Simultaneous Destination and Schedule Optimization
with Minemax Scheduling Technology at Newmont
Xiaolin Wu SME, Phoenix
Newmont Technical Services, Mine Engineering March 2010
Jim Butler
Minemax Pty Ltd
![Page 2: Simultaneous Destination and Schedule Optimization with ...€¦ · Simultaneous Destination and Schedule Optimization with Minemax Scheduling Technology at Newmont Xiaolin Wu SME,](https://reader034.vdocument.in/reader034/viewer/2022051815/603bad733a39296708289894/html5/thumbnails/2.jpg)
1. Newmont Overview
2. Minemax Overview
3. Production Scheduling Concept Through a Simple Example
4. Minemax Scheduler Features
5. Minemax Scheduler Implementation at Newmont
6. Minemax Scheduler Examples at Newmont
7. Concluding Remarks
Contents
2
![Page 3: Simultaneous Destination and Schedule Optimization with ...€¦ · Simultaneous Destination and Schedule Optimization with Minemax Scheduling Technology at Newmont Xiaolin Wu SME,](https://reader034.vdocument.in/reader034/viewer/2022051815/603bad733a39296708289894/html5/thumbnails/3.jpg)
History• Founded in 1921 and publicly traded since 1925
• Headquartered in Greenwood Village near Denver, Colorado
• ~31,000 employees and contractors people employed worldwide
• First gold company selected to be part of the Dow Jones Sustainability
World Index in 2007
• The only gold company included in the S&P 500 Index and Fortune 500
• Liquid gold stock with ~8 M shares traded daily
• Market capitalization: ~$23 B
• Proven and probable gold reserves of 85 million equity ounces and an aggregate
land position of ~38,840 square miles as of December 31, 2008
• Gold Produced: 6.3 Moz, Equity Gold Sales: 5.2 Moz, Copper Sales: 290 Mlb
Newmont Mining Corporation
3
![Page 4: Simultaneous Destination and Schedule Optimization with ...€¦ · Simultaneous Destination and Schedule Optimization with Minemax Scheduling Technology at Newmont Xiaolin Wu SME,](https://reader034.vdocument.in/reader034/viewer/2022051815/603bad733a39296708289894/html5/thumbnails/4.jpg)
Newmont’s Operations
4
Operations
Major Projects
Hope Bay
Nevada (3)
Conga (2)
Batu Hijau
Boddington
Ahafo (2)
Akyem
Jundee
Kalgoorlie
Tanami
Waihi
La Herradura (1)
Yanacocha (4)
Sites Using Minemax (# Projects) Sites Implementing Minemax (# Projects)
![Page 5: Simultaneous Destination and Schedule Optimization with ...€¦ · Simultaneous Destination and Schedule Optimization with Minemax Scheduling Technology at Newmont Xiaolin Wu SME,](https://reader034.vdocument.in/reader034/viewer/2022051815/603bad733a39296708289894/html5/thumbnails/5.jpg)
1. Newmont Overview
2. Minemax Overview
3. Production Scheduling Concept Through a Simple Example
4. Minemax Scheduler Features
5. Minemax Scheduler Implementation at Newmont
6. Minemax Scheduler Examples at Newmont
7. Concluding Remarks
Contents
5
![Page 6: Simultaneous Destination and Schedule Optimization with ...€¦ · Simultaneous Destination and Schedule Optimization with Minemax Scheduling Technology at Newmont Xiaolin Wu SME,](https://reader034.vdocument.in/reader034/viewer/2022051815/603bad733a39296708289894/html5/thumbnails/6.jpg)
History• Founded in 1996
• Based in Perth, Australia
• Vision to provide mining companies with easy-to-use software applications for creating practical and economically optimal plans
• Product innovation track record:
– Minemax Scheduler is the original solution for strategic planning and has set the standard for strategic schedule optimization at mid-to-large-size mining companies world-wide.
– iGantt for underground scheduling is the first product in the market to integrate a Gantt chart, 3D mine visualization, and dynamic reporting in a single application.
– Tempo is currently the only product in the market for integrated and optimized mine planning and scheduling in a collaborative environment.
• Minemax software is now used in over 35 countries by companies including Anglo, Barrick, BHP Billiton, Newmont, Rio Tinto, Vale and Xstrata
Minemax
6
![Page 7: Simultaneous Destination and Schedule Optimization with ...€¦ · Simultaneous Destination and Schedule Optimization with Minemax Scheduling Technology at Newmont Xiaolin Wu SME,](https://reader034.vdocument.in/reader034/viewer/2022051815/603bad733a39296708289894/html5/thumbnails/7.jpg)
1. Newmont Overview
2. Minemax Overview
3. Production Scheduling Concept Through a Simple Example
4. Minemax Scheduler Features
5. Minemax Scheduler Implementation at Newmont
6. Minemax Scheduler Examples at Newmont
7. Concluding Remarks
Contents
7
![Page 8: Simultaneous Destination and Schedule Optimization with ...€¦ · Simultaneous Destination and Schedule Optimization with Minemax Scheduling Technology at Newmont Xiaolin Wu SME,](https://reader034.vdocument.in/reader034/viewer/2022051815/603bad733a39296708289894/html5/thumbnails/8.jpg)
Why Optimization and Production Scheduling?
8
Example1. 10 ore blocks overlain by 10 waste
blocks
2. Mining: <= 5 blocks per year
3. Net value for an ore block is $200
4. Waste mining cost: $100 per block
5. Annual discounting rate: 10% starting
from the 2nd year
6. Total value
10 (ore block) x $200 – 10 (waste
blocks) x $100 = $1000
Modified from Hustrulid & Kuchta, 1995, Open Pit Mine Planning & Design, pp 565-569
Waste
Ore
![Page 9: Simultaneous Destination and Schedule Optimization with ...€¦ · Simultaneous Destination and Schedule Optimization with Minemax Scheduling Technology at Newmont Xiaolin Wu SME,](https://reader034.vdocument.in/reader034/viewer/2022051815/603bad733a39296708289894/html5/thumbnails/9.jpg)
Mine Sequences 1 & 2
9
Scenario 1. Removal of waste followed by ore mining
NPV = (-$500/1.100) + (-$500/1.101) + ($1000/1.102) + $1000/(1.103) = $623.2
Scenario 2. One year of pre-stripping followed by both ore (3 blocks/year)
and waste (2 blocks/year) miningNPV = (-$500/1.100) + ($400/1.101) + ($400/1.102) + $700/(1.103) = $720.1
Scenario 1
5W5W5O5O
$623.2
Scenario 2
5W2W3O2W3O1W4O
$720.1
1 3
1 3
1 3
1 3
1 3
2 4
2 4
2 4
2 4
2 4
1 2
1 2
1 2
1 3
1 3
2 3
2 4
3 4
3 4
4 4
![Page 10: Simultaneous Destination and Schedule Optimization with ...€¦ · Simultaneous Destination and Schedule Optimization with Minemax Scheduling Technology at Newmont Xiaolin Wu SME,](https://reader034.vdocument.in/reader034/viewer/2022051815/603bad733a39296708289894/html5/thumbnails/10.jpg)
Mine Sequences 3 & 4
10
Scenario 3. Mining of waste one block ahead of ore
NPV = (-$100/1.100) + (-$100/1.101) + ($100/1.102) + $700/(1.103) = $799.5
Scenario 4. Modified Scenario 3 (Years 3 and 4)NPV = ($100/1.100) + ($100/1.101) + ($400/1.102) + $400/(1.103) = $822.0
Scenario 3
3W2O3W2O3W2O1W4O
$799.5
Scenario 4
3W2O3W2O2W3O2W3O
$822.0
1 1
1 1
1 2
2 2
2 3
2 3
3 4
3 4
3 4
4 4
1 1
1 1
1 2
2 2
2 3
2 3
3 3
3 4
4 4
4 4
![Page 11: Simultaneous Destination and Schedule Optimization with ...€¦ · Simultaneous Destination and Schedule Optimization with Minemax Scheduling Technology at Newmont Xiaolin Wu SME,](https://reader034.vdocument.in/reader034/viewer/2022051815/603bad733a39296708289894/html5/thumbnails/11.jpg)
Scenario Sequence NPV $
1 5W5W5O5O 623.2
2 5W2W3O2W3O1W4O 720.1
3 3W2O3W2O3W2O1W4O 799.5
4 (Best) 3W2O3W2O2W3O2W3O 822.0
Mine Sequences Summary
11
NPV Difference: (822.0-623.2)/623.2 = 32%
![Page 12: Simultaneous Destination and Schedule Optimization with ...€¦ · Simultaneous Destination and Schedule Optimization with Minemax Scheduling Technology at Newmont Xiaolin Wu SME,](https://reader034.vdocument.in/reader034/viewer/2022051815/603bad733a39296708289894/html5/thumbnails/12.jpg)
Minemax Set-up
12
MineMax Model: Products and Attributes
![Page 13: Simultaneous Destination and Schedule Optimization with ...€¦ · Simultaneous Destination and Schedule Optimization with Minemax Scheduling Technology at Newmont Xiaolin Wu SME,](https://reader034.vdocument.in/reader034/viewer/2022051815/603bad733a39296708289894/html5/thumbnails/13.jpg)
Alternative Processes
13
Material could go to Mill or Waste Dump
![Page 14: Simultaneous Destination and Schedule Optimization with ...€¦ · Simultaneous Destination and Schedule Optimization with Minemax Scheduling Technology at Newmont Xiaolin Wu SME,](https://reader034.vdocument.in/reader034/viewer/2022051815/603bad733a39296708289894/html5/thumbnails/14.jpg)
Does Minemax Find the Best Sequence?
14
Maximum total movement: 5 blocks
![Page 15: Simultaneous Destination and Schedule Optimization with ...€¦ · Simultaneous Destination and Schedule Optimization with Minemax Scheduling Technology at Newmont Xiaolin Wu SME,](https://reader034.vdocument.in/reader034/viewer/2022051815/603bad733a39296708289894/html5/thumbnails/15.jpg)
Does Minemax Find the Best Sequence?
15
![Page 16: Simultaneous Destination and Schedule Optimization with ...€¦ · Simultaneous Destination and Schedule Optimization with Minemax Scheduling Technology at Newmont Xiaolin Wu SME,](https://reader034.vdocument.in/reader034/viewer/2022051815/603bad733a39296708289894/html5/thumbnails/16.jpg)
Does Minemax Find the Best Sequence?
16
• Bench by bench precedences within a stage
• Inter-stage precedence with lag
![Page 17: Simultaneous Destination and Schedule Optimization with ...€¦ · Simultaneous Destination and Schedule Optimization with Minemax Scheduling Technology at Newmont Xiaolin Wu SME,](https://reader034.vdocument.in/reader034/viewer/2022051815/603bad733a39296708289894/html5/thumbnails/17.jpg)
Does Minemax Find the Best Sequence?
17
![Page 18: Simultaneous Destination and Schedule Optimization with ...€¦ · Simultaneous Destination and Schedule Optimization with Minemax Scheduling Technology at Newmont Xiaolin Wu SME,](https://reader034.vdocument.in/reader034/viewer/2022051815/603bad733a39296708289894/html5/thumbnails/18.jpg)
Does Minemax Find the Best Sequence?
18
![Page 19: Simultaneous Destination and Schedule Optimization with ...€¦ · Simultaneous Destination and Schedule Optimization with Minemax Scheduling Technology at Newmont Xiaolin Wu SME,](https://reader034.vdocument.in/reader034/viewer/2022051815/603bad733a39296708289894/html5/thumbnails/19.jpg)
Does Minemax Find the Best Sequence?
19
Minemax
Schedule
Year 1 - 3W2O
Year 2 - 3W2O
Year 3 - 2W3O
Year 4 - 2W3O
= Best Scenario 4
Waste Blocks
Ore Blocks
![Page 20: Simultaneous Destination and Schedule Optimization with ...€¦ · Simultaneous Destination and Schedule Optimization with Minemax Scheduling Technology at Newmont Xiaolin Wu SME,](https://reader034.vdocument.in/reader034/viewer/2022051815/603bad733a39296708289894/html5/thumbnails/20.jpg)
Does Minemax Find the Best Sequence?
20
Minemax Schedule
Disc Cash Flow
Year 1 - $100
Year 2 - $91
Year 3 - $331
Year 4 - $301
Total: $822
= Best Scenario 4
![Page 21: Simultaneous Destination and Schedule Optimization with ...€¦ · Simultaneous Destination and Schedule Optimization with Minemax Scheduling Technology at Newmont Xiaolin Wu SME,](https://reader034.vdocument.in/reader034/viewer/2022051815/603bad733a39296708289894/html5/thumbnails/21.jpg)
1. Newmont Overview
2. Minemax Overview
3. Production Scheduling Concept Through a Simple Example
4. Minemax Scheduler Features
5. Minemax Scheduler Implementation at Newmont
6. Minemax Scheduler Examples at Newmont
7. Concluding Remarks
Contents
21
![Page 22: Simultaneous Destination and Schedule Optimization with ...€¦ · Simultaneous Destination and Schedule Optimization with Minemax Scheduling Technology at Newmont Xiaolin Wu SME,](https://reader034.vdocument.in/reader034/viewer/2022051815/603bad733a39296708289894/html5/thumbnails/22.jpg)
• A mixed-integer LP modeling and optimization tool for strategic and long range mine plan optimization and production scheduling
• Optimize life-of-mine NPV
subject to
Mining and process constraints
Stockpile and ore blending requirements
Product targets
Minemax Scheduler
22
NPV =
T - 1
t = 0
∑(Rprod
t– Cm
t– Cp
t– Cf
t)
(1+d)t
Rprod: revenue from the final product
Cm: mining cost
Cp: processing cost
Cf: fixed cost
T: number of time periods
d: discounting rate
t: time
![Page 23: Simultaneous Destination and Schedule Optimization with ...€¦ · Simultaneous Destination and Schedule Optimization with Minemax Scheduling Technology at Newmont Xiaolin Wu SME,](https://reader034.vdocument.in/reader034/viewer/2022051815/603bad733a39296708289894/html5/thumbnails/23.jpg)
• Designed in response to industry requirements, used by Rio Tinto, BHP, Newmont, Barrick, etc
• Simultaneously multi-period NPV optimization
• Min-Max mining limits by time period by mining phase ; tonnes or truck hours based
• Min-Max product targets by time period ; tonnes or mill hours based
• Ore blending controlled by the Min-Max attribute limits by time period
• Flexible time-dependent revenue definition by product prices, variable costs and recoveries
Minemax Scheduler Main Features 1
23
![Page 24: Simultaneous Destination and Schedule Optimization with ...€¦ · Simultaneous Destination and Schedule Optimization with Minemax Scheduling Technology at Newmont Xiaolin Wu SME,](https://reader034.vdocument.in/reader034/viewer/2022051815/603bad733a39296708289894/html5/thumbnails/24.jpg)
• Number of concurrent mining phases, mining precedence
• Concurrent schedule and process destination optimization
• Cut-off grade optimization
• Flexible modelling capabilities
– Series and parallel material flow
– Alternative process routes
– Immediate stockpiles
– Multiple mines
• Rich collection of spreadsheet reports and charts
Minemax Scheduler Main Features 2
24
![Page 25: Simultaneous Destination and Schedule Optimization with ...€¦ · Simultaneous Destination and Schedule Optimization with Minemax Scheduling Technology at Newmont Xiaolin Wu SME,](https://reader034.vdocument.in/reader034/viewer/2022051815/603bad733a39296708289894/html5/thumbnails/25.jpg)
• Minemax Scheduler enables the definition of key decision points associated with alternative material destinations
• Allows a single optimization to simultaneously consider both time of scheduling and material destination
Simultaneous Destination and Schedule Optimization
![Page 26: Simultaneous Destination and Schedule Optimization with ...€¦ · Simultaneous Destination and Schedule Optimization with Minemax Scheduling Technology at Newmont Xiaolin Wu SME,](https://reader034.vdocument.in/reader034/viewer/2022051815/603bad733a39296708289894/html5/thumbnails/26.jpg)
• Cut-off and cut-over grades are an output rather than an input into the optimization
Cut-over grades as an output
![Page 27: Simultaneous Destination and Schedule Optimization with ...€¦ · Simultaneous Destination and Schedule Optimization with Minemax Scheduling Technology at Newmont Xiaolin Wu SME,](https://reader034.vdocument.in/reader034/viewer/2022051815/603bad733a39296708289894/html5/thumbnails/27.jpg)
1. Newmont Overview
2. Minemax Overview
3. Production Scheduling Concept Through a Simple Example
4. Minemax Scheduler Features
5. Minemax Scheduler Implementation at Newmont
6. Minemax Scheduler Examples at Newmont
7. Concluding Remarks
Contents
27
![Page 28: Simultaneous Destination and Schedule Optimization with ...€¦ · Simultaneous Destination and Schedule Optimization with Minemax Scheduling Technology at Newmont Xiaolin Wu SME,](https://reader034.vdocument.in/reader034/viewer/2022051815/603bad733a39296708289894/html5/thumbnails/28.jpg)
• Address strategic and long range mine plan optimization and production scheduling tool gap– Replace manual spreadsheet based technique
– Apply Minemax in Strategic Scheduling, Operation Sizing and Long Range Scheduling
• Integrate Minemax in the long range mine planning process
• Provide solutions to complex mine planning problems through utilization of the proven optimization technology and software tool– Multi-mine and multi-phase with different ore types
– Multi-metal (gold, silver, copper, …) with variable recoveries
– Multi-process options (leach, mill, autoclave, …) with variable processing costs and plant throughputs by ore types
– Multi-destinations (leach pads, stockpiles and waste disposals)
– Ore feed blending requirements (head grades, arsenic, mercury, CuCN, zinc concentrate grade, argillic ore percent, etc.)
– Alternative process options to maximize revenues under process capacities
Minemax Scheduler Implementation Goals
28
![Page 29: Simultaneous Destination and Schedule Optimization with ...€¦ · Simultaneous Destination and Schedule Optimization with Minemax Scheduling Technology at Newmont Xiaolin Wu SME,](https://reader034.vdocument.in/reader034/viewer/2022051815/603bad733a39296708289894/html5/thumbnails/29.jpg)
• Software Demonstration – Feb 2007
• Proof of Concept Study – April 2007– Multi-process: mill and copper leach; Multi-metal: gold, copper and silver– Variable mining and process costs, metallurgical recoveries, mill throughputs– 24 mining phases
• Alternative Software Trial Evaluation – December, 2007
• Implementation/Training/Documentation/Validation and User Endorsement – June 2008 to December 2009– 10 Minemax Scheduler Setups: new projects, SA/NA/Africa operating mines, merge and acquisition projects
• Ongoing Minemax Projects, Training/Support/Documentation
Minemax Scheduler Implementation Milestones
29
Minemax
Demonstration
February 2007
Proof of
Concept
Study
April 2007
Alternative
Software
Evaluation
December 2007
Implementation
Training
September 2008
– December
2009
Ongoing
Projects
Training/
Support
Documentation
![Page 30: Simultaneous Destination and Schedule Optimization with ...€¦ · Simultaneous Destination and Schedule Optimization with Minemax Scheduling Technology at Newmont Xiaolin Wu SME,](https://reader034.vdocument.in/reader034/viewer/2022051815/603bad733a39296708289894/html5/thumbnails/30.jpg)
1. Pit Limit Determination
Geologic Models
Economic Inputs
Metallurgical Parameters
4. Strategic Scheduling
3. Pushback/Phase Design
5. Operation Sizing
6. Long Range Planning
7. Mid- Range Planning
2. Pit Limit Sensitivity
8. Short Range Planning
Pre
cis
ion
Ac
cu
rac
y
Minemax Usage
30
Minemax: 4, 5 and 6
![Page 31: Simultaneous Destination and Schedule Optimization with ...€¦ · Simultaneous Destination and Schedule Optimization with Minemax Scheduling Technology at Newmont Xiaolin Wu SME,](https://reader034.vdocument.in/reader034/viewer/2022051815/603bad733a39296708289894/html5/thumbnails/31.jpg)
Pit Optimization: LG Cones
31
![Page 32: Simultaneous Destination and Schedule Optimization with ...€¦ · Simultaneous Destination and Schedule Optimization with Minemax Scheduling Technology at Newmont Xiaolin Wu SME,](https://reader034.vdocument.in/reader034/viewer/2022051815/603bad733a39296708289894/html5/thumbnails/32.jpg)
Pit and Phase Design
32
Pit Mining Phases
![Page 33: Simultaneous Destination and Schedule Optimization with ...€¦ · Simultaneous Destination and Schedule Optimization with Minemax Scheduling Technology at Newmont Xiaolin Wu SME,](https://reader034.vdocument.in/reader034/viewer/2022051815/603bad733a39296708289894/html5/thumbnails/33.jpg)
Mine Plan Optimization and Scheduling
33
Year 1 Year 2 Year 3Legend
Mining Phases
Life-of-Mine Plan
Minemax
0
10
20
30
40
50
60
2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031
Y ear
0.0
0.5
1.0
1.5
2.0
2.5
3.0
3.5
4.0
4.5
5.0
5.5
6.0
6.5
7.0
7.5
8.0
8.5
9.0
9.5
10.0
Mi l l Or e Leach Or e on Pad Waste Mi l l Rev Cutof f ($ / ton)
![Page 34: Simultaneous Destination and Schedule Optimization with ...€¦ · Simultaneous Destination and Schedule Optimization with Minemax Scheduling Technology at Newmont Xiaolin Wu SME,](https://reader034.vdocument.in/reader034/viewer/2022051815/603bad733a39296708289894/html5/thumbnails/34.jpg)
1. Newmont Overview
2. Minemax Overview
3. Newmont Exercise to Validate Optimization Results
4. Minemax Scheduler Features
5. Minemax Scheduler Implementation at Newmont
6. Minemax Scheduler Examples at Newmont
7. Concluding Remarks
Contents
34
![Page 35: Simultaneous Destination and Schedule Optimization with ...€¦ · Simultaneous Destination and Schedule Optimization with Minemax Scheduling Technology at Newmont Xiaolin Wu SME,](https://reader034.vdocument.in/reader034/viewer/2022051815/603bad733a39296708289894/html5/thumbnails/35.jpg)
Minemax Scheduler Example 1
35
Yanacocha Mine Plan Optimization
- 7 Pits, 15 Mining Phases
- Three metals: gold, silver and copper
- Two process options: mill and oxide leach
- 10+ ore types (CuCN, SS, Ag, …)
- 5 Dumps and backfills
- 12 Leach ore destinations
- Sulfide ore stockpiles for future process
- Metal production targets
- Total dore sales constraint
- Haulage constraint
- Variable mill throughputs
- Silver, mercury, fines, CuCN grade blending
- Mining: 212 Mt, 1.8 Moz gold produced in 2008
![Page 36: Simultaneous Destination and Schedule Optimization with ...€¦ · Simultaneous Destination and Schedule Optimization with Minemax Scheduling Technology at Newmont Xiaolin Wu SME,](https://reader034.vdocument.in/reader034/viewer/2022051815/603bad733a39296708289894/html5/thumbnails/36.jpg)
Minemax Scheduler Example 1
36
Product Join Example
Truck Hour Join
Product Split Example
Oxide Leach Pads Split
![Page 37: Simultaneous Destination and Schedule Optimization with ...€¦ · Simultaneous Destination and Schedule Optimization with Minemax Scheduling Technology at Newmont Xiaolin Wu SME,](https://reader034.vdocument.in/reader034/viewer/2022051815/603bad733a39296708289894/html5/thumbnails/37.jpg)
• Multiple deposits (11 deposits) 11 open pits + 1 underground
Minemax Scheduler Example 2
37
![Page 38: Simultaneous Destination and Schedule Optimization with ...€¦ · Simultaneous Destination and Schedule Optimization with Minemax Scheduling Technology at Newmont Xiaolin Wu SME,](https://reader034.vdocument.in/reader034/viewer/2022051815/603bad733a39296708289894/html5/thumbnails/38.jpg)
• Variable mill costs and recoveries by pits/ore types
• Stockpiles by pit/ore types/revenue cutoffs (low/middle/high)– 11 pits x 2 ore types x 3 revenue cutoffs = 66 stockpiles
• North pits ore production <= 4.0 Mt/year
• Number of trucks and shovels constraints
• 1.6 million blocks contained in the design pits/phases
Minemax Scheduler Example 2
38
![Page 39: Simultaneous Destination and Schedule Optimization with ...€¦ · Simultaneous Destination and Schedule Optimization with Minemax Scheduling Technology at Newmont Xiaolin Wu SME,](https://reader034.vdocument.in/reader034/viewer/2022051815/603bad733a39296708289894/html5/thumbnails/39.jpg)
Minemax Scheduler Example 2
39
![Page 40: Simultaneous Destination and Schedule Optimization with ...€¦ · Simultaneous Destination and Schedule Optimization with Minemax Scheduling Technology at Newmont Xiaolin Wu SME,](https://reader034.vdocument.in/reader034/viewer/2022051815/603bad733a39296708289894/html5/thumbnails/40.jpg)
Minemax Scheduler Example 2
40
![Page 41: Simultaneous Destination and Schedule Optimization with ...€¦ · Simultaneous Destination and Schedule Optimization with Minemax Scheduling Technology at Newmont Xiaolin Wu SME,](https://reader034.vdocument.in/reader034/viewer/2022051815/603bad733a39296708289894/html5/thumbnails/41.jpg)
• Two multi-metal (gold, copper, silver) pits, 26 ore types, five mining phases
• Mine life: 15 to 20 years • Variable mill costs by ore types• Variable Au/Cu/Ag recoveries by ore types, grades
and concentrate grades• Variable mill throughputs by ore types• Blending requirements
– Zn in concentrate (<= 6%)– Arsenic in concentrate (<= 0.5%)– Argillic ore percentage in mill feed (<= 20%)– Actual mill rate can not exceed 102% of the design rate
Minemax Scheduler Example 3
41
![Page 42: Simultaneous Destination and Schedule Optimization with ...€¦ · Simultaneous Destination and Schedule Optimization with Minemax Scheduling Technology at Newmont Xiaolin Wu SME,](https://reader034.vdocument.in/reader034/viewer/2022051815/603bad733a39296708289894/html5/thumbnails/42.jpg)
Minemax Scheduler Example 3
42
![Page 43: Simultaneous Destination and Schedule Optimization with ...€¦ · Simultaneous Destination and Schedule Optimization with Minemax Scheduling Technology at Newmont Xiaolin Wu SME,](https://reader034.vdocument.in/reader034/viewer/2022051815/603bad733a39296708289894/html5/thumbnails/43.jpg)
1. Newmont Overview
2. Minemax Overview
3. Newmont Exercise to Validate Optimization Results
4. Minemax Scheduler Features
5. Minemax Scheduler Implementation at Newmont
6. Minemax Scheduler Examples at Newmont
7. Concluding Remarks
Contents
43
![Page 44: Simultaneous Destination and Schedule Optimization with ...€¦ · Simultaneous Destination and Schedule Optimization with Minemax Scheduling Technology at Newmont Xiaolin Wu SME,](https://reader034.vdocument.in/reader034/viewer/2022051815/603bad733a39296708289894/html5/thumbnails/44.jpg)
• Minemax Scheduler has become one of key strategic and long-range mine planning tools for new projects and operating mines at Newmont since 2008
• Newmont has been able to improve its mine planning process with increased efficiency and effectiveness
• With Minemax Scheduler, Newmont had been able to develop a range of optimal and achievable mine plans under complex mining and process constraints quickly
– Multi-mine (-metal, -process, -destination)
– Variable plant throughputs
– Ore blending constraints
– Loading and hauling capacities
• With the right resources and skill sets, Minemax can be integrated seamlessly with the general mine planning packages, and it is extremely easy to use when the scheduling requirements and models are correctly developed
Conclusions