state l university 3 rd edition applied management science for decision making, 2e © 2014 pearson...
TRANSCRIPT
STATE l UNIVERSITY
3rd EDITION
Applied Management Science for Decision Making, 2e © 2014 Pearson Learning Solutions Philip A. Vaccaro , PhD
Multiple ChoiceMultiple Choice
1. Intermittent flow operations: a. involve close management of workers. b. generate a high product mix. c. have few schedule changes.have few schedule changes. d. have high turnovers of raw materials and work-in-process inventories.
2. Continuous flow operations:
a. utilize general-purpose equipment.utilize general-purpose equipment. b. are capital-intensive operations. c. have unpredictable material flows. d. have work centers grouped together by function ( department ).
Multiple ChoiceMultiple Choice
3. Repetitive manufacturing:
a. assembles pre-made parts into finished goods. b. produces one basic product with minor variations. c. Is characterized by very low equipment utilization.Is characterized by very low equipment utilization. d. utilizes highly trained, flexible labor.
4. Design capacity is:
a. sustainable capacity.sustainable capacity. b. capacity dictated by the firm’s built-in organizational constraints. c. theoretical capacity. d. actual output.
Multiple ChoiceMultiple Choice
5. The stepping-stone method is used to:
a. obtain an initial ( 1st ) solution. b. balance source supply and destination demand. c. evaluate occupied cells ( routes ) for possible costevaluate occupied cells ( routes ) for possible cost reductions.reductions. d. evaluate empty cells ( routes ) for possible cost reductions.
6. Which of the following statements is true?
a. evaluation paths selected must be as short as possible. b. evaluation paths may contain diagonal movements. c. occupied cells may not be bypassed if turning move-occupied cells may not be bypassed if turning move- ments are desired.ments are desired. d. all occupied cells of each solution must be evaluated.
Multiple ChoiceMultiple Choice
7. The intent of the load-distance model is:
a. to minimize the number of workers. b. to minimize idle time per cycle. c. to minimize materials and/or information movementto minimize materials and/or information movement costs within a process layout.costs within a process layout. d. none of the above.d. none of the above.
8. Which of the statements about line-balancing is true?
a. if a precedence relationship exists between tasks A and B, they cannot be assigned to the same work station. b. if a line’s balance delay factor is maximized, its efficiencyif a line’s balance delay factor is maximized, its efficiency is maximized.is maximized. c. the theoretical minimum number of work stations can never be achieved, hence the name “theoretical”. d. if the cycle time is reduced, productivity will increase.
Multiple ChoiceMultiple Choice
9. Hybrid or combination layouts:
a. were developed by Henry Gantt in 1901.were developed by Henry Gantt in 1901. b. require the use of work-in-process inventories between the pure layouts. c. are similar in their characteristics to fixed-position layouts. d. are rarely encountered in industry.
10. Which of the following statements is true?
a. line-balancing attempts to eliminate bottleneck tasks via product redesign and better worker training. b. the efficiency of an assembly line cannot be improved by selecting a different task assignment heuristic for the line-balancing process. c. an assembly line is perfectly balanced when there are an equal number of tasks in each work station. d. “efficiency” is defined as an assembly line’s ability to meet “efficiency” is defined as an assembly line’s ability to meet desired daily output.desired daily output.
Multiple ChoiceMultiple Choice
11. The Behavioral School approach to job design which attempts to make a worker a “co-manager” is:
a. job enlargement.job enlargement. b. b. job enhancement. c. c. job rotation. d. job enrichment.
12.12. The 5 categories of activities ( operation, transportation, inspection, delay, and storage ) are used in which of the following methods of process analysis?
a. a. gang chart. b. b. simo chart. c. multiple activity chart.c. multiple activity chart. d. d. motion economy chart.
Multiple ChoiceMultiple Choice
13. The procedure that involves performance ratings and allowance factors is :
a. historical experience.historical experience. b. work sampling. c. direct time study. d. pre-determined time study.
True or FalseTrue or False
14. In cross-docking, labeled and presorted loads are received directly at the warehouse dock for immediate re-routing.
TRUETRUE FALSE
15. A job shop helps a firm follow a differentiation marketing strategy.
TRUETRUE FALSE
16. Group technology layouts are used to convert assembly lines into job shops.
TRUE TRUE FALSE
True or FalseTrue or False
17.17. The Northwest-Corner technique produces a deliberate cost- efficient solution for the transportation algorithm.
TRUE FALSEFALSE
18.18. Work sampling is widely used to analyze repetitive jobs.
TRUE TRUE FALSE
19.19. The maximum allowable cycle time guarantees that the firm will meet its daily production quota.
TRUETRUE FALSEFALSE
True or FalseTrue or False
20. The direct time study method makes allowances for unscheduled interruptions, unusual delays, and unusual mistakes on the part of the worker.
TRUE FALSEFALSE
21. In the transportation problem, the number of cells in an evalua- tion path should always be an odd number such as “5”, ”7”, or “9”.
TRUETRUE FALSE
22. One of the limitations of the transportation algorithm is that it cannot minimize shipping costs between two levels of the supply chain.
TRUETRUE FALSE
True or FalseTrue or False Nine ( 9 ) welders who perform the identical short-cycle job were observed by a time and motion engineer over six ( 6 ) cycles each. The total time recorded was three-hundred-ten ( 310 ) minutes. The performance rating for a particular welder was established at ninety-two percent ( 92% ). Additionally, each welder is granted a twelve percent ( 12% ) allowance for personal needs, fatigue, and routine delays.
23. The observed time ( OT ) for this job is 5.833 minutes. TRUETRUE FALSE
24. The normal time ( NT ) for the selected welder ≈ 5.280 minutes. TRUE FALSEFALSE
25. The standard time ( ST ) for the selected welder ≈ 6.000 minutes.
TRUE FALSEFALSE
True or FalseTrue or False Nine ( 9 ) welders who perform the identical short-cycle job were observed by a time and motion engineer over six ( 6 ) cycles each. The total time recorded was three-hundred-ten ( 310 ) minutes. The performance rating for a particular welder was established at ninety-two percent ( 92% ). Additionally, each welder is granted a twelve percent ( 12% ) allowance for personal needs, fatigue, and routine delays.
observed time ( OT ) = 310 / ( 9 x 6 ) = 5.7407
normal time ( NT ) = 5.7407 x .92 = 5.2814
standard time ( ST ) = 5.284 / ( 1 - .12 ) = 6.0045
Assembly Line Balancing ProblemAssembly Line Balancing Problem
A firm desires to achieve a production rate of seventy-five ( 75 ) units per six ( 6 ) hour day, utilizing an assembly line. The table below lists the nine ( 9 ) tasks that must be performed to produce each unit as well as the sequence in which they must be performed.
Problem 1
Assembly Line Balancing ProblemAssembly Line Balancing Problem
Task Predecessor ( s ) Time ( in seconds )
A none 60
B A 60
C A 120
D C 60
E C 180
F C 60
G D,E,F 60
H B 120
I G,H 60
Assembly Line Balancing ProblemAssembly Line Balancing ProblemFor your convenience, a precedence relationship ( s ) diagram has beenincluded below. The tasks are shown as nodes. The sequence require-ments are shown by arrows. The required standard task times are shownwithin each task’s respective node:
A60
B60
C120
D60
E180
F60
H120
I60
G60
Assembly Line Balancing ProblemAssembly Line Balancing Problem
REQUIREMENT:
A. The maximum allowable cycle time.
B. The theoretical minimum number of work stations.
C. The balanced assembly line under the longest operating time ( LOT ) assignment heuristic.
D. The balance delay factor of the assembly line.
E. The efficiency of the assembly line.
Problem 1
Assembly Line Balancing ProblemAssembly Line Balancing Problem
MaximumAllowable
Cycle Time=
Total available production time
Daily production quota
= 6 hours x 60 x 60
75 units
= 21,600 seconds
75 units
= 288 seconds
Multiple ChoiceMultiple Choice
26. In problem one, the maximum allowable cycle time is:
a. 288 seconds.288 seconds. b. 315 seconds. c. 348 seconds. d. 384 seconds.
Assembly Line Balancing ProblemAssembly Line Balancing Problem
TheoreticalMinimum
Number ofWork Stations
=Total time to produce one unit
Maximum allowable cycle time
=780 seconds
288 seconds= 2.7083 ≈ 3
Multiple ChoiceMultiple Choice
27. In problem one, the theoretical number of work stations is:
a. 11 b. 2 c. 3 d. 4
Assembly Line Balancing ProblemAssembly Line Balancing Problem
A60
B60
C120
D60
E180
F60
H120
I60
G60
CANDIDATE(S) FOR TASK 1 IN STATION 1
Assembly Line Balancing ProblemAssembly Line Balancing Problem
Cycle time
288
seconds
288
seconds
288
seconds
864
seconds
Station
1
Station
2
Station
3
Total
A (60)
Production Time
Idle Time
Balancing under the LOT assignment heuristicBalancing under the LOT assignment heuristic
Assembly Line Balancing ProblemAssembly Line Balancing Problem
A60
B60
C120
D60
E180
F60
H120
I60
G60
CANDIDATE(S) FOR TASK 2 IN STATION 1
XX
Assembly Line Balancing ProblemAssembly Line Balancing Problem
Cycle time
288
seconds
288
seconds
288
seconds
864
seconds
Station
1
Station
2
Station
3
Total
A (60)
C (120)
Production Time
Idle Time
Balancing under the LOT assignment heuristic
Assembly Line Balancing ProblemAssembly Line Balancing Problem
A60
B60
C120
D60
E180
F60
H120
I60
G60
CANDIDATE(S) FOR TASK 3 IN STATION 1
XXXX
Assembly Line Balancing ProblemAssembly Line Balancing Problem
Cycle time
288
seconds
288
seconds
288
seconds
864
seconds
Station
1
Station
2
Station
3
Total
A (60)
C (120)
B (60)
Production Time 240
Idle Time 48
Balancing under the LOT assignment heuristic
Assembly Line Balancing ProblemAssembly Line Balancing Problem
A60
B60
C120
D60
E180
F60
H120
I60
G60
CANDIDATE(S) FOR TASK 1 IN STATION 2
XX
XX
XX
Assembly Line Balancing ProblemAssembly Line Balancing Problem
Cycle time
288
seconds
288
seconds
288
seconds
864
seconds
Station
1
Station
2
Station
3
Total
A (60) E (180)
C (120)
B (60)
Production Time 240Idle Time 48
Balancing under the LOT assignment heuristic
Assembly Line Balancing ProblemAssembly Line Balancing Problem
A60
B60
C120
D60
E180
F60
H120
I60
G60
CANDIDATE(S) FOR TASK 2 IN STATION 2
XX
XX
XX XX
Assembly Line Balancing ProblemAssembly Line Balancing Problem
Cycle time
288
seconds
288
seconds
288
seconds
864
seconds
Station
1
Station
2
Station
3
Total
A (60) E (180)
C (120) D (60) D (60)
B (60)
Production Time 240 240240Idle Time 48 4848
Balancing under the LOT assignment heuristic
Assembly Line Balancing ProblemAssembly Line Balancing Problem
A60
B60
C120
D60
E180
F60
H120
I60
G60
CANDIDATE(S) FOR TASK 1 IN STATION 3
XX
XX
XXXX
XX
Assembly Line Balancing ProblemAssembly Line Balancing Problem
Cycle time
288
seconds
288
seconds
288
seconds
864
seconds
Station
1
Station
2
Station
3
Total
A (60) E (180) H (120)
C (120) D (60) D (60)
B (60)
Production Time 240 240240Idle Time 48 4848
Balancing under the LOT assignment heuristic
Assembly Line Balancing ProblemAssembly Line Balancing Problem
A60
B60
C120
D60
E180
F60
H120
I60
G60
CANDIDATE(S) FOR TASK 2 IN STATION 3
XXXX
XXXX
XX
XX
Assembly Line Balancing ProblemAssembly Line Balancing Problem
Cycle time
288
seconds
288
seconds
288
seconds
864
seconds
Station
1
Station
2
Station
3
Total
A (60) E (180) H (120)
C (120) D (60) D (60) F (60)
B (60)
Production Time 240240 240240Idle Time 48 4848
Balancing under the LOT assignment heuristic
Assembly Line Balancing ProblemAssembly Line Balancing Problem
A60
B60
C120
D60
E180
F60
H120
I60
G60
CANDIDATE(S) FOR TASK 3 IN STATION 3
XX
XX
XXXX
XX
XX
XX
Assembly Line Balancing ProblemAssembly Line Balancing Problem
Cycle time
288
seconds
288
seconds
288
seconds
864
seconds
Station
1
Station
2
Station
3
Total
A (60) E (180) H (120)
C (120) D (60) D (60) F (60)
B (60) G (60)
Production Time 240240 240240 240240Idle Time 48 4848 4848
Balancing under the LOT assignment heuristic
Assembly Line Balancing ProblemAssembly Line Balancing Problem
A60
B60
C120
D60
E180
F60
H120
I60
G60
CANDIDATE(S) FOR TASK 1 IN STATION 4
XX
XX
XX
XX
XX
XX
XX
XX
Assembly Line Balancing ProblemAssembly Line Balancing Problem
Cycle time
288
seconds
288
seconds
288
seconds
288
seconds
1,152
seconds
Station
1
Station
2
Station
3
Station
4
Total
A (60) E (180) H (120) I (60)
C (120) D (60) D (60) F (60)
B (60)
G (60)
Production Time
240 240 240 60 780
Idle Time 48 4848 4848 228228 372
Balancing under the LOT assignment heuristic
Assembly Line Balancing ProblemAssembly Line Balancing Problem
Cycle time
288
seconds
288
seconds
288
seconds
288
seconds
1,152
seconds
Station
1
Station
2
Station
3
Station
4
Total
A (60) E (180) H (120) I (60)
C (120) F (60) F (60) D (60)
B (60)
G (60)
Production Time
240 240 240 60 780
Idle Time 48 4848 4848 228228 372
Balancing under the LOT assignment heuristic
2nd SOLUTION
Assembly LineAssembly Line Balancing Problem Balancing Problem
LineEfficiency =
240 sec + 240 sec + 240 sec + 60 sec
288 sec x 4 stations
= 780 seconds
1,152 seconds
= 67.71%
Multiple ChoiceMultiple Choice
28. In problem one, the efficiency of the assembly line is:
a. 64%64% b. 68% c. 70% d. 72%
Assembly LineAssembly Line Balancing Problem Balancing Problem
BalanceDelayFactor
=48 sec + 48 sec + 48 sec + 228 sec
288 sec x 4 stations
= 372 seconds
1,152 seconds
= 32.29%
Multiple ChoiceMultiple Choice
29. In problem one, the balance delay factor is:
a. 28%28% b. 30% c. 32% d. 36%
Multiple ChoiceMultiple Choice
30. In problem one, the tasks assigned to work station ‘one’ are:
a. A,CA,C b. A,C,E c. A,C,D d. none of the above.
Assembly Line Balancing ProblemAssembly Line Balancing Problem
Cycle time
288
seconds
288
seconds
288
seconds
864
seconds
Station
1
Station
2
Station
3
Total
A (60)
C (120)
B (60)
Production Time 240
Idle Time 48
Balancing under the LOT assignment heuristic
Multiple ChoiceMultiple Choice
31. In problem one, the tasks assigned to work station ‘two’ are:
a. E,DE,D b. E,F c. E,D or E,F d. F,B,H,D
Assembly Line Balancing ProblemAssembly Line Balancing Problem
Cycle time
288
seconds
288
seconds
288
seconds
864
seconds
Station
1
Station
2
Station
3
Total
A (60) E (180)
C (120) D (60) D (60)
B (60)
Production Time 240 240240Idle Time 48 4848
Balancing under the LOT assignment heuristic
Assembly Line Balancing ProblemAssembly Line Balancing Problem
Cycle time
288
seconds
288
seconds
288
seconds
288
seconds
1,152
seconds
Station
1
Station
2
Station
3
Station
4
Total
A (60) E (180) H (120) I (60)
C (120) F (60) F (60) D (60)
B (60)
G (60)
Production Time
240 240 240 60 780
Idle Time 48 4848 4848 228228 372
Balancing under the LOT assignment heuristic
2nd SOLUTION
Transportation ProblemTransportation Problem
WAREHOUSE
1
WAREHOUSE
2
WAREHOUSE
3
WAREHOUSE
4
PLANT
AVAILABILITY
PLANT APLANT A 50
PLANT BPLANT B 30
PLANT CPLANT C 70
WAREHOUSE
DEMAND30 60 20 40
$19$19 $22$22 $25$25 $17$17
$24$24 $21$21 $19$19 $21$21
$29$29 $16$16 $21$21 $26$26
150
150
2020
3030
1010 2020 4040
3030
FROM
TOProblem 2
Transportation ProblemTransportation Problem
REQUIREMENT:
Evaluate the empty cells via the stepping-stone technique.
a. A-3b. B-1c. B-3
1. Do not attempt to evaluate any other empty cells2. Do not attempt a transfer operation3. Show all supporting calculations via “T” accounts
Problem 2
Transportation ProblemTransportation Problem
WAREHOUSE
1
WAREHOUSE
2
WAREHOUSE
3
WAREHOUSE
4
PLANT
AVAILABILITY
PLANT APLANT A 50
PLANT BPLANT B 30
PLANT CPLANT C 70
WAREHOUSE
DEMAND30 60 20 40
$19$19 $22$22 $25$25 $17$17
$24$24 $21$21 $19$19 $21$21
$29$29 $16$16 $21$21 $26$26
150
150
2020
3030
1010 2020 4040
3030
FROM
TO
EVALUATE EMPTY CELL A-3
+
+
-
-
Transportation ProblemTransportation ProblemEVALUATE EMPTY ROUTE A-3
A3 + $25 C3 - $21
C2 + $16 A2 - $22
+ $41 - $43
- $ 2
GROSSINCREASE
GROSSDECREASE
NET DECREASE
Multiple ChoiceMultiple Choice
32. In problem two, the evaluation number for empty cell ‘A-3’ is:
a. - 4- 4 b. + 4 c. -10 d. +10 e. none of the above.
Transportation ProblemTransportation Problem
WAREHOUSE
1
WAREHOUSE
2
WAREHOUSE
3
WAREHOUSE
4
PLANT
AVAILABILITY
PLANT APLANT A 50
PLANT BPLANT B 30
PLANT CPLANT C 70
WAREHOUSE
DEMAND30 60 20 40
$19$19 $22$22 $25$25 $17$17
$24$24 $21$21 $19$19 $21$21
$29$29 $16$16 $21$21 $26$26
150
150
2020
3030
1010 2020 4040
3030
FROM
TO
EVALUATE EMPTY CELL B-1
+
+
-
-
Transportation ProblemTransportation ProblemEVALUATE EMPTY ROUTE B-1
B1 + $24 A1 - $19
A2 + $22 B2 - $21
+ $46 - $40
+ $ 6
GROSSINCREASE
GROSSDECREASE
NET INCREASE
Multiple ChoiceMultiple Choice
33. In problem two, the evaluation number for empty cell ‘B-1’ is:
a. - 9- 9 b. + 9 c. - 7 d. + 7 e. none of the above.
Transportation ProblemTransportation Problem
WAREHOUSE
1
WAREHOUSE
2
WAREHOUSE
3
WAREHOUSE
4
PLANT
AVAILABILITY
PLANT APLANT A 50
PLANT BPLANT B 30
PLANT CPLANT C 70
WAREHOUSE
DEMAND30 60 20 40
$19$19 $22$22 $25$25 $17$17
$24$24 $21$21 $19$19 $21$21
$29$29 $16$16 $21$21 $26$26
150
150
2020
3030
1010 2020 4040
3030
FROM
TO
EVALUATE EMPTY CELL B-3
+
+ -
-
Transportation ProblemTransportation ProblemEVALUATE EMPTY ROUTE B-3
B3 + $19 C3 - $21
C2 + $16 B2 - $21
+ $35 - $42
- $ 7
GROSSINCREASE
GROSSDECREASE
NET DECREASE
Multiple ChoiceMultiple Choice
34. In problem two, the evaluation number for empty cell ‘B-3’ is:
a. - 4- 4 b. + 4 c. - 3 d. + 3 e. none of the above.
Transfer Operation ProblemTransfer Operation Problem
WAREHOUSE
1
WAREHOUSE
2
WAREHOUSE
3
WAREHOUSE
4
PLANT
AVAILABILITY
PLANT APLANT A 50
PLANT BPLANT B 30
PLANT CPLANT C 70
WAREHOUSE
DEMAND30 60 20 40
$19$19 $22$22 $25$25 $17$17
$24$24 $21$21 $19$19 $21$21
$29$29 $16$16 $21$21 $26$26
150
150
2020
3030
1010 2020 4040
3030
FROM
TO
Given the followingGiven the following transportation algorithm intermediate solution::
Problem 3
Transfer Operation ProblemTransfer Operation Problem
REQUIREMENT:
1. Perform a transfer operation on empty cell A-4.2. What are the new allocations for A-4’s evaluation path?
DO NOT COMPUTE THE NEXT INTERMEDIATE SOLUTION OR ITS COSTS
Problem 3
Transfer Operation ProblemTransfer Operation Problem
WAREHOUSE
1
WAREHOUSE
2
WAREHOUSE
3
WAREHOUSE
4
PLANT
AVAILABILITY
PLANT APLANT A 50
PLANT BPLANT B 30
PLANT CPLANT C 70
WAREHOUSE
DEMAND30 60 20 40
$19$19 $22$22 $25$25 $17$17
$24$24 $21$21 $19$19 $21$21
$29$29 $16$16 $21$21 $26$26
150
150
2020
3030
1010 2020 4040
3030
FROM
TO
CELL A - 4 TRANSFER OPERATION
+
+
-
-
Multiple ChoiceMultiple Choice
35. In problem three, the evaluation number for empty cell ‘A-4’ is:
a. + 2+ 2 b. - 32 c. + 15 d. - 15 e. none of the above.
Transfer Operation ProblemTransfer Operation Problem
WAREHOUSE
1
WAREHOUSE
2
WAREHOUSE
3
WAREHOUSE
4
PLANT
AVAILABILITY
PLANT APLANT A 50
PLANT BPLANT B 30
PLANT CPLANT C 70
WAREHOUSE
DEMAND30 60 20 40
$19$19 $22$22 $25$25 $17$17
$24$24 $21$21 $19$19 $21$21
$29$29 $16$16 $21$21 $26$26
150
150
2020
3030
3030 2020 2020
3030
FROM
TO
CELL A - 4 TRANSFER OPERATION
+
+
-
-
Transfer Operation ProblemTransfer Operation Problem
WAREHOUSE
1
WAREHOUSE
2
WAREHOUSE
3
WAREHOUSE
4
PLANT
AVAILABILITY
PLANT APLANT A 50
PLANT BPLANT B 30
PLANT CPLANT C 70
WAREHOUSE
DEMAND30 60 20 40
$19$19 $22$22 $25$25 $17$17
$24$24 $21$21 $19$19 $21$21
$29$29 $16$16 $21$21 $26$26
150
150
2020
3030
3030 2020 2020
3030
FROM
TO
NEW ALLOCATIONS FOR CELL A-4 EVALUATION PATH
Multiple ChoiceMultiple Choice
36. In problem three, the new allocation for cell ‘A-4’ is:
a. 15 b. 20 c. 25 d. 30 e. none of the above.
Multiple ChoiceMultiple Choice
37. In problem three, the new allocation for cell ‘C-2’ is:
a. 15 b. 20 c. 25 d. 30 e. none of the above.
Multiple ChoiceMultiple Choice
38. In problem three, the new allocation for cell ‘A-2’ is:
a. 15 b. 20 c. 25 d. 30 e. none of the above.
Gravity Location ProblemGravity Location ProblemA garden center has three ( 3 ) retail locations in Massachusetts.A garden center has three ( 3 ) retail locations in Massachusetts.The firm wants to construct a new central distribution center forThe firm wants to construct a new central distribution center forservicing its three retail sites:servicing its three retail sites:
RetailRetail
LocationLocation
Map CoordinatesMap Coordinates
( X , Y )( X , Y )
Daily Truck Daily Truck
Round TripsRound Trips
Acton ( 19,10 ) 6
Haverhill ( 24,14 ) 8
Northampton ( 7,6 ) 10
Problem 4
Gravity Location ProblemGravity Location Problem
REQUIREMENT:
A. Compute the location of the proposed facility in terms of the ‘x’ and ‘y’ coordinates.
NOTE: 1. Do not attempt to draw a graph. 2. The supporting calculations are sufficient.
Problem 4
Gravity Location ProblemGravity Location Problem
( 19 x 6 ) + ( 24 x 8 ) + ( 7 x 10 )
6 + 8 + 10
114 + 192 + 70
24
376
24
X =
= 15.67
0 5 10 15 20 250 5 10 15 20 25
XX++
Multiple ChoiceMultiple Choice
39. In problem four, the ‘X’ coordinate for the new central distribution center is:
a. 9.67 b. 14.00 c. 15.67 d. 30 e. none of the above.
Gravity LocaGravity Location Problemtion Problem
( 10 x 6 ) + ( 14 x 8 ) + ( 6 x 10 )
6 + 8 + 10
60 + 112 + 60
24
232
24
Y =
= 9.67
0 5 10 15 20 250 5 10 15 20 25XX
++1515
1010
55
00
YY
Multiple ChoiceMultiple Choice
40. In problem four, the ‘Y’ coordinate for the new central distribution center is:
a. 9.67 b. 14.00 c. 15.67 d. 30 e. none of the above.
Gravity Location ProblemGravity Location Problem
Y
X0 5 10 15 20 25 30 35
15
10
5
0
NORTHAMPTONNORTHAMPTON
ACTONACTON
HAVERHILLHAVERHILL
++THE NEW
DISTRIBUTIONCENTER
( 15.67, 9.67 )
++
True or FalseTrue or False
41. The sources of a transportation matrix are either factories or outside vendors.
TRUE FALSE
42. Evaluation numbers are either ‘positive’ or ‘negative’.
TRUE FALSE
43. When total source units exceed total destination units, an additional row must be included on the transportation matrix.
TRUE FALSE
True or FalseTrue or False
44. Qualitative factors are considered in the use of the transportation algorithm by the operations staff when locating retail facilities.
TRUE FALSE
45. The gravity location model uses shipping costs to locate a central distribution center. TRUE FALSE
46.The gravity location model locates the central distribution center at the geo- graphic center of the distribution system.
TRUE FALSE
True or FalseTrue or False
47. The transshipment model can accommodate multiple levels of the supply chain simultaneously. TRUE FALSE
48. The transshipment model can accommodate multiple modes of transport. TRUE FALSE
49. The transshipment model utilizes a sophisticated version of the transportation algorithm.
TRUE FALSE
50. The gravity location model draws part of its input from the current monthly or quarterly forecasted demands at each facility in the distribution system.
TRUE FALSE