SOUTHERN REGIONAL POWER COMMITTEE
BANGALORE
Minutes of the Special Meeting on pending protection issues in respect of M/s KPCL held on 06.03.2015:
Introduction
A Special Meeting was held on 06th
March 2015 in Southern Regional Power Committee,
Bangalore to discuss pending protection issues in respect of M/s KPCL. The list of
participants is enclosed at Annexure-I.
Shri S.R.Bhat, Member Secretary (MS), SRPC welcomed Technical Director, KPCL and
other Participants to the Meeting and stated the following:
Cooperation extended by KPCL and KPTCL in the Protection Committee forum was
appreciated.
There had earlier been instances of complete station outages at Sharavathy, Kadra and
Nagjheri HPS, which was a matter of some concern.
Petition No. 374 filed by TANTRANSCO before Hon’ble CERC seeking time extension
for Phase-I and Phase-II activities of Protection Audit Recommendations was heard on
15th
January 2015. All Southern Region Constituents had been directed to file status of
implementation of protection system in their respective system to the Commission by
31.03.2015.
Senior-level Officer could be nominated as Nodal Officer to monitor implementation of
various recommendations pertaining to KPCL stations.
Number of remedial actions were pending for considerable time in respect of KPCL
stations. This Meeting was therefore being conducted to have focused deliberations on
issues in presence of the higher management of M/s KPCL.
Following issues were deliberated in the Meeting:
A. Issues related to Hydro Power Stations in Kali complex
1. Complete outage of Nagjheri power station occurred at 11:09 hrs on 22-02-2015.
KPCL stated that while desynchronizing Unit-3, Y-pole of the circuit breaker got
stuck up and did not open. LBB protection got operated which in turn tripped the
220 kV bus including bus- sectionalizer, and all connected 220 kV lines and
running units at Nagjheri power station.
![Page 3: SOUTHERN REGIONAL POWER COMMITTEE - … · A Special Meeting was held on 06th March 2015 in Southern Regional Power Committee, ... LBB protection got operated which in turn tripped](https://reader030.vdocument.in/reader030/viewer/2022020303/5b84b0237f8b9ae5498cd0db/html5/thumbnails/3.jpg)
2
It was noted that complete outage of station was not desired. Only one 220 kV bus
should have tripped during the incident. KPCL was therefore requested to kindly
review trip logic for LBB both at Nagjheri and Sharavathy stations within a period
of one month. Further, since it was not clear as to what had initiated LBB, KPCL
was also requested to analyse cause for LBB operation and furnish the same along
with LBB protection scheme by next PCSC Meeting to SRPC.
During discussions it was informed by KPCL that Nagjheri Hydro station was
being operated on a single 220 kV bus. SRLDC and SRPC objected to single bus
operation since it was affecting station reliability and posing a threat to operational
security of grid during a complete outage of station. As per good operation
practice, it was requested to have two bus operation in all stations of KPCL where
two buses with bus coupler/ bus sectionalizer breaker is available. The protection
logic needed to be such that during any bus fault or LBB operation, only the
concerned affected bus should be isolated.
2. Complete outage of Kadra power station occurred at 12:56 hrs on 16-02-2015.
KPCL stated that a B phase to earth fault had occurred on 220 kV Kadra-Kodasalli
line, on account of which Kadra-Kodasalli line breaker tripped at Kodasalli end
while Kadra-Kaiga line breaker tripped at Kaiga end. However, breaker at Kadra
end of Kadra-Kodasalli line did not trip on distance protection on account of failure
of protection DC supply fuse fail. This had led to 220 kV bus-dead condition at
Kadra HPS. During fault, Units-1,2 & 3 were not in service while all four lines
were intact. These breakers were hand-tripped later at Kadra end.
KPCL stated that as part of remedial measures, the faulty fuse had been replaced
and protection DC supply was normalized. KPCL informed that there are two
battery banks (1 & 2), but supply to protection system is availed from one bank
only. Switching between the two battery banks is being carried out manually.
KPCL was requested to provide supply to Main-1& Main-2 relays and Trip Coils
(TC1, TC2) from independent/ separate battery banks. KPCL was asked to comply
with all the recommendations recommended by PSAG-10 at the earliest. KPCL
expressed that there were constraints in this regard, since many of its stations were
old. There would be a need to go for extensive rewiring etc. KPCL was requested
to examine this issue for implementation and furnish a road map for all the stations.
3. 220kV Nagjheri-Kodasalli lines kept opened from Nagjheri end.
KPCL stated that these lines were being kept open as per the instructions of SLDC.
During the course of deliberations, it was felt that these lines needed to be normally
kept in service and taken out only during any specific need based requirement.
![Page 4: SOUTHERN REGIONAL POWER COMMITTEE - … · A Special Meeting was held on 06th March 2015 in Southern Regional Power Committee, ... LBB protection got operated which in turn tripped](https://reader030.vdocument.in/reader030/viewer/2022020303/5b84b0237f8b9ae5498cd0db/html5/thumbnails/4.jpg)
3
B. Issues related to RTPS and BTPS Thermal power stations
KPCL stated that at RTPS Auto re-close had been enabled and functioning in all
400kV lines except on RTPS- Mahaboobnagar and RTPS-Munirabad lines. Existing
Micromho relays shall be replaced with Siemens make Numerical relays shortly.
Order had been placed on Siemens. At BTPS, Auto re-close was enabled for BTPS-
RTPS line. Shutdown required for other 3 lines for enabling and testing of auto re-
close function. KPCL was requested to complete the same at an early date in
coordination with KPTCL.
C. Compliance of Recommendations of the following Power System Analysis Group
(PSAG) Meetings:
PSAG-3 was held on 04.09.2013 to analyze the multiple trippings that occurred at
Sharavathy HPS on 18-08-2013. Compliance of the pending recommendations is
enclosed at Annexure-II.
PSAG- 6 was held on 05.02.2014 to analyze the multiple trippings at Raichur TPS
on 26-01-2014 and 30-01-2014. Compliance of the pending recommendations is
enclosed at Annexure -III.
PSAG-10 was held on 12.11.2014 to analyze the Grid Disturbances at Kadra,
Kodasalli and Kaiga Power Stations that occurred on 26-09-2014 and 05-10-2014.
Compliance of the pending recommendations is enclosed at Annexure -IV.
It was noted that generally recommendations involving procurement activities were
pending, for which also the steps had been taken to complete by Dec, 2015.
D. Pending Implementation of PCSC Recommendations
Latest status of implementation of recommendations of PCSC meetings relating to
Hydro Stations in Kali Complex and RTPS, BTPS is enclosed at Annexure -V.
It was noted that steps had been taken to implement various recommendations relating
to A/R scheme enabling, replacement of old electromechanical relays with numerical
relays at KPCL Stations.
E. Protection Audit Recommendations (Phase- I & II)
Latest status of implementation of protection audit recommendations (Phase I &
Phase II) as updated on 03.02.2015 is enclosed at Annexure -VI.
F. Action taken for inadequate response of the units of KPCL Stations with respect
to RGMO.
![Page 5: SOUTHERN REGIONAL POWER COMMITTEE - … · A Special Meeting was held on 06th March 2015 in Southern Regional Power Committee, ... LBB protection got operated which in turn tripped](https://reader030.vdocument.in/reader030/viewer/2022020303/5b84b0237f8b9ae5498cd0db/html5/thumbnails/5.jpg)
4
The status of implementation of RGMO in Hydro & thermal units as furnished by
KPCL is as follows:
*Kadra & Kodasalli units & R&M of 6Th
unit NPH & Bhadra two units
In total RGMO is implemented for 3,111.2 MW (87.88%) in Hydro Units, and for
2,510 MW (92.27%) in Thermal Units. Thus, combined RGMO implementation of
Thermal & Hydro Power stations of KPCL stood at 89.79%.
It was pointed out by SRLDC that RGMO response of Units of KPCL Stations
(especially thermal) with respect to desired quantum was not adequate. Details of
various instances for analysis were being posted in the RGMO web group regularly.
KPCL replied that this was mainly on account of poor quality of coal that thermal
power stations get.
SRLDC pointed out that KPCL’s practice of keeping CMC out at times based on
operational requirements was contrary to Regulations. Further, they should also avoid
wide-valve operation. KPCL was also requested to extend the status points (of
RGMO) to SLDC, for proper analysis and appropriate action.
Vote of Thanks
MS, SRPC thanked Technical Director, KPCL and other Officials from KPCL & KPTCL
for participating in the Meeting. He hoped that with active cooperation, visible
improvement would be witnessed in the near future on these pending protection issues.
X------------------------------------------X------------------------------------------X
![Page 6: SOUTHERN REGIONAL POWER COMMITTEE - … · A Special Meeting was held on 06th March 2015 in Southern Regional Power Committee, ... LBB protection got operated which in turn tripped](https://reader030.vdocument.in/reader030/viewer/2022020303/5b84b0237f8b9ae5498cd0db/html5/thumbnails/6.jpg)
Annexure - I
![Page 7: SOUTHERN REGIONAL POWER COMMITTEE - … · A Special Meeting was held on 06th March 2015 in Southern Regional Power Committee, ... LBB protection got operated which in turn tripped](https://reader030.vdocument.in/reader030/viewer/2022020303/5b84b0237f8b9ae5498cd0db/html5/thumbnails/7.jpg)
Latest status of implementation of recommendations of PSAG-3 for
the Gird incident occurred at SGS on 18.08.2013
S.N.
Recommendations
KPCL’s Compliances
e Disturbance Recorder facility e-NIT floated through e-portal on 04.02.2015. Pre bid meeting for the bid was held on 19.02.2015
f Providing GPS (Time synchronization) facility
e-NIT floated through e-portal on 04.02.2015. Pre bid meeting for the bid was held on 19.02.2015
g To replace both bus sectionalizing BOCBs with new circuit breakers
LOA issued to M/s. ABB India Ltd. on 12.12.2014. Review of drawings is in progress
Annexure-II
![Page 8: SOUTHERN REGIONAL POWER COMMITTEE - … · A Special Meeting was held on 06th March 2015 in Southern Regional Power Committee, ... LBB protection got operated which in turn tripped](https://reader030.vdocument.in/reader030/viewer/2022020303/5b84b0237f8b9ae5498cd0db/html5/thumbnails/8.jpg)
S.N Commitee observations KPCL Compliance
5
KPCL shall take action to arrange for GPS time
synchronisation of all EL's and provide DR for all
lines.
Job Order has been issued on M/s Siemens ltd., vide SEEM2/R4GM2/400KV/413 dtd:
02.02.2015 for retrofitting electromechanical relays with Numerical version for 400 KV lines of
Mehabobnagar, Munirabad, and ICT-1 & ICT-2 . Supply of GPS and time synchronization of all
the relays also included in the job order. The numerical Relays will be incorporated with EL &
Disturbance Recorder.
6KPCL shall take action for retrofitting of all old
electromagnetic relays with numerical relays.
Presently Raichur (PG)1&2 liines are already provided with numerical relays. Retrofitting of
static relays with numerical relays for BTPS line was completed on 18-03-2014. Job Order has
been issued on M/s Siemens ltd., vide SEEM2/R4GM2/400KV/413 dtd: 02.02.2015 for
retrofitting electromechanical relays with Numerical version for 400 KV lines of
Mehabobnagar, Munirabad, and ICT-1 & ICT-2.
Obtained the Budgetary offer for retrofitting the electromechanical relays of existing bus bar
protection with numerical version and is under process.
12Recommondations of protection Audit conducted
on 02.11.2012 shall be carried out.
Recommondations of protection Audit are being carried out.The latest status of activities in
phase-1 & phase-2 formats are enclosed here with as Annexure-A&B respectively. Most of
the observations already fulfilled except the activities where procurement is involved.
COMPLIANCES FOR THE RECOMMENDATIONS OF POWER SYSTEM ANALYSIS GROUP (PSAG-6) DURING THEIR VISIT TO RTPS ON 05.02.2014.
Annexure-III
![Page 9: SOUTHERN REGIONAL POWER COMMITTEE - … · A Special Meeting was held on 06th March 2015 in Southern Regional Power Committee, ... LBB protection got operated which in turn tripped](https://reader030.vdocument.in/reader030/viewer/2022020303/5b84b0237f8b9ae5498cd0db/html5/thumbnails/9.jpg)
1
The PSAG-10 members recommended to replace the Main I (Q21 static
Quadramho relay -SHPM 101) distance protection relays with Numerical relays
having DR and EL features.
e-NIT No. LOT/CEED/EE6/R&M/ Dist.Prot/1416 dtd:
28.07.2014 was floated through e-portal for Supply, Retrofit,
Testing & Commissioning of Numerical Distance protection
relays & GPS for Varahi, Gerusoppa, Kadra & Kodasalli
Power Houses of KPCL. Bid evaluation is under progress.
2The PSAG group also advised KPCL to test the Main II Relay (PZ1000
numerical relay) at the earliest .
Will be completed during last week of March 2015 in
coordination with KPTCL.
5
PSAG recommended to make the carrier aided protection functional for 220kV
Kadra-Kodasalli, 220kV Kadra-Kaiga and 220kV Kodasalli-Kaiga lines. In
addition, since most of the faults are seen as high resistance fault, PSAG
suggested to revise the existing PUR to POR scheme for all the lines at Kali
complex.
e-NIT No. LOT/CEED/EE6/R&M/ Dist.Prot/1416 dtd:
28.07.2014 was floated through e-portal for Supply, Retrofit,
Testing & Commissioning of Numerical Distance protection
relays & GPS for Varahi, Gerusoppa, Kadra & Kodasalli
Power Houses of KPCL. Bid evaluation is under progress.
Hence work shall be taken up in coordination with KPTCL
after installation of new relays.
6
The PSAG group noted that most of the faults were in the ‘B’ Phase (of RYB) to
ground faults. The group observed that it may be due to thick vegetation below
Kadra – Kodasalli, Kodasalli - Kaiga line, Kadra – Kaiga line. Hence the PSAG
group members advised to have regular thorough line patrolling and clearing the
corridor (i.e. Right Of Way).
To be implemented by KPTCL
9
KPCL informed that installation of GPS for time synchronization of all relays and
other protection devices is under process. KPCL is requested to expedite the
same.
e-NIT No. LOT/CEED/EE6/R&M/ Dist.Prot/1416 dtd:
28.07.2014 was floated through e-portal for Supply, Retrofit,
Testing & Commissioning of Numerical Distance protection
relays & GPS for Varahi, Gerusoppa, Kadra & Kodasalli
Power Houses of KPCL. Bid evaluation is under progress.
Compliance to recommendations of Meeting of Protection system Analysis Group (PSAG-10) at Kadra, Kodasalli and
Kaiga held on 12th & 13th November 2014 for discussing the Grid Disturbancea occurred on 26.09.2014 and
05.10.2014
Sl. No. Recommendations KPCL Compliances- Status as on 23.02.2015
Page 1 of 2
Annexure-IV
![Page 10: SOUTHERN REGIONAL POWER COMMITTEE - … · A Special Meeting was held on 06th March 2015 in Southern Regional Power Committee, ... LBB protection got operated which in turn tripped](https://reader030.vdocument.in/reader030/viewer/2022020303/5b84b0237f8b9ae5498cd0db/html5/thumbnails/10.jpg)
Sl. No. Recommendations KPCL Compliances- Status as on 23.02.2015
11
It was observed that Kodasalli – Nagjheri I & II lines were kept open at Nagjheri
end on 26.09.2014, 5.10.2014 & 14.10.2014 during bus dead conditions at
Kodasalli station. KPTCL (SLDC) is requested to clarify /review the issue
To be implemented by KPTCL/SLDC
Page 2 of 2
Annexure-IV
![Page 11: SOUTHERN REGIONAL POWER COMMITTEE - … · A Special Meeting was held on 06th March 2015 in Southern Regional Power Committee, ... LBB protection got operated which in turn tripped](https://reader030.vdocument.in/reader030/viewer/2022020303/5b84b0237f8b9ae5498cd0db/html5/thumbnails/11.jpg)
Meeting
No /
Index
Meeting
S.NODetails of Event Date Reason PCSC Recommendations
Utility
Responsible
to
implement*
Status of Recommendation RemarksUpdated Status based on the latest PCSC
meeting discussion - Status as on 10.02.2015
30/I/A 1 RTPS Tripping
incidents and the Spl
meeting held at RTPS
on 13th and 14th
March 2014
Mar-14 Spl meeting held at RTPS on 13th
and 14th
March 2014
The PCSC forum recommended for
replacement of existing electromechanical relays with Numerical
relays.
KPCL (1) e- Tender folated for the retrofit of
existing static relays with Numerical
version for lines M.nagar,M.bad,ICT-1
& 2 -Technical Bid opened & price bid
yet to be opened.
(2) Retrofit of existing bus bar (CAG-34)
with numerical version -Budgetetory
offers obtained and is under process.
1) Order placed on M/s Siemens to replace relays.
The work will be Completed by May - 2015.
2) Retrofit of existing bus bar (CAG-34) with
numerical version -Budgetetory offers obtained and
is under process.
33/II/3 9 400kV
Hiriyur-BTPS line-2
22-05-14 &
23/05/2014
B phase to ground fault had
occurred in line and line auto
reclosed at Hiriyur end but failed
to reclose at BTPS end.
• KPCL: A/R is not yet enabled at Raichur plant.
Recommendation:
The PCSC forum requested KPCL to enable the A/R feature at
RTPS end before next PCSC meeting (i.e. 31st July, 2014.
KPCL A/R at BTPS end will be enabled
during November 2014 end and needs
LC.
1) A/R for 220kV lines enabled already.
2) Shut down of lines availed to commission the
auto reclosing scheme for 400kV lines at BTPS.
3) A/R shall be enabled in next shut down
34/III/1 8 400kV
Raichur-BTPS line
26-06-2014 Transient fault in R-phase.
Line did not auto reclose
Recommendation:
A/R at BTPS end to be made operational within one month
KPCL A/R at BTPS end will be danbled
during November, 2014End and needs
LC
1) A/R for 220kV lines enabled already.
2) Shut down of lines availed to commission the
auto reclosing scheme for 400kV lines at BTPS.
3) A/R shall be enabled in next shut down
35/I/2 1 220 kV KAIGA –
KODASALLY an
220kV Kodasalli -
Nagjheri line
19-07-2014 220kV Kaiga-Kodasalli line
tripped on operation of over
current protection.
It was also reported that 220 kV
Kodasalli-Nagjheri line had
tripped due to fault.
From D.R of KAIGA station it
was observed that the fault
persisted for around 340 ms.
Recommendations:
a) KPCL was requested to send the detailed tripping analysis
report to SRLDC and SRPC.
b) The utilities are requested to send the single Line Diagram / Lay
out plan of the affected Substation/ System.
c) KPTCL /KPCL to review the SOTF settings for Kodasalli –
Nagjheri lines.
d) Resistive reach of the distance relay shall be reviewed to take
care of the high resistance fault.
KPCL (i) As per the proceeds of the PSAG-10
relays will be replaced. Temporarily
aranged.
(ii) SOTF setting already reviewed.
(iii) Resistive reach is calculated and
will be uploaded in the seond week of
Dec.2014.
i) Relays were replaced and wired up. testing &
commissioning shall be completed with the
assistance of KPTCL by last week of , 2015.
ii) Completed.
Iii)Completed
38/GD/3.
5
5 GD-1 at Kadra and
Kodasalli hydro power
station
13-11-2014 at
19:31hrs
A fault had occurred in 220 kV
Kadra and
Kodasalli. As A result, de-
energization of
220kV bus occurred at Kadra and
Kodasalli.
Recommendations & follow up:
Numerical Distance
Protection relay in Kadra –Kaiga and Kodasalli –Kaiga.
status of PSAG-10
recommendations within a week’s time.
KPCL All the recommendations of PSAG - 10 are
completed except the following pending issue:
i)e-NIT floated on 28.07.2014 for procurement of
Numerical distance relays & GPS. Bid evaluation
is under progress. The work will be completed by
December - 2015. Hower, as per the
recommendations of PSAG, Relays were
temporarily rearranged, replaced and wired up.
testing & commissioning shall be completed with
the assistance of KPTCL by last week of march,
2015.
KARNATAKA - KPCL
Annexure-V
![Page 12: SOUTHERN REGIONAL POWER COMMITTEE - … · A Special Meeting was held on 06th March 2015 in Southern Regional Power Committee, ... LBB protection got operated which in turn tripped](https://reader030.vdocument.in/reader030/viewer/2022020303/5b84b0237f8b9ae5498cd0db/html5/thumbnails/12.jpg)
Annexure-VI
![Page 13: SOUTHERN REGIONAL POWER COMMITTEE - … · A Special Meeting was held on 06th March 2015 in Southern Regional Power Committee, ... LBB protection got operated which in turn tripped](https://reader030.vdocument.in/reader030/viewer/2022020303/5b84b0237f8b9ae5498cd0db/html5/thumbnails/13.jpg)
Annexure-VI
![Page 14: SOUTHERN REGIONAL POWER COMMITTEE - … · A Special Meeting was held on 06th March 2015 in Southern Regional Power Committee, ... LBB protection got operated which in turn tripped](https://reader030.vdocument.in/reader030/viewer/2022020303/5b84b0237f8b9ae5498cd0db/html5/thumbnails/14.jpg)
Annexure-VI
![Page 15: SOUTHERN REGIONAL POWER COMMITTEE - … · A Special Meeting was held on 06th March 2015 in Southern Regional Power Committee, ... LBB protection got operated which in turn tripped](https://reader030.vdocument.in/reader030/viewer/2022020303/5b84b0237f8b9ae5498cd0db/html5/thumbnails/15.jpg)
Annexure-VI
![Page 16: SOUTHERN REGIONAL POWER COMMITTEE - … · A Special Meeting was held on 06th March 2015 in Southern Regional Power Committee, ... LBB protection got operated which in turn tripped](https://reader030.vdocument.in/reader030/viewer/2022020303/5b84b0237f8b9ae5498cd0db/html5/thumbnails/16.jpg)