social monitoring report pak: punjab irrigation agriculture ......gazette on july 11, 2014 and july...
TRANSCRIPT
Social Monitoring Report
March 2016
PAK: Punjab Irrigation Agriculture Investment Project – New Khanki Barrage Project Loan 2841
Internal Resettlement Monitoring Report
Prepared by the Project Management Office (PMO) for Punjab Barrages, Irrigation Department,
Punjab for the Asian Development Bank (ADB).
The social monitoring report is a document of the borrower. The views expressed herein do not
necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature.
In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
GOVERNMENT OF THE PUNJAB
IRRIGATION DEPARTMENT
New Khanki Barrage Project (NKBP)
ADB Loan No. 2841-PAK
Internal Resettlement Monitoring Report
(LCC Lead Channel Component)
For
Quarter January- March 2016
PROJECT MANAGEMENT OFFICE (PMO) FOR PUNJAB BARRAGES
IRRIGATION DEPARTMENT CANAL BANK MUSTAFABAD,
Lahore.
NKBP Internal Resettlement Monitoring Report
PMO For Punjab Barrages
New Khanki Barrage Project (NKBP)
Internal Resettlement Monitoring Report for the Quarter January -March 2016
1. LAND ACQUISITION AND RESETTLEMENT PLAN (LARP)
The project is category B for i volu tary resettle e t a d category C for i dige ous people. Draft Land Acquisition and Resettlement Plan (LARP) for New Khanki Barrage was
prepared and submitted to ADB for approval. ADB cleared the draft LARP on July 07, 2012.
LARP was revised/ updated and cleared by ADB in Feb 2014. Land Acquisition is in progress
according to requirement of Land Acquisition Act 1894. A total of 8.6 acres of land was
required for construction of Head Regulator and Head Reach of the new LCC. Section 4 and
section 5 of Land Acquisition Act for 8.6 acres of land were notified and published in the
Punjab Gazette on August 07, 2012 and January 21, 2013 respectively. Land price was
assessed, and the EA released the total amount Rs. 9.925 million to the Revenue
Department, Government of the Punjab.
However, due to change in engineering design, it was found that only 4.58 acres out of 8.6
acres of land was required along with a new piece of land 1 acre, 6 kanal, 3 marlas, and 4.5
Sarsai. Due to this change, process of land acquisition was re-initiated. The section 4 & 5 of
land Acquisition Act 1894 for additional land was notified and published in the Punjab
Gazette on July 11, 2014 and July 29, 2015 respectively.
Again due to change in engineering design of LCC Lead Channel, the procedure for acquiring
5 kanal, 10 Marla of private land from one landowner (Mr. Farooq Akbar Cheema) is still in
process. Compensation rates have been re-calculated to reflect current values and
procedures. The landowner has received full payment for crop losses, trees and structures.
The five affected families which are residing at the Dera of landowner, now they are shifted
in their new accommodation built by the landowner on his remaining land. Their livelihoods
remain unaffected. These households have received their relocation allowance (Pak Rupees
5,000/household) and cash assistance for vulnerable households (Pak Rupees72, 000/-
household). Alternative accommodation for the 15 no. of the affected families of Irrigation
staff is also being constructed and out of 15 No. AFs, 13 are shifted in new buildings. Funds
for the remaining compensation activities are available. All compensation payment of 6.625
acres land and relocation of the 02 affected households will be completed by June 2016.
LARP implementation activities for Tranche-2 relates to LCC Lead Channel (Component) of
New Khanki Barrage Project. Internal Resettlement Monitoring of all relevant activities is the
responsibility of PMO (Environment and Social Unit (ESU). Internal Monitoring Reports in
the shape of QPR are being regularly submitted to the Bank. PMO has selected an
NKBP Internal Resettlement Monitoring Report
PMO For Punjab Barrages
independent resettlement monitor (IM) to cover all tranches of the MFF. He has signed the
contract agreement with PMO and PMO has sent to the ADB for approval which is still
awaited. The IM will be mobilized by May 2016 and is expected to submit his first external
resettlement monitoring report by July 01, 2016.
ESU / PMO for Punjab Barrages is busy in Implementation of LARP since 2012.
The Implementation Schedule of LARP is given below:
Sr.
No.
Action Time Line Responsibility To date Status
1 Establishment of PMO - PID PMO is already in place
at Lahore.
2 Setting-up the ESU. In place
PMO ESU is already in place.
3 Setting-up the LIU at Khanki 30 June, 2012
PMO Notified
4 Establish Grievance Redress Cell. 30 Sep, 2012 PMO Notified.
5 Submission of draft LARP to ADB 30 June, 2012 PMO Submitted
6 Approval of LARP 15 June, 2012 ADB Cleared
7 Urdu translation and disclosure of
LARP
05 July, 2012 PD/ ESU Also paste at website
8 Formation of DPs Consultation
Committees (2 Nos.)
30 Jun 2012 LIU Formed and notified.
9 Deployment of Supervisory
Consultants
30 Sep. 2012 PMO Deployed
10 Deployment of Social & Environment 31 Dec 2012 PMO Deployed
11 Employment to DPs/ locals (age of
economic group)
June 2013 to
March 2017
Contractor/
Consultants/PMO
A list of willing and
potential DPs/ locals is
included in LARP. Also
given to DESCON
(Contractor) for action.
12 IMR submission before handing over
Barrage site for construction
31 Oct, 2012 PMO Done
13 NTP for Barrage - ADB Done
NKBP Internal Resettlement Monitoring Report
PMO For Punjab Barrages
14 Construction of Link LCC 30 Jun. 2016 Contractor/ PMO To be completed up to
30 Jun, 2016.
Land Acquisition
15 Section-4 Notification Dec. 2015 LAC Due to new / revised
drawing of LCC in
September 2015
16 Section-5 Notification January-2016 LAC Section 5 is cleared form
LAC and will be published
before April 15, 2016
17 Land Acquisition Process through
Private Negotiation
-- -- Not Applicable
18 LARP Updation Oct. 2015 Consultant LARP discussed with the
ADB representatives on
October 07, 2015.
19 Payment to DPs (Partial Payment) July 2015 Land owner/
PMO
100% payment has
released to land owner,
laborers are shifted in
alternate location at
nearby place.
20 Relocation of Farming labourers Dec., 2015 Land owner/Agri.
Labourers PMO
Farming laborers are
shifted in newly
constructed
accommodation by the
land owner.
21 Final payment to land owner after
confirmation by IM that labourers
have been relocated and paid as in
LARP.
May 2016 PMO Final payment of the land
will be made before
June, 2016 to the land
owner after confirmation
by the IM.
22 Possession/ Transfer of Land May 2016 LAC/ PMO Expected in the month of
May, 2016.
23 Relocation/ Construction of Staff
Colony
Dec. 2015 PMO Thirteen quarters are
completed and staff
shifted while two
quarters are under
constructions. After
construction remaining
will be shifted.
24 Relocation/ shifting of PID staff Dec. 2015 Residents/ PMO Thirteen shifted in new
accommodations while
two will be shifted
NKBP Internal Resettlement Monitoring Report
PMO For Punjab Barrages
after completion of
residences.
25 Construction of Community Lined
Watercourses
30 Jun 2016 Contractor/ PMO After completion of high
level channel W/C will be
lined and connected.
26 Construction of Lined Public
Watercourse
30 Jun 2016 Contractor/ PMO Construction will be
completed before June,
2016.
27 Construction of High Level Channel 30 June 2016 Contractor/ PMO -
28 Date of contract award (expected) 30 Sept.,
2012
PMO -
29 Full Implementation of LARP Dec. 2016 PMO -
30 IMR confirming LARP
implementation
Dec. 2016 IM Specialist/
PMO
-
31 Commencement of civil works Subject to
ADB approval
for NTP.
ADB Subject to ADB approval
on the satisfactory
implementation of LARP.
32 Redress of Community Complaints Continuous
activity
GRC/ PMO Ongoing activity till
project completion.
Total amount under LARP is Rs. 18.05 Million. Out of which, Rs. 13.446 is payable to Project
Affected Persons (PAPs) for their compensation and assistance. Rs. 9.925 Million has already
been paid to the Revenue Department for land Acquisition. Rupees 4.175 million have been
paid to the 21 No. of affected families as compensation amount for their structures, crop
compensation, Tubewell, hand pumps and trees. The vulnerability allowance & shifting
allowance is also paid. The detail is given in Annex-A & A-I.
2. ADJUSTMENT MADE IN THE COMPENSATION RATE DURING UPDATING OF
LARP
The LARP of New Khanki Barrage was approved in 2012. Again, it was updated and approved in
2014. The adjustment was made in compensation rates of the land after certification by the Revenue
Department, Government of Punjab.
The rates are still applicable up till now. The adjustment made in the compensation is given
in Annex-B.
NKBP Internal Resettlement Monitoring Report
PMO For Punjab Barrages
3. EMPLOYMENT FOR THE AFFECTED HOUSEHOLDS IN PROJECT RELATED
JOBS
Two types of affected families are residing at LCC Lead Channel. First are Irrigation Department
Employees and they are already serving in Irrigation Department. Second are the land owner and his
agriculture laborers, those are cultivating crops. They shifted in newly built houses. The Contractor is
ready to accommodate the affected families for jobs as and when they demand. ESU, PMO Punjab
Barrages requested to the Consultants to ask the Contractor to provide jobs under the project. As
per recommendation of the Engineer, the Contractor trace each of the person included in the list,
(The list of the potential persons of affected families requiring jobs under the project). The
Contractor offered them an appropriate employment. Out of 16 affected persons, only 3 residents of
Irrigation Colony were willing for jobs with the Contractor and the Contractor hired their services.
The Contractor also offered jobs to the family members of employees of Irrigation Department of
Khanki Division. Out of 26 applications, 20 family members of Irrigation staff were offered jobs and
the Contractor hired their services under the Project. Regarding employment to the unskilled labor
of the local area, the status of skilled and un-skilled labor employment for the month of January,
February and March, 2016 is given in Annex-C, D & E, which is 62%, 61% and 62 %
respectively.
4. RELOCATION OF AFFECTED HOUSEHOLDS AND THEIR CURRENT LIVING
CONDITION
Total Twenty One (21) affected families (AFs) are to be dislocated from LCC Lead Channel
Component of New Khanki Barrage Project. In first phase, land owner and his five (05) Agri-laborers
are relocated and an amount of Pak Rupees 4.10 million has been paid to the six (06) no. of affected
families as the compensation amount for their structure and other assets. During the quarter, the
shifting allowance amounting to PKR .075 million has been paid to 15 No of irrigation staff. Crop
compensation for 2.125 acre (remaining land) and private trees (100%) paid to Mr. Farooq Akbar
Cheema vide cheque No. 44598144 dated 07-12-2015. Out of Fifteen (15) No. of affected families of
Irrigation Department Employees 13 No. of families have been shifted to the newly constructed
residences. The remaining 02 No. of families shall be shifted in the month of May, 2016.
The owner of the land has built a new Dera along with the residences for the laborers. 05
No. of Agri. Laborers have been shifted in their new residences. Before and after
comparison of residences shall be presented in next quarterly report.
NKBP Internal Resettlement Monitoring Report
PMO For Punjab Barrages
Case No.1
Mr. Farooq Akbar Cheema is the only land owner fall in category of affected household. His land,
trees and residential structures were affected due to NKBP. A compensation payment of amounting
Pak Rs. 2.806 million was paid for crops, tube well, hand pumps, trees (fruit and timber trees) and
structures. Old status of land and structure can be viewed as under: The comparison of old and new
structures will be presented in next quarterly report.
Case No.2
Mr. Muhammad Anwar is the farm laborer of Mr. Farooq Akbar Cheema. He has been shifted to the
new constructed house by the land owner. He has collected an amount of Rs. 77,000/- as
compensation /poverty allowance and relocation allowance
Mr. Muhammad Anwar is standing in front of his house
NKBP Internal Resettlement Monitoring Report
PMO For Punjab Barrages
Case No.3
Mr. Amanat Ali is the farm laborer of Mr. Farooq Akbar Cheema. He has been shifted in the newly
constructed house by the land owner. He has obtained an amount of Rs. 77,000/- as compensation
/poverty allowance and relocation allowance.
Case No.4
Mr. Manzoor Hussain is the farm laborer of the Mr. Farooq Akbar Cheema. He built the residential
structure at the land of land owner. He has been shifted in newly constructed house and he has
obtained amount of Rs. 986,100/- as compensation for his structure, 1 No. hand pump, poverty
allowance and relocation allowance.
NKBP Internal Resettlement Monitoring Report
PMO For Punjab Barrages
Mr. Manzoor Hussainis standing near his dismantled house
Case No.5
Mr. Anayat Muhammad is the farm laborer of Mr. Farooq Akbar Cheema. He has been shifted in the
newly constructed house by the land owner. He has obtained an amount of Rs. 77,000/- as
compensation /poverty allowance and relocation allowance.
NKBP Internal Resettlement Monitoring Report
PMO For Punjab Barrages
Mr. Anayat Muhammad is standing near his dismantled house
Case No.6
Mr. Muhammad Ramzan is the farm laborer of Mr. Farooq Akbar Cheema. He has been shifted to
the newly constructed house by the land owner. He has obtained an amount of Rs. 77,000/- as
compensation /poverty allowance and relocation allowance.
Mr. Muhammad Ramzanis standing near his dismantled house
NKBP Internal Resettlement Monitoring Report
PMO For Punjab Barrages
Irrigation Employees
Out of fifteen Irrigation Employees, 13 No. have been shifted to their new residences constructed
under New Khanki Barrage Project. The remaining 2 No. of Irrigation employees shall be shifted to
their new residences in the month of May 2016.
Case No.7
Mr. Abdul Hameed (Guage Reader) is employee of the Irrigation Department and he was residing at
RoW of LCC Lead Chanel of NKBP. He has been relocated to newly allotted building in Canal
Colony Khanki and he has obtained Rs. 5,000/- as relocation / shifting allowance.
Case No. 7. Mr. Abdul Hameed (Guage Reader) with his family at current residence.
Case No.8
Mr. Muhammad Mansha (Beldar) is employee of the Irrigation Department and he was residing at
RoW of LCC Lead Chanel of NKBP. He has been relocated to newly allotted building in Canal
Colony Khanki and he has obtained Rs. 5,000/- as relocation / shifting allowance.
NKBP Internal Resettlement Monitoring Report
PMO For Punjab Barrages
Case No.9
Mr. Ghulam Abbas (Chowkidar) is employee of the Irrigation Department and he was residing at
RoW of LCC Lead Chanel of NKBP. He has been relocated to newly allotted building in Canal
Colony Khanki and he has obtained Rs. 5,000/- as relocation / shifting allowance.
Case No.10
Mr. Faisal Mehmood (NaibQasid) is employee of the Irrigation Department and he was residing at
RoW of LCC Lead Chanel of NKBP. He has been relocated to newly allotted building in Canal
Colony Khanki and he has obtained Rs. 5,000/- as relocation / shifting allowance.
NKBP Internal Resettlement Monitoring Report
PMO For Punjab Barrages
Case No.11
Mr. Muhammad Akram (Regulation Beldar) is employee of the Irrigation Department and he was
residing at Row of LCC Lead Chanel of NKBP. He has been relocated to newly allotted building in
Canal Colony Khanki and he has obtained Rs. 5,000/- as relocation / shifting allowance.
Case No.12
Mr. Muhammad Riaz (Boatman) is employee of the Irrigation Department and he was residing at
RoW of LCC Lead Chanel of NKBP. He has been relocated to newly allotted building in Canal
Colony Khanki and he has obtained Rs. 5,000/- as relocation / shifting allowance.
NKBP Internal Resettlement Monitoring Report
PMO For Punjab Barrages
Case No.13
Mr. Liaqat Ali (Regulation Beldar) is employee of the Irrigation Department and he was residing at
RoW of LCC Lead Chanel of NKBP. He has been relocated to newly allotted building in Canal
Colony Khanki and he has obtained Rs. 5,000/- as relocation / shifting allowance.
Case No.14
Mr. WalayatHussain (Head Boatman) is employee of the Irrigation Department and he was residing at
RoW of LCC Lead Chanel of NKBP. He has been relocated to newly allotted building in Canal
Colony Khanki and he has obtained Rs. 5,000/- as relocation / shifting allowance.
NKBP Internal Resettlement Monitoring Report
PMO For Punjab Barrages
Case No.15
Mr. Muhammad Shabbir is Irrigation Beldar and he is shifted in newly allotted building. He has
NKBP Internal Resettlement Monitoring Report
PMO For Punjab Barrages
obtained relocation allowance of Rs. 5,000/-. Mr. Muhammad Shabbir (Beldar) is standing in front of
his old residence. The comparison of old and new structures will be presented in next quarterly
report.
Case No.16
Mr. Muhammad Mushtaq (Beldar) is living in Government residence that needs to be relocated at
the earliest. He will be relocated to new allotted building and he has obtained relocation allowance
of Rs. 5,000/-.Mr. Muhammad Mushtaq (Beldar) is standing in front of his old residence. The
comparison of old and new structures will be presented in next quarterly report.
Case No.17
Mr. Ashraf Masih (Sweeper) has been relocated to the new residence and he has obtained relocation
allowance of Rs. 5,000/-. He is standing in front of his old residence. The comparison of old and new
structures will be presented in next quarterly report.
NKBP Internal Resettlement Monitoring Report
PMO For Punjab Barrages
Case No.18
Mr. Amanat Ali (Painter) has been shifted to newly constructed residence and he has obtained
relocation allowance of Rs. 5,000/-.) He is standing in front of his old residence. The comparison of
old and new structures will be presented in next quarterly report.
Case No.19
Mr. SibtUl Hassan (Sub Engineer) has been shifted to the newly constructed residence and he has
obtained relocation allowance of Rs. 5,000/-.) He is standing in front of his old residence. The
comparison of old and new structures will be presented in next quarterly report.
NKBP Internal Resettlement Monitoring Report
PMO For Punjab Barrages
Case No.20
Mr. Rana Ayub ((Sub Engineer)) is living in Govt. residence although his residence has been
completed. Rana will be shifted to newly constructed house next month due to the examinations of
his childrens.) RanaAyub is standing in front of his old residence. The comparison of old and new
structures will be presented in next quarterly report.
Case No.21
Mr. Muhammad Shabir (Sub Engineer) has been shifted to newly constructed residence and he has
obtained relocation allowance of Rs. 5,000/-.) Muhammad Shabbir is standing in front of his old
residence. The comparison of old and new structures will be presented in next quarterly report.
NKBP Internal Resettlement Monitoring Report
PMO For Punjab Barrages
5. GRIEVENCE REDRESSAL MECHANISM
Tranche-2 also has an operational Grievance Redressal Mechanism that covers all types of
grievances of NKBP, including resettlement. Complaint register is also being maintained by
the Consultants to record community concerns and their solutions. Out of 29 complaints, 25
complaints have been resolved while 4 complaints are yet to be resolved. The detail of
complaints is given in Annex-F.
6. COMMUNITY WORKS
A high school is constructed under the New Khanki Barrage Project. The construction work was
started on February 10, 2014 and work was completed on September 15, 2015. Total cost of the
project is Rs. 25.588 million. The school is handed over to the Education Department, Gujranwala.
Basic Health Unit (BHU) is constructed under the New Khanki Barrage Project. The construction work
was started on February 23, 2014 and work was completed on December 10, 2015. Total cost of the
project is Rs. 47.521 million. The Basic Health Unit is handed over to the Health Department,
Gujranwala.
NKBP Internal Resettlement Monitoring Report
PMO For Punjab Barrages
Annex –A
Implementation of LARP for New Khanki Barrage as of March 2016
Contract No. 2841-PAK
Sr.
N
o
Contract
No.
Status of
Preparatio
n, vetting
and
approval
of RP
No
. of
AF
s
Paymen
t Due
(PKR in
millions)
Tota
l AFs
paid
Amount
Paid
(PKR in
millions)
%
Impleme
ntation
%
Amount
Paid Remarks
1 2841-PAK
LARP for
LCC Lead
Channel
Component
(under
NKBP)
Draft LARP
of LCC Lead
Channel
was
prepared
and
approved
in 2012.
Later on
LARP was
revised,
updated
and
cleared by
ADB in Feb,
2014
21 13.446 21 4.175 95% 31.05 Cost of 6.625 acres @
1,200,000 is
amounting to Rs.
7,950,000 while PMO
has deposited Rs.
9.925 (million) to the
Revenue Department
for further payment to
the land owner.
Whole the payment of
land will be paid
before June, 2016
NKBP Internal Resettlement Monitoring Report
PMO For Punjab Barrages
New Khanki Barrage Construction Project (NKBP)
Compensation and Allowances paid as of March 31, 2016
Sr. # Registration Name Residential Crop
Coversation T/Well
Hand
Pump
Relocation
Assistance Trees
Vulnerability
Allowance Total
1 NKBP/LCC-1 FAROOQ AKBER
CHEEMA 1,678,724 821,500 148,000 20,000 5,000 132,600 2,805,824
2 NKBP/LCC-2 MUHAMMAD ANWER 5,000 72,000 77,000
3 NKBP/LCC-3 AMANAT ALI 5,000 72,000 77,000
4 NKBP/LCC-4 MANZOOR HUSSAIN 899,100 10,000 5,000 72,000 986,100
5 NKBP/LCC-5 ANAYAT
MUHAMMAD 5,000 72,000 77,000
6 NKBP/LCC-6 M.RAMZAN 5,000 72,000 77,000
7 NKBP/LCC-7 SHABIR AHMED 5,000 5,000
8 NKBP/LCC-8 SIBTUL HASSAN
CHEEMA 5,000 5,000
9 NKBP/LCC-9 MUHAMMAD
MANSHA 5,000 5,000
10 NKBP/LCC-10 LIAQAT ALI 5,000 5,000
Annex (A-I)
NKBP Internal Resettlement Monitoring Report
PMO For Punjab Barrages
New Khanki Barrage Construction Project (NKBP)
Compensation and Allowances paid as of March 31, 2016
Sr. # Registration Name Residential Crop
Coversation T/Well
Hand
Pump
Relocation
Assistance Trees
Vulnerability
Allowance Total
11 NKBP/LCC-11 MUHAMMAD AKRAM 5,000 5,000
12 NKBP/LCC-12 MUHAMMAD SHABIR 5,000 5,000
13 NKBP/LCC-13 MUSHTAQ AHMAD 5,000 5,000
14 NKBP/LCC-14 MUHAMMAD
WILLAYAT 5,000 5,000
15 NKBP/LCC-15 MUHAMMAD RIAZ 5,000 5,000
16 NKBP/LCC-16 MUHAMMAD AYUB 5,000 5,000
17 NKBP/LCC-17 ABDUL HAMEED 5,000 5,000
18 NKBP/LCC-18 GHULAM ABBAS 5,000 5,000
19 NKBP/LCC-19 FAISAL MEHMOOD 5,000 5,000
20 NKBP/LCC-20 AMANAT ALI 5,000 5,000
21 NKBP/LCC-21 ASHRAF MASEEH 5,000 5,000
4,174,924
Annex (A-I)
NKBP Internal Resettlement Monitoring Report
PMO For Punjab Barrages
Adjustment made in Compensation Rates in LARP July, 2014
Annex - B
Sr. No.
Description Unit Unit Rate of LARP 2012
Unit Rate of updated LARP
2014 Remarks
A) Mouza -Wise Acquisition of Private Land
I) Khanki Acres 0.474(Rs.Million) 1.2(Rs. Million)
The rates of
2012 were not applicable in
2014 so, after Consultation with Revenue
and Agriculture Department,
rate for land and crop
compensation were updated, while rates for structures and,
other i.e. Tree
compensation and livelihood assistance are
still applicable in 2015-16.
Therefore, there is no much changes
recognized for D, E, F and G
up till now.
B) Land Acquisition Compulsory Surcharge (15%)
- - -
C) Crop Compensation
Rabi Acres 32,236 42,000
Kharif Acres 54,373 82,000
D) Residential Structures (Houses)
Sq. ft. Rs.675/sqft Rs.675/sqft
- i) Pacca structure Sq. ft. - - - ii) Semi-Pacca structures - Sq. ft. - - - iii) Katcha/ thatched shed - Sq. ft. - -
E) Others - - - i) Cattle Yard Sq. ft. Rs.675/sqft Rs.675/sqft
ii) Borehole of a tube well / drilling
No 148000/ bore 148000/ bore
iii) Hand pump No 0.01 0.01
Cost of W/C 1 community ,Private
Meters 1445/m 1445/m
F) Tree Compensation
Fruit Trees
No 4208.33 4208.33
Timber wood trees
No 1663.16 1663.16
G) Livelihood Assistance - -
- Livelihood assistance to vulnerable families
- - -
a) impassion cash assistance /allowance equivalent to 6 months OPL adjustment amount , i.e.(Rs. 12000)
DFs 0.072 0.072
b) Relocation assistance Rs. 5000/- to be paid all the DPs requiring to move out of the ROW or Land acquired for the Project
DFs 0.005 0.005
NKBP Internal Resettlement Monitoring Report
PMO For Punjab Barrages
1- List of Potential Persons of Displaced Families (DFs) Requiring Jobs under the
Project
Sr.
No Name Father's Name
Father's
Designation
Age
(Years) Education Remarks
1
Mr. Muhammad
Nadeem Abdul Hameed Gurge Reader 21 Middle Out of Country
2
Mr. Muhammad
Sufian
Muhammad
Mansha Baildar 21 Middle Out of Country
3 Mr. Akhtar Ali
Muhammad
Mansha Baildar 21 Matric Out of Country
4 Mr. Paris Ali WalayatHussain
Head Boat
Man 24 Middle Not Willing
5 Mr. Rahat Ali WalayatHussain
Head Boat
Man 27 Middle
Hired
in year 2014-15
6
Ms. Rizwana
(female) W/O Pans Ali
Head Boat
Man 26
Intermedia
te Not Required
7 Mr. WaseemAkram
Muhammad
Akram Baildar 28 Middle
Hired
in year 2014-15
8 Mr. HusnanAkram
Muhammad
Akram Baildar 23 Middle
Hired
in year 2014-15
9 Mr. AhsanUllah Liaqat Ali Baildar 24 Middle Out of Country
10 Mr. ShafkatMushtaq Mustaq Ahmad
Head Boat
Man 21 Matric Not Willing
11
Mr.
MubasherSarfraz Malik Sarfraz Sub Engineer 22 M.Com Not Willing
2- Potential Persons available for Job from 5 Vulnerable DFs at DeraFarooq Akbar
Cheema, Village Khanki
Sr.
No Name Father's Name
Father's
Designation
Age
(Years) Education Remarks
1
Mr. Muhammad
Mustafa
MuanzoorHussa
in
Agricultural-
Labourer 25 Illiterate
Called for joining
but not joined
yet
2
Mr. Muhammad
Sarwar
Muhammad
Anayat
Agricultural-
Labourer 25 Illiterate
Called for joining
but not joined
yet
3 Mr. Ali Raza
Muhammad
Akram
Agricultural-
Labourer 23 Illiterate Migrate
4
Mr. Muhammad
Ramzan
Muhammad
Anayat
Agricultural-
Labourer 35 Illiterate Migrate
5 Mr. GhulamMurtaza Amanat Ali
Agricultural-
Labourer 21 Illiterate Migrate
Annex-C
NKBP Internal Resettlement Monitoring Report
PMO For Punjab Barrages
Application of employees sons of khanki division
Irrigation Department for Employment in DESCON Annex-D
Sr. No Name of
Applicant Father's Name
Father's
Designation
Post Applied
For Remarks
1 WaseemAkram Muhammad
Akram Signaler Helper Hired
2 Salman Niaz Muhammad Niaz Security Guard Safty Helper
3 Muhammad
Afzaal Muhammad Riaz Boatman Helper Hired
4 Faisal Iqbal Muhammad
Ashraf
Regulation
Jamadar Helper Hired
5 Muqarrab Ali Muhammad
Ashraf Guage Reader Helper Hired
6 Muhammad
Rehan GhulamRabbani Oil Man Helper Hired
7 AtifRaza Muhammad
Abbas Baildar Helper Hired
8 Shah Nawaz ManzoorHussain Baildar Helper Hired
9 Zaman Ali Nasrullah Khan Regulation
Baildar Helper Hired
10 ZubairHussain Muhammad
Anwar NaibQasid Helper Hired
11 Waqar Ali Late Muhammad
Aslam
Regulation
Baildar Helper Hired
12 Muhammad
Asim
Muhammad
Inayat
Regulation
Baildar Messon
13 QasirShahzad ManzoorHussain Baildar Driver Hired
NKBP Internal Resettlement Monitoring Report
PMO For Punjab Barrages
Sr. No Name of
Applicant Father's Name
Father's
Designation
Post Applied
For Remarks
14 Saeed Anwar Muhammad
Anwar Junior Clerk Office Boy Hired
15 Rahat Ali Muhammad
WalayatHussain Head Boat Man Helper Hired
16 Umar Farooq Muhammad
Azam
Regulation
Baildar Helper Hired
17 AmjadFarooq ManzoorHussain Baildar Helper Hired
18 Shahzad Ali ManzoorHussain Baildar Helper Hired
19 Shawal Ali Liaqat Ali Regulation
Baildar
Generator
Mechanic
20 KaleemUllah Irshad Ahmad
Butt Boatman Office Boy
21 Muhammad Bilal Muhammad
Younas
Regulation
Baildar Helper Hired
22 IrshadMasih Ashraf Masih Sweeper Sweeper
23 HusnainAkram Muhammad
Akram
Regulation
Baildar Safty helper Hired
24 Jazib Ali Irshad Ahmad
Butt Boatman Survey Helper Hired
25 Muhammad
Javed Muhammad Khan Bulock Man Helper Hired
26 Bilal Ahmad Muhammad Fazal NaibQasid Helper
Annex - E
New Khanki Barrage Project (NKBP)
District Wise Skilled / Unskilled Labour for the Month of January 2016
Sr #
Districts
DESCON
Total
Sub Contractor TOTAL
Total
Re
ma
rks
Skilled Unskilled Skilled Unskilled Skilled Unskilled
Th
ree n
um
be
r o
f em
plo
ye
es f
rom
aff
ecte
d f
am
ilie
s a
re w
ork
ing
wit
h t
he
co
ntr
acto
rs
1 GUJRANWALA 222 188 410 71 29 293 217 510
2 HAFIZABAD 43 16 59 38 22 81 38 119
3 CHINIOT 9 0 9
9 0 9
4 SHEIKHUPURA 30 14 44
30 14 44
5 NANKANA 24 4 28
24 4 28
6 FAISALABAD 68 12 80
68 12 80
7 JHANG 42 39 81
42 39 81
8 TOBA TEK SINGH 33 9 42
33 9 42
9 Gujrat (Barrage
Adjoining Villages 342 111 453 36 24 378 145 523
Total 813 393 1206 145 75 958 468 1436
%age 64.88% 60.93% 63.54% 45.89%
61.00% *62.00% 62%
Other Districts 440 252 692 171 35 611 287 898
Total Districts 1253 645 1898 316 110 1569 75 2334
*62% unskilled labouris used during the month of January 2016
NKBP Internal Resettlement Monitoring Report
PMO For Punjab Barrages
Annex - F
New Khanki Barrage Project (NKBP)
District Wise Skilled / Unskilled Labour for the Month of February 2016
Sr # Districts
DESCON
Total
Sub Contractor TOTAL
Total
Re
ma
rks
Skilled Unskilled Skilled Unskilled Skilled Unskilled
Th
ree n
um
be
r o
f em
plo
ye
es f
rom
aff
ecte
d f
am
ilie
s a
re w
ork
ing
wit
h t
he
co
ntr
acto
rs
1 GUJRANWALA 233 186 419
65 27 298 214 512
2 HAFIZABAD 41 18 59
32 23 73 36 109
3 CHINIOT 15 0 9
0 0 15 0 15
4 SHEIKHUPURA 28 12 40
0 0 28 12 40
5 NANKANA 23 8 31
0 0 23 8 31
6 FAISALABAD 65 19 84
0 0 64 14 78
7 JHANG 39 29 68
0 0 39 34 73
8 TOBA TEK
SINGH
29 11 40 0 0 29 9 38
9 Gujrat (Barrage
Adjoining Villages
311 115 429 28 25 339 126 465
Total 784 398 1182
125 75 844 453 1297
%age 62.57
% 60.98% 62.42%
40.87%
58% *61.00% 57%
Other Districts
432 263 695 163 31 595 281 876
Total Districts 1216 661 1877
288 106 1439 734 2173
* 61.00% unskilled labour is used in the month of February, 2016.
NKBP Internal Resettlement Monitoring Report
PMO For Punjab Barrages
Annex - G
New Khanki Barrage Project (NKBP)
District Wise Skilled / Unskilled Labour for the Month of March 2016
Sr #
Districts
DESCON
Total
Sub Contractor TOTAL
Total
Re
ma
rks
Skilled Unskilled Skilled Unskill
ed Skilled Unskilled
Th
ree n
um
be
r o
f em
plo
ye
es f
rom
aff
ecte
d f
am
ilie
s a
re w
ork
ing
wit
h t
he
co
ntr
acto
rs
1 GUJRANWALA 192 178 370 51 26 243 204 447
2 HAFIZABAD 43 16 59 42 15 85 31 116
3 CHINIOT 9 0 9 0 0 9 0 9
4 SHEIKHUPURA 30 14 44 0 0 30 14 44
5 NANKANA 24 4 28 0 0 24 4 28
6 FAISALABAD 68 12 80 0 0 68 12 80
7 JHANG 42 39 81 0 0 42 39 81
8 TOBA TEK SINGH 33 9 42 0 0 33 9 42
9 Gujrat (Barrage
Adjoining Villages 314 105 419 33 7 347 112 469
Total 755 377 1132 126 48 881 425 1306
%age 65.82% 66.37% 66.01% 52.94% 42.48% 64.00% 62.00% 63%
Other Districts 432 263 695 163 31 595 281 876
Total Districts 1187 640 1827 289 77 1476 706 2182
59% is used during the month of October 2015
NKBP Internal Resettlement Monitoring Report
PMO For Punjab Barrages
Status of Settlement of Complaints Annex –H
Sr# Date Complainant Location Sort of Complain Status
1 10/2/14 Imtiaz Ahmed
Lundpur
/complete
address
Demand for Culverts at
Chanawan Road Resolved
2 1/1/15 Zubair Ahmad BurjCheema
Demand for
Culverts/186+36 and
192+32 /Chanawan Road
Resolved
3 10/1/15 MansoorWarraich ThatthiBaloch
Demand for
Culverts134+71/Chanawan
Road
Resolved
4 5/1/14 Khizar Hayat ThatthiBaloch
Demand for
Culverts/115+70Chanawan
Road
Resolved
5 10/12/14 NaseemHussain ThatthiBaloch
Demand for
Culverts/84+93/Chanawan
Road
Resolved
6 15/12/14 Master Shafqat Ali Faqiranwali
Demand for
Culverts/56+37/Chanawana
Road
Resolved
7 14/10/14 Farooq Akbar Cheema LCC Increase the rate of land
/LCC In Process
8 26/12/14 Dr. AzharIqbalCheema KotJaffar Small Bridge /Gunayanwala
to KotJaffar Road Resolved
9 1/12/14 Rana Muhammad Khan BurjDhalla
Demand for
Culverts/19+200/
Chanawan Road 21+150
Resolved
10 Repeated
App Dr. AzharIqbalCheema KotJaffar No 8 Applicaton Repeated. Resolved
11 12/4/15 GhulamSarwarCheema BurjCheema Demand for
Culverts/Chanawan Road Resolved
12 21/05/15 Head Mistress Girls
School Khanki Play Ground/ Khanki
Resolved
13 16/5/15 GhulamRasool Ratowali
/Jamil Town
Cemented Ramp & Soling
/LMB Road In Process
14 21/5/15 Farooq Akbar Cheema Kot Imam Bux Drainage of flood
water/Chanawan Road In Process
NKBP Internal Resettlement Monitoring Report
PMO For Punjab Barrages
Status of Settlement of Complaints Annex –H
Sr# Date Complainant Location Sort of Complain Status
15 14/5/15 Umer Hayat BurjDhalla Demand for
Culverts/Chanawan Road Resolved
16 8/6/15 Hafiz SaifUllahChatta KotRatta Speed Breaker/ Footpath
/Chanawan Road In Process
17 9/6/15 Muhammad
AslamRandhawa KorRatta Outlet /Chanawan Road
Resolved
18 8/6/15 Haji
AmjadPervaizRandhawa KorRatta
Repair the old bridge
/Chanawan Road
Resolved
19 7/6/15 PervaizIqbalBhatti KotRatta Repair the old
bridge/Chanawan Road
Resolved
20 9/6/15 XEN Irrigation Khanki Boundary wall / Play
Ground/Irrigation Colony Resolved
21 6/4/15 Master NasirMahmood KotRatta Change the location of
culvert/Chanawan Road Resolved
22 11/4/15 WaqasChatta Advocate Lundpur Court Case /Chanawan
Road Resolved
23 9/7/15 SDO Headworks Khanki Breakage of High Level
Channel Resolved
24 7/7/15 Umer Hayat BurjDhalla Hurdle on Chanawan Road Resolved
25 14/7/15 Farooq Akbar Cheema Khanki Drainage of Rain water
from crops Resolved
26 22/7/15 Amanat Ali Khanki Standing Rain Water in
Colony Resolved
27 28/7/15 SDO Headworks Khanki Breakage of High Level
Channel Resolved
28 19/11/2015 Sibt-Ul-Hassan Khanki Boundary Wall of New
Irrigation Colony Resolved
29 22/03/2016 HameedSalemi Khanki Leveling of Road at Khanki In Process
Note : Out of 29 Complaints 24 are settled.