Communication Plan
State Recruitment Improvement Project
(SRIP)
1_/tt/file_convert/55849200d8b42ac1328b4858/document.doc
M A R C H 1 3 , 2 0 0 6
V E R S I O N : F I N A L
Revision History
Version Date Description of Revisions Author
1.0 01/18/2006 Initial Draft Roman
1.1 02/06/06 Added Names and communication strategies Roman
1.2 02/15/06 Defined team & finalized communications area Roman
1.3 02/16/06 Revised document Sheri
1.4 2/27/06 Added Org Chart and minor typos Sheri, Roman & Shaun
1.5 2/28/06 Updated Sponsors reporting processes Roman
1.6 3/13/06 Final comments/revisions Team
Revision Notice
Version Control is used to track progress and changes to the SRIP Communication Plan.
Comments and questions should be directed to Sheri Nees or Roman Martushev.
2_/tt/file_convert/55849200d8b42ac1328b4858/document.doc
Table of ContentsRevision History......................................................................................................................................2
1 Introduction.................................................................................................................4
1.1 Purpose.............................................................................................................................................41.2 Scope................................................................................................................................................41.3 Assumptions.....................................................................................................................................41.4 Project Information..........................................................................................................................41.5 Electronic Distribution.....................................................................................................................4
2 Roles and Responsibilities..........................................................................................5
3 Organization Chart.....................................................................................................6
4 Contact List.................................................................................................................8
5 Communications........................................................................................................10
5.1 Internal Program Communications................................................................................................105.2 External Communications.............................................................................................................115.3 Communication of Issues..............................................................................................................14
6 Issue Management.....................................................................................................15
3_/tt/file_convert/55849200d8b42ac1328b4858/document.doc
1 Introduction
1.1 Purpose
In order for change management to be successful, clear and concise communications among all stakeholders is essential. This plan will act as a road map and outline the basis for open communications during the State Recruitment Improvement Project (SRIP).
The SRIP project will operate as an enterprise wide project requiring shared resources amongst state agencies. This will occur under the direction of the Sponsors along with the support of the Advisory Committee in conjunction with Agency Representatives.
1.2 Scope
This communication plan relates to the planning, designing, development, operations, status reporting, controlling, closing, and maintenance of the project. It also encompasses how we communicate (including ad-hoc) to the following groups: Enterprise, Sponsors (Executive Committee), Advisory Committee, Agency Representatives, Stakeholders, and the Project Team.
1.3 Assumptions
This project will transform the way we do business for state recruitments. Therefore, the communication plan will be a very important element in the way we distribute timely and accurate information to all stakeholders. For enterprise wide projects that cross multiple agencies, this plan will serve in providing open communication among all stakeholders. Communication is a key element in the success of a shared service.
1.4 Project InformationThis project team will post information to the DAS – HRSD website for all stakeholders to view at anytime. The website is located at: www.oregon.gov/DAS/HR/SRIP.shtml.
To access project page through the HRSD home page, type www.oregon.gov/DAS/HR - the link for the SRIP Project is located under the Menu bar on the left side. Click on the SRIP link to view the project information.
1.5 Electronic DistributionThe project team will distribute relevant information electronically to all interested parties and stakeholders who choose to receive SRIP project communications. If interested in receiving project information, please subscribe at the following website: http://listsmart.osl.state.or.us/mailman/listinfo/sripcomlist.
4_/tt/file_convert/55849200d8b42ac1328b4858/document.doc
2 Roles and Responsibilities
SRIP Project Team
It is the responsibility of the SRIP Project Team to ensure all stakeholders have the opportunity to receive open communication at specified times as outlined in this plan. These communications should include, but are not limited to, Enterprise, Sponsors (Executive Committee), Advisory Committee, Agency Representatives, Stakeholders, Project Team, and Ad-hoc Communications.
It is also the responsibility of the Project Team to communicate any issues, problems or concerns to the Project Leader in a timely manner in order to mitigate all project related issues and resolve them before they escalate.
Sponsors
Sponsors will serve as the Executive Committee for the duration of this project. It is the responsibility of the Sponsors to communicate the project’s progress and its affects on state recruitments, at the Executive level, which includes agency heads.
Advisory Committee
Advisory Committee will provide advice and guidance on recruitment options, resource needs, change requests and other project related issues that need discussion in an open forum for the project team to continue moving forward.
Agency Representatives
Agency Representatives will participate in the project, as requested, and will provide clear communication to their agency HR staff on the project’s progress and other project related information.
Stakeholders
Stakeholders may request project related information from the Project Team, the Sponsors, Advisory Committee, or their Agency Representatives.
Ad-hoc Communication
It is the responsibility of the Team Leader or the Sponsor to provide any ad-hoc communications to the affected stakeholders, as necessary, to keep them informed.
5_/tt/file_convert/55849200d8b42ac1328b4858/document.doc
3 Organization Chart
Susan Wilson, Human Resource Services Division Administrator (Sponsor)Jennifer Lara, Statewide Training, Development and Recruitment Manager (Sponsor)
Roman Martushev, Project LeaderSheri Nees, SRIP Business Analyst Shaun Hansen, SRIP Research Analyst Laurie Grenya, Classification Analyst - (MQ/SOC) Jeannette Miley, PPDB Analyst Donna Lantz, PPDB Information Manager Tom Perry, Labor Relations Manager Craig Cowan, Labor Relations Manager Rebecca Gray, Rules & Policy AnalystIT Staff: Appl/Cert System Analysts TeamSite Developer - EDS
Greg Hickman, Employment Department Deputy DirectorVelva Warden, iMatchSkills Program Manager Greg Pelton, iMatchSkills Technician, Analyst & Testing Lead Tracy Olander, iMatchSkills Business Analyst Mary Wood, iMatchSkills Data Specialist (SOC/Skills)ITS Staff: System Architect iMatchSkills Lead Systems Analyst Database Administrator Network & Security Analyst
6_/tt/file_convert/55849200d8b42ac1328b4858/document.doc
7_/tt/file_convert/55849200d8b42ac1328b4858/document.doc
4 Contact List
State Recruitment Improvement Project – Contact List
Team Member Role Email Phone
Project OversightSusan Wilson Administrator [email protected] (503) 378-3020Jennifer Lara Statewide Training,
Development & Recruitment Program Manager
[email protected] (503) 378-3869
Roman Martushev Project Leader [email protected] (503) 373-7572Sheri Nees SRIP Business Analyst [email protected] (503) 378-8347Shaun Hansen Research Analyst - Temp [email protected] (503) 378-2287
DAS - HRSDTom Perry Labor Relations [email protected] (503) 378-4201Rebecca Gray Rules & Policy Analyst [email protected] (503) 378-8301Jeanette Miley PPDB Analyst [email protected] (503) 378-8548Donna Lantz HR Sys/Svc/Audit backup [email protected] (503) 378-3145Laurie Grenya State Class Analyst [email protected] (503) 373-7431Craig Cowan Labor Relations [email protected] (503) 378-5611
DAS - IRMDJoe Adelman Appl/Cert System Analyst [email protected] (503) 378-4946 x470 Kathy Flynn System Analyst [email protected] (503) 373-7484
Employment DepartmentVelva Warden iMatchSkills Program Mgr [email protected] (503) 947-1973Greg Pelton iMS Technician [email protected] (503) 947-1974Tracy Olander iMS Technician – State jobs [email protected] (503) 947-1236Mary Wood SOC Specialist [email protected] (503) 947-1975Rashmi Joshi System Architect [email protected] (503) 947-1849
Advisory CommitteeDAS Jerry Korson (Mgr ) [email protected] (503) 378.4006DCBS Belinda Teague (Mgr) [email protected] (503) 947-7292DHS Twyla Lawson (Interim) [email protected] (503) 945-6137 Salem
(971) 673-1296 PortldDOR Sandra McLernan (Mgr) [email protected] (503) 945-8554ODOT Blair Johnson [email protected] (503) 986-4057ODFW Jonathan Herman (HR Mgr) [email protected] (503) 947-6063 OED Cheri Tebeau-Harrell [email protected] (503) 947-1319PERS Helen Bamford [email protected] (503) 603 7707State Lands Div. Darrell Bennett [email protected] (503) 378-3805 x249Lottery Sheryl Warren [email protected] (503) 540-1135
8_/tt/file_convert/55849200d8b42ac1328b4858/document.doc
State Agency RepresentativesDASTBD Personnel DCBSAdele O’Neal Recruitment Manager [email protected] (503) 947-7296Rebecca Wilson Recruitment Specialist [email protected] (503) 947-7288DHSJennifer L. Rogers [email protected] (503) 945-5693Jean Fauth [email protected] (503) 945-6851DORPatricia E Galloway [email protected] (503) 945-8552ODOTDaniel Killam [email protected] (503) 378-6796Blair Johnson Back-up [email protected] (503) 986-4057ODFWBarbara Britch [email protected] (503) 947-6057Gaile Hamilton [email protected] (503) 947-6061OEDKirstin Madigan [email protected] (503) 947-1469Cheri Tebeau-Harrell Back-up [email protected] (503) 947-1319PERSSusan Korn [email protected] (503) 603 7550Helen Bamford Back-up [email protected] (503) 603 7707State Lands Div.Darrell Bennett DSL HR Mgr [email protected] (503) 378-3805 x249LotteryRyan Fleming [email protected] (503) 540-1322Machell DePina Back-up [email protected] (503) 540-1135DEQPatty O’Connor Human Resource Analyst [email protected] (503) 229-5119
9_/tt/file_convert/55849200d8b42ac1328b4858/document.doc
5 Communications
5.1 Internal Program CommunicationsProgram communications are internal communications between DAS HRSD and Employment Department regarding the State Recruitment Improvement Project.
Relevant project documentation (hard copy) located in the Project Leaders office. All related project documents are located in the SRIP Project Folder at DAS – HRSD.
Type of Report Description / Purpose Responsibility Distribution Media Timing TemplatesStandards
Project Status Reporting
Provide Sponsor(s) with timely project status
Project Leader provides updates
SRIP Business Analyst
Sponsors Project Team
MS Word, electronic via Email
Bi-Monthly –around 1st and the 15th of each month. Starting April 1st
Status Report template
Team Meetings Progress reports, schedule review, task assignments, major issues & risks, action items, roundtable discussions
Project Leader – facilitates
DAS and OED Project Team
Project Team Facilitated meeting, MS Word, electronic via Email
Weekly - Tuesdays @ 10:00 AM
Agenda and Meeting Minutes template
Project Schedule
Shows project schedule interdependencies with the complete set of project tasks and duration as well as the concurrent work activities
Project Leader – maintain, apply updates, post on web
Sponsors Project Team iMS Program Manager
MS Project, electronic via Email
Weekly – In conjunction with team meetings
Project Schedule
Risk Reviews
Identify new risks Review and update risk
assessments Review and update Risk
Management Plan
Project Leader - facilitate
Project Team Members – participate
Sponsors Project Team
MSWord or Excel, Electronic via Email
Weekly in conjunction with Team Meeting
Agenda and Meeting Minutes template
10_/tt/file_convert/55849200d8b42ac1328b4858/document.doc
5.2 External CommunicationsExternal communications are directed toward current or future users of State Recruitment services.
Project communications contribute to the objective of keeping the stakeholders apprised of progress, problems, timelines and deliverables.
Electronic versions of approved project documentation are located in the project’s website – www.Oregon.gov/DAS/HR/SRIP.shtml.
Type of Report Description / Purpose Responsibility Distribution Media Timing TemplatesStandards
SRIP Project Status Updates
Keep agencies and other stakeholders appraised of project status, issues, decisions, direction and what is on the horizon
Project Leader SRIP Business
Analyst Sponsors
Recruitment Managers Meetings HRSD Managers Meetings Agency Reps Advisory Committee
Web site PowerPoint or
Word Electronic
newsletters (as determined)
Starting on April 01, 2006
Monthly
Status Report Template or PowerPoint
Project Schedule
Task list of all activities required to complete the project
Includes tasks, dependencies, durations, start & finish dates, concurrent work activities, and responsible resources
Project Leader – maintain, apply updates, distribute
Agency Representatives
iMS Program Manager
MS Project, electronic via web
Monthly – with Project Status Report
Project Schedule
Issue Log Track issues for reporting and resolution - project team, stakeholders and agencies
Project Leader SRIP Business
Analyst
Sponsors Project Team Agency
Representatives Advisory
Committee
Excel Spreadsheet
Web Site
Ongoing Excel Spreadsheet (Issues, Actions & Decisions)
11_/tt/file_convert/55849200d8b42ac1328b4858/document.doc
Type of Report Description / Purpose Responsibility Distribution Media Timing TemplatesStandards
Advisory Committee & Operational Quality
Collect information to assist with providing advice and guidance
Report progress, delays and the impact over timeline
Advisory Role to the Team Leads
Share resources consumed for the project duration
Project LeaderSRIP Business Analyst
Sponsors iMS Program
Manager
Agency Representatives Sponsors Project Team OED team members
PowerPoint Web site
Monthly starting in March 2006
Meeting minutes
Project Change Requests
Track agency or program requests for project changes to scope or new system capabilities
Includes description of the impact and actions to implement change
Agency Representatives
Sponsors Advisory Committee
Sponsors DAS & OED business analysts Advisory Committee Project Team
Change Request Form in Word
Event driven as requested
Change Request Form
Executive Project Status Reports
Report to DAS Executives Business/Administrative
Mgrs Large Agency Heads Small Agency Heads
Sponsors Project Leader (as
requested)
DAS Executives Admin Managers Agency Heads
Executive Managers Meetings
Quarterly
Web Information
Provide project information relevant to any stakeholder
Project Leader & SRIP Business Analyst
DAS/HR/SRIP project page
Web page 24/7 access As approved
HR Managers Updates
Provide monthly updates of project status
Sponsor (J. Lara) List Serves – SRIP com list
E-mails Monthly or as determined
Recruitment Managers Updates
Provide monthly updates of project status
Sponsor (J. Lara) Project Leader or
SRIP Business Analyst
List Serves – SRIP com list
E-mails Monthly or as determined
12_/tt/file_convert/55849200d8b42ac1328b4858/document.doc
Type of Report Description / Purpose Responsibility Distribution Media Timing TemplatesStandards
Reviews & Sign-Offs
Formal sessions where Advisory Committee might need to review direction or decision for approval
Formal sign-off on selected decisions or deliverables by Sponsors
Project Leader (oversight)
SRIP Business Analyst – execute
Sponsors & iMS Program Manager
Sponsors Project Leader iMS Program
Manager
Facilitated meeting
MS Word, hard copy
As required Acceptance Form template
Quality Assurance
Increase focus on service, quality, promote collaboration, highlight successes, ensure clear understanding of expectations and enable the entire SRIP team to deliver against those expectations.
Project Leader – methodology & oversight
Project Team - strive for excellence & high quality work
Advisory Committee for assurance
Sponsors Advisory
Committee iMS Program Mgr Project Team
Advisory Meetings as needed
MS Word via email
Ongoing
As required
Deliverables Task Accomplishments and Oversight
13_/tt/file_convert/55849200d8b42ac1328b4858/document.doc
5.3 Communication of IssuesIssues are initiated whenever there is an unusual event that has affected or has the potential to affect the Project Team, Stakeholders and others.
Type of Report Description / Purpose Responsibility Distribution Media Timing TemplatesStandards
Issue Notification
Provide notification of issue to team, sponsors & stakeholders as necessary
Control rumors – provide factual information
Integrate Issue Response Plan
Project Leader SRIP Business
Analyst Sponsors iMS Program
Manager (as determined)
Project Team Sponsors Advisory Committee Agency Reps Stakeholders, as
needed
Electronic via Email
Phone
Depending on the severity of issue and the extent of the problem
Excel Spreadsheet
Issue Updates Control rumors – provide factual information
Enable agencies to provide accurate information
Update Issue Response Plan
Project Leader SRIP Business
Analyst Sponsors iMS Program
Manager
Agency Reps Sponsors Project Team
Advisory Committee
Electronic via Email
Phone
Hourly or upon significant change in status
Excel Spreadsheet
Issue Closure Control rumors – provide factual information & close out the issue
Create record for close-out, analysis & prevention tactics
Project Leader SRIP Business
Analyst Sponsors iMS Program
Manager
Sponsors Project Team iMS Program Advisory Committee
Formal document, usually Word via Email
Phone
What issue occurred, was resolved and strategy for prevention
Excel Spreadsheet
14_/tt/file_convert/55849200d8b42ac1328b4858/document.doc
6 Issue ManagementStandard issue management and tracking is described in the Issue Management Plan document. Issues become an item of escalation when the regular channels of communication fail to deliver the expected results or when the identified concern could result in immediate procedural or financial harm for the State of Oregon or the SRIP Project.
When an issue is created, it is assigned a priority number as described in the following table. Issues are also assigned a critical due date. Depending on the issue priority level, the critical due date should be within the number of days allowed for resolution of the reported issue.
Priority Number Description Resolution Period1 High
An issue assigned priority level 1 has the potential to ultimately cause procedural or financial harm to the project and/or client if not resolved. A delay in resolution will ultimately impact the project’s scope, schedule, quality, cost or resources.
1 working day or less
2 Medium An issue is assigned priority level 2 if it has limited
procedural impact on the project and/or client. A delay in resolution may impact the project’s scope, schedule, quality, cost, or resources.
2 - 5working days
3 Low An issue is assigned priority level 3 if it has no
procedural or financial impact on the project and/or client. A delay in resolution will not impact the project’s scope, schedule, quality, cost or resources.
Greater than 5 working days
ENH Enhancement An issue could be assigned as ENH if it is determined
to be an enhancement of the current scope of work and requires additional work in order to resolve it. This issue/enhancement will need to follow the change management process for approval in order to be considered for this project. A resolution might potentially impact one or more of the following: project’s scope, schedule, quality, cost or resources.
As determined by the Advisory Committee
Issues that are not resolved and closed by the critical due date or within the resolution period should be immediately escalated to the Project Leader.
See next page for escalation contacts.
Escalation Contacts
SRIP Contacts Position Escalation Point
Area of Focus
Phone and Email
Roman Martushev
Project Leader
Initial Project Issues
(503) [email protected]
Sheri Nees SRIP Business Analyst
Initial Backup
Project Issues
(503) [email protected]
Jennifer Lara Business Sponsor
Business Processes
Program Management
(503) [email protected]
Susan Wilson Executive Sponsor
Executive & Final
Overall Management
(503) [email protected]
OED iMatchSkills
Velva Warden iMatchSkills Program Manager
iMS Program Program Management
(503) [email protected]