S.Monteil COMMISSIONING 1 PS/SPD ELECTRONICS OUTLINE 1) STATUS OF PS/SPD FE BOARDS PRODUCTION 2) PHASES OF PS/SPD COMMISSIONING 1) LEDs AND DETECTORS 2) TUBES AND VFE 3) AVAILABILITIES FOR MARCH TESTS COMMISSIONING MEETING – FEBRUARY 2007

Upload: brittany-golden

Post on 19-Jan-2016

213 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: S.MonteilCOMMISSIONING1 PS/SPD ELECTRONICS OUTLINE 1)STATUS OF PS/SPD FE BOARDS PRODUCTION 2)PHASES OF PS/SPD COMMISSIONING 1)LEDs AND DETECTORS 2)TUBES

S.Monteil COMMISSIONING 1

PS/SPD ELECTRONICS

OUTLINE

1) STATUS OF PS/SPD FE BOARDS PRODUCTION

2) PHASES OF PS/SPD COMMISSIONING

1) LEDs AND DETECTORS2) TUBES AND VFE3) AVAILABILITIES FOR MARCH TESTS

COMMISSIONING MEETING – FEBRUARY 2007

Page 2: S.MonteilCOMMISSIONING1 PS/SPD ELECTRONICS OUTLINE 1)STATUS OF PS/SPD FE BOARDS PRODUCTION 2)PHASES OF PS/SPD COMMISSIONING 1)LEDs AND DETECTORS 2)TUBES

S.Monteil COMMISSIONING 2

1) STATUS OF PS/SPD FE BOARDS PRODUCTION AND TESTS

Pre-production of 14 boards launched after extensive tests of 2 example boards (mostly scrutiny of the trigger part) -> December 2006

Seven boards received so far (07/02/2006). They were measured OK by the manufacturer. The measurements of the 7 boards lasted one day.

Conclusions / bottomline :

4 boards are perfectly OK. 1 board ( 007 ) shows two dead ADC channel (no clock distribution/cured). 2 boards are off ( 006 & 009 ): TRIG device cannot be (re-)programmed with JTAG (unreachable or programmation failed at the end). Under investigation. In addition, one component of delay chips on one of these 2 boards ( 006 ) has to be replaced.

Page 3: S.MonteilCOMMISSIONING1 PS/SPD ELECTRONICS OUTLINE 1)STATUS OF PS/SPD FE BOARDS PRODUCTION 2)PHASES OF PS/SPD COMMISSIONING 1)LEDs AND DETECTORS 2)TUBES

S.Monteil COMMISSIONING 3

1) STATUS OF PS/SPD FE BOARDS PRODUCTION AND TESTS

Measurements :

I2C communication

Connectivity

Phasers

Data Processing

Trigger algorithms

DAQ path

Most of the answers are binary (error rate compared to a threshold).

Page 4: S.MonteilCOMMISSIONING1 PS/SPD ELECTRONICS OUTLINE 1)STATUS OF PS/SPD FE BOARDS PRODUCTION 2)PHASES OF PS/SPD COMMISSIONING 1)LEDs AND DETECTORS 2)TUBES

S.Monteil COMMISSIONING 4

1) STATUS OF PS/SPD FE BOARDS PRODUCTION AND TESTS

Measurements :

Quick status

Expanded status

Popup link to detailed log

Page 5: S.MonteilCOMMISSIONING1 PS/SPD ELECTRONICS OUTLINE 1)STATUS OF PS/SPD FE BOARDS PRODUCTION 2)PHASES OF PS/SPD COMMISSIONING 1)LEDs AND DETECTORS 2)TUBES

S.Monteil COMMISSIONING 5

1) STATUS OF PS/SPD FE BOARDS PRODUCTION AND TESTS

Synthesis of the measurements.

Page 6: S.MonteilCOMMISSIONING1 PS/SPD ELECTRONICS OUTLINE 1)STATUS OF PS/SPD FE BOARDS PRODUCTION 2)PHASES OF PS/SPD COMMISSIONING 1)LEDs AND DETECTORS 2)TUBES

S.Monteil COMMISSIONING 6

1) STATUS OF PS/SPD FE BOARDS PRODUCTION AND TESTS

Synthesis of the measurements.

Page 7: S.MonteilCOMMISSIONING1 PS/SPD ELECTRONICS OUTLINE 1)STATUS OF PS/SPD FE BOARDS PRODUCTION 2)PHASES OF PS/SPD COMMISSIONING 1)LEDs AND DETECTORS 2)TUBES

S.Monteil COMMISSIONING 7

1) STATUS OF PS/SPD FE BOARDS PRODUCTION AND TESTS

Schedule for the reception of the boards and their qualification:

Preserie : 7 boards received and tested (07/02/07) 7 boards expected for the end of the week

Check them extensively and give the green light for production of the serie end of february.

Serie : Start of production expected beginning of April. 6 weeks duration.

Delivery each week of a batch of 16 boards.

Qualification of a board is estimated to be half a day.

Page 8: S.MonteilCOMMISSIONING1 PS/SPD ELECTRONICS OUTLINE 1)STATUS OF PS/SPD FE BOARDS PRODUCTION 2)PHASES OF PS/SPD COMMISSIONING 1)LEDs AND DETECTORS 2)TUBES

S.Monteil COMMISSIONING 8

2) COMMISSIONING OF PS/SPD AND MARCH TEST

There shall be three phases :

1) LED+DETECTOR (photographs fibre ends at the PMT)

2) SPD and PS VFE +Tubes (Dedicated systems operated simultaneously to installation). Could start the second week of march.

3) March test: Will only have PS cabled.

Page 9: S.MonteilCOMMISSIONING1 PS/SPD ELECTRONICS OUTLINE 1)STATUS OF PS/SPD FE BOARDS PRODUCTION 2)PHASES OF PS/SPD COMMISSIONING 1)LEDs AND DETECTORS 2)TUBES

S.Monteil COMMISSIONING 9

2) COMMISSIONING OF PS/SPD AND MARCH TEST

1) DETECTOR:

We do already have a measurement w/ cosmics of all the modules giving the mip photostatistics. We would like to have a measurement of the channels response to LED excitation in the pit. Evgueni demonstrated photographs can be taken at the end of the 64-channels bundle. Allows to check all LEDs / channels / fibres after transportation and installation in the pit.

SPD schedule : possible now.

PS schedule : seems only possible simultaneously with the VFE electronics installation.

See Evgueni’s talk

Page 10: S.MonteilCOMMISSIONING1 PS/SPD ELECTRONICS OUTLINE 1)STATUS OF PS/SPD FE BOARDS PRODUCTION 2)PHASES OF PS/SPD COMMISSIONING 1)LEDs AND DETECTORS 2)TUBES

S.Monteil COMMISSIONING 10

2) COMMISSIONING OF PS/SPD

2) TUBES AND VFE : SPD

Barcelona team set up a moveable standalone bench to check VFE and tubes (see Xavier’s talk) .

Able to trig autonomously the LED drivers.

Able to supply the HV for the tubes.

Able to supply the LV VFE

Fully checked at lab.

Install VFE and check it beginning of march.

Page 11: S.MonteilCOMMISSIONING1 PS/SPD ELECTRONICS OUTLINE 1)STATUS OF PS/SPD FE BOARDS PRODUCTION 2)PHASES OF PS/SPD COMMISSIONING 1)LEDs AND DETECTORS 2)TUBES

S.Monteil COMMISSIONING 11

2) COMMISSIONING OF PS/SPD

2) TUBES AND VFE : PS

A dedicated system has been set up for testing the PS VFE cabling (See Pascal’s talk). As a by-product, commission tubes, VFE (and FE chain).

The setup is currently tested at home and consists in DC flashing for a short period with a LED matrix the 64-channels in a known order.

Required services :

HV from CW

LV patch panel for VFE boards. Cooling system not necessary since duration of the test is short.

Page 12: S.MonteilCOMMISSIONING1 PS/SPD ELECTRONICS OUTLINE 1)STATUS OF PS/SPD FE BOARDS PRODUCTION 2)PHASES OF PS/SPD COMMISSIONING 1)LEDs AND DETECTORS 2)TUBES

S.Monteil COMMISSIONING 12

2) COMMISSIONING OF PS/SPD

2) TUBES AND VFE : PS The readout is performed with one PS/SPD FE Board.

Output : store channel response in an electronics logbook.

Schedule : simultaneous to VFE installation and cabling. Start of the operation for the beginning of March.

Page 13: S.MonteilCOMMISSIONING1 PS/SPD ELECTRONICS OUTLINE 1)STATUS OF PS/SPD FE BOARDS PRODUCTION 2)PHASES OF PS/SPD COMMISSIONING 1)LEDs AND DETECTORS 2)TUBES

S.Monteil COMMISSIONING 13

2) COMMISSIONING OF PS/SPD

3) MARCH TESTS:

Availability of the electronics :

SPD VFE : installed and checked but not cabled

PS VFE : in principle OK w/ the installation schedule.

PS/SPD FE Boards : the target is to fill a crate. Consistent with the production planning.

SPD Control Board : 4 protoypes already available.

Page 14: S.MonteilCOMMISSIONING1 PS/SPD ELECTRONICS OUTLINE 1)STATUS OF PS/SPD FE BOARDS PRODUCTION 2)PHASES OF PS/SPD COMMISSIONING 1)LEDs AND DETECTORS 2)TUBES

S.Monteil COMMISSIONING 14

3) MARCH TESTS:

AIM I

At first, use PS/SPD FE Rams to inject signals. Common test last november was very useful. Software ECAL/PS is ready for that purpose. Generate random patterns and check the response. The minor issues reported from the common test on the PS/SPD TRIG device are solved (neighbours phase, BCIDreset convention(s) …).

2) COMMISSIONING OF PS/SPD

Page 15: S.MonteilCOMMISSIONING1 PS/SPD ELECTRONICS OUTLINE 1)STATUS OF PS/SPD FE BOARDS PRODUCTION 2)PHASES OF PS/SPD COMMISSIONING 1)LEDs AND DETECTORS 2)TUBES

S.Monteil COMMISSIONING 15

3) MARCH TESTS:

Automated processes under CAT exist to deal with :

Tests of connectivity

Setting the phasers ECAL and PS/SPD neighbours inputs.

Check internally algorithms

Define the pipelines for ECAL and PSFE neighbours inputs

Common software to check the correctness of the whole response at the TVB level.

AIM I Reproduce the common test and extend it to a crate.

2) COMMISSIONING OF PS/SPD

Page 16: S.MonteilCOMMISSIONING1 PS/SPD ELECTRONICS OUTLINE 1)STATUS OF PS/SPD FE BOARDS PRODUCTION 2)PHASES OF PS/SPD COMMISSIONING 1)LEDs AND DETECTORS 2)TUBES

S.Monteil COMMISSIONING 16

2) CONCLUSION

3) MARCH TESTS:

AIM II

Use PS LEDs. Simultaneous light on 64-channels of a tube.

One important goal would be to set up procedures to align in time the boards by tuning the start of the VFE charge integration, dealing with the different lengthes of fibre bundles.

INTENTIONS (open questions)

Define how to dispose the (hopefully) available 14 FE boards. Reads one supermodule ? Reads a crate ?

Check full board / half board configurations ….