snk final project

Upload: rajesh99mainframe

Post on 03-Apr-2018

224 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/29/2019 Snk Final Project

    1/57

    1

    CHAPTER 1

    INTRODUCTION

    1.1 HISTROY

    In the year 1882, Pentaerythritol was discovered by product of the reaction

    hydroxide and impure formaldehyde. The name Pentaerythritol which was assigned

    to this compound was derived from erithritol to indicate the presence of 4 - hydroxyl

    groups and the prefix Penta to show that there are 5 carbon atoms in the

    molecules.

    Pentaerythritol is a white crystalline compound. The high melting point, slight

    solubility in water and the ready reactivity of its 4 hydroxide groups have been

    attributed to the compact symmetric structure of the molecules. It is an optically

    inactive compound, resembling cane sugar in appearance and has a sweet taste

    characteristic of polyols.

    Pentaerithritol is nonhygroscopic and stable in air and sublimes slowly on

    heating. It is moderately soluble in cold water, quite soluble in hot water, and has

    only limited solubility in organic liquids. It is used in paints, varnishes industry and

    the production of resins. Pentaerithritol is increasingly used in resins manufacturing

    mainly because of its desirable characteristics and price stability.

    1.2 APPLICATION OF PENTAERITHRITOL

    It is used to manufacture of Paints & Varnishes.

    It is used to manufacture of Pentaerithritol Nitrate (P.E.T.N).

    It is used to manufacture of Plasticizers & Lubricants.

    Pentaerithritol combination with metal salts used as heat stabilizers.

    Acrolin prepared from Pentarithritol used for electrical insulation,surface

    coating films and fibers

    .

  • 7/29/2019 Snk Final Project

    2/57

    2

    CHAPTER 2

    AIM AND SCOPE

    The objective of the project work is to study the manufacture of Pentaerithritol for

    600 tons per annum.

    To solve the material balance and energy balance for the process

    To design the reactor and vacuum tray dryer involved in the process

    To study the plant layout, safety, health and environment aspects

    To estimate the cost and payback period of the process

    The scope of the project is to select the method for the manufacturing of

    pentaerithritol for the following features mentioned below

    Less energy consumption.

    High purity.

    High yield / conversion.

    Recovery of by product as sodiumformate.

  • 7/29/2019 Snk Final Project

    3/57

    3

    CHAPTER 3

    PROCESS DESCRIPTION AND DESIGN

    3.1. METHODS OF PRODUCTION

    3.1.1 Using soda ash as condensing agent

    Raw Materials Required

    a) Formaldehyde

    b) Ca (OH) 2 solution

    c) Acetaldehyde

    d) Soda ash

    3.1.2 Using Sodium hydroxide as condensing agent

    Raw materials required

    a) Formaldehyde

    b) Formic acid

    c) Acetaldehyde

    d) Sodium hydroxide

    3.1.3 Slection of method:

    Using NaOH as condensing agent

    4 HCHO + CH3CHO + NaoH (CH2OH) 4 C+ HCOONa

    Pentaerithritol

    Justification of Process Selection

    Yield 85-90%

    Less energy consumption

    Easy removal Recovery of by product as sodiumformate

    High yield / conversion

  • 7/29/2019 Snk Final Project

    4/57

    4

    3.1.4 Process description

    A solution of formadehyde (30%) is added to NaOH solution. The temperature is

    maintained at 30oC by suitable agitation. liquid acetaldehyde (99%) is added slowly

    added under the surface of formaldehyde alkali solution. External cooling is required

    to maintain the reaction temperature around 20-30o

    C the mole ratio of formaldehydeto acetaldehyde 5:1.A ratio of 1:1.5 mole hydroxide ion per mole of acetaldehyde

    appears to the optimum amount of condensing agent. The crude reaction mixture is

    then transferred to neutralization reactor. Formic acid is added here to reduce the Ph

    of the solution to 7.8-8.0 & to remove sodium ions present as Sodiumformate.The

    solution is then evaporated to a specific gravity of 1.270.ITt is then chilled to

    crystallize Pentaerithritol and resulting slurry is centrifuged & dried to obtain

    crystalline Pentaerithritol as final product.The mother liquor goes to recovery system to recover Sodiumformate by

    evaporative crystallization followed by centrifuging & drying to obtain crystalline

    Sodiumfomate as by product.

  • 7/29/2019 Snk Final Project

    5/57

    5

    3.1.5 Chemical Properties of Pentaerithritol

    1) Molecular Formula - (CH2OH)4C

    2) Molecular Weight - 136.15

    3) Boiling Point - 276C AT 760 mm of Hg

    4) Melting Point - 262C

    5) Density - 1.1318gm/cc

    6) CAS No. - 115-77-5

    3.1.6 Physical Properties of Pentaerithritol

    Pentaerithritol are crystalline solids.

    Those solids are soluble in water.

    Solubility decreases with increase in molecular weight.

    Their solubility and melting points show alternation or oscillation from one

    member to the near.

    It is moderately soluble in cold water, quite soluble in hot water, and has only

    limited solubility in organic liquids.

    It is an optically inactive compound, resembling cane sugar in appearance

    and has a sweet taste characteristic of polyols.

    Pentaerithritol is nonhygroscopic and stable in air and sublimes slowly on

    heating.

    3.1.7 Process flow diagram

  • 7/29/2019 Snk Final Project

    6/57

    6

    Figure 3.1: Process flow diagram (Manufacturing of pentaerithritol)

    3.1.7 Process flow diagram

    TO VACCUM

    HCHO

    NaOH REACTOR HCOOHCH3CHO NEUTRALISER EVAPORATOR

    C.W OUT

    CW IN

    TO VACCUM

    AIR OUT

    P.E.T

    CRYSTAL

    HOT AIR IN HCOONa + water

    HOLDIN

    G

    TANK

    VACUM

    CRSTALLI

    SER HOLDI

    NG

    TANK

    CENTRIFUGE

    DRIER

  • 7/29/2019 Snk Final Project

    7/57

    7

    TO VACUM

    VACCUM CRSTALLISER

    TO ATM

    DRIED HCOONa

    MOTHER LIQUOUR

    HOT AIR IN

    CENTRIFUGE

    DRIER

    CENTRIFUGE

    ML(P.E.T)

    Figure 3.2: Process flow diagram (Recovery of sodiumformate)

    3.2 MATERIAL BALANCE

    3.2.1 Material balance for P.E.T and sodiumformate manufacturing:

    BASIS:600 tons/annum

  • 7/29/2019 Snk Final Project

    8/57

    8

    2000 kg/day of Pentaerithritol

    REACTION:

    4 HCHO + CH3CHO + NaoH (CH2OH) 4C + HCOONa

    (4 x 30) 44 40 136.15 68

    3.2.2 Material balance around Reactor:

    Reactor input

    CH3CHO required = kgmoleCH3CHO/kgmole (CH2OH) 4C x kg P.E.T

    = (44/136.15) / 2000kg of P.E.T

    = 646.34 kg/day

    For 85% conversion = CH3CHO kg required / 0.85

    = 646.34 / 0.85= 765 kg/day

    CH3CHO purity(99%) = 765 / 0.99

    = 757.5 kg /day

    HCHO required = (CH3CHOkg/kgmoleCH3CHO) x kgmoleHCHO

    = (757.5 / 44) x 30

    = 2065 kg/day

    Mole ratio CH3CHO: HCHO= 1: 4.55

    = (CH3CHOkg/kgmoleCH3CHO) x

    kgmoleHCHOx4.55

    = 4.55 x (757.5 X 44) x 30

    = 2350 kg/days

    HCHO purity (37%) = 2350/0.37

    = 6350 kg/day

    NaoH required = (CH3CHOkg/kgmoleCH3CHO) x kgmole NaOH

    = (757.5 / 44) x 40

    = 688.4 kg

    Mole ratio CH3CHO:NaOH = 1 : 1.52

    = kg CH3CHO x kgmoleNaOH x 1.52

    = (757.5) x 40 x 1.52

    = 1050 kg

    NaOH purity(50%) = 1050 / 50

    = 2100 kg/day

    Reactor output:

  • 7/29/2019 Snk Final Project

    9/57

    9

    P.E.T produced = (CH3CHOkg/kgmoleCH3CHO)xkgmoleP.E.T

    (757.5/44) x136.5

    = 2341.23 kg/day

    HCOONa produced = (CH3CHOkg/kgmoleCH3CHO) x kgmoleHCOONa

    = (757.5 /44) x 68= 1170.0 kg/day

    Material balance around reactor:

    Component Input

    (kg/day)

    Output

    (kg/day)

    CH3CHO 757.50 -HCHO 2350.00 284.70

    NaoH 1050.00 361.60

    (CH2OH) 4C - 2341.23

    HCOONa - 1700.00

    H2O 5057.50 5057.50

    TOTAL 9125.00 9125.00

    3.2.3 Material balance around Neutralizer:

    NaOH + HCOOH HCOONa + H2O

    40 46 68 18

    Neutralizer input

    NaOH Unconverted = 316.6kg

    HCHO required for neutralization = (kgmoleHCHO/kgmoleNaOH) x 316.6

    = (46/40) x 316.6= 415.84 kg

  • 7/29/2019 Snk Final Project

    10/57

    10

    HCHO purity (34.6%) = 415.84 / 0.346

    = 1200 kg/day

    Neutralizer output:

    HCOONa produced = (kgmoleHCOONa/kgmoleNaOH) x 316.6

    +1170kg= 613.94 kg + 1170 kg

    = 1783.94 kg/day

    H2O produced = kgmoleH2O/kgmoleNaOH x 316.6

    = (18 / 40) x 361.6

    = 946.88 kg

    = 5057.5 +946.88

    = 6005.5 kg/dayMaterial balance around Neutralizer:

    3.2.4 Material balance around

    Evaporator

    Data required:Out going slurry:

    Material Input

    (kg/day)

    Output

    (kg/day)

    P.E.T 2341.23 2341.23

    HCOONa 1170.00 1783.94

    NaOH 361.60 ****

    HCHO 284.70 284.67

    HCOOH 1200.00 ****

    H2O 5057.50 6005.50

    TOTAL 10415.00 10415.00

    Component Specific gravity Weight(kg) Volume(lt)

    H2O 1.0 (x) (x)

    P.E.T 1.396 2341.23 1677.10

    HCOONa 1.8 1783.94 991.08

    TOTAL ***** 4125.17 + x 2668.18+ x

  • 7/29/2019 Snk Final Project

    11/57

    11

    Specific gravity of out going slurry = 1.27

    (Weight / volume) of out going slurry = 1.27

    (4125.17 + x) / (2668.18 + x) = 1.27

    H2O along with out going slurry (x) = 2727.94 kg/day

    H2O evaporated = 6005.16 2727.94= 3277.22 kg/day

    Material balance around Evaporator

    3.2.5 Material balance around Vacuum crystallizer:Assume -14.8% loss in solution

    P.E.T as crystal = 2341.23 x 0.148

    = 341.23 kg/day

    = 2341.23 341.23

    = 1194. kg/day

    Material balance around Vacuum crystallizer

    Material Input

    (kg/day)

    Output

    (kg/day)

    P.E.T 2341.23 2341.23

    HCOONa 1783.94 1783.94HCHO 284.67 ****

    HCHO(evaporated) **** 284.67

    H2O(evaporated) **** 3272.22

    H2O(along slurry) 6005.50 2727.94

    TOTAL 10415.00 10415.00

    MATERIAL INPUT OUTPUT

  • 7/29/2019 Snk Final Project

    12/57

    12

    3.2.6 Material balance around Centrifuge:

    Assume moisture accompanying with crystal = 9.0 %

    Hence moisture with crystal 0.09 = x / (x+1194)

    x = 127.28 kg

    Material balance around Centrifuge

    (kg/day) (kg/day)

    P.E.T 2341.23 ****

    HCOONa(in solution) 1783.94 1873.94

    P.E.T( In solution) **** 347.23

    P.E.T(As crystal) **** 1994.00

    H2O 2727.94 2727.94

    TOTAL 6583.11 6583.11

    Material INPUT

    (kg/day)

    OUTPUT

    (kg/day)

    P.E.T 1194.0 1194.0

    H2O 127.8 6.0

    H2O(to ***** 121.8

  • 7/29/2019 Snk Final Project

    13/57

    13

    3.2.7 Material balance around Dryer:

    Centrifuge mother liquor containing HCOONa + Water is sent to Evaporative vacuum

    crystallizer for HCOONa recovery

    atm)

    TOTAL 2121.8 2121.8

    Material INPUT

    (kg/day)

    OUTPUT

    (kg/day)

    P.E.T 1994.00 *****

    HCOONa (in solution) 1783.94 1783.94

    H2O( in solution) 2727.94 2600.66

    P.E.T(As soluble) 347.23 347.23

    P.E.T (in wet cake) ***** 1994.00

    H2O (in wet cake) ***** 127.28

    TOTAL 6853.11 6853.11P.E.T PRODUCED2000 kg/day

  • 7/29/2019 Snk Final Project

    14/57

    14

    3.2.8 Material balance around Evaporative vacuum crystallizer:

    Data required:

    Out going slurry:

    Specific gravity of out going slurry = 1.37

    (Weight / volume) of out going slurry = 1.37

    (2131.17 + x) /(1239.81 + x) = 1.37H2O along with out going slurry (x) = 1185.0 kg / day

    H2O evaporated = 2600.66 1185.0

    = 1415.66kg/day

    Material balance around Evaporative vacuum crystallizer

    3.2.9 Material balance around Centrifuge:

    Assume moisture accompanying with crystal = 4.0 %

    Hence moisture with crystal 0.04 = x / (x+1783.94)

    x = 71.1 kg

    Component Specific gravity Weight(kg/day) Volume(lt)

    H2O 1.0 (x) (x)

    P.E.T 1.396 347.23 248.73

    HCOONa 1.8 1783.94 991.08

    TOTAL ***** 2131.17 + (x) 1239.81 + (x)

    COMPONENT INPUT

    (kg/day)

    OUTPUT

    (kg/day)

    P.E.T 347.23 347.23

    HCOONa 1783.94 1783.94

    H2O 2600.00

    H2O evaporated ***** 1415.66

    TOTAL 4731.83 4731.83

  • 7/29/2019 Snk Final Project

    15/57

    15

    3.2.10 Material balance around Dryer:

    3.3 ENERGY BALANCE

    3.3.1 Energyrgy balance around Reactor:

    Mass of Acetadehyde(M CH3CHO) = 757.50 kg

    Mass of Sodium hydroxide (MNaoH) = 1050.00 kg

    Mass of Formaldehyde (M HCHO) = 2350..00

    Mass of Sodiumformate(M HCOONa) = 1170.00 kg

    Mass of P.E.T(MP.E.T) = 2341.23 kg

    COMPONENT INPUT

    (kg/day)

    OUTPUT

    (kg/day)

    HCOONa 1783.94 *****

    HCOONa (in ML) ***** 89.94

    H2O(in ML) 1185.00 1113.9

    P.E.T(in ML) 347.23 347.23

    HCOONa (in wet cake) ***** 1694.00

    H2O (in wet cake) ***** 71.00

    TOTAL 6853.11 6853.11

    COMPONENT INPUT

    (kg/day)

    OUTPUT

    (kg/day)

    HCOONa 1694.00 1694.00

    H2O 71.00 6.00

    H2O(to atm) ***** 65.0

    TOTAL 1765.00 1765.00

    HCOONa PRODUCED1700 kg/day

  • 7/29/2019 Snk Final Project

    16/57

    16

    Feed inlet temperature = 25C

    Product outlet temperature = 30C

    Reaction temperature = 80C

    Reference temperature = 25C

    Energy balance equation

    Heat input + (MP.E.T x heat of reaction) =Heat output+Heat load on Reactor

    Cooling jacket

    Heat input

    Feed temperature = reference temperature = 25C

    So, heat input = 0

    Table 3.1 Heat Values of Components

    COMPONENTREACTANT PRODUCT

    HCHO NaOH CH3CHO HCOONa P.E.T

    Specific heat

    capacity

    (Kcal/gmoC)

    0.526 0.540 0.312 0.269 0.386

  • 7/29/2019 Snk Final Project

    17/57

    17

    Heat of

    formation

    (kcal/gmole)

    -60.57 -72.01-142.53

    -226.0 -100.0

    Heat of reactionat 25 oC = HF product - HF reactant

    = (-326.65) - (-275.11)

    = - 51.49 Kcal/gm mole

    Enthalpy at 25 oC = (-51.49x 2341.231000)/136.15

    = -886396.56 Kcal/day

    HF reactant = m.Cp.dt

    = ((2350 x 0.526)+(1050x0.54)+

    (757.5x0.312)(298-303)

    = -10199.1 Kcal/day

    HF product = m.Cp.dt

    = (2341.23 x 0.386) + (1170 x 0.269) x 5

    = 6092.2 Kcal/day

    Q = HF product+HF reactant+ heat of reaction at 25oC

    = -101991.1 + 6092.2 - 886396.56

  • 7/29/2019 Snk Final Project

    18/57

    18

    Q = -890503.46Kcal/day

    Heat loss by

    radiation 10% = -89050.35Kcal/day

    Heat to be removed

    (Q) = 890503.46 - 89050.35

    = 801453.117Kcal/day

    Heat removed = Heat generated = Q = (mCpdt)Water

    Q = m*1*(303-293)

    = 801453.11 Kcal/day

    Mass of H2O

    required ( m ) = 801453.11 / 10

    = 80145.31 kg/day

    3.3.2 Energyrgy balance around Holding Tank:

    Here the reactor outlet mass is heated up to 90oC before feeding to evaporator.

    Temperature of the

    holding tank = 90 oC

    Heat to be supplied = mCpdt

    = (2341.23 x 0.386 +1783.94 x 0.269 + 6005.16 x 1+

    284.67x .576) x (90-30)

    = 453154.75 kcal/day

    Heat loss due to radiation = 10%

  • 7/29/2019 Snk Final Project

    19/57

    19

    Haet required = Heat supplied

    = (10%)x453154.75

    = 1.1*453154.75

    = 498470.2338kcal/day

    Heat loss by radiation = 498470.23-453154.75

    = 45315.47kcal/day

    Steam required @ 2.1125

    atm Ms = 498470.23/525.

    = 948.3kg/day

    Heat loss by condensation = 121.27x948.3

    = 115000 kcal/day

    Heat to be supplied by

    steam = (525.64-121.27) x 948.3

    = 383471.19kcal/day

  • 7/29/2019 Snk Final Project

    20/57

    20

    3.3.3 Energy balance around dryer:

    Amount of P.E.T to be dsried = 1994 kg/day

    Water to be removed = 121.28kg/day

    Sensible heat required to heat material from 25o

    C -100o

    C =mCpdt

    = (1994\x (100-75) x (0.386+ 121.80) x

    (100-75) x 1

    = 66822.3 Kcal /day

    Heat required for vaporization of 121.28 kg of water

    = 121.28 x 540

    = 65491.2 Kcal/day

    Hence total heat required = 66822.3+65491.2

    = 132313.50kcal/day

    Assuming 10% heat loss due to radiation

    Hence heat required = 1.1 x 132313.50

    = 145544.85 kcal/day

    Steam required = 145544.85/525.64

    = 276.88kg/day

  • 7/29/2019 Snk Final Project

    21/57

    21

    3.3.4 Energy balance around Evaporator:

    BASIS:

    P.E.T-2000kg/ day.

    Data required for calculation:

    As per evaporator material balance,

    Feed = 10415.00 kg/dayVapour = 3561.89kg/day

    Product = 6853.11kg/day

    Feed enters at = 90oC

    Steam table data

    Steam,2 atm,121oC (HS) = 645.26 Kcal/kg

    Condensate,1 atm,105oC(HC) = 105.60 Kcal/kg

    Table 5.1 Heat Values of Components

    General heat balance equation for evaporator

    F.HF + S(HS-HC) = E.HE + PHP 1

    REACTANT PRODUCT

    HCHO NaOH CH3CHO HCOONa P.E.T

    Specific heat

    capacity

    (Kcal/gmoC)

    0.526 0.540 0.312 0.269 0.386

    Heat of

    formation

    (kcal/gmole)

    -60.57 -72.01-142.53

    -226.0 -100.0

  • 7/29/2019 Snk Final Project

    22/57

    22

    Feed (F) = 10451 kg/day

    Enthalpy of feed = (mCpdt) feed

    = (2341.23x0.396) + (1783.94x0.269) +

    (6005.5x1) x 90

    F. HF = 679708.08 kcal/day= 28321.17 kcal/hr

    Vapour (E) = 3561.89 kg/day

    = Water vapor evaporated x Enthalpy at 100

    oC

    = 3561.89 kg/day x 644.22 kcal/kg

    = 2294640.776 kcal/day

    = 95610.03 kcal/day

    Product (P) = 6853.11kg/day

    Enthalpy of product (HP) = (mCpdt) product

    = (2341 x 0.368) + (2727.94 x1)

    + (1783.94 x 0.269) x 90

    = 411152.4kcal/day

    = 17131.39kcal/day

    Substituting the above values in equation -1

    Mass of steam(S) = 3717.20kg/day

    Steam economy = (kg water evaporated) / (kg of

    steam required)

    = (3561.89/3717.2)x10

    = 0.95

  • 7/29/2019 Snk Final Project

    23/57

    23

    3.4 EQUIPMENT DESIGN

    3.4.1 Design of vacuum tray drier

  • 7/29/2019 Snk Final Project

    24/57

    24

    Figure 3.1: Design of vacuum tray drier

    BASIS :

    48 Tray capacityShell :

    Length of the shell L = 1.7m

    Breadth of the shell b = 0.91m

    Area of the shell = Lx B

    Area of the shell = 1.547 m2

    Tray:

    Length of the tray L = 0.8mBreadth of the tray b = 0.4m

    Area of the tray = Lx B

    Total number of tray = 48 number

    Area of the tray = 0.32m

    Total area of the tray = 48 x 0.32

    = 15.36 m2

    Shelves:

    Length of the shelves L = 1.2m

    Breadth of the shelves b = 0.8m

    = Lx B

    = 16

    Area of the shelves = 0.96m

    Total area of the tray = 16 x 0.96

    Overall surface area of the drier = (1.547+15.6+15.36)

    = 32.27m2

  • 7/29/2019 Snk Final Project

    25/57

    25

    3.4.2 Design of Evaporator

    Circulation and heat transfer in this type of evaporator is strongly affected by

    the liquid level as indicated by an external gauge, which is only about half way of the

    tube. Slight reduction in level below the optimum results in incomplete wetting of the

    tube walls with a consequent increase in tendency to foul and causes rapid reductionin capacity. When this type of evaporator is used with a liquid that can deposit scale,

    it is customary to operate with the liquid level appreciably higher than the optimum

    level which is above the top tube sheet.

    Advantages of Short Tube Vertical Evaporator:

    High heat transfer coefficient

    Low head

    Easy mechanical descalingMild scaling solution can be used for mechanical cleaning as the tubes are short

    and large in diameter.

    Crystalline products can be removed using the agitatorProcedure followed in design

    of evaporator assembly (ref: Unit operation of chemical engineering Mc Cabe)

    Q = U.A dt

    Q = 1316857.14

    Q = 1316857.143 x 0.252 = 331848 Btu/hr

    U = 160 Btu/hr.ft2. oF

    Ref: Unit operation of chemical

    JM Coulson & JF RICHARDSON PAGE-520

    T = 45o

    F

    Hence A = (331848) / 45 X 160) = 46.09 ft2

    For Sheet Diameter:

  • 7/29/2019 Snk Final Project

    26/57

    26

    C/S Area of one tube = /4) d2)

    = (3.14/4) x (2.2)2x48

    = 182.463 in 2

    From Mc Cabe, 30% of A is the area of downcomer

    = 182.463 x 0.3

    = 54.4 in2

    ( /4) d2 = 54.4 in2

    Hence, d = 8 inches

    Length and Number of tubes:

    In standard short tube evaporators the length varies from 4 to 8 ft and the

    diameter is around 2 to 4 inches, In this case, the length is assumed as 4 ft and

    diameter as 2 inches.

    Outer area of each tube = d0l

    = 3.14 X (2.12/12) X4 = 2.1ft2

    Number of tubes required = 46.09/2.1

    = 22.2 tubes

    Hence we can take 22 to 24 tubes.

    A staggered arrangement is used as it permits higher tube accommodation, for a

    given distance between the tubes. From the approximate calculations, the shell

    inside diameter is taken as 21.2 inches.

    Thickness of Shell = (P.d) / (2.f.E) + Corrosion Allowance

    = (30 X 21.2) (2X0.8 X 3312.5) + 0.08

  • 7/29/2019 Snk Final Project

    27/57

    27

    = 0.2 inches maximum

    Hence Outer Diameter = 21.2 + 0.2 + 0.2

    = 21.6 inches

    Length of the evaporator is proportioned with respect to the length of tubes.

    Design of evaporator and its accessories:

    The standard evaporator consists of a vertical cylinder with calendria cross

    which the heat exchange takes place. The cylindrical body terminates at the top in a

    save all , the objective of which is to separate the liquid droplets which maybe

    entrained with vapour from the soilution. Previously the evaporator body was

    fabricated with cast iron; however more recently fabrication using steel plate is

    becoming more common.

    Height of the Vessel:

    The space above the tubular calendris represents the greater part of the volume

    taken up by the equipment. The objective is to diminish the risk of entrainment

    droplets of solution projected by boiling. Various MOC used as follows:

    Part Old Modern Special

    Shell Steel Bronze Mild Steel Stainless Steel

    Tubes Brass, Cast Iron Mild Steel -

    The height of the cylindrical portion above the steel plates is 1.5 to 2 times the length

    of the tube.

    Calendria:

    It is the continuation of the shell or body of the evaporator. It is often fixed to

    the shell. The bore of the holes provided in the tube plate is about 1/32 inch greater

  • 7/29/2019 Snk Final Project

    28/57

    28

    than the outer diameter of the tubes. Vertical baffles are often placed in the calendria

    with the object of compelling the steam to follow a certain path.

    Center Wall (Downcomer):

    The calendria is generally designed with a wide tube or center wall. Solution

    which has been projected over the top tube plate is returned to the bottom by the

    downcomer. This center well is often used to collect the concentrated solution in

    order to transfer it from vessel to other.

    Air source for condenser:

    Air introduced into the condensers comes from various sources such as air

    contained in the heating system, air introduced in the cold rejection water, air

    entering by leakage.

    Specification sheet of evaporator

    Number Required 1

    Type Short tube, vertical calendria

    type evaporator

    Normal Capacity 328.25 l/hr

    Working Pressure 2 atm

    Critical Dimension Overall height = 220 inch

  • 7/29/2019 Snk Final Project

    29/57

    29

    Inside diameter of Shell = 21.2 inch

    Inside diameter of tube = 2 inch

    Thickness of shell = 0.2 inch

    Thickness of tube = 0.1 inch

    Diameter of downcomer = 3 inch

    Length of tube = 48 inch

    Number of tubes = 22 to 24

    Material of construction Stainless steel

    Baffles As per requirement

    Nozzles or jet stream As steam inlet to increase velocity

    Cost Rs.6,00,000 (Approx)

    CHAPTER 4

    COST ESTIMATION,PLANT LATOUT,MATERIAL SAFETY

  • 7/29/2019 Snk Final Project

    30/57

    30

    4.1 COST ESTIMATION

    4.1.1 Estimation of Direct and Indirect cost:

    Marshall and Shift index in 1992 for equipments is 943.1

    Cost estimation based on the equipment

    Cost of the reactor = Rs 1.7 x 106

    Cost of the Neutraliser = Rs 0.62x106

    Cost of the Holding tank = Rs 1.1x106

    Cost of Crystallizer = Rs 0.71x106

    Cost of pump = Rs 0.25x106

    Cost of the Dryer = Rs 0.25x106

    Cost of the Centrifuge = Rs 0.32x106

    Total cost of the equipment = Rs 4.3x106.

    4.1.2 Estimation of total direct cost:

    Purchased equipment cost ( E ) = Rs 4.3x106

    Purchased equipment installation (39% of E) = 4.3x106x 0.39

    = Rs 1.677x106

    Instrumentation (installed cost), 28%E = 4.3x106x0.28

    = Rs 1.204x106

    Piping installed, 31%E = 4.3x106x0.31

    = Rs 1.333x106

    Electrical installation, 10%E = 4.3x106x0.1

    = Rs 0.43x106

    Yard improvement, 10%E = 4.3x106x0.1

  • 7/29/2019 Snk Final Project

    31/57

    31

    = Rs 0.43x106

    Service facility, 55%E = 4.3x106x0.55

    = Rs 2.365x106

    Land, 6%E = 4.3x106x0.06

    = Rs 0.258x106

    Total direct cost (D) = Rs 11.997x106

    4.1.3 Estimation of total indirect cost:

    1. Engg and supervision ( 32% E ) = Rs 1.376x106

    2. Construction + contractor fees (25% direct costs)

    = 11.997x106x0.25

    = Rs 2.99925 x106

    Therefore total indirect cost (I) = Rs 4.37525x106

    DIRECT AND INDIRECT COST (TOTAL) = Rs 16.37225x106

    Contingence (10%D+I) = (4.37525+0.1x11.997x106)

    = Rs 5.57495x106

    Fixed capital investment (FCI)

    Contingence + D + I = Rs 21.9472x106

  • 7/29/2019 Snk Final Project

    32/57

    32

    Working Capital: (10-20% of Fixed-capital investment)

    Consider the Working Capital = 15% of

    Fixed-capital investment

    i.e., Working capital = 15% of 21.9472*106 = 0.15 21.9472x106

    = Rs 3.29208x106

    Total Capital Investment (TCI):

    Total capital investment = Fixed capital investment +

    Working capital

    = Rs 25.23925x106

    i.e., Total capital investment = Rs 25.23925x106

    4.1.4 Estimation of Total Production cost:

    Manufacturing Cost = Direct production cost +

    Fixed charges +

    Plant overhead cost.

    4.1.5 Fixed charges:

    (10-20% total product cost)

  • 7/29/2019 Snk Final Project

    33/57

    33

    i. Depreciation: (depends on life period, salvage value and method of calculation-

    about 13% of FCI for machinery and equipment and 2-3% for Building Value for

    Buildings)

    Consider depreciation = 13% of FCI for machinery and equipment

    and 3% for Building Value for Buildings)

    i.e., Depreciation = Rs. 2.85313106

    ii. Local Taxes:(1-4% of fixed capital investment)

    Consider the local taxes = 3% of fixed capital investment

    i.e. Local Taxes = 0.0321.9472*10

    6

    = Rs. 0.6584106

    iii. Insurances:(0.4-1% of fixed capital investment)

    Consider the Insurance = 0.7% of fixed capital investment

    i.e. Insurance = 0.007s Rs 21.9472*106

    = Rs. 0.15363106

    iv. Rent: (8-12% of value of rented land and buildings)

    Consider rent = 10% of value of rented

    land and buildings

    Rent = Rs. 0.13023x106

    Thus, Fixed Charges = Rs. 3.79539106

  • 7/29/2019 Snk Final Project

    34/57

    34

    4.1.6 Direct production cost:

    (about 60% of total product cost)

    Now we have Fixed charges = 10-20% of total product charges

    Consider the Fixed charges = 15% of total product cost

    Total product charge = fixed charges/15%

    = 3. 7953910

    6

    /15%

    = 3. 79539106/0.15

    Total product charge (TPC) = Rs. 25.3026106

    i. Raw Materials:(10-50% of total product cost)

    Consider the cost of raw materials = 25% of total product cost

    Raw material cost = 25% of 25.3026106

    = Rs. 6.32565106

    ii. Operating Labour (OL):(10-20% of total product cost)

    Consider the cost of operating labour = 12% of total product cost

    Operating labour cost = 12% of 25.3026106

    = Rs 3.0363106

    iii. Direct Supervisory and Clerical Labour (DS & CL):

    (10-25% of OL)

  • 7/29/2019 Snk Final Project

    35/57

    35

    Consider the cost for Direct

    supervisory and clerical labour = 12% of OL

    Direct supervisory and clerical

    labour cost = 12% of 3.0363

    = Rs. 0.364357106

    iv. Utilities: (10-20% of total product cost)

    Consider the cost of Utilities = 12% of total product cos

    t

    Utilities cost = 12% of 25.3026106

    = Rs. 0.12 25.3026106

    = Rs. 3.036312106

    v. Maintenance and repairs (M & R):

    (2-10% of fixed capital investment)

    Consider the maintenance and repair

    cost = 5% of fixed capital investment

    i.e. Maintenance and repair cost = Rs. 0.0525.23925*106

    = Rs. 1.26196106

    vi. Operating Supplies:(10-20% of M & R or 0.5-1% of FCI)

    Consider the cost of Operating supplies = 15% of M & R

    Operating supplies cost = 15% of 1.26196106

    = Rs. 0.18929106

  • 7/29/2019 Snk Final Project

    36/57

    36

    vii. Laboratory Charges: (10-20% of OL)

    Consider the Laboratory charges = 15% of OL

    = 15% of 3.0363106

    Laboratory charges = Rs. 0.45544106

    viii. Patent and Royalties:(0-6% of total product cost)Consider the cost of Patent and

    royalties = 4% of total product co

    st

    = 4% of 25.3026106

    Patent and Royalties cost = Rs. 1.0121106

    Thus, Direct Production Cost = Rs. 15.68141106

    4.1.7 Plant over head cost:

    (50-70% of Operating labour, supervision, and maintenance or 5-15% of total

    product cost); includes for the following:

    general plant upkeep and overhead, payroll overhead, packaging, medical services,

    safety and protection, restaurants, recreation, salvage, laboratories, and storage

    facilities.

    Consider the plant overhead cost = 60% of OL, DS & CL, and M & R

    Plant overhead cost = 60% of ((3.0363106)

    + (0.364357106)

    + (1.26196106)

    Plant overhead cost = Rs. 2.79765106

  • 7/29/2019 Snk Final Project

    37/57

    37

    Thus, Manufacture cost = Direct production cost +

    Fixed charges +

    Plant overhead costs.

    Manufacture cost = 15.68141106 + 3.79539106

    + 2.79765106

    = Rs 22.27445106

    II. General Expenses = Administrative costs+ distribution and selling costs

    + Research and development costs

    Administrative costs :( 2-6% of total product cost)

    Consider the Administrative costs = 5% of total product cost

    Administrative costs = Rs. 1.26513106

    Distribution and Selling costs: (2-20% of total product cost);

    Includes costs for sales offices, salesmen, shipping, and advertising.

    Consider the Distribution and

    selling costs = 15% of total product cost

    Distribution and selling costs = 15% of 25.3026106

    Distribution and Selling costs = Rs. 3.75453106

    Research and Development costs: (about 5% of total product cost)

    Consider the Research and

    development costs = 5% of total product cost

    = 5% of 25.3026106

    Research and Development costs = Rs. 1.26513106

  • 7/29/2019 Snk Final Project

    38/57

    38

    Financing (interest):(0-10% of total capital investment)

    Consider interest = 5% of total capital investment

    i.e. interest = 5% of 25.23925x106

    Interest = Rs. 1.26196106

    Thus, General Expenses = (3.75453+1.26515+1.26195)

    x106

    = Rs 6.29163x10

    6

    III. Total Product cost = Manufacture cost +

    General Expenses

    Total product cost = 22.27445106+ 6.29163x106

    = Rs 28.55608 x106

    Gross Earnings/Income:

    Wholesale Selling Price of P.E.T per ton = $ 650

    Hence

    Wholesale Selling Price of P.E.T per ton. = 650 46

    = Rs. 29900

    Total Income = Selling price Quantity of

    product manufactured

    = 29900 (2 T/day)

    (300 days/year)

    Total Income = Rs. 17.94 106

  • 7/29/2019 Snk Final Project

    39/57

    39

    Gross income = Total Income Total

    Product Cost

    = Rs 17.94106 28.556106

    Gross Income = Rs10.62106

    Let the Tax rate be 45% (common)

    Taxes = 45% of Gross income

    = 45% of 10.62106

    Taxes = Rs. 4.61106

    Net Profit = Gross income Taxes

    = Gross income

    (1- Tax rate)

    Net profit = (10.62106) (4.62106)

    = Rs. 6.01106

    4.1.8 Rate of return:

    Rate of return = (Net profit100)/Total Capital Investment

    Rate of Return = (6.01106100)/ (25.23925106)

    Rate of Return = 23.99%

    4.1.9 Payback period:

    Payback period = (Total capital investment+total product cost) /net profit

    = (25.239 x 106+28.556x106 )/ 6.01x106

    = 4.3954 years

  • 7/29/2019 Snk Final Project

    40/57

    40

    4.2 INSTRUMENTATION

    The primary objective of a designer when specifying instrumentation and control.

    Safe plant operation

    To keep the process variable within known safe operating limits

    To detect dangerous situations as they develop and to provide alarmsautomatic shutdown systems

    To provide interlocks to prevent dangerous operating procedures

    To achieves the desired product output

    To maintain the product composition within the specified quality standards.

    Process may be controlled more precisely to give more uniform and higher

    quality products by the application of automatic co troll often leading to higher profitautomatic is also beneficial in certain remote, hazardous or routine operations

    For manual control, an operator periodically measures the temperature .if it is below

    the desired value, the operator increases the steam flow by opening the valve

    slightly for automatic control ,a temperature sensitive device is used to produce a

    signal (electrical , pneumatic etc.) propositional to the measured temperature .

    This signal is fed to a controller, which compares it with a preset desired

    values or set point . If a difference exists, the controller changes the opening of the

    steam control valve to correct the temperature.

    4.2.1 Control valve:

    The control valve contains a pneumatic device that moves the valve stem as

    the pressure on a spring loaded diaphragm changes .the stem positions a plug in the

    orifice of the valve body. as the pressure increases ,the plug moves downward and

    restricts the flow of fluid through the valve.

    The valve may also be constructed to have air to- open action. Most

    commercial valves move from fully open to fully closed as the valve top pressure

    changes from 3to 15psi. In general the flow rate of fluid through the valve depends

    upon the upstream and downstream fluid pressure and the size of the opening

    through the valve

    4.2.2 Controler:

  • 7/29/2019 Snk Final Project

    41/57

    41

    The control hardware is required to control the temperature of a stream

    leaving the heat exchanger. In general a controller contains

    Transducers (temperature to current )

    Controller-recorder (current to current)

    Converter(current to pressure) Pressure valve (pressure to flow rate)

    Thermocouple is used to measure the temperature, the signal from the

    thermocouple is sent to the transducer, which produces an output in the of 4-20mA,

    which is a linear function of the input. The output of the transducer enters the

    controller where it is compared to the set point to produce an error signal. The

    controller converts the error to an output in the range of 3-16 psig which is a linear

    function of the input.Finally, the output of the converter is sent to the top of the control valve,

    which adjusts the flow of cooling water to the heat exchanger. Electricity is needed

    for the transducer, controller and converter. A source of 20psig air is needed for the

    converter.

    In a well-tuned control system, the response of the temperature will oscillate

    around the set point before coming to a steady state.

    4.2.3 Instrment In Batch Reactor:

    Pressure gauge,

    Temperature indicator,

    Steam control valves,

    Cooling water control valves,

    Radar level indicator,

    Differential pressure level indicator,

    Pressure transmitter,

    Orifice plate,

  • 7/29/2019 Snk Final Project

    42/57

    42

    4.3 PLANT LOCATION AND LAYOUT

    4.3.1 Plant Layout and Site Selection:

    The following are the three necessary for the general plant layout

    The starting point or location or reference A kinetic diagram or directional factor

    A statement of the special requirement for various product ,raw material ,by

    product storage facilities and for processing department

    From known calculated or estimated space requirement for individual equipment.

    It is possible to obtain proper allocation of equipment and overall dimensions of the

    building

    Process Plant PipingThe American national standard institute (ANSI) and the American petroleum

    institute (API) have established dimensional standard for the most widely used piping

    components they list these standard of the American society for testing material

    (ASTM) and American welding society(AWS).The consideration to be evaluated

    when selecting pipe material are:

    Possible exposure to fire respect to loss of strength, degradation

    Ability of thermal insulation

    Susceptibility of the pipe to brittle failure

    Susceptibility of piping material to crevice corrosion

    The Susceptibility of packing ,seal gasket as well as compatibility with the fluid

    handled

    The refrigerating effect sudden loss of pressure as volatile fluid in determining

    the

    lowest expected service temperature

  • 7/29/2019 Snk Final Project

    43/57

    43

    The organization which generate standards of major importance to chemical

    process industries in United States are tested

    American national standard institute (ANSI)

    American society of mechanical engineers(ASME)

    American society for testing material (ASTM) International organization for testing material (ISO)

    The economic consideration and efficient operation of a process unit depend on

    how well plant and equipment specified on the process flow sheet is laid out .the

    major factors to be considered are

    Economic consideration construction and operating cost

    Damage to persons and property in case of fire explosion and toxic release

    Future expansion Modular construction

    In preparing the layout, one has to satisfy various regulation acts which are in

    force in the area where the plant is located. The main considerations are

    Factories act

    The explosives act

    Excise rules

    Health rules

    The boiler act

    4.3.2 Plant Layout

  • 7/29/2019 Snk Final Project

    44/57

    44

    Figure 4.1 Plant Layout

    4.4 MATERIAL HANDLNG AND SAFETY

    Safety is one of the important aspect in any chemical industry. To run the

    process effectively, safety rules and regulations has to be followed. the guide lines

    are provided by the government and the industries has to implement them. Here we

    present about the safety guidelines adopted in ammonia plant

  • 7/29/2019 Snk Final Project

    45/57

    45

    In any industry, whether it is a small or large scale industry, safety must be

    emphasized .there is a safety department to look after the safety procedures inside

    the industry

    4.4.1 Kinds of Safety:

    Careful precautions are given to the workers upon their work

    The safety officer looks after the loading and unloading operating operations

    inside the plant

    There is an emergency control center for meeting in the emergency period

    There are assembly points inside the plant for the assembling of the workers

    during the emergency period.

    Mock drills are conducted in every 3months and they check with theiravailabilities

    The management is conducting seminars for the workers once in a month on the

    related areas such as safety, occupational health hazard, first aid, etc.

    PPEs of all kind are provided to the workers

    Fresh air line and showers are provided

    Medical center is established for emergency situations

    4.4.2 Safety Equipment:

    Personal safety

    Equipment safety

    Material safety

    Personal Safety is for personnel proteciton

    Respiratory

    Non respiratory

  • 7/29/2019 Snk Final Project

    46/57

    46

    Respiratory is used for to ovid inhalation of chemical

    Air supplying respiratory

    Air purifying respiratory

    Other safety protection is mentioned below.

    Helmet Safety shoe

    Gloves

    Apron

    Goggles, etc .

    Equipment Safety is to safe operation. Some of the safety feature

    adopted in process is listed below. Rupture disc

    Pressure safety valve

    Set points

    Alarm

    Emergency shut off

    Trips

    Material Safety

    Set points

    Controls to temperature, pressure, ph, etc

    Standard operating procedure

    Material safety data sheet

    4.4.3 Fire Fighting Equipment:

    Mechanical form

    DCP etc,

    Hydrant

    Single headed fire hydrant

    Double headed fire hydrant

    Fire water monitor

    fire escape hydrant

    Foam trally With water monitor

  • 7/29/2019 Snk Final Project

    47/57

    47

    4.4.4 Safety in Batch Reactor:

    Rupture disk

    pressure safety valve

    alarm system

    tripping system set points

    Interlocks & control

    A rupture disc or bursting disc is a pressure relief device that protects a

    vessels or system from over pressurization.

    Rupture discs have a one-time use thin foil that fails at a predetermined

    pressure, either positive or vacuum.

    Rupture discs provide fast response to an increase in system pressurebut once the membrane has failed it will not reseal.The equipment must be

    protected against being subjected to an internal vacuum (i.e., low

    pressure) that is lower than the equipment can withstand.

    Vacuum relief valves are used to open at a predetermined low pressure

    limit and to admit air or an inert gas in to equipment so as control the amount

    of vacuum.

    If the chemical is drawn from the tank additional nitrogen pressure is fed to

    the tank by the blanketing regulator system. In case, if the nitrogen is not

    available from the source, then the tank may go under negative pressure and

    vacuum is created in the tank. due to this the tank may collapse. to avoid such

    accidents vacuum relief valve breathes in atmospheric air and protects the

    tank from further damage.

    Interlock is a device used to help prevent a machine from harming its

    operator or damaging itself by stopping the machine when tripped.

    Safety protection requirements are interlocked with the equipment

    operation to save the plant and person. Also called permissive.

    Interlock testing will be done based on the inter lock report which was

    already tested and certified. Interlock testing duration intervals are defined

    based on the criticality of the equipment.

    Is the condition to start or stop the equipment or valve or pump etc.

  • 7/29/2019 Snk Final Project

    48/57

    48

    If the interlocks are satisfied than only you can able to operate the require

    operation.

    For example if the centrifuge lid is in open condition you can not able to

    start the centrifuge.

    Interlock check reports are available for all critical equipments and testedperiodically.

  • 7/29/2019 Snk Final Project

    49/57

    49

    The following controls are used in batch reactor

    The flow rate of steam can be controlled by the manual set point of

    percentage of valve opening.

    The flow rate of steam can be controlled by setting the requirement ofsteam flow rate. Based on the steam flow rate the steam control valve will

    be regulated automatically.

    Manual mode:

    The flow rate of cooling water to the condenser can be controlled by the

    manual set point of percentage of valve opening.

    Auto mode:

    The flow rate of cooling water to the condenser can be controlled by settingthe requirement of cooling water flow rate based on the cooling water flow

    rate the control valve will be operated automatically.

    Cascade mode:

    The flow rate of cooling water to the condenser can be controlled based on

    the heat load of condenser.

    Temperature control:

    The flow rate of cooling water can be controlled based on the cooling water

    out let temperature of total condenser.

    4.5 EFFLUENT TREATMENT PLANT

    Effluent is any water that has been adversely affected in quality by pollutants

    and the same drained during the process of production by production and other

    service department

  • 7/29/2019 Snk Final Project

    50/57

    50

    4.5.1 Effluent origin:

    Utilities cooling waters(biocides ,heat ,slimes ,silt)

    Production process waste water

    Production process waste aqueous solution Residue from process

    Above Effluent Contains the Following

    High COD

    Extreme pH-from Process

    Traces of solvent

    4.5.2 Need for Effluent Treatment: Treated effluent should comply with the local and/or national regulation

    regarding disposal of effluent into community treatment plants or into rivers

    ,lakes or ocean

    For the above orchid established zero discharge effluent treatment facility

    so that the pollutant concentrations in the effluent is treated and reused for

    the utilities (water make up for cooling towers, in recovery column water

    reflux and solvent washing ,in ETP filtration system water washing)

    Effluent Treatment

    It is a group of unit process designed to separate ,modify remove ,and

    destroy undesirable substance carried by effluent sources

    Effluent Quality Indicator

    The quality of the effluent is characterized by the following parameters

    pH

    COD (hemical oxygen demand )

    BOD (Biological oxygen demand )

    DO(Dissolved oxygen)

    TDS (Total dissolved solids)

  • 7/29/2019 Snk Final Project

    51/57

    51

    Others (silica, Iron, Fluoride)

    4.5.3 Types of Effluent:

    Based on the incoming effluent characteristics we separated effluent into two

    streams for effective treatment to achieve the zero dischargeThe two effluent streams are

    1. LPS-Low polluted stream

    2. HPS-High polluted stream

    LPS &HPS Standard are mentioned as belove

    LPS

    1. COD Less than 15,000ppm

    2. fluoride ,iron,& traces solvent nilHPS

    1. COD more than 15,000ppm

    2. traces of Solvent

    LPS and HPS are treated as belove mentuned

    LPS (Low pollutant stream)is the effluent source which is treated by the bio

    chemical and filtration process to reuse for utilities

    HPS (High pollutant stream)is the effluent source which is treated by stripping

    evaporation and distillation processes to convert into LPS source and to reuse

    for

    cooling towers and other applicable usages

    4.5.4 Effluent Treatment Processes:

    Treatment stages in LPS

    Primary treatment

    Secondary treatment

    Advanced treatment

    Primary treatment

    Primary treatment or pretreatment processes address the problem of

    screening ,equalization , neutralization, removal of floating scum and removal

    of suspended matters

  • 7/29/2019 Snk Final Project

    52/57

    52

    Screening

    Screen grit chamber is used for screening process to separate the solid

    materials of more than 6mm from the LPS and to settle heavier particles at

    the bottom of the chamber

    The above said solid material from the screen and the settled particles are tobe cleaned periodically

    By purging air at the bottom of the equalization tank for homogeneous mixing

    of LPS equalize the parameters (temperature, etc)and uniform feeding

    Any abnormal Ph is observed in the Eeropac(pH is the less than 6.5 and 8.5)

    neutralization to be done

    The total suspended solids (chemical sludge )which is collected at the center

    of the clarifier is taken for circulation from the neutralization tank and thesettled TSS can be thickened further in centrifuge.

    Biological method s are cheaper ,effective and eco friendly the following

    biological methods are mainly used to reduce COD in the effluent by

    maintaining the MLSS&DO

    1. Fine bubble jet aeration system

    2. Coarse bubble surface aeration system

    By fine bubble jet aeration system we are effectively supplying the oxygen

    from

    the atmosphere air through the air blower to the bottom of the aeropac (circular

    tank used for fine bubble aeration)with the effluent emerging from the submersible

    pump connected to the FRP kit with spray nozzle .the same set up is kept in the

    each compartment of the aeropac.

    Coarse Bubble Surface Aeration System

    By surface aeration we are effectively supplying the oxygen from the

    atmosphere air through the aerator by splashing the surface of the liquid

    (rectangular tank used for the surface aeration)

    Advance Filtration Treatment Process

    This process mainly used to recycle the resource (effluent) and to achieve the

    zero discharge.

    Ultra filtration system

    Nano filtration system

    Reverse osmosis system

    Ultra filtration system is used for following reason as mentioned below

  • 7/29/2019 Snk Final Project

    53/57

    53

    After secondary treatment we still have suspended solids in effluent. Using

    filtration methods we can trap all the suspended maters.

    If the feed water passes through the any filtration system it can be separates

    as two components

    1. Permeate2. Reject

    The permeate water from the UF is taken for NF for further treatment.

    The reject water from the UF is recycled in our biological system.

    UF filtration steps

    Pre filtration

    Cartridge filter (S.S) 250 micron pore size

    To avoid membrane contamination Fine porous ceramic membrane are used for filtration

    .

    The Principle Nano filtration system is.Nano filtration working as same as the

    osmosis principle only filtration range is differs. When the feed water pass through

    the semipermiable membrane (poly amide) the movement of solvent phase (that is

    clear filtrate) takes place from the higher concentration to lower with continue till the

    applied pressure is greater than the osmotic pressure of the feed water.

    Dissolved macro particle shall be removed in this specific range of

    The permeate water from the NF is taken for RO for further treatment

    The reject water from the NF is send to ecology for HPS treatment

    NF filtration steps

    Pre filtration steps

    Cartridge filter (PP wounded) 5 micron pore size

    To avoid membrane contamination

    NF membrane filtration

    Membrane is made of spirally wounded fine porous poly amide

  • 7/29/2019 Snk Final Project

    54/57

    54

    Reverse osmosis system

    Principle

    When the feed water (concentrated)water pass through the semipermiable

    membrane (poly amide) the movement of solvent phase (that is clear filtrate) takes

    place from the higher concentration to lower with the applied pressure the filtrationwill continue till applied pressure is greater than the osmotic pressure of the feed

    water.

    Dissolved micro particle shall be removed in this specific range of filtration.

    The permeate water from the RO is used for cooling water make up in utilities &

    column reflux in the recovery plants.

    The reject water from the RO is send to ecology for HPS treatment.

    RO filtration steps Pre filtration Cartridge filter (PP wounded) 5 micron pore size

    To avoided membrane contamination

    RO membrane filtration Membrane is made of spirally wounded fine porous

    poly amide.

    Treatment process in HPS is mentioned below

    Stripping

    To remove mixed solvent in HPS

    Evaporation

    HPS is converted to LPS by evaporation

    (Three types of evaporator)

    Waste heat recovery

    Impure stream heat is transferred into pure stream

    Concentration (Concentrated as salt)

  • 7/29/2019 Snk Final Project

    55/57

    55

    CHAPTER 5

    CONCLUSION

    A detail study of manufacture of Pentaerithritol has been completed with

    material and energy balance calculation for the production capacity of 600 tones per

    annum. Design of the reactor and vacuum tray drier involved in the process has

    been studied as per requirements & also plant layout, safety, with respect to

    environment aspects has been studied. It has been estimated that Payback period

    of 4.329 can be achived by suitable selection of process. The effluent treatment for

    this process has been studied in detail manner. Safety related to material handling,

    fire fighting equipments and safety features of batch reactor is studied in detail.

    The application of penaerithritol is studied. By product sodiumformate recoveryis studied in detail with respect to material balance.in overall view it has been

    concluded that this method of process adopted for manufacturing of pentarerithritol

    and its by- product is most suitable economical process.

  • 7/29/2019 Snk Final Project

    56/57

  • 7/29/2019 Snk Final Project

    57/57