slide 1 risk in mega projects seminar and workshop mega projects life cycle: project execution and...
TRANSCRIPT
Slide 1
Risk in Mega Projects Seminar and Workshop
Mega Projects Life Cycle: Project Execution and Delivery Process
5 - 7, 2007
Trondheim, Norway
Dr. George Jergeas PEng.Professor of Project Management
University of Calgary, Alberta
part of the Aker group
References
This section is based on presentations by:
• Dr. Nick Lavingia, PE, Chevron
•Bill Watson, VP Engineering and Project Management, Husky Energy
• Public Works and Services Canada PDS
Slide 3
Agenda
■ This presentation is in two parts
1. Oil and gas industry experience
2. Infrastructure projects best practice
part of the Aker group
Project Development & Execution Process (PDEP)
in the Oil and Gas
part of the Aker group
Structured and Gated Process
Effective Communication Between Decision Makers, Multifunctional Project Team and Stakeholders
Slide 6
Objectives
To Gain:
■ Understanding of the PDE Process and framework for more effective delivery of projects and programs, based on shared experience & lessons learned
■ Structured and Gated Process to ensure Effective Communication Between Decision Makers, Multifunctional Project Team and Stakeholders
■ Understanding of processes and sub-processes associated with the PDE Process
■ Understanding of the opportunities for improving PM practices & the barriers to be overcome
Slide 7
Project Development & Execution Process (PDEP)
A Process that Facilitates the Optimal Use of Resources (Dollars, People and Technology) Over the Life of an Asset / Project to Maximize Value.
Desired Outcome
■ Select the Right Projects by Improving Decision Making
■ Improve Project Outcomes through Excellence in Execution of Decisions
Slide 8
PHASE 2SELECT fromAlternatives
Determine Project Feasibility andAlignment withBusiness Strategy
Project Phases
PHASE 1IDENTIFY & Assess
Opportunities
Finalize Project Scope, Cost and Schedule and Get the Project Funded
Select thePreferred Project Development Option
Evaluate Asset to Ensure Performance to Specifications and Maximum Return to the Shareholders
PHASE 3DEVELOP Preferred
Alternative
PHASE 4EXECUTE
(Detail EPC)
PHASE 5OPERATE &
Evaluate
Produce an Operating Asset Consistent with Scope, Cost and Schedule
1 2 3 4 5
AFE
-DBM- Application
-FEED-Long-Leads
- Reg. Approval- AFE
- Detailed Design- Procurement
- Fabrication-Construction
-Commissioning
-Start-Up - Perf’m Testing- De-bottleneck
-Feasibility
Slide 9
Project Phases
DBM
Feasibility
Regulatory Approval
AFE
Screening
FEED
Pre-AFE
Slide 10
PHASE 2SELECT fromAlternatives
Clearly Frame Goal
Test for Strategic Fit
Preliminary Overall Plan
Preliminary Assessment
~1 % Engng.
Phase 1 Estimate
Project Development & Execution Process (PDEP)
PHASE 1IDENTIFY & Assess
Opportunities
Fully Define Scope
Develop Detailed Execution Plans
Refine Estimate
Submit Funding for Approval
~25 % Engng.
Phase 3 Est. (+/- 10 % Accuracy)
Generate Alternatives
Preliminary Development of Alternatives
Develop Expected Value
Identify Preferred Alternative
Phase 2 Est.
Operate Asset
Monitor & Evaluate Performance
Identify New Opportunities
PHASE 3DEVELOP Preferred
Alternative
PHASE 4EXECUTE
(Detail EPC)
PHASE 5OPERATE &
Evaluate
Implement Execution Plan
Min. Changes
Finalize Operating Plan
Business Plan for Phase 5
Project Review
1 2 3 4 5
AFE
AFE = Appropriation For Expenditure
Slide 11
Phase 1 Flow Chart: Identify
DefineOpportunity
IdentifyStakeholders
IdentifyExpectations
FrameProject
Develop ProjectSpecific Business
Objectives
Plan forPhase 2
ConceptEvaluation
DevelopConceptual
Scope
Assess CurrentSituation
Phase 1Estimate
StrategicBusiness
Assessment
OK?
Yes
No
QualityReview
IDEA
To Phase 2
Recycle
Slide 12
Phase 1 Deliverables
Business Objectives & Priorities Business Objectives & Project Framework
Process Preliminary Block Flow Diagram, Preliminary Capacity
Site / Infrastructure Preliminary Site Selection, Integration, Development Plan
Execution Defining Vision of Success
Risk Analysis Strategic Risk Assessment
Permit / Regulatory requirements Preliminary Permitting Plan
Contracting
Estimate Phase 1 Estimate (High Contingency & Wide Accuracy)
Schedule Preliminary Milestone Schedule
Resource Plan Plan for Phase 2 Resources
Economics Preliminary NPV, ROR, DPI, Payout
Slide 13
Typical AssessAssessPhase Events
• Determine project feasibility and alignment with business strategy
• Define business objectives
• Identify technology options
• Determine market feasibility
• Preliminary risk identification and mitigation planning
• Establish preliminary HS&E issues
• Develop project execution plan for next phase
• Develop a work plan for the Select phase
• Identify joint ventures/partner issues & opportunities
• Develop a +/- 40% cost estimate ( ~/= 5% of total Engineering)
• Incorporate shared learnings from After Action Reviewson similar projects executed by Husky & Competitors
ASSESS
Slide 14
Phase 2 Flow Chart: Select
BeginExecutionPlanning
Prepare Pre AFE
Plan forPhase 3
Select and RefineAlternative
ProjectSelf-Evaluation
Pre AFEApproval
OK?
Yes
No
EstablishObjectives and
Priorities
ReviewPhase 1Package
Appoint ProjectSponsor, GPM,
PM and Op. Rep.
Generate andEvaluate
Alternatives
Phase 2Estimate
From Phase 1To Phase 3
Recycle
Slide 15
Phase 2 DeliverablesBusiness Objectives & Priorities Preliminary Facility & Project Objectives
Process PFDs, Equipment List, Technology Selected
Site / Infrastructure Site Selected, Utility Balances
Execution Defining Strategy for Success
Risk Analysis Project Risk Assessment
Permit / Regulatory requirements Detailed Permitting Plan
Contracting Preliminary Contracting Plan
Estimate Phase 2 Estimate (Moderate Contingency & Moderate Accuracy)
Schedule CPM Schedule
Resource Plan Plan for Phase 3 Resources
Economics Updated NPV, ROR, DPI, Payout
Slide 16
Typical SelectSelect Phase Events
• Select the preferred development option(s)• Identify critical and major equipment needs• Refine HS&E assessment • Submit permit application(s)• Update Market feasibility and partnering plan• Develop Exit strategy• Update Cost Estimates to +/- 25% (5-10% of Engineering)• Update Risk identification and Mitigation plan• Conduct a Peer Review - as appropriate• Update Market feasibility and partnering plan• Adjust core/extended project team membership• Update project execution plan for next phase• Develop a work plan for the next Phase (definition)
SELECT
Slide 17
Phase 3 Flow Chart: Develop
UpdatePermitting for
Selected Alternative
FinalizeExecution
Plan
Phase 3Estimate
AFEApproval
OK?
Yes
No
ContinueExecutionPlanning
BuildProjectTeam
DefineProject
IPA andSelf-Evaluation
From Phase 2 To Phase 4
Recycle
Slide 18
Phase 3 Deliverables
Business Objectives & Priorities Final Facility & Project Objectives
Process P&IDs
Site / Infrastructure Final Plot Plan, One Lines
Execution Defining Tools for Success
Risk Analysis Finalize Project Risk Assessment
Permit / Regulatory Requirements Update Detailed Permitting Plan
Contracting Detailed Contracting Plan
Estimate Phase 3 Estimate (+/- 10% Accuracy)
Schedule Resource Loaded CPM Schedule
Resource Plan Plan for Phase 4 Resources
Economics Final NPV, ROR, DPI, Payout
Slide 19
Typical DefineDefine Phase Events
• Finalize Project Scope, Cost and Schedule
• Prepare project AFE approval
• Prepare Decision Support Package (DSP) for project sanction
• Secure partner approvals if appropriate
• Finalize the Project Execution Plan (PEP)
• Update project team membership
• Conduct independent peer review
• Finalize cost estimates to +/- 10% (up to 20% of total Engineering)
• Conduct value engineering - as appropriate
• Finalize risk identification and mitigation plan
• Finalize the Design Basis Memorandum (DBM)
• Conduct After Action Review - as appropriate
DEFINE
Slide 20
Phase 4 Flow Chart: Execute
Turnover
Construction
Procurement
Training
OperationsPlanning
Commissioning
Detailed Design
ImplementExecution Plan
From Phase 3
To Phase 5
Recycle
Slide 21
Phase 4 DeliverablesBusiness Objectives & Priorities Deliver Operating Asset
Process Trained Personnel
Site / Infrastructure Manage Progress
Execution Implement Plan with Minimal Changes
Risk Analysis Manage Project Risk Register
Permit / Regulatory Requirements Manage Project Permit Schedule
Contracting Execute Contracting Plan
Estimate Monitor & Control Estimate
Schedule Monitor & Control CPM Schedule
Resource Plan Plan for Phase 5 Resources
Economics Monitor NPV, ROR, DPI, Payout
Slide 22
Organization for PDEP Phase 4 -- Execution
GeneralProject Manager
Project Manager
Execution Team
Business
Technical
Manufacturing
Corp. Strategy
Planning
Operations
Maintenance
Safety
Consultants
Specialists
Purchasing
DesignConstructability/Construction
Materials Management
Process Engineering
Project Finance
Metrics
IPA
Regulation
Environmental
Safety
Finance
Human Resources
Public Relations
MarketingProject
Sponsor
Project GoalsSBU Strategy
Slide 23
EXECUTE
• Execute project execution plan
• Deliver operating asset consistent with scope, cost & schedule
• Implement project controls and reports on project metrics and status
• Implement HS&E plan
• Implement contracting strategy
• Implement value practices
• Commission and startup
• Conduct After Action Review
EXECUTETypical ExecuteExecute Phase Events
Slide 24
Phase 5 Flow Chart: Operate
FullOperation
Post ProjectAssessment
Start-Up
Business Evaluation
From Phase 4
Slide 25
Phase 5 DeliverablesBusiness Objectives & Priorities Business Evaluation & Benchmark
Performance
Process Look for Debottlenecking Opportunities
Site / Infrastructure Look for Debottlenecking Opportunities
Execution Share Lessons Learned
Risk Analysis Update Risk database
Permit / Regulatory Requirements Update Permitting Database
Contracting Update Contractor Database
Estimate Update Cost Database
Schedule Update Schedule Database
Resource Plan Update Resource Database
Economics Validate NPV, ROR, DPI, Payout
Slide 26
OPERATE
• Operate and Evaluate the asset to ensure performance to specifications and maximum return to shareholders
• Conduct a final After Action Review and capture shared learnings
• Post appraise / evaluate the actual asset operation and business results versus the performance targets. The evaluation will be conducted under the approval market environment (pricing etc) and under the current market conditions.
• Identify potential improvement opportunities for future projects
• Develop a reservoir depletion plan - as appropriate
• Identify new opportunities
• Turn over operating documentation
OPERATE Typical OperateOperate Phase Events
Slide 27
Achieving World-Class Performance
EXECUTION
Diligently implement PDEP, Key Project Management Principles, and Project Management Best Practices. Strive for zero incidents.
COST
Final capital cost at least 10 percent below industry norm.
SCHEDULE
Final engineering/construction schedule amongst the best achieved by a similar project in the database.
ATTAINMENT
Attainment achieved at 100% design capacity per project objectives.
part of the Aker group
Project Delivery System for Infrastructure Projects
Slide 29
Project Delivery System
A framework within which projects are developed, acquired or implemented, and put into service
A series of project phases from inception to completion
Slide 30
Project Delivery System (PDS)
■ The six phases are:● Planning● Definition● Implementation● Commissioning● Operation● Evaluation
Slide 31
Planningphase
Operation
Evaluation
DefinitionPhase
Implementation
Commissioning
Investment
Analysis Report
EvaluationReport
Facility inuse
Comm.Report
Built works Project Brief
PROJECT DELIVERY SYSTEM
part of the Aker group
Phase 1
Slide 33
Objectives
■ Identify and define in detail the client investment opportunity, need or problem
■ Assess all feasible alternatives
■ Define organization and any required controls
■ Establish the project budget and completion date
■ Specify criteria for evaluating the project
Slide 34
Five Steps
1. Project Initiation2. Client Opportunity/Need
Identification3. Regulatory Considerations4. Options Analysis5. Owner/Investor Approval
Slide 35
Main Out Put: IAR
■ Investment Analysis Report (feasibility) ● To ascertain whether the concept for a project is
technically and/or economically feasible for further study
● Identify the optimum solution
part of the Aker group
Phase 2
Slide 37
Planning
Operation
Evaluation
Definition
Implementation
Commissioning
Investment
Analysis Report
EvaluationReport
Facility inuse
Comm.Report
Built works Project Brief
PROJECT DELIVERY SYSTEM
Slide 38
2. Objectives
■ Translate the IAR into verifiable technical criteria
■ Prepare Project Brief or Scope definition
■ Define implementation strategies, including project management controls
■ Transfer responsibility to the PM
■ Select best alternative, technology, capacities and site location
■ Choose consultant
Slide 39
Two Major Steps
1. Production of the Project Brief/Scope Definition
● Option Refinement● Resource Strategy● Project Team/WBS● Project Funding Agreement● Regulatory Concerns● User Requirement Definition/Project Brief
Slide 40
Two Major Steps
2- Consultant Selection
● Project Terms of Reference● Consultant Service Agreement preparation● Consultant Selection● Consultant Contract● Proponent Debrief
part of the Aker group
Phase 3
Slide 42
Planning
Operation
Evaluation
Definition
Implementation
Commissioning
Investment
Analysis Report
EvaluationReport
Facility inuse
Comm.Report
Built works Project Brief
PROJECT DELIVERY SYSTEM
part of the Aker group
Implementation
1. Design
2. Tendering and award
3. Construction
Slide 44
Design
Objective
■ The objective is to design the project in detail, obtain necessary approvals, estimate costs and prepare drawings and specification.
Slide 45
Design
■ Prepare:●a concept design●a detailed design drawings, specifications
and schedules●bills of quantities (if needed)●final cost estimates●time schedule
Slide 46
Design: 7 Steps
■ Set up design team
■ Define project control criteria
■ Pre-design report
■ Concept design
■ Design development
■ Project Approval
■ Construction documents
Slide 47
Tendering
Purpose■ To select a contractor, or a number of contractors who
will unconditionally meet all of the terms and conditions set out in the tender documents at a competitive market price.
Implementation
Slide 48
Contracting Policy
Contracting shall be conducted to:
■ Stand the test of public scrutiny in matters of prudence and probity, facilitate access, encourage competition, and reflect fairness in the spending of public funds.
■ Ensure the pre-eminence of operational requirements.
Slide 49
Contracting Policy
■ Three ingredients● Honesty● Fairness● Best Value
■ Public sector and private sector contract are fundamentally administered in the same way
■ More later about bidding.
Implementation - Design
Slide 50
Construction
Purpose: To physically construct the project within the agreed limits of cost and time, and to specified quality within safe and healthy environment.
● Construction is the most expensive, intensive and difficult phase
Slide 51
Construction
Activities
■ To plan, coordinate and control site operations
■ Planning includes the formulation of:● Time schedules● Site organization● Labour resources plan● Equipment plan● Material delivery plan
Slide 52
Construction
Activities
■ Site operations include● All temporary and permanent construction works,
and supply of all built-in furniture and equipment● The coordination of subcontractors● General supervision/inspection
Slide 53
Main Activities During Construction
1. Start-up meeting
2. Management
3. Construction process
4. Post construction
5. Contract closure
Slide 54
Phase 4
Slide 55
Planning
Operation
Evaluation
Definition
Implementation
Commissioning
Investment
Analysis Report
EvaluationReport
Facility inuse
Comm.Report
Built works Project Brief
PROJECT DELIVERY SYSTEM
Slide 56
Commissioning
■The process of advancing an installation from the state of static completion to full working order in accordance with the design intent.
Slide 57
Why Do You Commission?
■Commission From two Perspectives●The Engineering Perspective●The Contractual Perspective
Slide 58
Engineering Perspective
■ Ensure the design intent has been met relative to the design specifications.
■ Ensure the design intent will meet the operational requirements relative to:● Program● O&M● Cost● Safety
Slide 59
Contractual Perspective
■Ensure contractual responsibilities in terms of supply and installation versus design are not compromised or negated.
Slide 60
Phase 5
Slide 61
Planning
Operation
Evaluation
Definition
Implementation
Commissioning
Investment
Analysis Report
EvaluationReport
Facility inuse
Comm.Report
Built works Project Brief
PROJECT DELIVERY SYSTEM
Slide 62
Objectives
■ Establish and ensure reliable (operating systems) in the facility
■ Establish, test and record the operating performance of the systems
■ Maintain adequate operation and maintenance records
■ Establish a preventative maintenance program
■ Identify an operating and maintenance budget
■ Respond to specific requests for services from the Client
Slide 63
Phase 6
Slide 64
Planning
Operation
Evaluation
Definition
Implementation
Commissioning
Investment
Analysis Report
EvaluationReport
Facility inuse
Comm.Report
Built works Project Brief
PROJECT DELIVERY SYSTEM
Slide 65
Objectives
■ Four main objectives:
1. To assess the project in specific terms, comparing planned and actual;
2. To compare the actual performance with the plans and the appropriate norms considered, in order to determine any variances;
Slide 66
Objectives
3. To clearly identify variances outside acceptable limits, so they can be reviewed for further action; and
4. To record the project performance for: ● Management review● Sharing with other regions, and● Contributing to PWGSC’s lessons learned database
Slide 67
3. Types of Evaluation
1. Project evaluation
2. Contractor evaluation
3. Consultant evaluation
Slide 68
What We Learned
A good framework to deliver a Quality end product, on time and within budget to client satisfaction Procedural guide and reference for project team members
and managers Basis for training
Best practices are implemented
Achieves good working environment
Due diligence is exercised
Slide 69