and critical technical elements that allow SHMS to achieve the required performance. 12 Gev/c, 2 mStr, 1x 10^-3 dP/P, 5.5 degrees lab angle. We all think they represent good ideas but does anyone else think so? To answer this question we commissioned three feasibility studies.

Page 10: SHMS Feaisbility Studies of Q1 , QD30 and Support Structure · 2004. 1. 21. · 12 Gev/c, 2 mStr, 1x 10^-3 dP/P, 5.5 ... The Q1 current lead design will likely require redesign and

Q1 Feasibility Study Goal: study original design and verify that the magnet is still reliable at 30 % higher current. Makes use of the fact that the original Q1 was very conservative in many respects. Critical questions: Magnetic performance,required gradient with acceptable multipole content and EFL Note: This was verified by JLAB Superconductor performance , stability margins and viability of original SC wire Ability of cold iron yoke to contain the higher magnetic forces Systems acceptability at higher current ie.current leads, power supply , energy dump, quench detection, controls, cryogenics etc etc Cost to produce two to the same design in 2003 Who would produce these magnets?

Page 11: SHMS Feaisbility Studies of Q1 , QD30 and Support Structure · 2004. 1. 21. · 12 Gev/c, 2 mStr, 1x 10^-3 dP/P, 5.5 ... The Q1 current lead design will likely require redesign and

Q1 Feasibility Study It seemed natural to approach Oxford Instruments as the original manufacturer of the HMS cold iron quads However they are no longer in the "on of a kind " magnet business. An Oxford Instruments "spin off " company, Space Cryo-Magnetics(SCM) was selected The principals of SCM include John Ross lead engineer of CLAS Steve Milward lead engineer for HMS quads SCM principal business is the design and manufacturering of specialty one of a kind SC magnets usually with with extreme requirements! The study was performed by Steve Milward and Matt Coates of SCM And Martin Wilson (he literally wrote the book on SC magnet design)

Page 12: SHMS Feaisbility Studies of Q1 , QD30 and Support Structure · 2004. 1. 21. · 12 Gev/c, 2 mStr, 1x 10^-3 dP/P, 5.5 ... The Q1 current lead design will likely require redesign and

Q1 Feasibility Study-results The Q1 design uprated for operation at 1350 Amps is completely viable The Q1 superconductor would be stable at 1350 Amps by a more restricted definition and operation without training can be expected. Based on Minimum Quench Energy analysis fy Martin Wilson 10

Fig 1: The conductor specification

Reprinted from M.Wilson report "Computed Minimum Quench Energy for Q1 at 1350 amps" 12-18-02

Page 13: SHMS Feaisbility Studies of Q1 , QD30 and Support Structure · 2004. 1. 21. · 12 Gev/c, 2 mStr, 1x 10^-3 dP/P, 5.5 ... The Q1 current lead design will likely require redesign and

Fig 7 shows the same event as a function of time, plus a second run with slightly larger heat pulse which triggers a quench.

0 0.005 0.01 0.0154

6

8

10

12

U2 nt,

U22 nt,

nt dt⋅

Appendix 4 lists detailed results of all the MQE calculations, which are summarized in Table 1. For the same conductor, there are 12 different assumptions about heat transfer and 3 different critical currents.

Table 1: Summary of the MQE calculations for Q1 conductor.

Ic Amp ⇒ 2500 2000 1500 run Heat transfer MQE mJ 1 Zero heat transfer 3.69 2.79 1.49 2 Chandratilleke bare surface without transient HT 4.84 3.94 2.53 3 Ogata bare surface irreversible transition, no transient HT 5.44 4.65 4 Ogata bare surface reversible transition, no transient HT 5.49 4.65 3.43 5 Ogata bare surface reversible transition, with transient HT 26.1 24.4 22.0 6 Ogata bare surface irreversible transition, with transient HT 25.9 7 Chandra 5um coating reversible transition no transient 10.5 8.7 7.1 8 Chandra 5um coating reversible transition with transient 27.0 25.0 22.6 9 Ogata 15um coating reversible transition no transient 44.0 39.4 32.5 10 Ogata 15um coating reversible transition with transient 58.9 55.4 48.7 11 Chandra 50um coating reversible transition no transient 8.1 6.6 12 Chandra 50um coating reversible transition with transient 14.6 10.4

Reprinted from M.Wilson report "Computed Minimum Quench Energy for Q1 at 1350 amps" 12-18-02

Page 14: SHMS Feaisbility Studies of Q1 , QD30 and Support Structure · 2004. 1. 21. · 12 Gev/c, 2 mStr, 1x 10^-3 dP/P, 5.5 ... The Q1 current lead design will likely require redesign and

Table 2: MQE Calculated for Other Magnets

Magnet MQE mJ

LHC dipole 0.36 MRI solenoid 0.25 CLAS Torus 44

"According to the MQE calculations, it is not necessary to specify the critical current to be as high as 2500A. However, if it does not cost much more, the high Ic will be useful in providing some extra temperature margin for dealing with large distributed disturbances, if they exist. To summarize:

a) the specified conductor should be given a ~ 15µm coating of insulation. b) using this conductor, Q1 should reach it's operating current without any training." Reprinted from M.Wilson report "Computed Minimum Quench Energy for Q1 at 1350 amps" 12-18-02

Page 15: SHMS Feaisbility Studies of Q1 , QD30 and Support Structure · 2004. 1. 21. · 12 Gev/c, 2 mStr, 1x 10^-3 dP/P, 5.5 ... The Q1 current lead design will likely require redesign and

Q1 Feasibility-Results The original design of quench detection and quench protection would work and keep the magnet within safe temperature p in the event of a qu ed fast dump. The coil components are still conservative at the higher magnetic forces and especially the coil insulation would still be e.

he original yoke magnetic force restraint is adequate but SCM suggests a complete FE nalysis to verify the design of stainles force retaining ring around the yoke

safe

arameters ench induc

very conservativ

Ta The Q1 current lead design will likely require redesign and retesting to meet the fail requirement at the higher operating current.

Page 16: SHMS Feaisbility Studies of Q1 , QD30 and Support Structure · 2004. 1. 21. · 12 Gev/c, 2 mStr, 1x 10^-3 dP/P, 5.5 ... The Q1 current lead design will likely require redesign and

Conclusions from Study performed by SCM inc.

ay of rotecting the magnet from quench damage even at the higher current and has

lthough not covered by the scope of this work, we recommend that the following items should be reviewed: • The cross section of the magnet gas-cooled current leads will need to be increased in proportion to the increase in current. Account must be taken of possible over-running for demonstration purposes. • Pressure relief paths from the helium vessel to the outside must be checked for the worst-case fault condition of loss of insulating vacuum and quench protection failure. I would be very surprised if either of the above had a significant impact on the existing design. " Reprinted from S. Milward Space Cryo-Magnetics Letter to P. Brindza 21-02-03

• There are no structural reasons why the Q1 design cannot be run at the higher perating current. Note: we have assumed that the spacing between the o

magnets is sufficient for there not to be significant magnetic forces between the quadrupoles, and indeed between the quadrupoles and any other pieces of erromagnetic material. f

• The magnet will be acceptably stable against quenching as compared with other magnets known to be in operation but will not be cryostable. • The quench management system designed for the original Q1 is a good wpsufficient performance margin for the task (subject to review of contactors now available) A

Page 17: SHMS Feaisbility Studies of Q1 , QD30 and Support Structure · 2004. 1. 21. · 12 Gev/c, 2 mStr, 1x 10^-3 dP/P, 5.5 ... The Q1 current lead design will likely require redesign and

Q1 Feasibility - results

e cost for two Q1 magnets was estimated at 1.8 M$ commercially fabricated in 2003. Th It is reasonable to expect that SCM would be an interested fabricator for the Q1's

Page 18: SHMS Feaisbility Studies of Q1 , QD30 and Support Structure · 2004. 1. 21. · 12 Gev/c, 2 mStr, 1x 10^-3 dP/P, 5.5 ... The Q1 current lead design will likely require redesign and

QD Feasibility Study Somewhat unique design concept (identical except in size to MAD)

hares some similarities with MHD magnets from the late 70's and early 80's. arge very stable SC magnets with dipole and gradient fields superimposed.

Size comparable but QD fields are lower especially dipole component. Critical questions: Magnetic performance Superconductor performance , stability margins, reliable first operations Suitability of available SSC cable for this design Managable coil force containment with available structure Suitability of available SC magnet systems for this design ie. Power supplies , cryogenics, controls, quench protection, current leads, cold to warm supports Cost to produce without a prototype Who are likely candidate manufacturers?

SL

Page 19: SHMS Feaisbility Studies of Q1 , QD30 and Support Structure · 2004. 1. 21. · 12 Gev/c, 2 mStr, 1x 10^-3 dP/P, 5.5 ... The Q1 current lead design will likely require redesign and

QD Feasibility Study Consulting engineer Eddy Leung was selected Ed has a 30 year career working with SC magnets at FNAL , General Dynamics and

pany

er for the Chicago Cyclotron conversion at FNAL, orked on MFTF-B magnet system, coal separation quadrupole, SSC dipoles,

f the guest vestigator program

ombination of industry and lab experience and familiarity with JLAB was compelling.

General Atomics and now leads Magtech, an SC magnet consulting com Ed was lead enginewSC fault current limiters Ed worked on the design of the HMS SC dipole in 1988 at JLAB as part oin C

Page 20: SHMS Feaisbility Studies of Q1 , QD30 and Support Structure · 2004. 1. 21. · 12 Gev/c, 2 mStr, 1x 10^-3 dP/P, 5.5 ... The Q1 current lead design will likely require redesign and

QD Feasibility Study-results

ll be stable by conservative criteria and apable of excitation without training.

s.

ard forces from nt to

from Coils D1 and D5.

si sized to withstand external 15 psi and internal 50psi

ower supplies , current leads , instrumentation , quench protection and the JLAB magnet ontrol reservoir are all simple , reliable low risk readily available components.

QD30 coil with copper stabilized SSC cable wic Cold mass structure will be capable of supporting the coil forces with low stres The outer preload cylinder (3 cm. thick) is sufficient to support the outwthe Quad coils and the inner cylinder ( 1.25 cm thick) Helium vessel is sufficiesupport the inward forces Cryostat will be a low stress vessel designed to withstand an internal pressure of 50 PThe vacuum vessel is QD30 cryostat are just simple cylinders thus a low risk approach Pc

Page 21: SHMS Feaisbility Studies of Q1 , QD30 and Support Structure · 2004. 1. 21. · 12 Gev/c, 2 mStr, 1x 10^-3 dP/P, 5.5 ... The Q1 current lead design will likely require redesign and
Page 22: SHMS Feaisbility Studies of Q1 , QD30 and Support Structure · 2004. 1. 21. · 12 Gev/c, 2 mStr, 1x 10^-3 dP/P, 5.5 ... The Q1 current lead design will likely require redesign and
Page 23: SHMS Feaisbility Studies of Q1 , QD30 and Support Structure · 2004. 1. 21. · 12 Gev/c, 2 mStr, 1x 10^-3 dP/P, 5.5 ... The Q1 current lead design will likely require redesign and

SHMS QD30 Feasibility -results Cost to produce one QD30 in Industry with all overheads ans fees included 7.4 M$ Schedule to fabricate is 25months Design can be executed in industry at low risk. The outsatnding question though is which industry?

Page 24: SHMS Feaisbility Studies of Q1 , QD30 and Support Structure · 2004. 1. 21. · 12 Gev/c, 2 mStr, 1x 10^-3 dP/P, 5.5 ... The Q1 current lead design will likely require redesign and

Potential Sources for the QD30 foreign and domestic

ocal Source

rocure large sub-assemblies from industry Assemble, integrate and test at JLAB JLAB does not at present have a magnet assembly and test shop nor the staff to man one! US sources AMI and CMI make small one of a kind (usually) solenoids IGC and GE each make ~ 50 solenoids per year for MRI GA makes predominantly paper magnets Wang, NMR makes one of a kind magnets of any size Japan -- Mitsubishi, Hitachi , Toshiba Europe-- Ansaldo, Alsthon, Accel, SCM, Noel ….. Collaborative Procurement Sources National Labs that sometimes do work for others, usually on a cost plus basis! FNAL, BNL, LBL, NSCL, NHMFL, MIT/PFSC, Saclay, BINP

L Design at JLAB P

Page 25: SHMS Feaisbility Studies of Q1 , QD30 and Support Structure · 2004. 1. 21. · 12 Gev/c, 2 mStr, 1x 10^-3 dP/P, 5.5 ... The Q1 current lead design will likely require redesign and

Support Structure feasibility Critical questions:

ees

ppropriate available systems such as wheels, jacks, rotation drive and bearings

its in Hall C

its on existing pivot

its with HMS at 10.5 degrees

ost to design and produce

Reaches 5.5 degr Evaluation of JLAB concept as viable Supports Q1's and QD30 and roomy shield house with acceptable stress' A F F F C

Page 26: SHMS Feaisbility Studies of Q1 , QD30 and Support Structure · 2004. 1. 21. · 12 Gev/c, 2 mStr, 1x 10^-3 dP/P, 5.5 ... The Q1 current lead design will likely require redesign and

Support Structure feasibility Contract to study the SHMS structure was placed

ith a consulting engineer Roy M. Vaughn

oy was chief engineer for support structures for HMS, SOS and HRS

w R

Page 27: SHMS Feaisbility Studies of Q1 , QD30 and Support Structure · 2004. 1. 21. · 12 Gev/c, 2 mStr, 1x 10^-3 dP/P, 5.5 ... The Q1 current lead design will likely require redesign and

Support Structure feasibility A support carriage has been designed that adequately supports the magnets and shield

ouse with low stress.

he carriage fits the HMS and reaches 5.5 degrees when HMS is at 10.5

ue to the unusual shape of the main beam for this carriage necessary for clearance and chieving the small angle to the beam the inherent stiffness will not be as good as HMS nd deflections though elastic will be larger.

h T DaA

Page 28: SHMS Feaisbility Studies of Q1 , QD30 and Support Structure · 2004. 1. 21. · 12 Gev/c, 2 mStr, 1x 10^-3 dP/P, 5.5 ... The Q1 current lead design will likely require redesign and
Page 29: SHMS Feaisbility Studies of Q1 , QD30 and Support Structure · 2004. 1. 21. · 12 Gev/c, 2 mStr, 1x 10^-3 dP/P, 5.5 ... The Q1 current lead design will likely require redesign and
Page 30: SHMS Feaisbility Studies of Q1 , QD30 and Support Structure · 2004. 1. 21. · 12 Gev/c, 2 mStr, 1x 10^-3 dP/P, 5.5 ... The Q1 current lead design will likely require redesign and

Design cost estimate 777 K$ Structure Fabrication cost estimate 1827 K$ SHMS support structure can be fabricated as small ~ 100 K$ packages in competent local Tidewater Virginia Fab. shops just as HMS, SOS and HRS components were produced. Coincindentally, a 100 K$ welded steel artifact just fits thru the Hall C entrance!

Page 31: SHMS Feaisbility Studies of Q1 , QD30 and Support Structure · 2004. 1. 21. · 12 Gev/c, 2 mStr, 1x 10^-3 dP/P, 5.5 ... The Q1 current lead design will likely require redesign and

Future work for the SHMS Q1

forces 6 months nd the cold yoke design

Bid to award 12 months Fabrication 18-24 months Test and commissioning 6 months (minimum) Install working Q1's on SHMS in Hall C 3 months Cooldown and retest 1 month

Complete Finite element analysis of magnetic a Mechanical design revisions 3 months Preparation of Bid package 3 months

Page 32: SHMS Feaisbility Studies of Q1 , QD30 and Support Structure · 2004. 1. 21. · 12 Gev/c, 2 mStr, 1x 10^-3 dP/P, 5.5 ... The Q1 current lead design will likely require redesign and

Future work for SHMS QD30 Preliminary Engineering Design 24 months

Magnetic force analysis (3 mo.)

Finite element analysis of cold mass (3 mo.)

Coil manufacturing design (3 mo.)

Final Design and Fabrication of QD30 24 months Test and Commissioning 6 months Install on SHMS in Hall C 3 months Cooldown and Retest 1 month

Magnetic redesign (3mo.) Cold mass design (6 mo.) Cold mass drawings (3 mo.) Preparation of Technical Sepecification 3 months Preparation of bid package drawings 3 months Bid to award 12 months

Page 33: SHMS Feaisbility Studies of Q1 , QD30 and Support Structure · 2004. 1. 21. · 12 Gev/c, 2 mStr, 1x 10^-3 dP/P, 5.5 ... The Q1 current lead design will likely require redesign and

Future work for SHMS structure

id preliminary Engineering Design of structure 3 months

12 months

s 3 months

3 months

HMS support structure design and fabrication 18 months

Bid package preparation

hs

h

B Preliminary Engineering design Finite Element analysis of structure component Bid Final Detail Design S Detail design of components Fabrication of support structure components Installation and assembly in Hall C 12 mont Test controls for rotation 1 mont

Page 34: SHMS Feaisbility Studies of Q1 , QD30 and Support Structure · 2004. 1. 21. · 12 Gev/c, 2 mStr, 1x 10^-3 dP/P, 5.5 ... The Q1 current lead design will likely require redesign and

Conclusions

ound, verified and affordable concepts for all critical SHMS components

gn

D-0

ew Money

ew Staff - Present staff is not large enough to run the program and build SHMS! New Place to Test the SC magnets - Hall C is busy!

S Excellent design base to proceed to preliminary engineering and detailed desi Q1 and Support Structure fabrication path very clear QD30 fabrication will require some cultivation of the marketplace What do I need to do this !! C N N