Page 1: Social Monitoring Report · (as of December 2017) $1.00 = VND 22,350 ABBREVIATIONS ADB - Asian Development Bank AHs - affected households APs - affected persons CP - compensation

1

Social Monitoring Report

Quarterly Report October to December 2017 (Fourth Quarter of 2017) March 2019

VIE: Power Transmission Investment Program - Tranche 3 Prepared by Southern Power Project Management Board for the Asian Development Bank.

Page 2: Social Monitoring Report · (as of December 2017) $1.00 = VND 22,350 ABBREVIATIONS ADB - Asian Development Bank AHs - affected households APs - affected persons CP - compensation

2

CURRENCY EQUIVALENTS (as of December 2017)

$1.00 = VND 22,350

ABBREVIATIONS

ADB - Asian Development Bank AHs - affected households APs - affected persons CP - compensation plan CPC - Commune People’s Committee DCARB - District Compensation, Assistance and Resettlement Board DMS - detailed measurement survey DPC - District Peoples Committee DPs - displaced persons EA - executing agency EMA - external monitoring agency GOV - Government of Viet Nam IA - implementing agency IOL - inventory of losses km - kilometer kV - kilovolt LURC - land use right certificate MOLISA - Ministry of Labor, Invalid and Social Affairs MONRE - Ministry of Natural Resources and Environment m² - square meter MFF - multi-tranche financing facility NPT - National Power Transmission Corporation PIB - Public Information Brochure PIC - Project Implementation Consultants PPC - Provincial People’s Committee RCS - replacement cost study ROW - right-of-way RP - resettlement plan SPMB - Southern Vietnam Power Project Management Board SES - socioeconomic survey SPS - Safeguard Policy Statements TA - technical assistance TL - transmission line VND - Vietnam Dong (Vietnamese Currency)

Page 3: Social Monitoring Report · (as of December 2017) $1.00 = VND 22,350 ABBREVIATIONS ADB - Asian Development Bank AHs - affected households APs - affected persons CP - compensation

3

ELECTRICAL TERMINOLOGY

kV (kilovolt) 1,000 volts MW (Megawatt) 1,000 kW MVA (Megavolt-ampere) 1,000 kVA Transmission System 500 kV, 220 kV, 110 kV lines Medium Voltage Distribution (MV) 35 kV, 22 kV or 10 kV lines supplying distribution

substations Low Voltage Distribution (LV) 400/230 V distribution and service lines Load Factor Ratio of average power demand to maximum power

demand Electrical Losses Difference between energy delivered and energy

sent out

REMARKS

In this report, "$" refers to US dollars.

This social monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Page 4: Social Monitoring Report · (as of December 2017) $1.00 = VND 22,350 ABBREVIATIONS ADB - Asian Development Bank AHs - affected households APs - affected persons CP - compensation

4

Introduction and Project Overview1

Project Number and Title:

Loan 3374 - Power Transmission Investment Program - Tranche 3

Social Safeguards Category

Indigenous Peoples B

Involuntary Resettlement

A

Reporting period: October to December 2017

Last report date: 30 September 2017 (third quarterly report)

Key sub-project activities since last report:

- Pending issues in compensation payment for 3 AHs under 220 kV Vung Tau SS.

- SPMB recruit the new consultant for LIC position;

- Follow up the CAP implementation of second transfomer bank subprojects and associated facilities subprojects;

- DMS activities for 8 AH who affected by 110kV connection line to 220kV Vung Tau substation;

1 For projects categorized as A or B in Involuntary Resettlement and/or Indigenous People, the Borrowers/clients are required to submit semiannual/quarterly monitoring reports for ADB review and disclosure. This template can be used for periodic monitoring report (semiannual) and RP/REMDP/EMDP completion report to start the civil works in the impacted areas. The level of detail and comprehensiveness of a monitoring report is commensurate with the complexity and significance of social safeguards impacts (IR and IP) and with the recent status of project implementation phase. The project team can adjust the contents of the report as relevant with the project activity.

Page 5: Social Monitoring Report · (as of December 2017) $1.00 = VND 22,350 ABBREVIATIONS ADB - Asian Development Bank AHs - affected households APs - affected persons CP - compensation

5

TABLE OF CONTENTS

REMARKS ............................................................................................................................. 3

A. Executive Summary ........................................................................................................ 6

1. Public information disclosure and consultation .......................................................... 11

2. DMS process............................................................................................................. 12

3. Preparation and approval of compensation plans ...................................................... 13

4. Process of compensation payment ............................................................................ 13

5. Process of resettlement and site clearance ............................................................... 14

6. Income Restoration Program ..................................................................................... 15

1. Follow up Actions plan for the second bank subprojects ........................................... 18

2. Recommendations and Time-Bound Actions ............................................................. 25

Appendix 1 – Decision on approving coefficient plan of land price adjustment, compensation and assistance policy for land acquisition to implement 550kV My Tho-Duc Hoa TL section passing through Long Thuan Commune, Thu Thua District ................................................. 27

Decision No 4013/QĐ-UBND on approving coefficient plan of land price adjustment, compensation and assistance policy for land acquisition to implement 550kV My Tho-Duc Hoa TL section passing through Thanh Loi Commune, Ben Luc District .............................. 33

Appendix 2. List of AH who received the advance compensation ........................................ 38

Appendix 3. Payment receipt of Nguyen Van Chau ............................................................. 41

LIST OF TABLE

Table 1. List of Subprojects and Status of Social Safeguard Document Preparation .............. 7

Table 2. Scope of Impacts of the Subproject .......................................................................... 9

Table 3. Impacts on Land (m2) ............................................................................................. 10

Table 4. Consultation, Participation, and Information Disclosure by Subprojects ................. 12

Table 5. DMS Status of the Subprojects .............................................................................. 12

Table 6. General Progress in Compensation ....................................................................... 14

Table 7. General Progress in Land Clearance and Handing Over of Land for Civil Works ... 15

Table 8. Status of Safeguards-Related Loan Covenants ...................................................... 16

Table 9. Summary of shortcomings and corrective action implementation ........................... 19

Table 10. Time-bound Required Actions .............................................................................. 25

Page 6: Social Monitoring Report · (as of December 2017) $1.00 = VND 22,350 ABBREVIATIONS ADB - Asian Development Bank AHs - affected households APs - affected persons CP - compensation

6

A. Executive Summary

1. The Asian Development Bank (ADB) on 16 December 2011 approved a multi-tranche financing facility (MFF) in the amount of $730 million for the Power Transmission Investment Program (PTIP). The Vietnam Electricity National Power Transmission Corporation (NPT) is the executing agency (EA), while the Southern Power Project Management Board (SPMB) is the implementing agency (IA). ADB approved Tranche 1 in December 2011, Tranche 2 in November 2012, and Tranche 3 in December 2015.

2. Among the nine subprojects included in PTIP-Tranche 3, seven are under the management of SPMB. In which, three subprojects, namely the 500 kV My Tho-Duc Hoa Transmission Line (TL), 500 kV Duc Hoa Substation (SS), and 220 kV Vung Tau SS involve land acquisition while the four subprojects, which are the extension of (i) 220 kV Tra Vinh SS, (ii) 220 kV Uyen Hung SS, (iii) 220 kV Duc Hoa SS, and (iv) 500 kV Cau Bong SS requires the installation of second transformer within the boundary of the existing substations, thus no additional land acquisition impact is occurred.

3. As of December 2017, the subprojects of 500 kV My Tho-Duc Hoa TL and 500 kV Duc Hoa SS are identified to affect a total of 1,890.9 m2, affecting 3,005 households. In addition, the two subprojects will cause impacts on 17,396 m2 of houses and 8,162.4 m2 of secondary structures. As for 220 kV Vung Tau SS, the subproject affects 99 households (including 79 households at the substation location and 20 households by the connection line component) and acquires 36,485.8 m2. The 220 kV Vung Tau SS requires the relocation of 15 households who have already moved to the resettlement site in Ward 10 of Vung Tau City since 2016.

4. This internal social safeguard monitoring report is prepared covering the period from October to December 2017 and key activities implemented for the subprojects during the said period. These focus on the preparation of the updated Resettlement Plans (uRPs) based on the progress of DMS and consultation activities and compensation plan preparation for the affected households. Compensation payment activities under the 3 subprojects are reported as well as outstanding issues and further actions are also proposed in the report.

A. Background of the Report and Project Description

5. Recognizing the need to overcome current constraints in the power sector to ensure that the rapidly growing electricity demand could be met in an economically and environmentally sustainable manner, the Government of Viet Nam (GOV) approved in 2011 the National Power Sector Development Master Plan VII (PDMP VII). Under PDMP VII, the government approved multiple power generation and transmission projects to be implemented during 2011-2020.

6. The Asian Development Bank (ADB) on 16 December 2011 approved a multi-tranche financing facility (MFF) in the amount of $730 million for the Power Transmission Investment Program (PTIP). The Vietnam Electricity National Power Transmission Corporation (NPT) is the executing agency (EA), while the Central Power Project Management Board (CPMB) and Southern Power Project Management Board (SPMB) are the implementing agencies (IAs). ADB approved Tranche 1 in December 2011, Tranche 2 in November 2012, and Tranche 3 in June 2015. Tranche 3 is being carried out with nine subprojects, namely, the installation of a second transformer bank each for the (i) 220 kV Duc Hoa Substation (SS), (ii) 500 kV Cau Bong SS, (iii) 220 kV Tra Vinh SS, (iv) 220 kV Uyen Hung SS, and (v) 220 kV Vung Tau SS; construction of new transmission lines that include the 220 kV Binh Long-Tay Ninh Transmission Line (TL) and the 500 kV My Tho-Duc Hoa TL; and construction of new substations that include the 500 kV Chon Thanh SS and the 500 kV Duc Hoa SS and Connections. Among these subprojects, seven subprojects, namely the installation of second transformers for the 220 kV Duc Hoa SS, 500 kV Cau Bong SS, 220 kV Tra Vinh SS, 220 kV Uyen Hung SS, 220 kV Vung Tau SS and the construction of 500 kV My Tho-Duc Hoa TL and 500 kV Duc Hoa SS are under the management of SPMB whereas the remaining two subprojects are under the management of CPMB.

Page 7: Social Monitoring Report · (as of December 2017) $1.00 = VND 22,350 ABBREVIATIONS ADB - Asian Development Bank AHs - affected households APs - affected persons CP - compensation

7

7. The Project is categorized A for involuntary resettlement and B for indigenous peoples2. The social safeguards documents prepared during the preparation phase and requirements for social safeguard documents during the project implementation phase are summarized below:

Table 1. List of Subprojects and Status of Social Safeguard Document Preparation

Subproject

Social Safeguards Documents Prepared

during Preparation

Social Safeguards Documents Required in

Implementation

Status of Required Social

Safeguards Documents

Disclosure status of the

Social Safeguards Documents

Construction of 500 kV My Tho-Duc Hoa TL

2 RPs (one for each province)

Updated RPs (one for each

district)

Not yet due DMS are not complete

FS RPs disclosed on

ADB website in June 2015

Construction of 500 kV Duc Hoa SS and connection lines

1 RP for both substation and connection line

components

Updated RPs (one for the

substation and one for

connection lines)

Not yet due DMS are not complete

FS RP disclosed on ADB website

in June 2015

Extension of 220 kV Vung Tau SS*

1 RP for Vung Tau SS and 1 DDR for the

connection line

RP Addendum for the 110kV

connection line

Expected to be completed by the

end of December 2018.

FS RP and DDR disclosed on

ADB website in June 2015

Extension of 220 kV Tra Vinh SS

DDR Not required - DDR disclosed on ADB website

in June 2015

Extension of 220 kV Uyen Hung SS

DDR Not required

- DDR disclosed on ADB website

in June 2015

Extension of 220 kV Duc Hoa SS

DDR Not required

- DDR disclosed on ADB website

in June 2015

Extension of 500 kV Cau Bong SS

DDR Not required

- DDR disclosed on ADB website

in June 2015

8. It is noted that the Extension of 220kV Vung Tau SS does not involve land acquisition impacts. Social safeguard documents were prepared for Construction of 220kV Vung Tau SS-associated facility; therefore, impacts on land acquisition of 220kV Vung Tau SS will not be included in Table on Scope of impacts of Tranche 3. Results on Corrective Action Plan (CAP) and RP implementation of Vung Tau SS will be presented in corresponding sections of this report;

9. As presented in the table above, in 2015, during the project preparation phase, 4 resettlement plans and 1 due diligence report were prepared for three subprojects involved land acquisition under SPMB management. In addition, 4 DDRs were also prepared for the subprojects involved the installation of second transformer within the existing boundary of the substations.

2 Resettlement Ethnic Minority Development Plans (REMDPs) are required for the 220 kV Binh Long-Tay Ninh TL subproject under CPMB’s management whereas no REMP is required for the subprojects under SPMB’s management.

Page 8: Social Monitoring Report · (as of December 2017) $1.00 = VND 22,350 ABBREVIATIONS ADB - Asian Development Bank AHs - affected households APs - affected persons CP - compensation

8

10. During the implementation phase, based on the detailed design and detailed measurement survey (DMS) progress as well as compensation payment progress, the RPs will be updated by province or district and project as shown in the table above. Particularly for the 220 kV Vung Tau SS, due to the compensation payment which is already conducted and emergence of 28 additional affected households for the connection line, a resettlement plan addendum is therefore required for this subproject.

11. As of December 2017, the uRPs for the TL segment in Duc Hoa District in Long An Province under the 500 kV My Tho-Duc Hoa TL and Duc Hoa Substation Component under the 500 kV Duc Hoa SS and connection lines have not been prepared as the DMS has just been finished internal checking of land origins and compensation plan preparation are being conducted.

12. Internal monitoring of the subproject implementation under Tranche 3 is undertaken by SPMB with the support of Loan Implementation Consultant (LIC). The general objectives for internal monitoring are to ensure:

(i) The implementation of land acquisition and resettlement of project is in compliance with the approved Resettlement Plans, and the other safeguard documents

(ii) The availability of resources and the efficient, effective use of these resources to implement land acquisition and resettlement activities;

(iii) That resettlement institutions are well-functioning during the course of project implementation;

(iv) Resettlement activities are undertaken in accordance with the implementation schedule described in the RPs and the others safeguard documents;

(v) Identification of problems, if any, and proposal of remedial actions and solutions.

13. The internal monitoring report is submitted to NPT and ADB for review and concurrence on a quarterly and semi-annual basis. This quarterly report is prepared to cover the internal monitoring activities over the period of fourth quarter of 2017, from October to December 2017, concerning the subprojects of which the land acquisition, compensation, assistance, and resettlement activities are ongoing.

B. Scope of Impacts

14. As of December 2017, the scope of impacts of the subprojects are determined and summarized as follows:

Page 9: Social Monitoring Report · (as of December 2017) $1.00 = VND 22,350 ABBREVIATIONS ADB - Asian Development Bank AHs - affected households APs - affected persons CP - compensation

9

Table 2. Scope of Impacts of the Subproject

Subproject Total affected

area (m2) Total of AH/

organization (HHs) Impact on

houses (m2) Impact on

structures (m2) Impact on tree

(tree) Impact on crops (m2)

500 kV My Tho-Duc Hoa TL 57,057.2 1,179 5,856 - 8,731 180

Tien Giang Province 23,639.4 575 3,240 - - -

Chau Thanh District 6,441.5 218 2,040 - - -

Tan Phuoc District 17,197.9 357 1,200 - - -

Long An Province 33,417.8 604 2,616 - 8,731 180

Thanh Hoa District 6,232.9 70 180 - - -

Thu Thua District 11,299.8 132 1,380 - - -

Ben Luc District 10,742.3 229 516 - - -

Duc Hoa District 5,142.8 173 540 - 8,731 180

500 kV Duc Hoa SS and connection lines 271,422.7 1,826 11,540 8,162.4 6,631 133,626.90

Substation Component 140,590.7 32 79.7 5.8 6,631 133,626.90

Duc Hoa District 140,590.7 32 79.7 5.8 6,631 133,626.90

Connection Lines 130,832.0 1,794 11,460 8,156.6 - -

Duc Hoa District 97,820.3 1,015 9,660 8,156.6 - -

Ben Luc District 33,011.7 779 1,800 - - -

Extension of 220 kV Vung Tau SS 0 0 0 0 0 0

Extension of 220 kV Tra Vinh SS 0 0 0 0 0 0

Extension of 220 kV Uyen Hung SS 0 0 0 0 0 0

Extension of 220 kV Duc Hoa SS 0 0 0 0 0 0

Extension of 500 kV Cau Bong SS 0 0 0 0 0 0

Total 328,479.90 3,005 17,396.00 8,162.40 15,362.00 133,806.90

Source: District Land Fund Development Centers as of 31 December 2017

Notes: Data not yet finalized and updated based on the available data as of December 2017.

Page 10: Social Monitoring Report · (as of December 2017) $1.00 = VND 22,350 ABBREVIATIONS ADB - Asian Development Bank AHs - affected households APs - affected persons CP - compensation

10

15. The 2 subprojects, 500 kV My Tho-Duc Hoa TL and 500 kV Duc Hoa SS and Connection Lines affect a total of 328,479.9 m2, affecting 3,005 households. In addition, the two subprojects will cause impacts on 17,396 m2 of houses and 8,162.4 m2 of secondary structures. As DMS is ongoing and/or not yet conducted for most of the project districts, the impacts on houses and structures as well as on trees and crops are not yet available. To date, 15,362 trees of various kinds and 133,806.9 m2 of crops are affected in Duc Hoa District. The details on land impacts by district are presented in the Table 3 below.

Table 3. Impacts on Land (m2)

No. Project Component/ District Permanently acquired land area (m2)

Agricultural land Residential land Aquaculture land Forest land Others Total

I 500 kV My Tho-Duc Hoa TL 50,778.8 - - 6,278 - 57,057.2

A Tien Giang Province 21,308.5 0.0 0.0 2,330.9 0.0 23,639.4

1 Chau Thanh District 6,441.5 - - - - 6,441.5

2 Tan Phuoc District 14,867.0 - - 2,330.9 - 17,197.9

B Long An Province 29,470.3 0.0 0.0 3,947.5 0.0 33,417.8

1 Thanh Hoa District 5,414.6 - - 818.3 - 6,232.9

2 Thu Thua District 9,594.8 - - 1,705.0 - 11,299.8

3 Ben Luc District 9,318.1 - - 1,424.2 - 10,742.3

4 Duc Hoa District 5,142.8 - - - - 5,142.8

II 500 kV Duc Hoa SS and connection lines 249,663.2 8,627.6 0.0 13,131.9 0.0 271,422.7

A Substation Component 136,564.7 4,026.0 0.0 0.0 0.0 140,590.7

1 Duc Hoa District 136,564.7 4,026.0 - - - 140,590.7

B Connection Lines 113,098.5 4,601.6 0.0 13,131.9 0.0 130,832.0

1 Duc Hoa District 82,686.2 3,661.4 - 11,473 - 97,820.3

2 Ben Luc District 30,412.3 940.2 - 1,659 - 33,011.7

Total 300,442.00 8,627.60 0.00 19,409.90 0.00 328,479.90

Source: District Land Fund Development Centers as of 31 December 2017

Page 11: Social Monitoring Report · (as of December 2017) $1.00 = VND 22,350 ABBREVIATIONS ADB - Asian Development Bank AHs - affected households APs - affected persons CP - compensation

11

16. As of December 2017, the total affected land area in both subprojects are 328,479.9 m2. By land use, 300,442 m2 of these affected landholdings are agricultural land, accounting for 91.46% of the total affected land area; 8,627.6 m2 are residential land, equivalent to 2.63%; and 19,409.9 m2 are forest land, or 5.91%. The total number of severely affected households identified as of Dec 2017 is 26 households affected by the 500 kV Duc Hoa substation in Hoa Khanh Dong Commune, Duc Hoa District. The number of severely affected households, vulnerable households, and relocated households will continue being updated in the next internal monitoring reports when the data is available.

17. Vung Tau 220kV substation: the subproject affects 107 households (including 79 households at the substation location and 28 households by the 110kV connection line component) and acquires 36,485.8 m2. The 220 kV Vung Tau SS requires the relocation of 15 households who have already moved to the resettlement site in Ward 10 of Vung Tau City since 2016.

18. Four subprojects which install second transformers do not cause land acquisition impacts as well as economic impacts to any household or organization;

C. Detailed Resettlement Implementation Progress

1. Public information disclosure and consultation

19. Project information disclosure is an important task during project implementation. When this work is implemented effectively, it will facilitate project implementation process as local people will have comprehensive understanding of project information and benefits. Therefore, they will support and actively participate in the project. Project information disclosure and public consultation are aimed to: (i) increase local people’s awareness of the project; (ii) avoid the risks of project delay; (iii) design an appropriate resettlement program for APs and maximize the project’s socio-economic benefits; (iv) ensure that AP’s can really participate in making decisions on issues directly concerning their income and living standards; and (v) ensure transparency of all activities related to land acquisition, resettlement, and living restoration.

20. Public consultations have been conducted during the preparation process for all subprojects by the Project Preparation Consultant in 2015. In the implementation phase, before implementation of DMS, the DMS plan has been discussed and agreed between SPMB, District Compensation, Assistance, and Resettlement Boards (DCARBs), Commune People’s Committees (CPCs), village chiefs, representatives of local organizations and affected households and then disclosed on audio media. Women are encouraged to participate in all activities of DMS such as inventory on affected land and assets, participating in meetings to disseminate information to complete and announce the results, concerns over inventory.

21. DCARB and SPMB coordinate with the CPC have held meetings with village chiefs, representatives of mass organizations and all those affected to provide inventory form for the affected people to fill in themselves. The content of the inventory form has been explained and clarified for households to easily complete. During the DMS in 2017, also involved the participation of the party as the head of household, women, heads of villages and cadastral officials, representatives of the CPC and others. DMS outcome of each household is listed in public places (office of People Committee, the Cultural house of Village) within 07 days for households to crosscheck and edit errors.

22. Information disclosure. RPs and DDRs in English have been posted on the ADB website and the summary documents in Vietnamese have been disclosed to the affected households in 2015 for the subprojects.

Page 12: Social Monitoring Report · (as of December 2017) $1.00 = VND 22,350 ABBREVIATIONS ADB - Asian Development Bank AHs - affected households APs - affected persons CP - compensation

12

Table 4. Consultation, Participation, and Information Disclosure by Subprojects

Subproject

Participation, Consultation, Information disclosure in preparation

phase

Participation, Consultation, Information Disclosure in

implementation phase

Public consultation

Distribution of PIB

On ADB web

Public consultation

Disclosure of

uRP/DDR

500 kV My Tho-Duc Hoa TL Done Done Done Done (for some

districts) Not yet

500 kV Duc Hoa SS Done Done Done Done (for some

districts) Not yet

220 kV Vung Tau SS Done Done Done Done Ongoing

TOTAL Done Done Done - -

Source: District Land Fund Development Centers as of 31 December 2017

23. From October 2017 to December 2017, no public consultation and disclosure activities were carried out in the project area except for the issuance of relevant decisions as follows: on 3 November 2017 Long An PPC issued the Decision Number 4012/QD-UBND approving coefficient plan of land price adjustment, compensation and assistance policy for land acquisition to implement 550kV My Tho-Duc Hoa TL section passing through Long Thuan Commune, Thu Thua District and Decision Number 4013/QD-UBND approving coefficient plan of land price adjustment, compensation and assistance policy for land acquisition to implement 550kV My Tho-Duc Hoa TL section passing through Thanh Loi Commune, Ben Luc District (Refer to Annex 1 for the document). Based on these decisions, the Thu Thua and Ben Luc District Land Fund Development Centers shall prepare the draft compensation plans.

2. DMS process

24. As of December 2017, the DMS progress of the subprojects by district is as follows:

Table 5. DMS Status of the Subprojects

No. Subproject

DMS commencement

date

DMS completion

date Remarks

I 500 kV My Tho-Duc Hoa TL

1 Tien Giang Province

1.1 Chau Thanh District 10/06/2017 Ongoing Completed for DMS of AHs affected by permanent land acquisition at the tower foundations, not those within the ROW.

1.2 Tan Phuoc District 7/05/2017 Ongoing

2 Long An Province

2.1 Thanh Hoa District 01/07/2017 Ongoing

2.2 Thu Thua District 15/06/2017 20/07/2017

2.3 Ben Luc District 15/06/2017 10/09/2017

2.4 Duc Hoa District 16/07/2017 20/07/2017

II 500 kV Duc Hoa SS and connection lines

1 Substation Component

1.1 Duc Hoa District 05/06/2017 15/06/2017

2 Connection Lines Component

2.1 Duc Hoa District 20/05/2017 Ongoing

2.2 Ben Luc District 15/06/2017 Ongoing

Source: District Land Fund Development Centers as of 31 December 2017

Page 13: Social Monitoring Report · (as of December 2017) $1.00 = VND 22,350 ABBREVIATIONS ADB - Asian Development Bank AHs - affected households APs - affected persons CP - compensation

13

25. Regarding 500 kV My Tho-Duc Hoa TL, DMS has been completed for 3 districts in Long An Province whereas the DMS activities for 1 district in Long An and 2 districts in Tien Giang Province are ongoing. It is noted that the DMS activities in Tien Giang Province have been finished for the affected households subject to permanent land acquisition at the tower foundations while the DMS for the remaining households affected by restrictions on land use within the ROW has not been implemented.

26. Regarding 500 kV Duc Hoa SS and connection lines subproject, the DMS activities have been completed for the substation component in Duc Hoa District in June 2017 while the DMS for the connection lines component in Duc Hoa and Ben Luc districts are ongoing. The DMS for the connection lines components is anticipated to be completed in December 2018.

27. 5 subprojects, namely the installation of second transformers for the 220 kV Duc Hoa SS, 500 kV Cau Bong SS, 220 kV Tra Vinh SS, 220 kV Uyen Hung SS, and 220 kV Vung Tau SS do not cause impacts on land, impacts on trees and crops to any household and organization;

28. As for the 220 kV Vung Tau SS, DMS had been completed for all of the AHs in November 2015. For the 110kV connection line, there are 28 AHs, and the DMS was completed for 20 AHs but 8 AHs do not identify and SPMB posted an announcement on the Ba Ria – Vung Tau newspaper to find the owners of the affected lands (date 12, 14 and 15 August 2017) and until December 2017, no one has contacted SPMB or Vung Tau LFDC for DMS.

3. Preparation and approval of compensation plans

29. Corresponding to the DMS progress as described above, the compensation plans for the affected households has not yet been carried out;

30. Compensation plans for households affected by Vung Tau SS had been prepared, completed and approved from 2014 to the end of 2016;

31. For the connection line, the replacement cost was approved by People’s Committee of Ba Ria - Vung Tau province (Decision No.1549/QD-UBND dated June 09, 2017). CARB of Vung Tau City prepared the draft compensation plan with a provisional amount of 3,104,594,251 VN to disclose in August and submit for approval in September, 2017.

4. Process of compensation payment

32. For 500 kV My Tho-Duc Hoa TL subproject, during this reporting period, as of December 2017, no compensation activity was undertaken. However, 79 AHs received advance payment by the contractor so the construction units got their permissions to conduct advanced construction of 73 tower foundations, in Tan Phuoc (4 towers), Chau Thanh (5 towers) districts (Tien Giang province) and Thu Thua (27 towers), Thanh Hoa (7 towers), Duc Hoa (10 towers) and Ben Luc (20 towers) district in Long An; the total of advance is VND 20,036,173,500 (Please see Annex 2 for summary of compensation payment).

33. The advance payment procedures are as follows:

- The contractor has coordinated with the local authorities to meet with the affected households and disseminate to the household the reason for construction prior to compensation, negotiate on advanced payment for land and assets recovered by foundations. Negotiation on advanced payment is based on acquired land area, affected assets, provincial compensation rates and AH’s opinions;

- Once the agreement of the household has been reached, the contractor shall make a minute of advance payment and pay to the household. In the advance payment minute, the contractor also stated that this was only the advance; compensation payment will be made when the official compensation plan is approved in accordance with the PTIP policies.

- The 79 households commit to repay the advanced amount when receiving fully compensation according to the project policies.

Page 14: Social Monitoring Report · (as of December 2017) $1.00 = VND 22,350 ABBREVIATIONS ADB - Asian Development Bank AHs - affected households APs - affected persons CP - compensation

14

- The construction of tower foundations is only carried out after the advance payment is completed to the affected households.

34. As of the monitoring period, such activities have been stopped. The payments made will be assessed vis-à-vis requirements of the project resettlement policy in the uRPs which are currently being prepared. Corrective actions required will be included in the uRP as well. Land acquisition and resettlement activities will only proceed once the uRPs have been concurred by ADB. Construction activities will only proceed once compensation and assistance payments have been completed and rehabilitation measures are in place, and there are no more encumbrances in the site.

35. For 500 kV Duc Hoa SS and connection lines, the compensation payment has not yet been carried out as of December 2017.

36. For 220kV Vung Tau SS, compensation payment for households affected by SS and access road had been completed in the end of 2016; Compensation payment for households affected by 110kV connection lines has been conducted in December 2017: Site clearance has been conducted for 17 AHs received compensation and land has been handed over for 110kV connections line to 220kV Vung Tau SS. 03 AHs have not yet been paid compensation (as the land owners could not be contacted).

Table 6. General Progress in Compensation

No.

Project Component/ Location

AHs (APs) eligible for compensation and/or assistance/allowances

Total Number of AHs (APs)

Number of AHs (APs) received advance

compensation

Advance compensatio

n payment amount

Number of AHs (APs)

fully paid

% Progress

I 500 kV My Tho-Duc Hoa TL

1,179 79 1,535,305,500 0 0%

1 Tien Giang Province 575 15 120,000,000 0 0%

1.1 Chau Thanh District 218 11 N/A 0 0%

1.2 Tan Phuoc District 357 4 120,000,000 0 0%

2 Long An Province 604 64 1,415,305,500 0 0%

2.1 Thanh Hoa District 70 7 194,165,000 0 0%

2.2 Thu Thua District 132 20 352,705,500 0 0%

2.3 Ben Luc District 229 31 868,435,000 0 0%

2.4 Duc Hoa District 173 6 0 0%

II 500 kV Duc Hoa SS and connection lines

1,826 0 0 0 0%

1 Substation Component 32 0 0 0 0%

1.1 Duc Hoa District 32 0 0 0 0%

2 Connection Lines Component

1,794 0 0 0 0%

2.1 Duc Hoa District 1,015 0 0 0 0%

2.2 Ben Luc District 779 0 0 0 0%

Source: District Land Fund Development Centers as of 31 December 2017

5. Process of resettlement and site clearance

37. For 500kV My Tho-Duc Hoa TL, in this reporting period, 9,739.5m2 of additional land area has been handed over to construction units in Chau Thanh District and Tan Phuoc District

Page 15: Social Monitoring Report · (as of December 2017) $1.00 = VND 22,350 ABBREVIATIONS ADB - Asian Development Bank AHs - affected households APs - affected persons CP - compensation

15

of Tien Giang Province and Thu Thua District, Thanh Hoa District of Long An Province. Therefore, as of the end of December 2017, cumulative amount of land handed over was 11,630.40m2;

Table 7. General Progress in Land Clearance and Handing Over of Land for Civil Works

Project Component/

Location

Province/ District

Total affected

land area (m2)

Land handed over (m2) Land that still has to be acquired/handed over

(m2) Land Handed over this reporting

period

Cumulative amount of land handed over

Amount in m2

% of total affected

land

Amount in m2

% of total affected

land

500 kV My Tho-Duc Hoa TL

57,057.20 9,739.50 11,630.40 20% 45,426.80 80%

Tien Giang Province

23,639.40 4,562.00 4,562.00 19% 19,077.40 81%

Chau Thanh District

6,441.50 636.00 636.00 10% 5,805.50 90%

Tan Phuoc District 17,197.90 3,926.00 3,926.00 23% 13,271.90 77%

Long An Province

33,417.80 5,177.50 7,068.40 21% 26,349.40 79%

Thanh Hoa District 6,232.90 2,791.10 3,488.80 56% 2,744.10 44%

Thu Thua District 11,299.80 2,386.40 3,579.60 32% 7,720.20 68%

Ben Luc District 10,742.30 0.00 0.00 85% 10,742.30 100%

Duc Hoa District 5,142.80 0.00 0.00 0% 5,142.80 100%

500 kV Duc Hoa SS and connection lines

271,422.70 0.00 0.00 0% 271,422.70 100%

Substation component

140,590.70 0.00 0.00 0% 0 0%

Duc Hoa District 140,590.70 0.00 0.00 0% 140,590.70 100%

Connection lines component

130,832.00 0.00 0.00 0% 130,832.00 100%

Duc Hoa District 97,820.30 0.00 0.00 0% 97,820.30 100%

Ben Luc District 33,011.70 0.00 0.00 0% 33,011.70 100%

TOTAL 328,479.90 9,739.50 11,630.40 4% 316,849.50 96%

Source: District Land Fund Development Centers as of 31 December 2017

38. For 500kV Duc Hoa SS, as of December 31, 2017, land acquisition has not yet been carried out.

6. Income Restoration Program

39. The project is classified category A for Involuntary Resettlement and C for Indigenous People because there is no ethnic minority present in the project area of all subprojects under SPMB management. Severely affected households including those losing 10% and above of their productive landholdings and relocating households as well as vulnerable households are entitled to participate in the Income Restoration Program (IRP) of the Project. The IRP will be prepared during the RP updating. The finalization and progress of the IRP will be included in the next monitoring report.

Page 16: Social Monitoring Report · (as of December 2017) $1.00 = VND 22,350 ABBREVIATIONS ADB - Asian Development Bank AHs - affected households APs - affected persons CP - compensation

16

D. Operation of Grievance Redress Mechanism (GRM)

40. A grievance mechanism has been set up to help ensure that the complaints of AHs are resolved in a timely and satisfactory manner. Through the holding of consultations during RP preparation and implementation, including the distribution of PIBs, the AHs have been and will be made fully aware of their rights to file a complaint, as needed. The resolution of a complaint will pass through 3 stages, beginning with the commune, then the district, then the provincial level of the People’s Committee before it is elevated to a court of law as a last resort. The NPT will shoulder all administrative costs and legal fees incurred in the resolution of grievances.

41. As of the monitoring period, there is no complaint recorded from the affected households.

E. Institutional Matters and Capacity Training

42. In order to ensure the compliance of the project with regard to the implementation of safeguard policies of ADB, since the beginning time of project preparation stage, the SPMB has assigned an officer who take responsible for social safeguard policy issues, including social and land acquisition and environment with support of the Loan Implementation Consultant. In addition, for each subproject, SPMB has assigned additional staff to be responsible for land acquisition activities on site. However, due to the termination of the individual consultant contract (LIC), SPMB has encountered certain difficulties in monitoring activities as well as preparation of the internal monitoring reports. SPMB is in the process of recruiting a replacement of the LIC Consultant and it is expected that the new contract will be signed in July 2018.

F. Compliance Status

43. The table below summarizes the compliance status of the project activities with the loan covenants, 2009 ADB SPS on SR2 and SP3 and the approved RPs.

Table 8. Status of Safeguards-Related Loan Covenants

Covenant LA Reference Status

The Borrower shall cause NPT to ensure that all land and all rights-of-way required for the project are made available to the Works contractor in accordance with the schedule agreed under the related Works contract and all land acquisition and resettlement activities are implemented in compliance with: (a) the Borrower’s applicable laws and regulations relating to land acquisition and involuntary resettlement; (b) the Involuntary Resettlement Safeguards; and (c) all measures and requirements set forth in the RPs, REMDPs, and DDRS, and any corrective or preventative actions set forth in the Safeguards Monitoring Report.

LA, Schedule 5, Para 3

Being complied

(Advance compensation payments have been stopped. Updated resettlement plans shall be prepared including corrective actions. LAR activities will only proceed once the uRPs are concurred by ADB and construction activities will only proceed when compensation and assistance payments have been completed and rehabilitation measures are in place)

The Borrower shall cause NPT to ensure (a) that the local authorities do not commence any land acquisition and relocation activities until the uRPs, REMDPs, and DDRs (as applicable) have been prepared following detailed design, and (b) that the uRPs, REMDPs, and DDRs have been reviewed and approved by ADB. The Borrower shall cause NPT to further ensure that the APs are compensated at replacement cost and assisted before they are displaced from their houses, land, and assets. No APs shall be

LA, Schedule 5, Para 4

(a) Partially complied

(corrective actions have been prepared and advance compensation payment activities at some tower foundations have been stopped)

(b) Being complied

Page 17: Social Monitoring Report · (as of December 2017) $1.00 = VND 22,350 ABBREVIATIONS ADB - Asian Development Bank AHs - affected households APs - affected persons CP - compensation

17

displaced until suitable alternative land within the same or neighboring commune has been allocated to them or compensation has been paid that is sufficient to purchase suitable alternative land within the same or a neighboring commune.

(uRPs shall be prepared covering the valuation results carried out by the independent valuation consulting company to ensure that APs are compensated at replacement cost. Affected households will be compensated and assisted before they are displaced from their houses, land and assets)

The Borrower shall cause NPT to carry out internal monitoring of involuntary resettlement activities and updating of the RPs, REMDPs, and DDRs, and submit quarterly Safeguard Monitoring Reports to ADB together with the quarterly Project reporting requirements. The Borrower shall cause NPT to ensure that an independent external monitoring body or person is engaged. External monitoring reports shall be submitted to ADB every 6 months. Internal and external monitoring reports shall be uploaded onto the ADB website, until involuntary resettlement and income restoration programs are completed. The monitoring reports shall include resettlement audit statements and shall be verified by such independent resettlement monitoring body or person.

LA, Schedule 5, Para 5

Being complied.

(Internal and external monitoring activities are ongoing. Although LIC contract has been terminated, internal monitoring is undertaken by SPMB while SPMB is actively seeking solution to find a replacement for the LIC position)

Without limiting the application of the Involuntary Resettlement Safeguards or the RPs, REMDPs, and DDRs, the Borrower shall cause NPT to ensure that no physical or economic displacement takes place in connection with the project until compensation and other entitlements have been provided to the APs in accordance with the RPs, REMDPs, and DDRs; and a comprehensive income and livelihood restoration program has been established in accordance with the RPs, REMDPs, and DDRs.

LA, Schedule 5, Para 6

Being complied

(uRPs shall be prepared with the provisions/ requirements to ensure that no displacement takes place until compensation and other entitlements have been provided to the APs. Advance compensation payment has been stopped and LAR activities as well as construction shall not proceed until the uRPs are concurred by ADB and compensation and assistance payments have been completed and rehabilitation measures are in place).

The Borrower shall cause NPT to make available necessary budgetary and human resources to fully implement the EMPs, the CAPs, RPs, REMDPs, and DDRs.

LA, Schedule 5, Para 8

Being complied

(Available necessary budgetary and human resources are being arranged by NPT/SPMB)

Page 18: Social Monitoring Report · (as of December 2017) $1.00 = VND 22,350 ABBREVIATIONS ADB - Asian Development Bank AHs - affected households APs - affected persons CP - compensation

18

The Borrower shall cause NPT to ensure that all bidding documents and contracts for Works contain provisions that require contractors to: comply with the measures relevant to the contractor set forth in the IEEs, the EMPs, the CAPs, RPs, REMDPs, and DDRs and any corrective or preventive actions set forth in a Safeguards Monitoring Report; make available a budget for all such environmental and social measures; and provide NPT with a written notice of any unanticipated environmental, resettlement, or indigenous peoples risks or impacts that arise during construction, implementation, or operation of the project that were not considered in the IEEs, the EMPs, the CAPs, the RPs, the REMDPs, or the DDRs.

LA, Schedule 5, Para 9

Being complied

(Civil work contracts shall include provisions to ensure compliance with the relevant measures in RPs, DDRs, and corrective actions set forth)

The Borrower shall cause NPT to do the following: submit Safeguards Monitoring Reports to ADB quarterly during construction and semi-annually during project operation until the project completion and disclose relevant information from such reports to the APs promptly upon submission. If any unanticipated environmental and/or social risks and impacts arise during construction, implementation or operation of the project that were not considered in the IEEs, EMPs, CAPs, RPs, REMDPs, DDRs, and REMDF, as applicable, promptly inform ADB of the occurrence of such risks or impacts, with detailed description of the event and proposed corrective action plan.

LA, Schedule 5, Para 10

Being complied

(SMRs of Quarter 3 and Quarter 4 of 2017 and Second semiannual report 2017 have been prepared and submitted)

G. Follow up Actions, Recommendation and Disclosure

1. Follow up Actions plan for the second bank subprojects

44. 4 DDRs including 4 CAPs were also prepared for the subprojects involved the installation of second transformer within the existing boundary of the substations as mentioned above. As of December 2017, CAPs are being implemented and the results are summarized in the table below.

Page 19: Social Monitoring Report · (as of December 2017) $1.00 = VND 22,350 ABBREVIATIONS ADB - Asian Development Bank AHs - affected households APs - affected persons CP - compensation

19

Table 9. Summary of shortcomings and corrective action implementation

Areas of Concerns Gaps in the 2013 implementation of

land acquisition vis-à-vis PTIP resettlement policy

Corrective actions Implementation status Remark

I. INSTALLATION OF A SECOND TRANSFORMER BANK FOR 220 KV DUC HOA SUBSTATION

Missing signatures in the DMS records

The DMS records lacked the signature of the DMS group leader (4 forms), representative of the AHs (2 forms) and representative of Duc Hoa District DONRE (11 forms)

(i) Review the cited DMS forms to ensure that details of affected assets and entitlements in said forms are consistent with the approved compensation plans and compensation payment vouchers.

(ii) Ensure that the compensation plans and compensation payment vouchers of the 2 AHs that did not sign the DMS forms included the signatures of the household heads

- By comparison, it stated that the number of DMS assets which has been taken into calculation are adequate.

- The signature of affected households are available in DMS records

Completed

Identification of vulnerable households

The DMS did not determine who among the AHs belonged to one or more of the following vulnerable groups (i.e., women-headed AH with dependents, landless and poor AH, AH headed by a disabled person or by an elderly, ethnic minority AH). Per PTIP resettlement policy, a vulnerable AH is entitled to additional assistance to help improve the social and economic condition of the household

i) Determine who among the 12 AHs were vulnerable.

(ii) Prepare supplementary payment vouchers or plans for the vulnerable AH for approval by the PPC.

(iii) Pay supplementary allowance to the vulnerable AHs

No vulnerable households found Completed

Payment for life stabilization assistance

Losing 30% of one’s total agricultural (productive) land was used in determining who were severely affected. Only 1 AH was deemed severely affected and for which it was provided life stabilization assistance

(i) Review all DMs forms to find out which among the remaining 11 AHs lost 10%-29% of their total agricultural (productive) land.

(ii) Prepare payment vouchers or plans for AHs that lost 10%-29% of their total

Among 11 households, 6 households are losing more than 10% total of productive land area and not yet received the life stabilization assistance

SPMB will request the Compensation department to coordinate with Tan My commune

Page 20: Social Monitoring Report · (as of December 2017) $1.00 = VND 22,350 ABBREVIATIONS ADB - Asian Development Bank AHs - affected households APs - affected persons CP - compensation

20

Areas of Concerns Gaps in the 2013 implementation of

land acquisition vis-à-vis PTIP resettlement policy

Corrective actions Implementation status Remark

agricultural (productive) land for approval by the PPC.

(iii) Pay life stabilization assistance to the eligible AHs

conduct the survey on the total of land holding of AHs

II. INSTALLATION OF A SECOND TRANSFORMER BANK FOR 500 KB CAU BONG SUBSTATION

Identification of vulnerable affected households

The DMS did not determine who among the AHs belonged to one or more of the following vulnerable groups (i.e., women-headed AH with dependents, landless and poor AH, AH headed by a disabled person or by an elderly, ethnic minority AH). Per PTIP resettlement policy, a vulnerable AH is entitled to additional assistance to help improve the social and economic condition of the household.

(i) Determine who among the 158 AHs (i.e., 120 permanent loss of land, and 38 affected by land use restrictions) were vulnerable.

(ii) Prepare supplementary payment vouchers or plans for the vulnerable AH for approval by HCMCPC.

(iii) Provide supplementary assistance to the vulnerable AHs

No vulnerable affected households found completed

Payment for life stabilization assistance

Losing 30% or more of one’s total agricultural (productive) land was used for determining who were severely affected. 33 AHs (i.e., 13 lost 30% - 70%, and 20 lost more than 70% of productive lands) were deemed severely affected and for which they were provided life stabilization assistance

(i) Review all DMS forms to find out which among the remaining 87 AHs lost 10%-29% of their total agricultural (productive) land.

(ii) Prepare payment vouchers or plans for AHs that lost 10%-29% of their total agricultural (productive) land for approval by HCMCPC.

(iii) Pay life stabilization assistance to the eligible AHs

There are 32 household losing more than 10% total of productive land area but not yet received life stabilization assistance

SPMB will request the Compensation department to coordinate with Tan Phu Trung commune conduct the survey on the total of land holding of AHs

III. INSTALLATION OF A SECOND TRANSFORMER BANK FOR 220 KV TRA VINH SUBSTATION

Payment for life stabilization assistance

Losing 30% or more of one’s total agricultural (productive) land was used for determining who were severely

(i) Review the DMS forms of the remaining 5 AHs to find out who among them lost

There are 2 AHs losing more than 10% total of productive land area but not yet received life stabilization assistance

SPMB will request the Compensation

Page 21: Social Monitoring Report · (as of December 2017) $1.00 = VND 22,350 ABBREVIATIONS ADB - Asian Development Bank AHs - affected households APs - affected persons CP - compensation

21

Areas of Concerns Gaps in the 2013 implementation of

land acquisition vis-à-vis PTIP resettlement policy

Corrective actions Implementation status Remark

impacted and thus eligible to get life stabilization assistance. Six AHs (i.e., lost 30% or more of productive lands) were deemed severely affected. PTIP resettlement policy sets the benchmark for determining who are severely impacted at 10% loss of an AH’s total productive assets

10%-29% of their total agricultural (productive) land.

(ii) Prepare payment vouchers or plans for AHs that lost 10%-29% of their total agricultural (productive) landholdings for approval by the PPC.

(iii) Pay life stabilization assistance to the eligible AHs

department to coordinate with Tra Vinh town conduct the survey on the total of land holding of AHs

IV. INSTALLATION OF A SECOND TRANSFORMER BANK FOR 220 KV UYEN HUNG SUBSTATION

Un-resolved complaint of the AH

The extended delay in the resolution of the complaint of the AP is not consistent with the intent and spirit of the grievance redress process that calls for the speedy resolution of complaints

(i) Elevate the complaint of the AP to the PPC for resolution.

(ii) If the complaint is not resolved at the PPC level, bring the matter to the People’s Court for adjudication

- Consultation meetings with HH have been organized on 12/09/2012, 15/11/2012; 21/11/2012 but they were absent

- On 29th November 2012, HH has submitted complaints to the SPMB, the compliant stated ‘ If our land in use acquired is still the perennial agricultural land, it is kindly requested to conduct compensation as per unit rate of agricultural land and reproductive assistance as well as life stabilization allowance based on new decision of PPC in 2012”

- On 17th December 2012, SPMB has issued official letter no. 7548/AMN-DB to response to complaints of Mr Nguyen Chau Tri HH

- On 26th March 2013, direct discussion meeting with Mr Nguyen Chau Tri has been conducted at headquarter of Tan Uyen District People’s Committee.

Currently compensation cost has been transferred to the Bank account

Till now, the SPMB has not yet received any information stated that Mr Nguyen Chau submits complaint to PPC or brings the matter the Court for adjudication;

Will contact with Uyen Hung district and follow up this case;

Page 22: Social Monitoring Report · (as of December 2017) $1.00 = VND 22,350 ABBREVIATIONS ADB - Asian Development Bank AHs - affected households APs - affected persons CP - compensation

22

Areas of Concerns Gaps in the 2013 implementation of

land acquisition vis-à-vis PTIP resettlement policy

Corrective actions Implementation status Remark

V. 220 KV BA RIA – VUNG TAU TRANSMISSION LINE

Identification of vulnerable AHs

The DMS did not determine who among the AHs belonged to one or more of the vulnerable groups (i.e., women-headed AH with dependents, landless and poor AH, AH headed by a disabled person or by an elderly, ethnic minority AH). Per PTIP resettlement policy, a vulnerable AH is entitled to additional assistance to help improve the social and economic condition of the household.

(i) Determine who among the 140 AHs were vulnerable.

(ii) Prepare supplementary payment vouchers or plans for the vulnerable AH for approval by the PPC.

(iii) Pay supplementary allowance to the vulnerable AHs.

No vulnerable affected households found completed

Payment of life stabilization assistance

Losing 30% or more of one’s total agricultural (productive) land was used for determining who were severely affected. Eight AHs (i.e., lost 30% or more of productive lands) were deemed severely affected and for which they were provided life stabilization assistance.

(i) Review all DMs forms to find out which among the other 132 AHs lost 10%-29% of their total agricultural (productive) land.

(ii) Prepare payment vouchers or plans for AHs that lost 10%-29% of their total agricultural (productive) land for approval by the PPC.

(iii) Pay life stabilization assistance to the eligible AHs.

There are not any households who acquired more than 10% of total agricultural land;

completed

Compensation given to AHs

The DMS was completed in 2008, but preparation of compensation plans and payment of compensation was carried out over an extended period of time, from 2009 to 2014, depending on the availability of government funds. The CPs of AHs might not have been updated to reflect changes in fixed assets found on the affected lands (subsequent to the 2008 DMS) and the unit rates used to

(i) Review each CP of the 140 AHs and find when it was approved and when was compensation actually paid.

(ii) Regarding the matter of accuracy of affected assets found on the recovered land, check if the AH signed the CP in agreement

(ii) Regarding the unit rates used, if the period of approval of the CP and actual

(i) 140 AHs were fully received compensation;

(ii) Checking compensation documents, it was known that all AHs signed the CP.

(iii) 11 households were compensated more than one year after the compensation plan was approved . However, this is not the fault of the employer but rather the households. Therefore, there is no need to consider additional prices for

completed

Page 23: Social Monitoring Report · (as of December 2017) $1.00 = VND 22,350 ABBREVIATIONS ADB - Asian Development Bank AHs - affected households APs - affected persons CP - compensation

23

Areas of Concerns Gaps in the 2013 implementation of

land acquisition vis-à-vis PTIP resettlement policy

Corrective actions Implementation status Remark

calculate compensation for affected assets might not have been adjusted to reflect prevailing market rates at the time of payment of compensation.

payment of compensation was more than 1 year, compute compensation deficits for project-acquired assets (i.e., land, trees, crops, structures) due to inflation using consumer price index (CPI) at the time compensation was actually paid.

(iii) Prepare payment vouchers for approval by the PPC.

(iii) Pay compensation deficits to eligible AHs.

these households. The reasons for late payment are:

- Waiting to receive payment for affected households within the ROW: 4 AHs (AHs are affected by both foundation and ROW. The compensation plan was prepared for the foundation first; then prepared for ROW);

- Provide legal document late (LURC mortgaged in the bank): 4 AHs;

- compensation is not a big amount so the households are slow to receive: 2 AHs;

- Waiting to adjust the compensation plan, due to wrong information initially provided 1 AHs.

All AHs signed in the compensation documents (DMS, compensation plan, payment slip.

Incomplete land acquisition process

7 AHs with agricultural lands in the TL ROW were belatedly located in 2014. The DMS forms of these AHs have since been forwarded to authorities in their respective wards for the preparation of their CPs.

(i) Finalize the CPs of the 7 AHs for approval by the PPC

(ii) Pay compensation (assistance) to the 7 AHs.

The compensation plan was prepared and paid to 1 AH.

The compensation plans for 6 AHs are under preparation because CARB is collecting legal documents (land was sold many owners)

Follow-up status of preparing the compensation plans for 6 AHs

Incomplete DMS forms

The DMS forms of 6 AHs lacked the signatures of the affected households.

(i) Compare the amounts indicated in the respective DMS forms of the 6 AHs vis-à-vis the amounts indicated in their respective CPs and payment vouchers.

(ii) If there was a deficit in the amounts paid to the AHs vis-à-vis what were paid the AHs, confirm that the AHs were aware of and agree to the shortfall.

The signature of affected households is available in DMS records.

Completed

Page 24: Social Monitoring Report · (as of December 2017) $1.00 = VND 22,350 ABBREVIATIONS ADB - Asian Development Bank AHs - affected households APs - affected persons CP - compensation

24

Areas of Concerns Gaps in the 2013 implementation of

land acquisition vis-à-vis PTIP resettlement policy

Corrective actions Implementation status Remark

CAP for 500 kV My Tho Substation

Resolution of complaint of the AH

AH initially refused the compensation. To date a new compensation plan is prepared for the AH by Chau Thanh District LFDC.

Complete the new compensation plan and fully provide the AH with their compensation and assistances. .

New compensation plan of Nguyen Van Chau had been completed and the compensation amount of VND 205,599,760 was paid to AH. (see Appendix 3).

No complain to be found out.

Completed

Page 25: Social Monitoring Report · (as of December 2017) $1.00 = VND 22,350 ABBREVIATIONS ADB - Asian Development Bank AHs - affected households APs - affected persons CP - compensation

25

2. Recommendations and Time-Bound Actions

45. The termination of the LIC Consultant has affected the preparation of updated social safeguards documents as well as the implementation of internal monitoring activities. It is recommended that SPMB to accelerate the recruitment process to have a new consultant on board in July 2018.

46. DMS activities and compensation plans are available in the project districts in Long An Province under the 500 kV My Tho-Duc Hoa TL, the preparation of the uRPs for these districts should be carried out to ensure full compliance with process and procedure of the project on implementation of compensation, assistance, and resettlement. SPMB needs to cooperate closely with the DCARBs and CPCs to ensure that compensation procedures are in compliance with the regulations of the project policies.

47. As for the 220 kV Vung Tau Subproject, the compensation payment has been completed for 17 out of 28 AHs under the connection line component. The remaining 3 AHs are not yet provided with compensation due to several transactional activities, leading to the issue that the right land owners eligible to the compensation payment have not been identified. SPMB in close coordination with Vung Tau Land Fund Development Center and the local ward authorities should accelerate the identification of land owners via public announcement for identified 8 AHs who are affected by the 110 kV Vung Tau connection line, which is identified as a part of the phase-1 220 kV Vung Tau SS. Therefore, RP addendum will be prepared covering all of these 28 households, as they have to be compensated in line with project resettlement policy.

Table 10. Time-bound Required Actions

No. Issues Required Actions Responsibility Completion Time

1 Termination of LIC Consultant and replacement

Accelerate the recruitment of new consultant

SPMB July 2018

2

Preparation of uRPs for the districts where DMS and compensation plans are available. IRP for eligible households included in the uRPs.

Prepare and finalize the uRPs to submit to NPT and ADB for review and concurrence

SPMB, LIC By end of September 2018

3

Pending payment of 3 AHs under the connection line component

Identify the land owners eligible to the payment

SPMB, LIC, Vung Tau Land Fund Development Center, Ward People’s Committee

Identification of land owners- by end of September 2018

4 Issues of 8 AHs under 220 kV Vung Tau connection lines

Prepare Resettlement Plan Addendum of the 28 AHs

SPMB, LIC October 2018

5 Issues of CAP for 220kV Ba Ria - Vung Tau TL

SPMB to provide documentation to prove that compensation has been adequately paid to the 7 AHs

SPMB, LIC December 2018

6 Issues of CAP for Tra Vinh substation

There are 2 AHs losing more than 10% total of productive land area but not yet received life stabilization assistance;

SPMB, LIC December 2018

7 Issues of CAP for Uyen Hung substations

Follow up the complaint resolve

SPMB, LIC December 2018

Page 26: Social Monitoring Report · (as of December 2017) $1.00 = VND 22,350 ABBREVIATIONS ADB - Asian Development Bank AHs - affected households APs - affected persons CP - compensation

26

8 500 kV My Tho Substation

SPMB to provide documentation to prove that new compensation plan was completed and compensation were paid to the AHs

SPMB, LIC Completed

9 Vung Tau Substation

Review of all approved CPs and all compensation and allowances that have already been

provided to the AHs for the purpose of ensuring that the entitlements applied for all AHs are according to the

provisions of the PTIP resettlement policy.

SPMB, LIC Quarter 1, 2019

Page 27: Social Monitoring Report · (as of December 2017) $1.00 = VND 22,350 ABBREVIATIONS ADB - Asian Development Bank AHs - affected households APs - affected persons CP - compensation

27

Appendix 1 – Decision on approving coefficient plan of land price adjustment,

compensation and assistance policy for land acquisition to implement 550kV My Tho-

Duc Hoa TL section passing through Long Thuan Commune, Thu Thua District

Page 28: Social Monitoring Report · (as of December 2017) $1.00 = VND 22,350 ABBREVIATIONS ADB - Asian Development Bank AHs - affected households APs - affected persons CP - compensation

28

Page 29: Social Monitoring Report · (as of December 2017) $1.00 = VND 22,350 ABBREVIATIONS ADB - Asian Development Bank AHs - affected households APs - affected persons CP - compensation

29

Page 30: Social Monitoring Report · (as of December 2017) $1.00 = VND 22,350 ABBREVIATIONS ADB - Asian Development Bank AHs - affected households APs - affected persons CP - compensation

30

Page 31: Social Monitoring Report · (as of December 2017) $1.00 = VND 22,350 ABBREVIATIONS ADB - Asian Development Bank AHs - affected households APs - affected persons CP - compensation

31

English translation:

Coefficient plan of land price adjustment, compensation and assistance policy for land

acquisition to implement 550kV My Tho-Duc Hoa TL section passing through Long

Thuan Commune, Thu Thua District

Land types

Provincial rates according to Long An PPC’s Decision No. 60

(VND/m2)

Coefficient

(time)

Rural residential land

Provincial road 817 (Vam Thu-Binh Hoa Tay) (section from Vam Thu Bridge to Ba Giai Bridge)

The first 50m close to the road or the plot which is not close to the road but owned by the same land owner of the plot which is close to the road

700,000 1.393

Rural road larger than or equal to 3m covered with red stones and green gravel

The first 50m close to the road or the plot which is not close to the road but owned by the same land owner of the plot which is close to the road

250,000 1.448

The first 50m not close to the road and not owned by the same land owner of the plot close to the road; the first 50m close to the canal

200,000 1.475

Vam Co Tay River

The first 50m close to the river or the plot which is not close to the river but owned by the same land owner of the plot which is close to the river

200,000 1.550

The section after the 100th meter for the provincial road 817 (Vam Thu-Binh Hoa Tay); from the 50th meter for the rural road; from the 50th meter for Vam Co Tay river; and the remaining section (inside)

200,000 1.475

Internal road of the residential area Cau Day 1, Long Thuan 500,000 1.440

Agricultural land

Provincial road 817 (Vam Thu-Binh Hoa Tay) (section from Vam Thu Bridge to Ba Giai Bridge)

The first 50m close to the road or the plot which is not close to the road but owned by the same land owner of the plot which is close to the road

60,000 4.583

The first 50m not close to the road and not owned by the same land owned of the plot which is close to the road

45,000 4.289

Section from the 50th meter to the 100th meter for the provincial road

45,000 2.00

Rural road larger than or equal to 3m covered with red stones and green gravel

The first 50m close to the road or the plot which is not close to the road but owned by the same land owner of the plot which is close to the road

35,000 2.486

Page 32: Social Monitoring Report · (as of December 2017) $1.00 = VND 22,350 ABBREVIATIONS ADB - Asian Development Bank AHs - affected households APs - affected persons CP - compensation

32

Land types

Provincial rates according to Long An PPC’s Decision No. 60

(VND/m2)

Coefficient

(time)

The first 50m not close to the road and not owned by the same land owner of the plot close to the road; the first 50m close to the canal

35,000 2.000

Vam Co Tay River

The first 50m close to the river or the plot which is not close to the river but owned by the same land owner of the plot which is close to the river

50,000 2.000

The section after the 100th meter for the provincial road 817 (Vam Thu-Binh Hoa Tay); from the 50th meter for the rural road; from the 50th meter for Vam Co Tay river; and the remaining section (inside)

35,000 2.000

Page 33: Social Monitoring Report · (as of December 2017) $1.00 = VND 22,350 ABBREVIATIONS ADB - Asian Development Bank AHs - affected households APs - affected persons CP - compensation

33

Decision No 4013/QĐ-UBND on approving coefficient plan of land price adjustment,

compensation and assistance policy for land acquisition to implement 550kV My Tho-

Duc Hoa TL section passing through Thanh Loi Commune, Ben Luc District

Page 34: Social Monitoring Report · (as of December 2017) $1.00 = VND 22,350 ABBREVIATIONS ADB - Asian Development Bank AHs - affected households APs - affected persons CP - compensation

34

Page 35: Social Monitoring Report · (as of December 2017) $1.00 = VND 22,350 ABBREVIATIONS ADB - Asian Development Bank AHs - affected households APs - affected persons CP - compensation

35

Page 36: Social Monitoring Report · (as of December 2017) $1.00 = VND 22,350 ABBREVIATIONS ADB - Asian Development Bank AHs - affected households APs - affected persons CP - compensation

36

Page 37: Social Monitoring Report · (as of December 2017) $1.00 = VND 22,350 ABBREVIATIONS ADB - Asian Development Bank AHs - affected households APs - affected persons CP - compensation

37

English translation

Land types

Provincial rates according to Long An PPC’s Decision

No. 60 (VND/m2)

Coefficient

(time)

Rural residential land

Provincial road 816 (section from Vam Thu Doan to Duc Hue)

The first 50m close to the road or the plot which is not close to the road but owned by the same land owner of the plot which is close to the road

350,000 3.43

The first 50m not close to the road and not owned by the same land owner of the plot close to the road

245,000 3.43

Inside section 120,000 3.05

Agricultural land

National Road N2

The first 50m close to the road or the plot which is not close to the road but owned by the same land owner of the plot which is close to the road

108,000 13.83

The first 50m not close to the road and not owned by the same land owned of the plot which is close to the road

90,000 11.62

Section from the 50th meter to the 100th meter 90,000 6.64

Provincial road 816 (Vam Thu Doan-Duc Hue section)

The first 50m close to the road or the plot which is not close to the road but owned by the same land owner of the plot which is close to the road

108,000 7.73

The first 50m not close to the road and not owned by the same land owner of the plot close to the road

90,000 6.49

Section from the 50th meter to the 100th meter 90,000 3.71

Inside, close to the canal, close to the canal road

Land planted to perennial and annual crops 50,000 1.82

Forest land and aquaculture land 35,000 2.16

Page 38: Social Monitoring Report · (as of December 2017) $1.00 = VND 22,350 ABBREVIATIONS ADB - Asian Development Bank AHs - affected households APs - affected persons CP - compensation

38

Appendix 2. List of AH who received the advance compensation

List of AH who received the advance compensation

(Project: 500kV My Tho - Duc Hoa Transmission line)

No. Location Time of

payment Household head

Compensation Amount (VND)

Note

I Thanh Loi Commune, Ben Luc District, Long An Province 968,235,000

1 T83 April, 2017 Nguyễn Văn Linh

50,000,000

2 T86 April, 2017 Lê Thị Lá

100,000,000

3 T87 April, 2017 Nguyễn Minh Long

30,000,000

4 T88

August, 2017

Nguyên Văn Ba

24,500,000

5 August,

2017 Nguyễn.T.Kiều Nga

20,000,000

6 T92 May, 2017 Võ Văn Nhạt

46,400,000

7 T93

July, 2017 Trân Khăc Chung

15,000,000

8 July, 2017 Nguyên.T.N.Dung

27,000,000

9 T94

May, 2017 Lê Thi Thu Dung

18,400,000

10 May, 2017 Nguyễn Văn Vũ

16,750,000

11

T95

May, 2017 Huynh Văn Khanh

65,450,000

12 May, 2017 Huynh Văn Tuân

22,400,000

13 June, 2017 Huynh Hữu Như

33,600,000

14

T96

April, 2017 Nguyên Thi Châu

45,500,000

15 April, 2017 Vo Thanh Nhân

3,850,000

16 T97

April, 2017 Nguyên Văn Đi nh

10,000,000

17 April, 2017 Nguyên Văn Thơ

18,500,000

18 T98

May, 2017 Huynh Văn Cường (Chín Dậu) 30,000,000

19 May, 2017 Nguyên Văn Lâm 23,500,000

20

T99

May, 2017 La Diêu Vinh 20,500,000

21 May, 2017

Nguyên Văn Rinh 67,300,000

22 Ha Thi Gai

23 T 102 April, 2017 Nguyên Thi Ngào 55,520,000

24 T103 June, 2017 Trân Thi Thi a

13,700,000

25 T106 April, 2017 Nguyên Nhât Lênh

30,000,000

Page 39: Social Monitoring Report · (as of December 2017) $1.00 = VND 22,350 ABBREVIATIONS ADB - Asian Development Bank AHs - affected households APs - affected persons CP - compensation

39

26 April, 2017 Nguyên Ngoc Khai

3,365,000

27 T107

April, 2017 Nguyên Văn Lợi

40,000,000

28 April, 2017 Thái Thị Dung

23,000,000

29 T108 May, 2017 Hô Văn Đực

12,000,000

30 T109 May, 2017 Tri nh Thi Nữa

12,000,000

31 T110 April, 2017 Nguyên Văn Ha

90,000,000

II Duc Hoa District, Long An Province 166,068,000

II.1 Huu Thanh Commune, Duc Hoa District, Long An Province

32 T101 April, 2017 Nguyên Văn Thênh 36,548,000

33 T102 April, 2017 Nguyên Thi Ngào 55,520,000

34 T103 May, 2017 Trân Thi Thi a 20,000,000

35 T104

April, 2017 Phạm Thị Nga 20,000,000

36 April, 2017 Nguyên Văn Bởi 14,000,000

II.2 Hoa Khanh Dong Commune, Duc Hoa District, Long An Province

37 T111 April, 2017 Nguyên Văn Nôi 20,000,000

III Thu Thua District, Long An Province 352,705,500

III.1 Long Thuan Commune, Thu Thua District, Long An Province

38 T60 February,

2017 Nguyễn Văn Tất 19,500,000

39

T61

March, 2017 Trần Văn Niềm 22,000,000

40 March, 2017 Trần Văn Mừng 11,500,000

41 March, 2017 Trịnh Văn Hải 1,900,000

42 T62 March, 2017 Trần Văn Kỳ 26,000,000

43 T63 April, 2017 Phạm Thị Dầy 21,420,000

44 T64 March, 2017 Nguyễn Văn Thành 16,800,000

45 T65 March, 2017 Nguyễn Văn Thái 21,840,000

46 T66 March, 2017 Lê Văn Đê 19,700,000

47 T67 April, 2017 Đỗ Thành Nguyên 27,810,000

48 T68 April, 2017 Trần Thị Thu Hải 18,000,000

49 T69 March, 2017 Đỗ Quốc Trưởng 18,060,000

50 T70 March, 2017 Nguyễn Thị Sáu 18,060,000

51 T71 March, 2017 Hà Thanh Tùng 18,438,000

52 T72

April, 2017 Đặng Thanh Tuấn 16,730,000

53 April, 2017 Đặng Thanh Dũng 3,000,000

54 T73 March, 2017 Lê Dũng Chinh 22,260,000

55 T74 April, 2017 Ngô Đỗ Chánh 19,687,500

56 T04 April, 2017 Lê Thị Lợi 30,000,000

III.2 Tan Lap Commune, Thu Thua District, Long An Province

57

T75 Waste Treatment Company Land managed by CPC, do not pay

compensation T76 Waste Treatment Company

T77 Waste Treatment Company

Page 40: Social Monitoring Report · (as of December 2017) $1.00 = VND 22,350 ABBREVIATIONS ADB - Asian Development Bank AHs - affected households APs - affected persons CP - compensation

40

T78 Waste Treatment Company

T79 Waste Treatment Company

T80 Waste Treatment Company

T81 Waste Treatment Company

T82 Waste Treatment Company

IV Tan Tay Commune, Thanh Hoa District, Long An Province 194,165,000

58 T45 May, 2017 Nguyễn Văn Ngang 30,000,000

59 T46 April, 2017 Trần Văn Năm 20,965,000

60 T47 April, 2017 Nguyễn Văn Lăng 25,200,000

61 T48 April, 2017 Nguyễn Duy Thành 24,000,000

62 T49 April, 2017 Nguyễn Trung Hiếu 20,000,000

63 T51 April, 2017 Ngô Hoàng Lâm 20,000,000

64 T52 April, 2017 Dương Văn Ức 54,000,000

V Tan Phuoc District, Tien Giang Province 120,000,000

V.1 Phuoc Lap Commune, Tan Phuoc District, Tien Giang Province

65 T19 June, 2017 Nguyễn Văn Loan 50,000,000

66 T20

June, 2017 Phan Văn Phở 15,000,000

67 June, 2017 Phan Văn Linh 40,000,000

V.2 Tan Hoa Dong Commune, Tan Phuoc District, Tien Giang Province

68 T36 June, 2017 Nguyễn Thị Bé Tư 15,000,000

VI Diem Hy Commune, Chau Thanh District, Tien Giang Province 235,000,000

69

T05

March, 2017 Đồng Văn Hồng 20,000,000

70 March, 2017 Nguyễn Thanh Hùng 20,000,000

71 March, 2017 Nguyễn Văn Lý 4,000,000

72 T06

April, 2017 Phạm Văn Quang 20,000,000

73 April, 2017 Trần Văn Điền 1,000,000

74 T07 April, 2017 Huỳnh Thị Phượng 20,000,000

75

T09

March, 2017 Nguyễn Văn Châu 15,000,000

76 March, 2017 Nguyễn Văn Hùng 25,000,000

77 March, 2017 Nguyễn Văn Bợ 10,000,000

78 T10 April, 2017 Nguyễn Văn Phương 30,000,000

79 T10 April, 2017 Phạm Văn Sáng 70,000,000

Total 2,036,173,500

Page 41: Social Monitoring Report · (as of December 2017) $1.00 = VND 22,350 ABBREVIATIONS ADB - Asian Development Bank AHs - affected households APs - affected persons CP - compensation

41

Appendix 3. Payment receipt of Nguyen Van Chau

Page 42: Social Monitoring Report · (as of December 2017) $1.00 = VND 22,350 ABBREVIATIONS ADB - Asian Development Bank AHs - affected households APs - affected persons CP - compensation

42

English translation:

SOCIALIST REPUBLIC OF VIETNAM

Independence – Freedom - Happiness

Tien Giang Province, 2nd June 2015

RECIEPT AND COMMITMENT

On Compensation payment

Project: 500kV My Tho substation and connection line

Pursuant to Decision No.5418/QD-UBND dated October 06, 2014 by Chau Thanh DPC on approving compensation plan and cost estimates on compensation, assistance for 500kV My Tho substation and connection line project in Chau Thanh District, Tien Giang Province.

Owner receiving compensation: Nguyen Văn Chau

ID card: 310866221 dated September 07, 2007 issued by Tien Giang Police.

Address: Duong Diem Commune

I received compensation amount of: VND 205,599,760

(Two hundred and five million, five hundred and ninty nine thousand, seven hundred and sixty dong).

On amount of compensation, assistance for loss (land, crops, structuresi) for site clearance to construct 500kV My Tho SS and connection lines project.

I pledge to comply with the provisions of the Decree No.14/2014/ND-CP dated February 02, 2014by Government of Vietnam on stipulating in detail of Electricity Law regarding electricity safety upon the construction of high-voltage grid.

After receiving compensation, I pledge to comply with compensation plan and compensation decision approved by competent agency. If I do not comply with the commitments, I will take full responsibility before the law.

Officer in charge of payment

SPMB (signed)

OWNER RECEIVING PAYMENT (signed)

CONFIRMATION OF CPC (signed and sealed)

ON BEHALF OF DIRECTOR Vice director

(signed and sealed)