solar pv and stand-alone power systems in rural …...pv practical split into 5 or 6 groups each...

54
Solar PV and stand-alone power systems in rural settings Dr Matthew Little [email protected]

Upload: others

Post on 28-May-2020

31 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Solar PV and stand-alone power systems in rural …...PV Practical Split into 5 or 6 groups Each group will be given parts to build a solar PV power supply system Each will have a

Solar PV and stand-alone power

systems in rural settings

Dr Matthew Little

[email protected]

Page 2: Solar PV and stand-alone power systems in rural …...PV Practical Split into 5 or 6 groups Each group will be given parts to build a solar PV power supply system Each will have a

Stand-alone power supply

systems?

• SAPS are small electricity supply systems based

upon a single generator (sometimes a few

generators) that is physically close to the loads.

• No long transmission system, hence lower • No long transmission system, hence lower

voltages used

• No clear distinction between a national grid and a

large stand-alone power system

• Typical sizes: 10’s watts up to 10’s of Kilowatts

Page 3: Solar PV and stand-alone power systems in rural …...PV Practical Split into 5 or 6 groups Each group will be given parts to build a solar PV power supply system Each will have a

• Far from any national grid.

• Un-economic to connect to

a national grid.

Why use SAPS?

a national grid.

• National grid does not exist.

• Many reasons to use a stand-alone systems.

• Focus on community power supplies for developing world

applications, but the principles apply to all.

Page 4: Solar PV and stand-alone power systems in rural …...PV Practical Split into 5 or 6 groups Each group will be given parts to build a solar PV power supply system Each will have a

Why use SAPS?

• Around 1.6 billion people do not have access to an

electrical grid – mainly in developing countries.

• To locally supply electricity SAPS are used, with the vast

majority of SAPS are based on diesel generators.

• Depending upon the size of load and the distance to the

national grid, there is a point at which a stand-alone

system becomes economic.

• Can have lower investment costs, but may prove

expensive in the long term due to fuel and maintenance

costs.

Page 5: Solar PV and stand-alone power systems in rural …...PV Practical Split into 5 or 6 groups Each group will be given parts to build a solar PV power supply system Each will have a

Benefits of access to electricity

• Reduced hours spent doing labour intensive tasks

• Improved lighting

– Extended working hours can be economically beneficial

– Less indoor air pollution

• Improved communications

• Improved healthcare

– Access to refrigeration for medical supplies– Access to refrigeration for medical supplies

• Improved education

– Reduced time spent on labour intensive tasks

– Better lighting so more time for study

Page 6: Solar PV and stand-alone power systems in rural …...PV Practical Split into 5 or 6 groups Each group will be given parts to build a solar PV power supply system Each will have a

Diesel generator based SAPS

• Majority of SAPS are based on a diesel generator.

Problems with the use of diesel generators include:

Cost of fuel and its transportation

Local environmental effects

Global environmental effectsGlobal environmental effects

Security of fuel supply

Inefficient when partially loaded

Start-up response time

Noise

Require a high level of maintenance

Page 7: Solar PV and stand-alone power systems in rural …...PV Practical Split into 5 or 6 groups Each group will be given parts to build a solar PV power supply system Each will have a

Benefits of renewable energy

�Inherently distributed.

�Usually some form of renewable energy

locally available.

�Buffer from fluctuating fuel costs.

�Local environmental benefits.

�Local health benefits.

�Global environmental benefits.

Page 8: Solar PV and stand-alone power systems in rural …...PV Practical Split into 5 or 6 groups Each group will be given parts to build a solar PV power supply system Each will have a

Problems of integrating renewable

energy

• Variations in supply

• Variations in demand

• Aggregation• Aggregation

Page 9: Solar PV and stand-alone power systems in rural …...PV Practical Split into 5 or 6 groups Each group will be given parts to build a solar PV power supply system Each will have a

Variability of generation and

load

Variation of wind

Variation of typical loads

Variation of solar

Page 10: Solar PV and stand-alone power systems in rural …...PV Practical Split into 5 or 6 groups Each group will be given parts to build a solar PV power supply system Each will have a

Matching supply and demandP

ow

er

MismatchSupply

Demand

P

Time

Excess

Deficit

Page 11: Solar PV and stand-alone power systems in rural …...PV Practical Split into 5 or 6 groups Each group will be given parts to build a solar PV power supply system Each will have a

AggregationAggregation

Tota

l S

ignal

1 signal

10 signals

1000 signals

Time

Large networks with many generation units and loads benefit from aggregation

Page 12: Solar PV and stand-alone power systems in rural …...PV Practical Split into 5 or 6 groups Each group will be given parts to build a solar PV power supply system Each will have a

PV based water pumping

Page 13: Solar PV and stand-alone power systems in rural …...PV Practical Split into 5 or 6 groups Each group will be given parts to build a solar PV power supply system Each will have a

PV based battery charging

Page 14: Solar PV and stand-alone power systems in rural …...PV Practical Split into 5 or 6 groups Each group will be given parts to build a solar PV power supply system Each will have a

PV based battery charging

Page 15: Solar PV and stand-alone power systems in rural …...PV Practical Split into 5 or 6 groups Each group will be given parts to build a solar PV power supply system Each will have a

Wind - PV hybrid systems

Sitio Buli, Lubang Island, Philippines

1 kW wind turbine / 300 Wp solar

Potable water pumping system

Installed July 2007

Page 16: Solar PV and stand-alone power systems in rural …...PV Practical Split into 5 or 6 groups Each group will be given parts to build a solar PV power supply system Each will have a

Wind - PV hybrid systems

Page 17: Solar PV and stand-alone power systems in rural …...PV Practical Split into 5 or 6 groups Each group will be given parts to build a solar PV power supply system Each will have a

Wind based SAPS

• Barangay Lamag,

Quirino, Ilocos Sur,

Philippines

• 500 W wind turbine

• Electrification of church

building and rectory

• Installed March 2006

Page 18: Solar PV and stand-alone power systems in rural …...PV Practical Split into 5 or 6 groups Each group will be given parts to build a solar PV power supply system Each will have a

Wind based SAPS

Page 19: Solar PV and stand-alone power systems in rural …...PV Practical Split into 5 or 6 groups Each group will be given parts to build a solar PV power supply system Each will have a

SOLAR PV BASICS

Page 20: Solar PV and stand-alone power systems in rural …...PV Practical Split into 5 or 6 groups Each group will be given parts to build a solar PV power supply system Each will have a

PV practical

Dr Matthew Little

[email protected]

Page 21: Solar PV and stand-alone power systems in rural …...PV Practical Split into 5 or 6 groups Each group will be given parts to build a solar PV power supply system Each will have a

DC based systems• Main components:

– Energy source

– Energy storage

– Regulator/controller

Page 22: Solar PV and stand-alone power systems in rural …...PV Practical Split into 5 or 6 groups Each group will be given parts to build a solar PV power supply system Each will have a

System voltage

• System voltage is the DC voltage of the energy store, the

generators and loads.

• System voltage is the most important system parameter.

• Affects currents flowing through the system.

• Depends upon a number of factors:• Depends upon a number of factors:

– Cost of cable

– Cost of wind turbine rectifier, charge controller and

inverter.

– Availability of components rated at the system voltage

– Voltage requirement of the loads

Page 23: Solar PV and stand-alone power systems in rural …...PV Practical Split into 5 or 6 groups Each group will be given parts to build a solar PV power supply system Each will have a

Energy storage• Majority (99% of renewable energy based SAPS) use lead-

acid batteries as energy storage.

• Lead-acid batteries store energy in the form of chemical

energy using a reversible reaction.

• Why use them?

• Easily obtainable• Easily obtainable

• Relatively cheap

Page 24: Solar PV and stand-alone power systems in rural …...PV Practical Split into 5 or 6 groups Each group will be given parts to build a solar PV power supply system Each will have a

BATTERY TEST

Page 25: Solar PV and stand-alone power systems in rural …...PV Practical Split into 5 or 6 groups Each group will be given parts to build a solar PV power supply system Each will have a

System design process

• Load assessment

• Resource assessment

• Battery bank sizing• Battery bank sizing

• Wiring diagram

Page 26: Solar PV and stand-alone power systems in rural …...PV Practical Split into 5 or 6 groups Each group will be given parts to build a solar PV power supply system Each will have a

Load assessment• Need to know

– Loads on the system (ALL of them)

– Time the loads run for

– Power rating of loads

• Write a list:• Write a list:

Load Power Time Energy

Lights 25W 2hrs/day 50Whs

Pump 100W 5hrs/day 500Whs

TOTAL 550Whs

Page 27: Solar PV and stand-alone power systems in rural …...PV Practical Split into 5 or 6 groups Each group will be given parts to build a solar PV power supply system Each will have a

Resource assessment• Need to know the resource available.

• Depends upon the renewable energy source.

• Also depends upon size of renewable energy

collector.

Example for PV:Example for PV:

– 5 sun-hours per day available at location

– 50Wp solar panel

Total energy per day = 5 x 50W = 250Whs

Page 28: Solar PV and stand-alone power systems in rural …...PV Practical Split into 5 or 6 groups Each group will be given parts to build a solar PV power supply system Each will have a

Battery sizing

• Must store enough energy to cope with

variations in supply and demand.

• Number of days of autonomy

– Use number of days with no input (typically 4 – Use number of days with no input (typically 4

days)

– Take into account maximum depth of

discharge (typically 50%)

Page 29: Solar PV and stand-alone power systems in rural …...PV Practical Split into 5 or 6 groups Each group will be given parts to build a solar PV power supply system Each will have a

Battery charge protection

Batteries are used:

must maintain them for the longest lifetime.

• Typical lifetimes: 5-7years (well maintained), 2-4 years (average?)

• Batteries must be protected from over charging and over

discharging – to do this we use a….discharging – to do this we use a….

• Charge regulator

• Power electronic device to prevent over-charging

• Must have well trained and knowledgeable operator.

• Battery bank maintenance is essential

• Daily monitor

• Monthly maintenance

Page 30: Solar PV and stand-alone power systems in rural …...PV Practical Split into 5 or 6 groups Each group will be given parts to build a solar PV power supply system Each will have a

Wiring diagrams

Page 31: Solar PV and stand-alone power systems in rural …...PV Practical Split into 5 or 6 groups Each group will be given parts to build a solar PV power supply system Each will have a

Electricity basics

• Need to know:

• Voltage

• Current

• Resistance• Resistance

• Power – instantaneous rate of doing work

• Energy - the total work done

• V=IR and W = IV

Page 32: Solar PV and stand-alone power systems in rural …...PV Practical Split into 5 or 6 groups Each group will be given parts to build a solar PV power supply system Each will have a

Using a multi-meter

• Measure V in parallel

• Measure A in series

• DO NOT measure A in parallel with battery

Page 33: Solar PV and stand-alone power systems in rural …...PV Practical Split into 5 or 6 groups Each group will be given parts to build a solar PV power supply system Each will have a

Good installation practice

• Want the system to be reliable and robust.

• The solar panel will last over 20 years,

hence the system must be installed to last

the same length of time.the same length of time.

Page 34: Solar PV and stand-alone power systems in rural …...PV Practical Split into 5 or 6 groups Each group will be given parts to build a solar PV power supply system Each will have a

DC cable sizing• Cables must be correctly sized for the current they will be

required to carry

• Problem is voltage drop

• Due to resistance of cable and current flowing

• Resistance = (ρ x L) / A

• Voltage drop = Resistance x Current• Voltage drop = Resistance x Current

• Voltage drop must be kept within reasonable parameters

(typically 5%)

• Design for the highest current

Page 35: Solar PV and stand-alone power systems in rural …...PV Practical Split into 5 or 6 groups Each group will be given parts to build a solar PV power supply system Each will have a

Cable interconnections

• Good reliable connections especially

important in low voltage DC systems.

• Must keep the connection clean and dry.

Page 36: Solar PV and stand-alone power systems in rural …...PV Practical Split into 5 or 6 groups Each group will be given parts to build a solar PV power supply system Each will have a

Fusing• Every cable must be protected by some form of fuse or

breaker

• Due to the battery installed:

– Can supply 1000s of amps

in short circuit

– Damage to components

– Fire risk

• Many types available

• Ensure correct rating

• Without it many other much more expensive problems

can happen

Page 37: Solar PV and stand-alone power systems in rural …...PV Practical Split into 5 or 6 groups Each group will be given parts to build a solar PV power supply system Each will have a

System monitoring

• Why monitor?

• Operation

• Maintenance

• Knowledge

• What to monitor?

• System voltage

• Currents flowing

• Battery bank state of charge

Page 38: Solar PV and stand-alone power systems in rural …...PV Practical Split into 5 or 6 groups Each group will be given parts to build a solar PV power supply system Each will have a

Battery bank connectionsBattery Bank Design

SystemPositive

Ensure very thick cable usedfor battery bank interconnections

Use a good qualitybattery clamp

SystemNegative

Take +/- system connectionsfrom ‘opposite’ ends of the system.This will ensure each parallel battery is evenly charged and discharged.

battery clamp

Ensure battery bankinterconnections are kept short

Page 39: Solar PV and stand-alone power systems in rural …...PV Practical Split into 5 or 6 groups Each group will be given parts to build a solar PV power supply system Each will have a

Low voltage disconnects

• Prevents over-discharge of the battery

bank.

• Voltage controlled switch, which will

disconnect non-essential loads if the disconnect non-essential loads if the

battery bank voltage drops too far.

• Sometimes added to a system.

Page 40: Solar PV and stand-alone power systems in rural …...PV Practical Split into 5 or 6 groups Each group will be given parts to build a solar PV power supply system Each will have a

Inverters

Vo

lta

ge

Time

Vo

lta

ge

Time

Square Wave

Stepped Square Wave (or Modified ‘Sine’ Wave)

Pure sine wavefor reference

• Convert DC into AC

Vo

lta

ge

Time

Sine Wave

• Benefits

– Can use readily and cheaply available products

• Problems

– Cost and usually not locally manufactured

– Added complexity

Page 41: Solar PV and stand-alone power systems in rural …...PV Practical Split into 5 or 6 groups Each group will be given parts to build a solar PV power supply system Each will have a

PV System Practical

Page 42: Solar PV and stand-alone power systems in rural …...PV Practical Split into 5 or 6 groups Each group will be given parts to build a solar PV power supply system Each will have a

PV PracticalSplit into 5 or 6 groups

Each group will be given parts to build a solar PV

power supply system

Each will have a different load to power

Each group should:Each group should:

• Test the solar PV module

• Do a load and resource assessment

• Draw circuit diagram

• Build the system

Page 43: Solar PV and stand-alone power systems in rural …...PV Practical Split into 5 or 6 groups Each group will be given parts to build a solar PV power supply system Each will have a

Health and safety

• Using knives, drills and hammers

• Careful when using tools

Be aware of others around you• Be aware of others around you

Page 44: Solar PV and stand-alone power systems in rural …...PV Practical Split into 5 or 6 groups Each group will be given parts to build a solar PV power supply system Each will have a
Page 45: Solar PV and stand-alone power systems in rural …...PV Practical Split into 5 or 6 groups Each group will be given parts to build a solar PV power supply system Each will have a

Problems experienced

Failure analysis of 421 systems over 3 years in Taquile, Peru

50

60

70

80

Accu

mu

late

d f

ailu

res a

s %

of

tota

l

Modules

Batteries

0

10

20

30

40

50

0 6 12 18 24 30 36

Months

Accu

mu

late

d f

ailu

res a

s %

of

tota

l

Regulators

Lamps

Fuses

Page 46: Solar PV and stand-alone power systems in rural …...PV Practical Split into 5 or 6 groups Each group will be given parts to build a solar PV power supply system Each will have a

Problems experienced

• Incorrect fusing

Page 47: Solar PV and stand-alone power systems in rural …...PV Practical Split into 5 or 6 groups Each group will be given parts to build a solar PV power supply system Each will have a

Problems with lead-acid

batteries• They self-discharge at a rate of 1-5% total energy per

month

• Temperature affects both capacity and lifetime

• Capacity is dependant upon current

• Lifetime is dependant upon discharge cycles and depth of • Lifetime is dependant upon discharge cycles and depth of

discharge

• Their storage density is approximately 30 to 40 Wh/kg

• A periodic equalisation charge is required

• Lead-acid batteries cost around £40 per kWh

Page 48: Solar PV and stand-alone power systems in rural …...PV Practical Split into 5 or 6 groups Each group will be given parts to build a solar PV power supply system Each will have a

Problems with lead-acid batteries

• The technology has been around for over 100 years so

there is little potential for cost reduction.

• Often cheap car batteries with lead sponge plates are

used rather than deep-cycle batteries especially designed

for stand-alone operation which exacerbates these for stand-alone operation which exacerbates these

problems.

If possible try to avoid using lead-acid batteries

• Some applications (such as water pumping) can be directly

coupled to the renewable energy source. The energy is

then stored as potential in the water.

Page 49: Solar PV and stand-alone power systems in rural …...PV Practical Split into 5 or 6 groups Each group will be given parts to build a solar PV power supply system Each will have a

Problems experienced

Crazy

wiring

Incorrect cable

sizing

Page 50: Solar PV and stand-alone power systems in rural …...PV Practical Split into 5 or 6 groups Each group will be given parts to build a solar PV power supply system Each will have a

Problems experienced

Short circuits and burned out components

Page 51: Solar PV and stand-alone power systems in rural …...PV Practical Split into 5 or 6 groups Each group will be given parts to build a solar PV power supply system Each will have a

Problems experienced

Insects

Page 52: Solar PV and stand-alone power systems in rural …...PV Practical Split into 5 or 6 groups Each group will be given parts to build a solar PV power supply system Each will have a

Problems experienced

Lightning!

Page 53: Solar PV and stand-alone power systems in rural …...PV Practical Split into 5 or 6 groups Each group will be given parts to build a solar PV power supply system Each will have a

Problems experienced• Battery failure

• Systems changed by operator for ‘better’ operation

• Cable voltage drop

• Flooding

• Access to engineering skills• Access to engineering skills

• Inadequate training

• Access to spare parts

• Political situations

• No long-term strategy

• Community organisation problems

• Funding

• Bad resource assessment

Page 54: Solar PV and stand-alone power systems in rural …...PV Practical Split into 5 or 6 groups Each group will be given parts to build a solar PV power supply system Each will have a

Thanks for your attention.