In the era of Reverse Bidding, the districts with the best generation pack the maximum punch! The paper ranks the districts according to the generation expected.TRANSCRIPT
Solar District Championships In the era of Reverse Bidding, the districts with better generation pack the maximum punch. If everything else like Project Cost and Financial Assumptions are kept equal, the expected
generation from a site plays a very important role in bidding. With the bidding shortly due in
Uttarakhand, Telangana and Andhra Pradesh, Gensol team spent hours churning the Energy
Analytics engine to give you the comparison of generation expected in various districts of
these 3 states.
TELANGANA ANDHRA PRADESH UTTARAKHAND District Name PLF (%) District Name PLF (%) District Name PLF (%) Khammam 19.27 Nellore 19.50 Dehradun 21.04 Warangal 19.26 East Godavari 18.88 Champawat 20.69 Nizamabad 19.15 Srikakulam 18.80 Tehri Garhwal 20.63 Karimnagar 18.80 Vishakhapatnam 18.79 Haridwar 20.44 Medak 18.76 Vizianagaram 18.78 Bageshwar 20.30 Adilabad 18.63 Kurnool 18.76 Udham Singh Nagar 20.16 Mahbubnagar 18.29 West Godavari 18.75 Nainital 20.05 Rangareddy 18.18 Anantapur 18.46 Pauri Garhwal 19.99 Hyderabad 18.01 Chittoor 17.90 Rudraprayag 19.79 Nalgonda 17.81 Krishna 17.56 Almora 19.70 Guntur 17.30 Pithoragarth 19.18 Kadapa 17.29 Chamoli 18.40 Prakasam 17.22 Uttarkashi 17.70
The simulations are done for 1 MW Inverter (1.1 MWp Module) capacity solar power plant
taking Trina Solar 300Wp crystalline and ABB 1000 kW Grid connected Inverter.
Of course, Generation is only one aspect of bidding. Feel free to write to us at
[email protected] for assistance in Cost Estimation, Financial Modeling, Technology
Selection and Documentation Review.