sor analysis 2018 - mizoram · sor committee, p&e department government of mizoram mizoram :...

326
For Official use only GOVERNMENT OF MIZORAM POWER & ELECTRICITY DEPARTMENT SOR ANALYSIS 2018

Upload: others

Post on 12-Mar-2020

11 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

For Official use only

GOVERNMENT OF MIZORAM

POWER & ELECTRICITY DEPARTMENT

SOR ANALYSIS

2018

Page 2: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

SOR ANALYSIS : 2018

Published by

Engineer-In-Chief

Power & Electricity Department

Government of Mizoram

Mizoram : Aizawl

Copyright reserved by the publisher

1st Impression : May 2015, Copies : 500

2ndImpression : February 2017 Copies : 500

Layout Design :

SOR Committee, P&E Department

Government of Mizoram

Mizoram : Aizawl

All right reserved. No part of this publication may be reproduced, stored in a

retrieval system or transmitted in any form or by any means, electronic,

mechanical, photocopy, recording or otherwise without the prior permission of

the publisher

Printed at :

Page 3: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

DETAILED

ANALYSIS

(for New Works)

Page 4: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

Sl. No Contents Page No.

1 General Guidelines 5-7

1 Pole Erection 11-13

2 Cross Arm Fitting 14-21

3 Fitting of Disc Insulators 22

4 Stay Set Erection 23-24

5 Conductor Stringing 25-26

6 Earthing 27

7 Fitting of Lightining Spike and Lightning Arresters 28

8 Transformer Installation 29-35

9 Placing of Distribution Transformer 36

10 Laying and Fitting of Cables 37-41

11 Protection of Distribution Transformer 42-44

12 Fencing of Distribution Transformer 45

13 Installation of Meters 46-47

14 Street Lighting 48

15 LT Aerial Bunched Cables 49

16 11 kV Aerial Bunched Cables 50

17 Installation of 33kV equipment 51-52

18 Installation of Power Transformer 53

19 Cabling 54-55

20 Installation of C & R Panel 56

21 Installation of Battery & Charger 57

22 33kV Sub-Station Fencing 58

23 Graveling 59

24 Cable Trench 60

1 Pole Dismantling 63

2 Cross Arm Dismantling 64-66

3 Dismantling of Disc Insulators 67

4 Stay Set Dismantling 68

5 Conductor Dismantling 69

1 Transportation Cost 73-78

2Approximate Unit Weights of Lines and Distribution

Transformers 79-81

3 Drawings 85-135

SCHEDULE - III (Dismantling Works)

SCHEDULE - IV (Misc.)

INDEX

SCHEDULE - I

SCHEDULE - II (New Works)

Page 5: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

Sl. No Items Unit Rate/Unit

1001 Labour Skilled-I manday 380.00

1002 Labour Skilled-II manday 310.00

1003 Labour Semi-Skilled manday 250.00

1004 Labour Un-skilled manday 220.00

1005 Concrete Mixture 7-10tph Per Hour 270.00

1006 Niddle Vibrator Per Hour 101.00

1101

Swaged Steel Pole with base plate of thickness 6mm and

size of 200mmx200mm square welded at the bottom and

with pole cap of 6mm thick to be welded at the top

conforming to IS 2713/1980 or the latest version thereof

410 SP-17 of overall length 8.50m

No 9,011.25

1102

Swaged Steel Pole with base plate of thickness 6mm and

size of 200mmx200mm square welded at the bottom and

with pole cap of 6mm thick to be welded at the top

conforming to IS 2713/1980 or the latest version thereof

410 SP-29 of overall length 9.00m

No 12,656.25

1103

Swaged Steel Pole with base plate of thickness 6mm and

size of 200mmx200mm square welded at the bottom and

with pole cap of 6mm thick to be welded at the top

conforming to IS 2713/1980 or the latest version thereof

410 SP-35 of overall length 9.50m

No 13,061.25

1104

Swaged Steel Pole with base plate of thickness 6mm and

size of 200mmx200mm square welded at the bottom and

with pole cap of 6mm thick to be welded at the top

conforming to IS 2713/1980 or the latest version thereof

410 SP-58 of overall length 12.00m

No 18,832.50

1105 Pre stressed Concrete Pole: 8.5m No 5,828.00

1106 Pre stressed Concrete Pole: 9.75m No 8,190.00

1107

Galvanised Swaged Steel Pole with base plate of

thickness 6mm and size of 200mmx200mm square

welded at the bottom and with pole cap of 6mm thick to

be welded at the top conforming to IS 2713/1980 or the

latest version thereof 410 SP-17 of overall length 8.50m

No 13,233.00

1108

Galvanised Swaged Steel Pole with base plate of

thickness 6mm and size of 200mmx200mm square

welded at the bottom and with pole cap of 6mm thick to

be welded at the top conforming to IS 2713/1980 or the

latest version thereof 410 SP-29 of overall length 9.00m

No 17,640.00

1109

Galvanised Swaged Steel Pole with base plate of

thickness 6mm and size of 200mmx200mm square

welded at the bottom and with pole cap of 6mm thick to

be welded at the top conforming to IS 2713/1980 or the

latest version thereof 410 SP-35 of overall length 9.50m

No 19,179.00

BASIC AND TRANSPORTATION RATES

Page 1 of 15

Page 6: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

Sl. No Items Unit Rate/Unit

1110

Galvanised Swaged Steel Poles with base plate of

thickness 6mm and size of 200mmx200mm square

welded at the bottom and with pole cap of 6mm thick to

be welded at the top con forming to IS 2713/1980 or the

latest version thereof 410 SP-58 of overall length

12.00m

No 27,654.00

1201

Hard drawn standard aluminium conductors

conforming to IS 398(Part-I) with amendment No. 1, 2

and 3 or the latest version thereof bearing ISI mark

:Conductor AAC,7/3.10 mm Ant

Km 59,881.00

1202

Hard drawn standard aluminium conductors

conforming to IS 398(Part-I) with amendment No. 1, 2

and 3 or the latest version thereof bearing ISI mark

:Conductor AAC,7/2.91 mm Gnat

Km 31,889.00

1203

Hard drawn standard aluminium conductors

conforming to IS 398(Part-I) with amendment No. 1, 2

and 3 or the latest version thereof bearing ISI mark

:Conductor, AAC,7/3.91 mm Grasshopper

Km 89,420.00

1204

Hard drawn standard aluminium conductors galvanized

steelwire reinforced conforming to IS 398(Part-II) with

amendment No. 1, 2 and 3 or the latest version thereof

bearing ISI mark :ACSR 6/1/4 mm Racoon

Km 85,049.00

1205

Hard drawn standard aluminium conductors galvanized

steelwire reinforced conforming to IS 398(Part-II) with

amendment No. 1, 2 and 3 or the latest version thereof

bearing ISI mark :ACSR 6/1/2.59mm Weasel.

KM 33,399.00

1301

Out door type oil immersed naturally cooled 3-ph, 50Hz

Al-wound Distribution Transformer of vector group DYn-

11 conforming to IS : 1180 (1964) and IS : 2026 (1962)

or latest version thereof and ISI marked of the following

capacity 25 kVA 11/0.415 kV

No 68,850.00

1302

Out door type oil immersed naturally cooled 3-ph, 50Hz

Al-wound Distribution Transformer of vector group DYn-

11 conforming to IS : 1180 (1964) and IS : 2026 (1962)

or latest version thereof and ISI marked of the following

capacity 63 kVA 11/0.415 kV

No 1,22,850.00

1303

Out door type oil immersed naturally cooled 3-ph, 50Hz

Al-wound Distribution Transformer of vector group DYn-

11 conforming to IS : 1180 (1964) and IS : 2026 (1962)

or latest version thereof and ISI marked of the following

capacity 100 kVA 11/0.415 kV

No 1,79,887.50

Page 2 of 15

Page 7: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

Sl. No Items Unit Rate/Unit

1304

Out door type oil immersed naturally cooled 3-ph, 50Hz

Cu-wound Distribution Transformer of vector group DYn-

11 with tap changer conforming to IS : 1180 (1964) and

IS : 2026 (1962) or latest version thereof and ISI

marked of the following capacity 250 kVA 11/0.415 kV

No 3,75,300.00

1305

Out door type oil immersed naturally 3-ph, 10Hz Cu-

wound Distribution Transformer of vector group DYn-11

with tap changer and air breather with first filling oil

conforming to IS : 1180 (1964) and IS : 2026 (1962) or

latest version thereof and ISI marked of the following

capacity 500 kVA 11/0.415 kV

No 10,10,515.50

1306

Out door type oil immersed naturally 3-ph, 10Hz Cu-

wound Distribution Transformer of vector group DYn-11

with tap changer conforming to IS : 1180 (1964) and IS :

2026 (1962) or latest version thereof and ISI marked of

the following capacity 630 kVA 11/0.415 kV

No 10,99,575.00

1307

Out door type oil immersed naturally 3-ph, 10Hz Cu-

wound Distribution Transformer of vector group DYn-11

with tap changer conforming to IS : 1180 (1964) and IS :

2026 (1962) or latest version thereof and ISI marked of

the following capacity 750 kVA 11/0.415 kV

No 12,15,000.00

1308

Out door type oil immersed naturally cooled 3-ph, 50Hz

Cu-wound Distribution Transformer of vector group DYn-

11 with tap changer conforming to IS : 1180 (1964) and

IS : 2026 (1962) or latest version thereof and ISI

marked of the following capacity 1000 kVA 11/0.415 kV

No 17,71,875.00

1309

100kVA, 11/0.415 kV, Dyn11 CSS Transformer with off

circuit tap of rating +5 to-5 @ 2.5% comprising of

a) HT Switchgear: 11kV, 200A, Air Insulated Switchgear

consisting of Load Break Switchand Fuse for protection

of transformer, Interconnection between HTswitchgear

and transformer shall be using 1Cx3x25 sq.mm

Al.unarmorured XLPE Cable. The system includes HT &

LT metering components.

b) LT Switchboard: 250A 3P 36kA Fixed Manual MCCB

with Microprocessor based O/C, E/F, S/C release as

incomer cum outgoing.

No 19,51,000.00

Page 3 of 15

Page 8: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

Sl. No Items Unit Rate/Unit

1310

160kVA, 11/0.415 kV, Dyn11 CSS Transformer with off

circuit tap of rating +5 to-5 @ 2.5% comprising of

a) HT Switchgear: 11kV, 200A, Air Insulated Switchgear

consisting of Load Break Switchand Fuse for protection

of transformer, Interconnection between HTswitchgear

and transformer shall be using 1Cx3x25 sq.mm

Al.unarmorured XLPE Cable. The system includes HT &

LT metering components.

b) LT Switchboard: 250A 3P 36kA Fixed Manual MCCB

with Microprocessor based O/C, E/F, S/C release as

incomer cum outgoing.

No 23,80,000.00

1311

200kVA, 11/0.415 kV, Dyn11 CSS Transformer with off

circuit tap of rating +5 to-5 @ 2.5% comprising of

a) HT Switchgear: 11kV, 200A, Air Insulated Switchgear

consisting of Load Break Switchand Fuse for protection

of transformer, Interconnection between HTswitchgear

and transformer shall be using 1Cx3x25 sq.mm

Al.unarmorured XLPE Cable. The system includes HT &

LT metering components.

b) LT Switchboard: 320A 3P 36kA Fixed Manual MCCB

with Microprocessor based O/C, E/F, S/C release as

incomer cum outgoing.

No 26,75,000.00

1312

250kVA, 11/0.415 kV, Dyn11 with off circuit tap of

rating +5 to-5 @ 2.5% comprising of

a) HT Switchgear: 11kV,630A,21KA for 3sec, SF6

insulated Non-Extinsible Compact switchgear (Type DV)

consisting of one No. Direct Switch and One No. Fixed

Manual Vacuum Circuit Breaker in SF6 with insulated

stainless steel enclosure, with series trip, self powered

microprocessor based numerical relay for over current

and earth fault (IDMTL + Inst.) protection.

Interconnection between HT switchgear and transformer

shall be using 1Cx3x25 sq.mm Al. unarmorured XLPE

Cable. The systemincludes HT & LT metering

components

b) LT Switchboard: 400A 3P 36kA Fixed Manual MCCB

with Microprocessor based O/C, E/F, S/C release as

incomer cum outgoing.

No 29,40,600.00

Page 4 of 15

Page 9: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

Sl. No Items Unit Rate/Unit

1313

315kVA, 11/0.415 kV, Dyn11 with off circuit tap of

rating +5 to-5 @ 2.5% comprising of

a) HT Switchgear: 11kV,630A,21KA for 3sec, SF6

insulated Non-Extinsible Compact switchgear (Type DV)

consisting of one No. Direct Switch and One No. Fixed

Manual Vacuum Circuit Breaker in SF6 with insulated

stainlesssteel enclosure, with series trip, self powered

microprocessor based numerical relay for over current

and earth fault (IDMTL + Inst.) protection.

Interconnection between HT switchgear and

transformershall be using 1Cx3x25 sq.mm Al.

unarmorured XLPE Cable. The system includes HT & LT

metering components

b) LT Switchboard: 630A 3P 36kA Fixed Manual MCCB

with Microprocessor based O/C, E/F, S/C release as

incomer cum outgoing.

No 34,50,800.00

1314

400kVA, 11/0.415 kV, Dyn11 with off circuit tap of

rating +5 to-5 @ 2.5% comprising of

a) HT Switchgear: 11kV,630A,21KA for 3sec, SF6

insulated Non-Extinsible Compact switchgear (Type DV)

consisting of one No. Direct Switch and One No. Fixed

Manual Vacuum Circuit Breaker in SF6 with insulated

stainlesssteel enclosure, with series trip, self powered

microprocessor based numerical relay for over current

and earth fault (IDMTL + Inst.) protection.

Interconnection between HT switchgear and

transformershall be using 1Cx3x25 sq.mm Al.

unarmorured XLPE Cable. The system includes HT & LT

metering components

b) LT Switchboard: 630A 3P 36kA Fixed Manual ACCB

with Microprocessor based O/C, E/F, S/C release as

incomer cum outgoing.

No 37,45,000.00

1315

500kVA, 11/0.415 kV, Dyn11 with off circuit tap of

rating +5 to-5 @ 2.5% comprising of

a) HT Switchgear: 11kV,630A,21KA for 3sec, SF6

insulated Non-Extinsible Compact switchgear (Type DV)

consisting of one No. Direct Switch and One No. Fixed

Manual Vacuum Circuit Breaker in SF6 with insulated

stainlesssteel enclosure, with series trip, self powered

microprocessor based numerical relay for over current

and earth fault (IDMTL + Inst.) protection.

Interconnection between HT switchgear and

transformershall be using 1Cx3x25 sq.mm Al.

unarmorured XLPE Cable. The system includes HT & LT

metering components

b) LT Switchboard: 800A 3P 50kA Fixed Manual ACB

with Microprocessor based O/C, E/F, S/C release as

incomer cum outgoing.

No 39,80,400.00

Page 5 of 15

Page 10: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

Sl. No Items Unit Rate/Unit

1316

630kVA, 11/0.415 kV, Dyn11 with off circuit tap of

rating +5 to-5 @ 2.5% comprising of

a) HT Switchgear: 11kV,630A,21KA for 3sec, SF6

insulated Non-Extinsible Compact switchgear (Type DV)

consisting of one No. Direct Switch and One No. Fixed

Manual Vacuum Circuit Breaker in SF6 with insulated

stainlesssteel enclosure, with series trip, self powered

microprocessor based numerical relay for over current

and earth fault (IDMTL + Inst.) protection.

Interconnection between HT switchgear and

transformershall be using 1Cx3x25 sq.mm Al.

unarmorured XLPE Cable. The system includes HT & LT

metering components

b) LT Switchboard: 1000A 3P 50kA Fixed Manual ACB

with Microprocessor based O/C, E/F, S/C release as

incomer cum outgoing.

No 47,50,500.00

1317

750kVA, 11/0.415 kV, Dyn11 with off circuit tap of

rating +5 to-5 @ 2.5% comprising of

a) HT Switchgear: 11kV,630A,21KA for 3sec, SF6

insulated Non-Extinsible Compact switchgear (Type DV)

consisting of one No. Direct Switch and One No. Fixed

Manual Vacuum Circuit Breaker in SF6 with insulated

stainlesssteel enclosure, with series trip, self powered

microprocessor based numerical relay for over current

and earth fault (IDMTL + Inst.) protection.

Interconnection between HT switchgear and

transformershall be using 1Cx3x5 sq.mm Al.

unarmorured XLPE Cable. The system includes HT & LT

metering components

b) LT Switchboard: 1250A 3P 50kA Fixed Manual ACB

with Microprocessor based O/C, E/F, S/C release as

incomer cum outgoing.

No 49,30,900.00

1318

990/1000kVA, 11/0.415 kV, Dyn11 with off circuit tap

of rating +5 to-5 @ 2.5% comprising of

a) HT Switchgear: 11kV,630A,21KA for 3sec, SF6

insulated Non-Extinsible Compact switchgear (Type DV)

consisting of one No. Direct Switch and One No. Fixed

Manual Vacuum Circuit Breaker in SF6 with insulated

stainlesssteel enclosure, with series trip, self powered

microprocessor based numerical relay for over current

and earth fault (IDMTL + Inst.) protection.

Interconnection between HT switchgear and

transformershall be using 1Cx3x25 sq.mm Al.

unarmorured XLPE Cable. The system includes HT & LT

metering components

b) LT Switchboard: 1600A 3P 50kA Fixed Manual ACB

with Microprocessor based O/C, E/F, S/C release as

incomer cum outgoing.

No 55,68,000.00

1401 M.S. Channel 75 x 40 x 6 mm kg 105.84

1402 M.S. Channel 100 x 50 x 6 mm kg 105.84

1403 M.S. Angle Iron 40x40x6 mm kg 105.84

1404 M.S. Angle Iron 50x50x6 mm kg 105.84

Page 6 of 15

Page 11: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

Sl. No Items Unit Rate/Unit

1405 M.S. Flat Iron 40mmx6 mm kg 105.84

1406 M.S. Angle Iron 20x20x4 mm Kg 105.84

1407 M.S. Flat Iron 20x3 mm Kg 105.84

1501Lightning Arrester 9kV, 10kA Station Class-II as per

IEC:60099-4 & IS:3070 specificationNo 12,500.00

1502 Lightning Arrester 9 kV, 5 KA No 1,875.00

1503 Lightning Arrester 0.280 kV, 2.5 KA for LT Line No 657.00

1601

1.1 kV Aluminium Armoured Cable 1 core, 10 sq.mm

conforming to IS : 1554-1 (1988) or any ammendments m 87.00

1602

1.1 kV Aluminium Armoured Cable 1 core, 16 sq.mm

conforming to IS : 1554-1 (1988) or any ammendments m 102.00

1603

1.1 kV Aluminium Armoured Cable 1 core, 35 sq.mm

conforming to IS : 1554-1 (1988) or any ammendments m 147.00

1604

1.1 kV Aluminium Armoured Cable 1 core, 50 sq.mm

conforming to IS : 1554-1 (1988) or any ammendments m 191.00

1605

1.1 kV Aluminium Armoured Cable 1 core, 70 sq.mm

conforming to IS : 1554-1 (1988) or any ammendments m 225.00

1606

1.1 kV Aluminium Armoured Cable 1 core, 95 sq.mm

conforming to IS : 1554-1 (1988) or any ammendments m 278.00

1607

1.1 kV Aluminium Armoured Cable 1 core, 120 sq.mm

conforming to IS : 1554-1 (1988) or any ammendments m 375.00

1608

1.1 kV Aluminium Armoured Cable 1 core, 150 sq.mm

conforming to IS : 1554-1 (1988) or any ammendments m 525.00

1609

1.1 kV Aluminium Armoured Cable 1 core, 185 sq.mm

conforming to IS : 1554-1 (1988) or any ammendments m 585.00

1610

1.1 kV Aluminium Armoured Cable 1 core, 225 sq.mm

conforming to IS : 1554-1 (1988) or any ammendments m 772.00

1611

1.1 kV Aluminium Armoured Cable 1 core, 300 sq.mm

conforming to IS : 1554-1 (1988) or any ammendments m 960.00

1612

1.1 kV Aluminium Armoured Cable 1 core,400 sq.mm

conforming to IS : 1554-1 (1988) or any ammendments m 1,035.00

1613

1.1 kV Aluminium Armoured Cable 1 core, 630 sq.mm

conforming to IS : 1554-1 (1988) or any ammendments m 1,650.00

1614

PVC Insulated Aluminium Cable, 2.5 sq.mm, 2 Core,

conforming to IS : 1554-1 (1988), IS : 5831 (1984) or

any ammendments there of.

m 20.00

Page 7 of 15

Page 12: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

Sl. No Items Unit Rate/Unit

1615

PVC Insulated Aluminium Cable, 4 sq.mm, 2 Core,

conforming to IS : 1554-1 (1988), IS : 5831 (1984) or

any ammendments there of.

m 30.00

1616

PVC Insulated Aluminium Cable, 6 sq.mm, 2 Core,

conforming to IS : 1554-1 (1988), IS : 5831 (1984) or

any ammendments there of.

m 45.00

1617

PVC Insulated Aluminium Cable, 10 sq.mm, 2 Core,

conforming to IS : 1554-1 (1988), IS : 5831 (1984) or

any ammendments there of.

m 72.00

1618

PVC Insulated Aluminium Cable, 16 sq.mm, 2 Core,

conforming to IS : 1554-1 (1988), IS : 5831 (1984) or

any ammendments there of.

m 130.00

1619

PVC Insulated Aluminium Cable, 25 sq.mm, 2 Core,

conforming to IS : 1554-1 (1988), IS : 5831 (1984) or

any ammendments there of.

m 210.00

1620

PVC Insulated Aluminium Cable, 35 sq.mm, 2 Core,

conforming to IS : 1554-1 (1988), IS : 5831 (1984) or

any ammendments there of.

m 310.00

1621 PVC Insulated Copper Cable, 1.0 sq.mm m 30.00

1622 PVC Insulated Copper Cable, 1.5 sq.mm m 39.00

1623 PVC Insulated Copper Cable, 2.5 sq.mm m 67.50

1624 PVC Insulated Copper Cable, 4.0 sq.mm m 90.00

1625 PVC Insulated Copper Cable, 6.0 sq.mm m 127.50

1626 PVC Insulated Copper Cable, 10.0 sq.mm m 270.00

1627

1.1 kV Copper Control Cable, 2.5 sq.mm, 16 Core,

conforming to IS : 1554-1 (1988) or any amendments

there of.

m 575.00

1628

1.1 kV Copper Control Cable, 2.5 sq.mm, 12 Core,

conforming to IS : 1554-1 (1988) or any amendments

there of.

m 444.00

1629

1.1 kV Copper Control Cable, 2.5 sq.mm, 6 Core,

conforming to IS : 1554-1 (1988) or any amendments

there of.

m 174.00

1630

1.1 kV Copper Control Cable, 2.5 sq.mm, 4 Core,

conforming to IS : 1554-1 (1988) or any amendments

there of.

m 122.00

1631

1.1 kV Copper Control Cable, 2.5 sq.mm, 2 Core,

conforming to IS : 1554-1 (1988) or any amendments

there of.

m 96.00

1632 3 Core, 11kV XLPE Aluminium Cable, 185 sq.mm m 2,819.00

1633 3 Core, 11kV XLPE Aluminium Cable, 150 sq.mm m 2,323.00

1634 3 Core, 11kV XLPE Aluminium Cable, 120 sq.mm m 1,628.00

1635 11kV XLPE Aluminium Cable, 1 Core, 600 sq.mm m 4,000.00

1636 11kV XLPE Aluminium Cable, 1 Core, 400 sq.mm m 2,035.00

1637 11kV XLPE Aluminium Cable, 1 Core, 240 sq.mm m 1,201.00

1638 11kV XLPE Aluminium Cable, 1 Core, 185 sq.mm m 1,159.00

1639 11kV XLPE Aluminium Cable, 1 Core, 150 sq.mm m 1,138.00

1640 11kV XLPE Aluminium Cable, 1 Core, 120 sq.mm m 1,100.00

1641 11kV XLPE Aluminium Cable, 1 Core, 100 sq.mm m 1,083.00

1642 11kV XLPE Aluminium Cable, 1 Core, 95 sq.mm m 1,024.00

1643 PVC Insulated Copper Cable, 35.0 sq.mm m 550.00

1701 Aluminium Cable Lug long barrel , 10 Sq.mm No 5.00

Page 8 of 15

Page 13: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

Sl. No Items Unit Rate/Unit

1702 Aluminium Cable Lug long barrel , 16 Sq.mm No 8.00

1703 Aluminium Cable Lug long barrel , 35 Sq.mm No 12.00

1704 Aluminium Cable Lug long barrel , 50 Sq.mm No 15.00

1705 Aluminium Cable Lug long barrel , 70Sq.mm No 30.00

1706 Aluminium Cable Lug long barrel , 95 Sq.mm No 35.00

1707 Aluminium Cable Lug long barrel , 120 Sq.mm No 42.00

1708 Aluminium Cable Lug long barrel , 150 Sq.mm No 53.00

1709 Aluminium Cable Lug long barrel , 185 Sq.mm No 68.00

1710 Aluminium Cable Lug long barrel , 225 Sq.mm No 83.00

1711 Aluminium Cable Lug long barrel , 300 Sq.mm No 115.00

1712 Aluminium Cable Lug long barrel , 400 Sq.mm No 165.00

1713 Aluminium Cable Lug long barrel , 630Sq.mm No 188.00

1714 T-Connector for 300 sq.mm Cable No 1,600.00

1715 T-Connector for 400 sq.mm Cable No 1,760.00

1716 T-Connector for 630 sq.mm Cable No 1,936.00

1717 Copper Cable Lug, Ring/Fork/Pin type, 2.5 sq.mm No 27.00

1718 Cable Ferrule, 2.5 sq.mm [A-Z] 100 each Packet 2,340.00

1719 Cable Ferrule, 2.5 sq.mm [0-9] 100 each Packet 900.00

1801

Porcelain Disc Insulator, 45 kN, conforming IS : 731

(1971), IS : 2486 (1989), IS : 2544 (1973), IS : 5350

(1973) or any amendments up to date.

No 519.00

1802

Porcelain Disc Insulator, 70 kN, conforming IS : 731

(1971), IS : 2486 (1989), IS : 2544 (1973), IS : 5350

(1973) or any amendments up to date.

No 700.00

1803

Porcelain Disc Insulator, 90 kN, conforming IS : 731

(1971), IS : 2486 (1989), IS : 2544 (1973), IS : 5350

(1973) or any amendments up to date.

No 959.44

1804

33kV Pin insulator with GI Pin conforming IS : 731

(1971), IS : 2486 (1989), IS : 2544 (1973), IS : 5350

(1973) or any amendments up to date.

Set 894.00

1805

11kV Pin insulator with GI Pin conforming IS : 731

(1971), IS : 2486 (1989), IS : 2544 (1973), IS : 5350

(1973) or any amendments up to date.

Set 354.00

1806

Shackle Insulator (Pin/Strap Type) 70x90 mm

conforming to IS : 1445 (1977) or any amendments up

to date

No 39.00

1807 Shackle Strap for 70x90 mm Shackle Insulator Pair 14.00

1808 Shackle Nut Bolt 12x100 mm(GI) kg 174.96

180911kV Guy insulator (140x85mm) conforming to IS :

5300 (1969) or any amendments up to date.No 57.00

181033kV Guy insulator (140x85mm) conforming to IS :

5300 (1969) or any amendments up to date.No 57.00

1811LT Guy insulator (90x65mm) conforming to IS : 5300

(1969) or any amendments up to date.No 28.50

1901

G.I. Stay Set complete 16 mm rod dia. with plate

30x30x0.8 cm conforming to IS : 7887 (1992) or any

amendments up to date.

Set 810.00

1902

G.I. Stay set complete 19 mm rod dia. with plate

30x30x0.8 cm conforming to IS : 7887 (1992) or any

amendments up to date.

Set 1,407.00

Page 9 of 15

Page 14: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

Sl. No Items Unit Rate/Unit

1903

G.I. Stay set complete 19 mm rod dia. with plate

40x40x0.8 cm conforming to IS : 7887 (1992) or any

amendments up to date.

Set 1,694.00

1904

Stay wire 7/12 SWG conforming to IS : 2141 (1979), IS :

4826 (1979), IS : 6594 (1974) or any amendments up to

date.

kg 112.50

1905

Stay wire 7/14 SWG conforming to IS : 2141 (1979), IS :

4826 (1979), IS : 6594 (1974) or any amendments up to

date.

kg 118.50

1906

G.I Wire 8 SWG for earth wire conforming to IS : 280

(1978), IS : 7887 (1992) or any amendments up to date. kg 112.50

1907

Stay wire 7/10 SWG conforming to IS : 2141 (1979), IS :

4826 (1979), IS : 6594 (1974) or any amendments up to

date.

kg 116.00

2001

Tension Clamp with hardware strain fitting, 4-bolted

type complete with bolts, nuts, and washer (Racoon) No 474.00

2002

Tension Clamp with hardware strain fitting, 3-bolted

type complete with bolts, nuts, and washer (Weasel) No 445.00

2003P.G. Clamp for Grasshopper conductor (3 bolted type)

No 82.00

2004 P.G. Clamp for Ant conductor (2 bolted type) No 79.00

2005 P.G. Clamp for Gnat conductor (2 bolted type) No 72.00

2006 P.G. Clamp for Weasel conductor (3 bolted type) No 75.00

2007 P.G. Clamp for Racoon conductor (3 bolted type) No 112.50

2008 Jointing Sleeve for Weasel conductor No 265.00

2009 Jointing Sleeve for Racoon conductor No 354.00

2010 LT Cable Jointing Kit No 2,770.00

2011Cable Gland for 2.5 sq.mm, 16 Core Copper Control

CableNo 52.50

2012Cable Gland for 2.5 sq.mm, 12 Core Copper Control

CableNo 52.50

2013Cable Gland for 2.5 sq.mm, 6 Core Copper Control

CableNo 52.50

2014Cable Gland for 2.5 sq.mm, 4 Core Copper Control

CableNo 45.00

2015Cable Gland for 2.5 sq.mm, 2 Core Copper Control

CableNo 45.00

2016Cable Jointing Kit for 3 Core, 11kV XLPE Al. Cable, 185

sq.mm No 4,550.00

2017Cable Jointing Kit for 3 Core, 11kV XLPE Al. Cable, 150

sq.mm No 4,550.00

2018Cable Jointing Kit for 3 Core, 11kV XLPE Al. Cable, 120

sq.mm No 4,550.00

2019Cable Jointing Kit for 1 Core, 11kV XLPE Al. Cable,

1000 sq.mm No 15,000.00

2020Cable Jointing Kit for 1 Core, 11kV XLPE Al. Cable, 600

sq.mm No 13,500.00

2021Cable Jointing Kit for 1 Core, 11kV XLPE Al. Cable, 400

sq.mm No 9,200.00

Page 10 of 15

Page 15: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

Sl. No Items Unit Rate/Unit

2022Cable Jointing Kit for 1 Core, 11kV XLPE Al. Cable, 240

sq.mm No 4,970.00

2023Cable Jointing Kit for 1 Core, 11kV XLPE Al. Cable, 185

sq.mm No 4,550.00

2024Cable Jointing Kit for 1 Core, 11kV XLPE Al. Cable, 150

sq.mm No 4,550.00

2025Cable Jointing Kit for 1 Core, 11kV XLPE Al. Cable, 120

sq.mm No 4,550.00

2026Cable Jointing Kit for 1 Core, 11kV XLPE Al. Cable, 100

sq.mm No 4,450.00

2027Cable Jointing Kit for 1 Core, 11kV XLPE Al. Cable, 95

sq.mm No 4,450.00

2101

M.S. Nut & Bolt 16x75 mm full thread conforming to IS :

1364-2 (1992) or any amendments up to date. kg 162.00

2102

M.S. Nut & Bolt 16x50 mm full thread conforming to IS :

1364-2 (1992) or any amendments up to date. kg 162.00

2103

M.S. Nut & Bolt 16 x 155 mm full thread conforming to

IS : 1364-2 (1992) or any amendments up to date. kg 162.00

2104

M.S. Nut & Bolt 16 x 125 mm, Full thread conforming to

IS : 1364-2 (1992) or any amendments up to date. kg 162.00

2105

M.S. Nut & Bolt 16 x 175 mm, Full thread conforming to

IS : 1364-2 (1992) or any amendments up to date. kg 162.00

2106

M.S. Nut & Bolt 12 x 50 mm, Full thread conforming to

IS : 1364-2 (1992) or any amendments up to date. kg 162.00

2107

M.S. Washer for 16 mm diameter hole conforming to IS :

1364-2 (1992) or any amendments up to date. kg 132.00

2108

M.S. Nut & Bolt 16x50 mm full thread conforming to IS :

1364-2 (1992) or any amendments up to date. kg 162.00

2109 Brass Nuts & Bolt 16 x 50mm full tread Kg 250.00

2201 Aluminium Paint Lit 170.00

2202 Bituminious Alkali Paint Lit 120.00

2203 Red Oxide Paint Lit 125.00

2301 Cement cum 13,750.00

2302 River Sand cum 2,100.00

2303 Stone Aggregate 10-20 mm cum 1,890.00

2304GCI Sheet, 6 x 3 ft. conforming to IS : 277 (2003) or any

amendments up to date.No 375.00

2305 First class brick 203 x 101 x 76.2 mm No 20.00

2305 Bentonite Powder kg 30.00

2307 Binding wire kg 120.00

2308 Stone Masonry (8x5x5 inch) No 52.50

2306 Blasted Rubble cum 600.00

Page 11 of 15

Page 16: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

Sl. No Items Unit Rate/Unit

2307 Through and bond stone cum 2,500.00

2308 Cement mortar 1:3 cum 5,914.40

2309 Hot rolled deformed bars (Iron rod) kg 58.00

2310 1st Class Brick No 21.00

2311 Cement mortar 1:4 cum 4,739.50

2312 Stone Gravel (50 - 30mm size) Cum 5,100.00

2313 Stone Aggregate 50-30 mm Cum 1,075.00

2401 Caution notice board No 42.00

2402 Number plate No 42.00

2403 Wooden Plank (12x1 sq.ft.) No 1,000.00

2501

Lightning Spike made of iron rod,10 mm size, 1.5 m

length, 1 kg welded with MS Flat iron 40x5mm, 0.5kg

and 8 SWG GI wire 2.5kg

No 500.00

2502

Galvanized steel rod, 2 M length, 19 mm dia connected

with GI Wire complete with terminal connector No 850.00

2503

GI Earth pipe 2.5 metre long 40 mm dia with 8 mm

thickness fabricated for pole earthing complete with

terminal connector

No 543.00

2504Readymade fencing post 50 x 50x 6 mm, 2.7 m length

No 1,064.00

2505 Barbed wire kg 153.00

2506Goat proof fencing net, double twisted, 1 x 1 m with hole

size 50 x 50 mmm 166.00

2507 Steel Gate 1.5 m widthx 2 m height No 5,000.00

2504GI Pipe 40mm dia, 4.13m long with a GI base plate of

30x30x0.5cm welded at the bottomNo 2,742.59

2601

Outdoor type CT & PT combination with PT ratio

11/0.415 kV, for all rating of CT ratio as required by HT

side Ampere

No 70,000.00

2602

Outdoor type CT & PT combination with PT ratio

11/0.11 kV, for all rating of CT ratio as required by HT

side Ampere

No 70,000.00

2603

3-ph 4 wire Trivector Meter suitable for Automatic Meter

Reading (AMR), PTR 11/0.415kV, for all rating of CT

Ratio.

No 13,500.00

2604

3-ph 4 wire Trivector Meter suitable for Automatic Meter

Reading (AMR), PTR 11/0.11kV, for all rating of CT

Ratio.

No 13,500.00

2605

LT Outdoor DT Cubicle complete with MCCB, St light

Controller, metering system for both St light and

Consumer for 25kVA, 11/0.415 kV Transformer

No 53,235.00

2606

LT Outdoor DT Cubicle complete with MCCB, St light

Controller, metering system for both St light and

Consumer for 63kVA, 11/0.415 kV Transformer

No 56,778.75

2607

LT Outdoor DT Cubicle complete with MCCB, St light

Controller, metering system for both St light and

Consumer for 100kVA, 11/0.415 kV TransformerNo 62,685.00

Page 12 of 15

Page 17: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

Sl. No Items Unit Rate/Unit

2608

LT Outdoor DT Cubicle complete with MCCB, Consumer

metering system for 25kVA, 11/0.415 kV Transformer No 35,437.50

2609

LT Outdoor DT Cubicle complete with MCCB, Consumer

metering system for 63kVA, 11/0.415 kV Transformer No 38,981.25

2610

LT Outdoor DT Cubicle complete with MCCB, Consumer

metering system for 100kVA, 11/0.415 kV Transformer No 44,887.50

2611

Housing Cabinet for Trivertor Meter for all ratio of PTR

and CTR with suitable clamp in steel tabular pole No 1,500.00

2701

3 phase HRC Main Switch, 63 A conforming to IEC :

60947 (Part 3) - 1999 or any ammendments up to date. No 4,977.00

2702

3 phase HRC Main Switch, 100 A conforming to IEC :

60947 (Part 3) - 1999 or any ammendments up to date. No 6,678.00

2703

3 phase HRC Main Switch, 125 A conforming to IEC :

60947 (Part 3) - 1999 or any ammendments up to date. No 8,587.50

2704

3phase HRC Main Switch, 150 A conforming to IEC :

60947 (Part 3) - 1999 or any ammendments up to date. No 10,832.00

2705

3 phase HRC Main Switch, 200 A conforming to IEC :

60947 (Part 3) - 1999 or any ammendments up to date. No 12,300.00

2706

3 phase HRC Main Switch, 250 A conforming to IEC :

60947 (Part 3) - 1999 or any ammendments up to date. No 13,575.00

2707

3phase HRC Main Switch, 300 A conforming to IEC :

60947 (Part 3) - 1999 or any ammendments up to date. No 14,850.00

2708

3phase HRC Main Switch, 400 A conforming to IEC :

60947 (Part 3) - 1999 or any ammendments up to date. No 16,430.40

2709

3phase HRC Main Switch, 500 A conforming to IEC :

60947 (Part 3) - 1999 or any ammendments up to date. No 22,554.00

2710

3phase HRC Main Switch, 630 A conforming to IEC :

60947 (Part 3) - 1999 or any ammendments up to date. No 25,956.00

2711 Cut out, 32 A with suitable fuse No 325.00

2712 Cut out, 63 A with suitable fuse No 650.00

2713 Cut out, 100 A with suitable fuse No 868.00

2714 Cut out, 200 A with suitable fuse No 1,750.00

2715 Cut out, 400 A with suitable fuse No 2,100.00

2716 Cut out, 500 A with suitable fuse No 2,100.00

2717

415V, 3 phase Air break Manual Switch, 125A

conforming to IEC : 60947 (Part 3) - 1999 or any

ammendments up to date.

No 7,965.00

Page 13 of 15

Page 18: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

Sl. No Items Unit Rate/Unit

2718

415V, 3 phase Air break Manual Switch, 250A

conforming to IEC : 60947 (Part 3) - 1999 or any

ammendments up to date.

No 14,337.00

2719

415V, 3 phase Air break Manual Switch, 400A

conforming to IEC : 60947 (Part 3) - 1999 or any

ammendments up to date.

No 16,915.00

2801HRC Fuse, 63 A, conforming to IS : 13703 - 1993 or any

ammendments up to date.No 570.00

2802HRC Fuse, 100 A, conforming to IS : 13703 - 1993 or

any ammendments up to date.No 1,020.00

2803HRC Fuse, 125 A, conforming to IS : 13703 - 1993 or

any ammendments up to date.No 1,177.50

2804HRC Fuse, 150 A, conforming to IS : 13703 - 1993 or

any ammendments up to date.No 1,335.00

2805HRC Fuse, 200 A, conforming to IS : 13703 - 1993 or

any ammendments up to date.No 1,650.00

2806HRC Fuse, 250 A, conforming to IS : 13703 - 1993 or

any ammendments up to date.No 1,765.50

2807HRC Fuse, 300 A, conforming to IS : 13703 - 1993 or

any ammendments up to date.No 1,881.00

2808HRC Fuse, 400 A, conforming to IS : 13703 - 1993 or

any ammendments up to date.No 4,500.00

2809HRC Fuse, 500 A, conforming to IS : 13703 - 1993 or

any ammendments up to date.No 4,650.00

2810HRC Fuse, 630 A, conforming to IS : 13703 - 1993 or

any ammendments up to date.No 8,700.00

2811Tinned Copper Fuse Wire, 2.5 A, conforming to IS : 9926

- 1981 or any ammendments up to date.kg 1,040.00

2812Tinned Copper Fuse Wire, 5 A, conforming to IS : 9926 -

1981 or any ammendments up to date.kg 1,040.00

2813Tinned Copper Fuse Wire, 10 A, conforming to IS : 9926 -

1981 or any ammendments up to date.kg 1,040.00

2814Tinned Copper Fuse Wire, 15 A, conforming to IS : 9926 -

1981 or any ammendments up to date.kg 1,040.00

2815Tinned Copper Fuse Wire, 20 A, conforming to IS : 9926 -

1981 or any ammendments up to date.kg 1,040.00

2816Tinned Copper Fuse Wire, 25 A, conforming to IS : 9926 -

1981 or any ammendments up to date.kg 1,040.00

2817Tinned Copper Fuse Wire, 30 A, conforming to IS : 9926 -

1981 or any ammendments up to date.kg 1,040.00

2818Tinned Copper Fuse Wire, 35 A, conforming to IS : 9926 -

1981 or any ammendments up to date.kg 1,040.00

2819Tin-Copper Fuse Wire, 40 A, conforming to IS : 9926 -

1981 or any ammendments up to date.kg 1,040.00

2820 EADC Fuse, 2.5 A doz. 410.00

2821 EADC Fuse, 5 A doz. 410.00

2822 EADC Fuse, 10 A doz. 410.00

2823 EADC Fuse, 15 A doz. 410.00

2824 EADC Fuse, 20 A doz. 425.00

2825 EADC Fuse, 25 A doz. 425.00

2826 EADC Fuse, 30 A doz. 425.00

2827 EADC Fuse, 35 A doz. 425.00

Page 14 of 15

Page 19: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

Sl. No Items Unit Rate/Unit

2828 EADC Fuse, 40 A doz. 425.00

2829 11 kV Fibre Barrel with metallic parts No 315.00

2830 33 kV Fibre Barrel with metallic parts No 375.00

2901

11 kV Gang Operated Air Break Switch, 200 A,

conforming to IS : 2544 - 1973, IS : 9921 (Part I-V) or

any ammendments up to date

Set 14,490.00

2902

11 kV Fuse Unit with Arcing Horn, 200 A, conforming to

9385 (Part 2) - 1980 ammended up to date Set 7,087.50

2903

Horizontally operated Single break 11 kV Isolator

complete with Drop out Fuse unit, conforming to IS :

9921 and any other relevant standards ammended up to

date.

Set 34,650.00

3201

HPSV Lamp Street Light Fittings complete with Choke,

Condenser, Holder and Ignitor, 250 W, conforming to IS

: 10322 - 2012, IS : 2215 - 2006 and any other relevant

standards with amendments up to date.

Set 6,850.00

3202

HPSV Lamp Street Light Fittings complete with Choke,

Condenser, Holder and Ignitor, 150 W, conforming to IS

: 10322 - 2012, IS : 2215 - 2006 and any other relevant

standards with amendments up to date.

Set 6,165.00

3203

HPSV Lamp, 250 W, conforming to IS : 10322 - 2012

and any other relevant standards with amendments up

to date.

No 1,950.00

3204 Street Light Bracket No 590.00

3205D-Clamp for Street Light Bracket complete with Nuts &

BoltsSet 139.00

Page 15 of 15

Page 20: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

Page No -1-

Page 21: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

POLE (SP-29) ERECTION

1.02 Providing and erection of steel tubular pole (SP-29) strut in cement concrete 1:3:6

(1cement : 3 coarse sand: 6 graded stone aggregate 40 mm nominal size ) found ation

(0.342Cum inclusive of muffling) with planting depth of 1 .5m including pole painting;

excavation and back filling of pole pit; carriage of Materials at site as directed by the

engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

1102

Swaged Steel Pole with base

plate of thickness 6mm and

size of 200mmx200mm square

welded at the bottom and with

pole cap of 6mm thick to be

welded at the top conforming

to IS 2713/1980 or the latest

version thereof 410 SP-29 of

overall length 9.00m

No 12,656.25 1.00 12,656.25

2201 Aluminium Paint Lit 170.00 0.95 161.50

2202 Bituminious Alkali Paint Lit 120.00 0.48 57.60

2203 Red Oxide Paint Lit 125.00 0.95 118.75

2301 Cement cum 13,750.00 0.03 470.25

2302 River Sand cum 2,100.00 0.10 215.46

2303 Stone Aggregate 10-20 mm cum 1,890.00 0.21 387.83

2403 Wooden Plank (12x1 sq.ft.) No 1,000.00 2.00 2,000.00

2401 Caution notice board No 42.00 1.00 42.00

2402 Number plate No 42.00 1.00 42.00

Total Cost of Materials 16,151.64

Contingency (2% on Material Cost) 323.03

Sub-Total 16,474.67

Labours

1001 Labour Skilled-I manday 380 0.50 190.00

1002 Labour Skilled-II manday 310 0.50 155.00

1003 Labour Semi-Skilled manday 250 1.00 250.00

1004 Labour Un-skilled manday 220 10.67 2,346.67

Total Cost of Labours 2,941.67

Total 19,416.34

Add 15% for overhead & Profit 2,912.45

Grand Total 22,328.79

Say 22,329.00

Supervision (15% on Labour Cost) 441.25

Page No -2-

Page 22: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

POLE (SP-35) ERECTION

1.03 Providing and erection of steel tubular pole (SP-35) strut in cement concrete 1:3:6

(1cement : 3 coarse sand: 6 graded stone aggregate 40 mm nominal size ) foundation

(0.395Cum inclusive of muffling) with planting depth of 1.8m including pole painting;

excavation and back filling of pole pit; carriage of Materials at site as directed by the

engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

1103

Swaged Steel Pole with base

plate of thickness 6mm and

size of 200mmx200mm square

welded at the bottom and with

pole cap of 6mm thick to be

welded at the top conforming

to IS 2713/1980 or the latest

version thereof 410 SP-35 of

overall length 9.50m

No 13,061.25 1.00 13,061.25

2201 Aluminium Paint Lit 170.00 1.00 170.00

2202 Bituminious Alkali Paint Lit 120.00 0.50 60.00

2203 Red Oxide Paint Lit 125.00 1.00 125.00

2301 Cement cum 13,750.00 0.04 543.13

2302 River Sand cum 2,100.00 0.12 248.85

2303 Stone Aggregate 10-20 mm cum 1,890.00 0.24 447.93

2403 Wooden Plank (12x1 sq.ft.) No 1,000.00 2.00 2,000.00

2401 Caution notice board No 42.00 1.00 42.00

2402 Number plate No 42.00 1.00 42.00

Total Cost of Materials 16,740.16

Contingency (2% on Material Cost) 334.80

Sub-Total 17,074.96

Labours

1001 Labour Skilled-I manday 380.00 0.50 190.00

1002 Labour Skilled-II manday 310.00 0.50 155.00

1003 Labour Semi-Skilled manday 250.00 1.00 250.00

1004 Labour Un-skilled manday 220.00 13.03 2,867.33

Total Cost of Labours 3,462.33

Total 20,537.29

Add 15% for overhead & Profit 3,080.59

Grand Total 23,617.89

Say 23,618.00

Supervision (15% on Labour Cost) 519.35

Page No -3-

Page 23: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

POLE (SP-58) ERECTION

1.04 Providing and erection of steel tubular pole (SP-58) strut in cement concrete 1:3:6

(1cement : 3 coarse sand: 6 graded stone aggregate 40 mm nominal size ) foundation

(0.465Cum inclusive of muffling) with planting depth of 2m including pole painting;

excavation and back filling of pole pit; carriage of Materials at site as directed by the

engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

1104

Swaged Steel Pole with base

plate of thickness 6mm and

size of 200mmx200mm square

welded at the bottom and with

pole cap of 6mm thick to be

welded at the top conforming

to IS 27 13/1980 or the latest

version thereof 410 SP-58 of

overall length 12.00m

No 18,832.50 1.00 18,832.50

2201 Aluminium Paint Lit 170.00 1.10 187.00

2202 Bituminious Alkali Paint Lit 120.00 0.55 66.00

2203 Red Oxide Paint Lit 125.00 1.10 137.50

2301 Cement cum 13,750.00 0.05 639.38

2302 River Sand cum 2,100.00 0.14 292.95

2303 Stone Aggregate 10-20 mm cum 1,890.00 0.28 527.31

2403 Wooden Plank (12x1 sq.ft.) No 1,000.00 2.00 2,000.00

2401 Caution notice board No 42.00 1.00 42.00

2402 Number plate No 42.00 1.00 42.00

Total Cost of Materials 22,766.64

Contingency (2% on Material Cost) 455.33

Sub-Total 23,221.97

Labours

1001 Labour Skilled-I manday 380 0.50 190.00

1002 Labour Skilled-II manday 310 0.50 155.00

1003 Labour Semi-Skilled manday 250 1.00 250.00

1004 Labour Un-skilled manday 220 15.75 3,465.00

Total Cost of Labours 4,060.00

Total 27,281.97

Add 15% for overhead & Profit 4,092.30

Grand Total 31,374.26

Say 31,374.00

Supervision (15% on Labour Cost) 609.00

Page No -4-

Page 24: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

POLE (Pre-Stressed Concrete for a length of 8.5 metre) ERECTION

1.05 Providing and erection of Pre-Stressed Concrete for a length of 8.5 metre in cement

concrete 1:3:6 (1 cement: 3 coarse sand : 6 graded stone aggregate 40 mm nominal

size) foundation (0.573 Cum inclusive of muffling) with planting depth of 1.5m

including excavation and back filling of pole pit; carriage of Materials at site as

directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

1105 Pre stressed Concrete Pole: 8.5m No 5,828.00 1.00 5,828.00

2301 Cement cum 13,750.00 0.06 787.88

2302 River Sand cum 2,100.00 0.17 360.99

2303 Stone Aggregate 10-20 mm cum 1,890.00 0.34 649.78

2403 Wooden Plank (12x1 sq.ft.) No 1,000.00 2.00 2,000.00

2401 Caution notice board No 42.00 1.00 42.00

2402 Number plate No 42.00 1.00 42.00

Total Cost of Materials 9,710.65

Contingency (2% on Material Cost) 194.21

Sub-Total 9,904.86

Labours

1001 Labour Skilled-I manday 380.00 0.50 190.00

1002 Labour Skilled-II manday 310.00 0.50 155.00

1003 Labour Semi-Skilled manday 250.00 1.00 250.00

1004 Labour Un-skilled manday 220.00 13.67 3,006.67

Total Cost of Labours 3,601.67

Total 13,506.53

Add 15% for overhead & Profit 2,025.98

Grand Total 15,532.51

Say 15,533.00

Supervision (15% on Labour Cost) 540.25

Page No -5-

Page 25: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

POLE (Pre-Stressed Concrete for a length of 9.75 metre) ERECTION

1.06 Providing and erection of Pre-Stressed Concrete for a length of 9.75 metre in cement

concrete 1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 40 mm nominal

size) foundation (0.797Cum inclusive of muffling) with planting depth of 1.8m

including excavation and back filling of pole pit; carriage of Materials at site as

directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

1106 Pre stressed Concrete Pole:

9.75m No 8190.00

1.00 8190.00

2301 Cement cum 13,750.00 0.08 1,095.88

2302 River Sand cum 2,100.00 0.24 502.11

2303 Stone Aggregate 10-20 mm cum 1,890.00 0.48 903.80

2403 Wooden Plank (12x1 sq.ft.) No 1,000.00 2.00 2,000.00

2401 Caution notice board No 42.00 1.00 42.00

2402 Number plate No 42.00 1.00 42.00

Total Cost of Materials 12,775.78

Contingency (2% on Material Cost) 255.52

Sub-Total 13,031.30

Labours

1001 Labour Skilled-I manday 380.00 0.50 190.00

1002 Labour Skilled-II manday 310.00 0.50 155.00

1003 Labour Semi-Skilled manday 250.00 1.00 250.00

1004 Labour Un-skilled manday 220.00 16.67 3,666.67

Total Cost of Labours 4,261.67

Total 17,292.97

Add 15% for overhead & Profit 2,593.94

Grand Total 19,886.91

Say 19,887.00

Supervision (15% on Labour Cost) 639.25

Page No -6-

Page 26: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

Page No -7-

Page 27: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

GALVANISED STEEL TABULAR POLE (SP-29) ERECTION

1.08 Providing and erection of Galvanised steel tubular pole (SP-29) strut in cement concrete

1:3:6 (1 cement: 3 coarse sand : 6 graded stone aggregate 40 mm nominal size)

foundation (0.342Cum inclusive of muffling) with planting depth of 1 .5m including pole

painting; excavation and back filling of pole pit; carriage of Materials at site as directed

by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

1108

Galvanised Swaged Steel Pole

with base plate of thickness

6mm and size of

200mmx200mm square welded

at the bottom and with pole cap

of 6mm thick to be welded at the

top conforming to IS 2713/1980

or the latest version thereof 410

SP-29 of overall length 9.00m

No 18,900.00 1.00 18,900.00

2201 Aluminium Paint Lit 170.00 0.95 161.50

2202 Bituminious Alkali Paint Lit 120.00 0.48 57.60

2203 Red Oxide Paint Lit 125.00 0.95 118.75

2301 Cement cum 13,750.00 0.03 470.25

2302 River Sand cum 2,100.00 0.10 215.46

2303 Stone Aggregate 10-20 mm cum 1,890.00 0.21 387.83

2403 Wooden Plank (12x1 sq.ft.) No 1,000.00 2.00 2,000.00

2401 Caution notice board No 42.00 1.00 42.00

2402 Number plate No 42.00 1.00 42.00

Total Cost of Materials 22,395.39

Contingency (2% on Material Cost) 447.91

Sub-Total 22,843.30 Labours

1001 Labour Skilled-I manday 380.00 0.50 190.00

1002 Labour Skilled-II manday 310.00 0.50 155.00

1003 Labour Semi-Skilled manday 250.00 1.00 250.00

1004 Labour Un-skilled manday 220.00 10.67 2,346.67

Total Cost of Labours 2,941.67

Total 25,784.96

Add 15% for overhead & Profit 3,867.74

Grand Total 29,652.71

Say 29,653.00

Supervision (15% on Labour Cost) 441.25

Page No -8-

Page 28: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

Page No -9-

Page 29: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

Page No -10-

Page 30: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FITTING OF CROSSARM

2.01 Providing and fitting of horizontal Brackets with MS Angle Iron 40 mm X 40 mm X 6

mm (3.5Kg per metre) for 3 phase 5 wires LT overhead line conductors complete with

jam clamp, bolts and nuts for clamping to the poles including drilling of holes for

insulator pins/fitting bolts, nuts and washers etc and painting with primer and

finished paint as required (For SP- 17) as directed by the engineer in charge..

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials 1403 M.S. Angle Iron 40x40x6 mm kg 105.84 5.89 623.45

1405 M.S. Flat Iron 40mmx6 mm kg 105.84 1.78 187.95

21 02

M.S. Nut & Bolt 16x50 mm full

thread conforming to IS : 1 364- 2

(1992) or any amendments up to

date.

kg 162.00 0.88 141.91

21 07

M.S. Washer for 16 mm

diameter hole conforming to IS

: 1364-2 (1992) or any

amendments up to date.

kg 132.00 0.05 6.60

2201 Aluminium Paint Lit 170.00 0.30 51.00

2203 Red Oxide Paint Lit 125.00 0.30 37.50

Total Cost of Materials 1,048.41

Contingency (2% on Material Cost) 20.97

Sub-Total 1,069.38

Labours

1001 Labour Skilled-I manday 380.00 0.44 167.20

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.11 26.67

1004 Labour Un-skilled manday 220.00 0.75 164.27

Total Cost of Labours 358.13

Total 1,427.51

Add 15% for overhead & Profit 214.13

Grand Total 1,641.64

Say 1,642.00

Supervision (15% on Labour Cost) 53.72

Page No -11-

Page 31: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FITTING OF CROSSARM

2.02 Providing and fitting of Rectangular Brackets with MS Angle Iron 40 mm X 40 mm X 6

mm (3.5Kg per metre) for 3 phase 5 wires LT overhead line conductors complete with

jam clamp, bolts and nuts for clamping to the poles including drilling of holes for

insulator pins/fitting bolts, nuts and washers etc and painting with primer and

finished paint as required (For SP-17) as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials 1403 M.S. Angle Iron 40x40x6 mm kg 105.84 8.55 904.61

1405 M.S. Flat Iron 40mmx6 mm kg 105.84 1.18 125.30

21 02

M.S. Nut & Bolt 16x50 mm full

thread conforming to IS : 1 364- 2

(1992) or any amendments up to

date.

kg 162.00 0.58 94.61

21 07

M.S. Washer for 16 mm

diameter hole conforming to IS :

1364-2 (1992) or any

amendments up to date.

kg 132.00 0.05 6.60

2201 Aluminium Paint Lit 170.00 0.30 51.00

2203 Red Oxide Paint Lit 125.00 0.30 37.50

Total Cost of Materials 1,219.62

Contingency (2% on Material Cost) 24.39

Sub-Total 1,244.01

Labours

1001 Labour Skilled-I manday 380.00 0.27 101.20

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.07 16.58

1004 Labour Un-skilled manday 220.00 0.53 117.18

Total Cost of Labours 234.96

Total 1,478.97

Add 15% for overhead & Profit 221.85

Grand Total 1,700.82

Say 1,701.00

Supervision (15% on Labour Cost) 35.24

Page No -12-

Page 32: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FITTING OF CROSSARM

2.03 Providing and fitting of Single sided LT bracket with MS Angle Iron 40 mm X 40 mm X

6 mm (3.5Kg per metre) for 3 phase 5 wires LT overhead line conductors complete

with jam clamp, bolts and nuts for clamping to the poles including drilling of holes

for insulator pins/fitting bolts, nuts and washers etc and painting with primer and

finished paint as required (For SP-17) as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials 1403 M.S. Angle Iron 40x40x6 mm kg 105.84 8.96 948.74

1405 M.S. Flat Iron 40mmx6 mm kg 105.84 6.64 703.03

21 02

M.S. Nut & Bolt 16x50 mm full

thread conforming to IS : 1 364- 2

(1992) or any amendments up to

date.

kg 162.00 1.90 307.48

21 07

M.S. Washer for 16 mm

diameter hole conforming to IS :

1364-2 (1992) or any

amendments up to date.

kg 132.00 0.05 6.60

2201 Aluminium Paint Lit 170.00 0.30 51.00

2203 Red Oxide Paint Lit 125.00 0.30 37.50

Total Cost of Materials 2,054.35

Contingency (2% on Material Cost) 41.09

Sub-Total 2,095.44

Labours

1001 Labour Skilled-I manday 380.00 0.27 101.20

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.07 16.58

1004 Labour Un-skilled manday 220.00 0.53 117.18

Total Cost of Labours 234.96

Total 2,330.40

Add 15% for overhead & Profit 349.56

Grand Total 2,679.96

Say 2,680.00

Supervision (15% on Labour Cost) 35.24

Page No -13-

Page 33: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FITTING OF CROSSARM

2.04 Providing and fitting of Horizontal bracket with MS Angle Iron 40 mm X 40 mm X 6

mm (3.5Kg per metre) for 1 phase 3 wires LT overhead line conductors complete with

jam clamp, bolts and nuts for clamping to the poles including drilling of holes for

insulator pins/fitting bolts, nuts and washers etc and painting with primer and

finished paint as required (For SP-17) as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials 1403 M.S. Angle Iron 40x40x6 mm kg 105.84 3.93 415.63

1405 M.S. Flat Iron 40mmx6 mm kg 105.84 1.18 125.30

21 02

M.S. Nut & Bolt 16x50 mm full

thread conforming to IS : 1

364- 2 (1992) or any

amendments up to date.

kg 162.00 0.58 94.61

21 07

M.S. Washer for 16 mm

diameter hole conforming to IS

: 1364-2 (1992) or any

amendments up to date.

kg 132.00 0.05 6.60

2201 Aluminium Paint Lit 170.00 0.30 51.00

2203 Red Oxide Paint Lit 125.00 0.30 37.50

Total Cost of Materials 730.64

Contingency (2% on Material Cost) 14.61

Sub-Total 745.25

Labours

1001 Labour Skilled-I manday 380.00 0.27 101.20

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.07 16.58

1004 Labour Un-skilled manday 220.00 0.53 117.18

Total Cost of Labours 234.96

Total 980.21

Add 15% for overhead & Profit 147.03

Grand Total 1,127.24

Say 1,127.00

Supervision (15% on Labour Cost) 35.24

Page No -14-

Page 34: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FITTING OF CROSSARM

2.05 Providing and fitting of Horizontal Brackets with MS Angle Iron 40 mm X 40 mm X 6

mm (3.5Kg per metre) for 3 phase 5 wires LT overhead line conductors complete with

jam clamp, bolts and nuts for clamping to the poles including drilling of holes for

insulator pins/fitting bolts, nuts and washers etc and painting with primer and

finished paint as required (For SP-29) as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials 1403 M.S. Angle Iron 40x40x6 mm kg 105.84 5.89 623.45

1405 M.S. Flat Iron 40mmx6 mm kg 105.84 2.01 213.22

2102

M.S. Nut & Bolt 16x50 mm full

thread conforming to IS : 1364-

2 (1992) or any amendments up

to date.

kg 162.00 0.88 141.91

21 07

M.S. Washer for 16 mm

diameter hole conforming to IS

: 1364-2 (1992) or any

amendments up to date.

kg 132.00 0.05 6.60

2201 Aluminium Paint Lit 170.00 0.30 51.00

2203 Red Oxide Paint Lit 125.00 0.30 37.50

Total Cost of Materials 1,073.68

Contingency (2% on Material Cost) 21.47

Sub-Total 1,095.16

Labours

1001 Labour Skilled-I manday 380.00 0.44 167.20

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.11 26.67

1004 Labour Un-skilled manday 220.00 0.75 164.27

Total Cost of Labours 358.13

Total 1,453.29

Add 15% for overhead & Profit 217.99

Grand Total 1,671.28

Say 1,671.00

Supervision (15% on Labour Cost) 53.72

Page No -15-

Page 35: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FITTING OF CROSSARM

2.06 Providing and fitting of Rectangular Brackets with MS Angle Iron 40 mm X 40 mm X 6

mm (3.5Kg per metre) for 3 phase 5 wires LT overhead line conductors complete with

jam clamp, bolts and nuts for clamping to the poles including drilling of holes for

insulator pins/fitting bolts, nuts and washers etc and painting with primer and

finished paint as required (For SP-29) as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials 1403 M.S. Angle Iron 40x40x6 mm kg 105.84 8.55 904.61

1405 M.S. Flat Iron 40mmx6 mm kg 105.84 1.34 142.15

21 02

M.S. Nut & Bolt 16x50 mm full

thread conforming to IS : 1

364- 2 (1992) or any

amendments up to date.

kg 162.00 0.58 94.61

21 07

M.S. Washer for 16 mm

diameter hole conforming to IS

: 1364-2 (1992) or any

amendments up to date.

kg 132.00 0.05 6.60

2201 Aluminium Paint Lit 170.00 0.30 51.00

2203 Red Oxide Paint Lit 125.00 0.30 37.50

Total Cost of Materials 1,236.47

Contingency (2% on Material Cost) 24.73

Sub-Total 1,261.20

Labours

1001 Labour Skilled-I manday 380.00 0.27 101.20

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.07 16.58

1004 Labour Un-skilled manday 220.00 0.53 117.18

Total Cost of Labours 234.96

Total 1,496.16

Add 15% for overhead & Profit 224.42

Grand Total 1,720.58

Say 1,721.00

Supervision (15% on Labour Cost) 35.24

Page No -16-

Page 36: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FITTING OF CROSSARM

2.07 Providing and fitting of Single sided LT bracket with MS Angle Iron 40 mm X 40 mm X

6 mm (3.5Kg per metre) for 3 phase 5 wires LT overhead line conductors complete

with jam clamp, bolts and nuts for clamping to the poles including drilling of holes

for insulator pins/fitting bolts, nuts and washers etc and painting with primer and

finished paint as required (For SP-29) as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials 1403 M.S. Angle Iron 40x40x6 mm kg 105.84 9.11 964.39

1405 M.S. Flat Iron 40mmx6 mm kg 105.84 7.04 745.15

21 02

M.S. Nut & Bolt 16x50 mm full

thread conforming to IS : 1

364- 2 (1992) or any

amendments up to date.

kg 162.00 1.90 307.48

21 07

M.S. Washer for 16 mm

diameter hole conforming to IS

: 1364-2 (1992) or any

amendments up to date.

kg 132.00 0.05 6.60

2201 Aluminium Paint Lit 170.00 0.30 51.00

2203 Red Oxide Paint Lit 125.00 0.30 37.50

Total Cost of Materials 2,112.12

Contingency (2% on Material Cost) 42.24

Sub-Total 2,154.37

Labours

1001 Labour Skilled-I manday 380.00 0.27 101.20

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.07 16.58

1004 Labour Un-skilled manday 220.00 0.53 117.18

Total Cost of Labours 234.96

Total 2,389.32

Add 15% for overhead & Profit 358.40

Grand Total 2,747.72

Say 2,748.00

Supervision (15% on Labour Cost) 35.24

Page No -17-

Page 37: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FITTING OF CROSSARM

2.08 Providing and fitting of Horizontal bracket with MS Angle Iron 40 mm X 40 mm X 6

mm (3.5Kg per metre) for 1 phase 3 wires LT overhead line conductors complete with

jam clamp, bolts and nuts for clamping to the poles including drilling of holes for

insulator pins/fitting bolts, nuts and washers etc and painting with primer and

finished paint as required (For SP-29) as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials 1403 M.S. Angle Iron 40x40x6 mm kg 105.84 3.93 415.63

1405 M.S. Flat Iron 40mmx6 mm kg 105.84 1.34 142.15

21 02

M.S. Nut & Bolt 16x50 mm full

thread conforming to IS : 1

364- 2 (1992) or any

amendments up to date.

kg 162.00 0.58 94.61

21 07

M.S. Washer for 16 mm

diameter hole conforming to IS

: 1364-2 (1992) or any

amendments up to date.

kg 132.00 0.05 6.60

2201 Aluminium Paint Lit 170.00 0.30 51.00

2203 Red Oxide Paint Lit 125.00 0.30 37.50

Total Cost of Materials 747.49

Contingency (2% on Material Cost) 14.95

Sub-Total 762.44

Labours

1001 Labour Skilled-I manday 380.00 0.27 101.20

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.07 16.58

1004 Labour Un-skilled manday 220.00 0.53 117.18

Total Cost of Labours 234.96

Total 997.40

Add 15% for overhead & Profit 149.61

Grand Total 1,147.01

Say 1,147.00

Supervision (15% on Labour Cost) 35.24

Page No -18-

Page 38: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FITTING OF CROSSARM

2.09 Providing and fitting of Horizontal Brackets with MS Angle Iron 40 mm X 40 mm X 6

mm (3.5 Kg per metre) for 3 phase 5 wires LT overhead line conductors complete

with jam clamp, bolts and nuts for clamping to the poles including drilling of holes

for insulator pins/fitting bolts, nuts and washers etc and painting with primer and

finished paint as required (For Pre-Stressed Concrete 8.5 metres) as directed by the

engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials 1403 M.S. Angle Iron 40x40x6 mm kg 105.84 5.89 623.45

1405 M.S. Flat Iron 40mmx6 mm kg 105.84 3.14 331.95

2102

M.S. Nut & Bolt 16x50 mm full

thread conforming to IS : 1364-

2 (1992) or any amendments up

to date.

kg 162.00 0.88 141.91

21 07

M.S. Washer for 16 mm

diameter hole conforming to IS

: 1364-2 (1992) or any

amendments up to date.

kg 132.00 0.05 6.60

2201 Aluminium Paint Lit 170.00 0.30 51.00

2203 Red Oxide Paint Lit 125.00 0.30 37.50

Total Cost of Materials 1,192.41

Contingency (2% on Material Cost) 23.85

Sub-Total 1,216.26

Labours

1001 Labour Skilled-I manday 380.00 0.27 101.20

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.07 16.58

1004 Labour Un-skilled manday 220.00 0.53 117.18

Total Cost of Labours 234.96

Total 1,451.22

Add 15% for overhead & Profit 217.68

Grand Total 1,668.90

Say 1,669.00

Supervision (15% on Labour Cost) 35.24

Page No -19-

Page 39: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FITTING OF CROSSARM

2.10 Providing and fitting of Rectangular Brackets with MS Angle Iron 40 mm X 40 mm X

6 mm (3.5 Kg per metre) for 3 phase 5 wires LT overhead line conductors complete

with jam clamp, bolts and nuts for clamping to the poles including drilling of holes

for insulator pins/fitting bolts, nuts and washers etc and painting with primer and

finished paint as required (For Pre-Stressed Concrete 8.5 metres) as directed by the

engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials 1403 M.S. Angle Iron 40x40x6 mm kg 105.84 8.55 904.61

1405 M.S. Flat Iron 40mmx6 mm kg 105.84 2.09 221.30

21 02

M.S. Nut & Bolt 16x50 mm full

thread conforming to IS : 1 364-

2 (1992) or any amendments up

to date.

kg 162.00 0.58 94.61

21 07

M.S. Washer for 16 mm

diameter hole conforming to IS

: 1364-2 (1992) or any

amendments up to date.

kg 132.00 0.05 6.60

2201 Aluminium Paint Lit 170.00 0.30 51.00

2203 Red Oxide Paint Lit 125.00 0.30 37.50

Total Cost of Materials 1,315.62

Contingency (2% on Material Cost) 26.31

Sub-Total 1,341.93

Labours

1001 Labour Skilled-I manday 380.00 0.27 101.20

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.07 16.58

1004 Labour Un-skilled manday 220.00 0.53 117.18

Total Cost of Labours 234.96

Total 1,576.89

Add 15% for overhead & Profit 236.53

Grand Total 1,813.43

Say 1,813.00

Supervision (15% on Labour Cost) 35.24

Page No -20-

Page 40: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FITTING OF CROSSARM

2.11 Providing and fitting of Single sided Brackets with MS Angle Iron 40 mm X 40 mm X

6 mm (3.5 Kg per metre) for 3 phase 5 wires LT overhead line conductors complete

with jam clamp, bolts and nuts for clamping to the poles including drilling of holes

for insulator pins/fitting bolts, nuts and washers etc and painting with primer and

finished paint as required (For Pre-Stressed Concrete 8.5 metres) as directed by the

engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials 1403 M.S. Angle Iron 40x40x6 mm kg 105.84 10.09 1,068.42

1405 M.S. Flat Iron 40mmx6 mm kg 105.84 9.39 993.31

21 02

M.S. Nut & Bolt 16x50 mm full

thread conforming to IS : 1 364-

2 (1992) or any amendments up

to date.

kg 162.00 1.90 307.48

21 07

M.S. Washer for 16 mm

diameter hole conforming to IS

: 1364-2 (1992) or any

amendments up to date.

kg 132.00 0.05 6.60

2201 Aluminium Paint Lit 170.00 0.30 51.00

2203 Red Oxide Paint Lit 125.00 0.30 37.50

Total Cost of Materials 2,464.31

Contingency (2% on Material Cost) 49.29

Sub-Total 2,513.59

Labours

1001 Labour Skilled-I manday 380.00 0.27 101.20

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.07 16.58

1004 Labour Un-skilled manday 220.00 0.53 117.18

Total Cost of Labours 234.96

Total 2,748.55

Add 15% for overhead & Profit 412.28

Grand Total 3,160.83

Say 3,161.00

Supervision (15% on Labour Cost) 35.24

Page No -21-

Page 41: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FITTING OF CROSSARM

2.12 Providing and fitting of Horizontal Brackets with MS Angle Iron 40 mm X 40 mm X 6

mm (3.5 Kg per metre) for 1 phase 3 wires LT overhead line conductors complete

with jam clamp, bolts and nuts for clamping to the poles including drilling of holes

for insulator pins/fitting bolts, nuts and washers etc and painting with primer and

finished paint as required (For Pre-Stressed Concrete 8.5 metres) as directed by the

engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials 1403 M.S. Angle Iron 40x40x6 mm kg 105.84 3.93 415.63

1405 M.S. Flat Iron 40mmx6 mm kg 105.84 2.09 221.30

21 02

M.S. Nut & Bolt 16x50 mm full

thread conforming to IS : 1

364- 2 (1992) or any

amendments up to date.

kg 162.00 0.58 94.61

21 07

M.S. Washer for 16 mm

diameter hole conforming to IS

: 1364-2 (1992) or any

amendments up to date.

kg 132.00 0.05 6.60

2201 Aluminium Paint Lit 170.00 0.30 51.00

2203 Red Oxide Paint Lit 125.00 0.30 37.50

Total Cost of Materials 826.64

Contingency (2% on Material Cost) 16.53

Sub-Total 843.17

Labours

1001 Labour Skilled-I manday 380.00 0.27 101.20

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.07 16.58

1004 Labour Un-skilled manday 220.00 0.53 117.18

Total Cost of Labours 234.96

Total 1,078.13

Add 15% for overhead & Profit 161.72

Grand Total 1,239.85

Say 1,240.00

Supervision (15% on Labour Cost) 35.24

Page No -22-

Page 42: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FITTING OF CROSSARM

2.13 Providing and fitting of Horizontal Brackets with MS Angle Iron 40 mm X 40 mm X 6

mm (3.5 Kg per metre) for 3 phase 5 wires LT overhead line conductors complete

with jam clamp, bolts and nuts for clamping to the poles including drilling of holes

for insulator pins/fitting bolts, nuts and washers etc and painting with primer and

finished paint as required (For Pre-Stressed Concrete 9.75 metres) as directed by

the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials 1403 M.S. Angle Iron 40x40x6 mm kg 105.84 5.89 623.45

1405 M.S. Flat Iron 40mmx6 mm kg 105.84 3.37 357.10

2102

M.S. Nut & Bolt 16x50 mm full

thread conforming to IS : 1364-

2 (1992) or any amendments up

to date.

kg 162.00 0.88 141.91

21 07

M.S. Washer for 16 mm

diameter hole conforming to IS

: 1364-2 (1992) or any

amendments up to date.

kg 132.00 0.05 6.60

2201 Aluminium Paint Lit 170.00 0.30 51.00

2203 Red Oxide Paint Lit 125.00 0.30 37.50

Total Cost of Materials 1,217.56

Contingency (2% on Material Cost) 24.35

Sub-Total 1,241.91

Labours

1001 Labour Skilled-I manday 380.00 0.27 101.20

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.07 16.58

1004 Labour Un-skilled manday 220.00 0.53 117.18

Total Cost of Labours 234.96

Total 1,476.87

Add 15% for overhead & Profit 221.53

Grand Total 1,698.40

Say 1,698.00

Supervision (15% on Labour Cost) 35.24

Page No -23-

Page 43: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FITTING OF CROSSARM

2.14 Providing and fitting of Rectangular Brackets with MS Angle Iron 40 mm X 40 mm X

6 mm (3.5 Kg per metre) for 3 phase 5 wires LT overhead line conductors complete

with jam clamp, bolts and nuts for clamping to the poles including drilling of holes

for insulator pins/fitting bolts, nuts and washers etc and painting with primer and

finished paint as required (For Pre-Stressed Concrete 9.75 metres) as directed by

the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials 1403 M.S. Angle Iron 40x40x6 mm kg 105.84 8.55 904.61

1405 M.S. Flat Iron 40mmx6 mm kg 105.84 2.25 238.06

21 02

M.S. Nut & Bolt 16x50 mm full

thread conforming to IS : 1

364- 2 (1992) or any

amendments up to date.

kg 162.00 0.58 94.61

21 07

M.S. Washer for 16 mm

diameter hole conforming to IS

: 1364-2 (1992) or any

amendments up to date.

kg 132.00 0.05 6.60

2201 Aluminium Paint Lit 170.00 0.30 51.00

2203 Red Oxide Paint Lit 125.00 0.30 37.50

Total Cost of Materials 1,332.39

Contingency (2% on Material Cost) 26.65

Sub-Total 1,359.03

Labours

1001 Labour Skilled-I manday 380.00 0.27 101.20

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.07 16.58

1004 Labour Un-skilled manday 220.00 0.53 117.18

Total Cost of Labours 234.96

Total 1,593.99

Add 15% for overhead & Profit 239.10

Grand Total 1,833.09

Say 1,833.00

Supervision (15% on Labour Cost) 35.24

Page No -24-

Page 44: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FITTING OF CROSSARM

2.15 Providing and fitting of Single sided Brackets with MS Angle Iron 40 mm X 40 mm X

6 mm (3.5 Kg per metre) for 3 phase 5 wires LT overhead line conductors complete

with jam clamp, bolts and nuts for clamping to the poles including drilling of holes

for insulator pins/fitting bolts, nuts and washers etc and painting with primer and

finished paint as required (For Pre-Stressed Concrete 9.75 metres) as directed by

the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials 1403 M.S. Angle Iron 40x40x6 mm kg 105.84 10.33 1,092.87

1405 M.S. Flat Iron 40mmx6 mm kg 105.84 9.79 1,036.28

21 02

M.S. Nut & Bolt 16x50 mm full

thread conforming to IS : 1 364-

2 (1992) or any amendments up

to date.

kg 162.00 1.90 307.48

21 07

M.S. Washer for 16 mm

diameter hole conforming to IS

: 1364-2 (1992) or any

amendments up to date.

kg 132.00 0.05 6.60

2201 Aluminium Paint Lit 170.00 0.30 51.00

2203 Red Oxide Paint Lit 125.00 0.30 37.50

Total Cost of Materials 2,531.73

Contingency (2% on Material Cost) 50.63

Sub-Total 2,582.36

Labours

1001 Labour Skilled-I manday 380.00 0.27 101.20

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.07 16.58

1004 Labour Un-skilled manday 220.00 0.53 117.18

Total Cost of Labours 234.96

Total 2,817.32

Add 15% for overhead & Profit 422.60

Grand Total 3,239.92

Say 3,240.00

Supervision (15% on Labour Cost) 35.24

Page No -25-

Page 45: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FITTING OF CROSSARM

2.16 Providing and fitting of Horizontal Brackets with MS Angle Iron 40 mm X 40 mm X 6

mm (3.5 Kg per metre) for 1 phase 3 wires LT overhead line conductors complete

with jam clamp, bolts and nuts for clamping to the poles including drilling of holes

for insulator pins/fitting bolts, nuts and washers etc and painting with primer and

finished paint as required (For Pre-Stressed Concrete 9.75 metres) as directed by

the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials 1403 M.S. Angle Iron 40x40x6 mm kg 105.84 3.93 415.63

1405 M.S. Flat Iron 40mmx6 mm kg 105.84 2.25 238.06

21 02

M.S. Nut & Bolt 16x50 mm full

thread conforming to IS : 1 364-

2 (1992) or any amendments up

to date.

kg 162.00 0.58 94.61

21 07

M.S. Washer for 16 mm

diameter hole conforming to IS

: 1364-2 (1992) or any

amendments up to date.

kg 132.00 0.05 6.60

2201 Aluminium Paint Lit 170.00 0.30 51.00

2203 Red Oxide Paint Lit 125.00 0.30 37.50

Total Cost of Materials 843.41

Contingency (2% on Material Cost) 16.87

Sub-Total 860.27

Labours

1001 Labour Skilled-I manday 380.00 0.27 101.20

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.07 16.58

1004 Labour Un-skilled manday 220.00 0.53 117.18

Total Cost of Labours 234.96

Total 1,095.23

Add 15% for overhead & Profit 164.28

Grand Total 1,259.52

Say 1,260.00

Supervision (15% on Labour Cost) 35.24

Page No -26-

Page 46: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FITTING OF CROSSARM

2.17 Providing and erection of 2 nos. of MS Channel Iron 75 mm X 40 mm X 6 mm (7.14Kg

per metre) double pole cross arm for three wire 11 kV overhead line conductors

(horizontal formation) complete with through bolts and nuts for clamping to the poles

including drilling of holes for insulator pins/fitting bolts, nuts and washers etc and

painting with primer and finished paint as required including angle iron

reinforcement (for SP-29) as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials 1401 M.S. Channel 75 x 40 x 6 mm kg 105.84 34.56 3,657.58

1405 M.S. Flat Iron 40mmx6 mm kg 105.84 3.16 334.59

1403 M.S. Angle Iron 40x40x6 mm kg 105.84 45.94 4,861.87

21 03

M.S. Nut & Bolt 16 x 155 mm

full thread conforming to IS :

1364-2 (1992) or any

amendments up to date.

kg 162.00 5.20 842.72

21 02

M.S. Nut & Bolt 16x50 mm full

thread conforming to IS : 1

364- 2 (1992) or any

amendments up to date.

kg 162.00 1.17 189.22

2203 Red Oxide Paint Lit 125.00 0.10 12.50

2201 Aluminium Paint Lit 170.00 0.10 17.00

Total Cost of Materials 9,915.47

Contingency (2% on Material Cost) 198.31

Sub-Total 10,113.78

Labours

1001 Labour Skilled-I manday 380.00 0.68 259.67

1002 Labour Skilled-II manday 310.00 0.25 77.50

1003 Labour Semi-Skilled manday 250.00 0.27 66.67

1004 Labour Un-skilled manday 220.00 2.10 462.00

Total Cost of Labours 865.83

Total 10,979.61

Add 15% for overhead & Profit 1,646.94

Grand Total 12,626.56

Say 12,627.00

Supervision (15% on Labour Cost) 129.88

Page No -27-

Page 47: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FITTING OF CROSSARM

2.18 Providing and erection of 4 nos. of MS Channel Iron 75 mm X 40mm X 6 mm

(7.14Kg per metre) double pole crossarm for three wire 11 kV overhead line

conductors (triangular formation) complete with through bolts and nuts for

clamping to the poles including drilling of holes for insulator pins/fitting bolts, nuts

and washers etc and painting with primer and finished paint as required (for SP-29)

as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials 1401 M.S. Channel 75 x 40 x 6 mm kg 105.84 44.61 4,721.60

1405 M.S. Flat Iron 40mmx6 mm kg 105.84 6.32 669.17

2103

M.S. Nut & Bolt 16 x 155 mm

full thread conforming to IS :

1364-2 (1992) or any

amendments up to date.

kg 162.00 3.67 594.86

21 02

M.S. Nut & Bolt 16x50 mm full

thread conforming to IS : 1

364- 2 (1992) or any

amendments up to date.

kg 162.00 2.34 378.43

2201 Aluminium Paint Lit 170.00 0.20 34.00

2203 Red Oxide Paint Lit 125.00 0.20 25.00

Total Cost of Materials 6,423.07

Contingency (2% on Material Cost) 128.46

Sub-Total 6,551.53

Labours

1001 Labour Skilled-I manday 380.00 1.37 519.33

1002 Labour Skilled-II manday 310.00 0.50 155.00

1003 Labour Semi-Skilled manday 250.00 0.53 133.33

1004 Labour Un-skilled manday 220.00 4.20 924.00

Total Cost of Labours 1,731.67

Total 8,283.19

Add 15% for overhead & Profit 1,242.48

Grand Total 9,525.67

Say 9,526.00

Supervision (15% on Labour Cost) 259.75

Page No -28-

Page 48: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FITTING OF CROSSARM

2.19 Providing and erection of 12 nos. of MS Channel Iron 75 mm X 40 mm X 6 mm (7.14Kg

per metre) triple pole crossarm for three wire 11 kV overhead line conductors complete

with through bolts and nuts for clamping to the poles including drilling of holes for

insulator pins/fitting bolts, nuts and washers etc and painting with primer and finished

paint as required (for SP-29) as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials 1401 M.S. Channel 75 x 40 x 6 mm kg 105.84 133.83 14,164.80

1405 M.S. Flat Iron 40mmx6 mm kg 105.84 18.97 2,007.51

21 03

M.S. Nut & Bolt 16 x 155 mm

full thread conforming to IS :

1364-2 (1992) or any

amendments up to date.

kg 162.00 11.02 1,784.59

21 02

M.S. Nut & Bolt 16x50 mm full

thread conforming to IS : 1

364- 2 (1992) or any

amendments up to date.

kg 162.00 7.01 1,135.30

2201 Aluminium Paint Lit 170.00 0.60 102.00

2203 Red Oxide Paint Lit 125.00 0.60 75.00

Total Cost of Materials 19,269.20

Contingency (2% on Material Cost) 385.38

Sub-Total 19,654.58

Labours

1001 Labour Skilled-I manday 380.00 5.00 1,900.00

1002 Labour Skilled-II manday 310.00 2.00 620.00

1003 Labour Semi-Skilled manday 250.00 2.00 500.00

1004 Labour Un-skilled manday 220.00 14.40 3,168.00

Total Cost of Labours 6,188.00

Total 25,842.58

Add 15% for overhead & Profit 3,876.39

Grand Total 29,718.97

Say 29,719.00

Supervision (15% on Labour Cost) 928.20

Page No -29-

Page 49: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FITTING OF CROSSARM

2.20 Providing and erection of 16 nos. of MS Channel Iron 75 mm X 40 mm X 6 mm (7.14Kg

per metre) four pole crossarm for three wire 11 kV overhead line conductors complete

with through bolts and nuts for clamping to the poles including drilling of holes for

insulator pins/fitting bolts, nuts and washers etc and painting with primer and finished

paint as required (for SP-29) as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials 1401 M.S. Channel 75 x 40 x 6 mm kg 105.84 178.44 18,886.39

1405 M.S. Flat Iron 40mmx6 mm kg 105.84 25.29 2,676.68

21 03

M.S. Nut & Bolt 16 x 155 mm

full thread conforming to IS :

1364-2 (1992) or any

amendments up to date.

kg 162.00 14.69 2,379.46

21 02

M.S. Nut & Bolt 16x50 mm full

thread conforming to IS : 1

364- 2 (1992) or any

amendments up to date.

kg 162.00 9.34 1,513.73

2201 Aluminium Paint Lit 170.00 0.80 136.00

2203 Red Oxide Paint Lit 125.00 0.80 100.00

Total Cost of Materials 25,692.26

Contingency (2% on Material Cost) 513.85

Sub-Total 26,206.11

Labours

1001 Labour Skilled-I manday 380.00 5.47 2,077.33

1002 Labour Skilled-II manday 310.00 2.00 620.00

1003 Labour Semi-Skilled manday 250.00 2.13 533.33

1004 Labour Un-skilled manday 220.00 16.80 3,696.00

Total Cost of Labours 6,926.67

Total 33,132.77

Add 15% for overhead & Profit 4,969.92

Grand Total 38,102.69

Say 38,103.00

Supervision (15% on Labour Cost) 1,039.00

Page No -30-

Page 50: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FITTING OF CROSSARM

2.21 Providing and erection of 2 nos. of MS Channel Iron 75 mmX 40mm X 6mm (7.14Kg

per metre) double pole crossarm for three wire 11 kV overhead line conductors

(horizontal formation) complete with through bolts and nuts for clamping to the poles

including drilling of holes for insulator pins/fitting bolts, nuts and washers etc and

painting with primer and finished paint as required including angle iron

reinforcement (for SP-35) as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials 1401 M.S. Channel 75 x 40 x 6 mm kg 105.84 34.56 3,657.58

1405 M.S. Flat Iron 40mmx6 mm kg 105.84 3.16 334.59

1403 M.S. Angle Iron 40x40x6 mm kg 105.84 45.94 4,861.87

21 03

M.S. Nut & Bolt 16 x 155 mm

full thread conforming to IS :

1364-2 (1992) or any

amendments up to date.

kg 162.00 5.20 842.72

21 02

M.S. Nut & Bolt 16x50 mm full

thread conforming to IS : 1

364- 2 (1992) or any

amendments up to date.

kg 162.00 1.17 189.22

2201 Aluminium Paint Lit 170.00 0.10 17.00

2203 Red Oxide Paint Lit 125.00 0.10 12.50

Total Cost of Materials 9,915.47

Contingency (2% on Material Cost) 198.31

Sub-Total 10,113.78

Labours

1001 Labour Skilled-I manday 380.00 0.68 259.67

1002 Labour Skilled-II manday 310.00 0.25 77.50

1003 Labour Semi-Skilled manday 250.00 0.27 66.67

1004 Labour Un-skilled manday 220.00 2.10 462.00

Total Cost of Labours 865.83

Total 10,979.61

Add 15% for overhead & Profit 1,646.94

Grand Total 12,626.56

Say 12,627.00

Supervision (15% on Labour Cost) 129.88

Page No -31-

Page 51: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FITTING OF CROSSARM

2.22 Providing and erection of 4 nos. of MS Channel Iron 75 mmX 40mm X6 mm (7.14Kg

per metre) double pole crossarm for three wire 11 kV overhead line conductors

(triangular formation) complete with through bolts and nuts for clamping to the

poles including drilling of holes for insulator pins/fitting bolts, nuts and washers

etc and painting with primer and finished paint as required (for SP-35) as directed

by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials 1401 M.S. Channel 75 x 40 x 6 mm kg 105.84 44.61 4,721.60

1405 M.S. Flat Iron 40mmx6 mm kg 105.84 6.32 669.17

21 03

M.S. Nut & Bolt 16 x 155 mm

full thread conforming to IS :

1364-2 (1992) or any

amendments up to date.

kg 162.00 3.67 594.86

21 02

M.S. Nut & Bolt 16x50 mm full

thread conforming to IS : 1 364-

2 (1992) or any amendments up

to date.

kg 162.00 2.34 378.43

2201 Aluminium Paint Lit 170.00 0.20 34.00

2203 Red Oxide Paint Lit 125.00 0.20 25.00

Total Cost of Materials 6,423.07

Contingency (2% on Material Cost) 128.46

Sub-Total 6,551.53

Labours

1001 Labour Skilled-I manday 380.00 1.37 519.33

1002 Labour Skilled-II manday 310.00 0.50 155.00

1003 Labour Semi-Skilled manday 250.00 0.53 133.33

1004 Labour Un-skilled manday 220.00 4.20 924.00

Total Cost of Labours 1,731.67

Total 8,283.19

Add 15% for overhead & Profit 1,242.48

Grand Total 9,525.67

Say 9,526.00

Supervision (15% on Labour Cost) 259.75

Page No -32-

Page 52: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FITTING OF CROSSARM

2.23 Providing and erection of 12 nos. of MS Channel Iron 75 mm X 40 mm X 6 mm (7.14Kg

per metre) triple pole crossarm for three wire 11 kV overhead line conductors complete

with through bolts and nuts for clamping to the poles including drilling of holes for

insulator pins/fitting bolts, nuts and washers etc and painting with primer and finished

paint as required (for SP-35) as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials 1401 M.S. Channel 75 x 40 x 6 mm kg 105.84 133.83 14,164.80

1405 M.S. Flat Iron 40mmx6 mm kg 105.84 18.97 2,007.51

21 03

M.S. Nut & Bolt 16 x 155 mm

full thread conforming to IS :

1364-2 (1992) or any

amendments up to date.

kg 162.00 11.02 1,784.59

2102

M.S. Nut & Bolt 16x50 mm full

thread conforming to IS : 1364-

2 (1992) or any amendments up

to date.

kg 162.00 7.01 1,135.30

2201 Aluminium Paint Lit 170.00 0.60 102.00

2203 Red Oxide Paint Lit 125.00 0.60 75.00

Total Cost of Materials 19,269.20

Contingency (2% on Material Cost) 385.38

Sub-Total 19,654.58

Labours

1001 Labour Skilled-I manday 380.00 5.00 1,900.00

1002 Labour Skilled-II manday 310.00 2.00 620.00

1003 Labour Semi-Skilled manday 250.00 2.00 500.00

1004 Labour Un-skilled manday 220.00 14.40 3,168.00

Total Cost of Labours 6,188.00

Total 25,842.58

Add 15% for overhead & Profit 3,876.39

Grand Total 29,718.97

Say 29,719.00

Supervision (15% on Labour Cost) 928.20

Page No -33-

Page 53: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FITTING OF CROSSARM

2.24 Providing and erection of 16 nos. of MS Channel Iron 75 mm X 40 mm X 6 mm (7.14Kg

per metre) four pole crossarm for three wire 11 kV overhead line conductors complete

with through bolts and nuts for clamping to the poles including drilling of holes for

insulator pins/fitting bolts, nuts and washers etc and painting with primer and

finished paint as required (for SP-35) as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials 1401 M.S. Channel 75 x 40 x 6 mm kg 105.84 178.44 18,886.39

1405 M.S. Flat Iron 40mmx6 mm kg 105.84 25.29 2,676.68

21 03

M.S. Nut & Bolt 16 x 155 mm

full thread conforming to IS :

1364-2 (1992) or any

amendments up to date.

kg 162.00 14.69 2,379.46

21 02

M.S. Nut & Bolt 16x50 mm full

thread conforming to IS : 1 364-

2 (1992) or any amendments up

to date.

kg 162.00 9.34 1,513.73

2201 Aluminium Paint Lit 170.00 0.80 136.00

2203 Red Oxide Paint Lit 125.00 0.80 100.00

Total Cost of Materials 25,692.26

Contingency (2% on Material Cost) 513.85

Sub-Total 26,206.11

Labours

1001 Labour Skilled-I manday 380.00 5.47 2,077.33

1002 Labour Skilled-II manday 310.00 2.00 620.00

1003 Labour Semi-Skilled manday 250.00 2.13 533.33

1004 Labour Un-skilled manday 220.00 16.80 3,696.00

Total Cost of Labours 6,926.67

Total 33,132.77

Add 15% for overhead & Profit 4,969.92

Grand Total 38,102.69

Say 38,103.00

Supervision (15% on Labour Cost) 1,039.00

Page No -34-

Page 54: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FITTING OF CROSSARM

2.25 Providing and erection of 2 nos. of MS Channel Iron 100 mm X 50 mm X 6 mm (9.56Kg

per metre) double pole crossarm for three wire 33 kV overhead line conductors

(horizontal formation) complete with through bolts and nuts for clamping to the poles

including drilling of holes for insulator pins/fitting bolts, nuts and washers etc and

painting with primer and finished paint as required including angle iron

reinforcement (for SP-35) as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials 1402 M.S. Channel 100 x 50 x 6 mm kg 105.84 65.41 6,922.94

1405 M.S. Flat Iron 40mmx6 mm kg 105.84 3.16 334.59

1403 M.S. Angle Iron 40x40x6 mm kg 105.84 57.12 6,045.90

21 03

M.S. Nut & Bolt 16 x 155 mm

full thread conforming to IS :

1364-2 (1992) or any

amendments up to date.

kg 162.00 5.20 842.72

21 02

M.S. Nut & Bolt 16x50 mm full

thread conforming to IS : 1 364-

2 (1992) or any amendments up

to date.

kg 162.00 1.17 189.22

2201 Aluminium Paint Lit 170.00 0.10 17.00

2203 Red Oxide Paint Lit 125.00 0.10 12.50

Total Cost of Materials 14,364.87

Contingency (2% on Material Cost) 287.30

Sub-Total 14,652.16 Labours

1001 Labour Skilled-I manday 380.00 0.68 259.67

1002 Labour Skilled-II manday 310.00 0.25 77.50

1003 Labour Semi-Skilled manday 250.00 0.27 66.67

1004 Labour Un-skilled manday 220.00 2.10 462.00

Total Cost of Labours 865.83

Total 15,518.00

Add 15% for overhead & Profit 2,327.70

Grand Total 17,845.70

Say 17,846.00

Supervision (15% on Labour Cost) 129.88

Page No -35-

Page 55: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FITTING OF CROSSARM

2.26 Providing and erection of 4 nos. of MS Channel Iron 100 mm X 50 mm X 6 mm

(9.56Kg per metre) double pole crossarm for three wire 33 kV overhead line

conductors (triangular formation) complete with through bolts and nuts for clamping

to the poles including drilling of holes for insulator pins/fitting bolts, nuts and

washers etc and painting with primer and finished paint as required (for SP-35) as

directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

1402 M.S. Channel 100 x 50 x 6 mm kg 105.84 78.98 8,358.73

1405 M.S. Flat Iron 40mmx6 mm kg 105.84 6.32 669.17

2103

M.S. Nut & Bolt 16 x 155 mm

full thread conforming to IS :

1364-2 (1992) or any

amendments up to date.

kg 162.00 3.67 594.86

2102

M.S. Nut & Bolt 16x50 mm full

thread conforming to IS : 1364-

2 (1992) or any amendments

up to date.

kg 162.00 2.34 378.43

2201 Aluminium Paint Lit 170.00 0.10 17.00

2203 Red Oxide Paint Lit 125.00 0.10 12.50

Total Cost of Materials 10,030.70

Contingency (2% on Material Cost) 200.61

Sub-Total 10,231.31

Labours

1001 Labour Skilled-I manday 380.00 1.37 519.33

1002 Labour Skilled-II manday 310.00 0.50 155.00

1003 Labour Semi-Skilled manday 250.00 0.53 133.33

1004 Labour Un-skilled manday 220.00 4.20 924.00

Total Cost of Labours 1,731.67

Total 11,962.98

Add 15% for overhead & Profit 1,794.45

Grand Total 13,757.42

Say 13,757.00

Supervision (15% on Labour Cost) 259.75

Page No -36-

Page 56: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FITTING OF CROSSARM

2.27 Providing and erection of 12 nos. of MS Channel Iron 100 mm X 50 mm X 6 mm (9.56Kg

per metre) triple pole crossarm for three wire 33 kV overhead line conductors complete

with through bolts and nuts for clamping to the poles including drilling of holes for

insulator pins/fitting bolts, nuts and washers etc and painting with primer and finished

paint as required (for SP-35) as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials 1402 M.S. Channel 100 x 50 x 6 mm kg 105.84 236.93 25,076.19

1405 M.S. Flat Iron 40mmx6 mm kg 105.84 18.97 2,007.51

21 03

M.S. Nut & Bolt 16 x 155 mm

full thread conforming to IS :

1364-2 (1992) or any

amendments up to date.

kg 162.00 11.02 1,784.59

21 02

M.S. Nut & Bolt 16x50 mm full

thread conforming to IS : 1 364-

2 (1992) or any amendments up

to date.

kg 162.00 7.01 1,135.30

2201 Aluminium Paint Lit 170.00 0.60 102.00

2203 Red Oxide Paint Lit 125.00 0.60 75.00

Total Cost of Materials 30,180.59

Contingency (2% on Material Cost) 603.61

Sub-Total 30,784.20

Labours

1001 Labour Skilled-I manday 380.00 5.00 1,900.00

1002 Labour Skilled-II manday 310.00 2.00 620.00

1003 Labour Semi-Skilled manday 250.00 2.00 500.00

1004 Labour Un-skilled manday 220.00 14.40 3,168.00

Total Cost of Labours 6,188.00

Total 36,972.20

Add 15% for overhead & Profit 5,545.83

Grand Total 42,518.03

Say 42,518.00

Supervision (15% on Labour Cost) 928.20

Page No -37-

Page 57: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FITTING OF CROSSARM

2.28 Providing and erection of 16 nos. of MS Channel Iron 100 mm X 50 mm X 6 mm (9.56Kg

per metre) four pole crossarm for three wire 33 kV overhead line conductors complete

with through bolts and nuts for clamping to the poles including drilling of holes for

insulator pins/fitting bolts, nuts and washers etc and painting with primer and finished

paint as required (for SP-35) as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

1 402 M.S. Channel 1 00 x 50 x 6 mm kg 1 05.84 31 5.90

33,434.92

1405 M.S. Flat Iron 40mmx6 mm kg 105.84 25.29 2,676.68

21 03

M.S. Nut & Bolt 16 x 155 mm

full thread conforming to IS :

1364-2 (1992) or any

amendments up to date.

kg 162.00 14.69 2,379.46

21 02

M.S. Nut & Bolt 16x50 mm full

thread conforming to IS : 1 364-

2 (1992) or any amendments up

to date.

kg 162.00 9.34 1,513.73

2201 Aluminium Paint Lit 170.00 0.60 102.00

2203 Red Oxide Paint Lit 125.00 0.60 75.00

Total Cost of Materials 40,181.79

Contingency (2% on Material Cost) 803.64

Sub-Total 40,985.43

Labours

1001 Labour Skilled-I manday 380.00 5.47 2,077.33

1002 Labour Skilled-II manday 310.00 2.00 620.00

1003 Labour Semi-Skilled manday 250.00 2.13 533.33

1004 Labour Un-skilled manday 220.00 16.80 3,696.00

Total Cost of Labours 6,926.67

Total 47,912.09

Add 15% for overhead & Profit 7,186.81

Grand Total 55,098.91

Say 55,099.00

Supervision (15% on Labour Cost) 1,039.00

Page No -38-

Page 58: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FITTING OF CROSSARM

2.29 Providing and erection of 2 nos. of MS Channel Iron 100 mm X 50 mm X 6 mm

(9.56Kg per metre) double pole crossarm for three wire 33 kV overhead line

conductors (horizontal formation) complete with through bolts and nuts for clamping

to the poles including drilling of holes for insulator pins/fitting bolts, nuts and

washers etc and painting with primer and finished paint as required including angle

iron reinforcement (for SP-58) as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials 1402 M.S. Channel 100 x 50 x 6 mm kg 105.84 65.41 6,922.94

1405 M.S. Flat Iron 40mmx6 mm kg 105.84 3.79 401.44

1403 M.S. Angle Iron 40x40x6 mm kg 105.84 57.32 6,066.85

2103

M.S. Nut & Bolt 16 x 155 mm

full thread conforming to IS :

1364-2 (1992) or any

amendments up to date.

kg 162.00 5.20 842.72

2102

M.S. Nut & Bolt 16x50 mm full

thread conforming to IS : 1364-

2 (1992) or any amendments up

to date.

kg 162.00 1.17 189.22

2201 Aluminium Paint Lit 170.00 0.10 17.00

2203 Red Oxide Paint Lit 125.00 0.10 12.50

Total Cost of Materials 14,452.68

Contingency (2% on Material Cost) 289.05

Sub-Total 14,741.73

Labours

1001 Labour Skilled-I manday 380.00 0.68 259.67

1002 Labour Skilled-II manday 310.00 0.25 77.50

1003 Labour Semi-Skilled manday 250.00 0.27 66.67

1004 Labour Un-skilled manday 220.00 2.10 462.00

Total Cost of Labours 865.83

Total 15,607.57

Add 15% for overhead & Profit 2,341.13

Grand Total 17,948.70

Say 17,949.00

Supervision (15% on Labour Cost) 129.88

Page No -39-

Page 59: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FITTING OF CROSSARM

2.30 Providing and erection of 4 nos. of MS Channel Iron 100 mm X 50 mm X 6 mm

(9.56Kg per metre) double pole crossarm for three wire 33 kV overhead line

conductors (triangular formation) complete with through bolts and nuts for clamping

to the poles including drilling of holes for insulator pins/fitting bolts, nuts and

washers etc and painting with primer and finished paint as required (for SP-58) as

directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials 1402 M.S. Channel 100 x 50 x 6 mm kg 105.84 78.98 8,358.73

1405 M.S. Flat Iron 40mmx6 mm kg 105.84 7.59 802.88

2103

M.S. Nut & Bolt 16 x 155 mm

full thread conforming to IS :

1364-2 (1992) or any

amendments up to date.

kg 162.00 3.67 594.86

21 02

M.S. Nut & Bolt 16x50 mm full

thread conforming to IS : 1

364- 2 (1992) or any

amendments up to date.

kg 162.00 2.34 378.43

2201 Aluminium Paint Lit 170.00 0.10 17.00

2203 Red Oxide Paint Lit 125.00 0.10 12.50

Total Cost of Materials 10,164.41

Contingency (2% on Material Cost) 203.29

Sub-Total 10,367.70

Labours

1001 Labour Skilled-I manday 380.00 1.37 519.33

1002 Labour Skilled-II manday 310.00 0.50 155.00

1003 Labour Semi-Skilled manday 250.00 0.53 133.33

1004 Labour Un-skilled manday 220.00 4.20 924.00

Total Cost of Labours 1,731.67

Total 12,099.36

Add 15% for overhead & Profit 1,814.90

Grand Total 13,914.27

Say 13,914.00

Supervision (15% on Labour Cost) 259.75

Page No -40-

Page 60: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FITTING OF CROSSARM

2.31 Providing and erection of 12 nos. of MS Channel Iron 100 mm X 50 mm X 6 mm (9.56Kg

per metre) triple pole crossarm for three wire 33 kV overhead line conductors complete

with through bolts and nuts for clamping to the poles including drilling of holes for

insulator pins/fitting bolts, nuts and washers etc and painting with primer and finished

paint as required (for SP-58) as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials 1402 M.S. Channel 100 x 50 x 6 mm kg 105.84 236.93 25,076.19

1405 M.S. Flat Iron 40mmx6 mm kg 105.84 22.76 2,408.65

21 03

M.S. Nut & Bolt 16 x 155 mm

full thread conforming to IS :

1364-2 (1992) or any

amendments up to date.

kg 162.00 11.02 1,784.59

21 02

M.S. Nut & Bolt 16x50 mm full

thread conforming to IS : 1 364-

2 (1992) or any amendments up

to date.

kg 162.00 7.01 1,135.30

2201 Aluminium Paint Lit 170.00 0.60 102.00

2203 Red Oxide Paint Lit 125.00 0.60 75.00

Total Cost of Materials 30,581.73

Contingency (2% on Material Cost) 611.63

Sub-Total 31,193.36 Labours

1001 Labour Skilled-I manday 380.00 5.00 1,900.00

1002 Labour Skilled-II manday 310.00 2.00 620.00

1003 Labour Semi-Skilled manday 250.00 2.00 500.00

1004 Labour Un-skilled manday 220.00 14.40 3,168.00

Total Cost of Labours 6,188.00

Total 37,381.36

Add 15% for overhead & Profit 5,607.20

Grand Total 42,988.57

Say 42,989.00

Supervision (15% on Labour Cost) 928.20

Page No -41-

Page 61: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FITTING OF CROSSARM

2.32 Providing and erection of 16 nos. of MS Channel Iron 100 mm X 50 mm X 6 mm (9.56Kg

per metre) four pole crossarm for three wire 33 kV overhead line conductors complete

with through bolts and nuts for clamping to the poles including drilling of holes for

insulator pins/fitting bolts, nuts and washers etc and painting with primer and finished

paint as required (for SP-58) as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials 1401 M.S. Channel 75 x 40 x 6 mm kg 105.84 315.90 33,434.92

1405 M.S. Flat Iron 40mmx6 mm kg 105.84 30.34 3,211.53

21 03

M.S. Nut & Bolt 16 x 155 mm

full thread conforming to IS :

1364-2 (1992) or any

amendments up to date.

kg 162.00 14.69 2,379.46

21 02

M.S. Nut & Bolt 16x50 mm full

thread conforming to IS : 1

364- 2 (1992) or any

amendments up to date.

kg 162.00 9.34 1,513.73

2201 Aluminium Paint Lit 170.00 0.60 102.00

2203 Red Oxide Paint Lit 125.00 0.60 75.00

Total Cost of Materials 40,716.64

Contingency (2% on Material Cost) 814.33

Sub-Total 41,530.97

Labours

1001 Labour Skilled-I manday 380.00 5.47 2,077.33

1002 Labour Skilled-II manday 310.00 2.00 620.00

1003 Labour Semi-Skilled manday 250.00 2.13 533.33

1004 Labour Un-skilled manday 220.00 16.80 3,696.00

Total Cost of Labours 6,926.67

Total 48,457.63

Add 15% for overhead & Profit 7,268.65

Grand Total 55,726.28

Say 55,726.00

Supervision (15% on Labour Cost) 1,039.00

Page No -42-

Page 62: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FITTING OF COMPLETE SET OF SHACKLE INSULATOR (Pin Type, 1ph 3 wire)

3.01 Providing and erection of shackle insulator for LT over head lines (1ph 3 wire) with

galvanised pin, nuts, washers etc as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

1806

Shackle Insulator (Pin/Strap

Type) 70x90 mm conforming to

IS : 1445 (1977) or any

amendments up to date

No 39.00 3.00 117.00

1808 Shackle Nut Bolt 12x100 kg 174.96 1.00 174.96

Total Cost of Materials 291.96

Contingency (2% on Material Cost) 5.84

Sub-Total 297.80 Labours

1001 Labour Skilled-I manday 380.00 0.00 0.00

1002 Labour Skilled-II manday 310.00 0.00 0.00

1003 Labour Semi-Skilled manday 250.00 0.08 20.00

1004 Labour Un-skilled manday 220.00 0.02 4.40

Total Cost of Labours 24.40

Total 322.20

Add 15% for overhead & Profit 48.33

Grand Total 370.53

Say 371.00

Supervision (15% on Labour Cost) 3.66

Page No -43-

Page 63: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FITTING OF COMPLETE SET OF SHACKLE INSULATOR (STRAP TYPE, 1ph 3 wire)

3.02 Providing and erection of shackle insulator (strap type) for LT over head lines (1ph 3

wire) with galvanised shackle pin, bolts, nuts, washers etc as directed by the

engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

1806

Shackle Insulator (Pin/Strap

Type) 70x90 mm conforming to

IS : 1445 (1977) or any

amendments up to date

No 39.00 6.00 234.00

1 807 Shackle Strap for 70x90 mm

Shackle Insulator Pair 14.00 3.00 42.00

1808 Shackle Nut Bolt 12x100 kg 174.96 1.00 174.96

Total Cost of Materials 450.96

Contingency (2% on Material Cost) 9.02

Sub-Total 459.98 Labours

1001 Labour Skilled-I manday 380.00 0.00 0.00

1002 Labour Skilled-II manday 310.00 0.00 0.00

1003 Labour Semi-Skilled manday 250.00 0.08 20.00

1004 Labour Un-skilled manday 220.00 0.02 4.40

Total Cost of Labours 24.40

Total 484.38

Add 15% for overhead & Profit 72.66

Grand Total 557.04

Say 557.00

Supervision (15% on Labour Cost) 3.66

Page No -44-

Page 64: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FITTING OF COMPLETE SET OF SHACKLE INSULATOR (Pin Type, 3ph 5 wire)

3.03 Providing and erection of shackle insulator for LT over head lines (3ph 5 wire) with

galvanised pin, nuts, washers etc as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

1 806

Shackle Insulator (Pin/Strap

Type) 70x90 mm conforming to

IS : 1445 (1977) or any

amendments up to date

No 39.00 5.00 195.00

1808 Shackle Nut Bolt 12x100 kg 174.96 1.00 174.96

Total Cost of Materials 369.96

Contingency (2% on Material Cost) 7.40

Sub-Total 377.36 Labours

1001 Labour Skilled-I manday 380.00 0.00 0.00

1002 Labour Skilled-II manday 310.00 0.00 0.00

1003 Labour Semi-Skilled manday 250.00 0.08 20.00

1004 Labour Un-skilled manday 220.00 0.02 4.40

Total Cost of Labours 24.40

Total 401.76

Add 15% for overhead & Profit 60.26

Grand Total 462.02

Say 462.00

Supervision (15% on Labour Cost) 3.66

Page No -45-

Page 65: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FITTING OF COMPLETE SET OF SHACKLE INSULATOR (STRAP TYPE, 3ph 5 wire)

3.04 Providing and erection of shackle insulator (strap type) for LT over head lines (3ph 5

wire) with galvanised shackle pin, bolts, nuts, washers etc as directed by the

engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

1806

Shackle Insulator (Pin/Strap

Type) 70x90 mm conforming to

IS : 1445 (1977) or any

amendments up to date

No 39.00 10.00 390.00

1807 Shackle Strap for 70x90 mm

Shackle Insulator Pair 14.00 5.00 70.00

1808 Shackle Nut Bolt 12x100 kg 174.96 1.00 174.96

Total Cost of Materials 634.96

Contingency (2% on Material Cost) 12.70

Sub-Total 647.66 Labours

1001 Labour Skilled-I manday 380.00 0.00 0.00

1002 Labour Skilled-II manday 310.00 0.00 0.00

1003 Labour Semi-Skilled manday 250.00 0.08 20.00

1004 Labour Un-skilled manday 220.00 0.02 4.40

Total Cost of Labours 24.40

Total 672.06

Add 15% for overhead & Profit 100.81

Grand Total 772.87

Say 773.00

Supervision (15% on Labour Cost) 3.66

Page No -46-

Page 66: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FITTING OF PIN INSULATOR (11kV)

3.05 Providing and erection of pin insulator for 11 kV over head lines with galvanised pin, nuts,

washers etc as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

1805

11kV Pin insulator with GI Pin

conforming IS : 731 (1971), IS :

2486 (1989), IS : 2544 (1973),

IS : 5350 (1973) or any

amendments up to date.

Set 354.00 3.00 1062.00

Total Cost of Materials 1062.00

Contingency (2% on Material Cost) 21.24

Sub-Total 1083.24 Labours

1001 Labour Skilled-I manday 380.00 0.00 0.00

1002 Labour Skilled-II manday 310.00 0.00 0.00

1003 Labour Semi-Skilled manday 250.00 0.08 20.83

1004 Labour Un-skilled manday 220.00 0.08 18.33

Total Cost of Labours 39.17

Total 1122.41

Add 15% for overhead & Profit 168.36

Grand Total 1290.77

Say 1291.00

Supervision (15% on Labour Cost) 5.88

Page No -47-

Page 67: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FITTING OF DISC INSULATOR (11kV)

3.06 Providing and erection of disc insulator, 45 kN (2 nos. as a set) for 11 kV over head

lines with insulator fittings, ball and socket type and complete with aluminium alloy

tension clamps, bolts, nuts, washers etc as directed by the engineer in charge.

Sl. No. Description Unit Rate/ Unit Qty. Amount

Materials

1801

Porcelain Disc Insulator, 45 kN,

conforming IS : 731 (1971), IS :

2486 (1989), IS : 2544 (1973),

IS : 5350 (1973) or any

amendments up to date.

No 519.00 2.00 1038.00

2002

Tension Clamp with hardware

strain fitting, 3-bolted type

complete with bolts, nuts, and

washer (Weasel)

No 445.00 1.00 445.00

Total Cost of Materials 1483.00

Contingency (2% on Material Cost) 29.66

Sub-Total 1512.66 Labours

1001 Labour Skilled-I manday 380.00 0.33 126.67

1002 Labour Skilled-II manday 310.00 0.03 8.16

1003 Labour Semi-Skilled manday 250.00 0.00 0.00

1004 Labour Un-skilled manday 220.00 0.66 144.63

Total Cost of Labours 279.45

Total 1792.11

Add 15% for overhead & Profit 268.82

Grand Total 2060.93

Say 2061.00

Supervision (15% on Labour Cost) 41.92

Page No -48-

Page 68: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FITTING OF PIN INSULATOR (33kV)

3.07 Providing and erection of pin insulator for 33 kV over head lines with galvanised pin, nuts,

washers etc as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

1804

33kV Pin insulator with GI Pin

conforming IS : 731 (1971), IS :

2486 (1989), IS : 2544 (1973),

IS : 5350 (1973) or any

amendments up to date.

Set 894.00 3.00 2682.00

Total Cost of Materials 2682.00

Contingency (2% on Material Cost) 53.64

Sub-Total 2735.64 Labours

1001 Labour Skilled-I manday 380.00 0.00 0.00

1002 Labour Skilled-II manday 310.00 0.00 0.00

1003 Labour Semi-Skilled manday 250.00 0.11 27.78

1004 Labour Un-skilled manday 220.00 0.11 24.44

Total Cost of Labours 52.22

Total 2787.86

Add 15% for overhead & Profit 418.18

Grand Total 3206.04

Say 3206.00

Supervision (15% on Labour Cost) 7.83

Page No -49-

Page 69: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FITTING OF DISC INSULATOR (33kV)

3.08 Providing and erection of disc insulator, 70 kN (3 nos. as a set) for 33 kV over head

lines with insulator fittings, ball and socket type and complete with aluminium alloy

tension clamps, bolts, nuts, washers etc as directed by the engineer in charge.

Sl. No. Description Unit Rate/ Unit Qty. Amount

Materials

1802

Porcelain Disc Insulator, 70 kN,

conforming IS : 731 (1971), IS :

2486 (1989), IS : 2544 (1973),

IS : 5350 (1973) or any

amendments up to date.

No 700.00 3.00 2100.00

2001

Tension Clamp with hardware

strain fitting, 4-bolted type

complete with bolts, nuts, and

washer (Racoon)

No 474.00 1.00 474.00

Total Cost of Materials 2574.00

Contingency (2% on Material Cost) 51.48

Sub-Total 2625.48 Labours

1001 Labour Skilled-I manday 380.00 0.33 126.67

1002 Labour Skilled-II manday 310.00 0.03 8.16

1003 Labour Semi-Skilled manday 250.00 0.00 0.00

1004 Labour Un-skilled manday 220.00 0.76 166.63

Total Cost of Labours 301.45

Total 2926.93

Add 15% for overhead & Profit 439.04

Grand Total 3365.97

Say 3366.00

Supervision (15% on Labour Cost) 45.22

Page No -50-

Page 70: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

Erection of LT Stay Set

4.01 Providing and erection of galvanised stay set for LT over head lines complete with 16

mm rod dia. with plate 30x30x0.8 cm, 7/14 SWG G.I. stay wire, LT guy insulator

(90x65mm) and stay bow in cement concrete 1:3:6 (1 cement : 3 coarse sand : 6

graded stone aggregate) foundation including excavation and refilling etc (for SP-17) as

directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

1901 G.I. Stay Set complete 16

mm rod dia. with plate

30x30x0.8 cm conforming to

IS : 7887 (1992) or any

amendments up to date.

Set 810.00 1.000 810.00

1905 Stay wire 7/14 SWG

conforming to IS : 2141

(1979), IS : 4826 (1979), IS

: 6594 (1974) or any

amendments up to date.

kg 118.50 1.673 198.30

1811 LT Guy insulator

(90x65mm) conforming to

IS : 5300 (1969) or any

amendments up to date.

No 28.50 1.000 28.50

2301 Cement cum 13,750.00 0.023 316.25

2302 River Sand cum 2,100.00 0.069 144.90

2303 Stone Aggregate 10-20 mm cum 1,890.00 0.138 260.82

Total Cost of Materials 1,758.77

Contingency (2% on Material Cost) 35.18

Sub-Total 1,793.95

Labours

1001 Labour Skilled-I manday 380.00 0.00 -

1002 Labour Skilled-II manday 310.00 0.48 147.62

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 3.31 728.10

Total Cost of Labours 875.71

Total 2,669.66

Add 15% for overhead & Profit 400.45

Grand Total 3,070.11

Say 3,070.00

Supervision (15% on Labour Cost) 131.36

Page No -51-

Page 71: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

Erection of LT Stay Set

4.02 Providing and erection of galvanised stay set for LT over head lines complete with 16

mm rod dia. with plate 30x30x0.8 cm, 7/14 SWG G.I. stay wire, LT guy insulator

(90x65mm) and stay bow in cement concrete 1:3:6 (1 cement : 3 coarse sand : 6

graded stone aggregate) foundation including excavation and refilling etc (for SP-29) as

directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

1901 G.I. Stay Set complete 16

mm rod dia. with plate

30x30x0.8 cm conforming to

IS : 7887 (1992) or any

amendments up to date.

Set 810.00 1.000 810.00

1905 Stay wire 7/14 SWG

conforming to IS : 2141

(1979), IS : 4826 (1979), IS

: 6594 (1974) or any

amendments up to date.

kg 118.50 1.805 213.86

1811 LT Guy insulator

(90x65mm) conforming to

IS : 5300 (1969) or any

amendments up to date.

No 28.50 1.000 28.50

2301 Cement cum 13,750.00 0.023 316.25

2302 River Sand cum 2,100.00 0.069 144.90

2303 Stone Aggregate 10-20 mm cum 1,890.00 0.138 260.82

Total Cost of Materials 1,774.33

Contingency (2% on Material Cost) 35.49

Sub-Total 1,809.82

Labours

1001 Labour Skilled-I manday 380.00 0.00 -

1002 Labour Skilled-II manday 310.00 0.48 147.62

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 3.31 728.10

Total Cost of Labours 875.71

Total 2,685.53

Add 15% for overhead & Profit 402.83

Grand Total 3,088.36

Say 3,088.00

Supervision (15% on Labour Cost) 131.36

Page No -52-

Page 72: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

Erection of LT Stay Set

4.03 Providing and erection of galvanised stay set for LT over head lines complete with 16

mm rod dia. with plate 30x30x0.8 cm,7/14 SWG G.I. stay wire, LT guy insulator

(90x65mm) and stay bow in cement concrete 1:3:6 (1 cement : 3 coarse sand : 6

graded stone aggregate) foundation including excavation and refilling etc (for pre-

stressed concrete, 8.5 m height) as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

1901 G.I. Stay Set complete 16

mm rod dia. with plate

30x30x0.8 cm conforming to

IS : 7887 (1992) or any

amendments up to date.

Set 810.00 1.000 810.00

1905 Stay wire 7/14 SWG

conforming to IS : 2141

(1979), IS : 4826 (1979), IS

: 6594 (1974) or any

amendments up to date.

kg 118.50 1.673 198.30

1811 LT Guy insulator

(90x65mm) conforming to

IS : 5300 (1969) or any

amendments up to date.

No 28.50 1.000 28.50

2301 Cement cum 13,750.00 0.023 316.25

2302 River Sand cum 2,100.00 0.069 144.90

2303 Stone Aggregate 10-20 mm cum 1,890.00 0.138 260.82

Total Cost of Materials 1,758.77

Contingency (2% on Material Cost) 35.18

Sub-Total 1,793.95

Labours

1001 Labour Skilled-I manday 380.00 0.00 -

1002 Labour Skilled-II manday 310.00 0.48 147.62

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 3.31 728.10

Total Cost of Labours 875.71

Total 2,669.66

Add 15% for overhead & Profit 400.45

Grand Total 3,070.11

Say 3,070.00

Supervision (15% on Labour Cost) 131.36

Page No -53-

Page 73: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

Erection of LT Stay Set

4.04 Providing and erection of galvanised stay set for LT over head lines complete with 16

mm rod dia. with plate 30x30x0.8 cm, 7/14 SWG G.I. stay wire, LT guy insulator

(90x65mm) and stay bow in cement concrete 1:3:6 (1 cement : 3 coarse sand : 6

graded stone aggregate) foundation including excavation and refilling etc (for pre-

stressed concrete, 9.75 m height) as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

1901 G.I. Stay Set complete 16

mm rod dia. with plate

30x30x0.8 cm conforming to

IS : 7887 (1992) or any

amendments up to date.

Set 810.00 1.000 810.00

1905 Stay wire 7/14 SWG

conforming to IS : 2141

(1979), IS : 4826 (1979), IS

: 6594 (1974) or any

amendments up to date.

kg 118.50 1.925 228.10

1811 LT Guy insulator

(90x65mm) conforming to IS

: 5300 (1969) or any

amendments up to date.

No 28.50 1.000 28.50

2301 Cement cum 13,750.00 0.023 316.25

2302 River Sand cum 2,100.00 0.069 144.90

2303 Stone Aggregate 10-20 mm cum 1,890.00 0.138 260.82

Total Cost of Materials 1,788.57

Contingency (2% on Material Cost) 35.77

Sub-Total 1,824.34

Labours

1001 Labour Skilled-I manday 380.00 0.00 -

1002 Labour Skilled-II manday 310.00 0.48 147.62

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 3.31 728.10

Total Cost of Labours 875.71

Total 2,700.05

Add 15% for overhead & Profit 405.01

Grand Total 3,105.06

Say 3,105.00

Supervision (15% on Labour Cost) 131.36

Page No -54-

Page 74: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

Erection of 11 kV Stay Set

4.05 Providing and erection of galvanised stay set for 11 kV over head lines complete with 19

mm rod dia. with plate 30x30x0.8 cm, 7/12 SWG G.I. stay wire, 11kV guy insulator

(140x85mm) and stay bow in cement concrete 1:3:6 (1 cement: 3 coarse sand : 6

graded stone aggregate) foundation including excavation and refilling etc (for SP-29) as

directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

1902 G.I. Stay set complete 19

mm rod dia. with plate

30x30x0.8 cm conforming to

IS : 7887 (1992) or any

amendments up to date.

Set 1,407.00 1.000 1,407.00

1904 Stay wire 7/12 SWG

conforming to IS : 2141

(1979), IS : 4826 (1979), IS

: 6594 (1974) or any

amendments up to date.

kg 112.50 2.899 326.17

1809 11kV Guy insulator

(140x85mm) conforming to

IS : 5300 (1969) or any

amendments up to date.

No 57.00 1.000 57.00

2301 Cement cum 13,750.00 0.023 316.25

2302 River Sand cum 2,100.00 0.069 144.90

2303 Stone Aggregate 10-20 mm cum 1,890.00 0.138 260.82

Total Cost of Materials 2,512.14

Contingency (2% on Material Cost) 50.24

Sub-Total 2,562.38

Labours

1001 Labour Skilled-I manday 380.00 0.00 -

1002 Labour Skilled-II manday 310.00 0.48 147.62

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 3.31 728.10

Total Cost of Labours 875.71

Total 3,438.10

Add 15% for overhead & Profit 515.71

Grand Total 3,953.81

Say 3,954.00

Supervision (15% on Labour Cost) 131.36

Page No -55-

Page 75: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

Erection of 11 kV Stay Set

4.06 Providing and erection of galvanised stay set for 11 kV over head lines complete with 19

mm rod dia. with plate 30x30x0.8 cm, 7/12 SWG G.I. stay wire, 11kV guy insulator

(140x85mm) and stay bow in cement concrete 1:3:6 (1 cement: 3 coarse sand : 6

graded stone aggregate) foundation including excavation and refilling etc (for SP-35) as

directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

1902 G.I. Stay set complete 19

mm rod dia. with plate

30x30x0.8 cm conforming to

IS : 7887 (1992) or any

amendments up to date.

Set 1,407.00 1.000 1,407.00

1904 Stay wire 7/12 SWG

conforming to IS : 2141

(1979), IS : 4826 (1979), IS

: 6594 (1974) or any

amendments up to date.

kg 112.50 2.854 321.09

1809 11kV Guy insulator

(140x85mm) conforming to

IS : 5300 (1969) or any

amendments up to date.

No 57.00 1.000 57.00

2301 Cement cum 13,750.00 0.023 316.25

2302 River Sand cum 2,100.00 0.069 144.90

2303 Stone Aggregate 10-20 mm cum 1,890.00 0.138 260.82

Total Cost of Materials 2,507.06

Contingency (2% on Material Cost) 50.14

Sub-Total 2,557.20

Labours

1001 Labour Skilled-I manday 380.00 0.00 -

1002 Labour Skilled-II manday 310.00 0.48 147.62

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 3.31 728.10

Total Cost of Labours 875.71

Total 3,432.91

Add 15% for overhead & Profit 514.94

Grand Total 3,947.85

Say 3,948.00

Supervision (15% on Labour Cost) 131.36

Page No -56-

Page 76: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

Erection of 33 kV Stay Set

4.07 Providing and erection of galvanised stay set for 33 kV over head lines complete with 19

mm rod dia. with plate 40x40x0 .8 cm,7/ 10 SWG G.I. stay wire, 33kV guy insulator

(140x85mm) and stay bow in cement concrete 1:3:6 (1 cement: 3 coarse sand: 6

graded stone aggregate) foundation including excavation and refilling etc (for SP-35) as

directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

1903 G.I. Stay set complete 19

mm rod dia. with plate

40x40x0.8 cm conforming to

IS : 7887 (1992) or any

amendments up to date.

Set 1,694.00 1.000 1,694.00

1907

Stay wire 7/10 SWG

conforming to IS : 2141

(1979), IS : 4826 (1979), IS

: 6594 (1974) or any

amendments up to date.

kg 116.00 3.874 449.40

1810 33kV Guy insulator

(140x85mm) conforming to

IS : 5300 (1969) or any

amendments up to date.

No 57.00 1.000 57.00

2301 Cement cum 13,750.00 0.023 316.25

2302 River Sand cum 2,100.00 0.069 144.90

2303 Stone Aggregate 10-20 mm cum 1,890.00 0.138 260.82

Total Cost of Materials 2,922.37

Contingency (2% on Material Cost) 58.45

Sub-Total 2,980.82

Labours

1001 Labour Skilled-I manday 380.00 0.00 -

1002 Labour Skilled-II manday 310.00 0.48 147.62

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 3.31 728.10

Total Cost of Labours 875.71

Total 3,856.54

Add 15% for overhead & Profit 578.48

Grand Total 4,435.02

Say 4,435.00

Supervision (15% on Labour Cost) 131.36

Page No -57-

Page 77: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

Erection of 33 kV Stay Set

4.08 Providing and erection of galvanised stay set for 33 kV over head lines complete with 19

mm rod dia. with plate 40x40x0 .8 cm ,7/ 10 SWG G.I. stay wire ,33kV guy insulator

(140x85mm) and stay bow in cement concrete 1:3:6 (1 cement: 3 coarse sand : 6

graded stone aggregate) foundation including excavation and refilling etc (for SP-58) as

directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

1903 G.I. Stay set complete 19

mm rod dia. with plate

40x40x0.8 cm conforming to

IS : 7887 (1992) or any

amendments up to date.

Set 1,694.00 1.000 1,694.00

1907

Stay wire 7/10 SWG

conforming to IS : 2141

(1979), IS : 4826 (1979), IS

: 6594 (1974) or any

amendments up to date.

kg 116.00 5.420 628.77

1810 33kV Guy insulator

(140x85mm) conforming to

IS : 5300 (1969) or any

amendments up to date.

No 57.00 1.000 57.00

2301 Cement cum 13,750.00 0.023 316.25

2302 River Sand cum 2,100.00 0.069 144.90

2303 Stone Aggregate 10-20 mm cum 1,890.00 0.138 260.82

Total Cost of Materials 3,101.74

Contingency (2% on Material Cost) 62.03

Sub-Total 3,163.77

Labours

1001 Labour Skilled-I manday 380.00 0.00 -

1002 Labour Skilled-II manday 310.00 0.48 147.62

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 3.31 728.10

Total Cost of Labours 875.71

Total 4,039.49

Add 15% for overhead & Profit 605.92

Grand Total 4,645.41

Say 4,645.00

Supervision (15% on Labour Cost) 131.36

Page No -58-

Page 78: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

Page No -59-

Page 79: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

Page No -60-

Page 80: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

Page No -61-

Page 81: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

Page No -62-

Page 82: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

Page No -63-

Page 83: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

PROVIDING AND FITTING OF PG CLAMP

5.06 Providing and fitting of PG Clamps for Gnat Conductor jumpering of LT line per

number as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

2005 P.G. Clamp for Gnat

conductor (2 bolted type)

No 72.00 1 72.00

Total Cost of Materials 72.00

Contingency (2% on Material Cost) 1.44

Sub-Total 73.44

Labours

1001 Labour Skilled-I manday 380.00 0.00 -

1002 Labour Skilled-II manday 310.00 0.07 21.70

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 0.07 15.40

Total Cost of Labours 37.10

Total 110.54

Add 15% for overhead & Profit 16.58

Grand Total 127.12

Say 127.00

Supervision (15% on Labour Cost) 5.57

Page No -64-

Page 84: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

PROVIDING AND FITTING OF PG CLAMP

5.07 Providing and fitting of PG Clamps for Ant Conductor jumpering of LT line per

number as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

2004 P.G. Clamp for Ant

conductor (2 bolted type)

No 79.00 1 79.00

Total Cost of Materials 79.00

Contingency (2% on Material Cost) 1.58

Sub-Total 80.58

Labours

1001 Labour Skilled-I manday 380.00 0.00 -

1002 Labour Skilled-II manday 310.00 0.07 21.70

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 0.07 15.40

Total Cost of Labours 37.10

Total 117.68

Add 15% for overhead & Profit 17.65

Grand Total 135.33

Say 135.00

Supervision (15% on Labour Cost) 5.57

Page No -65-

Page 85: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

PROVIDING AND FITTING OF PG CLAMP

5.08 Providing and fitting of PG Clamps for Grasshopper Conductor jumpering of LT line

per number as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

2003 P.G. Clamp for

Grasshopper conductor

(3 bolted type)

No 82.00 1 82.00

Total Cost of Materials 82.00

Contingency (2% on Material Cost) 1.64

Sub-Total 83.64

Labours

1001 Labour Skilled-I manday 380.00 0.00 -

1002 Labour Skilled-II manday 310.00 0.07 21.70

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 0.07 15.40

Total Cost of Labours 37.10

Total 120.74

Add 15% for overhead & Profit 18.11

Grand Total 138.85

Say 139.00

Supervision (15% on Labour Cost) 5.57

Page No -66-

Page 86: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

PROVIDING AND FITTING OF PG CLAMP

5.09 Providing and fitting of PG Clamps for Weasel Conductor jumpering of 11kV line per

number as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

2006 P.G. Clamp for Weasel

conductor (3 bolted type)

No 75.00 1 75.00

Total Cost of Materials 75.00

Contingency (2% on Material Cost) 1.50

Sub-Total 76.50

Labours

1001 Labour Skilled-I manday 380.00 0.00 -

1002 Labour Skilled-II manday 310.00 0.10 31.00

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 0.10 22.00

Total Cost of Labours 53.00

Total 129.50

Add 15% for overhead & Profit 19.43

Grand Total 148.93

Say 149.00

Supervision (15% on Labour Cost) 7.95

Page No -67-

Page 87: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

PROVIDING AND FITTING OF PG CLAMP

5.10 Providing and fitting of PG Clamps for Racoon Conductor jumpering of 33kV line per

number as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

2007 P.G. Clamp for Racoon

conductor (3 bolted type)

No 112.50 1 112.50

Total Cost of Materials 112.50

Contingency (2% on Material Cost) 2.25

Sub-Total 114.75

Labours

1001 Labour Skilled-I manday 380.00 0.00 -

1002 Labour Skilled-II manday 310.00 0.10 31.00

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 0.10 22.00

Total Cost of Labours 53.00

Total 167.75

Add 15% for overhead & Profit 25.16

Grand Total 192.91

Say 193.00

Supervision (15% on Labour Cost) 7.95

Page No -68-

Page 88: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

PROVIDING & FITTING OF JOINTING SLEEVE

5.11 Providing and fitting of Jointing Sleeve for Weasel Conductor for 1 1kV line per

number as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

2008 Jointing Sleeve for

Weasel conductor

No 265.00 1 265.00

Total Cost of Materials 265.00

Contingency (2% on Material Cost) 5.30

Sub-Total 270.30

Labours

1001 Labour Skilled-I manday 380.00 0.00 -

1002 Labour Skilled-II manday 310.00 0.10 31.00

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 0.10 22.00

Total Cost of Labours 53.00

Total 323.30

Add 15% for overhead & Profit 48.50

Grand Total 371.80

Say 372.00

Supervision (15% on Labour Cost) 7.95

Page No -69-

Page 89: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

PROVIDING & FITTING OF JOINTING SLEEVE

5.12 Providing and fitting of Jointing Sleeve for Racoon Conductor for 33kV line per

number as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

2009 Jointing Sleeve for

Racoon conductor

No 354.00 1 354.00

Total Cost of Materials 354.00

Contingency (2% on Material Cost) 7.08

Sub-Total 361.08

Labours

1001 Labour Skilled-I manday 380.00 0.00 -

1002 Labour Skilled-II manday 310.00 0.10 31.00

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 0.10 22.00

Total Cost of Labours 53.00

Total 414.08

Add 15% for overhead & Profit 62.11

Grand Total 476.19

Say 476.00

Supervision (15% on Labour Cost) 7.95

Page No -70-

Page 90: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

LT POLE EARTHING

6.01 Providing and fitting of 2 m long, 19 mm diameter galvanized steel rod

fabricated for LT Pole Earthing, with accessories such as terminal connector, 8

SWG G.I. wire etc as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

2502

Galvanized steel rod, 2 M

length, 19 mm dia

connected with GI Wire

complete with terminal

connector

No 850.00 1.00 850.00

1906

G.I Wire 8 SWG for earth

wire conforming to IS : 280

(1978), IS : 7887 (1992) or

any amendments up to

date.

kg 112.50 2.00 225.00

Total Cost of Materials 1,075.00

Contingency (2% on Material Cost) 21.50

Sub-Total 1,096.50

Labours

1001 Labour Skilled-I manday 380.00 0.00 -

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.07 16.67

1004 Labour Un-skilled manday 220.00 0.12 25.67

Total Cost of Labours 42.33

Total 1,138.83

Add 15% for overhead & Profit 170.83

Grand Total 1,309.66

Say 1,310.00

Supervision (15% on Labour Cost) 6.35

Page No -71-

Page 91: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

11/33 kV POLE EARTHING

6.02 Providing and fitting of 2.5 m long, 40 mm diameter, 8 mm thick G.I. Earth Pipe

fabricated for 11 kV and 33 kV Pole Earthing, with accessories such as terminal

connector, bentonite powder, 8 SWG G.I. wire etc as directed by the engineer in

charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

2503 GI Earth pipe 2.5 metre long

40 mm dia with 8 mm

thickness fabricated for pole

earthing complete with

terminal connector

No 543.00 1.00 543.00

1906 G.I Wire 8 SWG for earth

wire conforming to IS : 280

(1978), IS : 7887 (1992) or

any amendments up to

date.

kg 112.50 2.00 225.00

2305 Bentonite Powder kg 30.00 50.00 1,500.00

Total Cost of Materials 2,268.00

Contingency (2% on Material Cost) 45.36

Sub-Total 2,313.36

Labours

1001 Labour Skilled-I manday 380.00 0.00 -

1002 Labour Skilled-II manday 310.00 0.10 31.00

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 1.20 264.00

Total Cost of Labours 295.00

Total 2,608.36

Add 15% for overhead & Profit 391.25

Grand Total 2,999.61

Say 3,000.00

Supervision (15% on Labour Cost) 44.25

Page No -72-

Page 92: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

DISTRIBUTION TRANSFORMER SUB-STATION OR 11KV CT PT COMBINATION

EARTHING

6.03 Providing and fitting of 2.5 m long, 40 mm diameter, 8 mm thick G.I. Earth

Pipe fabricated for Distribution Transformer Substation as per REC

Construction Standard F-5 Earthing, with accessories such as terminal

connector, bentonite powder, 8 SWG G.I. wire etc. as directed by the

engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

2503 GI Earth pipe 2.5 metre long

40 mm dia with 8 mm

thickness fabricated for pole

earthing complete with

terminal connector

No 543.00 3.00 1,629.00

1906 G.I Wire 8 SWG for earth

wire conforming to IS : 280

(1978), IS : 7887 (1992) or

any amendments up to

date.

kg 112.50 4.00 450.00

2305 Bentonite Powder kg 30.00 300.00 9,000.00

Total Cost of Materials 11,079.00

Contingency (2% on Material Cost) 221.58

Sub-Total 11,300.58

Labours

1001 Labour Skilled-I manday 380.00 0.00 -

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.10 25.00

1004 Labour Un-skilled manday 220.00 3.93 865.33

Total Cost of Labours 890.33

Total 12,190.91

Add 15% for overhead & Profit 1,828.64

Grand Total 14,019.55

Say 14,020.00

Supervision (15% on Labour Cost) 133.55

Page No -73-

Page 93: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FITTING OF LIGHTNING SPIKE

7.01 Providing and fitting of Lightning Spike made of iron rod,10 mm diameter, 1.5 m

length, 1 kg welded with MS Flat iron 40x5mm, 0.5kg and 8 SWG GI wire 2.5kg, as

directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

2501 Lightning Spike made of

iron rod,10 mm size, 1.5

m length, 1 kg welded

with MS Flat iron

40x5mm, 0.5kg and 8

SWG GI wire 2.5kg

No 500.00 1.00 500.00

Total Cost of Materials 500.00

Contingency (2% on Material Cost) 10.00

Sub-Total 510.00

Labours

1001 Labour Skilled-I manday 380.00 0.00 -

1002 Labour Skilled-II manday 310.00 0.33 103.33

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 1.00 220.00

Total Cost of Labours 323.33

Total 833.33

Add 15% for overhead & Profit 125.00

Grand Total 958.33

Say 958.00

Supervision (15% on Labour Cost) 48.50

Page No -74-

Page 94: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FITTING OF LIGHTNING ARRESTER

7.02 Providing and erection of 0.280 kV, 2.5 kA Lightning Arrester conforming to IS:

3070 and IEC: 60099-4 for LT Line complete with Hard drawn standard

aluminium conductors galvanised steel wire reinforced: ACSR 6/1/2.59 mm

Weasel, M.S. Flat Iron of size 40x6 mm and M.S. Nuts & Bolts of size 16x50

mm full thread, as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

1503 Lightning Arrester 0.280

kV, 2.5 KA for LT Line

No 657.00 1.00 657.00

1205 Hard drawn standard

aluminium conductors

galvanized steelwire

reinforced conforming

to IS 398(Part-II) with

amendment No. 1, 2

and 3 or the latest

version thereof bearing

ISI mark :ACSR

6/1/2.59mm Weasel.

KM 25,692.00 0.01 128.46

1405 M.S. Flat Iron 40mmx6

mm

kg 105.84 0.25 26.46

2102 M.S. Nut & Bolt 16x50

mm full thread

conforming to IS : 1364-

2 (1992) or any

amendments up to date.

kg 162.00 0.25 40.50

Total Cost of Materials 852.42

Contingency (2% on Material Cost) 17.05

Sub-Total 869.47

Labours

1001 Labour Skilled-I manday 380.00 0.00 -

1002 Labour Skilled-II manday 310.00 0.17 51.67

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 0.17 36.67

Total Cost of Labours 88.33

Total 957.80

Add 15% for overhead & Profit 143.67

Grand Total 1,101.47

Say 1,101.00

Supervision (15% on Labour Cost) 13.25

Page No -75-

Page 95: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FITTING OF LIGHTNING ARRESTER

7.03 Providing and erection of 9 kV, 5 kA Lightning Arrester conforming to IS: 3070

and IEC: 60099-4 complete with Hard drawn standard aluminium conductors

galvanised steel wire reinforced: ACSR 6/1/2.59 mm Weasel, M.S. Flat Iron of

size 40x6 mm and M.S. Nuts & Bolts of size 16x50 mm full thread, as directed

by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

1502 Lightning Arrester 9 kV,

5 KA

No 1,875.00 1.00 1,875.00

1205 Hard drawn standard

aluminium conductors

galvanized steelwire

reinforced conforming

to IS 398(Part-II) with

amendment No. 1, 2

and 3 or the latest

version thereof bearing

ISI mark :ACSR

6/1/2.59mm Weasel.

KM 25,692.00 0.01 128.46

1405 M.S. Flat Iron 40mmx6

mm

kg 105.84 0.25 26.46

2102 M.S. Nut & Bolt 16x50

mm full thread

conforming to IS : 1364-

2 (1992) or any

amendments up to date.

kg 162.00 0.25 40.50

Total Cost of Materials 2,070.42

Contingency (2% on Material Cost) 41.41

Sub-Total 2,111.83

Labours

1001 Labour Skilled-I manday 380.00 0.00 -

1002 Labour Skilled-II manday 310.00 0.17 51.67

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 0.17 36.67

Total Cost of Labours 88.33

Total 2,200.16

Add 15% for overhead & Profit 330.02

Grand Total 2,530.19

Say 2,530.00

Supervision (15% on Labour Cost) 13.25

Page No -76-

Page 96: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FITTING OF LIGHTNING ARRESTER

7.04 Providing and erection of 9 kV, 10 kA Lightning Arrester conforming to IS: 3070

and IEC: 60099-4 complete with Hard drawn stranded aluminium conductors

galvanised steel wire reinforced: ACSR 6/1/2.59 mm Weasel,M.S. Flat Iron of

size 40x6 mm and M.S. Nuts & Bolts of size 16x50 mm full thread, as directed

by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

1501 Lightning Arrester 9kV,

10kA Station Class-II as

per IEC:60099-4 &

IS:3070 specification

No 12,500.00 1.00 12,500.00

1205 Hard drawn standard

aluminium conductors

galvanized steelwire

reinforced conforming

to IS 398(Part-II) with

amendment No. 1, 2

and 3 or the latest

version thereof bearing

ISI mark :ACSR

6/1/2.59mm Weasel.

KM 25,692.00 0.01 128.46

1405 M.S. Flat Iron 40mmx6

mm

kg 105.84 0.25 26.46

2102 M.S. Nut & Bolt 16x50

mm full thread

conforming to IS : 1364-

2 (1992) or any

amendments up to date.

kg 162.00 0.25 40.50

Total Cost of Materials 12,695.42

Contingency (2% on Material Cost) 253.91

Sub-Total 12,949.33

Labours

1001 Labour Skilled-I manday 380.00 0.00 -

1002 Labour Skilled-II manday 310.00 0.17 51.67

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 0.17 36.67

Total Cost of Labours 88.33

Total 13,037.66

Add 15% for overhead & Profit 1,955.65

Grand Total 14,993.31

Say 14,993.00

Supervision (15% on Labour Cost) 13.25

Page No -77-

Page 97: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

INSTALLATION AND FITTING OF DISTRIBUTION TRANSFORMER

8.01 Providing and installation of Outdoor type, oil immersed, naturally cooled 3ph, 50 Hz, Al

wound Distribution Transformer of vector group DYn-1 1 conforming to IS: 1180 (1964),

IS: 2026 (1962) or any amendments there of and ISI marked of the capacity 25 kVA,

11/0.415 kV as directed by the engineer in charge. The transformer should be installed

at an appropriate height to facilitate safety working clearance as specified in Schedule

VII of the CEA (Measures relating to Safety and Electric Supply Regulations), 2010.

Sl. No. Description Unit Rate/Unit Qty. Amount

Material

1301

Out door type oil

immersed naturally cooled

3-ph, 50Hz Al-wound

Distribution Transformer

of vector group DYn-1 1

conforming to IS : 1180

(1964) and IS : 2026

(1962) or latest version

thereof and ISI marked of

the following capacity 25

kVA 11/0.415 kV

No 68,850.00 1.00 68,850.00

Total Cost of Materials 68,850.00

Contingency (2% on Material Cost) 1,377.00

Sub-Total 70,227.00

Labours

1001 Labour Skilled-I manday 380.00 1.00 380.00

1002 Labour Skilled-II manday 310.00 1.50 465.00

1003 Labour Semi-Skilled manday 250.00 1.00 250.00

1004 Labour Un-skilled manday 220.00 12.00 2,640.00

Total Cost of Labours 3,735.00

Total 73,962.00

Add 15% for overhead & Profit 11,094.30

Grand Total 85,056.30

Say 85,056.00

Supervision (15% on Labour Cost) 560.25

Page No -78-

Page 98: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

INSTALLATION AND FITTING OF DISTRIBUTION TRANSFORMER

8.02 Providing and installation of Outdoor type, oil immersed, naturally cooled 3ph, 50 Hz, Al

wound Distribution Transformer of vector group DYn-1 1 conforming to IS: 1180 (1964)

and IS: 2026 (1962) or any amendments there of and ISI marked of the capacity 63 kVA,

11/0.415 kV as directed by the engineer in charge. The transformer should be installed

at an appropriate height to facilitate safety working clearance as specified in Schedule

VII of the CEA (Measures relating to Safety and Electric Supply Regulations), 2010.

Sl. No. Description Unit Rate/Unit Qty. Amount

Material

1302

Out door type oil

immersed naturally cooled

3-ph, 50Hz Al-wound

Distribution Transformer

of vector group DYn-11

conforming to IS : 1180

(1964) and IS : 2026

(1962) or latest version

thereof and ISI marked of

the following capacity 63

kVA 11/0.415 kV

No 122,850.00 1.00 122,850.00

Total Cost of Materials 122,850.00

Contingency (2% on Material Cost) 2,457.00

Sub-Total 125,307.00

Labours

1001 Labour Skilled-I manday 380.00 1.00 380.00

1002 Labour Skilled-II manday 310.00 1.50 465.00

1003 Labour Semi-Skilled manday 250.00 1.00 250.00

1004 Labour Un-skilled manday 220.00 16.00 3,520.00

Total Cost of Labours 4,615.00

Total 129,922.00

Add 15% for overhead & Profit 19,488.30

Grand Total 149,410.30

Say 149,410.00

Supervision (15% on Labour Cost) 692.25

Page No -79-

Page 99: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

INSTALLATION AND FITTING OF DISTRIBUTION TRANSFORMER

8.03 Providing and installation of Outdoor type, oil immersed, naturally cooled 3ph, 50 Hz, Al

wound Distribution Transformer of vector group DYn-1 1 conforming to IS: 1180 (1964)

and IS: 2026 (1962) or any amendments there of and ISI marked of the capacity 100 kVA,

11/0.415 kV as directed by the engineer in charge. The transformer should be installed at

an appropriate height to facilitate safety working clearance as specified in Schedule VII of

the CEA (Measures relating to Safety and Electric Supply Regulations), 2010.

Sl. No. Description Unit Rate/Unit Qty. Amount

Material

1303

Out door type oil

immersed naturally cooled

3-ph, 50Hz Al-wound

Distribution Transformer

of vector group DYn- 11

conforming to IS : 1180

(1964) and IS : 2026

(1962) or latest version

thereof and ISI marked of

the following capacity 100

kVA 11/0.415 kV

No 179,887.50 1.00 179,887.50

Total Cost of Materials 179,887.50

Contingency (2% on Material Cost) 3,597.75

Sub-Total 183,485.25

Labours

1001 Labour Skilled-I manday 380.00 1.00 380.00

1002 Labour Skilled-II manday 310.00 1.50 465.00

1003 Labour Semi-Skilled manday 250.00 1.00 250.00

1004 Labour Un-skilled manday 220.00 18.00 3,960.00

Total Cost of Labours 5,055.00

Total 188,540.25

Add 15% for overhead & Profit 28,281.04

Grand Total 216,821.29

Say 216,821.00

Supervision (15% on Labour Cost) 758.25

Page No -80-

Page 100: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

INSTALLATION AND FITTING OF DISTRIBUTION TRANSFORMER

8.04 Providing and installation of Outdoor type, oil immersed, naturally cooled 3ph, 50 Hz, Cu

wound Distribution Transformer of vector group DYn-11 with tap changer conforming to

IS: 1180 (1964) and IS: 2026 (1962) or any amendments there of and ISI marked of the

capacity 250 kVA, 11/0.415 kV as directed by the engineer in charge. The transformer

should be installed at an appropriate height to facilitate safety working clearance as

specified in Schedule VII of the CEA (Measures relating to Safety and Electric Supply

Regulations), 2010.

Sl. No. Description Unit Rate/Unit Qty. Amount

Material

1304

Out door type oil

immersed naturally cooled

3-ph, 50Hz Cu-wound

Distribution Transformer

of vector group DYn-1 1

with tap changer

conforming to IS : 1180

(1964) and IS : 2026

(1962) or latest version

thereof and ISI marked of

the following capacity 250

kVA 11/0.415 kV

No 375 ,300.00 1.00 375 ,300.00

Total Cost of Materials 375,300.00

Contingency (2% on Material Cost) 7,506.00

Sub-Total 382,806.00

Labours

1001 Labour Skilled-I manday 380.00 1.00 380.00

1002 Labour Skilled-II manday 310.00 1.50 465.00

1003 Labour Semi-Skilled manday 250.00 1.00 250.00

1004 Labour Un-skilled manday 220.00 25.00 5,500.00

Total Cost of Labours 6,595.00

Total 389,401.00

Add 15% for overhead & Profit 58,410.15

Grand Total 447,811.15

Say 447,811.00

Supervision (15% on Labour Cost) 989.25

Page No -81-

Page 101: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

INSTALLATION AND FITTING OF DISTRIBUTION TRANSFORMER

8.05 Providing and installation of Outdoor type, oil immersed, naturally cooled 3ph, 50 Hz, Cu

wound Distribution Transformer of vector group DYn-1 1 with tap changer conforming to

IS: 1180 (1964) and IS: 2026 (1962) or any amendments there of and ISI marked of the

capacity 500 kVA, 11/0.415 kV as directed by the engineer in charge. The transformer

should be installed at an appropriate height to facilitate safety working clearance as

specified in Schedule VII of the CEA (Measures relating to Safety and Electric Supply

Regulations), 2010.

Sl. No. Description Unit Rate/Unit Qty. Amount

Material

1305

Out door type oil

immersed naturally 3-ph,

10Hz Cu-wound

Distribution Transformer

of vector group DYn-1 1

with tap changer and air

breather with first filling

oil conforming to IS : 1180

(1964) and IS : 2026

(1962) or latest version

thereof and ISI marked of

the following capacity 500

kVA 11/0.415 kV

No 1,010,515.50 1.00 1,010,515.50

Total Cost of Materials 1,010,515.50

Contingency (2% on Material Cost) 20,210.31

Sub-Total 1,030,725.81

Labours

1001 Labour Skilled-I manday 380.00 1.00 380.00

1002 Labour Skilled-II manday 310.00 2.50 775.00

1003 Labour Semi-Skilled manday 250.00 1.00 250.00

1004 Labour Un-skilled manday 220.00 32.50 7,150.00

Total Cost of Labours 8,555.00

Total 1,039,280.81

Add 15% for overhead & Profit 155,892.12

Grand Total 1,195,172.93

Say 1,195,173.00

Supervision (15% on Labour Cost) 1,283.25

Page No -82-

Page 102: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

INSTALLATION AND FITTING OF DISTRIBUTION TRANSFORMER

8.06 Providing and installation of Outdoor type, oil immersed, naturally cooled 3ph, 50 Hz, Cu

wound Distribution Transformer of vector group DYn-1 1 with tap changer conforming to

IS: 1180 (1964) and IS: 2026 (1962) or any amendments there of and ISI marked of the

capacity 630 kVA, 11/0.415 kV as directed by the engineer in charge. The transformer

should be installed at an appropriate height to facilitate safety working clearance as

specified in Schedule VII of the CEA (Measures relating to Safety and Electric Supply

Regulations), 2010.

Sl. No. Description Unit Rate/Unit Qty. Amount

Material

1306

Out door type oil immersed

naturally 3-ph, 10Hz Cu-

wound Distribution

Transformer of vector

group DYn-1 1 with tap

changer conforming to IS :

1180 (1964) and IS : 2026

(1962) or latest version

thereof and ISI marked of

the following capacity 630

kVA 11/0.415 kV

No 1,099,575.00 1.00 1,099,575.00

Total Cost of Materials 1,099,575.00

Contingency (2% on Material Cost) 21,991.50

Sub-Total 1,121,566.50

Labours

1001 Labour Skilled-I manday 380.00 1.00 380.00

1002 Labour Skilled-II manday 310.00 2.50 775.00

1003 Labour Semi-Skilled manday 250.00 1.00 250.00

1004 Labour Un-skilled manday 220.00 35.50 7,810.00

Total Cost of Labours 9,215.00

Total 1,130,781.50

Add 15% for overhead & Profit 169,617.23

Grand Total 1,300,398.73

Say 1,300,399.00

Supervision (15% on Labour Cost) 1,382.25

Page No -83-

Page 103: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

INSTALLATION AND FITTING OF DISTRIBUTION TRANSFORMER

8.07 Providing and installation of Outdoor type, oil immersed, naturally cooled 3ph, 50 Hz, Cu

wound Distribution Transformer of vector group DYn- 11 with tap changer conforming to

IS: 1180 (1964) and IS: 2026 (1964) or any amendments there of and ISI marked of the

capacity 750 kVA, 11/0.415 kV as directed by the engineer in charge. The transformer

should be installed at an appropriate height to facilitate safety working clearance as

specified in Schedule VII of the CEA (Measures relating to Safety and Electric Supply

Regulations), 2010.

Sl. No. Description Unit Rate/Unit Qty. Amount

Material

1307

Out door type oil immersed

naturally 3-ph, 10Hz Cu-

wound Distribution

Transformer of vector

group DYn-1 1 with tap

changer conforming to IS :

1180 (1964) and IS : 2026

(1962) or latest version

thereof and ISI marked of

the following capacity 750

kVA 11/0.415 kV

No 1,215,000.00 1.00 1,215,000.00

Total Cost of Materials 1,215,000.00

Contingency (2% on Material Cost) 24,300.00

Sub-Total 1,239,300.00

Labours

1001 Labour Skilled-I manday 380.00 1.00 380.00

1002 Labour Skilled-II manday 310.00 2.50 775.00

1003 Labour Semi-Skilled manday 250.00 1.00 250.00

1004 Labour Un-skilled manday 220.00 45.00 9,900.00

Total Cost of Labours 11,305.00

Total 1,250,605.00

Add 15% for overhead & Profit 187,590.75

Grand Total 1,438,195.75

Say 1,438,196.00

Supervision (15% on Labour Cost) 1,695.75

Page No -84-

Page 104: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

INSTALLATION AND FITTING OF DISTRIBUTION TRANSFORMER

8.08 Providing and installation of Outdoor type, oil immersed, naturally cooled 3ph, 50 Hz, Cu

wound Distribution Transformer of vector group DYn-1 1 with tap changer conforming to

IS: 1180 (1964) and IS: 2026 (1962) or any amendments there of and ISI marked of the

capacity 1000 kVA, 11/0.415 kV as directed by the engineer in charge. The transformer

should be installed at an appropriate height to facilitate safety working clearance as

specified in Schedule VII of the CEA (Measures relating to Safety and Electric Supply

Regulations), 2010.

Sl. No. Description Unit Rate/Unit Qty. Amount

Material

1308

Out door type oil

immersed naturally cooled

3-ph, 50Hz Cu-wound

Distribution Transformer

of vector group DYn- 11

with tap changer

conforming to IS : 1180

(1964) and IS : 2026

(1962) or latest version

thereof and ISI marked of

the following capacity

1000 kVA 11/0.415 kV

No 1 ,771 ,875.00 1.00 1 ,771 ,875.00

Total Cost of Materials 1,771,875.00

Contingency (2% on Material Cost) 35,437.50

Sub-Total 1,807,312.50

Labours

1001 Labour Skilled-I manday 380.00 1.00 380.00

1002 Labour Skilled-II manday 310.00 1.50 465.00

1003 Labour Semi-Skilled manday 250.00 1.00 250.00

1004 Labour Un-skilled manday 220.00 52.50 11,550.00

Total Cost of Labours 12,645.00

Total 1,819,957.50

Add 15% for overhead & Profit 272,993.63

Grand Total 2,092,951.13

Say 2,092,951.00

Supervision (15% on Labour Cost) 1,896.75

Page No -85-

Page 105: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

INSTALLATION OF COMPACT SWITCHGEAR SUBSTATION

8.09 Providing and installation of 100 kVA, 11/0.415 kV, DYn-1 1 Compact Switchgear

Substation (CSS) Transformer with off circuit tap of rating +5 to -5 @ 2.5% comprising of

the following components ; as directed by the engineer in charge

a) HT Switchgear: 11 kV, 200 A, Air Insulated Switchgear consisting of Load Break

Switchand Fuse for protection of transformer, Interconnection between HT switchgear

and transformer shall be using 1Cx3x25 sq.mm Al unarmoured XLPE cable. The system

includes HT&LT metering components.

b) LT Switchboard: 250 A, 3P, 36 kA Fixed manual MCCB with Microprocessor based O/C, E/F, S/C

release as incomer cum outgoing

Sl. No. Description Unit Rate/Unit Qty. Amount

Material

1309

100kVA, 11/0.415 kV,

Dyn1 1 CSS Transformer

with off circuit tap of

rating +5 to-5 @ 2.5%

comprising of

a) HT Switchgear: 11kV,

200A, Air Insulated

Switchgear consisting of

Load Break Switchand

Fuse for protection of

transformer,

Interconnection between

HTswitchgear and

transformer shall be using

1Cx3x25 sq.mm

Al.unarmorured XLPE

Cable. The system

includes HT & LT metering

components.

b) LT Switchboard: 250A 3P

36kA Fixed Manual MCCB

with Microprocessor based

O/C, E/F, S/C release as

incomer cum outgoing.

No 1 ,951 ,000.00 1.00 1 ,951 ,000.00

Total Cost of Materials 1,951,000.00

Contingency (2% on Material Cost) 39,020.00

Sub-Total 1,990,020.00

Labours

1001 Labour Skilled-I manday 380.00 2.00 760.00

1002 Labour Skilled-II manday 310.00 2.00 620.00

1003 Labour Semi-Skilled manday 250.00 5.00 1,250.00

1004 Labour Un-skilled manday 220.00 79.00 17,380.00

Total Cost of Labours 20,010.00

Total 2,010,030.00

Add 15% for overhead & Profit 301,504.50

Grand Total 2,311,534.50

Say 2,311,535.00

Supervision (15% on Labour Cost) 3,001.50

Page No -86-

Page 106: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

INSTALLATION OF COMPACT SWITCHGEAR SUBSTATION

8.10 Providing and installation of 160 kVA, 11/0.415 kV, DYn-11 Compact Switchgear Substation

(CSS) Transformer with off circuit tap of rating +5 to -5 @ 2.5% comprising of the following

components ; as directed by the engineer in charge

a) HT Switchgear: 11 kV, 200 A, Air Insulated Switchgear consisting of Load Break

Switchand Fuse for protection of transformer, Interconnection between HT switchgear and

transformer shall be using 1Cx3x25 sq.mm Al unarmoured XLPE cable. The system includes

HT&LT metering components.

b) LT Switchboard: 250 A, 3P, 36 kA Fixed manual MCCB with Microprocessor based O/C, E/F, S/C

release as incomer cum outgoing

Sl. No. Description Unit Rate/Unit Qty. Amount

Material

1310

160kVA, 11/0.415 kV, Dyn11

CSS Transformer with off

circuit tap of rating +5 to-5

@ 2.5% comprising of

a) HT Switchgear: 11kV, 200A,

Air Insulated Switchgear

consisting of Load Break

Switchand Fuse for protection

of transformer, Interconnection

between HTswitchgear and

transformer shall be using

1Cx3x25 sq.mm

Al.unarmorured XLPE Cable.

The system includes HT & LT

metering components.

b) LT Switchboard: 250A 3P 36kA

Fixed Manual MCCB with

Microprocessor based O/C, E/F,

S/C release as incomer cum

outgoing.

No 2,380,000.00 1.00 2,380,000.00

Total Cost of Materials 2,380,000.00

Contingency (2% on Material Cost) 47,600.00

Sub-Total 2,427,600.00

Labours

1001 Labour Skilled-I manday 380.00 2.00 760.00

1002 Labour Skilled-II manday 310.00 2.00 620.00

1003 Labour Semi-Skilled manday 250.00 5.00 1,250.00

1004 Labour Un-skilled manday 220.00 90.00 19,800.00

Total Cost of Labours 22,430.00

Total 2,450,030.00

Add 15% for overhead & Profit 367,504.50

Grand Total 2,817,534.50

Say 2,817,535.00

Supervision (15% on Labour Cost) 3,364.50

Page No -87-

Page 107: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

INSTALLATION OF COMPACT SWITCHGEAR SUBSTATION

8.11 Providing and installation of 200 kVA, 11/0.415 kV, DYn-11 Compact Switchgear Substation

(CSS) Transformer with off circuit tap of rating +5 to -5 @ 2.5% comprising of the following

components ; as directed by the engineer in charge

a) HT Switchgear: 11 kV, 200 A, Air Insulated Switchgear consisting of Load Break Switchand

Fuse for protection of transformer, Interconnection between HT switchgear and transformer

shall be using 1Cx3x25 sq.mm Al unarmoured XLPE cable. The system includes HT&LT

metering components.

b) LT Switchboard: 320 A, 3P, 36 kA Fixed manual MCCB with Microprocessor based O/C,

E/F, S/C release as incomer cum outgoing

Sl. No. Description Unit Rate/Unit Qty. Amount

Material

1311

200kVA, 11/0.415 kV,

Dyn11 CSS Transformer

with off circuit tap of rating

+5 to-5 @ 2.5% comprising of

a) HT Switchgear: 11kV,

200A, Air Insulated

Switchgear consisting of Load

Break Switchand Fuse for

protection of transformer,

Interconnection between

HTswitchgear and

transformer shall be using

1Cx3x25 sq.mm

Al.unarmorured XLPE Cable.

The system includes HT & LT

metering components.

b) LT Switchboard: 320A 3P

36kA Fixed Manual MCCB

with Microprocessor based

O/C, E/F, S/C release as

incomer cum outgoing.

No 2,675,000.00 1.00 2,675,000.00

Total Cost of Materials 2,675,000.00

Contingency (2% on Material Cost) 53,500.00

Sub-Total 2,728,500.00

Labours

1001 Labour Skilled-I manday 380.00 2.00 760.00

1002 Labour Skilled-II manday 310.00 2.00 620.00

1003 Labour Semi-Skilled manday 250.00 5.00 1,250.00

1004 Labour Un-skilled manday 220.00 105.00 23,100.00

Total Cost of Labours 25,730.00

Total 2,754,230.00

Add 15% for overhead & Profit 413,134.50

Grand Total 3,167,364.50

Say 3,167,365.00

Supervision (15% on Labour Cost) 3,859.50

Page No -88-

Page 108: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

INSTALLATION OF COMPACT SWITCHGEAR SUBSTATION

8.12 Providing and installation of 250 kVA, 11/0.415 kV, DYn-11 Compact Switchgear Substation (CSS)

Transformer with off circuit tap of rating +5 to -5 @ 2.5% comprising of the following components; as directed

by the engineer in charge:

a) HT Switchgear: 11 kV, 630 A, 21 kA for 3 sec, SF6 insulated Non-Extinsible Compact switchgear

(Type DV) consisting of one no. Direct Switch and one no. Fixed Manual Vacuum Circuit Breaker in

SF6 with insulated stainless steel enclosure, with series trip, self powered microprocessor based

numerical relay for over current and earth fault (IDMTL+inst.) protection, interconnection between

HT switchgear and transformer shall be using 1Cx3x25 sq.mm Al unarmoured XLPE cable. The

system includes HT&LT metering components.

b) LT Switchboard: 400 A, 3P, 36 kA Fixed manual MCCB with Microprocessor based O/C, E/F, S/C release

as incomer cum outgoing

Sl. No. Description Unit Rate/Unit Qty. Amount

Material

1312

250kVA, 11/0.415 kV, Dyn11 with off

circuit tap of rating +5 to-5 @ 2.5%

comprising of

a) HT Switchgear: 1 1kV,630A,2

1KA for 3sec, SF6 insulated Non-

Extinsible Compact switchgear

(Type DV) consisting of one No.

Direct Switch and One No. Fixed

Manual Vacuum Circuit Breaker in

SF6 with insulated stainless steel

enclosure, with series trip, self

powered microprocessor based

numerical relay for over current and

earth fault (IDMTL + Inst.)

protection. Interconnection between

HT switchgear and transformer

shall be using 1Cx3x25 sq.mm Al.

unarm orured XLPE Cable. The

systemincludes HT & LT metering

components

b) LT Switchboard: 400A 3P 36kA

Fixed Manual MCCB with

Microprocessor based O/C, E/F, S/C

release as incomer cum outgoing.

No 2,940,600.00 1.00 2,940,600.00

Total Cost of Materials 2,940,600.00

Contingency (2% on Material Cost) 58,812.00

Sub-Total 2,999,412.00

Labours

1001 Labour Skilled-I manday 380.00 2.00 760.00

1002 Labour Skilled-II manday 310.00 2.00 620.00

1003 Labour Semi-Skilled manday 250.00 5.00 1,250.00

1004 Labour Un-skilled manday 220.00 115.00 25,300.00

Total Cost of Labours 27,930.00

Total 3,027,342.00

Add 15% for overhead & Profit 454,101.30

Grand Total 3,481,443.30

Say 3,481,443.00

Supervision (15% on Labour Cost) 4,189.50

Page No -89-

Page 109: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

INSTALLATION OF COMPACT SWITCHGEAR SUBSTATION

8.13 Providing and installation of 315 kVA, 11/0.415 kV, DYn-11 Compact Switchgear Substation (CSS)

Transformer with off circuit tap of rating +5 to -5 @ 2.5% comprising of the following components; as

directed by the engineer in charge

a) HT Switchgear: 11 kV, 630 A, 21 kA for 3 sec, SF6 insulated Non-Extinsible Compact

switchgear (Type DV) consisting of one no. Direct Switch and one no. Fixed Manual Vacuum

Circuit Breaker in SF6 with insulated stainless steel enclosure, with series trip, self powered

microprocessor based numerical relay for over current and earth fault (IDMTL+inst.) protection,

interconnection between HT switchgear and transformer shall be using 1Cx3x25 sq.mm Al

unarmoured XLPE cable. The system includes HT&LT metering components.

b) LT Switchboard: 630 A, 3P, 36 kA Fixed manual MCCB with Microprocessor based O/C, E/F, S/C

release as incomer cum outgoing

Sl. No. Description Unit Rate/Unit Qty. Amount

Material

1313

315kVA, 11/0.415 kV, Dyn11 with off

circuit tap of rating +5 to-5 @ 2.5%

comprising of

a) HT Switchgear: 11kV,630A,21KA

for 3sec, SF6 insulated Non-

Extinsible Compact switchgear (Type

DV) consisting of one No. Direct

Switch and One No. Fixed Manual

Vacuum Circuit Breaker in SF6 with

insulated stainlesssteel enclosure,

with series trip, self powered

microprocessor based numerical

relay for over current and earth fault

(IDMTL + Inst.) protection.

Interconnection between HT

switchgear and transformershall be

using 1Cx3x25 sq.mm Al.

unarm orure d XLPE Cable. The

system includes HT & LT metering

components

b) LT Switchboard: 630A 3P 36kA

Fixed Manual MCCB with

Microprocessor based O/C, E/F, S/C

release as incomer cum outgoing.

No 3,450,800.00 1.00 3,450,800.00

Total Cost of Materials 3,450,800.00

Contingency (2% on Material Cost) 69,016.00

Sub-Total 3,519,816.00

Labours

1001 Labour Skilled-I manday 380.00 2.00 760.00

1002 Labour Skilled-II manday 310.00 2.00 620.00

1003 Labour Semi-Skilled manday 250.00 5.00 1,250.00

1004 Labour Un-skilled manday 220.00 130.00 28,600.00

Total Cost of Labours 31,230.00

Total 3,551,046.00

Add 15% for overhead & Profit 532,656.90

Grand Total 4,083,702.90

Say 4,083,703.00

Supervision (15% on Labour Cost) 4,684.50

Page No -90-

Page 110: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

INSTALLATION OF COMPACT SWITCHGEAR SUBSTATION

8.14 Providing and installation of 400 kVA, 11/0.415 kV, DYn-1 1 CSS Transformer with off circuit tap

of rating +5 to -5 @ 2.5% comprising of the following components ; as directed by the engineer in

charge

a) HT Switchgear: 11 kV, 630 A, 21 kA for 3 sec, SF6 insulated Non-Extinsible Compact switchgear

(Type DV) consisting of one no. Direct Switch and one no. Fixed Manual Vacuum Circuit Breaker in

SF6 with insulated stainless steel enclosure, with series trip, self powered microprocessor based

numerical relay for over current and earth fault (IDMTL+inst.) protection, interconnection between

HT switchgear and transformer shall be using 1Cx3x25 sq.mm Al unarmoured XLPE cable. The

system includes HT&LT metering components.

b) LT Switchboard: 630 A, 3P, 36 kA Fixed manual ACB with Microprocessor based O/C, E/F, S/C release

as incomer cum outgoing

Sl. No. Description Unit Rate/Unit Qty. Amount

Material

1314

400kVA, 11/0.415 kV, Dyn11 with off

circuit tap of rating +5 to-5 @ 2.5%

comprising of

a) HT Switchgear: 11kV,630A,21KA

for 3sec, SF6 insulated Non-

Extinsible Compact switchgear

(Type DV) consisting of one No.

Direct Switch and One No. Fixed

Manual Vacuum Circuit Breaker in

SF6 with insulated stainlesssteel

enclosure, with series trip, self

powered microprocessor based

numerical relay for over current and

earth fault (IDMTL + Inst.)

protection. Interconnection between

HT switchgear and transformershall

be using 1Cx3x25 sq.mm Al.

unarmorured XLPE Cable. The

system includes HT & LT metering

components

b) LT Switchboard: 630A 3P 36kA

Fixed Manual ACCB with

Microprocessor based O/C, E/F, S/C

release as incomer cum outgoing.

No 3 ,745 ,000.00 1.00 3 ,745 ,000.00

Total Cost of Materials 3,745,000.00

Contingency (2% on Material Cost) 74,900.00

Sub-Total 3,819,900.00

Labours

1001 Labour Skilled-I manday 380.00 2.00 760.00

1002 Labour Skilled-II manday 310.00 2.00 620.00

1003 Labour Semi-Skilled manday 250.00 5.00 1,250.00

1004 Labour Un-skilled manday 220.00 140.00 30,800.00

Total Cost of Labours 33,430.00

Total 3,853,330.00

Add 15% for overhead & Profit 577,999.50

Grand Total 4,431,329.50

Say 4,431,330.00

Supervision (15% on Labour Cost) 5,014.50

Page No -91-

Page 111: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

INSTALLATION OF COMPACT SWITCHGEAR SUBSTATION

8.15 Providing and installation of 500 kVA, 11/0.415 kV, DYn-11 CSS Transformer with offcircuit tap of

rating +5 to -5 @ 2.5% comprising of the following components ; as directed by the engineer in

charge

a) HT Switchgear: 11 kV, 630 A, 21 kA for 3 sec, SF6 insulated Non-Extinsible Compact switchgear

(Type DV) consisting of one no. Direct Switch and one no. Fixed Manual Vacuum Circuit Breaker

in SF6 with insulated stainless steel enclosure, with series trip, self powered microprocessor

based numerical relay for over current and earth fault (IDMTL+inst.) protection, interconnection

between HT switchgear and transformer shall be using 1Cx3x25 sq.mm Al unarmoured XLPE

cable. The system includes HT&LT metering components.

b ) T S Sl. No. 00 A, 3P, 50 k Description l ACB Unit h Microproc Rate/Unit base Qty. E/F, S/C Amount

Material

1315

500kVA, 11/0.415 kV, Dyn1 1 with off

circuit tap of rating +5 to-5 @ 2.5%

comprising of

a) HT Switchgear: 1 1kV,630A,21KA

for 3sec, SF6 insulated Non-

Extinsible Compact switchgear (Type

DV) consisting of one No. Direct

Switch and One No. Fixed Manual

Vacuum Circuit Breaker in SF6 with

insulated stainlesssteel enclosure,

with series trip, self powered

microprocessor based numerical

relay for over current and earth fault

(IDMTL + Inst.) protection.

Interconnection between HT

switchgear and transformershall be

using 1Cx3x25 sq.mm Al.

unarmorured XLPE Cable. The

system includes HT & LT metering

components

b) LT Switchboard: 800A 3P 50kA

Fixed Manual ACB with

Microprocessor based O/C, E/F, S/C

release as incomer cum outgoing.

No 3,980,400.00 1.00 3,980,400.00

Total Cost of Materials 3,980,400.00

Contingency (2% on Material Cost) 79,608.00

Sub-Total 4,060,008.00

1001 Labour Skilled-I manday 380.00 2.00 760.00

1002 Labour Skilled-II manday 310.00 2.00 620.00

1003 Labour Semi-Skilled manday 250.00 5.00 1,250.00

1004 Labour Un-skilled manday 220.00 150.00 33,000.00

Total Cost of Labours 35,630.00 Total 4,095,638.00

Add 15% for overhead & Profit 614,345.70

Grand Total 4,709,983.70

Say 4,709,984.00

Supervision (15% on Labour Cost) L

Page No -92-

Page 112: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

INSTALLATION OF COMPACT SW ITCHGEAR SUBSTATION

8.16 Providing and installation of 630 kVA, 11/0.415 kV, DYn-11 CSS Transformer with off circuit tap of

rating +5 to -5 @ 2.5% comprising of the following components ; as directed by the engineer in

charge

a) HT Switchgear: 11 kV, 630 A, 21 kA for 3 sec, SF6 insulated Non-Extinsible Compact switchgear

(Type DV) consisting of one no. Direct Switch and one no. Fixed Manual Vacuum Circuit Breaker in

SF6 with insulated stainless steel enclosure, with series trip, self powered microprocessor based

numerical relay for over current and earth fault (IDMTL+inst.) protection, interconnection between

HT switchgear and transformer shall be using 1Cx3x25 sq.mm Al unarmoured XLPE cable. The

system includes HT&LT metering components.

:

Labours

1001 Labour Skilled-I manday 380.00 2.00 760.00

1002 Labour Skilled-II manday 310.00 2.00 620.00

1003 Labour Semi-Skilled manday 250.00 5.00 1,250.00

1004 Labour Un-skilled manday 220.00 165.00 36,300.00

Total Cost of Labours 38,930.00

Total 4,884,440.00

Add 15% for overhead & Profit 732,666.00

Grand Total 5,617,106.00

Say 5,617,106.00

Supervision (15% on Labour Cost) Sl. No.

Page No -93-

Page 113: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

Sl. No.

Materials

Description

1401 M.S. Channel 75 x 40 x 6

mm

1405 M.S. Flat Iron 40mmx6

mm

2102 M.S. Nut & Bolt 16x50

mm full thread

conforming to IS : 1364-

2 (1992) or any

amendments up to date.

2103 M.S. Nut & Bolt 16 x

155 mm full thread

conforming to IS : 1364-

2 (1992) or any

amendments up to date.

2201 Aluminium Paint

2203 Red Oxide Paint

PLACING OF DISTRIBUTION TRANSFORMER

PREPARATION OF DT MOUNTING STRUCTURE

9.01 Providing and Erection of Mounting Structure for Distribution Transformer up to 100

kVA, GOAB Switch, Arcing Horn fuse Unit etc, mounted between two SP-35 (swagged

steel tubular poles) 2.44 m apart, as directed by the engineer in charge.The height of

DT mounting channel should facilitate safety working clearance, as specified in

Schedule VII of the CEA (Measures relating to Safety and Electric Supply

Regulations), 2010.

Unit Rate/Unit Qty.

kg 105.84 176.72

kg 105.84 4.39

kg 162.00 2.63

kg 162.00 6.73

Lit 170.00 0.10

Lit 125.00 0.10

Labours

Total 22,698.32

Add 15% for overhead & Profit 3,404.75

Grand Total 26,103.07

Say 26,103.00

Supervision (15% on Labour Cost) 235.50

Amount

18,703.52

464.70

425.74

1,090.58

17.00

12.50

Total Cost of Materials 20,714.04

Contingency (2% on Material Cost)

Sub-Total

414.28

21,128.32

Total Cost of Labours 1,570.00

1001 Labour Skilled-I man day 380.00 1.00

1002 Labour Skilled-II man day 310.00 1.00

1003 Labour Semi-Skilled manday 250.00 0.00

1004 Labour Un-skilled man day 220.00 4.00

380.00

310.00

-

880.00

Page No -94-

Page 114: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

Sl. No. Description

Materials

1401 M.S. Channel 75 x 40 x 6

mm

1405 M.S. Flat Iron 40mmx6

mm

2102 M.S. Nut & Bolt 16x50

mm full thread

conforming to IS : 1364-

2 (1992) or any

amendments up to date.

2103 M.S. Nut & Bolt 16 x

155 mm full thread

conforming to IS : 1364-

2 (1992) or any

amendments up to date.

2201 Aluminium Paint

2203 Red Oxide Paint

PREPARATION OF DT MOUNTING STRUCTURE

9.02 Providing and Erection of Mounting Structure for Distribution Transformer up to 100

kVA fitted with GOAB Switch, Drop Out Fuse Unit, mounted between two SP-35

(swagged steel tubular poles) 2.44 m apart, as directed by the engineer in charge. The

height of DT mounting channel should facilitate safety working clearance, as

specified in Schedule VII of the CEA (Measures relating to Safety and Electric Supply

Regulations), 2010.

Unit Rate/Unit Qty.

kg 105.84 176.72

kg 105.84 4.39

kg 162.00 2.63

kg 162.00 6.73

Lit 170.00 0.10

Lit 125.00 0.10

Labours

Total 22,698.32

Add 15% for overhead & Profit 3,404.75

Grand Total 26,103.07

Say 26,103.00

Supervision (15% on Labour Cost) 235.50

Amount

18,703.52

464.70

425.74

1,090.58

17.00

12.50

Total Cost of Materials 20,714.04

Contingency (2% on Material Cost) 414.28

Sub-Total 21,128.32

Total Cost of Labours 1,570.00

1001 Labour Skilled-I manday 380.00 1.00

1002 Labour Skilled-II manday 310.00 1.00

1003 Labour Semi-Skilled manday 250.00 0.00

1004 Labour Un-skilled manday 220.00 4.00

380.00

310.00

-

880.00

Page No -95-

Page 115: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

CONSTRUCTION OF GROUND MOUNTED DT PLATFORM

9.02 Construction of Ground Mounted Platform for Distribution Transformer above 100 kVA

upto 250 kVA at a height of 1.4 metres from ground level,1.5 x 2.0 metres

area,constructed with stone masonry and top PCC 15 cm thick.

Sl. No. Description Unit Rate/Unit Qty. Amount

Material 1401 M.S. Channel 75 x 40 x 6

mm

kg 105.84 329.47 34,870.67

1405 M.S. Flat Iron 40mmx6

mm

kg 105.84 4.39 464.70

2102 M.S. Nut & Bolt 16x50

mm full thread

conforming to IS : 13

64- 2 (1992) or any

amendments up to

kg 162.00 2.50 405.00

2201 Aluminium Paint Lit 170.00 0.45 76.50

2203 Red Oxide Paint Lit 125.00 0.45 56.25

2301 Cement cum 13,750.00 0.02 275.00

2302 River Sand cum 2,100.00 0.06 126.00

2303 Stone Aggregate 10-20

mm

cum 1,890.00 0.12 226.80

Total Cost of Materials 36,500.92

Labours

1001 Labour Skilled-I manday 380.00 1.00 380.00

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 1.00 250.00

1004 Labour Un-skilled manday 220.00 8.00 1,760.00

Total Cost of Labours 2,390.00

Total 38,890.92

Add 15% for overhead & Profit 5,833.64

Grand Total 44,724.56

Say 44,725.00

Supervision (15% on Labour Cost) 358.50

Page No -96-

Page 116: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

CONSTRUCTION OF GROUND MOUNTED DT PLATFORM

9.03 Construction of Ground Mounted Platform for Distribution Transformer above 100 kVA

upto 250 kVA at a height of 1.2 metres from ground level,1.5 x 2.0 metres

area,constructed with stone masonry and top PCC 15 cm thick, as directed by the

engineer in charge. The height of DT mounting channel should facilitate safety

working clearance, as specified in Schedule VII of the CEA (Measures relating to

Safety and Electric Supply Regulations) 201 0

A Regular coursed rubble masonry with hard stone in foundation upto one storey above and below

ground level including curing, etc. complete.

in cement mortar 1 : 3 ( 1cement : 3 fine sand)

Details of cost for 1.00 cum

Description Unit Rate/Unit Qty. Amount

(A) MATERIALS

(i) Blasted rubble cum 1.21 600.00 726.00

(ii) Through and bond sto n cum 0.16 2500.00 400.00

(7no x

0.24x0.24mx0.39m =

0.16 cum)

(iii) Cement mortar 1:3 cum 0.30 5914.40 1,774.32

(A) 2,900.32

(B) LABOURS

(i) 2nd class mason each 2.12 320.00 678.40

(i i ) Semi skilled each 0.90 250.00 225.00

(i i i )Unski l led each 1.95 220.00 429.00

1,332.40

Scaffolding @ 10% 133.24

Sundries and contingencies @ 3% 39.97

(B) 1,505.61

TOTAL (A) + (B) 4,405.93

Add water charge @ 1% 44.06

TOTAL 4,449.99

Add CPOH @ 15% 667.50

Cost for 1.00 cum 5,117.49

Sub-total cum 4.20 21,493.46

Page No -97-

Page 117: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

B Providing and laying in position cement concrete of specified grade excluding cost of centering

and shuttering - All work upto plinth level:

1:2:4 (1 cement :2 course sand :4 stone aggregate 20mm nominal size) Details

of Cost for 1.00 cum

Description Unit Rate/Unit Qty. Amount

(A) MATERIALS :

(i) Stone aggregate 20mm cum 0.67 1800.00 1,206.00

(ii) Stone aggregate 10mm cum 0.22 1800.00 396.00

Carriage of stone aggregat cum 0.89 73.42 65.34

(iii) Coarse sand cum 0.45 850.00 378.25

Carriage of course sand cum 0.45 73.42 32.67

(iv) Cement (0.2225 cum ) tonne 0.32 9000.00 2,880.00

(iii) Carriage of cement tonne 0.32 37.46 11.99

(B) LABOURS :

Ist class mason day 0.10 450.00 45.00

Unskilled day 1.63 220.00 358.60

Semi skilled day 0.70 250.00 175.00

Hire charge of concrete m i rday 0.07 1668.00 116.76

Vibrator day 0.07 1068.00 74.76

Sundries L.S 14.30 8.00 114.40

TOTAL 5,854.77

Add water charge @ 1% 58.55

TOTAL 5,913.32

Add CPOH @ 15% 887.00

Cost for 1.00 cum 6,800.32

Sub-total cum 0.45 3,060.14

Total Cost 24,553.60

24,554.00

Page No -98-

Page 118: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

CONSTRUCTION OF GROUND MOUNTED DT PLATFORM

9.04 Construction of Ground Mounted Platform for Distribution Transformer above 250 kVA

upto 1000 kVA at a height of 1.2 metres from ground level,2.5 x 2.0 metres

area,constructed with stone masonry and top PCC 15 cm thick, as directed by the

engineer in charge. The height of DT mounting channel should facilitate safety working

clearance, as specified in Schedule VII of the CEA (Measures relating to Safety and

Electric Supply Regulations) 2 0 1 0

Regular coursed rubble masonry with hard stone in foundation upto one storey above A

and below ground level including curing, etc. complete.

in cement mortar 1 : 3 ( 1cement : 3 fine sand)

Details of cost for 1.00 cum

Description Unit Rate/Unit Qty. Amount

(A) MATERIALS

(i) Blasted rubble cum 1.21 600.00 726.00

(ii) Through and bond sto n cum 0.16 2500.00 400.00

(7no x 0.24x0.24mx0.39m = 0.16 cum) (iii) Cement mortar 1:3 cum 0.30 5914.40 1,774.32

(A) 2,900.32

(B) LABOURS

(i) 2nd class mason each 2.12 320.00 678.40

(ii) Semi skilled each 0.90 250.00 225.00

(iii) Unskilled each 1.95 220.00 429.00

1,332.40

Scaffolding @ 10% 133.24

Sundries and contingencies @ 3% 39.97

(B) 1,505.61

TOTAL (A) + (B) 4,405.93

Add water charge @ 1% 44.06

TOTAL 4,449.99

Add CPOH @ 15% 667.50

Cost for 1.00 cum 5,117.49

Sub-total cum 5.00 25,587.45

Page No -99-

Page 119: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

B Providing and laying in position cement concrete of specified grade excluding cost

of centering and shuttering - All work upto plinth level:

1:2:4 (1 cement :2 course sand :4 stone aggregate 20mm nominal size) Details

of Cost for 1.00 cum

Description Unit Rate/Unit Qty. Amount

(A) MATERIALS :

(i) Stone aggregate 20mm cum 0.67 1800.00 1,206.00

(ii) Stone aggregate 10mm cum 0.22 1800.00 396.00

Carriage of stone aggregat cum 0.89 73.42 65.34

(iii) Coarse sand cum 0.45 850.00 378.25

Carriage of course sand cum 0.45 73.42 32.67

(iv) Cement (0.2225 cum ) tonne 0.32 9000.00 2,880.00

(iii) Carriage of cement tonne 0.32 37.46 11.99

(B) LABOURS :

Ist class mason day 0.10 450.00 45.00

Unskilled day 1.63 220.00 358.60

Semi skilled day 0.70 250.00 175.00

Hire charge of concrete m rday 0.07 1668.00 116.76

Vibrator day 0.07 1068.00 74.76

Sundries L.S 14.30 8.00 114.40

TOTAL 5,854.77

Add water charge @ 1% 58.55

TOTAL 5,913.32

Add CPOH @ 15% 887.00

Cost for 1.00 cum 6,800.32

Sub-total cum 0.75 5,100.24

Total Cost 30,687.69

30,688.00

Page No -100-

Page 120: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

LAYING AND Fitting OF CABLES

10.01 Providing and Fitting of per meter length 1.1kV Armoured cable 1 core, 10 sq.mm

conforming to IS: 1554-1 (1988) or any ammendments with 10 sq.mm Aluminium

Cable Lug long barrel, as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

1601 1.1 kV Aluminium

Armoured Cable 1 core, 10

sq.mm conforming to IS :

1554-1 (1988) or any

ammendments

m 87.00 25.00 2,175.00

Total Cost of Materials 2,175.00

Contingency (2% on Material Cost) 43.50

Sub-Total 2,218.50

Labours

1001 Labour Skilled-I manday 380.00 0.25 95.00

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 0.83 183.33

Total Cost of Labours 278.33

Total 2,496.83

Add 15% for overhead & Profit 374.53

Grand Total 2,871.36

Say 2,871.00

Say 115.00

Supervision (15% on Labour Cost) 1 .67

Running Circuit Metre Cost

114.84

Page No -10 1-

Page 121: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

LAYING AND FITTING OF CABLES

10.02 Providing and Fitting of 1.1kV Aluminium Armoured cable of per meter length, 1

core, 16 sq.mm conforming to IS : 1554-1 (1988) or any ammendments with 16

sq.mm Aluminium Cable Lug long barrel, as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

1602 1.1 kV Aluminium

Armoured Cable 1 core, 16

sq.mm conforming to IS :

1554-1 (1988) or any

ammendments

m 102.00 25.00 2,550.00

Total Cost of Materials 2,550.00

Contingency (2% on Material Cost) 51.00

Sub-Total 2,601.00

Labours

1001 Labour Skilled-I manday 380.00 0.25 95.00

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 0.83 183.33

Total Cost of Labours 278.33

Total 2,879.33

Add 15% for overhead & Profit 431.90

Grand Total 3,311.23

Say 3,311.00

Say 132.00

Supervision (15% on Labour Cost) 1 .67

Running Circuit Metre Cost

132.44

Page No -102-

Page 122: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

LAYING AND FITTING OF CABLES

10.03 Providing and Fitting of 1.1kV Armoured cable of per meter length, 1 core, 35 sq.mm

conforming to IS : 1554-1 (1988) or any ammendments with35 sq.mm Aluminium

Cable Lug long barrel, as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

1603 1.1 kV Aluminium

Armoured Cable 1 core,

35 sq.mm conforming to

IS : 1554-1 (1988) or any

ammendments

m 147.00 25.00 3,675.00

Total Cost of Materials 3,675.00

Contingency (2% on Material Cost) 73.50

Sub-Total 3,748.50

Labours

1001 Labour Skilled-I manday 380.00 0.25 95.00

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 1.08 238.33

Total Cost of Labours 333.33

Total 4,081.83

Add 15% for overhead & Profit 612.28

Grand Total 4,694.11

Say 4,694.00

Say 188.00

Supervision (15% on Labour Cost) 2.00

Running Circuit Metre Cost

187.76

Page No -103-

Page 123: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

LAYING AND FITTING OF CABLES

10.04 Providing and Fitting of length 1.1kV Armoured cable of per meter length, 1 core, 50

sq.mm conforming to IS : 1554-1 (1988) or any ammendments with 50 sq.mm

Aluminium Cable Lug long barrel, as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

1604 1.1 kV Aluminium

Armoured Cable 1 core,

50 sq.mm conforming to

IS : 1554-1 (1988) or any

ammendments

m 191.00 25.00 4,775.00

Total Cost of Materials 4,775.00

Contingency (2% on Material Cost) 95.50

Sub-Total 4,870.50

Labours

1001 Labour Skilled-I manday 380.00 0.25 95.00

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 1.08 238.33

Total Cost of Labours 333.33

Total 5,203.83

Add 15% for overhead & Profit 780.58

Grand Total 5,984.41

Say 5,984.00

Say 239.00

Supervision (15% on Labour Cost) 2.00

Running Circuit Metre Cost

239.36

Page No -104-

Page 124: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

LAYING AND FITTING OF CABLES

10.05 Providing and Fitting of length 1.1 kV Armoured cable of per meter length, 1 core, 70

sq.mm conforming to IS : 1554-1 (1988) or any ammendments with 70 sq.mm

Aluminium Cable Lug long barrel, as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

1605 1.1 kV Aluminium

Armoured Cable 1 core,

70 sq.mm conforming to

IS : 1554-1 (1988) or any

ammendments

m 225.00 25.00 5,625.00

Total Cost of Materials 5,625.00

Contingency (2% on Material Cost) 112.50

Sub-Total 5,737.50

Labours

1001 Labour Skilled-I manday 380.00 0.25 95.00

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 1.25 275.00

Total Cost of Labours 370.00

Total 6,107.50

Add 15% for overhead & Profit 916.13

Grand Total 7,023.63

Say 7,024.00

Say 281.00

Supervision (15% on Labour Cost) 2.22

Running Circuit Metre Cost

280.96

Page No -105-

Page 125: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

LAYING AND FITTING OF CABLES

10.06 Providing and Fitting of 1.1kV Armoured cable of per meter length, 1 core, 95 sq.mm

conforming to IS : 1554-1 (1988) or any ammendments with 95 sq.mm Aluminium

Cable Lug long barrel, as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

1606 1.1 kV Aluminium

Armoured Cable 1 core,

95 sq.mm conforming to

IS : 1554-1 (1988) or any

ammendments

m 278.00 25.00 6,950.00

Total Cost of Materials 6,950.00

Contingency (2% on Material Cost) 139.00

Sub-Total 7,089.00

Labours

1001 Labour Skilled-I manday 380.00 0.25 95.00

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 1.25 275.00

Total Cost of Labours 370.00

Total 7,459.00

Add 15% for overhead & Profit 1,118.85

Grand Total 8,577.85

Say 8,578.00

Say 343.00

Supervision (15% on Labour Cost) 2.22

Running Circuit Metre Cost

343.12

Page No -106-

Page 126: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

LAYING AND FITTING OF CABLES

10.07 Providing and Fitting of 1.1kV Armoured cable of per meter length, 1 core, 120 sq.mm

conforming to IS : 1554-1 (1988) or any ammendments with 120 sq.mm Aluminium

Cable Lug long barrel, as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

1607 1.1 kV Aluminium

Armoured Cable 1 core,

120 sq.mm conforming to

IS : 1554-1 (1988) or any

ammendments

m 375.00 25.00 9,375.00

Total Cost of Materials 9,375.00

Contingency (2% on Material Cost) 187.50

Sub-Total 9,562.50

Labours

1001 Labour Skilled-I manday 380.00 0.25 95.00

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 1.50 330.00

Total Cost of Labours 425.00

Total 9,987.50

Add 15% for overhead & Profit 1,498.13

Grand Total 11,485.63

Say 11,486.00

Say 459.00

Supervision (15% on Labour Cost) 2.55

Running Circuit Metre Cost

459.44

Page No -107-

Page 127: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

LAYING AND FITTING OF CABLES

10.08 Providing and Fitting of 1.1kV Armoured cable of per meter length, 1 core, 150 sq.mm

conforming to IS : 1554-1 (1988) or any ammendments with 150 sq.mm Cable Lug

long barrel, as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

1608 1.1 kV Aluminium

Armoured Cable 1 core,

150 sq.mm conforming

to IS : 1554-1 (1988) or

any ammendments

m 525.00 25.00 13,125.00

Total Cost of Materials 13,125.00

Contingency (2% on Material Cost) 262.50

Sub-Total 13,387.50

Labours

1001 Labour Skilled-I manday 380.00 0.25 95.00

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 1.50 330.00

Total Cost of Labours 425.00

Total 13,812.50

Add 15% for overhead & Profit 2,071.88

Grand Total 15,884.38

Say 15,884.00

Say 635.00

Supervision (15% on Labour Cost) 2 . 5 5

Running Circuit Metre Cost

635.36

Page No -108-

Page 128: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

LAYING AND FITTING OF CABLES

10.09 Providing and Fitting of length 1.1kV Armoured cable of per meter length, 1 core, 185

sq.mm conforming to IS : 1554-1 (1988) or any ammendments with 185 sq.mm

Aluminium Cable Lug long barrel, as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

1609 1.1 kV Aluminium

Armoured Cable 1 core,

185 sq.mm conforming to

IS : 1554-1 (1988) or any

ammendments

m 585.00 25.00 14,625.00

Total Cost of Materials 14,625.00

Contingency (2% on Material Cost) 292.50

Sub-Total 14,917.50

Labours

1001 Labour Skilled-I manday 380.00 0.25 95.00

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 1.50 330.00

Total Cost of Labours 425.00

Total 15,342.50

Add 15% for overhead & Profit 2,301.38

Grand Total 17,643.88

Say 17,644.00

Say 706.00

Supervision (15% on Labour Cost) 2.55

Running Circuit Metre Cost

705.76

Page No -109-

Page 129: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

LAYING AND FITTING OF CABLES

10.10 Providing and Fitting of 1.1kV Armoured cable of per meter length, 1 core, 225 sq.mm

conforming to IS : 1554-1 (1988) or any ammendments with 225 sq.mm Aluminium

Cable Lug long barrel, as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

1610 1.1 kV Aluminium

Armoured Cable 1 core,

225 sq.mm conforming

to IS : 1554-1 (1988) or

any ammendments

m 772.00 25.00 19,300.00

Total Cost of Materials 19,300.00

Contingency (2% on Material Cost) 386.00

Sub-Total 19,686.00

Labours

1001 Labour Skilled-I manday 380.00 0.25 95.00

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 1.50 330.00

Total Cost of Labours 425.00

Total 20,111.00

Add 15% for overhead & Profit 3,016.65

Grand Total 23,127.65

Say 23,128.00

Say 925.00

Supervision (15% on Labour Cost) 2 . 5 5

Running Circuit Metre Cost

925.12

Page No -110-

Page 130: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

LAYING AND FITTING OF CABLES

10.11 Providing and Fitting of 1.1kV Armoured cable of per meter length, 1 core, 300 sq.mm

conforming to IS : 1554-1 (1988) or any ammendments with 300 sq.mm Aluminium Cable Lug

long barrel, as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

1611 1.1 kV Aluminium

Armoured Cable 1 core, 300

sq.mm conforming to IS :

1554-1 (1988) or any

ammendments

m 960.00 25.00 24,000.00

Total Cost of Materials 24,000.00

Contingency (2% on Material Cost) 480.00

Sub-Total 24,480.00

Labours

1001 Labour Skilled-I manday 380.00 0.25 95.00

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 1.50 330.00

Total Cost of Labours 425.00

Total 24,905.00

Add 15% for overhead & Profit 3,735.75

Grand Total 28,640.75

Say 28,641.00

Say 1,146.00

Supervision (15% on Labour Cost) 2 . 5 5

Running Circuit Metre Cost

1,145.64

Page No -111-

Page 131: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

LAYING AND FITTING OF CABLES

10.12 Providing and Fitting of 1.1kV Armoured cable of per meter length, 1 core, 400 sq.mm

conforming to IS : 1554-1 (1988) or any ammendments with 400 sq.mm Aluminium

Cable Lug long barrel, as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

1612 1.1 kV Aluminium

Armoured Cable 1

core,400 sq.mm

conforming to IS : 1554- 1

(1988) or any

ammendments

m 1,035.00 25.00 25,875.00

Total Cost of Materials 25,875.00

Contingency (2% on Material Cost) 517.50

Sub-Total 26,392.50

Labours

1001 Labour Skilled-I manday 380.00 0.25 95.00

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 1.67 366.67

Total Cost of Labours 461.67

Total 26,854.17

Add 15% for overhead & Profit 4,028.13

Grand Total 30,882.29

Say 30,882.00

Say 1,235.00

Supervision (15% on Labour Cost) 2 . 7 7

Running Circuit Metre Cost

1,235.28

Page No -112-

Page 132: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

LAYING AND FITTING OF CABLES

10.13 Providing and Fitting of 1.1kV Armoured cable of per meter length, 1 core, 630 sq.mm

conforming to IS : 1554-1 (1988) or any ammendments with 630 sq.mm Aluminium

Cable Lug long barrel, as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

1613 1.1 kV Aluminium

Armoured Cable 1 core,

630 sq.mm conforming to

IS : 1554-1 (1988) or any

ammendments

m 1,650.00 25.00 41,250.00

Total Cost of Materials 41,250.00

Contingency (2% on Material Cost) 825.00

Sub-Total 42,075.00

Labours

1001 Labour Skilled-I manday 380.00 0.25 95.00

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 1.67 366.67

Total Cost of Labours 461.67

Total 42,536.67

Add 15% for overhead & Profit 6,380.50

Grand Total 48,917.17

Say 48,917.00

Say 1,957.00

Supervision (15% on Labour Cost) 2.77

Running Circuit Metre Cost

1,956.68

Page No -113-

Page 133: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

ERECTION OF GI POLE FOR LT BUS BAR ARRANGEMENT

INSTALLATION OF LT BUS BAR FOR ABOVE 250kVA, 11/0.415kV DISTRIBUTION TRANSFORMER

10.14 Providing and installation of LT Bus bar for above 250kVA, 11/0.415kV Distribution Transformer by

using GI Pipe 40mm dia structure with Grasshopper conductor bus bar and Strap type LT shackle

insulator and other accessories, as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

2504 GI Pipe 40mm dia, 4.13m long with a GI

base plate of 30x30x0.5cm welded at the

bottom

No 2,742.59 2.00 5,485.18

1203 Hard drawn standard aluminium

conductors conforming to IS 398(Part-I)

with amendment No. 1, 2 and 3 or the

latest version thereof bearing ISI mark

:Conductor, AAC,7/3.91 mm Grasshopper

Km 68,785.00 0.01 825.42

1806 Shackle Insulator (Pin/Strap Type) 70x90

mm conforming to IS : 1445 (1977) or any

amendments up to date

No 39.00 8.00 312.00

1807 Shackle Strap for 70x90 mm Shackle

Insulator

Pair 14.00 8.00 112.00

1808 Shackle Nut Bolt 12x100 mm(GI) kg 174.96 0.25 43.74

1405 M.S. Flat Iron 40mmx6 mm kg 105.84 7.90 836.14

2102 M.S. Nut & Bolt 16x50 mm full thread

conforming to IS : 1364-2 (1992) or any

amendments up to date.

kg 162.00 2.93 474.66

1401 M.S. Channel 75 x 40 x 6 mm kg 105.84 25.23 2,670.34

2301 Cement cum 13,750.00 0.34 4,675.00

2302 River Sand cum 2,100.00 1.00 2,100.00

2303 Stone Aggregate 10-20 mm cum 1,890.00 2.00 3,780.00

Total Cost of Materials 21,314.48

Contingency (2% on Material Cost) 426.29

Sub-Total 21,740.77

Labours

1001 Labour Skilled-I manday 380.00 1.50 570.00

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 1.00 250.00

1004 Labour Un-skilled manday 220.00 5.92 1,301.67

Total Cost of Labours 2,121.67

Total 23,862.44

Add 15% for overhead & Profit 3,579.37

Grand Total 27,441.80

Say 27,442.00

Supervision (15% on Labour Cost) 318.25

Page No -114-

Page 134: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FITTING OF CABLE JOINTING KIT

10.15 Providing and Fitting 1.1kV Armoured cable Jointing Kit per Number, 1 core, 10

sq.mm conforming to IS : 1554-1 (1988) or any ammendments with 10 sq.mm

Aluminium Cable Lug long barrel, as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

2010 LT Cable Jointing Kit No 2,770.00 1 2,770.00

1701 Aluminium Cable Lug

long barrel , 10 Sq.mm

No 5.00 1 5.00

Total Cost of Materials 2,775.00

Contingency (2% on Material Cost) 55.50

Sub-Total 2,830.50

Labours

1001 Labour Skilled-I manday 380.00 0.18 66.50

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 0.13 27.50

Total Cost of Labours 94.00

Total 2,924.50

Add 15% for overhead & Profit 438.68

Grand Total 3,363.18

Say 3,363.00

Supervision (15% on Labour Cost) 14.10

Page No -115-

Page 135: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FITTING OF CABLE JOINTING KIT

10.16 Providing and Fitting 1.1kV Armoured cable Jointing Kit per Number, 1 core, 16

sq.mm conforming to IS : 1554-1 (1988) or any ammendments with 16 sq.mm

Aluminium Cable Lug long barrel, as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

2010 LT Cable Jointing Kit No 2,770.00 1 2,770.00

1702 Aluminium Cable Lug

long barrel , 16 Sq.mm

No 8.00 1 8.00

Total Cost of Materials 2,778.00

Contingency (2% on Material Cost) 55.56

Sub-Total 2,833.56

Labours

1001 Labour Skilled-I manday 380.00 0.18 66.50

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 0.13 27.50

Total Cost of Labours 94.00

Total 2,927.56

Add 15% for overhead & Profit 439.13

Grand Total 3,366.69

Say 3,367.00

Supervision (15% on Labour Cost) 14.10

Page No -116-

Page 136: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FITTING OF CABLE JOINTING KIT

10.17 Providing and Fitting 1.1kV Armoured cable Jointing Kit per Number, 1 core, 35

sq.mm conforming to IS : 1554-1 (1988) or any ammendments with 35 sq.mm

Aluminium Cable Lug long barrel, as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

2010 LT Cable Jointing Kit No 2,770.00 1 2,770.00

1703 Aluminium Cable Lug

long barrel , 35 Sq.mm

No 12.00 1 12.00

Total Cost of Materials 2,782.00

Contingency (2% on Material Cost) 55.64

Sub-Total 2,837.64

Labours

1001 Labour Skilled-I manday 380.00 0.18 66.50

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 0.13 27.50

Total Cost of Labours 94.00

Total 2,931.64

Add 15% for overhead & Profit 439.75

Grand Total 3,371.39

Say 3,371.00

Supervision (15% on Labour Cost) 14.10

Page No -117-

Page 137: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FITTING OF CABLE JOINTING KIT

10.18 Providing and Fitting 1.1 kV Armoured cable Jointing Kit per Number, 1 core, 50

sq.mm conforming to IS : 1554-1 (1988) or any ammendments with 50 sq.mm

Aluminium Cable Lug long barrel, as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

2010 LT Cable Jointing Kit No 2,770.00 1 2,770.00

1704 Aluminium Cable Lug

long barrel , 50 Sq.mm

No 15.00 1 15.00

Total Cost of Materials 2,785.00

Contingency (2% on Material Cost) 55.70

Sub-Total 2,840.70

Labours

1001 Labour Skilled-I manday 380.00 0.18 66.50

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 0.13 27.50

Total Cost of Labours 94.00

Total 2,934.70

Add 15% for overhead & Profit 440.21

Grand Total 3,374.91

Say 3,375.00

Supervision (15% on Labour Cost) 14.10

Page No -118-

Page 138: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FITTING OF CABLE JOINTING KIT

10.19 Providing and Fitting 1.1kV Armoured cable Jointing Kit per Number, 1 core, 70

sq.mm conforming to IS : 1554-1 (1988) or any ammendments with 70 sq.mm

Aluminium Cable Lug long barrel, as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

2010 LT Cable Jointing Kit No 2,770.00 1.00 2,770.00

1705 Aluminium Cable Lug

long barrel , 70Sq.mm

No 30.00 1.00 30.00

Total Cost of Materials 2,800.00

Contingency (2% on Material Cost) 56.00

Sub-Total 2,856.00

Labours

1001 Labour Skilled-I manday 380.00 0.18 66.50

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 0.13 27.50

Total Cost of Labours 94.00

Total 2,950.00

Add 15% for overhead & Profit 442.50

Grand Total 3,392.50

Say 3,393.00

Supervision (15% on Labour Cost) 14.10

Page No -119-

Page 139: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FITTING OF CABLE JOINTING KIT

10.20 Providing and Fitting 1.1kV Armoured cable Jointing Kit per Number, 1 core, 95

sq.mm conforming to IS : 1554-1 (1988) or any ammendments with 95 sq.mm

Aluminium Cable Lug long barrel, as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

2010 LT Cable Jointing Kit No 2,770.00 1.00 2,770.00

1706 Aluminium Cable Lug

long barrel , 95 Sq.mm

No 35.00 1.00 35.00

Total Cost of Materials 2,805.00

Contingency (2% on Material Cost) 56.10

Sub-Total 2,861.10

Labours

1001 Labour Skilled-I manday 380.00 0.18 66.50

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 0.13 27.50

Total Cost of Labours 94.00

Total 2,955.10

Add 15% for overhead & Profit 443.27

Grand Total 3,398.37

Say 3,398.00

Supervision (15% on Labour Cost) 14.10

Page No -120-

Page 140: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FITTING OF CABLE JOINTING KIT

10.21 Providing and Fitting 1.1kV Armoured cable Jointing Kit per Number, 1 core, 120

sq.mm conforming to IS : 1554-1 (1988) or any ammendments with 120 sq.mm

Aluminium Cable Lug long barrel, as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

2010 LT Cable Jointing Kit No 2,770.00 1 2,770.00

1707 Aluminium Cable Lug

long barrel , 120 Sq.mm

No 42.00 1 42.00

Total Cost of Materials 2,812.00

Contingency (2% on Material Cost) 56.24

Sub-Total 2,868.24

Labours

1001 Labour Skilled-I manday 380.00 0.18 66.50

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 0.13 27.50

Total Cost of Labours 94.00

Total 2,962.24

Add 15% for overhead & Profit 444.34

Grand Total 3,406.58

Say 3,407.00

Supervision (15% on Labour Cost) 14.10

Page No -121-

Page 141: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FITTING OF CABLE JOINTING KIT

10.22 Providing and Fitting 1.1kV Armoured cable Jointing Kit per Number, 1 core, 150

sq.mm conforming to IS : 1554-1 (1988) or any ammendments with 150 sq.mm

Aluminium Cable Lug long barrel, as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

2010 LT Cable Jointing Kit No 2,770.00 1 2,770.00

1708 Aluminium Cable Lug

long barrel , 150 Sq.mm

No 53.00 1 53.00

Total Cost of Materials 2,823.00

Contingency (2% on Material Cost) 56.46

Sub-Total 2,879.46

Labours

1001 Labour Skilled-I manday 380.00 0.18 66.50

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 0.13 27.50

Total Cost of Labours 94.00

Total 2,973.46

Add 15% for overhead & Profit 446.02

Grand Total 3,419.48

Say 3,419.00

Supervision (15% on Labour Cost) 14.10

Page No -122-

Page 142: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FITTING OF CABLE JOINTING KIT

10.23 Providing and Fitting 1.1kV Armoured cable Jointing Kit per Number, 1 core, 185

sq.mm conforming to IS : 1554-1 (1988) or any ammendments with 185 sq.mm

Aluminium Cable Lug long barrel, as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

2010 LT Cable Jointing Kit No 2,770.00 1 2,770.00

1709 Aluminium Cable Lug

long barrel , 185 Sq.mm

No 68.00 1 68.00

Total Cost of Materials 2,838.00

Contingency (2% on Material Cost) 56.76

Sub-Total 2,894.76

Labours

1001 Labour Skilled-I manday 380.00 0.18 66.50

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 0.13 27.50

Total Cost of Labours 94.00

Total 2,988.76

Add 15% for overhead & Profit 448.31

Grand Total 3,437.07

Say 3,437.00

Supervision (15% on Labour Cost) 14.10

Page No -123-

Page 143: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FITTING OF CABLE JOINTING KIT

10.24 Providing and Fitting 1.1kV Armoured cable Jointing Kit per Number, 1 core, 225

sq.mm conforming to IS : 1554-1 (1988) or any ammendments with 225 sq.mm

Aluminium Cable Lug long barrel, as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

2010 LT Cable Jointing Kit No 2,770.00 1 2,770.00

1710 Aluminium Cable Lug

long barrel , 225 Sq.mm

No 83.00 1 83.00

Total Cost of Materials 2,853.00

Contingency (2% on Material Cost) 57.06

Sub-Total 2,910.06

Labours

1001 Labour Skilled-I manday 380.00 0.18 66.50

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 0.13 27.50

Total Cost of Labours 94.00

Total 3,004.06

Add 15% for overhead & Profit 450.61

Grand Total 3,454.67

Say 3,455.00

Supervision (15% on Labour Cost) 14.10

Page No -124-

Page 144: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FITTING OF CABLE JOINTING KIT

10.25 Providing and Fitting 1.1kV Armoured cable Jointing Kit per Number, 1 core, 300

sq.mm conforming to IS : 1554-1 (1988) or any ammendments with 300 sq.mm

Aluminium Cable Lug long barrel, as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

2010 LT Cable Jointing Kit No 2,770.00 1 2,770.00

1711 Aluminium Cable Lug

long barrel , 300 Sq.mm

No 115.00 1 115.00

Total Cost of Materials 2,885.00

Contingency (2% on Material Cost) 57.70

Sub-Total 2,942.70

Labours

1001 Labour Skilled-I manday 380.00 0.18 66.50

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 0.13 27.50

Total Cost of Labours 94.00

Total 3,036.70

Add 15% for overhead & Profit 455.51

Grand Total 3,492.21

Say 3,492.00

Supervision (15% on Labour Cost) 14.10

Page No -125-

Page 145: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FITTING OF CABLE JOINTING KIT

10.26 Providing and Fitting 1.1kV Armoured cable Jointing Kit per Number, 1 core, 400

sq.mm conforming to IS : 1554-1 (1988) or any ammendments with 400 sq.mm

Aluminium Cable Lug long barrel, as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

2010 LT Cable Jointing Kit No 2,770.00 1 2,770.00

1712 Aluminium Cable Lug

long barrel , 400 Sq.mm

No 165.00 1 165.00

Total Cost of Materials 2,935.00

Contingency (2% on Material Cost) 58.70

Sub-Total 2,993.70

Labours

1001 Labour Skilled-I manday 380.00 0.18 66.50

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 0.13 27.50

Total Cost of Labours 94.00

Total 3,087.70

Add 15% for overhead & Profit 463.16

Grand Total 3,550.86

Say 3,551.00

Supervision (15% on Labour Cost) 14.10

Page No -126-

Page 146: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FITTING OF CABLE JOINTING KIT

10.27 Providing and Fitting 1.1kV Armoured cable Jointing Kit per Number, 1 core, 630

sq.mm conforming to IS : 1554-1 (1988) or any ammendments with 630 sq.mm

Aluminium Cable Lug long barrel, as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

2010 LT Cable Jointing Kit No 2,770.00 1 2,770.00

1713 Aluminium Cable Lug

long barrel , 630Sq.mm

No 188.00 1 188.00

Total Cost of Materials 2,958.00

Contingency (2% on Material Cost) 59.16

Sub-Total 3,017.16

Labours

1001 Labour Skilled-I manday 380.00 0.18 66.50

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 0.13 27.50

Total Cost of Labours 94.00

Total 3,111.16

Add 15% for overhead & Profit 466.67

Grand Total 3,577.83

Say 3,578.00

Supervision (15% on Labour Cost) 14.10

Page No -127-

Page 147: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FITTING OF CABLES T-CONNECTOR

10.28 Providing and Fitting 1.1kV Armoured cable T-Connector per Number, 1 core, 300

sq.mm as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

1714 T-Connector for 300

sq.mm Cable

No 1,600.00 1 1,600.00

Total Cost of Materials 1,600.00

Contingency (2% on Material Cost) 32.00

Sub-Total 1,632.00

Labours

1001 Labour Skilled-I manday 380.00 0.13 47.50

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 0.13 27.50

Total Cost of Labours 75.00

Total 1,707.00

Add 15% for overhead & Profit 256.05

Grand Total 1,963.05

Say 1,963.00

Supervision (15% on Labour Cost) 11.25

Page No -128-

Page 148: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FITTING OF CABLES T-CONNECTOR

10.29 Providing and Fitting 1.1kV Armoured cable T-Connector per Number, 1 core, 400

sq.mm as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

1715 T-Connector for 400

sq.mm Cable

No 1,760.00 1 1,760.00

Total Cost of Materials 1,760.00

Contingency (2% on Material Cost) 35.20

Sub-Total 1,795.20

Labours

1001 Labour Skilled-I manday 380.00 0.13 47.50

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 0.13 27.50

Total Cost of Labours 75.00

Total 1,870.20

Add 15% for overhead & Profit 280.53

Grand Total 2,150.73

Say 2,151.00

Supervision (15% on Labour Cost) 11.25

Page No -129-

Page 149: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FITTING OF CABLES T-CONNECTOR

10.30 Providing and Fitting 1.1kV Armoured cable T-Connector per Number, 1 core, 630 sq.mm as

directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

1716 T-Connector for 630

sq.mm Cable

No 1,936.00 1 1,936.00

Total Cost of Materials 1,936.00

Contingency (2% on Material Cost) 38.72

Sub-Total 1,974.72

Labours

1001 Labour Skilled-I manday 380.00 0.13 47.50

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 0.13 27.50

Total Cost of Labours 75.00

Total 2,049.72

Add 15% for overhead & Profit 307.46

Grand Total 2,357.18

Say 2,357.00

Supervision (15% on Labour Cost) 11.25

Page No -130-

Page 150: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

PROTECTION OF DISTRIBUTION TRANSFORMER

FITTING OF GANG SWITCH COMPLETE

11.01 Providing and Fitting of 200A, 11 kV Gang Operated Air Break Switch conforming to

IS : 2544 - 1973, IS : 9921 (Part I-V) or any ammendments up to date with 200 A,

1 1 kV fuse unit with arcing horn, as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

2901 11 kV Gang Operated

Air Break Switch,

200 A, conforming to

IS : 2544 - 1973, IS :

9921 (Part I-V) or

any ammendments

Set 14,490.00 1.00 14,490.00

2902 11 kV Fuse Unit with

Arcing Horn, 200 A,

conforming to 9385

(Part 2) - 1980

ammended up to date

Set 7,087.50 1.00 7,087.50

Total Cost of Materials 21,577.50

Contingency (2% on Material Cost) 431.55

Sub-Total 22,009.05

Labours

1001 Labour Skilled-I manday 380.00 2.00 760.00

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 5.75 1,265.00

Total Cost of Labours 2,025.00

Total 24,034.05

Add 15% for overhead & Profit 3,605.11

Grand Total 27,639.16

Say 27,639.00

Supervision (15% on Labour Cost) 303.75

Page No -131-

Page 151: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FITTING OF VERTICALLY OPERATED GANG SWITCH

11.02 Providing and Fitting of Horizontally operated, Single break 11 kV Isolator complete

with Drop out Fuse unit, conforming to IS : 9921 and any other relevant standards

ammended up to date, as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

2903 Horizontally operated

Single break 11 kV

Isolator complete with

Drop out Fuse unit,

conforming to IS : 9921

and any other relevant

standards ammended

up to date.

Set 34,650.00 1.00 34,650.00

Total Cost of Materials 34,650.00

Contingency (2% on Material Cost) 693.00

Sub-Total 35,343.00

Labours

1001 Labour Skilled-I manday 380.00 2.00 760.00

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 5.00 1,100.00

Total Cost of Labours 1,860.00

Total 37,203.00

Add 15% for overhead & Profit 5,580.45

Grand Total 42,783.45

Say 42,783.00

Supervision (15% on Labour Cost) 279.00

Page No -132-

Page 152: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

INSTALLATION OF MAIN SWITCH

11.03 Providing and Installation of 63 A, 3 phase HRC Main Switch conforming to IEC :

60947 (Part 3) - 1999 or any ammendments up to date with 63 A HRC Fuse, as

directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

2701 3 phase HRC Main

Switch, 63 A conforming

to IEC : 60947 (Part 3) -

1999 or any

ammendments up to

date.

No 4,977.00 1.00 4,977.00

2801 HRC Fuse, 63 A,

conforming to IS :

13703 - 1993 or any

ammendments up to

date.

No 570.00 3.00 1,710.00

Total Cost of Materials 6,687.00

Contingency (2% on Material Cost) 133.74

Sub-Total 6,820.74

Labours

1001 Labour Skilled-I manday 380.00 0.00 -

1002 Labour Skilled-II manday 310.00 0.50 155.00

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 0.00 -

Total Cost of Labours 155.00

Total 6,975.74

Add 15% for overhead & Profit 1,046.36

Grand Total 8,022.10

Say 8,022.00

Supervision (15% on Labour Cost) 23.25

Page No -133-

Page 153: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

INSTALLATION OF MAIN SWITCH

11.04 Providing and Installation of 3 phase HRC Main Switch, 100 A conforming to IEC :

60947 (Part 3) - 1999 or any ammendments up to date with 100 A HRC Main Fuse,

as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

2702 3 phase HRC Main

Switch, 100 A

conforming to IEC :

60947 (Part 3) - 1999 or

any ammendments up

to date.

No 6,678.00 1.00 6,678.00

2802 HRC Fuse, 100 A,

conforming to IS :

13703 - 1993 or any

ammendments up to

date.

No 1,020.00 3.00 3,060.00

Total Cost of Materials 9,738.00

Contingency (2% on Material Cost) 194.76

Sub-Total 9,932.76

Labours

1001 Labour Skilled-I manday 380.00 0.00 -

1002 Labour Skilled-II manday 310.00 0.50 155.00

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 0.00 -

Total Cost of Labours 155.00

Total 10,087.76

Add 15% for overhead & Profit 1,513.16

Grand Total 11,600.92

Say 11,601.00

Supervision (15% on Labour Cost) 23.25

Page No -134-

Page 154: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

INSTALLATION OF MAIN SWITCH

11.05 Providing and Installation of 3 phase HRC Main Switch, 125 A conforming to IEC :

60947 (Part 3) - 1999 or any ammendments up to date with 125 A HRC Fuse, as

directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

2703 3 phase HRC Main

Switch, 125 A

conforming to IEC :

60947 (Part 3) - 1999 or

any ammendments up

to date.

No 8,587.50 1.00 8,587.50

2803 HRC Fuse, 125 A,

conforming to IS :

13703 - 1993 or any

ammendments up to

date.

No 1,177.50 3.00 3,532.50

Total Cost of Materials 12,120.00

Contingency (2% on Material Cost) 242.40

Sub-Total 12,362.40

Labours

1001 Labour Skilled-I manday 380.00 0.00 -

1002 Labour Skilled-II manday 310.00 0.50 155.00

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 0.00 -

Total Cost of Labours 155.00

Total 12,517.40

Add 15% for overhead & Profit 1,877.61

Grand Total 14,395.01

Say 14,395.00

Supervision (15% on Labour Cost) 23.25

Page No -135-

Page 155: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

INSTALLATION OF MAIN SWITCH

11.06 Providing and Installation of 3phase HRC Main Switch, 150 A conforming to IEC :

60947 (Part 3) - 1999 or any ammendments up to date with 150 A HRC Fuse,

as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

2704 3phase HRC Main

Switch, 150 A

conforming to IEC :

60947 (Part 3) - 1999 or

any ammendments up

to date.

No 10,832.00 1.00 10,832.00

2804 HRC Fuse, 150 A,

conforming to IS :

13703 - 1993 or any

ammendments up to

date.

No 1,335.00 3.00 4,005.00

Total Cost of Materials 14,837.00

Contingency (2% on Material Cost) 296.74

Sub-Total 15,133.74

Labours

1001 Labour Skilled-I manday 380.00 0.00 -

1002 Labour Skilled-II manday 310.00 0.50 155.00

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 0.00 -

Total Cost of Labours 155.00

Total 15,288.74

Add 15% for overhead & Profit 2,293.31

Grand Total 17,582.05

Say 17,582.00

Supervision (15% on Labour Cost) 23.25

Page No -136-

Page 156: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

INSTALLATION OF MAIN SWITCH

11.07 Providing and Installation of 3 phase HRC Main Switch, 200 A conforming to IEC :

60947 (Part 3) - 1999 or any ammendments up to date with 200 A HRC Fuse, as

directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

2705 3 phase HRC Main

Switch, 200 A

conforming to IEC :

60947 (Part 3) - 1999 or

any ammendments up

to date.

No 12,300.00 1.00 12,300.00

2805 HRC Fuse, 200 A,

conforming to IS :

13703 - 1993 or any

ammendments up to

date.

No 1,650.00 3.00 4,950.00

Total Cost of Materials 17,250.00

Contingency (2% on Material Cost) 345.00

Sub-Total 17,595.00

Labours

1001 Labour Skilled-I manday 380.00 0.00 -

1002 Labour Skilled-II manday 310.00 0.50 155.00

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 0.00 -

Total Cost of Labours 155.00

Total 17,750.00

Add 15% for overhead & Profit 2,662.50

Grand Total 20,412.50

Say 20,413.00

Supervision (15% on Labour Cost) 23.25

Page No -137-

Page 157: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

INSTALLATION OF MAIN SWITCH

11.08 Providing and Installation of 3 phase HRC Main Switch, 250 A conforming to IEC :

60947 (Part 3) - 1999 or any ammendments up to date with 250 A HRC Fuse, as

directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

2706 3 phase HRC Main

Switch, 250 A

conforming to IEC :

60947 (Part 3) - 1999 or

any ammendments up

to date.

No 13,575.00 1.00 13,575.00

2806 HRC Fuse, 250 A,

conforming to IS :

13703 - 1993 or any

ammendments up

to date.

No 1,765.50 3.00 5,296.50

Total Cost of Materials 18,871.50

Contingency (2% on Material Cost) 377.43

Sub-Total 19,248.93

Labours

1001 Labour Skilled-I manday 380.00 0.00 -

1002 Labour Skilled-II manday 310.00 0.50 155.00

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 0.00 -

Total Cost of Labours 155.00

Total 19,403.93

Add 15% for overhead & Profit 2,910.59

Grand Total 22,314.52

Say 22,315.00

Supervision (15% on Labour Cost) 23.25

Page No -138-

Page 158: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

INSTALLATION OF MAIN SWITCH

11.09 Providing and Installation of 3phase HRC Main Switch, 300 A conforming to IEC :

60947 (Part 3) - 1999 or any ammendments up to date with 300 A HRC Fuse, as

directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

2707 3phase HRC Main

Switch, 300 A

conforming to IEC :

60947 (Part 3) - 1999 or

any ammendments up

to date.

No 14,850.00 1.00 14,850.00

2807 HRC Fuse, 300 A,

conforming to IS :

13703 - 1993 or any

ammendments up to

date.

No 1,881.00 3.00 5,643.00

Total Cost of Materials 20,493.00

Contingency (2% on Material Cost) 409.86

Sub-Total 20,902.86

Labours

1001 Labour Skilled-I manday 380.00 0.00 -

1002 Labour Skilled-II manday 310.00 1.00 310.00

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 1.00 220.00

Total Cost of Labours 530.00

Total 21,432.86

Add 15% for overhead & Profit 3,214.93

Grand Total 24,647.79

Say 24,648.00

Supervision (15% on Labour Cost) 79.50

Page No -139-

Page 159: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

INSTALLATION OF MAIN SWITCH

11.10 Providing and Installation of 3phase HRC Main Switch, 400 A conforming to IEC :

60947 (Part 3) - 1999 or any ammendments up to date with 400 A HRC Fuse, as

directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

2708 3phase HRC Main

Switch, 400 A

conforming to IEC :

60947 (Part 3) - 1999 or

any ammendments up

to date.

No 16,430.40 1.00 16,430.40

2808 HRC Fuse, 400 A,

conforming to IS :

13703 - 1993 or any

ammendments up to

date.

No 4,500.00 3.00 13,500.00

Total Cost of Materials 29,930.40

Contingency (2% on Material Cost) 598.61

Sub-Total 30,529.01

Labours

1001 Labour Skilled-I manday 380.00 0.00 -

1002 Labour Skilled-II manday 310.00 1.00 310.00

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 1.00 220.00

Total Cost of Labours 530.00

Total 31,059.01

Add 15% for overhead & Profit 4,658.85

Grand Total 35,717.86

Say 35,718.00

Supervision (15% on Labour Cost) 79.50

Page No -140-

Page 160: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

CONSTRUCTION OF MAIN SWITCH SHED

11.11 Construction of Shed for Distribution Transformer Main Switch (2.03x0.915m)

1/2.07 Earthwork in excavation in foundation trenches or drain

b) Hard soil etc.

Foundation pit 4 x 0.25 x 0.25 x0.45 = 0.113 cum

Total = 0.113 cum

@ Rs. 435.4/cum.... Rs 49.20

2/4.03 Providing & Laying in position cement concrete

a) 1:03:06 4 x 0.25 x 0.25 x 0.60 = 0.150 cum

1 x 2.08 x 1.17 x 0.10 = 0.242 cum

Total = 0.392 cum

@ Rs. 5968.30/cum.... Rs 2,341.48

3/6.05 Half brick masonry with first class brick in foundation and plinth in

b) in cement mortar 1 : 4 2 x 1.53 x 0.15 = 0.459 sq.m

2 x 0.67 x 0.15 = 0.201 sq.m

Total = 0.66 sq.m

@ Rs. 968.90/sq.m.... Rs 639.47

4/2 1.32 15 mm cement plaster 1 : 3

2 x 2.080 x 0.15 = 0.624sq.m

2 x 1.165 x 0.15 = 0.350 sq.m

Total = 0.974 sq.m

@ Rs. 175.80/sq.m.... Rs 171.14

4 5/21 finishd .21 with floating coat of neat cement (Flooring)

1 x 2.080 x 1.17 = 2.423 sq.m

Total = 2.423 sq.m

@ Rs. 277.00/sq.m.... Rs 671.23

6/5.11 Centering & Shuttering etc. & removal of form works

a) Foundation 4 x 4.00 x 0.25 x 0.20 = 0.800 sq.m

Total = 0.800 sq.m

@ Rs. 299.70/sq.m.... Rs 239.76

7/10.07 Structural steel work; rivetted, bolted, welded in, build up section etc. (Channels)

100x75x75x5mm thick for main posts & Roof structures

2 x 2.100 x 9.56 kg/m = 40.152 sq.mm

2 x 1.972 x 9.56 kg/m = 37.705 sq.mm

2 x 1.830 x 9.56 kg/m = 34.990 sq.mm

2 x 0.922 x 9.56 kg/m = 17.629 sq.mm

NTT = 130.475 sq.mm

1 x 1.830 x 3.50 kg/m = 6.405 sq.mm

2 x 0.9 15 x 3.50 kg/m = 6.405 sq.mm

2 x 1.830 x 3.50 kg/m = 12.810 sq.mm

NTT = 25.620 sq.mm

G. Total = 156.095 sq.mm

@ Rs. 90.80/sq.m.... Rs 14,173.42

Page No -14 1-

Page 161: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

8/13.10 Providing 0.63mm IS thickness CGI sheet wa

Walling above 2 x 0.9 15 x (0.77+0.602)/2

0.77m from 1 x 1.830 x 0.602

Total

@ Rs. 596.30/sq.m....

= 1.255 sq.m

= 1.102 sq.m

= 2.357 sq.m

Rs 1405.50 sq.m

9/ 16.0 1 Providing 0.63mm IS thickness CGI sheet etc.

e) 0.63mm thick

1 x 2.130 x 1.251 = 665 sq.m

Total = 665 sq.m

@ Rs. 432.60/sq.m.... Rs ####

10/9.03 Providing first class local wood works for main switch fixi

1 x 1.830 x 0.025 x 0.30 = 0.0 137 sq.mm

Total = 0.0137 sq.mm

@ Rs. Rs 484.24

35281.40/sq.m....

G. TOTAL Rs 21328.16

Say Rs 21,300.00

Page No -142-

Page 162: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

Page No -143-

Page 163: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

Page No -144-

Page 164: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

Page No -145-

Page 165: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

Page No -146-

Page 166: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

Page No -147-

Page 167: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

Page No -148-

Page 168: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

Page No -149-

Page 169: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

Page No -150-

Page 170: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

Page No -151-

Page 171: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FENCING OF DISTRIBUTION TRANSFORMER SUBSTATION BY RCC PILLAR WITH

BRICK

12.01 Construction of (3.0l x 2.5b x 2.0h)m Fencing for Distribution Substation

Transformer upto 100kVA by using RCC Pillar, Brick etc, as directed by the

engineer in charge.

Earthwork in excavation in foundation trenches or drains etc. (not exceeding 1.5m A

in width or 10sqm on plan) including dressing of sides and ramming of bottoms, lift

upto 1.5m including getting out excavated soil and disposal of surplus excavated

soil as directed within a lead of 50 metres.

Hard Soil ( pick work )

(Coefficient for ordinary soil increased 1.5 times)

Details of cost for 10.00 cum.

Description Unit Qty. Rate/Unit Amount

LABOURS : Mate/Supervisor day 1.20 470.00 564.00

Unskilled day 12.30 220.00 2706.00

3270.00

Sundries and contingencies @ 3% 98.10

3368.10

Add for water charge @ 1% 33.68

3401.78

Add CPOH @ 15% 510.27

Cost for 10 cum 3912.05

cum 4.00 1564.82

Page No -152-

Page 172: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

Steel reinforcement for RCC work including straighthening, cutting, bending,

placing in position and binding all complete.

Hot rolled deformed bars

Details of cost for 1 quintal .

Description Unit Qty. Rate/Unit Amount

MATERIALS :

Deformed twisted steel bars = 1.00 Wastage 5% = 0.05 Total =

1.05q quintal 1.05 5800.00 6090.00

0.105t tonne 0.11 37.46 3.93

Cover block L.S. 10.00 8.00 80.00

LABOUR :

For straightening, cutting, bending,

binding and placing in position-

Blacksmith 1st class day 1.00 440.00 440.00

Beldar day 1.00 220.00 220.00

Sundries and binding wire L.S. 26.91 8.00 215.28

TOTAL 7049.21

Add water charge @ 1% 70.49

TOTAL 7119.70

Add CPOH @ 15% 1067.96

Cost for 100 kg 8187.66

kg 178.59 14622.34

B

Page No -153-

Page 173: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

C Centering and shuttering including strutting,propping etd. And removal of form

a Columns, pillars, piers, abutments, posts and struts.

Details of cost for a Column 30 cm square and 3.50 high : 4x0.30x3.50m = 4.20

Description Unit Qty. Rate/Unit Amount

(A) MATERIALS :

(i) Planks 38 mm thick. (2nd class ) : 2x0.30x3.50 sqm 2.10 : 2x0.48x3.50 sqm 3.36

Total sqm 5.46 Add for wastage @ 5% sqm 0.27 Total 5.73 cum 0.22 28000.00 6104.00

(ii) Ballies 125 mm for struts. : 4x3.80 Rm 15.20 45.00 684.00

Total 6788.00

Assuming that timber shall become

unserviceable after being used 7

times.

Cost of using once 969.71

Carriage & handling @ 2.5% 24.24

(A) 993.95

(B) LABOURS :

2nd class carpenter each 1.25 400.00 500.00

Unskilled each 1.25 220.00 275.00

775.00

Sundries & Contingencies @ 3% 23.25

(B) 798.25

(A) + (B) 1792.20

Add for water charge @ 1% 17.92

1810.12

Add CPOH @ 15% 271.52

Cost for 4.2 sqm 2081.64

sqm 12.00 5947.54

Page No -154-

Page 174: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

D b Lintels, beams, plinth beams, girders, bressumers and cantilevers, etc.

Consider a beam of 6.00 mm clear span, 0.50 m deep and 0.30 m wide and floor

height of 3.50 m.

Cubical content = 6.60x0.50x0.30 cum 0.99

Area in contact with concrete=1x1.3x6.0 sqm 7.8

Description Unit Qty. Rate/Unit Amount

(A) MATERIALS :

(i) Planks 38 mm thick. (2nd class) : 2x0.538x0.376 sqm 0.41 : 2x6.60x0.50 sqm 6.60

: 1x6.00x0.376 sqm 2.26 Total 9.26

Add for wastage @ 10% sqm 0.93 Total 10.19 cum 0.39 28000.00 10836.00

(ii) Ballies 125 mm dia. supports 0 .8 m apart : 8x3.50 Rm 28.00 45.00 1260.00

(iii) Ballies bracing for support : 6x2.00 Rm 12.00 45.00 540.00

Total 12636.00

Assuming that timber shall become

unserviceable after being used 7

times.

Cost of using once 1805.14

Carriage & handling @ 2.5% 45.13

(A) 1850.27

(B) LABOURS :

For assembling, errection,

dismantling and clearing.

2nd class carpenter each 1.25 400.00 500.00

Unskilled each 1.25 220.00 275.00

775.00

Sundries & Contingencies @ 3% 23.25

(B) 798.25

(A) + (B) 2648.52

Add for water charge @ 1% 26.49

2675.01

Add CPOH @ 15% 401.25

Cost for 7.8 sqm 3076.26

sqm 30.80 12147.30

Page No -155-

Page 175: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

Providing and laying in position reinforced cement concrete excluding cost of

centering and shuttering , finishing and reinforcement in -

1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20mm nominal size)

Details of cost for 1.00 cum.

Description Unit Qty. Rate/Unit Amount

MATERIALS :

Stone aggregate 20mm cum 0.67 1800.00 1206.00

Stone aggregate 10mm cum 0.22 1800.00 396.00

Carriage of stone aggregate cum 0.89 73.42 65.34

Coarse sand cum 0.45 850.00 378.25

Carriage of course sand cum 0.45 73.42 32.67

Cement (0.2833cum ) tonne 0.32 9000.00 2880.00

Carriage of cement tonne 0.32 37.46 11.99

LABOURS :

1st class mason day 0.17 450.00 76.50

Unskilled day 2.00 220.00 440.00

Semi-skilled day 0.90 250.00 225.00

Hire charge of concrete mixer day 0.07 1668.00 116.76

Vibrator day 0.07 1068.00 74.76

Sundries L.S 14.30 8.00 114.40

TOTAL 6017.67

Add water charge @ 1% 60.18

TOTAL 6077.85

Add CPOH @ 15% 911.68

For 1.00 cum 6989.53

olumn cum 0.25 1747.38

E

Page No -156-

C

Page 176: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20mm nominal size)

Details of cost for 9.18 cum.

Description Unit Qty. Rate/Unit Amount

MATERIALS :

Stone aggregate 20mm cum 6.15 1800.00 11071.08

Stone aggregate 10mm cum 2.02 1800.00 3635.28

Carriage of stone aggregate cum 8.17 73.42 599.84

Coarse sand cum 4.09 850.00 3472.34

Carriage of course sand cum 4.09 73.42 299.93

Cement (0.2833cum ) tonne 2.94 9000.00 26442.00

Carriage of cement tonne 2.94 37.46 110.06

LABOURS :

Unskilled day 11.29 220.00 2483.80

Coolie day 7.53 220.00 1656.60

Semi-skilled day 8.26 250.00 2065.00

1st class mason day 0.92 450.00 414.00

2nd class mason day 0.92 320.00 294.40

Hire charge of concrete mixer day 0.64 1668.00 1067.52

Vibrator day 0.64 1068.00 683.52

Sundries L.S 131.82 8.00 1054.56

Scaffolding L.S 420.03 8.00 3360.24

Extra labour for lifting material

upto floor V level.0.75x9. 18x2.5

Coolie day 17.20 250.00 4300.00

TOTAL 55349.93

Add water charge @ 1% 553.50

TOTAL 55903.43

Add CPOH @ 15% 8385.51

Cost for 9.18 cum 64288.94

cum 0.50 3501.58

Reinforced cement concrete work in walls including attached pillasters, columns,

F pillers, posts, piers, abutments, return walls, retaining walls, struts, buttresses,

string or lacing courses, fillets etc. upto floor five level excluding cost of centering

shuttering etc complete.

Page No -157-

Page 177: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

G Reinforced cement concrete work in beams, suspended floors, roofs having slope

upto 15° landings, balconies, shelves, chajjas, lintels, bands, window sills, stair

cases, spiral stair cases, cantilevers upto floor five level excluding cost of

centering shuttering etc complete. with 1:2:4(1cement : 2 coarse sand :4 stone

aggregate 20mm)

Beam:

1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20mm nominal size) Details

of cost for 1.00 cum.

Description Unit Qty. Rate/Unit Amount

MATERIALS :

Stone aggregate 20mm cum 0.67 1800.00 1206.00

Stone aggregate 10mm cum 0.22 1800.00 396.00

Carriage of stone aggregate cum 0.89 73.42 65.34

Coarse sand cum 0.45 850.00 378.25

Carriage of course sand cum 0.45 73.42 32.67

Cement (0.2225cum ) tonne 0.32 9000.00 2880.00

Carriage of cement tonne 0.32 37.46 11.99

LABOURS :

1st class mason day 0.24 450.00 108.00

Unskilled day 2.75 220.00 605.00

Semi-skilled day 0.90 250.00 225.00

Hire charge of concrete mixer day 0.08 1668.00 133.44

Vibrator day 0.08 1068.00 85.44

Sundries L.S 14.30 8.00 114.40

Extra labour for lifting material

upto floor V level.(2.5x0.75)

Coolie day 1.88 250.00 470.00

TOTAL 6241.53

Add water charge @ 1% 62.42

TOTAL 6303.95

Add CPOH @ 15% 945.59

Cost for 1.00 cum 7249.54

cum 1.10 7974.49

Page No -158-

Page 178: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

Filling available excavated earth (excluding rock) in trenches, plinth, sides of

H foundations etc. in layers not exceeding 20cm in depth, consolidating each

deposited layer by ramming and watering, lead up to 50 m and lift upto 1.5 m.

Details of cost for 10cum

Description Unit Qty. Rate/Unit Amount

LABOURS :

Mate day 0.20 470.00 94.00

Coolies day 2.50 220.00 550.00

Bhisti day 0.20 250.00 50.00

694.00

Add for water charges @1% 6.94

700.94

Add CPOH @ 15% 105.14

Cost for 10.00cum 806.08

cum 3.20 257.95

I Half brick masonry with first class brick in superstructure above plinth level

upto floor V level.

a) in cement mortar 1:3 ( 1 cement : 3 coarse sand )

Details of cost for 10.00 sqm

Description Unit Qty. Rate/Unit Amount

(A) MATERIALS:

(i) 1st class brick nos 565.00 10.00 5650.00

(ii) Cement mortar 1:3 Rate as per item no.3.04(b) of SH:

Mortars cum 0.28 6128.40 1715.95

Carriage of bricks nos 565.00 0.46 259.90

Sundries & scafolding L.S 13.52 8.00 108.16

(B) LABOURS :

1st class mason each 0.60 450.00 270.00

2nd class mason each 0.60 320.00 192.00

Exatra labour for lifting materials: 10x0.115x0.75x1.5 Coolie each 0.70 220.00 154.00

Semi skilled each 0.70 250.00 175.00

Unskilled each 1.55 220.00 341.00

TOTAL 8866.01

Add water charge @ 1% 88.66

TOTAL 8954.67

Add CPOH @ 15% 1343.20

Cost for 10.00 sqm 10297.87

sqm 20.25 20853.19

Page No -159-

Page 179: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

J 15 mm cement plaster 1:3 (1 cement : 3 fine sand)

Details of cost for 10.00 sqm.

Description Unit Qty. Rate/Unit Amount

(A) MATERIALS :

(i) Cement mortar 1:3 cum 0.17 5914.40 1017.28

(B) LABOURS :

(i) 1st class mason each 0.80 450.00 360.00

(ii) Semi-skilled each 0.99 250.00 247.50

(iii) Unskilled each 0.88 220.00 193.60

Scaffolding and sundries LS 12.61 8.00 100.88

TOTAL 1919.26

Add 1% for water charges 19.19

TOTAL 2039.33

Add CPOH @15% 305.90

Cost for 10.00 sqm 2345.23

sqm 57.70 13531.98

Providing & fixing 1mm thick M.S. door with frame of 40x40x6mm. Angle Iron &

K 3mm M.S.Gusset plates at the junction and corners, all necessary fittings

complete, including applying a priming coat of steel primer.

(a)Using M.S angles (40x40x6)mm for diagonal braces

Consider a double leaf door shutter of size 1200x2400mm giving an area

=2x1.20x2.40 = 5.76sqm

Details of cost of M.S. Sheet door of 5.76 sqm area

Description Unit Qty. Rate/Unit Amount

(A) MATERIALS

(i) M.S. Sheet 1mm thick. @ 7.85 kg/ sqm kg 45.2 16 Add for wastage @ 10% 4.522 49.738 qtl 0.497 4950 2460.15

Carriage & handling @ 2.5% 61.5

Total (I) = 2521.65

(ii) Gusset plates 3mm thick Area of one gusset plate 0.30 x 0.04 0.012 1/2 x 0.26 (0.04+0.30) 0.044 sqm 0.056 8 x 0.0562 sqm 0.45 2 x 22/7 x 1/4 x 0.30 x 0.30 sqm 0.141 sqm 0.591 @ 23.55 kg/sqm kg 13.918 Add for wastage @ 10% 1.392 15.31 qtl 0.153 4628 708.08

Carriage & handling @ 2.5% 17.7

Total (II) = 725.78

Page No -160-

Page 180: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

(iii) Angle Iron

40mm x 40mm x 6mm

Sides: 4x2.40 m 9.6 Top & Bottom: 2x2x1.20 m 4.8

Diagonals: 1x2x2.50 m 5 1x2x2.45 m 4.9

m 24.3

Add for wastage @ 10% m 2.43

m 26.73

@ 3.5 kg/Rm kg 93.555

qtl 0.936 6985 6537.96

Carriage & handling @ 2.5% 163.45

Total (III) = 6701.41

(iv) M.S Cleats.

(40x10) mm: 4 x 0.20 m 0.8

Add for wastage @ 25% m 0.2

m 1 @ 3.15 kg/m kg 3.15

qtl 0.032 70 2.24

Carriage & handling @ 2.5% 0.06

Total (IV) = 2.3

(v) Pin Clamps (Pintles) 50mm x 6 mm: 4 x 0.45 m 1.8

Add for wastage @ 11% m 0.198

m 1.998

@ 2.35 kg/m kg 4.695

qtl 0.047 4628 217.52

Carriage & handling @ 2.5% 5.44

Total (V) = 222.96

(vi) 20 mm diameter M.S. bar as

pin:

4 x 0.075 m m 0.3

Add for wastage @ 5% m 0.015

m 0.315 @ 2.47 kg/m kg 0.778

qtl 0.008 4000 32

Carriage & handling @ 2.5% 0.8

Total (VI) = 32.8

(vii) 12mm diameter bolts & nuts

60 mm long: 4 x 2 each 8

@ 0.183 kg/No kg 1.464

qtl 0.015 10929 163.94

Carriage & handling @ 2.5% 4.1

Total (VII) = 168.04

(viii) 10mm diameter 45 cm long

hooks. each 2 64.29 128.58

Page No -16 1-

Page 181: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

"(ix) C.C 1:3:6 to fix pin Clamps = 4 x 0.40 x 0.20 x 0.20 cum 0.064 5968.3 381.97

(x) C.C 1 :2:4 for a block to be

"embedded

in floor to keep shutters intact = 1 x 0.1 5 x 0.1 0 x 0.20 cum 0.003 0 0

(xi) Locking Arrangement & Handle each 1 51 .43 51 .43

"(xii) Priming Coat M.S.Sheet: 2 x 5.76 sqm 1 1 .52 Angle Iron: 24.30 x 0.1 6 sqm 3.888

1 5.408 36.6 563.93

Total (VIII) = 1 1 25.91

I + II + III + IV + V + VI + VII + VIII = (A) 1 1 500.85

(B) LABOUR

(i) 1 st class Fitter each 2 440 880

(ii) 1 st class Blacksmith each 3 440 1 320

(iii) 2nd class Blacksmith each 4 320 1 280

(iv) 1 st class Mason each 0.06 450 27

(v) 2nd class Mason each 0.06 320 1 9.2

(vi) Unskilled labour each 5 250 1 250

(B) 4776.2

(A) + (B) 1 6277.05

Add for Sundries & Contingencies @

3%

459.93

(Except on A,B & C ) Add for Water Charges & Electricity @

1 .5%

229.97

(Except on A,B & C ) Add 5% for Overhead charges

(Except on A,B & C )

766.56

Add 1 0% for contractor profit

(Except on A,B & C )

1 533.1 2

Cost of M.S. Sheet door of 5.76 sqm. 1 9266.63

Cost per sqm. 3344.9

sqm 1.75 5853.58

Total TOTAL Cost COST 88,002.14

Say 88,002.00

"

"

"

Page No -162-

Page 182: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FENCING OF DISTRIBUTION TRANSFORMER SUBSTATION BY RCC PILLAR WITH

BRICK

12.02 Construction of (3.5l x 3.0b x 2.0h)m Fencing for Distribution Substation

Transformer above 100kVA by using RCC Pillar, Brick etc, as directed by the

engineer in charge.

Earthwork in excavation in foundation trenches or drains etc. (not exceeding 1.

5m in width or 10sqm on plan) including dressing of sides and ramming of

bottoms, lift upto 1.5m including getting out excavated soil and disposal of

surplus excavated soil as directed within a lead of 50 metres.

Hard Soil ( pick work )

(Coefficient for ordinary soil increased 1.5 times) Details

of cost for 10.00 cum. Description Unit Qty. Rate/Unit Amount

LABOURS :

Mate/Supervisor day 1.20 470.00 564.00

Unskilled day 12.30 220.00 2706.00

3270.00

Sundries and contingencies @ 3% 98.10

3368.10

Add for water charge @ 1% 33.68

3401.78

Add CPOH @ 15% 510.27

Cost for 10 cum 3912.05

cum 4.00 1564.82

Steel reinforcement for RCC work including straighthening, cutting, bending,

placing in position and binding all complete.

Hot rolled deformed bars Details

of cost for 1 quintal .

Description Unit Qty. Rate/Unit Amount

MATERIALS :

Deformed twisted steel bars = 1.00 q Wastage 5% = 0.05 q

Total = 1.05 qquintal 1.05 5800.00 6090.00

Carriage of steel 1.05/10 = 0.105 tonne 0.11 37.46 3.93

Cover block L.S. 10.00 8.00 80.00

LABOUR :

For straightening, cutting, bending,

binding and placing in position-

Blacksmith 1st class day 1.00 440.00 440.00

Beldar day 1.00 220.00 220.00

Sundries and binding wire L.S. 26.91 8.00 215.28

TOTAL 7049.21

Add water charge @ 1% 70.49

TOTAL 7119.70

Add CPOH @ 15% 1067.96

Cost for 100 kg 8187.66

kg 199.70 16350.76

Page No -163-

A

B

Page 183: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

f or :

a Columns, pillars, piers, abutments, posts and struts.

Details of cost for a Column 30cm square and 3.50 high : 4x0.30x3.50m=4.20sqm

Description Unit Qty. Rate/Unit Amount

(A) MATERIALS :

(i) Planks 38 mm thick. (2nd class ) : 2x0.30x3.50 sqm 2.10 : 2x0.48x3.50 sqm 3.36

Total sqm 5.46 Add for wastage @ 5% sqm 0.27 Total 5.73

cum 0.22 28000.00 6,104.00

(ii) Ballies 125 mm for struts. : 4x3.80 Rm 15.20 45.00 684.00

Total 6,788.00

Assuming that timber shall become

unserviceable after being used 7

times.

Cost of using once 969.71

Carriage & handling @ 2.5% 24.24

(A) 993.95

(B) LABOURS :

2nd class carpenter each 1.25 400.00 500.00

Unskilled each 1.25 220.00 275.00

775.00

Sundries & Contingencies @ 3% 23.25

(B) 798.25

(A) + (B) 1,792.20

Add for water charge @ 1% 17.92

1,810.12

Add CPOH @ 15% 271.52

Cost for 4.2 sqm 2,081.64

sqm 12.00 5,947.54

C Centering and shuttering including strutting,propping etd. And removal of form

Page No -164-

Page 184: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

D b Lintels, beams, plinth beams, girders, bressumers and cantilevers, etc.

Consider a beam of 6.00 mm clear span, 0.50 m deep and 0.30 m wide and floor

height of 3.50 m.

Cubical content = 6.60x0.50x0.30 cum 0.99

Area in contact with concrete=1x1.3x6.0 sqm 7.8

Description Unit Qty. Rate/Unit Amount

(A) MATERIALS :

(i) Planks 38 mm thick. (2nd class) : 2x0.538x0.376 sqm 0.41 : 2x6.60x0.50 sqm 6.60 : 1x6.00x0.376 sqm 2.26

Total 9.26 Add for wastage @ 10% sqm 0.93

Total 10.19 cum 0.39 28000.00 10836.00

(ii) Ballies 125 mm dia. supports 0 .8 m apart : 8x3.50 Rm 28.00 45.00 1260.00

(iii) Ballies bracing for support : 6x2.00 Rm 12.00 45.00 540.00

Total 12636.00

Assuming that timber shall become

unserviceable after being used 7

times.

Cost of using once 1805.14

Carriage & handling @ 2.5% 45.13

(A) 1850.27

(B) LABOURS :

For assembling, errection,

dismantling and clearing.

2nd class carpenter each 1.25 400.00 500.00

Unskilled each 1.25 220.00 275.00

775.00

Sundries & Contingencies @ 3% 23.25

(B) 798.25

(A) + (B) 2648.52

Add for water charge @ 1% 26.49

2675.01

Add CPOH @ 15% 401.25

Cost for 7.8 sqm 3076.26

sqm 36.40 14355.88

Page No -165-

Page 185: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

Providing and laying in position reinforced cement concrete excluding cost of

centering and shuttering , finishing and reinforcement in -

1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20mm nominal size)

Details of cost for 1.00 cum.

Description Unit Qty. Rate/Unit Amount

MATERIALS :

Stone aggregate 20mm cum 0.67 1800.00 1206.00

Stone aggregate 10mm cum 0.22 1800.00 396.00

Carriage of stone aggregate cum 0.89 73.42 65.34

Coarse sand cum 0.45 850.00 378.25

Carriage of course sand cum 0.45 73.42 32.67

Cement (0.2833cum ) tonne 0.32 9000.00 2880.00

Carriage of cement tonne 0.32 37.46 11.99

LABOURS :

1st class mason day 0.17 450.00 76.50

Unskilled day 2.00 220.00 440.00

Semi-skilled day 0.90 250.00 225.00

Hire charge of concrete mixer day 0.07 1668.00 116.76

Vibrator day 0.07 1068.00 74.76

Sundries L.S 14.30 8.00 114.40

TOTAL 6017.67

Add water charge @ 1% 60.18

TOTAL 6077.85

Add CPOH @ 15% 911.68

For 1.00 cum 6989.53

olumn cum 0.25 1747.38

E

Page No -166-

C

Page 186: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20mm nominal size) Details

of cost for 9.18 cum.

Description Unit Qty. Rate/Unit Amount

MATERIALS :

Stone aggregate 20mm cum 6.15 1800.00 11071.08

Stone aggregate 10mm cum 2.02 1800.00 3635.28

Carriage of stone aggregate cum 8.17 73.42 599.84

Coarse sand cum 4.09 850.00 3472.34

Carriage of course sand cum 4.09 73.42 299.93

Cement (0.2833cum ) tonne 2.94 9000.00 26442.00

Carriage of cement tonne 2.94 37.46 110.06

LABOURS :

Unskilled day 11.29 220.00 2483.80

Coolie day 7.53 220.00 1656.60

Semi-skilled day 8.26 250.00 2065.00

1st class mason day 0.92 450.00 414.00

2nd class mason day 0.92 320.00 294.40

Hire charge of concrete mixer day 0.64 1668.00 1067.52

Vibrator day 0.64 1068.00 683.52

Sundries L.S 131.82 8.00 1054.56

Scaffolding L.S 420.03 8.00 3360.24

Extra labour for lifting material

upto floor V level.0.75x9. 18x2.5

Coolie day 17.20 250.00 4300.00

TOTAL 55349.93

Add water charge @ 1% 553.50

TOTAL 55903.43

Add CPOH @ 15% 8385.51

Cost for 9.18 cum 64288.94

cum 0.5 3501.58

pillers, posts, piers, abutments, return walls, retaining walls, struts, buttresses,

F string or lacing courses, fillets etc. upto floor five level excluding cost of centering

shuttering etc complete.

Page No -167-

Page 187: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

Reinforced cement concrete work in beams, suspended floors, roofs having slope upto

15° landings, balconies, shelves, chajjas, lintels, bands, window sills, stair

G cases, spiral stair cases, cantilevers upto floor five level excluding cost of centering

shuttering etc complete. with 1:2:4(1cement : 2 coarse sand :4 stone aggregate

20mm)

Beam:

1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20mm nominal size)

Details of cost for 1.00 cum.

Description Unit Qty. Rate/Unit Amount

MATERIALS :

Stone aggregate 20mm cum 0.67 1800.00 1206.00

Stone aggregate 10mm cum 0.22 1800.00 396.00

Carriage of stone aggregate cum 0.89 73.42 65.34

Coarse sand cum 0.45 850.00 378.25

Carriage of course sand cum 0.45 73.42 32.67

Cement (0.2225cum ) tonne 0.32 9000.00 2880.00

Carriage of cement tonne 0.32 37.46 11.99

LABOURS :

1st class mason day 0.24 450.00 108.00

Unskilled day 2.75 220.00 605.00

Semi-skilled day 0.90 250.00 225.00

Hire charge of concrete mixer day 0.08 1668.00 133.44

Vibrator day 0.08 1068.00 85.44

Sundries L.S 14.30 8.00 114.40

Extra labour for lifting material

upto floor V level.(2.5x0.75)

Coolie day 1.88 250.00 470.00

TOTAL 6241.53

Add water charge @ 1% 62.42

TOTAL 6303.95

Add CPOH @ 15% 945.59

Cost for 1.00 cum 7249.54

cum 1.63 11816.75

Page No -168-

Page 188: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

Filling available excavated earth (excluding rock) in trenches, plinth, sides of

H foundations etc. in layers not exceeding 20cm in depth, consolidating each

deposited layer by ramming and watering, lead up to 50 m and lift upto 1.5 m.

Details of cost for 10cum

Description Unit Qty. Rate/Unit Amount

LABOURS :

Mate day 0.20 470.00 94.00

Coolies day 2.50 220.00 550.00

Bhisti day 0.20 250.00 50.00

694.00

Add for water charges @1% 6.94

700.94

Add CPOH @ 15% 105.14

Cost for 10.00cum 806.08

cum 3.20 257.95

I Half brick masonry with first class brick in fsuperstructure above plinth level

a) in cement moratar 1:3 ( 1 cement : 3 coarse sand )

Details of cost for 10.00 sqm

Description Unit Qty. Rate/Unit Amount

(A) MATERIALS:

(i) 1st class brick nos 565.00 10.00 5650.00

(ii) Cement mortar 1:3 Rate as per item no.3.04(b) of SH:

Mortars cum 0.28 6128.40 1715.95

Carriage of bricks nos 565.00 0.46 259.90

Sundries & scafolding L.S 13.52 8.00 108.16

(B) LABOURS :

1st class mason each 0.60 450.00 270.00

2nd class mason each 0.60 320.00 192.00

Exatra labour for lifting materials: 10x0. 1 15x0.75x1.5 Coolie each 0.70 220.00 154.00

Semi skilled each 0.70 250.00 175.00

Unskilled each 1.55 220.00 341.00

TOTAL 8866.01

Add water charge @ 1% 88.66

TOTAL 8954.67

Add CPOH @ 15% 1343.20

Cost for 10.00 sqm 10297.87

sqm 24.25 24972.33

Page No -169-

Page 189: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

J 15 mm cement plaster 1:3 (1 cement : 3 fine sand)

Details of cost for 10.00 sqm.

Description Unit Qty. Rate/Unit Amount

(A) MATERIALS :

(i) Cement mortar 1:3 cum 0.17 5914.40 1017.28

(B) LABOURS :

(i) 1st class mason each 0.80 450.00 360.00

(ii) Semi-skilled each 0.99 250.00 247.50

(iii) Unskilled each 0.88 220.00 193.60

Scaffolding and sundries LS 12.61 8.00 100.88

TOTAL 1919.26

Add 1% for water charges 19.19

TOTAL 2039.33

Add CPOH @15% 305.90

Cost for 10.00 sqm 2345.23

sqm 69.85 16381.43

Providing & fixing 1mm thick M.S. door with frame of 40x40x6mm. Angle Iron &

K 3mm M.S.Gusset plates at the junction and corners, all necessary fittings

complete, including applying a priming coat of steel primer.

(a)Using M.S angles (40x40x6)mm for diagonal braces

Consider a double leaf door shutter of size 1200x2400mm giving an area

=2x1.20x2.40 = 5.76sqm

Details of cost of M.S. Sheet door of 5.76 sqm area

Description Unit Qty. Rate/Unit Amount

(A) MATERIALS

(i) M.S. Sheet 1mm thick. @ 7.85 kg/ sqm kg 45.22 Add for wastage @ 10% 4.52 49.74 qtl 0.50 4950.00 2460.15

Carriage & handling @ 2.5% 61.50

Total (I) = 2521.65

(ii) Gusset plates 3mm thick Area of one gusset plate 0.30 x 0.04 0.01 1/2 x 0.26 (0.04+0.30) 0.04 sqm 0.06 8 x 0.0562 sqm 0.45 2 x 22/7 x 1/4 x 0.30 x 0.30 sqm 0.14 sqm 0.59 @ 23.55 kg/sqm kg 13.92 Add for wastage @ 10% 1.39 15.31 qtl 0.15 4628.00 708.08

Carriage & handling @ 2.5% 17.70

Total (II) = 725.78

Page No -170-

Page 190: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

(iii) Angle Iron 40mm x 40mm x 6mm Sides: 4x2.40 m 9.60 Top & Bottom: 2x2x1.20 m 4.80 Diagonals: 1x2x2.50 m 5.00

1x2x2.45 m 4.90

m 24.30 Add for wastage @ 10% m 2.43

m 26.73 @ 3.5 kg/Rm kg 93.56

qtl 0.94 6985.00 6537.96

Carriage & handling @ 2.5% 163.45

Total (III) = 6701.41

(iv) M.S Cleats. (40x10) mm: 4 x 0.20 m 0.80 Add for wastage @ 25% m 0.20

m 1.00 @ 3.15 kg/m kg 3.15

qtl 0.03 70.00 2.24

Carriage & handling @ 2.5% 0.06

Total (IV) = 2.30

(v) Pin Clamps (Pintles) 50mm x 6 mm: 4 x 0.45 m 1.80 Add for wastage @ 11% m 0.20

m 2.00 @ 2.35 kg/m kg 4.70

qtl 0.05 4628.00 217.52

Carriage & handling @ 2.5% 5.44

Total (V) = 222.96

(vi) 20 mm diameter M.S. bar as pin: 4 x 0.075 m m 0.30 Add for wastage @ 5% m 0.02

m 0.32 @ 2.47 kg/m kg 0.78

qtl 0.01 4000.00 32.00

Carriage & handling @ 2.5% 0.80

Total (VI) = 32.80

(vii) 12mm diameter bolts & nuts 60 mm long: 4 x 2 each 8.00 @ 0.183 kg/No kg 1.46

qtl 0.02 10929.00 163.94

Page No -17 1-

Page 191: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

Carriage & handling @ 2.5% 4.10

Total (VII) = 168.04

hooks. each 2.00 64.29 128.58

I,(ix) C.C 1:3:6 to fix pin Clamps = 4 x 0.40 x 0.20 x 0.20 cum 0.06 5968.30 381.97

(x) C.C 1:2:4 for a block to be

I,embedded

in floor to keep shutters intact = 1 x 0.15 x 0.10 x 0.20 cum 0.00 0.00 0.00

(xi) Locking Arrangement & Handle each 1.00 51.43 51.43

I,(xii) Priming Coat M.S.Sheet: 2 x 5.76 sqm 11.52 Angle Iron: 24.30 x 0.16 sqm 3.89

15.41 36.60 563.93

Total (VIII) = 1125.91

I + II + III + IV + V + VI + VII + VIII = (A) 11500.85

(B) LABOUR

(i) 1st class Fitter each 2.00 440.00 880.00

(ii) 1st class Blacksmith each 3.00 440.00 1320.00

(iii) 2nd class Blacksmith each 4.00 320.00 1280.00

(iv) 1st class Mason each 0.06 450.00 27.00

(v) 2nd class Mason each 0.06 320.00 19.20

(vi) Unskilled labour each 5.00 250.00 1250.00

(B) 4776.20

(A) + (B) 16277.05

Add for Sundries & Contingencies @

3% (Except on A,B & C )

459.93

Add for Water Charges & Electricity @

1.5% (Except on A,B & C )

229.97

Add 5% for Overhead charges

(Except on A,B & C )

766.56

Add 10% for contractor profit

(Except on A,B & C )

1533.12

Cost of M.S. Sheet door of 5.76 sqm. 19266.63

Cost per sqm. 3344.90

sqm 1.75 5853.58

Total TOTAL Cost COST 102,750.00

Say 102,750.00

I,

I,

I,

Page No -172-

Page 192: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FENCING OF DISTRIBUTION TRANSFORMER SUBSTATION BY FENCING POST AND

FENCING NET

12.03 Construction of (3.0l x 2.5b x 2.0h)m Fencing for Distribution Substation

Transformer up to 100kVA by using fencing post and fencing net, as directed by the

engineer in charge.

A 2.0m high polysteel goat proof fencing with 2.6m angle iron posts 50 x 50 x 6mm

size placed 2.0m apart embedded in cement concrete block 1:3:6 (1 cement : 3 sand

: 6 stone agge gate) of size 25 x 25 x 60 cm fixing with nails and wire etc. including

earthwork complete.

Details of cost for 30 Rm.

Description Unit Qty. Rate/Unit Amount

(A) MATERIALS:

(i) Angle iron 50x50x6mm @ 4.50kg/m.

: 16 x 2.6 x 4.50 kg 187.20 Add for wastage @ 5% kg 9.36

kg 196.56 qtl 1.97 6985.00 13760.45

(ii) Polysteel goat proof wire : 2.0 x 0sqm 60.00 445.00 26700.00

(iii) Nails kg 2.00 80.00 160.00

40620.45

Carriage & handling @ 2.5% 1015.51

(iv) Cement concrete block 1 : 3 : 6 (1cement:3 sand:6 stone aggregate

20mm size)

: 16 x 0.25 x 0.25 x 0.60 cum 0.60 7602.30 4561.38

(v) Earthwork for cement concrete block : 16 x 0.25 x 0.25 x 0.60 cum 0.60 327.20 196.32

(A) 46393.66

(B) LABOURS :

(For drilling holes, fitting and fixing) (i) 1st class mason each 0.12 450.00 54.00

(ii) 2nd class mason each 0.12 320.00 38.40

(iii) 1st class blacksmith each 0.78 440.00 343.20

(iv) 2nd class blacksmith each 2.75 320.00 880.00

(v) Unskilled each 2.72 220.00 598.40

1914.00

Sundries & contingencies @ 3% 57.42

(B) 1971.42

(A) + (B) 48365.08

Add for water charge @ 1% except

on (A) iv & v, i.e. on Rs.

43607.38 436.07

TOTAL 48801.15

Add CPOH @ 15% 7320.17

Cost for 30.00 Rm 56121.32

Rm 10.00 18707.11

Page No -173-

Page 193: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

Providing & fixing 1mm thick M.S. door with frame of 40x40x6mm. Angle Iron & B

3mm M.S.Gusset plates at the junction and corners, all necessary fittings complete,

including applying a priming coat of steel primer.

(a)Using M.S angles (40x40x6)mm for diagonal braces

Consider a double leaf door shutter of size 1200x2400mm giving an area

=2x1.20x2.40 = 5.76sqm

Details of cost of M.S. Sheet door of 5.76 sqm area

Description Unit Qty. Rate/Unit Amount

(A) MATERIALS

(i) M.S. Sheet 1mm thick. @ 7.85 kg/ sqm kg 45.22 Add for wastage @ 10% 4.52 49.74 qtl 0.50 4950.00 2460.15

Carriage & handling @ 2.5% 61.50

Total (I) = 2521.65

(ii) Gusset plates 3mm thick Area of one gusset plate 0.30 x 0.04 0.01 1/2 x 0.26 (0.04+0.30) 0.04 sqm 0.06 8 x 0.0562 sqm 0.45 2 x 22/7 x 1/4 x 0.30 x 0.30 sqm 0.14 sqm 0.59 @ 23.55 kg/sqm kg 13.92 Add for wastage @ 10% 1.39 15.31 qtl 0.15 4628.00 708.08

Carriage & handling @ 2.5% 17.70

Total (II) = 725.78

(iii) Angle Iron 40mm x 40mm x 6mm Sides: 4x2.40 m 9.60 Top & Bottom: 2x2x1.20 m 4.80 Diagonals: 1x2x2.50 m 5.00

1x2x2.45 m 4.90 m 24.30 Add for wastage @ 10% m 2.43 m 26.73 @ 3.5 kg/Rm kg 93.56 qtl 0.94 6985.00 6537.96

Carriage & handling @ 2.5% 163.45

Total (III) = 6701.41

Page No -174-

Page 194: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

(iv) M.S Cleats. (40x10) mm: 4 x 0.20 m 0.80 Add for wastage @ 25% m 0.20 m 1.00 @ 3.15 kg/m kg 3.15 qtl 0.03 70.00 2.24

Carriage & handling @ 2.5% 0.06

Total (IV) = 2.30

(v) Pin Clamps (Pintles) 50mm x 6 mm: 4 x 0.45 m 1.80 Add for wastage @ 11% m 0.20 m 2.00 @ 2.35 kg/m kg 4.70 qtl 0.05 4628.00 217.52

Carriage & handling @ 2.5% 5.44

Total (V) = 222.96

(vi) 20 mm diameter M.S. bar as pin: 4 x 0.075 m m 0.30 Add for wastage @ 5% m 0.02 m 0.32 @ 2.47 kg/m kg 0.78 qtl 0.01 4000.00 32.00

Carriage & handling @ 2.5% 0.80

Total (VI) = 32.80

(vii) 12mm diameter bolts & nuts 60 mm long: 4 x 2 each 8.00 @ 0.183 kg/No kg 1.46 qtl 0.02 10929.00 163.94

Carriage & handling @ 2.5% 4.10

Total (VII) = 168.04

(viii) 10mm diameter 45 cm long hoo ks.each 2.00 64.29 128.58

"(ix) C.C 1:3:6 to fix pin Clamps = 4 x 0.40 x 0.20 x 0.20 cum 0.06 5968.30 381.97

"(x) C.C 1:2:4 for a block to be embedded in floor to keep shutters intact = 1 x 0.15 x 0.10 x 0.20 cum 0.00 0.00 0.00

(xi) Locking Arrangement & Handle each 1.00 51.43 51.43

"(xii) Priming Coat M.S.Sheet: 2 x 5.76 sqm 11.52 Angle Iron: 24.30 x 0.16 sqm 3.89 15.41 36.60 563.93

Total (VIII) = 1125.91

I + II + III + IV + V + VI + VII + VIII = (A) 11500.85

"

"

"

Page No -175-

Page 195: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

(B) LABOUR

(i) 1st class Fitter each 2.00 440.00 880.00

(ii) 1st class Blacksmith each 3.00 440.00 1320.00

(iii) 2nd class Blacksmith each 4.00 320.00 1280.00

(iv) 1st class Mason each 0.06 450.00 27.00

(v) 2nd class Mason each 0.06 320.00 19.20

(vi) Unskilled labour each 5.00 250.00 1250.00

(B) 4776.20

(A) + (B) 16277.05

Add for Sundries & Contingencies

@ 3% (Except on A,B & C )

459.93

Add for Water Charges & Electricity

@ 1.5% (Except on A,B & C )

229.97

Add 5% for Overhead charges

(Except on A,B & C )

766.56

Add 10% for contractor profit

(Except on A,B & C )

1533.12

Cost of M.S. Sheet door of 5.76 sqm. 19266.63

Cost per sqm. 3344.90

sqm 2.00 6689.80

TOTAL COST 25396.91

Say 25397.00

Page No -176-

Page 196: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FENCING OF DISTRIBUTION TRANSFORMER SUBSTATION BY FENCING POST AND

FENCING NET

12.04 Construction of (3.5l x 3.0b x 2.0h)m Fencing for Distribution Substation

Transformer above 100kVA by using fencing post and fencing net, as directed by

the engineer in charge.

2.0m high polysteel goat proof fencing with 2.6m angle iron posts 50 x 50 x 6mm size placed 2.0m apart embedded in cement concrete block 1 :3:6 (1 cement : 3

A sand : 6 stone aggegate) of size 25 x 25 x 60 cm fixing with nails and wire etc.

including earthwork complete.

Details of cost for 30 Rm.

Description Unit Qty. Rate/Unit Amount

(A) MATERIALS

(i) Angle iron 50x50x6mm @ 4.50kg/m. : 16 x 2.6 x 4.50 kg 187.20

Add for wastage @ 5% kg 9.36 kg 196.56 qtl 1.97 6985.00 13760.45

(ii) Polysteel goat proof wire : 2.0 x 0sqm 60.00 445.00 26700.00

(iii) Nails kg 2.00 80.00 160.00

40620.45

Carriage & handling @ 2.5% 1015.51

(iv) Cement concrete block 1 : 3 : 6 (1cement:3 sand:6 stone aggregate

20mm size)

: 16 x 0.25 x 0.25 x 0.60 cum 0.60 7602.30 4561.38

(v) Earthwork for cement concrete block : 16 x 0.25 x 0.25 x 0.60 cum 0.60 327.20 196.32

(A) 46393.66

(B) LABOURS :

(For drilling holes, fitting and fixing) (i) 1st class mason each 0.12 450.00 54.00

(ii) 2nd class mason each 0.12 320.00 38.40

(iii) 1st class blacksmith each 0.78 440.00 343.20

(iv) 2nd class blacksmith each 2.75 320.00 880.00

(v) Unskilled each 2.72 220.00 598.40

1914.00

Sundries & contingencies @ 3% 57.42

(B) 1971.42

(A) + (B) 48365.08

Add for water charge @ 1% except

on (A) iv & v, i.e. on Rs.

43607.38 436.07

TOTAL 48801.15

Add CPOH @ 15% 7320.17

Cost for 30.00 Rm 56121.32

Total Cost Rm 12.00 22448.53

Page No -177-

Page 197: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

Providing & fixing 1mm thick M.S. door with frame of 40x40x6mm. Angle Iron & B

3mm M.S.Gusset plates at the junction and corners, all necessary fittings complete,

including applying a priming coat of steel primer.

(a)Using M.S angles (40x40x6)mm for diagonal braces

Consider a double leaf door shutter of size 1200x2400mm giving an area

=2x1.20x2.40 = 5.76sqm

Details of cost of M.S. Sheet door of 5.76 sqm area

Description Unit Qty. Rate/Unit Amount

(A) MATERIALS

(i) M.S. Sheet 1mm thick. @ 7.85 kg/ sqm kg 45.22 Add for wastage @ 10% 4.52 49.74 qtl 0.50 4950.00 2460.15

Carriage & handling @ 2.5% 61.50

Total (I) 2521.65

(ii) Gusset plates 3mm thick Area of one gusset plate 0.30 x 0.04 0.01 1/2 x 0.26 (0.04+0.30) 0.04 sqm 0.06 8 x 0.0562 sqm 0.45 2 x 22/7 x 1/4 x 0.30 x 0.30 sqm 0.14 sqm 0.59 @ 23.55 kg/sqm kg 13.92 Add for wastage @ 10% 1.39 15.31 qtl 0.15 4628.00 708.08

Carriage & handling @ 2.5% 17.70

Total (II) 725.78

(iii) Angle Iron 40mm x 40mm x 6mm Sides: 4x2.40 m 9.60 Top & Bottom: 2x2x1.20 m 4.80 Diagonals: 1x2x2.50 m 5.00

1x2x2.45 m 4.90 m 24.30 Add for wastage @ 10% m 2.43 m 26.73 @ 3.5 kg/Rm kg 93.56 qtl 0.94 6985.00 6537.96

Carriage & handling @ 2.5% 163.45

Total (III) 6701.41

Page No -178-

Page 198: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

(iv) M.S Cleats.

(40x10) mm: 4 x 0.20 m 0.80 Add for wastage @ 25% m 0.20

m 1.00 @ 3.15 kg/m kg 3.15

qtl 0.03 70.00 2.24

Carriage & handling @ 2.5% 0.06

Total (IV) 2.30

(v) Pin Clamps (Pintles) 50mm x 6 mm: 4 x 0.45 m 1.80 Add for wastage @ 11% m 0.20

m 2.00 @ 2.35 kg/m kg 4.70

qtl 0.05 4628.00 217.52

Carriage & handling @ 2.5% 5.44

Total (V) 222.96

(vi) 20 mm diameter M.S. bar as pin: 4 x 0.075 m m 0.30 Add for wastage @ 5% m 0.02

m 0.32 @ 2.47 kg/m kg 0.78

qtl 0.01 4000.00 32.00

Carriage & handling @ 2.5% 0.80

Total (VI) 32.80

(vii) 12mm diameter bolts & nuts 60 mm long: 4 x 2 each 8.00 @ 0.183 kg/No kg 1.46

qtl 0.02 10929.00 163.94

Carriage & handling @ 2.5% 4.10

Total (VII) 168.04

(viii) 10mm diameter 45 cm long hook s.each 2.00 64.29 128.58

I,(ix) C.C 1:3:6 to fix pin Clamps = 4 x 0.40 x 0.20 x 0.20 cum 0.06 5968.30 381.97

I,(x) C.C 1:2:4 for a block to be embedded in floor to keep shutters intact = 1 x 0.15 x 0.10 x 0.20 cum 0.00 0.00 0.00

(xi) Locking Arrangement & Handle each 1.00 51.43 51.43

I,(xii) Priming Coat M.S.Sheet: 2 x 5.76 sqm 11.52 Angle Iron: 24.30 x 0.16 sqm 3.89

15.41 36.60 563.93

Total (VIII) 1125.91

I + II + III + IV + V + VI + VII + VIII = (A) 11500.85

I,

I,

I,

Page No -179-

Page 199: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

(B) LABOUR

(i) 1st class Fitter each 2.00 440.00 880.00

(ii) 1st class Blacksmith each 3.00 440.00 1320.00

(iii) 2nd class Blacksmith each 4.00 320.00 1280.00

(iv) 1st class Mason each 0.06 450.00 27.00

(v) 2nd class Mason each 0.06 320.00 19.20

(vi) Unskilled labour each 5.00 250.00 1250.00

(B) 4776.20

(A) + (B) 16277.05

Add for Sundries & Contingencies @

3% (Except on A,B & C )

459.93

Add for Water Charges & Electricity @

1.5% (Except on A,B & C )

229.97

Add 5% for Overhead charges

(Except on A,B & C )

766.56

Add 10% for contractor profit

(Except on A,B & C )

1533.12

Cost of M.S. Sheet door of 5.76 sqm. 19266.63

Cost per sqm. 3344.90

sqm 2.00 6689.80

TOTAL COST 29138.33

Say 29138.00

Page No -180-

Page 200: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

INSTALLATION OF HT METERING SYSTEM

13.01 Providing and Erection of 11kV outdoor type combined CT & PT metering equipment

with PT ratio 11/0.415kV and CT ratio as per requirement with 3-ph 4 wire

Automatic Meter Reading (AMR) Compatible Static Trivector Meter in separate

Housing cabinet with cables & accessories, as directed by the engineer in charge.

Sl.No. Description Unit Rate/Unit Qty. Amount

Materials

2601

Outdoor type CT & PT

combination with PT ratio

1 1 /0.41 5 kV, for all

rating of CT ratio as

required by HT side

Ampere

No 70,000.00 1 70,000.00

2603

3-ph 4 wire Trivector

Meter suitable for

Automatic Meter Reading

(AMR), PTR 11/0.415kV,

for all rating of CT Ratio.

No 13,500.00 1 13,500.00

1 623 PVC Insulated Copper

Cable, 2.5 sq.mm m 67.50 100.00 6,750.00

2611

Housing Cabinet for

Trivertor Meter for all ratio

of PTR and CTR with

suitable clamp in steel

tabular pole

No 1,500.00 1.00 1,500.00

Total Cost of Materials 91,750.00

Contingency (2% on Material Cost) 1,835.00

Sub-Total 93,585.00

Labours

1001 Labour Skilled-I manday 380.00 3.00 1,140.00

1002 Labour Skilled-II manday 310.00 4.00 1,240.00

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 27.00 5,940.00

Total Cost of Labours 8,320.00

Total 101,905.00

Add 15% for overhead & Profit 15,285.75

Grand Total 117,190.75

Say 117,191.00

Supervision (15% on Labour Cost) 1,248.00

Page No -181-

Page 201: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

INSTALLATION OF BOUNDARY METERING SYSTEM

13.02 Providing and Erection of 11kV outdoor type CT & PT metering equipment with PT

ratio 11/0.110 kV, CT ratio as per requirement; with 3-ph 4 wire Automatic Meter

Reading (AMR) Compatible Static Trivector Meter in separate Housing cabinet with

cables & accessories (Boundary Meter), as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

2602

Outdoor type CT & PT

combination with PT ratio

11/0.11 kV, for all rating

of CT ratio as required by

HT side Ampere

No 70,000.00 1.00 70,000.00

2604

3-ph 4 wire Trivector

Meter suitable for

Automatic Meter Reading

(AMR), PTR 11/0.11kV,

for all rating of CT Ratio.

No 13,500.00 1 13,500.00

1623 PVC Insulated Copper

Cable, 2.5 sq.mm m 67.50 100.00 6,750.00

2611

Housing Cabinet for

Trivertor Meter for all ratio

of PTR and CTR with

suitable clamp in steel

tabular pole

No 1,500.00 1.00 1,500.00

Total Cost of Materials 91,750.00

Contingency (2% on Material Cost) 1,835.00

Sub-Total 93,585.00

Labours

1001 Labour Skilled-I manday 380.00 3.00 1,140.00

1002 Labour Skilled-II manday 310.00 4.00 1,240.00

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 27.00 5,940.00

Total Cost of Labours 8,320.00

Total 101,905.00

Add 15% for overhead & Profit 15,285.75

Grand Total 117,190.75

Say 117,191.00

Supervision (15% on Labour Cost) 1,248.00

Page No -182-

Page 202: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

PREPARATION OF CT/PT MOUNTING STRUCTURE

13.03 Providing and Erection of Mounting Structure for 11KV CT/PT combined metering

equipment mounted between two SP-35 (swagged steel tubular poles) 2.44 m apart, as

directed by the engineer in charge. The height of CT/PT mounting channel should

facilitate safety working clearance, as specified in Schedule VII of the CEA (Measures

relating to Safety and Electric Supply Regulations), 2010.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

1401 M.S. Channel 75 x 40 x 6

mm kg 1 05.84

40.37 4,272.46

1405 M.S. Flat Iron 40mmx6

mm kg 1 05.84

0.75 79.03

2102

M.S. Nut & Bolt 16x50

mm full thread

conforming to IS : 1364-2

(1992) or any

amendments up to date.

kg 162.00 1.17 189.22

2103

M.S. Nut & Bolt 16 x 155

mm full thread

conforming to IS : 1364-2

(1992) or any

amendments up to date.

kg 162.00 2.45 396.58

Total Cost of Materials 4,937.29

Contingency (2% on Material Cost) 98.75

Sub-Total 5,036.03

Labours

1001 Labour Skilled-I manday 380.00 1.00 380.00

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 3.00 660.00

Total Cost of Labours 1,040.00

Total 6,076.03

Add 15% for overhead & Profit 911.40

Grand Total 6,987.44

Say 6,987.00

Supervision (15% on Labour Cost) 156.00

Page No -183-

Page 203: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

INSTALLATION OF DT CUBICLE

13.04 Providing and installation of LT Outdoor DT Cubicle complete with MCCB, Street

light controller, metering system for 25kVA, 1 1/0.415kV Transformer including

erection with cement etc, as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

2605

LT Outdoor DT Cubicle

complete with MCCB, St

light Controller, metering

system for both St light

and Consumer for 25kVA,

11/0.415 kV Transformer

No 53,235.00 1.00 53,235.00

2301 Cement cum 13,750.00 0.01 137.50

2302 River Sand cum 2,100.00 0.03 63.00

2303 Stone Aggregate 10-20 mm cum 1,890.00 0.06 113.40

Total Cost of Materials 53,548.90

Contingency (2% on Material Cost) 1,070.98

Sub-Total 54,619.88

Labours

1001 Labour Skilled-I manday 380.00 1.00 380.00

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 5.00 1,100.00

Total Cost of Labours 1,480.00

Total 56,099.88

Add 15% for overhead & Profit 8,414.98

Grand Total 64,514.86

Say 64,515.00

Supervision (15% on Labour Cost) 222.00

Page No -184-

Page 204: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

INSTALLATION OF DT CUBICLE

13.05 Providing and installation of LT Outdoor DT Cubicle complete with MCCB, Street

light controller, metering system for 63kVA, 11/0.415kV Transformer including

erection with cement etc, as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

2606

LT Outdoor DT Cubicle

complete with MCCB, St

light Controller, metering

system for both St light

and Consumer for 63kVA,

11/0.415 kV Transformer

No 56,778.75 1.00 56,778.75

2301 Cement cum 13,750.00 0.01 137.50

2302 River Sand cum 2,100.00 0.03 63.00

2303 Stone Aggregate 1 0-20

mm cum 1,890.00 0.06 113.40

Total Cost of Materials 57,092.65

Contingency (2% on Material Cost) 1,141.85

Sub-Total 58,234.50

Labours

1001 Labour Skilled-I manday 380.00 1.00 380.00

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 5.00 1,100.00

Total Cost of Labours 1,480.00

Total 59,714.50

Add 15% for overhead & Profit 8,957.18

Grand Total 68,671.68

Say 68,672.00

Supervision (15% on Labour Cost) 222.00

Page No -185-

Page 205: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

INSTALLATION OF DT CUBICLE

13.06 Providing and installation of LT Outdoor DT Cubicle complete with MCCB, Street

light controller, metering system for 100kVA, 1 1/0.415kV Transformer including

erection with cement etc, as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

2607

LT Outdoor DT Cubicle

complete with MCCB, St

light Controller, metering

system for both St light

and Consumer for

100kVA, 11/0.415 kV

Transformer

No 62,685.00 1.00 62,685.00

2301 Cement cum 13,750.00 0.01 137.50

2302 River Sand cum 2,100.00 0.03 63.00

2303 Stone Aggregate 1 0-20

mm cum 1,890.00 0.06 113.40

Total Cost of Materials 62,998.90

Contingency (2% on Material Cost) 1,259.98

Sub-Total 64,258.88

Labours

1001 Labour Skilled-I manday 380.00 1.00 380.00

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 5.50 1,210.00

Total Cost of Labours 1,590.00

Total 65,848.88

Add 15% for overhead & Profit 9,877.33

Grand Total 75,726.21

Say 75,726.00

Supervision (15% on Labour Cost) 238.50

Page No -186-

Page 206: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

INSTALLATION OF DT CUBICLE

13.07 Providing and installation of LT Outdoor DT Cubicle complete with MCCB and

Consumer metering system for 25kVA, 11/0.415kV Transformer including erection

with cement etc, as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

2608

LT Outdoor DT Cubicle

complete with MCCB,

Consumer metering

system for 25kVA,

11/0.415 kV Transformer

No 35,437.50 1.00 35,437.50

2301 Cement cum 13,750.00 0.01 137.50

2302 River Sand cum 2,100.00 0.03 63.00

2303 Stone Aggregate 10-20

mm cum 1,890.00 0.06 113.40

Total Cost of Materials 35,751.40

Contingency (2% on Material Cost) 715.03

Sub-Total 36,466.43

Labours

1001 Labour Skilled-I manday 380.00 1.00 380.00

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 5.00 1,100.00

Total Cost of Labours 1,480.00

Total 37,946.43

Add 15% for overhead & Profit 5,691.96

Grand Total 43,638.39

Say 43,638.00

Supervision (15% on Labour Cost) 222.00

Page No -187-

Page 207: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

INSTALLATION OF DT CUBICLE

13.08 Providing and installation of LT Outdoor DT Cubicle complete with MCCB and

Consumer metering system for 63kVA, 11/0.415kV Transformer including erection

with cement etc, as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

2609

LT Outdoor DT Cubicle

complete with MCCB,

Consumer metering

system for 63kVA,

11/0.415 kV Transformer

No 38,981.25 1.00 38,981.25

2301 Cement cum 13,750.00 0.01 137.50

2302 River Sand cum 2,100.00 0.03 63.00

2303 Stone Aggregate 10-20

mm cum 1,890.00 0.06 113.40

Total Cost of Materials 39,295.15

Contingency (2% on Material Cost) 785.90

Sub-Total 40,081.05

Labours

1001 Labour Skilled-I manday 380.00 1.00 380.00

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 5.00 1,100.00

Total Cost of Labours 1,480.00

Total 41,561.05

Add 15% for overhead & Profit 6,234.16

Grand Total 47,795.21

Say 47,795.00

Supervision (15% on Labour Cost) 222.00

Page No -188-

Page 208: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

INSTALLATION OF DT CUBICLE

13.09 Providing and installation of LT Outdoor DT Cubicle complete with MCCB and

Consumer metering system for 100kVA, 11/0.415kV Transformer including

erection with cement etc, as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

2610

LT Outdoor DT Cubicle

complete with MCCB,

Consumer metering

system for 100kVA,

11/0.415 kV Transformer

No 44,887.50 1.00 44,887.50

2301 Cement cum 13,750.00 0.01 137.50

2302 River Sand cum 2,100.00 0.03 63.00

2303 Stone Aggregate 10-20

mm cum 1,890.00 0.06 113.40

Total Cost of Materials 45,201.40

Contingency (2% on Material Cost) 904.03

Sub-Total 46,105.43

Labours

1001 Labour Skilled-I manday 380.00 1.00 380.00

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 5.50 1,210.00

Total Cost of Labours 1,590.00

Total 47,695.43

Add 15% for overhead & Profit 7,154.31

Grand Total 54,849.74

Say 54,850.00

Supervision (15% on Labour Cost) 238.50

Page No -189-

Page 209: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

STREET LIGHTING

14.01 Providing and Erection 250 W, HPSV Street Light complete with Lamp, Bracket, PVC

insulated aluminium cable and other accessories, as directed by the engineer in

charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Materials

3201

HPSV Lamp Street Light

Fittings complete with Choke,

Condenser, Holder and Ignitor,

250 W, conforming to IS :

10322 - 2012, IS : 2215 - 2006

and any other relevant

standards with amendments up

to date.

Set 6,850.00 1.00 6,850.00

3203

HPSV Lamp, 250 W, conforming to

IS : 1 0322 - 201 2 and any other

relevant standards with

amendments up to date.

No 1,950.00 1.00 1,950.00

3204 Street Light Bracket No 590.00 1.00 590.00

3205 D-Clamp for Street Light

Bracket complete with Nuts & Set 139.00 2.00 278.00

1614

PVC Insulated Aluminium

Cable, 2.5 sq.mm, 2 Core,

conforming to IS : 1554-1

(1988), IS : 5831 (1984) or

any ammendments there of.

m 20.00 4.00 80.00

Total Cost of Materials 9,748.00

Contingency (2% on Material Cost) 194.96

Sub-Total 9,942.96

Labours

1001 Labour Skilled-I manday 380.00 0.00 -

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.33 83.33

1004 Labour Un-skilled manday 220.00 0.67 146.67

Total Cost of Labours 230.00

Total 10,172.96

Add 15% for overhead & Profit 1,525.94

Grand Total 11,698.90

Say 11,699.00

Supervision (15% on Labour Cost) 34.50

Page No -190-

Page 210: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FITTING OF LT ABC

15.01 Providing and Fitting of LT ABC accessories for stringing (Tension Point), as directed by the

engineer in charge.

Sl.No. Description Unit Rate/Unit Quantity Amount

Materials

3301 Anchor clamp for LT

ABC as per NFC

standard

No. 1,509.30 2.00 3,018.60

3312 Eye Hook/Clamp

Holding Support

No. 322.50 1.00 322.50

3322 Pole clamp for Steel

Tubular Pole complete

set with nuts&bolts

No. 651.45 1.00 651.45

Total Cost of Materials 3,992.55

Contingency (2% on Material Cost) 79.85

Sub-Total 4,072.40

Labours

1001 Labour Skilled-I manday 380.00 0.20 76.00

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.20 50.00

1004 Labour Un-skilled manday 220.00 0.40 88.00

Total Cost of Labours 214.00

Total 4,286.40

Add 15% for overhead & Profit 642.96

Grand Total 4,929.36

Say 4,929.00

Supervision (15% on Labour Cost) 32.10

Page No -191-

Page 211: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FITTING OF LT ABC

15.02 Providing and Fitting of LT ABC accessories for stringing (Suspension Point), as directed by

the engineer in charge.

Sl.No. Description Unit Rate/Unit Quantity Amount

Materials

3326 Suspension clamp for No. 870.75 1.00 870.75

3312 LT ABC as per NF Eye Hook/Clamp

Holding Support

No. 322.50 1.00 322.50

3322 Pole clamp for Steel

Tubular Pole complete

set with nuts&bolts

No. 651.45 1.00 651.45

Total Cost of Materials 1,844.70

Contingency (2% on Material Cost) 36.89

Sub-Total 1,881.59

1001 Labour Skilled-I manday 380.00 0.20 76.00

1002 Labour Skilled-II manday 310.00 - -

1003 Labour Semi-Skilled manday 250.00 0.20 50.00

1004 Labour Un-skilled manday 220.00 0.40 88.00

Total Cost of Labours 214.00

Total 2,095.59

Add 15% for overhead & Profit 314.34

Grand Total 2,409.93

Say 2,410.00

Supervision (15% on Labour Cost) Labours

Page 212: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FITTING OF LT ABC

15.03 Providing and Fitting of LT ABC single phase distribution box with accessories, as directed by

the engineer in charge.

Sl.No. Description Unit Rate/Unit Quantity Amount

Materials

3310 Distribution Box with

spring loaded Bus Bars for

140A, 1 ph. 10

No. 4,836.21 1.00 4,836.21

3329 connectors Tie Plastic for cable

9mmx26 5mm

Pack 725.63 1.00 725.63

3314 Insulated Piercing

Connector for ABC to

ABC TEE connection

No. 490.20 1.00 490.20

3315 Insulated Piercing

Connector for

Distribution Box

charging (16-95 sq.mm

No. 265.74 4.00 1,062.96

3316 Insulated Piercing

Connector for street

light (16-9 5 sq.mm to

2.5-10sq.mm)

No. 250.00 2.00 500.00

3323 Service Main Anchor

Clamp

No. 398.61 4.00 1,594.44

3317 L.T Cable - 1x35 sq.mm for

charging DB

m 180.60 9.00 1,625.40

Total Cost of Materials 10,834.84

Contingency (2% on Material Cost) 216.70

Sub Total 11,051.54

Labours

1001 Labour Skilled I manday 380.00 0.58 221.67

1002 Labour Skilled II manday 310.00 0.00

0.58 145.83 1003 Labour Semi Skilled manday 250.00

1004 Labour Un-skilled manday 220.00 0.92 201.67

Total Cost of Labours 569.17

Total 11,620.70

Add 15% for overhead & Profit 1,743.11

Grand Total 13,363.81

Say 13,364.00

Supervision (15% on Labour Cost) 85.38

Page No -193-

Page 213: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FITTING OF LT ABC

15.04 Providing and Fitting of LT ABC three phase distribution box with accessories, as directed by

the engineer in charge.

Sl.No. Description Unit Rate/Unit Quantity Amount

Materials

3311 Distribution Box with

spring loaded Bus Bars for

140A, 3ph. 10

No. 7,233.03 1.00 7,233.03

3329 connectors Tie Plastic for cable

9mmx2 65mm

Pack 725.63 1.00 725.63

3314 Insulated Piercing

Connector for ABC to

ABC TEE connection

No. 490.20 1.00 490.20

3315 Insulated Piercing

Connector for

Distribution Box

charging (16-95 sq.mm

to 4-35sq.mm)

No. 265.74 4.00 1,062.96

3316 Insulated Piercing

Connector for street

light (16-9 5 sq.mm to

2.5- 10sq.mm)

No. 250.00 2.00 500.00

3323 Service Main Anchor

Clamp

No. 398.61 4.00 1,594.44

3317 L.T Cable - 1x35 sq.mm for

charging DB

m 180.60 27.00 4,876.20

Total Cost of Materials 16,482.46

Contingency (2% on Material Cost) 329.65

Sub-Total 16,812.11

Labours

1001 Labour Skilled-I manday 380.00 0.58 221.67

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.58 145.83

1004 Labour Un-skilled manday 220.00 0.92 201.67

Total Cost of Labours 569.17

Total 17,381.28

Add 15% for overhead & Profit 2,607.19

Grand Total 19,988.47

Say 19,988.00

Supervision (15% on Labour Cost) 85.38

Page No -194-

Page 214: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

STRINGING OF LT ABC (size 3x70 sq.mm)

15.05 Providing and stringing, clipping and piercing of LT line per single conductor per meter

using Aerial Bunched Cables (3x70 sq.mm) with jungle clearance, as directed by the

engineer in charge.

Sl.

No. Description Unit Rate/Unit Qty. Amount

Materials

3303 1.1 kV XLPE insulated Aerial

Bunched Cables, 3x70sq.mm,

with 16 sq.mm street light and

XLPE insulated messanger

1x25 sq.mm

m 487.30 36.75 17,908.28

3324 Steel Straps size 20mmx1m

long

No. 126.42 4.00 505.68

3308 Buckles for steel strap (pack of

100)

Pack 2,025.30 1.00 2,025.30

3318 Midspan joint for 16 sq.mm

ABC Cable

No. 296.70 1.00 296.70

3319 Midspan joint for 25 sq.mm for

ABC Cable

No. 310.89 1.00 310.89

3320 Midspan joint for 95 sq.mm for

ABC Cable

No. 357.33 1.00 357.33

3330 Water Proof pre-insulated

Hexagonal Compress for 16

sq.mm

No. 763.68 1.00 763.68

3331 Water Proof pre-insulated

Hexagonal Compress for 25

sq.mm

No. 793.35 1.00 793.35

3332 Water Proof pre-insulated

Hexagonal Compress for 95

sq.mm

No. 812.70 1.00 812.70

3313 Heat shrinkable repair tape No. 1,760.81 1.00 1,760.81

3309 Cable and Caps for ABC Cable No. 84.34 1.00 84.34

Total Cost of Materials 25,619.06

Contingency (2% on Material Cost) 512.38

Sub-Total 26,131.44

Labours

1001 Labour Skilled-I manday 380.00 0.83 316.67

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.83 208.33

1004 Labour Un-skilled manday 220.00 4.88 1,074.33

Total Cost of Labours 1,599.33

Total 27,730.77

Add 15% for overhead & Profit 4,159.62

Grand Total 31,890.38

Say 31,890.00

Say 911.00

Supervision (15% on Labour Cost) 239.90

Running Metre Cost

911.14

Page No -195-

Page 215: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

STRINGING OF LT ABC (Size 3x120 Sq.mm)

15.06 Providing and stringing, clipping and piercing of LT line per single conductor per meter

using Aerial Bunched Cables (3x120 sq.mm) with jungle clearance, as directed by the

engineer in charge.

Sl.

No. Description Unit Rate/Unit Qty. Amount

Materials

3302

1.1 kV XLPE insulated Aerial

Bunched Cables, 3x120

sq.mm, with 16 sq.mm street

light and XLPE insulated

messanger 95 sq.mm

m 541.80 37 19,911.15

3324 Steel Straps size 20mmx1m

long No. 126.42 4 505.68

3308 Buckles for steel strap (pack of

100) Pack 2,025.30 1 2,025.30

331 8 Midspan joint for 1 6 sq.mm

ABC Cable No. 296.70 1 296.70

3319 Midspan joint for 25 sq.mm for

ABC Cable No. 310.89 1 310.89

3320 Midspan joint for 95 sq.mm for

ABC Cable No. 357.33 1 357.33

3330

Water Proof pre-insulated

Hexagonal Compress for 16

sq.mm

No. 763.68 1 763.68

3331

Water Proof pre-insulated

Hexagonal Compress for 25

sq.mm

No. 793.35 1 793.35

3332

Water Proof pre-insulated

Hexagonal Compress for 95

sq.mm

No. 812.70 1 812.70

3313 Heat shrinkable repair tape No. 1,760.81 1 1,760.81

3309 Cable and Caps for ABC Cable No. 84.34 1 84.34

Total Cost of Materials 27,621.93

Contingency (2% on Material Cost) 552.44

Sub-Total 28,174.37

Labours

1001 Labour Skilled-I manday 380.00 0.83 316.67

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.83 208.33

1004 Labour Un-skilled manday 220.00 5.48 1,206.33

Total Cost of Labours 1,731.33

Total 29,905.70

Add 15% for overhead & Profit 4,485.86

Grand Total 34,391.56

Say 34,392.00

Say 983.00

Supervision (15% on Labour Cost) 259.70

Running Metre Cost

982.63

Page No -196-

Page 216: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

STRINGING OF LT ABC (Size 3x95 Sq.mm)

15.07 Providing and stringing, clipping and piercing of LT line per single conductor per meter

using Aerial Bunched Cables (3x95 sq.mm) with jungle clearance, as directed by the

engineer in charge.

Sl.

No. Description Unit Rate/Unit Qty. Amount

Materials

3304

1.1 kV XLPE insulated Aerial

Bunched Cables, 3x95 sq.mm,

with 16 sq.mm street light and

XLPE insulated messanger 25

sq.mm

m 503.10 37 18,488.93

3324 Steel Straps size 20mmx1m

long No. 126.42 4 505.68

3308 Buckles for steel strap (pack of

100) Pack 2,025.30 1 2,025.30

3318 Midspan joint for 16 sq.mm

ABC Cable No. 296.70 1 296.70

3319 Midspan joint for 25 sq.mm for

ABC Cable No. 310.89 1 310.89

3320 Midspan joint for 95 sq.mm for

ABC Cable No. 357.33 1 357.33

3330

Water Proof pre-insulated

Hexagonal Compress for 16

sq.mm

No. 763.68 1 763.68

3331

Water Proof pre-insulated

Hexagonal Compress for 25

sq.mm

No. 793.35 1 793.35

3332

Water Proof pre-insulated

Hexagonal Compress for 95

sq.mm

No. 812.70 1 812.70

3313 Heat shrinkable repair tape No. 1,760.81 1 1,760.81

3309 Cable and Caps for ABC Cable No. 84.34 1 84.34

Total Cost of Labours 26,199.71

Contingency (2% on Material Cost) 523.99

Sub-Total 26,723.70

Labours

1001 Labour Skilled-I manday 380.00 0.83 316.67

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.50 125.00

1004 Labour Un-skilled manday 220.00 4.80 1,056.00

Total Cost of Labours 1,497.67

Total 28,221.37

Add 15% for overhead & Profit 4,233.20

Grand Total 32,454.57

Say 32,455.00

Say 927.00

Supervision (15% on Labour Cost) 224.65

Running Metre Cost

927.29

Page No -197-

Page 217: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

Fitting of 11 kV ABC accessories

16.01 Providing and Fitting of 11 kV ABC accessories, as directed by the engineer in

Sl. Description Unit Rate/Unit Qty. Amount No.

Materials

3322 Pole clamp for Steel Tubular

Pole complete set with

No. 651.45 2.00 1,302.90

3312 Eye Hook/Clamp Holding

Support

No. 322.50 2.00 645.00

3301 Anchor clamp for LT ABC as

per NFC standard

No. 1,509.30 1.00 1,509.30

3326 Suspension clamp for LT

ABC as per NFC standard

No. 870.75 1.00 870.75

3328 Tie plastic Pkt. 724.98 6.00 4,349.88

Total Cost of Labours 8,677.83

Contingency (2% on Material Cost) 173.56

Sub-Total 8,851.39

Labours

1001 Labour Skilled-I manday 380.00 0.20 76.00

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.20 50.00

1004 Labour Un-skilled manday 220.00 0.40 88.00

Total Cost of Labours 214.00

Total 9,065.39

Add 15% for overhead & Profit 1,359.81

Grand Total 10,425.19

Say 10,425.00

Supervision (15% on Labour Cost) 32.10

Page No -198-

Page 218: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

STRINGING OF 11kV ABC ( Size 3x70 sq.mm)

16.02 Providing and stringing, clipping and piercing of 11 kV line per single conductor per

meter using Aerial Bunched Cables (3x70 sq.mm) with jungle clearance, as directed by

the engineer in charge.

Sl.

No.

Description Unit Rate/Unit Qty. Amount

Materials

3305 11kV XLPE insulated Aeiral

Bunched Cable size 3 x 70

sq.mm + 1x55 sq.mm (Base

m 516.00 36.75 18,963.00

3325 Straight joint for cable (ABC) Set 14,951.10 1.00 14,951.10

3327 Termination kit O/D HT ABC

AIC x 95 heat shrinkable

Set 14,951.10 1.00 14,951.10

3321 P.G Clamp suitable for

95 sq.mm ABC/C wedge

connector

No. 71.21 1.00 71.21

Total Cost of Labours 48,936.41

Contingency (2% on Material Cost) 978.73

Sub-Total 49,915.14

Labours

1001 Labour Skilled-I manday 380.00 0.83 316.67

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.83 208.33

1004 Labour Un-skilled manday 220.00 4.88 1,074.33

Total Cost of Labours 1,599.33

Total 51,514.47

Add 15% for overhead & Profit 7,727.17

Grand Total 59,241.64

Say 59,242.00

Say 1,693.00

Supervision (15% on Labour Cost) 239.90

Per meter cost 1,692.63

Page No -199-

Page 219: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

STRINGING OF 11kV ABC ( Size 3x95 sq.mm)

16.03 Providing and stringing, clipping and piercing of 11 kV line per single conductor per

meter using Aerial Bunched Cables (3x95 sq.mm) with jungle clearance, as directed by

the engineer in charge.

Sl. Description Unit Rate/Unit Qty. Amount

No. Materials

3306 11kV XLPE insulated Aeiral

Bunched Cable size 3x95

sq.mm+ 1x70 sq.mm (Bare

Messenger)

m 580.00 37 21,315.00

3325 Straight joint for cable (ABC) Set 14,951.10 1 14,951.10

3327 Termination kit O/D HT ABC

AIC x 95 heat shrinkable

Set 14,951.10 1 14,951.10

3321 P.G Clamp suitable for 95

sq.mm ABC/C wedge

connector

No. 71.21 1 71.21

Total Cost of Labours 51,288.41

Contingency (2% on Material Cost) 1,025.77

Sub-Total 52,314.18 Labours

1001 Labour Skilled-I manday 380.00 0.83 316.67

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.83 208.33

1004 Labour Un-skilled manday 220.00 5.13 1,129.33

Total Cost of Labours 1,654.33

Total 53,968.51

Add 15% for overhead & Profit 8,095.28

Grand Total 62,063.79

Say 62,064.00

Say 1,773.00

Supervision (15% on Labour Cost) 248.15

Running Metre Cost

1,773.26

Page No -200-

Page 220: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

33kV CIRCUIT BREAKER ERECTION

17.01 Providing and erection of 33kV Circuit Breaker with structure in complete set including

excavation and refilling of foundation pit 1.6mx1.25mx1.2m (lxbxh) in size; foundation casting -

footing PCC 1:3:6 (0.08m thick), RCC 1:2:4 (0.12m thick) and 2 column RCC 1:2:4

0.30mx0.65mx1.50m (lxbxh) in size with planting depth of 1.0m, 12mm thick 1:3 cement

plastering of plint 0.50m height; erection of Structure and Circuit Breaker as directed by

E n g i n e e Sl. No. Description Unit Rate/Unit Qty. Amount

Material

3401

33kV Circuit Breaker

(SF6/Vacuum), 36kV, 1250A,

25kA complete with mounting

structures, marshalling box,

foundation bolts and all other

accessories (3nos as 1 set)

conforming to IS : 13118 (1991)

or any amendments up to date.

Set 488 ,790.00 1.00 488 ,790.00

3512

T.S Rod 12mm conforming to

IS: 9417 (1989) or any

amendments there of. Kg 82.20 95.00

7,809.00

3513

T.S Rod 8mm conforming to IS:

9417 (1989) or any

amendments there of. Kg 82.20 20.00

1,644.00

3514 Binding Wire Kg 105.00 1.00 105.00

2301 Cement cum 13,750.00 0.20 2,750.00

2302 River Sand cum 2,100.00 0.40 840.00

2303 Stone Aggregate 10-20 mm cum 1,890.00 0.65 1,228.50

2403 Wooden Plank (12x1 sq.ft.) No 1,000.00 4.00 4,000.00

Total Cost of Materials 507,166.50

Labours

1001 Labour Skilled-I manday 380.00 7.00 2,660.00

1002 Labour Skilled-II manday 310.00 9.00 2,790.00

1003 Labour Semi-Skilled manday 250.00 8.00 2,000.00

1004 Labour Un-skilled manday 220.00 34.00 7,480.00

Total Cost of Labours 14,930.00

Total 522,096.50

Add 15% for overhead & Profit 78,314.48

Testing and Commissioning Charges 3,000.00

Grand Total 603,411.00

Supervision (15% on Labour Cost) 2,239.50

Page No -201-

Page 221: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

INSTALLATION OF 33kV ISOLATOR WITH EARTH SWITCH

17.02 Providing and erection of 33kV Isolator with earthswitch with structure in

complete set including excavation and refilling of foundation pit

2.84mx1.60mx1.20m (lxbxh) in size; foundation casting - footing PCC 1:3:6 (0.2m

thick) and 2 column RCC 1:2:4 0.45mx1.00mx1.50m (lxbxh) in size with planting

depth of 1.2m, 12mm thick 1:3 cement plastering of plint 0.50m height; erection

of mounting Structure and Isolator as directed by Engineer-in-charge

Sl. No. Description Unit Rate/Unit Qty. Amount

Material

341 0

33kV Isolator with

Earth Switch

complete with

mounting structure,

terminal connectors,

foundation bolts and

all other accessories

etc. conforming to IS:

9921 of the latest

version.

set 98,000.00 1.00 98,000.00

3512

T.S Rod 12mm

conforming to IS: 9417

(1989) or any

amendments there of.

Kg 82.20 68.00 5,589.60

3513

T.S Rod 8mm

conforming to IS: 9417

(1989) or any

amendments there of.

Kg 82.20 24.00 1,972.80

3514 Binding Wire Kg 105.00 1.00 105.00

2301 Cement cum 13,750.00 0.52 7,150.00

2302 River Sand cum 2,100.00 1.00 2,100.00

2303

Stone Aggregate 10- 20

mm cum 1,890.00 1.80 3,402.00

2403

Wooden Plank (12x1

sq.ft.) No 1,000.00 4.00 4,000.00

Total Cost of Materials 122,319.40

Labours

1001 Labour Skilled-I manday 380.00 6.00 2,280.00

1002 Labour Skilled-II manday 310.00 8.00 2,480.00

1003 Labour Semi-Skilled manday 250.00 5.00 1,250.00

1004 Labour Un-skilled manday 220.00 46.00 10,120.00

Total Cost of Labours 16,130.00

Total 138,449.40

Add 15% for overhead & Profit 20,767.41

Testing and Commissioning Charges 2,000.00

Grand Total 161,217.00

Supervision (15% on Labour Cost) 2,419.50

Page No -202-

Page 222: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

INSTALLATION 33kV ISOLATOR WITHOUT EARTH SWITCH

17.03 Providing and erection of 33kV Isolator without earthswitch with structure in

complete set including excavation and refilling of foundation pit

2.84mx1.60mx1.20m (lxbxh) in size; foundation casting - footing PCC 1:3:6 (0.1m

thick) and 2 column RCC 1:2:4 0.45mx1.00mx1.50m (lxbxh) in size with planting

depth of 1.0m, 12mm thick 1:3 cement plastering of plint 0.50m height; erection

of mounting Structure and Isolator as directed by Engineer-in-charge

Sl. No. Description Unit Rate/Unit Qty. Amount

Material

341 1

33kV Isolator without

Earth Switch

complete with

mounting structure,

terminal connectors,

foundation bolts and

all other accessories

etc. conforming to IS:

9921 of the latest

version.

set 95,655.00 1.0000 95,655.00

3512

T.S Rod 12mm

conforming to IS: 941

7 (1 989) or any

amendments there of.

Kg 82.20 68.0000 5,589.60

3513

T.S Rod 8mm

conforming to IS: 941

7 (1 989) or any

amendments there of.

Kg 82.20 24.0000 1 ,972.80

3514 Binding Wire Kg 105.00 1.0000 105.00

2301 Cement cum 13,750.00 0.5200 7,150.00

2302 River Sand cum 2,100.00 1.0000 2,100.00

2303

Stone Aggregate 10- 20

mm cum 1,890.00 1.8000 3,402.00

2403

Wooden Plank (12x1

sq.ft.) No 1,000.00 4.0000 4,000.00

Total Cost of Materials 119,974.40

Labours

1001 Labour Skilled-I manday 380.00 9.00 3,420.00

1002 Labour Skilled-II manday 310.00 9.00 2,790.00

1003 Labour Semi-Skilled manday 250.00 4.00 1,000.00

1004 Labour Un-skilled manday 220.00 47.00 10,340.00

Total Cost of Labours 17,550.00

Total 137,524.40

Add 15% for overhead & Profit 20,628.66

Testing and Commissioning Charges 2,000.00

Grand Total 160,153.00

Supervision (15% on Labour Cost) 2,632.50

Page No -203-

Page 223: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

INSTALLATION OF 11kV ISOLATOR WITH EARTH SWITCH

17.04 Providing and erection of 11kV Isolator with earth switch with structure in

complete set including excavation and refilling of foundation pit

2.84mx1.60mx1.20m (lxbxh) in size; foundation casting - footing PCC 1:3:6 (0.1m

thick) and 2 column RCC 1:2:4 0.45mx1.00mx1.50m (lxbxh) in size with planting

depth of 1.0m, 12mm thick 1:3 cement plastering of plint 0.50m height; erection

of mounting Structure and Isolator as directed by Engineer-in-charge

Sl. No. Description Unit Rate/Unit Qty. Amount

Material

3421

11 kV Isolator with

Earth Switch

complete with

mounting structure,

terminal connectors,

foundation bolts and

all other accessories

etc, conforming to IS:

13118 (1991) or any

amendments there of.

No 68,500.00 1.0000 68,500.00

3512

T.S Rod 12mm

conforming to IS:

9417 (1989) or any

amendments there of.

Kg 82.20 68.0000 5,589.60

3513

T.S Rod 8mm

conforming to IS:

9417 (1989) or any

amendments there of.

Kg 82.20 24.0000 1,972.80

3514 Binding Wire Kg 105.00 1.0000 105.00

2301 Cement cum 13,750.00 0.5200 7,150.00

2302 River Sand cum 2,100.00 1.0000 2,100.00

2303

Stone Aggregate 10- 20

mm cum 1,890.00 1.8000 3,402.00

2403

Wooden Plank (12x1

sq.ft.) No 1,000.00 4.0000 4 ,000.00

Total Cost of Materials 92,819.40

Labours

1001 Labour Skilled-I manday 380.00 9.00 3,420.00

1002 Labour Skilled-II manday 310.00 9.00 2,790.00

1003 Labour Semi-Skilled manday 250.00 4.00 1,000.00

1004 Labour Un-skilled manday 220.00 47.00 10,340.00

Total Cost of Labours 17,550.00

Total 110,369.40

Add 15% for overhead & Profit 16,555.41

Testing and Commissioning Charges 2,000.00

Grand Total 128,925.00

Supervision (15% on Labour Cost) 2,632.50

Page No -204-

Page 224: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

Page No -205-

Page 225: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

Page No -206-

Page 226: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

Page No -207-

Page 227: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

INSTALLATION OF 33kV HORN GAP FUSE UNIT

17.08 Providing and Installation of 33kV Horn Gap Fuse Unit

Sl. No. Description Unit Rate/Unit Qty. Amount

Material

3420

33 kV Horn Gap Fuse Unit

conforming to IS: 9921 of the

latest version.

No 14,000.00 1.00 14,000.00

Total Cost of Materials 14,000.00

Labours

1001 Labour Skilled-I manday 380.00 1.00 380.00

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 1.50 330.00

Total Cost of Labours 710.00

Total 14,710.00

Add 15% for overhead & Profit 2,206.50

Grand Total 16,917.00

Supervision (15% on Labour Cost) 106.50

Page No -208-

Page 228: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

INSTALLATION AND COMMISSIONING OF 33/11kV TRANSFORMERS

INSTALLATION AND COMMISSIONING OF 33/11kV, 6.3MVA POWER

TRANSFORMER

18.01 Providing and erection of 33/11kV, 6.3MVA Transfomer with construction of

foundation 2.8mx3.05mx1.4m in size (planting depth of 0.4m) with PCC 1:2:4 (1

cement : 2 coarse sand : 4 graded stone aggregate 40 mm nominal size ) including

commissioning as directed by Engineer-in-Charge

Sl. No. Description Unit Rate/Unit Qty. Amount

Material

3405

Outdoor type, oil

immersed,

naturally cooled

3ph, 50Hz, Cu

wound Power

Transformer of

vector group DynII

with tap changer

and air breather

etc. conforming to

IS:2026 of latest

version and ISI

marked of the

capacity 6.3 MVA,

33/11kV complete

with all

accessories.

No 3,723,921.00 1.00 3,723,921.00

2301 Cement cum 13,750.00 3.08 42,350.00

2302 River Sand cum 2,100.00 6.00 12,600.00

2303

Stone Aggregate

10-20 mm cum 1,890.00 11.00 20,790.00

2403

Wooden Plank

(12x1 sq.ft.) No 1,000.00 11.00 11,000.00

Total Cost of Materials 3,810,661.00

Labours

1001 Labour Skilled-I manday 380.00 14.00 5,320.00

1002 Labour Skilled-II manday 310.00 2.00 620.00

1003 Labour Semi- manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 92.00 20,240.00

Total Cost of Labours 26,180.00

Total 3,836,841.00

Add 15% for overhead & Profit 575,526.15

Testing and Commissioning Charges 3,000.00

Grand Total 4,415,367.00

Supervision (15% on Labour Cost) 3,927.00

Page No -209-

Page 229: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

INSTALLATION AND COMMISSIONING OF 33/11kV, 2.5MVA POWER TRANSFORMER

18.02 Providing and erection of 33/11kV, 2 .5MVA Transfomer with construction of

foundation 2.4mx2.8mx1.85m in size (planting depth of 0.4m) with PCC 1:2:4 (1

cement : 2 coarse sand : 4 graded stone aggregate 40 mm nominal size ) including

commissioning as directed by Engineer-in-Charge

Sl. No. Description Unit Rate/Unit Qty. Amount

Material

3406

Outdoor type, oil

immersed,

naturally cooled

3ph, 50Hz, Cu

wound Power

Transformer of

vector group Dyn-II

with tap changer

and air breather

etc. conforming to

IS:2026 of latest

version and ISI

marked of the

capacity 2.5 MVA,

33/11kV complete

with all accessories.

No 2,637,414.00 1.00 2,637,414.00

2301 Cement cum 13,750.00 2.41 33,137.50

2302 River Sand cum 2,100.00 5.00 10,500.00

2303

Stone Aggregate 10-

20 mm cum 1,890.00 9.50 17,955.00

2403

Wooden Plank

(12x1 sq.ft.) No 1,000.00 4.00 4,000.00

Total Cost of Materials 2,703,006.50

Labours

1001 Labour Skilled-I manday 380.00 14.00 5,320.00

1002 Labour Skilled-II manday 310.00 2.00 620.00

1003

Labour Semi-

Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 95.00 20,900.00

Total Cost of Labours 26,840.00

Total 2,729,846.50

Add 15% for overhead & Profit 409,476.98

Testing and Commissioning Charges 3,000.00

Grand Total 3,142,323.00

Supervision (15% on Labour Cost) 4,026.00

Page No -210-

Page 230: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

INSTALLATION AND COMMISSIONING OF 33/11kV, 1.6MVA POWER TRANSFORMER

18.03 Providing and erection of 33/11kV, 1 .6MVA Transfomer with construction of

foundation 2.0mx2.0mx1.92m in size (planting depth of 0.4m) with PCC 1:2:4 (1

cement : 2 coarse sand : 4 graded stone aggregate 40 mm nominal size ) including

commissioning as directed by Engineer-in-Charge

Sl. No. Description Unit Rate/Unit Qty. Amount

Material

3407

Outdoor type, oil

immersed,

naturally cooled

3ph, 50Hz, Cu

wound Power

Transformer of

vector group Dyn-II

with tap changer

and air breather etc.

conforming to

IS:2026 of latest

version and ISI

marked of the

capacity 1.6 MVA,

33/11kV complete

with all accessories.

No 1,916,070.00 1.00 1,916,070.00

2301 Cement cum 13,750.00 0.03 435.88

2302 River Sand cum 2,100.00 0.10 199.71

2303

Stone Aggregate 10-

20 mm cum 1,890.00 0.19 361.37

2403

Wooden Plank

(12x1 sq.ft.) No 1,000.00 4.00 4,000.00

Total Cost of Materials 1,921,066.95

Labours

1001 Labour Skilled-I manday 380.00 14.00 5,320.00

1002 Labour Skilled-II manday 310.00 2.00 620.00

1003 Labour Semi- manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 68.00 14,960.00

Total Cost of Labours 20,900.00

Total 1,941,966.95

Add 15% for overhead & Profit 291,295.04

Testing and Commissioning Charges 3,000.00

Grand Total 2,236,262.00

Supervision (15% on Labour Cost) 3,135.00

Page No -211-

Page 231: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

INSTALLATION AND COMMISSIONING OF 33/0.415kV, 100kVA STATION

TRANSFORMER

18.04 Providing and erection of 33/0.415kV, 100 kVA Transfomer with construction of

foundation 1.2mx1.2mx1.65m in size (planting depth of 0.4m) with PCC 1:2:4 (1

cement : 2 coarse sand : 4 graded stone aggregate 40 mm nominal size ) including

commissioning as directed by Engineer-in-Charge

Sl. No. Description Unit Rate/Unit Qty. Amount

Material

3408

Outdoor type, oil

immersed,

naturally cooled

3ph, 50Hz, Cu

wound Station

Transformer of

vector group Dyn-II

with tap changer

and air breather etc.

conforming to

IS:2026 of latest

version and ISI

marked of the

capacity 100 kVA,

33/0.415kV,

complete with all

accessories.

No 467,531.00 1.00 467,531.00

2301 Cement cum 13,750.00 0.68 9,350.00

2302 River Sand cum 2,100.00 1.40 2,940.00

2303

Stone Aggregate 10-

20 mm cum 1,890.00 2.70 5,103.00

2403

Wooden Plank

(12x1 sq.ft.) No 1,000.00 6.00 6,000.00

Total Cost of Materials 490,924.00

Labours

1001 Labour Skilled-I manday 380.00 8.00 3,040.00

1002 Labour Skilled-II manday 310.00 1.00 310.00

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 36.00 7,920.00

Total Cost of Labours 11,270.00

Total 502,194.00

Add 15% for overhead & Profit 75,329.10

Testing and Commissioning Charges 3,000.00

Grand Total 580,523.00

Supervision (15% on Labour Cost) 1,690.50

Page No -212-

Page 232: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

INSTALLATION AND COMMISSIONING OF 33/0.415kV, 250kVA STATION

TRANSFORMER

18.05 Providing and erection of 33/0.415kV, 250 kVA Transfomer with construction of

foundation 1.5mx2.0mx1.5m in size (planting depth of 0.4m) with PCC 1:2:4 (1

cement : 2 coarse sand : 4 graded stone aggregate 40 mm nominal size ) including

commissioning as directed by Engineer-in-Charge

Sl. No. Description Unit Rate/Unit Qty. Amount

Material

3409

Outdoor type, oil

immersed,

naturally cooled

3ph, 50Hz, Cu

wound Station

Transformer of

vector group Dyn-II

with tap changer

and air breather

etc. conforming to

IS:2026 of latest

version and ISI

marked of the

capacity 250 kVA,

33/0.415kV,

complete with all

accessories.

No 494,741.25 1.00 494,741.25

2301 Cement cum 13,750.00 1.24 17,050.00

2302 River Sand cum 2,100.00 2.50 5,250.00

2303

Stone Aggregate 10-

20 mm cum 1,890.00 4.85 9,166.50

2403

Wooden Plank

(12x1 sq.ft.) No 1,000.00 7.00 7,000.00

Total Cost of Materials 533,207.75

Labours

1001 Labour Skilled-I manday 380.00 8.00 3,040.00

1002 Labour Skilled-II manday 310.00 2.00 620.00

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 56.00 12,320.00

Total Cost of Labours 15,980.00

Total 549,187.75

Add 15% for overhead & Profit 82,378.16

Testing and Commissioning Charges 3,000.00

Grand Total 634,566.00

Supervision (15% on Labour Cost) 2,397.00

Page No -213-

Page 233: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FITTING OF COPPER CONTROL CABLES

19.01 Providing and Fitting of 1.1kV Copper Control Cable of per meter length, 16 Core, 2.5

sq.mm conforming to IS : 1554-1 (1988) or any ammendments with 2.5 sq.mm

Copper Cable Lug of Ring/Fork/Pin type, as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Material

1627

1.1 kV Copper Control

Cable, 2.5 sq.mm, 16

Core, conforming to IS

: 1554-1 (1988) or any

amendments there of.

m 575.00 50.00 28,750.00

1717

Copper Cable Lug,

Ring/Fork/Pin type,

2.5 sq.mm

No 27.00 32.00 864.00

2011

Cable Gland for 2.5

sq.mm, 16 Core

Copper Control Cable

No 52.50 2.00 105.00

1718 Cable Ferrule, 2.5

sq.mm [A-Z] 100 each Packet 2,340.00 1.00 2,340.00

1719 Cable Ferrule, 2.5

sq.mm [0-9] 100 each Packet 900.00 1.00 900.00

Total Cost of Materials 32,959.00

Labours

1001 Labour Skilled-I manday 380.00 0.50 190.00

1002 Labour Skilled-II manday 310.00 1.00 310.00

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 2.25 495.00

Total Cost of Labours 995.00

Total 33,954.00

Add 15% for overhead & Profit 5,093.10

Testing and Commissioning Charges 5,000.00

Grand Total 44,047.00

Per meter cost 881.00

Supervision (15% on Labour Cost) 149.25

Page No -214-

Page 234: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FITTING OF COPPER CONTROL CABLES

19.02 Providing and Fitting of 1.1kV Copper Control Cable of per meter length, 12 Core, 2.5

sq.mm conforming to IS : 1554-1 (1988) or any ammendments with 2.5 sq.mm

Copper Cable Lug of Ring/Fork/Pin type, as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Material

1628

1.1 kV Copper Control

Cable, 2.5 sq.mm, 12

Core, conforming to IS

: 1554-1 (1988) or any

amendments there of.

m 444.00 50.00 22,200.00

1717

Copper Cable Lug,

Ring/Fork/Pin type,

2.5 sq.mm

No 27.00 24.00 648.00

2012

Cable Gland for 2.5

sq.mm, 12 Core

Copper Control Cable

No 52.50 2.00 105.00

1718 Cable Ferrule, 2.5

sq.mm [A-Z] 100 each Packet 2,340.00 1.00 2,340.00

1719 Cable Ferrule, 2.5

sq.mm [0-9] 100 each Packet 900.00 1.00 900.00

Total Cost of Materials 26,193.00

Labours

1001 Labour Skilled-I manday 380.00 0.50 190.00

1002 Labour Skilled-II manday 310.00 1.00 310.00

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 1.70 374.00

Total Cost of Labours 874.00

Total 27,067.00

Add 15% for overhead & Profit 4,060.05

Testing and Commissioning Charges 5,000.00

Grand Total 36,127.00

Per meter cost 723.00

Supervision (15% on Labour Cost) 131.10

Page No -215-

Page 235: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FITTING OF COPPER CONTROL CABLES

19.03 Providing and Fitting of 1.1kV Copper Control Cable of per meter length, 6 Core, 2.5

sq.mm conforming to IS : 1554-1 (1988) or any ammendments with 2.5 sq.mm

Copper Cable Lug of Ring/Fork/Pin type, as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Material

1629

1.1 kV Copper Control

Cable, 2.5 sq.mm, 6

Core, conforming to IS

: 1554-1 (1988) or any

amendments there of.

m 174.00 50.00 8,700.00

1717

Copper Cable Lug,

Ring/Fork/Pin type,

2.5 sq.mm

No 27.00 24.00 648.00

2013

Cable Gland for 2.5

sq.mm, 6 Core Copper

Control Cable

No 52.50 2.00 105.00

1718 Cable Ferrule, 2.5

sq.mm [A-Z] 100 each Packet 2,340.00 1.00 2,340.00

1719 Cable Ferrule, 2.5

sq.mm [0-9] 100 each Packet 900.00 1.00 900.00

Total Cost of Materials 12,693.00

Labours

1001 Labour Skilled-I manday 380.00 0.50 190.00

1002 Labour Skilled-II manday 310.00 0.50 155.00

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 1.68 370.00

Total Cost of Labours 715.00

Total 13,408.00

Add 15% for overhead & Profit 2,011.20

Testing and Commissioning Charges 5,000.00

Grand Total 20,419.00

Per meter cost 408.00

Supervision (15% on Labour Cost) 107.25

Page No -216-

Page 236: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FITTING OF COPPER CONTROL CABLES

19.04 Providing and Fitting of 1.1kV Copper Control Cable of per meter length, 4 Core, 2.5

sq.mm conforming to IS : 1554-1 (1988) or any ammendments with 2.5 sq.mm

Copper Cable Lug of Ring/Fork/Pin type, as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Material

1630

1.1 kV Copper Control

Cable, 2.5 sq.mm, 4

Core, conforming to IS

: 1554-1 (1988) or any

amendments there of.

m 122.00 50.00 6,100.00

1717

Copper Cable Lug,

Ring/Fork/Pin type,

2.5 sq.mm

No 27.00 24.00 648.00

2014

Cable Gland for 2.5

sq.mm, 4 Core Copper

Control Cable

No 45.00 2.00 90.00

1718 Cable Ferrule, 2.5

sq.mm [A-Z] 100 each Packet 2,340.00 1.00 2,340.00

1719 Cable Ferrule, 2.5

sq.mm [0-9] 100 each Packet 900.00 1.00 900.00

Total Cost of Materials 10,078.00

Labours

1001 Labour Skilled-I manday 380.00 0.50 190.00

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 1.67 366.67

Total Cost of Labours 556.67

Total 10,634.67

Add 15% for overhead & Profit 1,595.20

Testing and Commissioning Charges 5,000.00

Grand Total 17,230.00

Per meter cost 345.00

Supervision (15% on Labour Cost) 83.50

Page No -217-

Page 237: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FITTING OF COPPER CONTROL CABLES

19.05 Providing and Fitting of 1.1kV Copper Control Cable of per meter length, 2 Core, 2.5

sq.mm conforming to IS : 1554-1 (1988) or any ammendments with 2.5 sq.mm

Copper Cable Lug of Ring/Fork/Pin type, as directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Material

1631

1.1 kV Copper Control

Cable, 2.5 sq.mm, 2

Core, conforming to IS

: 1554-1 (1988) or any

amendments there of.

m 96.00 50.00 4,800.00

1717

Copper Cable Lug,

Ring/Fork/Pin type,

2.5 sq.mm

No 27.00 24.00 648.00

2015

Cable Gland for 2.5

sq.mm, 2 Core Copper

Control Cable

No 45.00 2.00 90.00

1718 Cable Ferrule, 2.5

sq.mm [A-Z] 100 each Packet 2,340.00 1.00 2,340.00

1719 Cable Ferrule, 2.5

sq.mm [0-9] 100 each Packet 900.00 1.00 900.00

Total Cost of Materials 8,778.00

Labours

1001 Labour Skilled-I manday 380.00 0.00 -

1002 Labour Skilled-II manday 310.00 0.50 155.00

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 1.65 363.85

Total Cost of Labours 518.85

Total 9,296.85

Add 15% for overhead & Profit 1,394.53

Testing and Commissioning Charges 5,000.00

Grand Total 15,691.00

Per meter cost 314.00

Supervision (15% on Labour Cost) 77.83

Page No -218-

Page 238: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FITTING OF 11kV XLPE Al. CABLES

19.06 Providing and laying of 1 Core, 11kV XLPE Aluminium Cable of per meter length, 185

sq.mm conforming to IS 7098 Part 2 (1985) or any ammendments, as directed by the

engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Material

1638

11kV XLPE

Aluminium Cable, 1

Core, 185 sq.mm

m 1,159.00 50.00 57,950.00

Total Cost of Materials 57,950.00

Labours

1001 Labour Skilled-I manday 380.00 0.50 190.00

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 1.83 403.33

Total Cost of Labours 593.33

Total 58,543.33

Add 15% for overhead & Profit 8,781.50

Testing and Commissioning Charges 5,000.00

Grand Total 72,325.00

Per meter cost 1,447.00

Supervision (15% on Labour Cost) 89.00

Page No -219-

Page 239: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FITTING OF 11kV XLPE Al. CABLES

19.07 Providing and laying of 1 Core, 11kV XLPE Aluminium Cable of per meter length,

150sq.mm conforming to IS 7098 Part 2 (1985) or any ammendments, as directed

by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Material

1639

11kV XLPE

Aluminium Cable, 1

Core, 150 sq.mm

m 1,138.00 50.00 56,900.00

Total Cost of Materials 56,900.00

Labours

1001 Labour Skilled-I manday 380.00 0.50 190.00

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 1.79 392.86

Total Cost of Labours 582.86

Total 57,482.86

Add 15% for overhead & Profit 8,622.43

Testing and Commissioning Charges 5,000.00

Grand Total 71,105.00

Per meter cost 1,422.00

Supervision (15% on Labour Cost) 87.43

Page No -220-

Page 240: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FITTING OF 11kV XLPE Al. CABLES

19.08 Providing and laying of 1 Core, 11kV XLPE Aluminium Cable of per meter length,

120sq.mm conforming to IS 7098 Part 2 (1985) or any ammendments, as directed

by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Material

1640

11kV XLPE

Aluminium Cable, 1

Core, 120 sq.mm

m 1,100.00 50.00 55,000.00

Total Cost of Materials 55,000.00

Labours

1001 Labour Skilled-I manday 380.00 0.50 190.00

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 1.75 385.00

Total Cost of Labours 575.00

Total 55,575.00

Add 15% for overhead & Profit 8,336.25

Testing and Commissioning Charges 5,000.00

Grand Total 68,911.00

Per meter cost 1,378.00

Supervision (15% on Labour Cost) 86.25

Page No -22 1-

Page 241: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FITTING OF 11kV XLPE Al. CABLES JOINTING KIT

19.09 Providing and Fitting of 1 Core, 11kV XLPE Aluminium Cable Jointing Kit of One

Number, 185 sq.mm conforming to IS 7098 Part 2 (1985) or any ammendments, as

directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Material

2023

Cable Jointing Kit for

1 Core, 11kV XLPE

Al. Cable, 185 sq.mm

No 4,550.00 1.00 4,550.00

1709

Aluminium Cable Lug

long barrel , 185

Sq.mm

No 68.00 1.00 68.00

Total Cost of Materials 4,618.00

Labours

1001 Labour Skilled-I manday 380.00 0.67 253.33

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 0.67 146.67

Total Cost of Labours 400.00

Total 5,018.00

Add 15% for overhead & Profit 752.70

Grand Total 5,771.00

Supervision (15% on Labour Cost) 60.00

Page No -222-

Page 242: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FITTING OF 11kV XLPE Al. CABLES JOINTING KIT

19.10 Providing and Fitting of 1 Core, 11kV XLPE Aluminium Cable Jointing Kit of One

Number, 150 sq.mm conforming to IS 7098 Part 2 (1985) or any ammendments, as

directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Material

2024

Cable Jointing Kit for

1 Core, 11kV XLPE

Al. Cable, 150 sq.mm

No 4,550.00 1.00 4,550.00

1708

Aluminium Cable Lug

long barrel , 150

Sq.mm

No 53.00 1.00 53.00

Total Cost of Materials 4,603.00

Labours

1001 Labour Skilled-I manday 380.00 0.67 253.33

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 0.67 146.67

Total Cost of Labours 400.00

Total 5,003.00

Add 15% for overhead & Profit 750.45

Grand Total 5,753.00

Supervision (15% on Labour Cost) 60.00

Page No -223-

Page 243: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FITTING OF 11kV XLPE Al. CABLES JOINTING KIT

19.11 Providing and Fitting of 1 Core, 11kV XLPE Aluminium Cable Jointing Kit of One

Number, 120 sq.mm conforming to IS 7098 Part 2 (1985) or any ammendments, as

directed by the engineer in charge.

Sl. No. Description Unit Rate/Unit Qty. Amount

Material

2025

Cable Jointing Kit for

1 Core, 11kV XLPE

Al. Cable, 120 sq.mm

No 4,550.00 1.00 4,550.00

1707

Aluminium Cable Lug

long barrel , 120

Sq.mm

No 42.00 1.00 42.00

Total Cost of Materials 4,592.00

Labours

1001 Labour Skilled-I manday 380.00 0.67 253.33

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 0.67 146.67

Total Cost of Labours 400.00

Total 4,992.00

Add 15% for overhead & Profit 748.80

Grand Total 5,741.00

Supervision (15% on Labour Cost) 60.00

Page No -224-

Page 244: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

INSTALLATION OF 33 kV C&R TRANSFORMER PANEL

20.01 Providing and Installation of 33kV Control and Relay Transformer Panel

Sl. No. Description Unit Rate/Unit Qty. Amount

Material

3412

33 kV Control and Relay

Transformer Panel complete

with MW meter, ammeter,

voltmeter, indicators as

necessary, overcurrent and

earth fault relays (numerical

type) with time delay setting

facilities, trip circuit

supervising relay, Bucholz

relay, oil temperature relay,

winding temperature relay,

master trip relay, remote

switches, energy meter,

import & export recorder,

fault annunciator, digital

metering, event logger,

disturbance recorder,

communication facilities etc.

of the latest technology

conforming to IS: 3231 of the

latest versions. Aux. supply

of 1 10V DC. (Appropriate

transformation ratios should

be selected as per

requirements)

No 741,990.00 1.00 741,990.00

Total Cost of Materials 741,990.00

Labours

1001 Labour Skilled-I manday 380.00 0.33 126.67

1002 Labour Skilled-II manday 310.00 0.33 103.33

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 6.33 1,393.33

Total Cost of Labours 1,623.33

Total 743,613.33

Add 15% for overhead & Profit 111,542.00

Testing and Commissioning Charges 3,000.00

Grand Total 858,155.00

Supervision (15% on Labour Cost) 243.50

Page No -225-

Page 245: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

INSTALLATION OF 33 kV C&R FEEDER PANEL

20.02 Providing and Installation of 33kV Control and Relay Feeder Panel

Sl. No. Description Unit Rate/Unit Qty. Amount

Material

341 3

33 kV Control and Relay

Feeder Panel complete with

MW meter, ammeter,

voltmeter, frequency meter,

power factor meter,

indicators as necessary,

overcurrent and earth fault

relays (numerical type) with

time delay setting facilities,

trip supervising relay,

master trip relay, remote

switches, energy meter,

import & export recorder,

fault annunciator, digital

metering, event logger,

disturbance recorder,

communication facilities etc.

of the latest technology

conforming to IS: 3231 of

the latest versions. Aux.

supply of 1 10V DC.

(Appropriate transformation

ratios should be selected as

per requirements)

No 741 ,990.00 1.00 741,990.00

Total Cost of Materials 741,990.00

Labours

1001 Labour Skilled-I manday 380.00 0.33 126.67

1002 Labour Skilled-II manday 310.00 0.33 103.33

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 6.33 1,393.33

Total Cost of Labours 1,623.33

Total 743,613.33

Add 15% for overhead & Profit 111,542.00

Testing and Commissioning Charges 3,000.00

Grand Total 858,155.00

Supervision (15% on Labour Cost) 243.50

Page No -226-

Page 246: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

INSTALLATION OF 11kV INDOOR SWITCHBOARD PANEL

20.03 Providing and Installation of 1 1kV Indoor Switchboard Panel for Incoming Feeder.

Labours

1001 Labour Skilled-I manday 380.00 0.33 126.67

1002 Labour Skilled-II manday 310.00 0.33 103.33

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 6.33 1,393.33

Total Cost of Labours 1,623.33

Total 1,240,623.33

Add 15% for overhead & Profit 186,093.50

Testing and Commissioning Charges 3,000.00

Grand Total 1,429,717.00

Supervision (15% on Labour Cost) Sl. No. Descripti

Page No -227-

Page 247: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

INSTALLATION OF 11kV INDOOR SWITCHBOARD PANEL 20.04

Providing and Installation of 11kV Indoor Switchboard Panel for Outgoing Feeder.

Sl. No. Description Unit Rate/Unit Qty. Amount

Material

3415

11 kV Indoor Switchboard Panel for

Outgoing Feeder Panel with the

following:

12 kV, 350 MVA, 800 A, 18.4KA, Multi

panel, shunt trip, Indoor Type, motor

operated, spring closing Vacuum

Circuit Breaker, Current Transformer

having accuracy class of 0.2 for

metering & 5P10 for protection, MW

meter, ammeter, voltmeter,

overcurrent and earth fault relays

(numerical type) with time delay

setting facilities, trip supervising

relay, master trip relay, energy meter,

import & export recorder, SIM card

compatible fault annunciator, digital

metering, event logger, disturbance

recorder, communication facilities etc.

of the latest technology, conforming to

IS:13118 (1991), IEC:56 (1987).

(Appropriate transformation ratios

should be selected as per

requirements)

No 1,239,000.00 1.00 1,239,000.00

Total Cost of Materials 1,239,000.00

Labours

1001 Labour Skilled-I manday 380.00 0.33 126.67

1002 Labour Skilled-II manday 310.00 0.33 103.33

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 6.33 1,393.33

Total Cost of Labours 1,623.33

Total 1,240,623.33

Add 15% for overhead & Profit 186,093.50

Testing and Commissioning Charges 3,000.00

Grand Total 1,429,717.00

Supervision (15% on Labour Cost) 243.50

Page No -228-

Page 248: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

INSTALLATION OF 11kV INDOOR SWITCHBOARD PANEL

20.05 Providing and Installation of 11kV Indoor Switchboard Panel for Bus Coupler.

Sl. No. Description Unit Rate/Unit Qty. Amount

Material

3416

11 kV Indoor Switchboard Panel for Bus

Coupler Panel with the following:

12 kV, 350 MVA, 800 A, 18.4KA, Multi

panel, shunt trip, Indoor Type, motor

operated, spring closing Vacuum

Circuit Breaker, Current Transformer

having accuracy class of 0.2 for

metering & 5P10 for protection, MW

meter, ammeter, voltmeter,

overcurrent and earth fault relays

(numerical type) with time delay

setting facilities, trip supervising

relay, master trip relay, energy meter,

import & export recorder, SIM card

compatible fault annunciator, digital

metering, event logger, disturbance

recorder, communication facilities etc.

of the latest technology, conforming to

IS:13118 (1991), IEC:56 (1987).

(Appropriate transformation ratios

should be selected as per

requirements)

No 1 ,239,000.00 1.00 1 ,239,000.00

Total Cost of Materials 1,239,000.00

Labours

1001 Labour Skilled-I manday 380.00 0.33 126.67

1002 Labour Skilled-II manday 310.00 0.33 103.33

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 6.33 1,393.33

Total Cost of Labours 1,623.33

Total 1,240,623.33

Add 15% for overhead & Profit 186,093.50

Testing and Commissioning Charges 3,000.00

Grand Total 1,429,717.00

Supervision (15% on Labour Cost) 243.50

Page No -229-

Page 249: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

INSTALLATION OF BATTERY CHARGER WITH DCDB 21.01

Providing and Installation of 11 0V Battery Charger with DCDB.

Sl. No. Description Unit Rate/Unit Qty. Amount

Material

3417

1 10V DC Distribution Board,

Float cum Boost Battery Charger

(30A) suitable for charging 250 Ah

battery and supply of continuous

load at 15A.

No 580,135.00 1.00 580,135.00

Total Cost of Materials 580,135.00

Labours

1001 Labour Skilled-I manday 380.00 0.50 190.00

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 1.50 330.00

Total Cost of Labours 520.00

Total 580,655.00

Add 15% for overhead & Profit 87,098.25

Testing and Commissioning Charges 3,000.00

Grand Total 670,753.00

Supervision (15% on Labour Cost) 7 8 . 0 0

Page No -230-

Page 250: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

INSTALLATION OF BATTERY BANK

21.02 Providing and Installation of 11 0V, 1 50Ah Battery Bank.

Sl. No. Description Unit Rate/Unit Qty. Amount

Material

3418

1 10V DC, 250 Ah, SMF-

VRLA Battery Bank

consisting of 55 nos. cell.

Model: UPST-250 along

with MS Steel enclosure

and inter cell connection

complete with accessories

No 455,275.00 1.00 455,275.00

Total Cost of Materials 455,275.00

Labours

1001 Labour Skilled-I manday 380.00 1.00 380.00

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 7.00 1,540.00

Total Cost of Labours 1,920.00

Total 457,195.00

Add 15% for overhead & Profit 68,579.25

Testing and Commissioning Charges 3,000.00

Grand Total 528,774.00

Supervision (15% on Labour Cost) 288.00

Page No -23 1-

Page 251: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

INSTALLATION OF ACDB

21.03 Providing and Installation of AC Distribution Board.

Sl. No. Description Unit Rate/Unit Qty. Amount

Material 3419 AC Distribution Board No 74,990.00 1.00 74,990.00

Total Cost of Materials 74,990.00

Labours

1001 Labour Skilled-I manday 380.00 0.00 -

1002 Labour Skilled-II manday 310.00 1.00 310.00

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 3.00 660.00

Total Cost of Labours 970.00

To ta l 75 ,960 .00

Add 15% for overhead & Profit 11,394.00

Testing and Commissioning Charges 3,000.00

Grand Tota l 90,354.00

Supervision (15% on Labour Cost) 145.50

Page No -232-

Page 252: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

FENCING OF 33kV SUBSTATION BY RCC PILLAR WITH BRICK

22.01 Construction of 2m Height Fencing for 33kV Sub-Station by using RCC Pillar, Brick

etc, as directed by the engineer in charge.

Earthwork in excavation in foundation trenches or drains etc. (not exceeding 1 .5m

in width or 1 0sqm on plan) including dressing of sides and ramming of bottoms, lift A

upto 1.5m including getting out excavated soil and disposal of surplus excavated

soil as directed within a lead of 50 metres.

Hard Soil ( pick work )

(Coefficient for ordinary soil increased 1.5 times)

Details of cost for 10.00 cum.

Description Unit Qty. Rate/Unit Amount

LABOURS : Mate/Supervisor day 1.20 470.00 564.00

Unskilled day 12.30 220.00 2,706.00

3,270.00

Sundries and contingencies @ 3% 98.10

3,368.10

Add for water charge @ 1% 33.68

3,401.78

Add CPOH @ 15% 510.27

Cost for 10 cum 3,912.05

cum 4.00 1,564.82

Page No -233-

Page 253: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

B Steel reinforcement for RCC work including straighthening, cutting, bending,

placing in position and binding all complete.

Hot rolled deformed bars

Details of cost for 1 quintal .

Description Unit Qty. Rate/Unit Amount

MATERIALS :

Deformed twisted steel bars = Wastage 5% =

Total =

1.05q quintal 1.05 5,800.00 6,090.00

Carriage of steel 1.05/10 = tonne 0.11 37.46 3.93

Cover block L.S. 10.00 8.00 80.00

LABOUR :

For straightening, cutting,

bending, binding and placing

in position-

Blacksmith 1st class day 1.00 440.00 440.00

Beldar day 1.00 220.00 220.00

Sundries and binding wire L.S. 26.91 8.00 215.28

TOTAL 7,049.21

Add water charge @ 1% 70.49

TOTAL 7,119.70

Add CPOH @ 15% 1,067.96

Cost for 100 kg 8,187.66

kg 178.59 14,622.34

Page No -234-

Page 254: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

C Centering and shuttering including strutting,propping etd. And removal of form for:

a) Columns, pillars, piers, abutments, posts and struts.

Details of cost for a Column 30 cm square and 3.50 high : 4x0.30x3.50m= 4.20

sqm

Description Unit Qty. Rate/Unit Amount

(A) MATERIALS :

(i) Planks 38 mm thick. (2nd class ) : 2x0.30x3.50 sqm 2.10 : 2x0.48x3.50 sqm 3.36

Total sqm 5.46 Add for wastage @ 5% sqm 0.27 Total 5.73

cum 0.22 28,000.00 6,104.00

(ii) Ballies 125 mm for struts. : 4x3.80 Rm 15.20 45.00 684.00

Total 6,788.00

Assuming that timber shall

become unserviceable after

being used 7 times.

Cost of using once 969.71

Carriage & handling @ 2.5% 24.24

(A) 993.95

(B) LABOURS :

2nd class carpenter each 1.25 400.00 500.00

Unskilled each 1.25 220.00 275.00

775.00

Sundries & Contingencies @ 3% 23.25

(B) 798.25

(A) + (B) 1,792.20

Add for water charge @ 1% 17.92

1,810.12

Add CPOH @ 15% 271.52

Cost for 4.2 sqm 2,081.64

sqm 12.00 5,947.54

Page No -235-

Page 255: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

D b) Lintels, beams, plinth beams, girders, bressumers and cantilevers, etc.

Consider a beam of 6.00 mm clear span, 0.50 m deep and 0.30 m wide and floor

height of 3.50 m.

Cubical content = 6.60x0.50x0.30 cum 0.99

Area in contact with concrete= 1x1 .3x6.0 sqm 7.80

Description Unit Qty. Rate/Unit Amount

(A) MATERIALS :

(i) Planks 38 mm thick. (2nd class) : 2x0.538x0.376 sqm 0.41 : 2x6.60x0.50 sqm 6.60 : 1x6.00x0.376 sqm 2.26

Total 9.26 Add for wastage @ 10% sqm 0.93

Total 10.19

cum 0.39 28,000.00 10,836.00

(ii) Ballies 125 mm dia. supports 0 .8 m apart : 8x3.50 Rm 28.00 45.00 1,260.00

(iii) Ballies bracing for support : 6x2.00 Rm 12.00 45.00 540.00

Total 12,636.00

Assuming that timber shall

become unserviceable after

being used 7 times.

Cost of using once 1,805.14

Carriage & handling @ 2.5% 45.13

(A) 1,850.27

(B) LABOURS :

For assembling, errection,

dismantling and clearing.

2nd class carpenter each 1.25 400.00 500.00

Unskilled each 1.25 220.00 275.00

775.00

Sundries & Contingencies @ 3% 23.25

(B) 798.25

(A) + (B) 2,648.52

Add for water charge @ 1% 26.49

2,675.01

Add CPOH @ 15% 401.25

Cost for 7.8 sqm 3,076.26

sqm 30.80 12,147.30

Page No -236-

Page 256: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

Providing and laying in position reinforced cement concrete excluding cost of

centering and shuttering , finishing and reinforcement in -

1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20mm nominal size)

Details of cost for 1.00 cum. Description Unit Qty. Rate/Unit Amount

MATERIALS :

Stone aggregate 20mm cum 0.67 1,800.00 1,206.00

Stone aggregate 10mm cum 0.22 1,800.00 396.00

Carriage of stone aggregate cum 0.89 73.42 65.34

Coarse sand cum 0.45 850.00 378.25

Carriage of course sand cum 0.45 73.42 32.67

Cement (0.2833cum ) tonne 0.32 9,000.00 2,880.00

Carriage of cement tonne 0.32 37.46 11.99

LABOURS :

1st class mason day 0.17 450.00 76.50

Unskilled day 2.00 220.00 440.00

Semi-skilled day 0.90 250.00 225.00

Hire charge of concrete mixer day 0.07 1,668.00 116.76

Vibrator day 0.07 1,068.00 74.76

Sundries L.S 14.30 8.00 114.40

TOTAL 6,017.67

Add water charge @ 1% 60.18

TOTAL 6,077.85

Add CPOH @ 15% 911.68

For 1.00 cum 6,989.53

lumn

cum 0.25 1,747.38

E

Page No -237-

C

Page 257: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

Reinforced cement concrete work in walls including attached pillasters, columns,

pillers, posts, piers, abutments, return walls, retaining walls, struts, buttresses,

string or lacing courses, fillets etc. upto floor five level excluding cost of centering

shuttering etc complete.

1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20mm nominal size)

Details of cost for 9.18 cum.

Description Unit Qty. Rate/Unit Amount

MATERIALS :

Stone aggregate 20mm cum 6.15 1,800.00 11,071.08

Stone aggregate 10mm cum 2.02 1,800.00 3,635.28

Carriage of stone aggregate cum 8.17 73.42 599.84

Coarse sand cum 4.09 850.00 3,472.34

Carriage of course sand cum 4.09 73.42 299.93

Cement (0.2833cum ) tonne 2.94 9,000.00 26,442.00

Carriage of cement tonne 2.94 37.46 110.06

LABOURS :

Unskilled day 11.29 220.00 2,483.80

Coolie day 7.53 220.00 1,656.60

Semi-skilled day 8.26 250.00 2,065.00

1st class mason day 0.92 450.00 414.00

2nd class mason day 0.92 320.00 294.40

Hire charge of concrete mixer day 0.64 1,668.00 1,067.52

Vibrator day 0.64 1,068.00 683.52

Sundries L.S 131.82 8.00 1,054.56

Scaffolding L.S 420.03 8.00 3,360.24

Extra labour for lifting material

upto floor V level.0.75x9.18x2.5

Coolie day 17.20 250.00 4,300.00

TOTAL 55,349.93

Add water charge @ 1% 553.50

TOTAL 55,903.43

Add CPOH @ 15% 8,385.51

Cost for 9.18 cum 64,288.94

cum 0.50 3,501.58

F

Page No -238-

Page 258: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

Reinforced cement concrete work in beams, suspended floors, roofs having slope upto

15° landings, balconies, shelves, chajjas, lintels, bands, window sills, stair

cases, spiral stair cases, cantilevers upto floor five level excluding cost of centering G

shuttering etc complete. with 1:2:4(1cement : 2 coarse sand :4 stone aggregate

20mm)

Beam:

1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20mm nominal size)

Details of cost for 1.00 cum.

Description Unit Qty. Rate/Unit Amount

MATERIALS :

Stone aggregate 20mm cum 0.67 1,800.00 1,206.00

Stone aggregate 10mm cum 0.22 1,800.00 396.00

Carriage of stone aggregate cum 0.89 73.42 65.34

Coarse sand cum 0.45 850.00 378.25

Carriage of course sand cum 0.45 73.42 32.67

Cement (0.2225cum ) tonne 0.32 9,000.00 2,880.00

Carriage of cement tonne 0.32 37.46 11.99

LABOURS :

1st class mason day 0.24 450.00 108.00

Unskilled day 2.75 220.00 605.00

Semi-skilled day 0.90 250.00 225.00

Hire charge of concrete mixer day 0.08 1,668.00 133.44

Vibrator day 0.08 1,068.00 85.44

Sundries L.S 14.30 8.00 114.40

Extra labour for lifting material

upto floor V level.(2.5x0.75)

Coolie day 1.88 250.00 470.00

TOTAL 6,241.53

Add water charge @ 1% 62.42

TOTAL 6,303.95

Add CPOH @ 15% 945.59

Cost for 1.00 cum 7,249.54

cum 1.10 7,974.49

Page No -239-

Page 259: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

Filling available excavated earth (excluding rock) in trenches, plinth, sides of

foundations etc. in layers not exceeding 20cm in depth, consolidating each H

deposited layer by ramming and watering, lead up to 50 m and lift upto 1.5 m.

Details of cost for 10cum

Description Unit Qty. Rate/Unit Amount

LABOURS :

Mate day 0.20 470.00 94.00

Coolies day 2.50 220.00 550.00

Bhisti day 0.20 250.00 50.00

694.00

Add for water charges @1% 6.94

700.94

Add CPOH @ 15% 105.14

Cost for 10.00cum 806.08

cum 3.20 257.95

I Half brick masonry with first class brick in superstructure above plinth

level upto floor V level.

a) in cement mortar 1:3 ( 1 cement : 3 coarse sand )

Details of cost for 10.00 sqm

Description Unit Qty. Rate/Unit Amount

(A) MATERIALS:

(i) 1st class brick nos 565.00 10.00 5,650.00

(ii) Cement mortar 1:3 Rate as per item no.3.04(b) of

SH: Mortars cum 0.28 6,128.40 1,715.95

Carriage of bricks nos 565.00 0.46 259.90

Sundries & scafolding L.S 13.52 8.00 108.16

(B) LABOURS :

1st class mason each 0.60 450.00 270.00

2nd class mason each 0.60 320.00 192.00

Exatra labour for lifting materials: 10x0.1 15x0.75x1.5 Coolie each 0.70 220.00 154.00

Semi skilled each 0.70 250.00 175.00

Unskilled each 1.55 220.00 341.00

TOTAL 8,866.01

Add water charge @ 1% 88.66

TOTAL 8,954.67

Add CPOH @ 15% 1,343.20

Cost for 10.00 sqm 10,297.87

sqm 20.25 20,853.19

Page No -240-

Page 260: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

2.0m high polysteel goat proof fencing with 2.6m angle iron posts 50 x 50 x 6mm A size

placed 2.0m apart embedded in cement concrete block 1:3:6 (1 cement: 3 sand : 6 stone

aggegate) of size 25 x 25 x 60 cm fixing with nails and wire etc. including earthwo rk

complete.

Details of cost for 30 Rm.

Description Unit Qty. Rate/Unit Amount

(A) MATERIALS:

(i) Angle iron 50x50x6mm @ 4.50kg/m.

: 16 x 2.6 x 4.50 kg 187.20 Add for wastage @ 5% kg 9.36

kg 196.56

qtl 1.97 6,985.00 13,760.45

(ii) Polysteel goat proof wire :

2.0 x 30 sqm 60.00 445.00 26,700.00

(iii) Nails kg 2.00 80.00 160.00

40,620.45

Carriage & handling @ 2.5% 1,015.51

(iv) Cement concrete block 1 : 3 : 6 (1cement:3 sand:6 stone

aggregate 20mm size)

: 16 x 0.25 x 0.25 x 0.60 cum 0.60 7,602.30 4,561.38

(v) Earthwork for cement

concrete block

: 16 x 0.25 x 0.25 x 0.60 cum 0.60 327.20 196.32

(A) 46,393.66

(B) LABOURS :

(For drilling holes, fitting and

fixing)

(i) 1st class mason each 0.12 450.00 54.00

(ii) 2nd class mason each 0.12 320.00 38.40

(iii) 1st class blacksmith each 0.78 440.00 343.20

(iv) 2nd class blacksmith each 2.75 320.00 880.00

(v) Unskilled each 2.72 220.00 598.40

1,914.00

Sundries & contingencies @

3%

57.42

(B) 1,971.42

(A) + (B) 48,365.08

Add for water charge @ 1%

except on (A) iv & v, i.e. on Rs.

43,607.38 436.07

TOTAL 48,801.15

Add CPOH @ 15% 7,320.17

Cost for 30.00 Rm 56,121.32

Cost for 1Rm 1,870.71

Say 1,871.00

22.02 Construction of 2m height Fencing for 33kV Sub-Station by using fencing post and fencing

net, as directed by the engineer in charge.

Page No -241-

Page 261: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

Providing & fixing 1mm thick M.S. door with frame of 40x40x6mm. Angle Iron &

22.03 3mm M.S.Gusset plates at the junction and corners, all necessary fittings

complete, including applying a priming coat of steel primer.

(a) Using M.S angles (40x40x6)mm for diagonal braces

Consider a double leaf door shutter of size 1200x2400mm giving an area

=2x1.20x2.40 = 5.76sqm

Details of cost of M.S. Sheet door of 5.76 sqm area

Description Unit Qty. Rate/Unit Amount

(A) MATERIALS

(i) M.S. Sheet 1mm thick. @ 7.85 kg/ sqm kg 45.216 Add for wastage @ 10% 4.522

49.738

qtl 0.497 4,950.00 2,460.15

Carriage & handling @ 2.5% 61.50

Total (I) = 2,521.65

(ii) Gusset plates 3mm thick Area of one gusset plate 0.30 x 0.04 0.012 1/2 x 0.26 (0.04+0.30) 0.044

sqm 0.056 8 x 0.0562 sqm 0.45 2 x 22/7 x 1/4 x 0.30 x 0.30 sqm 0.141

sqm 0.591 @ 23.55 kg/sqm kg 13.918 Add for wastage @ 10% 1.392

15.31

qtl 0.153 4,628.00 708.08

Carriage & handling @ 2.5% 17.70

Total (II) = 725.78

(iii) Angle Iron 40mm x 40mm x 6mm Sides: 4x2.40 m 9.6 Top & Bottom: 2x2x1.20 m 4.8 Diagonals: 1x2x2.50 m 5

1x2x2.45 m 4.9

m 24.3 Add for wastage @ 10% m 2.43

m 26.73 @ 3.5 kg/Rm kg 93.555

qtl 0.936 6,985.00 6,537.96

Carriage & handling @ 2.5% 163.45

Total (III) = 6,701.41

Page No -242-

Page 262: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

(iv) M.S Cleats.

(40x10) mm: 4 x 0.20 m 0.8

Add for wastage @ 25% m 0.2

m 1 @ 3.15 kg/m kg 3.15

qtl 0.032 70.00 2.24

Carriage & handling @ 2.5% 0.06

Total (IV) = 2.30

(v) Pin Clamps (Pintles)

50mm x 6 mm: 4 x 0.45 m 1.8

Add for wastage @ 11% m 0.198

m 1.998

@ 2.35 kg/m kg 4.695

qtl 0.047 4,628.00 217.52

Carriage & handling @ 2.5% 5.44

Total (V) = 222.96

(vi) 20 mm diameter M.S. bar as

pin:

4 x 0.075 m m 0.3

Add for wastage @ 5% m 0.015

m 0.315 @ 2.47 kg/m kg 0.778

qtl 0.008 4,000.00 32.00

Carriage & handling @ 2.5% 0.80

Total (VI) = 32.80

(vii) 1 2mm diameter bolts &

nuts

60 mm long: 4 x 2 each 8

@ 0.183 kg/No kg 1.464

qtl 0.015 10,929.00 163.94

Carriage & handling @ 2.5% 4.10

Total (VII) = 168.04

(viii) 10mm diameter 45 cm

long hooks. each 2 64.29 128.58

(ix) C.C 1:3:6 to fix pin Clamps

= 4 x 0.40 x 0.20 x 0.20 cum 0.064 5,968.30 381.97

(x) C.C 1:2:4 for a block to be

embedded

in floor to keep shutters intact

= 1 x 0.15 x 0.10 x 0.20 cum 0.003 - -

(xi) Locking Arrangement &

Handle each 1 51.43 51.43

Page No -243-

Page 263: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

(xii) Priming Coat

M.S.Sheet: 2 x 5.76 sqm 11.52

Angle Iron: 24.30 x 0.16 sqm 3.888

15.408 36.60 563.93

Total (VIII) = 1,125.91

I + II + III + IV + V + VI + VII +

VIII =

(A) 11,500.85

(B) LABOUR

(i) 1st class Fitter each 2 440.00 880.00

(ii) 1st class Blacksmith each 3 440.00 1,320.00

(iii) 2nd class Blacksmith each 4 320.00 1,280.00

(iv) 1st class Mason each 0.06 450.00 27.00

(v) 2nd class Mason each 0.06 320.00 19.20

(vi) Unskilled labour each 5 250.00 1,250.00

(B) 4,776.20

(A) + (B) 16,277.05

Add for Sundries &

Contingencies @ 3%

459.93

(Except on A,B & C )

Add for Water Charges &

Electricity @ 1.5%

229.97

(Except on A,B & C )

Add 5% for Overhead charges

(Except on A,B & C )

766.56

Add 10% for contractor profit

(Except on A,B & C )

1,533.12

Cost of M.S. Sheet door of 5.76

sqm.

19,266.63

Cost per sqm. 3,344.90

Total Cost for 1 Sqm 3,345.00

"C

Page No -244-

Page 264: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

SWITCH YARD GRAVELING

23.01 Earthwork in surface excavation and dressing including cutting and filling upto 15 cm

depth, disposal of excavated earth upto 50m and lift upto 1.5m including antiweeds

treatment

Sl. No. Description Unit Rate/Unit Qty. Amount

Details of cost for 100sqm

1001 Labour Skilled-I manday 380.00 1 380.00

1004 Labour Un-skilled manday 220.00 14.29 3,142.86

Total Cost of Labours 3,522.86

Add 15% for overhead & Profit 528.43

Grand Total for 100 qm4,051.29

Total for 1 sqm 40.51

Say 41.00

Supervision (15% on Labour Cost) 6.15

Page No -245-

Page 265: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

23.02 Half brick masonry with first class brick in foundation upto one storey above and below

ground level including curing, in cement mortar 1:3 (1 Cement: 3 fine sand) etc.

complete.

in cement mortar 1:3 ( 1 cement : 3 fine sand )

Sl. No. Description Unit Rate/Unit Qty. Amount

Details of cost for 10.0 sqm

2310 1st Class Brick No 21.00 565 11,865.00

2308 Cement mortar 1:3 cum 5,914.40 0.28 1,656.03

Total Cost of Materials 13,521.03

Contingency (2% on Material Cost) 270.42

Sub-Total 13,791.45

Labours

1001 Labour Skilled-I manday 380.00 0.91 345.45

1002 Labour Skilled-II manday 310.00 0.91 281.82

1003 Labour Semi-Skilled manday 250.00 0.91 227.27

1004 Labour Un-skilled manday 220.00 0.91 200.00

Total Cost of Labours 1,054.55

Total 14,846.00

Add 15% for overhead & Profit 2,226.90

Grand Total 17,072.90

Say 17,073.00

Say 1,707.00

Supervision (15% on Labour Cost) 15.82

Cost for 1 sqm

1,707.30

Page No -246-

Page 266: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

23.03 Half brick masonry with first class brick in foundation upto one storey above and below

ground level including curing, in cement mortar 1:4 (1 Cement: 4 fine sand) etc.

complete.

in cement mortar 1:4 ( 1 cement : 4 fine sand )

Sl. No. Description Unit Rate/Unit Qty. Amount

Details of cost for 10.0 sqm

2310 1st Class Brick No 21.00 565 11,865.00

2311 Cement mortar 1:4 cum 4,739.50 0.28 1,327.06

Total Cost of Materials 13,192.06

Contingency (2% on Material Cost) 263.84

Sub-Total 13,455.90

Labours

1001 Labour Skilled-I manday 380.00 0.91 345.45

1002 Labour Skilled-II manday 310.00 0.91 281.82

1003 Labour Semi-Skilled manday 250.00 0.91 227.27

1004 Labour Un-skilled manday 220.00 0.91 200.00

Total Cost of Labours 1,054.55

Total 14,510.45

Add 15% for overhead & Profit 2,176.57

Grand Total 16,687.01

Say 16,687.00

Cost 1 sqm

1,668.70

Say 1,669.00

Supervision (15% on Labour Cost) 15.82

Page No -247-

Page 267: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

23.04 Providing and laying in position cement concrete of specified grade excluding cost of

centering and shuttering - All work upto plinth level:

1:3:6(1 cement :3 course sand :6 stone aggregate 20mm nominal size)

Sl. No. Description Unit Rate/Unit Qty. Amount

Details of cost for 1.0 cum

2301 Cement cum 13,750.00 0.22 3,025.00

2302 River Sand cum 2,100.00 0.44 924.00

2303 Stone Aggregate 10-20 mcum 1,890.00 0.88 1,663.20

Total Cost of Materials 5,612.20

Contingency (2% on Material Cost) 112.24

Sub-Total 5,724.44

Labours

1001 Labour Skilled-I manday 380.00 0.67 253.33

1003 Labour Semi-Skilled manday 250.00 0.67 166.67

1004 Labour Un-skilled manday 220.00 0.67 146.67

1005 Concrete Mixture 7-

1 0tph Per Hour 270.00 4.00 1,080.00

1006 Niddle Vibrator Per Hour 101.00 4.00 404.00

Total Cost of Labours 1,797.33

Total 1,797.33

Add 15% for overhead & Profit 269.60

Grand Total 2,066.93

Say 2,067.00

Cost 1 cum

2,067.00

Say 2,067.00

Supervision (15% on Labour Cost) 269.60

Page No -248-

Page 268: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

Page No -249-

Page 269: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

Page No -250-

Page 270: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

23.07 12 mm cement plaster of mix 1:4 (1 cement : 4 coarse sand)

Sl. No. Description Unit Rate/Unit Qty. Amount

Details of cost for 10 Sqm

2311 Cement mortar 1:4 cum 4,739.50 0.14 663.53

Total Cost of Materials 663.53

Contingency (2% on Material Cost) 13.27

Sub-Total 676.80

Labours

1001 Labour Skilled-I manday 380.00 1.18 447.06

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 1.18 294.12

1004 Labour Un-skilled manday 220.00 1.18 258.82

Total Cost of Labours 1,000.00

Total 1,676.80

Add 15% for overhead & Profit 251.52

Grand Total 1,928.32

Say 1,928.00

Cost 1 Sqm

192.80

Say 193.00

Supervision (15% on Labour Cost) 15.00

Page No -25 1-

Page 271: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

CABLE TRENCH

24.01 Earthwork in excavation in foundation trenches or drains etc. (not exceeding 1 .5m in

width or 10sqm on plan) including dressing of sides and ramming of bottoms, lift upto 1

.5m including getting out excavated soil and disposal of surplus excavated soil as

directed within a lead of 50 metres.

a) Ordinary Soil

Sl. No. Description Unit Rate/Unit Qty. Amount

Details of cost for 10cum

1004 Labour Un-skilled manday 220.00 20.00 4,400.00

Total Cost of Labours 4,400.00

Add 15% for overhead & Profit 660.00

Grand Total 5,060.00

Say 5,060.00

Cost 1 Cum

506.00

Say 506.00

Supervision (15% on Labour Cost) 66.00

b) Hard Soil (Co-efficient of ordinary soil increased by 1.5

Sl. No. Description Unit Rate/Unit Qty. Amount

Details of cost for 10cum

1004 Labour Un-skilled manday 220.00 30 6,600.00

Total Cost of Labours 6,600.00

Add 15% for overhead & Profit 990.00

Grand Total 7,590.00

Say 7,590.00

Cost 1 Cum

759.00

Say 759.00

Supervision (15% on Labour Cost) 99.00

Page No -252-

Page 272: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

c) Very Hard Soil (Co-efficient of ordinary soil increased by 2 times)

Sl. No. Description Unit Rate/Unit Qty. Amount

Details of cost for 10cum

1004 Labour Un-skilled manday 220.00 40.00 8,800.00

Total Cost of Labours 8,800.00

Add 15% for overhead & Profit 1,320.00

Grand Total 10,120.00

Say 10,120.00

Cost 1 Cum

1,012.00

Say 1,012.00

Supervision (15% on Labour Cost) 132.00

d) Soft Rock (Blasting Prohibited Works)

Sl. No. Description Unit Rate/Unit Qty. Amount

Details of cost for 10cum

1001 Labour Skilled-I manday 380.00 71.43 27,142.86

1004 Labour Un-skilled manday 220.00 214.29 47,142.86

Total Cost of Labours 74,285.71

Add 15% for overhead & Profit 11,142.86

Grand Total 11,142.86

Say 11,143.00

Cost 1 Cum

1,114.30

Say 1,114.00

Supervision (15% on Labour Cost) 1,114.29

e) Hard Rock (Blasting Prohibited Works)

Sl. No. Description Unit Rate/Unit Qty. Amount

Details of cost for 10cum

1001 Labour Skilled-I manday 380.00 100.00 38,000.00

1004 Labour Un-skilled manday 220.00 300.00 66,000.00

Total Cost of Labours 104,000.00

Add 15% for overhead & Profit 15,600.00

Grand Total 15,600.00

Say 15,600.00

Cost 1 Cum

1,560.00

Say 1,560.00

Supervision (15% on Labour Cost) 1,560.00

Page No -253-

Page 273: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

24.02 Half brick masonry with first class brick in foundation upto one storey

above and below ground level including curing, etc. complete. in

cement mortar 1:3 ( 1 cement : 3 fine sand )

Sl. No. Description Unit Rate/Unit Qty. Amount

Details of cost for 10.0 sqm

2310 1st Class Brick No 21.00 565 11,865.00

2308 Cement mortar 1:3 cum 5,914.40 0.28 1,656.03

Total Cost of Materials 13,521.03

Contingency (2% on Material Cost) 270.42

Sub-Total 13,791.45

Labours

1001 Labour Skilled-I manday 380.00 0.91 345.45

1002 Labour Skilled-II manday 310.00 0.91 281.82

1003 Labour Semi-Skilled manday 250.00 0.91 227.27

1004 Labour Un-skilled manday 220.00 0.91 200.00

Total Cost of Labours 1,054.55

TOTAL 14,846.00

Add 15% for overhead & Profit 2,226.90

Grand Total 17,072.90

Say 17,073.00

Say 1,707.00

Supervision (15% on Labour Cost) 15.82

Cost for 1 sqm

1,707.30

Page No -254-

Page 274: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

24.03 Half brick masonry with first class brick in foundation upto one storey above and below

ground level including curing, etc. complete.

in cement mortar 1:4 ( 1 cement : 4 fine sand )

Sl. No. Description Unit Rate/Unit Qty. Amount

Details of cost for 10.0 sqm

2310 1st Class Brick No 21.00 565 11,865.00

2311 Cement mortar 1:4 cum 4,739.50 0.28 1,327.06

Total Cost of Materials 13,192.06

Contingency (2% on Material Cost) 263.84

Sub-Total 13,455.90

Labours

1001 Labour Skilled-I manday 380.00 0.91 345.45

1002 Labour Skilled-II manday 310.00 0.91 281.82

1003 Labour Semi-Skilled manday 250.00 0.91 227.27

1004 Labour Un-skilled manday 220.00 0.91 200.00

Total Cost of Labours 1,054.55

TOTAL 14,510.45

Add 15% for overhead & Profit 2,176.57

Grand Total 16,687.01

Say 16,687.00

Say 1,669.00

Supervision (15% on Labour Cost) 15.82

Cost for 1 sqm

1,668.70

Page No -255-

Page 275: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

24.04 Providing and laying in position cement concrete of specified grade excluding cost of

centering and shuttering - All work upto plinth level:

1:3:6(1 cement :3 course sand :6 stone aggregate 20mm nominal size)

Sl. No. Description Unit Rate/Unit Qty. Amount

Details of cost for 1.0 cum

2301 Cement cum 13,750.00 0.22 3,025.00

2302 River Sand cum 2,100.00 0.44 924.00

2303 Stone Aggregate 10-

20 mm cum 1,890.00 0.88 1,663.20

Total Cost of Materials 5,612.20

Contingency (2% on Material Cost) 112.24

Sub-Total 5,724.44

Labours

1001 Labour Skilled-I manday 380.00 0.67 253.33

1003 Labour Semi-Skilled manday 250.00 0.67 166.67

1004 Labour Un-skilled manday 220.00 0.67 146.67

1005 Concrete Mixture 7-

1 0tph Per Hour 270.00 4.00 1,080.00

1006 Niddle Vibrator Per Hour 101.00 4.00 404.00

Total Cost of Labours 1,797.33

TOTAL 1,797.33

Add 15% for overhead & Profit 269.60

Grand Total 2,066.93

Say 2,067.00

Say 2,067.00

Supervision (15% on Labour Cost) 269.60

Cost for 1 cum 2,067.00

Page No -256-

Page 276: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

24.05 Providing and fixing of Angle Iron (40x40x6mm) for Cable rack including

necessary welding etc complete

Sl. No. Description Unit Rate/Unit Qty. Amount

Details of cost for 1 Cable rack

1403 M.S. Angle Iron

40x40x6 mm kg 105.84 2 211.68

Total Cost of Materials 211.68

Contingency (2% on Material Cost) 4.23

Sub-Total 215.91

Labours

1001 Labour Skilled-I manday 380.00 0.13 47.50

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.13 31.25

1004 Labour Un-skilled manday 220.00 0.13 27.50

Total Cost of Labours 106.25

TOTAL 322.16

Add 15% for overhead & Profit 48.32

Grand Total 370.49

Say 370.00

Say 370.00

Supervision (15% on Labour Cost) 15.94

Cost for 1 rack 370.00

Page No -257-

Page 277: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

24.06 12 mm cement plaster of mix 1:4 (1 cement : 4 coarse sand)

Sl. No. Description Unit Rate/Unit Qty. Amount

Details of cost for 10 Sqm

2311 Cement mortar 1:4 cum 4,739.50 0.14 663.53

Total Cost of Materials 663.53

Contingency (2% on Material Cost) 13.27

Sub-Total 676.80

Labours

1001 Labour Skilled-I manday 380.00 1.18 447.06

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 1.18 294.12

1004 Labour Un-skilled manday 220.00 1.18 258.82

Total Cost of Labours 1,000.00

TOTAL 1,676.80

Add 15% for overhead & Profit 251.52

Grand Total 1,928.32

Say 1,928.00

Say 193.00

Supervision (15% on Labour Cost) 15.00

Cost for 1 sqm

192.80

Page No -258-

Page 278: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

24.07 Providing and positioning of M.S Flat Chequer Plate 6mm thick

Sl. No. Description Unit Rate/Unit Qty. Amount

Details of cost for 100 Kgs

3209 Chequer Plate 6mm

thick kg 101.00 100 10,100.00

Total Cost of Materials 10,100.00

Contingency (2% on Material Cost) 202.00

Sub-Total 10,302.00

Labours

1001 Labour Skilled-I manday 380.00 0.25 95.00

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.25 62.50

1004 Labour Un-skilled manday 220.00 0.25 55.00

Total Cost of Labours 212.50

TOTAL 10,514.50

Add 15% for overhead & Profit 1,577.18

Grand Total 12,091.68

Say 12,092.00

Say 121.00

Supervision (15% on Labour Cost) 0 .32

Cost for 1 Kg

120.92

Page No -259-

Page 279: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

DISMANTLING OF STEEL TUBULAR POLE (SP-17)

101.01 Dismantling of steel tubular pole (SP- 17)

Sl. No. Description Unit Qty.

Materials

1101

Swaged Steel Poles with base

plate of thickness 6mm and

size of200mmx200mm

square welded at the bottom

and with pole cap of 6mm

thick to be welded at the top

con forming to IS 2713/1980

or the latest version thereof

410 SP-17 of overall length

8.50m

No 1.00

Labours

1001 Labour Skilled-I manday 380.00 0.00 0.00

1002 Labour Skilled-II manday 310.00 0.00 0.00

1003 Labour Semi-Skilled manday 250.00 0.00 0.00

1004 Labour Un-skilled manday 220.00 3.42 751.67

Total Cost of Labours 751.67

Total 751.67

Add 15% for overhead & Profit 112.75

Grand Total 864.42

Say 864.00

Supervision (15% on Labour Cost 112.75

Page No -260-

Page 280: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

DISMANTLING OF STEEL TUBULAR POLE (SP-29)

101.02 Dismantling of steel tubular pole (SP-29).

Sl. No. Description Unit Qty.

Materials

1 1 02

Swaged Steel Poles with base

plate of thickness 6mm and

size of200mmx200mm

square welded at the bottom

and with pole cap of 6mm

thick to be welded at the top

con forming to IS 27

13/1980 or the latest

version thereof 410 SP-29 of

overall length 9.00m

No 1.00

Labours

1001 Labour Skilled-I manday 380.00 0.00 0.00

1002 Labour Skilled-II manday 310.00 0.00 0.00

1003 Labour Semi-Skilled manday 250.00 0.00 0.00

1004 Labour Un-skilled manday 220.00 5.50 1210.00

Total Cost of Labours 1210.00

Total 1210.00

Add 15% for overhead & Profit 181.50

Grand Total 1391.50

Say 1392.00

Supervision (15% on Labour Cost 181.50

Page No -261-

Page 281: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

DISMANTLING OF STEEL TUBULAR POLE (SP-35)

101.03 Dismantling of steel tubular pole (SP-35).

Sl. No. Description Unit Qty.

Materials

1 1 03

Swaged Steel Poles with base

plate of thickness 6mm and

size of200mmx200mm

square welded at the bottom

and with pole cap of 6mm

thick to be welded at the top

con forming to IS 27

13/1980 or the latest

version thereof 410 SP-35 of

overall length 9.50m

No 1.00

Labours

1001 Labour Skilled-I manday 380.00 0.00 0.00

1002 Labour Skilled-II manday 310.00 0.00 0.00

1003 Labour Semi-Skilled manday 250.00 0.00 0.00

1004 Labour Un-skilled manday 220.00 8.00 1760.00

Total Cost of Labours 1760.00

Total 1760.00

Add 15% for overhead & Profit 264.00

Grand Total 2024.00

Say 2024.00

Supervision (15% on Labour Cost 264.00

Page No -262-

Page 282: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

DISMANTLING OF STEEL TUBULAR POLE (SP-58)

101.04 Dismantling of steel tubular pole (SP-58).

Sl. No. Description Unit Qty.

Materials

1 1 04

Swaged Steel Poles with base

plate of thickness 6mm and

size of200mmx200mm

square welded at the bottom

and with pole cap of 6mm

thick to be welded at the top

con forming to IS

2713/1980 or the latest

version thereof 410 SP-58 of

overall length 12 .00m

No 1.00

Labours

1001 Labour Skilled-I manday 380.00 0.00 0.00

1002 Labour Skilled-II manday 310.00 0.00 0.00

1003 Labour Semi-Skilled manday 250.00 0.00 0.00

1004 Labour Un-skilled manday 220.00 11.00 2420.00

Total Cost of Labours 2420.00

Total 2420.00

Add 15% for overhead & Profit 363.00

Grand Total 2783.00

Say 2783.00

Supervision (15% on Labour Cost 363.00

Page No -263-

Page 283: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

DISMANTLING OF PRE-STRESSED CONCRETE POLE (8.5 m)

101.05 Dismantling of Pre-Stressed Concrete Pole of length 8.5 metres.

Sl. No. Description Unit Qty.

Materials

1 1 05 Pre stressed Concrete Pole:

8.5m No

1.00

Labours

1001 Labour Skilled-I manday 380.00 0.00 0.00

1002 Labour Skilled-II manday 310.00 0.00 0.00

1003 Labour Semi-Skilled manday 250.00 0.00 0.00

1004 Labour Un-skilled manday 220.00 5.50 1210.00

Total Cost of Labours 1210.00

Total 1210.00

Add 15% for overhead & Profit 181.50

Grand Total 1391.50

Say 1392.00

Supervision (15% on Labour Cost 181.50

Page No -264-

Page 284: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

DISMANTLING OF PRE-STRESSED CONCRETE POLE (9.75 m)

101.06 Dismantling of Pre-Stressed Concrete Pole of length 9.75 metres.

Sl. No. Description Unit Qty.

Materials

1106 Pre stressed Concrete Pole:

9.75m No 1.00

Labours

1001 Labour Skilled-I manday 380.00 0.00 0.00

1002 Labour Skilled-II manday 310.00 0.00 0.00

1003 Labour Semi-Skilled manday 250.00 0.00 0.00

1004 Labour Un-skilled manday 220.00 6.50 1430.00

Total Cost of Labours 1430.00

Total 1430.00

Add 15% for overhead & Profit 214.50

Grand Total 1644.50

Say 1645.00

Supervision (15% on Labour Cost 214.50

Page No -265-

Page 285: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

DISMANTLING OF CROSS ARM

201.01 Dismantling of Horizontal Brackets with MS Angle Iron 40 mm X 40 mm X 6 mm

(3.5Kg per metre) for three phase five wires LT over head line (for SP- 17).

Sl. No. Description Unit Qty.

Materials

1403 M.S. Angle Iron 40x40x6

mm kg

5.89

1405 M.S. Flat Iron 40mmx6 mm kg 1.78

Labours

1001 Labour Skilled-I manday 380.00 0.00 -

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 0.65 143.00

Total Cost of Labours 143.00

Total 143.00

Add 15% for overhead & Profit 21.45

Grand Total 164.45

Say 164.00

Supervision (15% on Labour Cost) 21.45

Page No -266-

Page 286: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

DISMANTLING OF CROSS ARM

201.02 Dismantling of Rectangular Brackets with MS Angle Iron 40 mm X 40 mm X 6 mm

(3.5Kg per metre) for three phase five wires LT over head line (for SP-17).

Sl. No. Description Unit Qty.

Materials

1403 M.S. Angle Iron 40x40x6

mm kg

8.55

1405 M.S. Flat Iron 40mmx6 mm kg 1.18

Labours

1001 Labour Skilled-I manday 380.00 0.00 -

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 0.75 165.00

Total Cost of Labours 165.00

Total 165.00

Add 15% for overhead & Profit 24.75

Grand Total 189.75

Say 190.00

Supervision (15% on Labour Cost) 24.75

Page No -267-

Page 287: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

DISMANTLING OF CROSS ARM

201.03 Dismantling of Single sided LT bracket with MS Angle Iron 40 mm X 40 mm X 6

mm (3.5Kg per metre) for three phase five wires LT over head line (for SP-17).

Sl. No. Description Unit Qty.

Materials

1 403 M.S. Angle Iron 40x40x6

mm kg

8.96

1405 M.S. Flat Iron 40mmx6 mm kg 6.64

Labours

1001 Labour Skilled-I manday 380.00 0.00 -

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 0.83 183.33

Total Cost of Labours 183.33

Total 183.33

Add 15% for overhead & Profit 27.50

Grand Total 210.83

Say 211.00

Supervision (15% on Labour Cost) 27.50

Page No -268-

Page 288: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

DISMANTLING OF CROSS ARM

201.04 Dismantling of Horizontal bracket with MS Angle Iron 40 mm X 40 mm X 6 mm

(3.5Kg per metre) for Single phase three wires LT over head line (for SP-17).

Sl. No. Description Unit Qty.

Materials

1403 M.S. Angle Iron 40x40x6

mm kg

3.93

1405 M.S. Flat Iron 40mmx6 mm kg 1.18

Labours

1001 Labour Skilled-I manday 380.00 0.00 -

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 0.60 132.00

Total Cost of Labours 132.00

Total 132.00

Add 15% for overhead & Profit 19.80

Grand Total 151.80

Say 152.00

Supervision (15% on Labour Cost) 19.80

Page No -269-

Page 289: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

DISMANTLING OF CROSS ARM

201.05 Dismantling of Horizontal Brackets with MS Angle Iron 40 mm X 40 mm X 6 mm

(3.5Kg per metre) for three phase five wires LT over head line (for SP-29).

Sl. No. Description Unit Qty.

Materials

1403 M.S. Angle Iron 40x40x6

mm kg

5.89

1405 M.S. Flat Iron 40mmx6 mm kg 2.01

Labours

1001 Labour Skilled-I manday 380.00 0.00 -

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 0.65 143.00

Total Cost of Labours 143.00

Total 143.00

Add 15% for overhead & Profit 21.45

Grand Total 164.45

Say 164.00

Supervision (15% on Labour Cost) 21.45

Page No -270-

Page 290: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

DISMANTLING OF CROSS ARM

201.06 Dismantling of Rectangular Brackets with MS Angle Iron 40 mm X 40 mm X 6 mm

(3.5Kg per metre) for three phase five wires LT over head line (for SP-29).

Sl. No. Description Unit Qty.

Materials

1403 M.S. Angle Iron 40x40x6

mm kg

8.55

1405 M.S. Flat Iron 40mmx6 mm kg 1.34

Labours

1001 Labour Skilled-I manday 380.00 0.20 76.00

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 0.40 88.00

Total Cost of Labours 164.00

Total 164.00

Add 15% for overhead & Profit 24.60

Grand Total 188.60

Say 189.00

Supervision (15% on Labour Cost) 24.60

Page No -271-

Page 291: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

DISMANTLING OF CROSS ARM

201.07 Dismantling of Single sided LT bracket with MS Angle Iron 40 mm X 40 mm X 6

mm (3.5Kg per metre) for three phase five wires LT over head line (for SP-29).

Sl. No. Description Unit Qty.

Materials

1403 M.S. Angle Iron 40x40x6

mm kg

9.11

1405 M.S. Flat Iron 40mmx6 mm kg 7.04

Labours

1001 Labour Skilled-I manday 380.00 0.00 -

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 0.83 183.33

Total Cost of Labours 183.33

Total 183.33

Add 15% for overhead & Profit 27.50

Grand Total 210.83

Say 211.00

Supervision (15% on Labour Cost) 27.50

Page No -272-

Page 292: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

DISMANTLING OF CROSS ARM

201.08 Dismantling of Horizontal bracket with MS Angle Iron 40 mm X 40 mm X 6 mm

(3.5Kg per metre) for Single phase three wires LT over head line (for SP-29).

Sl. No. Description Unit Qty.

Materials

1403 M.S. Angle Iron 40x40x6

mm kg

3.93

1405 M.S. Flat Iron 40mmx6 mm kg 1.34

Labours

1001 Labour Skilled-I manday 380.00 0.00 -

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 0.60 132.00

Total Cost of Labours 132.00

Total 132.00

Add 15% for overhead & Profit 19.80

Grand Total 151.80

Say 152.00

Supervision (15% on Labour Cost) 19.80

Page No -273-

Page 293: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

DISMANTLING OF CROSS ARM

201.09 Dismantling of Horizontal Brackets with MS Angle Iron 40 mm X 40 mm X 6 mm (3.5

Kg per metre) for three phase five wires LT over head line (for Pre-Stressed Concrete

8.5 metres).

Sl. No. Description Unit Qty.

Materials

1403 M.S. Angle Iron 40x40x6

mm kg

5.89

1405 M.S. Flat Iron 40mmx6 mm kg 3.14

Labours

1001 Labour Skilled-I manday 380.00 0.00 -

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 0.70 154.00

Total Cost of Labours 154.00

Total 154.00

Add 15% for overhead & Profit 23.10

Grand Total 177.10

Say 177.00

Supervision (15% on Labour Cost) 23.10

Page No -274-

Page 294: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

DISMANTLING OF CROSS ARM

201.10 Dismantling of Rectangular Brackets with MS Angle Iron 40 mm X 40 mm X 6 mm (3.5

Kg per metre) for three phase five wires LT over head line conductors (for Pre-Stressed

Concrete 8.5 metres).

Sl. No. Description Unit Qty.

Materials

1403 M.S. Angle Iron 40x40x6

mm kg

8.55

1405 M.S. Flat Iron 40mmx6 mm kg 2.09

Labours

1001 Labour Skilled-I manday 380.00 0.00 -

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 0.80 176.00

Total Cost of Labours 176.00

Total 176.00

Add 15% for overhead & Profit 26.40

Grand Total 202.40

Say 202.00

Supervision (15% on Labour Cost) 26.40

Page No -275-

Page 295: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

DISMANTLING OF CROSS ARM

201.11 Dismantling of Single sided Brackets with MS Angle Iron 40 mm X 40 mm X 6 mm (3.5

Kg per metre) for three phase five wires LT over head line (for Pre-Stressed Concrete 8.5

metres).

Sl. No. Description Unit Qty.

Materials

1403 M.S. Angle Iron 40x40x6

mm kg

10.09

1405 M.S. Flat Iron 40mmx6 mm kg 9.39

Labours

1001 Labour Skilled-I manday 380.00 0.00 -

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 1.00 220.00

Total Cost of Labours 220.00

Total 220.00

Add 15% for overhead & Profit 33.00

Grand Total 253.00

Say 253.00

Supervision (15% on Labour Cost) 33.00

Page No -276-

Page 296: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

DISMANTLING OF CROSS ARM

201.12 Dismantling of Horizontal Brackets with MS Angle Iron 40 mm X 40 mm X 6 mm (3.5

Kg per metre) for single phase three wires LT over head line (for Pre-Stressed Concrete

8.5 metres).

Sl. No. Description Unit Qty.

Materials

1403 M.S. Angle Iron 40x40x6

mm kg

3.93

1405 M.S. Flat Iron 40mmx6 mm kg 2.09

Labours

1001 Labour Skilled-I manday 380.00 0.00 -

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 0.60 132.00

Total Cost of Labours 132.00

Total 132.00

Add 15% for overhead & Profit 19.80

Grand Total 151.80

Say 152.00

Supervision (15% on Labour Cost) 19.80

Page No -277-

Page 297: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

DISMANTLING OF CROSS ARM

201.13 Dismantling of Horizontal Brackets with MS Angle Iron 40 mm X 40 mm X 6 mm (3.5

Kg per metre) for three phase five wires LT over head line (for Pre-Stressed Concrete

9.75 metres).

Sl. No. Description Unit Qty.

Materials

1403 M.S. Angle Iron 40x40x6

mm kg

5.89

1405 M.S. Flat Iron 40mmx6 mm kg 3.37

Labours

1001 Labour Skilled-I manday 380.00 0.00 -

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 0.70 154.00

Total Cost of Labours 154.00

Total 154.00

Add 15% for overhead & Profit 23.10

Grand Total 177.10

Say 177.00

Supervision (15% on Labour Cost) 23.10

Page No -278-

Page 298: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

DISMANTLING OF CROSS ARM

201.14 Dismantling of Rectangular Brackets with MS Angle Iron 40 mm X 40 mm X 6 mm (3.5

Kg per metre) for three phase five wires LT over head line (for Pre-Stressed Concrete

9.75 metres).

Sl. No. Description Unit Qty.

Materials

1403 M.S. Angle Iron 40x40x6

mm kg

8.55

1405 M.S. Flat Iron 40mmx6 mm kg 2.25

Labours

1001 Labour Skilled-I manday 380.00 0.00 -

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 0.80 176.00

Total Cost of Labours 176.00

Total 176.00

Add 15% for overhead & Profit 26.40

Grand Total 202.40

Say 202.00

Supervision (15% on Labour Cost) 26.40

Page No -279-

Page 299: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

DISMANTLING OF CROSS ARM

201.15 Dismantling of Single sided Brackets with MS Angle Iron 40 mm X 40 mm X 6 mm (3.5

Kg per metre) for three phase five wires LT over head line (for Pre-Stressed Concrete

9.75 metres).

Sl. No. Description Unit Qty.

Materials

1403 M.S. Angle Iron 40x40x6

mm kg

10.33

1405 M.S. Flat Iron 40mmx6 mm kg 9.79

Labours

1001 Labour Skilled-I manday 380.00 0.00 -

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 1.00 220.00

Total Cost of Labours 220.00

Total 220.00

Add 15% for overhead & Profit 33.00

Grand Total 253.00

Say 253.00

Supervision (15% on Labour Cost) 33.00

Page No -280-

Page 300: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

DISMANTLING OF CROSS ARM

201.16 Dismantling of Horizontal Brackets with MS Angle Iron 40 mm X 40 mm X 6 mm (3.5

Kg per metre) for single phase three wires LT over head line (for Pre-Stressed Concrete

9.75 metres).

Sl. No. Description Unit Qty.

Materials

1403 M.S. Angle Iron 40x40x6

mm kg

3.93

1405 M.S. Flat Iron 40mmx6 mm kg 2.25

Labours

1001 Labour Skilled-I manday 380.00 0.00 -

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 0.60 132.00

Total Cost of Labours 132.00

Total 132.00

Add 15% for overhead & Profit 19.80

Grand Total 151.80

Say 152.00

Supervision (15% on Labour Cost) 19.80

Page No -28 1-

Page 301: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

DISMANTLING OF CROSS ARM

201.17 Dismantling of 2 nos. of MS Channel Iron 75 mm X 40 mm X 6 mm (7.14Kg per

metre) double pole cross arm for three wire 11 kV over head line conductors.

Sl. No. Description Unit Qty.

Materials

1401 M.S. Channel 75 x 40 x 6

mm kg

34.56

1405 M.S. Flat Iron 40mmx6 mm kg 3.16

1 403 M.S. Angle Iron 40x40x6

mm kg

45.94

Labours

1001 Labour Skilled-I manday 380.00 0.00 -

1002 Labour Skilled-II manday 310.00 0.25 77.50

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 1.57 344.67

Total Cost of Labours 422.17

Total 422.17

Add 15% for overhead & Profit 63.33

Grand Total 485.49

Say 485.00

Supervision (15% on Labour Cost) 63.33

Page No -282-

Page 302: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

DISMANTLING OF CROSS ARM

201.18 Dismantling of 4 nos. of MS Channel Iron 75 mm X 40 mm X 6 mm (7.14Kg per

metre) double pole cross arm for three wire 11 kV over head line conductors.

Sl. No. Description Unit Qty.

Materials

1 401 M.S. Channel 75 x 40 x 6

mm kg

44.61

1405 M.S. Flat Iron 40mmx6 mm kg 6.32

Labours

1001 Labour Skilled-I manday 380.00 0.00 -

1002 Labour Skilled-II manday 310.00 0.50 155.00

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 3.13 689.33

Total Cost of Labours 844.33

Total 844.33

Add 15% for overhead & Profit 126.65

Grand Total 970.98

Say 971.00

Supervision (15% on Labour Cost) 126.65

Page No -283-

Page 303: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

DISMANTLING OF CROSS ARM

201.19 Dismantling of 12 nos. of MS Channel Iron 75 mm X 40 mm X 6 mm (7.14Kg per

metre) triple pole cross arm for three wire 11 kV over head line conductors.

Sl. No. Description Unit Qty.

Materials

1 401 M.S. Channel 75 x 40 x 6

mm kg

1 33.83

1405 M.S. Flat Iron 40mmx6 mm kg 18.97

Labours

1001 Labour Skilled-I manday 380.00 0.00 -

1002 Labour Skilled-II manday 310.00 1.00 310.00

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 10.40 2,288.00

Total Cost of Labours 2,598.00

Total 2,598.00

Add 15% for overhead & Profit 389.70

Grand Total 2,987.70

Say 2,988.00

Supervision (15% on Labour Cost) 389.70

Page No -284-

Page 304: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

DISMANTLING OF CROSS ARM

201.20 Dismantling of 16 nos. of MS Channel Iron 75 mm X 40 mm X 6 mm (7.14Kg per

metre) four pole cross arm for three wire 11 kV over head line conductors.

Sl. No. Description Unit Qty.

Materials

1 401 M.S. Channel 75 x 40 x 6

mm kg

1 78.44

1405 M.S. Flat Iron 40mmx6 mm kg 25.29

Labours

1001 Labour Skilled-I manday 380.00 0.00 -

1002 Labour Skilled-II manday 310.00 0.50 155.00

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 12.53 2,757.33

Total Cost of Labours 2,912.33

Total 2,912.33

Add 15% for overhead & Profit (overhead-5% & profit-10%) 436.85

Grand Total 3,349.18

Say 3,349.00

Supervision (15% on Labour Cost) 436.85

Page No -285-

Page 305: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

DISMANTLING OF CROSS ARM

201.21 Dismantling of 2 nos. of MS Channel Iron 100 mm X 50 mm X 6 mm (9.56Kg per

metre) double pole cross arm for three wire 33 kV over head line conductors.

Sl. No. Description Unit Qty.

Materials

1402 M.S. Channel 100 x 50 x 6

mm kg

65.41

1405 M.S. Flat Iron 40mmx6 mm kg 3.16

1 403 M.S. Angle Iron 40x40x6

mm kg

57.12

Labours

1001 Labour Skilled-I manday 380.00 0.00 -

1002 Labour Skilled-II manday 310.00 0.25 77.50

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 1.97 432.67

Total Cost of Labours 510.17

Total 510.17

Add 15% for overhead & Profit 76.53

Grand Total 586.69

Say 587.00

Supervision (15% on Labour Cost) 76.53

Page No -286-

Page 306: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

DISMANTLING OF CROSS ARM

201.22 Dismantling of 4 nos. of MS Channel Iron 100 mm X 50 mm X 6 mm (9.56Kg per

metre) double pole cross arm for three wire 33 kV over head line conductors.

Sl. No. Description Unit Qty.

Materials

1402 M.S. Channel 100 x 50 x 6

mm kg 78.975

1405 M.S. Flat Iron 40mmx6 mm kg 6.322

Labours

1001 Labour Skilled-I manday 380.00 0.00 -

1002 Labour Skilled-II manday 310.00 0.50 155.00

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 3.33 733.33

Total Cost of Labours 888.33

Total 888.33

Add 15% for overhead & Profit 133.25

Grand Total 1,021.58

Say 1,022.00

Supervision (15% on Labour Cost) 133.25

Page No -287-

Page 307: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

DISMANTLING OF CROSS ARM

201.23 Dismantling of 12 nos. of MS Channel Iron 100 mm X 50 mm X 6 mm (9.56Kg per

metre) triple pole cross arm for three wire 33 kV over head line conductors (for SP-

35).

Sl. No. Description Unit Qty.

Materials

1402 M.S. Channel 100 x 50 x 6

mm kg

236.93

1405 M.S. Flat Iron 40mmx6 mm kg 18.97

Labours

1001 Labour Skilled-I manday 380.00 0.00 -

1002 Labour Skilled-II manday 310.00 1.00 310.00

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 12.00 2,640.00

Total Cost of Labours 2,950.00

Total 2,950.00

Add 15% for overhead & Profit 442.50

Grand Total 3,392.50

Say 3,393.00

Supervision (15% on Labour Cost) 442.50

Page No -288-

Page 308: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

DISMANTLING OF CROSS ARM

201.24 Dismantling of 16 nos. of MS Channel Iron 100 mm X 50 mm X 6 mm (9.56Kg per

metre) four pole cross arm for three wire 33 kV over head line conductors (for SP-

35).

Sl. No. Description Unit Qty.

Materials

1402 M.S. Channel 100 x 50 x 6

mm kg

315.90

1405 M.S. Flat Iron 40mmx6 mm kg 25.29

Labours

1001 Labour Skilled-I manday 380.00 0.00 -

1002 Labour Skilled-II manday 310.00 0.50 155.00

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 14.67 3,226.67

Total Cost of Labours 3,381.67

Total 3,381.67

Add 15% for overhead & Profit 507.25

Grand Total 3,888.92

Say 3,889.00

Supervision (15% on Labour Cost) 507.25

Page No -289-

Page 309: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

DISMANTLING OF COMPLETE SET OF SHACKLE INSULATOR (Pin Type, 1 3 wire)

301.01 Dismantling of shackle insulator for LT over head lines (1 ph 3 wire).

Sl.

No. Description Unit Qty.

Materials

1 806

Shackle Insulator (Pin/Strap

Type) 70x90 mm conforming to

IS : 1445 (1977) or any

amendments up to date

No 3.00

Labours

1001 Labour Skilled-I manday 380.00 0.00 -

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 0.07 16.13

Total Cost of Labours 16.13

Total 16.13

Add 15% for overhead & Profit 2.42

Grand Total 18.55

Say 19.00

Supervision (15% on Labour Cost) 2.42

Page No -290-

Page 310: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

DISMANTLING OF COMPLETE SET OF SHACKLE INSULATOR (STRAP TYPE, 1ph

3 wire)

301.02 Dismantling of shackle insulator (strap type) for LT over head lines (1ph

3 wire).

Sl.

No. Description Unit Qty.

Materials

1 806

Shackle Insulator (Pin/Strap

Type) 70x90 mm conforming to

IS : 1445 (1977) or any

amendments up to date

No 6.00

1807 Shackle Strap for 70x90 mm

Shackle Insulator Pair 3.00

Labours

1001 Labour Skilled-I manday 380.00 0.00 -

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 0.07 16.13

Total Cost of Labours 16.13

Total 16.13

Add 15% for overhead & Profit 2.42

Grand Total 18.55

Say 19.00

Supervision (15% on Labour Cost) 2.42

Page No -29 1-

Page 311: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

DISMANTLING OF COMPLETE SET OF SHACKLE INSULATOR (Pin Type, 3ph 5

wire)

301.03 Dismantling of shackle insulator for LT over head lines (3ph 5 wire).

Sl.

No. Description Unit Qty.

Materials

1 806

Shackle Insulator (Pin/Strap

Type) 70x90 mm conforming to

IS : 1445 (1977) or any

amendments up to date

No 5.00

Labours

1001 Labour Skilled-I manday 380.00 0.00 -

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 0.07 16.13

Total Cost of Labours 16.13

Total 16.13

Add 15% for overhead & Profit 2.42

Grand Total 18.55

Say 19.00

Supervision (15% on Labour Cost) 2.42

Page No -292-

Page 312: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

DISMANTLING OF COMPLETE SET OF SHACKLE INSULATOR (STRAP TYPE, 3ph

5 wire)

301.04 Dismantling of shackle insulator (strap type) for LT over head lines (3ph 5

wire).

Sl.

No. Description Unit Qty.

Materials

1 806

Shackle Insulator (Pin/Strap

Type) 70x90 mm conforming to

IS : 1445 (1977) or any

amendments up to date

No 10.00

1807 Shackle Strap for 70x90 mm

Shackle Insulator Pair 5.00

Labours

1001 Labour Skilled-I manday 380.00 0.00 -

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 0.07 16.13

Total Cost of Labours 16.13

Total 16.13

Add 15% for overhead & Profit 2.42

Grand Total 18.55

Say 19.00

Supervision (15% on Labour Cost) 2.42

Page No -293-

Page 313: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

DISMANTLING OF PIN INSULATOR (11kV)

301.05 Dismantling of pin insulator for 11 kV over head lines with galvanised pin, nuts,

washers etc as directed by the engineer in charge.

Sl.

No. Description Unit Qty.

Materials

1805

11kV Pin insulator with GI Pin

conforming IS : 731 (1971), IS :

2486 (1989), IS : 2544 (1973), IS

: 5350 (1973) or any

amendments up to date.

Set 3.00

Labours

1001 Labour Skilled-I manday 380.00 0.00 -

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 0.18 40.33

Total Cost of Labours 40.33

Total 40.33

Add 15% for overhead & Profit 6.05

Grand Total 46.38

Say 46.00

Supervision (15% on Labour Cost) 6.05

Page No -294-

Page 314: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

DISMANTLING OF DISC INSULATOR (11kV)

301.06 Dismantling of disc insulator, 45 kN (2 nos. as a set) for 11 kV over head

lines with insulator Dismantlings, ball and socket type and complete with

aluminium alloy tension clamps, bolts, nuts, washers etc as directed by the

engineer in charge.

Sl.

No. Description Unit Qty.

Materials

1801

Porcelain Disc Insulator, 45

kN, conforming IS : 731 (1971),

IS : 2486 (1989), IS : 2544

(1973), IS : 5350 (1973) or any

amendments up to date.

No 2.00

2002

Tension Clamp with hardware

strain fitting, 3-bolted type

complete with bolts, nuts, and

washer (Weasel)

No 1.00

Labours

1001 Labour Skilled-I manday 380.00 0.00 -

1002 Labour Skilled-II manday 310.00 0.05 15.50

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 0.65 144.05

Total Cost of Labours 159.55

Total 159.55

Add 15% for overhead & Profit 23.93

Grand Total 183.48

Say 183.00

Supervision (15% on Labour Cost) 23.93

Page No -295-

Page 315: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

DISMANTLING OF PIN INSULATOR (33kV)

301.07 Dismantling of pin insulator for 33 kV over head lines with galvanised pin, nuts,

washers etc as directed by the engineer in charge.

Sl.

No. Description Unit Qty.

Materials

1804

33kV Pin insulator with GI Pin

conforming IS : 731 (1971), IS :

2486 (1989), IS : 2544 (1973), IS

: 5350 (1973) or any

amendments up to date.

Set 3.00

Labours

1001 Labour Skilled-I manday 380.00 0.00 -

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 0.22 48.89

Total Cost of Labours 48.89

Total 48.89

Add 15% for overhead & Profit 7.33

Grand Total 56.22

Say 56.00

Supervision (15% on Labour Cost) 7.33

Page No -296-

Page 316: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

DISMANTLING OF DISC INSULATOR (33kV)

301.08 Dismantling of disc insulator, 70 kN (3 nos. as a set) for 33 kV over head

lines with insulator Dismantlings, ball and socket type and complete with

aluminium alloy tension clamps, bolts, nuts, washers etc as directed by the

engineer in charge.

Sl.

No. Description Unit Qty.

Materials

1802

Porcelain Disc Insulator, 70

kN, conforming IS : 731 (1971),

IS : 2486 (1989), IS : 2544

(1973), IS : 5350 (1973) or any

amendments up to date.

No 3.00

2001

Tension Clamp with hardware

strain fitting, 4-bolted type

complete with bolts, nuts, and

washer (Racoon)

No 1.00

Labours

1001 Labour Skilled-I manday 380.00 0.00 -

1002 Labour Skilled-II manday 310.00 0.03 8.16

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 0.76 166.63

Total Cost of Labours 174.78

Total 174.78

Add 15% for overhead & Profit 26.22

Grand Total 201.00

Say 201.00

Supervision (15% on Labour Cost) 26.22

Page No -297-

Page 317: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

Dismantling of LT Stay Set

401.01 Dismantling of galvanised stay set for LT over head lines complete with 16 mm rod

dia. with plate 30x30x0.8 cm as directed by the engineer in charge.

Sl.

No. Description Unit Qty.

Materials

1901

G.I. Stay Set complete 16 mm

rod dia. with plate 30x30x0.8

cm conforming to IS : 7887

(1992) or any amendments up

to date.

Set 1.000

1905

Stay wire 7/14 SWG

conforming to IS : 2141 (1979),

IS : 4826 (1979), IS : 6594

(1974) or any amendments up

to date.

kg 1.673

1811

LT Guy insulator (90x65mm)

conforming to IS : 5300 (1969) or

any amendments up to date.

No 1.000

Labours

1001 Labour Skilled-I manday 380.00 0.00 -

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 0.93 205.33

Total Cost of Labours 205.33

Total 205.33

Add 15% for overhead & Profit 30.80

Grand Total 236.13

Say 236.00

Supervision (15% on Labour Cost) 30.80

Page No -298-

Page 318: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

Dismantling of 11 kV Stay Set

401.02 Dismantling of galvanised stay set for 11 kV over head lines complete with

19 mm rod dia. with plate 30x30x0.8 cm, 7/12 SWG G.I. stay wire, 11kV

guy insulator (140x85mm) and stay bow as directed by the engineer in

charge.

Sl.

No. Description Unit Qty.

Materials

1902

G.I. Stay set complete 19 mm

rod dia. with plate 30x30x0.8

cm conforming to IS : 7887

(1992) or any amendments up

to date.

Set 1

1904

Stay wire 7/12 SWG

conforming to IS : 2141 (1979),

IS : 4826 (1979), IS : 6594

(1974) or any amendments up

to date.

kg 2.90

1809 11kV Guy insulator

(140x85mm) conforming to IS :

5300 (1969) or any

amendments up to date.

No

1

Labours

1001 Labour Skilled-I manday 380.00 0.00 -

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 1.03 227.33

Total Cost of Labours 227.33

Total 227.33

Add 15% for overhead & Profit 34.10

Grand Total 261.43

Say 261.00

Supervision (15% on Labour Cost) 34.10

Page No -299-

Page 319: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

Dismantling of 33 kV Stay Set

401.03 Dismantling of galvanised stay set for 33 kV over head lines complete with

19 mm rod dia. with plate 40x40x0.8 cm ,7/10 SWG G.I. stay wire ,33kV

guy insulator (140x85mm) and stay bow as directed by the engineer in

charge.

Sl.

No. Description Unit Qty.

Materials

1903

G.I. Stay set complete 19 mm

rod dia. with plate 40x40x0.8

cm conforming to IS : 7887

(1992) or any amendments up

to date.

Set 1

1907

Stay wire 7/10 SWG

conforming to IS : 2141 (1979),

IS : 4826 (1979), IS : 6594

(1974) or any amendments up

to date.

kg 5.42

1 81 0

33kV Guy insulator

(1 40x85mm) conforming to IS :

5300 (1969) or any

amendments up to date.

No 1

Labours

1001 Labour Skilled-I manday 380.00 0.00 -

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 1.23 271.33

Total Cost of Labours 271.33

Total 271.33

Add 15% for overhead & Profit 40.70

Grand Total 312.03

Say 312.00

Supervision (15% on Labour Cost) 40.70

Page No -300-

Page 320: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

DISMANTLING OF LT LINE

501.01 Dismantling of conductor, jumpering of LT line per conductor per meter using

Gnat conductors as directed by the engineer in charge.

Sl.

No. Description Unit Qty.

Materials

1202

Hard drawn standard

aluminium conductors

conforming to IS 398(Part-I)

with amendment No. 1, 2 and

3 or the latest version thereof

bearing ISI mark :Conductor

AAC,7/2.91 mm Gnat

Km 0.053

2005 P.G. Clamp for Gnat conductor

(2 bolted type) No 2.00

Labours

1001 Labour Skilled-I manday 380.00 0.00 -

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 1.02 223.67

Total Cost of Labours 223.67

Total 223.67

Add 15% for overhead & Profit 33.55

Grand Total 257.22

Say 257.00

Running Metre Cost

Say 5.00

Supervision (15% on Labour Cost) 33.55

Page No -301-

5.14

Page 321: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

DISMANTLING OF LT LINE

501.02 Dismantling of conductor, jumpering of LT line per single conductor per meter

using Ant conductors with jungle clearance, as directed by the engineer in

charge.

Sl.

No. Description Unit Qty.

Materials

1201

Hard drawn standard

aluminium conductors

conforming to IS 398(Part-I)

with amendment No. 1, 2 and

3 or the latest version thereof

bearing ISI mark :Conductor

AAC,7/3.10 mm Ant

Km 0.053

2004 P.G. Clamp for Ant conductor

(2 bolted type) No 2

Labours

1001 Labour Skilled-I manday 380.00 0.00 -

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 1.22 267.67

Total Cost of Labours 267.67

Total 267.67

Add 15% for overhead & Profit 40.15

Grand Total 307.82

Say 308.00

Running Metre Cost

Say 6.00

Supervision (15% on Labour Cost) 40.15

Page No -302-

6.16

Page 322: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

DISMANTLING OF LT LINE

501.03 Dismantling of conductor, jumpering of LT line per single conductor per meter

using Grasshopper conductors with jungle clearance, as directed by the engineer

in charge.

Sl.

No. Description Unit Qty.

Materials

1203

Hard drawn standard

aluminium conductors

conforming to IS 398(Part-I)

with amendment No. 1, 2 and

3 or the latest version thereof

bearing ISI mark :Conductor,

AAC,7/3.9 1 mm Grasshopper

Km 0.053

2003 P.G. Clamp for Grasshopper

conductor (3 bolted type) No 2

Labours

1001 Labour Skilled-I manday 380.00 0.00 -

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 1.42 311.67

Total Cost of Labours 311.67

Total 311.67

Add 15% for overhead & Profit 46.75

Grand Total 358.42

Say 358.00

Running Metre Cost

Say 7.00

Supervision (15% on Labour Cost) 46.75

Page No -303-

7.16

Page 323: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

DISMANTLING OF 11 kV LINE

501.04 Dismantling of conductor, jumpering of 1 1kV line per circuit meter using Weasel

conductors with jungle clearance, as directed by the engineer in charge.

Sl.

No. Description Unit Qty.

Materials

1205

Hard drawn standard

aluminium conductors

galvanized steelwire reinforced

conforming to IS 398(Part-II)

with amendment No. 1, 2 and 3

or the latest version thereof

bearing ISI mark :ACSR

6/1/2.59mm Weasel.

KM 0.378

2006 P.G. Clamp for Weasel

conductor (3 bolted type) No 9

2008 Jointing Sleeve for Weasel

conductor No 6

Labours

1001 Labour Skilled-I manday 380.00 0.00 -

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 7.00 1,540.00

Total Cost of Labours 1,540.00

Total 1,540.00

Add 15% for overhead & Profit 231.00

Grand Total 1,771.00

Say 1,771.00

Say 15.00

Supervision (15% on Labour Cost) 231.00

Running Metre Cost

14.76

Page No -304-

Page 324: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

DISMANTLING OF 33 kV LINE

501.05 Dismantling of conductor, jumpering of 33kV line per circuit meter using Racoon

conductors with jungle clearance, as directed by the engineer in charge.

Sl.

No. Description Unit Qty.

Materials

1 204

Hard drawn standard

aluminium conductors

galvanized steelwire reinforced

conforming to IS 398(Part-II)

with amendment No. 1, 2 and 3

or the latest version thereof

bearing ISI mark :ACSR 6/1/4

mm Racoon

Km 0.44 1

2007 P.G. Clamp for Racoon

conductor (3 bolted type) No 9

2009 Jointing Sleeve for Racoon

conductor No 10

Labours

1001 Labour Skilled-I manday 380.00 0.00 -

1002 Labour Skilled-II manday 310.00 0.00 -

1003 Labour Semi-Skilled manday 250.00 0.00 -

1004 Labour Un-skilled manday 220.00 9.00 1,980.00

Total Cost of Labours 1,980.00

Total 1,980.00

Add 15% for overhead & Profit 297.00

Grand Total 2,277.00

Say 2,277.00

Say 16.00

Supervision (15% on Labour Cost) 297.00

Running Metre Cost

16.26

Page No -305-

Page 325: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

Labour Analysis

Sl.No. Description Skilled-I Skilled-II Semi-Skill Unskilled Output per Day Day

1. Carriage of conductor up

to motorable site.

380 310 250 220.00 8.00 2 0.50

2 Dismantling of conductor and clamp.

10.00 2 0.50

Total Day Requirement 0.00 0.00 0.00 9.00

0 0 0 1,980.00 1980.00

APPROXIMATE WEIGHT OF MATERIALS

Sl. No. Name of Materials Unit Weight per unit (kg)

1 33kV Circuit Breaker no. 750.00

2 33kV Current Transformer no. 200.00

3 33kV Potential Transformer no. 200.00

4 33kV Isolator no. 200.00

5 33kV Surge Arrestor no. 150.00

6 33kV Control&Relay Panel no. 300.00

7 11kV Indoor Switchboard Panel no. 800.00

8 6.3MVA Power Transformer no. 13,500.00

9 2.5MVA Power Transformer no. 7,090.00

10 1.6MVA Power Transformer no. 5,100.00

Note: The above indicated weights are approximate and shall vary depending upon the

manufacturers

Page No -306-

Page 326: SOR ANALYSIS 2018 - Mizoram · SOR Committee, P&E Department Government of Mizoram Mizoram : Aizawl All right reserved. No part of this publication may be reproduced, stored in a

Page No -307-