sound chemicals management mainstream ing and upops

70
MINISTRY OF G Sound Chemicals Manage 2020ANNUA REPUBLIC OF KENYA ENVIRONMENT AND FORE GEF/UNDP/GOK Project ement Mainstreaming and UPOPs Reductio January 2021 AL PROGRESS REP 1 ESTRY on in Kenya PORT

Upload: others

Post on 11-Dec-2021

1 views

Category:

Documents


0 download

TRANSCRIPT

MINISTRY OF ENVIRONMENT AND FORESTRY

GEF/UNDP/GOK Project

Sound Chemicals Management Mainstream

2020ANNUAL

REPUBLIC OF KENYA

MINISTRY OF ENVIRONMENT AND FORESTRY

GEF/UNDP/GOK Project

Sound Chemicals Management Mainstreaming and UPOPs Reduction in Kenya

January 2021

ANNUAL PROGRESS REPORT

1

MINISTRY OF ENVIRONMENT AND FORESTRY

ing and UPOPs Reduction in Kenya

REPORT

2

Citation:2019 Annual Progress Report of the Sound Chemicals Management Mainstreaming and UPOPs Reduction in Kenya, Ministry of Environment and Forestry, GEF/UNDP/GoK Project.

For enquiries, please contact: UPOPs office physical address

N.H.I.F BUILDING, RAGATI ROAD P.O. Box 30126, NAIROBI

Telegrams: “NATURE”, Nairobi Telephone: 254-20- 2730808/9

Fax: 254-20- 2734722 Email :[email protected]

Website :www.environment.go.ke

Editors: Francis Kihumba and Washington Ayiemba

Contributors: ME&F: Francis Kihumba, NancyNarasha, Mercy Kimani

MOH: Gamaliel Omondi,LekolileLolem, NEMA: MuitungiMwai, John Mumbo

KAM: Georgina Wachuka GBM:Paul Thiong’o

Disclaimer: The 2020 Annual Report covers the period 1 January 2020 to 31 December 2020. All necessary effort has been made to ensure that the information contained in this publication is correct and not misleading. However, the possibility of errors or unintentional omissions cannot

be excluded. The views are those of the project implementers.

3

I. Table of Contents

Contents I. TABLE OF CONTENTS ............................................................................................................................... 3

II. LIST OF TABLES .......................................................................................................................................... 5

III. LIST OF PHOTOS ......................................................................................................................................... 6

IV. ACRONYMS .................................................................................................................................................. 8

V. PROJECT FACTS ........................................................................................................................................ 10

VI. FOREWORD ................................................................................................................................................ 12

VII. EXECUTIVE SUMMARY .......................................................................................................................... 13

VIII. PROJECT STATUS ..................................................................................................................................... 17

SECTION 1: RESULTS ACHIEVED AGAINST THE TARGET OUTCOMES IN 2020 ............................... 17

1.1 Activities and Achievements 2019 ............................................................................................................... 17

1.2 Project Support to MEF .......................................................................................................................... 17

b) Guidelines and policies on health care waste .............................................................................................. 18

SECTION 2: RESULTS ACHIEVED AGAINST THE TARGET OUTPUTS IN2020 .................................... 33

Additional training has been made on all the HCF. It is now appreciated that there is enough capacity, what is

required is enabling. ............................................................................................................................................ 37

Outcome3: Demonstration of sound healthcare waste disposal technologies in a selected number of

healthcare facilities in each county .................................................................................................................... 41

Table 5; Calculation of Teqs for The 13HCFS Calculations Feb 2020 ............................................................ 45

COMPONENT 4. MINIMIZING RELEASES OF UNINTENTIONALLY PRODUCED

PERSISTENT ORGANIC POLLUTANTS FROM ........................................................................................ 51

The activities of 2020 were a continuation ofthe activities of 2019. ............................................................... 51

Table 7. The activities for this component are summarized in the table below ...................................... 51

ID ............................................................................................................................................................................ 51

Activity .................................................................................................................................................................. 51 Planned delivery date ......................................................................................................................................... 51

Actual delivery date ............................................................................................................................................ 51 Completion status ............................................................................................................................................... 51

Budget Allocation ................................................................................................................................................ 51

Actual Budget Expenses ..................................................................................................................................... 51

1 ............................................................................................................................................................................... 51

Engage consultant to develop training module on composting and recycling (Simplified and

popular versions) .................................................................................................................................................. 51

June– Sept 2020 ..................................................................................................................................................... 51

February 2021 ........................................................................................................................................................ 51

Awaiting inception report ................................................................................................................................... 51

660,000 .................................................................................................................................................................... 51

1,700,000 ................................................................................................................................................................. 51

2 ............................................................................................................................................................................... 51

4

Conduct compost quality assessment and Sampling of produced organic fertilizer from all

composting CBOs with an accredited standardization and certification entity in Nakuru and

Kisumu Counties. ................................................................................................................................................. 51

October-December 2020 ....................................................................................................................................... 51

December2020 ....................................................................................................................................................... 51

Groups identified for assessment. ...................................................................................................................... 51

KEBs has given their charges for assessment ................................................................................................... 51

2,478,000 ................................................................................................................................................................. 51

343,800 .................................................................................................................................................................... 51

3 ............................................................................................................................................................................... 51

Communication materials printing .................................................................................................................... 51

June 2020 ................................................................................................................................................................ 51

July 2020 ................................................................................................................................................................. 51

Completed ............................................................................................................................................................. 51

2,032,000 ................................................................................................................................................................. 51

4 ............................................................................................................................................................................... 51

Consultancy for social economic benefits of sound chemicals management and applications of 3 RS

and .......................................................................................................................................................................... 51

Sept 2020 ................................................................................................................................................................ 51

Dec 2020 ................................................................................................................................................................. 51

Final Draft received .............................................................................................................................................. 51

Due for payment ................................................................................................................................................... 51

1,996,491.9 .............................................................................................................................................................. 51

998245.95 ................................................................................................................................................................ 51

5 ............................................................................................................................................................................... 51

Consultancy on inventory of hazardous waste disposal facilities in Kisumu, Nairobi, Nakuru and

Mombasa ............................................................................................................................................................... 51

Sept 2020 ................................................................................................................................................................ 51

Dec 2020 ................................................................................................................................................................. 51

Final Draft received .............................................................................................................................................. 51

Due for payment ................................................................................................................................................... 51

4,981,500 ................................................................................................................................................................. 51

2,490,750 ................................................................................................................................................................. 51

6 ............................................................................................................................................................................... 51

Validation of consultancy .................................................................................................................................... 51

Sept 2020 ................................................................................................................................................................ 51

Dec 2020 ................................................................................................................................................................. 51

Completed ............................................................................................................................................................. 51

2,000,000 ................................................................................................................................................................. 51

1,567,104 ................................................................................................................................................................. 51

7 ............................................................................................................................................................................... 51

Waste to energy forumn ...................................................................................................................................... 51

Jan 2020 .................................................................................................................................................................. 51

Dec 2020 ................................................................................................................................................................. 51

Completed ............................................................................................................................................................. 51

3,000,000 ................................................................................................................................................................. 51

1,212,640 ................................................................................................................................................................. 51

Total Component 4 .............................................................................................................................................. 51

5

10,344,539 ............................................................................................................................................................... 51

Needs of practitioners in collection, recycling and reuse ............................................................................... 55

Photo 10: Composting activities in Nakuru county ......................................................................................... 58

IX. RISKS AND ISSUES .................................................................................................................................. 61

X. LESSONS LEARNED (POSITIVE OR NEGATIVE) AND RECOMMENDATIONS. .................. 63

Table 6: Overview of available resources for the project duration 2018 ....................................................... 64

Table 6: Overview of available resources for the project duration 2020 ....................................................... 64

Table 7: Financial summary (Based on Project Transaction details) ............................................................. 64

Chart 1: Component Budget as a percentage of Total Budgetary Approved .............................................. 64

Chart 2: Component expenses as a percentage of Total Expenses ................................................................ 65

Chart 3: Component utilization percentage ............................................................................................................. 65

XI. MONITORING AND EVALUATION .................................................................................................... 66

XII. ANNEX 5.3 AWARENESS MATERIALS FROM SELECTED PRINT MEDIA .................................. 67

II. List of Tables

Section 1

No. Table title Pg No.

Table 1 Status Contracts and tenders in process 16

Table 2 Progress towards results for Component 1

20,21

Table 3 Progress towards results for Component 2 21,22

Table 4 Progress towards results for Component 3 23-26

Table 5 Progress towards results for Component 4 26-29

Table 6 Progress towards results: Project Objectives 45, 46

Table 7 The expected TEQs reduction in 2020 29,30

Section 2

No. Table title Pg No.

Table 1 The activities for the component 31,32

Table 2 The activities of the 2020 component 33-35

Table 3 Calculation of Teqs for The 13HCFS Calculations Feb 2020 37-39

Table 4 The activities for the component for 2020 40,41

6

Table 5 Calculation of Teqs for The 13HCFS Calculations Feb 2020 44,45

Table 6 The expected TEQs reduction in 2020 47

Table 7 The activities for this component 49,50

III. List of photos No. Photo title Pg No.

Photo 1 Evaluation team 16

Photo 2 Burning chamber in Naivasha sub county hospital. 18

Photo 3 Process loading 18

Photo 4 Standard state of the art incinerator 19

Photo 5 Burning Chamber at Likoni Hospital

42

Photo 6 Stored Material to be burnt in the open 42

Photo 7 Autoclave at Mombasa Coast General Hospital

43

Photo 8 Standard medium technology burner 46

Photo 9 Recyclers with their stocks 52

Photo 10 Bamburi Cement Plant Facility waste/fuel loading section 56

Photo 11 Mbagathi Waste Management distribution Handover 57

Photo 12 Assorted waste at the company and final products. 57

Photo 13 plastic flakes and pellets 57

7

Photo 14 Rejected plastic wastes at premier plastics ltd to be recycled.

57

Photo 15 Materials for recycling 57

Photo 16 Composting activities in Nakuru county. 58

8

IV. ACRONYMS

APCS Air Pollution Control System

BAT Best Available Technology

BEP Best Environmental Practices

BRS Basel, Rotterdam & Stockholm

COP Conference of Parties

CHMT

DOSHS

County Health Management Team

Department of Safety, Health and Services

ESM Environmentally Sound Management

GCD Government Chemist Department

GoK Government of Kenya

HCF Health Care facility

HCWM Health care Waste Management

ICCA International Council of Chemicals Association

IRAT Individual Rapid Assessment Toolkit

JKUAT Jomo Kenyatta University of Agriculture and Technology

JICA Japan International Cooperation Agency

KAM Kenya Association of Manufacturers

KEBS Kenya Bureau of Standards

KEPHIS Kenya Plant Health Inspectorate Services

KDC Kenya Disaster Concern

ME&F Ministry of Environment and Forestry

MOH Ministry of Health

MOU Memorandum of Understanding

MTRH Mathari Teaching and Referral Hospital

MMUST Masinde Muliro University of Science and Technology

NEMA National Environment Management Authority

NGOs Non-Governmental Organizations

NIP National Implementation Plan

PMU Project Management Unit

PCDD/F Polychlorobenzodioxins (PCDDs) and

polychlorodibenzofurans (PCDFs)

POPs Persistent Organic Pollutants

PRTR Pollutant Release Transfer Register

SAICM Strategic Approach to International Chemicals Management

SC Stockholm Convention

SOP Standard Operating Procedures

TOR Terms of Reference

9

TUK Technical University of Kenya

UPOPs Unintended Persistent Organic Pollutants

WRA Water Resources Authority

WHO World Health organization

UNEA United Nations Environment Assembly

UNDP United Nations Development Programme

UPOPS Unintentionally Produced Persistent Organic Pollutants

3RS Recover, Recycle, Reuse

10

V. PROJECT FACTS

Project Title: Sound Chemicals Management Mainstreaming and UPOPs reduction in

Kenya

Project Number: 00099820

Funding Sources: GEF, GoK & NGOs

Implementing Partner: Ministry of Environment and Forests (ME&F) (Government)

Project Duration: May 2016 to May 2021

1.0 Brief Project Description:

Kenya is party to the Stockholm Convention on persistent organic pollutants and is also

active in the strategic approach to international chemicals management (SAICM). The

above-named project is funded by the Global Environment Facility which is the

financing mechanism for the Stockholm Convention.

The project is intended to protect human health and the environment by managing the

risks posed by production, use, import and export of chemicals and

reducing/preventing the release of unintentionally produced persistent organic

pollutants (U-POPs and toxic compounds) originating from the unsafe management of

waste in two key sectors of health and municipal wastes.

The project is addressing how sound chemicals management can be mainstreamed into

development activities through their sound management, by implementing activities on

U-POPs monitoring, upgrading of the relevant regulations on chemicals, and

establishing a Pollutant Release and Transfer Register (PRTR) database.

For health care waste (HCW), the project will adopt an integrated approach aimed at

increasing the sound management of waste within the health sector and specifically in

13 select hospital facilities (increasing segregation, reducing waste generation) and by

replacing the disposal waste modalities currently in use (open burning or burning in

single chamber incinerators) with better environmental practices so as to avoid open

burning of waste. For the municipal waste, the project intends to reinforce the practice

of reduce, reuse, and recycle (3Rs) economy by enhancing their upstream collection,

ensuring the quality of recovered material, and securing access to national market by

promoting cooperation with private sector. This is for providing a valid alternative to

the dumpsite economy, and preventing the release in the environment of U-POPs and

toxic substance upon open burning of these waste streams.

11

1.1 Project Objective:

Reduction of the releases of U-POPs and other toxic substances of related health risk

concern through the implementation of environmentally sound management of

chemicals, municipal and healthcare waste and of an integrated institutional and

regulatory framework covering management and reporting of POPs Expected Project

Outcomes:

Streamlined sound management of chemicals and waste into national and

county development activities through capacity building of ME&F, MOH,

county governments of Nairobi, Kisumu, Nakuru and Mombasa and the

NGOs.

Introduced environmentally sound management of health care waste in

selected healthcare facilities; policy and strategic plans to prepare them to

adopt BAT and BE disposal.

Demonstrated sound healthcare waste disposal technologies in a selected

number of healthcare facilities in each county.

Minimized releases of unintentionally produced POPs from open burning

of waste.

Monitoring, learning, adaptive feedback, outreach and evaluation.

1.2 Annual Budget and Expenditure, 2020:

Project Annual

Budget (US$)

Total Project

expenses (US$)

Project Balance

(US$)

Total expended (%

of total budget)

1,971,024 785,544.43 1,185,479.57 43%

12

VI. Foreword

As the Project Executive and Focal Point to the Stockholm Convention on Persistent

Organic Pollutants (POPs) which Kenya is party to, I am pleased with the progress

given in this 2020 report of the UNDP/GEF/GOK Project on the sound chemicals

management mainstreaming and UPOPS reduction in Kenya. The project supports

Kenya as a party to the Stockholm Convention to act on listed intentionally produced

organic pollutions and to minimize the emissions of unintentionally produced organic

pollutants.,

The sound management of chemicals is essential for the achievement of sustainable

development, the eradication of poverty and disease, the improvement of human health

and the environment, and the elevation and maintenance of the citizen’s standard of

living in all sectors of development for any country.

This project is addressing unintentionally produced organic pollutants mainly dioxins

and furans in particular and how they impact on human health through the sectoral

activities - health, agriculture, labor and industry.

The 2020 Annual Project Report highlights the achievements by the project and its

partners who include government, non-governmental and private sector actors. Their

collective actions include reducing chemical risks, information and awareness,

governance, capacity building among others. The evidence is through targeted action

plans that assign roles to the various stakeholders putting in place the required

frameworks to address the challenges and gaps identified. The 2018 Toxic Chemicals

Regulations andthe Waste Bill 2018 have assisted in strengthening Kenya’s ability to

deal with chemicals threats and reduction of UPOPs emissions.

The Ministry is grateful to the Global Environment Facility (GEF) for the financial

assistance, the United Nations Development Programme (UNDP)for the project

implementation support and the various government, non-governmental and private

sector agencies for the co-financing that they bring into the project. In 2021 the project

will need stronger engagement and increased assumption of responsibility by all

chemical stakeholders downstream entities in production, use, storage, transport,

distribution of chemicals, throughout their life cycle. Their engagement by the project is

highly recommended, going forward in the remaining project period.

CHRIS KIPTOO, CBS

PRINCIPAL SECRETARY

13

VII. Executive Summary

In 2016 Kenya received a grant from the Global Environment Facility (GEF) towards

mainstreaming sound chemicals management and reduction of unintentionally

produced persistent organic pollutants (UPOPs) from open burning of waste and burn

disposal of health care waste. The 5 years, project is implemented by the Ministry of

Environment and Forestry (ME&F) in partnership with other ministries and county

government agencies, civil society, universities and the private sector.

Remarkable progress was made in 2019, the project’s fourth year of implementation

whose key deliverables is to improve Kenya’s compliance with the Stockholm

Convention on Persistent Organic Pollutants, particularly as regards to minimizing

emissions of dioxins and furans. So far the project has supported Kenyas commitment

in addressing air quality by avoiding emissions of POPs in general and UPOPS in

particular among other air pollutants. The role of open burning as a source of UPOPs

has been pushed forward by the project as indicated by a policy and legislative

measures to minimize open burning.

In 2020 the below listed have been achieved;

i. Chemical Policy review for its completeness and now under ME&F for ownership

and subsequent public participation

ii. Inter-ministerial coordination committee formalized and its meetings held

regularly.

iii. The newly listed POPS pesticides now under Pest control Products act(regulations).

iv. Report on the chemicals Communications Strategy

v. Report on the review of chemicals policy

vi. Development of a POPS Monitoring Protocol

vii. Report on the Pollutant Release and Transfer Register

viii. Procurement of Gas Chromatograph Mass Spectrometer for the Water Resources

Authority laboratories in central Laboratory and Kisumu Regional Laboratory

ix. Guidance on addressing chemicals residue in flower and horticulture

x. Guidance on chemicals residues in food

xi. Guidance on Social economic instruments for sound chemicals management

For component 2:

i. The guidelines of health Care Waste Management were completed

ii. The Standard Operating Procedures for Health Care management were

completed

iii. The Communication Strategy for Health Care waste were completed.

14

For component 3:

i. Procurement of health care waste commodities completed.

ii. Service Contracts for Mbagathi and JOORTH Hospitals to get the incinerators

upgraded finalized

iii. Service Contracts for Naivasha sub county Hospitals the to get a new incinerator

finalized.

For component 4

i. Contracts to procure bailers, shredders and bins completed and will be

distributed

ii. Assessment for turning organic waste to compost done and contract for training

on compositing awarded.

iii. Inventory on hazardous waste disposal facilities in the counties of Nairobi,

Mombasa a, Kisumu and Nakuru completed

iv. Adopting the Stockholm Convection Guidelines for waste to energy done.

Table 1: Status of contracts and tenders in process.

NAME OF TENDER Cost Ksh.

millions

payment COMMENTS

1 Consultancy service to develop a

communication strategy.

1.4 100%

done

Final report submitted

2 Supply, Delivery and

Commissioning of GAS

Chromatography-Mass

Spectrometry (GC-MS)

Equipment to WRA Laboratories

23.5 100%

done

Commissioning

remaining

3 Consultancy to review draft

chemicals policy and legislation

alignment with international

standards, Develop a Monitoring

Protocol and PRTR

3.6 70% Final draft submitted

4 Consultant to redesign guidelines/SOPs

Injection safety and medical waste

disposal communication strategy.

7.1 64% Final draft submitted

5 Health care Waste Management training

venue- Kisumu Hotel 6.1 30% in

process

Inception Report and

1st Draft Discussed

6 Consultancy service on social and

economic benefits of sound

chemical management and

2.0 80% in

process

Validation Done and

80% payment

underway

15

application of 3Rs.

7 Consultancy services to develop a

training module on composing

and recycling.

2.0 awarded Awaiting Inception

report

8 Development of an Inventory on

hazardous waste disposal

facilities in Kisumu, Mombasa,

Nakuru, Nairobi and surrounding

counties

5.0 80% in

process

Final Draft discussed by

PIC

9 Supply, delivery, installation,

Testing and commissioning of

bailers, waste plastic shredder/

shredding machine and waste

bins, as per specification.

18 Awarded Contract signed

10 Supply Delivery, Installation,

testing, and Commissioning of a

new incinerator at Naivasha Sub-

County Hospital

15 Awarded

and

Contract

signed

Awaiting delivery

11 Upgrading of Incinerator to SC

Compliance at Mbagathi Hospital

and JOOTRH

10 Awarded Contract to be signed

12 Supply, delivery, installation,

testing and commissioning of

infectious waste treatment system

with integrated Shredding and

steam Decontamination cycle at

Likoni and Mathare

30 0 To be advertised and

specifications revised

13 Construction of Ashpits, Glass

Crusher and needles at 4 HCF

10 0 Awaiting specification

from MOW

15 Medical Waste Truck 7 0 Awaiting specifications

approval

16 Additional Bins & PPE'S 1.7 P.O stage

17 Consultancy service on chemical

use in flower and horticulture

industry.

3.8 ongoing Validation done and

awaiting PIC report

18 Consultancy services to develop

an inventory on chemicals and

waste for Kajiado county.

2.7 Ongoing Validation done and

awaiting PIC report

16

19 Consultancy services to review

and update the priority concerns

related to chemical residues in

food.

3.2 ongoing Validation done and

awaiting PIC report

Consultancy to survey the waste

management, extent and impact

of leachate pollution in western

Kenya.

15 Re-

advertised

Awaiting Evaluation

Supply, Delivery, Construction,

Installation, Testing And

Commissioning Of Spray Races,

Water Storage Tanks, Cattle

Troughs And Water Points For

Domestic Use In Baringo, Narok,

Kajiado And Elgeyo Marakwet

Counties

15 ongoing Awaiting 1st

implementation report

Total tenders 182.1

Fig 1. Tender evaluation team

Photo 1: Evaluation team

17

VIII. PROJECT STATUS

SECTION 1: RESULTS ACHIEVED AGAINST THE TARGET OUTCOMES IN 2020

1.1 Activities and Achievements 2019

a) The year of 2020 was noted for the following:

Changes in the Project executives from Ms. Betty Maina to Dr. Chris Kiptoo

Principal Secretary and the retirement of Richard Mwendandu, replaced by Mr.

Cyrus Mageria Ag. Director Multilateral Environmental Agreements as Project

Coordinator.

Procurement and distribution of health care waste commodities for all project

supported facilities done.

The execution for consultancy services on legal policy ,monitoring protocol and

pollutant release and transfer register now being finalized

Completion of a chemical’s communication strategy for chemicals and waste

Start-up of partner projects on chemicals management by Ministries of

Agriculture, Health, Water and Industrialization and Enterprise Development

1.2 Project Support to MEF

Supported the Ministry in Reporting the 2018 Basel, Rotterdam and Stockholm

Conventions that lobbied for the BRS 2021 COPs to be hosted by Kenya

Supported Kenya’s participation in the fourth Conference of the Parties Minamata

Meeting on Mercury and led with Japan on the agenda item of the release of

Mercury from open burning of waste

Prepared Kenya participation in the SAICM open ended working group meeting

held on 22nd March ,2020

1.3 Component Outputs

a) Mainstreaming Sound chemicals management

i. Supported the development of National Action Plan for Artisanal Gold Mining.

ii. Development of training materials tailored for the Kenya situation on POPS

management made

iii. Consultancy to develop a POPS monitoring plan completed

iv. 80 staff coming from various counties and institutions affiliated to government

chemical industry trained on POPS issue

v. Capacity building of the Water Resources Authority and procurement for a Gas

Chromatograph Mass Spectrometer to analyze POPS in water

18

vi. University curricula for chemicals risk assessment and management of

hazardous chemicals developed by the University of Nairobi and is in the

process of being presented to the University Senate

b) Guidelines and policies on health care waste

i. Support strengthening activities with project partners (MOH) counties, private

sector by supplying commodities and personal protective equipment to select

HCF.Revisions/development of HCWM guidelines based on the last edition of

the WHO blue book and use of procedures for rapid assessment of HCWM

(target 24) completed and training about to commence

ii. Developed estimates of emission and discharge standards for HCWM burn

technologies currently in use in 13 HCF completed using I-rat Tool the individual

Assessment as a precursor for introducing environmentally sound management

of health care waste in 13 selected healthcare facilities in Mombasa, Nairobi,

Nakuru and Kisumu.

iii. Development of guidelines and SOPs for waste arising from HCW

iv. Promoting the use of lessons learnt through Inter-county benchmark field visits

for Mombasa, Nakuru and Kisumu HCW facilities.

v. Review of health care waste policy documents harmonizing guidelines on

HCWM and cascading them to the four project counties.

vi. Training of hospital staff on achieving Stockholm Convention guidelines on

incinerators and minimizing disposal of waste through open burning of waste

vii. Guideline on monitoring and evaluation for HCW finalized in HCFs.

viii. Installation of a microwave at Port Reitz Hospital.

ix. Procurement of new incinerator and upgrading of existing incinerators at the

final stages. The recipient HCF to be used as demonstration centres for good

environmental practices at county level.

d) Component 4 Municipal waste

i. Baseline Geographical Information System (GIS) mapping of dumpsites and

CBOs done for Nakuru, Mombasa and Kisumu.

ii. Inventory of harzadous chemicals and waste in Nairobi, Mombasa, Kisumu and

Nakuru done.

iii. .

iv. Selection of Community Based Organizations groups done for Nakuru,

Mombasa and Kisumu counties.

v. Development of material for Live television and radio programmes planning

meeting on UPOPs reduction and sound chemicals management and promotion

of 3Rs and on “trash to cash” initiatives.

19

vi. Printing of waste sensitization materials for public distribution.

vii. Development of modules on composting and recycling of non-hazard materials.

viii. Meetings to establish the capacity to fabricate equipment for Waste Management

Technologies with JKUAT. (Shredders, Composters, Compost turners and

bailers)

ix. Compacting of fresh waste to avoid burning in Kachok Dumpsite.

x. Approval of 3 materials recovery sites in Kisumu County.

xi. Review of performance of microwave and autoclave waste recycling possibilities

in Kisumu County.

2.0 Outcome assessment

Stakeholders in the international partners especially UNDP, and the Global

Environment facility, National government, the semi-autonomous state agencies, the

non-governmental organization in the four counties were generally satisfied with the

participatory approach employed by the PMU in the implementation of the project

giving the PMU and PSC a satisfactory rating in the midterm evaluation. Examples are

as given below. This was stated in several meetings and for a with the stakeholders

i. The MEF has concluded the chemicals policy, chemical regulations and

chemicals roadmap. It has also been very successful in resource mobilization for

project. The MEF need to strengthen its absorption and implementation capacity.

ii. The biggest gains are in the management of health care waste. The project has

trained over 200 trainers of trainers. In the 13 selected health care facilities, there

is now enough trained staff to make environmentally sound decisions on HCW.

More specifically MOH has put in place microwaves in the four counties.

Nakuru has expanded its microwave facility. Nairobi county has considered

energy to waste in Dandora and been advised by the project on selection of best

environmental practices. In Kisumu, the problematic Kachok dumping area with

a TEQ equivalent of ……has been closed

In the period January to December 2020, the following were the outcomes of the direct

intervention and support of the project:

i. Overall, the project contributed to comprehensive progress of relevant chemicals

and environment legislation in Kenya, based on ratification of Multilateral

Environment Agreements into various key institutions and especially NEMA,

Ministry of Health, Universities, Kenya Association of Manufacturers, Ministry

of Agriculture etc.

ii. HCWM Guidelines have already been reviewed. However, this work will

continue throughout the project, as experiences are gathered from the testing of

20

new technologies. The guidelines for the Environmentally Sound Management of

HCW, including rapid assessment based on the I-RAT tool, have been developed

and officially adopted. Substantial capacity building activities on HCW

especially for the four counties have been made. 200 health officers from

Mombasa, Kisumu, Nakuru and Nairobi counties, from selected HCFs, were

trained on HCWM, cessation of open burning of waste and waste separation /

sorting.

iii. A facility assessment of the 13 health facilities carried out to determine the

infrastructural status for best available techniques and best environmental

practice needs, as well as general HCWM situation in each facility. Priorities and

current state of the health care waste management (HCWM) needs of the 13

Health Care Facilities participating in the project have been documented. The

health care waste commodities documented for the 13 facilities procured and

distributed. The commodities included: Bin liners, weighing, scales, trolleys,

waste bins. The year 2020 focussed on the installation and action use of facilities

and equipment.

Photo 2: Burning chamber in Photo 3: Process loading

Naivasha sub county hospital.

Photo 4:standard state of the art incinerator

21

Tablle 2:

Outcome Status at MTR Assessment

Outcome 1.1:

Policies, strategies

regulatory and policy

framework integrating

the provisions of

streamlining chemicals

management into

development activities

(specifically those of

the Stockholm

convention and the

SAICM

recommendations)

adopted and

institutional capacity

on U-POPs and waste

management

enhanced.

On Track

Component 1 of the project pertains to

capacity building of relevant ministries

at the central level and the county

governments where the pilot activities

under the project are being carried out

(Nairobi, Kisumu, Nakuru and

Mombasa) and the NGOs/ CBOs.

Further, under this component of the

project, creation of a conducive

regulatory and policy framework,

along with the training of the relevant

institutions for implementation of the

SC and SAICM is envisaged.

Under Outcome 1.1 of the Component

1, Policies, strategies regulatory and

policy framework are to be integrated

with provisions of streamlining

chemicals management into

development activities, thereby

enhancing the institutional capacity on

UPOPs and waste management. As can

be seen from Table 8, some of the of the

activities (Outputs/Targets) for

achieving Outcome 1.1 has already

been carried out. However, a number

of activities (Outputs/Targets) are still

to be carried out.

All the pieces of legislation are all

nearly ready. What is waiting is

executive endorsement procedures not

fundamental technical issue.

A bit of catching up would need to be

done to achieve the Outcome 1.1 by the

end of the project.

The progress

towards

achievement

of results for

Outcome 1.1

has been rated

as moderately

Satisfactory

22

Outcome 1.2

Monitoring activities

intensified and

strengthened and

PRTR database in

place.

On Track

Outcome 1.2 relates to intensification

and strengthening of the monitoring

activities for chemicals and creation of

PRTR database. The work plans of the

project for the years 2017, 2018 and

2019 has not included any activity for

achieving the Targets for Outcome 1.2.

However, the project has already

initiated the efforts (prepared TOR for

appointing a consultant) for some of

the activities to achieve this outcome.

However, there are issues (project

design issues) with this Outcome

(please see recommendation 4). Due to

this reason the progress towards

achievement against this Outcome has

not been rated.

Not Rated

Table 3, Progress towards results for Component 2

Outcome

Status

as per

PIR1

Status at MTR Assessment

Outcome 2.1

Personnel of hospital

facilities and control

authorities at central

and county level have

enough capacity

guidance and

equipment to manage

healthcare waste in an

Environmental Sound

Manner

On

Track

Component 2 of the project is

focused on facilitating

demonstration of BEP and BAT for

treatment and disposal of the HCW

in the HCFs. While Outcome 2.1 of

Component 2 is focused on creation

of conducive conditions (regulations

and standards) for implementation

of the BEP and BAT at the national

level, Outcome 2.2 is focused on

facilitating implementation of BAP

and BAT at the selected HCFs.

Most of the activities/indicators

Most of the activities

planned are either been

carried out or are planned.

By the end of the project,

regulations are expected to

be in place. Accordingly,

the progress towards results

for this Outcome has been

rated as

Further analysis and

training means that this

task has been addressed

adequately

1 As Self-reported by the project team

23

Outcome

Status

as per

PIR1

Status at MTR Assessment

provided in the results frame-work

for Output 2.1 are either being

implemented and are planned.

It is likely that by the end of the

project the proposed regulations

and standards would be in place.

Outcome 2.2

Implementation of

BAT/BEP at selected

hospital facilities

successfully

demonstrated and

measured against the

baseline

On

Track

Facilitation is to be done by carryout

baseline assessment, training of the

staff of the HCFs, minimizing the

waste stream, segregation of waste

and introducing recycling activities

etc

As mentioned above Output 2.2 of

Component 2 of the project is

focused on facilitating

demonstration of BEP and BAT for

treatment and disposal of the HCW

in the selected HCFs.

Most of the equipment is in the

procurement process.

Their installation can be expected in

the 1st quarter

.

Most of the activities/indicators

provided in the results frame-work

for Output 2.2 are either being

implemented or are planned.

The impacts and effectiveness of

such activities is not visible. For

example, the staff of the HCFs are

still not clear about the need and

procedure for segregation of waste

(in terms of different types of wastes

Most of the targets/outputs

for this Outcome are

expected to be completed

by the end of the project.

However, the effectiveness

in terms of the Outputs in

terms of the desired

Outcome is missing, due to

absence of the

dissemination of the

knowledge regarding the

need to dispose of the

treated waste by a non-burn

method. The progress

towards results has been

rated as

The MTR rated it

Moderately Satisfactory.

With more work now it

should be rated satisfactory

24

Outcome

Status

as per

PIR1

Status at MTR Assessment

e.g. different types of plastics,

separation of needles from syringes)

which are necessary for

implementing BEP and BAT.

Further, there is a need to increase

the understanding amongst the staff

regarding the possibilities to recycle

some of the HCW (please see

recommendation 5).

Component 3

Table 4: Progress towards results for Component 3

Outcome

Status

as per

PIR2

Status General assesment

Outcome 3.1

Feasibility analysis

and procurement

of ESM

technologies for

healthcare waste

disposal

completed

On

Track

Component 3 of the project is a follow

up of the Component 2 of the project,

and is aimed at implementation of BEP

and BAT at the HCFs. While doing so

the project is to also make good use of

some of the existing facilities for non-

burn technologies (microwave,

autoclave) at some of the HCFs. Also,

the project is to upgrade the

incinerators at some of the HCFs to

minimise the release of UPOPs. Apart,

from the use of existing facilities for

non-burn technologies and up

gradation of the incinerators, the project

is to provide new equipment for

establishment of non-burn technologies

for treatment of HCW. The aim of

2020 saw full attention

given to developing the

specifications for the

technology.

It is evident technologies

anticipated are available

and are being put in project

HCF.

This component is

progressing well

2 As Self-reported by the project team

25

Outcome

Status

as per

PIR2

Status General assesment

Component 3 is to reduce the release of

UPOPs of about 19gTEq/yr.

Output 3.1 of Component 3, relates to

the feasibility study in terms of

technology type (microwave,

autoclave), technical specifications, and

cost effectiveness of the new non-burn

technologies based HCW treatment

facilities to be established under the

project. All these have been advertised

in in process of procurement

Output 3.1 also includes the technical

specification of the APCS for up-

gradation of some of the existing

incinerators. The project has already

worked out the TOR for the consultants

to be hired for carrying out the activities

for achieving the Output 3.1.

Accordingly, the progress towards

achievement of results for Outcome 3.1

is rated as Satisfactory. Now the

upgrading of facilities in Mbagathi and

JOOTH is progressing well

For a new incinerator in Naivasha

Subcounty should make all

surrounding hospitals and facilities

compliant

Outcome 3.2

BAT/BEP

technologies for

the disposal of

healthcare waste

On

Track

As mentioned above under Outcome

3.2, new non-burn technology based

HCW management facilities would be

created as some of the HCFs. The

activities for achieving this Outcome

26

Outcome

Status

as per

PIR2

Status General assesment

successfully

established and

demonstrated,

with a potential

reduction of U-

POPs emissions in

the order of

19gTeq/year

can only be carried out after

achievement of Outcome 3.1.

Considering that activities for achieving

3.1 are yet to be initiated, further,

considering the procurement and

establishment of HCWs management

facilities would be a time-consuming

process, the Outcome 3.2 would be

achieved only in case a no-cost

extension to the project is provided

(please see recommendation xx).

As mentioned before (under Outcome

2.2), presently there is no

understanding amongst the HCF staff

regarding the need to segregate the

waste, recycle the treated waste to the

extent possible etc. to ensure that there

is no release of UPOPs in the overall

process of using non-burn technologies

for HCW management. For the couple

of HCFs where non-burn technologies

are already in use (these non-burn

facilities were created with support

from the donor community in an earlier

project), the final disposal of the

shredded waste is carried out at the

dumpsites (where it eventually gets

burned) leading to release of UPOPs

(please see recommendation xx).

The project has targeted reduction of

release of 19.0 gTEq/ yr. of UPOPs from

the HCFs where the interventions on

the ground are being supported by the

project. This is against the baseline

figure of release of 19.0 gTEq/ yr. from

27

Outcome

Status

as per

PIR2

Status General assesment

these HCFs. Thus, the project is targeted

zero release of UPOPs due to treatment

of HCW at the targeted HCFs. It is to be

noted that this is not possible, firstly

because not all the facilities will be

using the non-burn technologies and

secondly as all the medical waste (after

treatment) can’t be recycled. Some of

the material like bandages, gauges etc.

would still need to be burned (please

see recommendation xx).

As the targeted reduction in the release

of UPOPs can’t be achieved, the

progress towards results for Outcome

3.2 is rated as Unsatisfactory. With the

correction in the figures for targeted

reduction in the release of UPOPs and

implementation of the

recommendations, the situation would

change by the end of the project.

Table 4: Progress towards results for Component 4

Outcome

Status

as per

PIR3

Status at MTR Assesment

Outcome 4.1

Awareness raising

and capacity

strengthening on

ESM of solid

waste ensured

On

Track

Component 4 of the project is focused on

reducing the release of UPOPs due to

management of SW.

Outcome 4.1 of Component 4 is to facilitate

implementation of the measures to reduce

the release of UPOPs by way of awareness

creation, training, capacity building of

stakeholders and regulations.

Regulations regarding

the management of SW

are likely to be in place

by the end of the project.

The progress towards

achievement of results

for Output 4.1 has been

rated as

3 As Self-reported by the project team

28

Outcome

Status

as per

PIR3

Status at MTR Assesment

Most of the activities/indicators provided in

the results frame-work for Output 4.1 has

already been implemented. The regulations

regarding the management of SW are likely

to be in place by the end of the project.

Satisfactory

Outcome 4.2

Sound

Management of

solid waste in

targeted

municipalities

implemented with

the support of

NGOs, and

Emergency plan

to reduce

exposure of

population to

harmful

substances

implemented with

a reduction of

unintentionally

produced POPs

from the burning

of solid waste of

23 gTEq/year (10

% of the current

estimate of 247 g

I-TEQ/year)

On

Track

Outcome 4.2 of the project pertaining to

reduction in the release of UPOPs due to

management of SW, is focused on the

engagement of communities already

involved in the informal management of

solid waste.

This includes waste separation and

recycling; development of small businesses

based on waste recycling and composting.

The reduction in the release of UPOPs is to

be achieved by enhancing the “3R” economy

and enabling municipalities to establish

Public Private Partnerships (PPP) schemes

with the support of NGOs that can at the

same time reduce the waste flows being

burnt, reduce poverty and provide an

alternative opportunity for people living at

the dumpsites. The targeted reduction in the

release of UPOPs by these measures above is

3.0 gTEq/ yr. Another 20.0 gTEq/year of

release of UPOPs is to be achieved by

carrying out the interventions (emergency

measures) at the dump sites (please see the

next row for Outcome 4.3)

In the baseline situation the inert parts (non-

decay-able like plastic, metals, glass, rubber)

of the SW were not getting combusted at the

dump sites as these were gets sorted out at

With the present scale of

activities for collection of

the waste at the source of

generation and

considering the fact that

the inert part of the SW

in the baseline case was

not getting combusted at

the dump sites, the

targeted reduction of 3.0

gTEq/ yr. is not expected

to be achieved, if

corrective actions are not

implemented.

The progress towards

results for Outcome 4.2

has been rated as

Moderately Satisfactory

29

Outcome

Status

as per

PIR3

Status at MTR Assesment

the dumpsites. Thus, it is the collection of

decay-able organic matter (food waste,

paper etc.) and their disposal in ways other

than dumping/burning which would lead

to reduction in the release of UPOPs.

The project has either implemented or is

planning to implement the

Targets/Activities mentioned in the results

framework to achieve the Outcome 4.2. The

project is supporting collection of waste

paper at the source of generation and its

recycling. The project is also supporting

collection of some of the organic waste at the

source of generation (markets, food outlets

etc.) and its disposal by the CBOs by

composting. However, the scale of such

activities is quite small, and is not expected

to lead to the reduction in the release of the

UPOPs up to the desired level.

Considering the present scale of activities

for collection of the waste at the source of

generation and considering the fact that the

inert part of the SW in the baseline case was

not getting combusted at the dump sites, the

targeted reduction of 3.0 gTEq/ yr. is

unlikely to be achieved, unless corrective

actions and recommendations are

implemented (please see recommendation

3).

Outcome 4.3

Municipal waste

disposal sites with

adequate

On

Track

Under Outcome 4.3 of the project, waste

management practises (non-burn

technology based emergency measures) are

to be implemented at dumpsites to reduce

the release of UPOPs due to burning of SW.

As implementation of

any emergency measure

to limit the release of

UPOPs from the

dumpsites (due to

30

Outcome

Status

as per

PIR3

Status at MTR Assesment

management

practices (non-

burn)

The targeted reduction in the release of

UPOPs due to the emergency measures is

20.0 gTEq/ yr.

The project has facilitated closure of two

existing dumpsites, but has not provided for

the use of the non-burn technology as an

alternative to the dumping of the SW. Due

to which the SW which was earlier dumped

at these dumpsites are now being diverted

to other dumpsites or is not being collected.

The project design has not provided for any

emergency measures for reduction of release

of emissions of UPOPs at the dumpsites

(please see recommendation 2 as well). Also,

there is no visibility regarding the funds

which would be required for carrying out

the emergency measures at the dumpsites.

There is no action on this front by the

project. With the present state of affairs, no

achievement towards reduction in the

release of UPOPs due to emergency

measures is expected.

burning) is unlikely,

there would not be any

reduction in the release

of UPOPs.

No achievement towards

reduction in the release

of UPOPs due to

emergency measures is

expected.

The progress towards

achievement of results

for Outcome 4.3 is rated

as

Unsatisfactory

Table 6: Progress towards results: Project Objectives

Indicator End of the

Project

Target4

Level at PIR5 Status and rating at

MTR

Indicator 1

Existence of a SC

compliant

institutional and

Target A

Guidelines

for relevant

Chemical Policy been finalized by

technical committee now awaits national

wide stakeholder validation forum as

required by law.

There is sufficient

progress towards

achievement of the

Target A of the project

4 Targets as per the Results Framework of the project provided in the ‘Project Document’ 5 Self-assessment by the project team

31

regulatory

framework

covering

management and

reporting of POPs.

institutions

on how to

streamline

chemicals

management

into their

policies,

strategies

and action

plans

Recommendations of the Institutional

Needs study consultancy on

Institutional Strengthening done in 2017

are being addressed

Key Output is that the Public Service

Commission has accepted the

establishment of chemicals and Waste

Department in the ME&F

Action Plan for Mercury-free processing

in Artisanal and Small Scale Gold

Mining being developed up to the 1st

Draft Report for Stakeholder validation

and backstopping support to UNDP

Country office in developing of the full

scale GEF Gold Child Project to its

signing by National Treasury

Activities to address mercury in

products have been addressed

Three Forums organized for university

to mainstream sound chemicals

management i.e. 50% of anticipated

activity.

Staff in key Institutions engaged in

chemicals management fully aware of

their responsibilities and obligations

50% in mainstreaming chemicals

management into their institutions

policies and strategies 80% done on this

component

Inter-ministerial TORs on sound

chemicals management developed and

shared with all relevant stakeholders.

Key issues addressed by the TORs

include regular meetings, (4times a

year), formation of committee and its

scope and responsibilities of each sector.

This activity is 80% done as it is awaiting

gazette notification of chemicals policy

objectives.

The progress towards

results for Target A is

rated as Satisfactory

32

33

SECTION 2: RESULTS ACHIEVED AGAINST THE TARGET OUTPUTS IN2020

Outcome 1: Streamlined sound management of chemicals and waste into national and

county development activities through capacity building of ME&F, MOH, county

governments of Nairobi, Kisumu, Nakuru and Mombasa and the NGOs

Table 2: The activities for the component

Id. Activity Planned

delivery

date

Actual

delivery

date

Completion

status

Budget

Allocation

Actual Budget

Expense

1 Consultancy for

Monitoring

Protocol

March -

May

20202

Dec 2020 Final Report

submitted

UNDP 4,621,440

2 Consultancy to

review draft

chemicals policy

and legislation

alignment with

international

standards

March -

May

20202

Dec 2020 Final Report

submitted

3 Consultancy for

PRTR concluded

and advertised by

UNDP

March -

May 2020

Dec 2020 Final Report

submitted

UNDP

4 Developing a data

base of chemicals

in water sources

(Nairobi, Athi river

and Kajiado

County)

Feb-

March

2020

Feb 2020

Scoping

exercise

done

Inspection of

WRA

equipment

0 183,400

5 Procurement of a

GCMS and HPLC

equipment to

support Water

Resources

Authority in

measuring POPs in

water

June 2020 October

2020

The

equipment

installed, Lab

works done in

Kisumu,

Training

completed.

26,349,286 23,703400

6 Interns stipend Monthly Monthly Monthly 1,500,000 900,000

Total Component 1 29,408,240

34

Output 1.1.1: Overall policy framework and specific regulatory measures covering

environmentally sound management of chemicals in general and POPs in particular

through chemicals life cycle management developed and implemented.

1. Finalization of consultancy on review of policy and legislation, monitoring

protocol and the pollutant release and transfer register.

2. Presentation for gazettement Draft Regulations for Industrial Chemicals.

3. Gazettement of the Draft Waste Management Policy.

4. Review of Consultancies granted for National Action Plan for Artisanal Gold

Mining.

5. Participation in health and environment health scientific conference.

6. Preparation for public consultations on the chemicals policy.

7. Start of the consultants for Sound Chemicals Management communication

strategy.

8. Planned start of the requisite Public Consultation for Kenya Chemicals Policy

9. Presentation for gazettement the draft cabinet memorandum for ratification

of the Minamata convention making progress.

10. Support meetings of the development of industrial chemicals regulations in

partnership with NEMA and the validation workshop for the regulations.

11. Development of a National Plan for environmental and industrial monitoring

of chemicals and waste.

12. The capacity to analyze POPs pesticides continue to be strengthened by the

government parties. Specifications for desirable GMS concluded and GCSM

procured awaiting installation at the Water Resources Management

Authority Central Testing facility.

13. Assisted the water resources Authority to develop a concept for analyzing

POPs in water coming from sludge and fly ash from incineration.

35

Outcome 2: Introduced environmentally sound management of health care waste in

selected healthcare facilities; policy and strategic plans to prepare them to adopt BAT

and BEP disposal.

Table 3. The activities of the 2020 component

No. Activity Planned

delivery

date

Actual

delivery

date

Completion

status

Budget

Allocatio

n

Actual

Budget

Expense

1 Consultant to redesign

guidelines/SOPs

Injection safety and

medical waste disposal

communication

strategy.

Sept 2020 Jan 2021 Final Report

submitted

7,182,000 4,596,480

2. Health care Waste

Management training

venue- Kisumu Hotel

June 2020 March

2020

Completed 150,000 125,000

3 Nairobi county waste

management referral

systems to minimize

open burning- KWS

Training Institute

Jan 2020 June

2020

Completed 233,99.35 233,99.35

4 Standard Operating

Procedures and

strategy development

for managing

Homebased care for

COVID 19

Sept 2020 Sept

2020

Completed 1,839,200 1,839,200

5 Health and

Environment forumns

Jan and

Nov 2020

Jan and

Nov

2020

Completed 2,000,000 396,000

6 Validation of workshop

for SOPs, Injection and

communication

strategy

Sept 2020 Dec 2020 Completed 1,500,000 1,108,800

Component 2 Totals 8,065,812.35

36

Outcome 2.1: Personnel of hospital facilities and control authorities at central and

county levels have enough capacity guidance and equipment to manage healthcare

waste in an environmental sound manner

i. Materials for segregation distributed

ii. In-house training in all the county facilities conducted.

iii. Over 200 staff trained

iv. Standard Operating Procedures and guidelines for hazardous waste

management at healthcare facilities built on lessons and examples from the

application of the I-RAT tool under the GEF4 /UNDP Global projects and on the

WHO bluebook “Safe Management of Wastes from Health-care Activities”

developed and adopted

For the component the following was done.

i. A draft national healthcare waste handbook containing guidelines for HCWM

drafted and adopted by the MoH.

ii. Draft standard procedures for HWM drafted and adopted awaiting

printing.

iii. Communication strategy for HCWM drafted.

iv. Implementation of BAT/BEP at selected hospital facilities successfully

demonstrated and measured against the baseline through evaluation of the

needs for each facility.

v. Each health facility allocated personal protective equipment.

vi. Data storage facilities distributed to Nairobi and Mombasa HCWM county

offices

Priorities for each facility and the waste as well as the Toxic Equivalents that can

be saved from open burning in respective facilities assessed and each facility will

benefit according to amount of wastes it generated.

vii. Listing and description of waste management equipment and utilities

commodities to better manage the waste done.

viii. Training and distribution of waste segregation equipment and personal

protective equipment (PPEs) for the project hospitals

ix. Specifications for HCWM technologies developed and procurement processes

started.

37

Output2.2.1: Hospital personnel at all level trained on implementation of the above

procedures

Additional training has been made on all the HCF. It is now appreciated that there is

enough capacity, what is required is enabling.

Output 2.2.2: Baseline assessment of each healthcare facility based on the assessment

procedures developed in 2.1.1 carried out, and waste management plans based on the

baseline assessment level drafted and implemented

Project deliverables:

Planning and budgeting capacity of Centre Health Management Teams (CHMT) and

Facility managers built:

Draft action plans and budgets developed for respective target health facilities.

The amount of PPE needed for each day of patient care will depend on various

factors including: the number of patients, the acuity of patients, projected number of

staff and healthcare team configuration, length of shifts, number of required breaks

for staff wearing PPE, isolation unit location and staff support strategies, waste

management strategy, lab location, lab testing demand, and hospital protocols for

products.

Hospitals were encouraged to partner with neighbouring hospitals, in-network

facilities, and/or healthcare coalitions to share inventory for any product that may

be in limited supply.

The procured PPE supplies were used for training.

Output 2.2.3: ESM management of healthcare waste (based on WHO bluebook)

implemented in facilities in each of the four counties (12 facilities) including

replacement of mercury devices with non-mercury

Facility baseline of 12 target HCF documented that quantified the levels of waste

segregation commodities. Detailed remedial measures will be developed. Kenyatta

National Hospital and Nairobi County to conclude on an MOU on utilization of the

microwave and that of Coast General hospital Mombasa is awaiting the installation of a

UPS for power support, while Kisumu is almost completing the housing.

In 2020 it was confirmed that personnel of hospital facilities and control

authorities at MOH headquarters, Kenya National Hospital and Nairobi,

Mombasa, Nakuru Counties county levels have enough capacity guidance.

38

2020 was the time for procurement of the facilities and a process of procurement

was undertaken

The strategy for the minimization of releases of UPOPS from open burning of

waste requires county governments to enforce the existing rules of handling

waste, provide for proper documentation and control of the waste disposal,

control that the personnel handling the waste wear protective clothing (gloves,

shoes) during collection, transportation and storage to reduce exposure at the

county level and facility level because waste management is a devolved activity

under the new constitutions. Activities for establishing standards and guidelines

for incinerators are also envisaged.

Table 3. Calculation of Teqs for The 13HCFS Calculations Feb 2020

No Health care

Facility

Number

of beds

Disposal

modality /

Comments

Emission

factor

Tons of

waste

generated

daily

PCDD/F

released

in the air

(gTEq /

year)

Tons of

waste

currently

PCDD/F

(gTEq /

year)

1 Mbagathi

sub county

Hospital

400 The stack

of the

single-

chamber

incinerator

is clogged.

40000 0.21 3.07 77 0.23

2 Mama

Lucy

Kibaki

County

Referral

Hospital;

130 Has two

double

chamber

incinerators

without

APCS and

one is not

functional

3000 0.15 55 0.16

3 Mathari

Mental

Hospital

100 Open

burning

4000 0.065 24 0.95

4 Naivasha

Subcounty

hospital

240 A minimal

part of the

waste are

burnt in a

basic

incinerator.

40000 0.126 1.84 46 1.84

39

No Health care

Facility

Number

of beds

Disposal

modality /

Comments

Emission

factor

Tons of

waste

generated

daily

PCDD/F

released

in the air

(gTEq /

year)

Tons of

waste

currently

PCDD/F

(gTEq /

year)

5 Nakuru

general

hospital

400 Most of the

waste are

burnt in the

open air

40000 0.21 3.07 1121 0

6 Kisumu

County

hospital

200 Small

double

chamber

incinerator

without

ACPS

3000 0.105 0.11 40 1.54

7 Kombewa

County

Hospital

41 Double

chamber

incinerator

without

ACPS

0.054 20 0.06

8 New

Nyanza

teaching

hospital

650 Recently

installed

double

chamber

incinerator

without

ACPS

3000 0.2 0.22 73 0.108

9 Ahero sub-

district

hospital

60 Open

burning

40000 0.0315 0.46 12 0.46

10 Mombasa

coast

hospital

700 Dumped in

the open -

possibly

open

burning

40000 0.3675 5.3 134 0.4

11 Port Reitz

hospital

178 Dumped in

the open -

possibly

open

burning

40000 0.09345 1.36 34 1.36

40

No Health care

Facility

Number

of beds

Disposal

modality /

Comments

Emission

factor

Tons of

waste

generated

daily

PCDD/F

released

in the air

(gTEq /

year)

Tons of

waste

currently

PCDD/F

(gTEq /

year)

12 Likoni

Health

Centre

30 open

burning

4000 0.015 6 0.22

13 Mlaleo

Hospital

5 Open

burning

0.01 3.7 0.14

Total 15.49 1645.7 7.468

41

Outcome3: Demonstration of sound healthcare waste disposal technologies in a

selected number of healthcare facilities in each county

Table4. The activities for the component for 2020 are summarized in table below

Id. Activity Planned

delivery

date

Actual

delivery

date

Completion

status

Budget

Allocation

Actual

Budget

Expense

1 Procurement

handover and

Distribution of waste

bins, bin liners, PPEs,

trolleys and

packaging cartons for

13 facilities for waste

transportation to

microwave waste

treatment sites

Feb 2020 May 2020 Completed 12,500,000 11,323,308

2. Local travel Visit to

Mrima Model health

facility (Likoni in

Mombasa) to learn

more on waste

segregation and

simple incineration

practices (4 officers

from each county and

Project management

Unit)

Nyeri outspan visit

Done Feb 2020 Completed 1,676,000

1,479,680

3. Consultancy services

to do comparative

study on burn and

non-burn

technologies in

HCWM.

Jan 2021 Feb 2021 Ongoing 6,050,000 1,211,800

4 Support project

health facilities to

measure, record and

report on monthly

basis the quantities of

Continuous Continuous ongoing 0

42

waste treated

through non- burn

technologies

5 Procure, install, test

and or retrofit the

selected incinerators

with APCS in at least

4 HCFs and make

them comply with

requirements of

Stockholm

convention on

incineration.

Dec 2020 March 2021 Contract

stage-

ongoing

20,000,000 0

6 Ashpit BQs and

design development

Dec 2020 Feb 2021 Ongoing 0 442,800

Total Amount Component 3 14,457,588

In general, the following has been done for this component in 2020

i. Conclusion of procurement process for some tenders for commodities.

ii. TEQ calculations and MOU Meetings held successfully with the 13 Project

Facilities used to determine what type of burn or non-burn technology is

appropriate.

iii. Incinerators audit for selected facilities held.

iv. Completion of the microwave housing and installation of Microwave and

shredders unit in Port Reitz Hospital and is now awaiting start.

v. Search for a site for a state of art incinerator for the medical waste incinerator

with the Japanese Government\.

vi. Scientific policy Meeting brought key experts together to discuss linkages

between environment chemicals and non-communicable diseases.

vii. Ministry of Health and Council of Governors held an assessment of status of

implementation of the microwave project in 10 Hospitals.

viii. Medical waste transportation Truck specifications developed and approved by

the chief mechanical engineer. MoH to submit the request for the trucks.

43

Output3.1.1: Feasibility study and term of reference for non-combustion or Low-U-

POPs emission technologies for healthcare waste disposal in selected hospitals or

waste management facilities.

Photo 5: Burning Chamber at Likoni Photo 6:Stored Material to be burnt in the

Hospital open

A consultancy to carry out an efficiency tests between burn and non-burn technologies

awarded and is in progress

Incineration review

Under this output, a double-chamber incinerator to be procured for Naivasha sub

county hospital..

Mbagathi and Jaramogi Oginga Odinga Referral Hospital were also assessed to be

upgraded with proper Air Pollution Control System to ensure the fulfilment of

Stockholm Convention recommended BAT standards for the release of U-POPs.

Both were selected to be upgraded to SC compliance status.

44

Outcome 3.2 BAT/BEP technologies for the disposal of healthcare waste successfully

established and demonstrated, with a potential reduction of U-POPs emissions in the

order of 19gTeq/year

An inspection for these facilities were done

Photo 7: Autoclave at Mombasa Coast General Hospital

The MOH is implementing non-burn practices in many of the project counties. Nakuru

County is already committed to non-burn in her HCF. It is also suspected that the

19gTeq might not be the 100% as waste generated could be more compared to the

estimates of 2015 during the PPG stage. The technical committee is to calculate the

present TEQs after the initial baseline assessments have been finalized. It will not take

long as they have already been done and only a confirmation or a change of the 19 Teqs

is required of the level of emissions. It is therefore suggested that the 19Teqs target

could remain as a moving target.

45

Table 5; Calculation of Teqs for The 13HCFS Calculations Feb 2020

No HCF Number

of beds

Disposal modality /

Comments

Emission

factor

Tons

/

daily

PC

DD/

F

(gT

Eq /

year

)

To

ns

of

wa

ste

cur

ren

tly

PCD

D/F

(gTEq

/

year)

1 Mbagathi sub

county Hospital

400 The stack of the

single-chamber

incinerator is

clogged.

40000 0.21 3.07 77 0.23

2 Mama Lucy Kibaki

County Referral

Hospital

130 Has two double

chamber

incinerators

without APCS and

one is not

functional

3000 0.15 55 0.16

3 Mathari Mental

Hospital

100 Open burning 4000 0.065 24 0.95

4 Naivasha

Subcounty hospital

240 A minimal part of

the waste is burnt

in a basic

incinerator, whilst

most of them are

dumped in a pit

and burnt.

40000 0.126 1.84 46 1.84

5 Nakuru general

hospital

400 Most of the waste

are burnt in the

open air

40000 0.21 3.07 112

1

0

6 Kisumu County

hospital

200 Small double

chamber incinerator

without ACPS

3000 0.105 0.11 40 1.54

7 Kombewa County

Hospital

41 Double chamber

incinerator without

ACPS

0.054 20 0.06

8 New Nyanza

teaching hospital

650 Recently installed

double chamber

incinerator without

3000 0.2 0.22 73 0.108

46

No HCF Number

of beds

Disposal modality /

Comments

Emission

factor

Tons

/

daily

PC

DD/

F

(gT

Eq /

year

)

To

ns

of

wa

ste

cur

ren

tly

PCD

D/F

(gTEq

/

year)

ACPS

9 Ahero sub-district

hospital

60 Open burning 40000 0.031

5

0.46 12 0.46

10 Mombasa coast

hospital

700 Dumped in the

open - possibly

open burning

40000 0.367

5

5.3 134 0.4

11 Port Reitz hospital 178 Dumped in the

open - possibly

open burning

40000 0.093

45

1.36 34 1.36

12 Likoni Health

Centre

30 open burning 4000 0.015 6 0.22

13 Mlaleo Hospital 5 Open burning 0.01 3.7 0.14

Total 15.4

9

164

5.7

7.468

Establishment of the baseline stack emission levels from incinerators in healthcare

facilities of Kisumu Nakuru Nairobi and Mombasa Counties.

The UPOPs reduction project under the 3rd quarter planned to establish the baseline

stack emission levels from the incinerators within the health facilities in the four project

counties of Kisumu Nakuru Nairobi and Mombasa. In this regard staff from the

Ministry of Environment and Forestry; National Environment Management Authority;

in collaboration with the Ministry of Health carried out an assessment of the compliance

of these incinerators to the requirements stipulated under the 3rd schedule of the Waste

Management Regulations of 2006 and the guidance pack on application for the emission

license on stack emission measurements.

Most burn facilities are rudimentary as in Photo5(a). the ideal would be a facility like

in (b) with complex units.The project is aiming at a facility in (c)

47

Photo 8: standard medium technology burner

Table 7(a)Demos fort incinerator (b) sketch of SC compliant and (c)

The assessment included incinerator:

a) Determination of the installed and operating capacities;

b) Determination of the stack diameters;

c) Determination of the stack heights;

d) Determination of the location of the flow disturbances;

e) Determination of the port sampling ports;

f) Review of the SOPS and Review of the maintenance program among others.

This criterion was used to analyse the bids for SC compliant incinerator for the

Naivasha sub-county hospital and for upgrading those at Mbagathi and JOORTH

hospitals.

An advertisement was placed for an incinerator. The responses indicated that most

bids relied on foreign technology for Air Pollution Control. However,

nonecontained technology for monitoring UPOPs. Therefore, Kenya has to

urgently get technology to do so.

Outcome 3.2: BAT/BEP technologies for the disposal of healthcare waste

successfully established and demonstrated, with a potential reduction of U-

POPs emission in the order of 19Teq/year.

48

Table. 6. The expected TEQs reduction in 2020 is calculated from the attached table

No HCF Num

ber of

beds

Disposal modality /

comments

Emis

sion

factor

Tons

of

waste

genera

ted

daily

PCDD/

F

release

d in

the air

(gTEq /

year)

Tons of

waste

currentl

y

PCDD/F

(gTEq /

year)

1 Mbagathi sub

county

Hospital

400 The stack of the single-

chamber incinerator is

clogged.

40000 0.21 3.07 77 0.23

4 Naivasha

Subcounty

hospital

240 A minimal part of the

waste are burnt in a

basic incinerator,

40000 0.126 1.84 46 1.84

5 Nakuru general

hospital

400 Most of the waste are

burnt in the open air

40000 0.21 3.07 1121 0

8 JOPORTH 650 Recently installed

double chamber

incinerator without

ACPS

3000 0.2 0.22 73 0.108

11 Port Reitz

hospital

178 Dumped in the open -

possibly open burning

40000 0.0934

5

1.36 34 1.36

Total 9.56 1645.7 3.538

Output3.2.1: Waste disposal activities of hospital facilities/programs are documented

and their performance is evaluated to exemplify best practices in healthcare waste

management.

The current outputs from the facilities under focus is 9.56 TEQs

With the measures taken 3.54 TEQS

Net gain for UPOPs reduction 6.02 TEQS

Efficiency of burn and non-burn technologies was conducted to determine the Best

Available Technologies and Best Environmental practices in the Kenya UPOP’s project

counties of Mombasa, Nairobi, Nakuru and Kisumu Counties. Based on need for

technology comparison, Nyeri and Uasin Gishu counties were included in the

assessment for both a burn (incinerator) and burn technology (Sterilwave). A total of six

incinerators and five non burn equipments were evaluated in this assessment, they

include diesel fired incinerators, Microwave technologies and medical waste autoclaves.

49

Efficiency test is an evaluation of how well a machine does the tasks that it is designed

to perform. The conceptual framework for this assessment was adapted from Harry L.

Field, John B. Solie6. This waste equipment efficiency conceptual framework looked into

the various aspects of these equipment that may affect the efficient operation, they

include human factors operation), environmental factors (location, turbulence, water

quality, sitting), equipment factors - functionality, maintenance and meeting standards

and stakeholder views.

Mix methods were relayed to assess the different technologies, for the burn

technologies - gaseous emissions were tested, dioxins and furans and bottom ash

analysis. The emissions tested include – PM, CO, NO, SO2, PCDD/PCDF, For the ash’s

analysis for heavy metals – Lead, Mercury, Cadmium and Arsenic. For the non-burn

technologies, mechanical, chemical, and biological tests were conducted based on

equipment standards. Temperature tests were done in all sites using data logger,

pressure monitoring, other mechanical tests done include the Bowie Dick tests, Water

PH, Hardness tests. In all the sites Geobacillus stearothermophilus spores Log6 were

used as recommended by manufactures of the equipment.

Key findings from the assessment: Tiers of hospitals assessed - Tier 6 – 1, Tier 5 – 3, Tier

4 -4 sites. Tier 6 hospitals generate an average of 2000Kg/waste per day, Tier 5 –

1000kg/day and tier 4 – 350kg/day. 83% (5) of the hospitals had both Burn and non-

burn technology on site, however 66% (4)of the non-burn sites were operational unlike

the burn sites that were all operational at the time of assessment except Kombewa

District Hospital that broke down prior to assessment and replaced with Nyeri PGH

Burn Technologies: 100% of all facilities assessed exceeded emitted of total PM with

limit of 20, PCDD/PCDF exceeding the limit of 1 ng/Nm3 – I TEQ. Other emissions;

NO, SO2 were within the required limits of EMC (Air Quality) 2014. Ash analysis for

Lead, Arsenic, Mercury, and Cadmium: results yet to be released from SGS’s testing

labs.

For Non-Burn technologies, 40 % (3) of the sites visited were fully operational. - Moi

Teaching and Referral Hospital, Nakuru PGH (AMB Ecosteryl) and Outspan Hospital –

Sterilwave, 100% of operators were trained to 0perate equipment On Job, none of them

had taken formal training on operating these types of equipment’s, All the non-burn

equipment achieved mechanical set characteristics – temperature, pressure, and

detention time. All sites had a negative biological test result Geobacillus

stearothermophilus spores Log6. Bowie dick test for the Autoclave in Coast Teaching

and Referral Hospital passed. Based on these results the non-burn technologies present

6Field H.L., Solie J.B. (2007) Equipment Efficiency and Capacity. Technology. Springer, Boston, MA. https://doi.org/10.1007/978-0-387-36915-0_9

50

a BAT/BEP technologies for medical waste management in the country due to their

working capacity, meeting set mechanical standards. To ensure these technologies are

implored well, institutionalizing preventive maintenance, regular efficiency testing and

continuous on job training will be required.

Photo 11: Handing over of waste management materials at Mbagathi Hospital

51

COMPONENT 4. MINIMIZING RELEASES OF UNINTENTIONALLY PRODUCED

PERSISTENT ORGANIC POLLUTANTS FROM

The activities of 2020 were a continuation ofthe activities of 2019.

Table 7. The activities for this component are summarized in the table below

ID Activity Planned

delivery date

Actual

delivery

date

Completion

status

Budget

Allocation

Actual

Budget

Expenses

1 Engage consultant to

develop training module

on composting and

recycling (Simplified and

popular versions)

June– Sept

2020

February

2021

Awaiting

inception

report

660,000 1,700,000

2 Conduct compost quality

assessment and Sampling

of produced organic

fertilizer from all

composting CBOs with an

accredited

standardization and

certification entity in

Nakuru and Kisumu

Counties.

October-

December

2020

December

2020

Groups

identified for

assessment.

KEBs has

given their

charges for

assessment

2,478,000 343,800

3 Communication materials

printing

June 2020 July 2020 Completed 2,032,000

4 Consultancy for social

economic benefits of

sound chemicals

management and

applications of 3 RS and

Sept 2020 Dec 2020 Final Draft

received

Due for

payment

1,996,491.9 998245.95

5 Consultancy on inventory

of hazardous waste

disposal facilities in

Kisumu, Nairobi, Nakuru

and Mombasa

Sept 2020 Dec 2020 Final Draft

received

Due for

payment

4,981,500 2,490,750

6 Validation of consultancy Sept 2020 Dec 2020 Completed 2,000,000 1,567,104

7 Waste to energy forumn Jan 2020 Dec 2020 Completed 3,000,000 1,212,640

Total Component 4 10,344,539

52

Strategy

In 2020 the focus for this component revolved around practical reduction in the release

of UPOPs due to management of solid waste. Activities focused on the procurement of

equipment and the inventory of wastes. This component also focused on communities

already involved in the informal management of solid waste. This includes;

development of small businesses based on waste separation , recycling and composting.

The reduction in the release of UPOPs was directed at enhancing the “3R” economy and

enabling counties to establish public private partnerships (PPP) schemes. This has been

done withthe support of NGOs that collect, treat and reduce the waste flows being

burnt thus reducing poverty and provide an alternative livelihood for dumpsite

families.

The main activity was to develop environmental economic tools to facilitate

communities.

The targeted reduction in the release of UPOPs by these measures above is 3.0gTEq/ yr.

Output 4.1.1: Awareness raising activities for the communities and the municipalities

aimed at enhancing 3Rs of waste..

The main activities revolved around visiting the sites and documenting ongoing

initiatives that can be up scaled . The information was collected through a geographical

information system (GIS) mapping of legal and illegal dumpsites. Field visits were

made to all the counties to carry out an inventory of waste handlers and promoted a

stop to open burning.

Output 4.1.2: Regulatory framework for the recovery of waste materials (glass,

organic, plastic) and for licensing of the recovery activity at county and central levels

improved to integrate SC requirements.

The Sustainable waste management bill has facilitated a new approach to

creatingbusiness out of waste management. The project initiated the procurement

process for materials and equipment for collection of waste from designated areas and

transport to sites of separation, reclamation, recycling and composting.

53

Output 4.1.3: Counties provided with training, manual, and technical assistance for

the management of solid wastes

\

Photo 9: Recyclers with their stocks Circular economy and the green economy model

Existing models and improvement;

In Kenya there are a few organizations that have embraced a systemic approach to

economic development designed to benefit businesses, society, and the environment.

Green Africa and Taka Taka solutions business models are based on circular economy

that incorporates community (collectors) and environment conservation (through 3Rs).

These models should be encouraged and supported through incentives to expand. The

only gap that exists in their model is the lack of involvement of users. We propose

material recovery facilities (MAREFA model), this is done through CBO and

community groups. Government could provide facilities which can be rented by the

community groups and CBOs..

The GoK could also setup a microfinance that can be used by the collectors strictly for

setting up waste trade shops. From MAREFA model, setting up of waste collection

shops in each sub county will significantly reduce open burning as the waste disposal

method of choice. CBOs and community groups involved in circular economy could

also be facilitated to set-up waste collection points. Most of these groups are operating

on road reserves, public land without authorization and private land which are allowed

for use based on good will which can be revoked any time.

Properly functioning recyclable waste shops will reduce the cost users pay to dispose of

their waste and instead of viewing wastes as a liability, they will view it as an asset

resulting in behavioral change.

54

55

Zero Waste Shops;

We propose that the government encourage and embrace Zero Waste Shops which

enables customers to live a more zero waste lifestyle through eliminating packaging

and encouraging the use of containers from home to fill and refill with bulk

wholefoods, beauty and cleaning products among others. Zero Waste Shops will cut out

wastes from the packaging materials used thus less plastics getting dumpsites.

Microfinancing;

Setting aside microfinance for people involved in circular economy to improve

efficiency especially CBOs. CBOs and community groups main goal is to recycle the

recyclable wastes that they collect, the only hurdle they face is the amount of money

required to procure machineries. They proposed a microfinance setup by the

government for circular economy players to help them acquire the necessary tools.

Electricity subsidies;

Recycling companies use heavy machinery that requires a lot of electricity, most

companies spend a lot of money on electricity which increases the cost of production.

The companies are forced to pass down this cost to recyclers leading to low buying

price of recyclable wastes from the collectors. Through this cycle, the collector is forced

to charge the public for waste collection hence the inefficiency witnessed. Government

should identify the players in circular economy and work out subsidy formula to

reduce electricity cost, by so doing, more money will circulate in the circular economy

encouraging positive behavior by collectors and users.

Needs of practitioners in collection, recycling and reuse

Training;

CBOs and community groups are only involved in one R in circular economy (reduce),

very few are involved in reuse. There is a very good chance of achieving the goal of

involvement in the 3R as most collectors are eager to recycle.

The main problem they face is lack of skills on how to recycle, where to take their

products and high cost of machinery used in recycling. To fully realize the circular

economy, CBOs and community groups must be sensitized and empowered to employ

the 3Rs fully which will increase price and demand of recyclable wastes, and output of

recycling material. With increased demand, the users will be able to get incentives from

recyclable wastes they sort.

56

Collectors restructuring;

It is proposed that CBOs and community groups involved in circular economy in each

county to be under one umbrella association with each collector’s area of operation

clearly defined, to improve efficiency of waste collection. With defined areas of

operation CBOs become more responsible thus ensuring UPOPs generating wastes are

mopped out. The association’s role is to conduct monitoring to ensure collectors’

assigned areas are clean by ensuring there is a mechanism for litter picking, prompt

collection of wastes from residential areas, encouraging residents to be responsible

(separate at source) and open burning is completely eliminated in collection centers.

With the umbrella association the economy of scale will improve. The main hindrance

of a well-functioning circular economy stems from the fact that most CBOs cannot

afford recycling equipment. By having one association, there will be pooling of

resources making the machines more affordable and recycling will increase revenue.

Another advantage of an association is it enhances partnerships, it’s easy for waste

collectors to champion their interests as a unit because many stakeholders and investors

are interested in a well-structured organization. It is easy to organize for empowerment

workshops and seminars. Centralized record keeping system will provide vital

information to the government entities involved in minimizing the impact of hazardous

waste on health and environment. One of them being it is easy to get the volumes of

wastes generated in the county if the collectors have one association that compiles and

keeps records from information provided by its members. It was noted with concern

that most counties involved in this research do not have accurate records of total waste

collected in their county, only Nakuru county association of CBOs and community

groups (NASWAMA) have kept and maintained up-to-date records of all wastes

produced in the county. There is need to enforce this recommendation, it will

tremendously reduce wastes in Kenya.

Elimination of third party between collectors and recyclers;

The middle men between the collectors and recyclers are blamed for derailing full

implementation of circular economy. All waste collectors from users are blaming non-

implementation of circular economy on the midddle men between collectors and

recyclers. The third party is the entity that links collectors and recyclers by buying

wastes at a cheap price and selling at a higher price making a profit of more than 100%.

This has demoralized most collectors leading to poor waste collection and sorting. The

main concern of collectors is third parties’ interest of putting profit before

environmental sustainability. Their presence in circular economy has crippled the cycle

57

and hence there is urgent need to eliminate that part in our circular economy. Instead of

what we have now (user – collector – third party collector – recycler – producer),

collectors and recyclers are proposing (user – collector – recycler – producer) and for a

very efficient system this was proposed (user – collector/recycler – producer), the

shorter the chain the more efficient the circular economy becomes.

Sorting at the source;

There is need for a structured waste collection model from the government which

should be enforced from the source (residential areas). The law should expect every

rental house owner to provide bins for different wastes and enforce it, to make sure

their tenants strictly adhere to it. Sorting wastes at the source will greatly reduce the

cost of cleaning recyclable wastes before they are recycled, medical waste and other

hazardous wastes can be handled better.

Hazardous waste handling by collectors

Most waste collector and a handful of recyclers lack basic knowledge of handling

wastes, empowerment through trainings, seminars, workshops and civic education will

make handling of wastes to be safe and enjoyable. This empowerment will also open

new opportunities in efficient waste reuse and recycling, linkage and partnership

between players in circular economy, management of recycled wastes, safe

transportation of wastes, new and emerging trends in waste recycling and handling

technologies, policies etc.

The new draft policy and bill are critical in that county governments will be required to

dispose of waste within their borders if a new waste management law is adopted. In the

proposed bill by the Ministry of Environment, counties will only be allowed to discard

their waste in other counties if there is an agreed framework for inter-county transport

of garbage.

Riding on the Bill the project is undertaking the following actions.

Communities have been selected for demonstrating plans and actions for the

reduction of solid waste’s open burning by promoting3Rsin waste management

including composting

The county Government of Mombasa selected Big Ship as the community Based

organisation to be engaged and supported in conducting project activities. Other

county’s selected CBOs and their representatives identified will officially be

recognized under the project.

A Memorandum of understanding and community

resources, list of activities, timeframe and quality check modalities are agreed

and signed by government and community re

Photo 10: Composting activities in Nakuru county

Communities in Mombasa county being briefed about plastic reuse at

Modern Soap recycling company

at Kisauni in Mombasa.

Photo 12: Assorted waste at the company and photo final products.

A Memorandum of understanding and community-driven projects on 3R with

resources, list of activities, timeframe and quality check modalities are agreed

and signed by government and community representatives will be made

ing activities in Nakuru county

Communities in Mombasa county being briefed about plastic reuse at

Modern Soap recycling company and Table 10, Communities visiting a SW initiative

Assorted waste at the company and photo 12: plastic flakes and pellets

58

driven projects on 3R with

resources, list of activities, timeframe and quality check modalities are agreed

presentatives will be made.

Communities in Mombasa county being briefed about plastic reuse at Mombasa

Communities visiting a SW initiative

: plastic flakes and pellets

Photo 14: Rejected plastic wastes at

Photo 10: Waste transported to Nakuru Gioto dumpsite

: Rejected plastic wastes at premier plastics ltd to be recycled.

Photo 10: Waste transported to Nakuru Gioto dumpsite

59

60

Component 5

The activities for this component are summarized in the table below

ID Activity Planned

delivery

date

Actual

delivery

date

Completion

status

Budget

Allocation

Actual

budget

expenses

1 Consultancy for

communication

strategy,

completed

April to

June 2020

September

2020

done 1,500,000 1,468,444

2 2020 PIR carried

out

July 2020 July-

August

September

2020

0 0

3 Virtual Project

Steering Control

Meeting

August

2020

August

2020

August

2020

1,000,000 0

4 Monitoring and

Evaluation

Meeting

September

2020

Sept 2020 Completed 350,000 231,900

4 Review project

document in

line with MTR

and project

tracking tool

Jan 2020 Jan 2020 Completed 800,000 904,700

5 Technical

Committee

Meetings to

monitor and

develop

workplans and

report (4)

Jan, April,

July,

December

2020

Jan, Sept,

December

2020

Completed 4,500,000 4,500,000

6 Gender

mainstreaming

consultancy

May 2020 - Not

completed

1,500,000 0

7 Lessons learnt

and

dissemination of

communication

strategy

Jan- May

2020

- Not

completed

1,500,000 0

8 Office

operations

500,000 269,000

Component 5 Totals 7,374,044

61

5.1 Project Implementation Report for the GEF PIR

5.2 Implementing the recommendations of midterm evaluation by UNDP

The MTR was conducted between August and November 2019. The Final Report

submitted on November 2019. UNDP and the Partners rate the outcome as Satisfactory

and participated in coming up with the management responses. The recommendations

clearly identify areas where the project team will need to refocus the ongoing

implementation, to ensure delivery of the project targets, have in place a sound

chemicals management framework for Kenya and track emissions.

The recommendations of the MTR are Annex 1. They informed greatly the 2020 Annual

Workplan

5.3 Management of multilateral environmental agreements

1. Support to GOLD Child, ChemObs, Special Programme, NAP projects

2. One HESA meeting held

3. HCWM-TWG,

4. Consultancy on Communication Strategy

IX. RISKS AND ISSUES

1 Non Prioritization of project Activities by the

partners especially component 1 implementer.

The partners are busy and

preoccupied with many activities

delaying the project activities. This

has led to delays in delivery of the

2019 specific work plan activities. It

was the same in 2019

2 Delay of procurement by UNDP of various

consultancies

This affected component 1 and 2

leading the MTR to label them not

on track

3 Cash flow - ME&F the Implementing Partner

pre-finance some of the activities on which it

leads as allowed under the HACT, on

occasions when the funds did not come

through after their disbursement to the Central

Bank. It could not extend this facility to the

other responsible parties in the project.

The title of the project was changed

on the request of UNDP, when it

changed the National Treasury took

too long to open an account. This

was discussed in a consultative

GOK/UNDP meeting held on ….

4 Account Name The donor was unable to transfer

funds to the implementing ministry

due to the project name at CBK. The

62

donor and the ministry have been

resolving the issue since June,2019.

Fortunately it is now finalized

5 Operation - Under the re-imbursement

financing modality to the IP and direct cash

transfer to the RPs, there have time lags in the

flow of resources and reporting.

The PMU continue to work towards

shorter approval and reporting

frameworks, that is supported with

enhanced M&E and tracking of

delivery.

Partnerships

Table 15.Plastic waste shredded and baled

63

X. LESSONS LEARNED (POSITIVE OR NEGATIVE) AND

RECOMMENDATIONS.

1. There is need to use personnel already timed and to reduce workshop type

forums for capacity building.

2. Enhancing inspection skills to customs officers, imparting knowledge and

handling skills to first responders such as the police and continuous awareness to

the public that come in contact with the goods on transit.

3. Data is key to precautionary and reactive measures to chemical and waste

disposal therefore the engagement of consultants to inform project interventions

is necessary to enable the project meet its objectives.

4. There is need to involve the Ministry’s management to understand how the

project is implemented for smooth operations. During this time, there were so

many changes in Management from the Cabinet secretary to support staffs which

led to delays in Bank account mandates. The project was severely affected since

there were minimal activities done. There is need for early preparation and risk

mitigations in terms of assessing funds

Table 6: Overview of available resources for the

Table 6: Overview of available resources for the project duration 2020

Donor Contribution Type

UNDP Direct Cash Transfer

Direct Payment

GoK Cash

In- Kind

Table 7: Financial summary (Based on Project Transaction details)

Project Output Budget

Component 1 57,326,786

Component 2 15,830,000

Component 3 65,376,000

Component 4 38,054,843

Component 5 22,880,000

Total 199,467,629

Chart 1: Component Budget as a percentage of Total Budgetary Approved

33%

19%

11%

Budget

Table 6: Overview of available resources for the project duration 2018

Table 6: Overview of available resources for the project duration 2020

Total expenses Balance

Year 2020

31,757,314.70

53,292,568.86

1,567,500.00

28,763,700.00

Table 7: Financial summary (Based on Project Transaction details)

Total expenses Balance % utilization

57,326,786 40,562,086.85 16,764,699.15

15,830,000 6,464,022.64 9,365,977.36

65,376,000 14,748,559.16 50,627,440.84

38,054,843 10,481,843.18 27,572,999.82

22,880,000 12,793,371.73 10,086,628.27

199,467,629 85,049,883.56 114,417,745.44

Chart 1: Component Budget as a percentage of Total Budgetary Approved

29%

8%

Budget

Component 1

Component 2

Component 3

Component 4

Component 5

64

project duration 2018

% utilization

71%

41%

23%

28%

56%

43%

Chart 1: Component Budget as a percentage of Total Budgetary Approved

Chart 2: Component expenses as a percentage of Total Expenses

Chart 3: Component utilization percentage

8%

17%

12%

15%

Total expenses

19%10%

13%

26%

% utilization

Chart 2: Component expenses as a percentage of Total Expenses

art 3: Component utilization percentage

48%

Total expenses

Component 1

Component 2

Component 3

Component 4

Component 5

32%

19%

% utilization

Component 1

Component 2

Component 3

Component 4

Component 5

65

66

XI. MONITORING AND EVALUATION

The HCWM M&E framework developed

A liaisons officer from planning department of ME&F appointed to support

PMU in the development of the M&E for the project.

XII. ANNEX 5.3 AWARENESS MATERIALS FROM SELECTED PRINT

MEDIA

ANNEX 5.3 AWARENESS MATERIALS FROM SELECTED PRINT

67

ANNEX 5.3 AWARENESS MATERIALS FROM SELECTED PRINT

68

69

70