small hydro resource mapping in vietnam final report - …...small hydro gis database and guidelines...
TRANSCRIPT
-
Small Hydro Resource Mapping in Vietnam
Final Report - Annexes
MARCH 2017
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
-
This report was prepared by Gesto Energy Consulting, under contract to The World Bank.
This is the final output from the small hydro resource mapping component of Energy Resource Mapping and Geospatial Planning Vietnam [Project ID: P145513]. This activity is funded and supported by the Energy Sector Management Assistance Program (ESMAP), a multi-donor trust fund administered by The World Bank, under a global initiative on Renewable Energy Resource Mapping. Further details on the initiative can be obtained from the ESMAP website. The Final Report summarizes the development of the Small Hydro GIS Database and Guidelines to review and Planning of Small Hydro and includes national maps of Small Hydropower in Vietnam. This is a final output and it has been validated through field-based surveys and peer-reviewed. It will be published via The World Bank s main website and listed on the ESMAP website along with the other project outputs - please refer to the corresponding country page.
Copyright © 2017 THE WORLD BANK Washington DC 20433 Telephone: +1-202-473-1000 Internet: www.worldbank.org
The World Bank, comprising the International Bank for Reconstruction and Development (IBRD) and the International Development Association (IDA), is the commissioning agent and copyright holder for this publication. However, this work is a product of the consultants listed, and not of World Bank staff. The findings, interpretations, and conclusions expressed in this work do not necessarily reflect the views of The World Bank, its Board of Executive Directors, or the governments they represent.
The World Bank does not guarantee the accuracy of the data included in this work and accept no responsibility for any consequence of their use. The boundaries, colors, denominations, and other information shown on any map in this work do not imply any judgment on the part of The World Bank concerning the legal status of any territory or the endorsement or acceptance of such boundaries.
The material in this work is subject to copyright. Because The World Bank encourages dissemination of its knowledge, this work may be reproduced, in whole or in part, for non-commercial purposes as long as full attribution to this work is given. Any queries on rights and licenses, including subsidiary rights, should be addressed to World Bank Publications, The World Bank Group, 1818 H Street NW, Washington, DC 20433, USA; fax: +1-202-522-2625; e-mail: [email protected]. Furthermore, the ESMAP Program Manager would appreciate receiving a copy of the publication that uses this publication for its source sent in care of the address above, or to [email protected].
http://www.gestoenergy.com/http://www.worldbank.org/http://www.esmap.org/re_mappinghttp://www.worldbank.org/
-
SMALL HYDROPOWER MAPPING AND PLANING IN VIETNAM
SMALL HYDRO GIS DATABASE AND GUIDELINES FOR REVIEW AND PLANNING ON SMALL HYDRO (DRAFT)
A-I.1 VN.2016.R.002.0
Annex I – Comments and recommendations on the Demo Version of the GIS database
ANNEX I – COMMENTS AND RECOMMENDATIONS ON THE DEMO VERSION OF THE
GIS DATABASE
Overall comments
Recommendation #1: Include summary data and report creation function;
Recommendation #2: Represent each project graphically by its size in terms of
capacity (e.g. “bubble” scale – smaller circles for small powers, larger for big
projects);
Recommendation #3: Improve search and advanced search functions.
Regarding web map layers, they appeared to be just non-editable basemaps (with
options for google layers in backdrop), and don’t include vector layers such as
administrative boundaries (provinces, districts), watersheds or main rivers. It is not clear
if the National Consultant designed spatial data layers in relationships with SHPs
attributes.
Recommendation #4: Include vector layers such as administrative boundaries,
watersheds and hydronetwork;
Recommendation #5: Include globally available data such as protected areas,
roads, railroads, DEM, meteo data, existing and planned grid, populated places,
etc. (information provided by the International Consultant on its Inception
Report).
The WebGIS functionality was limited with only clickable SHP icon for detailed
information (and virtually no interactive mapping functions). Search within a radius
(circle) or arbitrary polygon was not available. It is not clear if the National Consultant
designed GIS functions such as spatial search. The geometry attribute field of SHPs is
used to link with corresponding locations on web maps built on Openlayers & Geoserver.
The system has search engine for users to find needed information (mostly attributes)
of SHPs.
Recommendation #6: Improve spatial search.
The National Consultant adds data and functionality on “safe weir operation”, which is
not required in the original Terms of Reference (TOR).
-
SMALL HYDROPOWER MAPPING AND PLANING IN VIETNAM
SMALL HYDRO GIS DATABASE AND GUIDELINES FOR REVIEW AND PLANNING ON SMALL HYDRO (DRAFT)
A-I.2 VN.2016.R.002.0
Annex I – Comments and recommendations on the Demo Version of the GIS database
Recommendation #7: Clearly identify operational needs for weirs safety
(operators’ requirements are different from planners) and then, organize GIS
database with separate functionality accordingly - not to mix with the main
objectives of the assignment under the TOR.
Some of the format requirements of the TOR in terms of data, maps and images (Annex
A of the TOR) don’t seem to be fulfilled, like for instance the coordinate system
(currently VN2000 is used but WGS84 for data sharing & transfer among RE GIS
databases is required). This might lead to future incompatibility issues and non-
compliances with other Renewable Energy GIS databases.
Recommendation #8: Consult Annex A of the TOR (and its updated version) and
satisfy every format requirement.
Specific comments on GIS:
Following are specific comments and recommendations on the GIS structure and
functionality.
In terms of map layers:
Like stated before, it would be preferable if map layers could allow spatial search
and reporting summarization:
Recommendation #9: Design and add additional data layers as vector layers with
object-ID and relationships.
Locations of SHPs with weirs, reservoirs (as data collection in some provinces is
still ongoing, some SHPs do not have coordinates yet):
Recommendation #10: Separate weirs and reservoirs as independent (but inter-
related) point layers from SHPs and add separate search functions for each of
layers (different meaning/searching purposes) – selectable for visualization on a
menu1;
Data on large hydro:
1 Like, for instance, menu “layers” in Mozambique Atlas (http://mapviewer.atlasrenovaveis.co.mz/index.php) developed by the International Consultant
http://mapviewer.atlasrenovaveis.co.mz/index.php
-
SMALL HYDROPOWER MAPPING AND PLANING IN VIETNAM
SMALL HYDRO GIS DATABASE AND GUIDELINES FOR REVIEW AND PLANNING ON SMALL HYDRO (DRAFT)
A-I.3 VN.2016.R.002.0
Annex I – Comments and recommendations on the Demo Version of the GIS database
Recommendation #11: Add data as vector layer – selectable for visualization on a
menu2 visible on default and for searching within a certain cascade (may be an
additional field – like the cascade name – to be added to the related data tables).
Data on storage capacity:
Recommendation #12: Add polygon layer of large reservoirs if possible.
Provinces & districts:
Recommendation #13: Add them as vector layers – selectable for visualization on
a menu3 and for searching/reporting interactively on the web-map.
Main watersheds (14 readily available):
Recommendation #14: Add them as vector layers – selectable for visualization on
a menu and add layer of sub-watershed boundaries if possible.
Data on hydroelectric potential:
Recommendation #15: Add vector layer of main rivers with estimated
hydroelectric potential in MW – selectable for visualization on a menu4 and add
river tributaries where SHPs are located if possible.
In terms of GIS functionality:
Map visualization on WebGIS is static:
Recommendation #16: Organize map layers as selectable on a menu5 for better
interactive visualization.
Manage better interaction between visualization linking maps and attribute
tables:
Recommendation #17: Build relationships between vector layers with
corresponding tables and add more map control tools on WebGIS;
Printable web maps:
2 Like, for instance, menu “layers” in Mozambique Atlas (http://mapviewer.atlasrenovaveis.co.mz/index.php) developed by the International Consultant
3 See previous footnote
4 See previous footnote
5 See previous footnote
http://mapviewer.atlasrenovaveis.co.mz/index.php
-
SMALL HYDROPOWER MAPPING AND PLANING IN VIETNAM
SMALL HYDRO GIS DATABASE AND GUIDELINES FOR REVIEW AND PLANNING ON SMALL HYDRO (DRAFT)
A-I.4 VN.2016.R.002.0
Annex I – Comments and recommendations on the Demo Version of the GIS database
Recommendation #18: Design output maps of SHP locations and queried or
summarized maps with printout templates and export to PDF or PNG.
Reporting:
Recommendation #19: Add chart generation in combination with maps in query
or report making6;
Interactive selection on maps (on mouse click or right mouse):
Recommendation #20: Add spatial search by circle with radius or arbitrary
polygon. Search by rivers or cascades. Search by watersheds or by provinces.
Exporting map dataset:
Recommendation #21: Add exporting function to shapefile and/or to Excel.
In terms of map maintaining and updating, which is an issue that doesn’t seem to have
been addressed:
Recommendation #22: Add editing functions on maps – e.g., add a point by
coordinates or interactively by mouse and/or modify location of a spatial object.
In terms of integration with other RE GIS database systems – to be further discussed and
agreed with MOIT and ESMAP/WB.
Specific comments on System Interface & Functions:
Following are specific comments and recommendations on system interface and
functionality.
In terms of menu hierarchy and based on various information requirements by policy
makers, planners, operators and the public, the system menu should be developed
accordingly. One option would be to organize in hierarchy at different levels.
Recommendation #23: Organize menu hierarchy at macro level for policy and
decision makers using pre-defined reports of SHP by various grouping and
statistical summary by selected time periods including tables, maps and charts.
Recommendation #24: Organize menu hierarchy for planners & researchers using
pre-defined reports (as in macro level) and summary reports by various planning
6 Like suggested in the International Consultant’s Inception Report
-
SMALL HYDROPOWER MAPPING AND PLANING IN VIETNAM
SMALL HYDRO GIS DATABASE AND GUIDELINES FOR REVIEW AND PLANNING ON SMALL HYDRO (DRAFT)
A-I.5 VN.2016.R.002.0
Annex I – Comments and recommendations on the Demo Version of the GIS database
criteria (using advanced queries and filtering), project comparisons and data
extraction.
Recommendation #25: Organize menu hierarchy for operators and safety
managers and project coordinators, by maintaining operational data and
producing current operational reports – interactive warning and searching for
operational data (e.g., reservoirs and weirs safety and water level)
Recommendation #26: Organize menu hierarchy for the general public using a
simple search like in the current version.
Recommendation #27: Add advanced search option to include filtering by
watershed/sub-watershed, by cascades, by storage capacity, by time period, by
type of grid connection (on or off-grid) or by other criteria.
-
SMALL HYDROPOWER MAPPING AND PLANING IN VIETNAM
SMALL HYDRO GIS DATABASE AND GUIDELINES FOR REVIEW AND PLANNING ON SMALL HYDRO (DRAFT)
A-II.1 VN.2016.R.002.0
Annex II – National maps of small hydropower
ANNEX II – NATIONAL MAPS OF SMALL HYDROPOWER
National maps obtained based on the GIS database developed by the National Consultant are presented
next. In order to beneficiate the projects visualization, the territory was divided in four regions: North,
North-Center, South-Center and South and maps were obtained according to those regions (Figure A 1)
From Figure A 2 to Figure A 21 projects included into the software are presented by region, first all
projects and then projects aggregated by status.
-
SMALL HYDROPOWER MAPPING AND PLANING IN VIETNAM
SMALL HYDRO GIS DATABASE AND GUIDELINES FOR REVIEW AND PLANNING ON SMALL HYDRO (DRAFT)
A-II.2 VN.2016.R.002.0
Annex II – National maps of small hydropower
Figure A 1 – Definition of the four regions.
-
SMALL HYDROPOWER MAPPING AND PLANING IN VIETNAM
SMALL HYDRO GIS DATABASE AND GUIDELINES FOR REVIEW AND PLANNING ON SMALL HYDRO (DRAFT)
A-II.3 VN.2016.R.002.0
Annex II – National maps of small hydropower
Figure A 2 – North: hydropower projects identified in Vietnam.
-
SMALL HYDROPOWER MAPPING AND PLANING IN VIETNAM
SMALL HYDRO GIS DATABASE AND GUIDELINES FOR REVIEW AND PLANNING ON SMALL HYDRO (DRAFT)
A-II.4 VN.2016.R.002.0
Annex II – National maps of small hydropower
Figure A 3– North-Center: hydropower projects identified in Vietnam.
-
SMALL HYDROPOWER MAPPING AND PLANING IN VIETNAM
SMALL HYDRO GIS DATABASE AND GUIDELINES FOR REVIEW AND PLANNING ON SMALL HYDRO (DRAFT)
A-II.5 VN.2016.R.002.0
Annex II – National maps of small hydropower
Figure A 4 – South-Center: hydropower projects identified in Vietnam.
-
SMALL HYDROPOWER MAPPING AND PLANING IN VIETNAM
SMALL HYDRO GIS DATABASE AND GUIDELINES FOR REVIEW AND PLANNING ON SMALL HYDRO (DRAFT)
A-II.6 VN.2016.R.002.0
Annex II – National maps of small hydropower
Figure A 5– South: hydropower projects identified in Vietnam.
-
SMALL HYDROPOWER MAPPING AND PLANING IN VIETNAM
SMALL HYDRO GIS DATABASE AND GUIDELINES FOR REVIEW AND PLANNING ON SMALL HYDRO (DRAFT)
A-II.7 VN.2016.R.002.0
Annex II – National maps of small hydropower
Figure A 6 – Working projects located in the North region of Vietnam.
-
SMALL HYDROPOWER MAPPING AND PLANING IN VIETNAM
SMALL HYDRO GIS DATABASE AND GUIDELINES FOR REVIEW AND PLANNING ON SMALL HYDRO (DRAFT)
A-II.8 VN.2016.R.002.0
Annex II – National maps of small hydropower
Figure A 7 – Working projects located in the North-Center region of Vietnam.
-
SMALL HYDROPOWER MAPPING AND PLANING IN VIETNAM
SMALL HYDRO GIS DATABASE AND GUIDELINES FOR REVIEW AND PLANNING ON SMALL HYDRO (DRAFT)
A-II.9 VN.2016.R.002.0
Annex II – National maps of small hydropower
Figure A 8 – Working projects located in the South-Center region of Vietnam.
-
SMALL HYDROPOWER MAPPING AND PLANING IN VIETNAM
SMALL HYDRO GIS DATABASE AND GUIDELINES FOR REVIEW AND PLANNING ON SMALL HYDRO (DRAFT)
A-II.10 VN.2016.R.002.0
Annex II – National maps of small hydropower
Figure A 9 – Working projects located in the South region of Vietnam.
-
SMALL HYDROPOWER MAPPING AND PLANING IN VIETNAM
SMALL HYDRO GIS DATABASE AND GUIDELINES FOR REVIEW AND PLANNING ON SMALL HYDRO (DRAFT)
A-II.11 VN.2016.R.002.0
Annex II – National maps of small hydropower
Figure A 10 – Under construction projects located in the North region of Vietnam.
-
SMALL HYDROPOWER MAPPING AND PLANING IN VIETNAM
SMALL HYDRO GIS DATABASE AND GUIDELINES FOR REVIEW AND PLANNING ON SMALL HYDRO (DRAFT)
A-II.12 VN.2016.R.002.0
Annex II – National maps of small hydropower
Figure A 11 – Under construction projects located in the North-Center region of Vietnam.
-
SMALL HYDROPOWER MAPPING AND PLANING IN VIETNAM
SMALL HYDRO GIS DATABASE AND GUIDELINES FOR REVIEW AND PLANNING ON SMALL HYDRO (DRAFT)
A-II.13 VN.2016.R.002.0
Annex II – National maps of small hydropower
Figure A 12 – Under construction projects located in the South-Center region of Vietnam.
-
SMALL HYDROPOWER MAPPING AND PLANING IN VIETNAM
SMALL HYDRO GIS DATABASE AND GUIDELINES FOR REVIEW AND PLANNING ON SMALL HYDRO (DRAFT)
A-II.14 VN.2016.R.002.0
Annex II – National maps of small hydropower
Figure A 13 – Under construction projects located in the South region of Vietnam.
-
SMALL HYDROPOWER MAPPING AND PLANING IN VIETNAM
SMALL HYDRO GIS DATABASE AND GUIDELINES FOR REVIEW AND PLANNING ON SMALL HYDRO (DRAFT)
A-II.15 VN.2016.R.002.0
Annex II – National maps of small hydropower
Figure A 14 – Projects located in the North region of Vietnam in FS preparing.
-
SMALL HYDROPOWER MAPPING AND PLANING IN VIETNAM
SMALL HYDRO GIS DATABASE AND GUIDELINES FOR REVIEW AND PLANNING ON SMALL HYDRO (DRAFT)
A-II.16 VN.2016.R.002.0
Annex II – National maps of small hydropower
Figure A 15 – Projects located in the North-Center region of Vietnam in FS preparing.
-
SMALL HYDROPOWER MAPPING AND PLANING IN VIETNAM
SMALL HYDRO GIS DATABASE AND GUIDELINES FOR REVIEW AND PLANNING ON SMALL HYDRO (DRAFT)
A-II.17 VN.2016.R.002.0
Annex II – National maps of small hydropower
Figure A 16 – Projects located in the South-Center region of Vietnam in FS preparing.
-
SMALL HYDROPOWER MAPPING AND PLANING IN VIETNAM
SMALL HYDRO GIS DATABASE AND GUIDELINES FOR REVIEW AND PLANNING ON SMALL HYDRO (DRAFT)
A-II.18 VN.2016.R.002.0
Annex II – National maps of small hydropower
Figure A 17 – Projects located in the South region of Vietnam in FS preparing.
-
SMALL HYDROPOWER MAPPING AND PLANING IN VIETNAM
SMALL HYDRO GIS DATABASE AND GUIDELINES FOR REVIEW AND PLANNING ON SMALL HYDRO (DRAFT)
A-II.19 VN.2016.R.002.0
Annex II – National maps of small hydropower
Figure A 18 – Projects located in the North region of Vietnam in planning (without developer).
-
SMALL HYDROPOWER MAPPING AND PLANING IN VIETNAM
SMALL HYDRO GIS DATABASE AND GUIDELINES FOR REVIEW AND PLANNING ON SMALL HYDRO (DRAFT)
A-II.20 VN.2016.R.002.0
Annex II – National maps of small hydropower
Figure A 19 – Projects located in the North-Center region of Vietnam in planning (without developer).
-
SMALL HYDROPOWER MAPPING AND PLANING IN VIETNAM
SMALL HYDRO GIS DATABASE AND GUIDELINES FOR REVIEW AND PLANNING ON SMALL HYDRO (DRAFT)
A-II.21 VN.2016.R.002.0
Annex II – National maps of small hydropower
Figure A 20 – Projects located in the South-Center region of Vietnam in planning (without developer).
-
SMALL HYDROPOWER MAPPING AND PLANING IN VIETNAM
SMALL HYDRO GIS DATABASE AND GUIDELINES FOR REVIEW AND PLANNING ON SMALL HYDRO (DRAFT)
A-II.22 VN.2016.R.002.0
Annex II – National maps of small hydropower
Figure A 21 – Projects located in the South region of Vietnam in planning (without developer).
-
MINISTRY OF INDUSTRY
AND TRADE
--------
SOCIALIST REPUBLIC OF VIET NAM
Independence - Freedom – Happiness
---------------- No.: 43/2012/TT-BCT Ha Noi, December 27, 2012
CIRCULAR
REGULATION ON MANAGEMENT OF PLANNING, INVESTMENT AND
CONSTRUCTION OF HYDROPOWER PROJECT AND OPERATION OF
HYDROPOWER WORKS
Pursuant to the Electricity Law No. 28/2004/QH11 dated December 3, 2004;
Pursuant to the Construction Law No. 16/2003/QH11 dated November 26, 2003;
Pursuant to Law on Investment No. 59/2005/QH11 dated November 29, 2005;
Pursuant to the Law on amending and supplementing a number of articles of the Laws
relating to investment in capital construction No.38/2009/QH12 dated June 19, 2009 of the
National Assembly;
Pursuant to Decree No. 95/2012/ND-CP dated November 12, 2012 of the Government
defining the functions, tasks, powers and organizational structure of the Ministry of
Industry and Trade;
Under the leadership of Prime Minister in document No. 888/TTg-KTN dated May 31, 2010
on the strengthening of the management of hydropower projects;
At the proposal of the General Director of the Department of Energy;
The Minister of Industry and Trade issues Circular regulating the management of planning,
investment and construction of hydropower project and operation of hydropower works
Chapter I
GENERAL PROVISION
Article 1. Scope of adjustment and subject of application
1. This Circular provides for a number of contents on management of hydropower planning
and investment in hydropower project construction and operation of hydropower works on
the territory of Vietnam.
2. This Circular applies to organizations and individuals involved in activities related to
hydropower planning, investment in hydropower project construction and operation of
hydropower works on the territory of Vietnam.
Article 2. Explanation of terms
1. Cascade hydropower planning: is the planning to determine the hydropower projects
which can be invested in construction with the installed capacity greater than 30 MW on a
river or system of rivers of a river basin.
2. Small hydropower planning: is the planning to determine the hydropower projects which
can be invested in construction with the installed capacity up to 30 MW on the rivers and
streams of the river basin.
-
3. Pumped-storage hydropower planning: is the planning to determine locations to build
Pumped-storage hydropower plant to supply peak power output of sub-loading diagram of
the national power system
4. Multi-purpose hydropower project is the hydropower projects which, in addition to the
main task of power generation, also regulates and adds flow on the dry season and / or
reduces flood in service of socio-economic development of the lowlands.
Chapter II
MANAGEMENT OF HYDROPOWER PLANNING
Article 3. Hydropower planning
1. Hydropower planning includes cascade hydropower planning, pumped-storage
hydropower planning and small hydropower planning.
2. Cascade hydropower planning is formulated uniformly for each river basin not divided
by administrative boundaries. For river basins with the cascade hydropower planning
approved on the main river stream, the cascade hydropower planning is permitted but must
be consistent with the cascade hydropower planning on the main river stream
3. Pumped-storage hydropower planning is formulated nationwide or in each area and
region of the national power system.
4. Small hydropower planning is formulated in the areas of centrally-affiliated provinces
and cities (hereafter referred to as province).
Article 4. Principle of hydropower planning
1. Ensuring the compliance with current regulations of law on construction, water
resources, environmental protection, forestry protection and development and relevant
regulations.
2. Ensuring the compliance with the planning of socio-economic development, water
resource planning, irrigation sector planning, electricity development and other relevant
strategies and planning approved by the competent authorities.
3. Small hydropower planning must ensure the consistency with the cascade hydropower
planning and the pumped-storage hydropower planning approved; the pumped-storage
hydropower planning must be consistent with the cascade hydropower planning approved.
Article 5. Formulation of hydropower planning
1. Hydropower planning is formulated once and can be adjusted and added to be consistent
with the situation of social –economic development of each period.
2. Hydropower planning must be formulated by the functional and qualified consultation
agency in accordance with regulations of law.
3. Authority of organization of formulation of hydropower planning:
a) General Department of Energy shall organize the formulation of the cascade hydropower
planning and and the pumped-storage hydropower planning in the country.
b) Provincial People's Committee shall organize the formulation of small hydropower
planning in the area. For small hydropower project located in two or more provinces, the
-
Provincial People's Committee where the power plant is expectedly located shall agree with
the Provincial People's Committees of the relevant provinces for organization of planning.
In case the Provincial People's Committees do not agree with one another, the Provincial
People's Committee where the power plant is expectedly located shall send written report to
the Ministry of Industry and Trade for consideration and settlement.
Article 6. Content and dossier of hydropower planning.
1. The content of the cascade hydropower planning and small hydropower planning shall
comply with Annex 1 issued together with this Circular and must ensure the following
requirements:
a) Updating the planning, direction of socio-economic development of project area; present
condition and planning of relevant projects of extraction and use of water resources in the
basin approved by the competent authority.
b) Fully investigating, surveying and assessing the natural conditions (topography, geology,
meteorology, hydrology, tectonic earthquake), people’s livelihood, economy and society,
transport, power grid works ... in the planning study area.
c) Assessing the conformity and impact of the hydropower projects proposed planning and
other related projects in the basin.
d) Studying the plans, schemes and scale of extraction; evaluating the economic and energy
efficiency of the proposed projects to recommend the planning scheme.
e) Assessing the strategic environment under the provisions of Decree No. 29/2011/ND-CP
of April 18, 2011 of the Government on assessment of strategic environment and
environmental impact and environmental protection commitment (Decree No. 29/2011/ND-
CP).
g) Surveying and preliminarily assessing the impact of the projects with proposed planning
for population, land, extraction and use of water needs in the lowlands. Except for multi-
purpose hydropower projects, other projects with proposed planning must not occupy more
than 10 hectares of land of various types or relocate more than 01 households with 01 MW
installed capacity.
h) Preliminary assessing and proposing solutions to minimize the negative impact of the
project on the environment – society such as minimally discharging of flow to lowlands;
compensation, support, relocation and resettlement; plantation to recover forest area for
converted purpose use of the projects.
i) Priority is given to construction projects proposed on the basis of technical and economic
indicators and the socio-environmental impact of each project.
2. Content of the pumped-storage hydropower planning includes:
a) Contents specified in clause 1 of this Article.
b) Updating results of forecasting electricity demand and supply and the load diagrams of
the electrical system in the study of national electricity development plan which has been
approved; updating the operating status of the power plants and the progress of construction
investment of related power projects of the power system.
-
c) Analyzing and assessing the need and scale of the pumped-storage hydropower projects
and function in the peak power generation of sub-loading diagram of the national power
system.
3. Hydropower planning dossier including the printing copy stamped by the planning
advisory agency as prescribed and the CD with full contents of the planning content
specified in Clause 1 and 2 of this Article (hereinafter referred to as the hydropower
planning dossier).
Article 7. Appraisal and approval of hydropower planning
1. The agency organizing the formulation of planning as prescribed in Clause 3, Article 5 of
this Circular shall submit it to the Ministry of Industry and Trade for consideration and
approval attached to a dossier of hydropower planning.
2. Within 05 working days after receiving document for approval and a dossier of
hydropower planning, the Ministry of Industry and Trade shall appraise and issue document
attached to 01 copy of the printing copy of the dossier of planning for submission to
agencies and units concerned to gather opinions about hydropower planning as prescribed.
3. The agencies and units concerned are gathered opinions about hydropower planning
specified in Clause 2 of this Article including:
a) For the cascade hydropower planning and Pumped-storage hydropower planning: the
Ministry of Natural Resources and Environment, Ministry of Agriculture and Rural
Development, Ministry of Construction, Ministry of Transport, Ministry of Defense,
People's Committees of provinces of project area and other related agencies and units (if
necessary).
b) For small hydropower planning: the Ministry of Natural Resources and Environment,
Ministry of Agriculture and Rural Development and other related units (if necessary).
4. The content of appraisal and opinion contribution about hydropower planning must
include:
a) The compatibility of the proposal of hydropower planning with the existing projects and
works and other related strategy and planning which have been approved by the competent
authority.
b) The reliability and satisfaction of the quality requirements of the documents, data used
for planning.
c) The technical compatibility and economic efficiency of the ladder system and planning
of each project with proposed planning.
d) Assessment of impacts and measures to minimize negative impacts to the society and
environment of the projects with proposed planning.
e) The compatibility of the construction investment progress of projects proposed in the
plan with the present condition of power grid and electricity development planning in the
area.
5. The agencies and units concerned consulted on hydropower planning shall respond to the
Ministry of Industry and Trade within the time limit specified in the written consultation.
-
Beyond this time limit, if the agencies and units not having opinions shall be deemed to
have agreed with the planning content.
6. After having the assessment results and the written consultation of the relevant agencies
and units of hydropower planning, within 05 working days, the Ministry of Industry and
Trade shall have document to summarize the appraisal opinions, for submission to the
submitting agency for the planning approval to coordinate with the advisory agency to
formulate complete study planning of the content and dossier of hydropower planning
7. The submitting agency is responsible for making report and explanation and receiving of
appraisal opinions specified in Clause 6 of this Article, sending it to the Ministry of
Industry and Trade together documents with the revised and supplemented contents for
consideration of hydropower planning approval.
Article 8. Approval of hydropower planning
1. The hydropower planning to be approved must satisfy the following conditions:
a) Having adequate dossier and content of planning as prescribed.
b) Being consistent with the relevant strategies, planning, projects and works.
c) The materials, data, result of calculation and analysis in the planning must ensure the
quality and accuracy.
d) Rationally exploiting the hydro power resources of the basin under study, minimizing
the negative impact on the society and environment to achieve the highest benefit to society
and the State.
2. Within 10 working days after receiving a written explanation and appraisal opinion
receiving and planning dossier specified in Clause 7, Article 7 of this Circular, the Ministry
of Industry and Trade shall consider and make a decision on approval for hydropower
planning if meeting the conditions specified in Clause 8 of this Article or has a written
reply to the submitting agency on the reason why the hydropower planning was not (or has
not yet been) approved.
3. Main contents of hydropower planning approval includes
a) Information about the expected site for works construction (geographic coordinates,
name of commune, district, province, river and spring), extraction scheme, tasks and main
technical parameters (basin area to Flv dam line, the normal rising water level MNDBT and
dead water level MNC, flood prevention capacity Wpl (if any), the downstream water level
of smallest plant MNHLmin, installed capacity Nlm and average output power Eo) of
projects.
b) Technical and economic social and environmental issues of the projects should be taken
into account and implemented during the process of construction research.
c) Expected progress or priority over the construction of projects.
4. Within 03 working days after the approval of hydropower planning, the Ministry of
Industry and Trade shall send 01 original of approval decision together with 01 copy of the
dossier of complete planning to the provincial People's Committee and the Service of Trade
and Industry in the area where located the hydropower project; send 01 original of the
-
approval decision to the Vietnam Electricity Group, the ministries, sectors, agencies and
units concerned.
Article 9. Adjustment and addition to hydropower planning
1. The hydropower planning is adjusted and added in the following cases:
a) Adjusting the content of planning approval is specified at Point a, Clause 3, Article 8 of
this Circular for projects of hydropower planning approved to enhance economic efficiency
and minimize negative impacts on society and environment or comply with other relevant
plans.
b) Adding projects to the approved hydropower planning.
2. The adjustment and addition to hydropower planning are implemented as follows::
a) For projects specified at Point a, Clause 1 of this Article: Investors of projects shall
submit the planning to the Ministry of Industry and Trade for consideration and approval
together with a report on the planning adjustment with the content specified in Article 6 of
Circular or dossier of works construction investment project as prescribed. The appraisal
and approval of the planning adjustment shall comply with the provisions of Clauses 2, 4,
6, 7, Article 7 and Article 8 of this Circular. The consultation (if necessary) and feedback of
the agencies and units concerned about the contents of the planning adjustment of the
project shall comply with the provisions of Clause 2, Clause 3 and Clause 5, Article 7 of
this Circular.
b) For projects specified at Point b, Clause 1 of this Article: Complying with the provisions
of Article 4, Article 5, Article 6, Article 7 and Article 8 of this Circular.
Article 10. Publication of hydropower planning
1. The hydropower planning must be published within 30 days from the approval day to the
agencies, units, organizations and individuals for implementation.
2. The Ministry of Industry and Trade shall publish, guide, monitor and inspect the
implementation of the cascade hydropower planning and the pumped-storage hydropower
planning approved nationwide.
3. Provincial People’s Committee shall publish, guide, monitor and inspect the
implementation of small hydropower planning approved in provincial area.
Article 11. Funds for formulation, appraisal, approval and publication of hydropower
planning
1. Funds for formulation, appraisal, approval and publication of hydropower planning
(including adjustment and addition to hydropower planning) are balanced in annual budget
plan and other legal mobilized capital resources.
2. The Ministry of Industry and Trade shall register central budget under yearly plan for the
formulation, appraisal and approval, publish the cascade hydropower planning and
pumped-storage hydropower planning. The provincial People’s Committee shall register
the provincial budget under yearly plan for the formulation, appraisal, approval and
publication of small hydropower planning in provincial area.
-
3. The management and use of funds in Clause 1 of this Article shall comply with the
relevant provisions of law.
4. Encouraging business to invest in funds and participate in formulation of hydropower
planning to develop hydroelectric power after being approved by the state agencies
responsible for formulation under the provisions of Clause 3 of Article 5 of this Circular.
This funding is included in the cost of production of the enterprise but must be in
accordance with current regulations on price, cost norm for electricity development
planning.
Chapter III
MANAGEMENT OF HYDROPOWER PROJECT CONSTRUCTION
INVESTMENT
Article 12. Principle of management of hydropower project construction investment
1. The investment in construction of hydropower projects must ensure: compliance with the
regulations of the law on investment, construction, water resources, environmental
protection and other relevant regulations; compliance with the hydropower planning and in
accordance with the electricity development plan approved by the competent authority.
2. In case the projects are under the hydropower planning but not yet included in the
electricity development plan or not in accordance with the electricity power development
plan, the competent authorities permitting investment must consult the Ministry of Industry
and Trade of the compatibility of the project with electricity development planning before
considering permission for investment.
3. Any change in the legal status of the investor, scope, tasks, schedule of hydropower
projects in the construction process must be competent state agencies related to written
permissionbefore implementation.
Article 13. Requirements for investor of hydropower projects.
1. As enterprises of economic sectors established under the provisions of the Law on
Enterprises and having business line of construction investment of hydropower projects.
2. Having sufficient financial capacity to implement the project: Investors must ensure their
equity of at least 30% of the total investment of the project and being committed in writing
by the credit institutions, financial institutions, banks for the rest of the investment loan.
Investors must report to the competent authorities on the selection of the investors specified
in Clause 2, Article 15 of this Circular and on the plan to allocate investment capital for the
projects and ensure the compliance with progress of the project implementation.
3. Investor is not the investor of another project which is being slowly deployed or delayed
later than 12 months compared with regulation in the investment certificate, unless it is
suspended or extended for the implementation of the project by provisions of the law on
investment. Investors have to provide copies of dossiers relating to the implementation of
the projects in which they are investors to the investment authority for consideration and
shall be responsible for the accuracy of this information.
Article 14. Plan for implementation of construction investment of hydropower
projects
-
1. The plan for implementation of construction investment of hydropower projects
(including construction starting schedule, operation of generator and completion of the
works) is the foundation that allows the implementation of the project.
2. The plan for implementation of construction investment of hydropower projects must be
consistent with:
a) Electricity development plan approved by the competent authority.
b) Situation of economic and social development, sub-loading and the relevant power grid
works in the area.
3. Prior to November 30 annually, the provincial People’s Committee shall submit the plan
for implementation of construction investment of hydropower projects to the Ministry of
Industry and Trade for considerationand approval in the following year. In case the project
is located in two or more provinces, those provincial People’s Committees shall assume the
prime responsibility and agree with the related provincial People’s Committes for
submission to the Ministry of Industry and Trade for approval.
Article 15. Selection of investor of hydropower project
1. The selection of investor of hydropower project must ensure:
a) Compliance with current regulations of the law on investment, procurement and other
relevant regulations.
b) Proper selection of the investor with the highest capacity and experience to carry out
investment projects on schedule, quality assurance and minimization the negative impacts
of the project on the environment and society.
2. The selection of investor of hydropower project is implemented as follows:
a) For projects in the list of power in the national electricity development plan but the
investors are not identified: Complying with the regulation of the law on investment and
decision on approval of national electricity development plan of the Prime Minister. In
particular, the competent authorities selecting the investors must consult the ministries and
sectors and localities concerned for review before submission to the competent authorities
for the approval of the project investor.
b) For other projects: the provincial People’s Committee having projects shall organize the
selection of the investor; consult the Ministry of Industry and Trade about the compatibility
of the project with planning and the meeting the requirements of the investor; consult the
relevant agencies for consideration and approval.
3. In case the project is located in many provinces, the provincial People’s Committee shall
assume the prime responsibility and consult the Ministry of Industry and Trade and the
People’s Committees of provinces concerned and other agencies as prescribed to select the
investor.
4. The consulted agencies specified at Points a and b, Clause 2 of this Article shall reply
consulting agency within 10 working days from the date of receipt of a written request for
consultation. Beyond this time limit, if the relevant authorities have no opinion, they shall
be deemed to agree with the consulting agencies on the selection of project investors.
-
5. Encouraging the selection of an investor to carry out cluster of hydropower projects
related to the regulation of the flow or use power grid works of capacity transmission in
common of the hydropower plants.
6. Enterprises that have invested funds and participated in hydropower planning in
accordance with Clause 4, Article 8 of this Circular are prioritized to become the investor
of a number of hydropower projects in that planning study if registering investment and
meeting the prescribed requirements.
Article 16. Formulation of investment project in hydropower works construction
1. After having been permitted by the competent authority for investment under the current
regulations, the investor of hydropower projects shall formulate investment project in
hydropower works construction (hereinafter referred to as the investment project).
2. Contents of investment projects shall comply with the provisions of the law on the
management of works construction investment project and perform the following contents:
a) Investigating, surveying and carefully assessing natural conditions (topography, geology,
meteorology, hydrology, tectonic earthquake), people’s livelihood, the economy and
society, transportation, power grid works ... in the area.
b) Updating the present condition and planning the extraction and use of related water
resources in the basin, as a basis for calculation for determining the design hydrological
characteristics and the relationship between flow and water levels in study lines.
c) Calculating and determining the minimum flow specified in Decree No. 112/2008/ND-
CP of October 20, 2008 of the Government on management, protection and general
extraction of resources and environment of hydropower and irrigation reservoir (Decree
No. 112/2008/ND-CP) and the guidance of the Ministry of Natural Resources and
Environment; having measures to ensure minimum discharge of flow to the lowlands.
d) Analyzing and comparing alternatives to choose works line, the normal rising water
level, dead water level, installed capacity Nlm, number of plant units, structure of rolling
weir, size and structure of spillway, subsidiary solution, plan for connection of hydropower
plant to the power system to raise investment efficiency and minimize negative effect for
environment and society.
e) Assessing the project's impact on safety, output power, extraction capacity of the
adjacent works and projects in the basin that have been approved by the competent
authority.
g) Computing the safety, stability, durability, waterproof, hydraulic regime… of the main
items of works such as rolling weir, spillway, intake, tunnel, diversion channel, pressure
vessel, pressure tower, penstock, hydropower plant, discharge canal, foundation pit dug
roof in all working conditions of the works.
h) Arranging adequate devices monitoring activities of the works and foundation in
accordance with national technical regulation QCVN 04-05:2012 / BNNPTNT (Irrigation
works - The main provisions on the design) and national Standard TCVN 8215:2009
(Irrigation works - The main provisions of the design and layout of device monitoring
headworks cluster).
-
i) Planning the connection of hydropower plant to the national power system, ensuring the
compliance with the electricity development planning, connection planning of hydroelectric
power to the national power system which has been approved; having written agreement of
the Vietnam Electricity Group on technical plans for connection, measurement, control and
protection devices, of the electrical connection works.
k) Planning the transportation for the construction and operation of hydropower works to
ensure compliance with transportation development planning in the region; planning the
organization of construction and the works construction investment schedule to ensure the
safety, effectiveness and response to the electricity generation as prescribed.
l) Carefully assessing the impact of the project on the environment in the area in
accordance with Decree No. 29/2011/ND-CP. In particular investigating the specific land
occupation area of all types (residential land, rice land, crop land, protection forest land,
specialized land, production forest land, river and spring lan, etc.) of hydropower works,
and works in service of construction performance and operation, the area and / or
resettlement place, plantation area to recover forest for converted purpose use of the
projects.
m) Having written agreement of the policy of the relevant competent authorities on the
conversion of land use purpose for the project.
n) Consulting the related provincial People's Committees on the measures to minimize
negative impacts on the environment and society: the compensation, support, relocation and
resettlement; afforestation to replace the forest area to be converted the purpose of use for
the project; restoring the ground after construction of works.
o) Assessing other combining effects of projects such as: flood reduction, water supply for
lowlands; development of tourism, water transportation, aquaculture; labor force employed
in the process of investment, construction and operation of the project.
p) Having plans for allocation of investment capital in accordance with the progress of the
works construction investment; analyzing and assessing the financial and economic
efficiency of the project.
Article 17. Assessment and approval of hydropower investment Project
1. The assessment and approval of hydropower investment Project shall comply with
regulations of law on management of works construction investment Project
2. The focal units in project appraisal shall consult the sector management agencies, state
management agencies on construction and other relevant agencies about the investment
project and basic design for appraisal of project in accordance with regulations.
3. In case the study results of investment project are different from the contents of the
planning approval of the project specified at Point a, Clause 10, Article 7 of this Circular,
the investor must submit the study result to the Ministry of Industry and Trade for
consideration, approval and adjustment of hydropower planning as provided for at Point a,
Clause 1 and Point a, Clause 2, Article 8 of this Circular prior to approval of project
investment.
4. The content of assessment and consultation about investment project or basic design of
related agencies and units specified in Clause 2 of this Article must include:
-
a) Quality, reliability of the materials and data on meteorology, hydrology, topography,
geology, etc. used in the calculation of project design.
b) The compatibility of the overall layout plan of the works, the structure and main
parameters of reservoirs, rolling weir, spillways, subsidiary works, intake, tunnel, diversion
channel, penstock, pressure vessel, pressure tower, discharge canal, pit dug roof, hydro
mechanical equipment, electrical equipment ...
c) The compatibility of the energy parameters (installed capacity Nlm, guaranteed output
Nđb, output power Eo) and connection plan to the power system of the project.
d) The compatibility of the project design with the construction standards and regulation,
environment, fire prevention and fighting, etc. allowed to apply.
5. The person making a decision on investment in hydropower project only approves the
investment project after being approved or agreed by the competent state agencies with the
following contents:
a) Report on assessment of environmental impact or written commitment to environmental
protection as prescribed.
b) Plan or project of compensation, support, relocation, resettlement as prescribed.
6. After approval of the investment project, the investor shall submit 01 complete set of
dossier (including 01 copy and 01 CD recording the dossier content) with 01 original
approval decision to the Ministry of Industry and Trade, provincial People’s Committee
and Service of Trade and Industry of the project area to monitor, inspect and direct the
implementation of the project.
Article 18. Formulation, appraisal and approval of design of hydropower works
construction.
1. The investors shall organize the formulation, appraisal and approval of the technical
design (for project requiring 3 step design) or design of performance drawing (for project
requiring 3 step design) of the project as prescribed by law on the management of works
construction investment projects and are responsible for the approval content.
2. The technical design content (for project requiring 3 step design) or design of
performance drawing (for project requiring 3 step design) of the project must ensure
compliance with the basic design in the investment project approved. In case of change of
content, the investors should consult the relevant authorities in accordance with the
provisions of Clause 2, Article 16 of this Circular about the change of content in order to
approve the adjustment of the investment project before approval of technical design or
design of performance drawing.
Article 19. Starting construction of hydropower works
Investors only start the construction when meeting all the conditions stipulated in Article 72
of the Construction Law and the current provisions of the relevant law.
Article 20. Investment in construction of power connection and capacity transmission
works of hydropower plant.
The investment in construction of power connection and capacity transmission works of
hydropower plant shall comply with provisions in the Electricity Law and guiding
-
documents and detailed provisions on implementation of the Electricity Law. For
hydropower projects with installed capacity of less than 30MW, the investor must build the
connection line from the plant to power sale location as agreed with the buyer. In case of
failure of agreement, the investor shall request the Ministry of Industry and Trade for
consideration and approval for implementation. The relevant investment expenses shall be
included in the power sale price as prescribed.
Article 21. Management of construction of hydropower works
1. The management of hydropower works quality shall comply with regulation of law on
management of construction works quality particularly pay special attention to the
management of quality of rolling weir, spillway, valve gate of spillway, outlet through dam
body, intake, diversion tunnel, penstock, aqueduct bridge on water channel and hydropower
plant.
2. Other management contents on construction of hydropower works shall comply with
current regulations of the law on the management of works construction investment
projects.
3. The testing, survey and certification of eligibility for load-bearing safety, certification of
conformity of quality of construction works shall comply with current regulations on
management of works construction investment projects and quality of construction works
particularly requiring the performance of the test and certification of eligibility for load-
bearing safety before putting into use for items that when incidents occur due to loss of
bearing capacity can cause catastrophe for people, property and the environment (including
rolling weir, spillway, valve gate of spillway, outlet through dam body, intake, diversion
tunnel, penstock, aqueduct bridge on water channel and hydropower plant, etc.) of
hydropower works.
Article 22. Monitoring and assessment of construction investment of hydropower
project
The monitoring and assessment of investment in hydropower projects shall comply with the
provisions of Decree No. 113/2009/ND-CP of December 15, 2009 of the Government on
monitoring and assessment of investment; Decision No. 80/ 2005/QD-TTg of April 18,
2005 of the Prime Minister on promulgation of the Regulation on monitoring of investment
of community; Circulars of the Ministry of Planning and Investment No.13/2010/TT-BKH
of June 2, 2010 stipulating the form of report on monitoring and assessment of investment
No. 22/2010/TT-BKH of December 02, 2010 stipulating the norm of expense of monitoring
and assessment of investment, No.23/2010/TT-BKH of December 13, 2010 stipulating the
condition and capability of the organization and individual performing consultation and
assessment of investment projects and the relevant provisions of law.
Article 23. Dealing with the hydroelectric projects with slow progress
1. For hydropower projects permitted for investment or granted with investment certificate
but after 12 months the investors do not deploy or unable to comply with the prescribed
schedule (except the projects permitted for suspension or extension for performance), these
projects shall be recovered and transferred to the other investors in accordance with the
provisions of the law on investment.
2. The transfer of project to be recovered to other investors shall be done as follows
-
a) For projects under the national power development plan: Provincial People’s Committee
where the project is located shall make a report to the Ministry of Industry and Trade for
submission to the Prime Minister for consideration and decision.
b) For other projects: Provincial People’s Committee shall make a decision on recovery and
select another investor in accordance with current regulations and the contents of the
relevant provisions of Article 14 of this Circular.
Chapter IV
MANAGEMENT OF OPERATION OF HYDROPOWER WORKS
Article 24. Process of operation of hydropower reservoir.
1. The process of operation of hydropower reservoir must be approved by the competent
authority before the reservoir retain water for the first time, on the basis of the results of
investment study and works construction design, in accordance with the provisions of
Decree No. 112/2008/ND-CP and Decision No.285/2006/QD-TTg of December 25, 2006
of the Prime Minister on the content of promulgation authority and implementation of the
process of hydropower reservoir operation.
2. The formulation of process of reservoir operation shall be done by the project investor in
coordination with the consultation agencies that have function of appropriate hydropower
project design.
3. The process of reservoir operation must ensure the following requirements:
a) Safety for the works with all floods with scale smaller or equal to check flood of the
works as prescribed.
b) Operation, regulation and discharge of flood to ensure the safety for the lowlands
c) Complete performance of tasks of the project.
d) Compliance with the process of inter-reservoir operation approved by competent
authority (if any).
e) Minimization of the negative impacts of the project on the environment - society
g) Improvement of efficiency of hydro power exploitation of the works.
4. The main contents of the process of hydropower reservoir operation specified in Annex 2
issued together with this Circular.
5. Organizations and individuals concerned must comply with the process of reservoir
approved by the competent authority particularly paying special attention to the
implementation of regulations on the preparation of flood prevention and fighting; flood
discharge operation, power generation; minimum flow discharge to lowlands;coordination
mode, information and reports as prescribed.
6. Quarterly in the dry season and monthly during the flood season, the hydropower dam
owner must be a written report to the Ministry of Industry and Trade, the Ministry of
Natural Resources and Environment, the provincial People's Committees and the Service of
Trade of the project area on the reservoir operation.
Article 25. Operation of hydropowe plant in the national power system.
-
1. Prior to commercial operation, the project investor must be granted the power operation
Permit by the competent authority under the provisions of the Electricity Law and confirm
the implementation of works, environmental protection measures under the provisions of
Decree No. 29/2011/ND-CP.
2. In the course of operation and generation to the national power grid, the unit managing
and operating power plant must comply with the operational mode, command and
regulation order of the regulating unit of the power system; comply with the process,
technical regulations on power plant operation and power grid; comply with regulations on
hydropower dam safety and the process of reservoir operation approved by the competent
authority.
Article 26. Maintenance of hydropower works
The maintenance of hydropower projects shall comply with the provisions of Decree No.
114/2010/ND-CP of December 6, 2010 of the Government on maintenance of construction
works and other relevant regulations.
Article 27. Inspection and monitoring in the course of operation of hydropower
works.
Annually, the Ministry of Industry and Trade in collaboration with provincial People’s
Committee of the project area and the agencies and units concerned shall inspect and assess
the implementation of the process of reservoir operation and the power operation Permit of
the hydropower works having been put into operation.
Chapter V
IMPLEMENTATION PROVISION
Article 28. Implementation organization
1. General Department of Energy is responsible for organizing, guiding and coordinating
with the Service of Industry and Trade of provinces where hydropower project is located
for inspecting the implementation of this Circular.
2. People’s Committee of the provinces where hydropower project is located shall direct the
related agencies and units in the area to implement this Circular
3. Every six months, before June 20 and December 20 annually, the People’s Committee of
the provinces where hydropower project is located shall make a report to the Ministry of
Industry and Trade on the implementation of the planning, investment in construction of
hydroelectric projects and operation of the hydropower projects in the area.
Article 29. Effect
1. This Circular takes effect on February 10, 2013. The regulations and guidelines of the
Ministry of Trade and Industry (formerly the Ministry of Industry) issued related to the
management of the planning, investment in hydroelectric project construction and operation
of hydroelectric works contrary to the provisions of this Circular are annulled.
2. The hydropower planning already approved by competent authorities as prescribed
before this Circular takes effect shall continue complying with decisions issued.
-
3. The adjustment, addition of hydropower planning already approved by competent
authorities shall comply with the provisions of this Circular.
4. Any problem arising in the implementation of this Circular, the organizations and
individuals should reflect in writing to the Ministry of Trade and Industry (through the
General Department of Energy) for consideration and settlement. /.
PP. MINISTRY
DEPUTY MINISTRY
Le Duong Quang
------------------------------------------------------------------------------------------------------
This translation is made by LawSoft and for reference purposes only. Its copyright is
owned by LawSoft and protected under Clause 2, Article 14 of the Law on Intellectual
Property.Your comments are always welcomed
-
THE NATIONAL ASSEMBLY
-------
SOCIALIST REPUBLIC OF VIET NAM
Independence - Freedom - Happiness
---------- Law No. 17/2012/QH13 Hanoi, June 21, 2012
LAW
ON WATER RESOURCES
Pursuant to the 1992 Constitution of the Socialist Republic of Vietnam, which was amended
and supplemented under Resolution No. 51/2001/QH10;
The National Assembly promulgates Law on water resources.
Chapter I
GENERAL PROVISIONS
Article 1. Scope of regulation
1. This Law provides on management, protection, exploitation and use of water resources,
as well as the prevention of, combat against and overcoming of harmful effects caused by
water in the territory of the Socialist Republic of Vietnam.
2. Underground water and sea water in exclusive economic zones, continental shelves of
the Socialist Republic of Vietnam, mineral water, natural hot water are not subject to
adjustment of this Law.
Article 2. Interpretation of terms
In this Law, the below terms are construed as follows:
1. Water resources include underground water, surface water, rain water and sea water in
territory of the Socialist Republic of Vietnam.
2. Water sources mean accumulation shapes of natural or artificial water which may
exploit, use, including rivers, springs, canals, ditches, lakes, ponds, lagoons, seas,
underground aquifers; rain, ice, snow and other.
3. Surface water means water existing on surface mainland or islands.
4. Underground water means water existing in underground aquifers.
5. Inter-provincial water sources mean water sources being allocated on area of 02 or more
provinces or centrally-affiliated cities.
6. Intra-provincial water sources mean water sources being allocated on area of 01
province or centrally-affiliated city.
7. Inter-country water sources mean water sources flowing from Vietnam’s territory
through other country’s territory or vice versa or water sources on border line between
Vietnam and neighbor country.
8. River basin means land zone in which surface water, underground water flowing
naturally in rivers and escaping out a common gate or escaping out sea.
River basin includes inter-provincial river basin and intra-provincial river basin.
-
9. Inter-provincial river basin means river basin on area of 02 or more provinces or
centrally-affiliated cities.
10. Inter-provincial river basin means river basin on area of 01 province or centrally-
affiliated city.
11. Living water means clean water or water that may use for eating, drinking, and hygiene
of human.
12. Clean water means water with quality satisfying technical regulation on clean water of
Vietnam.
13. Living water sources mean water sources that may supply living water or treated into
living water.
14. Water source pollution means changes physical nature, chemical nature and biological
component of water that are not suitable to permitted technical regulations and standards,
cause bad effects to people and animals.
15. Water source deterioration means depletion on quantity, quality of water sources
compared to natural state or to state of Water sources observed in pre-period.
16. Water source depletion means serious depletion on quantity of water sources, causing
water sources fail to satisfying demand of exploitation, use and the aquatic ecology
preservation.
17. Water sources’ capacity to receive sewage means capacity of water sources receiving
additionally a sewage volume and still ensure quality of water sources for use purpose
under Vietnamese or foreign technical regulations and standards to which competent state
agencies permit to apply.
18. Minimum flow means the flow at the lowest level necessary for maintaining a river or
river section, ensuring the normal development of aquatic ecology and the minimum level
for water resource exploitation and use by water users.
19. Underground water exploitation threshold means limit permit to exploit underground
water aiming to ensure not causing salinization, degradation, water source depletion, land
subsidence, subsidence, bad impacts to surface water source and relevant environment.
20. Hygiene Protection Zone of area supplying living water means adjacent area of area
supplying living water from water sources being defined for compulsory protection to
prevent from, combat against the living water source pollution.
21. Function of water source means certain purposes of using water based on benefit values
of water source.
22. Protection corridor of water source means the limited land part being along water
source or surrounding it defined by competent state agencies.
Article 3. Principle of management, protection, exploitation and use of water
resources, as well as the prevention of, combat against and overcoming of harmful
effects caused by water
1. Management of water resources must ensure uniform with river basin, water sources,
combining with management based on administrative area.
-
2. Water resources must be managed in general, uniform of water quantity and quality,
between surface water and underground water; water on mainland and water on gate river
area, internal waters, and territorial waters; between upstream and downstream, combining
with management of other natural resources.
3. Protection, exploitation and use of water resources, as well as the prevention of, combat
against and overcoming of harmful effects caused by water must comply with strategy,
master plan on water resources have been approved by competent state management
agencies; linked with environmental protection, protection of natural landscapes, historic -
cultural vestiges, scenic places and other natural resources; assurance of national defense
and security, social order and safety.
4. Protection of water resources is duty of all agencies, organizations, individuals and
taking prevention as main duty, combining with protection, development of forest, capacity
of recycling water resources, combining with protection of water quality and aquatic
ecology, overcoming and restraining pollution, deterioration, depletion of water sources.
5. Exploitation, use of water resources must be in saving, safety and effectiveness; ensure
to synthetic use, for multiple objectives, be fair, reasonable, harmonious on benefit, equal
on interests and duties among organizations, individuals.
6. Prevention of, combat against and overcoming of harmful effects caused by water must
have active plan and measure; ensure harmonious combination of national benefits,
regional benefits and branch benefits; combination between modern science and technology
with traditional experiences of people and suitable to socio-economic conditions.
7. Master plan on protection, exploitation and use of water resources, as well as the
prevention of, combat against and overcoming of harmful effects caused by water must
contribute to develop society - economy and have measures ensuring life of inhabitants,
national defense and security, protection of historic - cultural vestiges, scenic places and
enviroment.
8. Master plans, plans. Programs, projects on development of society-economy, national
defense and security must associate with water sources, water resource protection; ensure
maintaining minimum flow on rivers not exceeding exploitation threshold with respect to
aquifers and have measure ensuring life of inhabitants.
9. Assurance of territory sovereignty, national benefits, equality and reasonable in
protection, exploitation, use and develoment of water resources, as well as the prevention
of, combat against and overcoming of harmful effects caused by water with respect to inter-
country water sources.
Article 4. State’s policies on water resources
1. To ensure water resources being managed, protected, exploited, use resonablely, in
saving and effectiveness, satisfying demand of socio-economic sustainable development
and assurance of national defense and security.
2. To invest and organize basic survey, master plans on water resources; to build system of
observation, overseeing water resources, information system, the water resource database,
to improve capacity of forecast on water resources, pollution of water sources, floods,
drought, salinization, sea-level rise and other harmful effects caused by water; to assist for
-
development of water sources and development of infrastructure relating to water
resources.
3. To prioritize to invest in research, explore, exploit water sources, have incentive policy
for investment projects on water exploitation in order to solve living and production water
for people in mountainous areas, areas of ethnic minority groups, border areas, inslands,
areas in difficult socio-economic conditions, areas in extremely difficult socio-economic
conditions, areas where fresh water is scarce.
4. To invest and have mechanism to encourage organizations, individuals for investment in
research, advanced science and technology application in order to manage, protect, develop
water sources, exploit, use in saving, effectiveness for water resources, handle sewage
meeting technical regulations and standards in order to reuse, process saline water, brackish
water into fresh water, collect, use rain water, supply artificial underground water, recover
water sources polluted,deteriorated, depleted , prevent, combat against and overcome
harmful effect caused by water.
5. To ensure state budget for operations of basic survey, master plan on water resources,
water resource protection, prevention of, combat against and overcoming of harmful effects
caused by water.
Article 5. Dissemination and education of water resources
1. Ministries, ministerial-level agencies, People’s Committees at levels within their duties,
powers shall coordinate with mass information agencies and training, educational facilities
to disseminate, educate on water resources, guide people for implementing measures of
water resource protection, use water in saving, effectiveness and comply with provisions of
law on water resources.
2. The Vietnam Fatherland Front Central Committee and organizations being its member
within their duties, powers shall coordinate with state management agencies of water
resources to disseminate, mobilize People to participate in water resource protection, using
water in saving, effectiveness and comply with provisions of law on water resources,
supervising protection, exploitation, use of water resources, prevention of, combat against
and overcoming of harmful effect caused by water.
Article 6. Taking opinions of inhabitant community and relevant organizations,
individuals in exploitation, use of water resources, discharge of sewage into water
sources
1. Organizations, individuals that invest projects in which include construction of works on
exploitation and use of water resources or have operations of discharge of sewage into
water sources affecting seriously to production and living of people in localities shall
coordinate with local authorities to implement the following operations:
a) To take opinions of representative of inhabitant community and relevant organizations,
individuals in areas influenced on project’ s contents relating to plan on exploitation, use of
water resources, and discharge of sewage into water sources; to sum up, make reception,
explanation and send enclosing dossier of project when submitting to competent state
agencies to decide investment;
-
b) To publicity information on project’s contents relating to exploitation, use water
resources, discharge of sewage into water sources and influences possible causing before
implementation;
c) Funds to implement operations specified in this clause shall be paid by organizations,
individuals investing in project.
2. If investment project has water transfer, in addition to implement provisions in clause 1
of this article, the investor being organization or individual must take opinions of People’s
Committee, river basin regarding scale of, plan on water transfer before making investment
project. Collection of opinions is prescribed as follows:
a) The relevant People’s Committee in communes, wards, towns (hereinafter referred to as
the communal People’s Committee), People’s Committee in districts, provincial-affiliated
towns, cities (hereinafter referred to as the district-level People’s Committee) for project
with water transfer in intra-provincial river basin.
b) The relevant People’s Committee in provinces, centrally-affiliated cities (hereinafter
referred to as the provincial People’s Committee) and river basin organization for project
with water transfer not subject to case specified in point a, this clause.
3. If investment project build lake, dam on river in inter province river basin without water
transfer, in addition to implement provisions in clause 1 of this article, before making
investment project, the investor being organization or individual shall:
a) Collection opinions of the relevant provincial People’s Committees and river basin
organization for scale, plan on proposal for construction of works on main flow;
b) To previous inform to the relevant provincial People’s Committees and river basin
organization of scale, plan on proposal for construction of works on sub-flow;
4. The Government details collection of opinions and publicity of information specified in
this article.
Article 7. List of river basins, list of water sources
1. List of river basins and list of water sources are basis in order to implement contents of
water resource management in according to river basin, water sources.
2. List of river basins includes:
a) The inter-provincial river basin;
b) The intra-provincial river basin;
3. List of water sources includes:
a) Inter-provincial water sources;
b) Intra-provincial water sources;
c) Inter-country water sources.
4. The Ministry of Natural Resources and Environment organizes making list of inter-
provincial river basin to submit to the Prime Minister for promulgation; makes,
promulgates list of intra-provincial river basin, list of inter-provincial water sources, inter-
country water sources.
-
5. Provincial People’s Committees make, promulgate list of intra-provincial water sources
in localities.
Article 8. Archival, use of water resource information
1. Archival of documents relating to water resources are sector-specialized archival and be
implemented as prescribed by law on archival.
2. Agencies in charge of task on state management on water resources shall supply
information on water resources for organizations, individuals when requested as prescribed
by law.
3. Organizations, individuals using information on water resources must pay charge for
using information as prescribed by law on charges, fees.
Article 9. The strictly prohibited acts
1. To discharge wastes, rubbish, discharge or leak toxic substances into water sources and
other acts causing pollution, deterioration, depletion for water sources.
2. To discharge sewage, bring waste into Hygiene Protection Zone of area supplying living
water, discharge sewage not yet processed or processed but not met technical regulations
and standards into water sources.
3. To discharge toxic exhaust directly into water sources; to discharge sewage into soil
through drilling wells, digging wells and other forms aiming to bring sewage into
subterranean; have frauds in discharging sewage.
4. To put obstacles, built architecture works, to plant trees unlawfully obstructing flood
drainage, water circulation in rivers, springs, lakes, cannels, ditches.
5. To exploit unlawfully sand, gravel on rivers, springs, canals, ditches, reservoirs; to
exploit minerals, drill, dig, build houses, architecture objects, works and other acts in
protection corridor of water sources causing landslide riversides, springs, canals, ditches,
reservoirs or causing serious influence threatening stabilization, safety of rivers, springs,
canals, ditches, reservoirs.
6. To destroy works for protection, exploitation, use, obversation, supervision of water
resources, works for prevention of, combat against and overcoming of harmful effects
caused by water.
7. To obstruct operation of water resource basic survey, the lawful right of exploitation, use
of water resources of organizations, individuals.
8. To explore, exploit, use water resources, to discharge sewage into water sources and
practice drilling of underground water unlawfully.
9. Not to obey process on operation of reservoirs, inter-reservoirs promulgated by
competent state agencies.
10. To build reservoirs, dams, works exploiting water contrary to master plan on water
resources.
Chapter II
BASIC SURVEY, STRATEGY, MASTER PLAN ON WATER RESOURCES
-
Section 1. BASIC SURVEY ON WATER RESOURCES
Article 10. The responsibility of State in basic survey on water resources
1. The basic survey on water resources must be implemented under master plan, plan
approved by competent authorities.
Funds for basic survey on water resources shall be allocated in annual State budget
estimates.
2. The Ministry of Natural Resources and Environment organizes making master plan on
water resource basic survey to submit to the Prime Minister for approval
3. Based on approved master plan on water resource basic survey, ministries, ministerial-
level agencies and provincial-level People’s Committee within their duties, powers shall
organize formulation of their plan on water resource basic survey.
Article 11. Master plan on water resource basic survey
1. Making master plan on water resource basic survey must ensure the following
requirements:
a) To satisfy requirement on formulating strategy, master plan, plan on socio-economic
development, national defense and security, regional planning, water resource strategy;
b) To make as basis for operation of water resource basic survey, servicing for planning on
water resources.
2. Bases to make master plan on water resource basic survey include:
a) Strategy, master plan, plan on socio-economic development, national defense and
security, regional planning, water resource strategy;
b) Result of implementing master plan on water resource basic survey of previous period.
3. Master plan on water resource basic survey includes the following main contents:
a) To identify requirements on information, figures regarding water resources, exploitation,
use of water resources in whole country;
b) To review, assess result of implementing basic survey or result of implementing master
plan on water resource basic survey in previous period;
c) To identify operations of water resource basic survey that need to execute for river
basins, areas, water sources being implemented water resource basic survey in planning
term;
d) To identify priority order of basic survey operation defined in point c, this clause;
e) Solutions, funds, plans and progress of implementation.
4. Period of master plan on water resource basic survey is 10 years, with vision to 20 years.
Article 12. Operation of basic survey on water resources
1. Basic survey on water resources includes the following operations:
a) Survey, assess on water resources;
b) Inventory of water resources periodically 05 year one time;
-
c) Survey of current status of exploitation, use of water resources, discharge of sewage,
exhaust, other waste into water sources;
d) To set up and maintain network systems for observation, supervision of water resources;
dd) To set up and maintain systems warning, forecasting flood, drought, salinization, sea-
level rise and other harmful effects caused by water;
e) To set up and maintain systems of information, database of water resources;
g) To formulate report on national water resources, report on water resources of central-
affiliated cities and provinces, report on exploitation, use of water resources in branches,
fields.
2. The content of survey, assessment of water resources specified in point a, clause 1 of this
Article includes:
a) To make specific maps of river basins, specific maps of rivers, springs, lakes, lagoons
and sea areas;
b) To make geological and hydrographic maps of aquifers, water containing structures and
water containing complexes;
c) To assess quantity and quality of water sources; search underground water sources;
d) To make map of water resources, map of zoning based on quality of water sources, maps
of specialized water resources;
dd) To assess situation on pollution, deterioration, depletion, saline infiltration of surface
water sources, underground water, sea water pollution; classify water sources in according
to exte