shri bharatkumar gangdasbhai patel · applicant: shri bharatkumar gangdasbhai patel mineral: black...
TRANSCRIPT
Project No. 716
Prefeasibility Study Report
Of
Black Trap Quarry
(Lease Area: 1-33-00 Hect.)
By Lease Holder
Shri Bharatkumar Gangdasbhai Patel
At Survey No.: In front of S. No. 333,334, Karad
River Bed,
Village: Amarapura,
Taluka: Savli,
District: Vadodara
August, 2018
Applicant: Shri Bharatkumar Gangdasbhai Patel Mineral: Black Trap Lease Area (Ha): 1-33-00
2 716
Index
Section Details Page No. 1. Executive Summary 1 2. Introduction of the Project/ Background
Information 1
3. Project Description 4 4. Site Analysis 10 5. Planning Brief (Planning Concepts) 12 6. Proposed Infrastructure 12 7. Rehabilitation and Resettlement (R&R) Plan 13 8. Project Schedule & Cost Estimates 14 9. Analysis of Proposals 15
List of Annexure
No. Title 1. Order of lease grant from district office 2. Lease Agreement 3. Lease Location Map
List of Plates
No. Title 1. Location Plan 2. Satellite Image Plan/ Key Plan (10 km Radius
Applicant: Shri Bharatkumar Gangdasbhai Patel Mineral: Black Trap Lease Area (Ha): 1-33-00
3 716
1. Executive Summary The existing lease area of Black Trap Quarry of Shri Bharatkumar Gangdasbhai Patel (Survey No. In front of S. No. 333,334, Karad River Bed) is located near village: Amarapura, Taluka: Savli, District: Vadodara of Gujarat state. The lease had been granted by district office order no. GV/QL/BLACKTRAP/3675/439-444 dated 19.01.2006 which further registered on 12:00:00 AM for 10 years. The lease area (1-33-00 Ha) comprises Govt waste Land type. This is an existing quarry which is worked upon by Open Cast semi-mechanized method. The present rate of production is 35000 MTPA, whereas the proposed rate of production is 80000 MT/ Year. The estimated project cost is Rs. 20,00,000. The expected life of mine is 5.3 Years. Basalt (Black Trap) deposits are source for demand in construction work in all sectors. Amarapura basalt deposits are huge source for demand in construction work in Vadodara and surrounding districts. Shri Bharatkumar Gangdasbhai Patel is experienced in Black Trap mining and involved in the quarry operation since 2006. As per the statutory obligation this project needs Environment Clearance (E.C.) from department of Gujarat Pollution Control Board (GPCB), Gujarat for grant of lease and to start quarry operations. Thus accordingly project proponent has submitted Form-1, PFR, and copy of approval letter from department of mines and Geology Gujarat to the state level environmental assessment authority (SEIAA) of Gujarat constituted by MOEF, GOI for issuing environmental clearance as per EIA, September 14th 2006 notification.
2. Introduction of the Project/ Background Information 2.1 Identification of Project and Project Proponent:
The existing lease area of Black Trap Quarry of Shri Bharatkumar Gangdasbhai Patel (Survey No. In front of S. No. 333,334, Karad River Bed) is located near village: Amarapura, Taluka: Savli, District: Vadodara of Gujarat state. The lease had been granted by district office order no. GV/QL/BLACKTRAP/3675/439-444 dated 19.01.2006 which further registered on 12:00:00 AM for 10 years. The lease area (1-33-00 Ha) comprises Govt waste Land type. The project was identified by the Department of Mines and Geology of Gujarat during exploration. This is an existing quarry which is worked upon by Open Cast semi-mechanized method. The present rate of production is 35000 MTPA, whereas the proposed rate of production is 80000 MT/ Year. The estimated project cost is Rs. 20,00,000. The expected life of mine is 5.3 Years. Shri Bharatkumar Gangdasbhai Patel is experienced in Black Trap mining and involved in the quarry operation since 2006.
2.2 Brief description of nature of the project:
This is an existing Black Trap mining project. As per EIA Notification dated 14th Sep, 2006 and as amended till date, the project falls under, Category “B2” by considering the area of project is 1-33-00 Ha only. A location map of the project is shown in the next section. It has been proposed to excavate approximately 80000 MTPA of Black Trap mineral from the S. No. In front of S. No. 333,334, Karad River Bed by open - cast semi mechanized method. The lease area is 1-33-00 ha. Total geological reserves are
Applicant: Shri Bharatkumar Gangdasbhai Patel Mineral: Black Trap Lease Area (Ha): 1-33-00
4 716
613560 MT. The expected life of mine will be 5.3 years. The mineral Black Trap will be transported by hired trucks. At the end of lease period, the total excavated area will be 1.15 ha. The entire
excavated area will be used as a water reservoir. Water reservoir will ultimately help
in recharging the water table and also help in cultivation and irrigation purpose for
nearby area. Water requirement of 1.0 KLD for the proposed project activity will be
met by water tankers supply from nearby village source. The depth of water table is
80 m (Pre-Monsoon) to 70 m (Post-Monsoon) below the general ground level. Thus,
water table will not encounter during working of the mine.
2.3 Need of the Project and It’s Importance to the Country/ Region
Black Trap is base of all types of Building works, Construction of Road, Construction of Cement Concrete road. The need of Stone in all fields are very essential as it is a compulsory material for all types of construction and Industries fields. Stone Mines are providing employments to the local Labour in Rural area, as the labour of rural area have no any work for labour. They are unemployed, thus this existing mine is providing work to many labours and it is a good employment. The Black Trap is treated as minor minerals. The operations of the quarries include blasting.
2.4 Demand – Supply Gap Black Trap is one of the important component in infrastructural development in
building construction projects in flooring & wall furnishing as well as construction of
monuments, temples mosques etc. It has high demand in the market due to increased
domestic, industrial and other infrastructural activities.
2.5 Imports Vs Indigenous Production In the current market scenario, import of Black Trap is not envisaged, it is for indigenous use only.
2.6 Export Possibility Not applicable as proposed mine is for domestic use.
2.7 Domestic/ Export Markets Domestic demand is one of the main reason for the rapid growth of Black Trap business in India. Thus, domestic market for Black Trap as road material is well established. Black Trap produced from the proposed quarry will be used to fulfill the domestic demand. No export is proposed at this stage
2.8 Employment Generation (Direct and Indirect) due to the Project
Direct Employment: Manager:- 01 Mine Workers:- 10 Indirect Employment:
Applicant: Shri Bharatkumar Gangdasbhai Patel Mineral: Black Trap Lease Area (Ha): 1-33-00
5 716
Truck driver for transportation, helpers and other ancillary activities of tea stall, workshop to repair trucks for the region which amount to employment of about 20 persons.
3. Project Description: 3.1 Type of project including interlinked and interdependent projects,
if any: The project is a small scale semi mechanized mining project. This project does not have any interlink or interdependency on any other projects.
3.2 Location (Map Showing General Location, Specific Location, and Project Boundary & Project Site Layout) With Coordinates
The Black Trap Quarry Project of lease area 1-33-00 hectare is located at Survey No.:
In front of S. No. 333,334, Karad River Bed, Village: Amarapura, Taluka: Savli, District:
Vadodara having geographical location Northing 22°38'1.13" & Easting 73°14'34.59"
and falls on Topo Sheet No. 46 F/2 of Survey of India. (Refer Plate No. 1)
A. General Location Map:
Applicant: Shri Bharatkumar Gangdasbhai Patel Mineral: Black Trap Lease Area (Ha): 1-33-00
6 716
B. Satellite Image (Satellite Image (Bird’s Eye View):
C. Plan View (Satellite Image)
Applicant: Shri Bharatkumar Gangdasbhai Patel Mineral: Black Trap Lease Area (Ha): 1-33-00
7 716
3.3 Details of alternate sites considered and the basis of selecting the proposed site, particularly the environmental considerations given into should be highlighted. No alternative site has been taken into consideration as the mineral (Black Trap) is available at this site.
3.4 Size of magnitude of Operation:
The quarry area of existing Black Trap mine is 1-33-00 hectare and proposed production capacity is 80000 MTPA.
3.4.1 Regional Geology: Regionally the Alluvium, Deccan Trap, Cretaceous rocks and Precambrian rocks are exposed in the region. The alluvial are Cambay basin deposits of recent age. Deccan Trap is thick lava flows which overlie the cretaceous sedimentary rocks. Cretaceous sedimentary rocks mainly sand stone, shale and conglomerate are found in the region. The Precambrian rocks of Granitic intrusions are found: Regional Geology:-
Alluvium
Deccan Lava flows Cretaceous sedimentary rocks
Precambrian Granitic intrusions 3.4.2 Local Geology:
Geologically the area comprises of Deccan traps. Deccan traps are found upto depth of 170 meters depths from the drilling of local tube wells. Intertrappean sedimentary bends are found at places.
3.5 Project description with Process detail: The mine will be worked by means of opencast semi-mechanized method which includes drilling, blasting, loading and transportation. 3.5.1 Open Cast Mining:
• The proposed operations will be carried out by open cast semi-mechanized method.
• The salient features of proposed mining method are:- • The excavation will be carried out by blasting, loading and transportation. • The proposed bench height will be kept up to the depth of the mine. Vertical
face will be developed as the rock is very compact. • The ultimate pit slope will be maintained as per IBM safety regulations. • Percussion drills will be used in combination with diesel operated
compressor. The diameter of the drill will be 32 mm. The depth of hole will be around 1.5 m.
Applicant: Shri Bharatkumar Gangdasbhai Patel Mineral: Black Trap Lease Area (Ha): 1-33-00
8 716
• Haul roads will be made at 1 in 16 gradient for connecting workings, stack and linking the nearest road.
• Loading of mineral is proposed manually or by excavators on dumpers. • Controlled blasting will be done by using explosives, boosters, detonators and
fuse. • Optimum quantity of explosives will be used per hole to prevent overcharging,
which will result in flying fragment and under charging to prevent formation of large boulders.
• Non-el initiation system of blasting will be used for minimizing ground vibrations.
3.5.2 General No. of Working days: 275/ year No. of shifts per day: 1 3.5.3 Mechanization: Major mining equipment is an integral part of mine production planning. The details of the equipment used in mining operation are listed below:-
S No. Machines Make with Numbers Specifications 1 Excavator* 1 Tata Hitachi 220 1.0 m3 bucket capacity 2 Tractor mounted
compressor 1 Ford 36 360 cfm
3 Percussion drill machine*
1 Atlas Copco 32 mm
4 Drill rods 2 Atlas Copco 32 mm 5 Dumper 1 Tata 15 m3 180 hp 6 Water pump 1 Crompton 5 HP
*On hire basis
3.5.4 Loading and Transportation: The Black Trap based industries requirement will be loaded by Shovel (1.0 m3) and transported by 25 T dumpers in crude for of various factories.
3.5.4 Loading and Transportation: The area is devoid of Top soil on mineralized zone. Waste produced during mining in coming years shall be dumped at the site shown on the plan. The site is very near to the working pits. There is no mineralization in the proposed site and the area is free from any agricultural activity also.
Process flow of Quarry project:
Drilling (32 mm dia holes)
Blasting (Spacing 1.0 m & Burden 0.8 m)
Applicant: Shri Bharatkumar Gangdasbhai Patel Mineral: Black Trap Lease Area (Ha): 1-33-00
9 716
Loading (1.0 m3 bucket capacity)
Transportation (15 m3 capacity)
3.6 Raw Material Required Along With Estimated Quantity, Likely Source, Marketing Area Of Final Products, Mode Of Transport Of Raw Material And Finished Product:
No raw material will be required for the production of mineral. ROM will be loaded on to the dumpers and sent to crushing plant for sizing and sorting.
3.7 Resource optimization/ Recycling and reuse envisaged in the project, if any ,
should be briefly outlined Not envisaged.
3.8 Availability of water its source, energy/ Power requirement and source should be given. Water is required for drinking and spraying purpose. The daily water requirement will be 1.0 KLD. Tube will outside the mines site will provide the water for all the purposes. 11 kv line is installed at the site from Gujarat Electricity Board which provides power required.
3.9 Quantity of wastes to be generated (liquid and solid) and scheme for their
management/ disposal Unsized pieces of stones are considered as waste and the same is crushed and re-used.
4.0 SITE ANALYSIS
4.1 CONNECTIVITY (Mine Site)
Table No.7: Connectivity
PARTICULARS DISTANCE & DIRECTION
( FROM LEASE BOUNDRY)
Nearest Railway Station Dakor Railway Station at 15.04 km towards NW direction
Nearest Airport Vadodra Airport at 33.75 km towards South direction
Nearest Highway NH-59 at 15.89 km towards NW direction,
SH-63 at 1.73 km towards East direction
Applicant: Shri Bharatkumar Gangdasbhai Patel Mineral: Black Trap Lease Area (Ha): 1-33-00
10 716
4.2 LAND FORM, LAND USE AND LAND OWNERSHIP
4.2.1 LAND FORM The mining lease area comprises of undulating terrain with highest elevation of 29
mRL and minimum elevation of 25 mRL. There is no water body or nallah within
the lease area.
4.2.2 LAND USE The present land use pattern is as below:-
Table 8: Land Use Pattern
4.2.3 LAND OWNERSHIP The land as per revenue records is Govt. waste Land (1-33-00 ha.). The location
Plan is enclosed as Plate No.-I
4.3 TOPOGRAPHY
The topography of this area is almost flat. The area is devoid of Top soil and with
scree of no agricultural importance. Hummocks rising 3 to 5 m from surrounding
level in the lease area. Highest elevation of 29 mRL and lowest elevation being 25
mRL.
S. No. Particulars Present Land-use
(ha.)
1. Top Soil 0.0000
2. Excavation Pit (Voids Only)
0.0000
3. Waste Dump (External*) 0.0500
4. Mineral Reject(External*) 0.0000
5. Infrastructure including office
Road
0.0080
6. Afforestation 0.0000
7. Undisturbed Area 1.2720
Total 1-33-00
Applicant: Shri Bharatkumar Gangdasbhai Patel Mineral: Black Trap Lease Area (Ha): 1-33-00
11 716
4.4 Existing land use pattern (agriculture ,non-agriculture ,forest, water bodies
(including area under crz), shortest distances from the periphery of the project to
periphery of the forest ,national park, wild life sanctuary, eco sensitive area, water
bodies (distance from the HFL of the river), CRZ.in case of notified industrial area, a
copy of the gazette notification should be given.
Land-use pattern: the area falls under level 2 categories of strip mine & quarry.
Lease area is located at 0.51 km distance from village Amarapura. No national park, the
lease area is located at topographic high, small tributaries originates from nearby areas, so
no HFL level of any river is applicable. CRZ is not applicable to the lease area.
4.5 EXISTING INFRASTRUCTURE
Railway: Dakor Railway Station at 15.04 km towards NW direction.
Airport: Vadodra Airport at 33.75 km towards South direction.
Highway: NH-59 at 15.89 km towards NW direction, SH-63 at 1.73 km towards East direction.
Power: Nearby villages Amarapura is having a power supply.
Water: Tube well outside the lease area will provide the water for all the purposes.
4.6 SOIL CLASSIFICATION
Soil may be defined as a thin layer of earth’s crust, which serves as a medium for the growth
of plants. The soil characteristics include both physical and chemical details. The soil found
in the region is in situ soil and found in consolidated from. The soil is brown to reddish in
color, fine to very fine-grained having a thickness of 0.5 to 1.0m.
4.7 CLIMATE DATA FROM SECONDARY SOURCES.
The climate of this region is characterized by a hot summer and dryness in the non- rainy
season. Climate in a year may be divided into four seasons. The cold season from December
to February is followed by the hot season from March to May. The south west monsoon
season is from June to September while the month of October and November from post
monsoon season.
The average annual rainfall for last five years in the district is 705 mm. following table shows
the month wise rainfall and departure for last five years.
Applicant: Shri Bharatkumar Gangdasbhai Patel Mineral: Black Trap Lease Area (Ha): 1-33-00
12 716
Table showing rainfall data for Vadodara district (last five years)
YEAR
January February March April May June
R/F
%DEP.
R/F
%DEP.
R/F
%DEP.
R/F
%DEP.
R/F
%DEP.
R/F %DEP.
2009 0 -50 0 -50 0 -50 0 -50 0 -50 1.7 -98 2010 0 -50 0 -50 0 -50 0 -50 0 -50 21.9 -79 2011 0 -50 0 -50 0 -50 0 -50 0 -50 4.1 -96 2012 0 -50 0 -50 0 -50 0 -50 0 -50 25 -77 2013 0 -50 0 -50 0 -50 6.8 1600 0 -50 127.
9 -16
YEAR
July Aug Sep Oct Nov Dec
R/F %DEP.
R/F %DEP.
R/F %DEP.
R/F
%DEP.
R/F
%DEP.
R/F
%DEP.
2009 285 -12 144.8
-44 3 -98 13.6
-11 2.8 -75 0 -50
2010 264.8
-18 408.6
57 117.3
-20 0 -50 33.8
196 0.6 -57
2011 145.8
-50 374.6
44 59.8 -60 0 -50 0 -50 0 -50
2012 112.9
-57 222.5
-14 272 81 0 -50 0 -50 0 -50
2013 409.8
41 191.5
-26 231.9
54 59.3
229 0 -50 0 -50
4.8 SOCIAL INFRASTRUCTURE AVAILABLE
The lease area is located at 7.63 km distance from Savli. Primary & Secondary education
facility is available at Savli. The Hospital is also situated at Savli.
5. Planning Brief
5.1 Planning concept (type of industrial, facilities, transportation etc.)
Town and Country planning/development authority classification
It is a mining industry in which open cast semi-mechanized mining method will be practiced.
Present rate to production is 35000 TPA and proposed rate of production is 80000 TPA.
5.2 Population Projection
There will be recruitment of local workers (10). There will be no change in the population
projection of the most nearest & farther most villages of the project. There are a total of 29
Applicant: Shri Bharatkumar Gangdasbhai Patel Mineral: Black Trap Lease Area (Ha): 1-33-00
13 716
villages in the buffer zone of the study area. As per census of India (2011) the total
population Amarapura population is 3914 with 817 household. Total male & female
population is 1988 & 1926 respectively.
5.3 Land Use Planning (Break-up along with green belt etc)
S. No. Particulars Present Land use (ha) At the end of Mine Life I Excavated Pits 0.6500 1.1500 II Top-soil storage 0.0000 0.0000 III Waste dump/ OB/
Backfill 0.0000 0.0000
IV Mineral Storage 0.0000 0.0000 V Roads/ Railways 0.0050 0.1100 Vi Green Belt 0.0000 0.0700 VII Tailing Pond 0.0000 0.0000 VIII Mineral
Processing Plan 0.0000 0.0000
IX Tailing ponds 0.0000 0.0000 X Others 0.0000 0.0000 XI Unworked Area 0.6750 0.0000 Total: 1.3300 1.3300
5.4 Assessment of infrastructure demand (physical & social).
Modern health facilities and medical stores are around.
5.5 Amenities/facilities
First AID-A first aid kit will be provided for giving aid to the injured person.
6.0 Proposed infrastructure
6.1 Industrial area (processing area).
The area is very well connected by road network to the mines, district headquarter
etc. The road area is self-sufficient to cater the needs of the project. Hence, no
infrastructure is proposed.
6.2 Green belt.
Green belt will be developed along the periphery of mines and backfilled area. 500
numbers of Plants will be planted during mine life in consultation with local forest
office and CPCB guidelines.
Applicant: Shri Bharatkumar Gangdasbhai Patel Mineral: Black Trap Lease Area (Ha): 1-33-00
14 716
6.3 Social infrastructure.
Education facilities: -for village school, distribution of books for children are proposed.
6.4 Connectivity (traffic and transportation road/ rail/ metro / water
ways etc.)
500m. of kutcha road having width of 5 mt. then there is pucca road of 5 mt width. No
railway, metro, water transportation is required.
6.5 Drinking water management (source & supply of water)
Tube well outside the lease area will provide the water for all the purposes.
6.6 Sewerage system
Domestic waste water will be directed to septic tank followed by soak which will be
cleaned time to time.
6.7 Industrial waste management.
As there is no industrial waste, hence not applicable
6.8 Solid waste management
Overburden is being stacked on the periphery of the boundary which will be backfilled
at the end of mine life. Plantation will be done on the backfilled area.
6.9 Power requirement & supply / source.
Power line of 11 kv is available at lease from Gujarat electricity board.
7. Rehabilitation and resettlement (R&R) plan
Policy to be adopted (central/state) in respect of the project affected persons including
home oustees, land oustees and landless laborer (a brief outline to be given).
Not applicable as there is no displacement or dislocation.
8. Project schedule & cost estimates
Likely date of starts of construction and likely of completion (Time schedule for
the project to be given).
This is an operating lease working since 2006. Mine life about 5.3 years.
Applicant: Shri Bharatkumar Gangdasbhai Patel Mineral: Black Trap Lease Area (Ha): 1-33-00
15 716
Cost of Project The approx cost of the proposed project will be 20 Lac. The details of the cost the project is given here under in Table:
Table : Cost of the Project
Sr. No Details Amount in Rs. Lac 1. Land & Building 02
2. Plant & Machinery 18 Total 20
9. Analysis of proposal (final recommendations)
Financial and social benefits with special emphasis on the benefit to the local people
including tribal population, if any, in the area.
The project will bring economic benefits to the state by the way of royalty for mineral. The
mining operations shall be providing employment to approximately 6 persons directly in the
excavation. Most of the local people are likely to be benefited. The project operation will
provide livelihood to the poorest section of the society. Mining is expected to have positive
impact on socio-economic life of people living in nearby villages.
(Signature of Applicant)
ANNEXURE 1: LEASE ORDER
ANNEXURE 2: LEASE DEED
ANNEXURE 3: LEASE MAP