sloan corporate finance tutorial i308[2]

Upload: lindsey-joseph

Post on 07-Apr-2018

216 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/6/2019 Sloan Corporate Finance Tutorial i308[2]

    1/36

  • 8/6/2019 Sloan Corporate Finance Tutorial i308[2]

    2/36

    2

    Todays Topic

    NPVA Simple Case Study

    Eagle Industry

  • 8/6/2019 Sloan Corporate Finance Tutorial i308[2]

    3/36

    3

    NPV (Net Present Value)

  • 8/6/2019 Sloan Corporate Finance Tutorial i308[2]

    4/36

    4

    NPV

    NPV = Discounted Cash Flow (Inflow outflow)

    In other words, it is the fundamental value of

    an asset at current period. Note: NPV is not necessarily equal to marketvalue! (Market value is determined by supplyand demand in the market. If the market is

    efficient, NPV is equal to market value.)

  • 8/6/2019 Sloan Corporate Finance Tutorial i308[2]

    5/36

    5

    Investment Decision and NPV

    What is the goal of a firm? Maximizingshareholders value

    NPV = shareholders value

    Therefore, Investment decisions should bebased on the NPV of the project.

  • 8/6/2019 Sloan Corporate Finance Tutorial i308[2]

    6/36

    6

    NPV

    NPV of cash on hand = amount of cash Ex) NPV of 100 on hand = 100

    Suppose annual interest rate is rf= 10% Ex 1) NPV of 100 of next year?

    Ans) 100/(1+rf) = 100/1.1 = 90.91 Ex 2) NPV of the following cash flow: 100(year 1), 100(year 2), 200(year 3) Ans) 100/1.1 + 100/1.12 + 200/1.13 = 323.82

    In general, you have NPV formula such that

    NPV = where Ct is cash flow at time t= +

    N

    t

    t

    t

    r

    C

    0 )1(

  • 8/6/2019 Sloan Corporate Finance Tutorial i308[2]

    7/36

    7

    NPV of Uncertain Cash Flow

    Calculating NPV is that simple! But, what ifyou have uncertain cash flow?

    Can we just use expected cash flow like the

    following? NPV = where E(C) is expectation of C

    The answer is no. Lets look at an example!

    = +

    N

    t

    t

    t

    r

    CE

    0 )1(

    )(

  • 8/6/2019 Sloan Corporate Finance Tutorial i308[2]

    8/36

    8

    Example: A Coin Tossing

    Consider a gamble where you pay a certain amountnow, and receive money next year. Next year youwill toss a coin, and you will get 100 if it is head,0 if it is tail.

    Expected cash flow (C) in the next year is E(C) =

    0.5*100+0.5*0 = 50Suppose annual interest rate is rf= 7%

    Are you willing to pay 50/(1+rf) = 50/1.07 = 47 forthis betting? Probably not!

    Probably, you want to pay somewhat lower than 47.Suppose you want to pay P = 35 for the gamble.

  • 8/6/2019 Sloan Corporate Finance Tutorial i308[2]

    9/36

    9

    Return on Coin Tossing

    The expected return on this betting is E(r) = E(C)/P 1 = 50/35 1 = 43%

    You want to ask for higher return than the interestrate because this is a risky choice. We call it riskpremium! E(r) = rf+ risk premium = 7% + 36%

    In general, this is decided by the risk of an asset. ex) CAPM: E(r) = rf+ (rM rf)

    Therefore, we can calculate NPV of uncertain cash

    flow by using an appropriate discount factorconsidering the risk of investment. (We will coverthis later in the cost of capital part.)

  • 8/6/2019 Sloan Corporate Finance Tutorial i308[2]

    10/36

    10

    A Simple Case Study

    Ginos Trattoria Case

    (Adapted from Brealey and Myers)

  • 8/6/2019 Sloan Corporate Finance Tutorial i308[2]

    11/36

    11

    Sample Problem

    Ginos Trattoria is considering a new project, which requires

    an investment of 2 million. The project is expected togenerate sales revenue of 1 million in the first year, 2million in the second year and 3 million each for year 3, 4and 5. The cost of goods sold is expected to be 75 percentof sales revenue. Other costs are expected to be 7 percentof sales in the first year and 5 percent of sales thereafter.

    The project will need working capital investment of 200,000 in the first year and an additional 100,000 in thesecond year. The investment in plant ( 2 million) will bedepreciated using 25% declining balance over 5 years. Ifthe companys opportunity cost of capital is 10 percent,calculate the NPV for the project. Assume that the plant willoperate for 5 years, and at the end of 5 years, the plant canbe sold for a salvage value of 600,000. The tax rate forthe company is 36 percent.

  • 8/6/2019 Sloan Corporate Finance Tutorial i308[2]

    12/36

    12

    Approach for the Case

    We need to calculate NPV to evaluate theproject

    Remember NPV is discounted cash flows

    Thus, all the information you will need is cashflowThe paragraph looks a bit too messy, and

    very boring. Instead of trying to read it, we

    can just pick up necessary information fromthe paragraph

  • 8/6/2019 Sloan Corporate Finance Tutorial i308[2]

    13/36

    13

    Cash Flow ?

    Cash Flow = Cash Flow from Operation + Cash Flow from Investment + Cash Flow from Financing

    = Net Income + Changes in WC + Capital Expenditure

    + Raising and Paying Debt orEquity

  • 8/6/2019 Sloan Corporate Finance Tutorial i308[2]

    14/36

    14ash Flow

    CF fromInvestmentCF fromOperation

    CF fromFinancing

    Investment

    Salvage

    Value

    Tax on differencebetweensalvage value andending book value=

    -

    +Cost

    Tax SavingsFrom

    Depreciation

    =

    Sales-

    Tax EffectofSales &Cost+-

    Change inWorking Capital

    +

    We wont havethis part in our

    simple example

    Ginos TrattoriaCase

  • 8/6/2019 Sloan Corporate Finance Tutorial i308[2]

    15/36

    15

    Necessary Information

    All the information you will need will be thefollowing blocks from the case:

    Investment SalvageValue

    Tax on differencebetweensalvage value andending book value

    Cost

    Tax SavingsFrom

    Depreciation

    Sales

    Tax EffectofSales &Cost

    lso, you will need to know tax rate, discount rate,nd depreciation rule.

    Change inWorkingCapital

  • 8/6/2019 Sloan Corporate Finance Tutorial i308[2]

    16/36

    16

    Step 1. Find Necessary Information

    1.1 Find Investment and salvage value Ginos Trattoria is considering a new project, which requires an investment of 2

    million. Assume that the plant will operate for 5 years, and at the end of 6 years, the plant can

    be sold for a salvage value of 600,000.

    1.2 Find Revenue (or Sales)

    The project is expected to generate sales revenue of 1 million in the first year, 2million in the second year and 3 million each for year 3, 4 and 5.

    1.3 Find Cost The cost of goods sold is expected to be 75 percent of sales revenue. Other costs

    are expected to be 7 percent of sales in the first year and 5 percent of sales thereafter.

    YearsInvestmentYearsSales

    Years 0 1 2 3 4 5 6COGS 750 1500 2250 2250 2250

    Other Costs 70 100 150 150 150

  • 8/6/2019 Sloan Corporate Finance Tutorial i308[2]

    17/36

    17

    Step 1. Find Necessary Information (2)

    1.4 Find Working Capital

    The project will need working capital investment of 200,000 in the first year and an additional$100,000 in the second year.

    1.5 Find Depreciation Rule The investment in plant ( 2 million) will be depreciated using 25% declining balance over

    schedule for the 5-year class.

    1.6 Find Tax Rate The tax rate for the company is 36 percent.

    1.7 Find Cost of Capital If the companys opportunity cost of capital is 10 percent, calculate the NPV for the project.

    1.8 Duration of the project Assume that the plant will operate for 5 years, and at the end of 5 years, the plant can be sold

    for a salvage value of 600,000.

    YearsChange in Work

    Capital

  • 8/6/2019 Sloan Corporate Finance Tutorial i308[2]

    18/36

    18

    Step 2. Calculate Profit, Tax effect of Sales&Costs,Depreciation, and Tax Savings

    2.1 Profit = Sale

    Years

    Sales2.2 Tax = tax rYears

  • 8/6/2019 Sloan Corporate Finance Tutorial i308[2]

    19/36

    19

    Step 2. Calculate Profit, Tax effect of Sales&Costs,Depreciation, and Tax Savings (2)

    2.4 Tax Saving

    YearsDepreciation

    Depreciation (25% Declining Rule) UK Tax Depreciationreciation in the first year = 25% of Value = .25 * 2000 = 500reciation after the second year = 75% of previous years depreciation = .75*500

    2.5 Thus, we caYears

  • 8/6/2019 Sloan Corporate Finance Tutorial i308[2]

    20/36

    20

    Step 3. Calculate Cash Flow

    Total Cash Flo

    Years

  • 8/6/2019 Sloan Corporate Finance Tutorial i308[2]

    21/36

    21

    Step 4. Calculate NPV, IRR, Payback,and so on..

    Using 10% cost of capital, we derive NPV = -220,962.07 IRR = 6.84%

    Payback Period = 5 yearsThen, we can evaluate the project by given

    criteria.

  • 8/6/2019 Sloan Corporate Finance Tutorial i308[2]

    22/36

    22

    Graham & Harvey (2007)s Survey

  • 8/6/2019 Sloan Corporate Finance Tutorial i308[2]

    23/36

    23

    NPV Criteria

    Investment Decision using NPV: accept the project if NPV > 0

    Strength

    Consistent with the goal of shareholder valuemaximization

    Weakness

    Relies on cash flow forecasts, which tend to beinaccurate and biased upwards.

  • 8/6/2019 Sloan Corporate Finance Tutorial i308[2]

    24/36

    24

    IRR Criteria

    Investment Decision using IRR: accept the project if IRR > opportunity costs of capital

    Strength

    IRR gives the same answer as NPV if used properly More intuitive (summarized to one number)

    Weakness

    Multiple solutions Easily misleading: timing, scale, etc

  • 8/6/2019 Sloan Corporate Finance Tutorial i308[2]

    25/36

    25

    Payback Period Criteria

    Investment Decision using Payback: accept the project if it pays back its initial investment within the

    cutoff period

    Strength

    Does not use distant cash flows which could be inaccurate ingeneral Make sure the initial investment is recovered within short term

    Weakness

    The payback rule ignores all cash flows after the cutoff date. The payback rule gives equal weight to all cash flows before thecutoff date. (It ignores the timing of cash flows within thepayback period)

  • 8/6/2019 Sloan Corporate Finance Tutorial i308[2]

    26/36

    26

    Quiz!

    The Campbell-Graham survey shows thatover half of their CFOs use payback period(in conjunction with NPV) to assess projects.

    Why do they use payback period?Payback period has its own strengths which

    NPV does not have although it is a bitoversimplified.

    Thus, payback period could provide a bettercriteria together with NPV.

  • 8/6/2019 Sloan Corporate Finance Tutorial i308[2]

    27/36

    27

    Best Criteria?

    In an ideal world (where forecasting isunbiased and accurate), NPV is the bestrule as we have seen.

    In reality, there is always the possibility of

    having optimistic bias, and other biases inforecasting. Given that, using other criteria(payback) together with NPV will give youmore effective way of investment decision

    making.

  • 8/6/2019 Sloan Corporate Finance Tutorial i308[2]

    28/36

    28

    A Review on Eagle Industry

    C Mi t k i E l I d t

  • 8/6/2019 Sloan Corporate Finance Tutorial i308[2]

    29/36

    29

    Common Mistakes in Eagle IndustryCase

    Tax savingsSunk Cost

    Opportunity Cost

    Minor mistakes

    Tax Savings

  • 8/6/2019 Sloan Corporate Finance Tutorial i308[2]

    30/36

    30

    Tax Savings(Straight-line Depreciation)

    Building (25 years straight line depreciation) Initial value: 1000, salvage value: 0

    After 5 years, the book value is still 800 although thesalvage value is 0. Therefore, the difference between theending book value and the salvage value could be usedfor tax savings.

    Tax Savings in year 6: 30%*(800)=240

    0 1 2 3 4 5 6

    Book Value 1000 960 920 880 840 800

    Depreciation 40 40 40 40 40 800

    Tax Savings 12 12 12 12 12 240

    Tax Savings

  • 8/6/2019 Sloan Corporate Finance Tutorial i308[2]

    31/36

    31

    Tax Savings(25% declining balance)

    Plant and machinery (25% declining balance) Initial value: 1200, salvage value: 100

    After 5 years, the book value is still 285 although the salvagevalue is 100. Therefore, the difference between the endingbook value and the salvage value could be used for taxsavings.

    Tax Savings in year 6: 30%*(285-100)=55

    Book Value 1200 900 675 506 380 285

    Depreciation 300 225 169 127 95 185

    Tax Savings 90 68 51 38 28 55

  • 8/6/2019 Sloan Corporate Finance Tutorial i308[2]

    32/36

    32

    Opportunity Cost

    Opportunity Cost of Land should be included in theanalysisThe criteria whether its a positive NPV project will be

    NPV > 0

    In case you dont include the opportunity cost Option 1: Run the project (Opportunity cost is not included)

    Option 2: Sell the land at 100,000

    The criteria whether its a positive NPV project will be NPV > 100,000

  • 8/6/2019 Sloan Corporate Finance Tutorial i308[2]

    33/36

    33

    Sunk Cost

    Sunk cost shouldnt be included R&D cost (500,000) over the past two years is

    a sunk cost, thus its not included in theanalysis

    How to decide whether to include or notIf something can be affected by the decision to

    accept or reject the project, it should beincluded.

    Otherwise, it should be ignored.

  • 8/6/2019 Sloan Corporate Finance Tutorial i308[2]

    34/36

    34

    Working Capital

    Working Capital = Current Asset Current Liability = Inventory + Account Receivable Account Payable

    Use change in working capital, not working capital

    itself to calculate cash flowThere is no tax effect on change in working capitalWith reasonable assumptions, working capital should

    be recovered after the projects duration

  • 8/6/2019 Sloan Corporate Finance Tutorial i308[2]

    35/36

    35

    Minor Mistakes

    Tax-free Grant In a development area, there is a tax free grant of 15%

    on the value ofinvestment in buildings, plant, andmachinery. (only in the first year!)

    15%*(1000+1200) = 330

    There are launching costs of 200 and 100 in eachof the first two years respectively:

    year 0 1 2 3 4 5

    launching costs 200 100

  • 8/6/2019 Sloan Corporate Finance Tutorial i308[2]

    36/36

    36

    Next Time (Tentative)

    Valuation with InflationSensitivity Analysis

    Capital Structure

    Fixed Income

    You can download materials from

    http://phd.london.edu/jhan.phd2005

    http://phd.london.edu/jhan.phd2005http://phd.london.edu/jhan.phd2005