smt capital equipment road map...production capacity, as we will be unable to responded quickly to...

18
SMT Capital Equipment Road Map SMT Hours in 2015 SMT Hours in 2020 100% capacity in 6 months Know you SMT capacity 50K CPH Capacity = 1 hour placing 50K parts

Upload: others

Post on 15-May-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: SMT Capital Equipment Road Map...production capacity, as we will be unable to responded quickly to customer demand. (Production hours per day) hours a day, times 5 days a week, times

SMT Capital Equipment Road Map

SMT Hours in 2015

SMT Hours in 2020

100% capacity in 6 months

Know you SMT capacity

50K CPH Capacity = 1 hour placing 50K parts

Presenter
Presentation Notes
“Planning is bringing the future into the present so that you can do something about it now” Alan Lakein
Page 2: SMT Capital Equipment Road Map...production capacity, as we will be unable to responded quickly to customer demand. (Production hours per day) hours a day, times 5 days a week, times

Seven Steps

2

Chart The Past

Project The Future

Calculate Your Capacity

Choose your Vender

Driving Factors

Use the software

Present Case Studies

supporting ROI

1

2

3

4

5

6

7

Page 3: SMT Capital Equipment Road Map...production capacity, as we will be unable to responded quickly to customer demand. (Production hours per day) hours a day, times 5 days a week, times

Chart The Past • SMT Hours Earned Over the Past 5 Years • Since 2011 we have seen a 226% growth in SMT Hours Earned

3 Data provided by finance

Presenter
Presentation Notes
SMT hours earned as recorded by finance, was the method chosen to project demand.
Page 4: SMT Capital Equipment Road Map...production capacity, as we will be unable to responded quickly to customer demand. (Production hours per day) hours a day, times 5 days a week, times

Project The Future SMT Hours Projections for the Next 5 Years We will look at the net increase using 3 methods. 1. 50% Straight increase each year as seen from History 2. 20% Straight increase each year from lowest yearly increase 3. 20% increase the first year, decreasing by 4% (20%-16%-12%,

ect…) every year after

4

Presenter
Presentation Notes
Bluetooth smart & smart ready market will grow from $2.3 billion in 2013 to $3.9 billion by 2020. -MarketsandMarkets Industrial IoT equipment MEMS market revenues will rise from $16 million in 2013 to $120 million in 2018. –HIS LED chipset demand is expected to increase from 35.8 million units in 2013 to 1.4 billion units in 2018, -DisplaySearch Graphene electronics market will grow at an estimated 46.8% CAGR to $1.512 billion by 2020. –Marketsand Markets
Page 5: SMT Capital Equipment Road Map...production capacity, as we will be unable to responded quickly to customer demand. (Production hours per day) hours a day, times 5 days a week, times

Calculate Your Capacity • SMT Hours Earned VS Capacity SMT lines

– 80% OEE netting hours in a 5 day work week per quarter • total hours in a 5 day work week, across all smt lines per quarter

• With modest growth, we need to add an SMT line capable of at least ****** SMT hours a week, every year each year for the next 5 years.

5

We should never let ourselves be at maximum production capacity, as we will be unable to responded quickly to customer demand. (Production hours per day) hours a day, times 5 days a week, times 13 weeks equals = total hours per SMT

line in a quarter.

80% OEE of SMT hours worked equals = SMT line hours per quarter.

Presenter
Presentation Notes
Page 6: SMT Capital Equipment Road Map...production capacity, as we will be unable to responded quickly to customer demand. (Production hours per day) hours a day, times 5 days a week, times

More SMT Capacity Required • By the start of the third quarter of 2016 we will need to add another SMT

line to keep up with production. • The current lines we have are failing with limited parts available for repairs.

6

• Each line has a trackable CPH or you might use a factory standard. Many factors will influence this number. The best to collect a running average over several production runs.

If it is new equipment, de-rate the stated IPC placement rate by 20% to be in the ball park. We will use 50,000 CPH for a duel CP7 line with a flex placer. • Finance has been tracking the loaded production hours. They have your

production history • You now have what you booked over the past 5 years and what capacity you

currently have. Now we just have to project and increase

Presenter
Presentation Notes
Production capacity was derived from historical data provided by finance.
Page 7: SMT Capital Equipment Road Map...production capacity, as we will be unable to responded quickly to customer demand. (Production hours per day) hours a day, times 5 days a week, times

Choose Your Vender

7

Top Tear Equipment Manufacture A high production quick change operation that will last 20+ years. Best in class technology Best in class Service and Support

Presenter
Presentation Notes
Severial pick and place manfactures battle for the top spot as the Technology Leader. NXT III first manufacture date was Dec 2013 (+7 to last DOM + 10 = 17 + years for service. Fuji Wins 2015 Technology Award for High Speed Component Placement of 0250125 (.250 mm X .125 mm) Fuji America Wins 2015 Circuits Assembly Magazine Service Excellence Award
Page 8: SMT Capital Equipment Road Map...production capacity, as we will be unable to responded quickly to customer demand. (Production hours per day) hours a day, times 5 days a week, times

Driving Factors • Manufactures planned support for their equipment. • Technical capability of the SMT equipment.

– Can place 0250125 (.25mm X .125mm) • Placement rate, Production tracking, Optimization. • Quote placement time reduction.

8

03015 metric 0.3mm X 0.15mm

Presenter
Presentation Notes
Future growth in the market is forecast to come from emerging opportunities in automotive electronics, medical device electronics, aerospace, defense and military electronics. Adoption of advanced SMT equipment will be driven by the shifting focus of end-use markets from defect detection to defect prevention. The scenario is also creating lucrative opportunities for sophisticated SMT placement and inspection equipment. Demand for SMT inspection equipment is driven by the need to reduce resource wastages stemming from manufacturing defects, improve manufacturing processes, reduce associated costs, increase yield and enhance margins. Rising demand for light emitting diodes (LED) technology is also fuelling demand for SMT equipment. Encouraged by the growing popularity of LEDs, SMT equipment manufacturers are planning production capacity additions to accommodate the increasing demand from commercial and consumer electronics sectors. -ELECTRONICS.CA PUBLICATIONS 2015
Page 9: SMT Capital Equipment Road Map...production capacity, as we will be unable to responded quickly to customer demand. (Production hours per day) hours a day, times 5 days a week, times

Technical Capability of the SMT Equipment

• Efforts should be made to insure we can routinely place 01005 and 12 mil pitch devices with little effort.

• As new lines are selected, the key factors are: – Accuracy – Placement rate – Technical support, and – Offline setup

9

.65mm CSP

Presenter
Presentation Notes
Amkor Technology, a large provider of chip assembly and test services, has seen the percentage of its revenue from advanced products (including flip chip, wafer-level processing and related test services) increase from 40.5 percent in 2011 to 49.1 percent in 2013. The company offers three options in WLCSP — CSPnl bump on repassivation, CSPnl bump on redistribution, and CSPn3. These packages can have from four to 196 solder balls. Advanced Semiconductor Engineering, another of the Big 4 in IC assembly and test services, offers a number of advanced packaging types, such as WLCSP, flip-chip CSP, flip-chip package-in-package, flip-chip ball grid array and its Advanced Single Sided Substrate, trademarked as aS 3. These types can accommodate from six to 2,916 leads.
Page 10: SMT Capital Equipment Road Map...production capacity, as we will be unable to responded quickly to customer demand. (Production hours per day) hours a day, times 5 days a week, times

SMT Equipment at End of Life • A CP6, small package camera went

out and was no longer carried by Fuji. • The following equipment is at end of

life and should be replace in the next 5 years – screen printers – chip shooters ( all CP6’s lines) – flex placers – reflow ovens

10

As with any manufactured item, the old 10 year unwritten rule applies. If it's been approximately 7-10 years since a model was produced for new sale distribution, then discontinuation of certain items for that model is possible. Dave Byker, Fuji America

Presenter
Presentation Notes
As with any manufactured item, the old 10 year unwritten rule applies. If it's been approximately 7-10 years since a model was produced for new sale distribution, then discontinuation of certain items for that model is possible. Dave Byker, Fuji America Due to a design issue with the Y axis, our CP-6 4000’s are not capable of placing a 0603 component. The CP642 0201 camera is no longer carried by Fuji. China is quickly becoming the last used parts sources for the older CP models..
Page 11: SMT Capital Equipment Road Map...production capacity, as we will be unable to responded quickly to customer demand. (Production hours per day) hours a day, times 5 days a week, times

Use The Software • Offline program and feeder setup • Optimal setups for multiple production programs • Real-time monitoring of production • Non-stop production Warnings before parts run out • Prevention of misplacements through smart feeders • Improve manufacturing processes

– Faster placement speeds – Increase yield – Enhance margins

11

Page 12: SMT Capital Equipment Road Map...production capacity, as we will be unable to responded quickly to customer demand. (Production hours per day) hours a day, times 5 days a week, times

High Capacity Line (104K CPH) • Eight NXTIII M6 Modules (4-H24, 2-V12, 1-H08, 2-H02 heads)

– 03015 at ±25 μm@>1.00 Cpk – 10 mil IC at ±25 μm@>1.00 Cpk

• 120 nozzles • 534 x 610 mm PCB size

• All within the foot print of a single cp6

219,000 CPH Stated 130,835 CPH IPC 104,668 CPH at 20% de-rate from IPC

Presenter
Presentation Notes
1.5 mill with 8 M6 modules and 300 feeders, setup tables and software H24G: 37,500 cph (Productivity priority mode) / 21,700 cph act V12: 26,000 cph /17,572 cph act H08: 11,500 cph /3,897 cph act H02: 5,500 cph / 2,009 cph act
Page 13: SMT Capital Equipment Road Map...production capacity, as we will be unable to responded quickly to customer demand. (Production hours per day) hours a day, times 5 days a week, times

Reclaimed Floor Space

13

Further Floor space can be saved by placing these lines back to back

Page 14: SMT Capital Equipment Road Map...production capacity, as we will be unable to responded quickly to customer demand. (Production hours per day) hours a day, times 5 days a week, times

Present Case Studies • Product “A” currently require 25% of the total SMT

hours available with a 7.56 sec top placement and 3.6 sec for bottom placement.

• The new equipment as quoted will deliver these in 2.06 sec and .61 sec respectively.

• Product “A” times will improve by 8.49 sec per unit for a product savings of (8.49 sec X SMT line price)

• SMT labor savings are (reduction of head count)

There is also a return of capacity of 5188 smt hours with a value of (5188 X Line price)**

14

Presenter
Presentation Notes
($line cost/3600= $variable SMT Line cost per sec) Total cycle time of ((11.16 sec * $line price) = $cost savings per unit. With the new line, the cycle time drops to 2.67 sec, times a variable line cost of $ is $0.0 per pcb. (2.67X. variable line cost = $.0741) Labor saving is ((8.49 sec per unit X production rate) @ $ hourly rate) = $labor savings Return of 5188 smt hours at a SMT line cost of $XXX is $______ of possible new revenue
Page 15: SMT Capital Equipment Road Map...production capacity, as we will be unable to responded quickly to customer demand. (Production hours per day) hours a day, times 5 days a week, times

Case Study / A Day of Small Runs

• A single customer required 147 total SMT hours (27 assemblies) in a single day.

• A single high capacity line would optimize that days production running it by it self in only two days

• Return SMT production hours back to other production. • Running small production 3 days a week (42%) nets 11,232

hours a year

15

Presenter
Presentation Notes
Page 16: SMT Capital Equipment Road Map...production capacity, as we will be unable to responded quickly to customer demand. (Production hours per day) hours a day, times 5 days a week, times

Added Benefits Not Included in the cost savings

• 22% energy reduction over perching a CP6 line and 122% with the reduction of a CP6 line.

• In line Laser Bar code marker will all but eliminate labels on the new line.

• Training a JIT work force burden will be reduced with each line bought. No more added head count.

• Feeder setup group to reduce change over, and burden from the SMT line.

• Software should be used to the verify the feeder bank before it is brought to the line.

16

Presenter
Presentation Notes
2.36 amps for each NXT X 8 units = 18.88 vs 12.02 amps for each CP6 x2=24.04 plus flex placer. Each quarter there are approximately 700 hours of setup Offline setup is expected to cut the setup time by 50% over the next 5 years
Page 17: SMT Capital Equipment Road Map...production capacity, as we will be unable to responded quickly to customer demand. (Production hours per day) hours a day, times 5 days a week, times

The Solution Add a line each year, with more then double the placement capacity of a current line that is ready for retirement.

– screen printer $166k – Placement modules $1.5 mil – Oven $100k – AOI $140k – Conveyors $120k – Software $100K – Laser PCBA marker $140K

17

Presenter
Presentation Notes
Page 18: SMT Capital Equipment Road Map...production capacity, as we will be unable to responded quickly to customer demand. (Production hours per day) hours a day, times 5 days a week, times

Return on Investment • “A” mas production (30% utilization) • “B” production high mix (42% utilization) • 10% Reduction of quoted times with the addition of a line yearly

savings on 50% setup reduction of this line • Floor Space

– leased space annually for each line – production line gain of 25%.

• Running these case studies offers a gross return of over $2mil a year based on a variable cost payback

18

Presenter
Presentation Notes
Using this line for high mix and high volume would utilize it 99% and offer a variable cost payback of $X in production savings at a $X variable cost rate.