smp sizing in redevelopment projects scenarios are countless tools –simple method –cn back...
TRANSCRIPT
![Page 1: SMP Sizing in Redevelopment Projects Scenarios are countless Tools –Simple method –CN back calculation –Peak Discharge Rate Chapter 10 Criteria List of](https://reader036.vdocument.in/reader036/viewer/2022081518/551b9cd1550346167e8b582b/html5/thumbnails/1.jpg)
SMP Sizing in Redevelopment Projects
• Scenarios are countless
• Tools– Simple method– CN back calculation– Peak Discharge Rate
• Chapter 10 Criteria
• List of Verified Practices
![Page 2: SMP Sizing in Redevelopment Projects Scenarios are countless Tools –Simple method –CN back calculation –Peak Discharge Rate Chapter 10 Criteria List of](https://reader036.vdocument.in/reader036/viewer/2022081518/551b9cd1550346167e8b582b/html5/thumbnails/2.jpg)
![Page 3: SMP Sizing in Redevelopment Projects Scenarios are countless Tools –Simple method –CN back calculation –Peak Discharge Rate Chapter 10 Criteria List of](https://reader036.vdocument.in/reader036/viewer/2022081518/551b9cd1550346167e8b582b/html5/thumbnails/3.jpg)
Site Description
• Total area = 4 acres
• Disturbed are = 1 acre
• Impervious area = .6 acre
• Precipitation = 1”
• Storm Type 2
• Justification
• Sizing and SMPs selection– 4 scenarios
Justification
![Page 4: SMP Sizing in Redevelopment Projects Scenarios are countless Tools –Simple method –CN back calculation –Peak Discharge Rate Chapter 10 Criteria List of](https://reader036.vdocument.in/reader036/viewer/2022081518/551b9cd1550346167e8b582b/html5/thumbnails/4.jpg)
Bethlehem, NY
• Site information– approximately 29.2% Imp– florist, green houses, parking, planting beds
• Proposed development – 54% impervious – condominium complex, 9 buildings and 4 covered garages
• Constraints– relocating a sanitary sewer– maintaining setbacks
• Proposed practice– CDS units– Underground storage
![Page 5: SMP Sizing in Redevelopment Projects Scenarios are countless Tools –Simple method –CN back calculation –Peak Discharge Rate Chapter 10 Criteria List of](https://reader036.vdocument.in/reader036/viewer/2022081518/551b9cd1550346167e8b582b/html5/thumbnails/5.jpg)
![Page 6: SMP Sizing in Redevelopment Projects Scenarios are countless Tools –Simple method –CN back calculation –Peak Discharge Rate Chapter 10 Criteria List of](https://reader036.vdocument.in/reader036/viewer/2022081518/551b9cd1550346167e8b582b/html5/thumbnails/6.jpg)
25% Impervious Cover Reduction
Scenario 1•Reconstruction of existing impervious area not exceeding footprint.•Selected Practice: Reduction of Impervious area by 25%•Plan appropriately•Document footprint reduction•Ensure adequate infiltration
•Soil amendment•Decompaction
![Page 7: SMP Sizing in Redevelopment Projects Scenarios are countless Tools –Simple method –CN back calculation –Peak Discharge Rate Chapter 10 Criteria List of](https://reader036.vdocument.in/reader036/viewer/2022081518/551b9cd1550346167e8b582b/html5/thumbnails/7.jpg)
![Page 8: SMP Sizing in Redevelopment Projects Scenarios are countless Tools –Simple method –CN back calculation –Peak Discharge Rate Chapter 10 Criteria List of](https://reader036.vdocument.in/reader036/viewer/2022081518/551b9cd1550346167e8b582b/html5/thumbnails/8.jpg)
Redevelopment Project with an Existing Detention Pond
Keep the detention pondAddress WQ treatment
![Page 9: SMP Sizing in Redevelopment Projects Scenarios are countless Tools –Simple method –CN back calculation –Peak Discharge Rate Chapter 10 Criteria List of](https://reader036.vdocument.in/reader036/viewer/2022081518/551b9cd1550346167e8b582b/html5/thumbnails/9.jpg)
![Page 10: SMP Sizing in Redevelopment Projects Scenarios are countless Tools –Simple method –CN back calculation –Peak Discharge Rate Chapter 10 Criteria List of](https://reader036.vdocument.in/reader036/viewer/2022081518/551b9cd1550346167e8b582b/html5/thumbnails/10.jpg)
WQv Calculation -1
![Page 11: SMP Sizing in Redevelopment Projects Scenarios are countless Tools –Simple method –CN back calculation –Peak Discharge Rate Chapter 10 Criteria List of](https://reader036.vdocument.in/reader036/viewer/2022081518/551b9cd1550346167e8b582b/html5/thumbnails/11.jpg)
WQv Calculation –2100% Impervious
Reduce upstream drainage and control an area that is all impervious.
<
<
![Page 12: SMP Sizing in Redevelopment Projects Scenarios are countless Tools –Simple method –CN back calculation –Peak Discharge Rate Chapter 10 Criteria List of](https://reader036.vdocument.in/reader036/viewer/2022081518/551b9cd1550346167e8b582b/html5/thumbnails/12.jpg)
WQv Calculation –3Rv Constant
![Page 13: SMP Sizing in Redevelopment Projects Scenarios are countless Tools –Simple method –CN back calculation –Peak Discharge Rate Chapter 10 Criteria List of](https://reader036.vdocument.in/reader036/viewer/2022081518/551b9cd1550346167e8b582b/html5/thumbnails/13.jpg)
25% Standard practice
Scenario 2•Reconstruction of existing impervious area not exceeding footprint.•Selected Practice: Infiltration Trench•Calc. WQv x 25%•Locate sub-catchment & diversion structure• Check feasibility & limitations•Document maintenance plan, etc.
![Page 14: SMP Sizing in Redevelopment Projects Scenarios are countless Tools –Simple method –CN back calculation –Peak Discharge Rate Chapter 10 Criteria List of](https://reader036.vdocument.in/reader036/viewer/2022081518/551b9cd1550346167e8b582b/html5/thumbnails/14.jpg)
Site DescriptionEddy Greenhouses
• Nursing facility in Cohoes• Area encompass 22 acres• Northwestern portion of the property undeveloped
(wetlands)• Remainder is buildings and parking areas• Existing impervious area 8.29 acres• Proposed construction 16 Greenhouses
– New construction 7.8 acres– Reconstruction 6.17 acres
![Page 15: SMP Sizing in Redevelopment Projects Scenarios are countless Tools –Simple method –CN back calculation –Peak Discharge Rate Chapter 10 Criteria List of](https://reader036.vdocument.in/reader036/viewer/2022081518/551b9cd1550346167e8b582b/html5/thumbnails/15.jpg)
![Page 16: SMP Sizing in Redevelopment Projects Scenarios are countless Tools –Simple method –CN back calculation –Peak Discharge Rate Chapter 10 Criteria List of](https://reader036.vdocument.in/reader036/viewer/2022081518/551b9cd1550346167e8b582b/html5/thumbnails/16.jpg)
Redevelopment Project with an Existing Detention Pond
May modify the pond to meet pond design standards
![Page 17: SMP Sizing in Redevelopment Projects Scenarios are countless Tools –Simple method –CN back calculation –Peak Discharge Rate Chapter 10 Criteria List of](https://reader036.vdocument.in/reader036/viewer/2022081518/551b9cd1550346167e8b582b/html5/thumbnails/17.jpg)
Redevelopment Project with Increased Footprint
![Page 18: SMP Sizing in Redevelopment Projects Scenarios are countless Tools –Simple method –CN back calculation –Peak Discharge Rate Chapter 10 Criteria List of](https://reader036.vdocument.in/reader036/viewer/2022081518/551b9cd1550346167e8b582b/html5/thumbnails/18.jpg)
![Page 19: SMP Sizing in Redevelopment Projects Scenarios are countless Tools –Simple method –CN back calculation –Peak Discharge Rate Chapter 10 Criteria List of](https://reader036.vdocument.in/reader036/viewer/2022081518/551b9cd1550346167e8b582b/html5/thumbnails/19.jpg)
Proposed PlanEddy Greenhouses
• Reduce impervious area by 25%• Design a P-1 Pond• Maintain existing water quantity controls in pond• Provide treatment for all the new disturbance• Provide treatment for a portion of the existing
imperviousness• Allow sheet flow for ½ of the site that did not have
detention in existing condition• Did not restore soil property• Increase HSG for new pervious area
![Page 20: SMP Sizing in Redevelopment Projects Scenarios are countless Tools –Simple method –CN back calculation –Peak Discharge Rate Chapter 10 Criteria List of](https://reader036.vdocument.in/reader036/viewer/2022081518/551b9cd1550346167e8b582b/html5/thumbnails/20.jpg)
75% Alternative practice
Scenario 3•Reconstruction of existing impervious area not exceeding footprint.•Selected Practice: Hydrodynamic System•Back calc. CN
•If only imp. Connected, CN = 98•Define flow rate•Locate sub-catchment, flow splitter•Look up the corresponding model from table 1•Check all the requirements for suitability of the practice, feasibility, limitations (head, soil, separation distance, etc.)•Document calculation method, manufacturer’s recommendation, maintenance plan, etc.
![Page 21: SMP Sizing in Redevelopment Projects Scenarios are countless Tools –Simple method –CN back calculation –Peak Discharge Rate Chapter 10 Criteria List of](https://reader036.vdocument.in/reader036/viewer/2022081518/551b9cd1550346167e8b582b/html5/thumbnails/21.jpg)
Redevelopment Project with Increased Footprint
![Page 22: SMP Sizing in Redevelopment Projects Scenarios are countless Tools –Simple method –CN back calculation –Peak Discharge Rate Chapter 10 Criteria List of](https://reader036.vdocument.in/reader036/viewer/2022081518/551b9cd1550346167e8b582b/html5/thumbnails/22.jpg)
![Page 23: SMP Sizing in Redevelopment Projects Scenarios are countless Tools –Simple method –CN back calculation –Peak Discharge Rate Chapter 10 Criteria List of](https://reader036.vdocument.in/reader036/viewer/2022081518/551b9cd1550346167e8b582b/html5/thumbnails/23.jpg)
![Page 24: SMP Sizing in Redevelopment Projects Scenarios are countless Tools –Simple method –CN back calculation –Peak Discharge Rate Chapter 10 Criteria List of](https://reader036.vdocument.in/reader036/viewer/2022081518/551b9cd1550346167e8b582b/html5/thumbnails/24.jpg)
![Page 25: SMP Sizing in Redevelopment Projects Scenarios are countless Tools –Simple method –CN back calculation –Peak Discharge Rate Chapter 10 Criteria List of](https://reader036.vdocument.in/reader036/viewer/2022081518/551b9cd1550346167e8b582b/html5/thumbnails/25.jpg)
Inputs Parameter Redevelop. UnitsNew Construction
Site Acreage A 2 acres 0.5
Impervious Area IA 1.5 acres 0.5
Impervious Cover% I 75 % 100
Runoff Coefficient Rv=.05+.009*I 0.73 constant 0.95
Min. Rv Rv 0.2 constant 0.2
90% Rainfall P 1 inches 1
Water Quality Volume WQv = [PRvA]/12 0.1216667 Acre-Feet 0.0395833
5299.8 ft^3 1724.25
Alternative Practice, sized to 75% of WQv, define priority areas that generate a runoff volume equivalent to the target WQv. Rv constant. 0.75 3974.85 Total (ft^3) 5699.1
![Page 26: SMP Sizing in Redevelopment Projects Scenarios are countless Tools –Simple method –CN back calculation –Peak Discharge Rate Chapter 10 Criteria List of](https://reader036.vdocument.in/reader036/viewer/2022081518/551b9cd1550346167e8b582b/html5/thumbnails/26.jpg)
![Page 27: SMP Sizing in Redevelopment Projects Scenarios are countless Tools –Simple method –CN back calculation –Peak Discharge Rate Chapter 10 Criteria List of](https://reader036.vdocument.in/reader036/viewer/2022081518/551b9cd1550346167e8b582b/html5/thumbnails/27.jpg)
EquationsWQv = [PRvA]/12Rv=.05+.009*I
I = imperviousness
P= precipitation (inch)
A= area
![Page 28: SMP Sizing in Redevelopment Projects Scenarios are countless Tools –Simple method –CN back calculation –Peak Discharge Rate Chapter 10 Criteria List of](https://reader036.vdocument.in/reader036/viewer/2022081518/551b9cd1550346167e8b582b/html5/thumbnails/28.jpg)
![Page 29: SMP Sizing in Redevelopment Projects Scenarios are countless Tools –Simple method –CN back calculation –Peak Discharge Rate Chapter 10 Criteria List of](https://reader036.vdocument.in/reader036/viewer/2022081518/551b9cd1550346167e8b582b/html5/thumbnails/29.jpg)
![Page 30: SMP Sizing in Redevelopment Projects Scenarios are countless Tools –Simple method –CN back calculation –Peak Discharge Rate Chapter 10 Criteria List of](https://reader036.vdocument.in/reader036/viewer/2022081518/551b9cd1550346167e8b582b/html5/thumbnails/30.jpg)
![Page 31: SMP Sizing in Redevelopment Projects Scenarios are countless Tools –Simple method –CN back calculation –Peak Discharge Rate Chapter 10 Criteria List of](https://reader036.vdocument.in/reader036/viewer/2022081518/551b9cd1550346167e8b582b/html5/thumbnails/31.jpg)
CN Back-CalculationPeak Discharge Rate
![Page 32: SMP Sizing in Redevelopment Projects Scenarios are countless Tools –Simple method –CN back calculation –Peak Discharge Rate Chapter 10 Criteria List of](https://reader036.vdocument.in/reader036/viewer/2022081518/551b9cd1550346167e8b582b/html5/thumbnails/32.jpg)
![Page 33: SMP Sizing in Redevelopment Projects Scenarios are countless Tools –Simple method –CN back calculation –Peak Discharge Rate Chapter 10 Criteria List of](https://reader036.vdocument.in/reader036/viewer/2022081518/551b9cd1550346167e8b582b/html5/thumbnails/33.jpg)
http://www.dec.ny.gov/chemical/29089.html
![Page 34: SMP Sizing in Redevelopment Projects Scenarios are countless Tools –Simple method –CN back calculation –Peak Discharge Rate Chapter 10 Criteria List of](https://reader036.vdocument.in/reader036/viewer/2022081518/551b9cd1550346167e8b582b/html5/thumbnails/34.jpg)
Hydrodynamic SystemsVortechs System
http://www.dec.ny.gov/chemical/29089.html
![Page 35: SMP Sizing in Redevelopment Projects Scenarios are countless Tools –Simple method –CN back calculation –Peak Discharge Rate Chapter 10 Criteria List of](https://reader036.vdocument.in/reader036/viewer/2022081518/551b9cd1550346167e8b582b/html5/thumbnails/35.jpg)
![Page 36: SMP Sizing in Redevelopment Projects Scenarios are countless Tools –Simple method –CN back calculation –Peak Discharge Rate Chapter 10 Criteria List of](https://reader036.vdocument.in/reader036/viewer/2022081518/551b9cd1550346167e8b582b/html5/thumbnails/36.jpg)
Hydrodynamic Systems
![Page 37: SMP Sizing in Redevelopment Projects Scenarios are countless Tools –Simple method –CN back calculation –Peak Discharge Rate Chapter 10 Criteria List of](https://reader036.vdocument.in/reader036/viewer/2022081518/551b9cd1550346167e8b582b/html5/thumbnails/37.jpg)
WQv VSM + VDL + (DP x ARG)
VSM = ARG x DSM x nSM
VDL (optional) = ARG x DDL x nDL
where:VSM = volume of the soil media [cubic feet]
VDL = volume of the drainage layer [cubic feet]
ARG = rain garden surface area [square feet]
DSM= depth of the soil media, typically 1.0 to 1.5 feet [feet]
DDL = depth of the drainage layer, typically .05 to 1.0 feet [feet]
DP = depth of ponding above surface, maximum 0.5 feet [feet]
nSM = porosity of the soil media (≥20%)
nDL = porosity of the drainage layer (≥40%)
WQv= Water Quality Volume [cubic feet], as defined in Chapter 4 of the New York Stormwater Management Design Manual
Alternative PracticesRain Garden
![Page 38: SMP Sizing in Redevelopment Projects Scenarios are countless Tools –Simple method –CN back calculation –Peak Discharge Rate Chapter 10 Criteria List of](https://reader036.vdocument.in/reader036/viewer/2022081518/551b9cd1550346167e8b582b/html5/thumbnails/38.jpg)
![Page 39: SMP Sizing in Redevelopment Projects Scenarios are countless Tools –Simple method –CN back calculation –Peak Discharge Rate Chapter 10 Criteria List of](https://reader036.vdocument.in/reader036/viewer/2022081518/551b9cd1550346167e8b582b/html5/thumbnails/39.jpg)
Redevelopment Project with Increased Footprint