sno+ mark chen snolab workshop august 22, 2007. outline science goals science goals –focusing on...
TRANSCRIPT
SNO+SNO+
Mark ChenMark Chen
SNOLAB WorkshopSNOLAB Workshop
August 22, 2007August 22, 2007
OutlineOutline
science goalsscience goals– focusing on Nd double beta decayfocusing on Nd double beta decay
R&D activities and progressR&D activities and progress budget and schedulebudget and schedule
SNO+ OriginSNO+ Origin
SNO+ concept was born in the CFI SNO+ concept was born in the CFI Proposal for SNOLABProposal for SNOLAB– a deep lab is required to eliminate a deep lab is required to eliminate
cosmogenic cosmogenic 1111C background to the C background to the peppep solar neutrino signal in a liquid scintillator solar neutrino signal in a liquid scintillator detectordetector
part of the Subatomic Physics Five-part of the Subatomic Physics Five-Year Plan since 2001Year Plan since 2001
LOI to SNOLAB submitted April 2004LOI to SNOLAB submitted April 2004
Fill with Liquid Scintillator SNO plus liquid scintillator physics
program pep and CNO low energy solar neutrinos
tests the neutrino-matter interaction, sensitive to new physics
geo-neutrinos 240 km baseline reactor neutrino oscillations supernova neutrinos double beta decay
• …sometimes referred to as SNO++
• it is possible to add isotopes to liquid scintillator, for example– dissolve Xe gas– organometallic chemistry (Nd, Se, Te)
– dispersion of nanoparticles (Nd2O3, TeO2)
• we researched these options and decided that the best isotope and technique is to make a Nd-loaded liquid scintillator
SNO+ Double Beta Decay
150Nd
3.37 MeV endpoint (9.7 ± 0.7 ± 1.0) × 1018 yr
2half-life
measured by NEMO-III
isotopic abundance 5.6%1% natural Nd-loaded liquid scintillator in SNO+ has 560 kg of 150Nd compared to 37 g in NEMO-III
cost: $1000 per kg for metallic Nd; cheaper is NdCl3…$86 per kg for 1 tonne
table from F. Avignone Neutrino 2004
• a liquid scintillator detector has poor energy resolution; but enormous quantities of isotope (high statistics) and low backgrounds help compensate
• large, homogeneous liquid detector leads to well-defined background model– fewer types of material near fiducial volume– meters of self-shielding
• possibly source in–source out capability
SNO+ Double Beta Decay
• using the carboxylate technique that was developed originally for LENS and now also used for Gd-loaded scintillator
• we successfully loaded Nd into pseudocumene and in linear alkylbenzene (>1% concentration)
• with 1% Nd loading (natural Nd) we found very good neutrinoless double beta decay sensitivity…
Nd-Loaded Scintillator
0: 1000 events peryear with 1% naturalNd-loaded liquidscintillator in SNO++
Test <m> = 0.150 eV
maximum likelihood statistical test of the shape to extract 0 and 2 components…~240 units of 2 significance after only 1 year!
Klapdor-Kleingrothaus et al., Phys. Lett. B 586, 198, (2004)
simulation:one year of data
Nd-LS Synthesis
• solvent-solvent extraction method to synthesize metal-loaded liquid scintillator
• this method was used to make Nd-LS at both BNL and Queen’s laboratories
linear alkylbenzene (LAB)
(organic phase) Nd(RCOO)3
(aqueous phase)
Nd3+(Cl-)3 + 3RCOO- → Nd(RCOO)3
NH3 + RCOOH → NH4+ + RCOO-
300 400 500 600 7000.0
0.2
0.4
0.6
0.8
350 360 370 380 390 400 410 420 4300.00
0.01
0.02
0.03
0.04
0.05
0.06
AB
S
(nm)
Nd-LAB, 1.45% Nd Nd-PC, 1.01% Nd, BNL Nd-DIN, 1.5% Nd PPO emission
AB
S
(nm)
Nd in Various Scintillation Solvents
• you can see that 1% Nd-loaded scintillator is blue– because Nd absorbs light
• fortunately it is blue– it means the blue scintillation light can propagate through
• but, not enough light output in SNO+ if using 1% Nd loading
• BUT, with enriched Nd (e.g. enrich to 56% 150Nd up from 5.6%) could have the same neutrinoless double beta decay sensitivity using 0.1% Nd loading…
Light Output from Nd Scintillator
• at 1% loading (natural Nd), there is too much light absorption by Nd– 47±6 pe/MeV (from Monte
Carlo)
• at 0.1% loading (isotopically enriched to 56%) our Monte Carlo predicts– 400±21 pe/MeV (from Monte
Carlo)– good enough to do the
experiment
Light Output and Concentration
Nd-150 Consortium
SuperNEMO and SNO+, MOON and DCBA are supporting efforts to maintain an existing French AVLIS facility that is capable of making 100’s of kg of enriched Nda facility that enriched 204 kg of U (from 0.7%
to 2.5%) in several hundred hours
2000–2003 Program : Menphis facility
Design : 2001Building : 20021st test : early 20031st full scale exp. : june 2003
EvaporatorDye laser chainYag laserCopper vapor laser
AVLIS for 150Nd is Known
SNO+ Nd Summary So Far…
• SNO+ plans to deploy 0.1% Nd-loaded liquid scintillator– ~500 kg of 150Nd if enriched Nd– 56 kg of 150Nd if natural Nd
• light output: 400 pe/MeV corresponds to 6.4% resolution FWHM at 150Nd Q-value
• why Nd?– high Q-value is above most backgrounds– Ge: Majorana and GERDA– Xe: EXO, XMASS– Te: CUORE– Mo: MOON– Ca: CANDLES– Cd: C0BRA– Nd: SNO+
• how we search for double beta decay?– fit 2 and 0 known spectral shapes along with knowable background
shapes (mainly from internal Th)
SNO+ Double Beta SNO+ Double Beta SpectrumSpectrum
1 yr, 500 kg isotope, m = 150 meV
Statistical Sensitivity in Statistical Sensitivity in SNO+ SNO+
500 kg isotope 56 kg isotope
• 3 sigma detection on at least 5 out of 10 fake data sets• 2/0 decay rates are from Elliott & Vogel, Ann. Rev. Nucl. Part. Sci. 52, 115 (2002)
corresponds to 0.1% natural Nd LSin SNO+
0.1% Natural Nd Loading0.1% Natural Nd Loading
1yr, 1000kg natural, 150meV
• for 50% enriched 150Nd (0.1% Nd LS in SNO+)– 3 statistical sensitivity reaches 30 meV– 5 sensitivity of 40 meV after 3 years– for background levels (U, Th) in the Nd LS to be at the
same level as KamLAND scintillator
– systematic error in energy response will likely be the limit of the experiment and not the statistics
– preliminary studies show that we can understand the energy resolution systematics at the level required to preserve sensitivity down to 50 meV
Statistical Sensitivity
Stability of Nd-LAB
300 400 500 600 7000.0
0.2
0.4
0.6
0.8
350 360 370 380 390 400 410 420 4300.000
0.005
0.010
0.015
0.020
AB
S
(nm)
Nd-LAB, 1.45% Nd, 1 year Nd-LAB, 1.45% Nd PPO emission
AB
S
(nm)
no change in optical properties after >1 year
external 241Am
Compton edge 137Cs207Bi conversionelectrons
Nd LS Works!small Nd-LS detector with , , sources demonstrates it works as scintillator
Nd PurificationNd Purification
NdClNdCl33 needs to be purified needs to be purified putting Nd into the organic accomplishes putting Nd into the organic accomplishes
purification (U, Th don’t get loaded into the purification (U, Th don’t get loaded into the liquid scintillator)liquid scintillator)
Nd liquid scintillator: after synthesis it is Nd liquid scintillator: after synthesis it is possible to perform online loop purificationpossible to perform online loop purification
150150Nd enrichment also removes unwanted Nd enrichment also removes unwanted ThTh
Radio-purification goals: Radio-purification goals: 228228Th and Th and 228228Ra in 10 Ra in 10
tonnes of 10% Nd (in form tonnes of 10% Nd (in form of NdClof NdCl33 salt) down to salt) down to
<<110-14 g 232Th/g Nd
Raw NdClRaw NdCl33 salt salt
measurement: measurement: 228228Th Th equivalents to equivalents to 32±2532±2510-9 g g 232232Th/g NdTh/g Nd
A reduction of >106 is required!!!
Purification Spike Tests
• spike scintillator with 228Th (80 Bq) which decays to 212Pb• counted by β- coincidence liquid scintillation counting
Spike Test Results: Extraction Efficiencies of Th and Ra in 10% NdCl3 using HZrO and BaSO4
PurificationPurification
methodmethod
AdsorbentAdsorbent
ConcConc
Extraction efficiencyExtraction efficiency
228Th228Th 226Ra226Ra
HZrO mixed-inHZrO mixed-in
0.1 mg/g Zr0.1 mg/g Zr
0.44 mg/g Zr0.44 mg/g Zr
0.82 mg/g Zr0.82 mg/g Zr
<5%<5%
99.06±0.22%99.06±0.22%
99.89±0.02%99.89±0.02%
<10%<10%
30.7±5.7%30.7±5.7%
30.1±9.0% 30.1±9.0%
BaSO4 mixed-inBaSO4 mixed-in 1.0 mg/g Ba1.0 mg/g Ba 9.5±4.7% 9.5±4.7% 63.4±1.9% 63.4±1.9%
BaSO4 co-precipitationBaSO4 co-precipitation
0.49 mg/g Ba0.49 mg/g Ba
1.39 mg/g Ba1.39 mg/g Ba
20.4±4.4%20.4±4.4%
62.8±2.3%62.8±2.3%
97.2±0.2%97.2±0.2%
99.89±0.03%99.89±0.03%
factor of 1000 purification per pass achieved for both Th and Ra!
SNO+ Nd: Summary
• good sensitivity and very timely• homogeneous liquid, well defined background
model– large volume gives self-shielding– Q-value is above most backgrounds
• thus “insensitive” to internal radon backgrounds• thus insensitive to “external” backgrounds (2.6 MeV )
• Th, Ra purification techniques are effective• huge amounts of isotope, thus high statistics,
can work for double beta decay search– requires exquisite calibration and knowledge of
detector response
Low Energy Solar Neutrinos
p + p 2H + e+ + e p + e− + p 2H + e
2H + p 3He +
3He + 3He 4He + 2 p 3He + p 4He + e+ + e
3He + 4He 7Be +
7Be + e− 7Li + + e7Be + p 8B +
7Li + p + 8B 2 + e+ + e
p-p Solar Fusion Chain
• complete our understanding of neutrinos from the Sun
pep, CNO, 7Be, pp
CNO Cycle12C + p → 13N + 13N → 13C + e+ + e
13C + p → 14N + 14N + p → 15O + 15O → 15N + e+ + e
15N + p → 12C +
Ga, Cl and SNO Data – Distilled
Barger, Marfatia, Whisnant, hep-ph/0501247
deduce the survival probabilityhigh energy: directly from SNOmedium energy: Cl minus highlow energy: Ga minus high, medium
we observe that the survival probability for solar neutrinos versus energy is not yet accurately determined from existing experiments
transition between vacuum and matteroscillations in the Sun has not been accurately determined
there is even some tension in existing low and medium data…
x is 13
Things You Could Learn…with precision data from low energy solar neutrinos
• fix m2 with KamLAND data, vary 13 (with 12 fixed or varying)– low energy solar neutrino data helps constrain 13
• extract m2 from solar data, strongly affected by the position of the transition – low energy solar neutrino data are key – compare with m2 from KamLAND– neutrinos versus antineutrinos, tests CPT invariance
• compare position/shape of the transition at lower energy with the prediction from LMA MSW oscillations– might reveal deviations from Standard Model couplings (due to non-standard
interactions or coupling to a sterile neutrino admixture)
…and many of these studies have been done, all pointing to the fact that at the transition (between 1-2 MeV) there is sensitivityto new neutrino physics!
(e.g. Balantekin or Friedland, Peña-Garay, Lunardini, or Barger and colleagues…)
Neutrino-Matter Interaction
• best-fit oscillation parameters suggest MSW occurs
• but we have no direct evidence of MSW– day-night effect not observed– no spectral distortion for 8B ’s
• testing the vacuum-matter transition is sensitive to new physics
for m2 = 8 × 10−5 eV2, = 34°Ne at the centre of the Sun →E is 1-2 MeV Hamiltonian for neutrino propagation in the Sun
from Peña-Garay
• MSW is linear in GF and limits from -scattering experiments ( g2) aren’t that restrictive
• oscillation solutions with NSI can fit existing solar and atmospheric neutrino data…NSI not currently constrained
• new pep solar data would reveal NSI
Friedland, Lunardini, Peña-Garay, hep-ph/0402266
pep solar neutrinos are at the “sweet spot” to test for new physics
New Physicsgood fit with NSI
Mass-Varying Neutrinos
• cosmological connection: mass scale of neutrinos and the mass scale of dark energy are similar
• postulating a scalar field and neutrino coupling results in neutrinos whose mass varies with the background field (e.g. of other neutrinos)
• solar neutrinos affected?• pep : a sensitive probe
Barger, Huber, Marfatia, hep-ph/0502196
Fardon, Nelson, Weiner, hep-ph/0309800
pep
pep
SNO CC/NC
m2 = 8.0 × 10−5 eV2
tan2 = 0.45
SSM pep flux:uncertainty ±1.5%
known sourceknown cross section (-e scattering)→ measuring the rate gives the survivalprobability→ precision test
Why pep Solar Neutrinos?
observing the rise confirms MSW and our understanding of solar neutrinos
stat + syst + SSM errors estimated
for neutrino physics with lowenergy solar neutrinos, have toachieve precision similar to SNO or better…it’s no longer sufficient to just detect the neutrinos
pep solar neutrinos:E = 1.44 MeV…are at the right energy to search for new physics
these plots from the KamLAND proposal muon rate in KamLAND: 26,000 d−1 compared with SNO: 70 d−1
11C Cosmogenic Background
depth to reduce/eliminate 11C background
good light output from the scintillator studied the effect of varying the energy
resolution; found not a steep dependence radiopurity
control of Rn exposure because of 210Bi eliminate 40K internal contamination
Requirements for a Liquid Scintillator pep Solar Detector
Solar Signals with Solar Signals with BackgroundsBackgrounds
SNO+ Solar Neutrino Projected Capability with backgrounds at KamLAND levels
U, Th achieved 210Pb and 40K post-purification KamLAND targets external backgrounds
calculated based upon SNO external activities fiducial volume 450 cm
pep uncertainties <±5% statistical (signal extraction from background) ±3% systematic ±1.5% SSM e.g. it would be a measurement of the survival
probability at 1.44 MeV of 0.55 ± 0.03
pep Sensitivity Dependence on 210Pb
allowing 210Pb contamination to increase by large factors does not have a large impact on the pep statistical uncertainty
peppep and and 1313
solar neutrinos are solar neutrinos are complementary to complementary to long baseline and long baseline and reactor experiments reactor experiments for for 1313
hypothetical 5% hypothetical 5% stat. 3% syst. 1.5% stat. 3% syst. 1.5% SSM measurementSSM measurement
has discriminating has discriminating power for power for 1313
pep
antineutrino events e + p → e+ + n:• KamLAND: 33 events per year (1000 tons CH2) / 142 events reactor• SNO+: 44 events per year (1000 tons CH2) / 38 events reactor
Geo-Neutrino SignalGeo-Neutrino Signal
SNO+ geo-neutrinos and reactor background KamLAND geo-neutrino detection…July 28, 2005 in Nature
KamLAND
Reactor Neutrino OscillationsReactor Neutrino Oscillations50 km
Bruce 240 km
Pickering 340 km Darlington 360 kmoscillation spectral features depend on m2
and move as L/E
Clarence J. VirtueNSERC SNO+ Review - 27 November 2006
SNO+ vs. Super-Kamiokande
CC: (260) 41% (7000) 91%
(30) 4.7%
(10) 1.5%
NC: (60) 9.3% (410) 5%
(270) 42%
ES: (12) 1.9% (300) 4%
SN Neutrino Detection in SNO+
Steps Required: SNO → SNO+
• AV hold down
• liquid scintillator procurement
• scintillator purification
• “minor” upgrades– cover gas– electronics– DAQ– calibration
SNO+ Liquid Scintillator “new” liquid scintillator developed
linear alkylbenzene (LAB) compatible with acrylic, undiluted high light yield pure (light attenuation length in excess of 20 m at 420 nm) low cost high flash point 130°C safe low toxicity safe smallest scattering of all scintillating solvents investigated density = 0.86 g/cm3
metal-loading compatible SNO+ light output (photoelectrons/MeV) will be
approximately 3-4× that of KamLAND ~900 p.e./MeV for 54% PMT area coverage
Daya Bay and Hanohano plan to use LAB; others LENS, Double CHOOZ, LENA, NOA considering
SNO+ AV Hold Down
ExistingAV SupportRopes
SNO+ AV Hold Down
AV Hold DownRopes
ExistingAV SupportRopes
SNO+ R&D 2005SNO+ R&D 2005Proof of PrincipleProof of Principle linear alkylbenzene developed linear alkylbenzene developed
by SNO+ as the liquid by SNO+ as the liquid scintillatorscintillator
AV hold-down for specific AV hold-down for specific gravity 0.86 is feasible (study gravity 0.86 is feasible (study by Bob Brewer)by Bob Brewer)
double beta decay potential double beta decay potential investigatedinvestigated– made 1.0% Nd-loaded made 1.0% Nd-loaded
scintillatorscintillator
SNO+ 2006SNO+ 2006Expanded R&DExpanded R&D AV hold-down implementation plan developedAV hold-down implementation plan developed designs for cover gas and universal interface designs for cover gas and universal interface
being preparedbeing prepared radon daughter removal from acrylic studiedradon daughter removal from acrylic studied scintillator purification tests: scintillator purification tests: factor >1000factor >1000
achievedachieved initial conceptual design and layout for initial conceptual design and layout for
scintillator purification and handlingscintillator purification and handling simulations: signals and backgroundssimulations: signals and backgrounds continued scintillator-acrylic compatibility testscontinued scintillator-acrylic compatibility tests learned of the existence of French AVLIS learned of the existence of French AVLIS
facility for enriching neodymiumfacility for enriching neodymium
all major questions have been answered
SNO+ 2007 ContinuingSNO+ 2007 ContinuingResearch ProgressResearch Progress NdClNdCl33 purification tests: purification tests: factor ~1000factor ~1000 per per
pass achievedpass achieved scintillator purification and process scintillator purification and process
engineering: Phase I design completedengineering: Phase I design completed hold-down net designs being evaluatedhold-down net designs being evaluated finite-element analysis of the hold-down net finite-element analysis of the hold-down net
in progressin progress
SNO+ ActivitiesSNO+ Activities2007 and Beyond2007 and Beyond completed engineering of hold-down completed engineering of hold-down
system system engineering and building new engineering and building new
glovebox and calibration manipulator glovebox and calibration manipulator systemssystems
completed engineering of scintillator completed engineering of scintillator purification system by Dec 2007purification system by Dec 2007
DAQ upgrade to accommodate DAQ upgrade to accommodate higher rateshigher rates
Previous Analysis for SNO Prelim Hold-down Conceptused previous SNO calculation
Set of weights on bottom of cavity
SNO+ AV Hold-DownSNO+ AV Hold-Down
V. Strickland doing a new FEA V. Strickland doing a new FEA calculation of the hold-down netcalculation of the hold-down net– loading and buckling studyloading and buckling study– optimization of the designoptimization of the design
flat ropes, round ropesflat ropes, round ropes number of ropesnumber of ropes rope spacingrope spacing circumferential rope(s) placementcircumferential rope(s) placement ……
S. Florian engineeering the PSUP S. Florian engineeering the PSUP penetrations and hold-down anchorspenetrations and hold-down anchors
Rope ConfigurationRope Configuration P. Harvey studying rope tensions and P. Harvey studying rope tensions and
geometrical placement for PSUP penetrationsgeometrical placement for PSUP penetrations
SNO+ Universal SNO+ Universal InterfaceInterface glove boxglove box cover gascover gas calibration manipulatorcalibration manipulator feedthrough for AV pipesfeedthrough for AV pipes
SNO Cover Gas SNO Cover Gas SystemSystem
SNO covergas system was not sealed; dealt with pressure swings by continuous venting
for SNO+ improvements to this system are being developed
SNO Calibration SourceSNO Calibration Source ManipulatorManipulator
Radon/Light Barrier
Umbilicals Manipulation Detector Interface
Accuracy
< 2 cm single axis
~ 5 cm triple axis
Remote Operation/Interlocks
Stringent Cleanliness Requirements
New Glove BoxNew Glove Box
SNO+ Electronics Upgrades Front End (with no hardware changes):
Re-tune integration time from ~420ns -> ~1s (max possible without hardware change)
Re-adjust short and long integration times for better match to scintillation time constants
Adjust FPGA code to optimize for higher hit rate
Front End (possible hardware changes):
Replace biasing resistors for lower trigger current.
Replace memory controller and 4 MByte memory SIMMS for larger event buffering.
Re-adjust references for ADCs to match higher charges.
SNO+ NSERC Review 27 Nov 2006Fraser Duncan, SNOLAB
SNO+ Electronics Upgrades Trigger (hardware changes):
Need re-design of final analog summing board to handle higher currents.
May also want to implement active baseline restoration to improve stability.
Replace analog measurement board with full transient digitizer to store energy sum trace with each event, possibly other trigger sum traces also.
Miscellaneous
Various small upgrades to electronics and electrics in the detector (items that were low priority during SNO operations).
SNO+ NSERC Review 27 Nov 2006Fraser Duncan, SNOLAB
Data Flow Upgrades
SNO+ NSERC Review 27 Nov 2006Fraser Duncan, SNOLAB
Replace existingSun Sparc Ultra 1with new system(Mac or Linux)
Possibly replacesingle ECPU withmultiple processors
Possibly replaceXL1/XL2 interfacecards with higherthroughput pair
Data Flow
DAQ Upgrades
SNO+ NSERC Review 27 Nov 2006Fraser Duncan, SNOLAB
Replace Mac OS9 system with OSX.Rewrite DAQ program(SHaRC) for OSX
Hardware Control
Improve remotemonitoring toolsfor remotedetector operation
OffSite
PMT Failures
Fraser Duncan, SNOLAB SNO+ NSERC Review 27 Nov 2006
Number of PMT Failures Between June 18, 1999 and Nov 23, 2006
00/01 01/01 02/01 03/01 04/01 05/01 06/01 07/01
Date
• Similar to water fill rate• Failures seem correlated with HV• No effect due to raised HV (+50 V Oct 2004)
Dead T
ubes
100
700
200
300
400
500
600
800
Turn
off
for
NC
D Inst
alla
tion
Turn
on a
fter
NC
D Inst
alla
tion
0.8% / yr
72 PMT FailuresPer Year
Electronics Failures Failure of SNO electronics have been tracked.
SNO+ NSERC Review 27 Nov 2006Fraser Duncan, SNOLAB
Motherboards DaughtercardsMain
Pow
er
LV
Pow
er S
upplie
s
HV
Supply
MTC
/D
MTC
/A (fi
x)
XL2
CTC
& e
sum
repairs
HV
backpla
in
HV
overh
aull
PM
TIC
(exclu
de W
EB
)
WE
B re
pair
PM
T p
ulle
d
PM
T re
sure
ctio
n
L.V
. Repairs
LV
Monito
r
FIF
O m
od (c
lean D
M)
Trig
ger re
pairs
Oth
er re
pairs
tota
l repairs
tota
l repla
ced
Trig
ger re
pairs
Cle
an D
M
Fix
bad c
hannels
Bad e
ca/p
ca re
pla
ce
tota
l repairs
Tota
l repla
ced
tota
l Repairs
Tota
l MB
/DB
repla
ced
Tota
l DM
Failu
res
2001 0 1 0 2 0 4 1 2 3 3 61 116 0 8 0 20 0 3 31 11 1 0 0 0 1 19 164 30 202002 1 0 1 0 0 1 2 0 0 5 103 153 0 5 10 16 3 1 35 15 3 0 0 14 3 22 201 37 342003 0 1 0 0 2 1 0 0 26 30 72 131 50 2 11 3 0 2 18 5 0 2 0 16 2 25 261 30 232004 0 0 1 0 1 1 7 0 1 2 29 52 0 5 2 4 0 0 11 8 1 4 58 8 63 19 139 27 162005 1 0 0 0 1 2 0 0 0 2 47 86 0 7 7 10 0 0 24 8 1 0 0 8 1 15 117 23 162006 0 0 0 0 0 0 0 0 0 1 21 30 0 10 9 5 5 1 23 1 0 0 0 3 0 7 54 8 13
Total 2 2 2 2 4 9 10 2 30 43 333 568 50 37 39 58 8 7 142 48 6 6 58 49 70 107 936 155 122
Daughter Cards (8 chs/card) are key components.
There are few conventional spares of some of the components.
Current failure rates are ~11 DCs/yr = 90 ch per year
Approximately the same rate as PMT failures.
Electronics Spares
SNO+ NSERC Review 27 Nov 2006Fraser Duncan, SNOLAB
Several actions will be taken to bolster the electronics spares:
1) Salvage “seconds” - components that were slightly outside the original acceptance criteria; and recover components for the “bone piles”.
2) Consolidate the dead PMTs in each rack. This will release
~30 Motherboards ~120 Daughtercards ~30 PMTICs
This would produce ~6yrs of spare components if no further action was taken.
As PMTs and electronics channels fail during SNO+ operations, periodically consolidate failed PMTs and channels.
Scintillator Purification
prelim design completed by KMPS (engineering company that designed the Borexino scintillator purification)
sizing completed, operating temperatures and pressures, flow rates calculated, performance simulated…
SNO+ Project Costs SNO+ Project Costs
estimated total estimated total costscostsExpenses: Cash Flow:
Canadian Costs to Convert SNO to SNO+ 2007/08 2008/09 $M $M $M procure liquid scintillator 2.00 0.00 2.00 AV hold-down conversion 2.25 0.30 1.95 scintillator purification plant 7.63 0.30 7.33 cover gas and universal interface 0.30 0.20 0.00 TOTAL 12.18 0.80 11.28 US Contribution (in addition to US SNO equipment) electronics and DAQ upgrade 0.5 obtain enriched Nd-150 4.00 0.00 4.00 TOTAL with Nd 16.18
Broadbrush ScheduleBroadbrush Schedule
Apr 2007: $400k NSERC funds received for continued developmentApr 2007: $400k NSERC funds received for continued development– expenditures on AV and cavity inspection, light water systemexpenditures on AV and cavity inspection, light water system– Phase I scintillator purification and process engineeringPhase I scintillator purification and process engineering– radon-reduced air systemradon-reduced air system
Aug-Sep 2007: begin light water refillAug-Sep 2007: begin light water refill Oct 1, 2007: submit NSERC portion of the SNO+ capital proposalOct 1, 2007: submit NSERC portion of the SNO+ capital proposal Oct 2007: AV contains light waterOct 2007: AV contains light water Q4 2007: $400k FedNor funds for continued development availableQ4 2007: $400k FedNor funds for continued development available Dec 2007-Jan 2008: submit capital proposal to CFIDec 2007-Jan 2008: submit capital proposal to CFI
Feb 2008: begin installation of radon-free airFeb 2008: begin installation of radon-free air Q2 2008: start of capital fundsQ2 2008: start of capital funds Q2 2008: begin construction of scintillator purification modulesQ2 2008: begin construction of scintillator purification modules Jun 2008: install “floating dock” inside AV using radon-free airJun 2008: install “floating dock” inside AV using radon-free air Jun 2008: start draining light water in AV; sand AV surfaces as water Jun 2008: start draining light water in AV; sand AV surfaces as water
is drainedis drained Sep 2008, AV is sanded, atmosphere is radon-free air; withdraw Sep 2008, AV is sanded, atmosphere is radon-free air; withdraw
floating docks, prepare AV sealfloating docks, prepare AV seal construction of AV hold-down follows; installation of scintillator construction of AV hold-down follows; installation of scintillator
process and purification; install new universal interface…process and purification; install new universal interface…
SNO+ Nd Broadbrush schedule
• end of 2009: fill and run with pure scintillator
• 2010: add Nd
• 2011: below 100 meV sensitivity reached if natural Nd and below 50 meV reached if enriched Nd
SNO+ Special SNO+ Special RequirementsRequirements 1000 tons of linear alkylbenzene1000 tons of linear alkylbenzene
– high flash point (130°C) high flash point (130°C) safesafe– low toxicity low toxicity safesafe
not classified as hazardous material for not classified as hazardous material for transportationtransportation
handling large quantity is a special requirementhandling large quantity is a special requirement– use SNO railcars for transportation: surface to use SNO railcars for transportation: surface to
detectordetector ~200 kW heating and <50 tons cooling ~200 kW heating and <50 tons cooling
limitations have been observed in the design of limitations have been observed in the design of the distillationthe distillation
11
0pseudocumene (2 4 0)diesel (0 2 0)
SNO+ is Already at SNO+ is Already at SNOLABSNOLAB scintillator purification replaces heavy scintillator purification replaces heavy
water purificationwater purification special requirement of 1000 tons LABspecial requirement of 1000 tons LAB
– prelim process design completedprelim process design completed– site visit to Petresa in Sep 2007site visit to Petresa in Sep 2007– preparation of documents describing the preparation of documents describing the
handling protocols for INCO and SNOLAB handling protocols for INCO and SNOLAB approvalapproval
otherwise SNO+ is like SNOotherwise SNO+ is like SNO
SNO+ Year 1 Activities SNO+ Year 1 Activities at SNOLABat SNOLAB inspection of the cavityinspection of the cavity inspection of the acrylic vesselinspection of the acrylic vessel modifications to the universal interface modifications to the universal interface
(glove box on top of the detector)(glove box on top of the detector) modifications to the cover gas (for both modifications to the cover gas (for both
installation and eventual running)installation and eventual running) deployment of some hardware for the cavity deployment of some hardware for the cavity
accessaccess completed engineering for the hold-down completed engineering for the hold-down
system and the scintillator purification system and the scintillator purification processprocess
consolidation of electronicsconsolidation of electronics
SNO+ Year 2 at SNO+ Year 2 at SNOLABSNOLAB construction: AV hold-downconstruction: AV hold-down construction scintillator purification construction scintillator purification
system (and fluid handling)system (and fluid handling) scintillator procurement contractsscintillator procurement contracts electronics/DAQ upgradeselectronics/DAQ upgrades
……aim for end of 2009 detector fillingaim for end of 2009 detector filling
Summary PointsSummary Points
diverse and exciting neutrino physicsdiverse and exciting neutrino physics SNO+ double beta decay is competitive and could SNO+ double beta decay is competitive and could
be leading the field with an early startbe leading the field with an early start SNO+ is the most interesting solar neutrino SNO+ is the most interesting solar neutrino
experiment to be done post-SNOexperiment to be done post-SNO SNO+ geo-neutrinos will be a SNO+ geo-neutrinos will be a NatureNature publication publication
of considerable popular science interest…for free!of considerable popular science interest…for free! SNO+ reactor neutrino “oscillation dip moves as SNO+ reactor neutrino “oscillation dip moves as
L/E” will be an easy L/E” will be an easy PRLPRL publication…for free! publication…for free! we have the required technical skills in our teamwe have the required technical skills in our team
– SNO+ includes KamLAND and Borexino members and SNO+ includes KamLAND and Borexino members and experienceexperience
we have proven SNO operations capabilitywe have proven SNO operations capability much of the development activity is much of the development activity is
straightforward engineering; nothing all that straightforward engineering; nothing all that exotic is being proposedexotic is being proposed
SNO+ CollaborationQueen’s
M. Boulay, M. Chen, X. Dai, E. Guillian, P. Harvey, C. Kraus, C. Lan,A. McDonald, V. Novikov, S. Quirk, P. Skensved, A. Wright
AlbertaA. Hallin, C. Krauss
CarletonK. Graham
LaurentianD. Hallman, C. Virtue
SNOLABB. Cleveland, F. Duncan, R. Ford, N. Gagnon, J. Heise, C. Jillings, I. Lawson
Brookhaven National LabR. Hahn, Y. Williamson, M. Yeh
Idaho State UniversityK. Keeter, J. Popp, E. Tatar
University of PennsylvaniaG. Beier, H. Deng, B. Heintzelman, J. Secrest
University of Texas at AustinJ. Klein
University of WashingtonN. Tolich, J. Wilkerson
University of SussexK. Zuber
LIP LisbonS. Andringa, N. Barros, J. Maneira
Nd Matrix Elements
• from Elliott and Vogel, hep-ph/0202264 v1 (2002)– 0.1 is Staudt, Muto and Klapdor– 0.2 is Faessler and Simkovic; Toivanen and Suhonen
• from Rodin et al., corrected (2007) value is 0.2-0.3