srp f91.pdf

62
SRP‟s Experience with P91 Piping Mike Rutledge August 10, 2009 John Alice, Metallurgist

Upload: ryan-welsh

Post on 25-Dec-2015

58 views

Category:

Documents


5 download

TRANSCRIPT

Page 1: SRP F91.pdf

SRP‟s Experience with P91 Piping

Mike Rutledge

August 10, 2009

John Alice, Metallurgist

Page 2: SRP F91.pdf

SRP (Salt River Project)

Supplier of Water & Power to Phoenix, AZ

Summer Load 2009, ~6500 MW

Resource Mix with P91:

1 Coal Plant, 400MW (scheduled to go commercial Dec. „09)

3 Combined Cycle Plants Desert Basin, 2X1, 600 MW

Kyrene, 1X1, 250 MW

Santan, 2X1 & 1X1, 860 MW

Page 3: SRP F91.pdf

Inspection LocationsShop and Field weldsFittingsTerminal points such as header

connections, valve connections, turbine connectionsDissimilar metal welds (P91 to P22 and

Cr-Mo-V) Areas of personnel trafficAs part of our HEP Inspection Program

Page 4: SRP F91.pdf

Inspection Methods for P91

Wet Fluorescent Magnetic Particle

Shear wave ultrasonics and radiography of

indications

Hardness

Surface replication at dissimilar metal

welds (DMW‟s) and „soft areas‟

Page 5: SRP F91.pdf

First P91 Inspection at SRP -

Desert Basin in March 2006

Desert Basin began operation in 2001

SRP purchased in 2003 from Reliant

2 SW 501FD2 CT‟s

2 NEM HRSG‟s

1 GE steam turbine

AE – Black and Veatch/Zachary

Page 6: SRP F91.pdf

March 2006

Main steam induction bend and reducer leading into north CMSV was unusually soft (140‟s HB).

Page 7: SRP F91.pdf

March 2006 Summary

Three MS induction bends - soft

One MS reducer -soft

Four sections of HRH pipe - soft

Page 8: SRP F91.pdf

October 2006

Replaced north soft main steam bend. (Rechecked north main steam induction

bend during the Summer of 2006. Found no change.)

Rechecked the south main steam bend. Confirmed still acceptable.

Checked more main steam induction bends & other P91 pipe.

Page 9: SRP F91.pdf

October 2006

Found two more soft main steam induction bends (140‟s HB).

Page 10: SRP F91.pdf

October 2006

Found four sections of hot reheat pipe to be soft

(150‟s HB)

Page 11: SRP F91.pdf

April 2007

◦ HRH induction bend had mid-span soft areas

◦ HRH induction bend low hardness at welds One of these welds had 3 -1” long linear indications

Ultimately determined to have significant subsurface depth

Welds ground out and redone

Page 12: SRP F91.pdf

March 2008

The section of pipe upstream of the Unit 1 main isolation valve was “soft”, including the drip leg.

Page 13: SRP F91.pdf

March 2008

The pressure equalization valves (F22) connected to the main steam isolation valve (C12A)

contained stainless steel piping and fittings (316/316L), which is undesirable in cycling service.

Page 14: SRP F91.pdf

March 2008

These two soft main steam induction bends found during the October 2006 inspection were replaced.

Page 15: SRP F91.pdf

October 2008

Three hard welds (>300HB) were found in the 10” diameter piping leading into the HP steam turbine bypass valves. They were PWHT‟d to reduce the hardness to <280HB.

Page 16: SRP F91.pdf

October 2008

Cracks were found at the toe of the saddle

weld connecting the trunnion to the main

steam pipe all around the weld on the pipe

side. This condition was found at both units.

Page 17: SRP F91.pdf

October 2008

One soft MS induction bend was found, about

140-180 HB.

Page 18: SRP F91.pdf

October 2008

Damage caused by alignment/

fit-up lugs.

Page 19: SRP F91.pdf

October 2008

A section of small diameter pipe that appeared to serve no purpose was found. In addition, it was P22 and

determined to have inadequate wall thickness. It was removed. The penetrations were replaced with RT plugs.

HP bypass valve

Page 20: SRP F91.pdf

HOT REHEAT

MAIN ISOLATION

VALVE LEAK

The crack was at

the 6 o‟clock

position and

extended from the

weld into the base

metal of the

pressure equalizer

piping.

November 2008

Page 21: SRP F91.pdf

Kyrene Unit 7 in May 2006

K7 began operation in late 2002

1 GE 7FA+e CT

1 Alstom HRSG

1 GE steam turbine

AE – Stanley Consultants

TIC – on site welding

Page 22: SRP F91.pdf

May 2006

Four small elbows at the outlet of the HP

Superheat were soft (140‟s HB).

400X

Page 23: SRP F91.pdf

May 2006

Hot reheat transition

piece from Alstom

(P22) to Stanley

(P91) was seam

welded P91.

B9-DMW

Page 24: SRP F91.pdf

May 2006

A reducer, pup piece and elbow of the main steam piping was soft (140‟s HB).

400X

Page 25: SRP F91.pdf

May 2006

Main steam transition piece welded to

MSSV was seam welded P91.

400X

Page 26: SRP F91.pdf

May 2006

Cracked 18”x14” weldolet of the hot reheat system. Mechanism was creep cavitation in the Type IV zone.

Page 27: SRP F91.pdf

May 2007

HP Steam Bypass Valve

P22 P91

Outlet Weld is a B9 DMW (P91-P22)

Page 28: SRP F91.pdf

May 2007

HP Steam Bypass Valve

Internal videoprobe inspection of outlet weld revealed thermal

fatigue cracks along the downstream weld toe.

Downstream-P22

Downstream-P22

Page 29: SRP F91.pdf

October 2007

HP Steam Bypass Valve

Outlet weld

Outlet Weld is a B9 DMW (P91-P22)

Flow

P22 P91

Page 30: SRP F91.pdf

October 2007

HP Steam Bypass Valve -replacedUpstream counterbore-P91

Downstream-P22

Internal videoprobe inspection of

outlet weld revealed thermal

fatigue cracks along counterbore

and weld toe.

Page 31: SRP F91.pdf

October 2007

HP Steam Bypass Valve -replaced

Mounted section from 12 o’clock

position

Mounted section from 6 o’clock

position

Page 32: SRP F91.pdf

October 2007

Hot Reheat “Transition Piece” Piping

HRSG P22 pipe

B9-DMWThe plate was

verified to be

Grade 91

material, but

the weld metal

was straight

9Cr – 1Mo (no

V or Nb).

Page 33: SRP F91.pdf

October 2007

Main Steam “Transition Piece” Piping

The plate was

verified to be

Grade 91

material, but

the weld metal

was straight

9Cr – 1Mo (no

V or Nb).

Page 34: SRP F91.pdf

February 2007

Hot Reheat Steam Bypass Valve

Page 35: SRP F91.pdf

February 2007

Hot Reheat Steam Bypass Valve

Page 36: SRP F91.pdf

Santan Units in December 2006

Santan new units began operation in

2005.

3 GE 7FA+e CT‟s

3 Alstom HRSG‟s

2 GE steam turbine

AE - Sargent & Lundy

Page 37: SRP F91.pdf

December 2006

High Press Superheat – one tee soft only on west side, three elbows marginally soft.

Page 38: SRP F91.pdf

December 2006

Reheat Steam – two center tees soft.

400X

Page 39: SRP F91.pdf

December 2006

Two main steam elbows soft.

Elbow microstructure, 400X

Page 40: SRP F91.pdf

December 2006

One weld soft on one side suggests problems during PWHT.

Page 41: SRP F91.pdf

October 2007

◦ 4 MS fittings;

1 elbow, 2 tees, 1 reducer - soft

◦ MS Flow element leak.

DMW issue.

Repaired and ultimately replaced.

Page 42: SRP F91.pdf

October 2007

Unit 5A flow element

Page 43: SRP F91.pdf

September 2007

The discolored (overcooked) fitting just below the HP turbine shell was found to be hard, which suggests it

was heated to above the lower critical temperature during postweld heat treatment.

Page 44: SRP F91.pdf

September 2007

316HSS

Inconel weld

Inconel weld

P91

P91

The flow element consists of an unusual combination of materials, that is, P91 welded

to 316HSS using Inconel filler.

Page 45: SRP F91.pdf

September 2007

The LP steam bypass valve outlet weld showed some erosion from the attemperator spray and

some crack – like linear indications along the counterbore and upstream weld toe.

Page 46: SRP F91.pdf

September 2007

The hot reheat steam bypass valve was replaced because of thermal

fatigue cracking in the outlet weld.

Page 47: SRP F91.pdf

May 2008

◦ HP/MS; 2 spool pieces, 2 elbows, 1 tee – soft

Page 48: SRP F91.pdf

May 2008

P91

P91P91Inconel Inconel

316SS

Main steam flow element

(316SS) joined to P91 with

Inconel.

Page 49: SRP F91.pdf

May 2008

HR Bypass Valve

Crack on the OD at the

weld toe

Page 50: SRP F91.pdf

May 2008

HR Bypass Valve Samples

Page 51: SRP F91.pdf

April 2008

The non-return valves are large castings and were found to

have low hardness, less than 170HB. The microstructure is

not typical of a casting.

Typical microstructure, 400X

Page 52: SRP F91.pdf

April 2008

The two short pup pieces just downstream of

the non-return valve at Unit 5A were very soft,

on the east side. The microstructure

consisted of ferrite and carbides.

Typical microstructure, 400X

Page 53: SRP F91.pdf

April 2008

The hardness of the stop valves was non-uniform

and ranged from 150 – 210HB. The microstructure

exhibited undesirable features, including some

delta ferrite.

Typical microstructure, 400X

Page 54: SRP F91.pdf

April 2008

The main steam elbows at Unit 5B

between welds W5 and W6 and welds W9

and W10 were soft, less than 160HB, on

the north side only. Their

microstructures were consistent with

degraded material.

For the common piping leading to the

turbine, the large tee between welds W12

and W13 was found to be soft, less than

175HB, on the east side only.

Page 55: SRP F91.pdf

SRP Outage Summaries

2006-2009 11 Outages

68 Findings (soft, weld metal issue, crack, etc.)

16 Repair/Replace Actions Needed

AVERAGES

◦ +6 Findings per Outage

◦ ~1.5 Repair/Replace Actions Needed

Page 56: SRP F91.pdf

Unresolved Issues Hardness Testing – suitable devices, surface prep, what

locations, how many readings ?? Some kind of protocol is needed. What do we do with components with marginal hardness ? Soft areas ??

Surface replication good enough ?? different methods or techniques?

Scoop samples ? Boat samples ? Devices ??

What is the expected lives of anomalous microstructures ?

What properties do we assume for expected life estimates ??

Should we hold the piping suppliers responsible for the replacement of soft pipe ?? Or, should we require them to prove that the component is fit for long term service by analysis ??

Etc.

Page 57: SRP F91.pdf

Specific Concerns

Fittings such as, elbows, tees, wyes, laterals, and reducers may not be heat treated properly and may not meet the ASME/ASTM requirements. There are no Code Police.

Welds can be pwht‟d improperly.

Large Weld-o-let‟s can be susceptible to Type IV cracking.

ASTM‟s do not have any minimum hardness limits. Codes are not enough!

Spool piece drawings needed to locate shop welds and any seam welded fittings...these are sometimes hard to come by.

Steam turbine bypass valves are particularly vulnerable to thermal fatigue cracking. Retrofitting with a liner is required for reliable operation.

Etc.

Page 58: SRP F91.pdf

Actions

P91 requires close surveillance during all phases of fabrication and construction to avoid problems. QC of all new materials is critical. Don‟t trust the supplier.

Component suppliers and fabricators must themselves possess, or must have access to detailed metallurgical expertise and experience to deal effectively with these materials.

Anomalous microstructures can be very difficult to interpret. Atlas of microstructures is needed and correlated with hardness.

Detailed purchasing specifications need to be developed and followed.

Etc.

Page 59: SRP F91.pdf

P-91 Remediation

If there‟s an issue:

◦ Can you leave it alone?

◦ Can you remove/replace now or later?

Page 60: SRP F91.pdf

P-91 Remediation

How do you answer these questions?

◦ Stress/creep life analysis

◦ Hanger inspection/evaluation

◦ Material availability

Page 61: SRP F91.pdf

P-91 Remediation

Long Term?

◦ Maintain a diligent inspection program

◦ Industry Forums

◦ EPRI/SI

“Life Management of Creep Strength Enhanced

Ferritic Steels-Solutions for the Performance of

Grade P-91 Steel” (CSEF)

Material Integrity

Life Management

Kicked off 11/07

Page 62: SRP F91.pdf

Finally…

Are we inspecting enough before a failure occurs ??

Long term performance and experience with P91 in power plant service needs to be shared.

Remember:

◦ Code compliant is not necessarily good enough.

◦ Monitor, monitor, monitor!!!