sor analysis 2018 - mizoram · sor committee, p&e department government of mizoram mizoram :...
TRANSCRIPT
For Official use only
GOVERNMENT OF MIZORAM
POWER & ELECTRICITY DEPARTMENT
SOR ANALYSIS
2018
SOR ANALYSIS : 2018
Published by
Engineer-In-Chief
Power & Electricity Department
Government of Mizoram
Mizoram : Aizawl
Copyright reserved by the publisher
1st Impression : May 2015, Copies : 500
2ndImpression : February 2017 Copies : 500
Layout Design :
SOR Committee, P&E Department
Government of Mizoram
Mizoram : Aizawl
All right reserved. No part of this publication may be reproduced, stored in a
retrieval system or transmitted in any form or by any means, electronic,
mechanical, photocopy, recording or otherwise without the prior permission of
the publisher
Printed at :
DETAILED
ANALYSIS
(for New Works)
Sl. No Contents Page No.
1 General Guidelines 5-7
1 Pole Erection 11-13
2 Cross Arm Fitting 14-21
3 Fitting of Disc Insulators 22
4 Stay Set Erection 23-24
5 Conductor Stringing 25-26
6 Earthing 27
7 Fitting of Lightining Spike and Lightning Arresters 28
8 Transformer Installation 29-35
9 Placing of Distribution Transformer 36
10 Laying and Fitting of Cables 37-41
11 Protection of Distribution Transformer 42-44
12 Fencing of Distribution Transformer 45
13 Installation of Meters 46-47
14 Street Lighting 48
15 LT Aerial Bunched Cables 49
16 11 kV Aerial Bunched Cables 50
17 Installation of 33kV equipment 51-52
18 Installation of Power Transformer 53
19 Cabling 54-55
20 Installation of C & R Panel 56
21 Installation of Battery & Charger 57
22 33kV Sub-Station Fencing 58
23 Graveling 59
24 Cable Trench 60
1 Pole Dismantling 63
2 Cross Arm Dismantling 64-66
3 Dismantling of Disc Insulators 67
4 Stay Set Dismantling 68
5 Conductor Dismantling 69
1 Transportation Cost 73-78
2Approximate Unit Weights of Lines and Distribution
Transformers 79-81
3 Drawings 85-135
SCHEDULE - III (Dismantling Works)
SCHEDULE - IV (Misc.)
INDEX
SCHEDULE - I
SCHEDULE - II (New Works)
Sl. No Items Unit Rate/Unit
1001 Labour Skilled-I manday 380.00
1002 Labour Skilled-II manday 310.00
1003 Labour Semi-Skilled manday 250.00
1004 Labour Un-skilled manday 220.00
1005 Concrete Mixture 7-10tph Per Hour 270.00
1006 Niddle Vibrator Per Hour 101.00
1101
Swaged Steel Pole with base plate of thickness 6mm and
size of 200mmx200mm square welded at the bottom and
with pole cap of 6mm thick to be welded at the top
conforming to IS 2713/1980 or the latest version thereof
410 SP-17 of overall length 8.50m
No 9,011.25
1102
Swaged Steel Pole with base plate of thickness 6mm and
size of 200mmx200mm square welded at the bottom and
with pole cap of 6mm thick to be welded at the top
conforming to IS 2713/1980 or the latest version thereof
410 SP-29 of overall length 9.00m
No 12,656.25
1103
Swaged Steel Pole with base plate of thickness 6mm and
size of 200mmx200mm square welded at the bottom and
with pole cap of 6mm thick to be welded at the top
conforming to IS 2713/1980 or the latest version thereof
410 SP-35 of overall length 9.50m
No 13,061.25
1104
Swaged Steel Pole with base plate of thickness 6mm and
size of 200mmx200mm square welded at the bottom and
with pole cap of 6mm thick to be welded at the top
conforming to IS 2713/1980 or the latest version thereof
410 SP-58 of overall length 12.00m
No 18,832.50
1105 Pre stressed Concrete Pole: 8.5m No 5,828.00
1106 Pre stressed Concrete Pole: 9.75m No 8,190.00
1107
Galvanised Swaged Steel Pole with base plate of
thickness 6mm and size of 200mmx200mm square
welded at the bottom and with pole cap of 6mm thick to
be welded at the top conforming to IS 2713/1980 or the
latest version thereof 410 SP-17 of overall length 8.50m
No 13,233.00
1108
Galvanised Swaged Steel Pole with base plate of
thickness 6mm and size of 200mmx200mm square
welded at the bottom and with pole cap of 6mm thick to
be welded at the top conforming to IS 2713/1980 or the
latest version thereof 410 SP-29 of overall length 9.00m
No 17,640.00
1109
Galvanised Swaged Steel Pole with base plate of
thickness 6mm and size of 200mmx200mm square
welded at the bottom and with pole cap of 6mm thick to
be welded at the top conforming to IS 2713/1980 or the
latest version thereof 410 SP-35 of overall length 9.50m
No 19,179.00
BASIC AND TRANSPORTATION RATES
Page 1 of 15
Sl. No Items Unit Rate/Unit
1110
Galvanised Swaged Steel Poles with base plate of
thickness 6mm and size of 200mmx200mm square
welded at the bottom and with pole cap of 6mm thick to
be welded at the top con forming to IS 2713/1980 or the
latest version thereof 410 SP-58 of overall length
12.00m
No 27,654.00
1201
Hard drawn standard aluminium conductors
conforming to IS 398(Part-I) with amendment No. 1, 2
and 3 or the latest version thereof bearing ISI mark
:Conductor AAC,7/3.10 mm Ant
Km 59,881.00
1202
Hard drawn standard aluminium conductors
conforming to IS 398(Part-I) with amendment No. 1, 2
and 3 or the latest version thereof bearing ISI mark
:Conductor AAC,7/2.91 mm Gnat
Km 31,889.00
1203
Hard drawn standard aluminium conductors
conforming to IS 398(Part-I) with amendment No. 1, 2
and 3 or the latest version thereof bearing ISI mark
:Conductor, AAC,7/3.91 mm Grasshopper
Km 89,420.00
1204
Hard drawn standard aluminium conductors galvanized
steelwire reinforced conforming to IS 398(Part-II) with
amendment No. 1, 2 and 3 or the latest version thereof
bearing ISI mark :ACSR 6/1/4 mm Racoon
Km 85,049.00
1205
Hard drawn standard aluminium conductors galvanized
steelwire reinforced conforming to IS 398(Part-II) with
amendment No. 1, 2 and 3 or the latest version thereof
bearing ISI mark :ACSR 6/1/2.59mm Weasel.
KM 33,399.00
1301
Out door type oil immersed naturally cooled 3-ph, 50Hz
Al-wound Distribution Transformer of vector group DYn-
11 conforming to IS : 1180 (1964) and IS : 2026 (1962)
or latest version thereof and ISI marked of the following
capacity 25 kVA 11/0.415 kV
No 68,850.00
1302
Out door type oil immersed naturally cooled 3-ph, 50Hz
Al-wound Distribution Transformer of vector group DYn-
11 conforming to IS : 1180 (1964) and IS : 2026 (1962)
or latest version thereof and ISI marked of the following
capacity 63 kVA 11/0.415 kV
No 1,22,850.00
1303
Out door type oil immersed naturally cooled 3-ph, 50Hz
Al-wound Distribution Transformer of vector group DYn-
11 conforming to IS : 1180 (1964) and IS : 2026 (1962)
or latest version thereof and ISI marked of the following
capacity 100 kVA 11/0.415 kV
No 1,79,887.50
Page 2 of 15
Sl. No Items Unit Rate/Unit
1304
Out door type oil immersed naturally cooled 3-ph, 50Hz
Cu-wound Distribution Transformer of vector group DYn-
11 with tap changer conforming to IS : 1180 (1964) and
IS : 2026 (1962) or latest version thereof and ISI
marked of the following capacity 250 kVA 11/0.415 kV
No 3,75,300.00
1305
Out door type oil immersed naturally 3-ph, 10Hz Cu-
wound Distribution Transformer of vector group DYn-11
with tap changer and air breather with first filling oil
conforming to IS : 1180 (1964) and IS : 2026 (1962) or
latest version thereof and ISI marked of the following
capacity 500 kVA 11/0.415 kV
No 10,10,515.50
1306
Out door type oil immersed naturally 3-ph, 10Hz Cu-
wound Distribution Transformer of vector group DYn-11
with tap changer conforming to IS : 1180 (1964) and IS :
2026 (1962) or latest version thereof and ISI marked of
the following capacity 630 kVA 11/0.415 kV
No 10,99,575.00
1307
Out door type oil immersed naturally 3-ph, 10Hz Cu-
wound Distribution Transformer of vector group DYn-11
with tap changer conforming to IS : 1180 (1964) and IS :
2026 (1962) or latest version thereof and ISI marked of
the following capacity 750 kVA 11/0.415 kV
No 12,15,000.00
1308
Out door type oil immersed naturally cooled 3-ph, 50Hz
Cu-wound Distribution Transformer of vector group DYn-
11 with tap changer conforming to IS : 1180 (1964) and
IS : 2026 (1962) or latest version thereof and ISI
marked of the following capacity 1000 kVA 11/0.415 kV
No 17,71,875.00
1309
100kVA, 11/0.415 kV, Dyn11 CSS Transformer with off
circuit tap of rating +5 to-5 @ 2.5% comprising of
a) HT Switchgear: 11kV, 200A, Air Insulated Switchgear
consisting of Load Break Switchand Fuse for protection
of transformer, Interconnection between HTswitchgear
and transformer shall be using 1Cx3x25 sq.mm
Al.unarmorured XLPE Cable. The system includes HT &
LT metering components.
b) LT Switchboard: 250A 3P 36kA Fixed Manual MCCB
with Microprocessor based O/C, E/F, S/C release as
incomer cum outgoing.
No 19,51,000.00
Page 3 of 15
Sl. No Items Unit Rate/Unit
1310
160kVA, 11/0.415 kV, Dyn11 CSS Transformer with off
circuit tap of rating +5 to-5 @ 2.5% comprising of
a) HT Switchgear: 11kV, 200A, Air Insulated Switchgear
consisting of Load Break Switchand Fuse for protection
of transformer, Interconnection between HTswitchgear
and transformer shall be using 1Cx3x25 sq.mm
Al.unarmorured XLPE Cable. The system includes HT &
LT metering components.
b) LT Switchboard: 250A 3P 36kA Fixed Manual MCCB
with Microprocessor based O/C, E/F, S/C release as
incomer cum outgoing.
No 23,80,000.00
1311
200kVA, 11/0.415 kV, Dyn11 CSS Transformer with off
circuit tap of rating +5 to-5 @ 2.5% comprising of
a) HT Switchgear: 11kV, 200A, Air Insulated Switchgear
consisting of Load Break Switchand Fuse for protection
of transformer, Interconnection between HTswitchgear
and transformer shall be using 1Cx3x25 sq.mm
Al.unarmorured XLPE Cable. The system includes HT &
LT metering components.
b) LT Switchboard: 320A 3P 36kA Fixed Manual MCCB
with Microprocessor based O/C, E/F, S/C release as
incomer cum outgoing.
No 26,75,000.00
1312
250kVA, 11/0.415 kV, Dyn11 with off circuit tap of
rating +5 to-5 @ 2.5% comprising of
a) HT Switchgear: 11kV,630A,21KA for 3sec, SF6
insulated Non-Extinsible Compact switchgear (Type DV)
consisting of one No. Direct Switch and One No. Fixed
Manual Vacuum Circuit Breaker in SF6 with insulated
stainless steel enclosure, with series trip, self powered
microprocessor based numerical relay for over current
and earth fault (IDMTL + Inst.) protection.
Interconnection between HT switchgear and transformer
shall be using 1Cx3x25 sq.mm Al. unarmorured XLPE
Cable. The systemincludes HT & LT metering
components
b) LT Switchboard: 400A 3P 36kA Fixed Manual MCCB
with Microprocessor based O/C, E/F, S/C release as
incomer cum outgoing.
No 29,40,600.00
Page 4 of 15
Sl. No Items Unit Rate/Unit
1313
315kVA, 11/0.415 kV, Dyn11 with off circuit tap of
rating +5 to-5 @ 2.5% comprising of
a) HT Switchgear: 11kV,630A,21KA for 3sec, SF6
insulated Non-Extinsible Compact switchgear (Type DV)
consisting of one No. Direct Switch and One No. Fixed
Manual Vacuum Circuit Breaker in SF6 with insulated
stainlesssteel enclosure, with series trip, self powered
microprocessor based numerical relay for over current
and earth fault (IDMTL + Inst.) protection.
Interconnection between HT switchgear and
transformershall be using 1Cx3x25 sq.mm Al.
unarmorured XLPE Cable. The system includes HT & LT
metering components
b) LT Switchboard: 630A 3P 36kA Fixed Manual MCCB
with Microprocessor based O/C, E/F, S/C release as
incomer cum outgoing.
No 34,50,800.00
1314
400kVA, 11/0.415 kV, Dyn11 with off circuit tap of
rating +5 to-5 @ 2.5% comprising of
a) HT Switchgear: 11kV,630A,21KA for 3sec, SF6
insulated Non-Extinsible Compact switchgear (Type DV)
consisting of one No. Direct Switch and One No. Fixed
Manual Vacuum Circuit Breaker in SF6 with insulated
stainlesssteel enclosure, with series trip, self powered
microprocessor based numerical relay for over current
and earth fault (IDMTL + Inst.) protection.
Interconnection between HT switchgear and
transformershall be using 1Cx3x25 sq.mm Al.
unarmorured XLPE Cable. The system includes HT & LT
metering components
b) LT Switchboard: 630A 3P 36kA Fixed Manual ACCB
with Microprocessor based O/C, E/F, S/C release as
incomer cum outgoing.
No 37,45,000.00
1315
500kVA, 11/0.415 kV, Dyn11 with off circuit tap of
rating +5 to-5 @ 2.5% comprising of
a) HT Switchgear: 11kV,630A,21KA for 3sec, SF6
insulated Non-Extinsible Compact switchgear (Type DV)
consisting of one No. Direct Switch and One No. Fixed
Manual Vacuum Circuit Breaker in SF6 with insulated
stainlesssteel enclosure, with series trip, self powered
microprocessor based numerical relay for over current
and earth fault (IDMTL + Inst.) protection.
Interconnection between HT switchgear and
transformershall be using 1Cx3x25 sq.mm Al.
unarmorured XLPE Cable. The system includes HT & LT
metering components
b) LT Switchboard: 800A 3P 50kA Fixed Manual ACB
with Microprocessor based O/C, E/F, S/C release as
incomer cum outgoing.
No 39,80,400.00
Page 5 of 15
Sl. No Items Unit Rate/Unit
1316
630kVA, 11/0.415 kV, Dyn11 with off circuit tap of
rating +5 to-5 @ 2.5% comprising of
a) HT Switchgear: 11kV,630A,21KA for 3sec, SF6
insulated Non-Extinsible Compact switchgear (Type DV)
consisting of one No. Direct Switch and One No. Fixed
Manual Vacuum Circuit Breaker in SF6 with insulated
stainlesssteel enclosure, with series trip, self powered
microprocessor based numerical relay for over current
and earth fault (IDMTL + Inst.) protection.
Interconnection between HT switchgear and
transformershall be using 1Cx3x25 sq.mm Al.
unarmorured XLPE Cable. The system includes HT & LT
metering components
b) LT Switchboard: 1000A 3P 50kA Fixed Manual ACB
with Microprocessor based O/C, E/F, S/C release as
incomer cum outgoing.
No 47,50,500.00
1317
750kVA, 11/0.415 kV, Dyn11 with off circuit tap of
rating +5 to-5 @ 2.5% comprising of
a) HT Switchgear: 11kV,630A,21KA for 3sec, SF6
insulated Non-Extinsible Compact switchgear (Type DV)
consisting of one No. Direct Switch and One No. Fixed
Manual Vacuum Circuit Breaker in SF6 with insulated
stainlesssteel enclosure, with series trip, self powered
microprocessor based numerical relay for over current
and earth fault (IDMTL + Inst.) protection.
Interconnection between HT switchgear and
transformershall be using 1Cx3x5 sq.mm Al.
unarmorured XLPE Cable. The system includes HT & LT
metering components
b) LT Switchboard: 1250A 3P 50kA Fixed Manual ACB
with Microprocessor based O/C, E/F, S/C release as
incomer cum outgoing.
No 49,30,900.00
1318
990/1000kVA, 11/0.415 kV, Dyn11 with off circuit tap
of rating +5 to-5 @ 2.5% comprising of
a) HT Switchgear: 11kV,630A,21KA for 3sec, SF6
insulated Non-Extinsible Compact switchgear (Type DV)
consisting of one No. Direct Switch and One No. Fixed
Manual Vacuum Circuit Breaker in SF6 with insulated
stainlesssteel enclosure, with series trip, self powered
microprocessor based numerical relay for over current
and earth fault (IDMTL + Inst.) protection.
Interconnection between HT switchgear and
transformershall be using 1Cx3x25 sq.mm Al.
unarmorured XLPE Cable. The system includes HT & LT
metering components
b) LT Switchboard: 1600A 3P 50kA Fixed Manual ACB
with Microprocessor based O/C, E/F, S/C release as
incomer cum outgoing.
No 55,68,000.00
1401 M.S. Channel 75 x 40 x 6 mm kg 105.84
1402 M.S. Channel 100 x 50 x 6 mm kg 105.84
1403 M.S. Angle Iron 40x40x6 mm kg 105.84
1404 M.S. Angle Iron 50x50x6 mm kg 105.84
Page 6 of 15
Sl. No Items Unit Rate/Unit
1405 M.S. Flat Iron 40mmx6 mm kg 105.84
1406 M.S. Angle Iron 20x20x4 mm Kg 105.84
1407 M.S. Flat Iron 20x3 mm Kg 105.84
1501Lightning Arrester 9kV, 10kA Station Class-II as per
IEC:60099-4 & IS:3070 specificationNo 12,500.00
1502 Lightning Arrester 9 kV, 5 KA No 1,875.00
1503 Lightning Arrester 0.280 kV, 2.5 KA for LT Line No 657.00
1601
1.1 kV Aluminium Armoured Cable 1 core, 10 sq.mm
conforming to IS : 1554-1 (1988) or any ammendments m 87.00
1602
1.1 kV Aluminium Armoured Cable 1 core, 16 sq.mm
conforming to IS : 1554-1 (1988) or any ammendments m 102.00
1603
1.1 kV Aluminium Armoured Cable 1 core, 35 sq.mm
conforming to IS : 1554-1 (1988) or any ammendments m 147.00
1604
1.1 kV Aluminium Armoured Cable 1 core, 50 sq.mm
conforming to IS : 1554-1 (1988) or any ammendments m 191.00
1605
1.1 kV Aluminium Armoured Cable 1 core, 70 sq.mm
conforming to IS : 1554-1 (1988) or any ammendments m 225.00
1606
1.1 kV Aluminium Armoured Cable 1 core, 95 sq.mm
conforming to IS : 1554-1 (1988) or any ammendments m 278.00
1607
1.1 kV Aluminium Armoured Cable 1 core, 120 sq.mm
conforming to IS : 1554-1 (1988) or any ammendments m 375.00
1608
1.1 kV Aluminium Armoured Cable 1 core, 150 sq.mm
conforming to IS : 1554-1 (1988) or any ammendments m 525.00
1609
1.1 kV Aluminium Armoured Cable 1 core, 185 sq.mm
conforming to IS : 1554-1 (1988) or any ammendments m 585.00
1610
1.1 kV Aluminium Armoured Cable 1 core, 225 sq.mm
conforming to IS : 1554-1 (1988) or any ammendments m 772.00
1611
1.1 kV Aluminium Armoured Cable 1 core, 300 sq.mm
conforming to IS : 1554-1 (1988) or any ammendments m 960.00
1612
1.1 kV Aluminium Armoured Cable 1 core,400 sq.mm
conforming to IS : 1554-1 (1988) or any ammendments m 1,035.00
1613
1.1 kV Aluminium Armoured Cable 1 core, 630 sq.mm
conforming to IS : 1554-1 (1988) or any ammendments m 1,650.00
1614
PVC Insulated Aluminium Cable, 2.5 sq.mm, 2 Core,
conforming to IS : 1554-1 (1988), IS : 5831 (1984) or
any ammendments there of.
m 20.00
Page 7 of 15
Sl. No Items Unit Rate/Unit
1615
PVC Insulated Aluminium Cable, 4 sq.mm, 2 Core,
conforming to IS : 1554-1 (1988), IS : 5831 (1984) or
any ammendments there of.
m 30.00
1616
PVC Insulated Aluminium Cable, 6 sq.mm, 2 Core,
conforming to IS : 1554-1 (1988), IS : 5831 (1984) or
any ammendments there of.
m 45.00
1617
PVC Insulated Aluminium Cable, 10 sq.mm, 2 Core,
conforming to IS : 1554-1 (1988), IS : 5831 (1984) or
any ammendments there of.
m 72.00
1618
PVC Insulated Aluminium Cable, 16 sq.mm, 2 Core,
conforming to IS : 1554-1 (1988), IS : 5831 (1984) or
any ammendments there of.
m 130.00
1619
PVC Insulated Aluminium Cable, 25 sq.mm, 2 Core,
conforming to IS : 1554-1 (1988), IS : 5831 (1984) or
any ammendments there of.
m 210.00
1620
PVC Insulated Aluminium Cable, 35 sq.mm, 2 Core,
conforming to IS : 1554-1 (1988), IS : 5831 (1984) or
any ammendments there of.
m 310.00
1621 PVC Insulated Copper Cable, 1.0 sq.mm m 30.00
1622 PVC Insulated Copper Cable, 1.5 sq.mm m 39.00
1623 PVC Insulated Copper Cable, 2.5 sq.mm m 67.50
1624 PVC Insulated Copper Cable, 4.0 sq.mm m 90.00
1625 PVC Insulated Copper Cable, 6.0 sq.mm m 127.50
1626 PVC Insulated Copper Cable, 10.0 sq.mm m 270.00
1627
1.1 kV Copper Control Cable, 2.5 sq.mm, 16 Core,
conforming to IS : 1554-1 (1988) or any amendments
there of.
m 575.00
1628
1.1 kV Copper Control Cable, 2.5 sq.mm, 12 Core,
conforming to IS : 1554-1 (1988) or any amendments
there of.
m 444.00
1629
1.1 kV Copper Control Cable, 2.5 sq.mm, 6 Core,
conforming to IS : 1554-1 (1988) or any amendments
there of.
m 174.00
1630
1.1 kV Copper Control Cable, 2.5 sq.mm, 4 Core,
conforming to IS : 1554-1 (1988) or any amendments
there of.
m 122.00
1631
1.1 kV Copper Control Cable, 2.5 sq.mm, 2 Core,
conforming to IS : 1554-1 (1988) or any amendments
there of.
m 96.00
1632 3 Core, 11kV XLPE Aluminium Cable, 185 sq.mm m 2,819.00
1633 3 Core, 11kV XLPE Aluminium Cable, 150 sq.mm m 2,323.00
1634 3 Core, 11kV XLPE Aluminium Cable, 120 sq.mm m 1,628.00
1635 11kV XLPE Aluminium Cable, 1 Core, 600 sq.mm m 4,000.00
1636 11kV XLPE Aluminium Cable, 1 Core, 400 sq.mm m 2,035.00
1637 11kV XLPE Aluminium Cable, 1 Core, 240 sq.mm m 1,201.00
1638 11kV XLPE Aluminium Cable, 1 Core, 185 sq.mm m 1,159.00
1639 11kV XLPE Aluminium Cable, 1 Core, 150 sq.mm m 1,138.00
1640 11kV XLPE Aluminium Cable, 1 Core, 120 sq.mm m 1,100.00
1641 11kV XLPE Aluminium Cable, 1 Core, 100 sq.mm m 1,083.00
1642 11kV XLPE Aluminium Cable, 1 Core, 95 sq.mm m 1,024.00
1643 PVC Insulated Copper Cable, 35.0 sq.mm m 550.00
1701 Aluminium Cable Lug long barrel , 10 Sq.mm No 5.00
Page 8 of 15
Sl. No Items Unit Rate/Unit
1702 Aluminium Cable Lug long barrel , 16 Sq.mm No 8.00
1703 Aluminium Cable Lug long barrel , 35 Sq.mm No 12.00
1704 Aluminium Cable Lug long barrel , 50 Sq.mm No 15.00
1705 Aluminium Cable Lug long barrel , 70Sq.mm No 30.00
1706 Aluminium Cable Lug long barrel , 95 Sq.mm No 35.00
1707 Aluminium Cable Lug long barrel , 120 Sq.mm No 42.00
1708 Aluminium Cable Lug long barrel , 150 Sq.mm No 53.00
1709 Aluminium Cable Lug long barrel , 185 Sq.mm No 68.00
1710 Aluminium Cable Lug long barrel , 225 Sq.mm No 83.00
1711 Aluminium Cable Lug long barrel , 300 Sq.mm No 115.00
1712 Aluminium Cable Lug long barrel , 400 Sq.mm No 165.00
1713 Aluminium Cable Lug long barrel , 630Sq.mm No 188.00
1714 T-Connector for 300 sq.mm Cable No 1,600.00
1715 T-Connector for 400 sq.mm Cable No 1,760.00
1716 T-Connector for 630 sq.mm Cable No 1,936.00
1717 Copper Cable Lug, Ring/Fork/Pin type, 2.5 sq.mm No 27.00
1718 Cable Ferrule, 2.5 sq.mm [A-Z] 100 each Packet 2,340.00
1719 Cable Ferrule, 2.5 sq.mm [0-9] 100 each Packet 900.00
1801
Porcelain Disc Insulator, 45 kN, conforming IS : 731
(1971), IS : 2486 (1989), IS : 2544 (1973), IS : 5350
(1973) or any amendments up to date.
No 519.00
1802
Porcelain Disc Insulator, 70 kN, conforming IS : 731
(1971), IS : 2486 (1989), IS : 2544 (1973), IS : 5350
(1973) or any amendments up to date.
No 700.00
1803
Porcelain Disc Insulator, 90 kN, conforming IS : 731
(1971), IS : 2486 (1989), IS : 2544 (1973), IS : 5350
(1973) or any amendments up to date.
No 959.44
1804
33kV Pin insulator with GI Pin conforming IS : 731
(1971), IS : 2486 (1989), IS : 2544 (1973), IS : 5350
(1973) or any amendments up to date.
Set 894.00
1805
11kV Pin insulator with GI Pin conforming IS : 731
(1971), IS : 2486 (1989), IS : 2544 (1973), IS : 5350
(1973) or any amendments up to date.
Set 354.00
1806
Shackle Insulator (Pin/Strap Type) 70x90 mm
conforming to IS : 1445 (1977) or any amendments up
to date
No 39.00
1807 Shackle Strap for 70x90 mm Shackle Insulator Pair 14.00
1808 Shackle Nut Bolt 12x100 mm(GI) kg 174.96
180911kV Guy insulator (140x85mm) conforming to IS :
5300 (1969) or any amendments up to date.No 57.00
181033kV Guy insulator (140x85mm) conforming to IS :
5300 (1969) or any amendments up to date.No 57.00
1811LT Guy insulator (90x65mm) conforming to IS : 5300
(1969) or any amendments up to date.No 28.50
1901
G.I. Stay Set complete 16 mm rod dia. with plate
30x30x0.8 cm conforming to IS : 7887 (1992) or any
amendments up to date.
Set 810.00
1902
G.I. Stay set complete 19 mm rod dia. with plate
30x30x0.8 cm conforming to IS : 7887 (1992) or any
amendments up to date.
Set 1,407.00
Page 9 of 15
Sl. No Items Unit Rate/Unit
1903
G.I. Stay set complete 19 mm rod dia. with plate
40x40x0.8 cm conforming to IS : 7887 (1992) or any
amendments up to date.
Set 1,694.00
1904
Stay wire 7/12 SWG conforming to IS : 2141 (1979), IS :
4826 (1979), IS : 6594 (1974) or any amendments up to
date.
kg 112.50
1905
Stay wire 7/14 SWG conforming to IS : 2141 (1979), IS :
4826 (1979), IS : 6594 (1974) or any amendments up to
date.
kg 118.50
1906
G.I Wire 8 SWG for earth wire conforming to IS : 280
(1978), IS : 7887 (1992) or any amendments up to date. kg 112.50
1907
Stay wire 7/10 SWG conforming to IS : 2141 (1979), IS :
4826 (1979), IS : 6594 (1974) or any amendments up to
date.
kg 116.00
2001
Tension Clamp with hardware strain fitting, 4-bolted
type complete with bolts, nuts, and washer (Racoon) No 474.00
2002
Tension Clamp with hardware strain fitting, 3-bolted
type complete with bolts, nuts, and washer (Weasel) No 445.00
2003P.G. Clamp for Grasshopper conductor (3 bolted type)
No 82.00
2004 P.G. Clamp for Ant conductor (2 bolted type) No 79.00
2005 P.G. Clamp for Gnat conductor (2 bolted type) No 72.00
2006 P.G. Clamp for Weasel conductor (3 bolted type) No 75.00
2007 P.G. Clamp for Racoon conductor (3 bolted type) No 112.50
2008 Jointing Sleeve for Weasel conductor No 265.00
2009 Jointing Sleeve for Racoon conductor No 354.00
2010 LT Cable Jointing Kit No 2,770.00
2011Cable Gland for 2.5 sq.mm, 16 Core Copper Control
CableNo 52.50
2012Cable Gland for 2.5 sq.mm, 12 Core Copper Control
CableNo 52.50
2013Cable Gland for 2.5 sq.mm, 6 Core Copper Control
CableNo 52.50
2014Cable Gland for 2.5 sq.mm, 4 Core Copper Control
CableNo 45.00
2015Cable Gland for 2.5 sq.mm, 2 Core Copper Control
CableNo 45.00
2016Cable Jointing Kit for 3 Core, 11kV XLPE Al. Cable, 185
sq.mm No 4,550.00
2017Cable Jointing Kit for 3 Core, 11kV XLPE Al. Cable, 150
sq.mm No 4,550.00
2018Cable Jointing Kit for 3 Core, 11kV XLPE Al. Cable, 120
sq.mm No 4,550.00
2019Cable Jointing Kit for 1 Core, 11kV XLPE Al. Cable,
1000 sq.mm No 15,000.00
2020Cable Jointing Kit for 1 Core, 11kV XLPE Al. Cable, 600
sq.mm No 13,500.00
2021Cable Jointing Kit for 1 Core, 11kV XLPE Al. Cable, 400
sq.mm No 9,200.00
Page 10 of 15
Sl. No Items Unit Rate/Unit
2022Cable Jointing Kit for 1 Core, 11kV XLPE Al. Cable, 240
sq.mm No 4,970.00
2023Cable Jointing Kit for 1 Core, 11kV XLPE Al. Cable, 185
sq.mm No 4,550.00
2024Cable Jointing Kit for 1 Core, 11kV XLPE Al. Cable, 150
sq.mm No 4,550.00
2025Cable Jointing Kit for 1 Core, 11kV XLPE Al. Cable, 120
sq.mm No 4,550.00
2026Cable Jointing Kit for 1 Core, 11kV XLPE Al. Cable, 100
sq.mm No 4,450.00
2027Cable Jointing Kit for 1 Core, 11kV XLPE Al. Cable, 95
sq.mm No 4,450.00
2101
M.S. Nut & Bolt 16x75 mm full thread conforming to IS :
1364-2 (1992) or any amendments up to date. kg 162.00
2102
M.S. Nut & Bolt 16x50 mm full thread conforming to IS :
1364-2 (1992) or any amendments up to date. kg 162.00
2103
M.S. Nut & Bolt 16 x 155 mm full thread conforming to
IS : 1364-2 (1992) or any amendments up to date. kg 162.00
2104
M.S. Nut & Bolt 16 x 125 mm, Full thread conforming to
IS : 1364-2 (1992) or any amendments up to date. kg 162.00
2105
M.S. Nut & Bolt 16 x 175 mm, Full thread conforming to
IS : 1364-2 (1992) or any amendments up to date. kg 162.00
2106
M.S. Nut & Bolt 12 x 50 mm, Full thread conforming to
IS : 1364-2 (1992) or any amendments up to date. kg 162.00
2107
M.S. Washer for 16 mm diameter hole conforming to IS :
1364-2 (1992) or any amendments up to date. kg 132.00
2108
M.S. Nut & Bolt 16x50 mm full thread conforming to IS :
1364-2 (1992) or any amendments up to date. kg 162.00
2109 Brass Nuts & Bolt 16 x 50mm full tread Kg 250.00
2201 Aluminium Paint Lit 170.00
2202 Bituminious Alkali Paint Lit 120.00
2203 Red Oxide Paint Lit 125.00
2301 Cement cum 13,750.00
2302 River Sand cum 2,100.00
2303 Stone Aggregate 10-20 mm cum 1,890.00
2304GCI Sheet, 6 x 3 ft. conforming to IS : 277 (2003) or any
amendments up to date.No 375.00
2305 First class brick 203 x 101 x 76.2 mm No 20.00
2305 Bentonite Powder kg 30.00
2307 Binding wire kg 120.00
2308 Stone Masonry (8x5x5 inch) No 52.50
2306 Blasted Rubble cum 600.00
Page 11 of 15
Sl. No Items Unit Rate/Unit
2307 Through and bond stone cum 2,500.00
2308 Cement mortar 1:3 cum 5,914.40
2309 Hot rolled deformed bars (Iron rod) kg 58.00
2310 1st Class Brick No 21.00
2311 Cement mortar 1:4 cum 4,739.50
2312 Stone Gravel (50 - 30mm size) Cum 5,100.00
2313 Stone Aggregate 50-30 mm Cum 1,075.00
2401 Caution notice board No 42.00
2402 Number plate No 42.00
2403 Wooden Plank (12x1 sq.ft.) No 1,000.00
2501
Lightning Spike made of iron rod,10 mm size, 1.5 m
length, 1 kg welded with MS Flat iron 40x5mm, 0.5kg
and 8 SWG GI wire 2.5kg
No 500.00
2502
Galvanized steel rod, 2 M length, 19 mm dia connected
with GI Wire complete with terminal connector No 850.00
2503
GI Earth pipe 2.5 metre long 40 mm dia with 8 mm
thickness fabricated for pole earthing complete with
terminal connector
No 543.00
2504Readymade fencing post 50 x 50x 6 mm, 2.7 m length
No 1,064.00
2505 Barbed wire kg 153.00
2506Goat proof fencing net, double twisted, 1 x 1 m with hole
size 50 x 50 mmm 166.00
2507 Steel Gate 1.5 m widthx 2 m height No 5,000.00
2504GI Pipe 40mm dia, 4.13m long with a GI base plate of
30x30x0.5cm welded at the bottomNo 2,742.59
2601
Outdoor type CT & PT combination with PT ratio
11/0.415 kV, for all rating of CT ratio as required by HT
side Ampere
No 70,000.00
2602
Outdoor type CT & PT combination with PT ratio
11/0.11 kV, for all rating of CT ratio as required by HT
side Ampere
No 70,000.00
2603
3-ph 4 wire Trivector Meter suitable for Automatic Meter
Reading (AMR), PTR 11/0.415kV, for all rating of CT
Ratio.
No 13,500.00
2604
3-ph 4 wire Trivector Meter suitable for Automatic Meter
Reading (AMR), PTR 11/0.11kV, for all rating of CT
Ratio.
No 13,500.00
2605
LT Outdoor DT Cubicle complete with MCCB, St light
Controller, metering system for both St light and
Consumer for 25kVA, 11/0.415 kV Transformer
No 53,235.00
2606
LT Outdoor DT Cubicle complete with MCCB, St light
Controller, metering system for both St light and
Consumer for 63kVA, 11/0.415 kV Transformer
No 56,778.75
2607
LT Outdoor DT Cubicle complete with MCCB, St light
Controller, metering system for both St light and
Consumer for 100kVA, 11/0.415 kV TransformerNo 62,685.00
Page 12 of 15
Sl. No Items Unit Rate/Unit
2608
LT Outdoor DT Cubicle complete with MCCB, Consumer
metering system for 25kVA, 11/0.415 kV Transformer No 35,437.50
2609
LT Outdoor DT Cubicle complete with MCCB, Consumer
metering system for 63kVA, 11/0.415 kV Transformer No 38,981.25
2610
LT Outdoor DT Cubicle complete with MCCB, Consumer
metering system for 100kVA, 11/0.415 kV Transformer No 44,887.50
2611
Housing Cabinet for Trivertor Meter for all ratio of PTR
and CTR with suitable clamp in steel tabular pole No 1,500.00
2701
3 phase HRC Main Switch, 63 A conforming to IEC :
60947 (Part 3) - 1999 or any ammendments up to date. No 4,977.00
2702
3 phase HRC Main Switch, 100 A conforming to IEC :
60947 (Part 3) - 1999 or any ammendments up to date. No 6,678.00
2703
3 phase HRC Main Switch, 125 A conforming to IEC :
60947 (Part 3) - 1999 or any ammendments up to date. No 8,587.50
2704
3phase HRC Main Switch, 150 A conforming to IEC :
60947 (Part 3) - 1999 or any ammendments up to date. No 10,832.00
2705
3 phase HRC Main Switch, 200 A conforming to IEC :
60947 (Part 3) - 1999 or any ammendments up to date. No 12,300.00
2706
3 phase HRC Main Switch, 250 A conforming to IEC :
60947 (Part 3) - 1999 or any ammendments up to date. No 13,575.00
2707
3phase HRC Main Switch, 300 A conforming to IEC :
60947 (Part 3) - 1999 or any ammendments up to date. No 14,850.00
2708
3phase HRC Main Switch, 400 A conforming to IEC :
60947 (Part 3) - 1999 or any ammendments up to date. No 16,430.40
2709
3phase HRC Main Switch, 500 A conforming to IEC :
60947 (Part 3) - 1999 or any ammendments up to date. No 22,554.00
2710
3phase HRC Main Switch, 630 A conforming to IEC :
60947 (Part 3) - 1999 or any ammendments up to date. No 25,956.00
2711 Cut out, 32 A with suitable fuse No 325.00
2712 Cut out, 63 A with suitable fuse No 650.00
2713 Cut out, 100 A with suitable fuse No 868.00
2714 Cut out, 200 A with suitable fuse No 1,750.00
2715 Cut out, 400 A with suitable fuse No 2,100.00
2716 Cut out, 500 A with suitable fuse No 2,100.00
2717
415V, 3 phase Air break Manual Switch, 125A
conforming to IEC : 60947 (Part 3) - 1999 or any
ammendments up to date.
No 7,965.00
Page 13 of 15
Sl. No Items Unit Rate/Unit
2718
415V, 3 phase Air break Manual Switch, 250A
conforming to IEC : 60947 (Part 3) - 1999 or any
ammendments up to date.
No 14,337.00
2719
415V, 3 phase Air break Manual Switch, 400A
conforming to IEC : 60947 (Part 3) - 1999 or any
ammendments up to date.
No 16,915.00
2801HRC Fuse, 63 A, conforming to IS : 13703 - 1993 or any
ammendments up to date.No 570.00
2802HRC Fuse, 100 A, conforming to IS : 13703 - 1993 or
any ammendments up to date.No 1,020.00
2803HRC Fuse, 125 A, conforming to IS : 13703 - 1993 or
any ammendments up to date.No 1,177.50
2804HRC Fuse, 150 A, conforming to IS : 13703 - 1993 or
any ammendments up to date.No 1,335.00
2805HRC Fuse, 200 A, conforming to IS : 13703 - 1993 or
any ammendments up to date.No 1,650.00
2806HRC Fuse, 250 A, conforming to IS : 13703 - 1993 or
any ammendments up to date.No 1,765.50
2807HRC Fuse, 300 A, conforming to IS : 13703 - 1993 or
any ammendments up to date.No 1,881.00
2808HRC Fuse, 400 A, conforming to IS : 13703 - 1993 or
any ammendments up to date.No 4,500.00
2809HRC Fuse, 500 A, conforming to IS : 13703 - 1993 or
any ammendments up to date.No 4,650.00
2810HRC Fuse, 630 A, conforming to IS : 13703 - 1993 or
any ammendments up to date.No 8,700.00
2811Tinned Copper Fuse Wire, 2.5 A, conforming to IS : 9926
- 1981 or any ammendments up to date.kg 1,040.00
2812Tinned Copper Fuse Wire, 5 A, conforming to IS : 9926 -
1981 or any ammendments up to date.kg 1,040.00
2813Tinned Copper Fuse Wire, 10 A, conforming to IS : 9926 -
1981 or any ammendments up to date.kg 1,040.00
2814Tinned Copper Fuse Wire, 15 A, conforming to IS : 9926 -
1981 or any ammendments up to date.kg 1,040.00
2815Tinned Copper Fuse Wire, 20 A, conforming to IS : 9926 -
1981 or any ammendments up to date.kg 1,040.00
2816Tinned Copper Fuse Wire, 25 A, conforming to IS : 9926 -
1981 or any ammendments up to date.kg 1,040.00
2817Tinned Copper Fuse Wire, 30 A, conforming to IS : 9926 -
1981 or any ammendments up to date.kg 1,040.00
2818Tinned Copper Fuse Wire, 35 A, conforming to IS : 9926 -
1981 or any ammendments up to date.kg 1,040.00
2819Tin-Copper Fuse Wire, 40 A, conforming to IS : 9926 -
1981 or any ammendments up to date.kg 1,040.00
2820 EADC Fuse, 2.5 A doz. 410.00
2821 EADC Fuse, 5 A doz. 410.00
2822 EADC Fuse, 10 A doz. 410.00
2823 EADC Fuse, 15 A doz. 410.00
2824 EADC Fuse, 20 A doz. 425.00
2825 EADC Fuse, 25 A doz. 425.00
2826 EADC Fuse, 30 A doz. 425.00
2827 EADC Fuse, 35 A doz. 425.00
Page 14 of 15
Sl. No Items Unit Rate/Unit
2828 EADC Fuse, 40 A doz. 425.00
2829 11 kV Fibre Barrel with metallic parts No 315.00
2830 33 kV Fibre Barrel with metallic parts No 375.00
2901
11 kV Gang Operated Air Break Switch, 200 A,
conforming to IS : 2544 - 1973, IS : 9921 (Part I-V) or
any ammendments up to date
Set 14,490.00
2902
11 kV Fuse Unit with Arcing Horn, 200 A, conforming to
9385 (Part 2) - 1980 ammended up to date Set 7,087.50
2903
Horizontally operated Single break 11 kV Isolator
complete with Drop out Fuse unit, conforming to IS :
9921 and any other relevant standards ammended up to
date.
Set 34,650.00
3201
HPSV Lamp Street Light Fittings complete with Choke,
Condenser, Holder and Ignitor, 250 W, conforming to IS
: 10322 - 2012, IS : 2215 - 2006 and any other relevant
standards with amendments up to date.
Set 6,850.00
3202
HPSV Lamp Street Light Fittings complete with Choke,
Condenser, Holder and Ignitor, 150 W, conforming to IS
: 10322 - 2012, IS : 2215 - 2006 and any other relevant
standards with amendments up to date.
Set 6,165.00
3203
HPSV Lamp, 250 W, conforming to IS : 10322 - 2012
and any other relevant standards with amendments up
to date.
No 1,950.00
3204 Street Light Bracket No 590.00
3205D-Clamp for Street Light Bracket complete with Nuts &
BoltsSet 139.00
Page 15 of 15
Page No -1-
POLE (SP-29) ERECTION
1.02 Providing and erection of steel tubular pole (SP-29) strut in cement concrete 1:3:6
(1cement : 3 coarse sand: 6 graded stone aggregate 40 mm nominal size ) found ation
(0.342Cum inclusive of muffling) with planting depth of 1 .5m including pole painting;
excavation and back filling of pole pit; carriage of Materials at site as directed by the
engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
1102
Swaged Steel Pole with base
plate of thickness 6mm and
size of 200mmx200mm square
welded at the bottom and with
pole cap of 6mm thick to be
welded at the top conforming
to IS 2713/1980 or the latest
version thereof 410 SP-29 of
overall length 9.00m
No 12,656.25 1.00 12,656.25
2201 Aluminium Paint Lit 170.00 0.95 161.50
2202 Bituminious Alkali Paint Lit 120.00 0.48 57.60
2203 Red Oxide Paint Lit 125.00 0.95 118.75
2301 Cement cum 13,750.00 0.03 470.25
2302 River Sand cum 2,100.00 0.10 215.46
2303 Stone Aggregate 10-20 mm cum 1,890.00 0.21 387.83
2403 Wooden Plank (12x1 sq.ft.) No 1,000.00 2.00 2,000.00
2401 Caution notice board No 42.00 1.00 42.00
2402 Number plate No 42.00 1.00 42.00
Total Cost of Materials 16,151.64
Contingency (2% on Material Cost) 323.03
Sub-Total 16,474.67
Labours
1001 Labour Skilled-I manday 380 0.50 190.00
1002 Labour Skilled-II manday 310 0.50 155.00
1003 Labour Semi-Skilled manday 250 1.00 250.00
1004 Labour Un-skilled manday 220 10.67 2,346.67
Total Cost of Labours 2,941.67
Total 19,416.34
Add 15% for overhead & Profit 2,912.45
Grand Total 22,328.79
Say 22,329.00
Supervision (15% on Labour Cost) 441.25
Page No -2-
POLE (SP-35) ERECTION
1.03 Providing and erection of steel tubular pole (SP-35) strut in cement concrete 1:3:6
(1cement : 3 coarse sand: 6 graded stone aggregate 40 mm nominal size ) foundation
(0.395Cum inclusive of muffling) with planting depth of 1.8m including pole painting;
excavation and back filling of pole pit; carriage of Materials at site as directed by the
engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
1103
Swaged Steel Pole with base
plate of thickness 6mm and
size of 200mmx200mm square
welded at the bottom and with
pole cap of 6mm thick to be
welded at the top conforming
to IS 2713/1980 or the latest
version thereof 410 SP-35 of
overall length 9.50m
No 13,061.25 1.00 13,061.25
2201 Aluminium Paint Lit 170.00 1.00 170.00
2202 Bituminious Alkali Paint Lit 120.00 0.50 60.00
2203 Red Oxide Paint Lit 125.00 1.00 125.00
2301 Cement cum 13,750.00 0.04 543.13
2302 River Sand cum 2,100.00 0.12 248.85
2303 Stone Aggregate 10-20 mm cum 1,890.00 0.24 447.93
2403 Wooden Plank (12x1 sq.ft.) No 1,000.00 2.00 2,000.00
2401 Caution notice board No 42.00 1.00 42.00
2402 Number plate No 42.00 1.00 42.00
Total Cost of Materials 16,740.16
Contingency (2% on Material Cost) 334.80
Sub-Total 17,074.96
Labours
1001 Labour Skilled-I manday 380.00 0.50 190.00
1002 Labour Skilled-II manday 310.00 0.50 155.00
1003 Labour Semi-Skilled manday 250.00 1.00 250.00
1004 Labour Un-skilled manday 220.00 13.03 2,867.33
Total Cost of Labours 3,462.33
Total 20,537.29
Add 15% for overhead & Profit 3,080.59
Grand Total 23,617.89
Say 23,618.00
Supervision (15% on Labour Cost) 519.35
Page No -3-
POLE (SP-58) ERECTION
1.04 Providing and erection of steel tubular pole (SP-58) strut in cement concrete 1:3:6
(1cement : 3 coarse sand: 6 graded stone aggregate 40 mm nominal size ) foundation
(0.465Cum inclusive of muffling) with planting depth of 2m including pole painting;
excavation and back filling of pole pit; carriage of Materials at site as directed by the
engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
1104
Swaged Steel Pole with base
plate of thickness 6mm and
size of 200mmx200mm square
welded at the bottom and with
pole cap of 6mm thick to be
welded at the top conforming
to IS 27 13/1980 or the latest
version thereof 410 SP-58 of
overall length 12.00m
No 18,832.50 1.00 18,832.50
2201 Aluminium Paint Lit 170.00 1.10 187.00
2202 Bituminious Alkali Paint Lit 120.00 0.55 66.00
2203 Red Oxide Paint Lit 125.00 1.10 137.50
2301 Cement cum 13,750.00 0.05 639.38
2302 River Sand cum 2,100.00 0.14 292.95
2303 Stone Aggregate 10-20 mm cum 1,890.00 0.28 527.31
2403 Wooden Plank (12x1 sq.ft.) No 1,000.00 2.00 2,000.00
2401 Caution notice board No 42.00 1.00 42.00
2402 Number plate No 42.00 1.00 42.00
Total Cost of Materials 22,766.64
Contingency (2% on Material Cost) 455.33
Sub-Total 23,221.97
Labours
1001 Labour Skilled-I manday 380 0.50 190.00
1002 Labour Skilled-II manday 310 0.50 155.00
1003 Labour Semi-Skilled manday 250 1.00 250.00
1004 Labour Un-skilled manday 220 15.75 3,465.00
Total Cost of Labours 4,060.00
Total 27,281.97
Add 15% for overhead & Profit 4,092.30
Grand Total 31,374.26
Say 31,374.00
Supervision (15% on Labour Cost) 609.00
Page No -4-
POLE (Pre-Stressed Concrete for a length of 8.5 metre) ERECTION
1.05 Providing and erection of Pre-Stressed Concrete for a length of 8.5 metre in cement
concrete 1:3:6 (1 cement: 3 coarse sand : 6 graded stone aggregate 40 mm nominal
size) foundation (0.573 Cum inclusive of muffling) with planting depth of 1.5m
including excavation and back filling of pole pit; carriage of Materials at site as
directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
1105 Pre stressed Concrete Pole: 8.5m No 5,828.00 1.00 5,828.00
2301 Cement cum 13,750.00 0.06 787.88
2302 River Sand cum 2,100.00 0.17 360.99
2303 Stone Aggregate 10-20 mm cum 1,890.00 0.34 649.78
2403 Wooden Plank (12x1 sq.ft.) No 1,000.00 2.00 2,000.00
2401 Caution notice board No 42.00 1.00 42.00
2402 Number plate No 42.00 1.00 42.00
Total Cost of Materials 9,710.65
Contingency (2% on Material Cost) 194.21
Sub-Total 9,904.86
Labours
1001 Labour Skilled-I manday 380.00 0.50 190.00
1002 Labour Skilled-II manday 310.00 0.50 155.00
1003 Labour Semi-Skilled manday 250.00 1.00 250.00
1004 Labour Un-skilled manday 220.00 13.67 3,006.67
Total Cost of Labours 3,601.67
Total 13,506.53
Add 15% for overhead & Profit 2,025.98
Grand Total 15,532.51
Say 15,533.00
Supervision (15% on Labour Cost) 540.25
Page No -5-
POLE (Pre-Stressed Concrete for a length of 9.75 metre) ERECTION
1.06 Providing and erection of Pre-Stressed Concrete for a length of 9.75 metre in cement
concrete 1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 40 mm nominal
size) foundation (0.797Cum inclusive of muffling) with planting depth of 1.8m
including excavation and back filling of pole pit; carriage of Materials at site as
directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
1106 Pre stressed Concrete Pole:
9.75m No 8190.00
1.00 8190.00
2301 Cement cum 13,750.00 0.08 1,095.88
2302 River Sand cum 2,100.00 0.24 502.11
2303 Stone Aggregate 10-20 mm cum 1,890.00 0.48 903.80
2403 Wooden Plank (12x1 sq.ft.) No 1,000.00 2.00 2,000.00
2401 Caution notice board No 42.00 1.00 42.00
2402 Number plate No 42.00 1.00 42.00
Total Cost of Materials 12,775.78
Contingency (2% on Material Cost) 255.52
Sub-Total 13,031.30
Labours
1001 Labour Skilled-I manday 380.00 0.50 190.00
1002 Labour Skilled-II manday 310.00 0.50 155.00
1003 Labour Semi-Skilled manday 250.00 1.00 250.00
1004 Labour Un-skilled manday 220.00 16.67 3,666.67
Total Cost of Labours 4,261.67
Total 17,292.97
Add 15% for overhead & Profit 2,593.94
Grand Total 19,886.91
Say 19,887.00
Supervision (15% on Labour Cost) 639.25
Page No -6-
Page No -7-
GALVANISED STEEL TABULAR POLE (SP-29) ERECTION
1.08 Providing and erection of Galvanised steel tubular pole (SP-29) strut in cement concrete
1:3:6 (1 cement: 3 coarse sand : 6 graded stone aggregate 40 mm nominal size)
foundation (0.342Cum inclusive of muffling) with planting depth of 1 .5m including pole
painting; excavation and back filling of pole pit; carriage of Materials at site as directed
by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
1108
Galvanised Swaged Steel Pole
with base plate of thickness
6mm and size of
200mmx200mm square welded
at the bottom and with pole cap
of 6mm thick to be welded at the
top conforming to IS 2713/1980
or the latest version thereof 410
SP-29 of overall length 9.00m
No 18,900.00 1.00 18,900.00
2201 Aluminium Paint Lit 170.00 0.95 161.50
2202 Bituminious Alkali Paint Lit 120.00 0.48 57.60
2203 Red Oxide Paint Lit 125.00 0.95 118.75
2301 Cement cum 13,750.00 0.03 470.25
2302 River Sand cum 2,100.00 0.10 215.46
2303 Stone Aggregate 10-20 mm cum 1,890.00 0.21 387.83
2403 Wooden Plank (12x1 sq.ft.) No 1,000.00 2.00 2,000.00
2401 Caution notice board No 42.00 1.00 42.00
2402 Number plate No 42.00 1.00 42.00
Total Cost of Materials 22,395.39
Contingency (2% on Material Cost) 447.91
Sub-Total 22,843.30 Labours
1001 Labour Skilled-I manday 380.00 0.50 190.00
1002 Labour Skilled-II manday 310.00 0.50 155.00
1003 Labour Semi-Skilled manday 250.00 1.00 250.00
1004 Labour Un-skilled manday 220.00 10.67 2,346.67
Total Cost of Labours 2,941.67
Total 25,784.96
Add 15% for overhead & Profit 3,867.74
Grand Total 29,652.71
Say 29,653.00
Supervision (15% on Labour Cost) 441.25
Page No -8-
Page No -9-
Page No -10-
FITTING OF CROSSARM
2.01 Providing and fitting of horizontal Brackets with MS Angle Iron 40 mm X 40 mm X 6
mm (3.5Kg per metre) for 3 phase 5 wires LT overhead line conductors complete with
jam clamp, bolts and nuts for clamping to the poles including drilling of holes for
insulator pins/fitting bolts, nuts and washers etc and painting with primer and
finished paint as required (For SP- 17) as directed by the engineer in charge..
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials 1403 M.S. Angle Iron 40x40x6 mm kg 105.84 5.89 623.45
1405 M.S. Flat Iron 40mmx6 mm kg 105.84 1.78 187.95
21 02
M.S. Nut & Bolt 16x50 mm full
thread conforming to IS : 1 364- 2
(1992) or any amendments up to
date.
kg 162.00 0.88 141.91
21 07
M.S. Washer for 16 mm
diameter hole conforming to IS
: 1364-2 (1992) or any
amendments up to date.
kg 132.00 0.05 6.60
2201 Aluminium Paint Lit 170.00 0.30 51.00
2203 Red Oxide Paint Lit 125.00 0.30 37.50
Total Cost of Materials 1,048.41
Contingency (2% on Material Cost) 20.97
Sub-Total 1,069.38
Labours
1001 Labour Skilled-I manday 380.00 0.44 167.20
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.11 26.67
1004 Labour Un-skilled manday 220.00 0.75 164.27
Total Cost of Labours 358.13
Total 1,427.51
Add 15% for overhead & Profit 214.13
Grand Total 1,641.64
Say 1,642.00
Supervision (15% on Labour Cost) 53.72
Page No -11-
FITTING OF CROSSARM
2.02 Providing and fitting of Rectangular Brackets with MS Angle Iron 40 mm X 40 mm X 6
mm (3.5Kg per metre) for 3 phase 5 wires LT overhead line conductors complete with
jam clamp, bolts and nuts for clamping to the poles including drilling of holes for
insulator pins/fitting bolts, nuts and washers etc and painting with primer and
finished paint as required (For SP-17) as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials 1403 M.S. Angle Iron 40x40x6 mm kg 105.84 8.55 904.61
1405 M.S. Flat Iron 40mmx6 mm kg 105.84 1.18 125.30
21 02
M.S. Nut & Bolt 16x50 mm full
thread conforming to IS : 1 364- 2
(1992) or any amendments up to
date.
kg 162.00 0.58 94.61
21 07
M.S. Washer for 16 mm
diameter hole conforming to IS :
1364-2 (1992) or any
amendments up to date.
kg 132.00 0.05 6.60
2201 Aluminium Paint Lit 170.00 0.30 51.00
2203 Red Oxide Paint Lit 125.00 0.30 37.50
Total Cost of Materials 1,219.62
Contingency (2% on Material Cost) 24.39
Sub-Total 1,244.01
Labours
1001 Labour Skilled-I manday 380.00 0.27 101.20
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.07 16.58
1004 Labour Un-skilled manday 220.00 0.53 117.18
Total Cost of Labours 234.96
Total 1,478.97
Add 15% for overhead & Profit 221.85
Grand Total 1,700.82
Say 1,701.00
Supervision (15% on Labour Cost) 35.24
Page No -12-
FITTING OF CROSSARM
2.03 Providing and fitting of Single sided LT bracket with MS Angle Iron 40 mm X 40 mm X
6 mm (3.5Kg per metre) for 3 phase 5 wires LT overhead line conductors complete
with jam clamp, bolts and nuts for clamping to the poles including drilling of holes
for insulator pins/fitting bolts, nuts and washers etc and painting with primer and
finished paint as required (For SP-17) as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials 1403 M.S. Angle Iron 40x40x6 mm kg 105.84 8.96 948.74
1405 M.S. Flat Iron 40mmx6 mm kg 105.84 6.64 703.03
21 02
M.S. Nut & Bolt 16x50 mm full
thread conforming to IS : 1 364- 2
(1992) or any amendments up to
date.
kg 162.00 1.90 307.48
21 07
M.S. Washer for 16 mm
diameter hole conforming to IS :
1364-2 (1992) or any
amendments up to date.
kg 132.00 0.05 6.60
2201 Aluminium Paint Lit 170.00 0.30 51.00
2203 Red Oxide Paint Lit 125.00 0.30 37.50
Total Cost of Materials 2,054.35
Contingency (2% on Material Cost) 41.09
Sub-Total 2,095.44
Labours
1001 Labour Skilled-I manday 380.00 0.27 101.20
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.07 16.58
1004 Labour Un-skilled manday 220.00 0.53 117.18
Total Cost of Labours 234.96
Total 2,330.40
Add 15% for overhead & Profit 349.56
Grand Total 2,679.96
Say 2,680.00
Supervision (15% on Labour Cost) 35.24
Page No -13-
FITTING OF CROSSARM
2.04 Providing and fitting of Horizontal bracket with MS Angle Iron 40 mm X 40 mm X 6
mm (3.5Kg per metre) for 1 phase 3 wires LT overhead line conductors complete with
jam clamp, bolts and nuts for clamping to the poles including drilling of holes for
insulator pins/fitting bolts, nuts and washers etc and painting with primer and
finished paint as required (For SP-17) as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials 1403 M.S. Angle Iron 40x40x6 mm kg 105.84 3.93 415.63
1405 M.S. Flat Iron 40mmx6 mm kg 105.84 1.18 125.30
21 02
M.S. Nut & Bolt 16x50 mm full
thread conforming to IS : 1
364- 2 (1992) or any
amendments up to date.
kg 162.00 0.58 94.61
21 07
M.S. Washer for 16 mm
diameter hole conforming to IS
: 1364-2 (1992) or any
amendments up to date.
kg 132.00 0.05 6.60
2201 Aluminium Paint Lit 170.00 0.30 51.00
2203 Red Oxide Paint Lit 125.00 0.30 37.50
Total Cost of Materials 730.64
Contingency (2% on Material Cost) 14.61
Sub-Total 745.25
Labours
1001 Labour Skilled-I manday 380.00 0.27 101.20
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.07 16.58
1004 Labour Un-skilled manday 220.00 0.53 117.18
Total Cost of Labours 234.96
Total 980.21
Add 15% for overhead & Profit 147.03
Grand Total 1,127.24
Say 1,127.00
Supervision (15% on Labour Cost) 35.24
Page No -14-
FITTING OF CROSSARM
2.05 Providing and fitting of Horizontal Brackets with MS Angle Iron 40 mm X 40 mm X 6
mm (3.5Kg per metre) for 3 phase 5 wires LT overhead line conductors complete with
jam clamp, bolts and nuts for clamping to the poles including drilling of holes for
insulator pins/fitting bolts, nuts and washers etc and painting with primer and
finished paint as required (For SP-29) as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials 1403 M.S. Angle Iron 40x40x6 mm kg 105.84 5.89 623.45
1405 M.S. Flat Iron 40mmx6 mm kg 105.84 2.01 213.22
2102
M.S. Nut & Bolt 16x50 mm full
thread conforming to IS : 1364-
2 (1992) or any amendments up
to date.
kg 162.00 0.88 141.91
21 07
M.S. Washer for 16 mm
diameter hole conforming to IS
: 1364-2 (1992) or any
amendments up to date.
kg 132.00 0.05 6.60
2201 Aluminium Paint Lit 170.00 0.30 51.00
2203 Red Oxide Paint Lit 125.00 0.30 37.50
Total Cost of Materials 1,073.68
Contingency (2% on Material Cost) 21.47
Sub-Total 1,095.16
Labours
1001 Labour Skilled-I manday 380.00 0.44 167.20
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.11 26.67
1004 Labour Un-skilled manday 220.00 0.75 164.27
Total Cost of Labours 358.13
Total 1,453.29
Add 15% for overhead & Profit 217.99
Grand Total 1,671.28
Say 1,671.00
Supervision (15% on Labour Cost) 53.72
Page No -15-
FITTING OF CROSSARM
2.06 Providing and fitting of Rectangular Brackets with MS Angle Iron 40 mm X 40 mm X 6
mm (3.5Kg per metre) for 3 phase 5 wires LT overhead line conductors complete with
jam clamp, bolts and nuts for clamping to the poles including drilling of holes for
insulator pins/fitting bolts, nuts and washers etc and painting with primer and
finished paint as required (For SP-29) as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials 1403 M.S. Angle Iron 40x40x6 mm kg 105.84 8.55 904.61
1405 M.S. Flat Iron 40mmx6 mm kg 105.84 1.34 142.15
21 02
M.S. Nut & Bolt 16x50 mm full
thread conforming to IS : 1
364- 2 (1992) or any
amendments up to date.
kg 162.00 0.58 94.61
21 07
M.S. Washer for 16 mm
diameter hole conforming to IS
: 1364-2 (1992) or any
amendments up to date.
kg 132.00 0.05 6.60
2201 Aluminium Paint Lit 170.00 0.30 51.00
2203 Red Oxide Paint Lit 125.00 0.30 37.50
Total Cost of Materials 1,236.47
Contingency (2% on Material Cost) 24.73
Sub-Total 1,261.20
Labours
1001 Labour Skilled-I manday 380.00 0.27 101.20
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.07 16.58
1004 Labour Un-skilled manday 220.00 0.53 117.18
Total Cost of Labours 234.96
Total 1,496.16
Add 15% for overhead & Profit 224.42
Grand Total 1,720.58
Say 1,721.00
Supervision (15% on Labour Cost) 35.24
Page No -16-
FITTING OF CROSSARM
2.07 Providing and fitting of Single sided LT bracket with MS Angle Iron 40 mm X 40 mm X
6 mm (3.5Kg per metre) for 3 phase 5 wires LT overhead line conductors complete
with jam clamp, bolts and nuts for clamping to the poles including drilling of holes
for insulator pins/fitting bolts, nuts and washers etc and painting with primer and
finished paint as required (For SP-29) as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials 1403 M.S. Angle Iron 40x40x6 mm kg 105.84 9.11 964.39
1405 M.S. Flat Iron 40mmx6 mm kg 105.84 7.04 745.15
21 02
M.S. Nut & Bolt 16x50 mm full
thread conforming to IS : 1
364- 2 (1992) or any
amendments up to date.
kg 162.00 1.90 307.48
21 07
M.S. Washer for 16 mm
diameter hole conforming to IS
: 1364-2 (1992) or any
amendments up to date.
kg 132.00 0.05 6.60
2201 Aluminium Paint Lit 170.00 0.30 51.00
2203 Red Oxide Paint Lit 125.00 0.30 37.50
Total Cost of Materials 2,112.12
Contingency (2% on Material Cost) 42.24
Sub-Total 2,154.37
Labours
1001 Labour Skilled-I manday 380.00 0.27 101.20
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.07 16.58
1004 Labour Un-skilled manday 220.00 0.53 117.18
Total Cost of Labours 234.96
Total 2,389.32
Add 15% for overhead & Profit 358.40
Grand Total 2,747.72
Say 2,748.00
Supervision (15% on Labour Cost) 35.24
Page No -17-
FITTING OF CROSSARM
2.08 Providing and fitting of Horizontal bracket with MS Angle Iron 40 mm X 40 mm X 6
mm (3.5Kg per metre) for 1 phase 3 wires LT overhead line conductors complete with
jam clamp, bolts and nuts for clamping to the poles including drilling of holes for
insulator pins/fitting bolts, nuts and washers etc and painting with primer and
finished paint as required (For SP-29) as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials 1403 M.S. Angle Iron 40x40x6 mm kg 105.84 3.93 415.63
1405 M.S. Flat Iron 40mmx6 mm kg 105.84 1.34 142.15
21 02
M.S. Nut & Bolt 16x50 mm full
thread conforming to IS : 1
364- 2 (1992) or any
amendments up to date.
kg 162.00 0.58 94.61
21 07
M.S. Washer for 16 mm
diameter hole conforming to IS
: 1364-2 (1992) or any
amendments up to date.
kg 132.00 0.05 6.60
2201 Aluminium Paint Lit 170.00 0.30 51.00
2203 Red Oxide Paint Lit 125.00 0.30 37.50
Total Cost of Materials 747.49
Contingency (2% on Material Cost) 14.95
Sub-Total 762.44
Labours
1001 Labour Skilled-I manday 380.00 0.27 101.20
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.07 16.58
1004 Labour Un-skilled manday 220.00 0.53 117.18
Total Cost of Labours 234.96
Total 997.40
Add 15% for overhead & Profit 149.61
Grand Total 1,147.01
Say 1,147.00
Supervision (15% on Labour Cost) 35.24
Page No -18-
FITTING OF CROSSARM
2.09 Providing and fitting of Horizontal Brackets with MS Angle Iron 40 mm X 40 mm X 6
mm (3.5 Kg per metre) for 3 phase 5 wires LT overhead line conductors complete
with jam clamp, bolts and nuts for clamping to the poles including drilling of holes
for insulator pins/fitting bolts, nuts and washers etc and painting with primer and
finished paint as required (For Pre-Stressed Concrete 8.5 metres) as directed by the
engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials 1403 M.S. Angle Iron 40x40x6 mm kg 105.84 5.89 623.45
1405 M.S. Flat Iron 40mmx6 mm kg 105.84 3.14 331.95
2102
M.S. Nut & Bolt 16x50 mm full
thread conforming to IS : 1364-
2 (1992) or any amendments up
to date.
kg 162.00 0.88 141.91
21 07
M.S. Washer for 16 mm
diameter hole conforming to IS
: 1364-2 (1992) or any
amendments up to date.
kg 132.00 0.05 6.60
2201 Aluminium Paint Lit 170.00 0.30 51.00
2203 Red Oxide Paint Lit 125.00 0.30 37.50
Total Cost of Materials 1,192.41
Contingency (2% on Material Cost) 23.85
Sub-Total 1,216.26
Labours
1001 Labour Skilled-I manday 380.00 0.27 101.20
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.07 16.58
1004 Labour Un-skilled manday 220.00 0.53 117.18
Total Cost of Labours 234.96
Total 1,451.22
Add 15% for overhead & Profit 217.68
Grand Total 1,668.90
Say 1,669.00
Supervision (15% on Labour Cost) 35.24
Page No -19-
FITTING OF CROSSARM
2.10 Providing and fitting of Rectangular Brackets with MS Angle Iron 40 mm X 40 mm X
6 mm (3.5 Kg per metre) for 3 phase 5 wires LT overhead line conductors complete
with jam clamp, bolts and nuts for clamping to the poles including drilling of holes
for insulator pins/fitting bolts, nuts and washers etc and painting with primer and
finished paint as required (For Pre-Stressed Concrete 8.5 metres) as directed by the
engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials 1403 M.S. Angle Iron 40x40x6 mm kg 105.84 8.55 904.61
1405 M.S. Flat Iron 40mmx6 mm kg 105.84 2.09 221.30
21 02
M.S. Nut & Bolt 16x50 mm full
thread conforming to IS : 1 364-
2 (1992) or any amendments up
to date.
kg 162.00 0.58 94.61
21 07
M.S. Washer for 16 mm
diameter hole conforming to IS
: 1364-2 (1992) or any
amendments up to date.
kg 132.00 0.05 6.60
2201 Aluminium Paint Lit 170.00 0.30 51.00
2203 Red Oxide Paint Lit 125.00 0.30 37.50
Total Cost of Materials 1,315.62
Contingency (2% on Material Cost) 26.31
Sub-Total 1,341.93
Labours
1001 Labour Skilled-I manday 380.00 0.27 101.20
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.07 16.58
1004 Labour Un-skilled manday 220.00 0.53 117.18
Total Cost of Labours 234.96
Total 1,576.89
Add 15% for overhead & Profit 236.53
Grand Total 1,813.43
Say 1,813.00
Supervision (15% on Labour Cost) 35.24
Page No -20-
FITTING OF CROSSARM
2.11 Providing and fitting of Single sided Brackets with MS Angle Iron 40 mm X 40 mm X
6 mm (3.5 Kg per metre) for 3 phase 5 wires LT overhead line conductors complete
with jam clamp, bolts and nuts for clamping to the poles including drilling of holes
for insulator pins/fitting bolts, nuts and washers etc and painting with primer and
finished paint as required (For Pre-Stressed Concrete 8.5 metres) as directed by the
engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials 1403 M.S. Angle Iron 40x40x6 mm kg 105.84 10.09 1,068.42
1405 M.S. Flat Iron 40mmx6 mm kg 105.84 9.39 993.31
21 02
M.S. Nut & Bolt 16x50 mm full
thread conforming to IS : 1 364-
2 (1992) or any amendments up
to date.
kg 162.00 1.90 307.48
21 07
M.S. Washer for 16 mm
diameter hole conforming to IS
: 1364-2 (1992) or any
amendments up to date.
kg 132.00 0.05 6.60
2201 Aluminium Paint Lit 170.00 0.30 51.00
2203 Red Oxide Paint Lit 125.00 0.30 37.50
Total Cost of Materials 2,464.31
Contingency (2% on Material Cost) 49.29
Sub-Total 2,513.59
Labours
1001 Labour Skilled-I manday 380.00 0.27 101.20
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.07 16.58
1004 Labour Un-skilled manday 220.00 0.53 117.18
Total Cost of Labours 234.96
Total 2,748.55
Add 15% for overhead & Profit 412.28
Grand Total 3,160.83
Say 3,161.00
Supervision (15% on Labour Cost) 35.24
Page No -21-
FITTING OF CROSSARM
2.12 Providing and fitting of Horizontal Brackets with MS Angle Iron 40 mm X 40 mm X 6
mm (3.5 Kg per metre) for 1 phase 3 wires LT overhead line conductors complete
with jam clamp, bolts and nuts for clamping to the poles including drilling of holes
for insulator pins/fitting bolts, nuts and washers etc and painting with primer and
finished paint as required (For Pre-Stressed Concrete 8.5 metres) as directed by the
engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials 1403 M.S. Angle Iron 40x40x6 mm kg 105.84 3.93 415.63
1405 M.S. Flat Iron 40mmx6 mm kg 105.84 2.09 221.30
21 02
M.S. Nut & Bolt 16x50 mm full
thread conforming to IS : 1
364- 2 (1992) or any
amendments up to date.
kg 162.00 0.58 94.61
21 07
M.S. Washer for 16 mm
diameter hole conforming to IS
: 1364-2 (1992) or any
amendments up to date.
kg 132.00 0.05 6.60
2201 Aluminium Paint Lit 170.00 0.30 51.00
2203 Red Oxide Paint Lit 125.00 0.30 37.50
Total Cost of Materials 826.64
Contingency (2% on Material Cost) 16.53
Sub-Total 843.17
Labours
1001 Labour Skilled-I manday 380.00 0.27 101.20
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.07 16.58
1004 Labour Un-skilled manday 220.00 0.53 117.18
Total Cost of Labours 234.96
Total 1,078.13
Add 15% for overhead & Profit 161.72
Grand Total 1,239.85
Say 1,240.00
Supervision (15% on Labour Cost) 35.24
Page No -22-
FITTING OF CROSSARM
2.13 Providing and fitting of Horizontal Brackets with MS Angle Iron 40 mm X 40 mm X 6
mm (3.5 Kg per metre) for 3 phase 5 wires LT overhead line conductors complete
with jam clamp, bolts and nuts for clamping to the poles including drilling of holes
for insulator pins/fitting bolts, nuts and washers etc and painting with primer and
finished paint as required (For Pre-Stressed Concrete 9.75 metres) as directed by
the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials 1403 M.S. Angle Iron 40x40x6 mm kg 105.84 5.89 623.45
1405 M.S. Flat Iron 40mmx6 mm kg 105.84 3.37 357.10
2102
M.S. Nut & Bolt 16x50 mm full
thread conforming to IS : 1364-
2 (1992) or any amendments up
to date.
kg 162.00 0.88 141.91
21 07
M.S. Washer for 16 mm
diameter hole conforming to IS
: 1364-2 (1992) or any
amendments up to date.
kg 132.00 0.05 6.60
2201 Aluminium Paint Lit 170.00 0.30 51.00
2203 Red Oxide Paint Lit 125.00 0.30 37.50
Total Cost of Materials 1,217.56
Contingency (2% on Material Cost) 24.35
Sub-Total 1,241.91
Labours
1001 Labour Skilled-I manday 380.00 0.27 101.20
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.07 16.58
1004 Labour Un-skilled manday 220.00 0.53 117.18
Total Cost of Labours 234.96
Total 1,476.87
Add 15% for overhead & Profit 221.53
Grand Total 1,698.40
Say 1,698.00
Supervision (15% on Labour Cost) 35.24
Page No -23-
FITTING OF CROSSARM
2.14 Providing and fitting of Rectangular Brackets with MS Angle Iron 40 mm X 40 mm X
6 mm (3.5 Kg per metre) for 3 phase 5 wires LT overhead line conductors complete
with jam clamp, bolts and nuts for clamping to the poles including drilling of holes
for insulator pins/fitting bolts, nuts and washers etc and painting with primer and
finished paint as required (For Pre-Stressed Concrete 9.75 metres) as directed by
the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials 1403 M.S. Angle Iron 40x40x6 mm kg 105.84 8.55 904.61
1405 M.S. Flat Iron 40mmx6 mm kg 105.84 2.25 238.06
21 02
M.S. Nut & Bolt 16x50 mm full
thread conforming to IS : 1
364- 2 (1992) or any
amendments up to date.
kg 162.00 0.58 94.61
21 07
M.S. Washer for 16 mm
diameter hole conforming to IS
: 1364-2 (1992) or any
amendments up to date.
kg 132.00 0.05 6.60
2201 Aluminium Paint Lit 170.00 0.30 51.00
2203 Red Oxide Paint Lit 125.00 0.30 37.50
Total Cost of Materials 1,332.39
Contingency (2% on Material Cost) 26.65
Sub-Total 1,359.03
Labours
1001 Labour Skilled-I manday 380.00 0.27 101.20
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.07 16.58
1004 Labour Un-skilled manday 220.00 0.53 117.18
Total Cost of Labours 234.96
Total 1,593.99
Add 15% for overhead & Profit 239.10
Grand Total 1,833.09
Say 1,833.00
Supervision (15% on Labour Cost) 35.24
Page No -24-
FITTING OF CROSSARM
2.15 Providing and fitting of Single sided Brackets with MS Angle Iron 40 mm X 40 mm X
6 mm (3.5 Kg per metre) for 3 phase 5 wires LT overhead line conductors complete
with jam clamp, bolts and nuts for clamping to the poles including drilling of holes
for insulator pins/fitting bolts, nuts and washers etc and painting with primer and
finished paint as required (For Pre-Stressed Concrete 9.75 metres) as directed by
the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials 1403 M.S. Angle Iron 40x40x6 mm kg 105.84 10.33 1,092.87
1405 M.S. Flat Iron 40mmx6 mm kg 105.84 9.79 1,036.28
21 02
M.S. Nut & Bolt 16x50 mm full
thread conforming to IS : 1 364-
2 (1992) or any amendments up
to date.
kg 162.00 1.90 307.48
21 07
M.S. Washer for 16 mm
diameter hole conforming to IS
: 1364-2 (1992) or any
amendments up to date.
kg 132.00 0.05 6.60
2201 Aluminium Paint Lit 170.00 0.30 51.00
2203 Red Oxide Paint Lit 125.00 0.30 37.50
Total Cost of Materials 2,531.73
Contingency (2% on Material Cost) 50.63
Sub-Total 2,582.36
Labours
1001 Labour Skilled-I manday 380.00 0.27 101.20
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.07 16.58
1004 Labour Un-skilled manday 220.00 0.53 117.18
Total Cost of Labours 234.96
Total 2,817.32
Add 15% for overhead & Profit 422.60
Grand Total 3,239.92
Say 3,240.00
Supervision (15% on Labour Cost) 35.24
Page No -25-
FITTING OF CROSSARM
2.16 Providing and fitting of Horizontal Brackets with MS Angle Iron 40 mm X 40 mm X 6
mm (3.5 Kg per metre) for 1 phase 3 wires LT overhead line conductors complete
with jam clamp, bolts and nuts for clamping to the poles including drilling of holes
for insulator pins/fitting bolts, nuts and washers etc and painting with primer and
finished paint as required (For Pre-Stressed Concrete 9.75 metres) as directed by
the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials 1403 M.S. Angle Iron 40x40x6 mm kg 105.84 3.93 415.63
1405 M.S. Flat Iron 40mmx6 mm kg 105.84 2.25 238.06
21 02
M.S. Nut & Bolt 16x50 mm full
thread conforming to IS : 1 364-
2 (1992) or any amendments up
to date.
kg 162.00 0.58 94.61
21 07
M.S. Washer for 16 mm
diameter hole conforming to IS
: 1364-2 (1992) or any
amendments up to date.
kg 132.00 0.05 6.60
2201 Aluminium Paint Lit 170.00 0.30 51.00
2203 Red Oxide Paint Lit 125.00 0.30 37.50
Total Cost of Materials 843.41
Contingency (2% on Material Cost) 16.87
Sub-Total 860.27
Labours
1001 Labour Skilled-I manday 380.00 0.27 101.20
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.07 16.58
1004 Labour Un-skilled manday 220.00 0.53 117.18
Total Cost of Labours 234.96
Total 1,095.23
Add 15% for overhead & Profit 164.28
Grand Total 1,259.52
Say 1,260.00
Supervision (15% on Labour Cost) 35.24
Page No -26-
FITTING OF CROSSARM
2.17 Providing and erection of 2 nos. of MS Channel Iron 75 mm X 40 mm X 6 mm (7.14Kg
per metre) double pole cross arm for three wire 11 kV overhead line conductors
(horizontal formation) complete with through bolts and nuts for clamping to the poles
including drilling of holes for insulator pins/fitting bolts, nuts and washers etc and
painting with primer and finished paint as required including angle iron
reinforcement (for SP-29) as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials 1401 M.S. Channel 75 x 40 x 6 mm kg 105.84 34.56 3,657.58
1405 M.S. Flat Iron 40mmx6 mm kg 105.84 3.16 334.59
1403 M.S. Angle Iron 40x40x6 mm kg 105.84 45.94 4,861.87
21 03
M.S. Nut & Bolt 16 x 155 mm
full thread conforming to IS :
1364-2 (1992) or any
amendments up to date.
kg 162.00 5.20 842.72
21 02
M.S. Nut & Bolt 16x50 mm full
thread conforming to IS : 1
364- 2 (1992) or any
amendments up to date.
kg 162.00 1.17 189.22
2203 Red Oxide Paint Lit 125.00 0.10 12.50
2201 Aluminium Paint Lit 170.00 0.10 17.00
Total Cost of Materials 9,915.47
Contingency (2% on Material Cost) 198.31
Sub-Total 10,113.78
Labours
1001 Labour Skilled-I manday 380.00 0.68 259.67
1002 Labour Skilled-II manday 310.00 0.25 77.50
1003 Labour Semi-Skilled manday 250.00 0.27 66.67
1004 Labour Un-skilled manday 220.00 2.10 462.00
Total Cost of Labours 865.83
Total 10,979.61
Add 15% for overhead & Profit 1,646.94
Grand Total 12,626.56
Say 12,627.00
Supervision (15% on Labour Cost) 129.88
Page No -27-
FITTING OF CROSSARM
2.18 Providing and erection of 4 nos. of MS Channel Iron 75 mm X 40mm X 6 mm
(7.14Kg per metre) double pole crossarm for three wire 11 kV overhead line
conductors (triangular formation) complete with through bolts and nuts for
clamping to the poles including drilling of holes for insulator pins/fitting bolts, nuts
and washers etc and painting with primer and finished paint as required (for SP-29)
as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials 1401 M.S. Channel 75 x 40 x 6 mm kg 105.84 44.61 4,721.60
1405 M.S. Flat Iron 40mmx6 mm kg 105.84 6.32 669.17
2103
M.S. Nut & Bolt 16 x 155 mm
full thread conforming to IS :
1364-2 (1992) or any
amendments up to date.
kg 162.00 3.67 594.86
21 02
M.S. Nut & Bolt 16x50 mm full
thread conforming to IS : 1
364- 2 (1992) or any
amendments up to date.
kg 162.00 2.34 378.43
2201 Aluminium Paint Lit 170.00 0.20 34.00
2203 Red Oxide Paint Lit 125.00 0.20 25.00
Total Cost of Materials 6,423.07
Contingency (2% on Material Cost) 128.46
Sub-Total 6,551.53
Labours
1001 Labour Skilled-I manday 380.00 1.37 519.33
1002 Labour Skilled-II manday 310.00 0.50 155.00
1003 Labour Semi-Skilled manday 250.00 0.53 133.33
1004 Labour Un-skilled manday 220.00 4.20 924.00
Total Cost of Labours 1,731.67
Total 8,283.19
Add 15% for overhead & Profit 1,242.48
Grand Total 9,525.67
Say 9,526.00
Supervision (15% on Labour Cost) 259.75
Page No -28-
FITTING OF CROSSARM
2.19 Providing and erection of 12 nos. of MS Channel Iron 75 mm X 40 mm X 6 mm (7.14Kg
per metre) triple pole crossarm for three wire 11 kV overhead line conductors complete
with through bolts and nuts for clamping to the poles including drilling of holes for
insulator pins/fitting bolts, nuts and washers etc and painting with primer and finished
paint as required (for SP-29) as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials 1401 M.S. Channel 75 x 40 x 6 mm kg 105.84 133.83 14,164.80
1405 M.S. Flat Iron 40mmx6 mm kg 105.84 18.97 2,007.51
21 03
M.S. Nut & Bolt 16 x 155 mm
full thread conforming to IS :
1364-2 (1992) or any
amendments up to date.
kg 162.00 11.02 1,784.59
21 02
M.S. Nut & Bolt 16x50 mm full
thread conforming to IS : 1
364- 2 (1992) or any
amendments up to date.
kg 162.00 7.01 1,135.30
2201 Aluminium Paint Lit 170.00 0.60 102.00
2203 Red Oxide Paint Lit 125.00 0.60 75.00
Total Cost of Materials 19,269.20
Contingency (2% on Material Cost) 385.38
Sub-Total 19,654.58
Labours
1001 Labour Skilled-I manday 380.00 5.00 1,900.00
1002 Labour Skilled-II manday 310.00 2.00 620.00
1003 Labour Semi-Skilled manday 250.00 2.00 500.00
1004 Labour Un-skilled manday 220.00 14.40 3,168.00
Total Cost of Labours 6,188.00
Total 25,842.58
Add 15% for overhead & Profit 3,876.39
Grand Total 29,718.97
Say 29,719.00
Supervision (15% on Labour Cost) 928.20
Page No -29-
FITTING OF CROSSARM
2.20 Providing and erection of 16 nos. of MS Channel Iron 75 mm X 40 mm X 6 mm (7.14Kg
per metre) four pole crossarm for three wire 11 kV overhead line conductors complete
with through bolts and nuts for clamping to the poles including drilling of holes for
insulator pins/fitting bolts, nuts and washers etc and painting with primer and finished
paint as required (for SP-29) as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials 1401 M.S. Channel 75 x 40 x 6 mm kg 105.84 178.44 18,886.39
1405 M.S. Flat Iron 40mmx6 mm kg 105.84 25.29 2,676.68
21 03
M.S. Nut & Bolt 16 x 155 mm
full thread conforming to IS :
1364-2 (1992) or any
amendments up to date.
kg 162.00 14.69 2,379.46
21 02
M.S. Nut & Bolt 16x50 mm full
thread conforming to IS : 1
364- 2 (1992) or any
amendments up to date.
kg 162.00 9.34 1,513.73
2201 Aluminium Paint Lit 170.00 0.80 136.00
2203 Red Oxide Paint Lit 125.00 0.80 100.00
Total Cost of Materials 25,692.26
Contingency (2% on Material Cost) 513.85
Sub-Total 26,206.11
Labours
1001 Labour Skilled-I manday 380.00 5.47 2,077.33
1002 Labour Skilled-II manday 310.00 2.00 620.00
1003 Labour Semi-Skilled manday 250.00 2.13 533.33
1004 Labour Un-skilled manday 220.00 16.80 3,696.00
Total Cost of Labours 6,926.67
Total 33,132.77
Add 15% for overhead & Profit 4,969.92
Grand Total 38,102.69
Say 38,103.00
Supervision (15% on Labour Cost) 1,039.00
Page No -30-
FITTING OF CROSSARM
2.21 Providing and erection of 2 nos. of MS Channel Iron 75 mmX 40mm X 6mm (7.14Kg
per metre) double pole crossarm for three wire 11 kV overhead line conductors
(horizontal formation) complete with through bolts and nuts for clamping to the poles
including drilling of holes for insulator pins/fitting bolts, nuts and washers etc and
painting with primer and finished paint as required including angle iron
reinforcement (for SP-35) as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials 1401 M.S. Channel 75 x 40 x 6 mm kg 105.84 34.56 3,657.58
1405 M.S. Flat Iron 40mmx6 mm kg 105.84 3.16 334.59
1403 M.S. Angle Iron 40x40x6 mm kg 105.84 45.94 4,861.87
21 03
M.S. Nut & Bolt 16 x 155 mm
full thread conforming to IS :
1364-2 (1992) or any
amendments up to date.
kg 162.00 5.20 842.72
21 02
M.S. Nut & Bolt 16x50 mm full
thread conforming to IS : 1
364- 2 (1992) or any
amendments up to date.
kg 162.00 1.17 189.22
2201 Aluminium Paint Lit 170.00 0.10 17.00
2203 Red Oxide Paint Lit 125.00 0.10 12.50
Total Cost of Materials 9,915.47
Contingency (2% on Material Cost) 198.31
Sub-Total 10,113.78
Labours
1001 Labour Skilled-I manday 380.00 0.68 259.67
1002 Labour Skilled-II manday 310.00 0.25 77.50
1003 Labour Semi-Skilled manday 250.00 0.27 66.67
1004 Labour Un-skilled manday 220.00 2.10 462.00
Total Cost of Labours 865.83
Total 10,979.61
Add 15% for overhead & Profit 1,646.94
Grand Total 12,626.56
Say 12,627.00
Supervision (15% on Labour Cost) 129.88
Page No -31-
FITTING OF CROSSARM
2.22 Providing and erection of 4 nos. of MS Channel Iron 75 mmX 40mm X6 mm (7.14Kg
per metre) double pole crossarm for three wire 11 kV overhead line conductors
(triangular formation) complete with through bolts and nuts for clamping to the
poles including drilling of holes for insulator pins/fitting bolts, nuts and washers
etc and painting with primer and finished paint as required (for SP-35) as directed
by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials 1401 M.S. Channel 75 x 40 x 6 mm kg 105.84 44.61 4,721.60
1405 M.S. Flat Iron 40mmx6 mm kg 105.84 6.32 669.17
21 03
M.S. Nut & Bolt 16 x 155 mm
full thread conforming to IS :
1364-2 (1992) or any
amendments up to date.
kg 162.00 3.67 594.86
21 02
M.S. Nut & Bolt 16x50 mm full
thread conforming to IS : 1 364-
2 (1992) or any amendments up
to date.
kg 162.00 2.34 378.43
2201 Aluminium Paint Lit 170.00 0.20 34.00
2203 Red Oxide Paint Lit 125.00 0.20 25.00
Total Cost of Materials 6,423.07
Contingency (2% on Material Cost) 128.46
Sub-Total 6,551.53
Labours
1001 Labour Skilled-I manday 380.00 1.37 519.33
1002 Labour Skilled-II manday 310.00 0.50 155.00
1003 Labour Semi-Skilled manday 250.00 0.53 133.33
1004 Labour Un-skilled manday 220.00 4.20 924.00
Total Cost of Labours 1,731.67
Total 8,283.19
Add 15% for overhead & Profit 1,242.48
Grand Total 9,525.67
Say 9,526.00
Supervision (15% on Labour Cost) 259.75
Page No -32-
FITTING OF CROSSARM
2.23 Providing and erection of 12 nos. of MS Channel Iron 75 mm X 40 mm X 6 mm (7.14Kg
per metre) triple pole crossarm for three wire 11 kV overhead line conductors complete
with through bolts and nuts for clamping to the poles including drilling of holes for
insulator pins/fitting bolts, nuts and washers etc and painting with primer and finished
paint as required (for SP-35) as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials 1401 M.S. Channel 75 x 40 x 6 mm kg 105.84 133.83 14,164.80
1405 M.S. Flat Iron 40mmx6 mm kg 105.84 18.97 2,007.51
21 03
M.S. Nut & Bolt 16 x 155 mm
full thread conforming to IS :
1364-2 (1992) or any
amendments up to date.
kg 162.00 11.02 1,784.59
2102
M.S. Nut & Bolt 16x50 mm full
thread conforming to IS : 1364-
2 (1992) or any amendments up
to date.
kg 162.00 7.01 1,135.30
2201 Aluminium Paint Lit 170.00 0.60 102.00
2203 Red Oxide Paint Lit 125.00 0.60 75.00
Total Cost of Materials 19,269.20
Contingency (2% on Material Cost) 385.38
Sub-Total 19,654.58
Labours
1001 Labour Skilled-I manday 380.00 5.00 1,900.00
1002 Labour Skilled-II manday 310.00 2.00 620.00
1003 Labour Semi-Skilled manday 250.00 2.00 500.00
1004 Labour Un-skilled manday 220.00 14.40 3,168.00
Total Cost of Labours 6,188.00
Total 25,842.58
Add 15% for overhead & Profit 3,876.39
Grand Total 29,718.97
Say 29,719.00
Supervision (15% on Labour Cost) 928.20
Page No -33-
FITTING OF CROSSARM
2.24 Providing and erection of 16 nos. of MS Channel Iron 75 mm X 40 mm X 6 mm (7.14Kg
per metre) four pole crossarm for three wire 11 kV overhead line conductors complete
with through bolts and nuts for clamping to the poles including drilling of holes for
insulator pins/fitting bolts, nuts and washers etc and painting with primer and
finished paint as required (for SP-35) as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials 1401 M.S. Channel 75 x 40 x 6 mm kg 105.84 178.44 18,886.39
1405 M.S. Flat Iron 40mmx6 mm kg 105.84 25.29 2,676.68
21 03
M.S. Nut & Bolt 16 x 155 mm
full thread conforming to IS :
1364-2 (1992) or any
amendments up to date.
kg 162.00 14.69 2,379.46
21 02
M.S. Nut & Bolt 16x50 mm full
thread conforming to IS : 1 364-
2 (1992) or any amendments up
to date.
kg 162.00 9.34 1,513.73
2201 Aluminium Paint Lit 170.00 0.80 136.00
2203 Red Oxide Paint Lit 125.00 0.80 100.00
Total Cost of Materials 25,692.26
Contingency (2% on Material Cost) 513.85
Sub-Total 26,206.11
Labours
1001 Labour Skilled-I manday 380.00 5.47 2,077.33
1002 Labour Skilled-II manday 310.00 2.00 620.00
1003 Labour Semi-Skilled manday 250.00 2.13 533.33
1004 Labour Un-skilled manday 220.00 16.80 3,696.00
Total Cost of Labours 6,926.67
Total 33,132.77
Add 15% for overhead & Profit 4,969.92
Grand Total 38,102.69
Say 38,103.00
Supervision (15% on Labour Cost) 1,039.00
Page No -34-
FITTING OF CROSSARM
2.25 Providing and erection of 2 nos. of MS Channel Iron 100 mm X 50 mm X 6 mm (9.56Kg
per metre) double pole crossarm for three wire 33 kV overhead line conductors
(horizontal formation) complete with through bolts and nuts for clamping to the poles
including drilling of holes for insulator pins/fitting bolts, nuts and washers etc and
painting with primer and finished paint as required including angle iron
reinforcement (for SP-35) as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials 1402 M.S. Channel 100 x 50 x 6 mm kg 105.84 65.41 6,922.94
1405 M.S. Flat Iron 40mmx6 mm kg 105.84 3.16 334.59
1403 M.S. Angle Iron 40x40x6 mm kg 105.84 57.12 6,045.90
21 03
M.S. Nut & Bolt 16 x 155 mm
full thread conforming to IS :
1364-2 (1992) or any
amendments up to date.
kg 162.00 5.20 842.72
21 02
M.S. Nut & Bolt 16x50 mm full
thread conforming to IS : 1 364-
2 (1992) or any amendments up
to date.
kg 162.00 1.17 189.22
2201 Aluminium Paint Lit 170.00 0.10 17.00
2203 Red Oxide Paint Lit 125.00 0.10 12.50
Total Cost of Materials 14,364.87
Contingency (2% on Material Cost) 287.30
Sub-Total 14,652.16 Labours
1001 Labour Skilled-I manday 380.00 0.68 259.67
1002 Labour Skilled-II manday 310.00 0.25 77.50
1003 Labour Semi-Skilled manday 250.00 0.27 66.67
1004 Labour Un-skilled manday 220.00 2.10 462.00
Total Cost of Labours 865.83
Total 15,518.00
Add 15% for overhead & Profit 2,327.70
Grand Total 17,845.70
Say 17,846.00
Supervision (15% on Labour Cost) 129.88
Page No -35-
FITTING OF CROSSARM
2.26 Providing and erection of 4 nos. of MS Channel Iron 100 mm X 50 mm X 6 mm
(9.56Kg per metre) double pole crossarm for three wire 33 kV overhead line
conductors (triangular formation) complete with through bolts and nuts for clamping
to the poles including drilling of holes for insulator pins/fitting bolts, nuts and
washers etc and painting with primer and finished paint as required (for SP-35) as
directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
1402 M.S. Channel 100 x 50 x 6 mm kg 105.84 78.98 8,358.73
1405 M.S. Flat Iron 40mmx6 mm kg 105.84 6.32 669.17
2103
M.S. Nut & Bolt 16 x 155 mm
full thread conforming to IS :
1364-2 (1992) or any
amendments up to date.
kg 162.00 3.67 594.86
2102
M.S. Nut & Bolt 16x50 mm full
thread conforming to IS : 1364-
2 (1992) or any amendments
up to date.
kg 162.00 2.34 378.43
2201 Aluminium Paint Lit 170.00 0.10 17.00
2203 Red Oxide Paint Lit 125.00 0.10 12.50
Total Cost of Materials 10,030.70
Contingency (2% on Material Cost) 200.61
Sub-Total 10,231.31
Labours
1001 Labour Skilled-I manday 380.00 1.37 519.33
1002 Labour Skilled-II manday 310.00 0.50 155.00
1003 Labour Semi-Skilled manday 250.00 0.53 133.33
1004 Labour Un-skilled manday 220.00 4.20 924.00
Total Cost of Labours 1,731.67
Total 11,962.98
Add 15% for overhead & Profit 1,794.45
Grand Total 13,757.42
Say 13,757.00
Supervision (15% on Labour Cost) 259.75
Page No -36-
FITTING OF CROSSARM
2.27 Providing and erection of 12 nos. of MS Channel Iron 100 mm X 50 mm X 6 mm (9.56Kg
per metre) triple pole crossarm for three wire 33 kV overhead line conductors complete
with through bolts and nuts for clamping to the poles including drilling of holes for
insulator pins/fitting bolts, nuts and washers etc and painting with primer and finished
paint as required (for SP-35) as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials 1402 M.S. Channel 100 x 50 x 6 mm kg 105.84 236.93 25,076.19
1405 M.S. Flat Iron 40mmx6 mm kg 105.84 18.97 2,007.51
21 03
M.S. Nut & Bolt 16 x 155 mm
full thread conforming to IS :
1364-2 (1992) or any
amendments up to date.
kg 162.00 11.02 1,784.59
21 02
M.S. Nut & Bolt 16x50 mm full
thread conforming to IS : 1 364-
2 (1992) or any amendments up
to date.
kg 162.00 7.01 1,135.30
2201 Aluminium Paint Lit 170.00 0.60 102.00
2203 Red Oxide Paint Lit 125.00 0.60 75.00
Total Cost of Materials 30,180.59
Contingency (2% on Material Cost) 603.61
Sub-Total 30,784.20
Labours
1001 Labour Skilled-I manday 380.00 5.00 1,900.00
1002 Labour Skilled-II manday 310.00 2.00 620.00
1003 Labour Semi-Skilled manday 250.00 2.00 500.00
1004 Labour Un-skilled manday 220.00 14.40 3,168.00
Total Cost of Labours 6,188.00
Total 36,972.20
Add 15% for overhead & Profit 5,545.83
Grand Total 42,518.03
Say 42,518.00
Supervision (15% on Labour Cost) 928.20
Page No -37-
FITTING OF CROSSARM
2.28 Providing and erection of 16 nos. of MS Channel Iron 100 mm X 50 mm X 6 mm (9.56Kg
per metre) four pole crossarm for three wire 33 kV overhead line conductors complete
with through bolts and nuts for clamping to the poles including drilling of holes for
insulator pins/fitting bolts, nuts and washers etc and painting with primer and finished
paint as required (for SP-35) as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
1 402 M.S. Channel 1 00 x 50 x 6 mm kg 1 05.84 31 5.90
33,434.92
1405 M.S. Flat Iron 40mmx6 mm kg 105.84 25.29 2,676.68
21 03
M.S. Nut & Bolt 16 x 155 mm
full thread conforming to IS :
1364-2 (1992) or any
amendments up to date.
kg 162.00 14.69 2,379.46
21 02
M.S. Nut & Bolt 16x50 mm full
thread conforming to IS : 1 364-
2 (1992) or any amendments up
to date.
kg 162.00 9.34 1,513.73
2201 Aluminium Paint Lit 170.00 0.60 102.00
2203 Red Oxide Paint Lit 125.00 0.60 75.00
Total Cost of Materials 40,181.79
Contingency (2% on Material Cost) 803.64
Sub-Total 40,985.43
Labours
1001 Labour Skilled-I manday 380.00 5.47 2,077.33
1002 Labour Skilled-II manday 310.00 2.00 620.00
1003 Labour Semi-Skilled manday 250.00 2.13 533.33
1004 Labour Un-skilled manday 220.00 16.80 3,696.00
Total Cost of Labours 6,926.67
Total 47,912.09
Add 15% for overhead & Profit 7,186.81
Grand Total 55,098.91
Say 55,099.00
Supervision (15% on Labour Cost) 1,039.00
Page No -38-
FITTING OF CROSSARM
2.29 Providing and erection of 2 nos. of MS Channel Iron 100 mm X 50 mm X 6 mm
(9.56Kg per metre) double pole crossarm for three wire 33 kV overhead line
conductors (horizontal formation) complete with through bolts and nuts for clamping
to the poles including drilling of holes for insulator pins/fitting bolts, nuts and
washers etc and painting with primer and finished paint as required including angle
iron reinforcement (for SP-58) as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials 1402 M.S. Channel 100 x 50 x 6 mm kg 105.84 65.41 6,922.94
1405 M.S. Flat Iron 40mmx6 mm kg 105.84 3.79 401.44
1403 M.S. Angle Iron 40x40x6 mm kg 105.84 57.32 6,066.85
2103
M.S. Nut & Bolt 16 x 155 mm
full thread conforming to IS :
1364-2 (1992) or any
amendments up to date.
kg 162.00 5.20 842.72
2102
M.S. Nut & Bolt 16x50 mm full
thread conforming to IS : 1364-
2 (1992) or any amendments up
to date.
kg 162.00 1.17 189.22
2201 Aluminium Paint Lit 170.00 0.10 17.00
2203 Red Oxide Paint Lit 125.00 0.10 12.50
Total Cost of Materials 14,452.68
Contingency (2% on Material Cost) 289.05
Sub-Total 14,741.73
Labours
1001 Labour Skilled-I manday 380.00 0.68 259.67
1002 Labour Skilled-II manday 310.00 0.25 77.50
1003 Labour Semi-Skilled manday 250.00 0.27 66.67
1004 Labour Un-skilled manday 220.00 2.10 462.00
Total Cost of Labours 865.83
Total 15,607.57
Add 15% for overhead & Profit 2,341.13
Grand Total 17,948.70
Say 17,949.00
Supervision (15% on Labour Cost) 129.88
Page No -39-
FITTING OF CROSSARM
2.30 Providing and erection of 4 nos. of MS Channel Iron 100 mm X 50 mm X 6 mm
(9.56Kg per metre) double pole crossarm for three wire 33 kV overhead line
conductors (triangular formation) complete with through bolts and nuts for clamping
to the poles including drilling of holes for insulator pins/fitting bolts, nuts and
washers etc and painting with primer and finished paint as required (for SP-58) as
directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials 1402 M.S. Channel 100 x 50 x 6 mm kg 105.84 78.98 8,358.73
1405 M.S. Flat Iron 40mmx6 mm kg 105.84 7.59 802.88
2103
M.S. Nut & Bolt 16 x 155 mm
full thread conforming to IS :
1364-2 (1992) or any
amendments up to date.
kg 162.00 3.67 594.86
21 02
M.S. Nut & Bolt 16x50 mm full
thread conforming to IS : 1
364- 2 (1992) or any
amendments up to date.
kg 162.00 2.34 378.43
2201 Aluminium Paint Lit 170.00 0.10 17.00
2203 Red Oxide Paint Lit 125.00 0.10 12.50
Total Cost of Materials 10,164.41
Contingency (2% on Material Cost) 203.29
Sub-Total 10,367.70
Labours
1001 Labour Skilled-I manday 380.00 1.37 519.33
1002 Labour Skilled-II manday 310.00 0.50 155.00
1003 Labour Semi-Skilled manday 250.00 0.53 133.33
1004 Labour Un-skilled manday 220.00 4.20 924.00
Total Cost of Labours 1,731.67
Total 12,099.36
Add 15% for overhead & Profit 1,814.90
Grand Total 13,914.27
Say 13,914.00
Supervision (15% on Labour Cost) 259.75
Page No -40-
FITTING OF CROSSARM
2.31 Providing and erection of 12 nos. of MS Channel Iron 100 mm X 50 mm X 6 mm (9.56Kg
per metre) triple pole crossarm for three wire 33 kV overhead line conductors complete
with through bolts and nuts for clamping to the poles including drilling of holes for
insulator pins/fitting bolts, nuts and washers etc and painting with primer and finished
paint as required (for SP-58) as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials 1402 M.S. Channel 100 x 50 x 6 mm kg 105.84 236.93 25,076.19
1405 M.S. Flat Iron 40mmx6 mm kg 105.84 22.76 2,408.65
21 03
M.S. Nut & Bolt 16 x 155 mm
full thread conforming to IS :
1364-2 (1992) or any
amendments up to date.
kg 162.00 11.02 1,784.59
21 02
M.S. Nut & Bolt 16x50 mm full
thread conforming to IS : 1 364-
2 (1992) or any amendments up
to date.
kg 162.00 7.01 1,135.30
2201 Aluminium Paint Lit 170.00 0.60 102.00
2203 Red Oxide Paint Lit 125.00 0.60 75.00
Total Cost of Materials 30,581.73
Contingency (2% on Material Cost) 611.63
Sub-Total 31,193.36 Labours
1001 Labour Skilled-I manday 380.00 5.00 1,900.00
1002 Labour Skilled-II manday 310.00 2.00 620.00
1003 Labour Semi-Skilled manday 250.00 2.00 500.00
1004 Labour Un-skilled manday 220.00 14.40 3,168.00
Total Cost of Labours 6,188.00
Total 37,381.36
Add 15% for overhead & Profit 5,607.20
Grand Total 42,988.57
Say 42,989.00
Supervision (15% on Labour Cost) 928.20
Page No -41-
FITTING OF CROSSARM
2.32 Providing and erection of 16 nos. of MS Channel Iron 100 mm X 50 mm X 6 mm (9.56Kg
per metre) four pole crossarm for three wire 33 kV overhead line conductors complete
with through bolts and nuts for clamping to the poles including drilling of holes for
insulator pins/fitting bolts, nuts and washers etc and painting with primer and finished
paint as required (for SP-58) as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials 1401 M.S. Channel 75 x 40 x 6 mm kg 105.84 315.90 33,434.92
1405 M.S. Flat Iron 40mmx6 mm kg 105.84 30.34 3,211.53
21 03
M.S. Nut & Bolt 16 x 155 mm
full thread conforming to IS :
1364-2 (1992) or any
amendments up to date.
kg 162.00 14.69 2,379.46
21 02
M.S. Nut & Bolt 16x50 mm full
thread conforming to IS : 1
364- 2 (1992) or any
amendments up to date.
kg 162.00 9.34 1,513.73
2201 Aluminium Paint Lit 170.00 0.60 102.00
2203 Red Oxide Paint Lit 125.00 0.60 75.00
Total Cost of Materials 40,716.64
Contingency (2% on Material Cost) 814.33
Sub-Total 41,530.97
Labours
1001 Labour Skilled-I manday 380.00 5.47 2,077.33
1002 Labour Skilled-II manday 310.00 2.00 620.00
1003 Labour Semi-Skilled manday 250.00 2.13 533.33
1004 Labour Un-skilled manday 220.00 16.80 3,696.00
Total Cost of Labours 6,926.67
Total 48,457.63
Add 15% for overhead & Profit 7,268.65
Grand Total 55,726.28
Say 55,726.00
Supervision (15% on Labour Cost) 1,039.00
Page No -42-
FITTING OF COMPLETE SET OF SHACKLE INSULATOR (Pin Type, 1ph 3 wire)
3.01 Providing and erection of shackle insulator for LT over head lines (1ph 3 wire) with
galvanised pin, nuts, washers etc as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
1806
Shackle Insulator (Pin/Strap
Type) 70x90 mm conforming to
IS : 1445 (1977) or any
amendments up to date
No 39.00 3.00 117.00
1808 Shackle Nut Bolt 12x100 kg 174.96 1.00 174.96
Total Cost of Materials 291.96
Contingency (2% on Material Cost) 5.84
Sub-Total 297.80 Labours
1001 Labour Skilled-I manday 380.00 0.00 0.00
1002 Labour Skilled-II manday 310.00 0.00 0.00
1003 Labour Semi-Skilled manday 250.00 0.08 20.00
1004 Labour Un-skilled manday 220.00 0.02 4.40
Total Cost of Labours 24.40
Total 322.20
Add 15% for overhead & Profit 48.33
Grand Total 370.53
Say 371.00
Supervision (15% on Labour Cost) 3.66
Page No -43-
FITTING OF COMPLETE SET OF SHACKLE INSULATOR (STRAP TYPE, 1ph 3 wire)
3.02 Providing and erection of shackle insulator (strap type) for LT over head lines (1ph 3
wire) with galvanised shackle pin, bolts, nuts, washers etc as directed by the
engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
1806
Shackle Insulator (Pin/Strap
Type) 70x90 mm conforming to
IS : 1445 (1977) or any
amendments up to date
No 39.00 6.00 234.00
1 807 Shackle Strap for 70x90 mm
Shackle Insulator Pair 14.00 3.00 42.00
1808 Shackle Nut Bolt 12x100 kg 174.96 1.00 174.96
Total Cost of Materials 450.96
Contingency (2% on Material Cost) 9.02
Sub-Total 459.98 Labours
1001 Labour Skilled-I manday 380.00 0.00 0.00
1002 Labour Skilled-II manday 310.00 0.00 0.00
1003 Labour Semi-Skilled manday 250.00 0.08 20.00
1004 Labour Un-skilled manday 220.00 0.02 4.40
Total Cost of Labours 24.40
Total 484.38
Add 15% for overhead & Profit 72.66
Grand Total 557.04
Say 557.00
Supervision (15% on Labour Cost) 3.66
Page No -44-
FITTING OF COMPLETE SET OF SHACKLE INSULATOR (Pin Type, 3ph 5 wire)
3.03 Providing and erection of shackle insulator for LT over head lines (3ph 5 wire) with
galvanised pin, nuts, washers etc as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
1 806
Shackle Insulator (Pin/Strap
Type) 70x90 mm conforming to
IS : 1445 (1977) or any
amendments up to date
No 39.00 5.00 195.00
1808 Shackle Nut Bolt 12x100 kg 174.96 1.00 174.96
Total Cost of Materials 369.96
Contingency (2% on Material Cost) 7.40
Sub-Total 377.36 Labours
1001 Labour Skilled-I manday 380.00 0.00 0.00
1002 Labour Skilled-II manday 310.00 0.00 0.00
1003 Labour Semi-Skilled manday 250.00 0.08 20.00
1004 Labour Un-skilled manday 220.00 0.02 4.40
Total Cost of Labours 24.40
Total 401.76
Add 15% for overhead & Profit 60.26
Grand Total 462.02
Say 462.00
Supervision (15% on Labour Cost) 3.66
Page No -45-
FITTING OF COMPLETE SET OF SHACKLE INSULATOR (STRAP TYPE, 3ph 5 wire)
3.04 Providing and erection of shackle insulator (strap type) for LT over head lines (3ph 5
wire) with galvanised shackle pin, bolts, nuts, washers etc as directed by the
engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
1806
Shackle Insulator (Pin/Strap
Type) 70x90 mm conforming to
IS : 1445 (1977) or any
amendments up to date
No 39.00 10.00 390.00
1807 Shackle Strap for 70x90 mm
Shackle Insulator Pair 14.00 5.00 70.00
1808 Shackle Nut Bolt 12x100 kg 174.96 1.00 174.96
Total Cost of Materials 634.96
Contingency (2% on Material Cost) 12.70
Sub-Total 647.66 Labours
1001 Labour Skilled-I manday 380.00 0.00 0.00
1002 Labour Skilled-II manday 310.00 0.00 0.00
1003 Labour Semi-Skilled manday 250.00 0.08 20.00
1004 Labour Un-skilled manday 220.00 0.02 4.40
Total Cost of Labours 24.40
Total 672.06
Add 15% for overhead & Profit 100.81
Grand Total 772.87
Say 773.00
Supervision (15% on Labour Cost) 3.66
Page No -46-
FITTING OF PIN INSULATOR (11kV)
3.05 Providing and erection of pin insulator for 11 kV over head lines with galvanised pin, nuts,
washers etc as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
1805
11kV Pin insulator with GI Pin
conforming IS : 731 (1971), IS :
2486 (1989), IS : 2544 (1973),
IS : 5350 (1973) or any
amendments up to date.
Set 354.00 3.00 1062.00
Total Cost of Materials 1062.00
Contingency (2% on Material Cost) 21.24
Sub-Total 1083.24 Labours
1001 Labour Skilled-I manday 380.00 0.00 0.00
1002 Labour Skilled-II manday 310.00 0.00 0.00
1003 Labour Semi-Skilled manday 250.00 0.08 20.83
1004 Labour Un-skilled manday 220.00 0.08 18.33
Total Cost of Labours 39.17
Total 1122.41
Add 15% for overhead & Profit 168.36
Grand Total 1290.77
Say 1291.00
Supervision (15% on Labour Cost) 5.88
Page No -47-
FITTING OF DISC INSULATOR (11kV)
3.06 Providing and erection of disc insulator, 45 kN (2 nos. as a set) for 11 kV over head
lines with insulator fittings, ball and socket type and complete with aluminium alloy
tension clamps, bolts, nuts, washers etc as directed by the engineer in charge.
Sl. No. Description Unit Rate/ Unit Qty. Amount
Materials
1801
Porcelain Disc Insulator, 45 kN,
conforming IS : 731 (1971), IS :
2486 (1989), IS : 2544 (1973),
IS : 5350 (1973) or any
amendments up to date.
No 519.00 2.00 1038.00
2002
Tension Clamp with hardware
strain fitting, 3-bolted type
complete with bolts, nuts, and
washer (Weasel)
No 445.00 1.00 445.00
Total Cost of Materials 1483.00
Contingency (2% on Material Cost) 29.66
Sub-Total 1512.66 Labours
1001 Labour Skilled-I manday 380.00 0.33 126.67
1002 Labour Skilled-II manday 310.00 0.03 8.16
1003 Labour Semi-Skilled manday 250.00 0.00 0.00
1004 Labour Un-skilled manday 220.00 0.66 144.63
Total Cost of Labours 279.45
Total 1792.11
Add 15% for overhead & Profit 268.82
Grand Total 2060.93
Say 2061.00
Supervision (15% on Labour Cost) 41.92
Page No -48-
FITTING OF PIN INSULATOR (33kV)
3.07 Providing and erection of pin insulator for 33 kV over head lines with galvanised pin, nuts,
washers etc as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
1804
33kV Pin insulator with GI Pin
conforming IS : 731 (1971), IS :
2486 (1989), IS : 2544 (1973),
IS : 5350 (1973) or any
amendments up to date.
Set 894.00 3.00 2682.00
Total Cost of Materials 2682.00
Contingency (2% on Material Cost) 53.64
Sub-Total 2735.64 Labours
1001 Labour Skilled-I manday 380.00 0.00 0.00
1002 Labour Skilled-II manday 310.00 0.00 0.00
1003 Labour Semi-Skilled manday 250.00 0.11 27.78
1004 Labour Un-skilled manday 220.00 0.11 24.44
Total Cost of Labours 52.22
Total 2787.86
Add 15% for overhead & Profit 418.18
Grand Total 3206.04
Say 3206.00
Supervision (15% on Labour Cost) 7.83
Page No -49-
FITTING OF DISC INSULATOR (33kV)
3.08 Providing and erection of disc insulator, 70 kN (3 nos. as a set) for 33 kV over head
lines with insulator fittings, ball and socket type and complete with aluminium alloy
tension clamps, bolts, nuts, washers etc as directed by the engineer in charge.
Sl. No. Description Unit Rate/ Unit Qty. Amount
Materials
1802
Porcelain Disc Insulator, 70 kN,
conforming IS : 731 (1971), IS :
2486 (1989), IS : 2544 (1973),
IS : 5350 (1973) or any
amendments up to date.
No 700.00 3.00 2100.00
2001
Tension Clamp with hardware
strain fitting, 4-bolted type
complete with bolts, nuts, and
washer (Racoon)
No 474.00 1.00 474.00
Total Cost of Materials 2574.00
Contingency (2% on Material Cost) 51.48
Sub-Total 2625.48 Labours
1001 Labour Skilled-I manday 380.00 0.33 126.67
1002 Labour Skilled-II manday 310.00 0.03 8.16
1003 Labour Semi-Skilled manday 250.00 0.00 0.00
1004 Labour Un-skilled manday 220.00 0.76 166.63
Total Cost of Labours 301.45
Total 2926.93
Add 15% for overhead & Profit 439.04
Grand Total 3365.97
Say 3366.00
Supervision (15% on Labour Cost) 45.22
Page No -50-
Erection of LT Stay Set
4.01 Providing and erection of galvanised stay set for LT over head lines complete with 16
mm rod dia. with plate 30x30x0.8 cm, 7/14 SWG G.I. stay wire, LT guy insulator
(90x65mm) and stay bow in cement concrete 1:3:6 (1 cement : 3 coarse sand : 6
graded stone aggregate) foundation including excavation and refilling etc (for SP-17) as
directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
1901 G.I. Stay Set complete 16
mm rod dia. with plate
30x30x0.8 cm conforming to
IS : 7887 (1992) or any
amendments up to date.
Set 810.00 1.000 810.00
1905 Stay wire 7/14 SWG
conforming to IS : 2141
(1979), IS : 4826 (1979), IS
: 6594 (1974) or any
amendments up to date.
kg 118.50 1.673 198.30
1811 LT Guy insulator
(90x65mm) conforming to
IS : 5300 (1969) or any
amendments up to date.
No 28.50 1.000 28.50
2301 Cement cum 13,750.00 0.023 316.25
2302 River Sand cum 2,100.00 0.069 144.90
2303 Stone Aggregate 10-20 mm cum 1,890.00 0.138 260.82
Total Cost of Materials 1,758.77
Contingency (2% on Material Cost) 35.18
Sub-Total 1,793.95
Labours
1001 Labour Skilled-I manday 380.00 0.00 -
1002 Labour Skilled-II manday 310.00 0.48 147.62
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 3.31 728.10
Total Cost of Labours 875.71
Total 2,669.66
Add 15% for overhead & Profit 400.45
Grand Total 3,070.11
Say 3,070.00
Supervision (15% on Labour Cost) 131.36
Page No -51-
Erection of LT Stay Set
4.02 Providing and erection of galvanised stay set for LT over head lines complete with 16
mm rod dia. with plate 30x30x0.8 cm, 7/14 SWG G.I. stay wire, LT guy insulator
(90x65mm) and stay bow in cement concrete 1:3:6 (1 cement : 3 coarse sand : 6
graded stone aggregate) foundation including excavation and refilling etc (for SP-29) as
directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
1901 G.I. Stay Set complete 16
mm rod dia. with plate
30x30x0.8 cm conforming to
IS : 7887 (1992) or any
amendments up to date.
Set 810.00 1.000 810.00
1905 Stay wire 7/14 SWG
conforming to IS : 2141
(1979), IS : 4826 (1979), IS
: 6594 (1974) or any
amendments up to date.
kg 118.50 1.805 213.86
1811 LT Guy insulator
(90x65mm) conforming to
IS : 5300 (1969) or any
amendments up to date.
No 28.50 1.000 28.50
2301 Cement cum 13,750.00 0.023 316.25
2302 River Sand cum 2,100.00 0.069 144.90
2303 Stone Aggregate 10-20 mm cum 1,890.00 0.138 260.82
Total Cost of Materials 1,774.33
Contingency (2% on Material Cost) 35.49
Sub-Total 1,809.82
Labours
1001 Labour Skilled-I manday 380.00 0.00 -
1002 Labour Skilled-II manday 310.00 0.48 147.62
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 3.31 728.10
Total Cost of Labours 875.71
Total 2,685.53
Add 15% for overhead & Profit 402.83
Grand Total 3,088.36
Say 3,088.00
Supervision (15% on Labour Cost) 131.36
Page No -52-
Erection of LT Stay Set
4.03 Providing and erection of galvanised stay set for LT over head lines complete with 16
mm rod dia. with plate 30x30x0.8 cm,7/14 SWG G.I. stay wire, LT guy insulator
(90x65mm) and stay bow in cement concrete 1:3:6 (1 cement : 3 coarse sand : 6
graded stone aggregate) foundation including excavation and refilling etc (for pre-
stressed concrete, 8.5 m height) as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
1901 G.I. Stay Set complete 16
mm rod dia. with plate
30x30x0.8 cm conforming to
IS : 7887 (1992) or any
amendments up to date.
Set 810.00 1.000 810.00
1905 Stay wire 7/14 SWG
conforming to IS : 2141
(1979), IS : 4826 (1979), IS
: 6594 (1974) or any
amendments up to date.
kg 118.50 1.673 198.30
1811 LT Guy insulator
(90x65mm) conforming to
IS : 5300 (1969) or any
amendments up to date.
No 28.50 1.000 28.50
2301 Cement cum 13,750.00 0.023 316.25
2302 River Sand cum 2,100.00 0.069 144.90
2303 Stone Aggregate 10-20 mm cum 1,890.00 0.138 260.82
Total Cost of Materials 1,758.77
Contingency (2% on Material Cost) 35.18
Sub-Total 1,793.95
Labours
1001 Labour Skilled-I manday 380.00 0.00 -
1002 Labour Skilled-II manday 310.00 0.48 147.62
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 3.31 728.10
Total Cost of Labours 875.71
Total 2,669.66
Add 15% for overhead & Profit 400.45
Grand Total 3,070.11
Say 3,070.00
Supervision (15% on Labour Cost) 131.36
Page No -53-
Erection of LT Stay Set
4.04 Providing and erection of galvanised stay set for LT over head lines complete with 16
mm rod dia. with plate 30x30x0.8 cm, 7/14 SWG G.I. stay wire, LT guy insulator
(90x65mm) and stay bow in cement concrete 1:3:6 (1 cement : 3 coarse sand : 6
graded stone aggregate) foundation including excavation and refilling etc (for pre-
stressed concrete, 9.75 m height) as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
1901 G.I. Stay Set complete 16
mm rod dia. with plate
30x30x0.8 cm conforming to
IS : 7887 (1992) or any
amendments up to date.
Set 810.00 1.000 810.00
1905 Stay wire 7/14 SWG
conforming to IS : 2141
(1979), IS : 4826 (1979), IS
: 6594 (1974) or any
amendments up to date.
kg 118.50 1.925 228.10
1811 LT Guy insulator
(90x65mm) conforming to IS
: 5300 (1969) or any
amendments up to date.
No 28.50 1.000 28.50
2301 Cement cum 13,750.00 0.023 316.25
2302 River Sand cum 2,100.00 0.069 144.90
2303 Stone Aggregate 10-20 mm cum 1,890.00 0.138 260.82
Total Cost of Materials 1,788.57
Contingency (2% on Material Cost) 35.77
Sub-Total 1,824.34
Labours
1001 Labour Skilled-I manday 380.00 0.00 -
1002 Labour Skilled-II manday 310.00 0.48 147.62
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 3.31 728.10
Total Cost of Labours 875.71
Total 2,700.05
Add 15% for overhead & Profit 405.01
Grand Total 3,105.06
Say 3,105.00
Supervision (15% on Labour Cost) 131.36
Page No -54-
Erection of 11 kV Stay Set
4.05 Providing and erection of galvanised stay set for 11 kV over head lines complete with 19
mm rod dia. with plate 30x30x0.8 cm, 7/12 SWG G.I. stay wire, 11kV guy insulator
(140x85mm) and stay bow in cement concrete 1:3:6 (1 cement: 3 coarse sand : 6
graded stone aggregate) foundation including excavation and refilling etc (for SP-29) as
directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
1902 G.I. Stay set complete 19
mm rod dia. with plate
30x30x0.8 cm conforming to
IS : 7887 (1992) or any
amendments up to date.
Set 1,407.00 1.000 1,407.00
1904 Stay wire 7/12 SWG
conforming to IS : 2141
(1979), IS : 4826 (1979), IS
: 6594 (1974) or any
amendments up to date.
kg 112.50 2.899 326.17
1809 11kV Guy insulator
(140x85mm) conforming to
IS : 5300 (1969) or any
amendments up to date.
No 57.00 1.000 57.00
2301 Cement cum 13,750.00 0.023 316.25
2302 River Sand cum 2,100.00 0.069 144.90
2303 Stone Aggregate 10-20 mm cum 1,890.00 0.138 260.82
Total Cost of Materials 2,512.14
Contingency (2% on Material Cost) 50.24
Sub-Total 2,562.38
Labours
1001 Labour Skilled-I manday 380.00 0.00 -
1002 Labour Skilled-II manday 310.00 0.48 147.62
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 3.31 728.10
Total Cost of Labours 875.71
Total 3,438.10
Add 15% for overhead & Profit 515.71
Grand Total 3,953.81
Say 3,954.00
Supervision (15% on Labour Cost) 131.36
Page No -55-
Erection of 11 kV Stay Set
4.06 Providing and erection of galvanised stay set for 11 kV over head lines complete with 19
mm rod dia. with plate 30x30x0.8 cm, 7/12 SWG G.I. stay wire, 11kV guy insulator
(140x85mm) and stay bow in cement concrete 1:3:6 (1 cement: 3 coarse sand : 6
graded stone aggregate) foundation including excavation and refilling etc (for SP-35) as
directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
1902 G.I. Stay set complete 19
mm rod dia. with plate
30x30x0.8 cm conforming to
IS : 7887 (1992) or any
amendments up to date.
Set 1,407.00 1.000 1,407.00
1904 Stay wire 7/12 SWG
conforming to IS : 2141
(1979), IS : 4826 (1979), IS
: 6594 (1974) or any
amendments up to date.
kg 112.50 2.854 321.09
1809 11kV Guy insulator
(140x85mm) conforming to
IS : 5300 (1969) or any
amendments up to date.
No 57.00 1.000 57.00
2301 Cement cum 13,750.00 0.023 316.25
2302 River Sand cum 2,100.00 0.069 144.90
2303 Stone Aggregate 10-20 mm cum 1,890.00 0.138 260.82
Total Cost of Materials 2,507.06
Contingency (2% on Material Cost) 50.14
Sub-Total 2,557.20
Labours
1001 Labour Skilled-I manday 380.00 0.00 -
1002 Labour Skilled-II manday 310.00 0.48 147.62
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 3.31 728.10
Total Cost of Labours 875.71
Total 3,432.91
Add 15% for overhead & Profit 514.94
Grand Total 3,947.85
Say 3,948.00
Supervision (15% on Labour Cost) 131.36
Page No -56-
Erection of 33 kV Stay Set
4.07 Providing and erection of galvanised stay set for 33 kV over head lines complete with 19
mm rod dia. with plate 40x40x0 .8 cm,7/ 10 SWG G.I. stay wire, 33kV guy insulator
(140x85mm) and stay bow in cement concrete 1:3:6 (1 cement: 3 coarse sand: 6
graded stone aggregate) foundation including excavation and refilling etc (for SP-35) as
directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
1903 G.I. Stay set complete 19
mm rod dia. with plate
40x40x0.8 cm conforming to
IS : 7887 (1992) or any
amendments up to date.
Set 1,694.00 1.000 1,694.00
1907
Stay wire 7/10 SWG
conforming to IS : 2141
(1979), IS : 4826 (1979), IS
: 6594 (1974) or any
amendments up to date.
kg 116.00 3.874 449.40
1810 33kV Guy insulator
(140x85mm) conforming to
IS : 5300 (1969) or any
amendments up to date.
No 57.00 1.000 57.00
2301 Cement cum 13,750.00 0.023 316.25
2302 River Sand cum 2,100.00 0.069 144.90
2303 Stone Aggregate 10-20 mm cum 1,890.00 0.138 260.82
Total Cost of Materials 2,922.37
Contingency (2% on Material Cost) 58.45
Sub-Total 2,980.82
Labours
1001 Labour Skilled-I manday 380.00 0.00 -
1002 Labour Skilled-II manday 310.00 0.48 147.62
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 3.31 728.10
Total Cost of Labours 875.71
Total 3,856.54
Add 15% for overhead & Profit 578.48
Grand Total 4,435.02
Say 4,435.00
Supervision (15% on Labour Cost) 131.36
Page No -57-
Erection of 33 kV Stay Set
4.08 Providing and erection of galvanised stay set for 33 kV over head lines complete with 19
mm rod dia. with plate 40x40x0 .8 cm ,7/ 10 SWG G.I. stay wire ,33kV guy insulator
(140x85mm) and stay bow in cement concrete 1:3:6 (1 cement: 3 coarse sand : 6
graded stone aggregate) foundation including excavation and refilling etc (for SP-58) as
directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
1903 G.I. Stay set complete 19
mm rod dia. with plate
40x40x0.8 cm conforming to
IS : 7887 (1992) or any
amendments up to date.
Set 1,694.00 1.000 1,694.00
1907
Stay wire 7/10 SWG
conforming to IS : 2141
(1979), IS : 4826 (1979), IS
: 6594 (1974) or any
amendments up to date.
kg 116.00 5.420 628.77
1810 33kV Guy insulator
(140x85mm) conforming to
IS : 5300 (1969) or any
amendments up to date.
No 57.00 1.000 57.00
2301 Cement cum 13,750.00 0.023 316.25
2302 River Sand cum 2,100.00 0.069 144.90
2303 Stone Aggregate 10-20 mm cum 1,890.00 0.138 260.82
Total Cost of Materials 3,101.74
Contingency (2% on Material Cost) 62.03
Sub-Total 3,163.77
Labours
1001 Labour Skilled-I manday 380.00 0.00 -
1002 Labour Skilled-II manday 310.00 0.48 147.62
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 3.31 728.10
Total Cost of Labours 875.71
Total 4,039.49
Add 15% for overhead & Profit 605.92
Grand Total 4,645.41
Say 4,645.00
Supervision (15% on Labour Cost) 131.36
Page No -58-
Page No -59-
Page No -60-
Page No -61-
Page No -62-
Page No -63-
PROVIDING AND FITTING OF PG CLAMP
5.06 Providing and fitting of PG Clamps for Gnat Conductor jumpering of LT line per
number as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
2005 P.G. Clamp for Gnat
conductor (2 bolted type)
No 72.00 1 72.00
Total Cost of Materials 72.00
Contingency (2% on Material Cost) 1.44
Sub-Total 73.44
Labours
1001 Labour Skilled-I manday 380.00 0.00 -
1002 Labour Skilled-II manday 310.00 0.07 21.70
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 0.07 15.40
Total Cost of Labours 37.10
Total 110.54
Add 15% for overhead & Profit 16.58
Grand Total 127.12
Say 127.00
Supervision (15% on Labour Cost) 5.57
Page No -64-
PROVIDING AND FITTING OF PG CLAMP
5.07 Providing and fitting of PG Clamps for Ant Conductor jumpering of LT line per
number as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
2004 P.G. Clamp for Ant
conductor (2 bolted type)
No 79.00 1 79.00
Total Cost of Materials 79.00
Contingency (2% on Material Cost) 1.58
Sub-Total 80.58
Labours
1001 Labour Skilled-I manday 380.00 0.00 -
1002 Labour Skilled-II manday 310.00 0.07 21.70
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 0.07 15.40
Total Cost of Labours 37.10
Total 117.68
Add 15% for overhead & Profit 17.65
Grand Total 135.33
Say 135.00
Supervision (15% on Labour Cost) 5.57
Page No -65-
PROVIDING AND FITTING OF PG CLAMP
5.08 Providing and fitting of PG Clamps for Grasshopper Conductor jumpering of LT line
per number as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
2003 P.G. Clamp for
Grasshopper conductor
(3 bolted type)
No 82.00 1 82.00
Total Cost of Materials 82.00
Contingency (2% on Material Cost) 1.64
Sub-Total 83.64
Labours
1001 Labour Skilled-I manday 380.00 0.00 -
1002 Labour Skilled-II manday 310.00 0.07 21.70
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 0.07 15.40
Total Cost of Labours 37.10
Total 120.74
Add 15% for overhead & Profit 18.11
Grand Total 138.85
Say 139.00
Supervision (15% on Labour Cost) 5.57
Page No -66-
PROVIDING AND FITTING OF PG CLAMP
5.09 Providing and fitting of PG Clamps for Weasel Conductor jumpering of 11kV line per
number as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
2006 P.G. Clamp for Weasel
conductor (3 bolted type)
No 75.00 1 75.00
Total Cost of Materials 75.00
Contingency (2% on Material Cost) 1.50
Sub-Total 76.50
Labours
1001 Labour Skilled-I manday 380.00 0.00 -
1002 Labour Skilled-II manday 310.00 0.10 31.00
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 0.10 22.00
Total Cost of Labours 53.00
Total 129.50
Add 15% for overhead & Profit 19.43
Grand Total 148.93
Say 149.00
Supervision (15% on Labour Cost) 7.95
Page No -67-
PROVIDING AND FITTING OF PG CLAMP
5.10 Providing and fitting of PG Clamps for Racoon Conductor jumpering of 33kV line per
number as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
2007 P.G. Clamp for Racoon
conductor (3 bolted type)
No 112.50 1 112.50
Total Cost of Materials 112.50
Contingency (2% on Material Cost) 2.25
Sub-Total 114.75
Labours
1001 Labour Skilled-I manday 380.00 0.00 -
1002 Labour Skilled-II manday 310.00 0.10 31.00
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 0.10 22.00
Total Cost of Labours 53.00
Total 167.75
Add 15% for overhead & Profit 25.16
Grand Total 192.91
Say 193.00
Supervision (15% on Labour Cost) 7.95
Page No -68-
PROVIDING & FITTING OF JOINTING SLEEVE
5.11 Providing and fitting of Jointing Sleeve for Weasel Conductor for 1 1kV line per
number as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
2008 Jointing Sleeve for
Weasel conductor
No 265.00 1 265.00
Total Cost of Materials 265.00
Contingency (2% on Material Cost) 5.30
Sub-Total 270.30
Labours
1001 Labour Skilled-I manday 380.00 0.00 -
1002 Labour Skilled-II manday 310.00 0.10 31.00
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 0.10 22.00
Total Cost of Labours 53.00
Total 323.30
Add 15% for overhead & Profit 48.50
Grand Total 371.80
Say 372.00
Supervision (15% on Labour Cost) 7.95
Page No -69-
PROVIDING & FITTING OF JOINTING SLEEVE
5.12 Providing and fitting of Jointing Sleeve for Racoon Conductor for 33kV line per
number as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
2009 Jointing Sleeve for
Racoon conductor
No 354.00 1 354.00
Total Cost of Materials 354.00
Contingency (2% on Material Cost) 7.08
Sub-Total 361.08
Labours
1001 Labour Skilled-I manday 380.00 0.00 -
1002 Labour Skilled-II manday 310.00 0.10 31.00
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 0.10 22.00
Total Cost of Labours 53.00
Total 414.08
Add 15% for overhead & Profit 62.11
Grand Total 476.19
Say 476.00
Supervision (15% on Labour Cost) 7.95
Page No -70-
LT POLE EARTHING
6.01 Providing and fitting of 2 m long, 19 mm diameter galvanized steel rod
fabricated for LT Pole Earthing, with accessories such as terminal connector, 8
SWG G.I. wire etc as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
2502
Galvanized steel rod, 2 M
length, 19 mm dia
connected with GI Wire
complete with terminal
connector
No 850.00 1.00 850.00
1906
G.I Wire 8 SWG for earth
wire conforming to IS : 280
(1978), IS : 7887 (1992) or
any amendments up to
date.
kg 112.50 2.00 225.00
Total Cost of Materials 1,075.00
Contingency (2% on Material Cost) 21.50
Sub-Total 1,096.50
Labours
1001 Labour Skilled-I manday 380.00 0.00 -
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.07 16.67
1004 Labour Un-skilled manday 220.00 0.12 25.67
Total Cost of Labours 42.33
Total 1,138.83
Add 15% for overhead & Profit 170.83
Grand Total 1,309.66
Say 1,310.00
Supervision (15% on Labour Cost) 6.35
Page No -71-
11/33 kV POLE EARTHING
6.02 Providing and fitting of 2.5 m long, 40 mm diameter, 8 mm thick G.I. Earth Pipe
fabricated for 11 kV and 33 kV Pole Earthing, with accessories such as terminal
connector, bentonite powder, 8 SWG G.I. wire etc as directed by the engineer in
charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
2503 GI Earth pipe 2.5 metre long
40 mm dia with 8 mm
thickness fabricated for pole
earthing complete with
terminal connector
No 543.00 1.00 543.00
1906 G.I Wire 8 SWG for earth
wire conforming to IS : 280
(1978), IS : 7887 (1992) or
any amendments up to
date.
kg 112.50 2.00 225.00
2305 Bentonite Powder kg 30.00 50.00 1,500.00
Total Cost of Materials 2,268.00
Contingency (2% on Material Cost) 45.36
Sub-Total 2,313.36
Labours
1001 Labour Skilled-I manday 380.00 0.00 -
1002 Labour Skilled-II manday 310.00 0.10 31.00
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 1.20 264.00
Total Cost of Labours 295.00
Total 2,608.36
Add 15% for overhead & Profit 391.25
Grand Total 2,999.61
Say 3,000.00
Supervision (15% on Labour Cost) 44.25
Page No -72-
DISTRIBUTION TRANSFORMER SUB-STATION OR 11KV CT PT COMBINATION
EARTHING
6.03 Providing and fitting of 2.5 m long, 40 mm diameter, 8 mm thick G.I. Earth
Pipe fabricated for Distribution Transformer Substation as per REC
Construction Standard F-5 Earthing, with accessories such as terminal
connector, bentonite powder, 8 SWG G.I. wire etc. as directed by the
engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
2503 GI Earth pipe 2.5 metre long
40 mm dia with 8 mm
thickness fabricated for pole
earthing complete with
terminal connector
No 543.00 3.00 1,629.00
1906 G.I Wire 8 SWG for earth
wire conforming to IS : 280
(1978), IS : 7887 (1992) or
any amendments up to
date.
kg 112.50 4.00 450.00
2305 Bentonite Powder kg 30.00 300.00 9,000.00
Total Cost of Materials 11,079.00
Contingency (2% on Material Cost) 221.58
Sub-Total 11,300.58
Labours
1001 Labour Skilled-I manday 380.00 0.00 -
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.10 25.00
1004 Labour Un-skilled manday 220.00 3.93 865.33
Total Cost of Labours 890.33
Total 12,190.91
Add 15% for overhead & Profit 1,828.64
Grand Total 14,019.55
Say 14,020.00
Supervision (15% on Labour Cost) 133.55
Page No -73-
FITTING OF LIGHTNING SPIKE
7.01 Providing and fitting of Lightning Spike made of iron rod,10 mm diameter, 1.5 m
length, 1 kg welded with MS Flat iron 40x5mm, 0.5kg and 8 SWG GI wire 2.5kg, as
directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
2501 Lightning Spike made of
iron rod,10 mm size, 1.5
m length, 1 kg welded
with MS Flat iron
40x5mm, 0.5kg and 8
SWG GI wire 2.5kg
No 500.00 1.00 500.00
Total Cost of Materials 500.00
Contingency (2% on Material Cost) 10.00
Sub-Total 510.00
Labours
1001 Labour Skilled-I manday 380.00 0.00 -
1002 Labour Skilled-II manday 310.00 0.33 103.33
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 1.00 220.00
Total Cost of Labours 323.33
Total 833.33
Add 15% for overhead & Profit 125.00
Grand Total 958.33
Say 958.00
Supervision (15% on Labour Cost) 48.50
Page No -74-
FITTING OF LIGHTNING ARRESTER
7.02 Providing and erection of 0.280 kV, 2.5 kA Lightning Arrester conforming to IS:
3070 and IEC: 60099-4 for LT Line complete with Hard drawn standard
aluminium conductors galvanised steel wire reinforced: ACSR 6/1/2.59 mm
Weasel, M.S. Flat Iron of size 40x6 mm and M.S. Nuts & Bolts of size 16x50
mm full thread, as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
1503 Lightning Arrester 0.280
kV, 2.5 KA for LT Line
No 657.00 1.00 657.00
1205 Hard drawn standard
aluminium conductors
galvanized steelwire
reinforced conforming
to IS 398(Part-II) with
amendment No. 1, 2
and 3 or the latest
version thereof bearing
ISI mark :ACSR
6/1/2.59mm Weasel.
KM 25,692.00 0.01 128.46
1405 M.S. Flat Iron 40mmx6
mm
kg 105.84 0.25 26.46
2102 M.S. Nut & Bolt 16x50
mm full thread
conforming to IS : 1364-
2 (1992) or any
amendments up to date.
kg 162.00 0.25 40.50
Total Cost of Materials 852.42
Contingency (2% on Material Cost) 17.05
Sub-Total 869.47
Labours
1001 Labour Skilled-I manday 380.00 0.00 -
1002 Labour Skilled-II manday 310.00 0.17 51.67
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 0.17 36.67
Total Cost of Labours 88.33
Total 957.80
Add 15% for overhead & Profit 143.67
Grand Total 1,101.47
Say 1,101.00
Supervision (15% on Labour Cost) 13.25
Page No -75-
FITTING OF LIGHTNING ARRESTER
7.03 Providing and erection of 9 kV, 5 kA Lightning Arrester conforming to IS: 3070
and IEC: 60099-4 complete with Hard drawn standard aluminium conductors
galvanised steel wire reinforced: ACSR 6/1/2.59 mm Weasel, M.S. Flat Iron of
size 40x6 mm and M.S. Nuts & Bolts of size 16x50 mm full thread, as directed
by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
1502 Lightning Arrester 9 kV,
5 KA
No 1,875.00 1.00 1,875.00
1205 Hard drawn standard
aluminium conductors
galvanized steelwire
reinforced conforming
to IS 398(Part-II) with
amendment No. 1, 2
and 3 or the latest
version thereof bearing
ISI mark :ACSR
6/1/2.59mm Weasel.
KM 25,692.00 0.01 128.46
1405 M.S. Flat Iron 40mmx6
mm
kg 105.84 0.25 26.46
2102 M.S. Nut & Bolt 16x50
mm full thread
conforming to IS : 1364-
2 (1992) or any
amendments up to date.
kg 162.00 0.25 40.50
Total Cost of Materials 2,070.42
Contingency (2% on Material Cost) 41.41
Sub-Total 2,111.83
Labours
1001 Labour Skilled-I manday 380.00 0.00 -
1002 Labour Skilled-II manday 310.00 0.17 51.67
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 0.17 36.67
Total Cost of Labours 88.33
Total 2,200.16
Add 15% for overhead & Profit 330.02
Grand Total 2,530.19
Say 2,530.00
Supervision (15% on Labour Cost) 13.25
Page No -76-
FITTING OF LIGHTNING ARRESTER
7.04 Providing and erection of 9 kV, 10 kA Lightning Arrester conforming to IS: 3070
and IEC: 60099-4 complete with Hard drawn stranded aluminium conductors
galvanised steel wire reinforced: ACSR 6/1/2.59 mm Weasel,M.S. Flat Iron of
size 40x6 mm and M.S. Nuts & Bolts of size 16x50 mm full thread, as directed
by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
1501 Lightning Arrester 9kV,
10kA Station Class-II as
per IEC:60099-4 &
IS:3070 specification
No 12,500.00 1.00 12,500.00
1205 Hard drawn standard
aluminium conductors
galvanized steelwire
reinforced conforming
to IS 398(Part-II) with
amendment No. 1, 2
and 3 or the latest
version thereof bearing
ISI mark :ACSR
6/1/2.59mm Weasel.
KM 25,692.00 0.01 128.46
1405 M.S. Flat Iron 40mmx6
mm
kg 105.84 0.25 26.46
2102 M.S. Nut & Bolt 16x50
mm full thread
conforming to IS : 1364-
2 (1992) or any
amendments up to date.
kg 162.00 0.25 40.50
Total Cost of Materials 12,695.42
Contingency (2% on Material Cost) 253.91
Sub-Total 12,949.33
Labours
1001 Labour Skilled-I manday 380.00 0.00 -
1002 Labour Skilled-II manday 310.00 0.17 51.67
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 0.17 36.67
Total Cost of Labours 88.33
Total 13,037.66
Add 15% for overhead & Profit 1,955.65
Grand Total 14,993.31
Say 14,993.00
Supervision (15% on Labour Cost) 13.25
Page No -77-
INSTALLATION AND FITTING OF DISTRIBUTION TRANSFORMER
8.01 Providing and installation of Outdoor type, oil immersed, naturally cooled 3ph, 50 Hz, Al
wound Distribution Transformer of vector group DYn-1 1 conforming to IS: 1180 (1964),
IS: 2026 (1962) or any amendments there of and ISI marked of the capacity 25 kVA,
11/0.415 kV as directed by the engineer in charge. The transformer should be installed
at an appropriate height to facilitate safety working clearance as specified in Schedule
VII of the CEA (Measures relating to Safety and Electric Supply Regulations), 2010.
Sl. No. Description Unit Rate/Unit Qty. Amount
Material
1301
Out door type oil
immersed naturally cooled
3-ph, 50Hz Al-wound
Distribution Transformer
of vector group DYn-1 1
conforming to IS : 1180
(1964) and IS : 2026
(1962) or latest version
thereof and ISI marked of
the following capacity 25
kVA 11/0.415 kV
No 68,850.00 1.00 68,850.00
Total Cost of Materials 68,850.00
Contingency (2% on Material Cost) 1,377.00
Sub-Total 70,227.00
Labours
1001 Labour Skilled-I manday 380.00 1.00 380.00
1002 Labour Skilled-II manday 310.00 1.50 465.00
1003 Labour Semi-Skilled manday 250.00 1.00 250.00
1004 Labour Un-skilled manday 220.00 12.00 2,640.00
Total Cost of Labours 3,735.00
Total 73,962.00
Add 15% for overhead & Profit 11,094.30
Grand Total 85,056.30
Say 85,056.00
Supervision (15% on Labour Cost) 560.25
Page No -78-
INSTALLATION AND FITTING OF DISTRIBUTION TRANSFORMER
8.02 Providing and installation of Outdoor type, oil immersed, naturally cooled 3ph, 50 Hz, Al
wound Distribution Transformer of vector group DYn-1 1 conforming to IS: 1180 (1964)
and IS: 2026 (1962) or any amendments there of and ISI marked of the capacity 63 kVA,
11/0.415 kV as directed by the engineer in charge. The transformer should be installed
at an appropriate height to facilitate safety working clearance as specified in Schedule
VII of the CEA (Measures relating to Safety and Electric Supply Regulations), 2010.
Sl. No. Description Unit Rate/Unit Qty. Amount
Material
1302
Out door type oil
immersed naturally cooled
3-ph, 50Hz Al-wound
Distribution Transformer
of vector group DYn-11
conforming to IS : 1180
(1964) and IS : 2026
(1962) or latest version
thereof and ISI marked of
the following capacity 63
kVA 11/0.415 kV
No 122,850.00 1.00 122,850.00
Total Cost of Materials 122,850.00
Contingency (2% on Material Cost) 2,457.00
Sub-Total 125,307.00
Labours
1001 Labour Skilled-I manday 380.00 1.00 380.00
1002 Labour Skilled-II manday 310.00 1.50 465.00
1003 Labour Semi-Skilled manday 250.00 1.00 250.00
1004 Labour Un-skilled manday 220.00 16.00 3,520.00
Total Cost of Labours 4,615.00
Total 129,922.00
Add 15% for overhead & Profit 19,488.30
Grand Total 149,410.30
Say 149,410.00
Supervision (15% on Labour Cost) 692.25
Page No -79-
INSTALLATION AND FITTING OF DISTRIBUTION TRANSFORMER
8.03 Providing and installation of Outdoor type, oil immersed, naturally cooled 3ph, 50 Hz, Al
wound Distribution Transformer of vector group DYn-1 1 conforming to IS: 1180 (1964)
and IS: 2026 (1962) or any amendments there of and ISI marked of the capacity 100 kVA,
11/0.415 kV as directed by the engineer in charge. The transformer should be installed at
an appropriate height to facilitate safety working clearance as specified in Schedule VII of
the CEA (Measures relating to Safety and Electric Supply Regulations), 2010.
Sl. No. Description Unit Rate/Unit Qty. Amount
Material
1303
Out door type oil
immersed naturally cooled
3-ph, 50Hz Al-wound
Distribution Transformer
of vector group DYn- 11
conforming to IS : 1180
(1964) and IS : 2026
(1962) or latest version
thereof and ISI marked of
the following capacity 100
kVA 11/0.415 kV
No 179,887.50 1.00 179,887.50
Total Cost of Materials 179,887.50
Contingency (2% on Material Cost) 3,597.75
Sub-Total 183,485.25
Labours
1001 Labour Skilled-I manday 380.00 1.00 380.00
1002 Labour Skilled-II manday 310.00 1.50 465.00
1003 Labour Semi-Skilled manday 250.00 1.00 250.00
1004 Labour Un-skilled manday 220.00 18.00 3,960.00
Total Cost of Labours 5,055.00
Total 188,540.25
Add 15% for overhead & Profit 28,281.04
Grand Total 216,821.29
Say 216,821.00
Supervision (15% on Labour Cost) 758.25
Page No -80-
INSTALLATION AND FITTING OF DISTRIBUTION TRANSFORMER
8.04 Providing and installation of Outdoor type, oil immersed, naturally cooled 3ph, 50 Hz, Cu
wound Distribution Transformer of vector group DYn-11 with tap changer conforming to
IS: 1180 (1964) and IS: 2026 (1962) or any amendments there of and ISI marked of the
capacity 250 kVA, 11/0.415 kV as directed by the engineer in charge. The transformer
should be installed at an appropriate height to facilitate safety working clearance as
specified in Schedule VII of the CEA (Measures relating to Safety and Electric Supply
Regulations), 2010.
Sl. No. Description Unit Rate/Unit Qty. Amount
Material
1304
Out door type oil
immersed naturally cooled
3-ph, 50Hz Cu-wound
Distribution Transformer
of vector group DYn-1 1
with tap changer
conforming to IS : 1180
(1964) and IS : 2026
(1962) or latest version
thereof and ISI marked of
the following capacity 250
kVA 11/0.415 kV
No 375 ,300.00 1.00 375 ,300.00
Total Cost of Materials 375,300.00
Contingency (2% on Material Cost) 7,506.00
Sub-Total 382,806.00
Labours
1001 Labour Skilled-I manday 380.00 1.00 380.00
1002 Labour Skilled-II manday 310.00 1.50 465.00
1003 Labour Semi-Skilled manday 250.00 1.00 250.00
1004 Labour Un-skilled manday 220.00 25.00 5,500.00
Total Cost of Labours 6,595.00
Total 389,401.00
Add 15% for overhead & Profit 58,410.15
Grand Total 447,811.15
Say 447,811.00
Supervision (15% on Labour Cost) 989.25
Page No -81-
INSTALLATION AND FITTING OF DISTRIBUTION TRANSFORMER
8.05 Providing and installation of Outdoor type, oil immersed, naturally cooled 3ph, 50 Hz, Cu
wound Distribution Transformer of vector group DYn-1 1 with tap changer conforming to
IS: 1180 (1964) and IS: 2026 (1962) or any amendments there of and ISI marked of the
capacity 500 kVA, 11/0.415 kV as directed by the engineer in charge. The transformer
should be installed at an appropriate height to facilitate safety working clearance as
specified in Schedule VII of the CEA (Measures relating to Safety and Electric Supply
Regulations), 2010.
Sl. No. Description Unit Rate/Unit Qty. Amount
Material
1305
Out door type oil
immersed naturally 3-ph,
10Hz Cu-wound
Distribution Transformer
of vector group DYn-1 1
with tap changer and air
breather with first filling
oil conforming to IS : 1180
(1964) and IS : 2026
(1962) or latest version
thereof and ISI marked of
the following capacity 500
kVA 11/0.415 kV
No 1,010,515.50 1.00 1,010,515.50
Total Cost of Materials 1,010,515.50
Contingency (2% on Material Cost) 20,210.31
Sub-Total 1,030,725.81
Labours
1001 Labour Skilled-I manday 380.00 1.00 380.00
1002 Labour Skilled-II manday 310.00 2.50 775.00
1003 Labour Semi-Skilled manday 250.00 1.00 250.00
1004 Labour Un-skilled manday 220.00 32.50 7,150.00
Total Cost of Labours 8,555.00
Total 1,039,280.81
Add 15% for overhead & Profit 155,892.12
Grand Total 1,195,172.93
Say 1,195,173.00
Supervision (15% on Labour Cost) 1,283.25
Page No -82-
INSTALLATION AND FITTING OF DISTRIBUTION TRANSFORMER
8.06 Providing and installation of Outdoor type, oil immersed, naturally cooled 3ph, 50 Hz, Cu
wound Distribution Transformer of vector group DYn-1 1 with tap changer conforming to
IS: 1180 (1964) and IS: 2026 (1962) or any amendments there of and ISI marked of the
capacity 630 kVA, 11/0.415 kV as directed by the engineer in charge. The transformer
should be installed at an appropriate height to facilitate safety working clearance as
specified in Schedule VII of the CEA (Measures relating to Safety and Electric Supply
Regulations), 2010.
Sl. No. Description Unit Rate/Unit Qty. Amount
Material
1306
Out door type oil immersed
naturally 3-ph, 10Hz Cu-
wound Distribution
Transformer of vector
group DYn-1 1 with tap
changer conforming to IS :
1180 (1964) and IS : 2026
(1962) or latest version
thereof and ISI marked of
the following capacity 630
kVA 11/0.415 kV
No 1,099,575.00 1.00 1,099,575.00
Total Cost of Materials 1,099,575.00
Contingency (2% on Material Cost) 21,991.50
Sub-Total 1,121,566.50
Labours
1001 Labour Skilled-I manday 380.00 1.00 380.00
1002 Labour Skilled-II manday 310.00 2.50 775.00
1003 Labour Semi-Skilled manday 250.00 1.00 250.00
1004 Labour Un-skilled manday 220.00 35.50 7,810.00
Total Cost of Labours 9,215.00
Total 1,130,781.50
Add 15% for overhead & Profit 169,617.23
Grand Total 1,300,398.73
Say 1,300,399.00
Supervision (15% on Labour Cost) 1,382.25
Page No -83-
INSTALLATION AND FITTING OF DISTRIBUTION TRANSFORMER
8.07 Providing and installation of Outdoor type, oil immersed, naturally cooled 3ph, 50 Hz, Cu
wound Distribution Transformer of vector group DYn- 11 with tap changer conforming to
IS: 1180 (1964) and IS: 2026 (1964) or any amendments there of and ISI marked of the
capacity 750 kVA, 11/0.415 kV as directed by the engineer in charge. The transformer
should be installed at an appropriate height to facilitate safety working clearance as
specified in Schedule VII of the CEA (Measures relating to Safety and Electric Supply
Regulations), 2010.
Sl. No. Description Unit Rate/Unit Qty. Amount
Material
1307
Out door type oil immersed
naturally 3-ph, 10Hz Cu-
wound Distribution
Transformer of vector
group DYn-1 1 with tap
changer conforming to IS :
1180 (1964) and IS : 2026
(1962) or latest version
thereof and ISI marked of
the following capacity 750
kVA 11/0.415 kV
No 1,215,000.00 1.00 1,215,000.00
Total Cost of Materials 1,215,000.00
Contingency (2% on Material Cost) 24,300.00
Sub-Total 1,239,300.00
Labours
1001 Labour Skilled-I manday 380.00 1.00 380.00
1002 Labour Skilled-II manday 310.00 2.50 775.00
1003 Labour Semi-Skilled manday 250.00 1.00 250.00
1004 Labour Un-skilled manday 220.00 45.00 9,900.00
Total Cost of Labours 11,305.00
Total 1,250,605.00
Add 15% for overhead & Profit 187,590.75
Grand Total 1,438,195.75
Say 1,438,196.00
Supervision (15% on Labour Cost) 1,695.75
Page No -84-
INSTALLATION AND FITTING OF DISTRIBUTION TRANSFORMER
8.08 Providing and installation of Outdoor type, oil immersed, naturally cooled 3ph, 50 Hz, Cu
wound Distribution Transformer of vector group DYn-1 1 with tap changer conforming to
IS: 1180 (1964) and IS: 2026 (1962) or any amendments there of and ISI marked of the
capacity 1000 kVA, 11/0.415 kV as directed by the engineer in charge. The transformer
should be installed at an appropriate height to facilitate safety working clearance as
specified in Schedule VII of the CEA (Measures relating to Safety and Electric Supply
Regulations), 2010.
Sl. No. Description Unit Rate/Unit Qty. Amount
Material
1308
Out door type oil
immersed naturally cooled
3-ph, 50Hz Cu-wound
Distribution Transformer
of vector group DYn- 11
with tap changer
conforming to IS : 1180
(1964) and IS : 2026
(1962) or latest version
thereof and ISI marked of
the following capacity
1000 kVA 11/0.415 kV
No 1 ,771 ,875.00 1.00 1 ,771 ,875.00
Total Cost of Materials 1,771,875.00
Contingency (2% on Material Cost) 35,437.50
Sub-Total 1,807,312.50
Labours
1001 Labour Skilled-I manday 380.00 1.00 380.00
1002 Labour Skilled-II manday 310.00 1.50 465.00
1003 Labour Semi-Skilled manday 250.00 1.00 250.00
1004 Labour Un-skilled manday 220.00 52.50 11,550.00
Total Cost of Labours 12,645.00
Total 1,819,957.50
Add 15% for overhead & Profit 272,993.63
Grand Total 2,092,951.13
Say 2,092,951.00
Supervision (15% on Labour Cost) 1,896.75
Page No -85-
INSTALLATION OF COMPACT SWITCHGEAR SUBSTATION
8.09 Providing and installation of 100 kVA, 11/0.415 kV, DYn-1 1 Compact Switchgear
Substation (CSS) Transformer with off circuit tap of rating +5 to -5 @ 2.5% comprising of
the following components ; as directed by the engineer in charge
a) HT Switchgear: 11 kV, 200 A, Air Insulated Switchgear consisting of Load Break
Switchand Fuse for protection of transformer, Interconnection between HT switchgear
and transformer shall be using 1Cx3x25 sq.mm Al unarmoured XLPE cable. The system
includes HT< metering components.
b) LT Switchboard: 250 A, 3P, 36 kA Fixed manual MCCB with Microprocessor based O/C, E/F, S/C
release as incomer cum outgoing
Sl. No. Description Unit Rate/Unit Qty. Amount
Material
1309
100kVA, 11/0.415 kV,
Dyn1 1 CSS Transformer
with off circuit tap of
rating +5 to-5 @ 2.5%
comprising of
a) HT Switchgear: 11kV,
200A, Air Insulated
Switchgear consisting of
Load Break Switchand
Fuse for protection of
transformer,
Interconnection between
HTswitchgear and
transformer shall be using
1Cx3x25 sq.mm
Al.unarmorured XLPE
Cable. The system
includes HT & LT metering
components.
b) LT Switchboard: 250A 3P
36kA Fixed Manual MCCB
with Microprocessor based
O/C, E/F, S/C release as
incomer cum outgoing.
No 1 ,951 ,000.00 1.00 1 ,951 ,000.00
Total Cost of Materials 1,951,000.00
Contingency (2% on Material Cost) 39,020.00
Sub-Total 1,990,020.00
Labours
1001 Labour Skilled-I manday 380.00 2.00 760.00
1002 Labour Skilled-II manday 310.00 2.00 620.00
1003 Labour Semi-Skilled manday 250.00 5.00 1,250.00
1004 Labour Un-skilled manday 220.00 79.00 17,380.00
Total Cost of Labours 20,010.00
Total 2,010,030.00
Add 15% for overhead & Profit 301,504.50
Grand Total 2,311,534.50
Say 2,311,535.00
Supervision (15% on Labour Cost) 3,001.50
Page No -86-
INSTALLATION OF COMPACT SWITCHGEAR SUBSTATION
8.10 Providing and installation of 160 kVA, 11/0.415 kV, DYn-11 Compact Switchgear Substation
(CSS) Transformer with off circuit tap of rating +5 to -5 @ 2.5% comprising of the following
components ; as directed by the engineer in charge
a) HT Switchgear: 11 kV, 200 A, Air Insulated Switchgear consisting of Load Break
Switchand Fuse for protection of transformer, Interconnection between HT switchgear and
transformer shall be using 1Cx3x25 sq.mm Al unarmoured XLPE cable. The system includes
HT< metering components.
b) LT Switchboard: 250 A, 3P, 36 kA Fixed manual MCCB with Microprocessor based O/C, E/F, S/C
release as incomer cum outgoing
Sl. No. Description Unit Rate/Unit Qty. Amount
Material
1310
160kVA, 11/0.415 kV, Dyn11
CSS Transformer with off
circuit tap of rating +5 to-5
@ 2.5% comprising of
a) HT Switchgear: 11kV, 200A,
Air Insulated Switchgear
consisting of Load Break
Switchand Fuse for protection
of transformer, Interconnection
between HTswitchgear and
transformer shall be using
1Cx3x25 sq.mm
Al.unarmorured XLPE Cable.
The system includes HT & LT
metering components.
b) LT Switchboard: 250A 3P 36kA
Fixed Manual MCCB with
Microprocessor based O/C, E/F,
S/C release as incomer cum
outgoing.
No 2,380,000.00 1.00 2,380,000.00
Total Cost of Materials 2,380,000.00
Contingency (2% on Material Cost) 47,600.00
Sub-Total 2,427,600.00
Labours
1001 Labour Skilled-I manday 380.00 2.00 760.00
1002 Labour Skilled-II manday 310.00 2.00 620.00
1003 Labour Semi-Skilled manday 250.00 5.00 1,250.00
1004 Labour Un-skilled manday 220.00 90.00 19,800.00
Total Cost of Labours 22,430.00
Total 2,450,030.00
Add 15% for overhead & Profit 367,504.50
Grand Total 2,817,534.50
Say 2,817,535.00
Supervision (15% on Labour Cost) 3,364.50
Page No -87-
INSTALLATION OF COMPACT SWITCHGEAR SUBSTATION
8.11 Providing and installation of 200 kVA, 11/0.415 kV, DYn-11 Compact Switchgear Substation
(CSS) Transformer with off circuit tap of rating +5 to -5 @ 2.5% comprising of the following
components ; as directed by the engineer in charge
a) HT Switchgear: 11 kV, 200 A, Air Insulated Switchgear consisting of Load Break Switchand
Fuse for protection of transformer, Interconnection between HT switchgear and transformer
shall be using 1Cx3x25 sq.mm Al unarmoured XLPE cable. The system includes HT<
metering components.
b) LT Switchboard: 320 A, 3P, 36 kA Fixed manual MCCB with Microprocessor based O/C,
E/F, S/C release as incomer cum outgoing
Sl. No. Description Unit Rate/Unit Qty. Amount
Material
1311
200kVA, 11/0.415 kV,
Dyn11 CSS Transformer
with off circuit tap of rating
+5 to-5 @ 2.5% comprising of
a) HT Switchgear: 11kV,
200A, Air Insulated
Switchgear consisting of Load
Break Switchand Fuse for
protection of transformer,
Interconnection between
HTswitchgear and
transformer shall be using
1Cx3x25 sq.mm
Al.unarmorured XLPE Cable.
The system includes HT & LT
metering components.
b) LT Switchboard: 320A 3P
36kA Fixed Manual MCCB
with Microprocessor based
O/C, E/F, S/C release as
incomer cum outgoing.
No 2,675,000.00 1.00 2,675,000.00
Total Cost of Materials 2,675,000.00
Contingency (2% on Material Cost) 53,500.00
Sub-Total 2,728,500.00
Labours
1001 Labour Skilled-I manday 380.00 2.00 760.00
1002 Labour Skilled-II manday 310.00 2.00 620.00
1003 Labour Semi-Skilled manday 250.00 5.00 1,250.00
1004 Labour Un-skilled manday 220.00 105.00 23,100.00
Total Cost of Labours 25,730.00
Total 2,754,230.00
Add 15% for overhead & Profit 413,134.50
Grand Total 3,167,364.50
Say 3,167,365.00
Supervision (15% on Labour Cost) 3,859.50
Page No -88-
INSTALLATION OF COMPACT SWITCHGEAR SUBSTATION
8.12 Providing and installation of 250 kVA, 11/0.415 kV, DYn-11 Compact Switchgear Substation (CSS)
Transformer with off circuit tap of rating +5 to -5 @ 2.5% comprising of the following components; as directed
by the engineer in charge:
a) HT Switchgear: 11 kV, 630 A, 21 kA for 3 sec, SF6 insulated Non-Extinsible Compact switchgear
(Type DV) consisting of one no. Direct Switch and one no. Fixed Manual Vacuum Circuit Breaker in
SF6 with insulated stainless steel enclosure, with series trip, self powered microprocessor based
numerical relay for over current and earth fault (IDMTL+inst.) protection, interconnection between
HT switchgear and transformer shall be using 1Cx3x25 sq.mm Al unarmoured XLPE cable. The
system includes HT< metering components.
b) LT Switchboard: 400 A, 3P, 36 kA Fixed manual MCCB with Microprocessor based O/C, E/F, S/C release
as incomer cum outgoing
Sl. No. Description Unit Rate/Unit Qty. Amount
Material
1312
250kVA, 11/0.415 kV, Dyn11 with off
circuit tap of rating +5 to-5 @ 2.5%
comprising of
a) HT Switchgear: 1 1kV,630A,2
1KA for 3sec, SF6 insulated Non-
Extinsible Compact switchgear
(Type DV) consisting of one No.
Direct Switch and One No. Fixed
Manual Vacuum Circuit Breaker in
SF6 with insulated stainless steel
enclosure, with series trip, self
powered microprocessor based
numerical relay for over current and
earth fault (IDMTL + Inst.)
protection. Interconnection between
HT switchgear and transformer
shall be using 1Cx3x25 sq.mm Al.
unarm orured XLPE Cable. The
systemincludes HT & LT metering
components
b) LT Switchboard: 400A 3P 36kA
Fixed Manual MCCB with
Microprocessor based O/C, E/F, S/C
release as incomer cum outgoing.
No 2,940,600.00 1.00 2,940,600.00
Total Cost of Materials 2,940,600.00
Contingency (2% on Material Cost) 58,812.00
Sub-Total 2,999,412.00
Labours
1001 Labour Skilled-I manday 380.00 2.00 760.00
1002 Labour Skilled-II manday 310.00 2.00 620.00
1003 Labour Semi-Skilled manday 250.00 5.00 1,250.00
1004 Labour Un-skilled manday 220.00 115.00 25,300.00
Total Cost of Labours 27,930.00
Total 3,027,342.00
Add 15% for overhead & Profit 454,101.30
Grand Total 3,481,443.30
Say 3,481,443.00
Supervision (15% on Labour Cost) 4,189.50
Page No -89-
INSTALLATION OF COMPACT SWITCHGEAR SUBSTATION
8.13 Providing and installation of 315 kVA, 11/0.415 kV, DYn-11 Compact Switchgear Substation (CSS)
Transformer with off circuit tap of rating +5 to -5 @ 2.5% comprising of the following components; as
directed by the engineer in charge
a) HT Switchgear: 11 kV, 630 A, 21 kA for 3 sec, SF6 insulated Non-Extinsible Compact
switchgear (Type DV) consisting of one no. Direct Switch and one no. Fixed Manual Vacuum
Circuit Breaker in SF6 with insulated stainless steel enclosure, with series trip, self powered
microprocessor based numerical relay for over current and earth fault (IDMTL+inst.) protection,
interconnection between HT switchgear and transformer shall be using 1Cx3x25 sq.mm Al
unarmoured XLPE cable. The system includes HT< metering components.
b) LT Switchboard: 630 A, 3P, 36 kA Fixed manual MCCB with Microprocessor based O/C, E/F, S/C
release as incomer cum outgoing
Sl. No. Description Unit Rate/Unit Qty. Amount
Material
1313
315kVA, 11/0.415 kV, Dyn11 with off
circuit tap of rating +5 to-5 @ 2.5%
comprising of
a) HT Switchgear: 11kV,630A,21KA
for 3sec, SF6 insulated Non-
Extinsible Compact switchgear (Type
DV) consisting of one No. Direct
Switch and One No. Fixed Manual
Vacuum Circuit Breaker in SF6 with
insulated stainlesssteel enclosure,
with series trip, self powered
microprocessor based numerical
relay for over current and earth fault
(IDMTL + Inst.) protection.
Interconnection between HT
switchgear and transformershall be
using 1Cx3x25 sq.mm Al.
unarm orure d XLPE Cable. The
system includes HT & LT metering
components
b) LT Switchboard: 630A 3P 36kA
Fixed Manual MCCB with
Microprocessor based O/C, E/F, S/C
release as incomer cum outgoing.
No 3,450,800.00 1.00 3,450,800.00
Total Cost of Materials 3,450,800.00
Contingency (2% on Material Cost) 69,016.00
Sub-Total 3,519,816.00
Labours
1001 Labour Skilled-I manday 380.00 2.00 760.00
1002 Labour Skilled-II manday 310.00 2.00 620.00
1003 Labour Semi-Skilled manday 250.00 5.00 1,250.00
1004 Labour Un-skilled manday 220.00 130.00 28,600.00
Total Cost of Labours 31,230.00
Total 3,551,046.00
Add 15% for overhead & Profit 532,656.90
Grand Total 4,083,702.90
Say 4,083,703.00
Supervision (15% on Labour Cost) 4,684.50
Page No -90-
INSTALLATION OF COMPACT SWITCHGEAR SUBSTATION
8.14 Providing and installation of 400 kVA, 11/0.415 kV, DYn-1 1 CSS Transformer with off circuit tap
of rating +5 to -5 @ 2.5% comprising of the following components ; as directed by the engineer in
charge
a) HT Switchgear: 11 kV, 630 A, 21 kA for 3 sec, SF6 insulated Non-Extinsible Compact switchgear
(Type DV) consisting of one no. Direct Switch and one no. Fixed Manual Vacuum Circuit Breaker in
SF6 with insulated stainless steel enclosure, with series trip, self powered microprocessor based
numerical relay for over current and earth fault (IDMTL+inst.) protection, interconnection between
HT switchgear and transformer shall be using 1Cx3x25 sq.mm Al unarmoured XLPE cable. The
system includes HT< metering components.
b) LT Switchboard: 630 A, 3P, 36 kA Fixed manual ACB with Microprocessor based O/C, E/F, S/C release
as incomer cum outgoing
Sl. No. Description Unit Rate/Unit Qty. Amount
Material
1314
400kVA, 11/0.415 kV, Dyn11 with off
circuit tap of rating +5 to-5 @ 2.5%
comprising of
a) HT Switchgear: 11kV,630A,21KA
for 3sec, SF6 insulated Non-
Extinsible Compact switchgear
(Type DV) consisting of one No.
Direct Switch and One No. Fixed
Manual Vacuum Circuit Breaker in
SF6 with insulated stainlesssteel
enclosure, with series trip, self
powered microprocessor based
numerical relay for over current and
earth fault (IDMTL + Inst.)
protection. Interconnection between
HT switchgear and transformershall
be using 1Cx3x25 sq.mm Al.
unarmorured XLPE Cable. The
system includes HT & LT metering
components
b) LT Switchboard: 630A 3P 36kA
Fixed Manual ACCB with
Microprocessor based O/C, E/F, S/C
release as incomer cum outgoing.
No 3 ,745 ,000.00 1.00 3 ,745 ,000.00
Total Cost of Materials 3,745,000.00
Contingency (2% on Material Cost) 74,900.00
Sub-Total 3,819,900.00
Labours
1001 Labour Skilled-I manday 380.00 2.00 760.00
1002 Labour Skilled-II manday 310.00 2.00 620.00
1003 Labour Semi-Skilled manday 250.00 5.00 1,250.00
1004 Labour Un-skilled manday 220.00 140.00 30,800.00
Total Cost of Labours 33,430.00
Total 3,853,330.00
Add 15% for overhead & Profit 577,999.50
Grand Total 4,431,329.50
Say 4,431,330.00
Supervision (15% on Labour Cost) 5,014.50
Page No -91-
INSTALLATION OF COMPACT SWITCHGEAR SUBSTATION
8.15 Providing and installation of 500 kVA, 11/0.415 kV, DYn-11 CSS Transformer with offcircuit tap of
rating +5 to -5 @ 2.5% comprising of the following components ; as directed by the engineer in
charge
a) HT Switchgear: 11 kV, 630 A, 21 kA for 3 sec, SF6 insulated Non-Extinsible Compact switchgear
(Type DV) consisting of one no. Direct Switch and one no. Fixed Manual Vacuum Circuit Breaker
in SF6 with insulated stainless steel enclosure, with series trip, self powered microprocessor
based numerical relay for over current and earth fault (IDMTL+inst.) protection, interconnection
between HT switchgear and transformer shall be using 1Cx3x25 sq.mm Al unarmoured XLPE
cable. The system includes HT< metering components.
b ) T S Sl. No. 00 A, 3P, 50 k Description l ACB Unit h Microproc Rate/Unit base Qty. E/F, S/C Amount
Material
1315
500kVA, 11/0.415 kV, Dyn1 1 with off
circuit tap of rating +5 to-5 @ 2.5%
comprising of
a) HT Switchgear: 1 1kV,630A,21KA
for 3sec, SF6 insulated Non-
Extinsible Compact switchgear (Type
DV) consisting of one No. Direct
Switch and One No. Fixed Manual
Vacuum Circuit Breaker in SF6 with
insulated stainlesssteel enclosure,
with series trip, self powered
microprocessor based numerical
relay for over current and earth fault
(IDMTL + Inst.) protection.
Interconnection between HT
switchgear and transformershall be
using 1Cx3x25 sq.mm Al.
unarmorured XLPE Cable. The
system includes HT & LT metering
components
b) LT Switchboard: 800A 3P 50kA
Fixed Manual ACB with
Microprocessor based O/C, E/F, S/C
release as incomer cum outgoing.
No 3,980,400.00 1.00 3,980,400.00
Total Cost of Materials 3,980,400.00
Contingency (2% on Material Cost) 79,608.00
Sub-Total 4,060,008.00
1001 Labour Skilled-I manday 380.00 2.00 760.00
1002 Labour Skilled-II manday 310.00 2.00 620.00
1003 Labour Semi-Skilled manday 250.00 5.00 1,250.00
1004 Labour Un-skilled manday 220.00 150.00 33,000.00
Total Cost of Labours 35,630.00 Total 4,095,638.00
Add 15% for overhead & Profit 614,345.70
Grand Total 4,709,983.70
Say 4,709,984.00
Supervision (15% on Labour Cost) L
Page No -92-
INSTALLATION OF COMPACT SW ITCHGEAR SUBSTATION
8.16 Providing and installation of 630 kVA, 11/0.415 kV, DYn-11 CSS Transformer with off circuit tap of
rating +5 to -5 @ 2.5% comprising of the following components ; as directed by the engineer in
charge
a) HT Switchgear: 11 kV, 630 A, 21 kA for 3 sec, SF6 insulated Non-Extinsible Compact switchgear
(Type DV) consisting of one no. Direct Switch and one no. Fixed Manual Vacuum Circuit Breaker in
SF6 with insulated stainless steel enclosure, with series trip, self powered microprocessor based
numerical relay for over current and earth fault (IDMTL+inst.) protection, interconnection between
HT switchgear and transformer shall be using 1Cx3x25 sq.mm Al unarmoured XLPE cable. The
system includes HT< metering components.
:
Labours
1001 Labour Skilled-I manday 380.00 2.00 760.00
1002 Labour Skilled-II manday 310.00 2.00 620.00
1003 Labour Semi-Skilled manday 250.00 5.00 1,250.00
1004 Labour Un-skilled manday 220.00 165.00 36,300.00
Total Cost of Labours 38,930.00
Total 4,884,440.00
Add 15% for overhead & Profit 732,666.00
Grand Total 5,617,106.00
Say 5,617,106.00
Supervision (15% on Labour Cost) Sl. No.
Page No -93-
Sl. No.
Materials
Description
1401 M.S. Channel 75 x 40 x 6
mm
1405 M.S. Flat Iron 40mmx6
mm
2102 M.S. Nut & Bolt 16x50
mm full thread
conforming to IS : 1364-
2 (1992) or any
amendments up to date.
2103 M.S. Nut & Bolt 16 x
155 mm full thread
conforming to IS : 1364-
2 (1992) or any
amendments up to date.
2201 Aluminium Paint
2203 Red Oxide Paint
PLACING OF DISTRIBUTION TRANSFORMER
PREPARATION OF DT MOUNTING STRUCTURE
9.01 Providing and Erection of Mounting Structure for Distribution Transformer up to 100
kVA, GOAB Switch, Arcing Horn fuse Unit etc, mounted between two SP-35 (swagged
steel tubular poles) 2.44 m apart, as directed by the engineer in charge.The height of
DT mounting channel should facilitate safety working clearance, as specified in
Schedule VII of the CEA (Measures relating to Safety and Electric Supply
Regulations), 2010.
Unit Rate/Unit Qty.
kg 105.84 176.72
kg 105.84 4.39
kg 162.00 2.63
kg 162.00 6.73
Lit 170.00 0.10
Lit 125.00 0.10
Labours
Total 22,698.32
Add 15% for overhead & Profit 3,404.75
Grand Total 26,103.07
Say 26,103.00
Supervision (15% on Labour Cost) 235.50
Amount
18,703.52
464.70
425.74
1,090.58
17.00
12.50
Total Cost of Materials 20,714.04
Contingency (2% on Material Cost)
Sub-Total
414.28
21,128.32
Total Cost of Labours 1,570.00
1001 Labour Skilled-I man day 380.00 1.00
1002 Labour Skilled-II man day 310.00 1.00
1003 Labour Semi-Skilled manday 250.00 0.00
1004 Labour Un-skilled man day 220.00 4.00
380.00
310.00
-
880.00
Page No -94-
Sl. No. Description
Materials
1401 M.S. Channel 75 x 40 x 6
mm
1405 M.S. Flat Iron 40mmx6
mm
2102 M.S. Nut & Bolt 16x50
mm full thread
conforming to IS : 1364-
2 (1992) or any
amendments up to date.
2103 M.S. Nut & Bolt 16 x
155 mm full thread
conforming to IS : 1364-
2 (1992) or any
amendments up to date.
2201 Aluminium Paint
2203 Red Oxide Paint
PREPARATION OF DT MOUNTING STRUCTURE
9.02 Providing and Erection of Mounting Structure for Distribution Transformer up to 100
kVA fitted with GOAB Switch, Drop Out Fuse Unit, mounted between two SP-35
(swagged steel tubular poles) 2.44 m apart, as directed by the engineer in charge. The
height of DT mounting channel should facilitate safety working clearance, as
specified in Schedule VII of the CEA (Measures relating to Safety and Electric Supply
Regulations), 2010.
Unit Rate/Unit Qty.
kg 105.84 176.72
kg 105.84 4.39
kg 162.00 2.63
kg 162.00 6.73
Lit 170.00 0.10
Lit 125.00 0.10
Labours
Total 22,698.32
Add 15% for overhead & Profit 3,404.75
Grand Total 26,103.07
Say 26,103.00
Supervision (15% on Labour Cost) 235.50
Amount
18,703.52
464.70
425.74
1,090.58
17.00
12.50
Total Cost of Materials 20,714.04
Contingency (2% on Material Cost) 414.28
Sub-Total 21,128.32
Total Cost of Labours 1,570.00
1001 Labour Skilled-I manday 380.00 1.00
1002 Labour Skilled-II manday 310.00 1.00
1003 Labour Semi-Skilled manday 250.00 0.00
1004 Labour Un-skilled manday 220.00 4.00
380.00
310.00
-
880.00
Page No -95-
CONSTRUCTION OF GROUND MOUNTED DT PLATFORM
9.02 Construction of Ground Mounted Platform for Distribution Transformer above 100 kVA
upto 250 kVA at a height of 1.4 metres from ground level,1.5 x 2.0 metres
area,constructed with stone masonry and top PCC 15 cm thick.
Sl. No. Description Unit Rate/Unit Qty. Amount
Material 1401 M.S. Channel 75 x 40 x 6
mm
kg 105.84 329.47 34,870.67
1405 M.S. Flat Iron 40mmx6
mm
kg 105.84 4.39 464.70
2102 M.S. Nut & Bolt 16x50
mm full thread
conforming to IS : 13
64- 2 (1992) or any
amendments up to
kg 162.00 2.50 405.00
2201 Aluminium Paint Lit 170.00 0.45 76.50
2203 Red Oxide Paint Lit 125.00 0.45 56.25
2301 Cement cum 13,750.00 0.02 275.00
2302 River Sand cum 2,100.00 0.06 126.00
2303 Stone Aggregate 10-20
mm
cum 1,890.00 0.12 226.80
Total Cost of Materials 36,500.92
Labours
1001 Labour Skilled-I manday 380.00 1.00 380.00
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 1.00 250.00
1004 Labour Un-skilled manday 220.00 8.00 1,760.00
Total Cost of Labours 2,390.00
Total 38,890.92
Add 15% for overhead & Profit 5,833.64
Grand Total 44,724.56
Say 44,725.00
Supervision (15% on Labour Cost) 358.50
Page No -96-
CONSTRUCTION OF GROUND MOUNTED DT PLATFORM
9.03 Construction of Ground Mounted Platform for Distribution Transformer above 100 kVA
upto 250 kVA at a height of 1.2 metres from ground level,1.5 x 2.0 metres
area,constructed with stone masonry and top PCC 15 cm thick, as directed by the
engineer in charge. The height of DT mounting channel should facilitate safety
working clearance, as specified in Schedule VII of the CEA (Measures relating to
Safety and Electric Supply Regulations) 201 0
A Regular coursed rubble masonry with hard stone in foundation upto one storey above and below
ground level including curing, etc. complete.
in cement mortar 1 : 3 ( 1cement : 3 fine sand)
Details of cost for 1.00 cum
Description Unit Rate/Unit Qty. Amount
(A) MATERIALS
(i) Blasted rubble cum 1.21 600.00 726.00
(ii) Through and bond sto n cum 0.16 2500.00 400.00
(7no x
0.24x0.24mx0.39m =
0.16 cum)
(iii) Cement mortar 1:3 cum 0.30 5914.40 1,774.32
(A) 2,900.32
(B) LABOURS
(i) 2nd class mason each 2.12 320.00 678.40
(i i ) Semi skilled each 0.90 250.00 225.00
(i i i )Unski l led each 1.95 220.00 429.00
1,332.40
Scaffolding @ 10% 133.24
Sundries and contingencies @ 3% 39.97
(B) 1,505.61
TOTAL (A) + (B) 4,405.93
Add water charge @ 1% 44.06
TOTAL 4,449.99
Add CPOH @ 15% 667.50
Cost for 1.00 cum 5,117.49
Sub-total cum 4.20 21,493.46
Page No -97-
B Providing and laying in position cement concrete of specified grade excluding cost of centering
and shuttering - All work upto plinth level:
1:2:4 (1 cement :2 course sand :4 stone aggregate 20mm nominal size) Details
of Cost for 1.00 cum
Description Unit Rate/Unit Qty. Amount
(A) MATERIALS :
(i) Stone aggregate 20mm cum 0.67 1800.00 1,206.00
(ii) Stone aggregate 10mm cum 0.22 1800.00 396.00
Carriage of stone aggregat cum 0.89 73.42 65.34
(iii) Coarse sand cum 0.45 850.00 378.25
Carriage of course sand cum 0.45 73.42 32.67
(iv) Cement (0.2225 cum ) tonne 0.32 9000.00 2,880.00
(iii) Carriage of cement tonne 0.32 37.46 11.99
(B) LABOURS :
Ist class mason day 0.10 450.00 45.00
Unskilled day 1.63 220.00 358.60
Semi skilled day 0.70 250.00 175.00
Hire charge of concrete m i rday 0.07 1668.00 116.76
Vibrator day 0.07 1068.00 74.76
Sundries L.S 14.30 8.00 114.40
TOTAL 5,854.77
Add water charge @ 1% 58.55
TOTAL 5,913.32
Add CPOH @ 15% 887.00
Cost for 1.00 cum 6,800.32
Sub-total cum 0.45 3,060.14
Total Cost 24,553.60
24,554.00
Page No -98-
CONSTRUCTION OF GROUND MOUNTED DT PLATFORM
9.04 Construction of Ground Mounted Platform for Distribution Transformer above 250 kVA
upto 1000 kVA at a height of 1.2 metres from ground level,2.5 x 2.0 metres
area,constructed with stone masonry and top PCC 15 cm thick, as directed by the
engineer in charge. The height of DT mounting channel should facilitate safety working
clearance, as specified in Schedule VII of the CEA (Measures relating to Safety and
Electric Supply Regulations) 2 0 1 0
Regular coursed rubble masonry with hard stone in foundation upto one storey above A
and below ground level including curing, etc. complete.
in cement mortar 1 : 3 ( 1cement : 3 fine sand)
Details of cost for 1.00 cum
Description Unit Rate/Unit Qty. Amount
(A) MATERIALS
(i) Blasted rubble cum 1.21 600.00 726.00
(ii) Through and bond sto n cum 0.16 2500.00 400.00
(7no x 0.24x0.24mx0.39m = 0.16 cum) (iii) Cement mortar 1:3 cum 0.30 5914.40 1,774.32
(A) 2,900.32
(B) LABOURS
(i) 2nd class mason each 2.12 320.00 678.40
(ii) Semi skilled each 0.90 250.00 225.00
(iii) Unskilled each 1.95 220.00 429.00
1,332.40
Scaffolding @ 10% 133.24
Sundries and contingencies @ 3% 39.97
(B) 1,505.61
TOTAL (A) + (B) 4,405.93
Add water charge @ 1% 44.06
TOTAL 4,449.99
Add CPOH @ 15% 667.50
Cost for 1.00 cum 5,117.49
Sub-total cum 5.00 25,587.45
Page No -99-
B Providing and laying in position cement concrete of specified grade excluding cost
of centering and shuttering - All work upto plinth level:
1:2:4 (1 cement :2 course sand :4 stone aggregate 20mm nominal size) Details
of Cost for 1.00 cum
Description Unit Rate/Unit Qty. Amount
(A) MATERIALS :
(i) Stone aggregate 20mm cum 0.67 1800.00 1,206.00
(ii) Stone aggregate 10mm cum 0.22 1800.00 396.00
Carriage of stone aggregat cum 0.89 73.42 65.34
(iii) Coarse sand cum 0.45 850.00 378.25
Carriage of course sand cum 0.45 73.42 32.67
(iv) Cement (0.2225 cum ) tonne 0.32 9000.00 2,880.00
(iii) Carriage of cement tonne 0.32 37.46 11.99
(B) LABOURS :
Ist class mason day 0.10 450.00 45.00
Unskilled day 1.63 220.00 358.60
Semi skilled day 0.70 250.00 175.00
Hire charge of concrete m rday 0.07 1668.00 116.76
Vibrator day 0.07 1068.00 74.76
Sundries L.S 14.30 8.00 114.40
TOTAL 5,854.77
Add water charge @ 1% 58.55
TOTAL 5,913.32
Add CPOH @ 15% 887.00
Cost for 1.00 cum 6,800.32
Sub-total cum 0.75 5,100.24
Total Cost 30,687.69
30,688.00
Page No -100-
LAYING AND Fitting OF CABLES
10.01 Providing and Fitting of per meter length 1.1kV Armoured cable 1 core, 10 sq.mm
conforming to IS: 1554-1 (1988) or any ammendments with 10 sq.mm Aluminium
Cable Lug long barrel, as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
1601 1.1 kV Aluminium
Armoured Cable 1 core, 10
sq.mm conforming to IS :
1554-1 (1988) or any
ammendments
m 87.00 25.00 2,175.00
Total Cost of Materials 2,175.00
Contingency (2% on Material Cost) 43.50
Sub-Total 2,218.50
Labours
1001 Labour Skilled-I manday 380.00 0.25 95.00
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 0.83 183.33
Total Cost of Labours 278.33
Total 2,496.83
Add 15% for overhead & Profit 374.53
Grand Total 2,871.36
Say 2,871.00
Say 115.00
Supervision (15% on Labour Cost) 1 .67
Running Circuit Metre Cost
114.84
Page No -10 1-
LAYING AND FITTING OF CABLES
10.02 Providing and Fitting of 1.1kV Aluminium Armoured cable of per meter length, 1
core, 16 sq.mm conforming to IS : 1554-1 (1988) or any ammendments with 16
sq.mm Aluminium Cable Lug long barrel, as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
1602 1.1 kV Aluminium
Armoured Cable 1 core, 16
sq.mm conforming to IS :
1554-1 (1988) or any
ammendments
m 102.00 25.00 2,550.00
Total Cost of Materials 2,550.00
Contingency (2% on Material Cost) 51.00
Sub-Total 2,601.00
Labours
1001 Labour Skilled-I manday 380.00 0.25 95.00
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 0.83 183.33
Total Cost of Labours 278.33
Total 2,879.33
Add 15% for overhead & Profit 431.90
Grand Total 3,311.23
Say 3,311.00
Say 132.00
Supervision (15% on Labour Cost) 1 .67
Running Circuit Metre Cost
132.44
Page No -102-
LAYING AND FITTING OF CABLES
10.03 Providing and Fitting of 1.1kV Armoured cable of per meter length, 1 core, 35 sq.mm
conforming to IS : 1554-1 (1988) or any ammendments with35 sq.mm Aluminium
Cable Lug long barrel, as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
1603 1.1 kV Aluminium
Armoured Cable 1 core,
35 sq.mm conforming to
IS : 1554-1 (1988) or any
ammendments
m 147.00 25.00 3,675.00
Total Cost of Materials 3,675.00
Contingency (2% on Material Cost) 73.50
Sub-Total 3,748.50
Labours
1001 Labour Skilled-I manday 380.00 0.25 95.00
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 1.08 238.33
Total Cost of Labours 333.33
Total 4,081.83
Add 15% for overhead & Profit 612.28
Grand Total 4,694.11
Say 4,694.00
Say 188.00
Supervision (15% on Labour Cost) 2.00
Running Circuit Metre Cost
187.76
Page No -103-
LAYING AND FITTING OF CABLES
10.04 Providing and Fitting of length 1.1kV Armoured cable of per meter length, 1 core, 50
sq.mm conforming to IS : 1554-1 (1988) or any ammendments with 50 sq.mm
Aluminium Cable Lug long barrel, as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
1604 1.1 kV Aluminium
Armoured Cable 1 core,
50 sq.mm conforming to
IS : 1554-1 (1988) or any
ammendments
m 191.00 25.00 4,775.00
Total Cost of Materials 4,775.00
Contingency (2% on Material Cost) 95.50
Sub-Total 4,870.50
Labours
1001 Labour Skilled-I manday 380.00 0.25 95.00
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 1.08 238.33
Total Cost of Labours 333.33
Total 5,203.83
Add 15% for overhead & Profit 780.58
Grand Total 5,984.41
Say 5,984.00
Say 239.00
Supervision (15% on Labour Cost) 2.00
Running Circuit Metre Cost
239.36
Page No -104-
LAYING AND FITTING OF CABLES
10.05 Providing and Fitting of length 1.1 kV Armoured cable of per meter length, 1 core, 70
sq.mm conforming to IS : 1554-1 (1988) or any ammendments with 70 sq.mm
Aluminium Cable Lug long barrel, as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
1605 1.1 kV Aluminium
Armoured Cable 1 core,
70 sq.mm conforming to
IS : 1554-1 (1988) or any
ammendments
m 225.00 25.00 5,625.00
Total Cost of Materials 5,625.00
Contingency (2% on Material Cost) 112.50
Sub-Total 5,737.50
Labours
1001 Labour Skilled-I manday 380.00 0.25 95.00
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 1.25 275.00
Total Cost of Labours 370.00
Total 6,107.50
Add 15% for overhead & Profit 916.13
Grand Total 7,023.63
Say 7,024.00
Say 281.00
Supervision (15% on Labour Cost) 2.22
Running Circuit Metre Cost
280.96
Page No -105-
LAYING AND FITTING OF CABLES
10.06 Providing and Fitting of 1.1kV Armoured cable of per meter length, 1 core, 95 sq.mm
conforming to IS : 1554-1 (1988) or any ammendments with 95 sq.mm Aluminium
Cable Lug long barrel, as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
1606 1.1 kV Aluminium
Armoured Cable 1 core,
95 sq.mm conforming to
IS : 1554-1 (1988) or any
ammendments
m 278.00 25.00 6,950.00
Total Cost of Materials 6,950.00
Contingency (2% on Material Cost) 139.00
Sub-Total 7,089.00
Labours
1001 Labour Skilled-I manday 380.00 0.25 95.00
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 1.25 275.00
Total Cost of Labours 370.00
Total 7,459.00
Add 15% for overhead & Profit 1,118.85
Grand Total 8,577.85
Say 8,578.00
Say 343.00
Supervision (15% on Labour Cost) 2.22
Running Circuit Metre Cost
343.12
Page No -106-
LAYING AND FITTING OF CABLES
10.07 Providing and Fitting of 1.1kV Armoured cable of per meter length, 1 core, 120 sq.mm
conforming to IS : 1554-1 (1988) or any ammendments with 120 sq.mm Aluminium
Cable Lug long barrel, as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
1607 1.1 kV Aluminium
Armoured Cable 1 core,
120 sq.mm conforming to
IS : 1554-1 (1988) or any
ammendments
m 375.00 25.00 9,375.00
Total Cost of Materials 9,375.00
Contingency (2% on Material Cost) 187.50
Sub-Total 9,562.50
Labours
1001 Labour Skilled-I manday 380.00 0.25 95.00
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 1.50 330.00
Total Cost of Labours 425.00
Total 9,987.50
Add 15% for overhead & Profit 1,498.13
Grand Total 11,485.63
Say 11,486.00
Say 459.00
Supervision (15% on Labour Cost) 2.55
Running Circuit Metre Cost
459.44
Page No -107-
LAYING AND FITTING OF CABLES
10.08 Providing and Fitting of 1.1kV Armoured cable of per meter length, 1 core, 150 sq.mm
conforming to IS : 1554-1 (1988) or any ammendments with 150 sq.mm Cable Lug
long barrel, as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
1608 1.1 kV Aluminium
Armoured Cable 1 core,
150 sq.mm conforming
to IS : 1554-1 (1988) or
any ammendments
m 525.00 25.00 13,125.00
Total Cost of Materials 13,125.00
Contingency (2% on Material Cost) 262.50
Sub-Total 13,387.50
Labours
1001 Labour Skilled-I manday 380.00 0.25 95.00
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 1.50 330.00
Total Cost of Labours 425.00
Total 13,812.50
Add 15% for overhead & Profit 2,071.88
Grand Total 15,884.38
Say 15,884.00
Say 635.00
Supervision (15% on Labour Cost) 2 . 5 5
Running Circuit Metre Cost
635.36
Page No -108-
LAYING AND FITTING OF CABLES
10.09 Providing and Fitting of length 1.1kV Armoured cable of per meter length, 1 core, 185
sq.mm conforming to IS : 1554-1 (1988) or any ammendments with 185 sq.mm
Aluminium Cable Lug long barrel, as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
1609 1.1 kV Aluminium
Armoured Cable 1 core,
185 sq.mm conforming to
IS : 1554-1 (1988) or any
ammendments
m 585.00 25.00 14,625.00
Total Cost of Materials 14,625.00
Contingency (2% on Material Cost) 292.50
Sub-Total 14,917.50
Labours
1001 Labour Skilled-I manday 380.00 0.25 95.00
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 1.50 330.00
Total Cost of Labours 425.00
Total 15,342.50
Add 15% for overhead & Profit 2,301.38
Grand Total 17,643.88
Say 17,644.00
Say 706.00
Supervision (15% on Labour Cost) 2.55
Running Circuit Metre Cost
705.76
Page No -109-
LAYING AND FITTING OF CABLES
10.10 Providing and Fitting of 1.1kV Armoured cable of per meter length, 1 core, 225 sq.mm
conforming to IS : 1554-1 (1988) or any ammendments with 225 sq.mm Aluminium
Cable Lug long barrel, as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
1610 1.1 kV Aluminium
Armoured Cable 1 core,
225 sq.mm conforming
to IS : 1554-1 (1988) or
any ammendments
m 772.00 25.00 19,300.00
Total Cost of Materials 19,300.00
Contingency (2% on Material Cost) 386.00
Sub-Total 19,686.00
Labours
1001 Labour Skilled-I manday 380.00 0.25 95.00
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 1.50 330.00
Total Cost of Labours 425.00
Total 20,111.00
Add 15% for overhead & Profit 3,016.65
Grand Total 23,127.65
Say 23,128.00
Say 925.00
Supervision (15% on Labour Cost) 2 . 5 5
Running Circuit Metre Cost
925.12
Page No -110-
LAYING AND FITTING OF CABLES
10.11 Providing and Fitting of 1.1kV Armoured cable of per meter length, 1 core, 300 sq.mm
conforming to IS : 1554-1 (1988) or any ammendments with 300 sq.mm Aluminium Cable Lug
long barrel, as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
1611 1.1 kV Aluminium
Armoured Cable 1 core, 300
sq.mm conforming to IS :
1554-1 (1988) or any
ammendments
m 960.00 25.00 24,000.00
Total Cost of Materials 24,000.00
Contingency (2% on Material Cost) 480.00
Sub-Total 24,480.00
Labours
1001 Labour Skilled-I manday 380.00 0.25 95.00
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 1.50 330.00
Total Cost of Labours 425.00
Total 24,905.00
Add 15% for overhead & Profit 3,735.75
Grand Total 28,640.75
Say 28,641.00
Say 1,146.00
Supervision (15% on Labour Cost) 2 . 5 5
Running Circuit Metre Cost
1,145.64
Page No -111-
LAYING AND FITTING OF CABLES
10.12 Providing and Fitting of 1.1kV Armoured cable of per meter length, 1 core, 400 sq.mm
conforming to IS : 1554-1 (1988) or any ammendments with 400 sq.mm Aluminium
Cable Lug long barrel, as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
1612 1.1 kV Aluminium
Armoured Cable 1
core,400 sq.mm
conforming to IS : 1554- 1
(1988) or any
ammendments
m 1,035.00 25.00 25,875.00
Total Cost of Materials 25,875.00
Contingency (2% on Material Cost) 517.50
Sub-Total 26,392.50
Labours
1001 Labour Skilled-I manday 380.00 0.25 95.00
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 1.67 366.67
Total Cost of Labours 461.67
Total 26,854.17
Add 15% for overhead & Profit 4,028.13
Grand Total 30,882.29
Say 30,882.00
Say 1,235.00
Supervision (15% on Labour Cost) 2 . 7 7
Running Circuit Metre Cost
1,235.28
Page No -112-
LAYING AND FITTING OF CABLES
10.13 Providing and Fitting of 1.1kV Armoured cable of per meter length, 1 core, 630 sq.mm
conforming to IS : 1554-1 (1988) or any ammendments with 630 sq.mm Aluminium
Cable Lug long barrel, as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
1613 1.1 kV Aluminium
Armoured Cable 1 core,
630 sq.mm conforming to
IS : 1554-1 (1988) or any
ammendments
m 1,650.00 25.00 41,250.00
Total Cost of Materials 41,250.00
Contingency (2% on Material Cost) 825.00
Sub-Total 42,075.00
Labours
1001 Labour Skilled-I manday 380.00 0.25 95.00
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 1.67 366.67
Total Cost of Labours 461.67
Total 42,536.67
Add 15% for overhead & Profit 6,380.50
Grand Total 48,917.17
Say 48,917.00
Say 1,957.00
Supervision (15% on Labour Cost) 2.77
Running Circuit Metre Cost
1,956.68
Page No -113-
ERECTION OF GI POLE FOR LT BUS BAR ARRANGEMENT
INSTALLATION OF LT BUS BAR FOR ABOVE 250kVA, 11/0.415kV DISTRIBUTION TRANSFORMER
10.14 Providing and installation of LT Bus bar for above 250kVA, 11/0.415kV Distribution Transformer by
using GI Pipe 40mm dia structure with Grasshopper conductor bus bar and Strap type LT shackle
insulator and other accessories, as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
2504 GI Pipe 40mm dia, 4.13m long with a GI
base plate of 30x30x0.5cm welded at the
bottom
No 2,742.59 2.00 5,485.18
1203 Hard drawn standard aluminium
conductors conforming to IS 398(Part-I)
with amendment No. 1, 2 and 3 or the
latest version thereof bearing ISI mark
:Conductor, AAC,7/3.91 mm Grasshopper
Km 68,785.00 0.01 825.42
1806 Shackle Insulator (Pin/Strap Type) 70x90
mm conforming to IS : 1445 (1977) or any
amendments up to date
No 39.00 8.00 312.00
1807 Shackle Strap for 70x90 mm Shackle
Insulator
Pair 14.00 8.00 112.00
1808 Shackle Nut Bolt 12x100 mm(GI) kg 174.96 0.25 43.74
1405 M.S. Flat Iron 40mmx6 mm kg 105.84 7.90 836.14
2102 M.S. Nut & Bolt 16x50 mm full thread
conforming to IS : 1364-2 (1992) or any
amendments up to date.
kg 162.00 2.93 474.66
1401 M.S. Channel 75 x 40 x 6 mm kg 105.84 25.23 2,670.34
2301 Cement cum 13,750.00 0.34 4,675.00
2302 River Sand cum 2,100.00 1.00 2,100.00
2303 Stone Aggregate 10-20 mm cum 1,890.00 2.00 3,780.00
Total Cost of Materials 21,314.48
Contingency (2% on Material Cost) 426.29
Sub-Total 21,740.77
Labours
1001 Labour Skilled-I manday 380.00 1.50 570.00
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 1.00 250.00
1004 Labour Un-skilled manday 220.00 5.92 1,301.67
Total Cost of Labours 2,121.67
Total 23,862.44
Add 15% for overhead & Profit 3,579.37
Grand Total 27,441.80
Say 27,442.00
Supervision (15% on Labour Cost) 318.25
Page No -114-
FITTING OF CABLE JOINTING KIT
10.15 Providing and Fitting 1.1kV Armoured cable Jointing Kit per Number, 1 core, 10
sq.mm conforming to IS : 1554-1 (1988) or any ammendments with 10 sq.mm
Aluminium Cable Lug long barrel, as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
2010 LT Cable Jointing Kit No 2,770.00 1 2,770.00
1701 Aluminium Cable Lug
long barrel , 10 Sq.mm
No 5.00 1 5.00
Total Cost of Materials 2,775.00
Contingency (2% on Material Cost) 55.50
Sub-Total 2,830.50
Labours
1001 Labour Skilled-I manday 380.00 0.18 66.50
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 0.13 27.50
Total Cost of Labours 94.00
Total 2,924.50
Add 15% for overhead & Profit 438.68
Grand Total 3,363.18
Say 3,363.00
Supervision (15% on Labour Cost) 14.10
Page No -115-
FITTING OF CABLE JOINTING KIT
10.16 Providing and Fitting 1.1kV Armoured cable Jointing Kit per Number, 1 core, 16
sq.mm conforming to IS : 1554-1 (1988) or any ammendments with 16 sq.mm
Aluminium Cable Lug long barrel, as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
2010 LT Cable Jointing Kit No 2,770.00 1 2,770.00
1702 Aluminium Cable Lug
long barrel , 16 Sq.mm
No 8.00 1 8.00
Total Cost of Materials 2,778.00
Contingency (2% on Material Cost) 55.56
Sub-Total 2,833.56
Labours
1001 Labour Skilled-I manday 380.00 0.18 66.50
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 0.13 27.50
Total Cost of Labours 94.00
Total 2,927.56
Add 15% for overhead & Profit 439.13
Grand Total 3,366.69
Say 3,367.00
Supervision (15% on Labour Cost) 14.10
Page No -116-
FITTING OF CABLE JOINTING KIT
10.17 Providing and Fitting 1.1kV Armoured cable Jointing Kit per Number, 1 core, 35
sq.mm conforming to IS : 1554-1 (1988) or any ammendments with 35 sq.mm
Aluminium Cable Lug long barrel, as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
2010 LT Cable Jointing Kit No 2,770.00 1 2,770.00
1703 Aluminium Cable Lug
long barrel , 35 Sq.mm
No 12.00 1 12.00
Total Cost of Materials 2,782.00
Contingency (2% on Material Cost) 55.64
Sub-Total 2,837.64
Labours
1001 Labour Skilled-I manday 380.00 0.18 66.50
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 0.13 27.50
Total Cost of Labours 94.00
Total 2,931.64
Add 15% for overhead & Profit 439.75
Grand Total 3,371.39
Say 3,371.00
Supervision (15% on Labour Cost) 14.10
Page No -117-
FITTING OF CABLE JOINTING KIT
10.18 Providing and Fitting 1.1 kV Armoured cable Jointing Kit per Number, 1 core, 50
sq.mm conforming to IS : 1554-1 (1988) or any ammendments with 50 sq.mm
Aluminium Cable Lug long barrel, as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
2010 LT Cable Jointing Kit No 2,770.00 1 2,770.00
1704 Aluminium Cable Lug
long barrel , 50 Sq.mm
No 15.00 1 15.00
Total Cost of Materials 2,785.00
Contingency (2% on Material Cost) 55.70
Sub-Total 2,840.70
Labours
1001 Labour Skilled-I manday 380.00 0.18 66.50
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 0.13 27.50
Total Cost of Labours 94.00
Total 2,934.70
Add 15% for overhead & Profit 440.21
Grand Total 3,374.91
Say 3,375.00
Supervision (15% on Labour Cost) 14.10
Page No -118-
FITTING OF CABLE JOINTING KIT
10.19 Providing and Fitting 1.1kV Armoured cable Jointing Kit per Number, 1 core, 70
sq.mm conforming to IS : 1554-1 (1988) or any ammendments with 70 sq.mm
Aluminium Cable Lug long barrel, as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
2010 LT Cable Jointing Kit No 2,770.00 1.00 2,770.00
1705 Aluminium Cable Lug
long barrel , 70Sq.mm
No 30.00 1.00 30.00
Total Cost of Materials 2,800.00
Contingency (2% on Material Cost) 56.00
Sub-Total 2,856.00
Labours
1001 Labour Skilled-I manday 380.00 0.18 66.50
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 0.13 27.50
Total Cost of Labours 94.00
Total 2,950.00
Add 15% for overhead & Profit 442.50
Grand Total 3,392.50
Say 3,393.00
Supervision (15% on Labour Cost) 14.10
Page No -119-
FITTING OF CABLE JOINTING KIT
10.20 Providing and Fitting 1.1kV Armoured cable Jointing Kit per Number, 1 core, 95
sq.mm conforming to IS : 1554-1 (1988) or any ammendments with 95 sq.mm
Aluminium Cable Lug long barrel, as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
2010 LT Cable Jointing Kit No 2,770.00 1.00 2,770.00
1706 Aluminium Cable Lug
long barrel , 95 Sq.mm
No 35.00 1.00 35.00
Total Cost of Materials 2,805.00
Contingency (2% on Material Cost) 56.10
Sub-Total 2,861.10
Labours
1001 Labour Skilled-I manday 380.00 0.18 66.50
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 0.13 27.50
Total Cost of Labours 94.00
Total 2,955.10
Add 15% for overhead & Profit 443.27
Grand Total 3,398.37
Say 3,398.00
Supervision (15% on Labour Cost) 14.10
Page No -120-
FITTING OF CABLE JOINTING KIT
10.21 Providing and Fitting 1.1kV Armoured cable Jointing Kit per Number, 1 core, 120
sq.mm conforming to IS : 1554-1 (1988) or any ammendments with 120 sq.mm
Aluminium Cable Lug long barrel, as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
2010 LT Cable Jointing Kit No 2,770.00 1 2,770.00
1707 Aluminium Cable Lug
long barrel , 120 Sq.mm
No 42.00 1 42.00
Total Cost of Materials 2,812.00
Contingency (2% on Material Cost) 56.24
Sub-Total 2,868.24
Labours
1001 Labour Skilled-I manday 380.00 0.18 66.50
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 0.13 27.50
Total Cost of Labours 94.00
Total 2,962.24
Add 15% for overhead & Profit 444.34
Grand Total 3,406.58
Say 3,407.00
Supervision (15% on Labour Cost) 14.10
Page No -121-
FITTING OF CABLE JOINTING KIT
10.22 Providing and Fitting 1.1kV Armoured cable Jointing Kit per Number, 1 core, 150
sq.mm conforming to IS : 1554-1 (1988) or any ammendments with 150 sq.mm
Aluminium Cable Lug long barrel, as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
2010 LT Cable Jointing Kit No 2,770.00 1 2,770.00
1708 Aluminium Cable Lug
long barrel , 150 Sq.mm
No 53.00 1 53.00
Total Cost of Materials 2,823.00
Contingency (2% on Material Cost) 56.46
Sub-Total 2,879.46
Labours
1001 Labour Skilled-I manday 380.00 0.18 66.50
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 0.13 27.50
Total Cost of Labours 94.00
Total 2,973.46
Add 15% for overhead & Profit 446.02
Grand Total 3,419.48
Say 3,419.00
Supervision (15% on Labour Cost) 14.10
Page No -122-
FITTING OF CABLE JOINTING KIT
10.23 Providing and Fitting 1.1kV Armoured cable Jointing Kit per Number, 1 core, 185
sq.mm conforming to IS : 1554-1 (1988) or any ammendments with 185 sq.mm
Aluminium Cable Lug long barrel, as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
2010 LT Cable Jointing Kit No 2,770.00 1 2,770.00
1709 Aluminium Cable Lug
long barrel , 185 Sq.mm
No 68.00 1 68.00
Total Cost of Materials 2,838.00
Contingency (2% on Material Cost) 56.76
Sub-Total 2,894.76
Labours
1001 Labour Skilled-I manday 380.00 0.18 66.50
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 0.13 27.50
Total Cost of Labours 94.00
Total 2,988.76
Add 15% for overhead & Profit 448.31
Grand Total 3,437.07
Say 3,437.00
Supervision (15% on Labour Cost) 14.10
Page No -123-
FITTING OF CABLE JOINTING KIT
10.24 Providing and Fitting 1.1kV Armoured cable Jointing Kit per Number, 1 core, 225
sq.mm conforming to IS : 1554-1 (1988) or any ammendments with 225 sq.mm
Aluminium Cable Lug long barrel, as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
2010 LT Cable Jointing Kit No 2,770.00 1 2,770.00
1710 Aluminium Cable Lug
long barrel , 225 Sq.mm
No 83.00 1 83.00
Total Cost of Materials 2,853.00
Contingency (2% on Material Cost) 57.06
Sub-Total 2,910.06
Labours
1001 Labour Skilled-I manday 380.00 0.18 66.50
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 0.13 27.50
Total Cost of Labours 94.00
Total 3,004.06
Add 15% for overhead & Profit 450.61
Grand Total 3,454.67
Say 3,455.00
Supervision (15% on Labour Cost) 14.10
Page No -124-
FITTING OF CABLE JOINTING KIT
10.25 Providing and Fitting 1.1kV Armoured cable Jointing Kit per Number, 1 core, 300
sq.mm conforming to IS : 1554-1 (1988) or any ammendments with 300 sq.mm
Aluminium Cable Lug long barrel, as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
2010 LT Cable Jointing Kit No 2,770.00 1 2,770.00
1711 Aluminium Cable Lug
long barrel , 300 Sq.mm
No 115.00 1 115.00
Total Cost of Materials 2,885.00
Contingency (2% on Material Cost) 57.70
Sub-Total 2,942.70
Labours
1001 Labour Skilled-I manday 380.00 0.18 66.50
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 0.13 27.50
Total Cost of Labours 94.00
Total 3,036.70
Add 15% for overhead & Profit 455.51
Grand Total 3,492.21
Say 3,492.00
Supervision (15% on Labour Cost) 14.10
Page No -125-
FITTING OF CABLE JOINTING KIT
10.26 Providing and Fitting 1.1kV Armoured cable Jointing Kit per Number, 1 core, 400
sq.mm conforming to IS : 1554-1 (1988) or any ammendments with 400 sq.mm
Aluminium Cable Lug long barrel, as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
2010 LT Cable Jointing Kit No 2,770.00 1 2,770.00
1712 Aluminium Cable Lug
long barrel , 400 Sq.mm
No 165.00 1 165.00
Total Cost of Materials 2,935.00
Contingency (2% on Material Cost) 58.70
Sub-Total 2,993.70
Labours
1001 Labour Skilled-I manday 380.00 0.18 66.50
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 0.13 27.50
Total Cost of Labours 94.00
Total 3,087.70
Add 15% for overhead & Profit 463.16
Grand Total 3,550.86
Say 3,551.00
Supervision (15% on Labour Cost) 14.10
Page No -126-
FITTING OF CABLE JOINTING KIT
10.27 Providing and Fitting 1.1kV Armoured cable Jointing Kit per Number, 1 core, 630
sq.mm conforming to IS : 1554-1 (1988) or any ammendments with 630 sq.mm
Aluminium Cable Lug long barrel, as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
2010 LT Cable Jointing Kit No 2,770.00 1 2,770.00
1713 Aluminium Cable Lug
long barrel , 630Sq.mm
No 188.00 1 188.00
Total Cost of Materials 2,958.00
Contingency (2% on Material Cost) 59.16
Sub-Total 3,017.16
Labours
1001 Labour Skilled-I manday 380.00 0.18 66.50
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 0.13 27.50
Total Cost of Labours 94.00
Total 3,111.16
Add 15% for overhead & Profit 466.67
Grand Total 3,577.83
Say 3,578.00
Supervision (15% on Labour Cost) 14.10
Page No -127-
FITTING OF CABLES T-CONNECTOR
10.28 Providing and Fitting 1.1kV Armoured cable T-Connector per Number, 1 core, 300
sq.mm as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
1714 T-Connector for 300
sq.mm Cable
No 1,600.00 1 1,600.00
Total Cost of Materials 1,600.00
Contingency (2% on Material Cost) 32.00
Sub-Total 1,632.00
Labours
1001 Labour Skilled-I manday 380.00 0.13 47.50
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 0.13 27.50
Total Cost of Labours 75.00
Total 1,707.00
Add 15% for overhead & Profit 256.05
Grand Total 1,963.05
Say 1,963.00
Supervision (15% on Labour Cost) 11.25
Page No -128-
FITTING OF CABLES T-CONNECTOR
10.29 Providing and Fitting 1.1kV Armoured cable T-Connector per Number, 1 core, 400
sq.mm as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
1715 T-Connector for 400
sq.mm Cable
No 1,760.00 1 1,760.00
Total Cost of Materials 1,760.00
Contingency (2% on Material Cost) 35.20
Sub-Total 1,795.20
Labours
1001 Labour Skilled-I manday 380.00 0.13 47.50
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 0.13 27.50
Total Cost of Labours 75.00
Total 1,870.20
Add 15% for overhead & Profit 280.53
Grand Total 2,150.73
Say 2,151.00
Supervision (15% on Labour Cost) 11.25
Page No -129-
FITTING OF CABLES T-CONNECTOR
10.30 Providing and Fitting 1.1kV Armoured cable T-Connector per Number, 1 core, 630 sq.mm as
directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
1716 T-Connector for 630
sq.mm Cable
No 1,936.00 1 1,936.00
Total Cost of Materials 1,936.00
Contingency (2% on Material Cost) 38.72
Sub-Total 1,974.72
Labours
1001 Labour Skilled-I manday 380.00 0.13 47.50
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 0.13 27.50
Total Cost of Labours 75.00
Total 2,049.72
Add 15% for overhead & Profit 307.46
Grand Total 2,357.18
Say 2,357.00
Supervision (15% on Labour Cost) 11.25
Page No -130-
PROTECTION OF DISTRIBUTION TRANSFORMER
FITTING OF GANG SWITCH COMPLETE
11.01 Providing and Fitting of 200A, 11 kV Gang Operated Air Break Switch conforming to
IS : 2544 - 1973, IS : 9921 (Part I-V) or any ammendments up to date with 200 A,
1 1 kV fuse unit with arcing horn, as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
2901 11 kV Gang Operated
Air Break Switch,
200 A, conforming to
IS : 2544 - 1973, IS :
9921 (Part I-V) or
any ammendments
Set 14,490.00 1.00 14,490.00
2902 11 kV Fuse Unit with
Arcing Horn, 200 A,
conforming to 9385
(Part 2) - 1980
ammended up to date
Set 7,087.50 1.00 7,087.50
Total Cost of Materials 21,577.50
Contingency (2% on Material Cost) 431.55
Sub-Total 22,009.05
Labours
1001 Labour Skilled-I manday 380.00 2.00 760.00
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 5.75 1,265.00
Total Cost of Labours 2,025.00
Total 24,034.05
Add 15% for overhead & Profit 3,605.11
Grand Total 27,639.16
Say 27,639.00
Supervision (15% on Labour Cost) 303.75
Page No -131-
FITTING OF VERTICALLY OPERATED GANG SWITCH
11.02 Providing and Fitting of Horizontally operated, Single break 11 kV Isolator complete
with Drop out Fuse unit, conforming to IS : 9921 and any other relevant standards
ammended up to date, as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
2903 Horizontally operated
Single break 11 kV
Isolator complete with
Drop out Fuse unit,
conforming to IS : 9921
and any other relevant
standards ammended
up to date.
Set 34,650.00 1.00 34,650.00
Total Cost of Materials 34,650.00
Contingency (2% on Material Cost) 693.00
Sub-Total 35,343.00
Labours
1001 Labour Skilled-I manday 380.00 2.00 760.00
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 5.00 1,100.00
Total Cost of Labours 1,860.00
Total 37,203.00
Add 15% for overhead & Profit 5,580.45
Grand Total 42,783.45
Say 42,783.00
Supervision (15% on Labour Cost) 279.00
Page No -132-
INSTALLATION OF MAIN SWITCH
11.03 Providing and Installation of 63 A, 3 phase HRC Main Switch conforming to IEC :
60947 (Part 3) - 1999 or any ammendments up to date with 63 A HRC Fuse, as
directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
2701 3 phase HRC Main
Switch, 63 A conforming
to IEC : 60947 (Part 3) -
1999 or any
ammendments up to
date.
No 4,977.00 1.00 4,977.00
2801 HRC Fuse, 63 A,
conforming to IS :
13703 - 1993 or any
ammendments up to
date.
No 570.00 3.00 1,710.00
Total Cost of Materials 6,687.00
Contingency (2% on Material Cost) 133.74
Sub-Total 6,820.74
Labours
1001 Labour Skilled-I manday 380.00 0.00 -
1002 Labour Skilled-II manday 310.00 0.50 155.00
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 0.00 -
Total Cost of Labours 155.00
Total 6,975.74
Add 15% for overhead & Profit 1,046.36
Grand Total 8,022.10
Say 8,022.00
Supervision (15% on Labour Cost) 23.25
Page No -133-
INSTALLATION OF MAIN SWITCH
11.04 Providing and Installation of 3 phase HRC Main Switch, 100 A conforming to IEC :
60947 (Part 3) - 1999 or any ammendments up to date with 100 A HRC Main Fuse,
as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
2702 3 phase HRC Main
Switch, 100 A
conforming to IEC :
60947 (Part 3) - 1999 or
any ammendments up
to date.
No 6,678.00 1.00 6,678.00
2802 HRC Fuse, 100 A,
conforming to IS :
13703 - 1993 or any
ammendments up to
date.
No 1,020.00 3.00 3,060.00
Total Cost of Materials 9,738.00
Contingency (2% on Material Cost) 194.76
Sub-Total 9,932.76
Labours
1001 Labour Skilled-I manday 380.00 0.00 -
1002 Labour Skilled-II manday 310.00 0.50 155.00
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 0.00 -
Total Cost of Labours 155.00
Total 10,087.76
Add 15% for overhead & Profit 1,513.16
Grand Total 11,600.92
Say 11,601.00
Supervision (15% on Labour Cost) 23.25
Page No -134-
INSTALLATION OF MAIN SWITCH
11.05 Providing and Installation of 3 phase HRC Main Switch, 125 A conforming to IEC :
60947 (Part 3) - 1999 or any ammendments up to date with 125 A HRC Fuse, as
directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
2703 3 phase HRC Main
Switch, 125 A
conforming to IEC :
60947 (Part 3) - 1999 or
any ammendments up
to date.
No 8,587.50 1.00 8,587.50
2803 HRC Fuse, 125 A,
conforming to IS :
13703 - 1993 or any
ammendments up to
date.
No 1,177.50 3.00 3,532.50
Total Cost of Materials 12,120.00
Contingency (2% on Material Cost) 242.40
Sub-Total 12,362.40
Labours
1001 Labour Skilled-I manday 380.00 0.00 -
1002 Labour Skilled-II manday 310.00 0.50 155.00
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 0.00 -
Total Cost of Labours 155.00
Total 12,517.40
Add 15% for overhead & Profit 1,877.61
Grand Total 14,395.01
Say 14,395.00
Supervision (15% on Labour Cost) 23.25
Page No -135-
INSTALLATION OF MAIN SWITCH
11.06 Providing and Installation of 3phase HRC Main Switch, 150 A conforming to IEC :
60947 (Part 3) - 1999 or any ammendments up to date with 150 A HRC Fuse,
as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
2704 3phase HRC Main
Switch, 150 A
conforming to IEC :
60947 (Part 3) - 1999 or
any ammendments up
to date.
No 10,832.00 1.00 10,832.00
2804 HRC Fuse, 150 A,
conforming to IS :
13703 - 1993 or any
ammendments up to
date.
No 1,335.00 3.00 4,005.00
Total Cost of Materials 14,837.00
Contingency (2% on Material Cost) 296.74
Sub-Total 15,133.74
Labours
1001 Labour Skilled-I manday 380.00 0.00 -
1002 Labour Skilled-II manday 310.00 0.50 155.00
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 0.00 -
Total Cost of Labours 155.00
Total 15,288.74
Add 15% for overhead & Profit 2,293.31
Grand Total 17,582.05
Say 17,582.00
Supervision (15% on Labour Cost) 23.25
Page No -136-
INSTALLATION OF MAIN SWITCH
11.07 Providing and Installation of 3 phase HRC Main Switch, 200 A conforming to IEC :
60947 (Part 3) - 1999 or any ammendments up to date with 200 A HRC Fuse, as
directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
2705 3 phase HRC Main
Switch, 200 A
conforming to IEC :
60947 (Part 3) - 1999 or
any ammendments up
to date.
No 12,300.00 1.00 12,300.00
2805 HRC Fuse, 200 A,
conforming to IS :
13703 - 1993 or any
ammendments up to
date.
No 1,650.00 3.00 4,950.00
Total Cost of Materials 17,250.00
Contingency (2% on Material Cost) 345.00
Sub-Total 17,595.00
Labours
1001 Labour Skilled-I manday 380.00 0.00 -
1002 Labour Skilled-II manday 310.00 0.50 155.00
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 0.00 -
Total Cost of Labours 155.00
Total 17,750.00
Add 15% for overhead & Profit 2,662.50
Grand Total 20,412.50
Say 20,413.00
Supervision (15% on Labour Cost) 23.25
Page No -137-
INSTALLATION OF MAIN SWITCH
11.08 Providing and Installation of 3 phase HRC Main Switch, 250 A conforming to IEC :
60947 (Part 3) - 1999 or any ammendments up to date with 250 A HRC Fuse, as
directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
2706 3 phase HRC Main
Switch, 250 A
conforming to IEC :
60947 (Part 3) - 1999 or
any ammendments up
to date.
No 13,575.00 1.00 13,575.00
2806 HRC Fuse, 250 A,
conforming to IS :
13703 - 1993 or any
ammendments up
to date.
No 1,765.50 3.00 5,296.50
Total Cost of Materials 18,871.50
Contingency (2% on Material Cost) 377.43
Sub-Total 19,248.93
Labours
1001 Labour Skilled-I manday 380.00 0.00 -
1002 Labour Skilled-II manday 310.00 0.50 155.00
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 0.00 -
Total Cost of Labours 155.00
Total 19,403.93
Add 15% for overhead & Profit 2,910.59
Grand Total 22,314.52
Say 22,315.00
Supervision (15% on Labour Cost) 23.25
Page No -138-
INSTALLATION OF MAIN SWITCH
11.09 Providing and Installation of 3phase HRC Main Switch, 300 A conforming to IEC :
60947 (Part 3) - 1999 or any ammendments up to date with 300 A HRC Fuse, as
directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
2707 3phase HRC Main
Switch, 300 A
conforming to IEC :
60947 (Part 3) - 1999 or
any ammendments up
to date.
No 14,850.00 1.00 14,850.00
2807 HRC Fuse, 300 A,
conforming to IS :
13703 - 1993 or any
ammendments up to
date.
No 1,881.00 3.00 5,643.00
Total Cost of Materials 20,493.00
Contingency (2% on Material Cost) 409.86
Sub-Total 20,902.86
Labours
1001 Labour Skilled-I manday 380.00 0.00 -
1002 Labour Skilled-II manday 310.00 1.00 310.00
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 1.00 220.00
Total Cost of Labours 530.00
Total 21,432.86
Add 15% for overhead & Profit 3,214.93
Grand Total 24,647.79
Say 24,648.00
Supervision (15% on Labour Cost) 79.50
Page No -139-
INSTALLATION OF MAIN SWITCH
11.10 Providing and Installation of 3phase HRC Main Switch, 400 A conforming to IEC :
60947 (Part 3) - 1999 or any ammendments up to date with 400 A HRC Fuse, as
directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
2708 3phase HRC Main
Switch, 400 A
conforming to IEC :
60947 (Part 3) - 1999 or
any ammendments up
to date.
No 16,430.40 1.00 16,430.40
2808 HRC Fuse, 400 A,
conforming to IS :
13703 - 1993 or any
ammendments up to
date.
No 4,500.00 3.00 13,500.00
Total Cost of Materials 29,930.40
Contingency (2% on Material Cost) 598.61
Sub-Total 30,529.01
Labours
1001 Labour Skilled-I manday 380.00 0.00 -
1002 Labour Skilled-II manday 310.00 1.00 310.00
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 1.00 220.00
Total Cost of Labours 530.00
Total 31,059.01
Add 15% for overhead & Profit 4,658.85
Grand Total 35,717.86
Say 35,718.00
Supervision (15% on Labour Cost) 79.50
Page No -140-
CONSTRUCTION OF MAIN SWITCH SHED
11.11 Construction of Shed for Distribution Transformer Main Switch (2.03x0.915m)
1/2.07 Earthwork in excavation in foundation trenches or drain
b) Hard soil etc.
Foundation pit 4 x 0.25 x 0.25 x0.45 = 0.113 cum
Total = 0.113 cum
@ Rs. 435.4/cum.... Rs 49.20
2/4.03 Providing & Laying in position cement concrete
a) 1:03:06 4 x 0.25 x 0.25 x 0.60 = 0.150 cum
1 x 2.08 x 1.17 x 0.10 = 0.242 cum
Total = 0.392 cum
@ Rs. 5968.30/cum.... Rs 2,341.48
3/6.05 Half brick masonry with first class brick in foundation and plinth in
b) in cement mortar 1 : 4 2 x 1.53 x 0.15 = 0.459 sq.m
2 x 0.67 x 0.15 = 0.201 sq.m
Total = 0.66 sq.m
@ Rs. 968.90/sq.m.... Rs 639.47
4/2 1.32 15 mm cement plaster 1 : 3
2 x 2.080 x 0.15 = 0.624sq.m
2 x 1.165 x 0.15 = 0.350 sq.m
Total = 0.974 sq.m
@ Rs. 175.80/sq.m.... Rs 171.14
4 5/21 finishd .21 with floating coat of neat cement (Flooring)
1 x 2.080 x 1.17 = 2.423 sq.m
Total = 2.423 sq.m
@ Rs. 277.00/sq.m.... Rs 671.23
6/5.11 Centering & Shuttering etc. & removal of form works
a) Foundation 4 x 4.00 x 0.25 x 0.20 = 0.800 sq.m
Total = 0.800 sq.m
@ Rs. 299.70/sq.m.... Rs 239.76
7/10.07 Structural steel work; rivetted, bolted, welded in, build up section etc. (Channels)
100x75x75x5mm thick for main posts & Roof structures
2 x 2.100 x 9.56 kg/m = 40.152 sq.mm
2 x 1.972 x 9.56 kg/m = 37.705 sq.mm
2 x 1.830 x 9.56 kg/m = 34.990 sq.mm
2 x 0.922 x 9.56 kg/m = 17.629 sq.mm
NTT = 130.475 sq.mm
1 x 1.830 x 3.50 kg/m = 6.405 sq.mm
2 x 0.9 15 x 3.50 kg/m = 6.405 sq.mm
2 x 1.830 x 3.50 kg/m = 12.810 sq.mm
NTT = 25.620 sq.mm
G. Total = 156.095 sq.mm
@ Rs. 90.80/sq.m.... Rs 14,173.42
Page No -14 1-
8/13.10 Providing 0.63mm IS thickness CGI sheet wa
Walling above 2 x 0.9 15 x (0.77+0.602)/2
0.77m from 1 x 1.830 x 0.602
Total
@ Rs. 596.30/sq.m....
= 1.255 sq.m
= 1.102 sq.m
= 2.357 sq.m
Rs 1405.50 sq.m
9/ 16.0 1 Providing 0.63mm IS thickness CGI sheet etc.
e) 0.63mm thick
1 x 2.130 x 1.251 = 665 sq.m
Total = 665 sq.m
@ Rs. 432.60/sq.m.... Rs ####
10/9.03 Providing first class local wood works for main switch fixi
1 x 1.830 x 0.025 x 0.30 = 0.0 137 sq.mm
Total = 0.0137 sq.mm
@ Rs. Rs 484.24
35281.40/sq.m....
G. TOTAL Rs 21328.16
Say Rs 21,300.00
Page No -142-
Page No -143-
Page No -144-
Page No -145-
Page No -146-
Page No -147-
Page No -148-
Page No -149-
Page No -150-
Page No -151-
FENCING OF DISTRIBUTION TRANSFORMER SUBSTATION BY RCC PILLAR WITH
BRICK
12.01 Construction of (3.0l x 2.5b x 2.0h)m Fencing for Distribution Substation
Transformer upto 100kVA by using RCC Pillar, Brick etc, as directed by the
engineer in charge.
Earthwork in excavation in foundation trenches or drains etc. (not exceeding 1.5m A
in width or 10sqm on plan) including dressing of sides and ramming of bottoms, lift
upto 1.5m including getting out excavated soil and disposal of surplus excavated
soil as directed within a lead of 50 metres.
Hard Soil ( pick work )
(Coefficient for ordinary soil increased 1.5 times)
Details of cost for 10.00 cum.
Description Unit Qty. Rate/Unit Amount
LABOURS : Mate/Supervisor day 1.20 470.00 564.00
Unskilled day 12.30 220.00 2706.00
3270.00
Sundries and contingencies @ 3% 98.10
3368.10
Add for water charge @ 1% 33.68
3401.78
Add CPOH @ 15% 510.27
Cost for 10 cum 3912.05
cum 4.00 1564.82
Page No -152-
Steel reinforcement for RCC work including straighthening, cutting, bending,
placing in position and binding all complete.
Hot rolled deformed bars
Details of cost for 1 quintal .
Description Unit Qty. Rate/Unit Amount
MATERIALS :
Deformed twisted steel bars = 1.00 Wastage 5% = 0.05 Total =
1.05q quintal 1.05 5800.00 6090.00
0.105t tonne 0.11 37.46 3.93
Cover block L.S. 10.00 8.00 80.00
LABOUR :
For straightening, cutting, bending,
binding and placing in position-
Blacksmith 1st class day 1.00 440.00 440.00
Beldar day 1.00 220.00 220.00
Sundries and binding wire L.S. 26.91 8.00 215.28
TOTAL 7049.21
Add water charge @ 1% 70.49
TOTAL 7119.70
Add CPOH @ 15% 1067.96
Cost for 100 kg 8187.66
kg 178.59 14622.34
B
Page No -153-
C Centering and shuttering including strutting,propping etd. And removal of form
a Columns, pillars, piers, abutments, posts and struts.
Details of cost for a Column 30 cm square and 3.50 high : 4x0.30x3.50m = 4.20
Description Unit Qty. Rate/Unit Amount
(A) MATERIALS :
(i) Planks 38 mm thick. (2nd class ) : 2x0.30x3.50 sqm 2.10 : 2x0.48x3.50 sqm 3.36
Total sqm 5.46 Add for wastage @ 5% sqm 0.27 Total 5.73 cum 0.22 28000.00 6104.00
(ii) Ballies 125 mm for struts. : 4x3.80 Rm 15.20 45.00 684.00
Total 6788.00
Assuming that timber shall become
unserviceable after being used 7
times.
Cost of using once 969.71
Carriage & handling @ 2.5% 24.24
(A) 993.95
(B) LABOURS :
2nd class carpenter each 1.25 400.00 500.00
Unskilled each 1.25 220.00 275.00
775.00
Sundries & Contingencies @ 3% 23.25
(B) 798.25
(A) + (B) 1792.20
Add for water charge @ 1% 17.92
1810.12
Add CPOH @ 15% 271.52
Cost for 4.2 sqm 2081.64
sqm 12.00 5947.54
Page No -154-
D b Lintels, beams, plinth beams, girders, bressumers and cantilevers, etc.
Consider a beam of 6.00 mm clear span, 0.50 m deep and 0.30 m wide and floor
height of 3.50 m.
Cubical content = 6.60x0.50x0.30 cum 0.99
Area in contact with concrete=1x1.3x6.0 sqm 7.8
Description Unit Qty. Rate/Unit Amount
(A) MATERIALS :
(i) Planks 38 mm thick. (2nd class) : 2x0.538x0.376 sqm 0.41 : 2x6.60x0.50 sqm 6.60
: 1x6.00x0.376 sqm 2.26 Total 9.26
Add for wastage @ 10% sqm 0.93 Total 10.19 cum 0.39 28000.00 10836.00
(ii) Ballies 125 mm dia. supports 0 .8 m apart : 8x3.50 Rm 28.00 45.00 1260.00
(iii) Ballies bracing for support : 6x2.00 Rm 12.00 45.00 540.00
Total 12636.00
Assuming that timber shall become
unserviceable after being used 7
times.
Cost of using once 1805.14
Carriage & handling @ 2.5% 45.13
(A) 1850.27
(B) LABOURS :
For assembling, errection,
dismantling and clearing.
2nd class carpenter each 1.25 400.00 500.00
Unskilled each 1.25 220.00 275.00
775.00
Sundries & Contingencies @ 3% 23.25
(B) 798.25
(A) + (B) 2648.52
Add for water charge @ 1% 26.49
2675.01
Add CPOH @ 15% 401.25
Cost for 7.8 sqm 3076.26
sqm 30.80 12147.30
Page No -155-
Providing and laying in position reinforced cement concrete excluding cost of
centering and shuttering , finishing and reinforcement in -
1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20mm nominal size)
Details of cost for 1.00 cum.
Description Unit Qty. Rate/Unit Amount
MATERIALS :
Stone aggregate 20mm cum 0.67 1800.00 1206.00
Stone aggregate 10mm cum 0.22 1800.00 396.00
Carriage of stone aggregate cum 0.89 73.42 65.34
Coarse sand cum 0.45 850.00 378.25
Carriage of course sand cum 0.45 73.42 32.67
Cement (0.2833cum ) tonne 0.32 9000.00 2880.00
Carriage of cement tonne 0.32 37.46 11.99
LABOURS :
1st class mason day 0.17 450.00 76.50
Unskilled day 2.00 220.00 440.00
Semi-skilled day 0.90 250.00 225.00
Hire charge of concrete mixer day 0.07 1668.00 116.76
Vibrator day 0.07 1068.00 74.76
Sundries L.S 14.30 8.00 114.40
TOTAL 6017.67
Add water charge @ 1% 60.18
TOTAL 6077.85
Add CPOH @ 15% 911.68
For 1.00 cum 6989.53
olumn cum 0.25 1747.38
E
Page No -156-
C
1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20mm nominal size)
Details of cost for 9.18 cum.
Description Unit Qty. Rate/Unit Amount
MATERIALS :
Stone aggregate 20mm cum 6.15 1800.00 11071.08
Stone aggregate 10mm cum 2.02 1800.00 3635.28
Carriage of stone aggregate cum 8.17 73.42 599.84
Coarse sand cum 4.09 850.00 3472.34
Carriage of course sand cum 4.09 73.42 299.93
Cement (0.2833cum ) tonne 2.94 9000.00 26442.00
Carriage of cement tonne 2.94 37.46 110.06
LABOURS :
Unskilled day 11.29 220.00 2483.80
Coolie day 7.53 220.00 1656.60
Semi-skilled day 8.26 250.00 2065.00
1st class mason day 0.92 450.00 414.00
2nd class mason day 0.92 320.00 294.40
Hire charge of concrete mixer day 0.64 1668.00 1067.52
Vibrator day 0.64 1068.00 683.52
Sundries L.S 131.82 8.00 1054.56
Scaffolding L.S 420.03 8.00 3360.24
Extra labour for lifting material
upto floor V level.0.75x9. 18x2.5
Coolie day 17.20 250.00 4300.00
TOTAL 55349.93
Add water charge @ 1% 553.50
TOTAL 55903.43
Add CPOH @ 15% 8385.51
Cost for 9.18 cum 64288.94
cum 0.50 3501.58
Reinforced cement concrete work in walls including attached pillasters, columns,
F pillers, posts, piers, abutments, return walls, retaining walls, struts, buttresses,
string or lacing courses, fillets etc. upto floor five level excluding cost of centering
shuttering etc complete.
Page No -157-
G Reinforced cement concrete work in beams, suspended floors, roofs having slope
upto 15° landings, balconies, shelves, chajjas, lintels, bands, window sills, stair
cases, spiral stair cases, cantilevers upto floor five level excluding cost of
centering shuttering etc complete. with 1:2:4(1cement : 2 coarse sand :4 stone
aggregate 20mm)
Beam:
1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20mm nominal size) Details
of cost for 1.00 cum.
Description Unit Qty. Rate/Unit Amount
MATERIALS :
Stone aggregate 20mm cum 0.67 1800.00 1206.00
Stone aggregate 10mm cum 0.22 1800.00 396.00
Carriage of stone aggregate cum 0.89 73.42 65.34
Coarse sand cum 0.45 850.00 378.25
Carriage of course sand cum 0.45 73.42 32.67
Cement (0.2225cum ) tonne 0.32 9000.00 2880.00
Carriage of cement tonne 0.32 37.46 11.99
LABOURS :
1st class mason day 0.24 450.00 108.00
Unskilled day 2.75 220.00 605.00
Semi-skilled day 0.90 250.00 225.00
Hire charge of concrete mixer day 0.08 1668.00 133.44
Vibrator day 0.08 1068.00 85.44
Sundries L.S 14.30 8.00 114.40
Extra labour for lifting material
upto floor V level.(2.5x0.75)
Coolie day 1.88 250.00 470.00
TOTAL 6241.53
Add water charge @ 1% 62.42
TOTAL 6303.95
Add CPOH @ 15% 945.59
Cost for 1.00 cum 7249.54
cum 1.10 7974.49
Page No -158-
Filling available excavated earth (excluding rock) in trenches, plinth, sides of
H foundations etc. in layers not exceeding 20cm in depth, consolidating each
deposited layer by ramming and watering, lead up to 50 m and lift upto 1.5 m.
Details of cost for 10cum
Description Unit Qty. Rate/Unit Amount
LABOURS :
Mate day 0.20 470.00 94.00
Coolies day 2.50 220.00 550.00
Bhisti day 0.20 250.00 50.00
694.00
Add for water charges @1% 6.94
700.94
Add CPOH @ 15% 105.14
Cost for 10.00cum 806.08
cum 3.20 257.95
I Half brick masonry with first class brick in superstructure above plinth level
upto floor V level.
a) in cement mortar 1:3 ( 1 cement : 3 coarse sand )
Details of cost for 10.00 sqm
Description Unit Qty. Rate/Unit Amount
(A) MATERIALS:
(i) 1st class brick nos 565.00 10.00 5650.00
(ii) Cement mortar 1:3 Rate as per item no.3.04(b) of SH:
Mortars cum 0.28 6128.40 1715.95
Carriage of bricks nos 565.00 0.46 259.90
Sundries & scafolding L.S 13.52 8.00 108.16
(B) LABOURS :
1st class mason each 0.60 450.00 270.00
2nd class mason each 0.60 320.00 192.00
Exatra labour for lifting materials: 10x0.115x0.75x1.5 Coolie each 0.70 220.00 154.00
Semi skilled each 0.70 250.00 175.00
Unskilled each 1.55 220.00 341.00
TOTAL 8866.01
Add water charge @ 1% 88.66
TOTAL 8954.67
Add CPOH @ 15% 1343.20
Cost for 10.00 sqm 10297.87
sqm 20.25 20853.19
Page No -159-
J 15 mm cement plaster 1:3 (1 cement : 3 fine sand)
Details of cost for 10.00 sqm.
Description Unit Qty. Rate/Unit Amount
(A) MATERIALS :
(i) Cement mortar 1:3 cum 0.17 5914.40 1017.28
(B) LABOURS :
(i) 1st class mason each 0.80 450.00 360.00
(ii) Semi-skilled each 0.99 250.00 247.50
(iii) Unskilled each 0.88 220.00 193.60
Scaffolding and sundries LS 12.61 8.00 100.88
TOTAL 1919.26
Add 1% for water charges 19.19
TOTAL 2039.33
Add CPOH @15% 305.90
Cost for 10.00 sqm 2345.23
sqm 57.70 13531.98
Providing & fixing 1mm thick M.S. door with frame of 40x40x6mm. Angle Iron &
K 3mm M.S.Gusset plates at the junction and corners, all necessary fittings
complete, including applying a priming coat of steel primer.
(a)Using M.S angles (40x40x6)mm for diagonal braces
Consider a double leaf door shutter of size 1200x2400mm giving an area
=2x1.20x2.40 = 5.76sqm
Details of cost of M.S. Sheet door of 5.76 sqm area
Description Unit Qty. Rate/Unit Amount
(A) MATERIALS
(i) M.S. Sheet 1mm thick. @ 7.85 kg/ sqm kg 45.2 16 Add for wastage @ 10% 4.522 49.738 qtl 0.497 4950 2460.15
Carriage & handling @ 2.5% 61.5
Total (I) = 2521.65
(ii) Gusset plates 3mm thick Area of one gusset plate 0.30 x 0.04 0.012 1/2 x 0.26 (0.04+0.30) 0.044 sqm 0.056 8 x 0.0562 sqm 0.45 2 x 22/7 x 1/4 x 0.30 x 0.30 sqm 0.141 sqm 0.591 @ 23.55 kg/sqm kg 13.918 Add for wastage @ 10% 1.392 15.31 qtl 0.153 4628 708.08
Carriage & handling @ 2.5% 17.7
Total (II) = 725.78
Page No -160-
(iii) Angle Iron
40mm x 40mm x 6mm
Sides: 4x2.40 m 9.6 Top & Bottom: 2x2x1.20 m 4.8
Diagonals: 1x2x2.50 m 5 1x2x2.45 m 4.9
m 24.3
Add for wastage @ 10% m 2.43
m 26.73
@ 3.5 kg/Rm kg 93.555
qtl 0.936 6985 6537.96
Carriage & handling @ 2.5% 163.45
Total (III) = 6701.41
(iv) M.S Cleats.
(40x10) mm: 4 x 0.20 m 0.8
Add for wastage @ 25% m 0.2
m 1 @ 3.15 kg/m kg 3.15
qtl 0.032 70 2.24
Carriage & handling @ 2.5% 0.06
Total (IV) = 2.3
(v) Pin Clamps (Pintles) 50mm x 6 mm: 4 x 0.45 m 1.8
Add for wastage @ 11% m 0.198
m 1.998
@ 2.35 kg/m kg 4.695
qtl 0.047 4628 217.52
Carriage & handling @ 2.5% 5.44
Total (V) = 222.96
(vi) 20 mm diameter M.S. bar as
pin:
4 x 0.075 m m 0.3
Add for wastage @ 5% m 0.015
m 0.315 @ 2.47 kg/m kg 0.778
qtl 0.008 4000 32
Carriage & handling @ 2.5% 0.8
Total (VI) = 32.8
(vii) 12mm diameter bolts & nuts
60 mm long: 4 x 2 each 8
@ 0.183 kg/No kg 1.464
qtl 0.015 10929 163.94
Carriage & handling @ 2.5% 4.1
Total (VII) = 168.04
(viii) 10mm diameter 45 cm long
hooks. each 2 64.29 128.58
Page No -16 1-
"(ix) C.C 1:3:6 to fix pin Clamps = 4 x 0.40 x 0.20 x 0.20 cum 0.064 5968.3 381.97
(x) C.C 1 :2:4 for a block to be
"embedded
in floor to keep shutters intact = 1 x 0.1 5 x 0.1 0 x 0.20 cum 0.003 0 0
(xi) Locking Arrangement & Handle each 1 51 .43 51 .43
"(xii) Priming Coat M.S.Sheet: 2 x 5.76 sqm 1 1 .52 Angle Iron: 24.30 x 0.1 6 sqm 3.888
1 5.408 36.6 563.93
Total (VIII) = 1 1 25.91
I + II + III + IV + V + VI + VII + VIII = (A) 1 1 500.85
(B) LABOUR
(i) 1 st class Fitter each 2 440 880
(ii) 1 st class Blacksmith each 3 440 1 320
(iii) 2nd class Blacksmith each 4 320 1 280
(iv) 1 st class Mason each 0.06 450 27
(v) 2nd class Mason each 0.06 320 1 9.2
(vi) Unskilled labour each 5 250 1 250
(B) 4776.2
(A) + (B) 1 6277.05
Add for Sundries & Contingencies @
3%
459.93
(Except on A,B & C ) Add for Water Charges & Electricity @
1 .5%
229.97
(Except on A,B & C ) Add 5% for Overhead charges
(Except on A,B & C )
766.56
Add 1 0% for contractor profit
(Except on A,B & C )
1 533.1 2
Cost of M.S. Sheet door of 5.76 sqm. 1 9266.63
Cost per sqm. 3344.9
sqm 1.75 5853.58
Total TOTAL Cost COST 88,002.14
Say 88,002.00
"
"
"
Page No -162-
FENCING OF DISTRIBUTION TRANSFORMER SUBSTATION BY RCC PILLAR WITH
BRICK
12.02 Construction of (3.5l x 3.0b x 2.0h)m Fencing for Distribution Substation
Transformer above 100kVA by using RCC Pillar, Brick etc, as directed by the
engineer in charge.
Earthwork in excavation in foundation trenches or drains etc. (not exceeding 1.
5m in width or 10sqm on plan) including dressing of sides and ramming of
bottoms, lift upto 1.5m including getting out excavated soil and disposal of
surplus excavated soil as directed within a lead of 50 metres.
Hard Soil ( pick work )
(Coefficient for ordinary soil increased 1.5 times) Details
of cost for 10.00 cum. Description Unit Qty. Rate/Unit Amount
LABOURS :
Mate/Supervisor day 1.20 470.00 564.00
Unskilled day 12.30 220.00 2706.00
3270.00
Sundries and contingencies @ 3% 98.10
3368.10
Add for water charge @ 1% 33.68
3401.78
Add CPOH @ 15% 510.27
Cost for 10 cum 3912.05
cum 4.00 1564.82
Steel reinforcement for RCC work including straighthening, cutting, bending,
placing in position and binding all complete.
Hot rolled deformed bars Details
of cost for 1 quintal .
Description Unit Qty. Rate/Unit Amount
MATERIALS :
Deformed twisted steel bars = 1.00 q Wastage 5% = 0.05 q
Total = 1.05 qquintal 1.05 5800.00 6090.00
Carriage of steel 1.05/10 = 0.105 tonne 0.11 37.46 3.93
Cover block L.S. 10.00 8.00 80.00
LABOUR :
For straightening, cutting, bending,
binding and placing in position-
Blacksmith 1st class day 1.00 440.00 440.00
Beldar day 1.00 220.00 220.00
Sundries and binding wire L.S. 26.91 8.00 215.28
TOTAL 7049.21
Add water charge @ 1% 70.49
TOTAL 7119.70
Add CPOH @ 15% 1067.96
Cost for 100 kg 8187.66
kg 199.70 16350.76
Page No -163-
A
B
f or :
a Columns, pillars, piers, abutments, posts and struts.
Details of cost for a Column 30cm square and 3.50 high : 4x0.30x3.50m=4.20sqm
Description Unit Qty. Rate/Unit Amount
(A) MATERIALS :
(i) Planks 38 mm thick. (2nd class ) : 2x0.30x3.50 sqm 2.10 : 2x0.48x3.50 sqm 3.36
Total sqm 5.46 Add for wastage @ 5% sqm 0.27 Total 5.73
cum 0.22 28000.00 6,104.00
(ii) Ballies 125 mm for struts. : 4x3.80 Rm 15.20 45.00 684.00
Total 6,788.00
Assuming that timber shall become
unserviceable after being used 7
times.
Cost of using once 969.71
Carriage & handling @ 2.5% 24.24
(A) 993.95
(B) LABOURS :
2nd class carpenter each 1.25 400.00 500.00
Unskilled each 1.25 220.00 275.00
775.00
Sundries & Contingencies @ 3% 23.25
(B) 798.25
(A) + (B) 1,792.20
Add for water charge @ 1% 17.92
1,810.12
Add CPOH @ 15% 271.52
Cost for 4.2 sqm 2,081.64
sqm 12.00 5,947.54
C Centering and shuttering including strutting,propping etd. And removal of form
Page No -164-
D b Lintels, beams, plinth beams, girders, bressumers and cantilevers, etc.
Consider a beam of 6.00 mm clear span, 0.50 m deep and 0.30 m wide and floor
height of 3.50 m.
Cubical content = 6.60x0.50x0.30 cum 0.99
Area in contact with concrete=1x1.3x6.0 sqm 7.8
Description Unit Qty. Rate/Unit Amount
(A) MATERIALS :
(i) Planks 38 mm thick. (2nd class) : 2x0.538x0.376 sqm 0.41 : 2x6.60x0.50 sqm 6.60 : 1x6.00x0.376 sqm 2.26
Total 9.26 Add for wastage @ 10% sqm 0.93
Total 10.19 cum 0.39 28000.00 10836.00
(ii) Ballies 125 mm dia. supports 0 .8 m apart : 8x3.50 Rm 28.00 45.00 1260.00
(iii) Ballies bracing for support : 6x2.00 Rm 12.00 45.00 540.00
Total 12636.00
Assuming that timber shall become
unserviceable after being used 7
times.
Cost of using once 1805.14
Carriage & handling @ 2.5% 45.13
(A) 1850.27
(B) LABOURS :
For assembling, errection,
dismantling and clearing.
2nd class carpenter each 1.25 400.00 500.00
Unskilled each 1.25 220.00 275.00
775.00
Sundries & Contingencies @ 3% 23.25
(B) 798.25
(A) + (B) 2648.52
Add for water charge @ 1% 26.49
2675.01
Add CPOH @ 15% 401.25
Cost for 7.8 sqm 3076.26
sqm 36.40 14355.88
Page No -165-
Providing and laying in position reinforced cement concrete excluding cost of
centering and shuttering , finishing and reinforcement in -
1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20mm nominal size)
Details of cost for 1.00 cum.
Description Unit Qty. Rate/Unit Amount
MATERIALS :
Stone aggregate 20mm cum 0.67 1800.00 1206.00
Stone aggregate 10mm cum 0.22 1800.00 396.00
Carriage of stone aggregate cum 0.89 73.42 65.34
Coarse sand cum 0.45 850.00 378.25
Carriage of course sand cum 0.45 73.42 32.67
Cement (0.2833cum ) tonne 0.32 9000.00 2880.00
Carriage of cement tonne 0.32 37.46 11.99
LABOURS :
1st class mason day 0.17 450.00 76.50
Unskilled day 2.00 220.00 440.00
Semi-skilled day 0.90 250.00 225.00
Hire charge of concrete mixer day 0.07 1668.00 116.76
Vibrator day 0.07 1068.00 74.76
Sundries L.S 14.30 8.00 114.40
TOTAL 6017.67
Add water charge @ 1% 60.18
TOTAL 6077.85
Add CPOH @ 15% 911.68
For 1.00 cum 6989.53
olumn cum 0.25 1747.38
E
Page No -166-
C
1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20mm nominal size) Details
of cost for 9.18 cum.
Description Unit Qty. Rate/Unit Amount
MATERIALS :
Stone aggregate 20mm cum 6.15 1800.00 11071.08
Stone aggregate 10mm cum 2.02 1800.00 3635.28
Carriage of stone aggregate cum 8.17 73.42 599.84
Coarse sand cum 4.09 850.00 3472.34
Carriage of course sand cum 4.09 73.42 299.93
Cement (0.2833cum ) tonne 2.94 9000.00 26442.00
Carriage of cement tonne 2.94 37.46 110.06
LABOURS :
Unskilled day 11.29 220.00 2483.80
Coolie day 7.53 220.00 1656.60
Semi-skilled day 8.26 250.00 2065.00
1st class mason day 0.92 450.00 414.00
2nd class mason day 0.92 320.00 294.40
Hire charge of concrete mixer day 0.64 1668.00 1067.52
Vibrator day 0.64 1068.00 683.52
Sundries L.S 131.82 8.00 1054.56
Scaffolding L.S 420.03 8.00 3360.24
Extra labour for lifting material
upto floor V level.0.75x9. 18x2.5
Coolie day 17.20 250.00 4300.00
TOTAL 55349.93
Add water charge @ 1% 553.50
TOTAL 55903.43
Add CPOH @ 15% 8385.51
Cost for 9.18 cum 64288.94
cum 0.5 3501.58
pillers, posts, piers, abutments, return walls, retaining walls, struts, buttresses,
F string or lacing courses, fillets etc. upto floor five level excluding cost of centering
shuttering etc complete.
Page No -167-
Reinforced cement concrete work in beams, suspended floors, roofs having slope upto
15° landings, balconies, shelves, chajjas, lintels, bands, window sills, stair
G cases, spiral stair cases, cantilevers upto floor five level excluding cost of centering
shuttering etc complete. with 1:2:4(1cement : 2 coarse sand :4 stone aggregate
20mm)
Beam:
1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20mm nominal size)
Details of cost for 1.00 cum.
Description Unit Qty. Rate/Unit Amount
MATERIALS :
Stone aggregate 20mm cum 0.67 1800.00 1206.00
Stone aggregate 10mm cum 0.22 1800.00 396.00
Carriage of stone aggregate cum 0.89 73.42 65.34
Coarse sand cum 0.45 850.00 378.25
Carriage of course sand cum 0.45 73.42 32.67
Cement (0.2225cum ) tonne 0.32 9000.00 2880.00
Carriage of cement tonne 0.32 37.46 11.99
LABOURS :
1st class mason day 0.24 450.00 108.00
Unskilled day 2.75 220.00 605.00
Semi-skilled day 0.90 250.00 225.00
Hire charge of concrete mixer day 0.08 1668.00 133.44
Vibrator day 0.08 1068.00 85.44
Sundries L.S 14.30 8.00 114.40
Extra labour for lifting material
upto floor V level.(2.5x0.75)
Coolie day 1.88 250.00 470.00
TOTAL 6241.53
Add water charge @ 1% 62.42
TOTAL 6303.95
Add CPOH @ 15% 945.59
Cost for 1.00 cum 7249.54
cum 1.63 11816.75
Page No -168-
Filling available excavated earth (excluding rock) in trenches, plinth, sides of
H foundations etc. in layers not exceeding 20cm in depth, consolidating each
deposited layer by ramming and watering, lead up to 50 m and lift upto 1.5 m.
Details of cost for 10cum
Description Unit Qty. Rate/Unit Amount
LABOURS :
Mate day 0.20 470.00 94.00
Coolies day 2.50 220.00 550.00
Bhisti day 0.20 250.00 50.00
694.00
Add for water charges @1% 6.94
700.94
Add CPOH @ 15% 105.14
Cost for 10.00cum 806.08
cum 3.20 257.95
I Half brick masonry with first class brick in fsuperstructure above plinth level
a) in cement moratar 1:3 ( 1 cement : 3 coarse sand )
Details of cost for 10.00 sqm
Description Unit Qty. Rate/Unit Amount
(A) MATERIALS:
(i) 1st class brick nos 565.00 10.00 5650.00
(ii) Cement mortar 1:3 Rate as per item no.3.04(b) of SH:
Mortars cum 0.28 6128.40 1715.95
Carriage of bricks nos 565.00 0.46 259.90
Sundries & scafolding L.S 13.52 8.00 108.16
(B) LABOURS :
1st class mason each 0.60 450.00 270.00
2nd class mason each 0.60 320.00 192.00
Exatra labour for lifting materials: 10x0. 1 15x0.75x1.5 Coolie each 0.70 220.00 154.00
Semi skilled each 0.70 250.00 175.00
Unskilled each 1.55 220.00 341.00
TOTAL 8866.01
Add water charge @ 1% 88.66
TOTAL 8954.67
Add CPOH @ 15% 1343.20
Cost for 10.00 sqm 10297.87
sqm 24.25 24972.33
Page No -169-
J 15 mm cement plaster 1:3 (1 cement : 3 fine sand)
Details of cost for 10.00 sqm.
Description Unit Qty. Rate/Unit Amount
(A) MATERIALS :
(i) Cement mortar 1:3 cum 0.17 5914.40 1017.28
(B) LABOURS :
(i) 1st class mason each 0.80 450.00 360.00
(ii) Semi-skilled each 0.99 250.00 247.50
(iii) Unskilled each 0.88 220.00 193.60
Scaffolding and sundries LS 12.61 8.00 100.88
TOTAL 1919.26
Add 1% for water charges 19.19
TOTAL 2039.33
Add CPOH @15% 305.90
Cost for 10.00 sqm 2345.23
sqm 69.85 16381.43
Providing & fixing 1mm thick M.S. door with frame of 40x40x6mm. Angle Iron &
K 3mm M.S.Gusset plates at the junction and corners, all necessary fittings
complete, including applying a priming coat of steel primer.
(a)Using M.S angles (40x40x6)mm for diagonal braces
Consider a double leaf door shutter of size 1200x2400mm giving an area
=2x1.20x2.40 = 5.76sqm
Details of cost of M.S. Sheet door of 5.76 sqm area
Description Unit Qty. Rate/Unit Amount
(A) MATERIALS
(i) M.S. Sheet 1mm thick. @ 7.85 kg/ sqm kg 45.22 Add for wastage @ 10% 4.52 49.74 qtl 0.50 4950.00 2460.15
Carriage & handling @ 2.5% 61.50
Total (I) = 2521.65
(ii) Gusset plates 3mm thick Area of one gusset plate 0.30 x 0.04 0.01 1/2 x 0.26 (0.04+0.30) 0.04 sqm 0.06 8 x 0.0562 sqm 0.45 2 x 22/7 x 1/4 x 0.30 x 0.30 sqm 0.14 sqm 0.59 @ 23.55 kg/sqm kg 13.92 Add for wastage @ 10% 1.39 15.31 qtl 0.15 4628.00 708.08
Carriage & handling @ 2.5% 17.70
Total (II) = 725.78
Page No -170-
(iii) Angle Iron 40mm x 40mm x 6mm Sides: 4x2.40 m 9.60 Top & Bottom: 2x2x1.20 m 4.80 Diagonals: 1x2x2.50 m 5.00
1x2x2.45 m 4.90
m 24.30 Add for wastage @ 10% m 2.43
m 26.73 @ 3.5 kg/Rm kg 93.56
qtl 0.94 6985.00 6537.96
Carriage & handling @ 2.5% 163.45
Total (III) = 6701.41
(iv) M.S Cleats. (40x10) mm: 4 x 0.20 m 0.80 Add for wastage @ 25% m 0.20
m 1.00 @ 3.15 kg/m kg 3.15
qtl 0.03 70.00 2.24
Carriage & handling @ 2.5% 0.06
Total (IV) = 2.30
(v) Pin Clamps (Pintles) 50mm x 6 mm: 4 x 0.45 m 1.80 Add for wastage @ 11% m 0.20
m 2.00 @ 2.35 kg/m kg 4.70
qtl 0.05 4628.00 217.52
Carriage & handling @ 2.5% 5.44
Total (V) = 222.96
(vi) 20 mm diameter M.S. bar as pin: 4 x 0.075 m m 0.30 Add for wastage @ 5% m 0.02
m 0.32 @ 2.47 kg/m kg 0.78
qtl 0.01 4000.00 32.00
Carriage & handling @ 2.5% 0.80
Total (VI) = 32.80
(vii) 12mm diameter bolts & nuts 60 mm long: 4 x 2 each 8.00 @ 0.183 kg/No kg 1.46
qtl 0.02 10929.00 163.94
Page No -17 1-
Carriage & handling @ 2.5% 4.10
Total (VII) = 168.04
hooks. each 2.00 64.29 128.58
I,(ix) C.C 1:3:6 to fix pin Clamps = 4 x 0.40 x 0.20 x 0.20 cum 0.06 5968.30 381.97
(x) C.C 1:2:4 for a block to be
I,embedded
in floor to keep shutters intact = 1 x 0.15 x 0.10 x 0.20 cum 0.00 0.00 0.00
(xi) Locking Arrangement & Handle each 1.00 51.43 51.43
I,(xii) Priming Coat M.S.Sheet: 2 x 5.76 sqm 11.52 Angle Iron: 24.30 x 0.16 sqm 3.89
15.41 36.60 563.93
Total (VIII) = 1125.91
I + II + III + IV + V + VI + VII + VIII = (A) 11500.85
(B) LABOUR
(i) 1st class Fitter each 2.00 440.00 880.00
(ii) 1st class Blacksmith each 3.00 440.00 1320.00
(iii) 2nd class Blacksmith each 4.00 320.00 1280.00
(iv) 1st class Mason each 0.06 450.00 27.00
(v) 2nd class Mason each 0.06 320.00 19.20
(vi) Unskilled labour each 5.00 250.00 1250.00
(B) 4776.20
(A) + (B) 16277.05
Add for Sundries & Contingencies @
3% (Except on A,B & C )
459.93
Add for Water Charges & Electricity @
1.5% (Except on A,B & C )
229.97
Add 5% for Overhead charges
(Except on A,B & C )
766.56
Add 10% for contractor profit
(Except on A,B & C )
1533.12
Cost of M.S. Sheet door of 5.76 sqm. 19266.63
Cost per sqm. 3344.90
sqm 1.75 5853.58
Total TOTAL Cost COST 102,750.00
Say 102,750.00
I,
I,
I,
Page No -172-
FENCING OF DISTRIBUTION TRANSFORMER SUBSTATION BY FENCING POST AND
FENCING NET
12.03 Construction of (3.0l x 2.5b x 2.0h)m Fencing for Distribution Substation
Transformer up to 100kVA by using fencing post and fencing net, as directed by the
engineer in charge.
A 2.0m high polysteel goat proof fencing with 2.6m angle iron posts 50 x 50 x 6mm
size placed 2.0m apart embedded in cement concrete block 1:3:6 (1 cement : 3 sand
: 6 stone agge gate) of size 25 x 25 x 60 cm fixing with nails and wire etc. including
earthwork complete.
Details of cost for 30 Rm.
Description Unit Qty. Rate/Unit Amount
(A) MATERIALS:
(i) Angle iron 50x50x6mm @ 4.50kg/m.
: 16 x 2.6 x 4.50 kg 187.20 Add for wastage @ 5% kg 9.36
kg 196.56 qtl 1.97 6985.00 13760.45
(ii) Polysteel goat proof wire : 2.0 x 0sqm 60.00 445.00 26700.00
(iii) Nails kg 2.00 80.00 160.00
40620.45
Carriage & handling @ 2.5% 1015.51
(iv) Cement concrete block 1 : 3 : 6 (1cement:3 sand:6 stone aggregate
20mm size)
: 16 x 0.25 x 0.25 x 0.60 cum 0.60 7602.30 4561.38
(v) Earthwork for cement concrete block : 16 x 0.25 x 0.25 x 0.60 cum 0.60 327.20 196.32
(A) 46393.66
(B) LABOURS :
(For drilling holes, fitting and fixing) (i) 1st class mason each 0.12 450.00 54.00
(ii) 2nd class mason each 0.12 320.00 38.40
(iii) 1st class blacksmith each 0.78 440.00 343.20
(iv) 2nd class blacksmith each 2.75 320.00 880.00
(v) Unskilled each 2.72 220.00 598.40
1914.00
Sundries & contingencies @ 3% 57.42
(B) 1971.42
(A) + (B) 48365.08
Add for water charge @ 1% except
on (A) iv & v, i.e. on Rs.
43607.38 436.07
TOTAL 48801.15
Add CPOH @ 15% 7320.17
Cost for 30.00 Rm 56121.32
Rm 10.00 18707.11
Page No -173-
Providing & fixing 1mm thick M.S. door with frame of 40x40x6mm. Angle Iron & B
3mm M.S.Gusset plates at the junction and corners, all necessary fittings complete,
including applying a priming coat of steel primer.
(a)Using M.S angles (40x40x6)mm for diagonal braces
Consider a double leaf door shutter of size 1200x2400mm giving an area
=2x1.20x2.40 = 5.76sqm
Details of cost of M.S. Sheet door of 5.76 sqm area
Description Unit Qty. Rate/Unit Amount
(A) MATERIALS
(i) M.S. Sheet 1mm thick. @ 7.85 kg/ sqm kg 45.22 Add for wastage @ 10% 4.52 49.74 qtl 0.50 4950.00 2460.15
Carriage & handling @ 2.5% 61.50
Total (I) = 2521.65
(ii) Gusset plates 3mm thick Area of one gusset plate 0.30 x 0.04 0.01 1/2 x 0.26 (0.04+0.30) 0.04 sqm 0.06 8 x 0.0562 sqm 0.45 2 x 22/7 x 1/4 x 0.30 x 0.30 sqm 0.14 sqm 0.59 @ 23.55 kg/sqm kg 13.92 Add for wastage @ 10% 1.39 15.31 qtl 0.15 4628.00 708.08
Carriage & handling @ 2.5% 17.70
Total (II) = 725.78
(iii) Angle Iron 40mm x 40mm x 6mm Sides: 4x2.40 m 9.60 Top & Bottom: 2x2x1.20 m 4.80 Diagonals: 1x2x2.50 m 5.00
1x2x2.45 m 4.90 m 24.30 Add for wastage @ 10% m 2.43 m 26.73 @ 3.5 kg/Rm kg 93.56 qtl 0.94 6985.00 6537.96
Carriage & handling @ 2.5% 163.45
Total (III) = 6701.41
Page No -174-
(iv) M.S Cleats. (40x10) mm: 4 x 0.20 m 0.80 Add for wastage @ 25% m 0.20 m 1.00 @ 3.15 kg/m kg 3.15 qtl 0.03 70.00 2.24
Carriage & handling @ 2.5% 0.06
Total (IV) = 2.30
(v) Pin Clamps (Pintles) 50mm x 6 mm: 4 x 0.45 m 1.80 Add for wastage @ 11% m 0.20 m 2.00 @ 2.35 kg/m kg 4.70 qtl 0.05 4628.00 217.52
Carriage & handling @ 2.5% 5.44
Total (V) = 222.96
(vi) 20 mm diameter M.S. bar as pin: 4 x 0.075 m m 0.30 Add for wastage @ 5% m 0.02 m 0.32 @ 2.47 kg/m kg 0.78 qtl 0.01 4000.00 32.00
Carriage & handling @ 2.5% 0.80
Total (VI) = 32.80
(vii) 12mm diameter bolts & nuts 60 mm long: 4 x 2 each 8.00 @ 0.183 kg/No kg 1.46 qtl 0.02 10929.00 163.94
Carriage & handling @ 2.5% 4.10
Total (VII) = 168.04
(viii) 10mm diameter 45 cm long hoo ks.each 2.00 64.29 128.58
"(ix) C.C 1:3:6 to fix pin Clamps = 4 x 0.40 x 0.20 x 0.20 cum 0.06 5968.30 381.97
"(x) C.C 1:2:4 for a block to be embedded in floor to keep shutters intact = 1 x 0.15 x 0.10 x 0.20 cum 0.00 0.00 0.00
(xi) Locking Arrangement & Handle each 1.00 51.43 51.43
"(xii) Priming Coat M.S.Sheet: 2 x 5.76 sqm 11.52 Angle Iron: 24.30 x 0.16 sqm 3.89 15.41 36.60 563.93
Total (VIII) = 1125.91
I + II + III + IV + V + VI + VII + VIII = (A) 11500.85
"
"
"
Page No -175-
(B) LABOUR
(i) 1st class Fitter each 2.00 440.00 880.00
(ii) 1st class Blacksmith each 3.00 440.00 1320.00
(iii) 2nd class Blacksmith each 4.00 320.00 1280.00
(iv) 1st class Mason each 0.06 450.00 27.00
(v) 2nd class Mason each 0.06 320.00 19.20
(vi) Unskilled labour each 5.00 250.00 1250.00
(B) 4776.20
(A) + (B) 16277.05
Add for Sundries & Contingencies
@ 3% (Except on A,B & C )
459.93
Add for Water Charges & Electricity
@ 1.5% (Except on A,B & C )
229.97
Add 5% for Overhead charges
(Except on A,B & C )
766.56
Add 10% for contractor profit
(Except on A,B & C )
1533.12
Cost of M.S. Sheet door of 5.76 sqm. 19266.63
Cost per sqm. 3344.90
sqm 2.00 6689.80
TOTAL COST 25396.91
Say 25397.00
Page No -176-
FENCING OF DISTRIBUTION TRANSFORMER SUBSTATION BY FENCING POST AND
FENCING NET
12.04 Construction of (3.5l x 3.0b x 2.0h)m Fencing for Distribution Substation
Transformer above 100kVA by using fencing post and fencing net, as directed by
the engineer in charge.
2.0m high polysteel goat proof fencing with 2.6m angle iron posts 50 x 50 x 6mm size placed 2.0m apart embedded in cement concrete block 1 :3:6 (1 cement : 3
A sand : 6 stone aggegate) of size 25 x 25 x 60 cm fixing with nails and wire etc.
including earthwork complete.
Details of cost for 30 Rm.
Description Unit Qty. Rate/Unit Amount
(A) MATERIALS
(i) Angle iron 50x50x6mm @ 4.50kg/m. : 16 x 2.6 x 4.50 kg 187.20
Add for wastage @ 5% kg 9.36 kg 196.56 qtl 1.97 6985.00 13760.45
(ii) Polysteel goat proof wire : 2.0 x 0sqm 60.00 445.00 26700.00
(iii) Nails kg 2.00 80.00 160.00
40620.45
Carriage & handling @ 2.5% 1015.51
(iv) Cement concrete block 1 : 3 : 6 (1cement:3 sand:6 stone aggregate
20mm size)
: 16 x 0.25 x 0.25 x 0.60 cum 0.60 7602.30 4561.38
(v) Earthwork for cement concrete block : 16 x 0.25 x 0.25 x 0.60 cum 0.60 327.20 196.32
(A) 46393.66
(B) LABOURS :
(For drilling holes, fitting and fixing) (i) 1st class mason each 0.12 450.00 54.00
(ii) 2nd class mason each 0.12 320.00 38.40
(iii) 1st class blacksmith each 0.78 440.00 343.20
(iv) 2nd class blacksmith each 2.75 320.00 880.00
(v) Unskilled each 2.72 220.00 598.40
1914.00
Sundries & contingencies @ 3% 57.42
(B) 1971.42
(A) + (B) 48365.08
Add for water charge @ 1% except
on (A) iv & v, i.e. on Rs.
43607.38 436.07
TOTAL 48801.15
Add CPOH @ 15% 7320.17
Cost for 30.00 Rm 56121.32
Total Cost Rm 12.00 22448.53
Page No -177-
Providing & fixing 1mm thick M.S. door with frame of 40x40x6mm. Angle Iron & B
3mm M.S.Gusset plates at the junction and corners, all necessary fittings complete,
including applying a priming coat of steel primer.
(a)Using M.S angles (40x40x6)mm for diagonal braces
Consider a double leaf door shutter of size 1200x2400mm giving an area
=2x1.20x2.40 = 5.76sqm
Details of cost of M.S. Sheet door of 5.76 sqm area
Description Unit Qty. Rate/Unit Amount
(A) MATERIALS
(i) M.S. Sheet 1mm thick. @ 7.85 kg/ sqm kg 45.22 Add for wastage @ 10% 4.52 49.74 qtl 0.50 4950.00 2460.15
Carriage & handling @ 2.5% 61.50
Total (I) 2521.65
(ii) Gusset plates 3mm thick Area of one gusset plate 0.30 x 0.04 0.01 1/2 x 0.26 (0.04+0.30) 0.04 sqm 0.06 8 x 0.0562 sqm 0.45 2 x 22/7 x 1/4 x 0.30 x 0.30 sqm 0.14 sqm 0.59 @ 23.55 kg/sqm kg 13.92 Add for wastage @ 10% 1.39 15.31 qtl 0.15 4628.00 708.08
Carriage & handling @ 2.5% 17.70
Total (II) 725.78
(iii) Angle Iron 40mm x 40mm x 6mm Sides: 4x2.40 m 9.60 Top & Bottom: 2x2x1.20 m 4.80 Diagonals: 1x2x2.50 m 5.00
1x2x2.45 m 4.90 m 24.30 Add for wastage @ 10% m 2.43 m 26.73 @ 3.5 kg/Rm kg 93.56 qtl 0.94 6985.00 6537.96
Carriage & handling @ 2.5% 163.45
Total (III) 6701.41
Page No -178-
(iv) M.S Cleats.
(40x10) mm: 4 x 0.20 m 0.80 Add for wastage @ 25% m 0.20
m 1.00 @ 3.15 kg/m kg 3.15
qtl 0.03 70.00 2.24
Carriage & handling @ 2.5% 0.06
Total (IV) 2.30
(v) Pin Clamps (Pintles) 50mm x 6 mm: 4 x 0.45 m 1.80 Add for wastage @ 11% m 0.20
m 2.00 @ 2.35 kg/m kg 4.70
qtl 0.05 4628.00 217.52
Carriage & handling @ 2.5% 5.44
Total (V) 222.96
(vi) 20 mm diameter M.S. bar as pin: 4 x 0.075 m m 0.30 Add for wastage @ 5% m 0.02
m 0.32 @ 2.47 kg/m kg 0.78
qtl 0.01 4000.00 32.00
Carriage & handling @ 2.5% 0.80
Total (VI) 32.80
(vii) 12mm diameter bolts & nuts 60 mm long: 4 x 2 each 8.00 @ 0.183 kg/No kg 1.46
qtl 0.02 10929.00 163.94
Carriage & handling @ 2.5% 4.10
Total (VII) 168.04
(viii) 10mm diameter 45 cm long hook s.each 2.00 64.29 128.58
I,(ix) C.C 1:3:6 to fix pin Clamps = 4 x 0.40 x 0.20 x 0.20 cum 0.06 5968.30 381.97
I,(x) C.C 1:2:4 for a block to be embedded in floor to keep shutters intact = 1 x 0.15 x 0.10 x 0.20 cum 0.00 0.00 0.00
(xi) Locking Arrangement & Handle each 1.00 51.43 51.43
I,(xii) Priming Coat M.S.Sheet: 2 x 5.76 sqm 11.52 Angle Iron: 24.30 x 0.16 sqm 3.89
15.41 36.60 563.93
Total (VIII) 1125.91
I + II + III + IV + V + VI + VII + VIII = (A) 11500.85
I,
I,
I,
Page No -179-
(B) LABOUR
(i) 1st class Fitter each 2.00 440.00 880.00
(ii) 1st class Blacksmith each 3.00 440.00 1320.00
(iii) 2nd class Blacksmith each 4.00 320.00 1280.00
(iv) 1st class Mason each 0.06 450.00 27.00
(v) 2nd class Mason each 0.06 320.00 19.20
(vi) Unskilled labour each 5.00 250.00 1250.00
(B) 4776.20
(A) + (B) 16277.05
Add for Sundries & Contingencies @
3% (Except on A,B & C )
459.93
Add for Water Charges & Electricity @
1.5% (Except on A,B & C )
229.97
Add 5% for Overhead charges
(Except on A,B & C )
766.56
Add 10% for contractor profit
(Except on A,B & C )
1533.12
Cost of M.S. Sheet door of 5.76 sqm. 19266.63
Cost per sqm. 3344.90
sqm 2.00 6689.80
TOTAL COST 29138.33
Say 29138.00
Page No -180-
INSTALLATION OF HT METERING SYSTEM
13.01 Providing and Erection of 11kV outdoor type combined CT & PT metering equipment
with PT ratio 11/0.415kV and CT ratio as per requirement with 3-ph 4 wire
Automatic Meter Reading (AMR) Compatible Static Trivector Meter in separate
Housing cabinet with cables & accessories, as directed by the engineer in charge.
Sl.No. Description Unit Rate/Unit Qty. Amount
Materials
2601
Outdoor type CT & PT
combination with PT ratio
1 1 /0.41 5 kV, for all
rating of CT ratio as
required by HT side
Ampere
No 70,000.00 1 70,000.00
2603
3-ph 4 wire Trivector
Meter suitable for
Automatic Meter Reading
(AMR), PTR 11/0.415kV,
for all rating of CT Ratio.
No 13,500.00 1 13,500.00
1 623 PVC Insulated Copper
Cable, 2.5 sq.mm m 67.50 100.00 6,750.00
2611
Housing Cabinet for
Trivertor Meter for all ratio
of PTR and CTR with
suitable clamp in steel
tabular pole
No 1,500.00 1.00 1,500.00
Total Cost of Materials 91,750.00
Contingency (2% on Material Cost) 1,835.00
Sub-Total 93,585.00
Labours
1001 Labour Skilled-I manday 380.00 3.00 1,140.00
1002 Labour Skilled-II manday 310.00 4.00 1,240.00
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 27.00 5,940.00
Total Cost of Labours 8,320.00
Total 101,905.00
Add 15% for overhead & Profit 15,285.75
Grand Total 117,190.75
Say 117,191.00
Supervision (15% on Labour Cost) 1,248.00
Page No -181-
INSTALLATION OF BOUNDARY METERING SYSTEM
13.02 Providing and Erection of 11kV outdoor type CT & PT metering equipment with PT
ratio 11/0.110 kV, CT ratio as per requirement; with 3-ph 4 wire Automatic Meter
Reading (AMR) Compatible Static Trivector Meter in separate Housing cabinet with
cables & accessories (Boundary Meter), as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
2602
Outdoor type CT & PT
combination with PT ratio
11/0.11 kV, for all rating
of CT ratio as required by
HT side Ampere
No 70,000.00 1.00 70,000.00
2604
3-ph 4 wire Trivector
Meter suitable for
Automatic Meter Reading
(AMR), PTR 11/0.11kV,
for all rating of CT Ratio.
No 13,500.00 1 13,500.00
1623 PVC Insulated Copper
Cable, 2.5 sq.mm m 67.50 100.00 6,750.00
2611
Housing Cabinet for
Trivertor Meter for all ratio
of PTR and CTR with
suitable clamp in steel
tabular pole
No 1,500.00 1.00 1,500.00
Total Cost of Materials 91,750.00
Contingency (2% on Material Cost) 1,835.00
Sub-Total 93,585.00
Labours
1001 Labour Skilled-I manday 380.00 3.00 1,140.00
1002 Labour Skilled-II manday 310.00 4.00 1,240.00
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 27.00 5,940.00
Total Cost of Labours 8,320.00
Total 101,905.00
Add 15% for overhead & Profit 15,285.75
Grand Total 117,190.75
Say 117,191.00
Supervision (15% on Labour Cost) 1,248.00
Page No -182-
PREPARATION OF CT/PT MOUNTING STRUCTURE
13.03 Providing and Erection of Mounting Structure for 11KV CT/PT combined metering
equipment mounted between two SP-35 (swagged steel tubular poles) 2.44 m apart, as
directed by the engineer in charge. The height of CT/PT mounting channel should
facilitate safety working clearance, as specified in Schedule VII of the CEA (Measures
relating to Safety and Electric Supply Regulations), 2010.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
1401 M.S. Channel 75 x 40 x 6
mm kg 1 05.84
40.37 4,272.46
1405 M.S. Flat Iron 40mmx6
mm kg 1 05.84
0.75 79.03
2102
M.S. Nut & Bolt 16x50
mm full thread
conforming to IS : 1364-2
(1992) or any
amendments up to date.
kg 162.00 1.17 189.22
2103
M.S. Nut & Bolt 16 x 155
mm full thread
conforming to IS : 1364-2
(1992) or any
amendments up to date.
kg 162.00 2.45 396.58
Total Cost of Materials 4,937.29
Contingency (2% on Material Cost) 98.75
Sub-Total 5,036.03
Labours
1001 Labour Skilled-I manday 380.00 1.00 380.00
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 3.00 660.00
Total Cost of Labours 1,040.00
Total 6,076.03
Add 15% for overhead & Profit 911.40
Grand Total 6,987.44
Say 6,987.00
Supervision (15% on Labour Cost) 156.00
Page No -183-
INSTALLATION OF DT CUBICLE
13.04 Providing and installation of LT Outdoor DT Cubicle complete with MCCB, Street
light controller, metering system for 25kVA, 1 1/0.415kV Transformer including
erection with cement etc, as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
2605
LT Outdoor DT Cubicle
complete with MCCB, St
light Controller, metering
system for both St light
and Consumer for 25kVA,
11/0.415 kV Transformer
No 53,235.00 1.00 53,235.00
2301 Cement cum 13,750.00 0.01 137.50
2302 River Sand cum 2,100.00 0.03 63.00
2303 Stone Aggregate 10-20 mm cum 1,890.00 0.06 113.40
Total Cost of Materials 53,548.90
Contingency (2% on Material Cost) 1,070.98
Sub-Total 54,619.88
Labours
1001 Labour Skilled-I manday 380.00 1.00 380.00
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 5.00 1,100.00
Total Cost of Labours 1,480.00
Total 56,099.88
Add 15% for overhead & Profit 8,414.98
Grand Total 64,514.86
Say 64,515.00
Supervision (15% on Labour Cost) 222.00
Page No -184-
INSTALLATION OF DT CUBICLE
13.05 Providing and installation of LT Outdoor DT Cubicle complete with MCCB, Street
light controller, metering system for 63kVA, 11/0.415kV Transformer including
erection with cement etc, as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
2606
LT Outdoor DT Cubicle
complete with MCCB, St
light Controller, metering
system for both St light
and Consumer for 63kVA,
11/0.415 kV Transformer
No 56,778.75 1.00 56,778.75
2301 Cement cum 13,750.00 0.01 137.50
2302 River Sand cum 2,100.00 0.03 63.00
2303 Stone Aggregate 1 0-20
mm cum 1,890.00 0.06 113.40
Total Cost of Materials 57,092.65
Contingency (2% on Material Cost) 1,141.85
Sub-Total 58,234.50
Labours
1001 Labour Skilled-I manday 380.00 1.00 380.00
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 5.00 1,100.00
Total Cost of Labours 1,480.00
Total 59,714.50
Add 15% for overhead & Profit 8,957.18
Grand Total 68,671.68
Say 68,672.00
Supervision (15% on Labour Cost) 222.00
Page No -185-
INSTALLATION OF DT CUBICLE
13.06 Providing and installation of LT Outdoor DT Cubicle complete with MCCB, Street
light controller, metering system for 100kVA, 1 1/0.415kV Transformer including
erection with cement etc, as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
2607
LT Outdoor DT Cubicle
complete with MCCB, St
light Controller, metering
system for both St light
and Consumer for
100kVA, 11/0.415 kV
Transformer
No 62,685.00 1.00 62,685.00
2301 Cement cum 13,750.00 0.01 137.50
2302 River Sand cum 2,100.00 0.03 63.00
2303 Stone Aggregate 1 0-20
mm cum 1,890.00 0.06 113.40
Total Cost of Materials 62,998.90
Contingency (2% on Material Cost) 1,259.98
Sub-Total 64,258.88
Labours
1001 Labour Skilled-I manday 380.00 1.00 380.00
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 5.50 1,210.00
Total Cost of Labours 1,590.00
Total 65,848.88
Add 15% for overhead & Profit 9,877.33
Grand Total 75,726.21
Say 75,726.00
Supervision (15% on Labour Cost) 238.50
Page No -186-
INSTALLATION OF DT CUBICLE
13.07 Providing and installation of LT Outdoor DT Cubicle complete with MCCB and
Consumer metering system for 25kVA, 11/0.415kV Transformer including erection
with cement etc, as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
2608
LT Outdoor DT Cubicle
complete with MCCB,
Consumer metering
system for 25kVA,
11/0.415 kV Transformer
No 35,437.50 1.00 35,437.50
2301 Cement cum 13,750.00 0.01 137.50
2302 River Sand cum 2,100.00 0.03 63.00
2303 Stone Aggregate 10-20
mm cum 1,890.00 0.06 113.40
Total Cost of Materials 35,751.40
Contingency (2% on Material Cost) 715.03
Sub-Total 36,466.43
Labours
1001 Labour Skilled-I manday 380.00 1.00 380.00
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 5.00 1,100.00
Total Cost of Labours 1,480.00
Total 37,946.43
Add 15% for overhead & Profit 5,691.96
Grand Total 43,638.39
Say 43,638.00
Supervision (15% on Labour Cost) 222.00
Page No -187-
INSTALLATION OF DT CUBICLE
13.08 Providing and installation of LT Outdoor DT Cubicle complete with MCCB and
Consumer metering system for 63kVA, 11/0.415kV Transformer including erection
with cement etc, as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
2609
LT Outdoor DT Cubicle
complete with MCCB,
Consumer metering
system for 63kVA,
11/0.415 kV Transformer
No 38,981.25 1.00 38,981.25
2301 Cement cum 13,750.00 0.01 137.50
2302 River Sand cum 2,100.00 0.03 63.00
2303 Stone Aggregate 10-20
mm cum 1,890.00 0.06 113.40
Total Cost of Materials 39,295.15
Contingency (2% on Material Cost) 785.90
Sub-Total 40,081.05
Labours
1001 Labour Skilled-I manday 380.00 1.00 380.00
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 5.00 1,100.00
Total Cost of Labours 1,480.00
Total 41,561.05
Add 15% for overhead & Profit 6,234.16
Grand Total 47,795.21
Say 47,795.00
Supervision (15% on Labour Cost) 222.00
Page No -188-
INSTALLATION OF DT CUBICLE
13.09 Providing and installation of LT Outdoor DT Cubicle complete with MCCB and
Consumer metering system for 100kVA, 11/0.415kV Transformer including
erection with cement etc, as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
2610
LT Outdoor DT Cubicle
complete with MCCB,
Consumer metering
system for 100kVA,
11/0.415 kV Transformer
No 44,887.50 1.00 44,887.50
2301 Cement cum 13,750.00 0.01 137.50
2302 River Sand cum 2,100.00 0.03 63.00
2303 Stone Aggregate 10-20
mm cum 1,890.00 0.06 113.40
Total Cost of Materials 45,201.40
Contingency (2% on Material Cost) 904.03
Sub-Total 46,105.43
Labours
1001 Labour Skilled-I manday 380.00 1.00 380.00
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 5.50 1,210.00
Total Cost of Labours 1,590.00
Total 47,695.43
Add 15% for overhead & Profit 7,154.31
Grand Total 54,849.74
Say 54,850.00
Supervision (15% on Labour Cost) 238.50
Page No -189-
STREET LIGHTING
14.01 Providing and Erection 250 W, HPSV Street Light complete with Lamp, Bracket, PVC
insulated aluminium cable and other accessories, as directed by the engineer in
charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Materials
3201
HPSV Lamp Street Light
Fittings complete with Choke,
Condenser, Holder and Ignitor,
250 W, conforming to IS :
10322 - 2012, IS : 2215 - 2006
and any other relevant
standards with amendments up
to date.
Set 6,850.00 1.00 6,850.00
3203
HPSV Lamp, 250 W, conforming to
IS : 1 0322 - 201 2 and any other
relevant standards with
amendments up to date.
No 1,950.00 1.00 1,950.00
3204 Street Light Bracket No 590.00 1.00 590.00
3205 D-Clamp for Street Light
Bracket complete with Nuts & Set 139.00 2.00 278.00
1614
PVC Insulated Aluminium
Cable, 2.5 sq.mm, 2 Core,
conforming to IS : 1554-1
(1988), IS : 5831 (1984) or
any ammendments there of.
m 20.00 4.00 80.00
Total Cost of Materials 9,748.00
Contingency (2% on Material Cost) 194.96
Sub-Total 9,942.96
Labours
1001 Labour Skilled-I manday 380.00 0.00 -
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.33 83.33
1004 Labour Un-skilled manday 220.00 0.67 146.67
Total Cost of Labours 230.00
Total 10,172.96
Add 15% for overhead & Profit 1,525.94
Grand Total 11,698.90
Say 11,699.00
Supervision (15% on Labour Cost) 34.50
Page No -190-
FITTING OF LT ABC
15.01 Providing and Fitting of LT ABC accessories for stringing (Tension Point), as directed by the
engineer in charge.
Sl.No. Description Unit Rate/Unit Quantity Amount
Materials
3301 Anchor clamp for LT
ABC as per NFC
standard
No. 1,509.30 2.00 3,018.60
3312 Eye Hook/Clamp
Holding Support
No. 322.50 1.00 322.50
3322 Pole clamp for Steel
Tubular Pole complete
set with nuts&bolts
No. 651.45 1.00 651.45
Total Cost of Materials 3,992.55
Contingency (2% on Material Cost) 79.85
Sub-Total 4,072.40
Labours
1001 Labour Skilled-I manday 380.00 0.20 76.00
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.20 50.00
1004 Labour Un-skilled manday 220.00 0.40 88.00
Total Cost of Labours 214.00
Total 4,286.40
Add 15% for overhead & Profit 642.96
Grand Total 4,929.36
Say 4,929.00
Supervision (15% on Labour Cost) 32.10
Page No -191-
FITTING OF LT ABC
15.02 Providing and Fitting of LT ABC accessories for stringing (Suspension Point), as directed by
the engineer in charge.
Sl.No. Description Unit Rate/Unit Quantity Amount
Materials
3326 Suspension clamp for No. 870.75 1.00 870.75
3312 LT ABC as per NF Eye Hook/Clamp
Holding Support
No. 322.50 1.00 322.50
3322 Pole clamp for Steel
Tubular Pole complete
set with nuts&bolts
No. 651.45 1.00 651.45
Total Cost of Materials 1,844.70
Contingency (2% on Material Cost) 36.89
Sub-Total 1,881.59
1001 Labour Skilled-I manday 380.00 0.20 76.00
1002 Labour Skilled-II manday 310.00 - -
1003 Labour Semi-Skilled manday 250.00 0.20 50.00
1004 Labour Un-skilled manday 220.00 0.40 88.00
Total Cost of Labours 214.00
Total 2,095.59
Add 15% for overhead & Profit 314.34
Grand Total 2,409.93
Say 2,410.00
Supervision (15% on Labour Cost) Labours
FITTING OF LT ABC
15.03 Providing and Fitting of LT ABC single phase distribution box with accessories, as directed by
the engineer in charge.
Sl.No. Description Unit Rate/Unit Quantity Amount
Materials
3310 Distribution Box with
spring loaded Bus Bars for
140A, 1 ph. 10
No. 4,836.21 1.00 4,836.21
3329 connectors Tie Plastic for cable
9mmx26 5mm
Pack 725.63 1.00 725.63
3314 Insulated Piercing
Connector for ABC to
ABC TEE connection
No. 490.20 1.00 490.20
3315 Insulated Piercing
Connector for
Distribution Box
charging (16-95 sq.mm
No. 265.74 4.00 1,062.96
3316 Insulated Piercing
Connector for street
light (16-9 5 sq.mm to
2.5-10sq.mm)
No. 250.00 2.00 500.00
3323 Service Main Anchor
Clamp
No. 398.61 4.00 1,594.44
3317 L.T Cable - 1x35 sq.mm for
charging DB
m 180.60 9.00 1,625.40
Total Cost of Materials 10,834.84
Contingency (2% on Material Cost) 216.70
Sub Total 11,051.54
Labours
1001 Labour Skilled I manday 380.00 0.58 221.67
1002 Labour Skilled II manday 310.00 0.00
0.58 145.83 1003 Labour Semi Skilled manday 250.00
1004 Labour Un-skilled manday 220.00 0.92 201.67
Total Cost of Labours 569.17
Total 11,620.70
Add 15% for overhead & Profit 1,743.11
Grand Total 13,363.81
Say 13,364.00
Supervision (15% on Labour Cost) 85.38
Page No -193-
FITTING OF LT ABC
15.04 Providing and Fitting of LT ABC three phase distribution box with accessories, as directed by
the engineer in charge.
Sl.No. Description Unit Rate/Unit Quantity Amount
Materials
3311 Distribution Box with
spring loaded Bus Bars for
140A, 3ph. 10
No. 7,233.03 1.00 7,233.03
3329 connectors Tie Plastic for cable
9mmx2 65mm
Pack 725.63 1.00 725.63
3314 Insulated Piercing
Connector for ABC to
ABC TEE connection
No. 490.20 1.00 490.20
3315 Insulated Piercing
Connector for
Distribution Box
charging (16-95 sq.mm
to 4-35sq.mm)
No. 265.74 4.00 1,062.96
3316 Insulated Piercing
Connector for street
light (16-9 5 sq.mm to
2.5- 10sq.mm)
No. 250.00 2.00 500.00
3323 Service Main Anchor
Clamp
No. 398.61 4.00 1,594.44
3317 L.T Cable - 1x35 sq.mm for
charging DB
m 180.60 27.00 4,876.20
Total Cost of Materials 16,482.46
Contingency (2% on Material Cost) 329.65
Sub-Total 16,812.11
Labours
1001 Labour Skilled-I manday 380.00 0.58 221.67
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.58 145.83
1004 Labour Un-skilled manday 220.00 0.92 201.67
Total Cost of Labours 569.17
Total 17,381.28
Add 15% for overhead & Profit 2,607.19
Grand Total 19,988.47
Say 19,988.00
Supervision (15% on Labour Cost) 85.38
Page No -194-
STRINGING OF LT ABC (size 3x70 sq.mm)
15.05 Providing and stringing, clipping and piercing of LT line per single conductor per meter
using Aerial Bunched Cables (3x70 sq.mm) with jungle clearance, as directed by the
engineer in charge.
Sl.
No. Description Unit Rate/Unit Qty. Amount
Materials
3303 1.1 kV XLPE insulated Aerial
Bunched Cables, 3x70sq.mm,
with 16 sq.mm street light and
XLPE insulated messanger
1x25 sq.mm
m 487.30 36.75 17,908.28
3324 Steel Straps size 20mmx1m
long
No. 126.42 4.00 505.68
3308 Buckles for steel strap (pack of
100)
Pack 2,025.30 1.00 2,025.30
3318 Midspan joint for 16 sq.mm
ABC Cable
No. 296.70 1.00 296.70
3319 Midspan joint for 25 sq.mm for
ABC Cable
No. 310.89 1.00 310.89
3320 Midspan joint for 95 sq.mm for
ABC Cable
No. 357.33 1.00 357.33
3330 Water Proof pre-insulated
Hexagonal Compress for 16
sq.mm
No. 763.68 1.00 763.68
3331 Water Proof pre-insulated
Hexagonal Compress for 25
sq.mm
No. 793.35 1.00 793.35
3332 Water Proof pre-insulated
Hexagonal Compress for 95
sq.mm
No. 812.70 1.00 812.70
3313 Heat shrinkable repair tape No. 1,760.81 1.00 1,760.81
3309 Cable and Caps for ABC Cable No. 84.34 1.00 84.34
Total Cost of Materials 25,619.06
Contingency (2% on Material Cost) 512.38
Sub-Total 26,131.44
Labours
1001 Labour Skilled-I manday 380.00 0.83 316.67
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.83 208.33
1004 Labour Un-skilled manday 220.00 4.88 1,074.33
Total Cost of Labours 1,599.33
Total 27,730.77
Add 15% for overhead & Profit 4,159.62
Grand Total 31,890.38
Say 31,890.00
Say 911.00
Supervision (15% on Labour Cost) 239.90
Running Metre Cost
911.14
Page No -195-
STRINGING OF LT ABC (Size 3x120 Sq.mm)
15.06 Providing and stringing, clipping and piercing of LT line per single conductor per meter
using Aerial Bunched Cables (3x120 sq.mm) with jungle clearance, as directed by the
engineer in charge.
Sl.
No. Description Unit Rate/Unit Qty. Amount
Materials
3302
1.1 kV XLPE insulated Aerial
Bunched Cables, 3x120
sq.mm, with 16 sq.mm street
light and XLPE insulated
messanger 95 sq.mm
m 541.80 37 19,911.15
3324 Steel Straps size 20mmx1m
long No. 126.42 4 505.68
3308 Buckles for steel strap (pack of
100) Pack 2,025.30 1 2,025.30
331 8 Midspan joint for 1 6 sq.mm
ABC Cable No. 296.70 1 296.70
3319 Midspan joint for 25 sq.mm for
ABC Cable No. 310.89 1 310.89
3320 Midspan joint for 95 sq.mm for
ABC Cable No. 357.33 1 357.33
3330
Water Proof pre-insulated
Hexagonal Compress for 16
sq.mm
No. 763.68 1 763.68
3331
Water Proof pre-insulated
Hexagonal Compress for 25
sq.mm
No. 793.35 1 793.35
3332
Water Proof pre-insulated
Hexagonal Compress for 95
sq.mm
No. 812.70 1 812.70
3313 Heat shrinkable repair tape No. 1,760.81 1 1,760.81
3309 Cable and Caps for ABC Cable No. 84.34 1 84.34
Total Cost of Materials 27,621.93
Contingency (2% on Material Cost) 552.44
Sub-Total 28,174.37
Labours
1001 Labour Skilled-I manday 380.00 0.83 316.67
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.83 208.33
1004 Labour Un-skilled manday 220.00 5.48 1,206.33
Total Cost of Labours 1,731.33
Total 29,905.70
Add 15% for overhead & Profit 4,485.86
Grand Total 34,391.56
Say 34,392.00
Say 983.00
Supervision (15% on Labour Cost) 259.70
Running Metre Cost
982.63
Page No -196-
STRINGING OF LT ABC (Size 3x95 Sq.mm)
15.07 Providing and stringing, clipping and piercing of LT line per single conductor per meter
using Aerial Bunched Cables (3x95 sq.mm) with jungle clearance, as directed by the
engineer in charge.
Sl.
No. Description Unit Rate/Unit Qty. Amount
Materials
3304
1.1 kV XLPE insulated Aerial
Bunched Cables, 3x95 sq.mm,
with 16 sq.mm street light and
XLPE insulated messanger 25
sq.mm
m 503.10 37 18,488.93
3324 Steel Straps size 20mmx1m
long No. 126.42 4 505.68
3308 Buckles for steel strap (pack of
100) Pack 2,025.30 1 2,025.30
3318 Midspan joint for 16 sq.mm
ABC Cable No. 296.70 1 296.70
3319 Midspan joint for 25 sq.mm for
ABC Cable No. 310.89 1 310.89
3320 Midspan joint for 95 sq.mm for
ABC Cable No. 357.33 1 357.33
3330
Water Proof pre-insulated
Hexagonal Compress for 16
sq.mm
No. 763.68 1 763.68
3331
Water Proof pre-insulated
Hexagonal Compress for 25
sq.mm
No. 793.35 1 793.35
3332
Water Proof pre-insulated
Hexagonal Compress for 95
sq.mm
No. 812.70 1 812.70
3313 Heat shrinkable repair tape No. 1,760.81 1 1,760.81
3309 Cable and Caps for ABC Cable No. 84.34 1 84.34
Total Cost of Labours 26,199.71
Contingency (2% on Material Cost) 523.99
Sub-Total 26,723.70
Labours
1001 Labour Skilled-I manday 380.00 0.83 316.67
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.50 125.00
1004 Labour Un-skilled manday 220.00 4.80 1,056.00
Total Cost of Labours 1,497.67
Total 28,221.37
Add 15% for overhead & Profit 4,233.20
Grand Total 32,454.57
Say 32,455.00
Say 927.00
Supervision (15% on Labour Cost) 224.65
Running Metre Cost
927.29
Page No -197-
Fitting of 11 kV ABC accessories
16.01 Providing and Fitting of 11 kV ABC accessories, as directed by the engineer in
Sl. Description Unit Rate/Unit Qty. Amount No.
Materials
3322 Pole clamp for Steel Tubular
Pole complete set with
No. 651.45 2.00 1,302.90
3312 Eye Hook/Clamp Holding
Support
No. 322.50 2.00 645.00
3301 Anchor clamp for LT ABC as
per NFC standard
No. 1,509.30 1.00 1,509.30
3326 Suspension clamp for LT
ABC as per NFC standard
No. 870.75 1.00 870.75
3328 Tie plastic Pkt. 724.98 6.00 4,349.88
Total Cost of Labours 8,677.83
Contingency (2% on Material Cost) 173.56
Sub-Total 8,851.39
Labours
1001 Labour Skilled-I manday 380.00 0.20 76.00
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.20 50.00
1004 Labour Un-skilled manday 220.00 0.40 88.00
Total Cost of Labours 214.00
Total 9,065.39
Add 15% for overhead & Profit 1,359.81
Grand Total 10,425.19
Say 10,425.00
Supervision (15% on Labour Cost) 32.10
Page No -198-
STRINGING OF 11kV ABC ( Size 3x70 sq.mm)
16.02 Providing and stringing, clipping and piercing of 11 kV line per single conductor per
meter using Aerial Bunched Cables (3x70 sq.mm) with jungle clearance, as directed by
the engineer in charge.
Sl.
No.
Description Unit Rate/Unit Qty. Amount
Materials
3305 11kV XLPE insulated Aeiral
Bunched Cable size 3 x 70
sq.mm + 1x55 sq.mm (Base
m 516.00 36.75 18,963.00
3325 Straight joint for cable (ABC) Set 14,951.10 1.00 14,951.10
3327 Termination kit O/D HT ABC
AIC x 95 heat shrinkable
Set 14,951.10 1.00 14,951.10
3321 P.G Clamp suitable for
95 sq.mm ABC/C wedge
connector
No. 71.21 1.00 71.21
Total Cost of Labours 48,936.41
Contingency (2% on Material Cost) 978.73
Sub-Total 49,915.14
Labours
1001 Labour Skilled-I manday 380.00 0.83 316.67
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.83 208.33
1004 Labour Un-skilled manday 220.00 4.88 1,074.33
Total Cost of Labours 1,599.33
Total 51,514.47
Add 15% for overhead & Profit 7,727.17
Grand Total 59,241.64
Say 59,242.00
Say 1,693.00
Supervision (15% on Labour Cost) 239.90
Per meter cost 1,692.63
Page No -199-
STRINGING OF 11kV ABC ( Size 3x95 sq.mm)
16.03 Providing and stringing, clipping and piercing of 11 kV line per single conductor per
meter using Aerial Bunched Cables (3x95 sq.mm) with jungle clearance, as directed by
the engineer in charge.
Sl. Description Unit Rate/Unit Qty. Amount
No. Materials
3306 11kV XLPE insulated Aeiral
Bunched Cable size 3x95
sq.mm+ 1x70 sq.mm (Bare
Messenger)
m 580.00 37 21,315.00
3325 Straight joint for cable (ABC) Set 14,951.10 1 14,951.10
3327 Termination kit O/D HT ABC
AIC x 95 heat shrinkable
Set 14,951.10 1 14,951.10
3321 P.G Clamp suitable for 95
sq.mm ABC/C wedge
connector
No. 71.21 1 71.21
Total Cost of Labours 51,288.41
Contingency (2% on Material Cost) 1,025.77
Sub-Total 52,314.18 Labours
1001 Labour Skilled-I manday 380.00 0.83 316.67
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.83 208.33
1004 Labour Un-skilled manday 220.00 5.13 1,129.33
Total Cost of Labours 1,654.33
Total 53,968.51
Add 15% for overhead & Profit 8,095.28
Grand Total 62,063.79
Say 62,064.00
Say 1,773.00
Supervision (15% on Labour Cost) 248.15
Running Metre Cost
1,773.26
Page No -200-
33kV CIRCUIT BREAKER ERECTION
17.01 Providing and erection of 33kV Circuit Breaker with structure in complete set including
excavation and refilling of foundation pit 1.6mx1.25mx1.2m (lxbxh) in size; foundation casting -
footing PCC 1:3:6 (0.08m thick), RCC 1:2:4 (0.12m thick) and 2 column RCC 1:2:4
0.30mx0.65mx1.50m (lxbxh) in size with planting depth of 1.0m, 12mm thick 1:3 cement
plastering of plint 0.50m height; erection of Structure and Circuit Breaker as directed by
E n g i n e e Sl. No. Description Unit Rate/Unit Qty. Amount
Material
3401
33kV Circuit Breaker
(SF6/Vacuum), 36kV, 1250A,
25kA complete with mounting
structures, marshalling box,
foundation bolts and all other
accessories (3nos as 1 set)
conforming to IS : 13118 (1991)
or any amendments up to date.
Set 488 ,790.00 1.00 488 ,790.00
3512
T.S Rod 12mm conforming to
IS: 9417 (1989) or any
amendments there of. Kg 82.20 95.00
7,809.00
3513
T.S Rod 8mm conforming to IS:
9417 (1989) or any
amendments there of. Kg 82.20 20.00
1,644.00
3514 Binding Wire Kg 105.00 1.00 105.00
2301 Cement cum 13,750.00 0.20 2,750.00
2302 River Sand cum 2,100.00 0.40 840.00
2303 Stone Aggregate 10-20 mm cum 1,890.00 0.65 1,228.50
2403 Wooden Plank (12x1 sq.ft.) No 1,000.00 4.00 4,000.00
Total Cost of Materials 507,166.50
Labours
1001 Labour Skilled-I manday 380.00 7.00 2,660.00
1002 Labour Skilled-II manday 310.00 9.00 2,790.00
1003 Labour Semi-Skilled manday 250.00 8.00 2,000.00
1004 Labour Un-skilled manday 220.00 34.00 7,480.00
Total Cost of Labours 14,930.00
Total 522,096.50
Add 15% for overhead & Profit 78,314.48
Testing and Commissioning Charges 3,000.00
Grand Total 603,411.00
Supervision (15% on Labour Cost) 2,239.50
Page No -201-
INSTALLATION OF 33kV ISOLATOR WITH EARTH SWITCH
17.02 Providing and erection of 33kV Isolator with earthswitch with structure in
complete set including excavation and refilling of foundation pit
2.84mx1.60mx1.20m (lxbxh) in size; foundation casting - footing PCC 1:3:6 (0.2m
thick) and 2 column RCC 1:2:4 0.45mx1.00mx1.50m (lxbxh) in size with planting
depth of 1.2m, 12mm thick 1:3 cement plastering of plint 0.50m height; erection
of mounting Structure and Isolator as directed by Engineer-in-charge
Sl. No. Description Unit Rate/Unit Qty. Amount
Material
341 0
33kV Isolator with
Earth Switch
complete with
mounting structure,
terminal connectors,
foundation bolts and
all other accessories
etc. conforming to IS:
9921 of the latest
version.
set 98,000.00 1.00 98,000.00
3512
T.S Rod 12mm
conforming to IS: 9417
(1989) or any
amendments there of.
Kg 82.20 68.00 5,589.60
3513
T.S Rod 8mm
conforming to IS: 9417
(1989) or any
amendments there of.
Kg 82.20 24.00 1,972.80
3514 Binding Wire Kg 105.00 1.00 105.00
2301 Cement cum 13,750.00 0.52 7,150.00
2302 River Sand cum 2,100.00 1.00 2,100.00
2303
Stone Aggregate 10- 20
mm cum 1,890.00 1.80 3,402.00
2403
Wooden Plank (12x1
sq.ft.) No 1,000.00 4.00 4,000.00
Total Cost of Materials 122,319.40
Labours
1001 Labour Skilled-I manday 380.00 6.00 2,280.00
1002 Labour Skilled-II manday 310.00 8.00 2,480.00
1003 Labour Semi-Skilled manday 250.00 5.00 1,250.00
1004 Labour Un-skilled manday 220.00 46.00 10,120.00
Total Cost of Labours 16,130.00
Total 138,449.40
Add 15% for overhead & Profit 20,767.41
Testing and Commissioning Charges 2,000.00
Grand Total 161,217.00
Supervision (15% on Labour Cost) 2,419.50
Page No -202-
INSTALLATION 33kV ISOLATOR WITHOUT EARTH SWITCH
17.03 Providing and erection of 33kV Isolator without earthswitch with structure in
complete set including excavation and refilling of foundation pit
2.84mx1.60mx1.20m (lxbxh) in size; foundation casting - footing PCC 1:3:6 (0.1m
thick) and 2 column RCC 1:2:4 0.45mx1.00mx1.50m (lxbxh) in size with planting
depth of 1.0m, 12mm thick 1:3 cement plastering of plint 0.50m height; erection
of mounting Structure and Isolator as directed by Engineer-in-charge
Sl. No. Description Unit Rate/Unit Qty. Amount
Material
341 1
33kV Isolator without
Earth Switch
complete with
mounting structure,
terminal connectors,
foundation bolts and
all other accessories
etc. conforming to IS:
9921 of the latest
version.
set 95,655.00 1.0000 95,655.00
3512
T.S Rod 12mm
conforming to IS: 941
7 (1 989) or any
amendments there of.
Kg 82.20 68.0000 5,589.60
3513
T.S Rod 8mm
conforming to IS: 941
7 (1 989) or any
amendments there of.
Kg 82.20 24.0000 1 ,972.80
3514 Binding Wire Kg 105.00 1.0000 105.00
2301 Cement cum 13,750.00 0.5200 7,150.00
2302 River Sand cum 2,100.00 1.0000 2,100.00
2303
Stone Aggregate 10- 20
mm cum 1,890.00 1.8000 3,402.00
2403
Wooden Plank (12x1
sq.ft.) No 1,000.00 4.0000 4,000.00
Total Cost of Materials 119,974.40
Labours
1001 Labour Skilled-I manday 380.00 9.00 3,420.00
1002 Labour Skilled-II manday 310.00 9.00 2,790.00
1003 Labour Semi-Skilled manday 250.00 4.00 1,000.00
1004 Labour Un-skilled manday 220.00 47.00 10,340.00
Total Cost of Labours 17,550.00
Total 137,524.40
Add 15% for overhead & Profit 20,628.66
Testing and Commissioning Charges 2,000.00
Grand Total 160,153.00
Supervision (15% on Labour Cost) 2,632.50
Page No -203-
INSTALLATION OF 11kV ISOLATOR WITH EARTH SWITCH
17.04 Providing and erection of 11kV Isolator with earth switch with structure in
complete set including excavation and refilling of foundation pit
2.84mx1.60mx1.20m (lxbxh) in size; foundation casting - footing PCC 1:3:6 (0.1m
thick) and 2 column RCC 1:2:4 0.45mx1.00mx1.50m (lxbxh) in size with planting
depth of 1.0m, 12mm thick 1:3 cement plastering of plint 0.50m height; erection
of mounting Structure and Isolator as directed by Engineer-in-charge
Sl. No. Description Unit Rate/Unit Qty. Amount
Material
3421
11 kV Isolator with
Earth Switch
complete with
mounting structure,
terminal connectors,
foundation bolts and
all other accessories
etc, conforming to IS:
13118 (1991) or any
amendments there of.
No 68,500.00 1.0000 68,500.00
3512
T.S Rod 12mm
conforming to IS:
9417 (1989) or any
amendments there of.
Kg 82.20 68.0000 5,589.60
3513
T.S Rod 8mm
conforming to IS:
9417 (1989) or any
amendments there of.
Kg 82.20 24.0000 1,972.80
3514 Binding Wire Kg 105.00 1.0000 105.00
2301 Cement cum 13,750.00 0.5200 7,150.00
2302 River Sand cum 2,100.00 1.0000 2,100.00
2303
Stone Aggregate 10- 20
mm cum 1,890.00 1.8000 3,402.00
2403
Wooden Plank (12x1
sq.ft.) No 1,000.00 4.0000 4 ,000.00
Total Cost of Materials 92,819.40
Labours
1001 Labour Skilled-I manday 380.00 9.00 3,420.00
1002 Labour Skilled-II manday 310.00 9.00 2,790.00
1003 Labour Semi-Skilled manday 250.00 4.00 1,000.00
1004 Labour Un-skilled manday 220.00 47.00 10,340.00
Total Cost of Labours 17,550.00
Total 110,369.40
Add 15% for overhead & Profit 16,555.41
Testing and Commissioning Charges 2,000.00
Grand Total 128,925.00
Supervision (15% on Labour Cost) 2,632.50
Page No -204-
Page No -205-
Page No -206-
Page No -207-
INSTALLATION OF 33kV HORN GAP FUSE UNIT
17.08 Providing and Installation of 33kV Horn Gap Fuse Unit
Sl. No. Description Unit Rate/Unit Qty. Amount
Material
3420
33 kV Horn Gap Fuse Unit
conforming to IS: 9921 of the
latest version.
No 14,000.00 1.00 14,000.00
Total Cost of Materials 14,000.00
Labours
1001 Labour Skilled-I manday 380.00 1.00 380.00
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 1.50 330.00
Total Cost of Labours 710.00
Total 14,710.00
Add 15% for overhead & Profit 2,206.50
Grand Total 16,917.00
Supervision (15% on Labour Cost) 106.50
Page No -208-
INSTALLATION AND COMMISSIONING OF 33/11kV TRANSFORMERS
INSTALLATION AND COMMISSIONING OF 33/11kV, 6.3MVA POWER
TRANSFORMER
18.01 Providing and erection of 33/11kV, 6.3MVA Transfomer with construction of
foundation 2.8mx3.05mx1.4m in size (planting depth of 0.4m) with PCC 1:2:4 (1
cement : 2 coarse sand : 4 graded stone aggregate 40 mm nominal size ) including
commissioning as directed by Engineer-in-Charge
Sl. No. Description Unit Rate/Unit Qty. Amount
Material
3405
Outdoor type, oil
immersed,
naturally cooled
3ph, 50Hz, Cu
wound Power
Transformer of
vector group DynII
with tap changer
and air breather
etc. conforming to
IS:2026 of latest
version and ISI
marked of the
capacity 6.3 MVA,
33/11kV complete
with all
accessories.
No 3,723,921.00 1.00 3,723,921.00
2301 Cement cum 13,750.00 3.08 42,350.00
2302 River Sand cum 2,100.00 6.00 12,600.00
2303
Stone Aggregate
10-20 mm cum 1,890.00 11.00 20,790.00
2403
Wooden Plank
(12x1 sq.ft.) No 1,000.00 11.00 11,000.00
Total Cost of Materials 3,810,661.00
Labours
1001 Labour Skilled-I manday 380.00 14.00 5,320.00
1002 Labour Skilled-II manday 310.00 2.00 620.00
1003 Labour Semi- manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 92.00 20,240.00
Total Cost of Labours 26,180.00
Total 3,836,841.00
Add 15% for overhead & Profit 575,526.15
Testing and Commissioning Charges 3,000.00
Grand Total 4,415,367.00
Supervision (15% on Labour Cost) 3,927.00
Page No -209-
INSTALLATION AND COMMISSIONING OF 33/11kV, 2.5MVA POWER TRANSFORMER
18.02 Providing and erection of 33/11kV, 2 .5MVA Transfomer with construction of
foundation 2.4mx2.8mx1.85m in size (planting depth of 0.4m) with PCC 1:2:4 (1
cement : 2 coarse sand : 4 graded stone aggregate 40 mm nominal size ) including
commissioning as directed by Engineer-in-Charge
Sl. No. Description Unit Rate/Unit Qty. Amount
Material
3406
Outdoor type, oil
immersed,
naturally cooled
3ph, 50Hz, Cu
wound Power
Transformer of
vector group Dyn-II
with tap changer
and air breather
etc. conforming to
IS:2026 of latest
version and ISI
marked of the
capacity 2.5 MVA,
33/11kV complete
with all accessories.
No 2,637,414.00 1.00 2,637,414.00
2301 Cement cum 13,750.00 2.41 33,137.50
2302 River Sand cum 2,100.00 5.00 10,500.00
2303
Stone Aggregate 10-
20 mm cum 1,890.00 9.50 17,955.00
2403
Wooden Plank
(12x1 sq.ft.) No 1,000.00 4.00 4,000.00
Total Cost of Materials 2,703,006.50
Labours
1001 Labour Skilled-I manday 380.00 14.00 5,320.00
1002 Labour Skilled-II manday 310.00 2.00 620.00
1003
Labour Semi-
Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 95.00 20,900.00
Total Cost of Labours 26,840.00
Total 2,729,846.50
Add 15% for overhead & Profit 409,476.98
Testing and Commissioning Charges 3,000.00
Grand Total 3,142,323.00
Supervision (15% on Labour Cost) 4,026.00
Page No -210-
INSTALLATION AND COMMISSIONING OF 33/11kV, 1.6MVA POWER TRANSFORMER
18.03 Providing and erection of 33/11kV, 1 .6MVA Transfomer with construction of
foundation 2.0mx2.0mx1.92m in size (planting depth of 0.4m) with PCC 1:2:4 (1
cement : 2 coarse sand : 4 graded stone aggregate 40 mm nominal size ) including
commissioning as directed by Engineer-in-Charge
Sl. No. Description Unit Rate/Unit Qty. Amount
Material
3407
Outdoor type, oil
immersed,
naturally cooled
3ph, 50Hz, Cu
wound Power
Transformer of
vector group Dyn-II
with tap changer
and air breather etc.
conforming to
IS:2026 of latest
version and ISI
marked of the
capacity 1.6 MVA,
33/11kV complete
with all accessories.
No 1,916,070.00 1.00 1,916,070.00
2301 Cement cum 13,750.00 0.03 435.88
2302 River Sand cum 2,100.00 0.10 199.71
2303
Stone Aggregate 10-
20 mm cum 1,890.00 0.19 361.37
2403
Wooden Plank
(12x1 sq.ft.) No 1,000.00 4.00 4,000.00
Total Cost of Materials 1,921,066.95
Labours
1001 Labour Skilled-I manday 380.00 14.00 5,320.00
1002 Labour Skilled-II manday 310.00 2.00 620.00
1003 Labour Semi- manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 68.00 14,960.00
Total Cost of Labours 20,900.00
Total 1,941,966.95
Add 15% for overhead & Profit 291,295.04
Testing and Commissioning Charges 3,000.00
Grand Total 2,236,262.00
Supervision (15% on Labour Cost) 3,135.00
Page No -211-
INSTALLATION AND COMMISSIONING OF 33/0.415kV, 100kVA STATION
TRANSFORMER
18.04 Providing and erection of 33/0.415kV, 100 kVA Transfomer with construction of
foundation 1.2mx1.2mx1.65m in size (planting depth of 0.4m) with PCC 1:2:4 (1
cement : 2 coarse sand : 4 graded stone aggregate 40 mm nominal size ) including
commissioning as directed by Engineer-in-Charge
Sl. No. Description Unit Rate/Unit Qty. Amount
Material
3408
Outdoor type, oil
immersed,
naturally cooled
3ph, 50Hz, Cu
wound Station
Transformer of
vector group Dyn-II
with tap changer
and air breather etc.
conforming to
IS:2026 of latest
version and ISI
marked of the
capacity 100 kVA,
33/0.415kV,
complete with all
accessories.
No 467,531.00 1.00 467,531.00
2301 Cement cum 13,750.00 0.68 9,350.00
2302 River Sand cum 2,100.00 1.40 2,940.00
2303
Stone Aggregate 10-
20 mm cum 1,890.00 2.70 5,103.00
2403
Wooden Plank
(12x1 sq.ft.) No 1,000.00 6.00 6,000.00
Total Cost of Materials 490,924.00
Labours
1001 Labour Skilled-I manday 380.00 8.00 3,040.00
1002 Labour Skilled-II manday 310.00 1.00 310.00
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 36.00 7,920.00
Total Cost of Labours 11,270.00
Total 502,194.00
Add 15% for overhead & Profit 75,329.10
Testing and Commissioning Charges 3,000.00
Grand Total 580,523.00
Supervision (15% on Labour Cost) 1,690.50
Page No -212-
INSTALLATION AND COMMISSIONING OF 33/0.415kV, 250kVA STATION
TRANSFORMER
18.05 Providing and erection of 33/0.415kV, 250 kVA Transfomer with construction of
foundation 1.5mx2.0mx1.5m in size (planting depth of 0.4m) with PCC 1:2:4 (1
cement : 2 coarse sand : 4 graded stone aggregate 40 mm nominal size ) including
commissioning as directed by Engineer-in-Charge
Sl. No. Description Unit Rate/Unit Qty. Amount
Material
3409
Outdoor type, oil
immersed,
naturally cooled
3ph, 50Hz, Cu
wound Station
Transformer of
vector group Dyn-II
with tap changer
and air breather
etc. conforming to
IS:2026 of latest
version and ISI
marked of the
capacity 250 kVA,
33/0.415kV,
complete with all
accessories.
No 494,741.25 1.00 494,741.25
2301 Cement cum 13,750.00 1.24 17,050.00
2302 River Sand cum 2,100.00 2.50 5,250.00
2303
Stone Aggregate 10-
20 mm cum 1,890.00 4.85 9,166.50
2403
Wooden Plank
(12x1 sq.ft.) No 1,000.00 7.00 7,000.00
Total Cost of Materials 533,207.75
Labours
1001 Labour Skilled-I manday 380.00 8.00 3,040.00
1002 Labour Skilled-II manday 310.00 2.00 620.00
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 56.00 12,320.00
Total Cost of Labours 15,980.00
Total 549,187.75
Add 15% for overhead & Profit 82,378.16
Testing and Commissioning Charges 3,000.00
Grand Total 634,566.00
Supervision (15% on Labour Cost) 2,397.00
Page No -213-
FITTING OF COPPER CONTROL CABLES
19.01 Providing and Fitting of 1.1kV Copper Control Cable of per meter length, 16 Core, 2.5
sq.mm conforming to IS : 1554-1 (1988) or any ammendments with 2.5 sq.mm
Copper Cable Lug of Ring/Fork/Pin type, as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Material
1627
1.1 kV Copper Control
Cable, 2.5 sq.mm, 16
Core, conforming to IS
: 1554-1 (1988) or any
amendments there of.
m 575.00 50.00 28,750.00
1717
Copper Cable Lug,
Ring/Fork/Pin type,
2.5 sq.mm
No 27.00 32.00 864.00
2011
Cable Gland for 2.5
sq.mm, 16 Core
Copper Control Cable
No 52.50 2.00 105.00
1718 Cable Ferrule, 2.5
sq.mm [A-Z] 100 each Packet 2,340.00 1.00 2,340.00
1719 Cable Ferrule, 2.5
sq.mm [0-9] 100 each Packet 900.00 1.00 900.00
Total Cost of Materials 32,959.00
Labours
1001 Labour Skilled-I manday 380.00 0.50 190.00
1002 Labour Skilled-II manday 310.00 1.00 310.00
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 2.25 495.00
Total Cost of Labours 995.00
Total 33,954.00
Add 15% for overhead & Profit 5,093.10
Testing and Commissioning Charges 5,000.00
Grand Total 44,047.00
Per meter cost 881.00
Supervision (15% on Labour Cost) 149.25
Page No -214-
FITTING OF COPPER CONTROL CABLES
19.02 Providing and Fitting of 1.1kV Copper Control Cable of per meter length, 12 Core, 2.5
sq.mm conforming to IS : 1554-1 (1988) or any ammendments with 2.5 sq.mm
Copper Cable Lug of Ring/Fork/Pin type, as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Material
1628
1.1 kV Copper Control
Cable, 2.5 sq.mm, 12
Core, conforming to IS
: 1554-1 (1988) or any
amendments there of.
m 444.00 50.00 22,200.00
1717
Copper Cable Lug,
Ring/Fork/Pin type,
2.5 sq.mm
No 27.00 24.00 648.00
2012
Cable Gland for 2.5
sq.mm, 12 Core
Copper Control Cable
No 52.50 2.00 105.00
1718 Cable Ferrule, 2.5
sq.mm [A-Z] 100 each Packet 2,340.00 1.00 2,340.00
1719 Cable Ferrule, 2.5
sq.mm [0-9] 100 each Packet 900.00 1.00 900.00
Total Cost of Materials 26,193.00
Labours
1001 Labour Skilled-I manday 380.00 0.50 190.00
1002 Labour Skilled-II manday 310.00 1.00 310.00
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 1.70 374.00
Total Cost of Labours 874.00
Total 27,067.00
Add 15% for overhead & Profit 4,060.05
Testing and Commissioning Charges 5,000.00
Grand Total 36,127.00
Per meter cost 723.00
Supervision (15% on Labour Cost) 131.10
Page No -215-
FITTING OF COPPER CONTROL CABLES
19.03 Providing and Fitting of 1.1kV Copper Control Cable of per meter length, 6 Core, 2.5
sq.mm conforming to IS : 1554-1 (1988) or any ammendments with 2.5 sq.mm
Copper Cable Lug of Ring/Fork/Pin type, as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Material
1629
1.1 kV Copper Control
Cable, 2.5 sq.mm, 6
Core, conforming to IS
: 1554-1 (1988) or any
amendments there of.
m 174.00 50.00 8,700.00
1717
Copper Cable Lug,
Ring/Fork/Pin type,
2.5 sq.mm
No 27.00 24.00 648.00
2013
Cable Gland for 2.5
sq.mm, 6 Core Copper
Control Cable
No 52.50 2.00 105.00
1718 Cable Ferrule, 2.5
sq.mm [A-Z] 100 each Packet 2,340.00 1.00 2,340.00
1719 Cable Ferrule, 2.5
sq.mm [0-9] 100 each Packet 900.00 1.00 900.00
Total Cost of Materials 12,693.00
Labours
1001 Labour Skilled-I manday 380.00 0.50 190.00
1002 Labour Skilled-II manday 310.00 0.50 155.00
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 1.68 370.00
Total Cost of Labours 715.00
Total 13,408.00
Add 15% for overhead & Profit 2,011.20
Testing and Commissioning Charges 5,000.00
Grand Total 20,419.00
Per meter cost 408.00
Supervision (15% on Labour Cost) 107.25
Page No -216-
FITTING OF COPPER CONTROL CABLES
19.04 Providing and Fitting of 1.1kV Copper Control Cable of per meter length, 4 Core, 2.5
sq.mm conforming to IS : 1554-1 (1988) or any ammendments with 2.5 sq.mm
Copper Cable Lug of Ring/Fork/Pin type, as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Material
1630
1.1 kV Copper Control
Cable, 2.5 sq.mm, 4
Core, conforming to IS
: 1554-1 (1988) or any
amendments there of.
m 122.00 50.00 6,100.00
1717
Copper Cable Lug,
Ring/Fork/Pin type,
2.5 sq.mm
No 27.00 24.00 648.00
2014
Cable Gland for 2.5
sq.mm, 4 Core Copper
Control Cable
No 45.00 2.00 90.00
1718 Cable Ferrule, 2.5
sq.mm [A-Z] 100 each Packet 2,340.00 1.00 2,340.00
1719 Cable Ferrule, 2.5
sq.mm [0-9] 100 each Packet 900.00 1.00 900.00
Total Cost of Materials 10,078.00
Labours
1001 Labour Skilled-I manday 380.00 0.50 190.00
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 1.67 366.67
Total Cost of Labours 556.67
Total 10,634.67
Add 15% for overhead & Profit 1,595.20
Testing and Commissioning Charges 5,000.00
Grand Total 17,230.00
Per meter cost 345.00
Supervision (15% on Labour Cost) 83.50
Page No -217-
FITTING OF COPPER CONTROL CABLES
19.05 Providing and Fitting of 1.1kV Copper Control Cable of per meter length, 2 Core, 2.5
sq.mm conforming to IS : 1554-1 (1988) or any ammendments with 2.5 sq.mm
Copper Cable Lug of Ring/Fork/Pin type, as directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Material
1631
1.1 kV Copper Control
Cable, 2.5 sq.mm, 2
Core, conforming to IS
: 1554-1 (1988) or any
amendments there of.
m 96.00 50.00 4,800.00
1717
Copper Cable Lug,
Ring/Fork/Pin type,
2.5 sq.mm
No 27.00 24.00 648.00
2015
Cable Gland for 2.5
sq.mm, 2 Core Copper
Control Cable
No 45.00 2.00 90.00
1718 Cable Ferrule, 2.5
sq.mm [A-Z] 100 each Packet 2,340.00 1.00 2,340.00
1719 Cable Ferrule, 2.5
sq.mm [0-9] 100 each Packet 900.00 1.00 900.00
Total Cost of Materials 8,778.00
Labours
1001 Labour Skilled-I manday 380.00 0.00 -
1002 Labour Skilled-II manday 310.00 0.50 155.00
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 1.65 363.85
Total Cost of Labours 518.85
Total 9,296.85
Add 15% for overhead & Profit 1,394.53
Testing and Commissioning Charges 5,000.00
Grand Total 15,691.00
Per meter cost 314.00
Supervision (15% on Labour Cost) 77.83
Page No -218-
FITTING OF 11kV XLPE Al. CABLES
19.06 Providing and laying of 1 Core, 11kV XLPE Aluminium Cable of per meter length, 185
sq.mm conforming to IS 7098 Part 2 (1985) or any ammendments, as directed by the
engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Material
1638
11kV XLPE
Aluminium Cable, 1
Core, 185 sq.mm
m 1,159.00 50.00 57,950.00
Total Cost of Materials 57,950.00
Labours
1001 Labour Skilled-I manday 380.00 0.50 190.00
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 1.83 403.33
Total Cost of Labours 593.33
Total 58,543.33
Add 15% for overhead & Profit 8,781.50
Testing and Commissioning Charges 5,000.00
Grand Total 72,325.00
Per meter cost 1,447.00
Supervision (15% on Labour Cost) 89.00
Page No -219-
FITTING OF 11kV XLPE Al. CABLES
19.07 Providing and laying of 1 Core, 11kV XLPE Aluminium Cable of per meter length,
150sq.mm conforming to IS 7098 Part 2 (1985) or any ammendments, as directed
by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Material
1639
11kV XLPE
Aluminium Cable, 1
Core, 150 sq.mm
m 1,138.00 50.00 56,900.00
Total Cost of Materials 56,900.00
Labours
1001 Labour Skilled-I manday 380.00 0.50 190.00
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 1.79 392.86
Total Cost of Labours 582.86
Total 57,482.86
Add 15% for overhead & Profit 8,622.43
Testing and Commissioning Charges 5,000.00
Grand Total 71,105.00
Per meter cost 1,422.00
Supervision (15% on Labour Cost) 87.43
Page No -220-
FITTING OF 11kV XLPE Al. CABLES
19.08 Providing and laying of 1 Core, 11kV XLPE Aluminium Cable of per meter length,
120sq.mm conforming to IS 7098 Part 2 (1985) or any ammendments, as directed
by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Material
1640
11kV XLPE
Aluminium Cable, 1
Core, 120 sq.mm
m 1,100.00 50.00 55,000.00
Total Cost of Materials 55,000.00
Labours
1001 Labour Skilled-I manday 380.00 0.50 190.00
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 1.75 385.00
Total Cost of Labours 575.00
Total 55,575.00
Add 15% for overhead & Profit 8,336.25
Testing and Commissioning Charges 5,000.00
Grand Total 68,911.00
Per meter cost 1,378.00
Supervision (15% on Labour Cost) 86.25
Page No -22 1-
FITTING OF 11kV XLPE Al. CABLES JOINTING KIT
19.09 Providing and Fitting of 1 Core, 11kV XLPE Aluminium Cable Jointing Kit of One
Number, 185 sq.mm conforming to IS 7098 Part 2 (1985) or any ammendments, as
directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Material
2023
Cable Jointing Kit for
1 Core, 11kV XLPE
Al. Cable, 185 sq.mm
No 4,550.00 1.00 4,550.00
1709
Aluminium Cable Lug
long barrel , 185
Sq.mm
No 68.00 1.00 68.00
Total Cost of Materials 4,618.00
Labours
1001 Labour Skilled-I manday 380.00 0.67 253.33
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 0.67 146.67
Total Cost of Labours 400.00
Total 5,018.00
Add 15% for overhead & Profit 752.70
Grand Total 5,771.00
Supervision (15% on Labour Cost) 60.00
Page No -222-
FITTING OF 11kV XLPE Al. CABLES JOINTING KIT
19.10 Providing and Fitting of 1 Core, 11kV XLPE Aluminium Cable Jointing Kit of One
Number, 150 sq.mm conforming to IS 7098 Part 2 (1985) or any ammendments, as
directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Material
2024
Cable Jointing Kit for
1 Core, 11kV XLPE
Al. Cable, 150 sq.mm
No 4,550.00 1.00 4,550.00
1708
Aluminium Cable Lug
long barrel , 150
Sq.mm
No 53.00 1.00 53.00
Total Cost of Materials 4,603.00
Labours
1001 Labour Skilled-I manday 380.00 0.67 253.33
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 0.67 146.67
Total Cost of Labours 400.00
Total 5,003.00
Add 15% for overhead & Profit 750.45
Grand Total 5,753.00
Supervision (15% on Labour Cost) 60.00
Page No -223-
FITTING OF 11kV XLPE Al. CABLES JOINTING KIT
19.11 Providing and Fitting of 1 Core, 11kV XLPE Aluminium Cable Jointing Kit of One
Number, 120 sq.mm conforming to IS 7098 Part 2 (1985) or any ammendments, as
directed by the engineer in charge.
Sl. No. Description Unit Rate/Unit Qty. Amount
Material
2025
Cable Jointing Kit for
1 Core, 11kV XLPE
Al. Cable, 120 sq.mm
No 4,550.00 1.00 4,550.00
1707
Aluminium Cable Lug
long barrel , 120
Sq.mm
No 42.00 1.00 42.00
Total Cost of Materials 4,592.00
Labours
1001 Labour Skilled-I manday 380.00 0.67 253.33
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 0.67 146.67
Total Cost of Labours 400.00
Total 4,992.00
Add 15% for overhead & Profit 748.80
Grand Total 5,741.00
Supervision (15% on Labour Cost) 60.00
Page No -224-
INSTALLATION OF 33 kV C&R TRANSFORMER PANEL
20.01 Providing and Installation of 33kV Control and Relay Transformer Panel
Sl. No. Description Unit Rate/Unit Qty. Amount
Material
3412
33 kV Control and Relay
Transformer Panel complete
with MW meter, ammeter,
voltmeter, indicators as
necessary, overcurrent and
earth fault relays (numerical
type) with time delay setting
facilities, trip circuit
supervising relay, Bucholz
relay, oil temperature relay,
winding temperature relay,
master trip relay, remote
switches, energy meter,
import & export recorder,
fault annunciator, digital
metering, event logger,
disturbance recorder,
communication facilities etc.
of the latest technology
conforming to IS: 3231 of the
latest versions. Aux. supply
of 1 10V DC. (Appropriate
transformation ratios should
be selected as per
requirements)
No 741,990.00 1.00 741,990.00
Total Cost of Materials 741,990.00
Labours
1001 Labour Skilled-I manday 380.00 0.33 126.67
1002 Labour Skilled-II manday 310.00 0.33 103.33
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 6.33 1,393.33
Total Cost of Labours 1,623.33
Total 743,613.33
Add 15% for overhead & Profit 111,542.00
Testing and Commissioning Charges 3,000.00
Grand Total 858,155.00
Supervision (15% on Labour Cost) 243.50
Page No -225-
INSTALLATION OF 33 kV C&R FEEDER PANEL
20.02 Providing and Installation of 33kV Control and Relay Feeder Panel
Sl. No. Description Unit Rate/Unit Qty. Amount
Material
341 3
33 kV Control and Relay
Feeder Panel complete with
MW meter, ammeter,
voltmeter, frequency meter,
power factor meter,
indicators as necessary,
overcurrent and earth fault
relays (numerical type) with
time delay setting facilities,
trip supervising relay,
master trip relay, remote
switches, energy meter,
import & export recorder,
fault annunciator, digital
metering, event logger,
disturbance recorder,
communication facilities etc.
of the latest technology
conforming to IS: 3231 of
the latest versions. Aux.
supply of 1 10V DC.
(Appropriate transformation
ratios should be selected as
per requirements)
No 741 ,990.00 1.00 741,990.00
Total Cost of Materials 741,990.00
Labours
1001 Labour Skilled-I manday 380.00 0.33 126.67
1002 Labour Skilled-II manday 310.00 0.33 103.33
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 6.33 1,393.33
Total Cost of Labours 1,623.33
Total 743,613.33
Add 15% for overhead & Profit 111,542.00
Testing and Commissioning Charges 3,000.00
Grand Total 858,155.00
Supervision (15% on Labour Cost) 243.50
Page No -226-
INSTALLATION OF 11kV INDOOR SWITCHBOARD PANEL
20.03 Providing and Installation of 1 1kV Indoor Switchboard Panel for Incoming Feeder.
Labours
1001 Labour Skilled-I manday 380.00 0.33 126.67
1002 Labour Skilled-II manday 310.00 0.33 103.33
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 6.33 1,393.33
Total Cost of Labours 1,623.33
Total 1,240,623.33
Add 15% for overhead & Profit 186,093.50
Testing and Commissioning Charges 3,000.00
Grand Total 1,429,717.00
Supervision (15% on Labour Cost) Sl. No. Descripti
Page No -227-
INSTALLATION OF 11kV INDOOR SWITCHBOARD PANEL 20.04
Providing and Installation of 11kV Indoor Switchboard Panel for Outgoing Feeder.
Sl. No. Description Unit Rate/Unit Qty. Amount
Material
3415
11 kV Indoor Switchboard Panel for
Outgoing Feeder Panel with the
following:
12 kV, 350 MVA, 800 A, 18.4KA, Multi
panel, shunt trip, Indoor Type, motor
operated, spring closing Vacuum
Circuit Breaker, Current Transformer
having accuracy class of 0.2 for
metering & 5P10 for protection, MW
meter, ammeter, voltmeter,
overcurrent and earth fault relays
(numerical type) with time delay
setting facilities, trip supervising
relay, master trip relay, energy meter,
import & export recorder, SIM card
compatible fault annunciator, digital
metering, event logger, disturbance
recorder, communication facilities etc.
of the latest technology, conforming to
IS:13118 (1991), IEC:56 (1987).
(Appropriate transformation ratios
should be selected as per
requirements)
No 1,239,000.00 1.00 1,239,000.00
Total Cost of Materials 1,239,000.00
Labours
1001 Labour Skilled-I manday 380.00 0.33 126.67
1002 Labour Skilled-II manday 310.00 0.33 103.33
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 6.33 1,393.33
Total Cost of Labours 1,623.33
Total 1,240,623.33
Add 15% for overhead & Profit 186,093.50
Testing and Commissioning Charges 3,000.00
Grand Total 1,429,717.00
Supervision (15% on Labour Cost) 243.50
Page No -228-
INSTALLATION OF 11kV INDOOR SWITCHBOARD PANEL
20.05 Providing and Installation of 11kV Indoor Switchboard Panel for Bus Coupler.
Sl. No. Description Unit Rate/Unit Qty. Amount
Material
3416
11 kV Indoor Switchboard Panel for Bus
Coupler Panel with the following:
12 kV, 350 MVA, 800 A, 18.4KA, Multi
panel, shunt trip, Indoor Type, motor
operated, spring closing Vacuum
Circuit Breaker, Current Transformer
having accuracy class of 0.2 for
metering & 5P10 for protection, MW
meter, ammeter, voltmeter,
overcurrent and earth fault relays
(numerical type) with time delay
setting facilities, trip supervising
relay, master trip relay, energy meter,
import & export recorder, SIM card
compatible fault annunciator, digital
metering, event logger, disturbance
recorder, communication facilities etc.
of the latest technology, conforming to
IS:13118 (1991), IEC:56 (1987).
(Appropriate transformation ratios
should be selected as per
requirements)
No 1 ,239,000.00 1.00 1 ,239,000.00
Total Cost of Materials 1,239,000.00
Labours
1001 Labour Skilled-I manday 380.00 0.33 126.67
1002 Labour Skilled-II manday 310.00 0.33 103.33
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 6.33 1,393.33
Total Cost of Labours 1,623.33
Total 1,240,623.33
Add 15% for overhead & Profit 186,093.50
Testing and Commissioning Charges 3,000.00
Grand Total 1,429,717.00
Supervision (15% on Labour Cost) 243.50
Page No -229-
INSTALLATION OF BATTERY CHARGER WITH DCDB 21.01
Providing and Installation of 11 0V Battery Charger with DCDB.
Sl. No. Description Unit Rate/Unit Qty. Amount
Material
3417
1 10V DC Distribution Board,
Float cum Boost Battery Charger
(30A) suitable for charging 250 Ah
battery and supply of continuous
load at 15A.
No 580,135.00 1.00 580,135.00
Total Cost of Materials 580,135.00
Labours
1001 Labour Skilled-I manday 380.00 0.50 190.00
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 1.50 330.00
Total Cost of Labours 520.00
Total 580,655.00
Add 15% for overhead & Profit 87,098.25
Testing and Commissioning Charges 3,000.00
Grand Total 670,753.00
Supervision (15% on Labour Cost) 7 8 . 0 0
Page No -230-
INSTALLATION OF BATTERY BANK
21.02 Providing and Installation of 11 0V, 1 50Ah Battery Bank.
Sl. No. Description Unit Rate/Unit Qty. Amount
Material
3418
1 10V DC, 250 Ah, SMF-
VRLA Battery Bank
consisting of 55 nos. cell.
Model: UPST-250 along
with MS Steel enclosure
and inter cell connection
complete with accessories
No 455,275.00 1.00 455,275.00
Total Cost of Materials 455,275.00
Labours
1001 Labour Skilled-I manday 380.00 1.00 380.00
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 7.00 1,540.00
Total Cost of Labours 1,920.00
Total 457,195.00
Add 15% for overhead & Profit 68,579.25
Testing and Commissioning Charges 3,000.00
Grand Total 528,774.00
Supervision (15% on Labour Cost) 288.00
Page No -23 1-
INSTALLATION OF ACDB
21.03 Providing and Installation of AC Distribution Board.
Sl. No. Description Unit Rate/Unit Qty. Amount
Material 3419 AC Distribution Board No 74,990.00 1.00 74,990.00
Total Cost of Materials 74,990.00
Labours
1001 Labour Skilled-I manday 380.00 0.00 -
1002 Labour Skilled-II manday 310.00 1.00 310.00
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 3.00 660.00
Total Cost of Labours 970.00
To ta l 75 ,960 .00
Add 15% for overhead & Profit 11,394.00
Testing and Commissioning Charges 3,000.00
Grand Tota l 90,354.00
Supervision (15% on Labour Cost) 145.50
Page No -232-
FENCING OF 33kV SUBSTATION BY RCC PILLAR WITH BRICK
22.01 Construction of 2m Height Fencing for 33kV Sub-Station by using RCC Pillar, Brick
etc, as directed by the engineer in charge.
Earthwork in excavation in foundation trenches or drains etc. (not exceeding 1 .5m
in width or 1 0sqm on plan) including dressing of sides and ramming of bottoms, lift A
upto 1.5m including getting out excavated soil and disposal of surplus excavated
soil as directed within a lead of 50 metres.
Hard Soil ( pick work )
(Coefficient for ordinary soil increased 1.5 times)
Details of cost for 10.00 cum.
Description Unit Qty. Rate/Unit Amount
LABOURS : Mate/Supervisor day 1.20 470.00 564.00
Unskilled day 12.30 220.00 2,706.00
3,270.00
Sundries and contingencies @ 3% 98.10
3,368.10
Add for water charge @ 1% 33.68
3,401.78
Add CPOH @ 15% 510.27
Cost for 10 cum 3,912.05
cum 4.00 1,564.82
Page No -233-
B Steel reinforcement for RCC work including straighthening, cutting, bending,
placing in position and binding all complete.
Hot rolled deformed bars
Details of cost for 1 quintal .
Description Unit Qty. Rate/Unit Amount
MATERIALS :
Deformed twisted steel bars = Wastage 5% =
Total =
1.05q quintal 1.05 5,800.00 6,090.00
Carriage of steel 1.05/10 = tonne 0.11 37.46 3.93
Cover block L.S. 10.00 8.00 80.00
LABOUR :
For straightening, cutting,
bending, binding and placing
in position-
Blacksmith 1st class day 1.00 440.00 440.00
Beldar day 1.00 220.00 220.00
Sundries and binding wire L.S. 26.91 8.00 215.28
TOTAL 7,049.21
Add water charge @ 1% 70.49
TOTAL 7,119.70
Add CPOH @ 15% 1,067.96
Cost for 100 kg 8,187.66
kg 178.59 14,622.34
Page No -234-
C Centering and shuttering including strutting,propping etd. And removal of form for:
a) Columns, pillars, piers, abutments, posts and struts.
Details of cost for a Column 30 cm square and 3.50 high : 4x0.30x3.50m= 4.20
sqm
Description Unit Qty. Rate/Unit Amount
(A) MATERIALS :
(i) Planks 38 mm thick. (2nd class ) : 2x0.30x3.50 sqm 2.10 : 2x0.48x3.50 sqm 3.36
Total sqm 5.46 Add for wastage @ 5% sqm 0.27 Total 5.73
cum 0.22 28,000.00 6,104.00
(ii) Ballies 125 mm for struts. : 4x3.80 Rm 15.20 45.00 684.00
Total 6,788.00
Assuming that timber shall
become unserviceable after
being used 7 times.
Cost of using once 969.71
Carriage & handling @ 2.5% 24.24
(A) 993.95
(B) LABOURS :
2nd class carpenter each 1.25 400.00 500.00
Unskilled each 1.25 220.00 275.00
775.00
Sundries & Contingencies @ 3% 23.25
(B) 798.25
(A) + (B) 1,792.20
Add for water charge @ 1% 17.92
1,810.12
Add CPOH @ 15% 271.52
Cost for 4.2 sqm 2,081.64
sqm 12.00 5,947.54
Page No -235-
D b) Lintels, beams, plinth beams, girders, bressumers and cantilevers, etc.
Consider a beam of 6.00 mm clear span, 0.50 m deep and 0.30 m wide and floor
height of 3.50 m.
Cubical content = 6.60x0.50x0.30 cum 0.99
Area in contact with concrete= 1x1 .3x6.0 sqm 7.80
Description Unit Qty. Rate/Unit Amount
(A) MATERIALS :
(i) Planks 38 mm thick. (2nd class) : 2x0.538x0.376 sqm 0.41 : 2x6.60x0.50 sqm 6.60 : 1x6.00x0.376 sqm 2.26
Total 9.26 Add for wastage @ 10% sqm 0.93
Total 10.19
cum 0.39 28,000.00 10,836.00
(ii) Ballies 125 mm dia. supports 0 .8 m apart : 8x3.50 Rm 28.00 45.00 1,260.00
(iii) Ballies bracing for support : 6x2.00 Rm 12.00 45.00 540.00
Total 12,636.00
Assuming that timber shall
become unserviceable after
being used 7 times.
Cost of using once 1,805.14
Carriage & handling @ 2.5% 45.13
(A) 1,850.27
(B) LABOURS :
For assembling, errection,
dismantling and clearing.
2nd class carpenter each 1.25 400.00 500.00
Unskilled each 1.25 220.00 275.00
775.00
Sundries & Contingencies @ 3% 23.25
(B) 798.25
(A) + (B) 2,648.52
Add for water charge @ 1% 26.49
2,675.01
Add CPOH @ 15% 401.25
Cost for 7.8 sqm 3,076.26
sqm 30.80 12,147.30
Page No -236-
Providing and laying in position reinforced cement concrete excluding cost of
centering and shuttering , finishing and reinforcement in -
1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20mm nominal size)
Details of cost for 1.00 cum. Description Unit Qty. Rate/Unit Amount
MATERIALS :
Stone aggregate 20mm cum 0.67 1,800.00 1,206.00
Stone aggregate 10mm cum 0.22 1,800.00 396.00
Carriage of stone aggregate cum 0.89 73.42 65.34
Coarse sand cum 0.45 850.00 378.25
Carriage of course sand cum 0.45 73.42 32.67
Cement (0.2833cum ) tonne 0.32 9,000.00 2,880.00
Carriage of cement tonne 0.32 37.46 11.99
LABOURS :
1st class mason day 0.17 450.00 76.50
Unskilled day 2.00 220.00 440.00
Semi-skilled day 0.90 250.00 225.00
Hire charge of concrete mixer day 0.07 1,668.00 116.76
Vibrator day 0.07 1,068.00 74.76
Sundries L.S 14.30 8.00 114.40
TOTAL 6,017.67
Add water charge @ 1% 60.18
TOTAL 6,077.85
Add CPOH @ 15% 911.68
For 1.00 cum 6,989.53
lumn
cum 0.25 1,747.38
E
Page No -237-
C
Reinforced cement concrete work in walls including attached pillasters, columns,
pillers, posts, piers, abutments, return walls, retaining walls, struts, buttresses,
string or lacing courses, fillets etc. upto floor five level excluding cost of centering
shuttering etc complete.
1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20mm nominal size)
Details of cost for 9.18 cum.
Description Unit Qty. Rate/Unit Amount
MATERIALS :
Stone aggregate 20mm cum 6.15 1,800.00 11,071.08
Stone aggregate 10mm cum 2.02 1,800.00 3,635.28
Carriage of stone aggregate cum 8.17 73.42 599.84
Coarse sand cum 4.09 850.00 3,472.34
Carriage of course sand cum 4.09 73.42 299.93
Cement (0.2833cum ) tonne 2.94 9,000.00 26,442.00
Carriage of cement tonne 2.94 37.46 110.06
LABOURS :
Unskilled day 11.29 220.00 2,483.80
Coolie day 7.53 220.00 1,656.60
Semi-skilled day 8.26 250.00 2,065.00
1st class mason day 0.92 450.00 414.00
2nd class mason day 0.92 320.00 294.40
Hire charge of concrete mixer day 0.64 1,668.00 1,067.52
Vibrator day 0.64 1,068.00 683.52
Sundries L.S 131.82 8.00 1,054.56
Scaffolding L.S 420.03 8.00 3,360.24
Extra labour for lifting material
upto floor V level.0.75x9.18x2.5
Coolie day 17.20 250.00 4,300.00
TOTAL 55,349.93
Add water charge @ 1% 553.50
TOTAL 55,903.43
Add CPOH @ 15% 8,385.51
Cost for 9.18 cum 64,288.94
cum 0.50 3,501.58
F
Page No -238-
Reinforced cement concrete work in beams, suspended floors, roofs having slope upto
15° landings, balconies, shelves, chajjas, lintels, bands, window sills, stair
cases, spiral stair cases, cantilevers upto floor five level excluding cost of centering G
shuttering etc complete. with 1:2:4(1cement : 2 coarse sand :4 stone aggregate
20mm)
Beam:
1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20mm nominal size)
Details of cost for 1.00 cum.
Description Unit Qty. Rate/Unit Amount
MATERIALS :
Stone aggregate 20mm cum 0.67 1,800.00 1,206.00
Stone aggregate 10mm cum 0.22 1,800.00 396.00
Carriage of stone aggregate cum 0.89 73.42 65.34
Coarse sand cum 0.45 850.00 378.25
Carriage of course sand cum 0.45 73.42 32.67
Cement (0.2225cum ) tonne 0.32 9,000.00 2,880.00
Carriage of cement tonne 0.32 37.46 11.99
LABOURS :
1st class mason day 0.24 450.00 108.00
Unskilled day 2.75 220.00 605.00
Semi-skilled day 0.90 250.00 225.00
Hire charge of concrete mixer day 0.08 1,668.00 133.44
Vibrator day 0.08 1,068.00 85.44
Sundries L.S 14.30 8.00 114.40
Extra labour for lifting material
upto floor V level.(2.5x0.75)
Coolie day 1.88 250.00 470.00
TOTAL 6,241.53
Add water charge @ 1% 62.42
TOTAL 6,303.95
Add CPOH @ 15% 945.59
Cost for 1.00 cum 7,249.54
cum 1.10 7,974.49
Page No -239-
Filling available excavated earth (excluding rock) in trenches, plinth, sides of
foundations etc. in layers not exceeding 20cm in depth, consolidating each H
deposited layer by ramming and watering, lead up to 50 m and lift upto 1.5 m.
Details of cost for 10cum
Description Unit Qty. Rate/Unit Amount
LABOURS :
Mate day 0.20 470.00 94.00
Coolies day 2.50 220.00 550.00
Bhisti day 0.20 250.00 50.00
694.00
Add for water charges @1% 6.94
700.94
Add CPOH @ 15% 105.14
Cost for 10.00cum 806.08
cum 3.20 257.95
I Half brick masonry with first class brick in superstructure above plinth
level upto floor V level.
a) in cement mortar 1:3 ( 1 cement : 3 coarse sand )
Details of cost for 10.00 sqm
Description Unit Qty. Rate/Unit Amount
(A) MATERIALS:
(i) 1st class brick nos 565.00 10.00 5,650.00
(ii) Cement mortar 1:3 Rate as per item no.3.04(b) of
SH: Mortars cum 0.28 6,128.40 1,715.95
Carriage of bricks nos 565.00 0.46 259.90
Sundries & scafolding L.S 13.52 8.00 108.16
(B) LABOURS :
1st class mason each 0.60 450.00 270.00
2nd class mason each 0.60 320.00 192.00
Exatra labour for lifting materials: 10x0.1 15x0.75x1.5 Coolie each 0.70 220.00 154.00
Semi skilled each 0.70 250.00 175.00
Unskilled each 1.55 220.00 341.00
TOTAL 8,866.01
Add water charge @ 1% 88.66
TOTAL 8,954.67
Add CPOH @ 15% 1,343.20
Cost for 10.00 sqm 10,297.87
sqm 20.25 20,853.19
Page No -240-
2.0m high polysteel goat proof fencing with 2.6m angle iron posts 50 x 50 x 6mm A size
placed 2.0m apart embedded in cement concrete block 1:3:6 (1 cement: 3 sand : 6 stone
aggegate) of size 25 x 25 x 60 cm fixing with nails and wire etc. including earthwo rk
complete.
Details of cost for 30 Rm.
Description Unit Qty. Rate/Unit Amount
(A) MATERIALS:
(i) Angle iron 50x50x6mm @ 4.50kg/m.
: 16 x 2.6 x 4.50 kg 187.20 Add for wastage @ 5% kg 9.36
kg 196.56
qtl 1.97 6,985.00 13,760.45
(ii) Polysteel goat proof wire :
2.0 x 30 sqm 60.00 445.00 26,700.00
(iii) Nails kg 2.00 80.00 160.00
40,620.45
Carriage & handling @ 2.5% 1,015.51
(iv) Cement concrete block 1 : 3 : 6 (1cement:3 sand:6 stone
aggregate 20mm size)
: 16 x 0.25 x 0.25 x 0.60 cum 0.60 7,602.30 4,561.38
(v) Earthwork for cement
concrete block
: 16 x 0.25 x 0.25 x 0.60 cum 0.60 327.20 196.32
(A) 46,393.66
(B) LABOURS :
(For drilling holes, fitting and
fixing)
(i) 1st class mason each 0.12 450.00 54.00
(ii) 2nd class mason each 0.12 320.00 38.40
(iii) 1st class blacksmith each 0.78 440.00 343.20
(iv) 2nd class blacksmith each 2.75 320.00 880.00
(v) Unskilled each 2.72 220.00 598.40
1,914.00
Sundries & contingencies @
3%
57.42
(B) 1,971.42
(A) + (B) 48,365.08
Add for water charge @ 1%
except on (A) iv & v, i.e. on Rs.
43,607.38 436.07
TOTAL 48,801.15
Add CPOH @ 15% 7,320.17
Cost for 30.00 Rm 56,121.32
Cost for 1Rm 1,870.71
Say 1,871.00
22.02 Construction of 2m height Fencing for 33kV Sub-Station by using fencing post and fencing
net, as directed by the engineer in charge.
Page No -241-
Providing & fixing 1mm thick M.S. door with frame of 40x40x6mm. Angle Iron &
22.03 3mm M.S.Gusset plates at the junction and corners, all necessary fittings
complete, including applying a priming coat of steel primer.
(a) Using M.S angles (40x40x6)mm for diagonal braces
Consider a double leaf door shutter of size 1200x2400mm giving an area
=2x1.20x2.40 = 5.76sqm
Details of cost of M.S. Sheet door of 5.76 sqm area
Description Unit Qty. Rate/Unit Amount
(A) MATERIALS
(i) M.S. Sheet 1mm thick. @ 7.85 kg/ sqm kg 45.216 Add for wastage @ 10% 4.522
49.738
qtl 0.497 4,950.00 2,460.15
Carriage & handling @ 2.5% 61.50
Total (I) = 2,521.65
(ii) Gusset plates 3mm thick Area of one gusset plate 0.30 x 0.04 0.012 1/2 x 0.26 (0.04+0.30) 0.044
sqm 0.056 8 x 0.0562 sqm 0.45 2 x 22/7 x 1/4 x 0.30 x 0.30 sqm 0.141
sqm 0.591 @ 23.55 kg/sqm kg 13.918 Add for wastage @ 10% 1.392
15.31
qtl 0.153 4,628.00 708.08
Carriage & handling @ 2.5% 17.70
Total (II) = 725.78
(iii) Angle Iron 40mm x 40mm x 6mm Sides: 4x2.40 m 9.6 Top & Bottom: 2x2x1.20 m 4.8 Diagonals: 1x2x2.50 m 5
1x2x2.45 m 4.9
m 24.3 Add for wastage @ 10% m 2.43
m 26.73 @ 3.5 kg/Rm kg 93.555
qtl 0.936 6,985.00 6,537.96
Carriage & handling @ 2.5% 163.45
Total (III) = 6,701.41
Page No -242-
(iv) M.S Cleats.
(40x10) mm: 4 x 0.20 m 0.8
Add for wastage @ 25% m 0.2
m 1 @ 3.15 kg/m kg 3.15
qtl 0.032 70.00 2.24
Carriage & handling @ 2.5% 0.06
Total (IV) = 2.30
(v) Pin Clamps (Pintles)
50mm x 6 mm: 4 x 0.45 m 1.8
Add for wastage @ 11% m 0.198
m 1.998
@ 2.35 kg/m kg 4.695
qtl 0.047 4,628.00 217.52
Carriage & handling @ 2.5% 5.44
Total (V) = 222.96
(vi) 20 mm diameter M.S. bar as
pin:
4 x 0.075 m m 0.3
Add for wastage @ 5% m 0.015
m 0.315 @ 2.47 kg/m kg 0.778
qtl 0.008 4,000.00 32.00
Carriage & handling @ 2.5% 0.80
Total (VI) = 32.80
(vii) 1 2mm diameter bolts &
nuts
60 mm long: 4 x 2 each 8
@ 0.183 kg/No kg 1.464
qtl 0.015 10,929.00 163.94
Carriage & handling @ 2.5% 4.10
Total (VII) = 168.04
(viii) 10mm diameter 45 cm
long hooks. each 2 64.29 128.58
(ix) C.C 1:3:6 to fix pin Clamps
= 4 x 0.40 x 0.20 x 0.20 cum 0.064 5,968.30 381.97
(x) C.C 1:2:4 for a block to be
embedded
in floor to keep shutters intact
= 1 x 0.15 x 0.10 x 0.20 cum 0.003 - -
(xi) Locking Arrangement &
Handle each 1 51.43 51.43
Page No -243-
(xii) Priming Coat
M.S.Sheet: 2 x 5.76 sqm 11.52
Angle Iron: 24.30 x 0.16 sqm 3.888
15.408 36.60 563.93
Total (VIII) = 1,125.91
I + II + III + IV + V + VI + VII +
VIII =
(A) 11,500.85
(B) LABOUR
(i) 1st class Fitter each 2 440.00 880.00
(ii) 1st class Blacksmith each 3 440.00 1,320.00
(iii) 2nd class Blacksmith each 4 320.00 1,280.00
(iv) 1st class Mason each 0.06 450.00 27.00
(v) 2nd class Mason each 0.06 320.00 19.20
(vi) Unskilled labour each 5 250.00 1,250.00
(B) 4,776.20
(A) + (B) 16,277.05
Add for Sundries &
Contingencies @ 3%
459.93
(Except on A,B & C )
Add for Water Charges &
Electricity @ 1.5%
229.97
(Except on A,B & C )
Add 5% for Overhead charges
(Except on A,B & C )
766.56
Add 10% for contractor profit
(Except on A,B & C )
1,533.12
Cost of M.S. Sheet door of 5.76
sqm.
19,266.63
Cost per sqm. 3,344.90
Total Cost for 1 Sqm 3,345.00
"C
Page No -244-
SWITCH YARD GRAVELING
23.01 Earthwork in surface excavation and dressing including cutting and filling upto 15 cm
depth, disposal of excavated earth upto 50m and lift upto 1.5m including antiweeds
treatment
Sl. No. Description Unit Rate/Unit Qty. Amount
Details of cost for 100sqm
1001 Labour Skilled-I manday 380.00 1 380.00
1004 Labour Un-skilled manday 220.00 14.29 3,142.86
Total Cost of Labours 3,522.86
Add 15% for overhead & Profit 528.43
Grand Total for 100 qm4,051.29
Total for 1 sqm 40.51
Say 41.00
Supervision (15% on Labour Cost) 6.15
Page No -245-
23.02 Half brick masonry with first class brick in foundation upto one storey above and below
ground level including curing, in cement mortar 1:3 (1 Cement: 3 fine sand) etc.
complete.
in cement mortar 1:3 ( 1 cement : 3 fine sand )
Sl. No. Description Unit Rate/Unit Qty. Amount
Details of cost for 10.0 sqm
2310 1st Class Brick No 21.00 565 11,865.00
2308 Cement mortar 1:3 cum 5,914.40 0.28 1,656.03
Total Cost of Materials 13,521.03
Contingency (2% on Material Cost) 270.42
Sub-Total 13,791.45
Labours
1001 Labour Skilled-I manday 380.00 0.91 345.45
1002 Labour Skilled-II manday 310.00 0.91 281.82
1003 Labour Semi-Skilled manday 250.00 0.91 227.27
1004 Labour Un-skilled manday 220.00 0.91 200.00
Total Cost of Labours 1,054.55
Total 14,846.00
Add 15% for overhead & Profit 2,226.90
Grand Total 17,072.90
Say 17,073.00
Say 1,707.00
Supervision (15% on Labour Cost) 15.82
Cost for 1 sqm
1,707.30
Page No -246-
23.03 Half brick masonry with first class brick in foundation upto one storey above and below
ground level including curing, in cement mortar 1:4 (1 Cement: 4 fine sand) etc.
complete.
in cement mortar 1:4 ( 1 cement : 4 fine sand )
Sl. No. Description Unit Rate/Unit Qty. Amount
Details of cost for 10.0 sqm
2310 1st Class Brick No 21.00 565 11,865.00
2311 Cement mortar 1:4 cum 4,739.50 0.28 1,327.06
Total Cost of Materials 13,192.06
Contingency (2% on Material Cost) 263.84
Sub-Total 13,455.90
Labours
1001 Labour Skilled-I manday 380.00 0.91 345.45
1002 Labour Skilled-II manday 310.00 0.91 281.82
1003 Labour Semi-Skilled manday 250.00 0.91 227.27
1004 Labour Un-skilled manday 220.00 0.91 200.00
Total Cost of Labours 1,054.55
Total 14,510.45
Add 15% for overhead & Profit 2,176.57
Grand Total 16,687.01
Say 16,687.00
Cost 1 sqm
1,668.70
Say 1,669.00
Supervision (15% on Labour Cost) 15.82
Page No -247-
23.04 Providing and laying in position cement concrete of specified grade excluding cost of
centering and shuttering - All work upto plinth level:
1:3:6(1 cement :3 course sand :6 stone aggregate 20mm nominal size)
Sl. No. Description Unit Rate/Unit Qty. Amount
Details of cost for 1.0 cum
2301 Cement cum 13,750.00 0.22 3,025.00
2302 River Sand cum 2,100.00 0.44 924.00
2303 Stone Aggregate 10-20 mcum 1,890.00 0.88 1,663.20
Total Cost of Materials 5,612.20
Contingency (2% on Material Cost) 112.24
Sub-Total 5,724.44
Labours
1001 Labour Skilled-I manday 380.00 0.67 253.33
1003 Labour Semi-Skilled manday 250.00 0.67 166.67
1004 Labour Un-skilled manday 220.00 0.67 146.67
1005 Concrete Mixture 7-
1 0tph Per Hour 270.00 4.00 1,080.00
1006 Niddle Vibrator Per Hour 101.00 4.00 404.00
Total Cost of Labours 1,797.33
Total 1,797.33
Add 15% for overhead & Profit 269.60
Grand Total 2,066.93
Say 2,067.00
Cost 1 cum
2,067.00
Say 2,067.00
Supervision (15% on Labour Cost) 269.60
Page No -248-
Page No -249-
Page No -250-
23.07 12 mm cement plaster of mix 1:4 (1 cement : 4 coarse sand)
Sl. No. Description Unit Rate/Unit Qty. Amount
Details of cost for 10 Sqm
2311 Cement mortar 1:4 cum 4,739.50 0.14 663.53
Total Cost of Materials 663.53
Contingency (2% on Material Cost) 13.27
Sub-Total 676.80
Labours
1001 Labour Skilled-I manday 380.00 1.18 447.06
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 1.18 294.12
1004 Labour Un-skilled manday 220.00 1.18 258.82
Total Cost of Labours 1,000.00
Total 1,676.80
Add 15% for overhead & Profit 251.52
Grand Total 1,928.32
Say 1,928.00
Cost 1 Sqm
192.80
Say 193.00
Supervision (15% on Labour Cost) 15.00
Page No -25 1-
CABLE TRENCH
24.01 Earthwork in excavation in foundation trenches or drains etc. (not exceeding 1 .5m in
width or 10sqm on plan) including dressing of sides and ramming of bottoms, lift upto 1
.5m including getting out excavated soil and disposal of surplus excavated soil as
directed within a lead of 50 metres.
a) Ordinary Soil
Sl. No. Description Unit Rate/Unit Qty. Amount
Details of cost for 10cum
1004 Labour Un-skilled manday 220.00 20.00 4,400.00
Total Cost of Labours 4,400.00
Add 15% for overhead & Profit 660.00
Grand Total 5,060.00
Say 5,060.00
Cost 1 Cum
506.00
Say 506.00
Supervision (15% on Labour Cost) 66.00
b) Hard Soil (Co-efficient of ordinary soil increased by 1.5
Sl. No. Description Unit Rate/Unit Qty. Amount
Details of cost for 10cum
1004 Labour Un-skilled manday 220.00 30 6,600.00
Total Cost of Labours 6,600.00
Add 15% for overhead & Profit 990.00
Grand Total 7,590.00
Say 7,590.00
Cost 1 Cum
759.00
Say 759.00
Supervision (15% on Labour Cost) 99.00
Page No -252-
c) Very Hard Soil (Co-efficient of ordinary soil increased by 2 times)
Sl. No. Description Unit Rate/Unit Qty. Amount
Details of cost for 10cum
1004 Labour Un-skilled manday 220.00 40.00 8,800.00
Total Cost of Labours 8,800.00
Add 15% for overhead & Profit 1,320.00
Grand Total 10,120.00
Say 10,120.00
Cost 1 Cum
1,012.00
Say 1,012.00
Supervision (15% on Labour Cost) 132.00
d) Soft Rock (Blasting Prohibited Works)
Sl. No. Description Unit Rate/Unit Qty. Amount
Details of cost for 10cum
1001 Labour Skilled-I manday 380.00 71.43 27,142.86
1004 Labour Un-skilled manday 220.00 214.29 47,142.86
Total Cost of Labours 74,285.71
Add 15% for overhead & Profit 11,142.86
Grand Total 11,142.86
Say 11,143.00
Cost 1 Cum
1,114.30
Say 1,114.00
Supervision (15% on Labour Cost) 1,114.29
e) Hard Rock (Blasting Prohibited Works)
Sl. No. Description Unit Rate/Unit Qty. Amount
Details of cost for 10cum
1001 Labour Skilled-I manday 380.00 100.00 38,000.00
1004 Labour Un-skilled manday 220.00 300.00 66,000.00
Total Cost of Labours 104,000.00
Add 15% for overhead & Profit 15,600.00
Grand Total 15,600.00
Say 15,600.00
Cost 1 Cum
1,560.00
Say 1,560.00
Supervision (15% on Labour Cost) 1,560.00
Page No -253-
24.02 Half brick masonry with first class brick in foundation upto one storey
above and below ground level including curing, etc. complete. in
cement mortar 1:3 ( 1 cement : 3 fine sand )
Sl. No. Description Unit Rate/Unit Qty. Amount
Details of cost for 10.0 sqm
2310 1st Class Brick No 21.00 565 11,865.00
2308 Cement mortar 1:3 cum 5,914.40 0.28 1,656.03
Total Cost of Materials 13,521.03
Contingency (2% on Material Cost) 270.42
Sub-Total 13,791.45
Labours
1001 Labour Skilled-I manday 380.00 0.91 345.45
1002 Labour Skilled-II manday 310.00 0.91 281.82
1003 Labour Semi-Skilled manday 250.00 0.91 227.27
1004 Labour Un-skilled manday 220.00 0.91 200.00
Total Cost of Labours 1,054.55
TOTAL 14,846.00
Add 15% for overhead & Profit 2,226.90
Grand Total 17,072.90
Say 17,073.00
Say 1,707.00
Supervision (15% on Labour Cost) 15.82
Cost for 1 sqm
1,707.30
Page No -254-
24.03 Half brick masonry with first class brick in foundation upto one storey above and below
ground level including curing, etc. complete.
in cement mortar 1:4 ( 1 cement : 4 fine sand )
Sl. No. Description Unit Rate/Unit Qty. Amount
Details of cost for 10.0 sqm
2310 1st Class Brick No 21.00 565 11,865.00
2311 Cement mortar 1:4 cum 4,739.50 0.28 1,327.06
Total Cost of Materials 13,192.06
Contingency (2% on Material Cost) 263.84
Sub-Total 13,455.90
Labours
1001 Labour Skilled-I manday 380.00 0.91 345.45
1002 Labour Skilled-II manday 310.00 0.91 281.82
1003 Labour Semi-Skilled manday 250.00 0.91 227.27
1004 Labour Un-skilled manday 220.00 0.91 200.00
Total Cost of Labours 1,054.55
TOTAL 14,510.45
Add 15% for overhead & Profit 2,176.57
Grand Total 16,687.01
Say 16,687.00
Say 1,669.00
Supervision (15% on Labour Cost) 15.82
Cost for 1 sqm
1,668.70
Page No -255-
24.04 Providing and laying in position cement concrete of specified grade excluding cost of
centering and shuttering - All work upto plinth level:
1:3:6(1 cement :3 course sand :6 stone aggregate 20mm nominal size)
Sl. No. Description Unit Rate/Unit Qty. Amount
Details of cost for 1.0 cum
2301 Cement cum 13,750.00 0.22 3,025.00
2302 River Sand cum 2,100.00 0.44 924.00
2303 Stone Aggregate 10-
20 mm cum 1,890.00 0.88 1,663.20
Total Cost of Materials 5,612.20
Contingency (2% on Material Cost) 112.24
Sub-Total 5,724.44
Labours
1001 Labour Skilled-I manday 380.00 0.67 253.33
1003 Labour Semi-Skilled manday 250.00 0.67 166.67
1004 Labour Un-skilled manday 220.00 0.67 146.67
1005 Concrete Mixture 7-
1 0tph Per Hour 270.00 4.00 1,080.00
1006 Niddle Vibrator Per Hour 101.00 4.00 404.00
Total Cost of Labours 1,797.33
TOTAL 1,797.33
Add 15% for overhead & Profit 269.60
Grand Total 2,066.93
Say 2,067.00
Say 2,067.00
Supervision (15% on Labour Cost) 269.60
Cost for 1 cum 2,067.00
Page No -256-
24.05 Providing and fixing of Angle Iron (40x40x6mm) for Cable rack including
necessary welding etc complete
Sl. No. Description Unit Rate/Unit Qty. Amount
Details of cost for 1 Cable rack
1403 M.S. Angle Iron
40x40x6 mm kg 105.84 2 211.68
Total Cost of Materials 211.68
Contingency (2% on Material Cost) 4.23
Sub-Total 215.91
Labours
1001 Labour Skilled-I manday 380.00 0.13 47.50
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.13 31.25
1004 Labour Un-skilled manday 220.00 0.13 27.50
Total Cost of Labours 106.25
TOTAL 322.16
Add 15% for overhead & Profit 48.32
Grand Total 370.49
Say 370.00
Say 370.00
Supervision (15% on Labour Cost) 15.94
Cost for 1 rack 370.00
Page No -257-
24.06 12 mm cement plaster of mix 1:4 (1 cement : 4 coarse sand)
Sl. No. Description Unit Rate/Unit Qty. Amount
Details of cost for 10 Sqm
2311 Cement mortar 1:4 cum 4,739.50 0.14 663.53
Total Cost of Materials 663.53
Contingency (2% on Material Cost) 13.27
Sub-Total 676.80
Labours
1001 Labour Skilled-I manday 380.00 1.18 447.06
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 1.18 294.12
1004 Labour Un-skilled manday 220.00 1.18 258.82
Total Cost of Labours 1,000.00
TOTAL 1,676.80
Add 15% for overhead & Profit 251.52
Grand Total 1,928.32
Say 1,928.00
Say 193.00
Supervision (15% on Labour Cost) 15.00
Cost for 1 sqm
192.80
Page No -258-
24.07 Providing and positioning of M.S Flat Chequer Plate 6mm thick
Sl. No. Description Unit Rate/Unit Qty. Amount
Details of cost for 100 Kgs
3209 Chequer Plate 6mm
thick kg 101.00 100 10,100.00
Total Cost of Materials 10,100.00
Contingency (2% on Material Cost) 202.00
Sub-Total 10,302.00
Labours
1001 Labour Skilled-I manday 380.00 0.25 95.00
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.25 62.50
1004 Labour Un-skilled manday 220.00 0.25 55.00
Total Cost of Labours 212.50
TOTAL 10,514.50
Add 15% for overhead & Profit 1,577.18
Grand Total 12,091.68
Say 12,092.00
Say 121.00
Supervision (15% on Labour Cost) 0 .32
Cost for 1 Kg
120.92
Page No -259-
DISMANTLING OF STEEL TUBULAR POLE (SP-17)
101.01 Dismantling of steel tubular pole (SP- 17)
Sl. No. Description Unit Qty.
Materials
1101
Swaged Steel Poles with base
plate of thickness 6mm and
size of200mmx200mm
square welded at the bottom
and with pole cap of 6mm
thick to be welded at the top
con forming to IS 2713/1980
or the latest version thereof
410 SP-17 of overall length
8.50m
No 1.00
Labours
1001 Labour Skilled-I manday 380.00 0.00 0.00
1002 Labour Skilled-II manday 310.00 0.00 0.00
1003 Labour Semi-Skilled manday 250.00 0.00 0.00
1004 Labour Un-skilled manday 220.00 3.42 751.67
Total Cost of Labours 751.67
Total 751.67
Add 15% for overhead & Profit 112.75
Grand Total 864.42
Say 864.00
Supervision (15% on Labour Cost 112.75
Page No -260-
DISMANTLING OF STEEL TUBULAR POLE (SP-29)
101.02 Dismantling of steel tubular pole (SP-29).
Sl. No. Description Unit Qty.
Materials
1 1 02
Swaged Steel Poles with base
plate of thickness 6mm and
size of200mmx200mm
square welded at the bottom
and with pole cap of 6mm
thick to be welded at the top
con forming to IS 27
13/1980 or the latest
version thereof 410 SP-29 of
overall length 9.00m
No 1.00
Labours
1001 Labour Skilled-I manday 380.00 0.00 0.00
1002 Labour Skilled-II manday 310.00 0.00 0.00
1003 Labour Semi-Skilled manday 250.00 0.00 0.00
1004 Labour Un-skilled manday 220.00 5.50 1210.00
Total Cost of Labours 1210.00
Total 1210.00
Add 15% for overhead & Profit 181.50
Grand Total 1391.50
Say 1392.00
Supervision (15% on Labour Cost 181.50
Page No -261-
DISMANTLING OF STEEL TUBULAR POLE (SP-35)
101.03 Dismantling of steel tubular pole (SP-35).
Sl. No. Description Unit Qty.
Materials
1 1 03
Swaged Steel Poles with base
plate of thickness 6mm and
size of200mmx200mm
square welded at the bottom
and with pole cap of 6mm
thick to be welded at the top
con forming to IS 27
13/1980 or the latest
version thereof 410 SP-35 of
overall length 9.50m
No 1.00
Labours
1001 Labour Skilled-I manday 380.00 0.00 0.00
1002 Labour Skilled-II manday 310.00 0.00 0.00
1003 Labour Semi-Skilled manday 250.00 0.00 0.00
1004 Labour Un-skilled manday 220.00 8.00 1760.00
Total Cost of Labours 1760.00
Total 1760.00
Add 15% for overhead & Profit 264.00
Grand Total 2024.00
Say 2024.00
Supervision (15% on Labour Cost 264.00
Page No -262-
DISMANTLING OF STEEL TUBULAR POLE (SP-58)
101.04 Dismantling of steel tubular pole (SP-58).
Sl. No. Description Unit Qty.
Materials
1 1 04
Swaged Steel Poles with base
plate of thickness 6mm and
size of200mmx200mm
square welded at the bottom
and with pole cap of 6mm
thick to be welded at the top
con forming to IS
2713/1980 or the latest
version thereof 410 SP-58 of
overall length 12 .00m
No 1.00
Labours
1001 Labour Skilled-I manday 380.00 0.00 0.00
1002 Labour Skilled-II manday 310.00 0.00 0.00
1003 Labour Semi-Skilled manday 250.00 0.00 0.00
1004 Labour Un-skilled manday 220.00 11.00 2420.00
Total Cost of Labours 2420.00
Total 2420.00
Add 15% for overhead & Profit 363.00
Grand Total 2783.00
Say 2783.00
Supervision (15% on Labour Cost 363.00
Page No -263-
DISMANTLING OF PRE-STRESSED CONCRETE POLE (8.5 m)
101.05 Dismantling of Pre-Stressed Concrete Pole of length 8.5 metres.
Sl. No. Description Unit Qty.
Materials
1 1 05 Pre stressed Concrete Pole:
8.5m No
1.00
Labours
1001 Labour Skilled-I manday 380.00 0.00 0.00
1002 Labour Skilled-II manday 310.00 0.00 0.00
1003 Labour Semi-Skilled manday 250.00 0.00 0.00
1004 Labour Un-skilled manday 220.00 5.50 1210.00
Total Cost of Labours 1210.00
Total 1210.00
Add 15% for overhead & Profit 181.50
Grand Total 1391.50
Say 1392.00
Supervision (15% on Labour Cost 181.50
Page No -264-
DISMANTLING OF PRE-STRESSED CONCRETE POLE (9.75 m)
101.06 Dismantling of Pre-Stressed Concrete Pole of length 9.75 metres.
Sl. No. Description Unit Qty.
Materials
1106 Pre stressed Concrete Pole:
9.75m No 1.00
Labours
1001 Labour Skilled-I manday 380.00 0.00 0.00
1002 Labour Skilled-II manday 310.00 0.00 0.00
1003 Labour Semi-Skilled manday 250.00 0.00 0.00
1004 Labour Un-skilled manday 220.00 6.50 1430.00
Total Cost of Labours 1430.00
Total 1430.00
Add 15% for overhead & Profit 214.50
Grand Total 1644.50
Say 1645.00
Supervision (15% on Labour Cost 214.50
Page No -265-
DISMANTLING OF CROSS ARM
201.01 Dismantling of Horizontal Brackets with MS Angle Iron 40 mm X 40 mm X 6 mm
(3.5Kg per metre) for three phase five wires LT over head line (for SP- 17).
Sl. No. Description Unit Qty.
Materials
1403 M.S. Angle Iron 40x40x6
mm kg
5.89
1405 M.S. Flat Iron 40mmx6 mm kg 1.78
Labours
1001 Labour Skilled-I manday 380.00 0.00 -
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 0.65 143.00
Total Cost of Labours 143.00
Total 143.00
Add 15% for overhead & Profit 21.45
Grand Total 164.45
Say 164.00
Supervision (15% on Labour Cost) 21.45
Page No -266-
DISMANTLING OF CROSS ARM
201.02 Dismantling of Rectangular Brackets with MS Angle Iron 40 mm X 40 mm X 6 mm
(3.5Kg per metre) for three phase five wires LT over head line (for SP-17).
Sl. No. Description Unit Qty.
Materials
1403 M.S. Angle Iron 40x40x6
mm kg
8.55
1405 M.S. Flat Iron 40mmx6 mm kg 1.18
Labours
1001 Labour Skilled-I manday 380.00 0.00 -
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 0.75 165.00
Total Cost of Labours 165.00
Total 165.00
Add 15% for overhead & Profit 24.75
Grand Total 189.75
Say 190.00
Supervision (15% on Labour Cost) 24.75
Page No -267-
DISMANTLING OF CROSS ARM
201.03 Dismantling of Single sided LT bracket with MS Angle Iron 40 mm X 40 mm X 6
mm (3.5Kg per metre) for three phase five wires LT over head line (for SP-17).
Sl. No. Description Unit Qty.
Materials
1 403 M.S. Angle Iron 40x40x6
mm kg
8.96
1405 M.S. Flat Iron 40mmx6 mm kg 6.64
Labours
1001 Labour Skilled-I manday 380.00 0.00 -
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 0.83 183.33
Total Cost of Labours 183.33
Total 183.33
Add 15% for overhead & Profit 27.50
Grand Total 210.83
Say 211.00
Supervision (15% on Labour Cost) 27.50
Page No -268-
DISMANTLING OF CROSS ARM
201.04 Dismantling of Horizontal bracket with MS Angle Iron 40 mm X 40 mm X 6 mm
(3.5Kg per metre) for Single phase three wires LT over head line (for SP-17).
Sl. No. Description Unit Qty.
Materials
1403 M.S. Angle Iron 40x40x6
mm kg
3.93
1405 M.S. Flat Iron 40mmx6 mm kg 1.18
Labours
1001 Labour Skilled-I manday 380.00 0.00 -
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 0.60 132.00
Total Cost of Labours 132.00
Total 132.00
Add 15% for overhead & Profit 19.80
Grand Total 151.80
Say 152.00
Supervision (15% on Labour Cost) 19.80
Page No -269-
DISMANTLING OF CROSS ARM
201.05 Dismantling of Horizontal Brackets with MS Angle Iron 40 mm X 40 mm X 6 mm
(3.5Kg per metre) for three phase five wires LT over head line (for SP-29).
Sl. No. Description Unit Qty.
Materials
1403 M.S. Angle Iron 40x40x6
mm kg
5.89
1405 M.S. Flat Iron 40mmx6 mm kg 2.01
Labours
1001 Labour Skilled-I manday 380.00 0.00 -
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 0.65 143.00
Total Cost of Labours 143.00
Total 143.00
Add 15% for overhead & Profit 21.45
Grand Total 164.45
Say 164.00
Supervision (15% on Labour Cost) 21.45
Page No -270-
DISMANTLING OF CROSS ARM
201.06 Dismantling of Rectangular Brackets with MS Angle Iron 40 mm X 40 mm X 6 mm
(3.5Kg per metre) for three phase five wires LT over head line (for SP-29).
Sl. No. Description Unit Qty.
Materials
1403 M.S. Angle Iron 40x40x6
mm kg
8.55
1405 M.S. Flat Iron 40mmx6 mm kg 1.34
Labours
1001 Labour Skilled-I manday 380.00 0.20 76.00
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 0.40 88.00
Total Cost of Labours 164.00
Total 164.00
Add 15% for overhead & Profit 24.60
Grand Total 188.60
Say 189.00
Supervision (15% on Labour Cost) 24.60
Page No -271-
DISMANTLING OF CROSS ARM
201.07 Dismantling of Single sided LT bracket with MS Angle Iron 40 mm X 40 mm X 6
mm (3.5Kg per metre) for three phase five wires LT over head line (for SP-29).
Sl. No. Description Unit Qty.
Materials
1403 M.S. Angle Iron 40x40x6
mm kg
9.11
1405 M.S. Flat Iron 40mmx6 mm kg 7.04
Labours
1001 Labour Skilled-I manday 380.00 0.00 -
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 0.83 183.33
Total Cost of Labours 183.33
Total 183.33
Add 15% for overhead & Profit 27.50
Grand Total 210.83
Say 211.00
Supervision (15% on Labour Cost) 27.50
Page No -272-
DISMANTLING OF CROSS ARM
201.08 Dismantling of Horizontal bracket with MS Angle Iron 40 mm X 40 mm X 6 mm
(3.5Kg per metre) for Single phase three wires LT over head line (for SP-29).
Sl. No. Description Unit Qty.
Materials
1403 M.S. Angle Iron 40x40x6
mm kg
3.93
1405 M.S. Flat Iron 40mmx6 mm kg 1.34
Labours
1001 Labour Skilled-I manday 380.00 0.00 -
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 0.60 132.00
Total Cost of Labours 132.00
Total 132.00
Add 15% for overhead & Profit 19.80
Grand Total 151.80
Say 152.00
Supervision (15% on Labour Cost) 19.80
Page No -273-
DISMANTLING OF CROSS ARM
201.09 Dismantling of Horizontal Brackets with MS Angle Iron 40 mm X 40 mm X 6 mm (3.5
Kg per metre) for three phase five wires LT over head line (for Pre-Stressed Concrete
8.5 metres).
Sl. No. Description Unit Qty.
Materials
1403 M.S. Angle Iron 40x40x6
mm kg
5.89
1405 M.S. Flat Iron 40mmx6 mm kg 3.14
Labours
1001 Labour Skilled-I manday 380.00 0.00 -
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 0.70 154.00
Total Cost of Labours 154.00
Total 154.00
Add 15% for overhead & Profit 23.10
Grand Total 177.10
Say 177.00
Supervision (15% on Labour Cost) 23.10
Page No -274-
DISMANTLING OF CROSS ARM
201.10 Dismantling of Rectangular Brackets with MS Angle Iron 40 mm X 40 mm X 6 mm (3.5
Kg per metre) for three phase five wires LT over head line conductors (for Pre-Stressed
Concrete 8.5 metres).
Sl. No. Description Unit Qty.
Materials
1403 M.S. Angle Iron 40x40x6
mm kg
8.55
1405 M.S. Flat Iron 40mmx6 mm kg 2.09
Labours
1001 Labour Skilled-I manday 380.00 0.00 -
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 0.80 176.00
Total Cost of Labours 176.00
Total 176.00
Add 15% for overhead & Profit 26.40
Grand Total 202.40
Say 202.00
Supervision (15% on Labour Cost) 26.40
Page No -275-
DISMANTLING OF CROSS ARM
201.11 Dismantling of Single sided Brackets with MS Angle Iron 40 mm X 40 mm X 6 mm (3.5
Kg per metre) for three phase five wires LT over head line (for Pre-Stressed Concrete 8.5
metres).
Sl. No. Description Unit Qty.
Materials
1403 M.S. Angle Iron 40x40x6
mm kg
10.09
1405 M.S. Flat Iron 40mmx6 mm kg 9.39
Labours
1001 Labour Skilled-I manday 380.00 0.00 -
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 1.00 220.00
Total Cost of Labours 220.00
Total 220.00
Add 15% for overhead & Profit 33.00
Grand Total 253.00
Say 253.00
Supervision (15% on Labour Cost) 33.00
Page No -276-
DISMANTLING OF CROSS ARM
201.12 Dismantling of Horizontal Brackets with MS Angle Iron 40 mm X 40 mm X 6 mm (3.5
Kg per metre) for single phase three wires LT over head line (for Pre-Stressed Concrete
8.5 metres).
Sl. No. Description Unit Qty.
Materials
1403 M.S. Angle Iron 40x40x6
mm kg
3.93
1405 M.S. Flat Iron 40mmx6 mm kg 2.09
Labours
1001 Labour Skilled-I manday 380.00 0.00 -
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 0.60 132.00
Total Cost of Labours 132.00
Total 132.00
Add 15% for overhead & Profit 19.80
Grand Total 151.80
Say 152.00
Supervision (15% on Labour Cost) 19.80
Page No -277-
DISMANTLING OF CROSS ARM
201.13 Dismantling of Horizontal Brackets with MS Angle Iron 40 mm X 40 mm X 6 mm (3.5
Kg per metre) for three phase five wires LT over head line (for Pre-Stressed Concrete
9.75 metres).
Sl. No. Description Unit Qty.
Materials
1403 M.S. Angle Iron 40x40x6
mm kg
5.89
1405 M.S. Flat Iron 40mmx6 mm kg 3.37
Labours
1001 Labour Skilled-I manday 380.00 0.00 -
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 0.70 154.00
Total Cost of Labours 154.00
Total 154.00
Add 15% for overhead & Profit 23.10
Grand Total 177.10
Say 177.00
Supervision (15% on Labour Cost) 23.10
Page No -278-
DISMANTLING OF CROSS ARM
201.14 Dismantling of Rectangular Brackets with MS Angle Iron 40 mm X 40 mm X 6 mm (3.5
Kg per metre) for three phase five wires LT over head line (for Pre-Stressed Concrete
9.75 metres).
Sl. No. Description Unit Qty.
Materials
1403 M.S. Angle Iron 40x40x6
mm kg
8.55
1405 M.S. Flat Iron 40mmx6 mm kg 2.25
Labours
1001 Labour Skilled-I manday 380.00 0.00 -
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 0.80 176.00
Total Cost of Labours 176.00
Total 176.00
Add 15% for overhead & Profit 26.40
Grand Total 202.40
Say 202.00
Supervision (15% on Labour Cost) 26.40
Page No -279-
DISMANTLING OF CROSS ARM
201.15 Dismantling of Single sided Brackets with MS Angle Iron 40 mm X 40 mm X 6 mm (3.5
Kg per metre) for three phase five wires LT over head line (for Pre-Stressed Concrete
9.75 metres).
Sl. No. Description Unit Qty.
Materials
1403 M.S. Angle Iron 40x40x6
mm kg
10.33
1405 M.S. Flat Iron 40mmx6 mm kg 9.79
Labours
1001 Labour Skilled-I manday 380.00 0.00 -
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 1.00 220.00
Total Cost of Labours 220.00
Total 220.00
Add 15% for overhead & Profit 33.00
Grand Total 253.00
Say 253.00
Supervision (15% on Labour Cost) 33.00
Page No -280-
DISMANTLING OF CROSS ARM
201.16 Dismantling of Horizontal Brackets with MS Angle Iron 40 mm X 40 mm X 6 mm (3.5
Kg per metre) for single phase three wires LT over head line (for Pre-Stressed Concrete
9.75 metres).
Sl. No. Description Unit Qty.
Materials
1403 M.S. Angle Iron 40x40x6
mm kg
3.93
1405 M.S. Flat Iron 40mmx6 mm kg 2.25
Labours
1001 Labour Skilled-I manday 380.00 0.00 -
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 0.60 132.00
Total Cost of Labours 132.00
Total 132.00
Add 15% for overhead & Profit 19.80
Grand Total 151.80
Say 152.00
Supervision (15% on Labour Cost) 19.80
Page No -28 1-
DISMANTLING OF CROSS ARM
201.17 Dismantling of 2 nos. of MS Channel Iron 75 mm X 40 mm X 6 mm (7.14Kg per
metre) double pole cross arm for three wire 11 kV over head line conductors.
Sl. No. Description Unit Qty.
Materials
1401 M.S. Channel 75 x 40 x 6
mm kg
34.56
1405 M.S. Flat Iron 40mmx6 mm kg 3.16
1 403 M.S. Angle Iron 40x40x6
mm kg
45.94
Labours
1001 Labour Skilled-I manday 380.00 0.00 -
1002 Labour Skilled-II manday 310.00 0.25 77.50
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 1.57 344.67
Total Cost of Labours 422.17
Total 422.17
Add 15% for overhead & Profit 63.33
Grand Total 485.49
Say 485.00
Supervision (15% on Labour Cost) 63.33
Page No -282-
DISMANTLING OF CROSS ARM
201.18 Dismantling of 4 nos. of MS Channel Iron 75 mm X 40 mm X 6 mm (7.14Kg per
metre) double pole cross arm for three wire 11 kV over head line conductors.
Sl. No. Description Unit Qty.
Materials
1 401 M.S. Channel 75 x 40 x 6
mm kg
44.61
1405 M.S. Flat Iron 40mmx6 mm kg 6.32
Labours
1001 Labour Skilled-I manday 380.00 0.00 -
1002 Labour Skilled-II manday 310.00 0.50 155.00
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 3.13 689.33
Total Cost of Labours 844.33
Total 844.33
Add 15% for overhead & Profit 126.65
Grand Total 970.98
Say 971.00
Supervision (15% on Labour Cost) 126.65
Page No -283-
DISMANTLING OF CROSS ARM
201.19 Dismantling of 12 nos. of MS Channel Iron 75 mm X 40 mm X 6 mm (7.14Kg per
metre) triple pole cross arm for three wire 11 kV over head line conductors.
Sl. No. Description Unit Qty.
Materials
1 401 M.S. Channel 75 x 40 x 6
mm kg
1 33.83
1405 M.S. Flat Iron 40mmx6 mm kg 18.97
Labours
1001 Labour Skilled-I manday 380.00 0.00 -
1002 Labour Skilled-II manday 310.00 1.00 310.00
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 10.40 2,288.00
Total Cost of Labours 2,598.00
Total 2,598.00
Add 15% for overhead & Profit 389.70
Grand Total 2,987.70
Say 2,988.00
Supervision (15% on Labour Cost) 389.70
Page No -284-
DISMANTLING OF CROSS ARM
201.20 Dismantling of 16 nos. of MS Channel Iron 75 mm X 40 mm X 6 mm (7.14Kg per
metre) four pole cross arm for three wire 11 kV over head line conductors.
Sl. No. Description Unit Qty.
Materials
1 401 M.S. Channel 75 x 40 x 6
mm kg
1 78.44
1405 M.S. Flat Iron 40mmx6 mm kg 25.29
Labours
1001 Labour Skilled-I manday 380.00 0.00 -
1002 Labour Skilled-II manday 310.00 0.50 155.00
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 12.53 2,757.33
Total Cost of Labours 2,912.33
Total 2,912.33
Add 15% for overhead & Profit (overhead-5% & profit-10%) 436.85
Grand Total 3,349.18
Say 3,349.00
Supervision (15% on Labour Cost) 436.85
Page No -285-
DISMANTLING OF CROSS ARM
201.21 Dismantling of 2 nos. of MS Channel Iron 100 mm X 50 mm X 6 mm (9.56Kg per
metre) double pole cross arm for three wire 33 kV over head line conductors.
Sl. No. Description Unit Qty.
Materials
1402 M.S. Channel 100 x 50 x 6
mm kg
65.41
1405 M.S. Flat Iron 40mmx6 mm kg 3.16
1 403 M.S. Angle Iron 40x40x6
mm kg
57.12
Labours
1001 Labour Skilled-I manday 380.00 0.00 -
1002 Labour Skilled-II manday 310.00 0.25 77.50
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 1.97 432.67
Total Cost of Labours 510.17
Total 510.17
Add 15% for overhead & Profit 76.53
Grand Total 586.69
Say 587.00
Supervision (15% on Labour Cost) 76.53
Page No -286-
DISMANTLING OF CROSS ARM
201.22 Dismantling of 4 nos. of MS Channel Iron 100 mm X 50 mm X 6 mm (9.56Kg per
metre) double pole cross arm for three wire 33 kV over head line conductors.
Sl. No. Description Unit Qty.
Materials
1402 M.S. Channel 100 x 50 x 6
mm kg 78.975
1405 M.S. Flat Iron 40mmx6 mm kg 6.322
Labours
1001 Labour Skilled-I manday 380.00 0.00 -
1002 Labour Skilled-II manday 310.00 0.50 155.00
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 3.33 733.33
Total Cost of Labours 888.33
Total 888.33
Add 15% for overhead & Profit 133.25
Grand Total 1,021.58
Say 1,022.00
Supervision (15% on Labour Cost) 133.25
Page No -287-
DISMANTLING OF CROSS ARM
201.23 Dismantling of 12 nos. of MS Channel Iron 100 mm X 50 mm X 6 mm (9.56Kg per
metre) triple pole cross arm for three wire 33 kV over head line conductors (for SP-
35).
Sl. No. Description Unit Qty.
Materials
1402 M.S. Channel 100 x 50 x 6
mm kg
236.93
1405 M.S. Flat Iron 40mmx6 mm kg 18.97
Labours
1001 Labour Skilled-I manday 380.00 0.00 -
1002 Labour Skilled-II manday 310.00 1.00 310.00
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 12.00 2,640.00
Total Cost of Labours 2,950.00
Total 2,950.00
Add 15% for overhead & Profit 442.50
Grand Total 3,392.50
Say 3,393.00
Supervision (15% on Labour Cost) 442.50
Page No -288-
DISMANTLING OF CROSS ARM
201.24 Dismantling of 16 nos. of MS Channel Iron 100 mm X 50 mm X 6 mm (9.56Kg per
metre) four pole cross arm for three wire 33 kV over head line conductors (for SP-
35).
Sl. No. Description Unit Qty.
Materials
1402 M.S. Channel 100 x 50 x 6
mm kg
315.90
1405 M.S. Flat Iron 40mmx6 mm kg 25.29
Labours
1001 Labour Skilled-I manday 380.00 0.00 -
1002 Labour Skilled-II manday 310.00 0.50 155.00
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 14.67 3,226.67
Total Cost of Labours 3,381.67
Total 3,381.67
Add 15% for overhead & Profit 507.25
Grand Total 3,888.92
Say 3,889.00
Supervision (15% on Labour Cost) 507.25
Page No -289-
DISMANTLING OF COMPLETE SET OF SHACKLE INSULATOR (Pin Type, 1 3 wire)
301.01 Dismantling of shackle insulator for LT over head lines (1 ph 3 wire).
Sl.
No. Description Unit Qty.
Materials
1 806
Shackle Insulator (Pin/Strap
Type) 70x90 mm conforming to
IS : 1445 (1977) or any
amendments up to date
No 3.00
Labours
1001 Labour Skilled-I manday 380.00 0.00 -
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 0.07 16.13
Total Cost of Labours 16.13
Total 16.13
Add 15% for overhead & Profit 2.42
Grand Total 18.55
Say 19.00
Supervision (15% on Labour Cost) 2.42
Page No -290-
DISMANTLING OF COMPLETE SET OF SHACKLE INSULATOR (STRAP TYPE, 1ph
3 wire)
301.02 Dismantling of shackle insulator (strap type) for LT over head lines (1ph
3 wire).
Sl.
No. Description Unit Qty.
Materials
1 806
Shackle Insulator (Pin/Strap
Type) 70x90 mm conforming to
IS : 1445 (1977) or any
amendments up to date
No 6.00
1807 Shackle Strap for 70x90 mm
Shackle Insulator Pair 3.00
Labours
1001 Labour Skilled-I manday 380.00 0.00 -
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 0.07 16.13
Total Cost of Labours 16.13
Total 16.13
Add 15% for overhead & Profit 2.42
Grand Total 18.55
Say 19.00
Supervision (15% on Labour Cost) 2.42
Page No -29 1-
DISMANTLING OF COMPLETE SET OF SHACKLE INSULATOR (Pin Type, 3ph 5
wire)
301.03 Dismantling of shackle insulator for LT over head lines (3ph 5 wire).
Sl.
No. Description Unit Qty.
Materials
1 806
Shackle Insulator (Pin/Strap
Type) 70x90 mm conforming to
IS : 1445 (1977) or any
amendments up to date
No 5.00
Labours
1001 Labour Skilled-I manday 380.00 0.00 -
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 0.07 16.13
Total Cost of Labours 16.13
Total 16.13
Add 15% for overhead & Profit 2.42
Grand Total 18.55
Say 19.00
Supervision (15% on Labour Cost) 2.42
Page No -292-
DISMANTLING OF COMPLETE SET OF SHACKLE INSULATOR (STRAP TYPE, 3ph
5 wire)
301.04 Dismantling of shackle insulator (strap type) for LT over head lines (3ph 5
wire).
Sl.
No. Description Unit Qty.
Materials
1 806
Shackle Insulator (Pin/Strap
Type) 70x90 mm conforming to
IS : 1445 (1977) or any
amendments up to date
No 10.00
1807 Shackle Strap for 70x90 mm
Shackle Insulator Pair 5.00
Labours
1001 Labour Skilled-I manday 380.00 0.00 -
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 0.07 16.13
Total Cost of Labours 16.13
Total 16.13
Add 15% for overhead & Profit 2.42
Grand Total 18.55
Say 19.00
Supervision (15% on Labour Cost) 2.42
Page No -293-
DISMANTLING OF PIN INSULATOR (11kV)
301.05 Dismantling of pin insulator for 11 kV over head lines with galvanised pin, nuts,
washers etc as directed by the engineer in charge.
Sl.
No. Description Unit Qty.
Materials
1805
11kV Pin insulator with GI Pin
conforming IS : 731 (1971), IS :
2486 (1989), IS : 2544 (1973), IS
: 5350 (1973) or any
amendments up to date.
Set 3.00
Labours
1001 Labour Skilled-I manday 380.00 0.00 -
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 0.18 40.33
Total Cost of Labours 40.33
Total 40.33
Add 15% for overhead & Profit 6.05
Grand Total 46.38
Say 46.00
Supervision (15% on Labour Cost) 6.05
Page No -294-
DISMANTLING OF DISC INSULATOR (11kV)
301.06 Dismantling of disc insulator, 45 kN (2 nos. as a set) for 11 kV over head
lines with insulator Dismantlings, ball and socket type and complete with
aluminium alloy tension clamps, bolts, nuts, washers etc as directed by the
engineer in charge.
Sl.
No. Description Unit Qty.
Materials
1801
Porcelain Disc Insulator, 45
kN, conforming IS : 731 (1971),
IS : 2486 (1989), IS : 2544
(1973), IS : 5350 (1973) or any
amendments up to date.
No 2.00
2002
Tension Clamp with hardware
strain fitting, 3-bolted type
complete with bolts, nuts, and
washer (Weasel)
No 1.00
Labours
1001 Labour Skilled-I manday 380.00 0.00 -
1002 Labour Skilled-II manday 310.00 0.05 15.50
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 0.65 144.05
Total Cost of Labours 159.55
Total 159.55
Add 15% for overhead & Profit 23.93
Grand Total 183.48
Say 183.00
Supervision (15% on Labour Cost) 23.93
Page No -295-
DISMANTLING OF PIN INSULATOR (33kV)
301.07 Dismantling of pin insulator for 33 kV over head lines with galvanised pin, nuts,
washers etc as directed by the engineer in charge.
Sl.
No. Description Unit Qty.
Materials
1804
33kV Pin insulator with GI Pin
conforming IS : 731 (1971), IS :
2486 (1989), IS : 2544 (1973), IS
: 5350 (1973) or any
amendments up to date.
Set 3.00
Labours
1001 Labour Skilled-I manday 380.00 0.00 -
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 0.22 48.89
Total Cost of Labours 48.89
Total 48.89
Add 15% for overhead & Profit 7.33
Grand Total 56.22
Say 56.00
Supervision (15% on Labour Cost) 7.33
Page No -296-
DISMANTLING OF DISC INSULATOR (33kV)
301.08 Dismantling of disc insulator, 70 kN (3 nos. as a set) for 33 kV over head
lines with insulator Dismantlings, ball and socket type and complete with
aluminium alloy tension clamps, bolts, nuts, washers etc as directed by the
engineer in charge.
Sl.
No. Description Unit Qty.
Materials
1802
Porcelain Disc Insulator, 70
kN, conforming IS : 731 (1971),
IS : 2486 (1989), IS : 2544
(1973), IS : 5350 (1973) or any
amendments up to date.
No 3.00
2001
Tension Clamp with hardware
strain fitting, 4-bolted type
complete with bolts, nuts, and
washer (Racoon)
No 1.00
Labours
1001 Labour Skilled-I manday 380.00 0.00 -
1002 Labour Skilled-II manday 310.00 0.03 8.16
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 0.76 166.63
Total Cost of Labours 174.78
Total 174.78
Add 15% for overhead & Profit 26.22
Grand Total 201.00
Say 201.00
Supervision (15% on Labour Cost) 26.22
Page No -297-
Dismantling of LT Stay Set
401.01 Dismantling of galvanised stay set for LT over head lines complete with 16 mm rod
dia. with plate 30x30x0.8 cm as directed by the engineer in charge.
Sl.
No. Description Unit Qty.
Materials
1901
G.I. Stay Set complete 16 mm
rod dia. with plate 30x30x0.8
cm conforming to IS : 7887
(1992) or any amendments up
to date.
Set 1.000
1905
Stay wire 7/14 SWG
conforming to IS : 2141 (1979),
IS : 4826 (1979), IS : 6594
(1974) or any amendments up
to date.
kg 1.673
1811
LT Guy insulator (90x65mm)
conforming to IS : 5300 (1969) or
any amendments up to date.
No 1.000
Labours
1001 Labour Skilled-I manday 380.00 0.00 -
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 0.93 205.33
Total Cost of Labours 205.33
Total 205.33
Add 15% for overhead & Profit 30.80
Grand Total 236.13
Say 236.00
Supervision (15% on Labour Cost) 30.80
Page No -298-
Dismantling of 11 kV Stay Set
401.02 Dismantling of galvanised stay set for 11 kV over head lines complete with
19 mm rod dia. with plate 30x30x0.8 cm, 7/12 SWG G.I. stay wire, 11kV
guy insulator (140x85mm) and stay bow as directed by the engineer in
charge.
Sl.
No. Description Unit Qty.
Materials
1902
G.I. Stay set complete 19 mm
rod dia. with plate 30x30x0.8
cm conforming to IS : 7887
(1992) or any amendments up
to date.
Set 1
1904
Stay wire 7/12 SWG
conforming to IS : 2141 (1979),
IS : 4826 (1979), IS : 6594
(1974) or any amendments up
to date.
kg 2.90
1809 11kV Guy insulator
(140x85mm) conforming to IS :
5300 (1969) or any
amendments up to date.
No
1
Labours
1001 Labour Skilled-I manday 380.00 0.00 -
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 1.03 227.33
Total Cost of Labours 227.33
Total 227.33
Add 15% for overhead & Profit 34.10
Grand Total 261.43
Say 261.00
Supervision (15% on Labour Cost) 34.10
Page No -299-
Dismantling of 33 kV Stay Set
401.03 Dismantling of galvanised stay set for 33 kV over head lines complete with
19 mm rod dia. with plate 40x40x0.8 cm ,7/10 SWG G.I. stay wire ,33kV
guy insulator (140x85mm) and stay bow as directed by the engineer in
charge.
Sl.
No. Description Unit Qty.
Materials
1903
G.I. Stay set complete 19 mm
rod dia. with plate 40x40x0.8
cm conforming to IS : 7887
(1992) or any amendments up
to date.
Set 1
1907
Stay wire 7/10 SWG
conforming to IS : 2141 (1979),
IS : 4826 (1979), IS : 6594
(1974) or any amendments up
to date.
kg 5.42
1 81 0
33kV Guy insulator
(1 40x85mm) conforming to IS :
5300 (1969) or any
amendments up to date.
No 1
Labours
1001 Labour Skilled-I manday 380.00 0.00 -
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 1.23 271.33
Total Cost of Labours 271.33
Total 271.33
Add 15% for overhead & Profit 40.70
Grand Total 312.03
Say 312.00
Supervision (15% on Labour Cost) 40.70
Page No -300-
DISMANTLING OF LT LINE
501.01 Dismantling of conductor, jumpering of LT line per conductor per meter using
Gnat conductors as directed by the engineer in charge.
Sl.
No. Description Unit Qty.
Materials
1202
Hard drawn standard
aluminium conductors
conforming to IS 398(Part-I)
with amendment No. 1, 2 and
3 or the latest version thereof
bearing ISI mark :Conductor
AAC,7/2.91 mm Gnat
Km 0.053
2005 P.G. Clamp for Gnat conductor
(2 bolted type) No 2.00
Labours
1001 Labour Skilled-I manday 380.00 0.00 -
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 1.02 223.67
Total Cost of Labours 223.67
Total 223.67
Add 15% for overhead & Profit 33.55
Grand Total 257.22
Say 257.00
Running Metre Cost
Say 5.00
Supervision (15% on Labour Cost) 33.55
Page No -301-
5.14
DISMANTLING OF LT LINE
501.02 Dismantling of conductor, jumpering of LT line per single conductor per meter
using Ant conductors with jungle clearance, as directed by the engineer in
charge.
Sl.
No. Description Unit Qty.
Materials
1201
Hard drawn standard
aluminium conductors
conforming to IS 398(Part-I)
with amendment No. 1, 2 and
3 or the latest version thereof
bearing ISI mark :Conductor
AAC,7/3.10 mm Ant
Km 0.053
2004 P.G. Clamp for Ant conductor
(2 bolted type) No 2
Labours
1001 Labour Skilled-I manday 380.00 0.00 -
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 1.22 267.67
Total Cost of Labours 267.67
Total 267.67
Add 15% for overhead & Profit 40.15
Grand Total 307.82
Say 308.00
Running Metre Cost
Say 6.00
Supervision (15% on Labour Cost) 40.15
Page No -302-
6.16
DISMANTLING OF LT LINE
501.03 Dismantling of conductor, jumpering of LT line per single conductor per meter
using Grasshopper conductors with jungle clearance, as directed by the engineer
in charge.
Sl.
No. Description Unit Qty.
Materials
1203
Hard drawn standard
aluminium conductors
conforming to IS 398(Part-I)
with amendment No. 1, 2 and
3 or the latest version thereof
bearing ISI mark :Conductor,
AAC,7/3.9 1 mm Grasshopper
Km 0.053
2003 P.G. Clamp for Grasshopper
conductor (3 bolted type) No 2
Labours
1001 Labour Skilled-I manday 380.00 0.00 -
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 1.42 311.67
Total Cost of Labours 311.67
Total 311.67
Add 15% for overhead & Profit 46.75
Grand Total 358.42
Say 358.00
Running Metre Cost
Say 7.00
Supervision (15% on Labour Cost) 46.75
Page No -303-
7.16
DISMANTLING OF 11 kV LINE
501.04 Dismantling of conductor, jumpering of 1 1kV line per circuit meter using Weasel
conductors with jungle clearance, as directed by the engineer in charge.
Sl.
No. Description Unit Qty.
Materials
1205
Hard drawn standard
aluminium conductors
galvanized steelwire reinforced
conforming to IS 398(Part-II)
with amendment No. 1, 2 and 3
or the latest version thereof
bearing ISI mark :ACSR
6/1/2.59mm Weasel.
KM 0.378
2006 P.G. Clamp for Weasel
conductor (3 bolted type) No 9
2008 Jointing Sleeve for Weasel
conductor No 6
Labours
1001 Labour Skilled-I manday 380.00 0.00 -
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 7.00 1,540.00
Total Cost of Labours 1,540.00
Total 1,540.00
Add 15% for overhead & Profit 231.00
Grand Total 1,771.00
Say 1,771.00
Say 15.00
Supervision (15% on Labour Cost) 231.00
Running Metre Cost
14.76
Page No -304-
DISMANTLING OF 33 kV LINE
501.05 Dismantling of conductor, jumpering of 33kV line per circuit meter using Racoon
conductors with jungle clearance, as directed by the engineer in charge.
Sl.
No. Description Unit Qty.
Materials
1 204
Hard drawn standard
aluminium conductors
galvanized steelwire reinforced
conforming to IS 398(Part-II)
with amendment No. 1, 2 and 3
or the latest version thereof
bearing ISI mark :ACSR 6/1/4
mm Racoon
Km 0.44 1
2007 P.G. Clamp for Racoon
conductor (3 bolted type) No 9
2009 Jointing Sleeve for Racoon
conductor No 10
Labours
1001 Labour Skilled-I manday 380.00 0.00 -
1002 Labour Skilled-II manday 310.00 0.00 -
1003 Labour Semi-Skilled manday 250.00 0.00 -
1004 Labour Un-skilled manday 220.00 9.00 1,980.00
Total Cost of Labours 1,980.00
Total 1,980.00
Add 15% for overhead & Profit 297.00
Grand Total 2,277.00
Say 2,277.00
Say 16.00
Supervision (15% on Labour Cost) 297.00
Running Metre Cost
16.26
Page No -305-
Labour Analysis
Sl.No. Description Skilled-I Skilled-II Semi-Skill Unskilled Output per Day Day
1. Carriage of conductor up
to motorable site.
380 310 250 220.00 8.00 2 0.50
2 Dismantling of conductor and clamp.
10.00 2 0.50
Total Day Requirement 0.00 0.00 0.00 9.00
0 0 0 1,980.00 1980.00
APPROXIMATE WEIGHT OF MATERIALS
Sl. No. Name of Materials Unit Weight per unit (kg)
1 33kV Circuit Breaker no. 750.00
2 33kV Current Transformer no. 200.00
3 33kV Potential Transformer no. 200.00
4 33kV Isolator no. 200.00
5 33kV Surge Arrestor no. 150.00
6 33kV Control&Relay Panel no. 300.00
7 11kV Indoor Switchboard Panel no. 800.00
8 6.3MVA Power Transformer no. 13,500.00
9 2.5MVA Power Transformer no. 7,090.00
10 1.6MVA Power Transformer no. 5,100.00
Note: The above indicated weights are approximate and shall vary depending upon the
manufacturers
Page No -306-
Page No -307-