Page 1: Solar Thermal Power Generation - A Spanish Success Story

1

Solar Thermal Power Generation - A Spanish Success Story

Jose Alfonso NebreraDirector General de ACS SCE

Madrid, 26 de febrero de 2008

Page 2: Solar Thermal Power Generation - A Spanish Success Story

2

Introduction to COBRA and ACS

A global leading player of applied engineering services and EPC contractorDevelopment of Renewable Energy Projects

Cobra Group is responsible for the development of renewable energy project inside the ACS group

Page 3: Solar Thermal Power Generation - A Spanish Success Story

3

Highlights

Parabolic-trough and solar tower plants are the most developed concentrating solar power (CSP) technologies realized up to date, with more than 420 MW of commercial plants operating

Spain has one of the most favorable feed-in tariffs for CSP plants paying at least 39 cents US$ per kWh

At the end of 2007 more than 50 CSP projects with about 2150 MW have been registered by the Ministry of Industry making Spain the leading country in CSP development worldwide

ACS/Cobra is building three plants and has the objective to operate eight CSP plants with a total capacity of 400 MW within five years

At this moment ACS/Cobra is the only turn-key contractor with experience in constructing parabolic-trough power plants which combine solar fields with molten salt storage tanks

Page 4: Solar Thermal Power Generation - A Spanish Success Story

4

Technology overview

Parabolic-trough and solar tower plants are the most developed concentrating solar power (CSP) technologies realized up to date, with more than 420 MW of commercial plants operating

Sources PSA, SNL, Solarmundo, SBP)

Our focus

• 354 MW SEGS (California)• 64 MW Nevada Solar One• 10 MW PS 10 (Seville, Spain)

Commercials plants:

Page 5: Solar Thermal Power Generation - A Spanish Success Story

5

Current Situation in Spain

50 MW

500 MW

500 MW

50 MW

50 MW

150 MW

500 MW

350 MW

At the end of 2007 more than 50 CSP projects with about 2150 MW have been registered by the Ministry of Industry

Page 6: Solar Thermal Power Generation - A Spanish Success Story

6

Andasol: Simplified Scheme

Support boiler

Steam turbine

Electricity Generator

Condenser

Low pressure warmer

Degasification

Solar warmer

Solar pre-warmer

Solar warmer Water circuit pump

Solar steam

generator

Expansion Tank

Thermal fluid pump

Heated collecting main pipeSolar field

Steam CycleStorage

Melted salts storage

Euro

thou

ghCo

llect

ors

Heated tank of

melted salts

Heat exchanger between thermal

fluid and melted salts

Cooled tank of

melted salts

Cooled collecting main pipe

Our 50 MWel CSP plants consists of three parts: Solar field, storage tanks and power generation

Page 7: Solar Thermal Power Generation - A Spanish Success Story

7

Characteristics

Parabolic trough collectors

Metal structure.

Parabolic reflecting surface

Absorbing pipes

Andasol: Solar field

• 156 loops in 200 Ha

• 500,000 m2 of mirrors

• Thermal fluid 292ºC – 392ªC

More than 500,000 m2 of mirrors have been lined up to build the solar field

Page 8: Solar Thermal Power Generation - A Spanish Success Story

8

Two storage tanks (ø= 36 m, h=14 m)• Storage capacity (h): 7,5h @ 50 MW• Molten salts: 28.000 Metric Tons/• Melting temperature: 221º C• Allowance range: 291º C - 384º C

IMPROVEDMANAGEABILITY

Andasol: Thermal storage

The molten salt storage tank system increases the running time of the CSP plant up to 3.500 hours/per year

Page 9: Solar Thermal Power Generation - A Spanish Success Story

9

ANDALUCIA EXTREMADURA

CASTILLA-LA MANCHA

ANDASOL-1

ANDASOL-2

ANDASOL-4

ANDASOL-3

ANDASOL-5

ANDASOL-6

ANDASOL-7

EXTRESOL-1

EXTRESOL-2

EXTRESOL-3

MANCHASOL-1

MANCHASOL-2

manchasol-1,2

andasol-1,2,3,4,5,6,7

extresol1,2,3

•Three plants being built•Objective 2012: 400 MW on operation

Projects pipeline

Cobra is building three plants and has the objective to operate eight CSP plants with a total capacity of 400 MW within five years

Page 10: Solar Thermal Power Generation - A Spanish Success Story

10

Andasol-1

Andasol 1 - Under construction

•Municipality of Aldeire (Granada).•Under construction.•Start Date: 3Q 2008.•Infrastructures of evacuation: October 2007.•Line and SE 66 kV: October 2007.•Satellite Plant of Gas: October 2007.

Page 11: Solar Thermal Power Generation - A Spanish Success Story

11

Andasol-2

•Municipality of Aldeire and La Calahorra (Granada).•Under construction. Movement of lands.•Start Date: 1Q 2008.•Infrastructures of evacuation: October 2007.•Line and SE 66 kV: October 2007.•Satellite Plan of Gas: October 2007.

Andasol 2 - Under construction

Page 12: Solar Thermal Power Generation - A Spanish Success Story

12

Extresol-1

•Municipality of Torre de Miguel Sesmero (Badajoz).•Under construction. Engineering Development and contracting of main supplies.•Start Date: August 2007.•Infrastructures of evacuation: October 2008.•Satellite Plan of gas: October 2008.

Extresol 1 - Under construction

Page 13: Solar Thermal Power Generation - A Spanish Success Story

13

Extresol-2 and Extresol-3

•Municipality of Torre de Miguel Sesmero (Badajoz).•Under promotion. Condition of Generator in Special Regime.•Permitting Projects: 11/07•Evacuation:

• Extresol 2: Sevillana Endesa. Granted point of evacuation.

• Extresol 3: REE. Granted point of evacuation.

•Extresol 2:• Start of construction: 08/08• Start Date: 08/10

•Extresol 3:• Start of construction: 02/09• Satart Date: 02/11

Page 14: Solar Thermal Power Generation - A Spanish Success Story

14

Manchasol-1 and Manchasol-2

•Municipality of Alcázar de San Juan (Ciudad Real).•Under promotion. Condition of Generator in Special Regime.•Permitting Projects: 10/07•Evacuation: REE. Granted point of evacuation•Start of construction: 09/08•Start Date: 09/10

Manchasol 1 and 2 - Under promotion

Page 15: Solar Thermal Power Generation - A Spanish Success Story

15

Andasol 4

•Municipality of Puebla de Don Fadrique (Granada).•Under promotion. •Execution Projects: 06/07•Evacuation: Requested point of connection to Sevillana-Endesa.•Start of construction: 11/09•Start Date: 11/11

Andasol 4 - Under promotion

Page 16: Solar Thermal Power Generation - A Spanish Success Story

16

Development Plan

20062006 20072007 20082008 20092009 20102010 20112011

Andasol-1

Andasol-2

Extresol-1

Extresol-2

Extresol-3

Manchasol-1

Manchasol-2

TOTAL: 400 MW

Andasol-4

Construction time for a CSP plants is about 24 -26 months

At this moment Cobra is the only turn-key contractor with experience in constructing parabolic-trough power plants which combine solar fields with molten salt storage tanks